CN106320368A - A construction method suitable for open-cut pipelines in composite strata - Google Patents

A construction method suitable for open-cut pipelines in composite strata Download PDF

Info

Publication number
CN106320368A
CN106320368A CN201610695867.2A CN201610695867A CN106320368A CN 106320368 A CN106320368 A CN 106320368A CN 201610695867 A CN201610695867 A CN 201610695867A CN 106320368 A CN106320368 A CN 106320368A
Authority
CN
China
Prior art keywords
excavation
layer
trench
slope
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610695867.2A
Other languages
Chinese (zh)
Inventor
崔立志
姚亚军
王婧馨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201610695867.2A priority Critical patent/CN106320368A/en
Publication of CN106320368A publication Critical patent/CN106320368A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention relates to the field of building construction, in particular to a construction method suitable for an open cut pipeline of a composite stratum, which comprises the following steps: measuring paying off, replacing and filling the mixture in the excavation lines at two sides of the excavation groove, digging a slope on the upper soil layer, digging a slope on the lower rock layer, replacing and filling the sand and stone at the bottom of the foundation pit of the excavation groove, installing a pipeline and backfilling medium and coarse sand and earthwork; the invention adopts a construction method of the 'hidden cofferdam', the bad soil layers on the upper parts of the two sides of the groove are filled with the mixture of cement and plain soil which are mixed in advance, the hidden cofferdam is formed by layering and compacting to achieve the water stopping effect, the side slope is hung with a net and anchored in the excavation process of the groove, the rock layer on the lower part is broken by a breaking hammer, the construction process is simple, the construction difficulty is low, the requirement of mechanical equipment is less, the construction period is shortened, the construction cost is saved, and the method is safe and effective.

Description

一种适用于复合地层明挖管道的施工方法A construction method suitable for open-cut pipelines in composite strata

技术领域technical field

本发明涉及建筑施工领域,具体涉及富水、岩土复合地层条件下深基坑明挖管道施工方法。The invention relates to the field of building construction, in particular to a method for constructing open-cut pipelines in deep foundation pits under the conditions of water-rich and rock-soil composite strata.

背景技术Background technique

在改革开放以来,我国政治、经济、文化事业的快速发展,带来了城市建设的高潮,在城市排水、雨污水治理过程中,地下管道、管廊的建设,成为一大发展趋势。为此,复杂地质条件下深基坑明挖管道施工变得日益频繁。如何确保富水、岩土复合地质条件下深基坑明挖管道施工过程中沟槽支护、止水成为一项重点和难点。目前经常采用的为拉森钢板桩支护结构类型。以下简单叙述一下拉森钢板桩支护结构存在的不足之处:Since the reform and opening up, the rapid development of my country's political, economic, and cultural undertakings has brought about a climax of urban construction. In the process of urban drainage and rainwater treatment, the construction of underground pipes and pipe galleries has become a major development trend. For this reason, the construction of open-cut pipelines in deep foundation pits under complex geological conditions has become increasingly frequent. How to ensure trench support and water stop during the construction of open excavation pipelines in deep foundation pits under water-rich and rock-soil complex geological conditions has become an important and difficult point. Larsen steel sheet pile support structure is often used at present. The following is a brief description of the shortcomings of the Larsen steel sheet pile support structure:

拉森钢板桩支护是先施打拉森钢板桩,其钢板桩的入土深度与沟槽深度比不得小于1:1,施打完成后土方开挖至设计钢围檩位置时安装钢围檩、钢支撑,将钢支撑的两端与钢围檩焊接牢固,以达到支撑水平荷载和止水的效果,但是当遇到沟槽上部为不良土层且出水量极大,下部为弱风化岩层的复杂地质条件情况下,拉森钢板桩无法入岩,在安装钢围檩、钢支撑支护后用机械无法破除下部岩层,只能采用人工破除,这样存在较大的安全隐患,止水效果不佳,导致施工工期过长,时间成本较高,直接影响经济效益。The Larsen steel sheet pile support is to install the Larsen steel sheet pile first, and the ratio of the depth of the steel sheet pile to the trench depth should not be less than 1:1. After the excavation is completed, the steel purlin will be installed when the earthwork is excavated to the designed steel purlin position. , Steel support, weld the two ends of the steel support with the steel purlins firmly to achieve the effect of supporting horizontal loads and stopping water. However, when the upper part of the trench is a bad soil layer with a large amount of water, the lower part is a weakly weathered rock layer Under complex geological conditions, Larsen steel sheet piles cannot enter the rock, and after installing steel purlins and steel supports, the lower rock formations cannot be removed by machinery, and can only be removed manually. Poor construction results in long construction period and high time cost, which directly affects economic benefits.

