JP2011038381A - Reconstruction method for existing building - Google Patents

Reconstruction method for existing building Download PDF

Info

Publication number
JP2011038381A
JP2011038381A JP2009189484A JP2009189484A JP2011038381A JP 2011038381 A JP2011038381 A JP 2011038381A JP 2009189484 A JP2009189484 A JP 2009189484A JP 2009189484 A JP2009189484 A JP 2009189484A JP 2011038381 A JP2011038381 A JP 2011038381A
Authority
JP
Japan
Prior art keywords
supported
cable
column
load
existing building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009189484A
Other languages
Japanese (ja)
Other versions
JP5503223B2 (en
Inventor
Hiroshi Shinjo
浩 新上
Yasushi Takahashi
靖 高橋
Shuji Senna
修二 仙名
Ken Kayanuma
健 萱沼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Mitsui Construction Co Ltd
Original Assignee
Sumitomo Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Mitsui Construction Co Ltd filed Critical Sumitomo Mitsui Construction Co Ltd
Priority to JP2009189484A priority Critical patent/JP5503223B2/en
Publication of JP2011038381A publication Critical patent/JP2011038381A/en
Application granted granted Critical
Publication of JP5503223B2 publication Critical patent/JP5503223B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a reconstruction method for an existing building, which removes a middle column which reduces the number of cables or tension force, facilitates work, and can also be applied to a girder of a large span. <P>SOLUTION: A block 13 to be supported which is supported by a cable 17 is provided in a position lower than the connection of the middle column 3 with the upper beam 5, and tight-installation blocks 16 used for tightly installing the cable 17 are each provided in the position of a pair of outer peripheral columns 2 higher than the block 13 to be supported. Then the cable 17 is constructed between the pair of the tight-installation blocks 16 so that it can pass through the block 13 to be supported. After that, the cable 17 is retained by the tight-installation blocks 16 in a tension state, and the block 13 to be supported is supported by the cable 17. The part of the middle column 3 which is lower than the block 13 to be supported is removed in a state where the block 13 to be supported is supported. <P>COPYRIGHT: (C)2011,JPO&amp;INPIT

Description

本発明は、既存建物の改造方法に係り、より詳しくは、中間柱と、該中間柱を平面視で挟む位置に配置され、それぞれ梁によって該中間柱と連結された一対の外側柱とを有する既存建物において、中間柱を撤去する改造方法に関する。   The present invention relates to a method for remodeling an existing building, and more specifically, includes an intermediate column and a pair of outer columns arranged at positions sandwiching the intermediate column in plan view and connected to the intermediate column by beams. The present invention relates to a remodeling method for removing an intermediate pillar in an existing building.

工場や倉庫、オフィスビルなどの大型の建物は、重量鉄骨造や鉄筋コンクリート造でラーメン構造に構築されることが多い。重量鉄骨造や鉄筋コンクリート造は、木造や軽量鉄骨造などに比べて建設コストが高い一方、耐用年数が長いという特徴を有する。しかし、近年、周辺環境の変化に応じて建物の用途を変更したり、同一用途であっても建物に収容する装置や製品が技術の進歩等に伴って大型化したりすることがあり、間仕切り壁や既存床、梁や中間柱を撤去して大きな空間を提供できる建物に改造したいというニーズが高まっている。   Large buildings such as factories, warehouses, and office buildings are often constructed in a rigid frame structure with heavy steel structures or reinforced concrete structures. Heavy steel structures and reinforced concrete structures are characterized by high construction costs and long service life compared to wooden structures and lightweight steel structures. However, in recent years, the usage of buildings has been changed according to changes in the surrounding environment, and even if the same usage is used, the equipment and products housed in the building can become larger due to technological advances, etc. There is a growing need to renovate buildings that can provide large spaces by removing existing floors, beams and intermediate columns.

ところが、ラーメン構造の建物では、屋根や床を支持する大梁が建物外周に配置された外周柱だけでなく建物内部に配置された中間柱によっても支持されているため、既存建物において何ら補強することなく中間柱を撤去することはできない。そこで、既存建物の中間柱を撤去する改造方法として、外周部架構の耐震補強または免震装置の導入を行った上で、撤去する中間柱の近傍位置で大梁を仮サポートで支持した状態で、中間柱をその頭部で切断して撤去し、大梁の両端における接合部を解体して単純支持状態にした状態で、大梁にケーブルを設置してポストテンションを導入し、その後、大梁の両端部解体箇所を外周部架構に対して剛体接合状態にまで修復する発明が提案されている(特許文献1参照)。この発明によれば、ケーブルによるポストテンションによって大梁の曲げ応力を低減するとともに、外周柱の曲げ応力を低減することができる。   However, in a ramen-structured building, the beams that support the roof and floor are supported not only by the outer pillars arranged on the outer periphery of the building but also by the intermediate pillars arranged inside the building. The middle pillar cannot be removed. Therefore, as a remodeling method to remove the intermediate column of the existing building, after installing the seismic reinforcement of the outer frame or the seismic isolation device, with the large beam supported by the temporary support in the vicinity of the intermediate column to be removed, Cut the intermediate pillar at its head and remove it, disassemble the joints at both ends of the girder and put it in a simple support state, install a cable on the girder and introduce post tension, and then both ends of the girder An invention has been proposed in which a dismantled part is restored to a rigid joint state with respect to the outer frame (see Patent Document 1). According to this invention, it is possible to reduce the bending stress of the large beam and the bending stress of the outer peripheral column by the post tension by the cable.

