JP2019031821A - Construction method of underground tank - Google Patents

Construction method of underground tank Download PDF

Info

Publication number
JP2019031821A
JP2019031821A JP2017153005A JP2017153005A JP2019031821A JP 2019031821 A JP2019031821 A JP 2019031821A JP 2017153005 A JP2017153005 A JP 2017153005A JP 2017153005 A JP2017153005 A JP 2017153005A JP 2019031821 A JP2019031821 A JP 2019031821A
Authority
JP
Japan
Prior art keywords
heater
underground
continuous wall
tank
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2017153005A
Other languages
Japanese (ja)
Inventor
幹雄 柏木
Mikio Kashiwagi
幹雄 柏木
藤永 友三郎
Tomosaburo Fujinaga
友三郎 藤永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2017153005A priority Critical patent/JP2019031821A/en
Publication of JP2019031821A publication Critical patent/JP2019031821A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

To provide a construction method of underground tank capable of reducing the construction period.SOLUTION: A construction method of an underground tank comprises: a first drilling step of drilling a continuous wall hole part 7A in which an underground continuous wall 5 is installed in the ground G; an underground continuous wall construction step of constructing the underground continuous wall 5 in the continuous wall hole 7A; a second drilling step of drilling a heater hole portion 7B for installing a side heater 6 on the outside the continuous wall hole portion 7A; a side heater setting step of installing the side heater 6 in the heater hole portion 7B; a tank body construction step of constructing a tank main body 10 having a bottom plate 2 and a cylindrical side wall 3 inside the underground continuous wall 5; and an embankment step of embanking so as to cover the outside of the tank body 10. The side heater setting step is carried out before the tank main body building step.SELECTED DRAWING: Figure 1

Description

本発明は、地下タンクの施工方法に関するものである。   The present invention relates to an underground tank construction method.

従来から、液化天然ガス(LNG)等の低温液体は、地中に埋設された地下タンクに貯蔵されている。地下タンクは、底版と、底版の周囲に沿って構築された側壁と、側壁の上部を覆う屋根と、を備えている。この地下タンク内の液体の冷熱により、地下タンク周辺の地盤が凍結することを防止するために、地下タンクの側方(側壁の外方)等に側部ヒータが設置されたものが広く知られている(下記の特許文献1〜3参照)。   Conventionally, low-temperature liquids such as liquefied natural gas (LNG) are stored in underground tanks buried in the ground. The underground tank includes a bottom plate, a side wall constructed around the bottom plate, and a roof covering an upper portion of the side wall. In order to prevent the ground around the underground tank from freezing due to the cold heat of the liquid in the underground tank, it is widely known that a side heater is installed on the side of the underground tank (outside the side wall). (See Patent Documents 1 to 3 below).

このような地下タンクの施工手順としては、地中に筒状の地中連続壁を構築し、地中連続壁の内部を掘削して、底版、側壁、屋根等の躯体を構築し、最後に盛土を行っている。一方、側部ヒータの設置は、側壁の構築後に側部ヒータを設置するための穴を掘削(削孔)し、盛土をする際に穴内に側部ヒータを設置している。   The construction procedure for such underground tanks is to build a cylindrical underground continuous wall in the ground, excavate the interior of the underground continuous wall, and build a frame such as a bottom plate, side walls, and roof. Performing embankment. On the other hand, the side heater is installed by excavating (drilling) a hole for installing the side heater after the side wall is constructed, and installing the side heater in the hole when embankment is performed.

特開2000−282495号公報JP 2000-282495 A 特開昭62−83599号公報JP-A-62-83599 特開平6−221028号公報JP-A-6-221028

しかしながら、側部ヒータの削孔作業は屋根の構築作業と時期が重なるとともに、側部ヒータの設置作業は盛土作業と時期が重なるため、屋根の構築作業や盛土作業が側部ヒータの削孔作業や設置作業に影響を与える(あるいは、側部ヒータの削孔作業や設置作業が屋根の構築作業や盛土作業に影響を与える)クリティカルパスとなっているという問題点がある。   However, the side heater drilling work overlaps with the roof construction work, and the side heater installation work overlaps with the embankment work, so the roof construction work and embankment work is the side heater drilling work. There is a problem that it is a critical path that affects the installation work (or the side heater drilling work or installation work affects the roof construction work or the banking work).

