JP2010121724A - Pipeline laying and burying method on steep slope - Google Patents

Pipeline laying and burying method on steep slope Download PDF

Info

Publication number
JP2010121724A
JP2010121724A JP2008296660A JP2008296660A JP2010121724A JP 2010121724 A JP2010121724 A JP 2010121724A JP 2008296660 A JP2008296660 A JP 2008296660A JP 2008296660 A JP2008296660 A JP 2008296660A JP 2010121724 A JP2010121724 A JP 2010121724A
Authority
JP
Japan
Prior art keywords
pipe
laying
burying
pipeline
transported
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008296660A
Other languages
Japanese (ja)
Other versions
JP5115456B2 (en
Inventor
Tooru Ogawara
徹 小川原
Naoyuki Teranishi
直之 寺西
Hirohiko Adachi
裕彦 足立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
JFE Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Engineering Corp filed Critical JFE Engineering Corp
Priority to JP2008296660A priority Critical patent/JP5115456B2/en
Publication of JP2010121724A publication Critical patent/JP2010121724A/en
Application granted granted Critical
Publication of JP5115456B2 publication Critical patent/JP5115456B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a pipeline laying and burying method capable of construction limited to a small-scale range along a burying position of a pipeline, without requiring a large-scale site, when laying and burying the pipeline on a steep slope. <P>SOLUTION: A construction procedure of (a) an excavation process, (b) a pipe carrying and installing process, (c) a pipe welding process and (d) a backfilling process, is taken by properly combining an excavator 21 for a slope and a cableway 22. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、急斜面にパイプラインを敷設・埋設するためのパイプライン敷設・埋設方法であり、傾斜地におけるガス、上下水道、石油等の輸送パイプラインの敷設・埋設工事に適用される。特に、このパイプライン敷設・埋設方法は、傾斜地の区間が長い場合でも適用可能なため、山間部のパイプライン敷設・埋設工事に適している。   The present invention is a pipeline laying and burying method for laying and burying pipelines on steep slopes, and is applied to laying and burying transportation pipelines for gas, water and sewage, oil, etc. on slopes. In particular, this pipeline laying and burying method can be applied even when the slope section is long, and is therefore suitable for pipeline laying and burying work in mountainous areas.

従来、急斜面にパイプラインを敷設・埋設するための施工技術については、例えば特許文献1や特許文献2に記載されているように、油圧ショベル(バックホー)による法面整形や掘削等の作業を行う施工方法や施工装置について開示されている。
特開平05−105122号公報 特開2002−167762号公報
Conventionally, with respect to construction techniques for laying and burying pipelines on steep slopes, for example, as described in Patent Literature 1 and Patent Literature 2, operations such as slope shaping and excavation by a hydraulic excavator (backhoe) are performed. A construction method and a construction apparatus are disclosed.
JP 05-105122 A JP 2002-167762 A

しかし、図2に示すように、油圧ショベル(バックホー)51を用いて斜面上に埋設溝を掘削するには、平坦な重機足場や、キャリアダンプ52による掘削土の搬出および資機材の運搬のための通路を斜面上にジグザグ形状に築造しなければならなかった。   However, as shown in FIG. 2, in order to excavate a buried groove on a slope using a hydraulic excavator (backhoe) 51, a flat heavy machinery scaffolding, a carrier dump 52 for carrying out excavated soil and transporting materials and equipment. Had to be built in a zigzag shape on the slope.

このため、作業用地として広い面積を必要とし、用地確保のために大規模な樹木伐採や施工後の切盛り部復旧や緑化復旧の作業を行っていた。   For this reason, a large area is required as a work site, and large-scale tree cutting, restoration of the filling section after construction, and restoration of greening have been performed to secure the site.

また、斜面上は部分的に崩落しやすい個所が存在するなど均質な地盤条件とは限らないため、通路築造位置の選定が難しく、雨水降水の影響等による通路補修の発生などの問題があった。   In addition, because the ground conditions are not always uniform, such as the presence of a part that tends to collapse partially on the slope, it is difficult to select the passage construction position, and there were problems such as passage repair due to the effects of rainwater precipitation, etc. .

