JP2008308945A - Concrete foundation combined with tension pile, and construction method thereof - Google Patents
Concrete foundation combined with tension pile, and construction method thereof Download PDFInfo
- Publication number
- JP2008308945A JP2008308945A JP2007159895A JP2007159895A JP2008308945A JP 2008308945 A JP2008308945 A JP 2008308945A JP 2007159895 A JP2007159895 A JP 2007159895A JP 2007159895 A JP2007159895 A JP 2007159895A JP 2008308945 A JP2008308945 A JP 2008308945A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- foundation
- connecting rod
- pile
- tensile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Foundations (AREA)
Abstract
Description
本発明は、鉄骨構造物等、建築物の柱材を安定的に支える引張杭併用コンクリート基礎及びその構築方法に関する。 The present invention relates to a tension pile combined concrete foundation that stably supports a pillar of a building such as a steel structure and a construction method thereof.
従来、例えば倉庫等の骨組みを形鋼で構築した鉄骨構造物では、地中に埋め込んだ鉄筋コンクリート製の基礎の上に柱材を立てている。
通常、鉄筋コンクリート製基礎は、根切りによって形成した穴に割ぐり石を敷き、その割ぐり石を転圧した後、必要に応じて捨てコンクリートを打設した後、鉄筋を配筋し、しかる後、割ぐり石、或いは捨てコンクリートの上に基礎コンクリートを打設している。さらに、必要に応じて、その基礎コンクリート上に仮枠を組立て、立上りコンクリートを打設して構築されている(例えば特許文献1参照)。
2. Description of the Related Art Conventionally, in a steel structure in which a framework such as a warehouse is constructed of a shape steel, a pillar material is erected on a reinforced concrete foundation embedded in the ground.
Usually, a reinforced concrete foundation is laid with a quarry stone in a hole formed by root cutting, after rolling the quarry stone, throwing away concrete as needed, and then arranging the reinforced bar. , Foundation concrete is placed on quarry stone or discarded concrete. Furthermore, if necessary, a temporary frame is assembled on the foundation concrete, and a rising concrete is placed (see, for example, Patent Document 1).
また、一般の建築設計では用いないが平鋼を捩じったねじり平鋼を、複数本地面に捩じ込み、各ねじり平鋼の上部を、上部にアンカーボルトを出した鉄骨入りのコンクリートブロックで固めて構造物の基礎を構築する工法も提案されている(特許文献2参照)。
ところで、建築物用基礎としての鉄筋コンクリート製基礎は、建物が水平力を受けた場合の柱に作用する引き抜き力に対して、コンクリート及び埋め戻し土の重量によって抵抗するように設計するのが一般的であり、筋かい構造などの柱の引き抜き力が大きくなるような建物では、基礎の重量を大きくするため、基礎の容積自体が大きくならざるを得ない。 By the way, reinforced concrete foundations as building foundations are generally designed to resist the pulling force acting on the pillars when the building receives horizontal force by the weight of the concrete and backfill soil. However, in a building where the pulling-out force of a pillar such as a brace structure is large, the foundation volume itself is inevitably increased in order to increase the weight of the foundation.
したがって、根切りによって形成する穴を大きくすることが必要となる。掘削に要するコストが高くなるばかりでなく、残土の処理費用もかさむことになる。また、多量の鉄筋を配することに伴って、費用が嵩む結果となっている。 Therefore, it is necessary to enlarge the hole formed by root cutting. Not only will the cost of excavation become high, but the disposal cost of the remaining soil will also increase. Moreover, it is a result that expense increases with arranging a lot of reinforcing bars.
本発明は、このような問題を解消すべく案出されたものであり、根切りの大きさを小さくしたコンクリート基礎であっても、併用した杭の形状・構造を工夫することにより、引き抜き抵抗の高い基礎及びそれを構築する方法を提供することを目的とする。 The present invention has been devised to solve such a problem, and even with a concrete foundation having a small size of root cutting, by devising the shape and structure of the combined pile, the pulling resistance The purpose is to provide a high foundation and a method of constructing it.