そこで、本発明は、上記事情に鑑みてなされたものであり、工期を短縮できる地下タンクの施工方法を提供する。   Then, this invention is made | formed in view of the said situation, and provides the construction method of the underground tank which can shorten a construction period.

上記目的を達成するために、本発明は以下の手段を採用している。
すなわち、本発明に係る地下タンクの施工方法は、地盤中に構築され、筒状に形成された地中連続壁と、該地中連続壁の内側に構築され、液体が貯蔵可能なタンク本体と、前記地中連続壁の外側に設置された側部ヒータと、を備える地下タンクの施工方法であって、前記地盤中に、前記地中連続壁が設置される環状の連続壁用穴部を掘削する第一削孔工程と、前記連続壁用穴部に前記地中連続壁を構築する地中連続壁構築工程と、前記連続壁用穴部の外側に、前記側部ヒータが設置されるヒータ用穴部を掘削する第二削孔工程と、前記ヒータ用穴部に前記側部ヒータを設置する側部ヒータ設置工程と、前記地中連続壁の内側に、底版と筒状の側壁とを有するタンク本体を構築するタンク本体構築工程と、前記タンク本体の外側を覆うように盛土を行う盛土工程と、を備え、前記側部ヒータ設置工程は、前記タンク本体構築工程の前に行うことを特徴とする。
In order to achieve the above object, the present invention employs the following means.
That is, the underground tank construction method according to the present invention includes a continuous underground wall formed in the ground and formed into a cylindrical shape, and a tank body that is built inside the continuous underground wall and can store liquid. An underground tank construction method comprising: a side heater installed outside the continuous underground wall, wherein an annular continuous wall hole in which the underground continuous wall is installed in the ground A first drilling step for excavation; an underground continuous wall construction step for constructing the underground continuous wall in the continuous wall hole portion; and the side heater is installed outside the continuous wall hole portion. A second drilling step of excavating the heater hole, a side heater installation step of installing the side heater in the heater hole, a bottom plate and a cylindrical side wall inside the underground continuous wall; A tank body construction step for constructing a tank body having And a fill step of performing said second heater installation process is characterized in that it is carried out in the front of the tank body building process.

このように構成された地下タンクの施工方法では、側部ヒータ設置工程をタンク本体構築工程の前に行うことで、側部ヒータ設置工程がクリティカルパスから外れるため、従来と比較して工期短縮を図ることができる。   In the construction method of the underground tank constructed in this way, the side heater installation process deviates from the critical path by performing the side heater installation process before the tank body construction process. Can be planned.

また、本発明に係る地下タンクの施工方法は、前記側部ヒータ設置工程で設置された前記側部ヒータを、前記盛土の高さ分上方に延伸する側部ヒータ延伸工程と、前記タンク本体構築工程で構築された前記側壁を、前記盛土の高さ分上方に延伸する側壁延伸工程と、を備え、前記側部ヒータ延伸工程及び前記側壁延伸工程を、前記タンク本体構築工程の後、且つ前記盛土工程の前に行うことが好ましい。   The underground tank construction method according to the present invention includes a side heater extending step of extending the side heater installed in the side heater installation step upward by the height of the embankment, and the tank body construction. A side wall extending step of extending the side wall constructed in the process upward by the height of the embankment, and the side heater extending step and the side wall extending step after the tank body constructing step, and It is preferable to carry out before the embankment process.

このように構成された地下タンクの施工方法では、側部ヒータ延伸工程及び側壁延伸工程で、それぞれ上方に延伸した側部ヒータ及び側壁は、その後の盛土工程で盛土に確実に埋設される。さらに、側部ヒータ延伸工程及び側壁延伸工程を盛土工程の前に行うことで、側部ヒータ延伸工程がクリティカルパスから外れるため、従来と比較して工期短縮を確実に図ることができる。   In the construction method of the underground tank configured as described above, the side heater and the side wall extended upward in the side heater extending step and the side wall extending step are reliably embedded in the embankment in the subsequent embankment step. Furthermore, since the side heater stretching step and the side wall stretching step are performed before the embankment step, the side heater stretching step deviates from the critical path, so that the work period can be shortened as compared with the conventional method.