本発明は、上記のよう事情に鑑みてなされたものであり、急斜面にパイプラインを敷設・埋設するに際して、大規模な用地を必要とせずに、パイプラインの埋設位置に沿った小規模な範囲に限定した施工を可能とするパイプライン敷設・埋設方法を提供することを目的とするものである。   The present invention has been made in view of the circumstances as described above, and does not require a large-scale site when laying and burying a pipeline on a steep slope, and a small range along the burial position of the pipeline. It aims at providing the pipeline laying and embedding method which enables construction limited to.

上記課題を解決するために、本発明は以下の特徴を有する。   In order to solve the above problems, the present invention has the following features.

[1]急斜面にパイプラインを敷設・埋設する方法であって、
パイプラインを敷設・埋設する個所を急傾斜地用油圧ショベルによって掘削する掘削工程と、
敷設・埋設する管を索道によって運搬し、運搬した管を前記掘削工程で掘削した敷設・埋設個所に設置する管運搬・設置工程と、
前記管運搬・設置工程で設置した管と管を溶接する管溶接工程と、
埋め戻し材料を索道によって運搬し、運搬した埋め戻し材料を用いて、掘削した敷設・埋設個所を索道と急傾斜地用油圧ショベルによって埋め戻しする埋め戻し工程と
を備えていることを特徴とする急斜面のパイプライン敷設・埋設方法。
[1] A method of laying and burying a pipeline on a steep slope,
An excavation process for excavating the place where the pipeline is laid and buried with a hydraulic excavator for steep slopes;
A pipe transportation / installation process in which a pipe to be laid / buried is transported by a cableway, and the transported pipe is installed in a laying / burial site excavated in the excavation process;
A pipe welding process for welding the pipe installed in the pipe transportation / installation process; and
A steep slope characterized by having a backfilling process in which the backfill material is transported by a cableway, and the excavated laying / burying site is backfilled by a cableway and a steep slope hydraulic excavator using the transported backfill material. Pipeline laying and burying method.

本発明においては、急斜面にパイプラインを敷設・埋設するに際して、大規模な用地を必要とせずに、パイプラインの埋設位置に沿った小規模な範囲に限定した施工が可能になる。   In the present invention, when laying and burying a pipeline on a steep slope, it is possible to perform construction limited to a small area along the pipeline burying position without requiring a large-scale site.

本発明の一実施形態を述べる。   One embodiment of the present invention will be described.

本発明の一実施形態においては、急斜面にパイプラインを敷設・埋設するに際して、図1に示すように、傾斜地用ショベル21と索道(ケーブルクレーン)22を適切に組み合わせて、(a)掘削工程、(b)管運搬・設置工程、(c)管溶接工程、(d)埋め戻し工程の施工手順をとるようにしている。   In one embodiment of the present invention, when laying and burying a pipeline on a steep slope, as shown in FIG. 1, an excavation step, (a) excavation step, The construction procedure of (b) pipe transportation / installation process, (c) pipe welding process, (d) backfilling process is taken.

まず、(a)掘削工程においては、図1(a)に示すように、既存の傾斜地用ショベル21を用いて、パイプラインの敷設・埋設作業に必要な最小限の範囲20の掘削を行う。   First, in (a) the excavation process, as shown in FIG. 1 (a), excavation in a minimum range 20 necessary for pipeline laying and burying work is performed using an existing excavator 21 for inclined land.

なお、掘削土の運搬については、傾斜地用ショベル21によって掘削土の運搬を行う場合は、傾斜下部へ撒き出すか、傾斜地用ショベル21のバケットによって運搬することになるため効率的でないので、索道22を併用することによって安全で効率的に運搬できる。   In addition, about conveyance of excavation soil, when excavation soil is conveyed with the excavator 21 for sloping ground, it is not efficient because it is carried out to the lower part of the sloping or is transported by the bucket of the excavator 21 for sloping land. Can be transported safely and efficiently.

