JP2007323680A - Management decision support system - Google Patents

Management decision support system Download PDF

Info

Publication number
JP2007323680A
JP2007323680A JP2007233539A JP2007233539A JP2007323680A JP 2007323680 A JP2007323680 A JP 2007323680A JP 2007233539 A JP2007233539 A JP 2007233539A JP 2007233539 A JP2007233539 A JP 2007233539A JP 2007323680 A JP2007323680 A JP 2007323680A
Authority
JP
Japan
Prior art keywords
plan
loss
profit
decision support
schedule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007233539A
Other languages
Japanese (ja)
Inventor
Koichi Kitamura
浩一 北村
Kentaro Taguchi
謙太郎 田口
Teruo Nakada
輝男 仲田
Satoshi Katsube
聡 勝部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2007233539A priority Critical patent/JP2007323680A/en
Publication of JP2007323680A publication Critical patent/JP2007323680A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To conduct speedy and appropriate real-time management among management hierarchies. <P>SOLUTION: This management decision support system for supporting management judgment is provided with a management decision support device which accepts input data of a long range schedule plan, a profit and loss target, a sales target, an inventory target, and a profit-loss decision support system which receives the long range schedule plan, the profit and loss target and the sales target, performs simulation calculation on whether it is executable the long range schedule plan or not after developing the long range schedule plan into a middle range schedule plan, and calculates first prediction data of a correction plan, profit and loss prediction and sales prediction of the long range schedule on the basis of the result. The management decision support system further has an inventory/procurement planning support system for calculating a procurement plan on the basis of the middle range schedule plan and calculating second prediction data of inventory prediction and evaluation loss, and pay-out cost schedule on the basis of the middle range schedule, the supply plan and a predetermined purchase unit price. The first and second prediction data are output and displayed on a display means of the management decision support device. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は,製品の中大量販売・生産の経営的な意思決定を支援するシステムに関する。   The present invention relates to a system that supports managerial decision making for mass sales and production of products.

製品の中大量販売・生産の計画立案では,非特許文献1にあるように,生産レベル,在庫レベル,労働力レベルの算出を目的とした大日程計画を立案し,大日程計画に基づいて,品目別の製品生産量の確定,および工数計画,材料所要量計画の前提の確定を目的として,中日程計画を立案する。大日程計画は,計画期間が6ヶ月〜1年半,日程の単位は月〜週,計画修正の頻度は毎月,製品カテゴリーは製品グループ別であるのに対し,中日程計画は,計画期間が1〜3ヶ月,日程の単位は旬〜日,計画修正の頻度は毎月〜毎旬,製品カテゴリーは仕様別である。これらの属性の違いから,対象とする事業への影響は大日程計画の方が大きく,中日程計画は大日程計画を目標とした計画となる。その意味で,大日程計画は,その事業を統括する最高責任者(以後,この者を経営者と呼ぶ。)により立案・承認され,中日程計画はその事業の販売・生産の責任者(以後,この者を販売・生産担当部長と呼ぶ。)により立案・承認される。大日程計画も中日程計画も,計画期間に先立って計画期間分の計画が立案され,修正頻度で見直される。   In the planning of medium-volume sales and production of products, as described in Non-Patent Document 1, a large-scale plan for the purpose of calculating the production level, inventory level, and labor force level is prepared, and based on the large-scale plan, A mid-schedule plan is drawn up for the purpose of finalizing product production by item and finalizing assumptions for man-hour planning and material requirements planning. Large schedules have a planning period of 6 months to a year and a half, a schedule unit of months to weeks, a schedule revision frequency of every month, and product categories by product group, while medium schedules have a planning period of 1 to 3 months, the unit of the schedule is seasonal to daily, the frequency of plan correction is monthly to seasonal, and the product category is by specification. Due to the difference in these attributes, the impact on the target project is greater for the large schedule, and the medium schedule is a plan that targets the large schedule. In that sense, the large schedule is planned and approved by the chief executive who oversees the business (hereinafter referred to as the manager), and the medium schedule is responsible for the sales and production of the business (hereinafter referred to as the manager). This person is called the sales and production manager). Both large schedule plans and medium schedule plans are planned for the planning period prior to the planning period, and are reviewed with a correction frequency.

計画立案時点では,事業部長が大日程計画を立案し,これに基づいて販売・生産担当部長が中日程計画を立案する。大日程計画の見直し時には,中日程計画に基づいて既に手配されている材料供給契約(以後,供給制約と呼ぶ)や,雇用契約および設備導入計画の能力の制約(以後,能力制約と呼ぶ)が問題となるため,大日程計画を見直した後,販売・生産担当部長が大日程計画を中日程計画に展開して,供給制約や能力制約の中で大日程計画の実行可能性を確認する。仮に実行不可能であれば,事業部長と販売・生産担当部長との間で,大日程計画と中日程計画の見直しを繰り返す。   At the time of planning, the general manager makes a large schedule, and based on this, the sales and production manager makes a medium schedule. When reviewing a large schedule, there are material supply contracts (hereinafter referred to as supply constraints) that have already been arranged based on the medium schedule, and capacity restrictions (hereinafter referred to as capacity constraints) in employment contracts and equipment introduction plans. Because it becomes a problem, after reviewing the large schedule, the manager in charge of sales and production expands the large schedule into a medium schedule and confirms the feasibility of the large schedule within supply constraints and capacity constraints. If it is not feasible, repeat the review of the large schedule plan and medium schedule plan between the general manager and the sales / production manager.

「生産マネジメント入門I」藤本隆宏著,日本経済新聞社発行(2001年)"Introduction to Production Management I" by Takahiro Fujimoto, published by Nikkei Inc. (2001)

経営者の視点に立ったとき,従来の大日程計画立案の策定方法には,以下のよ
うな問題がある。
問題1:大日程計画と中日程計画が不整合となる。
問題2:大日程計画(生産台数、販売台数の計画)の策定にあたり、売上,原価
,利益といった損益判断に関する情報が考慮されていない。
問題3:死蔵化リスクのある棚資残高(以後,棚残と呼ぶ)の情報を持たない。
問題4:仮に,問題2と3に対する情報が提供されても,これらを判断しやすい
表示形式に加工し,迅速に判断可能とするような表示手段を持たない。
From the manager's point of view, there are the following problems in the conventional method of formulating a large schedule.
Problem 1: Large and medium schedules are inconsistent.
Problem 2: Information related to profit / loss judgments such as sales, costs, and profits is not taken into account when formulating large-scale plans (plans for production and sales).
Problem 3: There is no information on the balance of shelves that are at risk of being stored (hereinafter referred to as the remaining shelf).
Problem 4: Even if information on problems 2 and 3 is provided, the information is processed into a display format that is easy to determine, and there is no display means that enables quick determination.

以下,それぞれの問題を詳細に説明する。   Each problem is described in detail below.

問題1に関して:
前述のように,大日程計画では,製品グループ別の計画しか立案しない。これ
に対して,中日程計画では製品仕様別に,供給制約および能力制約の範囲内で実
行可能な計画を立案する。見直し前の大日程計画と製品グループと中日程計画の
仕様の親子関係と大日程計画と中日程計画の数量の関係を保持していないので,
大日程計画を見直した時に,新大日程計画と中日程計画が不整合となる。また,
大日程計画を中日程計画に展開しない限り,供給制約および能力制約との比較が
出来ないため,大日程計画立案時点では,その計画の実行可否が分からない。こ
のため,大日程計画を見直し前の関係を用いて中日程計画に展開し,供給制約や
能力制約と比較して,中日程計画が実行不可能だった場合に初めて大日程計画も
実行不可能となることが分かる。さらに、実行可能な中日程計画として,大日程
計画と整合を取るためには,大日程計画見直しと中日程計画見直しの作業を実行
可能となるまで,繰り返さなければ成らならず,整合性を保つのが困難であった。
Regarding issue 1:
As mentioned above, in the large schedule, only plans for each product group are made. On the other hand, in the medium schedule plan, a plan that can be executed within the scope of supply constraints and capacity constraints is made for each product specification. Since the parent-child relationship of the specifications of the large schedule plan, product group, and medium schedule plan before the review and the relationship between the quantity of the large schedule plan and the medium schedule plan are not maintained,
When the large schedule is reviewed, the new large schedule and the medium schedule are inconsistent. Also,
Unless a large schedule is developed into a medium schedule, it cannot be compared with supply constraints and capacity constraints. At the time of planning a large schedule, it is not known whether the plan can be executed. For this reason, a large schedule plan is developed into a medium schedule plan using the relationship before the review, and when a medium schedule plan is not feasible compared to supply constraints and capacity constraints, a large schedule plan is not feasible for the first time. It turns out that it becomes. Furthermore, as a feasible medium schedule plan, in order to align with the large schedule plan, the work of the large schedule plan review and the medium schedule plan review must be repeated until it becomes feasible, and the consistency is maintained. It was difficult.

問題2に関して:
従来,損益の判断と販売量・生産量の計画立案は切り離されていた。これは,
個々の製品の粗利(=売価−標準原価)がプラスで,固定費を回収するだけの売
上が達成されれば,それ以上の売上が利益に直結するため,売上予算を越えるこ
とのみを目標としていたからである。すなわち,製品に競争力があり,必ず固定
費を回収できるだけの売上数と粗利を確保できるのであれば,後はできる限り製
造原価を下げて,目標の売上数量を販売・生産することに注力すれば良かったの
で,販売・生産において損益を考える必要がなかったのである。しかし,競合相
手との競争が激しく,利益率が低いか,若しくは固定費を回収可能な程度の売上
しか得られない厳しい経営状況においては,販売量の変動が損益に大きく影響を
与える。特に製品種が複数有り,製品種毎の利益率が異なり,かつ製品種毎の需
要予測精度が大きくばらつく場合には,製品種毎の販売量がより大きく損益に影
響を与える。上記のような厳しい経営状況において従来手法では,精緻な損益判
断を行うことは困難であった。
Regarding issue 2:
Previously, profit / loss judgment and sales / production planning were separated. this is,
If the gross profit (= selling price-standard cost) of each product is positive and sales enough to recover fixed costs are achieved, the higher sales are directly linked to profits, so the goal is to exceed the sales budget. Because it was. In other words, if the product is competitive and the number of sales and the gross margin that can always recover fixed costs can be secured, the production cost will be lowered as much as possible to focus on selling and producing the target sales volume. It was all right, so there was no need to consider profit or loss in sales and production. However, in a severe business situation where competition with competitors is intense and profit margins are low or fixed sales can only be recovered, fluctuations in sales volume have a large impact on profit and loss. In particular, when there are multiple product types, the profit rate for each product type is different, and the demand forecast accuracy for each product type varies greatly, the sales volume for each product type has a greater effect on profit and loss. In the severe business situation as described above, it has been difficult to make a precise profit / loss judgment with the conventional method.

問題3に関して:
販売計画通りに売れれば,在庫を作る必要はない。また,注文を受けてから,
顧客の要求納期(以後,受注リードタイムと呼ぶ)までに,調達, 生産,配送(
以後,この期間のことを生産リードタイムと呼ぶ)が可能であれば在庫を作る必
要がない。通常,中大量産品においては,受注リードタイムに対して,生産リー
ドタイムが長い。また,販売計画通りに売れるということは,ほとんどない。し
かし,従来の経営的意思決定では,販売計画を目標として,目標が達成されるこ
とを前提に予算が立案されていた。販売計画通りに製品が販売されるのであれば
,前述のように在庫が発生すること自体,有り得ないことであるため,従来の経
営的意思決定では,在庫は重視されていなかった。しかし,他社との競合が激し
く需要予測の精度が低い状況では,実際の販売が販売計画に未達ということは頻
繁に起こり得る。また,製品のライフサイクルが短くなると,旧製品の在庫が完
全に売れ残り,安値販売や滅却などにより,損を出す可能性が高くなる。このた
め,高めの販売計画を設定した場合には,販売計画が未達の場合の棚残リスクを
評価しなければならない。
Regarding issue 3:
If you sell as planned, you don't have to make inventory. After receiving the order,
Procurement, production, delivery (by customer lead time)
From now on, this period will be referred to as production lead time). In general, the production lead time is longer than the order lead time for medium and high volume products. Also, there is almost no selling as planned. However, in the conventional management decision-making, the budget is drawn up on the assumption that the target is achieved with the sales plan as the target. If a product is sold according to the sales plan, it is impossible for the stock to be generated as described above, so the stock has not been emphasized in the conventional management decision making. However, in a situation where competition with other companies is intense and the accuracy of demand forecasts is low, it is often possible that actual sales will not meet the sales plan. Also, if the product life cycle is shortened, the stock of the old product will not be sold completely, and there is a high possibility of loss due to low price sales or destruction. For this reason, when a higher sales plan is set, the remaining shelf risk when the sales plan is not achieved must be evaluated.

問題4に関して:
問題2と3にある売上,原価,利益,棚残といった指標は,それぞれ関係を持
っている。例えば,売上が増えれば,通常は利益も増える。売上,原価,利益の
間には等式が成り立つ。売上が増えれば,通常は棚残も増える。原価が高くなれ
ば,棚残も高くなる。といった具合に,それぞれの指標が関係を持っているため
に,これらが個別に提供されたとしても,個別に表示したのでは,その関係を読
みとるのに時間を要してしまう。すなわち,表示する指標を増やすことは,意思
決定に必要であるにも関わらず,普通に表示しただけでは,その意思決定のスピ
ードを落としてしまうのである。
Regarding issue 4:
Indicators such as sales, cost, profit, and shelf remaining in problems 2 and 3 are related to each other. For example, profits usually increase as sales increase. An equation holds between sales, cost, and profit. As sales increase, the shelf space usually increases. The higher the cost, the higher the remaining shelf. For example, since each index has a relationship, even if these are provided individually, if they are individually displayed, it takes time to read the relationship. In other words, increasing the number of indicators to be displayed is necessary for decision making, but just displaying them normally slows down the decision making speed.

そこで、上記課題を解決するために、本発明では、大日程計画の見直しに合わ
せて,見直し前大日程計画と見直し前中日程計画の関係を保ちながら,即座に中
日程計画に展開し,中日程計画が供給制約および能力制約の範囲内に収まるか否
かを判別し,大日程計画の実行可能性を経営者が経営的意思決定をする装置上に
表示する。また,中日程計画の見直し結果を,見直し前大日程計画と見直し前中
日程計画の関係から,大日程計画案に逆に展開し,即座に経営者が経営的意思決
定をする装置上に表示する。また,販売計画に対する実需要の変動の影響を予測
し、経営者側のシステムに経営の判断材料として提供する。
Therefore, in order to solve the above problems, in the present invention, in accordance with the review of the large schedule plan, while maintaining the relationship between the pre-review large schedule plan and the pre-review medium schedule plan, It is determined whether or not the schedule is within the limits of supply constraints and capacity constraints, and the feasibility of the large schedule is displayed on a device on which the manager makes a management decision. In addition, the review result of the medium schedule plan is displayed on the device where the manager makes a managerial decision immediately after developing the reverse schedule to the large schedule plan from the relationship between the pre-review large schedule plan and the pre-review medium schedule plan. To do. It also predicts the impact of actual demand fluctuations on the sales plan and provides it to the management's system as management judgment material.

また,上記課題を解決するために、本発明では、大日程計画のレベル(製品カ
テゴリー,計画期間,日程単位)で売上,コスト,利益の予測結果を,対応する
中日程計画に基づいて算出し,それらの予測結果を経営者が経営的意思決定をす
る装置上に表示する。また、大日程計画の見直しに基づいた中日程計画の見直し
結果を基にした損益情報(売上,利益,原価)を,経営者が判断し易い指標の組
み合わせでグラフィカルに,経営的意思決定をする装置上に表示する。このとき
,原価の予測精度向上するために,販売計画の見直しによる在庫量予測の変化に
起因する払出単価変動を予測する必要がある。また,販売計画に対する実需要が
変動した場合の,損益に対する影響を予測できる必要がある。
In order to solve the above problems, the present invention calculates the forecast results of sales, cost and profit at the level of the large schedule (product category, planning period, schedule unit) based on the corresponding middle schedule. , These prediction results are displayed on a device on which the manager makes a management decision. In addition, profit and loss information (sales, profit, cost) based on the review result of the medium schedule plan based on the review of the large schedule plan is used to make a management decision graphically with a combination of indicators that managers can easily judge. Display on the device. At this time, in order to improve the cost prediction accuracy, it is necessary to predict the change in the payout unit price due to the change in the inventory forecast due to the review of the sales plan. In addition, it is necessary to be able to predict the impact on profit and loss when actual demand for the sales plan fluctuates.

また、上記課題を解決するために、本発明では、大日程計画の見直しに合わせ
て,即座に中日程計画に基づいて棚残を予測し,経営者が経営的意思決定をする
装置上に表示する。このとき,棚残予測金額の精度向上のために,在庫予測の変
化に起因する払出単価変動を予測する。また,販売計画に対して実需要が変動し
た場合の,棚残に対する影響を予測する。加えて,内部プロセスの改善効果を予
測に組み込むため,調達リードタイム,生産リードタイム,安全在庫量,調達ロ
ットサイズ,生産ロットサイズ,調達頻度,生産頻度を改善した場合の棚残への
影響を予測する。
Further, in order to solve the above-mentioned problems, the present invention immediately predicts the shelf remaining based on the medium schedule plan in accordance with the review of the large schedule plan, and displays it on a device on which the manager makes a management decision. To do. At this time, in order to improve the accuracy of the remaining shelf forecast amount, the fluctuation of the payout unit price due to the change in the stock forecast is predicted. It also predicts the impact on shelf racks when actual demand fluctuates with respect to the sales plan. In addition, in order to incorporate the improvement effect of internal processes into the forecast, the impact on the shelf remaining when the procurement lead time, production lead time, safety stock quantity, procurement lot size, production lot size, procurement frequency, and production frequency are improved. Predict.

また、上記課題を解決するために、本発明では、大日程計画の新規立案に関し
ては,売上,原価,利益,棚残といった指標の過去からの推移を元に計画を立案
する。このとき,これらの指標そのものの推移と,各指標間の関係の推移を一度
に閲覧できるような表示方法を提供する。例えば,売上の推移に合わせて,売上
と利益の関係である売上高利益率の推移も同時に表示するというような方法であ
る。
In order to solve the above-mentioned problems, in the present invention, a new plan for a large schedule is made based on the past changes in indicators such as sales, cost, profit, and shelf remaining. At this time, a display method is provided so that the transition of these indices themselves and the transition of the relationship between the indices can be viewed at a time. For example, in accordance with the change in sales, the change in sales profit ratio, which is the relationship between sales and profit, is displayed at the same time.

また,大日程計画の更新に関しては,売上,原価,利益,棚残といった指標の
現在値,その現在値が計画に対して,どの程度の進捗なのか,また今後の予測値
に基づく予算の達成度といったものを同時に閲覧できるような表示方法を提供す
る。合わせて,上記,指標の現在値,現在の進捗,予算の達成度予測についても
,各指標間の関係を同時に閲覧できるような表示方法を提供する。
In addition, regarding the update of large schedules, the current values of indicators such as sales, cost, profits, and remaining inventory, how far the current values are progressing with respect to the plans, and the achievement of budget based on future forecasts Provide a display method that allows you to view things at the same time. In addition, the present invention provides a display method that allows the user to view the relationship between each index at the same time for the current index value, current progress, and budget achievement prediction.

本発明の実施の形態により、経営意思決定層間の情報伝達を迅速に行うことが
でき、損益や棚残の情報に基づいた予測結果を用いるため、経営者の経営意思決
定を精度よく的確に支援することができる。
According to the embodiment of the present invention, it is possible to quickly communicate information between management decision-making layers, and use prediction results based on information on profit and loss and remaining inventory, so that management decisions of management are accurately and accurately supported. can do.

以下、本発明による経営意思決定支援システムの実施の形態(第1の実施形態
)を図面により詳細に説明する。
Hereinafter, an embodiment (first embodiment) of a management decision support system according to the present invention will be described in detail with reference to the drawings.

図1は本発明の一実施形態による経営意思決定支援システムにおける装置構成
と装置間の情報の流れを説明する図である。図1において,101は、経営者が
大日程計画案の新規作成や進捗に応じた変更を行うことを支援する経営意思決定
支援装置である。また、102は、販売・生産計画担当部長が経営者の入力した
大日程計画案108に基づいて配分率や製品売価予定を作成し、大日程計画10
8(修正後の大日程計画案117でもよい。)の実行可否を出力表示する損益意
思決定支援装置であり、103は、大日程計画108(115は転送データ)の
実行可否を予測演算する損益シミュレーション装置である。また、104は、損
益シミュレーション装置103の出力する中日程計画案124に基づいて部品調
達計画120を立案する調達計画立案装置であり、106は、経営者の入力する
棚残目標108(112は転送データ)と、後述する棚残シミュレーション装置
105の予測出力する棚残予測および評価損のデータ121に基づいて、棚残・
調達計画部長が調達計画案の修正をする棚残・調達計画支援装置であり、105
は、中日程計画案124と調達計画案120(修正後の調達計画案113でもよ
い。)に基づいて、棚残予測および評価損121の予測演算をする棚残シミュレ
ーション装置である。
FIG. 1 is a diagram for explaining a device configuration and a flow of information between devices in a management decision support system according to an embodiment of the present invention. In FIG. 1, reference numeral 101 denotes a management decision support device that supports a manager to newly create a large schedule plan and to make changes according to progress. Reference numeral 102 denotes a distribution schedule and a product sales price schedule based on a large schedule plan 108 input by the manager of the sales / production plan manager.
8 is a profit / loss decision support device that outputs and displays whether or not execution of 8 (may be a revised large schedule plan 117) is possible, and 103 is a profit or loss that predicts whether or not the large schedule 108 (115 is transfer data) can be executed. This is a simulation device. Reference numeral 104 denotes a procurement plan drafting device for drafting a parts procurement plan 120 based on the medium schedule plan 124 output from the profit / loss simulation device 103. Reference numeral 106 denotes a remaining shelf target 108 (112 is a transfer). Data) and the remaining shelf prediction and evaluation loss data 121 output by the remaining shelf simulation apparatus 105, which will be described later.
A shelf plan / procurement plan support device for a procurement plan manager to correct a procurement plan draft,
Is a remaining shelf simulation device that performs a remaining shelf prediction and a prediction calculation of the evaluation loss 121 based on the medium schedule plan 124 and the procurement plan 120 (or the corrected procurement plan 113).