本発明に係る地下タンクの施工方法によれば、工期を短縮することができる。   According to the construction method of the underground tank according to the present invention, the construction period can be shortened.

本発明の一実施形態に係る地下タンクを示す模式的な縦断面図である。It is a typical longitudinal section showing an underground tank concerning one embodiment of the present invention. 本発明の一実施形態に係る地下タンクを示す模式的な平面図である。It is a typical top view showing an underground tank concerning one embodiment of the present invention. 本発明の一実施形態に係る地下タンクの施工方法の地中連続壁構築工程を示す図である。It is a figure which shows the underground continuous wall construction process of the construction method of the underground tank which concerns on one Embodiment of this invention. 本発明の一実施形態に係る地下タンクの施工方法の側部ヒータ設置工程を示す図である。It is a figure which shows the side part heater installation process of the construction method of the underground tank which concerns on one Embodiment of this invention. 本発明の一実施形態に係る地下タンクの施工方法のタンク本体構築工程を示す図である。It is a figure which shows the tank main body construction process of the construction method of the underground tank which concerns on one Embodiment of this invention. 本発明の一実施形態に係る地下タンクの施工方法の側部ヒータ延伸工程及び側壁延伸工程を示す図である。It is a figure which shows the side part heater extending process and side wall extending process of the construction method of the underground tank which concerns on one Embodiment of this invention. 本発明の一実施形態に係る地下タンクの施工方法の盛土工程を示す図である。It is a figure which shows the embankment process of the construction method of the underground tank which concerns on one Embodiment of this invention.

本発明の一実施形態に係る地下タンクの施工方法について、図面を用いて説明する。
まず、地下タンクについて説明する。
図1は、本発明の一実施形態に係る地下タンクを示す模式的な縦断面図である。図2は、本発明の一実施形態に係る地下タンクを示す模式的な平面図である。
図1及び図2に示すように、本実施形態に係る地下タンク1は、例えば、LNG貯蔵タンクとして使用されるものである。地下タンク1は、タンク本体10と、タンク本体10の外周面に沿って構築された地中連続壁5と、地中連続壁5の外側に設けられた側部ヒータ6と、を備えている。
The construction method of the underground tank which concerns on one Embodiment of this invention is demonstrated using drawing.
First, the underground tank will be described.
FIG. 1 is a schematic longitudinal sectional view showing an underground tank according to an embodiment of the present invention. FIG. 2 is a schematic plan view showing an underground tank according to an embodiment of the present invention.
As shown in FIG.1 and FIG.2, the underground tank 1 which concerns on this embodiment is used as an LNG storage tank, for example. The underground tank 1 includes a tank main body 10, an underground continuous wall 5 constructed along the outer peripheral surface of the tank main body 10, and a side heater 6 provided outside the underground continuous wall 5. .

タンク本体10は、地盤G面よりも下方に設置された平面視略円形状の底版2と、略円筒状の側壁3と、側壁3の上端部3aに支持されたドーム状の屋根4と、を有している。   The tank body 10 includes a bottom plate 2 having a substantially circular shape in plan view installed below the ground G surface, a substantially cylindrical side wall 3, and a dome-shaped roof 4 supported by the upper end 3 a of the side wall 3, have.

底版2は、鉄筋コンクリート造で、掘削された地盤G上に設けられた砕石層11の上部に構築されている。底版2の内部には、地下タンク1内の温度調整を行う底部ヒータ(不図示)が設置されている。   The bottom slab 2 is made of reinforced concrete, and is constructed on the crushed stone layer 11 provided on the ground G excavated. A bottom heater (not shown) for adjusting the temperature in the underground tank 1 is installed inside the bottom plate 2.