また、小規模なパイプライン敷設・埋設工事の場合には、掘削土の運搬は索道22ではなく、モノレールを用いてもよい。   Further, in the case of a small-scale pipeline laying / buried construction, the excavated soil may be transported not by the cableway 22 but by a monorail.

次に、(b)管運搬・設置工程においては、図1(b)に示すように、斜面下部もしくは斜面上部に設営した資材ヤードより管11を索道22によって運搬し、掘削工程で掘削した敷設・埋設個所に管11を設置する。このように、管11の運搬・設置を索道22によって行うことで、管11を安全で迅速に運搬・設置することができる。   Next, in the (b) pipe transport / installation process, as shown in FIG. 1 (b), the pipe 11 is transported by the cableway 22 from the material yard constructed at the lower part of the slope or the upper part of the slope, and laid by excavation in the excavation process.・ Install the pipe 11 in the buried part. Thus, by carrying and installing the pipe 11 by the cableway 22, the pipe 11 can be safely and quickly carried and installed.

次に、(c)管溶接工程においては、図1(c)に示すように、既に敷設されている管(敷設管)10と新たに設置した管11とを溶接する。   Next, in the (c) pipe welding process, as shown in FIG. 1 (c), the pipe (laying pipe) 10 already laid and the newly installed pipe 11 are welded.

その際に、溶接員31が溶接作業を行うために、平坦な溶接作業床を掘削する必要があるが、傾斜地用ショベル21を用いることで、必要・充分な寸法の溶接作業床を無駄なく効率的に掘削することができる。   At that time, in order for the welder 31 to perform the welding work, it is necessary to excavate a flat welding work floor. By using the excavator 21 for the sloping ground, the necessary and sufficient size of the welding work floor can be efficiently used. Can be excavated.

また、溶接用の機材や検査用の機材等を斜面上部もしくは斜面下部に設営された資材ヤードより迅速に運搬することができる。   In addition, welding equipment, inspection equipment, and the like can be quickly transported from the material yard set up at the upper or lower slope.

最後に、(d)埋め戻し工程においては、図1(d)に示すように、索道22を用いて、埋め戻し材料(良質土)を土砂バケット(又は底開き大型土嚢等)33によって運搬し、その埋め戻し材料を土砂バケット(又は底開き大型土嚢等)33から掘削溝30に投入する。そして、転圧・締め固め作業を行う。   Finally, (d) in the backfilling process, as shown in FIG. 1 (d), the backfilling material (good quality soil) is transported by the earth and sand bucket (or large open sandbag etc.) 33 using the cableway 22. Then, the backfill material is put into the excavation groove 30 from the earth and sand bucket (or the large sandbag or the like having a bottom opening) 33. Then, rolling and compacting work is performed.

その際、急傾斜地では人力による転圧・締め固めは非効率なため、管11の保護のため管11の周囲は人力により転圧・締め固めを行い、その他は傾斜地用ショベル21による機械転圧・締め固めを行う。これにより、充分な締め固めが行われ、傾斜面の安定性を確保することができる。   At that time, since rolling and compacting by manpower is inefficient in steep slopes, the circumference of the tube 11 is compacted and compacted by manpower to protect the tube 11, and the others are mechanically compacted by the excavator 21 for sloping land.・ Consolidate. Thereby, sufficient compaction is performed and the stability of an inclined surface can be ensured.

このようにして、この実施形態においては、急斜面にパイプラインを敷設・埋設するに際して、傾斜地用ショベル21と索道(ケーブルクレーン)22を適切に組み合わせて施工するようにしているので、従来のような大規模な仮設道等の造成工事が不要となり、限定された位置での施工ができるため、事前に地質調査を行うことで、斜面上のより安定した地質条件位置を選定し施工できる。これにより、施工の確実性が向上し、工事中および工事復旧後の斜面安定性に優れている。また、工事のための伐採、開発行為を最小限とすることができる。   Thus, in this embodiment, when laying and burying a pipeline on a steep slope, the excavator 21 for sloping land and the cableway (cable crane) 22 are appropriately combined, so that Since construction work such as a large-scale temporary road is not required and construction can be performed at a limited location, it is possible to select and construct more stable geological condition positions on the slope by conducting a geological survey in advance. As a result, the certainty of construction is improved, and the slope stability during construction and after construction restoration is excellent. In addition, logging for construction and development activities can be minimized.