特許第3878900号公報Japanese Patent No. 3878900

しかしながら、特許文献1に記載の改造方法では、ケーブルが大梁の両端部で大梁上部に位置し、大梁の長手方向中央部で大梁下部に位置するように、ケーブル定着部材やケーブル方向変更部材を大梁の側面部に設置するため、大梁の梁成以上にケーブルのライズ(高低差)をとることができず、大梁の曲げ応力低減量に対して要するケーブルの緊張力が大きい。そのため、ケーブルの本数が多くなったり、ケーブルの断面寸法が大型化したりするだけでなく、スパン数が多く、必要とされる大梁の曲げ応力低減量が大きい場合、大梁の側面にケーブルを設置しただけでは全ての中間柱を撤去することが不可能となることもある。更に、大きな緊張力をケーブルに付与する必要があるため、ケーブルを緊張する緊張具も大型化し、その取り扱いが困難となって作業性も悪い。   However, in the remodeling method described in Patent Document 1, the cable fixing member and the cable direction changing member are arranged so that the cable is positioned above the large beam at both ends of the large beam and positioned below the large beam at the longitudinal center of the large beam. Because the cable is installed on the side surface of the cable, the cable cannot be raised more than the beam of the large beam, and the cable tension required for the bending stress reduction amount of the large beam is large. Therefore, when the number of cables increases and the cross-sectional dimensions of the cables increase, the number of spans is large, and when the required amount of bending stress reduction for large beams is large, cables are installed on the sides of the large beams. It may not be possible to remove all the intermediate pillars alone. Furthermore, since it is necessary to apply a large tension force to the cable, the tension tool for tensioning the cable is also increased in size, making it difficult to handle and poor workability.

本発明は、このような背景に鑑みなされたもので、ケーブルの本数或いは緊張力を低減し、容易に作業できるとともに、大スパンの大梁にも適用可能な中間柱を撤去する既存建物の改造方法を提供することを目的とする。   The present invention has been made in view of such a background, and reduces the number of cables or tension, can be easily operated, and removes an intermediate column applicable to a large span large beam. The purpose is to provide.

上記課題を解決するために、第1の発明は、中間柱(3)と、中間柱(3)を平面視で挟む位置に配置され、それぞれ梁(5)によって中間柱(3)と連結された一対の外側柱(2)とを有する既存建物(1)において、中間柱(3)を撤去する改造方法であって、中間柱(3)における梁(5)との接合部よりも低い位置にケーブル(17)による支持に供される被支持手段(13)を設けるステップと、一対の外側柱(2)における被支持手段(13)よりも高い位置にケーブル(17)を張設するための張設手段(16,21)をそれぞれ設けるステップと、被支持手段(13)を通るように一対の張設手段(16,21)間にケーブル(17)を架設するステップと、張設手段(16,21)にケーブル(17)を緊張状態で保持させ、ケーブル(17)に被支持手段(13)を支持させるステップと、ケーブル(17)に被支持手段(13)を支持させた状態で中間柱(3)における被支持手段(13)よりも下側の部位を撤去するステップとを有することを特徴とする。   In order to solve the above problems, the first invention is arranged at a position sandwiching the intermediate column (3) and the intermediate column (3) in plan view, and is connected to the intermediate column (3) by a beam (5), respectively. In the existing building (1) having a pair of outer pillars (2), it is a modification method for removing the intermediate pillar (3), which is lower than the joint with the beam (5) in the intermediate pillar (3) A step of providing a supported means (13) to be supported by the cable (17), and a tensioning of the cable (17) at a position higher than the supported means (13) in the pair of outer columns (2) Respectively, a step of laying a cable (17) between the pair of tensioning means (16, 21) so as to pass through the supported means (13), and a tensioning means Hold the cable (17) in tension in (16, 21) A step of supporting the supported means (13) by the cable (17), and a state where the supported means (13) is supported by the cable (17) below the supported means (13) of the intermediate column (3). And removing the side portion.

ここで、外側柱とは、建物外周に配置された外周柱だけでなく、1列に2本以上の中間柱を有する建物においては、撤去する中間柱に隣接する中間柱を含むものであり、撤去する中間柱の建物外周側に隣接する柱を意味するものである。また、梁とは、屋根や屋上スラブを支持する最上部のものに限られず、中間階や最上階のスラブを支持するものも含むものである。そして、既存建物は、一階建ての平屋に限られるものではなく、複数の階層を有する多層建物も含み、撤去する中間柱は1列につき1本に限られるものではなく、1階層の中間柱に限られるものでもない。また、被支持手段を支持させるとは、被支持手段に加わる荷重および自重を合計した全荷重を支持する形態に限られず、その一部を支持する形態も含む。   Here, the outer column includes not only the outer column arranged on the outer periphery of the building but also the intermediate column adjacent to the intermediate column to be removed in a building having two or more intermediate columns in one row, It means a column adjacent to the outer peripheral side of the intermediate column to be removed. Further, the beam is not limited to the uppermost one that supports the roof or the roof slab, but includes those that support the slabs on the intermediate floor or the uppermost floor. And the existing building is not limited to a one-story one-storied house, but also includes multi-story buildings with multiple levels, and the number of intermediate pillars to be removed is not limited to one per row, but one level of intermediate pillars. It is not limited to. Further, supporting the supported means is not limited to the form of supporting the total load including the load applied to the supported means and the own weight, and includes a form of supporting a part thereof.

