JP2007284931A - Method for constructing multi-inter-diameter continuous composite girder - Google Patents
Method for constructing multi-inter-diameter continuous composite girder Download PDFInfo
- Publication number
- JP2007284931A JP2007284931A JP2006111511A JP2006111511A JP2007284931A JP 2007284931 A JP2007284931 A JP 2007284931A JP 2006111511 A JP2006111511 A JP 2006111511A JP 2006111511 A JP2006111511 A JP 2006111511A JP 2007284931 A JP2007284931 A JP 2007284931A
- Authority
- JP
- Japan
- Prior art keywords
- girder
- pier
- steel
- composite girder
- continuous composite
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は、鋼コンクリート合成桁を、その延長方向に連結した状態で2径間以上の橋脚上に架設する多径間連続合成桁の架設方法に関する。 The present invention relates to a construction method for a multi-span continuous composite girder in which a steel-concrete composite girder is erected on a pier having two or more spans in a state where the steel-concrete composite girder is connected in its extending direction.
従来、図8に示すように、H型鋼からなる鋼桁部1の一方のフランジ2と一体にコンクリート桁部3を一体に備えた鋼コンクリート合成桁A(プレビーム−商標)が知られている(例えば特許文献1)。この鋼コンクリート合成桁Aは、鋼桁部1を曲げ方向に荷重を掛けて変形させた状態でコンクリート桁部3をこれと一体に成型し、コンクリートに所定の強度が発現した後曲げ方向の荷重を取り除くことによって生じる鋼桁部1戻り力によってコンクリート桁部3にプレストレスを導入させている。
Conventionally, as shown in FIG. 8, a steel-concrete composite girder A (Prebeam-trademark) having a
この鋼コンクリート合成桁Aを使用した橋梁の架設に際しては、図9に示すように、多数の鋼コンクリート合成桁A,A……を延長方向に連結した状態で橋脚4,4……上に連続させて架設するものであり、その際に互いに隣り合う鋼コンクリート合成桁A,A間の連結は、橋脚上ではなく橋脚間においてなされるものであり、また、隣り合う橋脚4,4間に複数本の鋼コンクリート合成桁A,A……を連結させた状態で架設される場合もある。
When building a bridge using this steel-concrete composite girder A, as shown in FIG. 9, a number of steel-concrete composite girders A, A ... are continuously connected to the
また、このような鋼コンクリート合成桁の架設に際しては、径間長さが長くなればなる程、図8に示すように架設時において過大な正曲げモーメントが生じる。このため従来は、橋脚間の鋼コンクリート合成桁接合位置に架設受け台5を立設し、この架設受け台(ベント)5にも鋼コンクリート合成桁Aの荷重を受け持たせることによって正曲げモーメントの増大を防止している。図9において符号aは接合完成時、bは受け台5を設けた場合、cは架設受け台を設けない場合の曲げモーメント曲線を示している。
上述の如き従来の方法では、架設受け台が必要であるため、その構築及び解体に多くの工程を要し、工期が長くなるとともに橋梁架設コストも高くなるという問題がある。更に、例えば流水のある河川内で施工する場合には仮設桟橋の構築が必要になり、また、深い谷や海上等、架設受け台が構築できない場所では施工できないという問題がある。 In the conventional method as described above, since a erection cradle is required, many steps are required for its construction and dismantling, and there is a problem that the construction period becomes longer and the bridge erection cost increases. Furthermore, for example, when construction is performed in a river with running water, it is necessary to construct a temporary pier, and there is a problem that construction cannot be performed in a place where a construction base cannot be constructed, such as a deep valley or the sea.
本発明はこのような従来の問題に鑑み、径間における鋼コンクリート合成桁連結部分に架設用受け台を必要とせずに、短期間でしかも低コストで連続鋼コンクリート合成桁の架設が可能な多径間連続合成桁の架設方法の提供を目的としてなされたものである。 In view of such a conventional problem, the present invention eliminates the need for a cradle for erection at a steel-concrete composite girder connecting portion between spans, and allows a continuous steel-concrete composite girder to be erected in a short period of time and at a low cost. It was made for the purpose of providing a construction method for continuous span girders.