发明内容Contents of the invention

针对上述问题,本发明要解决的技术问题在于利用“暗围堰”法来止水,提供一种适用于富水、岩土复合地层条件下深基坑明挖管道施工方法。In view of the above-mentioned problems, the technical problem to be solved by the present invention is to use the "hidden cofferdam" method to stop water, and to provide a deep foundation pit open-cut pipeline construction method suitable for water-rich and rock-soil composite stratum conditions.

为达到上述目的,本发明采用技术方案如下:To achieve the above object, the present invention adopts technical scheme as follows:

一种适用于复合地层明挖管道的施工方法,包括以下步骤:A construction method suitable for open-cut pipelines in composite strata, comprising the following steps:

1)测量放线:根据施工现场检查井的井位和开挖沟槽的深度,测放出开挖沟槽两侧的田螺层、液化土层的2米宽的开挖线;1) Measurement and setting out: According to the well position of the inspection well on the construction site and the depth of the excavation trench, measure and release the 2-meter-wide excavation line of the snail layer and liquefied soil layer on both sides of the excavation trench;

2)开挖沟槽两侧开挖线内拌合物的换填:根据开挖线由上至下开挖施工,首先将开挖线内上部的土层挖除,再将下部的田螺层、液化土层挖除;当田螺层、液化土层挖除完毕后,将预先搅拌制备的水泥和素土的拌合物分层回填夯实,每层铺摊的厚度为500-800毫米,每层摊铺完成后采用挖掘机进行碾压,然后使用振动夯夯实,每层碾压和夯实的遍数大于等于3-5遍;所述拌合物中水泥的质量与素土的湿质量比为10%~15%;2) Replacement of the mixture in the excavation line on both sides of the excavation trench: according to the excavation line from top to bottom, first excavate the upper soil layer in the excavation line, and then remove the lower snail layer 1. Excavation of the liquefied soil layer; when the snail layer and the liquefied soil layer have been excavated, backfill and compact the mixture of cement and plain soil prepared by mixing in advance, and the thickness of each layer of paving is 500-800 mm. After layer paving is completed, an excavator is used for rolling, and then a vibratory tamp is used for compaction. The number of times for each layer of rolling and compaction is greater than or equal to 3-5 times; the mass ratio of cement in the mixture to the wet mass of plain soil 10% to 15%;

3)上部土层放坡开挖:开挖沟槽内的上部土层按坡度1:0.5放坡开挖,开挖后对上部土层的坡面进行挂网喷射混泥土处理;3) Slope excavation of the upper soil layer: the upper soil layer in the excavation trench is excavated according to the slope of 1:0.5, and the slope of the upper soil layer is treated with hanging net spraying concrete after excavation;

4)下部岩层放坡开挖:开挖沟槽内的上部土层开挖至风华岩及灰岩层时,于沟槽两侧各留1米宽的台阶,再采用破碎锤将台阶以下的岩层按坡度1:0.5放坡开挖;4) Slope excavation of the lower rock layer: When excavating the upper soil layer in the trench to the Fenghua rock and limestone layer, leave a step with a width of 1 meter on both sides of the trench, and then use a breaker to break the rock layer below the step. Grading and excavation according to the slope of 1:0.5;

5)开挖沟槽基坑底的砂石料换填:岩层开挖完成后,用砂石料对基坑底部换填找平至管道底部预设标高;5) Replacement of sand and gravel at the bottom of excavated trench foundation pit: After the excavation of the rock layer is completed, replace and level the bottom of the foundation pit with sand and gravel to the preset elevation of the bottom of the pipeline;

6)管道安装;6) Pipeline installation;

7)中粗砂及土方回填。7) Medium-coarse sand and earthwork backfill.