側壁3は、鉄筋コンクリート造で、下端部3bが底版2の外縁部2aに剛に接合されている。底版2及び側壁3により、有底円筒状に構成されている。底版2及び側壁3の内面には、図示しない保冷材及びメンブレン材が設置されている。   The side wall 3 is made of reinforced concrete, and the lower end 3 b is rigidly joined to the outer edge 2 a of the bottom plate 2. The bottom plate 2 and the side wall 3 form a bottomed cylindrical shape. On the inner surfaces of the bottom plate 2 and the side wall 3, a cold insulating material and a membrane material (not shown) are installed.

側壁3の上部側の外周には地下タンク1の施工中に盛土されているため、地下タンク1は地下に配置された構成となっている。   Since the outer periphery of the upper side of the side wall 3 is embanked during construction of the underground tank 1, the underground tank 1 is configured to be disposed underground.

屋根4は、鉄筋コンクリート造で、平面視において円形状に形成され、側壁3の上端部3aに接続されている。   The roof 4 is made of reinforced concrete, has a circular shape in plan view, and is connected to the upper end 3 a of the side wall 3.

また、側壁3の下端部3b側の外周の地盤Gには、側壁3の外周面に沿った形状で平面視円環状の地中連続壁5が設けられている。   The ground G on the outer periphery on the lower end 3 b side of the side wall 3 is provided with an underground continuous wall 5 having an annular shape in plan view in a shape along the outer peripheral surface of the side wall 3.

地中連続壁5は、土留めとして地盤Gの崩落を防ぐ機能や止水機能を備えている。地中連続壁5は、地下タンク1の底版2よりもさらに深く構築されており、下端部5bは難透水層(洪積粘性土層)13まで達している。地中連続壁5は、例えば、鉄筋コンクリートなどで構築されている。   The underground continuous wall 5 has a function of preventing the ground G from collapsing and a water stop function as a soil retaining. The underground continuous wall 5 is constructed deeper than the bottom slab 2 of the underground tank 1, and the lower end portion 5 b reaches the hardly permeable layer (cold clay layer) 13. The underground continuous wall 5 is constructed of, for example, reinforced concrete.

地中連続壁5の外側には、複数の側部ヒータ6が設置されている。側部ヒータ6は、地中連続壁5の周方向に間隔を有して配置されている。側部ヒータ6は、地盤Gの凍結膨張を抑制するためのものである。本実施形態では、側部ヒータ6は、平面視略円形状をなしている。例えば、側部ヒータ6は、温水を流すため2重構造で構成されている。   A plurality of side heaters 6 are installed outside the underground continuous wall 5. The side heaters 6 are arranged at intervals in the circumferential direction of the underground continuous wall 5. The side heater 6 is for suppressing freezing and expansion of the ground G. In the present embodiment, the side heater 6 has a substantially circular shape in plan view. For example, the side heater 6 has a double structure for flowing warm water.

次に、上述した地下タンク1の施工方法について説明する。
予め、地盤改良工事や、地盤Gの表層部を盤下げ掘削し周囲の地盤Gよりも低くなるようにする地盤表層部掘削工事を行っておく。
Next, the construction method of the above-described underground tank 1 will be described.
In advance, ground improvement work or ground surface layer excavation work for lowering the surface layer portion of the ground G so as to be lower than the surrounding ground G is performed.

(第一削孔工程)
地中連続壁5の設置予定箇所に沿って、連続壁用溝(連続壁用穴部)7Aを設ける。平面視で、連続壁用溝7Aは環状をなしている。
(First drilling process)
A continuous wall groove (continuous wall hole) 7 </ b> A is provided along the planned location of the underground continuous wall 5. In plan view, the continuous wall groove 7A has an annular shape.

(地中連続壁構築工程)
図3は、地中連続壁構築工程を示す図である。
図3に示すように、連続壁用溝7Aに、鉄筋を配置してコンクリートを打設する周知技術により、地中連続壁5を構築する。
(Underground continuous wall construction process)
FIG. 3 is a diagram illustrating an underground continuous wall construction process.
As shown in FIG. 3, the underground continuous wall 5 is constructed by a well-known technique in which concrete is placed by placing reinforcing bars in the continuous wall groove 7A.