上述の如き従来の問題を解決し、所期の目的を達成するための請求項1に記載の発明の特徴は、H型鋼からなる鋼桁部の少なくとも一方のフランジと一体にコンクリート桁部を備え、前記鋼桁部の曲げ戻り力によって前記コンクリート桁部にプレストレスが導入されている鋼コンクリート合成桁を、その延長方向に連結した状態で2径間以上の橋脚上に架設する多径間連続合成桁の架設方法において、前記架設しようとする予定数の橋脚上に連続させてガーダを架設するとともに、各橋脚上に横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各鋼コンクリート合成桁間を前記ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置によって前記橋脚上の所定の位置に架設することにある。 In order to solve the above-described conventional problems and achieve the intended object, the feature of the invention according to claim 1 is that a concrete girder part is provided integrally with at least one flange of a steel girder part made of H-shaped steel. Multi-span continuous construction of steel-concrete composite girders in which pre-stress is introduced to the concrete girder part by bending return force of the steel girder part in a state where they are connected in the extension direction on two or more piers In the composite girder erection method, girder will be erected continuously on the planned number of piers to be erected, and a horizontal device will be installed on each pier, and the girder will be erected across multiple spans. Each of the steel concrete composite girders is sequentially sent out to a predetermined erection position, and the steel concrete composite girders adjacent to each other in the extending direction are connected on the girder to obtain a predetermined multi-span construction length. Assembling a single multi-span continuous synthesis digits that binding, the multi span continuous synthesis digits by the intercepting device on each pier is to erection to a predetermined position on the pier.
請求項2に記載の発明の特徴は、請求項1の構成に加え、前記架設しようとする予定数の橋脚上に連続させてガーダを架設するとともに、各橋脚上に、該橋脚の橋梁幅方向の両端に支持される一対の支柱部の上端間に水平梁部を一体に横架させた門型支持部材と、該門型支持部材の前記水平梁部上にその長手方向に移動可能に支持された横送り手段と、該横送り手段に支持された吊り持ち手段とを有する横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各前記鋼コンクリート合成桁間を該ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置の吊り持ち手段によって同時に吊り上げ、該横取り装置の前記横送り手段を同時に作動させて前記多径間連続合成桁を横方向に水平移動させ、前記橋脚上の所定の橋梁幅方向位置で降下させて多径間に亘る連結合成桁を同時に架設することにある。 According to a second aspect of the present invention, in addition to the structure of the first aspect, a girder is continuously installed on the planned number of piers to be installed, and on each pier, the bridge width direction of the pier A gate-type support member in which a horizontal beam part is horizontally mounted integrally between the upper ends of a pair of column parts supported at both ends of the support member, and is supported on the horizontal beam part of the gate-type support member so as to be movable in its longitudinal direction. A horizontal feeding device having a horizontal feeding means and a suspension means supported by the horizontal feeding means is installed, and a predetermined number of the steel-concrete composite girders to be installed across multiple diameters on the girder are respectively determined. The steel concrete composite girders adjacent to each other in the extending direction are connected on the girder to assemble one multi-span continuous composite girder connected to the planned multi-span construction length. The multi-span continuous composite girders on the side of each pier The multi-span continuous composite girder is moved horizontally in the horizontal direction by simultaneously lifting the horizontal feed means of the pre-seat device, and descending at a predetermined bridge width direction position on the pier. In this way, a connecting composite girder spanning multiple spans is installed at the same time.