具体的,所述开挖线采用灰白粉洒线。Specifically, the excavation line is sprinkled with gray and white powder.

具体的,所述步骤2)和步骤3)中均以20米长的开挖沟槽为一段,分段开挖。Specifically, in the step 2) and step 3), the 20-meter-long excavation trench is used as a section, and excavated in sections.

具体的,所述步骤3)中挂网喷射混泥土处理步骤如下:在坡面垂直楔入若干直径10毫米,长40厘米的插筋,插筋纵横间距为1米,于各插筋上铺设一层Φ1*40*40的钢丝网,挂网完成后即可喷射混凝土,所述混凝土为强度C20的细石混凝土,混泥土喷射厚度为100毫米。Concretely, in the above step 3), the treatment steps of hanging net sprayed concrete are as follows: Wedging a number of 10 mm diameter and 40 cm long insert bars vertically on the slope surface, the vertical and horizontal spacing of the insert bars is 1 meter, and laying on each insert bar A layer of Φ1*40*40 steel wire mesh can be sprayed concrete after hanging the mesh. The concrete is fine stone concrete with a strength of C20, and the thickness of the concrete sprayed is 100 mm.

具体的,所述步骤6)按以下步骤进行:管道吊装、管材安装、标高及轴线控制、管道外接口挂网抹带、180°包管混凝土浇筑、管道内接口抹带。Specifically, the step 6) is carried out according to the following steps: pipe hoisting, pipe installation, elevation and axis control, pipe outer interface hanging net wiping tape, 180° guaranteed concrete pouring, and pipe inner interface wiping tape.

具体的,所述步骤7)包括以下步骤:在安装好的管道两侧同时均匀下料中粗砂回填,每层回填厚度500毫米,并逐层洒水夯实,回填的中粗砂干重大于等于16KN/m³;回填至管道顶部以上500毫米处时,采用开挖沟槽挖出的土回填至原地面标高,于开挖沟槽两侧对称回填并分层夯实。Specifically, the step 7) includes the following steps: backfill medium-coarse sand evenly on both sides of the installed pipeline, each layer of backfill thickness is 500 mm, and water and tamp layer by layer, the dry weight of the medium-coarse sand backfilled is greater than or equal to 16KN/m³; when backfilling to 500 mm above the top of the pipeline, backfill with soil excavated from the excavation trench to the original ground level, backfill symmetrically on both sides of the excavation trench and compact it in layers.

本发明的有益效果在于:本发明可以在很大程度的节约成本、缩短工期、降低施工难度、减少安全隐患。The beneficial effect of the present invention is that: the present invention can save cost to a great extent, shorten construction period, reduce construction difficulty and reduce potential safety hazards.

由于在富水、岩土复杂地质条件下深基坑明挖管道施工过程中,需要对基坑进行支护和止水,否则无法进行管道安装作业,而拉森钢板桩支护施工钢板桩无法入岩,尤其在下部岩层断面凹凸不平的情况下钢板桩下端与岩层接触位置存在较大空隙导致止水效果不佳,出水量大,在沟槽开挖、管道安装施工过程中影响作业,存在较大的安全隐患,并且在安装钢围檩、钢支撑支护后沟槽下部石方用机械难以破除只能采用人工破除,在遇到弱分化岩层时人工作业效率差,严重的延长了施工工期,增加了施工成本,施工难度较大。Due to the deep foundation pit open excavation pipeline construction process under rich water and complex rock and soil geological conditions, the foundation pit needs to be supported and water-stopped, otherwise the pipeline installation operation cannot be carried out, and the Larsen steel sheet pile support construction steel sheet pile cannot Into the rock, especially in the case of uneven cross-section of the lower rock formation, there is a large gap between the lower end of the steel sheet pile and the rock formation, resulting in poor water-stop effect and large water output, which affects the operation during trench excavation and pipeline installation. Larger safety hazards, and after installing steel purlins and steel supports, the stonework at the lower part of the trench is difficult to break with machinery and can only be broken manually. When encountering weakly differentiated rock formations, the efficiency of manual work is poor, which seriously prolongs the The construction period increases the construction cost and makes the construction more difficult.