本発明の引張杭併用コンクリート基礎は、その目的を達成するため、基礎コンクリートとその下部に立設された鋼製引張杭からなり、鋼製引張杭が、連結棒と、その下端に取り付けられた抵抗板を備えるとともに、連結棒上部に結合環が形成されており、該結合環及び連結棒の上部が前記基礎コンクリート中に埋め込まれていることを特徴とする。
また、連結棒上端の結合環は、基礎コンクリート中に配設した鉄筋を挿通させていることが好ましい。
In order to achieve the purpose, the tensile pile combined concrete foundation of the present invention is composed of a foundation concrete and a steel tensile pile standing on the lower part thereof, and the steel tensile pile is attached to the connecting rod and the lower end thereof. A resistance plate is provided, and a connecting ring is formed on the upper portion of the connecting rod, and the upper portion of the connecting ring and the connecting rod is embedded in the foundation concrete.
Moreover, it is preferable that the connecting ring at the upper end of the connecting rod is inserted through a reinforcing bar disposed in the basic concrete.
このような引張杭併用コンクリート基礎は、掘削された根切り穴の中央に、引張杭を設置する。
請求項2の溝形抵抗板付き杭は、アースオーガー等を用いて穴を掘り、該溝形抵抗板付き杭を設置し、掘削した土を数回にわけ転圧する。
請求項3のスクリュー杭は、専用治具をつけた回転工具で所定の位置まで回転させながら設置する。
請求項4の拡張型杭は、専用治具にて所定の位置まで打込み、抵抗板を広げ設置する。
なお、上記のような引張杭は1つの基礎コンクリートに対して複数本設けることが好ましい。
これらの引張杭を構築した後、前記連結棒の上部を埋め込むように前記根切り内に基礎コンクリートを打設することにより構築される。
連結棒上端に結合環が設けられている態様では、当該結合環に引張杭固定用鉄筋を挿通した後、連結棒の上部を埋め込むように前記根切り内に基礎コンクリートを打設することが好ましい。
Such a tension pile combined concrete foundation installs a tension pile in the center of the excavated root cut hole.
The pile with a resistance resistor plate according to claim 2 digs a hole using an earth auger or the like, installs the pile with a resistance resistor plate, and rolls the excavated soil several times.
The screw pile according to claim 3 is installed while being rotated to a predetermined position with a rotary tool provided with a dedicated jig.
The expandable pile according to
In addition, it is preferable to provide a plurality of tensile piles as described above for one foundation concrete.
After constructing these tensile piles, it is constructed by placing foundation concrete in the root cutting so as to embed the upper part of the connecting rod.
In an aspect in which a connecting ring is provided at the upper end of the connecting rod, it is preferable to place foundation concrete in the root cutting so as to embed the upper portion of the connecting rod after inserting the reinforcing bar for fixing the tensile pile into the connecting ring. .
本発明の引張杭併用コンクリート基礎は、通常の基礎コンクリートの下部に、引き抜き耐力の極めて大きい鋼製引張杭が立設されている。
このため、大きなコンクリート基礎を構築するための大きな根切りを掘削する必要がなくなり、残土の処理も軽便に行うことができるため、結果的に耐力の大きい基礎を低コストで構築することができる。そして、設置する引張杭の本数により、引き抜き耐力を増減させることができる。
さらに、残土処理が少なくなり環境に優しい点が挙げられる。
さらにまた、1箇所あたりに設置する引張杭の本数により、引き抜き耐力を増減させることができる。
The concrete pile combined concrete foundation of the present invention has a steel tensile pile having a very high pulling strength standing upright below the normal foundation concrete.
For this reason, it is not necessary to excavate a large root cut for constructing a large concrete foundation, and the remaining soil can be treated easily. As a result, a foundation having a high yield strength can be constructed at low cost. And pulling-out yield strength can be increased / decreased with the number of tension piles to install.
Furthermore, there are less soil disposal treatments and environmentally friendly points.
Furthermore, the drawing strength can be increased or decreased depending on the number of tension piles installed per place.
本発明者等は、鉄骨構造物における柱材を立てる基礎として、引き抜き耐力の極めて大きい基礎を、大きな根切りを掘削することなく構築する方法について検討し、本発明に到達した。
以下に、添付図面を参照しながら、その詳細を説明する。
本発明の引張杭併用コンクリート基礎1は、基礎コンクリート2とその下部に立設された鋼製引張杭3から構成されている。
The inventors of the present invention have studied a method for constructing a foundation having a very high pulling strength as a foundation for standing a pillar in a steel structure without excavating a large root cut, and have reached the present invention.
Details will be described below with reference to the accompanying drawings.