請求項3に記載の発明の特徴は、請求項1の構成に加え、前記架設しようとする予定数の橋脚上に連続させたガーダを、該橋脚の橋梁幅方向に移動できる横移動手段上に支持させるとともに、各橋脚上に、該橋脚の橋梁幅方向の両端に支持される一対の支柱部の上端間に水平梁部を一体に横架させた門型支持部材と、該門型支持部材の前記水平梁部上にその長手方向に移動可能に支持された横送り手段と、該横送り手段に支持された吊り持ち手段とを有する横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各鋼コンクリート合成桁間を該ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置の吊り持ち手段によって同時に吊り上げた後、前記ガーダを前記橋脚上の横移動手段によって前記多径間連続合成桁下から外れる位置に移動させ、しかる後該多径間連続合成桁を橋脚上に降下させることにより多径間に亘る連結合成桁を同時に架設することにある。 According to a third aspect of the present invention, in addition to the configuration of the first aspect, the girder continued on the planned number of bridge piers to be installed on the lateral movement means capable of moving in the bridge width direction of the pier. A gate-type support member that is supported on each bridge pier, and a horizontal beam portion is horizontally mounted integrally between the upper ends of a pair of support columns supported at both ends of the bridge pier in the bridge width direction, and the gate-type support member On the horizontal beam portion of the horizontal beam portion is installed so as to be movable in the longitudinal direction of the horizontal beam portion, and a crossing device having a suspension means supported by the horizontal feed means is installed, and the girder is spaced between multiple diameters. The planned number of steel-concrete composite girders to be installed across is sent sequentially to a predetermined installation position, and the steel-concrete composite girders adjacent to each other in the extending direction are connected on the girder, and the planned multi-diameter span length Set one multi-span continuous composite girder connected to The multi-span continuous composite girder is lifted at the same time by the lifting means of the pretensioning device on each pier, and then the girder is moved away from the multi-span continuous synthetic girder by the horizontal moving unit on the pier. It is intended to construct a combined composite girder spanning multiple spans simultaneously by moving and then lowering the continuous composite span across multiple spans onto the pier.
請求項4に記載の発明の特徴は、請求項2又は3の構成に加え、前記吊り持ち手段は、前記門型支持部材の前記水平梁部上に移動可能に設置した移動台に支持させた下向き油圧シリンダーを有し、各橋脚上の全横取り装置の前記下向き油圧シリンダーを自動コントロール手段によって同期させて動作させることによって前記多径間連続合成桁を上下方向に平行移動させることにある。 According to a fourth aspect of the present invention, in addition to the configuration of the second or third aspect, the suspension means is supported by a movable base that is movably installed on the horizontal beam portion of the gate-type support member. The multi-span continuous composite girder is translated in the vertical direction by having a downward hydraulic cylinder and operating the downward hydraulic cylinders of all the horizontal interceptors on each pier in synchronization with automatic control means.
請求項5に記載の発明の特徴は、請求項2,3又は4の構成に加え、前記横取り装置の横送り手段は、前記門型支持部材の前記水平梁部上に移動可能に設置した移動台と前記水平梁部上の任意の位置に固定できる反力受け台との間に横向き油圧シリンダー介在させて攻勢され、各橋脚上の全横取り装置の前記横向き油圧シリンダーを自動コントロール手段によって同期させて動作させることによって前記多径間連続合成桁を水平方向に平行移動させることにある。 According to a fifth aspect of the present invention, in addition to the configuration of the second, third, or fourth aspect, the lateral feed means of the horizontal capturing device is movably installed on the horizontal beam portion of the portal support member. A horizontal hydraulic cylinder is interposed between the base and a reaction force receiving base that can be fixed at an arbitrary position on the horizontal beam portion, and the horizontal hydraulic cylinder of all the horizontal capture devices on each pier is synchronized by automatic control means. The multi-span continuous composite girder is translated in the horizontal direction.
請求項6に記載の発明の特徴は、請求項1〜4又は6に記載の多径間連続合成桁の架設方法において、前記架設しようとする橋台及び予定数の橋脚上に連続させてガーダを架設するとともに、前記橋台及び各橋脚及び上に横取り装置を設置し、前記ガーダ上で予定の多径間架設長さに連結した1本の多径間連続合成桁を、前記橋台及び各橋脚上の横取り装置によって該橋台及び各橋脚上の所定の位置に架設する多径間連続合成桁の架設方法。According to a sixth aspect of the present invention, in the multi-span continuous composite girder construction method according to any one of the first to fourth or sixth aspects, the girder is continuously provided on the abutment to be constructed and a predetermined number of piers. In addition to erection, install a pre-installation device on the abutment and each pier, and connect one multi-span continuous composite girder connected to the planned multi-span span on the girder on the abutment and each pier. A multi-span continuous composite girder erection method that is constructed at a predetermined position on the abutment and each pier by using a pre-emption device.