この発明によれば、中間柱における梁との接合部よりも低い位置に被支持手段を設け、一対の外側柱における被支持手段よりも高い位置に張設手段を設けたため、一対の張設手段間に張設されるケーブルのライズを大きくすることができる。そのため、梁の曲げ応力低減量に対するケーブルの緊張力が小さくなり、ケーブルの本数低減、或いはケーブルの断面寸法の縮小化を図ることができる。また、既存の中間柱をその上部を残して束として利用するため、寸法の大きな束部材を別途用意して梁に堅固に固定する必要がない。また、被支持手段等を設ける位置を変更することで梁の曲げ応力低減量に対するケーブルの緊張力を小さくすることが可能なため、スパン数が多く、必要とされる大梁の曲げ応力低減量が大きい場合であっても、比較的小さな緊張力で全ての中間柱を撤去することも可能である。加えて、ケーブルに印加する緊張力が小さいため、小型の緊張具で施工することができ、作業性も良い。   According to the present invention, since the supported means is provided at a position lower than the joint portion of the intermediate column with the beam, and the extending means is provided at a position higher than the supported means at the pair of outer columns, the pair of extending means The rise of the cable stretched between them can be increased. Therefore, the tension of the cable with respect to the amount of bending stress reduction of the beam is reduced, and the number of cables can be reduced or the cross-sectional dimension of the cable can be reduced. In addition, since the existing intermediate pillar is used as a bundle leaving its upper part, it is not necessary to separately prepare a bundle member having a large size and firmly fix it to the beam. Also, since the tension of the cable against the bending stress reduction amount of the beam can be reduced by changing the position where the supported means is provided, the number of spans is large, and the required bending stress reduction amount of the large beam is reduced. Even if it is large, it is possible to remove all the intermediate pillars with a relatively small tension. In addition, since the tension force applied to the cable is small, it can be constructed with a small tension tool, and the workability is also good.

また、第2の発明は、第1の発明に係る既存建物(1)の改造方法において、中間柱(3)における被支持手段(13)設置部位に荷重迂回手段(仮支持架台14,仮支持ピース18)を設けるステップと、荷重迂回手段(14,18)に、被支持手段(13)設置部位に伝達する伝達荷重を迂回させるステップと、荷重迂回手段(14,18)に伝達荷重を迂回させた状態で、或いは荷重迂回手段(14,18)に伝達荷重を迂回させつつ、被支持手段(13)の下端近傍で中間柱(3)を切断するステップとを、ケーブル(17)に被支持手段(13)を支持させるステップの前に更に有することを特徴とする。   The second invention is a method of remodeling an existing building (1) according to the first invention, wherein a load bypass means (temporary support frame 14, temporary support) is provided at a place where the supported means (13) is installed in the intermediate column (3). A step of providing the piece 18), a step of bypassing the transmission load transmitted to the supported portion (13) installation site in the load bypassing means (14, 18), and a bypass of the transmission load in the load bypassing means (14, 18) Cutting the intermediate column (3) in the vicinity of the lower end of the supported means (13) while the load is bypassed or while the load bypassing means (14, 18) is bypassed. It further has before the step which supports a support means (13), It is characterized by the above-mentioned.

この発明によれば、撤去する中間柱が負担する荷重を荷重迂回手段によって被支持部材設置部位を通らないように迂回させ、荷重が加わってない安全な状態で撤去すべき中間柱を切断することができる。また、ケーブルを緊張しながら荷重迂回手段の伝達荷重を確認することで、荷重迂回手段による支持荷重を徐々にケーブルに移行させることができ、中間柱を撤去する前にケーブルに所期の支持力を発揮させることができる。したがって、改造作業の安全性が向上する。   According to this invention, the load borne by the intermediate pillar to be removed is bypassed by the load bypass means so as not to pass through the supported member installation site, and the intermediate pillar to be removed is cut in a safe state where no load is applied. Can do. Also, by confirming the transmission load of the load bypassing means while tensioning the cable, the support load by the load bypassing means can be gradually transferred to the cable, and the desired bearing force is applied to the cable before removing the intermediate column. Can be demonstrated. Therefore, the safety of the remodeling work is improved.

また、第3の発明は、第1または第2の発明に係る既存建物(1)の改造方法において、張設手段(21)を外側柱(2)における梁(5)との接合部よりも高い位置に設けたことを特徴とする。   Moreover, 3rd invention is a remodeling method of the existing building (1) which concerns on 1st or 2nd invention, and is provided with tension means (21) rather than the junction part with the beam (5) in an outer pillar (2). It is provided at a high position.

上記したように、被支持手段の設置位置を梁との接合部から下方に離すほど、ケーブルのライズがとれるようになって梁の曲げ応力を小さくすることができるが、被支持手段が梁よりも下方に突出するほどその階の最低天井高が小さくなる。この発明によれば、被支持手段の設置位置を下げるのではなく、逆に張設手段を梁との接合部よりも高い位置に移すことでケーブルのライズを確保し、下方に形成される空間の最低天井高を大きくして空間の有効利用を図ることができる。   As described above, the farther the installation position of the supported means is from the joint with the beam, the more the cable rises and the bending stress of the beam can be reduced. The lower the ceiling is, the lower the minimum ceiling height is. According to this invention, instead of lowering the installation position of the supported means, conversely, the tensioning means is moved to a position higher than the joint portion with the beam to ensure the rise of the cable, and the space formed below The minimum ceiling height can be increased for effective use of the space.