本実施の形態では,その事業の最高意思決定者である経営者から入力される1
08の大日程計画案,損益目標,売上目標,棚残目標を経営意思決定支援装置1
01が受け付ける。そして、「損益目標と売上目標」111を損益意思決定支援
装置102に,棚残目標112を棚残・調達計画支援装置106に,大日程計画
案115を損益シミュレーション装置103に転送し,損益シミュレーション装
置103と棚残シミュレーション装置105を稼働させる。この本実施の形態に
おける演算により,経営意思決定支援装置101は,損益シミュレーション装置
103より,118の大日程計画案,補正計画,損益予測,売上予測を,棚残シ
ミュレーション装置105より,119の棚残予測と評価損を取得し,107の
販売実績,生産実績,棚残実績のデータと合わせて,経営者に提供することで,
経営者の意思決定を支援する。ここで、各装置間のデータ送信・受信は、社内LA
N(Local Area Network)やインターネット等の通信手段により実現する事がで
きる。
In this embodiment, 1 is input from the manager who is the highest decision maker of the business.
Management decision support device 1 for 08 large schedule plan, profit / loss target, sales target, and shelf remaining target
01 accepts. Then, the “profit / loss target and sales target” 111 is transferred to the profit / loss decision making support device 102, the remaining shelf target 112 is transferred to the remaining shelf / procurement plan support device 106, and the large schedule plan 115 is transferred to the profit / loss simulation device 103. The apparatus 103 and the remaining shelf simulation apparatus 105 are operated. By the calculation in this embodiment, the management decision support apparatus 101 receives 118 large schedule plans, correction plans, profit / loss forecasts, and sales forecasts from the profit / loss simulation apparatus 103, and 119 shelves from the shelf remaining simulation apparatus 105. By acquiring the remaining forecast and valuation loss and providing them to the manager together with 107 sales performance, production performance, and remaining shelf performance data,
Support managers' decision making. Here, data transmission / reception between each device is done in-house LA
It can be realized by communication means such as N (Local Area Network) or the Internet.

図2に,各装置間の情報交換のタイミングであるシーケンス図を詳細に示す。
図に示すステップに従って説明していく。
FIG. 2 shows in detail a sequence diagram that is the timing of information exchange between the devices.
This will be described according to the steps shown in the figure.

まず,S201では、経営意思決定支援装置101から損益意思決定支援装置
102に,「損益目標」「売上目標」(111)のデータが送信される。また、
S202では、経営意思決定支援装置101から棚残・調達計画支援装置106
に、「棚残目標」(112)のデータが送信される。また、S203では、「大
日程計画案」(115)のデータが経営意思決定支援装置101から損益シミュ
レーション装置103に送信される。この時、経営意思決定支援装置101から
損益意思決定支援装置102および棚残・調達計画支援装置106に起動指示が
送信される。起動指示を受けた損益意思決定支援装置102は,販売担当部長お
よび生産計画担当部長からの入力(大日程計画案、配分率の117や、製品売価
予定110)を受けて,損益シミュレーション装置103に122の大日程計画
案,配分率,および製品売価予定を転送し,損益シミュレーション装置103の
起動指示を発行して送信する。起動指示を受けて損益シミュレーション装置10
3は,調達計画立案装置104と棚残シミュレーション装置105を稼働させる
。また、逆に経営意思決定支援装置101から起動指示を受けた棚残・調達計画
支援装置106が、棚残シミュレーション装置105や調達計画立案装置104
や損益シミュレーション装置103を起動させる仕組みでも同様に「経営-損益-
棚残のシステム」の立ち上げを実現できる。
First, in S201, data of “profit / loss target” and “sales target” (111) is transmitted from the management decision support apparatus 101 to the profit / loss decision support apparatus 102. Also,
In S202, the management decision support device 101 to the shelf remaining / procurement plan support device 106
In addition, the data of “remaining shelf target” (112) is transmitted. In S 203, data of “large schedule plan” (115) is transmitted from the management decision support apparatus 101 to the profit / loss simulation apparatus 103. At this time, an activation instruction is transmitted from the management decision support apparatus 101 to the profit / loss decision determination support apparatus 102 and the shelf remaining / procurement plan support apparatus 106. The profit / loss decision-making support apparatus 102 that has received the start-up instruction receives input from the sales manager and production planning manager (large schedule plan, allocation rate 117 and product sales price schedule 110), and the profit / loss simulation apparatus 103 receives it. 122 transfers the large schedule plan, the distribution rate, and the product sales price schedule, and issues and transmits an activation instruction for the profit / loss simulation apparatus 103. Profit and loss simulation apparatus 10 upon receiving the start instruction
3, the procurement plan planning device 104 and the shelf remaining simulation device 105 are operated. Conversely, the remaining shelf / procurement plan support device 106 that has received an activation instruction from the management decision support device 101 replaces the remaining shelf simulation device 105 or the procurement plan planning device 104.
And the mechanism for starting the profit / loss simulation apparatus 103 "Management-Profit-
The launch of a “shelf-remaining system” can be realized.

S204では、経営意思決定支援装置101から転送された「大日程計画案」
と、損益意思決定支援装置102から転送された「配分率」(中日程計画案の製
品仕様毎の販売・生産に関する比率)と、製品仕様毎の「製品売価予定」に基づ
いて、「中日程計画案」や「計画実行可否」を損益シミュレーション装置103
の演算処理により算出し、損益意思決定支援装置102に送信する。損益シミュ
レーション装置103における予測演算では、大日程計画案、機種構成情報12
6(図1)、配分率に基づいて大日程計画展開演算を実行し「中日程計画案」を
算出し、その後、所要量計算マスタ127を利用して、計画実行可否演算を実行
する。損益意思決定支援に関する具体的な実施形態については、後述する第2の
実施形態において詳述する。
In S204, the “large schedule plan” transferred from the management decision support apparatus 101
Based on the “allocation ratio” (the ratio of sales / production for each product specification of the medium schedule plan) transferred from the profit / loss decision support device 102 and the “product price schedule” for each product specification, The “plan” and “plan execution” are displayed on the profit / loss simulation apparatus 103
And is transmitted to the profit / loss decision-making support apparatus 102. In the prediction calculation in the profit and loss simulation apparatus 103, a large schedule plan, model configuration information 12
6 (FIG. 1), a large schedule plan expansion calculation is executed based on the distribution ratio to calculate a “medium schedule plan”, and then a plan execution availability calculation is executed using the requirement calculation master 127. A specific embodiment related to profit / loss decision making support will be described in detail in a second embodiment to be described later.

S205では、後述する第3の実施形態にて算出される払出原価予定125を
考慮した損益予測・売上予測・原価予測および製品売価予定を算出し、損益意思
決定支援装置102に送信する。上記算出情報は、機種構成情報126と組み合
わされて図43に示すようなツリー構造形式で損益意思決定支援装置102の表
示画面に出力される。この表示情報により、販売・生産計画担当部長は、当初の
「大日程計画案」「配分率」「製品売価予定」の数値を損益意思決定支援装置1
02によって変更修正することができる。本実施の形態では、そのうちの「大日
程計画案」「配分率」について次のS206において変更修正し、「製品売価予
定」についてはS209において変更修正する場合を例に説明するが、3つのデ
ータを同時に修正変更(S206として)することもでき、その場合は、損益予
測や売上予測の演算(S210)は、後述するS207の演算と同時期に実行さ
れる。
In S <b> 205, the profit / loss forecast / sales forecast / cost forecast and product sales price schedule taking into account the payout cost schedule 125 calculated in the third embodiment to be described later are calculated and transmitted to the profit / loss decision making support apparatus 102. The calculation information is combined with the model configuration information 126 and output to the display screen of the profit / loss decision-making support apparatus 102 in a tree structure as shown in FIG. Based on this display information, the manager in charge of sales / production planning calculates the initial “large schedule plan”, “distribution rate”, and “product sales price plan” numerical values for the profit and loss decision support device 1.
02 can be changed and corrected. In this embodiment, the “large schedule plan” and “distribution rate” are changed and corrected in the next S206, and the “product selling price schedule” is changed and corrected in S209. Can also be modified and changed at the same time (as S206). In this case, the calculation of profit / loss and sales forecast (S210) is executed at the same time as the calculation of S207 described later.

S206では、販売・生産計画担当部長の入力を受けて、損益意思決定支援装
置102から「大日程計画案」「配分率」(修正値)を損益シミュレーション装
置103に送信する。S207では、修正された大日程計画等の情報に基づいて
、大日程計画展開演算や計画実行可否の演算を実行し、演算結果を損益意思決定
支援装置102に送信する。
In step S <b> 206, in response to the input of the sales / production plan manager, the profit / loss decision support apparatus 102 transmits “large schedule plan” and “distribution rate” (corrected value) to the profit / loss simulation apparatus 103. In S <b> 207, based on information such as the revised large schedule plan, a large schedule plan expansion calculation and a plan execution possibility calculation are executed, and the calculation result is transmitted to the profit / loss decision making support apparatus 102.

S208では、前述したS205と同様に、後述する第3の実施形態の棚残シ
ミュレーションによって再計算された払出原価予定125に基づいて、損益予測
・売上予測・原価予測および製品売価予定を損益シミュレーション装置103の
演算により算出し、算出結果を損益意思決定支援装置102に送信する。販売・
生産計画担当部長は、その結果を受けて「製品売価予定」を変更修正することが
でき、修正データは損益シミュレーション装置103に送信される(S209)
。損益シミュレーション装置103は、修正された「製品売価予定」に基づいて
「損益予測」「売上予測」を算出して、損益意思決定支援装置102に送信する
(S210)。
In S208, similar to S205 described above, the profit / loss forecast / sales forecast / cost forecast and product sales price schedule are calculated based on the payout cost schedule 125 recalculated by the remaining shelf simulation of the third embodiment to be described later. The calculation result is transmitted to the profit / loss decision making support apparatus 102. Sales /
The manager in charge of production planning can change and modify the “product sales price schedule” in response to the result, and the correction data is transmitted to the profit / loss simulation apparatus 103 (S209).
. The profit / loss simulation apparatus 103 calculates “profit / loss forecast” and “sales forecast” based on the revised “product sales price schedule”, and transmits it to the profit / loss decision support apparatus 102 (S210).

一方、S211では、調達計画立案装置104は損益シミュレーション装置1
03により算出された中日程計画案124を受けて、調達計画案120を立案算
出する。調達計画立案装置104は、立案された調達計画案を棚残・調達計画支
援装置106および棚残シミュレーション装置105に送信する(S212,S
213)。棚残シミュレーション装置105では、日単位で詳細化された「日別
中日程計画」の入力も受け(S214)、棚残予測演算、評価損予測演算を実行
して、実行結果(棚残予測・評価損予測121)を棚残・調達計画支援装置10
6に送信する。棚残・調達計画部長が、棚残・調達計画支援装置106の表示画
面に表示される棚残予測データ、評価損予測データ114を考慮して調達計画案
120を修正する場合には、修正後の調達計画案113の入力を受けて棚残シミ
ュレーション装置105に送信する(S216)。修正による変更があった場合
には、再度棚残シミュレーション計算が実行されて、算出される「棚残予測」「
評価損予測」データは棚残・調達計画支援装置106および経営意思決定支援装
置101に送信される(S217、S218)。算出される「払出原価予定」の
データは、損益シミュレーション装置103に送信される(S219)。そして
、「払出原価予定」を考慮した損益シミュレーションの再計算により算出された
中日程計画データを受信し(S220)、その変更された中日程計画に基づいて
調達計画立案装置104は、再度調達計画案120を立案し、S221,S22
2により各装置に送信する。上述のステップと同様に、調達計画立案装置104
は日別中日程計画案を算出し(S223)、棚残シミュレーション装置105は
再度棚残予測演算と評価損予測演算を実行し(S224)、棚残・調達計画部長
による修正がされた場合には調達計画案113が棚残シミュレーション装置10
5に送信されて、改めて棚残シミュレーション計算が実行される。尚、本実施の
形態では、「大日程計画案」と「配分率」の変更修正(S206)をした場合で
あるので、S220〜S228の再計算処理がなされるが、「製品売価予定」の
みを修正変更した場合は、当該再計算処理はなされず、前述したS210の処理
がされる。
On the other hand, in S211, the procurement plan planning device 104 executes the profit / loss simulation device 1.
In response to the medium schedule plan 124 calculated by 03, the procurement plan 120 is calculated. The procurement plan drafting device 104 transmits the drafted procurement plan draft to the remaining shelf / purchasing plan support device 106 and the remaining shelf simulation device 105 (S212, S).
213). The shelf-remaining simulation apparatus 105 also receives an input of “daily daily schedule plan” that is detailed on a daily basis (S214), executes the remaining shelf prediction calculation and the evaluation loss prediction calculation, and executes the execution result (remaining shelf prediction / Evaluation loss forecast 121) is used to store shelf / procurement plan support device 10
6 to send. When the shelf remaining / procurement plan manager corrects the procurement plan 120 in consideration of the remaining shelf prediction data and the evaluation loss prediction data 114 displayed on the display screen of the remaining shelf / procurement plan support apparatus 106, the corrected The procurement plan 113 is received and transmitted to the remaining shelf simulation device 105 (S216). If there is a change due to correction, the remaining shelf simulation calculation is executed again, and the calculated “remaining shelf prediction” “
The “evaluation loss prediction” data is transmitted to the remaining shelf / procurement plan support device 106 and the management decision support device 101 (S217, S218). The calculated “paid out cost schedule” data is transmitted to the profit / loss simulation apparatus 103 (S219). Then, the medium schedule data calculated by the recalculation of the profit and loss simulation considering the “paid out cost schedule” is received (S220), and the procurement plan planning device 104 again performs the procurement plan based on the changed medium schedule plan. Plan 120, S221, S22
2 to each device. Similar to the above steps, the procurement planning device 104
Calculates the daily schedule plan (S223), and the shelf-remaining simulation apparatus 105 executes the remaining shelf prediction calculation and the evaluation loss prediction calculation again (S224), and when the shelf remaining / procurement plan manager makes corrections. The procurement plan 113 is the remaining shelf simulation device 10
The remaining shelf simulation calculation is executed again. In this embodiment, since the “large schedule plan” and the “distribution rate” are changed and corrected (S206), the recalculation processing of S220 to S228 is performed, but only “product sales price schedule” is performed. Is corrected and changed, the recalculation process is not performed, and the process of S210 described above is performed.

再計算された「棚残予測データ」と「評価損予測データ」は、棚残・調達計画
支援装置106および経営意思決定支援装置101に送信され(S226、S2
27)、「払出原価予定」は、損益シミュレーション装置103に送信されて(
S228)、損益予測演算や売上予測演算に利用される。そして、S229にて
、「損益予測」「売上予測」「実行可能な大日程計画案」が経営意思決定支援装
置101に送信されて、S227で送信された情報とあわせて表示画面に表示さ
れる。このような処理フローによって、経営意思決定支援装置101は,経営者
に109の大日程計画案,実行可否,損益予測,売上予測,棚残予測,および評
価損を提供可能であり、これらの処理の繰り返しにより、リアルタイムに経営意
思決定の支援情報の提供を可能とし、迅速で的確な経営判断をすることが可能と
なる。
The recalculated “shelf remaining prediction data” and “evaluation loss prediction data” are transmitted to the shelf remaining / procurement plan support apparatus 106 and the management decision support apparatus 101 (S226, S2).
27) The “paid out cost schedule” is transmitted to the profit / loss simulation apparatus 103 (
S228), used for profit / loss prediction calculation and sales prediction calculation. In S229, “Profit / Loss Forecast”, “Sales Forecast”, and “Executable Large Schedule Plan” are transmitted to the management decision support apparatus 101 and displayed on the display screen together with the information transmitted in S227. . With such a processing flow, the management decision support apparatus 101 can provide the manager with 109 large-scale schedule plans, feasibility, profit / loss prediction, sales prediction, shelf remaining prediction, and evaluation loss. By repeating the above, it becomes possible to provide support information for management decision making in real time, and it becomes possible to make a quick and accurate management decision.

次に、経営意思決定支援装置101にて提供される情報の画面の例を,図3か
ら図15を使って詳細に説明する。
Next, examples of information screens provided by the management decision support apparatus 101 will be described in detail with reference to FIGS.

図3は,経営意思決定支援装置101の画面遷移を表す。概要を説明すると、
まず、初期状態より,ログインし(301),コマンド待ちの状態に至る(30
2)。コマンド待ち状態から2つのコマンドが実行可能である。一つは実績経緯
表示(303),もう一つは実績予測推移表示(実推表示)である(304)。
それぞれの表示機能とも,幾つかのオプション機能を持つ。実績経緯表示は,表
示項目選択(305),表示指標選択(306),と目標値設定画面(307)
のオプション機能を有する。実推表示では,表示項目選択(308),表示指標
選択(309),目標値見直し画面(310),大日程計画変更画面(311)
,シナリオレビュー画面(312)のオプション機能を有する。それぞれの機能
は,図3に示すような関係で接続されているが,詳細は各機能の説明時に説明す
る。
FIG. 3 shows a screen transition of the management decision support apparatus 101. In brief,
First, from the initial state, the user logs in (301) and waits for a command (30
2). Two commands can be executed from the command waiting state. One is a result history display (303), and the other is a result prediction transition display (actual prediction display) (304).
Each display function has several optional functions. The result history display includes display item selection (305), display index selection (306), and target value setting screen (307).
With optional features. In actual guess display, display item selection (308), display index selection (309), target value review screen (310), large schedule plan change screen (311)
, The scenario review screen (312) has an optional function. Each function is connected in a relationship as shown in FIG. 3, and details will be described when each function is described.

まず、ユーザーは、経営意思決定支援装置101のログイン画面(301)で
,ユーザーIDとパスワードを入力し,ログインボタンをクリックすることで,
ユーザーの認証を行い,認証された時だけ,次のコマンド待ち画面(302)へ
移動する。
First, the user inputs a user ID and password on the login screen (301) of the management decision support apparatus 101 and clicks the login button.
Only when the user is authenticated, the screen moves to the next command waiting screen (302).

コマンド待ち画面(302)では、「実績予測推移表示」「実績経緯表示」「
ログオフ」のいずれかのボタンがクリックされるのを待っている。実績経緯表示
がクリックされた場合,実績経緯表示に移動する(303)。実績予測推移表示
がクリックされた場合,実績予測推移表示に移動する(304)。
On the command waiting screen (302), “result prediction transition display” “result history display” “
Waiting for any of the “Log Off” buttons to be clicked. When the result history display is clicked, the result history display is displayed (303). When the result prediction transition display is clicked, the display moves to the result prediction transition display (304).

図4に実績経緯表示画面の例を示す。図4では画面表示を4つに分割し、そのう
ちの3つに、限界利益(利益)推移,収益性推移,在庫の過去からの推移を表示
し、残りの1つに製品機種(F30、F310、F330)に関するデータを表
示する例を示す。これらの表示は、図1に示す「販売実績」「生産実績」「棚残
実績」のデータベース107に蓄積される情報に基づいて実行される。尚、大日
程計画の製品カテゴリーである製品グループは、上述した製品機種(F330等
)に限らず、例えば、製品機種より上位のグループである製品形態(CT:クラ
イアント,PS:PCサーバ,US:UNIX(R)サーバ)の製品グループであって
もよい。これらの関係は、図37に示すようなツリー構造により関連付けられて
おり、経営者の意思により、任意のグループレベルを選択することができる。
FIG. 4 shows an example of a history record display screen. In FIG. 4, the screen display is divided into four, three of which are marginal profit (profit) transition, profitability transition and inventory transition from the past, and the remaining one is the product model (F30, F310). , F330) shows an example of displaying data. These displays are executed based on information stored in the database 107 of “sales record”, “production record”, and “shelf remaining record” shown in FIG. The product group that is the product category of the large schedule is not limited to the above-described product model (F330, etc.), but, for example, the product form (CT: client, PS: PC server, US: higher group than the product model). UNIX (R) server) product group. These relationships are related by a tree structure as shown in FIG. 37, and an arbitrary group level can be selected according to the intention of the manager.

まず、限界利益推移グラフでは,横軸を期、縦軸を製品機種別の売上、変動費
とした過去実績の積み上げ棒グラフと、縦軸を限界利益とした推移グラフを表示
している。過去の期の売上、変動費は塗りつぶしで、限界利益は実線で表示して
いる。今期(01/下(10月〜3月))については、期首予算売上高、期首予算
変動費が半透明の塗りつぶしで、期首予算限界利益は点線で表示されている。
First, in the marginal profit trend graph, a pasted bar graph with the horizontal axis as the period, the vertical axis as sales by product model and variable costs, and a trend graph with the marginal profit as the vertical axis are displayed. Sales and variable costs in the past period are filled in, and marginal profit is shown in solid lines. For the current period (01 / Lower (October to March)), the beginning budget sales and the beginning budget fluctuation costs are translucent, and the beginning budget marginal profit is indicated by a dotted line.

収益性グラフでは,横軸に期毎の売上、縦軸に期毎の限界利益をとる。製品機
種毎に、過去の期の売上と限界利益を実線で表示し,今期(01/下(10月〜3
月))についての、期首予算売上高と期首予算限界利益については半透明線で表
示され、時系列情報は「矢印」によって順序が示されている。このように、「限
界利益」と「売上高」の関係で推移グラフを表示することで、2つの経営判断指
標の動向を同時に把握することができる。また、本実施の形態による表示形態に
より、売上の推移(伸び又は下降)に対する限界利益の推移(伸び又は下降)の
2つの指標の関係(収益性)の推移が瞬時に把握できるため、経営者が「損益目
標」や「売上目標」を設定する際に、双方の目標値または双方の目標値範囲を同
時に決定することができる。また更に、例えば、図4では、製品機種F330の
収益性が高く(売上に対する比率の観点で)かつその伸び率も高いため、経営者
が利益増大を目標にする場合、現状は売上高が低い製品機種F330を重点製品
機種と位置付ける経営方針を、容易に立案することができる。このように、本実
施の形態の経営意思決定支援装置101によれば、経営者が、利益増大方針をと
るか、売上増大方針をとるか、または双方の増大を図る方針をとるかによる、そ
れぞれの方針に応じた迅速かつ的確な経営目標の立案(重点製品機種の把握、売
上目標、損益目標等)を支援することができる。
In the profitability graph, the horizontal axis represents sales for each period and the vertical axis represents marginal profit for each period. For each product model, sales and marginal profit in the past period are displayed in solid lines, and this term (01 / below (October-3)
The initial budget sales and the marginal profit at the beginning of the month are displayed with a semi-transparent line, and the order of the time series information is indicated by “arrows”. In this way, by displaying the transition graph with the relationship between “marginal profit” and “sales”, it is possible to simultaneously grasp the trends of the two management judgment indexes. In addition, the display form according to the present embodiment makes it possible to instantly grasp the relationship (profitability) between the two indicators of the marginal profit transition (growth or decline) to the sales trend (growth or decline). When setting “profit / loss target” and “sales target”, both target values or both target value ranges can be determined simultaneously. Still further, for example, in FIG. 4, the profitability of the product model F330 is high (in terms of the ratio to sales) and the rate of growth is high. A management policy that positions the product model F330 as a priority product model can be easily planned. As described above, according to the management decision support device 101 of the present embodiment, the management depends on whether to take a profit increase policy, a sales increase policy, or a policy to increase both. It is possible to support quick and accurate management target planning (understanding key product models, sales targets, profit / loss targets, etc.) according to the policy of the company.