本発明においては、H型鋼からなる鋼桁部の少なくとも一方のフランジと一体にコンクリート桁部を備え、前記鋼桁部の曲げ戻り力によって前記コンクリート桁部にプレストレスが導入されている鋼コンクリート合成桁を、その延長方向に連結した状態で2径間以上の橋脚上に架設する多径間連続合成桁の架設方法において、前記架設しようとする予定数の橋脚上に連続させてガーダを架設するとともに、各橋脚上に横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各鋼コンクリート合成桁間を前記ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置によって前記橋脚上の所定の位置に架設するようにしたことにより、従来のように鋼コンクリート合成桁の接合位置に架設受け台を必要としなくなり、従って流水のある河川や、深い谷部分等、架設受け台を設置し難い場所においても、多径間連続合成桁の架設が比較的容易にできる。 In the present invention, the steel-concrete composite is provided with a concrete girder part integrally with at least one flange of a steel girder part made of H-shaped steel, and prestress is introduced into the concrete girder part by a bending return force of the steel girder part. In a multi-span continuous composite girder construction method in which a girder is erected on a pier having two or more spans in a state where the girder is connected in the extension direction, girder is constructed continuously on the planned number of piers to be constructed. In addition, a pre-installation device is installed on each pier, and a predetermined number of the steel-concrete composite girders that are installed over the girder across multiple diameters are sequentially sent to a predetermined installation position. The concrete composite girders are connected on the girder to assemble one multi-span continuous composite girder connected to the planned multi-span construction length, and the multi-span continuous composite girder By installing it at a predetermined position on the pier by means of a stray device on the pedestal, there is no need for a pedestal at the joining position of the steel-concrete composite girder as in the prior art. Even in places where it is difficult to install an erection cradle, such as a valley, it is relatively easy to construct a multi-span continuous composite girder.
また、本発明においては、架設しようとする予定数の橋脚上に連続させてガーダを架設するとともに、各橋脚上に、該橋脚の橋梁幅方向の両端に支持される一対の支柱部の上端間に水平梁部を一体に横架させた門型支持部材と、該門型支持部材の前記水平梁部上にその長手方向に移動可能に支持された横送り手段と、該横送り手段に支持された吊り持ち手段とを有する横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各前記鋼コンクリート合成桁間を該ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置の吊り持ち手段によって同時に吊り上げ、該横取り装置の前記横送り手段を同時に作動させて前記多径間連続合成桁を横方向に水平移動させ、前記橋脚上の所定の橋梁幅方向位置で降下させて多径間に亘る連結合成桁を同時に架設するようにすることにより、1本に連結した長い多径間連続合成桁であっても、その横取りが容易となり、長大な多径間連続合成桁の架設が経済的になされる。 Further, in the present invention, the girder is continuously installed on the planned number of piers to be installed, and between the upper ends of a pair of support columns supported on both ends of the bridge pier in the bridge width direction. A gate-type support member in which a horizontal beam portion is horizontally mounted on the horizontal beam portion, lateral feed means supported on the horizontal beam portion of the gate-type support member so as to be movable in the longitudinal direction thereof, and supported by the lateral feed means And installing a pretensioning device having a suspended holding means, and sequentially sending out a predetermined number of the steel-concrete composite girders to be laid over the girder across multiple diameters to a predetermined erection position, and adjacent to each other in the extending direction. Each steel-concrete composite girder is connected on the girder to assemble one multi-span continuous composite girder connected to a planned multi-span span length, and the multi-span continuous composite girder is connected to each pier It is the same by the suspension means of The multi-span continuous composite girder is moved horizontally in the horizontal direction by simultaneously operating the cross-feeding means of the horizontal capture device, and is lowered at a predetermined position in the bridge width direction on the pier so as to span the multi-span. By linking the combined composite girder at the same time, even if it is a long multi-span continuous composite girder connected to one, it is easy to intercept and economically install a long multi-span continuous composite girder. Made.
