JP2009228300A - Construction method of enlarging space under girder of river bridge - Google Patents

Construction method of enlarging space under girder of river bridge Download PDF

Info

Publication number
JP2009228300A
JP2009228300A JP2008074882A JP2008074882A JP2009228300A JP 2009228300 A JP2009228300 A JP 2009228300A JP 2008074882 A JP2008074882 A JP 2008074882A JP 2008074882 A JP2008074882 A JP 2008074882A JP 2009228300 A JP2009228300 A JP 2009228300A
Authority
JP
Japan
Prior art keywords
bridge
girder
river
existing
bridge girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008074882A
Other languages
Japanese (ja)
Other versions
JP5015048B2 (en
Inventor
Akikage Suzuki
顕彰 鈴木
Toshihiko Miwa
俊彦 三輪
Hiroshi Yamanoguchi
寛 山之口
Tatsuya Ueda
達哉 上田
Hidekimi Imanishi
秀公 今西
Toshikuni Kudo
敏邦 工藤
Jun Arita
淳 有田
Akinori Kikuchi
晃徳 菊地
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP2008074882A priority Critical patent/JP5015048B2/en
Publication of JP2009228300A publication Critical patent/JP2009228300A/en
Application granted granted Critical
Publication of JP5015048B2 publication Critical patent/JP5015048B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method of enlarging a space under the girder of a river bridge can minimize the effect of construction on traffic by reducing a construction period, eliminating a need for a site for developing a road, and can reduce an environmental load by using the upper structure of an existing bridge to suppress the occurrence of noise and dust and reduce the generated amount of refuse. <P>SOLUTION: The space under the girder of the existing river bridge is enlarged by a step of installing a strut at a proper position under the bridge girder 10, a step of installed a hydraulic jack 110 between a bent 90 and the bridge girder 10, a step of raising the bridge girder 10 by driving the hydraulic jack 110, a step of receiving the raised bridge girder 10 by a steel saddle 100 and removing an existing bearing 130, and a step of constructing a new skeleton and a new bearing 140 at a position matching the position of the raised bridge girder 10 above the existing bridge pier 40. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、河川橋梁の桁下空間拡大工法に関するもので、さらに詳しくは、既設の橋桁を利用して、短期間で桁下空間を拡大することが可能な工法に関するものである。   The present invention relates to an undergrowth space expansion method for river bridges, and more particularly, to a method for expanding an underarm space in a short period of time using an existing bridge girder.

近年、集中豪雨や熱帯性低気圧(台風)の上陸により、人々の生活に甚大な被害を及ぼす洪水が多発している。洪水が発生する原因の1つとして、洪水量に対して河川の流下断面が不足していることが挙げられる。河川の流下断面を確保するためには、河道の拡幅や河川堤防の整備が考えられる。しかし、既設の河川橋梁の桁下高が低い場合は、河道の拡幅や河川堤防の整備のみでは充分な効果を得ることができない。   In recent years, floods have caused frequent damage to people's lives due to heavy rains and the landing of tropical cyclones (typhoons). One of the causes of floods is the lack of river cross sections relative to the flood volume. In order to secure the cross section of the river, widening of the river channel and improvement of the river dike can be considered. However, when the existing bridge height of the river bridge is low, sufficient effects cannot be obtained only by widening the river channel and improving the river bank.

そこで、計画高水位に対して十分な桁下高を確保して、洪水流下のボトルネックとなることを防止するため、既設の河川橋梁を架け替えることが考えられる。従来、河川橋梁を架け替えるには、まず、既設橋梁の傍らに仮設橋梁を設置して一時的に道路を切り回す。そして、既設橋梁を撤去して新設橋梁を建設する。その後、道路を復旧して新設橋梁の供用を開始し、仮設橋梁を撤去していた。このため、工事が大がかりなものとなり、工期が長くなると共に、コストが上昇するという問題があった。さらに、道路切り回しに伴う用地が必要であり、切り回しに伴う道路線形変更の影響で慢性的な交通渋滞が発生するおそれがあった。   Therefore, it is conceivable to replace existing river bridges in order to secure a sufficient girder height for the planned high water level and prevent it from becoming a bottleneck in the flood flow. Conventionally, in order to replace a river bridge, first, a temporary bridge is installed beside the existing bridge, and the road is temporarily turned around. Then, the existing bridge is removed and a new bridge is constructed. After that, the road was restored and the new bridge was put into service, and the temporary bridge was removed. For this reason, there has been a problem that the construction becomes large, the construction period becomes longer, and the cost increases. Further, a site for road turning is necessary, and there is a possibility that chronic traffic congestion may occur due to the influence of the road alignment change accompanying turning.