(第二削孔工程)
図2に示すように、側部ヒータ6の設置予定箇所に沿って、ヒータ用穴(ヒータ用穴部)7Bをボーリングマシン等で設ける。平面視で、ヒータ用穴7Bは、円形状をなしている。ヒータ用穴7Bは、連続壁用溝7Aの外側に、つまり連続壁用溝7Aの径方向外側に、連続壁用溝7Aの周方向に間隔を有して複数設けられる。
(Second drilling process)
As shown in FIG. 2, a heater hole (heater hole) 7 </ b> B is provided along a planned installation location of the side heater 6 by a boring machine or the like. In plan view, the heater hole 7B has a circular shape. A plurality of heater holes 7B are provided outside the continuous wall groove 7A, that is, outside the continuous wall groove 7A in the radial direction, with an interval in the circumferential direction of the continuous wall groove 7A.

(側部ヒータ設置工程)
図4は、側部ヒータ設置工程を示す図である。
図4に示すように、ヒータ用穴7Bに、側部ヒータ6を設置する。本実施形態では、側部ヒータ6の下端部6b側(下部ヒータ6Xと称する)が設置される。換言すると、図1に示す側部ヒータ6の上端部6a側はこの段階ではまだ設置されていない。
(Side heater installation process)
FIG. 4 is a diagram illustrating a side heater installation process.
As shown in FIG. 4, the side heater 6 is installed in the heater hole 7B. In the present embodiment, the lower end 6b side (referred to as the lower heater 6X) of the side heater 6 is installed. In other words, the upper end 6a side of the side heater 6 shown in FIG. 1 is not yet installed at this stage.

(タンク本体構築工程)
図5は、タンク本体構築工程を示す図である。
図5に示すように、地中連続壁5の内部を掘削し、鉄筋を配置してコンクリートを打設する周知技術により、底版2及び側壁3の下端部3b側(下部側壁3Xと称する)を構築する。換言すると、図1に示す側壁3の上端部3a側はこの段階ではまた構築されていない。
(Tank body construction process)
FIG. 5 is a diagram showing a tank body construction process.
As shown in FIG. 5, the bottom plate 2 and the lower end 3b side (referred to as the lower side wall 3X) of the bottom plate 2 and the side wall 3 are known by excavating the inside of the underground continuous wall 5 and placing concrete by placing reinforcing bars. To construct. In other words, the upper end 3a side of the side wall 3 shown in FIG. 1 is not constructed again at this stage.

(側部ヒータ延伸工程及び側壁延伸工程)
図6は、側部ヒータ延伸工程及び側壁延伸工程を示す図である。
図6に示すように、側部ヒータ設置工程で設置した下部ヒータ6Xの上方に、側部ヒータ6の上端部6a側(上部ヒータ6Yと称する)を接続して、側部ヒータ6全体を構築する。また、タンク本体構築工程で構築した下部側壁3Xの上方に、側壁3の上端部3a側(上部側壁3Yと称する)を構築して、側壁3を構築する。その後、屋根4(図1参照)を構築する。上部ヒータ6Y及び上部側壁3Yの高さは、後述する盛土Ga(図7参照)の高さに相当する。
(Side heater stretching process and side wall stretching process)
FIG. 6 is a diagram illustrating a side heater stretching step and a side wall stretching step.
As shown in FIG. 6, the upper side 6a side (referred to as the upper heater 6Y) of the side heater 6 is connected to the upper side of the lower heater 6X installed in the side heater installation process, and the entire side heater 6 is constructed. To do. Also, the side wall 3 is constructed by constructing the upper end 3a side (referred to as the upper side wall 3Y) of the side wall 3 above the lower side wall 3X constructed in the tank body construction process. Thereafter, the roof 4 (see FIG. 1) is constructed. The height of the upper heater 6Y and the upper side wall 3Y corresponds to the height of embankment Ga (see FIG. 7) described later.