更に本発明では、架設しようとする予定数の橋脚上に連続させたガーダを、該橋脚の橋梁幅方向に移動できる横移動手段上に支持させるとともに、各橋脚上に、該橋脚の橋梁幅方向の両端に支持される一対の支柱部の上端間に水平梁部を一体に横架させた門型支持部材と、該門型支持部材の前記水平梁部上にその長手方向に移動可能に支持された横送り手段と、該横送り手段に支持された吊り持ち手段とを有する横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各鋼コンクリート合成桁間を該ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置の吊り持ち手段によって同時に吊り上げた後、前記ガーダを前記橋脚上の横移動手段によって前記多径間連続合成桁下から外れる位置に移動させ、しかる後該多径間連続合成桁を橋脚上に降下させることにより多径間に亘る連結合成桁を同時に架設するようにすることにより、多径間連続合成桁を横移動のない上下方向の操作によって可能となるため、大重量の多径間連続合成桁であってもその架設作業が容易となる。 Further, in the present invention, the girder continued on the planned number of piers to be installed is supported on a lateral movement means that can move in the bridge width direction of the pier, and on each pier, in the bridge width direction of the pier. A gate-type support member in which a horizontal beam part is horizontally mounted integrally between the upper ends of a pair of column parts supported at both ends of the support member, and is supported on the horizontal beam part of the gate-type support member so as to be movable in its longitudinal direction. A horizontal feeding device having a horizontal feeding means and a suspension means supported by the horizontal feeding means is installed, and a predetermined number of the steel-concrete composite girders to be installed across multiple diameters on the girder are respectively determined. The steel-concrete composite girders adjacent to each other in the extending direction are connected on the girder, and one multi-span continuous composite girder connected to the planned multi-span construction length is assembled. The multi-span continuous composite girder is placed on each pier. After being lifted simultaneously by the suspension means of the pretending device, the girder is moved to a position where it is removed from the bottom of the multi-span continuous composite girder by the lateral movement unit on the pier, and then the multi-span continuous composite girder is moved on the pier. It is possible to operate a multi-span continuous composite girder by operating in the vertical direction without lateral movement by simultaneously constructing a combined composite girder that spans multiple diameters by lowering to a large diameter. Even a continuous composite girder can be easily installed.
更に本発明では、吊り持ち手段及び横送り手段に油圧シリンダーを使用し、各橋脚上の横取り装置の前記油圧ジャッキを自動コントロール手段によって同期させて動作させることによって前記多径間連続合成桁を上下方向及び水平方向に平行移動させることにより、移動中における多径間連続合成桁の変形を少なくでき、より安全に架設作業ができる。 Further, in the present invention, a hydraulic cylinder is used for the suspension means and the lateral feed means, and the multi-span continuous composite girders are moved up and down by operating the hydraulic jacks of the horizontal take-up device on each pier in synchronization with the automatic control means. By translating in the horizontal and horizontal directions, the deformation of the multi-span continuous composite girder during movement can be reduced, and construction work can be performed more safely.
更に本発明に係る多径間連続合成桁の架設方法では、複数の橋脚上に跨らせて1本の多径間連続合成桁を架設する他、橋台と複数の橋脚に跨らせて架設するようにしても良い。Furthermore, in the construction method of the multi-span continuous composite girder according to the present invention, the multi-span continuous composite girder is constructed over a plurality of piers, and is constructed over the abutment and a plurality of piers. You may make it do.
次に本発明の実施の形態を図面に示した実施例に基づいて説明する。尚、前述した従来技術と同一部分には同一の符号を付して重複説明を省略する。 Next, embodiments of the present invention will be described based on examples shown in the drawings. In addition, the same code | symbol is attached | subjected to the part same as the prior art mentioned above, and duplication description is abbreviate | omitted.