このような不都合を解消するため、河川橋梁の架け替え効率を向上させるための技術が種々開示されている(特許文献1、特許文献2参照)。
特許文献1に記載されている技術は、既設橋梁を新設橋梁に架け替えるための工法において、既設橋梁の傍らに、既設橋梁を挟んで第1の台船と第2の台船とを配置する。そして、第2の台船上で新設橋梁の桁を地組みすると共に、第1の台船上に切断した既設橋梁の桁を支持させて架橋場所から移動させる。続いて、新設橋梁の桁を載置した第2の台船を架橋場所へ移動させて新設橋梁を据え付けることにより、既設橋梁を撤去して新設橋梁を設置するようになっている。
In order to eliminate such inconvenience, various techniques for improving the efficiency of river bridge replacement have been disclosed (see Patent Document 1 and Patent Document 2).
In the technique described in Patent Document 1, in a construction method for replacing an existing bridge with a new bridge, a first trolley and a second trolley are arranged beside the existing bridge with the existing bridge interposed therebetween. . Then, the new bridge girder is grounded on the second trolley, and the existing bridge girder cut on the first trolley is supported and moved from the bridge location. Subsequently, the existing bridge is removed and the new bridge is installed by moving the second carriage loaded with the new bridge girder to the bridge location and installing the new bridge.

特許文献2に記載されている技術は、既設橋梁を幅方向に対して中央部と両側部とに切断する。そして、中央部又は両側部のいずれか一方に昇降装置を設置して、他方を撤去すると共に新設橋梁を設置するようになっている。   The technique described in Patent Document 2 cuts an existing bridge into a central portion and both side portions in the width direction. And the raising / lowering apparatus is installed in any one of a center part or both sides, and while the other is removed, a new bridge is installed.

特開2007−321474号公報JP 2007-32174 A 特開2007−321476号公報JP 2007-32476 A

しかし、上記した特許文献1及び特許文献2に記載された技術では、既設橋梁を撤去して新設橋梁を設置するため、既設橋梁に再利用できる部材があったとしても廃棄せざるを得ず、コストが上昇するだけではなく、環境負荷も増大するという問題があった。また、既設橋脚の解体作業を行わなければならないため、騒音や粉塵の発生が危惧される。   However, in the technology described in Patent Document 1 and Patent Document 2 described above, the existing bridge is removed and a new bridge is installed, so even if there is a reusable member in the existing bridge, it must be discarded. There was a problem that not only the cost increased but also the environmental load increased. In addition, since the existing piers must be dismantled, there is a risk of noise and dust generation.

本発明は上述した事情に鑑み提案されたもので、工期を短縮することにより、交通への影響を最小限に抑制すると共に道路切り回しのための用地を必要とせず、さらに、既設橋梁の上部工をそのまま利用することにより、解体工事に伴う騒音や粉塵の発生を抑制すると共に廃棄物の発生量を削減して、環境負荷を低減することが可能な河川橋梁の桁下空間拡大工法を提供することを目的とする。   The present invention has been proposed in view of the above-described circumstances, and by shortening the construction period, it is possible to suppress the influence on traffic to the minimum and do not require a site for turning around the road. By using the work as it is, we provide a method for expanding the under-sparing space of river bridges that can reduce the environmental impact by reducing the amount of waste generated by suppressing the generation of noise and dust associated with demolition work. The purpose is to do.

本発明に係る河川橋梁の桁下空間拡大工法は、上述した目的を達成するため、以下の特徴点を備えている。
すなわち、本発明に係る河川橋梁の桁下空間拡大工法は、既設の河川橋梁の桁下空間を拡大するための工法であって、橋桁下方の適宜位置に支柱(ベント)を設置する工程と、支柱と橋桁との間にジャッキを設置する工程と、ジャッキを駆動して橋桁を上昇させる工程と、上昇した橋桁を支台(サンドル)で受け替えて既設の支承を除去する工程と、既設の橋脚の上部に、上昇した橋桁の位置に合致した新たな躯体及び支承を構築する工程と、を含むことを特徴とするものである。
The under-girder space expansion method for river bridges according to the present invention has the following features in order to achieve the above-described object.
That is, the under-girder space expansion method of the river bridge according to the present invention is a method for expanding the under-girder space of the existing river bridge, the step of installing a column (vent) at an appropriate position below the bridge girder, A step of installing a jack between the column and the bridge girder, a step of driving the jack to raise the bridge girder, a step of replacing the raised bridge girder with a support (sanddle), and a step of removing the existing support, And a step of constructing a new frame and a bearing in conformity with the position of the elevated bridge girder at the upper part of the pier.