The
基礎コンクリートそのものには特に工夫を凝らす必要はない。通常の基礎と同様、コンクリート基礎そのものの耐力向上のため、通常と同様の主筋4、帯筋5が配されている。柱9を固定するためのアンカーボルト10も埋め込まれる。図1は立上り部を有する基礎を示し、かつ鋼製引張杭3に溝形抵抗板付き杭を取り付けた場合を示す。図2は、同じく立上り部を有する基礎を示し、かつスクリュー杭を用いた場合を示すものである。図3は立上がりのない埋め込み型の基礎を示し、かつ溝形抵抗板付き杭を取り付けた場合を示す。さらに図4は、同じく立上がりのない埋め込み型の基礎を示し、かつ拡張型杭を示すものである。そして、6は通常の割ぐり石であり、7は捨てコンクリートである。
なお、図中、12はベースプレート11を水平に取り付けるためのレベル調整用モルタルであり、8は本発明引張杭を固定するための鉄筋である。
There is no need to devise any particular means for the foundation concrete itself. Similar to the normal foundation, the
In the figure, 12 is a level adjusting mortar for attaching the
基礎コンクリートの下部に立設された鋼製引張杭3は、上端が基礎コンクリートに埋め込まれ、下方は土中に埋め込まれている。
引き抜き抵抗を大きくするために、鋼製引張杭3を構成する連結棒13の下端に、各種抵抗板が取り付けられる。図1や図3の場合、平面部及びその両側端から略垂直に立ち上がる縦壁部をもち、平面部の縦壁部中央が前記連結棒の下端を取り付けられる抵抗板14を具えている。
The steel tensile pile 3 erected at the lower part of the foundation concrete has the upper end embedded in the foundation concrete and the lower part embedded in the soil.
In order to increase the pulling resistance, various resistance plates are attached to the lower ends of the connecting
また、図2の場合、鋼製引張杭3を構成する連結棒13の下端に、鋼板をスクリュー状に成型した抵抗板15を取り付けている。
さらに、図4の場合、連結棒13の下端に二枚の抵抗板17が取り付けられ、抵抗板17のそれぞれの他端には補助棒18の下端が取り付けられ、2本の補助棒18の上端は上方で一体化されて、前記連結棒13の中間部に接続されている。
なお、図示はしていないが、先端に抵抗板を備えた鋼製引張杭3を複数本、基礎コンクリート2の下部に立設することが好ましい。
Moreover, in the case of FIG. 2, the
Further, in the case of FIG. 4, two
Although not shown, it is preferable that a plurality of steel tensile piles 3 each having a resistance plate at the tip are erected under the
抵抗板14,15,17としては、引き抜き耐力を増加する意味では、面積の広いものほど好ましい。前記したように、杭の引き抜き耐力は杭の抵抗板の面積と埋め込み深さで決まる。したがって、抵抗板14,15,17が広く、かつ、深く埋設されているほど引き抜き耐力が向上することになる。抵抗板14,15,17に用いる材料としては鋼板で十分である。耐久性を良くするためには、めっき鋼板、例えばZn−Al−Mg系のめっきを施したものを用いることが好ましい。
As the
連結棒13の上端に、棒体先端を湾曲させて形作った結合環16が設けられている。この結合環16は、基礎コンクリート中に配設する際に杭固定用鉄筋8を挿通させて基礎コンクリートの引き抜き耐力向上に寄与するものである。
At the upper end of the connecting
次にこのような引張杭併用コンクリート基礎を構築する方法について、図1の溝形抵抗板14付き杭を例に、説明する。
本件引張杭併用コンクリート基礎を構築する位置を確認し、所定の大きさの根切り用の穴を掘削する(図5のa)。その穴の略中央に、溝形抵抗板付き杭の抵抗板14の大きさ及び本体棒の長さに応じた穴を、抱きスコップ等を用いて人力で、或いはアースオーガー等を用いて機械的に掘る(図5のb)。作業性を考慮すると、アースオーガーを用いることが好ましい。
Next, a method for constructing such a concrete foundation combined with a tensile pile will be described by taking a pile with a
The position where the concrete foundation combined with the present tension pile is constructed is confirmed, and a hole for root cutting having a predetermined size is excavated (a in FIG. 5). In the center of the hole, a hole corresponding to the size of the
この穴の底面に、溝形抵抗板付き杭を設置し(図5のc)、掘削した土を埋め戻す(図5のd)。アンカー杭の引抜き力を高くするためには、埋め戻しの際に、埋め戻した土を締め固める必要がある。
締め固め力を高めるためには、埋め戻しを数回に分割し、その都度、角材やランマー等を用いて突き固めたり、専用の突き固め治具を用いて突き固めたりすることが好ましい。
A pile with a resistance resistor plate is installed on the bottom of the hole (FIG. 5c), and the excavated soil is backfilled (d in FIG. 5). In order to increase the pulling force of the anchor pile, it is necessary to compact the backfilled soil during backfilling.