而本发明“暗围堰”施工方法是将沟槽两侧上部不良土层用提前拌制而成的水泥、素土拌合物换填,分层压实形成暗围堰来达到止水效果,在沟槽开挖过程中对边坡挂网喷锚,下部岩层用破碎锤破除,施工工艺简单,施工难度低,机械设备需求少,缩短了施工工期,节约施工成本,安全有效。The "dark cofferdam" construction method of the present invention is to replace the unfavorable soil layers on both sides of the ditch with cement and plain soil mixture mixed in advance, and layer and compact to form a dark cofferdam to achieve the water-stop effect. , In the process of trench excavation, spray anchors to the slope, and break the lower rock formation with a breaker. The construction process is simple, the construction difficulty is low, the demand for mechanical equipment is small, the construction period is shortened, the construction cost is saved, and it is safe and effective.

附图说明Description of drawings

下面结合附图就本发明的具体实施方式作进一步说明,其中:The specific embodiment of the present invention will be further described below in conjunction with accompanying drawing, wherein:

图1是本发明中开挖沟槽两侧开挖线放线示意图;Fig. 1 is a schematic diagram of the excavation line setting-out on both sides of the excavation trench in the present invention;

图2是本发明中开挖沟槽内分层放坡开挖示意图。Fig. 2 is a schematic diagram of layered slope excavation in an excavation trench according to the present invention.

具体实施方式detailed description

本发明的一种适用于复合地层明挖管的道施工方法,具体施工操作步骤如下:A kind of road construction method that is applicable to the open-cut pipe of compound stratum of the present invention, concrete construction operation steps are as follows:

(1)测量放线(1) Measuring and setting out

参照图1所示,根据施工现场的检查井2的井位和开挖沟槽1的深度测放开挖沟槽1两侧的田螺层、液化土层的2米宽的开挖线3,开挖沟槽宽度d由施工管道要求而定,开挖线3用白灰粉洒线,避免欠挖或超挖。With reference to shown in Fig. 1, according to the well position of the inspection well 2 on the construction site and the depth of excavation trench 1, release the snail layer on both sides of excavation trench 1, the excavation line 3 of 2 meters wide of liquefied soil layer, The width d of the excavation trench is determined by the requirements of the construction pipeline, and the excavation line 3 is sprinkled with lime powder to avoid under-excavation or over-excavation.

(2)开挖沟槽两侧开挖线内拌合物的换填(2) Replacement of the mixture in the excavation line on both sides of the excavation trench

①田螺层、液化土层开挖:开挖施工至上而下,根据开挖线首先将开挖线内上部土层清除,再进行田螺、液化土层挖除,开挖宽度开挖线宽2m,以每20m作为一段进行开挖,挖除过程中严禁超挖侧边或底部稳定土层,严格控制开挖深度。现场做到随挖随运,采用自卸汽车运至指定地点集中堆放,以免污染环境。①Excavation of snail layer and liquefied soil layer: Excavation is carried out from top to bottom. According to the excavation line, the upper soil layer inside the excavation line is first removed, and then the snail and liquefied soil layer are excavated. The width of the excavation line is 2m , and excavate every 20m as a section. During the excavation process, it is strictly forbidden to over-excavate the side or bottom to stabilize the soil layer, and the excavation depth is strictly controlled. On-site excavation and transportation are carried out, and dump trucks are used to transport them to designated locations for centralized stacking to avoid environmental pollution.

②水泥、土拌合物换填施工:在田螺层、液化层土层清除完毕后立即将预先拌制的水泥、素土拌合物分层回填夯实(水泥参入比为:水泥的质量:素土的湿质量=10%-15%),以防止出现坍塌现象影响止水效果;每层铺摊厚度为500-800mm,每层摊铺完成后采用挖机进行碾压,然后使用振动夯夯实,每层碾压和夯实遍数不少于3-5遍。② Cement and soil mixture replacement construction: Immediately after the snail layer and liquefied layer soil layer are removed, the pre-mixed cement and plain soil mixture shall be backfilled and compacted in layers (the ratio of cement participation is: cement mass: plain Wet mass of soil = 10%-15%) to prevent collapse and affect the water-stop effect; the thickness of each layer of paving is 500-800mm, and after each layer of paving is completed, it is rolled by an excavator, and then compacted with a vibrating ram , the number of rolling and tamping times for each layer is not less than 3-5 times.