在庫グラフについては,横軸に期毎の売上、縦軸に期毎の在庫金額をとる。製
品機種毎に、過去の期の在庫金額は実線で表示し、今期(01/下)についての
、期首予算在庫金額は半透明線で表示され、時系列情報は「矢印」によって順序
が示されている。このように「売上高」と「在庫金額」の関係で推移グラフを表
示することで、先の収益性の場合と同様に、2つの経営判断指標を同時に把握す
ることができる。また、在庫金額が売上高と比べて大きい場合には、その製品機
種を重点製品と位置付ける経営方針を容易に立案することができ、売上目標を考
慮しながら棚残目標を検討するという経営者の意思支援を迅速かつ的確に実現で
きる。
For the inventory graph, the horizontal axis represents sales for each period, and the vertical axis represents inventory values for each period. For each product model, the stock price in the past period is displayed as a solid line, the initial budget stock value for the current period (01 / bottom) is displayed as a semi-transparent line, and the time series information is shown in the order by "arrows". ing. By displaying the transition graph with the relationship between “sales” and “inventory amount” in this way, it is possible to simultaneously grasp the two management judgment indexes as in the case of the previous profitability. In addition, when the stock amount is large compared to sales, it is possible to easily formulate a management policy that positions the product model as a priority product, and the management's Can provide support quickly and accurately.

実績経緯表示303の画面には,図4の左上部に示すように3つのオプション
機能がある。表示項目選択305,表示指標選択306,目標値設定307の3
つである。それぞれ、ボタンがクリックされると,対応する画面へ移動する。表
示項目選択305については図5で,表示指標選択306については図6で,目
標値設定307については,図7を用いて詳細に説明する。実績経緯表示画面3
03の画面には、その他に2つのボタンがあります。実績予測推移表示ボタンと
,ログオフボタンです。実績予測推移表示ボタンをクリックすると,実績予測推
移表示304に移動します。詳細は,後述します。ログオフボタンをクリックす
ると,ログイン画面301に移動します。
As shown in the upper left part of FIG. 4, the option history display screen 303 has three optional functions. Display item selection 305, display index selection 306, target value setting 307 3
One. When each button is clicked, it moves to the corresponding screen. The display item selection 305 will be described in detail with reference to FIG. 5, the display index selection 306 with reference to FIG. 6, and the target value setting 307 with reference to FIG. Results history display screen 3
There are two other buttons on the 03 screen. A button for displaying the predicted transition of results and a logoff button. Clicking on the predicted result transition display button moves to the predicted result transition display 304. Details will be described later. Click the logoff button to move to the login screen 301.

図5は、実績経緯表示303の表示項目選択画面である。横軸にグラフ表示す
る期、縦軸にグラフ表示する製品機種が表示され、チェックボックスで選択可能
である。最初に、この画面が表示されたときに、その時点でのグラフ表示状況が
表示される。例えば、過去3期分が表示されていたら、3期分のチェックボック
スにチェックされているように表示される。縦横それぞれでチェックされた行、
列の交差点の色が変わる。OKがクリックされたら、その時点でチェックされて
いる組合せにグラフが変更される。
FIG. 5 is a display item selection screen for the history record display 303. The period for displaying the graph on the horizontal axis and the product model to be displayed on the vertical axis are displayed and can be selected with a check box. First, when this screen is displayed, the graph display status at that time is displayed. For example, if the past three periods are displayed, it is displayed as if the check boxes for the three periods are checked. Checked lines, both vertically and horizontally,
The color of the row intersection changes. If OK is clicked, the graph is changed to the combination currently checked.

図6は、実績経緯表示303の表示指標選択画面である。「4分割表示」又は
「分割なし表示」のいずれかを、ラジオボタンで選択可能である。グラフ配置位
置に対応したプルダウンメニューで各パートの表示内容を選択可能である。選択
肢は「限界利益推移」「収益性」「在庫」。「4分割表示」がクリックされたら
、プルダウンメニューが4つ表示される。「分割なし表示」がクリックされたら
、プルダウンメニューを1つにする。このとき、左上の選択肢を引き継がれる。
OKがクリックされたら、その時点でチェックされている組合せにグラフが変更
されて,実績経緯表示画面303に表示される。キャンセルボタンがクリックさ
れたら,何も変更せずにもとの実績経緯表示画面303に戻る。
FIG. 6 is a display index selection screen for the performance history display 303. Either “4-division display” or “non-division display” can be selected with a radio button. The display contents of each part can be selected from a pull-down menu corresponding to the graph arrangement position. The choices are “marginal profit trend”, “profitability”, and “inventory”. When “4-segment display” is clicked, four pull-down menus are displayed. When “No division display” is clicked, the pull-down menu is set to one. At this time, the upper left choice is carried over.
When OK is clicked, the graph is changed to the combination checked at that time, and displayed on the actual result display screen 303. If the cancel button is clicked, the original history display screen 303 is returned to without changing anything.

図7は、実績経緯表示303の目標値設定画面である。縦軸に目標項目とその
細目,横軸に期が表示される。この例の場合,目標項目は,売上高,限界利益,
変動費,在庫金額である。それぞれの目標値に関して,細目として,製品機種別
に分かれている。01/下が計画対象期で,他の期が過去期もしくは現状の期であ
る。各細目の計画対象期の欄に該当する目標値を入力する。OKボタンがクリッ
クされると計画対象期の欄に書き込まれた値が取り込まれ,目標値として設定さ
れ,実績経緯表示に戻る。Cancelボタンがクリックされたら,すべての入
力は無視され,実績経緯表示に戻る。本実施の形態では、目標値設定画面により
経営者が数値を直接入力する方法で説明したが、図4の実績経緯表示画面303
のグラフにおいて、グラフ上の位置をクリック又は微調整することで目標値の入
力をすることもできる。例えば、図4の収益性グラフにおいて、ある製品機種を
指定した上で目標位置をクリックすると、「売上目標」と「損益(限界利益)目
標」を同時に設定することができる。この場合、グラフ上のポインターの位置に
対応した「売上」と「損益(限界利益)」の数値を表示すると、経営者は更に目
標値の設定を容易に行うことができる。
FIG. 7 is a target value setting screen of the result history display 303. The target item and its details are displayed on the vertical axis, and the period is displayed on the horizontal axis. In this example, the target items are sales, marginal profit,
Variable costs and inventory amounts. Each target value is divided according to product type as a detail. 01 / below is the target period, and the other period is the past period or the present period. Enter the target value that corresponds to the target period for each detail. When the OK button is clicked, the value written in the plan target period column is fetched, set as the target value, and the actual result display is returned. If the Cancel button is clicked, all inputs are ignored and the history display is displayed. In the present embodiment, the method has been described in which the manager directly inputs a numerical value on the target value setting screen. However, the result history display screen 303 in FIG.
In the graph, the target value can be input by clicking or fine-tuning the position on the graph. For example, in the profitability graph of FIG. 4, when a target product model is designated and a target position is clicked, a “sales target” and a “profit / loss (marginal profit) target” can be set simultaneously. In this case, if the numerical values of “sales” and “profit / loss (marginal profit)” corresponding to the position of the pointer on the graph are displayed, the manager can further easily set the target value.

図7に示す目標値設定画面(経営意思決定支援装置101の有する表示画面)
において、経営者が種々の目標値の設定後、OKボタンを押すと、損益・売上・
棚残等に関する目標値データは、損益意思決定支援装置102や損益シミュレー
ション装置103や棚残・調達計画支援装置106に送信される。そして、図2
において説明した処理により、「実行可能な大日程計画案、補正計画、損益予測
、売上予測、棚残予測、評価損」(118,119)の情報が算出され、当該情
報は経営意思決定支援装置101に送信された後、後述する方法によりグラフ用
データに編集・加工されて表示画面に出力表示される(実績予測推移表示304
)。
Target value setting screen shown in FIG. 7 (display screen of management decision support apparatus 101)
When the manager presses the OK button after setting various target values, profit / loss / sales /
The target value data related to the remaining shelf is transmitted to the profit / loss decision making support device 102, the profit / loss simulation device 103, and the remaining shelf / procurement plan support device 106. And FIG.
The information described in “Available large schedule plan, correction plan, profit / loss forecast, sales forecast, inventory prediction, loss on valuation” (118, 119) is calculated. After being transmitted to 101, it is edited and processed into graph data by a method described later and output and displayed on the display screen (actual predicted transition display 304
).

図8に、実績予測推移表示(実推表示画面)304を示す。実推表示304で
は、シナリオ1に基づいた「販売」「業績」「収益性」「在庫」などの複数の経
営指標を一度に閲覧可能としている。実線グラフは、それぞれ過去の期及び当期
(01/上(4月〜9月))の現在以前の実推表示であり、データベース107に
記憶される「販売実績、生産実績、棚残実績」の実績データに基づいて、グラフ
用データが生成される。また、点線グラフの部分は、当期(01/上(4月〜9月
))の現在以降の予測推移表示であり、「損益予測」「売上予測」「棚残予測」
「評価損予測」等の予測データに基づきグラフ用データは生成される。ここで、
シナリオとは、損益シミュレーション装置103の出力する「大日程計画案(修
正後の新計画)」と「補正計画(実行可能な中日程計画)」と、販売・生産計画
担当部長又は棚残・調達計画担当部長の選択した「需要ケース(需要予測データ
)」の組合せにより定められる予測データであり、図14に示すように、実行可
能な大日程計画案の個数と実行可能な補正計画案の個数(図14では2通り)と
需要予測ケースの個数(図14では3通り)の組合せ個数分がS229の段階で
用意される。
FIG. 8 shows a result prediction transition display (actual prediction display screen) 304. In the actual guess display 304, a plurality of management indexes such as “sales”, “performance”, “profitability”, and “inventory” based on the scenario 1 can be browsed at a time. The solid line graphs are actual predictions of the past period and current period (01 / above (April to September)) before the present, and “sales record, production record, remaining shelf record” stored in the database 107 are shown. Graph data is generated based on the result data. In addition, the dotted line graph is the forecast transition display for the current period (01 / above (April to September)) from now on. “Profit / Loss Forecast”, “Sales Forecast”, “Shelves Forecast”
Graph data is generated based on prediction data such as “valuation loss prediction”. here,
Scenarios include “large schedule plan draft (new plan after correction)” and “correction plan (executable medium schedule plan)” output by profit / loss simulation apparatus 103, sales / production plan manager or remaining inventory / procurement This is forecast data determined by the combination of “demand cases (demand forecast data)” selected by the general manager in charge of the plan. As shown in FIG. 14, the number of executable large-scale schedule plans and the number of executable corrected plan plans The number of combinations (two in FIG. 14) and the number of demand prediction cases (three in FIG. 14) are prepared in the stage of S229.

これらの指標の中で,売上,販売台数,利益などのストックの指標は,累積で
表示される。累積で評価することにより,期末の目標に対しての進捗を容易に把
握することが可能である。また,図8の収益性のグラフでは,X軸に時間ではな
く,売上の指標をとり、図示していないが市況指標のグラフでは、X軸に販売台
数などの指標をとる。これにより,台数と売上の変化率による販売単価の推移や
,売上と利益の変化率による利益率の推移などを少ない画面で同時に把握するこ
とが可能となる。また,「重ね合わせ」での選択により,実績データベース10
7より過去の同一期のデータと重ね合わせて表示される。これにより,現在の進
捗の評価を容易に下すことが可能となる。また,点線で表される今後の予測値は
,図2で示した損益シミュレーション装置103および棚残シミュレーション装
置105との連携により算出される。その予測値は、それぞれ予測の基になるシ
ナリオ(大日程計画案、補正計画(中日程計画)、需要ケース)に基づいて算出
され、図8ではシナリオ1に基づく予測グラフを示す。複数のシナリオのそれぞ
れに基づいて予測グラフを表示する場合は、図15のように示される(シナリオ
1〜3)。大日程計画案は、経営者が当初入力した大日程計画案(新計画)の場
合もあるが、図2のシミュレーション処理で修正変更がされた場合には、修正後
の大日程計画案がシナリオの要素として用いられることになる。ここで、図8の
「新計画」は、図13に示す大日程計画編集で経営者により作成される当初の大
日程計画値を制約として、大日程計画展開機能により中日程計画を作成した場合
の経営指標の累積グラフ表示(月単位)であり、「補正計画」は損益シミュレー
ション装置103で大日程計画から展開された中日程計画値を参考にして、損益
意思決定支援装置で販売・生産計画担当部長により作成(修正・変更)された中
日程計画に基づいた経営指標の累積グラフ表示(月単位)である。
Among these indicators, stock indicators such as sales, sales volume, and profit are displayed cumulatively. By evaluating cumulatively, it is possible to easily grasp the progress toward the target at the end of the term. In the profitability graph of FIG. 8, an index of sales is taken on the X axis instead of time, and an index such as the number of units sold is taken on the X axis in the graph of the market condition index, which is not shown. As a result, it is possible to simultaneously grasp the change in the unit sales price due to the change rate of the number of units and the sales and the change in the profit rate due to the change rate of the sales and the profit with a small screen. In addition, the result database 10 is selected by selecting “overlay”.
7 is displayed superimposed with the data of the same period in the past. This makes it possible to easily evaluate the current progress. Further, future predicted values represented by dotted lines are calculated in cooperation with the profit / loss simulation apparatus 103 and the shelf remaining simulation apparatus 105 shown in FIG. The predicted values are calculated based on scenarios (a large schedule plan, a correction plan (medium schedule plan), and a demand case) that are the basis of prediction, and FIG. 8 shows a prediction graph based on scenario 1. When a prediction graph is displayed based on each of a plurality of scenarios, it is shown as in FIG. 15 (scenarios 1 to 3). The large schedule plan may be a large schedule plan (new plan) initially entered by the manager, but if a modification is changed in the simulation process of FIG. 2, the revised large schedule plan is a scenario. It will be used as an element. Here, the “new plan” in FIG. 8 is a case where a medium schedule plan is created by the large schedule plan expansion function with the initial large schedule plan value created by the manager in the large schedule plan editing shown in FIG. 13 as a constraint. Is a cumulative graph display (monthly) of the management index of, and the "correction plan" is a sales / production plan by the profit / loss decision support device with reference to the medium schedule plan value developed from the large schedule by the profit / loss simulation apparatus 103 This is a cumulative graph display (monthly) of management indicators based on the medium schedule plan created (corrected / changed) by the general manager.

経営者は、経営意思決定支援装置101に表示される実績予測推移表示304
の情報を参照して、更に経営指標の見直しを行うことができるが、その場合の支
援方法について、以下に詳述する。
The manager displays the result prediction transition display 304 displayed on the management decision support apparatus 101.
The management index can be further reviewed with reference to the above information, and the support method in that case will be described in detail below.

実績予測推移表示304には,5つのオプション機能がある。表示項目選択3
08,表示指標選択309,目標値見直し310,大日程計画編集311,シナ
リオレビュー312の5つである。図8の画面左側に示すような、それぞれのボ
タンがクリックされると,対応する画面へ移動する。表示項目選択308につい
ては図9,表示指標選択309については図10,目標値見直し310について
は図12,大日程計画編集311については図13,シナリオレビュー312に
ついては図14でより詳細に述べる。
The actual predicted transition display 304 has five optional functions. Display item selection 3
08, display index selection 309, target value review 310, large schedule plan edit 311, scenario review 312. When each button is clicked as shown on the left side of the screen in FIG. 8, the screen moves to the corresponding screen. 9 for the display item selection 308, FIG. 10 for the display index selection 309, FIG. 12 for the target value review 310, FIG. 13 for the large schedule plan edit 311, and FIG. 14 for the scenario review 312.

図9は、実推表示の表示項目選択画面308である。横軸にグラフ表示する期
、縦軸にグラフ表示する製品機種が表示され、チェックボックスで選択可能であ
る。最初に、このダイアログが表示されたときに、その時点でのグラフ表示状況
が表示される。例えば、過去3期分が表示されていたら、3期分のチェックボッ
クスにチェックされているように表示される。縦横それぞれでチェックされた行
、列の交差点の色が変わる。OKがクリックされたら、その時点でチェックされ
ている組合せにグラフが変更される。
FIG. 9 shows a display item selection screen 308 for actual guess display. The period for displaying the graph on the horizontal axis and the product model to be displayed on the vertical axis are displayed and can be selected with a check box. First, when this dialog is displayed, the current graph display status is displayed. For example, if the past three periods are displayed, it is displayed as if the check boxes for the three periods are checked. The color of the intersection of the checked row and column changes vertically and horizontally. If OK is clicked, the graph is changed to the combination currently checked.

図10は、実推表示の表示指標選択画面309である。「4分割表示」又は「
分割なし表示」のいずれかをラジオボタンで選択可能である。グラフ配置位置に
対応したプルダウンメニューで各パートの表示内容を選択可能である。選択肢は
「売上」「業績」「収益性」「評価損」「在庫」等があり、ここでは前者の4つ
を選択する。「4分割表示」がクリックされたら、プルダウンメニューが4つ表
示される。「分割なし表示」がクリックされたら、プルダウンメニューを1つに
する。このとき、左上の選択肢を引き継がれる。OKがクリックされたら、その
時点でチェックされている組合せにグラフを変更され,実推表示画面304に戻
る。キャンセルボタンがクリックされたら,何も変更せずに実推表示画面304
に戻る。
FIG. 10 shows a display index selection screen 309 for actual estimation display. "Quarter display" or "
One of “display without division” can be selected with a radio button. The display contents of each part can be selected from a pull-down menu corresponding to the graph arrangement position. Options include “sales”, “performance”, “profitability”, “valuation loss”, “inventory”, and the like. Here, the former four are selected. When “4-segment display” is clicked, four pull-down menus are displayed. When “No division display” is clicked, the pull-down menu is set to one. At this time, the upper left choice is carried over. If OK is clicked, the graph is changed to the combination checked at that time, and the screen returns to the actual guess display screen 304. If the cancel button is clicked, the actual display screen 304 is displayed without changing anything.
Return to.

図11は,図8の画面を用いて,右下のグラフを在庫から評価損に変更してみ
た例である。
FIG. 11 shows an example in which the lower right graph is changed from inventory to valuation loss using the screen of FIG.

図12が実推表示の目標値見直し画面310である。縦軸に目標項目とその細
目,横軸に期が表示される。この例の場合,目標項目は,売上高,限界利益,変
動費,在庫金額である。それぞれの目標値に関して,細目として,製品機種別に
分かれている。この例の場合、01/下が当期で,他の期が過去期である。各細目
の当期である01/下見直しの欄に該当する目標値を入力する。OKボタンがクリ
ックされると01/下見直しの欄に書き込まれた値が取り込まれ,目標値として設
定され,実推表示に戻る。Cancelボタンがクリックされたら,すべての入
力は無視され,実推表示に戻る。見直しの目標値(大日程計画案、損益、棚残、
売上等の目標値)は、図2で説明した方法でシミュレーション展開され、担当部
長の修正を経て算出決定される新たな大日程計画や補正計画や種々の予測値を、
経営意思決定支援装置101に送信する。
FIG. 12 shows a target value review screen 310 for actual estimation display. The target item and its details are displayed on the vertical axis, and the period is displayed on the horizontal axis. In this example, the target items are sales, marginal profit, variable cost, and inventory amount. Each target value is divided according to product type as a detail. In this example, 01 / below is the current period and the other period is the past period. Enter the target value in the 01 / down review column, which is the current period for each detail. When the OK button is clicked, the value written in the 01 / down review column is taken in, set as the target value, and the actual display returns. If the Cancel button is clicked, all inputs are ignored and the actual display is returned. Target value for review (large schedule plan, profit / loss, shelf remaining,
The target value such as sales) is developed by the method described in FIG. 2, and a new large schedule plan, correction plan, and various predicted values that are calculated and determined through correction by the manager in charge,
It transmits to the management decision support apparatus 101.

図13は、実推表示の大日程計画編集画面311である。この画面では、横軸
に製品機種、縦軸に大日程計画のタイムバケット単位の期間が表示される。この
マトリクスに、現行の大日程計画(旧)が表示され、これをもとに「新」の欄に
新しい大日程計画を書き込む。後述するが大日程計画が新規に作成されるたびに
、計画値とパラメータ(中日程計画や需要ケース)の想定値の組合せであるシナ
リオを新たに生成する。個々のシナリオはシナリオ番号で区別される。このシナ
リオ番号が、図8の実推表示画面の右上に表示されている。
FIG. 13 shows a large schedule plan edit screen 311 of actual estimation display. On this screen, the horizontal axis indicates the product model, and the vertical axis indicates the time period in units of time buckets for the large schedule. The current large schedule (old) is displayed in this matrix, and the new large schedule is written in the "new" column based on this. As will be described later, each time a large schedule is newly created, a scenario that is a combination of a plan value and an assumed value of a parameter (medium schedule plan or demand case) is newly generated. Individual scenarios are distinguished by scenario numbers. This scenario number is displayed at the upper right of the actual guess display screen of FIG.

図14は、シナリオレビュー画面312である。シナリオとは前述のように、大
日程計画、大日程計画を基に補正された補正計画、需要予測とは実態の需要が乖
離する場合を想定した需要ケースの組合せである。今まで説明してきた実推表示
は、このシナリオの一つについて表示しているだけである。複数のシナリオを同
時に評価可能なのがこの画面である。表形式で、それぞれの項目が、選択、シナ
リオ番号、大日程計画番号、補正計画番号、需要ケース番号、累積売上高、累積
売上台数、累積限界利益、在庫金額、評価損となっている。選択は、実推表示で
表示されている現状のシナリオを示す印である。この列の各欄をクリックするこ
とで、実推表示にシナリオを選択し、大日程計画自体を選択することが可能であ
る。シナリオ番号はシナリオを識別する番号である。新規の大日程計画が作成さ
れる場合や、新規の補正計画が作成される場合や、大日程計画と補正計画の組合
せに対して新規の需要ケースが適用される場合に、新規のシナリオが作成され、
新しい番号が付与される。大日程計画番号は、大日程計画を識別する番号である
。大日程計画の番号値はハイパーリンクになっており、大日程計画編集画面31
1とリンクしている。大日程計画番号がクリックされると、その番号の大日程計
画が編集画面に表示される。補正計画番号も大日程計画番号と同様である。異な
る点は、番号表示のハイパーリンクから移動する先の画面において、計画編集機
能を持たず、閲覧機能だけであることである。これは、補正計画編集は経営意思
決定支援装置の機能ではなく、損益意思決定支援装置の機能だからである。損益
意思決定支援装置にて、編集された補正計画の閲覧のために、ここにハイパーリ
ンクが存在する。需要ケースも補正計画と同様である。累積売上高、累積売上台
数、累積限界利益、在庫金額、評価損の項目名と値のそれぞれにハイパーリンク
がある。これは、時間による変動を表示するためのハイパーリンクである。この
詳細は、図15で述べる。このように、シナリオレビュー画面312は、シナリ
オ毎の評価値の違いを一覧可能とすることにより、経営意思決定を容易にするこ
とが可能となる。
FIG. 14 is a scenario review screen 312. As described above, the scenario is a combination of demand cases assuming that the actual demand is different from the large schedule, the corrected plan corrected based on the large schedule, and the demand forecast. The actual reasoning display that has been described so far is only for one of these scenarios. This screen allows you to evaluate multiple scenarios simultaneously. In the tabular form, each item is selected, scenario number, large schedule plan number, correction plan number, demand case number, cumulative sales, cumulative unit sales, cumulative marginal profit, inventory amount, and valuation loss. The selection is a mark indicating the current scenario displayed in the actual display. By clicking on each column in this column, it is possible to select a scenario for actual display and to select a large schedule plan itself. The scenario number is a number for identifying a scenario. A new scenario is created when a new large schedule is created, when a new compensation plan is created, or when a new demand case is applied to a combination of a large schedule and compensation plan And
A new number is given. The large schedule plan number is a number for identifying the large schedule plan. The large schedule plan number is a hyperlink, and the large schedule plan edit screen 31
Linked to 1. When a large schedule number is clicked, the large schedule plan with that number is displayed on the edit screen. The correction plan number is the same as the large schedule number. The difference is that the screen to which the user moves from the hyperlink of the number display does not have the plan editing function but only the browsing function. This is because the correction plan editing is not a function of the management decision support device, but a function of the profit and loss decision support device. A hyperlink exists here for browsing the correction plan edited by the profit / loss decision support apparatus. The demand case is the same as the correction plan. There are hyperlinks in the item names and values of cumulative sales, cumulative unit sales, cumulative marginal profit, inventory value, and valuation loss. This is a hyperlink for displaying changes over time. Details of this will be described with reference to FIG. In this way, the scenario review screen 312 can facilitate management decision making by making it possible to list differences in evaluation values for each scenario.