本実施例の多径間連続合成桁の架設方法は、先ず図1に示すように、架設しようとする多径間連続合成桁の長さに応じ、橋台4a及び各橋脚4,4……上に連続させてガーダ10を架設する。このガーダ10には鋼製桁材を連結したものを使用し、架設しようとする橋梁の一端側の資材搬入路11から順次押し出して橋台4a及び所用数の橋脚4,4……上に連続して跨らせた状態に架設する。このガーダ10上には、図には詳示してないが搬入用台車12が走行できるレールを長手方向に連続させて設置しておく。
First, as shown in FIG. 1, according to the length of the multi-span continuous composite girder to be installed, the abutment 4a and each
次いで、このガーダ10を利用して橋台4a及び橋脚4上に横取り装置20を構成する部材を搬入しこれを組み立てる。この横取り装置20は、図3、図7に示す如き門型支持部材21、該門型支持部材21に支持させた横送り手段22及び横送り手段に支持させた吊り持ち手段23とから構成されている。
Next, the
門型支持手段21は、橋台4a及び橋脚4の橋梁幅方向の両端部に下端が支持される一対の支柱部25,25と、その上端間に掛け渡された一対のH型鋼からなる水平梁部26,26とから構成されており、支柱部25,25は支えワイヤー27,27によって直立状態が維持されるようになっている。
The gate-type support means 21 includes a pair of
横送り手段22は、滑り板上にスライド自在に載置させた移動台30と、この移動台30を水平梁部長さ方向に移動させるための油圧シリンダーを使用した横送り駆動装置31とから構成されている。 The transverse feed means 22 includes a moving table 30 slidably mounted on a sliding plate, and a transverse feed drive device 31 using a hydraulic cylinder for moving the moving table 30 in the horizontal beam length direction. Has been.
両水平梁部26,26上には表面が平滑なステンレス板からなるスライドガイド板28,28が固定されており、その上に移動台30が水平梁部26の長手方向にスライド自在に載置されている。この移動台30の底面にはフッ素化合樹脂(テフロン:商標)製の滑り板30aが貼り付けられており、スライドガイド板28,28上を容易に滑り動くことができるように構成されている。
On both
の両側縁部にはガイドブラケット32,32が下向きに突設され、これが両水平梁部26,26の側縁部外側に垂下され、これによって移動台30の水平梁部幅方向の移動を阻止している。
横送り駆動装置31は、両水平梁部26,26に対する任意の位置に固定できる反力受け台33と、この反力受け台33と前記移動台30間に介在させた横向き油圧シリンダー34とから構成されている。反力受け台33は、その両側部に水平梁部26,26のフランジ部を把持するクランプ35,35が備えられており、このクランプ35,35によって反力受け台33を水平梁部26,26上の任意の位置に固定できるようになっており、この反力受け台33を水平梁部に固定した状態で油圧シリンダー34を伸縮させることにより、移動台30が水平梁部の長手方向に往復移動されるようになっている。
The lateral feed drive device 31 includes a reaction
移動台30の必要な移動長さが横向き油圧シリンダー34のストロークより大きい場合には、油圧シリンダー34の1ストローク分だけ移動台30を移動させた後、クランプ35による水平梁部26との固定を解除し、油圧シリンダー34を短縮又は伸張させることにより反力受け台33を移動させ、その移動位置で再度クランプ35により固定させ、再度移動台30の移動作業を繰り返すことによって移動台3を必要な長さだけ移動させる。
When the required moving length of the moving
吊り持ち手段23は、図4に示すように移動台30に固定した一対の下向き油圧シリンダー36,36と、その各油圧シリンダー36,36の動作軸に支持させた吊りワイヤー37,37と、両吊りワイヤー37,37の先端に吊り持ちさせた吊り金具38とからなっており、吊り金具38は、図には詳示されてないが後述する鋼コンクリート合成桁Aの鋼桁部1を把持できる構造となっている。
As shown in FIG. 4, the suspension means 23 includes a pair of downward
このようにして橋台4a及び各橋脚4,4……上にそれぞれ横取り装置20,20……を設置した後、ガーダ10に連続させた資材搬入路11上で、搬入用台車12,12上にトレーラー等の運搬手段によって運び込まれた鋼コンクリート合成桁Aを載せ、所用数の鋼コンクリート合成桁Aを順次ガーダ10上に支持させて所定の架設位置まで移動させる。
In this way, after installing the intercepting
このようにして予め設計された所用本数の鋼コンクリート合成桁A,A……を図2に示すように、ガーダ10上で互いに延長方向に突き合わせ、各接合部40,41……を従来と同様に、溶接又は連結金具のボルト止め等の各種の連結方法によって互いに連結し、ガーダ10上で一本の多径間連続合成桁Bとなす。
As shown in FIG. 2, the required number of steel-concrete composite girders A, A... Designed in advance in this manner are butted against each other on the
上述のように、ガーダ10上で所用長さに組み立てられた多径間連続合成桁Bを橋台4a及び各橋脚4,4……上の各横送り装置20,20……を使用して横取りし、所定の位置に移動させて架設する。この横取り作業は、先ず、吊り持ち手段23によって多径間連続合成桁Bを吊り上げる。この吊り上げ作業は、移動台30を多径間連続合成桁B上まで移動させて停止させる。次いでの下向きシリンダー36,36を作動させて吊り金具38を降下させ、該吊り金具38にて鋼桁部1を把持させる。この状態で各横取り装置20,20……の全ての下向き油圧シリンダー36を同期させて作動させ、1本の多径間連続合成桁Bの各吊り位置を同じ速度で同じ高さに吊り上げる。
As described above, the multi-span continuous composite girder B assembled to the required length on the
この時の各油圧シリンダー36のコントロールは、ロータリーエンコーダ等の移動検出器によって各油圧シリンダー36の動作長さを検出させ、その検出データをコントローラにフィードバックすることによって各油圧シリンダー35が同期して作動するようにコントロールしている。