In order to increase the compaction force, it is preferable to divide the backfilling into several times, and each time it is tamped using a square or rammer, or rammed using a dedicated tamping jig.
引張杭を構築した後、割ぐり石の敷設と捨てコンクリートの打設を行う(図5のe)。その後、捨てコンクリート上に配筋を施す。この際、通常の主筋、帯筋の他に杭固定用の鉄筋を別途配する。そして、前記連結棒の先端に設けた結合環にこの杭固定用の鉄筋を挿通させる(図5のf)。
配筋がなされた基礎部の底盤部に底盤用型枠を配し(図5のg)、底盤部コンクリートを打設する(図5のh)。
After constructing the tension pile, laying stones and placing discarded concrete (e in Fig. 5). After that, place reinforcement on the discarded concrete. At this time, in addition to the normal main bar and band bars, reinforcing bars for fixing the piles are separately arranged. Then, the reinforcing rod for fixing the pile is inserted through the connecting ring provided at the tip of the connecting rod (f in FIG. 5).
A base plate formwork is arranged on the bottom plate portion of the foundation portion where the bar arrangement is made (g in FIG. 5), and the bottom plate portion concrete is placed (h in FIG. 5).
底盤部コンクリートが固化した後、その上に立上り部用型枠を配し(図5のi)、立上り部コンクリートを打設する(図5のj)。そして、立上り部コンクリートが固化した後、型枠を撤去し(図5のk)、根切り穴を埋め戻して(図5のl)、引張杭併用コンクリート基礎の構築作業を終える。
なお、図5では、立上り部を有する基礎の構築手順を説明したが、立上り部のない基礎底盤部のみからなる基礎を構築する際には、図5のi,jの工程が省略され、kの工程の型枠撤去後に柱を立設し、その後に埋め戻されることになる。
After the bottom base concrete is solidified, a rising portion formwork is placed thereon (i in FIG. 5), and the rising portion concrete is placed (j in FIG. 5). Then, after the rising portion concrete is solidified, the formwork is removed (k in FIG. 5), the root hole is backfilled (l in FIG. 5), and the construction work of the concrete foundation combined with the tensile pile is finished.
In FIG. 5, the construction procedure of the foundation having the rising portion has been described. However, when constructing the foundation including only the foundation bottom plate portion without the rising portion, the steps i and j in FIG. 5 are omitted, and k After removing the formwork in this process, a pillar is erected and then backfilled.
1:引張杭併用コンクリート基礎 2:基礎コンクリート 3:引張杭
4:主筋 5:帯筋 6:割ぐり石 7:捨てコンクリート 8:杭固定用鉄筋 9:柱 10:アンカーボルト 11:レベル調整用モルタル
12:ベースプレート 13:連結棒 14,15,17:抵抗板 16:結合環
1: Concrete foundation combined with tensile piles 2: Foundation concrete 3: Tensile piles
4: Main bars 5: Band bars 6: Granite 7: Discarded concrete 8: Reinforcing bars 9: Pillars 10: Anchor bolts 11: Mortar for level adjustment
12: Base plate 13: Connecting
Claims (8)
鋼製引張杭が、連結棒と、該連結棒の上端に取り付けられた連結環と、前記連結棒の下端に取り付けられた抵抗板からなり、該抵抗板が平面部及びその両側端から略垂直に立ち上がる縦壁部とをもち、前記抵抗板平面部の縦壁部中央に前記連結棒の下端が取り付けられているとともに、
前記連結棒の上部及び結合環が前記基礎コンクリート中に埋め込まれていることを特徴とする引張杭併用コンクリート基礎。 Consists of foundation concrete and steel tensile piles standing underneath,
A steel tensile pile is composed of a connecting rod, a connecting ring attached to the upper end of the connecting rod, and a resistance plate attached to the lower end of the connecting rod, and the resistance plate is substantially vertical from the flat portion and both side ends thereof. And the lower end of the connecting rod is attached to the center of the vertical wall portion of the resistance plate flat portion,
A concrete foundation combined with a tensile pile, wherein an upper part of the connecting rod and a connecting ring are embedded in the foundation concrete.