(盛土工程)
図7は、盛土工程を示す図である。
図7に示すように、側壁3の外周面が地中に埋設されるように、側壁3の上端部3a付近の高さまで盛土を行う。図1において、盛土された地盤GをGaと示す。
(Filling process)
FIG. 7 is a diagram illustrating the embankment process.
As shown in FIG. 7, embankment is performed to a height near the upper end portion 3 a of the side wall 3 so that the outer peripheral surface of the side wall 3 is buried in the ground. In FIG. 1, the embankment ground G is shown as Ga.

このように構成された地下タンク1の施工方法によれば、側部ヒータ設置工程をタンク本体構築工程の前に行うことで、側部ヒータ設置工程がクリティカルパスから外れるため、従来と比較して工期短縮を図ることができる。   According to the construction method of the underground tank 1 configured as described above, the side heater installation process is deviated from the critical path by performing the side heater installation process before the tank body construction process. The construction period can be shortened.

また、側部ヒータ延伸工程及び側壁延伸工程で、それぞれ上方に延伸した側部ヒータ(上部ヒータ6Y)及び側壁(上部側壁3Y)は、その後の盛土工程で盛土に確実に埋設される。さらに、側部ヒータ延伸工程及び側壁延伸工程を盛土工程の前に行うことで、側部ヒータ延伸工程がクリティカルパスから外れるため、従来と比較して工期短縮を確実に図ることができる。   Further, the side heater (upper heater 6Y) and the side wall (upper side wall 3Y) extending upward in the side heater extending step and the side wall extending step are reliably embedded in the embankment in the subsequent embedding step. Furthermore, since the side heater stretching step and the side wall stretching step are performed before the embankment step, the side heater stretching step deviates from the critical path, so that the work period can be shortened as compared with the conventional method.

なお、上述した実施の形態において示した各構成部材の諸形状や組み合わせ等は一例であって、本発明の主旨から逸脱しない範囲において設計要求等に基づき種々変更可能である。   The various shapes and combinations of the constituent members shown in the above-described embodiments are merely examples, and various modifications can be made based on design requirements and the like without departing from the gist of the present invention.

1…地下タンク
2…底版
3…側壁
4…屋根
5…地中連続壁
6…側部ヒータ
7A…連続壁用溝(連続壁用穴部)
7B…ヒータ用穴(ヒータ用穴部)
10…タンク本体
11…砕石層
G…地盤
DESCRIPTION OF SYMBOLS 1 ... Underground tank 2 ... Bottom slab 3 ... Side wall 4 ... Roof 5 ... Underground continuous wall 6 ... Side heater 7A ... Continuous wall groove (hole for continuous wall)
7B ... Heater hole (Heater hole)
10 ... Tank body 11 ... Crushed stone layer G ... Ground

Claims (2)

地盤中に構築され、筒状に形成された地中連続壁と、該地中連続壁の内側に構築され、液体が貯蔵可能なタンク本体と、前記地中連続壁の外側に設置された側部ヒータと、を備える地下タンクの施工方法であって、
前記地盤中に、前記地中連続壁が設置される環状の連続壁用穴部を掘削する第一削孔工程と、
前記連続壁用穴部に前記地中連続壁を構築する地中連続壁構築工程と、
前記連続壁用穴部の外側に、前記側部ヒータが設置されるヒータ用穴部を掘削する第二削孔工程と、
前記ヒータ用穴部に前記側部ヒータを設置する側部ヒータ設置工程と、
前記地中連続壁の内側に、底版と筒状の側壁とを有するタンク本体を構築するタンク本体構築工程と、
前記タンク本体の外側を覆うように盛土を行う盛土工程と、を備え、
前記側部ヒータ設置工程は、前記タンク本体構築工程の前に行うことを特徴とする地下タンクの施工方法。
An underground continuous wall constructed in the ground and formed into a cylindrical shape, a tank body constructed inside the underground continuous wall and capable of storing liquid, and a side installed outside the underground continuous wall An underground tank construction method comprising:
A first drilling step of excavating an annular continuous wall hole in which the underground continuous wall is installed in the ground;
An underground continuous wall construction step of constructing the underground continuous wall in the hole for the continuous wall;
A second drilling step of excavating a heater hole in which the side heater is installed outside the continuous wall hole;
A side heater installation step of installing the side heater in the heater hole;
A tank body construction step for constructing a tank body having a bottom plate and a cylindrical side wall inside the underground continuous wall;
A banking step of banking to cover the outside of the tank body,
The underground heater construction method, wherein the side heater installation step is performed before the tank body construction step.
前記側部ヒータ設置工程で設置された前記側部ヒータを、前記盛土の高さ分上方に延伸する側部ヒータ延伸工程と、
前記タンク本体構築工程で構築された前記側壁を、前記盛土の高さ分上方に延伸する側壁延伸工程と、を備え、
前記側部ヒータ延伸工程及び前記側壁延伸工程を、前記タンク本体構築工程の後、且つ前記盛土工程の前に行うことを特徴とする請求項1に記載の地下タンクの施工方法。
A side heater extending step of extending the side heater installed in the side heater installing step upward by the height of the embankment;
A side wall extending step of extending the side wall constructed in the tank main body construction step upward by the height of the embankment,
The underground tank construction method according to claim 1, wherein the side heater stretching step and the side wall stretching step are performed after the tank body construction step and before the embankment step.
JP2017153005A 2017-08-08 2017-08-08 Construction method of underground tank Pending JP2019031821A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017153005A JP2019031821A (en) 2017-08-08 2017-08-08 Construction method of underground tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017153005A JP2019031821A (en) 2017-08-08 2017-08-08 Construction method of underground tank