At this time, each
このようにして各横取り装置20の吊り持ち手段23によって多径間連続合成桁Bを吊り上げた状態で各移動台30をそれぞれの横向き油圧シリンダー34を作動させて横送りさせる。この時、全横向き油圧シリンダー34の動作を、前述した下向き油圧シリンダーと同様にした同期させ、多径間連続合成桁Bが1直線状態を維持したままで横送りさせる。
In this way, each
このようにして多径間連続合成桁Bを所定の架設位置まで横送りした後、各下向き油圧シリンダー35を同期させて前述とは逆に作動させることにより、多径間連続合成桁Bを橋脚4の所定位置に載せ、1本の多径間連続合成桁Bの架設を終了する。
In this way, the multi-span continuous composite girder B is laterally fed to a predetermined erection position, and then the downward
上述した作業を順次繰り返して必要数の多径間連続合成桁Bを架設する。 The required number of multi-span continuous composite girders B are erected in order by repeating the above operations.
尚、上述の実施例では、ガーダ10を橋脚4の橋梁幅方向の定位置に設置して作業を行う場合について示しているが、この他、図7示すように、ガーダ10を橋台4a及び各橋脚4上にて、油圧ジャッキ等のガーダ横移動手段によって横移動可能に設置し、前述と同様にしてガーダ10上で1本の多径間連続合成桁Bを組み立て、吊り持ち手段23によって吊り上げた後、ガーダ10を横移動させて多径間連続合成桁Bの設置位置を開け、しかる後に多径間連続合成桁Bを横取りすることなく橋脚4上に架設するようにしてもよい。
In the embodiment described above, shows the case of performing work by installing a
A 鋼コンクリート合成桁
B 多径間連続合成桁
a,b 曲げモーメント曲線
1 鋼桁部
2 フランジ
3 コンクリート桁部
4 橋脚
4a 橋台
5 架設受け台
10 ガーダ
11 資材搬入路
12 搬入用台車
20 横取り装置
21 門型支持部材
22 横送り手段
23 吊り持ち手段
25 支柱部
26 水平梁部
27 支えワイヤー
28 スライドガイド板
30 移動台
30a 滑り板
31 横送り駆動装置
32 ガイドブラケット
33 反力受け台
34 横向き油圧シリンダー
35 クランプ
36 下向き油圧シリンダー
37 吊りワイヤー
38 吊り金具
40 接合部
A Steel-concrete composite girder B Multi-span continuous composite girder a, b Bending moment curve 1
Claims (5)
前記架設しようとする予定橋脚数上に連続させてガーダを架設するとともに、各橋脚上に横取り装置を設置し、前記ガーダ上を多径間に渡って架設する予定数の前記鋼コンクリート合成桁をそれぞれ所定の架設位置まで順次送り出し、互いに延長方向に隣り合う各鋼コンクリート合成桁間を前記ガーダ上で連結し、予定の多径間架設長さに連結した1本の多径間連続合成桁を組み立て、該多径間連続合成桁を前記各橋脚上の横取り装置によって前記橋脚上の所定の位置に架設することを特徴としてなる多径間連続合成桁の架設方法。 A steel-concrete composite girder integrally provided with a concrete girder part integrally with at least one flange of a steel girder part made of H-shaped steel, and prestress is introduced into the concrete girder part by a bending return force of the steel girder part, In the construction method of the multi-span continuous composite girder that is erected on the pier of 2 spans or more in the state of being connected in the extension direction,
The girder is erected continuously on the planned number of piers to be erected, and a pre-installation device is installed on each pier, and the steel concrete composite girder of the expected number to be erected across the girder between multiple diameters. Each steel concrete composite girder adjacent to each other in the extending direction is connected on the girder, and one multi-span continuous composite girder is connected to the planned multi-span installation length. An assembly method for a multi-span continuous composite girder, characterized in that the multi-span continuous composite girder is erected at a predetermined position on the pier by means of a take-off device on each pier.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006111511A JP2007284931A (en) | 2006-04-14 | 2006-04-14 | Method for constructing multi-inter-diameter continuous composite girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006111511A JP2007284931A (en) | 2006-04-14 | 2006-04-14 | Method for constructing multi-inter-diameter continuous composite girder |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2007284931A true JP2007284931A (en) | 2007-11-01 |