図15が累積売上高シナリオ比較画面である。図14において、累積売上高の
項目名がクリックされたときの例を示す。図15は、各シナリオの累積売上高の
変動をグラフ化したものである。ここでは、画面下部の大日程計画のプルダウン
から大日程計画番号を、又、補正計画(中日程計画)のプルダウンから補正計画
(中日程計画)番号を選択すると、選択された大日程計画を基に補正された中日
程計画の需要ケース毎の累積売上高が表示される。他の評価項目についても同様
である。
FIG. 15 is a cumulative sales scenario comparison screen. FIG. 14 shows an example when the item name of accumulated sales is clicked. FIG. 15 is a graph of changes in cumulative sales for each scenario. Here, if you select the large schedule plan number from the large schedule plan pull-down at the bottom of the screen and the correction plan (medium schedule plan) number from the correction plan (medium schedule plan) pull-down, the selected large schedule plan will be used. The accumulated sales for each demand case of the medium schedule plan corrected in is displayed. The same applies to other evaluation items.

次に,図16から図28を用いて,101の経営意思決定支援装置の処理の詳
細を示す。まず,図16を用いて,101の経営意思決定支援装置の機能構成と
、機能間の情報交換のプロトコルを示す。
Next, details of processing of the management decision support apparatus 101 will be described with reference to FIGS. 16 to 28. First, a functional configuration of the management decision support apparatus 101 and a protocol for exchanging information between functions will be described with reference to FIG.

1601は実績集計機能である。1602は画面用データである。1603は
グラフ用データ生成機能である。1604はグラフ用データである。1605は
画面表示機能である。1606はユーザー入力受付機能である。1607は経営
者が設定する種々の目標値である。
Reference numeral 1601 denotes a result totaling function. Reference numeral 1602 denotes screen data. Reference numeral 1603 denotes a graph data generation function. Reference numeral 1604 denotes graph data. Reference numeral 1605 denotes a screen display function. Reference numeral 1606 denotes a user input reception function. Reference numeral 1607 denotes various target values set by the manager.

実績集計機能1601は,発生単位で登録されている「販売実績,生産実績,
棚残実績」107を集計単位期間(例えば,月,週など)に集計し,その値を画
面用データ1602に出力する機能である。グラフ用データ生成機能1603は
,画面用データ1602を用いて,グラフにプロットする点列データであるグラ
フ用データ1604を生成する。また,グラフ用データ生成機能1603は,グ
ラフデータの変曲点を抽出して,その属性をグラフ用データ1604に書き込む
。1605の画面表示機能は,グラフ用データ1604と,損益目標,売上目標
,棚残目標,評価損目標とから,画面に図3から図17に示す画面を表示する。
ユーザー入力受付機能1606は大日程計画案および損益目標,売上目標,棚残
目標,評価損目標を変更する機能である。
The result totaling function 1601 is “sales results, production results,
This is a function of totaling the “shelf remaining record” 107 in the total unit period (for example, month, week, etc.) and outputting the value to the screen data 1602. The graph data generation function 1603 uses the screen data 1602 to generate graph data 1604 that is point sequence data to be plotted on the graph. The graph data generation function 1603 extracts the inflection point of the graph data and writes the attribute to the graph data 1604. The screen display function 1605 displays the screens shown in FIGS. 3 to 17 on the screen from the graph data 1604 and the profit / loss target, the sales target, the remaining shelf target, and the valuation loss target.
The user input acceptance function 1606 is a function for changing the large schedule plan and the profit / loss target, the sales target, the remaining shelf target, and the valuation loss target.

図17から図20を用いて,データベース107の販売実績,生産実績,棚残
実績の詳細を示す。図17と図18は,データベース107の販売実績の詳細で
ある。販売実績は,図17の売上実績と図18の損益実績より構成される。売上
実績は,図17に示すように,売上が発生した単位に,発生日,製品(製品仕様
),チャネル(図37に示すツリー構造のノードに相当),販売価格(単価),
台数,売上から構成される。ここで、製品(製品仕様)とは、製品機種(PC製
品のラインナップ)中の一機種であり、本実施の形態では製品(PC)の特徴事
項であるCPUの名称で識別している。損益実績は,図18に示すように,単位
期間(月もしくは,週もしくは日)で集計した単位に集計日,製品(製品仕様)
,チャネル,売上,原価,利益より構成される。図19は,生産実績の詳細であ
る。生産実績は,図19に示すように,各生産ロットの計上毎に蓄積されたデー
タで,計上日,製品(製品仕様),台数,原価,払出ベースの総原価,購入ベー
スの総原価より構成される。図20は,棚残実績の詳細を示す。棚残実績は,図
20に示すように,集計日毎,製品単位に集計される。
The details of the sales record, production record, and shelf remaining record of the database 107 will be described with reference to FIGS. FIG. 17 and FIG. 18 show details of sales results in the database 107. The sales record is composed of the sales record of FIG. 17 and the profit / loss record of FIG. As shown in FIG. 17, the sales results are shown in units of sales, date of occurrence, product (product specification), channel (corresponding to the node of the tree structure shown in FIG. 37), sales price (unit price),
Consists of number of units and sales. Here, the product (product specification) is one of the product models (PC product lineup), and is identified by the name of the CPU, which is a feature of the product (PC) in this embodiment. As shown in FIG. 18, the profit and loss results are calculated in the unit calculated by the unit period (month, week or day), and the product (product specification).
, Channel, sales, cost, profit. FIG. 19 shows details of production results. As shown in FIG. 19, production results are data accumulated for each production lot, and are composed of the date of recording, product (product specification), number of units, cost, total cost of payout, and total cost of purchase. Is done. FIG. 20 shows the details of the remaining shelf record. As shown in FIG. 20, the shelf remaining results are tabulated on a tabulation date and product basis.

図21から図25を用いて,ユーザー入力受付機能1606により編集するデ
ータである大日程計画案,損益目標,売上目標,棚残目標,評価損目標の詳細を
示す。
FIG. 21 to FIG. 25 show details of a large schedule plan, profit / loss target, sales target, remaining shelf target, and valuation loss target, which are data edited by the user input reception function 1606.

図21は,大日程計画案の一例を示す。大日程計画案は,計画番号,計画対象
期(例えば2001年4月1日〜4月31日),製品機種,チャネル,台数から構成され
る。ここでは、計画対象期を1ヶ月としたが、合計して半年とすることもできる
。計画番号は,複数の計画案を「新規」「補正」といった形で区別するための情
報である。
FIG. 21 shows an example of a large schedule plan. The large schedule plan is composed of a plan number, a plan target period (for example, April 1 to April 31, 2001), a product model, a channel, and the number of units. Here, the target period for planning is one month, but the total period can be six months. The plan number is information for distinguishing a plurality of plans in the form of “new” and “correction”.

図22は,損益目標の一例を示す。損益目標は、対象期,製品機種,チャネル
,利益で構成される。図23は,売上目標を示す。売上目標は対象期,製品機種
,チャネル,売上で構成される。図24は,棚残目標を示す。棚残目標は対象期
,製品機種,棚残金額で構成される。
FIG. 22 shows an example of the profit / loss target. The profit / loss target consists of target period, product model, channel, and profit. FIG. 23 shows the sales target. The sales target consists of target period, product model, channel, and sales. FIG. 24 shows the remaining shelf target. The remaining shelf target consists of the target period, product type, and remaining shelf price.

図25から図28を用いて,118の売上予測と損益予測,119の棚残予測
と評価損予測の詳細を示す。図25は,売上予測の詳細である。売上予測は,図
25に示すように,予測区分(シナリオ番号),予測対象日,製品(製品仕様)
,チャネル,販売価格,台数,売上で構成される。予測区分とは,予測のシナリ
オを表すデータであり、前述の大日程計画案(新計画)と補正された中日程計画
に基づく大日程計画案を区別するために使われる。予測対象日とは,将来のどの
時点を予測しているかを表す。図26は,損益予測の詳細である。損益予測は,
図26に示すように,予測区分,予測対象日,製品(製品仕様),チャネル,売
上,原価,利益より構成される。図27は,棚残予測の詳細である。棚残予測は
,図27に示すように,予測区分,予測対象日,製品(製品仕様),棚残金額で
構成される。図28は,評価損予測の詳細である。評価損予測は,図28に示す
ように,予測区分,予測対象日,製品(製品仕様),棚残金額で構成される。
The details of 118 sales forecast and profit / loss forecast and 119 shelf remaining forecast and valuation loss forecast will be described with reference to FIGS. FIG. 25 shows the details of the sales forecast. As shown in FIG. 25, the sales forecast includes a forecast category (scenario number), a forecast target date, and a product (product specification).
, Channel, sales price, number of units, sales. The prediction category is data representing a scenario for prediction, and is used for distinguishing the above-mentioned large schedule plan (new plan) from the large schedule plan based on the corrected medium schedule plan. The prediction target date indicates which point in the future is predicted. FIG. 26 shows details of the profit / loss prediction. The profit and loss forecast is
As shown in FIG. 26, it is composed of a prediction category, a prediction target date, a product (product specification), a channel, sales, cost, and profit. FIG. 27 shows the details of the remaining shelf prediction. As shown in FIG. 27, the remaining shelf prediction includes a prediction category, a prediction target date, a product (product specification), and a remaining shelf price. FIG. 28 shows details of the evaluation loss prediction. As shown in FIG. 28, the evaluation loss prediction includes a prediction category, a prediction target date, a product (product specification), and a remaining shelf price.

このように、本実施の形態では、経営意思決定支援装置101を図16に示し
たような構成とすることにより、経営意思決定のための有益な指標をグラフ表示
することができ、また他の損益シミュレーション装置103や棚残シミュレーシ
ョン装置105との連携により、経営者に対して迅速かつ的確に経営指標を提供
することができる。
As described above, in the present embodiment, the management decision support apparatus 101 is configured as shown in FIG. 16 so that useful indicators for management decision making can be displayed in a graph. By linking with the profit / loss simulation apparatus 103 and the shelf-remaining simulation apparatus 105, it is possible to provide a management index quickly and accurately to the manager.

以上の実施の形態では、経営意思決定支援装置101、損益意思決定支援装置
102、損益シミュレーション装置103、調達計画立案装置104、棚残シミ
ュレーション装置105、棚残・調達計画支援装置106が同一企業内にある場
合を想定して説明したが、本発明はこの場合に限られず、他の企業との連携システ
ムであってもよい。例えば、経営意思決定支援装置101はA社の保有するシス
テムであり、他の装置群は、製造受託会社Bや物流管理会社Cが保有し、ネット
ワークを介して情報の授受を行うことで経営意思決定支援を実現することができ
る。また、本発明は、経営意思決定支援装置101と損益意思決定支援装置10
2と棚残・調達計画支援装置106は、同一企業又は複数企業で保有し、損益シ
ミュレーション装置103と調達計画立案装置104と棚残シミュレーション装
置105は、シミュレーションサービス提供会社D(ASP: Application Ser
vice Provider)が保有する形態とすることもできる。この場合、企業側は、G
UI機能を動作させるハードウェアを保有するだけで、経営意思決定支援サービ
スの提供(シミュレーションサービスの提供)を受けることができ、ASP側は
、当該サービスに対する対価を受けることができる。
In the above embodiment, the management decision support device 101, the profit / loss decision support device 102, the profit / loss simulation device 103, the procurement plan planning device 104, the shelf remaining simulation device 105, and the shelf remaining / procurement plan support device 106 are within the same company. However, the present invention is not limited to this case, and may be a cooperation system with other companies. For example, the management decision support device 101 is a system owned by company A, and the other device groups are owned by the contract manufacturing company B and the logistics management company C, and they exchange management information through the network. Decision support can be realized. The present invention also includes a management decision support device 101 and a profit / loss decision support device 10.
2 and the shelf remaining / procurement plan support device 106 are owned by the same company or a plurality of companies, and the profit / loss simulation device 103, the procurement plan planning device 104, and the shelf remaining simulation device 105 are connected to a simulation service providing company D (ASP: Application Server).
vice Provider). In this case, the company
The management decision support service can be provided (simulation service provided) simply by holding the hardware that operates the UI function, and the ASP side can receive a price for the service.

次に、本発明の第2の実施形態について説明する。   Next, a second embodiment of the present invention will be described.

以下,本発明による損益意思決定支援システムの実施形態を図面により詳細に
説明する。
Embodiments of a profit / loss decision making support system according to the present invention will be described below in detail with reference to the drawings.

図29は、本実施形態による損益意思決定支援システムにおける各種の情報お
よび装置の関連を説明する図である。図29において、図1と同じ部分について
は、同一の表記をするものとし、同じ部分でも細分化しているものについては改
めて記号を付けている。
FIG. 29 is a diagram illustrating the relationship between various types of information and devices in the profit / loss decision making support system according to the present embodiment. 29, the same parts as those in FIG. 1 are denoted by the same notation, and the same parts are subdivided with symbols again.

2907は損益目標情報,2908は売上目標情報,2909は損益シミュレ
ーション装置103の出力する大日程計画案情報,2910は中日程計画案情報
,2911は配分率情報,2912は計画実行可否情報,2913損益・売上・
原価情報,2914は製品売価予定(仕切率,価格)情報,2915は販売・生
産計画担当部長により修正された大日程計画情報,2916は配分率情報,29
17製品売価予定(仕切率,価格)情報,2922は損益シミュレーション装置
103が経営意思決定支援装置101に出力する大日程計画案情報、2923は
損益予測情報,2924は売上予測情報である。
2907 is profit / loss target information, 2908 is sales target information, 2909 is large schedule plan information output by the profit / loss simulation apparatus 103, 2910 is medium schedule plan information, 2911 is allocation rate information, 2912 is plan execution possibility information, and 2913 profit / loss ·Sales·
Cost information, 2914 is a product selling price schedule (partition rate, price) information, 2915 is a large schedule plan information modified by the sales / production plan manager, 2916 is allocation rate information, 29
17 product sales price schedule (partition rate, price) information, 2922 is large schedule plan information output by the profit / loss simulation apparatus 103 to the management decision support apparatus 101, 2923 is profit / loss forecast information, and 2924 is sales forecast information.

本実施形態による損益意思決定支援システムは、図29に示すように、各種経
営指標や大日程計画案を生成する経営意思決定支援装置101と、経営意思決定
支援装置101により生成された大日程計画案115を中日程計画案に展開し,
その損益情報を算出・保持する損益シミュレーション装置103と,販売・生産
担当部長側に設置され,損益シミュレーション装置103の保持する情報及び経
営意思決定支援装置101から提供された損益目標や売上目標を参照しながら各
種情報の変更を行う損益意思決定支援装置103により構成される。
As shown in FIG. 29, the profit and loss decision support system according to this embodiment includes a management decision support apparatus 101 that generates various management indexes and a large schedule plan, and a large schedule plan generated by the management decision support apparatus 101. Develop plan 115 into a medium schedule plan,
The profit / loss simulation apparatus 103 for calculating / holding the profit / loss information, and the information held by the sales / production simulator 103 and the profit / loss target and the sales target provided by the management decision support apparatus 101 are referred to. The profit / loss decision support apparatus 103 is configured to change various types of information.

また,その際,展開された中日程計画案124をベースに調達計画案120(
図1)を立案する調達計画立案装置104と,中日程計画案124と調達計画案
120とから払出原価予定を算出する機能を有する棚残シミュレーション装置1
05を用いることにより,損益シミュレーション装置103で利用する払出原価
予定を動的に算出する。
At that time, the procurement plan 120 (based on the developed medium schedule 124)
1), a shelf plan simulation device 1 having a function of calculating a payout cost schedule from the medium schedule plan 124 and the procurement plan 120.
By using 05, the payout cost schedule used in the profit / loss simulation apparatus 103 is dynamically calculated.

各種情報を提供する損益意思決定支援装置102は,各意思決定者からもアク
セス可能で、保持されている情報を各意思決定支援者側の端末に取り込むことが
できるように、Web、ブラウザ等を利用した装置として構成されている。
The profit and loss decision support device 102 that provides various information can be accessed by each decision maker, and the Web, browser, etc. can be used so that the stored information can be taken into the terminal of each decision support side. It is configured as a used device.

図30のシーケンス図を用いて、損益意思決定支援システムについて説明する。   The profit and loss decision support system will be described with reference to the sequence diagram of FIG.

図30は,図29にて示した各装置間の処理及び情報のやりとりを時系列に記
したシーケンス図であり、第1の実施形態において説明した図2のシーケンス図
と共通する。図30では、図2のS204を、大日程計画案展開処理3002、
実行可能性チェック処理3003と詳細化し、S207を大日程計画案展開処理
3008、実行可能性チェック処理3009と詳細化している点が異なる。
FIG. 30 is a sequence diagram illustrating processing and information exchange between the devices illustrated in FIG. 29 in time series, and is common to the sequence diagram of FIG. 2 described in the first embodiment. In FIG. 30, S204 of FIG.
It differs from the feasibility check process 3003 in that S207 is refined into a large schedule plan development process 3008 and an feasibility check process 3009.

まず、経営意思決定支援装置101で立案された新規の大日程計画案115は
,損益シミュレーション装置103に提供・保持される。同時に,損益目標29
07及び売上目標2908は,損益意思決定支援装置102に提供・保持される。
First, a new large-scale schedule 115 prepared by the management decision support apparatus 101 is provided and held in the profit / loss simulation apparatus 103. At the same time, profit / loss target 29
07 and the sales target 2908 are provided and held in the profit and loss decision support apparatus 102.

新規の大日程計画案115を受け取った損益シミュレーション装置103は,
まず大日程計画展開機能3002により新規の大日程計画案を展開し,新規の中
日程計画案(124、2910)を作成する。
The profit and loss simulation apparatus 103 that has received the new large schedule 115 is:
First, a new large schedule plan is developed by the large schedule plan development function 3002 to create a new medium schedule plan (124, 2910).

その後,実行可能性チェック機能3003により,新規の中日程計画案が実行
可能かどうかのチェックを行う。作成された計画実行可否情報2912および新
規の大日程計画案2909・中日程計画案2910,配分率2911は,損益意
思決定支援装置に転送・保持される。
Thereafter, the feasibility check function 3003 checks whether or not the new medium schedule plan can be executed. The created plan execution availability information 2912, the new large schedule plan 2909, the medium schedule plan 2910, and the distribution rate 2911 are transferred and held in the profit and loss decision support apparatus.

同時に,新規の中日程計画案124は調達計画立案装置104に転送される。
調達計画立案装置104では,調達計画立案機能3004により新規の中日程計
画案124をベースに新規の調達計画案を作成する。立案された新規の調達計画
案は棚残シミュレーション装置105に転送され,払出原価計算機能3005に
より中日程計画レベルの払出原価予定125が算出される。算出された払出原価
予定125は損益シミュレーション装置103に提供される。
At the same time, the new medium schedule plan 124 is transferred to the procurement plan planning device 104.
In the procurement plan planning device 104, a new procurement plan is created based on the new medium schedule plan 124 by the procurement plan planning function 3004. The drafted new procurement plan is transferred to the shelf-remaining simulation apparatus 105, and the payout cost plan 125 at the middle schedule plan level is calculated by the payout cost calculation function 3005. The calculated payout cost schedule 125 is provided to the profit / loss simulation apparatus 103.

払出原価125を受け取った損益シミュレーション装置103は,新規の中日
程計画と払出原価と製品売価予定を元に損益計算機能3006によって損益計算
を行い,その結果として得られる「損益・売上情報と払出原価」2913と製品
売価予定2914を損益意思決定支援装置102に提供する。
The profit / loss simulation apparatus 103 that has received the payout cost 125 performs profit / loss calculation by the profit / loss calculation function 3006 based on the new medium schedule plan, the payout cost, and the product selling price schedule, and obtains the “profit / loss information and payout cost” obtained as a result. 2913 and product sales price schedule 2914 are provided to the profit and loss decision support apparatus 102.

損益・売上情報を受け取った損益意思決定支援装置は,事前に受け取っている
計画実行可否情報2912,新規の大日程計画案2909・中日程計画案291
0,配分率2911およびツリー構造で表される機種構成情報126を利用して
これらの情報を画面に表示する。表示画面の一例は、図37に示す。
The profit / loss decision-making support apparatus that has received the profit / loss / sales information receives the plan execution availability information 2912 received in advance, the new large schedule plan 2909, and the medium schedule plan 291.
These pieces of information are displayed on the screen using 0, the distribution rate 2911, and the model configuration information 126 represented by a tree structure. An example of the display screen is shown in FIG.

また,損益意思決定支援装置102の「大日程計画変更機能および配分率変更機能」3007を用いてこれらの値を変更することが可能である。補正された大日程計画案2915,配分率2916は損益シミュレーション装置に転送され,ふたたび大日程計画展開機能3008,実行可能性チェック機能3009によって展開・実行可能性チェックがされる。   These values can be changed using the “large schedule plan change function and distribution rate change function” 3007 of the profit and loss decision support apparatus 102. The corrected large schedule plan 2915 and the distribution ratio 2916 are transferred to the profit / loss simulation apparatus, and the expansion / executability check is performed again by the large schedule plan expansion function 3008 and the feasibility check function 3009.

作成された計画実行可否情報2912および補正後の大日程計画案2909・
中日程計画案2910,配分率2911は,損益意思決定支援装置102に転送
・保持される。
Created plan execution availability information 2912 and the revised large schedule plan 2909.
The medium schedule plan 2910 and the distribution rate 2911 are transferred and held in the profit / loss decision making support apparatus 102.