Publications (1)

Publication Number Publication Date
JP2019031821A true JP2019031821A (en) 2019-02-28

Family

ID=65524116

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017153005A Pending JP2019031821A (en) 2017-08-08 2017-08-08 Construction method of underground tank

Country Status (1)

Country Link
JP (1) JP2019031821A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112849796A (en) * 2020-12-31 2021-05-28 山东京博控股集团有限公司 Built-in valve chamber of full earthing tank body

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112849796A (en) * 2020-12-31 2021-05-28 山东京博控股集团有限公司 Built-in valve chamber of full earthing tank body
CN112849796B (en) * 2020-12-31 2021-10-22 山东京博控股集团有限公司 Full soil covering tank system with built-in valve chamber
US11702279B2 (en) 2020-12-31 2023-07-18 Shandong Chambroad Equipment Manufacture Installation Co., Ltd. Built-in valve chamber of tank completely covered with soil

Similar Documents

Publication Publication Date Title
JP6650348B2 (en) Underground diaphragm wall construction method, underground diaphragm wall
KR101641293B1 (en) Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall
JP2016089404A (en) Grout method for cast-in-place concrete pile
JP2017172280A (en) Body lining wall and construction method thereof
US3854265A (en) Method for constructing an underground storage tank
JP2011106229A (en) Method for constructing temporary pile
JP2019031821A (en) Construction method of underground tank
JP2012158891A (en) Construction method of pit-in type tank
KR101734026B1 (en) Retaining Wal1 Construction Method Using PHC Pile
JP2019031820A (en) Underground tank and construction method of underground tank
JP6225458B2 (en) Retaining wall and its construction method
JP4702674B1 (en) Construction method of underground tank
KR20090055790A (en) Underground burial type lng storage equipments and its construction method
JP2019031822A (en) Underground tank and construction method of underground tank
JP6770857B2 (en) How to build a continuous underground wall, and a continuous underground wall
JP6584979B2 (en) Construction method of underground tank structure, underground tank structure
JPH09501377A (en) Method for operating an underground cavity for storing low temperature hydrocarbons and low temperature hydrocarbon storage facility
KR101960499B1 (en) Underground column wall construction method using waterstop rubber and waterstop housing, and underground column wall therewith
JP6778528B2 (en) How to update the tank
KR101862761B1 (en) the method of constructing underground basic structure
JP4475116B2 (en) Vertical shaft structure and its construction method
JP7021419B2 (en) Construction method of underground widening part
KR100941438B1 (en) Upper girder part waterproof method for 2 arch tunnel
JP5037474B2 (en) Pumping pipe and method for constructing pumping pipe
WO2019185963A1 (en) Method for building concrete foundations for lattice-type offshore structures, and foundations built using this method