Family
ID=38756968
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006111511A Pending JP2007284931A (en) | 2006-04-14 | 2006-04-14 | Method for constructing multi-inter-diameter continuous composite girder |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2007284931A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113849888A (en) * | 2021-09-18 | 2021-12-28 | 中铁大桥局集团有限公司 | Calculation method for matching cutting amount of continuous steel truss girder closure member piece erected hole by hole |
-
2006
- 2006-04-14 JP JP2006111511A patent/JP2007284931A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113849888A (en) * | 2021-09-18 | 2021-12-28 | 中铁大桥局集团有限公司 | Calculation method for matching cutting amount of continuous steel truss girder closure member piece erected hole by hole |
CN113849888B (en) * | 2021-09-18 | 2024-03-19 | 中铁大桥局集团有限公司 | Calculation method for hole-by-hole erection of continuous steel truss girder closure rod piece matching and cutting amount |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2008088782A (en) | Cantilever overhang erection method of corrugated steel plate web bridge | |
JP3223264U (en) | Moving device for roofing work platform | |
CN103821087B (en) | Prefabricated bridge Steel Space pipe concrete truss combination beams and construction method | |
JP4377506B2 (en) | Bridge erection device and bridge erection method | |
JP4777319B2 (en) | Bridge erection method | |
JP4558609B2 (en) | Extrusion construction method of bridge | |
JP6247496B2 (en) | Steel structure construction method | |
CN113323405A (en) | Sliding construction method applied to large-span steel structure | |
JP6215037B2 (en) | Roof erection method and roof structure | |
CN113846563A (en) | Construction method for side span and auxiliary span steel truss girder erection of large-span cable-stayed bridge | |
CN111877166A (en) | Incremental launching construction method for bridge steel box girder with slope | |
JP2003221875A (en) | Rail-less slide method | |
JP2011038381A (en) | Reconstruction method for existing building | |
JP5106989B2 (en) | Corrugated steel web bridge erection device and corrugated steel web bridge erection method | |
JP6425779B2 (en) | Roof structure | |
JP2008274638A (en) | Corrugated steel plate web bridge erection device and corrugated steel plate web bridge erection method | |
JP2007284931A (en) | Method for constructing multi-inter-diameter continuous composite girder | |
JP2000234311A (en) | Side moving method for bridge beam, etc., and side moving device therefor | |
CN102155095B (en) | Arranging method of concrete reinforcements of steel rib of large-scale metallurgical workshop | |
JP6375141B2 (en) | Scaffolding device and concrete frame construction method using the scaffolding device | |
JP4880374B2 (en) | How to build a bridge | |
JP4351523B2 (en) | Column head construction method | |
JP6794235B2 (en) | How to erection a bridge | |
JP6508958B2 (en) | Demolition system and demolition method | |
JP3905099B2 (en) | Hand girder delivery construction method for bridge girder |