同時に,補正後の中日程計画案124は調達計画立案装置104に転送される
。調達計画立案装置104では,調達計画立案機能3010により補正後の中日
程計画案124をベースに新規の調達計画案を作成する。立案された補正後の調
達計画案は棚残シミュレーション装置105に転送され,払出原価計算機能30
11により中日程計画レベルの払出原価予定125が改めて算出される。
At the same time, the corrected medium schedule plan 124 is transferred to the procurement plan planning apparatus 104. In the procurement plan planning device 104, a new procurement plan is created based on the corrected medium schedule plan 124 by the procurement plan planning function 3010. The corrected procurement plan draft that has been drafted is transferred to the shelf-remaining simulation apparatus 105 and the paid-out cost calculation function 30
11, the payout cost schedule 125 at the medium schedule level is calculated again.

算出された払出原価はふたたび損益シミュレーション装置103に提供される。   The calculated payout cost is provided to the profit / loss simulation apparatus 103 again.

払出原価を受け取った損益シミュレーション装置103は,補正後の中日程計
画と払出原価と製品売価予定を元に損益計算機能3012によって再度、損益計
算を行い,その結果として得られる「損益・売上情報と払出原価」2913と製
品売価予定2914を損益意思決定支援装置102に提供する。
The profit / loss simulation apparatus 103 that has received the paid-out cost calculates the profit / loss again by the profit / loss calculating function 3012 based on the corrected medium schedule plan, the paid-out cost, and the product selling price schedule. The “paid out cost” 2913 and the product sales price schedule 2914 are provided to the profit / loss decision making support apparatus 102.

さらに,損益意思決定支援装置上の製品売価予定変更機能3013を用い,製
品売価予定を変更することが可能である。この場合,補正された製品売価予定3
017は損益シミュレーション装置103に転送され,損益シミュレーション装
置103の損益計算機能3014により損益計算され,その結果を再度損益意思
決定支援装102に転送し,表示機能によって画面上に表示される。ここで、図
30では、「大日程計画変更機能および配分率変更機能」3007と「製品売価予
定変更機能」3013を分けて記載したが、これは、その変更後の処理が異なる
為、便宜的に分けて記載しただけであり、1つの変更機能としてまとめてもよい。
Further, the product selling price schedule change function 3013 on the profit / loss decision making support apparatus can be used to change the product selling price schedule. In this case, the revised product selling price schedule 3
017 is transferred to the profit / loss simulation apparatus 103, and profit / loss is calculated by the profit / loss calculation function 3014 of the profit / loss simulation apparatus 103, and the result is transferred again to the profit / loss decision making support apparatus 102 and displayed on the screen by the display function. Here, in FIG. 30, the “large schedule plan change function and distribution rate change function” 3007 and the “product sales price schedule change function” 3013 are described separately, but this is for convenience because the processing after the change is different. It is only described separately, and may be summarized as one change function.

このようなシミュレーションを数回行い,販売・生産担当部長が満足するよう
な計画実行可能な大日程計画案が作成されたら,損益意思決定支援装置102を
終了する(3015)ことにより,損益予測情報2923,売上予測情報292
4,補正後の大日程計画案2922が経営意思決定支援装置101に転送され,
一連の処理が終了する。
When such a simulation is performed several times and a large-scale plan plan that can be executed so as to satisfy the sales / production manager is created, the profit / loss decision-making support apparatus 102 is terminated (3015). 2923, sales forecast information 292
4. The corrected large schedule plan 2922 is transferred to the management decision support apparatus 101,
A series of processing ends.

本実施の形態では、需要変動等の不確定要素によって計画と実績が乖離した場
合のシミュレーションを実施するため,損益意思決定支援装置上でシナリオ毎に
設定された大日程計画案・補正計画番号・需要ケース番号を用いて複数の解を算
出し、経営者に提供することが可能である。
In this embodiment, in order to perform a simulation when the plan and the actual result deviate due to uncertain factors such as fluctuations in demand, a large schedule plan / corrected plan number set for each scenario on the profit / loss decision support device It is possible to calculate a plurality of solutions using the demand case number and provide them to the manager.

図31は、損益シミュレーション装置103の機能構成と入出力情報を詳細に
説明したものである。
FIG. 31 illustrates the functional configuration and input / output information of the profit / loss simulation apparatus 103 in detail.

損益シミュレーション装置103は大日程計画展開機能3101と,実行可能
性チェック機能3102と,損益計算機能3103で構成される。損益シミュレ
ーション装置103は,図31の上段および左辺に示した大日程計画案,機種構
成情報,配分率,所要量計算マスタ,製品売価予定(仕切率,価格),払出原価
予定を入力情報とし,図31の下段および右辺に示した大日程計画案,中日程計
画案,配分率,計画実行可否,損益,売上,原価情報,製品売価予定(仕切率,
価格)を出力情報とする。
The profit / loss simulation apparatus 103 includes a large schedule plan development function 3101, an feasibility check function 3102, and a profit / loss calculation function 3103. The profit / loss simulation apparatus 103 uses, as input information, a large schedule plan, model configuration information, distribution rate, requirement calculation master, product sales price schedule (partition rate, price), and payout cost schedule shown in the upper and left sides of FIG. Large schedule plan, middle schedule plan, allocation rate, plan execution availability, profit / loss, sales, cost information, product selling price schedule (partition rate,
Price) as output information.

大日程計画展開機能3101は,図40に示すような,計画区分と計画対象期
(月単位)と機種とチャネルと台数情報を持つ計画値である大日程計画案と,図
41に示すような,構成IDと親構成要素情報と子構成要素情報を持ち製品のツ
リーを作成するために必要な機種構成情報126と,図42に示すような,計画
区分と計画対象期(月単位)と構成IDと配分率を持ち展開時に使用する配分率
を提供する配分率情報を入力とし,図43に示すような,計画区分と計画対象期
(月単位)と製品名称(部品名称)と台数を持つ詳細レベルの計画値である中日
程計画案と,入力情報と同一フォーマットである大日程計画案,配分率を出力す
る。大日程計画展開機能は,後述する図32で説明する手順により算出する。
The large schedule plan development function 3101 includes a large schedule plan that is a plan value having a plan category, a target period (monthly), a model, a channel, and the number of units as shown in FIG. 42. Model configuration information 126 having a configuration ID, parent component information, and child component information, and necessary for creating a product tree, as shown in FIG. 42, a plan category, a target period (monthly), and a configuration The distribution rate information that has the ID and the distribution rate and provides the distribution rate to be used at the time of deployment is input, and as shown in FIG. 43, it has the plan classification, the target period (monthly), the product name (part name), and the number of units. The medium schedule plan, which is the detailed level plan value, the large schedule plan, which has the same format as the input information, and the allocation rate are output. The large schedule plan development function is calculated according to the procedure described later with reference to FIG.

実行可能性チェック機能3102は,所要量計算を行うために必要なマスタ情
報である所要量計算マスタ127と,大日程計画展開機能の出力情報である中日
程計画案を入力とし,図44に示すような,計画区分と計画対象期と製品名称と
実行可否情報を持つ計画実行可否情報を出力する。実行可能性チェック機能は,
後述する図33で説明する手順により算出する。
The feasibility check function 3102 receives the requirement calculation master 127, which is master information necessary for calculating the requirement, and the medium schedule plan, which is output information of the large schedule development function, as shown in FIG. The plan execution availability information having the plan classification, the planning target period, the product name, and the execution availability information is output. The feasibility check function
Calculation is performed according to a procedure described later with reference to FIG.

損益計算機能3103は,図45に示すような,計画区分と計画対象期とチャ
ネル情報と仕切率をもつ製品売価予定(仕切率予定)と,図46に示すような,
計画対象期と製品と標準価格情報を持つ製品価格予定と,大日程計画展開機能3
101で出力された大日程計画案,機種構成情報,配分率を入力とし,図47に
示すような,計画区分と計画対象期と構成IDと損益情報と売上情報と原価情報
を持つ損益・売上・原価情報を出力する。損益計算機能は,後述する図34で説
明する手順により算出する。
The profit / loss calculation function 3103 has a plan for selling a product (planned partition rate) having a plan category, a plan target period, channel information, and a partition rate as shown in FIG.
Product price plan with plan target period, product and standard price information, and large schedule plan deployment function 3
The large schedule plan, model configuration information, and distribution rate output in 101 are input, and the profit / loss / sales with plan classification, plan target period, configuration ID, profit / loss information, sales information, and cost information as shown in FIG.・ Output cost information. The profit / loss calculation function is calculated according to the procedure described later with reference to FIG.

ここで,図32に示すフローを参照して,大日程計画展開機能の行う計算手順
を説明する。
Here, with reference to the flow shown in FIG. 32, the calculation procedure performed by the large schedule plan development function will be described.

ステップ3201では,機種構成情報126に基づき,大日程計画案を配分率
に従って展開し,中日程計画案を算出する。
In step 3201, based on the model configuration information 126, the large schedule plan is developed according to the distribution rate, and the medium schedule plan is calculated.

ステップ3202では,F330などといった製品機種レベルの大日程計画案
を,機種構成情報に基づいて上位階層に積み上げ計算する。積み上げ計算により
、例えば、F30、F310、F330の売上の総計を算出して、更に上位の製
品形態レベル(DT:デスクトップ)の損益計算をすることができる(図37参
照)。
In step 3202, a large-scale schedule plan at the product model level such as F330 is accumulated and calculated in the upper hierarchy based on the model configuration information. By the accumulation calculation, for example, the total sales of F30, F310, and F330 can be calculated, and the profit / loss calculation of the higher product form level (DT: desktop) can be performed (see FIG. 37).

ステップ3203では,展開対象期間を1期後ろへずらす。   In step 3203, the development target period is shifted backward by one period.

ステップ3204では,計算対象期間が計算対象外かどうかチェックし,計算
対象外で無ければステップ3201へ戻り処理を続け,計算対象外ならば大日程
計画展開処理を終了する。
In step 3204, it is checked whether or not the calculation target period is not a calculation target. If the calculation target period is not a calculation target, the process returns to step 3201 to continue the process.

次に,図33で示すフローを参照して,実行可能性チェック機能の行う計算手
順を説明する。
Next, a calculation procedure performed by the feasibility check function will be described with reference to the flow shown in FIG.

ステップ3301では,部品の所要量から発注単位などを考慮した公知の所要
調達量を算出する方法を用いて,中日程計画案から部材所要量を算出する。
In step 3301, the member requirement is calculated from the medium schedule plan by using a known method for calculating the required procurement amount considering the ordering unit from the component requirement.

ステップ3302では,ステップ3301で展開された部材の所要量と,供給
制約,能力制約とを比較し,ステップ3303で所要量<制約の場合,ステップ
3905に進む。所要量>制約の場合は,ステップ3304にて計画実行可否情
報の実行可否欄にNGフラグをたて,ステップ3305に進む。
In Step 3302, the required amount of the member developed in Step 3301 is compared with the supply constraint and the capability constraint. If the required amount is less than the constraint in Step 3303, the process proceeds to Step 3905. If the requirement> constraint, an NG flag is set in the execution availability column of the plan execution availability information in step 3304, and the process proceeds to step 3305.

ステップ3305展開対象となる中日程計画案を1つ後ろへずらす。   Step 3305: Shift the middle schedule plan to be expanded one step backward.

ステップ3306では,未計算の中日程計画案があるかどうかチェックし,未
計算の中日程計画案がある場合はステップ3301へ戻り処理を続け,なければ
制約チェック展開処理を終了する。
In step 3306, it is checked whether there is an uncalculated medium schedule plan. If there is an uncalculated medium schedule plan, the process returns to step 3301, and if not, the constraint check expansion process is terminated.

次に,図34で示すフローを参照して,損益計算機能の行う計算手順を説明す
る。
Next, the calculation procedure performed by the profit / loss calculation function will be described with reference to the flow shown in FIG.

ステップ3401では,製品価格予定情報に仕切率を掛け,製品毎の売価情報
を算出する。この際,対象とする製品を含むツリーのチャネル情報を機種構成情
報から特定し,そのチャネルに設定されている仕切値を利用する。
In step 3401, the product price schedule information is multiplied by the partition rate to calculate selling price information for each product. At this time, the channel information of the tree including the target product is specified from the model configuration information, and the partition value set for the channel is used.

ステップ3402では,ステップ3401で算出した売価を,中日程計画の台
数に掛け,中日程計画レベルの合計売価を算出する。
In step 3402, the selling price calculated in step 3401 is multiplied by the number of the middle schedule plan to calculate the total selling price at the middle schedule plan level.

ステップ3403では,棚残シミュレーション装置より提供された払出原価予
定を,中日程計画の台数に掛け,中日程計画レベルの合計原価を算出する。
In step 3403, the payout cost schedule provided from the remaining shelf simulation apparatus is multiplied by the number of medium schedules to calculate the total cost at the medium schedule level.

ステップ3404では,ステップ3402で算出された合計売価からステップ
3403で算出された合計原価の金額を減算し,中日程計画レベルの損益を算出
する。
In Step 3404, the amount of the total cost calculated in Step 3403 is subtracted from the total selling price calculated in Step 3402 to calculate the profit / loss at the middle schedule plan level.

ステップ3405では,ステップ3404で算出された中日程計画レベルの損
益情報を,上位階層まで積上計算し,機種構成ツリー全体での損益情報を算出す
る。
In step 3405, the profit / loss information at the medium schedule level calculated in step 3404 is calculated up to the upper hierarchy, and the profit / loss information in the entire model configuration tree is calculated.

ステップ3406では,展開対象期間を1期後ろへずらす。   In step 3406, the expansion target period is shifted backward by one period.

ステップ3407では,計算対象期間が計算対象外かどうかチェックし,計算
対象外で無ければステップ3401へ戻り処理を続け,計算対象外ならば損益計
画処理を終了する。
In step 3407, it is checked whether or not the calculation target period is not a calculation target. If the calculation target period is not a calculation target, the process returns to step 3401 and if not, the profit / loss planning process is terminated.

図35は,損益意思決定支援装置の提供する機能について説明した図である。
損益意思決定支援装置102は,経営意思決定支援装置101から提供される売
上目標,損益目標を画面上に表示する売上目標表示機能3501および損益目標
表示機能3502と,損益シミュレーション装置から提供される損益・売上・原
価,大日程計画案,機種構成情報,中日程計画案,配分率,計画実行可否,製品
売価予定(仕切率・価格)を画面上に表示する損益・売上・原価表示機能350
3,大日程計画表示機能3504,機種構成表示機能3505,中日程計画表示
機能3506,配分率表示機能3507,計画実行可否表示機能3508および
製品売価予定表示機能3509と,大日程計画案,配分率,製品売価予定を画面
上で変更する大日程計画変更機能3510,配分率変更機能3511および製品
売価予定変更機能3512から構成される。
FIG. 35 is a diagram for explaining functions provided by the profit / loss decision making support apparatus.
The profit / loss decision support apparatus 102 includes a sales target provided from the management decision support apparatus 101, a sales target display function 3501 for displaying the profit / loss target on the screen, a profit / loss target display function 3502, and a profit / loss provided from the profit / loss simulation apparatus.・ Sales / cost, large schedule plan, model configuration information, medium schedule plan, allocation rate, plan execution availability, product sales price schedule (partition rate / price) on the screen Profit / loss / sales / cost display function 350
3, large schedule plan display function 3504, model configuration display function 3505, medium schedule plan display function 3506, distribution rate display function 3507, plan execution availability display function 3508, product sales price schedule display function 3509, large schedule plan draft, allocation rate , A large schedule plan changing function 3510 for changing the product selling price schedule on the screen, an allocation rate changing function 3511, and a product selling price schedule changing function 3512.

各機能を実現するためのユーザインタフェース画面の表示例を図37〜39に
,その画面の遷移を示したものを図36に示す。
Display examples of user interface screens for realizing each function are shown in FIGS. 37 to 39, and transitions of the screens are shown in FIG.

図36は損益意思決定支援装置102にアクセスした後の販売・生産担当部長
側の端末に表示される画面の遷移について説明する図である。
FIG. 36 is a diagram for explaining the transition of the screen displayed on the terminal of the sales / production manager in charge after accessing the profit and loss decision support apparatus 102.

図36に示すように,メインメニューから損益意思決定支援装置の起動をマウ
スのクリック等により選択することにより,図37に示すような損益意思決定支
援装置の構成ツリー画面(以下構成ツリー画面)に遷移する。構成ツリー画面で
は各種情報の表示,変更が可能であり,情報を変更した場合。即座にその情報が
損益シミュレーション装置103に渡され,再計算した結果が損益意思決定支援
装置102に渡され,新たな値を表示させることが可能である。
As shown in FIG. 36, by selecting activation of the profit / loss decision making support apparatus from the main menu by clicking the mouse or the like, the profit / loss decision support apparatus shown in FIG. 37 has a configuration tree screen (hereinafter referred to as a configuration tree screen). Transition. Various information can be displayed and changed on the configuration tree screen, and the information is changed. The information is immediately passed to the profit and loss simulation apparatus 103, and the recalculated result is passed to the profit and loss decision support apparatus 102 to display a new value.

また,構成ツリー画面上の構成要素のいずれかを例えばマウスの右クリック等
で選択する事により,図38に示すような配分率変更画面に遷移することが可能
である。
Further, by selecting any of the constituent elements on the configuration tree screen by, for example, right-clicking the mouse, it is possible to transit to the distribution rate change screen as shown in FIG.

さらに,構成ツリー画面上の構成要素のいずれかを例えばマウスの左クリック
等で選択することにより,図39に示すような詳細情報表示画面に遷移すること
が可能である。
Furthermore, it is possible to transition to a detailed information display screen as shown in FIG. 39 by selecting any of the constituent elements on the configuration tree screen with, for example, a left click of the mouse.

以下,販売・生産担当部長側に表示される画面による販売・生産担当部長の操
作について簡単に説明する。
The operation of the sales / production manager in charge of the screen displayed on the sales / production manager will be briefly described below.

図37は,構成ツリー画面の表示例を示した図である。構成ツリー画面では,
まず3701に示す対象期間選択欄より表示させたい期間を選択する。期間を選
択すると,その期間における各種情報が表示される。
FIG. 37 is a diagram showing a display example of the configuration tree screen. In the configuration tree screen,
First, a period to be displayed is selected from the target period selection field 3701. When a period is selected, various information for that period is displayed.

構成ツリー画面では,損益シミュレーション装置103から提供される大日程
計画案,中日程計画案,製品売価予定,配分率,計画実行可否,また経営意思決
定支援装置101から提供される売上目標および損益目標,さらに機種構成情報
126を用いることによって,3702の領域に最上位階層から最下位階層まで
ツリー構成に従って各種情報を表示させることが可能である。
また,ツリービュー画面上には,各構成要素3703に関する情報を数個表示
することが可能な情報表示欄3704が用意されており,この欄には,台数,配
分率,価格,仕切率,損益,原価,計画実行可否といった損益意思決定支援装置
102が保持する情報の中から,ユーザーの選択した任意の値を表示させること
が可能である。
On the configuration tree screen, a large schedule plan, medium schedule plan, product price plan, distribution rate, plan execution availability provided from the profit / loss simulation apparatus 103, and sales target and profit / loss target provided from the management decision support apparatus 101 are displayed. Further, by using the model configuration information 126, various information can be displayed in the area 3702 according to the tree configuration from the highest hierarchy to the lowest hierarchy.
In addition, on the tree view screen, an information display field 3704 capable of displaying several pieces of information regarding each component 3703 is prepared. In this field, the number of units, allocation rate, price, partition rate, profit / loss It is possible to display an arbitrary value selected by the user from the information held by the profit / loss decision making support apparatus 102 such as cost, plan execution possibility, and the like.

さらに,この情報表示欄に表示させた情報のうち,大日程計画案,配分率,製
品売価予定(仕切率予定)の情報に関しては,この表示欄にカーソルをあわせ変
更したい数値を上書き入力することにより,情報の変更処理が可能である。
Furthermore, of the information displayed in this information display column, for the information on the large schedule plan, allocation rate, and product sales price schedule (partition rate schedule), place the cursor in this display field and enter the value you want to change. Thus, information change processing is possible.

図38は,配分率変更画面の表示例を示した図である。図の3801の欄には
ある親構成要素に付随する兄弟構成要素情報が一覧表示され,3802の欄にそ
の構成要素毎に設定された配分率が表示される。この情報を確認しながら,38
03の欄に変更したい値を入力し,OKボタンをクリックすることによって,即
座に配分率の変更が損益シミュレーション装置103に転送され,再計算が行わ
れる。
FIG. 38 is a diagram showing a display example of the distribution rate change screen. In the column 3801, sibling component information associated with a parent component is displayed in a list, and in the column 3802, the distribution ratio set for each component is displayed. While confirming this information,
By inputting the value to be changed in the field 03 and clicking the OK button, the change of the allocation rate is immediately transferred to the profit / loss simulation apparatus 103 and recalculated.

また,3804のチェックボックスにチェックを入れることにより,兄弟全体
での配分率合計を固定値とし,ある構成要素の配分率を変えずに他の値だけを変
更する,といった処理も可能である。
In addition, by checking the check box 3804, it is possible to set the total allocation rate of all siblings as a fixed value and change only another value without changing the allocation rate of a certain component.

なお,3805の欄は,変更した配分率に基づいて展開を行うとその構成要素
に対応する台数が何台になるのかを事前に表示される台数表示部である。
Note that the column 3805 is a unit display unit that displays in advance how many units corresponding to the constituent elements will be when development is performed based on the changed distribution rate.

図39は,詳細情報画面の表示例を示した図である。詳細情報画面は,あるひ
とつの構成要素が持つ全ての情報を3901で示す領域に表示させることが可能
な画面である。また,詳細画面は,3902欄にあるように,先行数期の計画を
時系列に表示させることも可能となっている。この画面でも図37と同様,変更
可能な情報の欄にカーソルをあわせ変更したい数値を上書き入力することにより
,情報の変更処理が可能である。
FIG. 39 is a diagram showing a display example of the detailed information screen. The detailed information screen is a screen that can display all the information of a certain component in the area indicated by 3901. In addition, as shown in the 3902 column, the detailed screen can display the plans of the preceding several periods in time series. Similarly to FIG. 37, information can be changed on this screen by placing the cursor on the changeable information column and overwriting the numerical value to be changed.

次に、本発明の第3の実施形態について、詳細に説明する。   Next, a third embodiment of the present invention will be described in detail.

以下、本発明における調達意思決定支援システムの実施の形態を図面により詳
細に説明する。
Embodiments of a procurement decision support system according to the present invention will be described below in detail with reference to the drawings.

図48は、本発明における実施形態である調達意思決定支援システムの装置と
装置間の情報の入出力を説明する図である。図48において、図1と共通する箇
所については同一の符号を付け、相違する箇所または細分化した箇所について新
たな符号を付ける。128は予定購入単価、129は品目区分マスタ、4801
は日別中日程計画案、4802は棚残予測、4803は評価損である。
FIG. 48 is a diagram for explaining input / output of information between devices of the procurement decision support system according to the embodiment of the present invention. In FIG. 48, the same reference numerals are assigned to portions common to FIG. 1, and new portions are attached to different portions or subdivided portions. 128 is the planned purchase unit price, 129 is the item classification master, 4801
Is the daily schedule plan, 4802 is the remaining shelf forecast, and 4803 is the valuation loss.