(3)上部土层放坡开挖(3) Slope excavation of the upper soil layer

参照图2所示,开挖段沟槽采用放坡开挖,坡度为1:0.5,在开挖过程中严格控制开挖边线,按上述换填施工的20m分段,分段施工,上一段管道安装完成后进行下一段土方开挖施工,严禁超挖,防止将已换填的水泥、素土拌合物挖除起不到止水效果。Referring to Figure 2, the trenches in the excavation section are excavated by grading, with a slope of 1:0.5. During the excavation process, the excavation sideline is strictly controlled, and the construction is carried out in sections according to the above-mentioned 20m replacement construction. After the pipeline installation is completed, the next section of earthwork excavation is to be carried out. Over-excavation is strictly prohibited to prevent the excavation of the cement and plain soil mixture that has been replaced and the water-stop effect will not be achieved.

由于开挖沟槽上部3-5m范围为不良土层,出水量大,边坡稳定性差,为防止坡面受雨水冲刷而产生溜坡现象,开挖后立即对修好的坡面进行挂网喷射混凝土:即在坡面垂直楔入直径10mm,长40cm的插筋,插筋纵横间距1m,于其上铺设一层Φ1*40*40的钢丝网4,钢丝网4挂网完成后即可喷射混凝土,混凝土强度为C20细石混凝土,厚度为100mm。Since the upper 3-5m range of the excavation trench is poor soil layer, the water output is large, and the stability of the slope is poor. In order to prevent the slope from being washed by the rainwater and cause the slope to slide, immediately spray the repaired slope with a net after excavation. Concrete: that is, wedging bars with a diameter of 10mm and a length of 40cm vertically on the slope, with a vertical and horizontal distance of 1m between the bars, and laying a layer of Φ1*40*40 steel wire mesh 4 on it. After the steel mesh 4 is hung, it can be sprayed Concrete, the concrete strength is C20 fine stone concrete, and the thickness is 100mm.

(4)下部岩层放坡开挖(4) Grading and excavation of the lower rock formation

上部土层土方放坡开挖完毕后,为防止上部不良土层在岩层破除过程中造成局部坍塌影响施工,待开挖至风化岩及灰岩层时,两边各留1m的台阶5,采用破碎锤破除岩层按1:0.5放坡开挖,开挖时严格控制基底标高,严禁超挖。After the slope excavation of the upper soil layer is completed, in order to prevent the upper unfavorable soil layer from causing local collapse during the rock layer breaking process and affecting the construction, when the weathered rock and limestone layers are excavated, a 1m step 5 is left on each side, and a breaker is used to Break the rock formation and excavate according to 1:0.5 grading, strictly control the base elevation during excavation, and over-excavation is strictly prohibited.

(5)开挖沟槽基坑底的砂石料换填(5) Replacement of sand and gravel at the bottom of excavated trench foundation pit

用破碎锤破除岩层时基坑底的标高应低于安装管道6底部的标高600mm,破除完成后用砂石料换填找平基坑至管道6底部设计标高,防止管道安装过程中管道6下沉。When breaking the rock formation with a breaker, the elevation of the bottom of the foundation pit should be 600mm lower than the elevation of the bottom of the installation pipeline 6. After the destruction is completed, replace and level the foundation pit with sand and gravel to the design elevation of the bottom of the pipeline 6, so as to prevent the pipeline 6 from sinking during the pipeline installation process.

(6)管道安装(6) Pipe installation

按以下步骤操作:管道吊装→管材安装→标高、轴线控制→管道外接口挂网抹带→180°包管混凝土浇筑→管道内接口抹带。Follow the steps below: pipe hoisting→pipe installation→elevation, axis control→pipeline external interface hang net wiping tape→180°pipe guarantee concrete pouring→pipe inner interface wiping tape.