ここで、支柱の設置位置は、例えば橋脚及び橋台近傍の一側あるいは両側である。支柱(ベント)の設置に先立って、仮締切工、掘削及び基礎コンクリート打設、橋桁の補強等が適宜行われる。ジャッキにより橋桁を上昇させる工程では、適宜なスパンでジャッキアップを行って、支台(サンドル)で橋桁を受け替える作業を複数回繰り返すことにより、所望の高さまで橋桁を上昇させる。新たな躯体及び支承を構築する工程では、新たな支承を固定するための鋼製枠をアンカーボルトにより固定し、鋼製枠の上部に新たな支承を設置・固定し、再びジャッキアップして橋桁荷重を支台(サンドル)から新たな支承に盛り替え、橋脚及び橋台の躯体上部工の鉄筋を組み立てて型枠を設置し、躯体コンクリートを打設する。上述した工程が終了すると、仮設備や仮締切を撤去する。この際、並行して橋桁の本舗装や標識工を行う。   Here, the installation position of the column is, for example, one side or both sides in the vicinity of the pier and the abutment. Prior to installation of the columns (vents), temporary closing work, excavation and foundation concrete placement, bridge girder reinforcement, etc. are performed as appropriate. In the step of raising the bridge girder by the jack, the bridge girder is raised to a desired height by repeating the work of jacking up with an appropriate span and changing the bridge girder at the abutment (sanddle) a plurality of times. In the process of constructing a new frame and support, a steel frame for fixing the new support is fixed with anchor bolts, a new support is installed and fixed on the upper part of the steel frame, and the bridge girder is jacked up again. The load is changed from the abutment (sandle) to the new support, the reinforcing bars of the pier and the abutment frame superstructure are assembled, the formwork is installed, and the concrete frame is placed. When the above-described steps are completed, the temporary equipment and the temporary deadline are removed. At the same time, the main pavement and sign construction of the bridge girder will be performed in parallel.

本発明に係る河川橋梁の桁下空間拡大工法においては、橋脚、橋台高の増加に伴い、地震時慣性力が増加するため、新たな支承を免震支承にしたり、各工程と並行して、橋台背面を軽量盛土に置き換えたり、橋脚を補強する工程を含ませたりする等により、橋台、橋脚の耐震性能を向上させる。   In the undergirder space expansion method for river bridges according to the present invention, as the pier and the height of the abutment increase, the inertial force during the earthquake increases, so the new bearing is made a seismic isolation bearing, or in parallel with each process, Improve the seismic performance of the abutment and pier by replacing the back of the abutment with a lightweight embankment or including a step to reinforce the pier.

本発明に係る河川橋梁の桁下空間拡大工法によれば、既設の橋桁をそのままジャッキアップして桁下空間を拡大しているので、道路の切り回しを必要とせず、最小限の交通規制で急速施工が可能となる。
また、既設橋梁の上部工をそのまま利用しているので、必要以上の工事が発生せず、騒音・振動や粉塵の発生を抑制すると共に廃棄物の発生量を削減して、環境負荷を低減することが可能となる。
さらに、道路の切り回しを必要とせず、利用可能な既存の設備を再利用することに加えて、工期が短縮されるので、河川橋梁の桁下空間拡大に要するコストの大幅な削減と共に、周辺の交通負荷の軽減が可能となる。
According to the method for expanding the under-girder space of the river bridge according to the present invention, the existing bridge girder is jacked up as it is to expand the under-girder space. Rapid construction is possible.
In addition, since the superstructure of the existing bridge is used as it is, no unnecessary work is required, noise and vibration and dust generation are suppressed, and the amount of waste generated is reduced, reducing the environmental burden. It becomes possible.
Furthermore, in addition to reusing existing equipment that does not require road cutting, the construction period is shortened, so the cost required for expanding the space under the river bridge can be significantly reduced and the surrounding area can be reduced. Can reduce the traffic load.

<桁下空間拡大工法の概要>
本発明に係る河川橋梁の桁下空間拡大工法は、既設の橋桁をそのままジャッキアップして桁下空間を拡大するものである。本工法における桁下の拡大高さは、最新の計画河川水位に基づいて決定されるが、一般的には1.0〜2.0m程度の桁上げが行われる。また、本工法は、特に、短期間の交通遮断が可能な中小規模の道路橋を対象とし、単純若しくは連続構造の鋼桁橋が主な施工対象となる。
<Outline of under-girder space expansion method>
The under-girder space expansion method for a river bridge according to the present invention jacks up an existing bridge girder as it is to expand the under-girder space. The height under the girders in this method is determined based on the latest planned river water level, but in general, a carry of about 1.0 to 2.0 m is performed. In addition, this construction method is particularly intended for medium- and small-sized road bridges that can block traffic for a short period of time, and the main construction target is a steel girder bridge with a simple or continuous structure.

<実施形態>
以下、図面を参照して、本発明に係る河川橋梁の桁下空間拡大工法の実施形態を説明する。図1〜図8は、本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図である。
<Embodiment>
Hereinafter, with reference to drawings, the embodiment of the under-sparing space expansion method of the river bridge concerning the present invention is described. FIGS. 1-8 is explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention.