本実施の形態である調達意思決定支援システムの全体およびその周辺システムは、図48に示すように、入力される払出原価予定125を基に中日程計画案124を出力する損益シミュレーション装置103と、入力される中日程計画案124と所要量計算マスタ127を基に調達計画案120と日単位に細分化した日別中日程計画案4801を出力する調達計画立案装置104と、入力される調達計画案120と日別中日程計画案4801と予定購入単価128と所要量計算マスタ127を基に払出原価予定125と棚残予測4802と評価損4803を出力する棚残シミュレーション装置105と、入力される棚残予測4802と評価損4803を表示し、棚残目標を出力する経営意思決定支援装置101と、入力される棚残予測4802と評価損4803と棚残目標112と併せて表示し、棚残・調達計画担当部長による調達計画案120の変更入力を受け付け、棚残シミュレーション装置105に当該変更後の調達計画案120を出力する棚残・調達計画支援装置106で構成される。調達意思決定支援システムは、特にその中で調達計画立案装置104と棚残シミュレーション装置105と棚残・調達計画支援装置106を構成要素とする。   As shown in FIG. 48, the entire procurement decision support system according to the present embodiment and its peripheral system include a profit / loss simulation apparatus 103 that outputs a medium schedule plan 124 based on an input payout cost schedule 125, A procurement plan drafting device 104 that outputs a procurement schedule 120 based on the inputted medium schedule plan 124 and the requirement calculation master 127, and a daily medium schedule plan 4801 subdivided into daily units, and an inputted procurement plan The remaining inventory simulation device 105 that outputs the estimated cost of purchase 125, the remaining inventory forecast 4802, and the estimated loss 4803 based on the proposed schedule 120, the daily schedule plan 4801, the planned purchase unit price 128, and the requirement calculation master 127 is input. The management decision support device 101 that displays the remaining shelf prediction 4802 and the evaluation loss 4803 and outputs the remaining shelf target, and the input remaining shelf prediction 480 Are displayed together with the unrealized loss 4803 and the remaining shelf target 112, and the change input of the procurement plan 120 by the manager in charge of the remaining shelf / procurement plan is received, and the changed procurement plan 120 is output to the remaining shelf simulation device 105. It is composed of a shelf remaining / procurement plan support device 106. In particular, the procurement decision support system includes the procurement plan planning device 104, the shelf remaining simulation device 105, and the shelf remaining / procurement plan support device 106 as components.

図49は、装置の処理の順序と装置間の情報の流れる順序を説明したものであ
る。図中の4901〜4907は、各装置の処理ステップを表している。ステッ
プ4901で経営意思決定支援装置101が棚残目標112を棚残・調達計画支
援装置106へ送る。ステップ4902で損益シミュレーション装置103が中
日程計画案124を調達計画立案装置104へ送る。ステップ4903で調達計
画立案装置104が調達計画案120を生成し、調達計画案120と日別中日程
計画案4801を棚残シミュレーション装置105へ送り、調達計画案120を
棚残・調達計画支援装置106へ送る。ステップ4904で棚残シミュレーショ
ン装置105が調達計画立案装置104より送られた調達計画案120を用いて
「払出原価予定125」と「棚残予測4802」と「評価損4803」を生成し
、「払出原価予測125」を損益シミュレーション装置103へ送り、「棚残予
測4802」と「評価損4803」を棚残・調達計画支援装置106へ送る。ス
テップ4905で棚残・調達計画支援装置106は入力された各指標を表示画面
上に表示し、棚残・調達計画担当部長により調達計画案変更を行い、その変更さ
れた調達計画案120を棚残シミュレーション装置105へ送る。ステップ49
06で棚残シミュレーション装置105が棚残・調達計画支援装置106から送
られた修正変更された調達計画案120を用いて「払出原価予定125'」と「
棚残予測4802'」と「評価損4803'」を改めて再計算により生成し、「払
出原価予測125'」を損益シミュレーション装置103へ再度送り、「棚残予
測4802'」と「評価損4803'」を棚残・調達計画支援装置106と経営意
思決定支援装置101へ再度送る。ステップ4907で経営意思決定支援装置1
01は入力された各指標を再表示する。
FIG. 49 illustrates the order of processing of devices and the order in which information flows between devices. Reference numerals 4901 to 4907 in the figure represent processing steps of each device. In step 4901, the management decision support device 101 sends the remaining shelf target 112 to the remaining shelf / procurement plan support device 106. In step 4902, the profit / loss simulation apparatus 103 sends the medium schedule plan 124 to the procurement plan planning apparatus 104. In step 4903, the procurement plan drafting device 104 generates the procurement plan draft 120, sends the procurement plan draft 120 and the daily schedule plan 4801 to the shelf remaining simulation device 105, and the procurement plan draft 120 is sent to the shelf remaining / procurement plan support device. 106. In step 4904, the remaining shelf simulation apparatus 105 generates the “paid out cost plan 125”, the “remaining shelf forecast 4802”, and the “valuation loss 4803” using the procurement plan 120 sent from the procurement planning apparatus 104. The “cost forecast 125” is sent to the profit / loss simulation apparatus 103, and the “shelf remaining prediction 4802” and the “valuation loss 4803” are sent to the shelf remaining / procurement plan support apparatus 106. In step 4905, the shelf remaining / procurement plan support apparatus 106 displays each input index on the display screen, the shelf remaining / procurement plan manager changes the procurement plan, and the modified procurement plan 120 is stored on the shelf. This is sent to the remaining simulation device 105. Step 49
In 06, the remaining shelf simulation device 105 uses the revised and changed procurement plan 120 sent from the remaining shelf / procurement plan support device 106 to “paid out cost schedule 125 ′” and “
The remaining inventory prediction 4802 ′ ”and the“ valuation loss 4803 ′ ”are generated again by recalculation, and the“ paid out cost prediction 125 ′ ”is sent again to the profit / loss simulation apparatus 103, and the“ remaining inventory prediction 4802 ′ ”and the“ valuation loss 4803 ′ ”are transmitted. Is again sent to the shelf remaining / procurement plan support device 106 and the management decision support device 101. Management decision support device 1 at step 4907
01 redisplays each input index.

図50は棚残シミュレーション装置105の機能構成と入出力情報を詳細に説
明したものである。棚残シミュレーション装置105は棚残計算機能5001と
払出原価計算機能5002と評価損計算機能5003と棚残金額計算機能500
4で構成される。棚残シミュレーション装置は、図50の最上段に示した予定購
入単価128、調達計画案120、日別中日程計画案4801、所要量計算マス
タ127を他の装置より入力され、図50の最下段に示した評価損4803、払
出原価予定125、棚残予測(数量、金額)4802を他の装置へ出力する。
FIG. 50 illustrates the functional configuration and input / output information of the shelf remaining simulation device 105 in detail. The shelf remaining simulation device 105 includes a shelf remaining calculation function 5001, a paid-out cost calculation function 5002, a valuation loss calculation function 5003, and a shelf remaining amount calculation function 500.
It is composed of four. The shelf-remaining simulation apparatus receives the planned purchase unit price 128, the procurement plan 120, the daily schedule plan 4801 and the requirement calculation master 127 shown in the uppermost part of FIG. The evaluation loss 4803, the payout cost schedule 125, and the remaining shelf forecast (quantity, amount) 4802 shown in FIG.

棚残計算機能5001は、図64に例示する部品、調達計画区分、納期日、数
量を持つ部品単位の調達情報である調達計画案120と、図67で例示する製品
、計画区分、出荷予定日、台数の項目を持つ製品単位の販売情報である日別中日
程計画案4801と、特開2001-266045号公報の「受発注システム」において詳
細に説明されている所要量計算を行うために必要な情報である所要量計算マスタ
127を入力とする。そして、棚残計算機能5001による演算処理により、部
品、所要日、数量の項目を持つ出庫情報である出庫量と、部品、納入日、数量の
項目を持つ入庫情報である入庫量と、品目(部品、製品、半製品全てを含む)、
対象期、期末在庫量、仕掛フラグの項目を持つ数量ベースの棚残情報である棚残
予測(数量のみ)を出力する。棚残計算機能5001による演算処理は、図51
で説明する手順により実行される。
The shelf remaining calculation function 5001 includes a procurement plan 120 which is procurement information of a part unit having parts, a procurement plan classification, a delivery date, and a quantity illustrated in FIG. 64, and a product, a plan classification, and a scheduled shipping date illustrated in FIG. Necessary for carrying out the required amount calculation described in detail in the daily mid-term schedule 4801 which is the sales information of the product unit with the item of the number of units, and the “ordering system” in Japanese Patent Laid-Open No. 2001-266045 Requirement calculation master 127, which is a large amount of information, is input. Then, by the calculation process by the remaining shelf calculation function 5001, the quantity of goods that are goods information having items of parts, required date, and quantity, the quantity of goods that is goods receipt information having items of parts, delivery date, and quantity, and item ( Including all parts, products and semi-finished products),
Outputs inventory forecast (quantity only), which is quantity-based inventory information with items for the target period, end-of-period inventory, and work in progress flag. The calculation processing by the shelf remaining calculation function 5001 is shown in FIG.
It is executed according to the procedure described in the above.

払出原価計算機能5002は、棚残計算機能5001が算出した入庫量と棚残
予測(数量のみ)と、部品、対象期、購入単価の項目を持つ購入情報である予定
購入単価128を入力とし、図65で例示する品目、予測区分、対象期、部品の
払出時の単価である払出単価、製品、半製品の払出時の単価である払出原価の項
目を持つ予定の払出原価予定125を出力する。払出原価計算機能5002によ
る演算処理は、図52で説明する手順より実行される。
The payout cost calculation function 5002 receives the amount of warehousing and the remaining inventory prediction (only the quantity) calculated by the remaining inventory calculation function 5001 and the planned purchase unit price 128, which is purchase information having items of parts, target period, and purchase unit price. 65, the planned payout cost plan 125 having the items of item, forecast category, target period, payout unit price that is the unit price when parts are paid out, and payout cost that is the unit price when products and semi-finished products are paid out is output. . The calculation process by the payout cost calculation function 5002 is executed according to the procedure described in FIG.

評価損計算機能5003は、棚残計算機能5001が算出した出庫量と払出原
価計算機能5002が算出した払出原価予定125と予定購入単価128を入力
とし、部品、予測区分、対象期、評価損金額の項目を持つ評価損情報である評価
損を図55で説明する手順により算出する。
The valuation loss calculation function 5003 inputs the amount of goods issued by the remaining shelf calculation function 5001, the payout cost schedule 125 calculated by the payout cost calculation function 5002 and the planned purchase unit price 128, and inputs parts, forecast category, target period, and valuation loss amount. An evaluation loss, which is evaluation loss information having the following items, is calculated by the procedure described with reference to FIG.

棚残金額計算機能5004は、棚残計算機能5001が算出した棚残予測(数
量のみ)と払出原価計算機能5002が算出した払出原価予定125を入力とし
、図66で例示する品目、予測区分、対象期、期末在庫量、期末在庫金額、仕掛
フラグの項目を持つ棚残情報である棚残予測(数量、金額)を図56で説明する
手順により算出する。
The shelf remaining amount calculation function 5004 receives the shelf remaining prediction (quantity only) calculated by the shelf remaining calculation function 5001 and the payout cost schedule 125 calculated by the payout cost calculation function 5002 as inputs. The items illustrated in FIG. The shelf remaining prediction (quantity, amount), which is the remaining shelf information having items of the target period, the end-of-period inventory quantity, the end-of-period inventory amount, and the in-process flag, is calculated by the procedure described in FIG.

ここで、図51に示すフローを参照して、棚残計算機能5001の行う計算手
順を説明する。
Here, the calculation procedure performed by the remaining shelf calculation function 5001 will be described with reference to the flow shown in FIG.

ステップ5101では、特開2001-266045号公報の「受発注システム」におい
て詳細に説明されている部品の所要量から発注単位などを考慮した所要調達量を
算出する方法を用いて、調達計画案から所要調達量を算出し、それに入庫予定量
(発注残)を加え入庫量とする。
In step 5101, from the procurement plan draft using the method of calculating the required procurement quantity considering the ordering unit from the required quantity of parts described in detail in “Ordering System” of JP-A-2001-266045. Calculate the required procurement amount and add the planned receipt amount (order remaining) to the receipt amount.

ステップ5102では、特開2001-266045号公報の「受発注システム」におい
て詳細に説明されている製品レベルの計画数から部品の所要量を求める所要量計
算方法を用いて、日別中日程計画案4801から所要量を算出し、それを出庫量
とする。
In step 5102, a daily schedule plan is prepared using a requirement calculation method for obtaining the required amount of parts from the number of product-level plans described in detail in “Ordering System” of JP-A-2001-266045. The required amount is calculated from 4801, and is used as the outgoing amount.

ステップ5103では、各部品目について(数1)に示すように該当期の前の
期の期末在庫量に該当期の入庫量の総和を加え、さらに該当期の出庫量の総和を
引いて、該当期末在庫量を算出する。
In step 5103, as shown in (Equation 1) for each part, add the sum of the warehousing amount for the relevant period to the ending inventory quantity for the period before the relevant period, and further subtract the sum of the amount of goods issued for the relevant period. Calculate inventory.

該当期末在庫量=該当期の前の期の期末在庫量
+Σ該当期内の入庫量
−Σ該当期内の出庫量 (数1)
ステップ5104では、全ての部品について期末在庫量を算出したかをチェッ
クし、未処理の部品があった場合は、ステップ5101に戻って処理を続け、未
処理の部品が無ければステップ5105へ進む。
Stock at the end of the period = Stock quantity at the end of the previous period
+ Σ Receipt amount within the applicable period
-Σ Issued volume within the applicable period (Equation 1)
In step 5104, it is checked whether or not the end-of-period inventory quantity has been calculated for all the parts. If there are unprocessed parts, the process returns to step 5101 to continue the process, and if there are no unprocessed parts, the process proceeds to step 5105.

ステップ5105では、該当期末日に製造途中である製品もしくは半製品の仕
掛かり品に関する在庫量を算出する。製品もしくは半製品の該当期末日の翌日か
ら、該当期末日を起点として生産リードタイム分先の日までの出荷予定数の和を
その製品もしくは半製品の仕掛かり在庫量とし、それを仕掛かりフラグの付いた
該当期末在庫量とする。
In step 5105, an inventory quantity relating to a work-in-process product or a semi-finished product that is being manufactured at the end of the corresponding period is calculated. The sum of the planned shipment quantity from the day following the end of the applicable period of the product or semi-finished product to the day ahead of the production lead time is used as the in-process inventory for that product or semi-finished product, and this is the in-process indicator The amount of stock at the end of the period marked with.

ステップ5106では、全ての製品、半製品について仕掛フラグ付き期末在庫
量を算出したかをチェックし、未処理の製品、半製品があった場合、ステップ5
105へ戻り処理を続け、未処理の製品、半製品が無ければステップ5107へ
進む。
In step 5106, it is checked whether or not the end-of-period inventory with in-process flag is calculated for all products and semi-finished products. If there are unprocessed products and semi-finished products, step 5106
Returning to 105, the processing is continued, and if there is no unprocessed product or semi-finished product, the processing proceeds to step 5107.

ステップ5107では、計算対象期を1つ先へ進める。   In step 5107, the calculation target period is advanced by one.

ステップ5108では、計算対象期が計算対象外かどうかチェックし、計算対
象外で無ければステップ5101へ戻り処理を続け、計算対象外ならば棚残計算
を終了する。以上の演算方法によって出庫量、入庫量、棚残予測(数量のみ)の
算出処理を実行することができる。
In step 5108, it is checked whether or not the calculation target period is not a calculation target. If the calculation target period is not a calculation target, the process returns to step 5101 to continue the process. With the above calculation method, it is possible to execute a process for calculating the quantity of goods delivered, the quantity of goods received, and the remaining shelf prediction (only the quantity).

次に図52で示すフローを参照して、払出原価計算機能5002の行う計算手
順を説明する。
Next, a calculation procedure performed by the payout cost calculation function 5002 will be described with reference to the flow shown in FIG.

ステップ5201では、各部品について(数2)に示す計算式で予定払出単価
を算出する。又、図53において予定払出単価の計算例を示して説明する。この
時、予定購入単価の通貨は、為替レートを用いて一つに統一しておく。
In step 5201, the planned payout unit price is calculated for each part by the calculation formula shown in (Formula 2). FIG. 53 shows an example of calculating the scheduled payout unit price. At this time, the currency of the planned purchase unit price is unified with the exchange rate.

払出単価予定=(該当期の前の期末在庫量×該当期の前の期の払出単価
+該当期内の入庫量の総和×予定購入単価)
÷(該当期の前の期末在庫量+該当期内の入庫の総和) (数2)
図53は、各月毎の払出単価予定を算出する例を示したものである。ここでは
、2月の払出単価予定の算出について説明する。1月の月末在庫量は50で払出
単価は200であり、2月の入庫量は60で予定購入単価は150であるとする
と、2月の払出単価予定は、(50×200+60×150)÷(50+60)
=173となる。3月、4月の払出単価予定の算出についても、同様にして算出
できる。
Disbursement unit price plan = (end-of-period inventory before the relevant period x withdrawal unit price prior to the relevant period
+ Total amount of goods received in the relevant period x Planned purchase unit price)
÷ (Stock at the end of the period before the relevant period + Sum of warehousing within the relevant period) (Number 2)
FIG. 53 shows an example of calculating the payout unit price schedule for each month. Here, calculation of the payout unit price schedule for February will be described. Assuming that the end-of-month inventory in January is 50, the payout unit price is 200, the warehousing amount in February is 60, and the planned purchase unit price is 150, the payout unit price plan for February is (50 x 200 + 60 x 150) / (50 + 60)
= 173. The calculation of the payout unit price schedule in March and April can be similarly performed.

ステップ5202は、全ての部品について払出単価予定を算出したかをチェッ
クし、未処理の部品があった場合、ステップ5201に戻り処理を続け、未処理
の部品が無かった場合、ステップ5203へ進む。
In step 5202, it is checked whether the payout unit price schedule has been calculated for all the parts. If there are unprocessed parts, the process returns to step 5201 to continue the process. If there are no unprocessed parts, the process proceeds to step 5203.

ステップ5203では、製品、半製品を構成している部品の払出単価予定を部
品構成表に基づいて積み上げ計算し、製品、半製品の払出原価予定を算出する。
具体的な例を、図54を用いて説明する。
In step 5203, the payout unit price schedule of the parts constituting the product and the semi-finished product is calculated based on the parts structure table, and the payout cost schedule of the product and the semi-finished product is calculated.
A specific example will be described with reference to FIG.

図54は、ある製品P、半製品X,半製品Yの払出原価予定を算出する例を示
したものである。部品構成表によると、製品Pは半製品Xが1つと半製品Yが1
つで構成され、又、半製品Xは部品Aが1つと部品Bが1つで構成され、又、半
製品Yは部品Cが1つと部品Dが2つで構成される。ここで、部品A,部品B,
部品C,部品Dの払出単価予定がそれぞれ50,30,10,25とすると、半
製品Xの払出原価予定は、半製品Xを構成している部品Aの払出単価予定×構成
数と部品Bの払出単価予定×構成数で算出され、50×1+30×1=80とな
る。同様に半製品Yの払出原価予定は、10×1+25×2=60となる。さら
に、製品Pの払出原価予定は、半製品Xと半製品Yの払出原価予定を用いて80
×1+60×1=140と算出される。
FIG. 54 shows an example of calculating a payout cost schedule for a certain product P, semi-finished product X, and semi-finished product Y. According to the BOM, product P has one semi-finished product X and one semi-finished product Y
The semi-finished product X is composed of one part A and one part B, and the semi-finished product Y is composed of one part C and two parts D. Here, part A, part B,
If the payout unit price schedule for parts C and D is 50, 30, 10, 25, respectively, the payout cost schedule for semi-finished product X is the payout unit price schedule for parts A composing semi-finished product X × number of components and part B The payout unit price plan × the number of components is 50 × 1 + 30 × 1 = 80. Similarly, the payout cost schedule of the semi-finished product Y is 10 × 1 + 25 × 2 = 60. Further, the payout cost schedule for product P is 80 using the payout cost schedule for semi-finished product X and semi-finished product Y.
It is calculated as x1 + 60x1 = 140.

ステップ5204では、全ての製品、半製品について払出原価予定を算出した
かをチェックし、未処理の製品、半製品があった場合、ステップ5203へ戻り
処理を続け、未処理の製品、半製品が無かった場合、ステップ5205へ進む。
In step 5204, it is checked whether the payout cost schedule has been calculated for all products and semi-finished products. If there are unprocessed products and semi-finished products, the process returns to step 5203 to continue the processing. If not, the process proceeds to Step 5205.

ステップ5205では、計算対象期を1つ先へ進める。   In step 5205, the calculation target period is advanced by one.

ステップ5206では、計算対象期が計算対象外かどうかチェックし、計算対
象外で無ければステップ5201へ戻り処理を続け、計算対象外ならばステップ
5207へ進む。
In step 5206, it is checked whether or not the calculation target period is not a calculation target. If the calculation target period is not a calculation target, the process returns to step 5201, and if not, the process proceeds to step 5207.

ステップ5207では、払出原価予定の予測区分に中日程計画の計画区分(新
規計画又は補正計画の中のシナリオ)を代入する。
In step 5207, the plan category of the medium schedule plan (scenario in the new plan or the correction plan) is substituted into the forecast category of the payout cost schedule.

次に図55で示すフローを参照して、評価損計算機能5003の行う計算手順
を説明する。
Next, a calculation procedure performed by the valuation loss calculation function 5003 will be described with reference to the flow shown in FIG.

ステップ5501では、各部品について(数3)に示す計算式で評価損を算出
する。
In step 5501, an evaluation loss is calculated for each part using the calculation formula shown in (Formula 3).

評価損=(払出単価予定−予定購入単価)×出庫量 (数3)
ステップ5502では、全ての部品について評価損を算出したかをチェックし
、未処理の部品があった場合、ステップ5501へ戻り処理を続け、未処理の部
品が無かった場合、ステップ5503へ進む。
Valuation loss = (scheduled unit price-planned unit price) x amount of goods issued (Equation 3)
In step 5502, it is checked whether or not evaluation loss has been calculated for all parts. If there is an unprocessed part, the process returns to step 5501 and the process continues. If there is no unprocessed part, the process proceeds to step 5503.

ステップ5503では、計算対象期を1つ先へ進める。   In step 5503, the calculation target period is advanced by one.

ステップ5504では、計算対象期が計算対象外かどうかチェックし、計算対
象外で無ければステップ5501へ戻り処理を続け、計算対象外ならばステップ
5505へ進む。
In step 5504, it is checked whether or not the calculation target period is not a calculation target. If the calculation target period is not a calculation target, the process returns to step 5501 and if not, the process proceeds to step 5505.

ステップ5505では、評価損の予測区分に中日程計画の計画区分(新規計画
、補正計画の中のシナリオ)を代入する。
In step 5505, the plan category of the medium schedule plan (scenario in the new plan and the correction plan) is substituted for the forecast category of valuation loss.