(7)中粗砂及土方回填(7) Medium-coarse sand and earthwork backfill

在安装好的管道两侧同时均匀下料中粗砂回填,每层回填厚度500毫米,并逐层洒水夯实,回填的中粗砂干重大于等于16KN/m³;回填至管道顶部以上500毫米处时,采用开挖沟槽挖出的土回填至原地面标高,于开挖沟槽两侧对称回填并分层夯实。On both sides of the installed pipeline, medium-coarse sand is evenly fed and backfilled. The thickness of each layer of backfill is 500mm, and it is watered and compacted layer by layer. The dry weight of the backfilled medium-coarse sand is greater than or equal to 16KN/m³; backfill to 500mm above the top of the pipeline. When using the excavated trench, backfill it with the soil excavated to the original ground level, backfill symmetrically on both sides of the excavated trench and tamp it layer by layer.

以上所述,仅为本发明较佳具体实施方式,但本发明保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明披露的技术范围内,可轻易想到的变化或替换,都应涵盖在本发明的保护范围之内。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, any changes or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in the present invention, All should be covered within the protection scope of the present invention.

Claims (6)

1.一种适用于复合地层明挖管道的施工方法,其特征在于,包括以下步骤:1. A construction method suitable for open-cut pipelines in composite strata, characterized in that it may further comprise the steps: 1)测量放线:根据施工现场检查井的井位和开挖沟槽的深度,测放出开挖沟槽两侧的田螺层、液化土层的2米宽的开挖线;1) Measurement and setting out: According to the well position of the inspection well on the construction site and the depth of the excavation trench, measure and release the 2-meter-wide excavation line of the snail layer and liquefied soil layer on both sides of the excavation trench; 2)开挖沟槽两侧开挖线内拌合物的换填:根据开挖线由上至下开挖施工,首先将开挖线内上部的土层挖除,再将下部的田螺层、液化土层挖除;当田螺层、液化土层挖除完毕后,将预先搅拌制备的水泥和素土的拌合物分层回填夯实,每层铺摊的厚度为500-800毫米,每层摊铺完成后采用挖掘机进行碾压,然后使用振动夯夯实,每层碾压和夯实的遍数大于等于3-5遍;所述拌合物中水泥的质量与素土的湿质量比为10%~15%;2) Replacement of the mixture in the excavation line on both sides of the excavation trench: according to the excavation line from top to bottom, first excavate the upper soil layer in the excavation line, and then remove the lower snail layer 1. Excavation of the liquefied soil layer; when the snail layer and the liquefied soil layer have been excavated, backfill and compact the mixture of cement and plain soil prepared by mixing in advance, and the thickness of each layer of paving is 500-800 mm. After layer paving is completed, an excavator is used for rolling, and then a vibratory tamp is used for compaction. The number of times for each layer of rolling and compaction is greater than or equal to 3-5 times; the mass ratio of cement in the mixture to the wet mass of plain soil 10% to 15%; 3)上部土层放坡开挖:开挖沟槽内的上部土层按坡度1:0.5放坡开挖,开挖后对上部土层的坡面进行挂网喷射混泥土处理;3) Slope excavation of the upper soil layer: the upper soil layer in the excavation trench is excavated according to the slope of 1:0.5, and the slope of the upper soil layer is treated with hanging net spraying concrete after excavation; 4)下部岩层放坡开挖:开挖沟槽内的上部土层开挖至风华岩及灰岩层时,于沟槽两侧各留1米宽的台阶,再采用破碎锤将台阶以下的岩层按坡度1:0.5放坡开挖;4) Slope excavation of the lower rock layer: When excavating the upper soil layer in the trench to the Fenghua rock and limestone layer, leave a step with a width of 1 meter on both sides of the trench, and then use a breaker to break the rock layer below the step. Grading and excavation according to the slope of 1:0.5; 5)开挖沟槽基坑底的砂石料换填:岩层开挖完成后,用砂石料对基坑底部换填找平至管道底部预设标高;5) Replacement of sand and gravel at the bottom of excavated trench foundation pit: After the excavation of the rock layer is completed, replace and level the bottom of the foundation pit with sand and gravel to the preset elevation of the bottom of the pipeline; 6)管道安装;6) Pipeline installation; 7)中粗砂及土方回填。7) Medium-coarse sand and earthwork backfill. 2.根据权利要求1所述的一种适用于复合地层明挖管道的施工方法,其特征在于,所述开挖线采用灰白粉洒线。2. A construction method suitable for open-cut pipelines in composite strata according to claim 1, characterized in that the excavation line is sprinkled with gray and white powder. 3.