<準備工/堤防背面・河床部掘削>
本発明に係る河川橋梁の桁下空間拡大工法では、まず初めに、進入路や仮設ヤード等を造成する準備工が行われる。続いて、図1に示すように、橋桁10の下方における空頭確保や作業盤の敷地造成等を目的として、堤防20の背面や河床部30等を掘削する。
<Preparation work / Backside of dyke and riverbed excavation>
In the method for enlarging the under-girder space of a river bridge according to the present invention, first, a preparatory work for creating an approach road, a temporary yard, and the like is performed. Subsequently, as shown in FIG. 1, the back of the levee 20, the river bed 30, and the like are excavated for the purpose of securing an empty head below the bridge girder 10, creating a site for the work panel, and the like.

また、橋桁10のジャッキアップ作業前に、必要に応じて、橋脚40の耐震補強を実施する。この橋脚40の耐震補強工事は、例えば、補強鋼材(帯鉄筋)を内包した高耐久性プレキャストパネルを用いて橋脚40を巻きたてる工法を採用することができる。橋脚40の耐震補強工事を行うことにより、桁上げによる耐震強度の低下を未然に防止して、安全な河川橋梁とすることができる。   Further, before jacking up the bridge girder 10, the pier 40 is subjected to seismic reinforcement as necessary. For the seismic reinforcement work of the pier 40, for example, a method of winding the pier 40 using a highly durable precast panel including a reinforcing steel material (band reinforcing bar) can be employed. By performing the seismic reinforcement work for the pier 40, it is possible to prevent a decrease in the seismic strength due to the carry and to make a safe river bridge.

なお、図1〜図8中、橋梁部や河床部の工事を行う重機として、ラフタークレーン210、小型クローラークレーン220、バックホー230、トラックミキサー240、コンクリートポンプ車250、アスファルトフィニッシャー260、タイヤローラー270、ダンプトラック280が示してある。   1 to 8, as heavy machinery for carrying out the construction of the bridge portion and the riverbed portion, a rough terrain crane 210, a small crawler crane 220, a backhoe 230, a truck mixer 240, a concrete pump vehicle 250, an asphalt finisher 260, a tire roller 270, A dump truck 280 is shown.

<ベント設置箇所確保/基礎コンクリート打設>
続いて、図2に示すように、ベント(四角形に枠組みした鋼製の支柱)90の建て込み位置が河川内の場合は、大型土嚢50等を用いて仮締め切りし、仮締切内をドライアップし、地耐力を確保するために、基礎コンクリート60を打設する。なお、堤体や河床の土質条件によっては、予め表層改良などの地盤改良を実施することが好ましい。
<Securing vent installation location / founding concrete foundation>
Next, as shown in FIG. 2, when the installation position of the vent (steel support framed in a square shape) 90 is in a river, it is temporarily closed using a large sandbag 50 or the like, and the inside of the temporary deadline is dried up. And foundation concrete 60 is laid in order to ensure earth strength. Depending on the soil conditions of the levee body and river bed, it is preferable to implement ground improvement such as surface improvement in advance.

<枠組足場設置/橋桁補強/ベント建込み/鋼製サンドル/油圧ジャッキ設置>
続いて、図3に示すように、橋脚40及び橋台70の近傍に枠組足場80を設置する。また、予め、ジャッキアップ箇所や仮支持箇所の橋桁10を補強する。続いて、小型クローラークレーン220等を用いて所定位置にベント90を建て込み。続いて、ベント90の上部に鋼製サンドル(井桁状に組み上げた支台)100と油圧ジャッキ110を設置する。
<Framed scaffold installation / Bridge girder reinforcement / Bent installation / Steel sandle / Hydraulic jack installation>
Subsequently, as shown in FIG. 3, a frame scaffold 80 is installed in the vicinity of the pier 40 and the abutment 70. Moreover, the bridge girder 10 of a jackup location or a temporary support location is reinforced in advance. Subsequently, the vent 90 is built in a predetermined position using a small crawler crane 220 or the like. Subsequently, a steel sanddle (abutment assembled like a cross beam) 100 and a hydraulic jack 110 are installed on the top of the vent 90.