本発明の一実施形態における施工手順を示す図である。It is a figure which shows the construction procedure in one Embodiment of this invention. 従来技術を示す図である。It is a figure which shows a prior art.

符号の説明Explanation of symbols

10 敷設管
11 管
21 傾斜地用ショベル
22 索道(ケーブルクレーン)
30 掘削範囲(掘削溝)
31 溶接員
32 溶接作業床
33 土砂バケット又は底開き大型土嚢等
51 油圧ショベル(バックホー)
52 キャリアダンプ
10 Laying pipe 11 Pipe 21 Excavator for sloping land 22 Cableway (cable crane)
30 Excavation range (excavation groove)
31 Welders 32 Welding floor 33 Sediment bucket or large opening sandbag 51 Hydraulic excavator (backhoe)
52 Carrier dump

Claims (1)

急斜面にパイプラインを敷設・埋設する方法であって、
パイプラインを敷設・埋設する個所を急傾斜地用油圧ショベルによって掘削する掘削工程と、
敷設・埋設する管を索道によって運搬し、運搬した管を前記掘削工程で掘削した敷設・埋設個所に設置する管運搬・設置工程と、
前記管運搬・設置工程で設置した管と管を溶接する管溶接工程と、
埋め戻し材料を索道によって運搬し、運搬した埋め戻し材料を用いて、掘削した敷設・埋設個所を索道と急傾斜地用油圧ショベルによって埋め戻しする埋め戻し工程と
を備えていることを特徴とする急斜面のパイプライン敷設・埋設方法。
A method of laying and burying pipelines on steep slopes,
An excavation process for excavating the place where the pipeline is laid and buried with a hydraulic excavator for steep slopes;
A pipe transportation / installation process in which a pipe to be laid / buried is transported by a cableway, and the transported pipe is installed at a laying / burial site excavated in the excavation process;
A pipe welding process of welding the pipe and the pipe installed in the pipe transportation / installation process;
A steep slope characterized by having a backfilling process in which the backfill material is transported by a cableway, and the excavated laying / burying site is backfilled by a cableway and a steep slope hydraulic excavator using the transported backfill material. Pipeline laying and burying method.
JP2008296660A 2008-11-20 2008-11-20 Laying and burying pipelines on steep slopes Active JP5115456B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008296660A JP5115456B2 (en) 2008-11-20 2008-11-20 Laying and burying pipelines on steep slopes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008296660A JP5115456B2 (en) 2008-11-20 2008-11-20 Laying and burying pipelines on steep slopes

Publications (2)

Publication Number Publication Date
JP2010121724A true JP2010121724A (en) 2010-06-03
JP5115456B2 JP5115456B2 (en) 2013-01-09

Family

ID=42323235

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008296660A Active JP5115456B2 (en) 2008-11-20 2008-11-20 Laying and burying pipelines on steep slopes

Country Status (1)

Country Link
JP (1) JP5115456B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108662280A (en) * 2018-05-28 2018-10-16 中国化学工程第三建设有限公司 A kind of Novel flue gas pipeline construction method
CN111677976A (en) * 2020-07-09 2020-09-18 中国电建集团成都勘测设计研究院有限公司 Water supply pipeline protection structure capable of being used for hydroelectric engineering side slope region in canyon region