根据权利要求1所述的一种适用于复合地层明挖管道的施工方法,其特征在于,所述步骤2)和步骤3)中均以20米长的开挖沟槽为一段,分段开挖。3. A construction method suitable for open-cut pipelines in composite strata according to claim 1, characterized in that, in the step 2) and step 3), the 20-meter-long excavation trench is divided into one section and divided into two sections. segment excavation. 4.根据权利要求1所述的一种适用于复合地层明挖管道的施工方法,其特征在于,所述步骤3)中挂网喷射混泥土处理步骤如下:在坡面垂直楔入若干直径10毫米,长40厘米的插筋,插筋纵横间距为1米,于各插筋上铺设一层Φ1*40*40的钢丝网,挂网完成后即可喷射混凝土,所述混凝土为强度C20的细石混凝土,混泥土喷射厚度为100毫米。4. A construction method suitable for open-cut pipelines in composite strata according to claim 1, characterized in that, in the step 3), the sprayed concrete treatment steps are as follows: Wedging several diameters 10 vertically on the slope surface mm, 40 cm in length, the vertical and horizontal spacing of the bars is 1 meter, and a layer of Φ1*40*40 steel wire mesh is laid on each of the bars, and the concrete can be sprayed after the net is hung. The concrete is of strength C20 Fine stone concrete, the concrete spraying thickness is 100mm. 5.根据权利要求1所述的一种适用于复合地层明挖管道的施工方法,其特征在于,所述步骤6)按以下步骤进行:管道吊装、管材安装、标高及轴线控制、管道外接口挂网抹带、180°包管混凝土浇筑、管道内接口抹带。5. A construction method suitable for open-cut pipelines in composite strata according to claim 1, characterized in that the step 6) is carried out according to the following steps: pipeline hoisting, pipe installation, elevation and axis control, pipeline external interface Hanging net wiping tape, 180° guaranteed concrete pouring, and pipe inner interface wiping tape. 6.根据权利要求1所述的一种适用于复合地层明挖管道的施工方法,其特征在于,所述步骤7)包括以下步骤:在安装好的管道两侧同时均匀下料中粗砂回填,每层回填厚度500毫米,并逐层洒水夯实,回填的中粗砂干重大于等于16KN/m³;回填至管道顶部以上500毫米处时,采用开挖沟槽挖出的土回填至原地面标高,于开挖沟槽两侧对称回填并分层夯实。6. A construction method suitable for open-cut pipelines in composite strata according to claim 1, characterized in that the step 7) includes the following steps: uniformly blanking medium coarse sand and backfilling both sides of the installed pipeline at the same time , the backfill thickness of each layer is 500 mm, and watering and compacting layer by layer, the dry weight of the medium-coarse sand backfilled is greater than or equal to 16KN/m³; when backfilling to a position 500 mm above the top of the pipeline, use the soil excavated from the excavation trench to backfill to the original ground Elevation, backfill symmetrically on both sides of the excavated trench and compact it layer by layer.
CN201610695867.2A 2016-08-21 2016-08-21 A construction method suitable for open-cut pipelines in composite strata Pending CN106320368A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610695867.2A CN106320368A (en) 2016-08-21 2016-08-21 A construction method suitable for open-cut pipelines in composite strata

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610695867.2A CN106320368A (en) 2016-08-21 2016-08-21 A construction method suitable for open-cut pipelines in composite strata

Publications (1)

Publication Number Publication Date
CN106320368A true CN106320368A (en) 2017-01-11

Family

ID=57743357

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610695867.2A Pending CN106320368A (en) 2016-08-21 2016-08-21 A construction method suitable for open-cut pipelines in composite strata

Country Status (1)

Country Link
CN (1) CN106320368A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106978843A (en) * 2017-04-25 2017-07-25 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology
CN108412016A (en) * 2018-03-15 2018-08-17 中建五局土木工程有限公司 Underground tube body assures construction method
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN115978296A (en) * 2022-12-08 2023-04-18 宁波市政工程建设集团股份有限公司 Anti-deformation construction method for electric melting connection of large-diameter flexible pipeline
CN117822611A (en) * 2023-12-08 2024-04-05 中水淮河规划设计研究有限公司 A method for landfilling construction of foundation pit pipe wells in water conservancy projects