<交通遮断/桁下ジャッキアップ/鋼製サンドルによる受替え/橋台背面掘削>
続いて、交通遮断を行った後、図4に示すように、橋梁部の工事として、油圧ジャッキ110を作動させ、鋼製サンドル100で盛替えながら橋桁10を徐々にジャッキアップする。この際、橋脚40側と橋台70側の油圧ジャッキ110を連動させながら1スパンずつジャッキアップを行って橋桁10の水平を保つ。そして、橋桁10が所定の高さ(例えば1.0〜2.0m程度)まで上昇したら、鋼製サンドル100で受け替える。また、アプローチ部120の工事として、バックホー230等を用いて、橋台70の背面に存在する土砂を掘削する。
<Traffic interception / Girder jack-up / Replacement with steel sanddle / Back excavation of abutment>
Subsequently, after the traffic is cut off, as shown in FIG. 4, as the construction of the bridge portion, the hydraulic jack 110 is operated, and the bridge girder 10 is gradually jacked up while being replaced with the steel sanddle 100. At this time, the bridge girder 10 is kept horizontal by jacking up one span at a time while interlocking the hydraulic jacks 110 on the pier 40 side and the abutment 70 side. Then, when the bridge girder 10 rises to a predetermined height (for example, about 1.0 to 2.0 m), the steel girdle 100 is used. Moreover, as construction of the approach part 120, the earth and sand which exist in the back surface of the abutment 70 are excavated using the backhoe 230 grade | etc.,.

<既設支承撤去/新支承固定用鋼製枠設置/新支承設置/軽量盛土工>
続いて、図5に示すように、橋梁部の工事として、既設の支承130(図1〜図4参照)を切断して撤去し、新たな支承140を固定するための鋼製枠150を、アンカーボルト(図示せず)を用いて橋脚40の上部に固定し、鋼製枠150の上部に新たな支承140を設置して固定する。この際、新たな支承140として、公知の免震支承を用いることで、桁下空間拡大に伴う地震時慣性力の増加に対応した耐震強度を持つ河川橋梁とすることができる。
<Removal of existing bearings / Installation of steel frame for fixing new bearings / Installation of new bearings / Lightweight embankment>
Subsequently, as shown in FIG. 5, as a bridge work, the existing support 130 (see FIGS. 1 to 4) is cut and removed, and a steel frame 150 for fixing a new support 140 is provided. It fixes to the upper part of the pier 40 using an anchor bolt (not shown), and installs and fixes a new support 140 on the upper part of the steel frame 150. At this time, by using a known seismic isolation bearing as the new bearing 140, a river bridge having seismic strength corresponding to an increase in the inertial force at the time of earthquake accompanying expansion of the under-girder space can be obtained.

また、アプローチ部120の工事として、橋台70の背面掘削部とアプローチ部120に、トラックミキサー240及びコンクリートポンプ車250等を用いて、軽量盛土160を施工する。この際、原料土、セメント、水及び気泡等を混合した気泡混合軽量土を用いた軽量盛土工法を用いることで、桁下空間拡大に伴う土圧の増加に対応する。   Moreover, as construction of the approach part 120, the lightweight embankment 160 is constructed in the back excavation part of the abutment 70 and the approach part 120 using the truck mixer 240, the concrete pump truck 250, etc. FIG. At this time, by using a lightweight embankment method using a light-weight mixed light soil in which raw material soil, cement, water, air bubbles and the like are mixed, it is possible to cope with an increase in earth pressure accompanying expansion of the under-sparing space.

<支承盛替え/アプローチ部仮舗装工/交通遮断解除>
続いて、図6に示すように、橋梁部の工事として、油圧ジャッキ110を作動させて橋桁10を再びジャッキアップし、橋桁10の荷重を仮設の鋼製サンドル100から新たな支承140に盛替える。また、アプローチ部120の工事として、アプローチ斜路部の仮舗装を行う。以上の作業の完了後に交通遮断を解除する。なお、橋桁10とアプローチ部120との間には、仮設桁170を設置する。
<Replacement of bearings / Temporary pavement approach / Release of traffic blockage>
Subsequently, as shown in FIG. 6, as the construction of the bridge portion, the hydraulic jack 110 is operated to jack up the bridge girder 10 again, and the load on the bridge girder 10 is replaced with the new support 140 from the temporary steel sanddle 100. . Moreover, as construction of the approach part 120, temporary paving of the approach ramp part is performed. After the above work is completed, the traffic block is released. A temporary girder 170 is installed between the bridge girder 10 and the approach unit 120.

<躯体上部工鉄筋・型枠組立/躯体コンクリート打設>
続いて、図7に示すように、橋脚40及び橋台70の躯体上部工の鉄筋180を組み立てて、型枠190を設置する。この際、鉛直鉄筋は、既設躯体内に接着系アンカー等を用いて配筋する。続いて、トラックミキサー240及びコンクリートポンプ車250等を用いて、型枠190内に躯体コンクリートを打設する。この際、既にコンクリートが内部に打設されている新たな支承140の固定枠を躯体コンクリートで巻き込む。
<Cast body superstructure reinforcement and formwork assembly / Concrete concrete placement>
Subsequently, as shown in FIG. 7, the reinforcing bars 180 of the upper structure of the pier 40 and the abutment 70 are assembled, and the formwork 190 is installed. At this time, the vertical reinforcing bars are arranged using an adhesive anchor or the like in the existing housing. Subsequently, using the truck mixer 240 and the concrete pump truck 250, etc., the concrete is placed in the mold 190. At this time, the fixed frame of the new bearing 140 in which the concrete is already placed inside is rolled up with the frame concrete.