次に図56で示すフローを参照して、棚残金額計算機能5004の行う計算手
順を説明する。
Next, a calculation procedure performed by the remaining shelf price calculation function 5004 will be described with reference to the flow shown in FIG.

ステップ5601では、各部品について(数4)に示す計算式で棚残金額を算
出し、又、各製品、半製品について(数5)に示す計算式で棚残金額を算出する。
In step 5601, the remaining shelf price is calculated for each part using the formula shown in (Formula 4), and the remaining shelf price is calculated using the formula shown in (Formula 5) for each product and semi-finished product.

棚残金額=払出単価予定×期末在庫量 (数4)
棚残金額=払出原価予定×期末在庫量 (数5)
ステップ5602では、全ての部品及び全ての製品、半製品について棚残金額
を算出したかをチェックし、未処理の部品若しくは製品、半製品があった場合、
ステップ5601へ戻り処理を続け、未処理の部品若しくは製品、半製品が無か
った場合、ステップ5603へ進む。
Shelf remaining amount = planned payout unit price × end-of-period inventory (number 4)
Shelf remaining amount = planned payout cost x end-of-period inventory (5)
In step 5602, it is checked whether the shelf remaining amount has been calculated for all parts, all products, and semi-finished products. If there are unprocessed parts, products, and semi-finished products,
Returning to step 5601, the process is continued, and if there is no unprocessed part, product, or semi-finished product, the process proceeds to step 5603.

ステップ5603では、計算対象期を1つ先へ進める。   In step 5603, the calculation target period is advanced by one.

ステップ5604では、計算対象期が計算対象外かどうかチェックし、計算対
象外で無ければステップ5601へ戻り処理を続け、計算対象外ならばステップ
5605へ進む。
In step 5604, it is checked whether or not the calculation target period is not a calculation target. If the calculation target period is not a calculation target, the process returns to step 5601 to continue the process.

ステップ5605では、棚残予測(数量・金額)の予測区分に中日程計画の計
画区分(新規計画、又は補正計画の中のシナリオ)を代入する。
In step 5605, the plan category of the medium schedule plan (new plan or scenario in the correction plan) is substituted for the forecast category of the remaining shelf forecast (quantity / amount).

図57は、調達計画立案装置104の機能構成と入出力情報を詳細に説明した
ものである。調達計画立案装置104は、調達計画立案機能5701と中日程計
画日割り機能5702で構成される。調達計画立案装置104は、図57の最上
段に示した中日程計画案125と所要量計算マスタ129を他の装置から入力さ
れ、図57の最下段に示した日別中日程計画案4801と調達計画案120を他
の装置へ出力する。
FIG. 57 illustrates the functional configuration and input / output information of the procurement plan planning apparatus 104 in detail. The procurement plan planning apparatus 104 includes a procurement plan planning function 5701 and a medium schedule plan daily function 5702. The procurement plan planning device 104 receives the medium schedule plan 125 and the requirement calculation master 129 shown in the uppermost part of FIG. 57 from another device, and the daily schedule plan 4801 shown in the lowermost part of FIG. The procurement plan 120 is output to another device.

調達計画立案機能5701は、日別中日程計画案4801と所要量計算マスタ
129を入力とし、特開2001-266045号公報の「受発注システム」において詳細
に説明されている製品レベルの計画数から部品の所要量を求める所要量計算方法
を用いて、日別中日程計画案4801から調達計画案120を算出し、この時の
調達計画区分を「オリジナル」と設定する。ここで「オリジナル」とは、損益シ
ミュレーション装置103から送信された中日程計画案124に基づいて、調達
計画立案装置104によって自動計算された最初の調達計画という意味であり、
棚残・調達計画担当部長による修正が加わった場合には、調達計画区分は「変更
1」「変更2」といった内容に設定する。
The procurement planning function 5701 receives the daily schedule plan 4801 and the requirement calculation master 129 as inputs, and from the number of plans at the product level described in detail in “Ordering System” of Japanese Patent Laid-Open No. 2001-266045. The procurement plan 120 is calculated from the daily schedule plan 4801 using the requirement calculation method for obtaining the required amount of parts, and the procurement plan classification at this time is set to “original”. Here, “original” means the first procurement plan automatically calculated by the procurement plan planning device 104 based on the medium schedule plan 124 transmitted from the profit / loss simulation device 103.
When correction is made by the manager in charge of the remaining shelf / procurement plan, the procurement plan classification is set to contents such as “change 1” and “change 2”.

中日程計画日割り機能5702は、中日程計画案125を入力とし、中日程計
画案のある期単位の計画数を日単位の計画数に日割りして、日別中日程計画案4
801を算出する。
The mid-schedule plan schedule function 5702 receives the mid-schedule plan 125 as an input, divides the number of plans for each period with the mid-schedule plan into the number of plans per day, and creates a daily schedule plan 4
801 is calculated.

図58は、棚残・調達計画支援装置の機能構成と入出力情報を詳細に説明した
ものである。棚残・調達計画支援装置は調達計画変更機能5801と指標表示機
能5802で構成される。棚残・調達計画支援装置は図58の最上段に示した調
達計画案120と棚残目標112と評価損4803と棚残予測(数量・金額)4
802と品目区分マスタ129を他の装置から入力され、図58の最下段に示し
た調達計画案120を出力する。
FIG. 58 illustrates in detail the functional configuration and input / output information of the shelf remaining / procurement plan support apparatus. The shelf remaining / procurement plan support apparatus includes a procurement plan change function 5801 and an index display function 5802. The shelf remaining / procurement plan support apparatus includes a procurement plan 120, a shelf remaining target 112, a valuation loss 4803, and a remaining shelf prediction (quantity / amount) 4 shown in the uppermost part of FIG.
802 and the item classification master 129 are input from another device, and the procurement plan 120 shown at the bottom of FIG. 58 is output.

調達計画変更機能5801は、入力された調達計画案120の数量を品目別且
つ納期日別に表示する機能と入力された調達計画案120の数量を任意に変更出
来る機能と変更したい品目についての調達計画を検索する機能を有する。図59
において、調達計画変更機能の画面を示し、詳細に説明する。
The procurement plan change function 5801 is a function for displaying the quantity of the input procurement plan 120 by item and by delivery date, a function for arbitrarily changing the quantity of the input procurement plan 120 and a procurement plan for the item to be changed. It has a function to search. FIG.
Shows the screen of the procurement plan change function and will be described in detail.

図59において、5901は調達計画案120の数量を品目別(表の縦方向)
且つ納期日別(表の横方向)に表示し、且つ数量を枠の中に入力することで調達
計画案の数量を変更出来る調達計画表示・入力部である。5902はこのボタン
をクリックすることで変更された調達計画案の調達計画区分を「変更1」等とし
て保存する調達計画登録実行ボタンである。5903は検索したい品目の品目若
しくは品目コードを入力する検索入力部である。5904はこのボタンをクリッ
クすることで5903に入力された品目若しくは品目コードの検索を良く知られ
ている検索手法で実行する検索実行ボタンで、5905はこのボタンをクリック
することで調達計画変更機能を終了する終了実行部である。棚残・調達計画担当
部長等の調達計画変更者は、変更したい品目について5903の検索入力部に品
目若しくは品目コードを入力し、5904の検索実行部をクリックし、検索され
調達計画表示・入力部に表示された品目の調達計画の数量を調達計画表示・入力
部の枠の中に数量を入力することで書き換え、5902の調達計画登録実行ボタ
ンをクリックすることで調達計画案120を変更することが出来る。
In FIG. 59, 5901 indicates the quantity of the procurement plan 120 by item (vertical direction in the table).
In addition, the procurement plan display / input unit can display the delivery date (horizontal direction of the table) and change the quantity of the procurement plan by inputting the quantity in the frame. Reference numeral 5902 denotes a procurement plan registration execution button for saving the procurement plan classification of the procurement plan changed by clicking this button as “change 1” or the like. Reference numeral 5903 denotes a search input unit for inputting an item or item code of an item to be searched. 5904 is a search execution button for executing a search of an item or item code input to 5903 by a well-known search method by clicking this button, and 5905 is a procurement plan change function by clicking this button. It is an end execution unit that ends. The procurement plan changer, such as the manager in charge of the remaining inventory / procurement plan, inputs the item or item code in the search input section 5903 for the item to be changed, clicks the search execution section 5904, and is searched and the procurement plan display / input section is searched. Rewrite the quantity of the procurement plan of the item displayed in the item by entering the quantity in the frame of the procurement plan display / input section, and change the procurement plan 120 by clicking the procurement plan registration execution button of 5902 I can do it.

指標表示機能5802は、図24で例示する棚残目標と、評価損と、図66で
例示する棚残予測(数量・金額)と、品目と機種区分や(部品/製品/半製品)の区
分である費目という集計のための区分情報を持つ品目区分マスタを入力とし、棚
残予測4802や評価損4803を集計、表示する機能であり棚残・調達計画支
援装置106によって実行される。集計処理は、品目単位の棚残金額や評価損金
額を品目区分マスタの区分に従って集計する。但し、製品、半製品の完成品在庫
と仕掛かり在庫の区分は棚残予測の仕掛かりフラグを参照して区分する。表示処
理については、まず、図60に棚残・調達計画支援装置106における表示画面
の概要を示し、図61〜図63に表示される画面の具体例を示す。
The index display function 5802 includes a shelf remaining target illustrated in FIG. 24, a valuation loss, a shelf remaining prediction (quantity / amount) illustrated in FIG. 66, and item and model classification and (part / product / semi-finished product) classification. This function is a function that counts and displays the remaining shelf prediction 4802 and the evaluation loss 4803, and is executed by the remaining shelf / procurement plan support apparatus 106. In the aggregation process, the remaining shelf amount and the valuation loss amount for each item are totaled according to the item classification master. However, the finished product inventory and in-process stock of products and semi-finished products are classified by referring to the in-process flag of the shelf remaining prediction. Regarding the display processing, first, FIG. 60 shows an outline of a display screen in the shelf remaining / procurement plan support apparatus 106, and specific examples of the screens displayed in FIGS.

図60は、棚残目標112と棚残シミュレーション結果の各指標を表示するた
めの画面の概要を示したものである。6001は棚残目標表示部であり、図61
において具体例で説明する。6002は棚残予測表示部であり、図62と63に
おいて具体例で説明する。6003は評価損表示部であり、図62や図63と同
様な表示形式にて表示することができる。6004は、棚残予測表示と評価損表
示の表示条件を入力若しくは選択する表示条件入力部である。表示条件とは、棚
残予測や評価損を機種別や費目別や部品目別といった様々な区分で表示させるた
めの区分方法のことを言う。6005は、入力された棚残予測(数量・金額)も
しくは評価損の予測区分(シナリオ1、2等の区分)を表示し、6006は入力
された調達計画案の調達計画区分(オリジナル、変更1、変更2等)を表示する。
FIG. 60 shows an outline of a screen for displaying each indicator of the remaining shelf target 112 and the remaining shelf simulation result. Reference numeral 6001 denotes a shelf remaining target display section.
A specific example will be described. Reference numeral 6002 denotes a shelf remaining prediction display unit, which will be described with a specific example in FIGS. An evaluation loss display unit 6003 can be displayed in the same display format as in FIGS. Reference numeral 6004 denotes a display condition input unit that inputs or selects display conditions for shelf remaining prediction display and evaluation loss display. The display condition refers to a sorting method for displaying the remaining shelf prediction and evaluation loss in various categories such as model type, expense item, and component item. Reference numeral 6005 indicates the input shelf residual prediction (quantity / amount) or evaluation loss prediction classification (scenario 1, 2 etc.), and reference numeral 6006 indicates the procurement plan classification (original, change 1) of the input procurement plan. , Change 2 etc.) are displayed.

図61は、棚残目標表示部6601に表示される例を示したものである。経営
者が経営意思決定支援装置101にて入力した棚残目標金額を機種別、達成すべ
き時期別に表形式で表示する。
FIG. 61 shows an example displayed on the remaining shelf target display portion 6601. The remaining shelf target amount input by the manager using the management decision support apparatus 101 is displayed in a table format by model and by the time to be achieved.

図62と図63は、棚残予測表示部6602に表示される例を示したものであ
る。図62は、表示条件として機種別を指定した場合の表示例で、横軸に時間(
日単位、週単位、月単位等)、縦軸に金額を取り、機種別に集計区分された棚残
金額がグラフ表示される。図63は、表示条件として機種別と費目別を指定した
場合の表示例で、横軸に時間、縦軸に金額を取り、機種別と費目別に集計区分さ
れた棚残金額がグラフ表示される。また、図示しないが、表示条件として費目別
や部品目別や特定品目の棚残数量を指定した場合でも、同様にグラフ表示ができ
る。
62 and 63 show an example displayed on the shelf remaining prediction display portion 6602. FIG. FIG. 62 shows a display example when the model type is specified as the display condition.
Daily amount, weekly unit, monthly unit, etc.), the amount of money is plotted on the vertical axis, and the remaining amount of shelves that are aggregated and classified by model are displayed in a graph. FIG. 63 is a display example in which model type and cost item are specified as display conditions. The horizontal axis indicates time, the vertical axis indicates the amount of money, and the remaining shelf amount that is tabulated according to model type and cost item is displayed in a graph. . Although not shown in the figure, even when the item by cost, the item by item, or the remaining quantity of a specific item is specified as the display condition, the graph can be displayed in the same manner.

このような表示形態により、棚残目標と、棚残予測に関する種々の情報を同時
に表示でき、また調達計画の変更や予測区分の変更等も併せて実行できるため、
棚残・調達計画担当部長の意思決定を適切かつ迅速にサポートすることができる。
With such a display form, it is possible to simultaneously display various information related to the shelf remaining target and the shelf remaining prediction, and also to change the procurement plan, change the prediction category, etc.
It is possible to appropriately and promptly support the decision making by the department manager in charge of inventory remaining and procurement.

図70は、取引先選択意思決定支援装置7005の機能構成と入出力情報を詳
細に説明したものである。取引先選択意思決定支援装置7005は為替レートシ
ナリオ設定機能7001と為替変動影響確認機能7002と取引先取引条件設定
機能7003と取引先比較機能7004で構成される。取引先選択意思決定支援
装置7005は図70の最上段に示した為替レートシナリオ毎、若しくは、取引
先毎の払出原価予定125と棚残予測(数量・金額)5402と品目区分マスタ
129を他の装置から入力され、図70の最下段に示した為替レート(図68に
例示)と取引条件(図69に例示)を出力する。
FIG. 70 illustrates the functional configuration and input / output information of the supplier selection decision support apparatus 7005 in detail. A supplier selection decision support apparatus 7005 includes an exchange rate scenario setting function 7001, an exchange fluctuation effect confirmation function 7002, a supplier transaction condition setting function 7003, and a supplier comparison function 7004. The supplier selection decision support device 7005 stores the payout cost schedule 125, the remaining inventory forecast (quantity / amount) 5402, and the item classification master 129 for each exchange rate scenario shown in the top row of FIG. The exchange rate (illustrated in FIG. 68) and transaction conditions (illustrated in FIG. 69) shown at the bottom of FIG. 70 are output from the apparatus.

為替レートシナリオ設定機能7001は、複数の為替レートシナリオを設定す
る機能を有する。図71において、為替レートシナリオ設定の画面を示し、詳細
に説明する。
The exchange rate scenario setting function 7001 has a function of setting a plurality of exchange rate scenarios. FIG. 71 shows a screen for setting an exchange rate scenario, which will be described in detail.

図71は為替レートシナリオ設定画面の概要を示したものである。入力部71
01には、為替レートシナリオ名が入力され、このシナリオ名で区別することで
、複数の為替レートシナリオを登録できる。入力部7102は、設定する為替レ
ートの適用対象期間が入力される。入力部7103,7104には、為替レート
と通貨名が入力される。登録ボタン7105の押下によって、入力した為替レー
トが登録される。
FIG. 71 shows an outline of the exchange rate scenario setting screen. Input unit 71
In 01, an exchange rate scenario name is input, and a plurality of exchange rate scenarios can be registered by distinguishing by the scenario name. The input unit 7102 receives an application target period of a set exchange rate. In the input units 7103 and 7104, an exchange rate and a currency name are input. When the registration button 7105 is pressed, the input exchange rate is registered.

為替変動影響確認機能7002は、為替レートシナリオ毎の棚残予測(金額・
数量)と払出原価予測、品目区分マスタを入力とし、為替レートシナリオ毎の棚
残金額と任意の製品の原価を棚残シミュレーション装置105により計算し、為
替レートシナリオ毎に表示する機能を有する。本実施の形態による計算は、為替
変動予測情報(為替レートシナリオ)を考慮したシミュレーション計算により実
現できる。
The exchange fluctuation impact confirmation function 7002 is used to estimate the remaining inventory for each exchange rate scenario.
Quantity), paid-out cost prediction, and item classification master, the remaining shelf amount for each exchange rate scenario and the cost of any product are calculated by the remaining shelf simulation device 105 and displayed for each exchange rate scenario. The calculation according to the present embodiment can be realized by a simulation calculation considering exchange fluctuation prediction information (exchange rate scenario).

図72は、為替変動影響確認の画面の一例を示す。図72は、設定された為替
レートシナリオごとに棚残計算と払出原価計算を行った結果を表示する画面の例
を示したものである。7201は棚残金額を表示する部分で、為替レートシナリ
オ毎の棚残金額を並べて表示することで、各為替レートシナリオの影響を比較す
ることができる。又、7203は製品原価を表示する部分で、為替レートシナリ
オ毎の製品原価を並べて表示することで、各為替レートシナリオの影響を比較す
ることができる。ここで表示する製品原価は、7202で選択された製品につい
ての原価を表示する。また、為替変動影響確認計算は、部品単位で実行すること
もできる。
FIG. 72 shows an example of a screen for confirming the effect of exchange rate fluctuations. FIG. 72 shows an example of a screen that displays the result of the remaining shelf calculation and the payout cost calculation for each set exchange rate scenario. 7201 is a portion for displaying the remaining amount of shelf, and by displaying the remaining amount of shelf for each exchange rate scenario side by side, the influence of each exchange rate scenario can be compared. Reference numeral 7203 denotes a part for displaying the product cost. By displaying the product cost for each exchange rate scenario side by side, the influence of each exchange rate scenario can be compared. The product cost displayed here is the cost for the product selected in 7202. Further, the exchange fluctuation effect confirmation calculation can be executed in units of parts.

取引先取引条件設定機能7003は、取引先毎の取引条件を設定する機能を有
する。図73に、取引先取引条件設定の画面の表示例を示す。
The supplier transaction condition setting function 7003 has a function of setting transaction conditions for each supplier. FIG. 73 shows a display example of a supplier transaction condition setting screen.

図73は、取引先との取引条件を設定する画面の概要を示したものである。取
引条件とは、取引される部品についての調達にかかる時間である調達リードタイ
ム、発注数量の単位であるロットサイズ、発注ロットの最低数である最低ロット
数等の調達ルールと部品の単価情報のことである。入力部7301には、取引先
名称若しくは取引先コード等の取引先を特定する情報が入力される。入力部73
02には、取引条件の調達ルールが入力され、品目コード、調達リードタイム、
ロットサイズ、また取引する際の最低ロット数等を入力することができる。入力
部7303には、取引条件の単価情報が入力される。登録ボタン7304を押下
することで、入力した取引先の取引条件が登録される。ここで、調達側のユーザ
ーは、比較したい各取引先の取引条件を登録する。
FIG. 73 shows an outline of a screen for setting transaction conditions with a business partner. The transaction conditions are the procurement lead time, which is the time required for procurement of the parts to be traded, the lot size, which is the unit of order quantity, the minimum number of lots, which is the minimum number of order lots, and the unit price information of parts. That is. In the input unit 7301, information specifying a business partner such as a business partner name or a business partner code is input. Input unit 73
In 02, the procurement rules for the transaction conditions are entered, and the item code, procurement lead time,
You can enter the lot size and the minimum number of lots to trade. Unit price information of transaction conditions is input to the input unit 7303. By pressing a registration button 7304, the input transaction condition of the supplier is registered. Here, the user on the procurement side registers the transaction conditions of each business partner to be compared.

取引先比較機能7004は、取引先取引条件毎の棚残予測(金額・数量)と払
出原価予測、品目区分マスタを入力とし、取引先毎の棚残金額と任意の製品の原
価を表示する機能を有する。図74において、取引先比較の画面を示し、詳細に
説明する。
The supplier comparison function 7004 is a function for displaying the remaining shelf price for each supplier and the cost of an arbitrary product by inputting the remaining inventory forecast (amount / quantity), the paid-out cost forecast for each supplier transaction condition, and the item classification master. Have FIG. 74 shows a supplier comparison screen, which will be described in detail.

図74は、設定された取引先の取引条件ごとに棚残計算と払出原価計算を行っ
た結果を表示する画面の例を示したものである。7401は棚残金額を表示する
部分で、各取引先と取引した場合の棚残金額を並べて表示することで、各取引先
と取引した場合の棚残推移を比較することができる。又、7403は製品原価を
表示する部分で、各取引先と取引した場合の製品原価を並べて表示することで、
各取引先と取引した場合の製品原価を比較することができる。ここで表示する製
品原価は、7402で選択された製品又は部品についての原価を表示する。
FIG. 74 shows an example of a screen that displays the result of performing the remaining shelf calculation and the payout cost calculation for each transaction condition of the set business partner. 7401 is a portion for displaying the remaining amount of shelf, and by arranging and displaying the remaining amount of shelf when dealing with each business partner, it is possible to compare the transition of remaining shelf when dealing with each business partner. In addition, 7403 is a part for displaying the product cost. By displaying the product cost when dealing with each customer side by side,
You can compare product costs when dealing with each business partner. The product cost displayed here displays the cost for the product or part selected in 7402.

このように、本実施の形態によれば、製品又は部品毎に為替変動を考慮した棚
残金額推移や製品原価推移のシミュレーション予測をすることができる。また、
取引先毎に取引条件を設定して棚残シミュレーション予測ができるため、為替変
動予測を考慮した棚残予測情報を、調達側のユーザーに提供することができる。
これにより、調達側ユーザーは為替リスクを考慮した取引先の選定を行うことが
できる。
As described above, according to the present embodiment, it is possible to make a simulation prediction of a shelf remaining amount transition and a product cost transition in consideration of exchange rate fluctuations for each product or part. Also,
Since it is possible to predict the remaining inventory simulation by setting transaction conditions for each business partner, it is possible to provide the user on the procurement side with the remaining inventory prediction information considering the exchange rate fluctuation prediction.
As a result, the procurement user can select a supplier in consideration of exchange rate risk.