また、第4の発明は、第1〜第3のいずれかの発明に係る既存建物(1)の改造方法において、既存建物(1)は、複数層の梁(4,5)を有する多層建物であり、ケーブル(17)に被支持手段(13)を支持させる前に、中間柱(3)における被支持手段(13)よりも低い位置に接合する梁(4)の一対の外側柱(2)に対する縁を切るステップと、ケーブル(17)に被支持手段(13)を支持させた後に、一対の外側柱(2)に対する縁が切られた梁(4)を撤去するステップとを更に有することを特徴とする。   The fourth invention is a method of remodeling an existing building (1) according to any one of the first to third inventions, wherein the existing building (1) is a multi-layer building having a plurality of beams (4, 5). Before the supported means (13) is supported by the cable (17), the pair of outer pillars (2) of the beam (4) joined at a position lower than the supported means (13) in the intermediate pillar (3) ) And a step of removing the edge-cut beam (4) with respect to the pair of outer pillars (2) after the cable (17) supports the supported means (13). It is characterized by that.

この発明によれば、梁或いはこれと共に床を複数層有する多層建物において、中間柱だけでなく、ケーブルで補強された梁の下方に位置する梁(或いは梁および床)をも撤去する場合に、ケーブルに被支持手段を支持させると、その緊張力によって外側柱に応力が発生し、その影響で下側の梁と外側柱との接合部および下側の梁にも応力が発生するため、複雑な応力計算が必要になるだけでなく、応力が発生した危険な状態で下側の梁を切断する必要が生じるが、ケーブルに被支持手段を支持させる前に下側の梁と外側柱との縁を切っておくことで、このような応力の発生しない安全な状態で下側の梁を切断することができる。したがって、梁の撤去作業の安全性を確保できるとともに、応力計算も簡単になり施工計画も容易である。また、下側の梁(或いは梁および床)を撤去することで、階高の大きな空間を提供できるだけでなく、既存建物自体の荷重が小さくなるため、地震耐力の向上或いは、外側柱を補強する必要がある場合にはその補強規模の低減を図ることができる。   According to the present invention, when removing a beam (or a beam and a floor) located below a beam reinforced with a cable as well as an intermediate pillar in a multi-layer building having a plurality of layers with a beam or a floor together with the beam, When the cable supports the supported means, stress is generated in the outer column due to the tension, and stress is also generated in the joint between the lower beam and the outer column and the lower beam. In addition to the need to calculate the stress, it is necessary to cut the lower beam in a dangerous state where stress has occurred, but before supporting the supported means on the cable, the lower beam and the outer column By cutting the edge, the lower beam can be cut in a safe state in which such stress does not occur. Therefore, the safety of the beam removal work can be ensured, the stress calculation is simplified, and the construction plan is easy. Also, by removing the lower beams (or beams and floors), not only can the space of large floors be provided, but the load on the existing building itself is reduced, so the earthquake resistance is improved or the outer pillars are reinforced. When necessary, the scale of reinforcement can be reduced.

このように本発明によれば、ケーブルの本数或いは緊張力を低減し、容易に作業できるとともに、大スパンの大梁にも適用可能な中間柱を撤去する既存建物の改造方法を提供することができる。   As described above, according to the present invention, it is possible to provide a method for remodeling an existing building that reduces the number of cables or tension, can be easily operated, and removes an intermediate column that can be applied to a large span large beam. .

第1実施形態に係る既存建物の改造前の概略断面図Schematic sectional view before remodeling of an existing building according to the first embodiment 第1実施形態に係る既存建物の改造後の概略断面図Schematic sectional view after remodeling of an existing building according to the first embodiment 第1実施形態に係る既存建物の改造手順を示す説明図Explanatory drawing which shows the remodeling procedure of the existing building which concerns on 1st Embodiment 第1実施形態に係る既存建物の改造手順を示す説明図Explanatory drawing which shows the remodeling procedure of the existing building which concerns on 1st Embodiment 第2実施形態に係る既存建物の改造手順を示す説明図Explanatory drawing which shows the remodeling procedure of the existing building which concerns on 2nd Embodiment 第2実施形態に係る既存建物の改造手順を示す説明図Explanatory drawing which shows the remodeling procedure of the existing building which concerns on 2nd Embodiment 第3実施形態に係る既存建物の概略断面図Schematic sectional view of an existing building according to the third embodiment 第3実施形態に係る既存建物の要部平面図The principal part top view of the existing building which concerns on 3rd Embodiment

以下、本発明の実施の形態を、図面を参照しながら説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

≪第1実施形態≫
図1に示すように、第1実施形態に係る改造前の既存建物1は、鉄骨造2階建ての工場であり、建物外周に配置された一対の外周柱2と、外周柱2間に等間隔且つ一列に配置された2本の中間柱3と、これら柱2,3をその中間高さ位置において水平且つ直線状に連結する中間梁4と、これら柱2,3の上端部を平面視で直線状に連結する上梁5とをその一断面に有している。既存建物1は、水平な地盤G上に構築され、2本の外周柱2および2本の中間柱3はそれぞれ同一地上長さとされ、且つ外周柱2の地上長さが中間柱3の地上長さよりも幾分短くされている。したがって、上梁5は、中間柱3同士を連結する部位では水平に延在するが、中間柱3と外周柱2とを連結する部位では外周柱2に向かって下り勾配の傾斜状態に延在している。なお、中間梁4上にはスラブ6(図3参照)が構築され、上梁5上には屋根(図示省略)が架設され、外周柱2には既存建物1の外周に沿う外壁(図示省略)が接続されている。
<< First Embodiment >>
As shown in FIG. 1, the existing building 1 before remodeling according to the first embodiment is a steel-framed two-story factory, and a pair of outer peripheral columns 2 disposed on the outer periphery of the building, between the outer peripheral columns 2 and the like. Two intermediate pillars 3 arranged at intervals and in a row, an intermediate beam 4 connecting the pillars 2 and 3 horizontally and linearly at the intermediate height position, and the upper ends of the pillars 2 and 3 in plan view And the upper beam 5 connected in a straight line. The existing building 1 is constructed on a horizontal ground G, the two outer pillars 2 and the two intermediate pillars 3 have the same ground length, and the ground length of the outer pillar 2 is the ground length of the intermediate pillar 3. Somewhat shorter than that. Therefore, the upper beam 5 extends horizontally at a portion where the intermediate columns 3 are connected to each other, but extends at a downward slope toward the outer peripheral column 2 at a portion where the intermediate columns 3 and the outer peripheral column 2 are connected. is doing. A slab 6 (see FIG. 3) is constructed on the intermediate beam 4, a roof (not shown) is installed on the upper beam 5, and an outer wall (not shown) along the outer periphery of the existing building 1 is provided on the outer column 2. ) Is connected.