<仮設備撤去/本舗装・標識工/仮締切撤去/堤防復旧工>
続いて、ベント90や足場等の仮設備を順次解体して撤去する。また、河川内を仮締め切りしていた大型土嚢50を撤去する。この際、仮締切内の基礎コンクリート60も撤去する。また、橋台70の前面の堤防20を工事前の状況に復旧する。また、交通量が少ない夜間等に片側交通規制を行い、アスファルトフィニッシャー260及びタイヤローラー270等を用いて、アプローチ部120を本舗装すると共に、標識等の施設を設置する。
<Temporary equipment removal / main pavement / marker / temporary deadline removal / dyke restoration work>
Subsequently, temporary equipment such as the vent 90 and scaffolding are sequentially dismantled and removed. Moreover, the large sandbag 50 which temporarily closed the river is removed. At this time, the foundation concrete 60 in the temporary deadline is also removed. Moreover, the embankment 20 in front of the abutment 70 is restored to the state before construction. In addition, one-side traffic regulation is performed at night when traffic volume is low, and the asphalt finisher 260 and the tire roller 270 are used to pave the approach section 120 and install facilities such as signs.

上述した各工程を実施することにより、図8に示す完成状態となる。本実施形態に係る桁下空間拡大工法を用いることにより、例えば10日間程度の交通遮断期間で、工事前と比較して橋桁10を1.0〜2.0m程度上昇させ、橋梁の桁下空間を拡大することができる。   By performing the above-described steps, the completed state shown in FIG. 8 is obtained. By using the under-girder space expansion method according to the present embodiment, the bridge girder 10 is raised by about 1.0 to 2.0 m compared to before construction in a traffic interruption period of about 10 days, for example, and the under-girder space of the bridge Can be enlarged.

<好適な適用例>
上述したように、本発明に係る河川橋梁の桁下空間拡大工法は、単純に桁下高が不足している河川橋梁に好適に適用され、橋長が河川幅に対して短く、横堤が流下を阻害している橋梁、橋梁の老化が著しく上部工や下部工の再利用が不可能な橋梁、河積阻害率が大きい橋梁、数日間の交通制限が不可能な橋梁等については、橋梁の架け替え工法が好適である。
<Preferred application example>
As described above, the undergrowth space expansion method for a river bridge according to the present invention is preferably applied to a river bridge that simply lacks the undergirder height, the bridge length is shorter than the river width, and the horizontal levee flows down. For bridges that are hindered, bridges that are extremely aging, bridges that cannot be reused for superstructures and substructures, bridges that have a large river blockage rate, bridges that cannot be restricted for several days, etc. The replacement method is suitable.

本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程1)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 1). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程2)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 2). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程3)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 3). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程4)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 4). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程5)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 5). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程6)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 6). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程7)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 7). 本発明の実施形態に係る河川橋梁の桁下空間拡大工法を説明するための説明図(工程8)。Explanatory drawing for demonstrating the under-girder space expansion construction method of the river bridge which concerns on embodiment of this invention (process 8).

符号の説明Explanation of symbols

10 橋桁
20 堤防
30 河床部
40 橋脚
50 大型土嚢
60 基礎コンクリート
70 橋台
80 枠組足場
90 ベント(支柱)
100 鋼製サンドル(支台)
110 油圧ジャッキ
120 アプローチ部
130 既設の支承
140 新たな支承
150 鋼製枠
160 軽量盛土
170 仮設桁
180 躯体上部工の鉄筋
190 型枠
210 ラフタークレーン
220 小型クローラークレーン
230 バックホー
240 トラックミキサー
250 コンクリートポンプ車
260 アスファルトフィニッシャー
270 タイヤローラー
280 ダンプトラック
10 Bridge Girder 20 Embankment 30 Riverbed 40 Bridge Pier 50 Large Sandbag 60 Foundation Concrete 70 Abutment 80 Frame Scaffolding 90 Vent (Post)
100 steel sandals (abutments)
DESCRIPTION OF SYMBOLS 110 Hydraulic jack 120 Approach part 130 Existing support 140 New support 150 Steel frame 160 Light embankment 170 Temporary girder 180 Reinforcement of superstructure of frame 190 Formwork 210 Rough terrain crane 220 Small crawler crane 230 Backhoe 240 Truck mixer 250 Concrete pump car 260 Asphalt finisher 270 Tire roller 280 Dump truck