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1469028A1 (en) * 1986-07-02 1989-03-30 Московский гидромелиоративный институт Trench for laying thin-walled pipeline
CN1851144A (en) * 2006-05-12 2006-10-25 江西基业科技有限公司 Column-hammer strong-tamper displacing base kit supporting construction method
CN101749485A (en) * 2008-12-18 2010-06-23 上海市机械施工有限公司 Pipeline laying construction method combining non-excavation jacking and liquid nitrogen horizontal freezing excavation laying
CN103527847A (en) * 2013-10-30 2014-01-22 重庆大学 Pipe burying structure capable of reducing pipe top vertical loads and construction method for pipe burying structure
CN103526768A (en) * 2013-11-01 2014-01-22 科达集团股份有限公司 Construction method for partitioning strong permeable stratum

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1469028A1 (en) * 1986-07-02 1989-03-30 Московский гидромелиоративный институт Trench for laying thin-walled pipeline
CN1851144A (en) * 2006-05-12 2006-10-25 江西基业科技有限公司 Column-hammer strong-tamper displacing base kit supporting construction method
CN101749485A (en) * 2008-12-18 2010-06-23 上海市机械施工有限公司 Pipeline laying construction method combining non-excavation jacking and liquid nitrogen horizontal freezing excavation laying
CN103527847A (en) * 2013-10-30 2014-01-22 重庆大学 Pipe burying structure capable of reducing pipe top vertical loads and construction method for pipe burying structure
CN103526768A (en) * 2013-11-01 2014-01-22 科达集团股份有限公司 Construction method for partitioning strong permeable stratum

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106978843A (en) * 2017-04-25 2017-07-25 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology
CN106978843B (en) * 2017-04-25 2019-11-15 杭州之江市政建设有限公司 Municipal drainage pipeline construction technology
CN108412016A (en) * 2018-03-15 2018-08-17 中建五局土木工程有限公司 Underground tube body assures construction method
CN110306616A (en) * 2019-08-02 2019-10-08 中交上海航道局有限公司 A kind of construction method of sewage conduct
CN115978296A (en) * 2022-12-08 2023-04-18 宁波市政工程建设集团股份有限公司 Anti-deformation construction method for electric melting connection of large-diameter flexible pipeline
CN117822611A (en) * 2023-12-08 2024-04-05 中水淮河规划设计研究有限公司 A method for landfilling construction of foundation pit pipe wells in water conservancy projects
CN117822611B (en) * 2023-12-08 2026-04-07 中水淮河规划设计研究有限公司 A method for backfilling and burying manholes in water conservancy engineering foundation pits

Similar Documents

Publication Publication Date Title
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN110847224A (en) Filling slope gravity retaining wall reinforcing structure and construction method thereof
CN106836244A (en) Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
CN111322087A (en) Construction method for soft soil highway tunnel entrance semi-open semi-hidden tunnel in mountainous area
CN106320368A (en) A construction method suitable for open-cut pipelines in composite strata
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN206736963U (en) Ditch millet section high water level district lid tunnel stagnant water structure
CN110306989B (en) Non-open-cut assembled pipe trench excavation supporting and reinforcing method
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN103215958A (en) Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN211421169U (en) Reinforcement Structure of Gravity Retaining Wall for Filled Slope
CN102561362A (en) Construction method for foundation pit supporting by dynamic compaction replacement of muddy soil
CN114575355A (en) Soil protection and descent construction method
CN114033427A (en) A construction method for tunnel entry of a unilateral air-side oblique biased tunnel
CN215976663U (en) Excavation area composite foundation treatment structure crossing under high-voltage line
CN116043871A (en) Channel Excavation Support Method Applied to Deep and Thick Soft Foundation Containing Block Rocks on the Side of Built Road
CN110792440B (en) Construction method of water-rich loess tunnel penetrating through loess towards valley

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170111

RJ01 Rejection of invention patent application after publication