図2に示すように、改造後の既存建物1は、2階部分のスラブ6(図3参照)を支持する中間梁4が撤去されるとともに2本の中間柱3(図1参照)が撤去され、外周柱2(およびこれに接続する図示しない外壁)および上梁5(およびこれに接続する図示しない屋根)によって画成された1つの大きな空間が形成されている。なお、詳細は後に説明するが、2本の中間柱3は、上梁5が接合する接合部およびその下方に延出する延出部(以下、総称して頭部3aと称する)がそれぞれ存置されている。そして、各頭部3aの最下部にケーブル17による支持に供される被支持ブロック13が取り付けられるとともに、各外周柱2の最上部にケーブル17を張設するための張設ブロック16が取り付けられ、両張設ブロック16間に架け渡されたケーブル17が被支持ブロック13を支持している。   As shown in FIG. 2, in the existing building 1 after remodeling, the intermediate beam 4 supporting the slab 6 (see FIG. 3) on the second floor is removed and the two intermediate pillars 3 (see FIG. 1) are removed. Thus, one large space defined by the outer peripheral column 2 (and an outer wall (not shown) connected thereto) and the upper beam 5 (and a roof (not shown) connected thereto) is formed. Although the details will be described later, the two intermediate pillars 3 each have a joint portion to which the upper beam 5 is joined and an extension portion (hereinafter collectively referred to as a head portion 3a) extending below the joint portion. Has been. A supported block 13 to be supported by the cable 17 is attached to the lowermost part of each head 3a, and a tension block 16 for tensioning the cable 17 is attached to the uppermost part of each outer peripheral column 2. The cable 17 spanned between the two stretched blocks 16 supports the supported block 13.

次に、図3および図4を参照しながら本実施形態に係る既存建物1の改造方法について説明する。先ず、図3(A)に示すように、地盤G上の外周柱2の近傍に仮柱11を建て込んで中間梁4を支持させる。具体的には、仮柱11に、撤去する中間梁4の建物外側の切断部近傍を支持させる。   Next, a method for remodeling the existing building 1 according to the present embodiment will be described with reference to FIGS. 3 and 4. First, as shown in FIG. 3A, the temporary column 11 is built in the vicinity of the outer peripheral column 2 on the ground G to support the intermediate beam 4. Specifically, the temporary column 11 supports the vicinity of the cut portion outside the building of the intermediate beam 4 to be removed.

次に、(B)に示すように、外周柱2を適宜な補強部材12を用いて補強するとともに、撤去する各中間柱3に対し、頭部3aの最下部に被支持ブロック13を取り付ける。なお、補強部材12は、中間柱3の撤去により増大する支持荷重を外周柱2が支持し得るようにするものであれば如何なる形態でもよい。なお、図示は省略するが、本実施形態では補強部材12は、スラブ6の一部を撤去した後に、外周柱2の基礎と中間梁4との間および、中間梁4と上梁5との間の2箇所にI型鋼からなる補強柱を設置し、この補強柱を外周柱2、中間梁4および上梁5にそれぞれ接合するとともに、I型鋼からなる中間梁4のフランジ間に連結板を溶接して上下両補強柱のフランジを連結している。一方、被支持ブロック13は、H型鋼からなる中間柱3を挟み込む一対の鋼製の部材からなり、各部材は断面円形の貫通孔或いは下方に開口する溝等、ケーブル17を挿通或いは受容してケーブル17による上方向への荷重を受ける荷重受け部を備え、通しボルトによって中間柱3に摩擦接合される。   Next, as shown in (B), the outer peripheral column 2 is reinforced with an appropriate reinforcing member 12, and a supported block 13 is attached to the lowermost portion of the head 3a for each intermediate column 3 to be removed. The reinforcing member 12 may have any form as long as the outer peripheral column 2 can support the supporting load that is increased by removing the intermediate column 3. In addition, although illustration is abbreviate | omitted, in this embodiment, after removing a part of slab 6, the reinforcement member 12 is between the foundation of the outer periphery column 2, the intermediate beam 4, and the intermediate beam 4 and the upper beam 5. Reinforcing columns made of I-shaped steel are installed at two locations in between, and these reinforcing columns are joined to the outer peripheral column 2, the intermediate beam 4 and the upper beam 5, respectively, and a connecting plate is provided between the flanges of the intermediate beam 4 made of I-shaped steel. The flanges of the upper and lower reinforcing columns are connected by welding. On the other hand, the supported block 13 is composed of a pair of steel members sandwiching the intermediate pillar 3 made of H-shaped steel, and each member inserts or receives the cable 17 such as a through hole having a circular cross section or a groove opening downward. A load receiving portion that receives an upward load by the cable 17 is provided, and is frictionally joined to the intermediate column 3 by a through bolt.