Claims (4)

既設の河川橋梁の桁下空間を拡大するための工法であって、
橋桁下方の適宜位置に支柱を設置する工程と、
支柱と橋桁との間にジャッキを設置する工程と、
ジャッキを駆動して橋桁を上昇させる工程と、
上昇した橋桁を支台で受け替えて既設の支承を除去する工程と、
既設の橋脚の上部に、上昇した橋桁の位置に合致した新たな躯体及び支承を構築する工程と、
を含むことを特徴とする河川橋梁の桁下空間拡大工法。
A method for expanding the space under the existing river bridge,
Installing a column at an appropriate position below the bridge girder;
Installing a jack between the column and the bridge girder;
Driving the jack to raise the bridge girder,
The process of removing the existing support by replacing the elevated bridge girder with the abutment,
Constructing a new frame and support that matches the position of the elevated bridge girder at the top of the existing pier;
An undergrowth space expansion method for river bridges characterized by including
前記新たな支承は、免震支承であることを特徴とする請求項1に記載の河川橋梁の桁下空間拡大工法。   The method according to claim 1, wherein the new bearing is a seismic isolation bearing. 前記各工程と並行して、橋脚を補強する工程を含むことを特徴とする請求項1又は2に記載の河川橋梁の桁下空間拡大工法。   The undergrowth space expansion method for river bridges according to claim 1 or 2, further comprising a step of reinforcing a bridge pier in parallel with each of the steps. 前記各工程と並行して、橋台背面のアプローチ部を軽量盛土で嵩上げする工程を含むことを特徴とする請求項1〜3のいずれか1項に記載の河川橋梁の桁下空間拡大工法。   The undergrowth space expansion method of the river bridge according to any one of claims 1 to 3, further comprising a step of raising the approach portion on the back surface of the abutment with a lightweight embankment in parallel with each step.
JP2008074882A 2008-03-24 2008-03-24 Expansion method under space of river bridge Active JP5015048B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008074882A JP5015048B2 (en) 2008-03-24 2008-03-24 Expansion method under space of river bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008074882A JP5015048B2 (en) 2008-03-24 2008-03-24 Expansion method under space of river bridge

Publications (2)

Publication Number Publication Date
JP2009228300A true JP2009228300A (en) 2009-10-08
JP5015048B2 JP5015048B2 (en) 2012-08-29

Family

ID=41243999

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008074882A Active JP5015048B2 (en) 2008-03-24 2008-03-24 Expansion method under space of river bridge

Country Status (1)

Country Link
JP (1) JP5015048B2 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101056671B1 (en) 2011-02-23 2011-08-12 우경건설 주식회사 The bridge upper part structure lift for which bridge upper part structure support lift equipment and this were used
JP2011247060A (en) * 2010-05-31 2011-12-08 Tokyu Construction Co Ltd Reinforcement method of abutment and back face banking
JP2020122356A (en) * 2019-01-31 2020-08-13 株式会社三井E&S鉄構エンジニアリング Method for replacing bridge bearing
JP2020153104A (en) * 2019-03-19 2020-09-24 株式会社奥村組 Repair method of bridge pier
CN112431140A (en) * 2020-12-03 2021-03-02 武汉思力特种工程机械施工有限公司 Construction method for performing high-position beam falling of large bridge by means of walking machine
CN113216015A (en) * 2021-04-26 2021-08-06 浙江交工集团股份有限公司 Construction method of viaduct jacking bearing platform pier column upgrading structure
CN113235465A (en) * 2021-06-03 2021-08-10 中电建生态环境集团有限公司 Positioning and moving device for river channel water-blocking bridge reconstruction construction
CN114086440A (en) * 2021-12-21 2022-02-25 石家庄铁道大学 Construction method of half-sinking self-balancing fusiform double-arch assembly type overpass
JP2022126444A (en) * 2021-02-18 2022-08-30 鹿島建設株式会社 Girder replacement method and bridge pier removal method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107524093A (en) * 2017-09-13 2017-12-29 无锡厚发自动化设备有限公司 A kind of bridge jacking method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268841A (en) * 1994-04-04 1995-10-17 Nippon Jido Kiko Kk Lifting sealing strip for closing notch on parapet
JPH0921115A (en) * 1995-07-06 1997-01-21 Noda Eng:Kk Installation method of evacuation equipment for bridge and device thereof
JPH10280328A (en) * 1997-04-01 1998-10-20 Nkk Corp Removal and erection method for bridge and pontoon equipment used to the method
JP2001295222A (en) * 2000-04-18 2001-10-26 Kajima Corp Replacing method for bridge girder support
JP2003206509A (en) * 2002-01-10 2003-07-25 Kaimon:Kk Function change repair construction method for existing elastic support
JP2005016196A (en) * 2003-06-27 2005-01-20 Yasuhiko Okochi Construction method for embankment on backside of substructure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268841A (en) * 1994-04-04 1995-10-17 Nippon Jido Kiko Kk Lifting sealing strip for closing notch on parapet
JPH0921115A (en) * 1995-07-06 1997-01-21 Noda Eng:Kk Installation method of evacuation equipment for bridge and device thereof
JPH10280328A (en) * 1997-04-01 1998-10-20 Nkk Corp Removal and erection method for bridge and pontoon equipment used to the method
JP2001295222A (en) * 2000-04-18 2001-10-26 Kajima Corp Replacing method for bridge girder support
JP2003206509A (en) * 2002-01-10 2003-07-25 Kaimon:Kk Function change repair construction method for existing elastic support
JP2005016196A (en) * 2003-06-27 2005-01-20 Yasuhiko Okochi Construction method for embankment on backside of substructure