鋼製引張杭が、連結棒と、該連結棒の上端に取り付けられた連結環と、前記連結棒の下端に取り付けられた抵抗板からなり、該抵抗板が鋼板をスクリュー状に成型したものであるとともに、
前記連結棒の上部及び結合環が前記基礎コンクリート中に埋め込まれていることを特徴とする引張杭併用コンクリート基礎。 Consists of foundation concrete and steel tensile piles standing underneath,
A steel tensile pile is composed of a connecting rod, a connecting ring attached to the upper end of the connecting rod, and a resistance plate attached to the lower end of the connecting rod, and the resistance plate is formed by screwing a steel plate into a screw shape. As well as
A concrete foundation combined with a tensile pile, wherein an upper part of the connecting rod and a connecting ring are embedded in the foundation concrete.
鋼製引張杭が、連結棒と、該連結棒の上端に取り付けられた連結環と、前記連結棒の下端に一端が取り付けられて側方に拡がる二枚の抵抗板と、該二枚の抵抗板のそれぞれの他端に下端が取り付けられ、上端が上方で一体化されて前記連結棒の中間部に接続される二本の補助棒とからなるとともに、
前記連結棒の上部及び結合環が前記基礎コンクリート中に埋め込まれていることを特徴とする引張杭併用コンクリート基礎。 Consists of foundation concrete and steel tensile piles standing underneath,
The steel tensile pile includes a connecting rod, a connecting ring attached to the upper end of the connecting rod, two resistance plates having one end attached to the lower end of the connecting rod and extending laterally, and the two resistances. The lower end is attached to each other end of the plate, and the upper end is integrated at the upper side and consists of two auxiliary rods connected to the middle part of the connecting rod,
A concrete foundation combined with a tensile pile, wherein an upper part of the connecting rod and a connecting ring are embedded in the foundation concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007159895A JP2008308945A (en) | 2007-06-18 | 2007-06-18 | Concrete foundation combined with tension pile, and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007159895A JP2008308945A (en) | 2007-06-18 | 2007-06-18 | Concrete foundation combined with tension pile, and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2008308945A true JP2008308945A (en) | 2008-12-25 |
Family
ID=40236783
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007159895A Pending JP2008308945A (en) | 2007-06-18 | 2007-06-18 | Concrete foundation combined with tension pile, and construction method thereof |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2008308945A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2192245A1 (en) * | 2008-11-27 | 2010-06-02 | Vestas Wind Systems A/S | Tower for a wind turbine and a method for assembling the tower |
US8225576B2 (en) | 2005-11-24 | 2012-07-24 | Vestas Wind Systems A/S | Wind turbine tower, connection means for assembling a wind turbine tower and methods thereof |
JP2013253445A (en) * | 2012-06-08 | 2013-12-19 | Hiroaki Ishihara | Foundation construction method, photovoltaic power generation panel construction method and building construction method |
CN104153311A (en) * | 2014-08-19 | 2014-11-19 | 崔洪军 | Road guardrail reinforcing device and reinforcing method thereof |
CN105350564A (en) * | 2015-12-07 | 2016-02-24 | 湖南皓诺工程有限公司 | Bonding structure of wind turbine foundation steel ring and concrete and construction method |
CN109440800A (en) * | 2018-12-18 | 2019-03-08 | 南京工业大学 | A kind of novel peg board composite foundation and construction method |
CN109680709A (en) * | 2019-02-12 | 2019-04-26 | 苏州朗捷通智能科技有限公司 | A kind of monitoring upright bar native pile foundation and its construction method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5611823B2 (en) * | 1978-11-11 | 1981-03-17 | ||
JPS5919639A (en) * | 1982-07-27 | 1984-02-01 | Furukawa Electric Co Ltd:The | Electrode wire for wire-cut electric discharge machining |
JPS61102640A (en) * | 1984-10-25 | 1986-05-21 | Ricoh Co Ltd | Lighting device |
JPS61142224A (en) * | 1984-12-13 | 1986-06-30 | Watanabe Hikoitsu | Branch line block |
JPS6391531A (en) * | 1986-10-06 | 1988-04-22 | Yamatake Honeywell Co Ltd | Diaphragm fixing structure |
JP2006161442A (en) * | 2004-12-08 | 2006-06-22 | Nisshin Steel Co Ltd | Anchor pile |
-
2007