次に、(C)に示すように、中間梁4の外周柱2との縁を切る、即ち中間梁4を補強部材12の建物内側の面に沿って切断して中間柱3側の部位と外周柱2の一部となった端部とに分割する。また、中間梁4に支持されたスラブ6上に、支持荷重可変手段としての油圧ジャッキ15が組み込まれ、被支持ブロック13を仮支持するための仮支持架台14を設置した上で、油圧ジャッキ15を駆動してその支持荷重を増大させて中間柱3における被支持ブロック13設置部位に伝達する荷重、即ち中間柱3が支持する上梁5や屋根等の荷重並びに、中間柱3の頭部3aおよび被支持ブロック13の荷重を支持させる。なお、仮支持架台14は、中間柱3の被支持ブロック13設置部位に伝達する荷重を、後に切断する頭部3aの下端部に伝達させることなく迂回させ、中間梁4、即ち被支持ブロック13の直下の梁に伝達するものである。迂回した荷重はその殆どが中間梁4を介して元の中間柱3に再び伝達する。   Next, as shown in (C), the edge of the intermediate beam 4 with the outer peripheral column 2 is cut, that is, the intermediate beam 4 is cut along the surface of the reinforcing member 12 on the inner side of the building, It divides | segments into the edge part which became a part of outer periphery pillar 2. FIG. In addition, a hydraulic jack 15 as a support load variable means is incorporated on the slab 6 supported by the intermediate beam 4 and a temporary support base 14 for temporarily supporting the supported block 13 is installed. To increase the support load and transmit the load to the support block 13 installation site in the intermediate column 3, that is, the load on the upper beam 5 and the roof supported by the intermediate column 3, and the head 3a of the intermediate column 3 The load of the supported block 13 is supported. The temporary support base 14 bypasses the load transmitted to the support block 13 installation site of the intermediate column 3 without transmitting it to the lower end of the head 3a to be cut later, so that the intermediate beam 4, that is, the supported block 13 is bypassed. It is transmitted to the beam immediately below. Most of the detoured load is transmitted again to the original intermediate column 3 via the intermediate beam 4.

そして、図4(D)に示すように、両外周柱2の上端部建物外側にケーブル17を張設するための張設ブロック16をそれぞれ接合する。なお、張設ブロック16は、被支持ブロック13よりも高い位置に設置される。その後、ケーブル17を、被支持ブロック13の荷重受け部を通るように両張設ブロック16間に架け渡す。なお、本実施形態では、ケーブル17は被支持ブロック13に対応して2本架設されるが、2本に限定されないことは言うまでもない。そして、ポストテンション用ジャッキ等、適宜な緊張具を用いてケーブル17に引張力を加える。この際、仮支持架台14が支持する荷重を計測する手段として油圧ジャッキ15に設けられた油圧計で支持荷重を確認しながらその値が略0になるまでケーブル17の引張力を徐々に上げてゆく。そして、仮支持架台14による支持荷重が略0になった状態、即ち被支持ブロック13に伝達する全荷重がケーブル17によって支持された状態で、張設ブロック16にケーブル17を保持させる。なお、張設ブロック16によるケーブル17の保持は、楔状の定着具等を用いることで容易且つ確実に行うことができる。   And as shown in FIG.4 (D), the extending | stretching block 16 for extending the cable 17 is joined to the outer side of the upper end part building of both the outer periphery pillars 2, respectively. The tension block 16 is installed at a position higher than the supported block 13. Thereafter, the cable 17 is bridged between the two stretched blocks 16 so as to pass through the load receiving portion of the supported block 13. In the present embodiment, two cables 17 are installed corresponding to the supported block 13, but it goes without saying that the number is not limited to two. Then, a tensile force is applied to the cable 17 using an appropriate tension tool such as a post tension jack. At this time, the tensile force of the cable 17 is gradually increased until the value becomes substantially zero while confirming the supporting load with a hydraulic gauge provided in the hydraulic jack 15 as means for measuring the load supported by the temporary support base 14. go. Then, the cable 17 is held by the tension block 16 in a state where the support load by the temporary support base 14 becomes substantially zero, that is, in a state where the total load transmitted to the supported block 13 is supported by the cable 17. The cable 17 can be held by the tension block 16 easily and reliably by using a wedge-shaped fixing tool or the like.

次に、(E)に示すように、中間柱3を頭部3aの下端、即ち被支持ブロック13の下端面に沿って切断する。なお、この状態では、中間柱3の切断部位の応力(特に鉛直荷重による圧縮応力)は実質的に0になっているため、切断作業を安全に行うことができる。中間柱3を切断して頭部3aとそれ以外の下側部位とに分割した後、中間柱3の2階部分を撤去するとともに、仮支持架台14を撤去する。   Next, as shown in (E), the intermediate column 3 is cut along the lower end of the head 3 a, that is, the lower end surface of the supported block 13. In this state, since the stress (particularly the compressive stress due to the vertical load) at the cutting portion of the intermediate column 3 is substantially zero, the cutting operation can be performed safely. After the intermediate pillar 3 is cut and divided into the head 3a and the other lower part, the second floor portion of the intermediate pillar 3 is removed and the temporary support base 14 is removed.