本発明のシステム構成及び各装置間の受け渡し情報を示す。The system configuration | structure of this invention and the delivery information between each apparatus are shown. 本発明における,各装置間の情報交換の手順の一例を示す。An example of the procedure for exchanging information between devices in the present invention will be described. 本発明の経営意思決定支援装置が提供する画面の遷移を示す。The transition of the screen which the management decision support apparatus of this invention provides is shown. 本発明の経営意思決定支援装置の示す実績経緯表示画面の一例を示す。An example of the results history display screen shown by the management decision support apparatus of the present invention is shown. 本発明の実績経緯表示の表示項目選択画面を示す。The display item selection screen of the performance history display of this invention is shown. 本発明の実績経緯表示の指標選択画面を示す。The index selection screen of the results history display of the present invention is shown. 本発明での経営指標の目標値設定画面の一例を示す。An example of the management index target value setting screen in the present invention is shown. 本発明の実推表示画面の一例を示す。An example of the actual display screen of this invention is shown. 本発明の実推表示の表示項目選択画面の一例を示す。An example of the display item selection screen of the actual guess display of this invention is shown. 本発明の実推表示の指標選択画面の一例を示す。An example of the parameter | index selection screen of the actual guess display of this invention is shown. 本発明の他の実推表示画面の一例を示す。An example of the other actual guess display screen of the present invention is shown. 本発明の経営指標の目標値見直し画面の一例を示す。An example of the target value review screen of the management index of this invention is shown. 本発明の大日程計画編集画面の一例を示す。An example of the large schedule plan edit screen of this invention is shown. 本発明のシナリオレビュー画面の一例を示す。An example of the scenario review screen of this invention is shown. 本発明のシナリオ毎の比較画面の一例を示す。An example of the comparison screen for every scenario of this invention is shown. 本発明の経営意思決定支援装置の機能構成を示す。The functional structure of the management decision support apparatus of this invention is shown. 売上実績データのデータ構造を示す。The data structure of sales performance data is shown. 損益実績データのデータ構造を示す。The data structure of the profit and loss performance data is shown. 生産実績データのデータ構造を示す。The data structure of production performance data is shown. 棚残実績データのデータ構造を示す。The data structure of shelf residual performance data is shown. 大日程計画案のデータ構造を示す。The data structure of the large schedule plan is shown. 損益目標のデータ構造を示す。The data structure of the profit / loss target is shown. 売上目標のデータ構造を示す。The sales target data structure is shown. 棚残目標のデータ構造を示す。The data structure of the remaining shelf target is shown. 売上予測データのデータ構造を示す。The data structure of sales forecast data is shown. 損益予測データのデータ構造を示す。The data structure of profit and loss forecast data is shown. 棚残予測データのデータ構造を示す。The data structure of shelf prediction data is shown. 評価損予測データのデータ構造を示す。The data structure of evaluation loss prediction data is shown. 本発明の損益意思決定支援システムを中心とした情報授受を示す。The information exchange centering on the profit-and-loss decision support system of this invention is shown. 本発明のシステムを構成する各装置間の情報交換の手順の一例を示す。An example of the procedure of information exchange between each apparatus which comprises the system of this invention is shown. 本発明の損益シミュレーション装置の機能構成を示す。The function structure of the profit and loss simulation apparatus of this invention is shown. 本発明の大日程計画展開機能の詳細フローを示す。The detailed flow of the large schedule plan expansion | deployment function of this invention is shown. 本発明の実行可能性チェック機能の詳細フローを示す。The detailed flow of the feasibility check function of this invention is shown. 本発明の損益計算機能の詳細フローを示す。The detailed flow of the profit-and-loss calculation function of this invention is shown. 本発明の損益意思決定支援装置の機能構成を示す。The functional structure of the profit-and-loss decision-making support apparatus of this invention is shown. 本発明の損益意思決定支援装置での画面フローを示す。The screen flow in the profit and loss decision support apparatus of this invention is shown. 本発明の製品構成ツリー画面の一例を示す。An example of the product structure tree screen of this invention is shown. 本発明の付加率変更画面の一例を示す。An example of the addition rate change screen of this invention is shown. 本発明の詳細情報画面の一例を示す。An example of the detailed information screen of this invention is shown. 大日程計画案のデータを示す。The data of the big schedule plan is shown. 機種構成情報のデータを示す。Indicates model configuration data. 配分率のデータを示す。The allocation rate data is shown. 中日程計画案のデータを示す。The data for the medium schedule plan is shown. 計画実行可否の出力結果のデータを示す。Indicates the output result data indicating whether the plan can be executed. 仕切り率予定のデータを示す。The data of the partition ratio is shown. 製品売価予定のデータを示す。Shows data of product sales schedule. 損益・売上・原価のデータを示す。Shows profit / loss / sales / cost data. 本発明の棚残・調達計画支援システムを中心とした情報授受を示す。The information exchange centering on the shelf remaining and procurement plan support system of this invention is shown. 本発明のシステムを構成する各装置間の情報交換の手順の一例を示す。An example of the procedure of information exchange between each apparatus which comprises the system of this invention is shown. 本発明の棚残シミュレーション装置の機能構成を示す。The functional structure of the shelf remaining simulation apparatus of this invention is shown. 本発明の棚残計算機能の詳細フローを示す。The detailed flow of the shelf remaining calculation function of this invention is shown. 本発明の払出原価計算機能の詳細フローを示す。The detailed flow of the paid-out cost calculation function of this invention is shown. 払出単価予定の計算方法を示す。The calculation method of the payout unit price schedule is shown. 本発明の払出原価予定の計算方法の一例を示す。An example of the calculation method of the payout cost schedule of this invention is shown. 本発明の評価損計算機能の詳細フローを示す。The detailed flow of the evaluation loss calculation function of this invention is shown. 本発明の棚残計算機能の詳細フローを示す。The detailed flow of the shelf remaining calculation function of this invention is shown. 本発明の調達計画立案装置の機能構成を示す。1 shows a functional configuration of a procurement plan planning apparatus of the present invention. 本発明の棚残・調達計画支援装置の機能構成を示す。1 shows a functional configuration of a shelf remaining / procurement plan support apparatus according to the present invention. 本発明の調達計画変更機能による画面表示の一例を示す。An example of the screen display by the procurement plan change function of this invention is shown. 本発明の指標指示機能による画面表示の一例を示す。An example of the screen display by the parameter | index instruction | indication function of this invention is shown. 本発明の棚残目標表示部に示される一例を示す。An example shown by the shelf remaining target display part of this invention is shown. 本発明の棚残予測表示部に示される一例を示す。An example shown by the shelf remaining prediction display part of this invention is shown. 本発明の棚残予測表示部に示される一例を示す。An example shown by the shelf remaining prediction display part of this invention is shown. 本発明の調達計画案データの一例を示す。An example of the procurement plan data of this invention is shown. 本発明の払出原価予定データの一例を示す。An example of the payout cost schedule data of this invention is shown. 本発明の棚残予測(数量・金額)データの一例を示す。An example of shelf prediction (quantity / amount) data of the present invention is shown. 本発明の日別中日程計画データの一例を示す。An example of the daily schedule data of this invention is shown. 本発明の為替レートデータの一例を示す。An example of the exchange rate data of this invention is shown. 本発明の取引条件データの一例を示す。An example of transaction condition data of the present invention is shown. 本発明の取引先選択意思決定支援装置の機能構成を示す。The functional structure of the supplier selection decision support apparatus of this invention is shown. 本発明の為替レートシナリオ設定画面の一例を示す。An example of the exchange rate scenario setting screen of this invention is shown. 本発明の為替変動影響確認画面の一例を示す。An example of the exchange fluctuation influence confirmation screen of this invention is shown. 本発明の取引条件設定画面の一例を示す。An example of the transaction condition setting screen of this invention is shown. 本発明の取引先比較の結果の一例を示す。An example of the result of the supplier comparison of the present invention is shown.

符号の説明Explanation of symbols

101・・・経営意思決定支援装置、102・・・損益意思決定支援装置、
103・・・損益シミュレーション装置、104・・・調達計画立案装置、
105・・・棚残シミュレーション装置、106・・・棚残・調達計画支援装置
101 ... Management decision support device, 102 ... Profit and loss decision support device,
103 ... Profit and loss simulation device, 104 ... Procurement planning device,
105 ... shelf remaining simulation device, 106 ... shelf remaining / procurement plan support device

Claims (10)

経営判断を支援する経営意思決定支援システムにおいて、
大日程計画案と損益目標と売上目標の入力支援画面を表示手段に出力し、当該
入力支援画面により入力される入力データを損益意思決定支援システムに送信す
る経営意思決定支援装置を有し、
前記損益意思決定支援システムにより前記大日程計画の実行可否のシミュレー
ション演算を実行した結果に基づいて算出される、大日程計画案の補正計画、損
益予測、売上予測の予測データを経営意思決定支援装置が受信した場合、当該予
測データを、経営意思決定支援装置の表示手段に出力表示することを特徴とする
経営意思決定支援システム。
In a management decision support system that supports management decisions,
It has a management decision support device that outputs a large schedule plan, profit / loss target and sales target input support screen to the display means, and transmits input data input by the input support screen to the profit / loss decision support system,
Management decision support apparatus for correcting data of large schedule plan, profit / loss forecast, forecast data of sales forecast calculated based on the result of executing simulation calculation of execution possibility of the large schedule plan by the profit / loss decision support system The management decision support system characterized in that, when received, the prediction data is output and displayed on the display means of the management decision support apparatus.
経営判断を支援する経営意思決定支援システムにおいて、
大日程計画案と損益目標と売上目標の入力支援画面を表示手段に出力し、当該
入力支援画面により大日程計画案と損益目標と売上目標の入力データを受け付け
る経営意思決定支援装置と、
前記入力データを前記経営意思決定支援装置から受信し、前記大日程計画案の
実行可否のシミュレーション演算を実行し、その結果に基づいて大日程計画案の
補正計画、損益予測、売上予測の予測データを算出する損益意思決定支援システ
ムと、
を有し、当該予測データを、経営意思決定支援装置の表示手段に出力表示する
ことを特徴とする経営意思決定支援システム。
In a management decision support system that supports management decisions,
A management decision support device that outputs a large schedule plan, profit / loss target and sales target input support screen to the display means, and receives input data of the large schedule plan, profit / loss target and sales target by the input support screen,
The input data is received from the management decision support device, a simulation operation is performed to determine whether or not the large schedule plan can be executed, and based on the result, a correction plan for the large schedule plan, profit and loss forecast, forecast data for sales forecast Profit and loss decision support system for calculating
A management decision support system characterized in that the prediction data is output and displayed on the display means of the management decision support apparatus.
経営判断を支援する経営意思決定支援システムにおいて、
大日程計画案と損益目標と売上目標と棚残目標の入力支援画面を表示手段に出
力し、当該入力支援画面により大日程計画案と損益目標と売上目標と棚残目標の
入力データを受け付ける経営意思決定支援装置と、
前記入力データのうちの大日程計画案と損益目標と売上目標を前記経営意思決
定支援装置から受信し、前記大日程計画案を中日程計画に展開した後に前記大日
程計画案の実行可否のシミュレーション演算を実行し、その結果に基づいて大日
程計画案の補正計画、損益予測、売上予測の第1の予測データを算出する損益意
思決定支援システムと、
前記損益意思決定支援システムから送信される前記中日程計画案に基づいて調
達計画を算出し、前記中日程計画案と前記調達計画と予定購入単価に基づいて、
棚残予測と評価損の第2の予測データ及び払出原価予定を算出する棚残・調達計
画支援システムと、
を有し、前記第1及び第2の予測データを、経営意思決定支援装置の表示手段
に出力表示し、前記払出原価予定を前記損益意思決定支援装置に送信することを
特徴とする経営意思決定支援システム。
In a management decision support system that supports management decisions,
Management that accepts input data for large schedule plans, profit / loss targets, sales targets, and remaining inventory targets on the display, and accepts input data for large schedule plans, profit / loss targets, sales targets, and remaining inventory targets A decision support device;
A simulation of whether to execute the large schedule plan after receiving the large schedule plan, the profit / loss target, and the sales target from the management decision support device in the input data, and expanding the large schedule plan into a medium schedule plan A profit and loss decision support system that performs a calculation and calculates first forecast data of a correction plan, profit and loss forecast, and sales forecast of a large schedule based on the result;
Calculate a procurement plan based on the medium schedule plan sent from the profit and loss decision support system, and based on the medium schedule plan, the procurement plan and the planned purchase unit price,
Shelf remaining / procurement plan support system for calculating shelf remaining forecast and second forecast data of valuation loss and payout cost schedule;
Management decision making, wherein the first and second forecast data are output and displayed on a display means of a management decision support device, and the payout cost schedule is transmitted to the profit / loss decision support device Support system.
請求項1乃至3のいずれかに記載の経営意思決定支援システムにおいて、
前記損益意思決定支援システムは、大日程計画案や配分率や製品売価予定の修
正入力を受け付ける損益意思決定支援装置と、払出原価予定に基づいて大日程計
画の実行可否のシミュレーション演算を実行し、実行可能な大日程計画案と損益
予測と売上予測の予測データを算出する損益シミュレーション装置を有すること
を特徴とする経営意思決定支援システム。
In the management decision support system according to any one of claims 1 to 3,
The profit and loss decision support system executes a simulation calculation of whether or not to execute a large schedule based on a profit and loss decision support apparatus that accepts a correction input of a large schedule plan, an allocation rate, and a product sales price schedule, A management decision support system characterized by having a profit and loss simulation device for calculating a feasible large schedule plan and profit and loss forecast and sales forecast data.
請求項3に記載の経営意思決定支援システムにおいて、
前記棚残・調達計画支援システムは、前記中日程計画を用いて調達計画を算出
する調達計画立案装置と、前記調達計画と前記中日程計画案と前記予定購入単価
に基づいて棚残予測と評価損と払出原価予定を算出する棚残シミュレーション装
置と、調達計画の修正入力を受け付ける棚残・調達計画支援装置を有することを
特徴とする経営意思決定支援システム。
In the management decision support system according to claim 3,
The shelf remaining / procurement plan support system includes a procurement plan drafting device that calculates a procurement plan using the middle schedule plan, and a remaining shelf forecast and evaluation based on the procurement plan, the middle schedule plan, and the planned purchase unit price. A management decision support system comprising: a remaining shelf simulation device for calculating a loss and a payout cost schedule, and a remaining shelf / procurement plan support device for receiving a correction input for a procurement plan.
請求項1乃至5のいずれかに記載の経営意思決定支援システムにおいて、
販売実績、生産実績、棚残実績のデータベースのデータに基づいて算出される
経営指標の実績経緯を、2つの経営指標を軸とするXY座標系により、大日程計
画レベルの製品グループ毎に表示することを特徴とする経営意思決定支援システ
ム。
In the management decision support system according to any one of claims 1 to 5,
The history of management indicators calculated based on the database data of sales results, production results, and remaining shelf records is displayed for each product group at the high scheduling level using the XY coordinate system with two management indexes as axes. A management decision support system characterized by that.
請求項1又は2に記載の経営意思決定支援システムにおいて、
販売実績、生産実績、棚残実績のデータベースのデータに基づいて算出される
経営指標の実績経緯と、前記予測データに基づく予測推移とを、2つの経営指標
を軸とするXY座標系により、大日程計画レベルの製品グループ毎に表示するこ
とを特徴とする経営意思決定支援システム。
In the management decision support system according to claim 1 or 2,
Based on the XY coordinate system with the two management indices as the axis, the history of management indices calculated based on the database data of sales performance, production performance, and shelf record performance, and the predicted transition based on the forecast data A management decision support system characterized by displaying each product group at the scheduling level.
請求項3乃至5のいずれかに記載の経営意思決定支援システムにおいて、
販売実績、生産実績、棚残実績のデータベースのデータに基づいて算出される
経営指標の実績経緯と、前記第1の予測データ又は前記第2の予測データに基づ
く予測推移とを、2つの経営指標を軸とするXY座標系により、大日程計画レベ
ルの製品グループ毎に表示することを特徴とする経営意思決定支援システム。
In the management decision support system according to any one of claims 3 to 5,
Two management indicators are the history of the management index calculated based on the data of the sales record, production record, and shelf record record, and the forecast transition based on the first forecast data or the second forecast data. A management decision support system characterized by displaying each product group at a large schedule level using an XY coordinate system with the axis as the axis.
請求項7又は8に記載の経営意思決定支援システムにおいて、
シミュレーション展開前の大日程計画案(新規計画)に基づくグラフ表示と、
シミュレーション展開後の大日程計画案(補正計画)に基づくグラフ表示を、併
せて表示することを特徴とする経営意思決定支援システム。
In the management decision support system according to claim 7 or 8,
A graph display based on a large-scale schedule plan (new plan) before the simulation,
A management decision support system characterized by displaying a graph display based on a large schedule plan (amendment plan) after the simulation.
請求項7乃至9のいずれかに記載の経営意思決定支援システムにおいて、
大日程計画と補正計画と需要予測ケースとの組合せにより定まるシナリオ毎に
、前記表示を行うことを特徴とする経営意思決定支援システム。
In the management decision support system according to any one of claims 7 to 9,
A management decision support system, wherein the display is performed for each scenario determined by a combination of a large schedule plan, a correction plan, and a demand prediction case.
JP2007233539A 2007-09-10 2007-09-10 Management decision support system Pending JP2007323680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007233539A JP2007323680A (en) 2007-09-10 2007-09-10 Management decision support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007233539A JP2007323680A (en) 2007-09-10 2007-09-10 Management decision support system

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2002172200A Division JP2004021364A (en) 2002-06-13 2002-06-13 Management intention decision support system

Publications (1)

Publication Number Publication Date
JP2007323680A true JP2007323680A (en) 2007-12-13

Family

ID=38856378

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007233539A Pending JP2007323680A (en) 2007-09-10 2007-09-10 Management decision support system

Country Status (1)

Country Link
JP (1) JP2007323680A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012221020A (en) * 2011-04-05 2012-11-12 Hitachi Solutions Ltd Cost simulation device
JP2016110610A (en) * 2014-12-08 2016-06-20 未央 古尾谷 Management support program
CN105956390A (en) * 2016-04-27 2016-09-21 重庆交通大学 Ecological safety early-warning and evaluating visualization system and method
JP2016184407A (en) * 2015-03-26 2016-10-20 株式会社オービック Cost management device, cost management method, and cost management program
JP2018055216A (en) * 2016-09-27 2018-04-05 株式会社オービック Shipment control apparatus, shipment control method, and shipment control program
JP2019008691A (en) * 2017-06-28 2019-01-17 セイコーエプソン株式会社 Business management support device, business management method and program
WO2021132603A1 (en) * 2019-12-27 2021-07-01 株式会社覚王山総研 Information processing device, information processing method, and program
KR20210103660A (en) * 2020-02-14 2021-08-24 (주)그루퍼 In-house material inventory pre-forecasting method reflecting material transportation period
JP7444966B2 (en) 2020-03-04 2024-03-06 株式会社マネーフォワード Information processing device, information processing method and program

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04184602A (en) * 1990-11-20 1992-07-01 Hitachi Ltd System and method for preparation of production schedule
JPH05342220A (en) * 1992-06-09 1993-12-24 Sekisui Chem Co Ltd Process plan evaluating system
JPH08185439A (en) * 1994-12-27 1996-07-16 F Kenkyusho:Kk Business assistance system
JPH1011502A (en) * 1996-06-20 1998-01-16 Fujitsu General Ltd Production plan evaluation system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04184602A (en) * 1990-11-20 1992-07-01 Hitachi Ltd System and method for preparation of production schedule
JPH05342220A (en) * 1992-06-09 1993-12-24 Sekisui Chem Co Ltd Process plan evaluating system
JPH08185439A (en) * 1994-12-27 1996-07-16 F Kenkyusho:Kk Business assistance system
JPH1011502A (en) * 1996-06-20 1998-01-16 Fujitsu General Ltd Production plan evaluation system

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012221020A (en) * 2011-04-05 2012-11-12 Hitachi Solutions Ltd Cost simulation device
JP2016110610A (en) * 2014-12-08 2016-06-20 未央 古尾谷 Management support program
JP2020129420A (en) * 2015-03-26 2020-08-27 株式会社オービック Cost management device, cost management method, and cost management program
JP2016184407A (en) * 2015-03-26 2016-10-20 株式会社オービック Cost management device, cost management method, and cost management program
JP6997830B2 (en) 2015-03-26 2022-01-18 株式会社オービック Cost control equipment, cost control methods, and cost control programs
CN105956390A (en) * 2016-04-27 2016-09-21 重庆交通大学 Ecological safety early-warning and evaluating visualization system and method
JP2018055216A (en) * 2016-09-27 2018-04-05 株式会社オービック Shipment control apparatus, shipment control method, and shipment control program
JP2019008691A (en) * 2017-06-28 2019-01-17 セイコーエプソン株式会社 Business management support device, business management method and program
WO2021132603A1 (en) * 2019-12-27 2021-07-01 株式会社覚王山総研 Information processing device, information processing method, and program
JPWO2021132603A1 (en) * 2019-12-27 2021-07-01
JP7180050B2 (en) 2019-12-27 2022-11-30 株式会社覚王山総研 Information processing device, information processing method and program
KR20210103660A (en) * 2020-02-14 2021-08-24 (주)그루퍼 In-house material inventory pre-forecasting method reflecting material transportation period
KR102297145B1 (en) * 2020-02-14 2021-09-02 (주)그루퍼 In-house material inventory pre-forecasting method reflecting material transportation period
JP7444966B2 (en) 2020-03-04 2024-03-06 株式会社マネーフォワード Information processing device, information processing method and program

Similar Documents

Publication Publication Date Title
US20090043643A1 (en) Managerial decision support system and method
US7870012B2 (en) Method for managing a workflow process that assists users in procurement, sourcing, and decision-support for strategic sourcing
US20020072956A1 (en) System and method for determining the optimum configuration strategy for systems with multiple decision options
JP2007323680A (en) Management decision support system
US20030009410A1 (en) Collaboration bill of material
JP2006503352A (en) Systems and methods for improving planning, scheduling and supply chain management
US20020087382A1 (en) Method and system for assigning and tracking tasks, such as under an electronic auction
US20150066592A1 (en) Methods of semiconductor manufacturing and supply chain management systems
US20040148209A1 (en) System and method for producing an infrastructure project estimate for information technology
US20080172348A1 (en) Statistical Determination of Multi-Dimensional Targets
JP2004517378A (en) Systems and methods for optimizing shipping and transportation
Framinan et al. Guidelines for the deployment and implementation of manufacturing scheduling systems
JP2012247964A (en) Progress management apparatus and progress management program
US11328255B2 (en) Automated computer-based prediction of rejections of requisitions
US20170169392A1 (en) Automatic bill of talent generation
Huang Information architecture for effective Workload Control: an insight from a successful implementation
Dominguez et al. Model for integrating the supply chain of an appliance company: a value of information approach
US20140379417A1 (en) System and Method for Data Quality Business Impact Analysis
US8046252B2 (en) Sales plan evaluation support system
US20210304272A1 (en) Graphical user interface-based platform supporting request for x (rfx) creation and management and response compliance checking
EP1750225A1 (en) Supply scheduling
Prakash et al. Effects of inventory classifications on CONWIP system: a case study
JP2003346023A (en) Ordering and order-reception processing system
WO2022172534A1 (en) Component configuration determination assistance device, component configuration determination assistance method, and program
Pradhan Demand and supply planning with SAP APO

Legal Events

Date Code Title Description
A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20071005

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071005

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100406

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100727