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011247060A (en) * 2010-05-31 2011-12-08 Tokyu Construction Co Ltd Reinforcement method of abutment and back face banking
KR101056671B1 (en) 2011-02-23 2011-08-12 우경건설 주식회사 The bridge upper part structure lift for which bridge upper part structure support lift equipment and this were used
JP2020122356A (en) * 2019-01-31 2020-08-13 株式会社三井E&S鉄構エンジニアリング Method for replacing bridge bearing
JP7229793B2 (en) 2019-01-31 2023-02-28 三井住友建設鉄構エンジニアリング株式会社 Bridge bearing replacement method
JP2020153104A (en) * 2019-03-19 2020-09-24 株式会社奥村組 Repair method of bridge pier
JP7185567B2 (en) 2019-03-19 2022-12-07 株式会社奥村組 Bridge pier repair method
CN112431140A (en) * 2020-12-03 2021-03-02 武汉思力特种工程机械施工有限公司 Construction method for performing high-position beam falling of large bridge by means of walking machine
JP2022126444A (en) * 2021-02-18 2022-08-30 鹿島建設株式会社 Girder replacement method and bridge pier removal method
JP7386824B2 (en) 2021-02-18 2023-11-27 鹿島建設株式会社 Girder replacement method and pier removal method
CN113216015B (en) * 2021-04-26 2022-06-21 浙江交工集团股份有限公司 Construction method of viaduct jacking bearing platform pier column upgrading structure
CN113216015A (en) * 2021-04-26 2021-08-06 浙江交工集团股份有限公司 Construction method of viaduct jacking bearing platform pier column upgrading structure
CN113235465A (en) * 2021-06-03 2021-08-10 中电建生态环境集团有限公司 Positioning and moving device for river channel water-blocking bridge reconstruction construction
CN114086440A (en) * 2021-12-21 2022-02-25 石家庄铁道大学 Construction method of half-sinking self-balancing fusiform double-arch assembly type overpass

Also Published As

Publication number Publication date
JP5015048B2 (en) 2012-08-29

Similar Documents

Publication Publication Date Title
JP5015048B2 (en) Expansion method under space of river bridge
JP5666081B2 (en) Reconstruction method of existing bridge
CN102286924B (en) Bridge construction method with inverted procedures
CN101294447B (en) Buildings pile underpinning method
KR101111594B1 (en) Method for constructing underground structure
KR100949601B1 (en) Method for broadening width of existing bridge without Temporary road
KR100571525B1 (en) Expansion method of a bridge using concrete structure
JP6543176B2 (en) Building method
KR20130105147A (en) The construction method of steel-concrete underpass
CN109629576B (en) Suspension protection system for water supply pipe crossing foundation pit and construction method
JP5015049B2 (en) Pier extension method
JP3586864B2 (en) Underground structure construction method and elevated traffic path
KR101011805B1 (en) Method of constructing underground structure crossing pile bases in a pile-based ground and underground structure constructed using the same
KR20050108867A (en) A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents.
JP2016204938A (en) Ground lowering method for existing tunnel
JP2018172953A (en) Method of forming roadbed of ballast track
CN108277750B (en) Construction method of high-fill deep-thick soft foundation pile-supported large-section porous cast-in-place box culvert
KR101701220B1 (en) Road expansion structure and construction method thereof
KR101330145B1 (en) Longitudinal direction bridge structures carrying system and rapid replacing method of the bridge using the same
JP2008223291A (en) Rigid frame bridge formed integrally with revetment and method of constructing same
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
KR100699022B1 (en) A railroad bridge repair method used low and longer girder
JP2011063993A (en) Method for reclaiming bridge
JP4233025B2 (en) How to construct a three-dimensional intersection
CN114134829B (en) Prestressed hollow slab girder bridge dismantling system and construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110304

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120531

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120605

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120606

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150615

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 5015048

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250