最後に、2階のスラブ6、中間梁4、中間柱3の1階部分および仮柱11を撤去して、2階部分の中間梁4および2本の中間柱3を撤去する改造が完了する。   Finally, the slab 6 on the second floor, the intermediate beam 4, the first floor portion of the intermediate pillar 3 and the temporary pillar 11 are removed, and the modification for removing the intermediate beam 4 and the two intermediate pillars 3 on the second floor is completed. .

このように、頭部3aの下端に被支持ブロック13を設けることにより、張設ブロック16が被支持ブロック13よりも高い位置に配置され、ケーブル17のライズを大きくとることができるようになり、比較的小さな引張力で上梁5の曲げ応力を大幅に低減可能となっている。   Thus, by providing the supported block 13 at the lower end of the head 3a, the tensioning block 16 is arranged at a higher position than the supported block 13, and the rise of the cable 17 can be increased. The bending stress of the upper beam 5 can be greatly reduced with a relatively small tensile force.

また、上記実施形態のように、中間柱3を2本撤去して3スパン分の上梁5を1スパンにする場合、従来のプレストレスを加える技術では不可能なこともあり得たが、頭部3aの長さ(束の長さ)を調整することで同じ引張力でもケーブル17による支持力を大きくすることが可能であるため、本発明によれば中間柱3を撤去する改造方法の適用範囲が格段に広がる。   Further, as in the above embodiment, when two intermediate pillars 3 are removed and the upper beam 5 for three spans is set to one span, it may not be possible with a conventional prestressing technique. By adjusting the length of the head 3a (the length of the bundle), it is possible to increase the support force by the cable 17 even with the same tensile force. Therefore, according to the present invention, a modification method for removing the intermediate column 3 is possible. The scope of application is greatly expanded.

また、撤去する中間柱3が負担する支持荷重を一旦仮支持架台14に支持させ、ケーブル17の引張力を徐々に高めて支持荷重を仮支持架台14からケーブル17に移行させ、油圧ジャッキ15の支持荷重を油圧計で確認することで、ケーブル17に所期の支持力を発揮させることができ、中間柱3の撤去すべき下側部位に鉛直荷重が加わってない安全な状態で中間柱3を切断することができる。したがって、中間柱3の撤去作業を安全に行うことができる。なお、本実施形態では、先ず頭部3aの下端で中間柱3を切断しているが、中間柱3の切断は中間柱3の撤去すべき下側部位のいずれの位置で行ってもよい。   Further, the support load borne by the intermediate pillar 3 to be removed is temporarily supported by the temporary support base 14, the tensile force of the cable 17 is gradually increased, and the support load is transferred from the temporary support base 14 to the cable 17. By confirming the supporting load with a hydraulic gauge, the cable 17 can exert the desired supporting force, and the intermediate column 3 can be safely removed with no vertical load applied to the lower portion of the intermediate column 3 to be removed. Can be cut off. Therefore, the removal work of the intermediate pillar 3 can be performed safely. In the present embodiment, the intermediate column 3 is first cut at the lower end of the head 3a. However, the intermediate column 3 may be cut at any position on the lower part of the intermediate column 3 to be removed.

そして、2階スラブ6を支持する中間梁4をも撤去する上記実施形態では、ケーブル17に被支持ブロック13を支持させると、その応力変化によって外周柱2にも応力が発生し、その影響で中間梁4と外周柱2との接合部および中間梁4にも応力が発生するため、複雑な応力計算が必要になるが、ケーブル17に被支持ブロック13を支持させる前に中間梁4と外周柱2との縁を切っておくことで、このような応力のない安全な状態で中間梁4を切断することができる。したがって、中間梁4の撤去作業を安全に行うことができるとともに、応力計算も簡単になり施工計画も容易である。   And in the said embodiment which also removes the intermediate beam 4 which supports the 2nd floor slab 6, when the supported block 13 is supported by the cable 17, the stress is also generated in the outer peripheral column 2 due to the change in the stress. Since stress is also generated at the joint between the intermediate beam 4 and the outer peripheral column 2 and the intermediate beam 4, complicated stress calculation is required. Before the cable 17 supports the supported block 13, the intermediate beam 4 and the outer periphery By cutting the edge with the column 2, the intermediate beam 4 can be cut in a safe state without such stress. Therefore, the removal work of the intermediate beam 4 can be performed safely, the stress calculation is simplified, and the construction plan is easy.

≪第2実施形態≫
次に、本発明に係る第2実施形態について図5および図6を参照しながら説明する。なお、図5(A)、図6(F)に示す手順は、第1実施形態の図3(A)、図4(F)を参照した手順と同一であるため、説明を省略する。重複する詳細な説明も省略し、第1実施形態と同一の部材には同一の符号を付す。
<< Second Embodiment >>
Next, a second embodiment according to the present invention will be described with reference to FIGS. The procedures shown in FIGS. 5A and 6F are the same as the procedures referring to FIGS. 3A and 4F of the first embodiment, and thus the description thereof is omitted. The detailed description which overlaps is also abbreviate | omitted and the same code | symbol is attached | subjected to the member same as 1st Embodiment.