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6181307A (en) * 1984-09-26 1986-04-24 Yoshihiro Otani Method for taking-out of lumber from thinning
JPH05105122A (en) * 1991-10-16 1993-04-27 Kobelco Kenki Eng Kk Working vehicle for steep slope
JP2002167762A (en) * 2000-11-30 2002-06-11 Komatsu Ltd Slope face executing machine and slope face executing method
JP2003063383A (en) * 2001-08-22 2003-03-05 Nikkari Co Ltd Long material transporting device and long material transporting method by the same
JP2004284768A (en) * 2003-03-24 2004-10-14 Komatsu Ltd Pipe layer
JP2005155220A (en) * 2003-11-27 2005-06-16 Sekisui House Ltd Use method of excavated soil
JP2006300219A (en) * 2005-04-21 2006-11-02 Jfe Engineering Kk Anchor structure of pipeline

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6181307A (en) * 1984-09-26 1986-04-24 Yoshihiro Otani Method for taking-out of lumber from thinning
JPH05105122A (en) * 1991-10-16 1993-04-27 Kobelco Kenki Eng Kk Working vehicle for steep slope
JP2002167762A (en) * 2000-11-30 2002-06-11 Komatsu Ltd Slope face executing machine and slope face executing method
JP2003063383A (en) * 2001-08-22 2003-03-05 Nikkari Co Ltd Long material transporting device and long material transporting method by the same
JP2004284768A (en) * 2003-03-24 2004-10-14 Komatsu Ltd Pipe layer
JP2005155220A (en) * 2003-11-27 2005-06-16 Sekisui House Ltd Use method of excavated soil
JP2006300219A (en) * 2005-04-21 2006-11-02 Jfe Engineering Kk Anchor structure of pipeline

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108662280A (en) * 2018-05-28 2018-10-16 中国化学工程第三建设有限公司 A kind of Novel flue gas pipeline construction method
CN108662280B (en) * 2018-05-28 2019-11-12 中国化学工程第三建设有限公司 A kind of Novel flue gas pipeline construction method
CN111677976A (en) * 2020-07-09 2020-09-18 中国电建集团成都勘测设计研究院有限公司 Water supply pipeline protection structure capable of being used for hydroelectric engineering side slope region in canyon region

Also Published As

Publication number Publication date
JP5115456B2 (en) 2013-01-09

Similar Documents

Publication Publication Date Title
CN106369223B (en) A kind of silt stratum pipe jacking construction method
RU2573086C2 (en) Device to install pipelines in soil
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN110219359A (en) A kind of Submersed type inspection well and its construction method
CN104895111B (en) The construction method of integrated pipe canal in weak soil ground
CN105387273A (en) Method for constructing natural gas pipelines in mountain environment
JP5115456B2 (en) Laying and burying pipelines on steep slopes
CN106320368A (en) Construction method applicable to open-excavation pipeline at compound stratum
CN108797609A (en) Environmentally protective steel pipe steel plate combination construction method for supporting
RU2696886C1 (en) Method of stimulating degassing of landfill
CN113404050A (en) Installation method of integrated steel cylinder underwater protection system
JP4863311B2 (en) Excavation method
CN106247007B (en) The underlying laying direct-burried construction method of remote major diameter industrial pipeline deadweight displacement
JP5142269B2 (en) Casing installation device and buried object laying method
JP2021080798A (en) Pipeline construction method using propulsion method
RU2561954C2 (en) Pipeline section exposure
KR102420920B1 (en) Horizontal Directional Drilling method for riverside and beach poor ground
CN107326929A (en) A kind of method of Duo Cang undergrounds integrated pipe earth excavation under Larsen steel sheet pile supporting
CN112815145B (en) Double-pipe immersed pipe construction method and heating pipeline system
CN106896418A (en) A kind of detection method of underground utilities
CN206956730U (en) Multiple tracks annular concrete support pit earthwork outward transport constructing structure
Henderson et al. Case Study: Design and Construction of the 2015 London Burbrook Trunk Storm Sewer
JP3724734B2 (en) Underground cavity filling method
RU2591073C2 (en) Technological complex for opening section of underground pipeline
Schneider et al. Innovative design and deep trench excavation for a groundwater collection improvement project: Part 2 of 2 case study from the former Sullivan Mine, Kimberley BC

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110304

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20120321

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20120327

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120813

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120918

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121001

R150 Certificate of patent or registration of utility model

Ref document number: 5115456

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151026

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350