- 2007-06-18 JP JP2007159895A patent/JP2008308945A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5611823B2 (en) * | 1978-11-11 | 1981-03-17 | ||
JPS5919639A (en) * | 1982-07-27 | 1984-02-01 | Furukawa Electric Co Ltd:The | Electrode wire for wire-cut electric discharge machining |
JPS61102640A (en) * | 1984-10-25 | 1986-05-21 | Ricoh Co Ltd | Lighting device |
JPS61142224A (en) * | 1984-12-13 | 1986-06-30 | Watanabe Hikoitsu | Branch line block |
JPS6391531A (en) * | 1986-10-06 | 1988-04-22 | Yamatake Honeywell Co Ltd | Diaphragm fixing structure |
JP2006161442A (en) * | 2004-12-08 | 2006-06-22 | Nisshin Steel Co Ltd | Anchor pile |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8225576B2 (en) | 2005-11-24 | 2012-07-24 | Vestas Wind Systems A/S | Wind turbine tower, connection means for assembling a wind turbine tower and methods thereof |
EP2192245A1 (en) * | 2008-11-27 | 2010-06-02 | Vestas Wind Systems A/S | Tower for a wind turbine and a method for assembling the tower |
JP2013253445A (en) * | 2012-06-08 | 2013-12-19 | Hiroaki Ishihara | Foundation construction method, photovoltaic power generation panel construction method and building construction method |
CN104153311A (en) * | 2014-08-19 | 2014-11-19 | 崔洪军 | Road guardrail reinforcing device and reinforcing method thereof |
CN105350564A (en) * | 2015-12-07 | 2016-02-24 | 湖南皓诺工程有限公司 | Bonding structure of wind turbine foundation steel ring and concrete and construction method |
CN109440800A (en) * | 2018-12-18 | 2019-03-08 | 南京工业大学 | A kind of novel peg board composite foundation and construction method |
CN109680709A (en) * | 2019-02-12 | 2019-04-26 | 苏州朗捷通智能科技有限公司 | A kind of monitoring upright bar native pile foundation and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101696916B1 (en) | Construction method of permanent wall with retaining wall combined PHC pile and steel pipe | |
KR100762991B1 (en) | Precast piling method injected with high-strength mortar | |
KR20100068597A (en) | A shoring method using arch plate pile and h-pile | |
JP2008308945A (en) | Concrete foundation combined with tension pile, and construction method thereof | |
KR101793037B1 (en) | Construction method of permanent wall with retaining wall combined PHC pile and steel pipe | |
CN110777836A (en) | Reinforced concrete plate-anchor rod composite foundation and using method thereof | |
JP4925267B2 (en) | Independent foundation and its construction method | |
KR101341260B1 (en) | Method of reinforcing existing concrete footing structure using micropile | |
KR20140013497A (en) | Method for constructing block type reinforced retaining wall in cut site | |
JP4190360B2 (en) | Masonry wall reinforcement structure and method | |
KR20080077721A (en) | The method of constructing bloclk for wall | |
JP5229913B2 (en) | Slope reinforcement method | |
KR100638178B1 (en) | Marine structure and construction method thereof | |
KR100923290B1 (en) | Abutment structure of bridge | |
KR20190109890A (en) | Composite phc pile for soil retaining wall | |
KR101210368B1 (en) | Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts. | |
JP2015183366A (en) | Structure and construction method for banking structure | |
KR100910884B1 (en) | Multistaged cone foundation | |
JP2005282043A (en) | Earth retaining wall reinforcing method | |
JP5016521B2 (en) | Earth anchor and its removal method | |
JP5830068B2 (en) | Slope reinforcement method | |
JP6860895B2 (en) | Retaining wall and its construction method | |
JP4154492B2 (en) | Pile head connection structure of ready-made piles | |
JP2011157719A (en) | Earth retaining method | |
KR101047257B1 (en) | Construction method of earth wall using composite sheet pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20090928 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20110524 |
|
A977 | Report on retrieval |
Effective date: 20110525 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20110629 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20111018 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20120224 |