本実施形態では、図5(B)に示すように、外周柱2を適宜な補強部材12を用いて補強するとともに、撤去する各中間柱3に対し、頭部3aと下側撤去部位との境界を上下に跨ぐように仮支持ピース18を取り付ける。本実施形態の仮支持ピース18は、略コ字状を呈する一対の鋼材であり、被支持ブロック13の取り付けに支障を来さない範囲で可能な限り上下寸法が小さくされており、その上端部および下端部が中間柱3に溶接される。そして、仮支持ピース18は、後述するように、上端部で受けた中間柱3の荷重を迂回させて下端部で再び中間柱3に伝達する荷重迂回機能を果たす。   In this embodiment, as shown in FIG. 5 (B), the outer peripheral column 2 is reinforced with an appropriate reinforcing member 12, and the head 3a and the lower removal site are separated from each intermediate column 3 to be removed. The temporary support piece 18 is attached so as to straddle the boundary up and down. The temporary support piece 18 of the present embodiment is a pair of steel materials exhibiting a substantially U-shape, and the vertical dimension is made as small as possible within a range that does not hinder the attachment of the supported block 13, and its upper end portion. And a lower end part is welded to the intermediate | middle pillar 3. FIG. And the temporary support piece 18 fulfill | performs the load detouring function which detours the load of the intermediate pillar 3 received by the upper end part, and transmits to the intermediate pillar 3 again by a lower end part so that it may mention later.

その後、(C)に示すように、中間梁4の外周柱2との縁を切る。また、中間柱3を頭部3aの下端部で切断するとともに、頭部3aの最下部に被支持ブロック13を取り付ける。中間柱3を切断する際には、仮支持ピース18が中間柱3の荷重を迂回させておらず、切断部に上梁5等の荷重による圧縮応力が発生しているが、仮支持ピース18はその上下寸法が小さいため、荷重印加に伴う圧縮歪みが非常に小さくなる。したがって、中間柱3の切断作業の進行に伴って中間柱3を伝達する荷重が徐々に仮支持ピース18に加わり、中間柱3の切断完了時に中間柱3の全ての荷重が仮支持ピース18に伝達し(迂回し)、伝達荷重の全てが仮支持ピース18の下端部から再び中間柱3に伝達する。即ち、中間柱3を切断する作業が仮支持ピース18に伝達荷重を迂回させる作業となる。   Thereafter, as shown in (C), the edge of the intermediate beam 4 with the outer peripheral column 2 is cut. Further, the intermediate column 3 is cut at the lower end portion of the head portion 3a, and the supported block 13 is attached to the lowermost portion of the head portion 3a. When cutting the intermediate column 3, the temporary support piece 18 does not bypass the load of the intermediate column 3, and compressive stress due to the load of the upper beam 5 or the like is generated in the cut portion. Since the vertical dimension is small, the compressive strain accompanying the load application is very small. Therefore, as the cutting work of the intermediate column 3 proceeds, a load that transmits the intermediate column 3 is gradually applied to the temporary support piece 18, and all the loads of the intermediate column 3 are applied to the temporary support piece 18 when the cutting of the intermediate column 3 is completed. All the transmission load is transmitted from the lower end portion of the temporary support piece 18 to the intermediate column 3 again. That is, the work of cutting the intermediate pillar 3 is the work of bypassing the transmission load to the temporary support piece 18.

そして、図6(D)に示すように、両外周柱2の上端部建物外側に張設ブロック16をそれぞれ接合し、ケーブル17を、被支持ブロック13の荷重受け部を通るように両張設ブロック16間に架け渡す。そして、適宜な緊張具を用いてケーブル17に引張力を加え、中間柱3における被支持ブロック13設置部位に伝達する全荷重をケーブル17に支持させた状態で、張設ブロック16にケーブル17を保持させる。なお、仮支持ピース18を迂回する中間柱3の全荷重がケーブル17に支持されたか否かを判断するために、仮支持ピース18を中間柱3に溶接した後に、伝達荷重を計測する手段としての歪み形を仮支持ピース18の鉛直部に設け、中間柱3切断前の歪み量になったことを確認してもよい。   Then, as shown in FIG. 6D, the extension block 16 is joined to the outside of the upper end building of both outer peripheral pillars 2, and the cable 17 is extended to pass through the load receiving part of the supported block 13. It is bridged between the blocks 16. Then, a tension force is applied to the cable 17 using an appropriate tension tool, and the cable 17 is supported on the tensioning block 16 in a state where the total load transmitted to the supported block 13 installation site in the intermediate pillar 3 is supported by the cable 17. Hold. As a means for measuring the transmission load after welding the temporary support piece 18 to the intermediate column 3 in order to determine whether or not the entire load of the intermediate column 3 bypassing the temporary support piece 18 is supported by the cable 17. May be provided in the vertical portion of the temporary support piece 18 to confirm that the amount of distortion before cutting the intermediate column 3 is reached.

その後、(E)に示すように、仮支持ピース18を撤去し、最後に(F)に示すように、中間柱3の2階部分を撤去するとともに、2階のスラブ6、中間梁4、中間柱3の1階部分および仮柱11を撤去して、2階部分の中間梁4および2本の中間柱3を撤去する改造が完了する。   Thereafter, as shown in (E), the temporary support piece 18 is removed, and finally, as shown in (F), the second floor portion of the intermediate pillar 3 is removed and the slab 6 on the second floor, the intermediate beam 4, The remodeling of removing the first floor portion of the intermediate pillar 3 and the temporary pillar 11 and removing the intermediate beam 4 and the two intermediate pillars 3 of the second floor portion is completed.

なお、本実施形態では、仮支持ピース18を鋼材のみで構成しているが、設置時に鉛直に延在する中間部分に第1実施形態と同様に油圧ジャッキを設けてもよい。   In addition, in this embodiment, although the temporary support piece 18 is comprised only with steel materials, you may provide a hydraulic jack similarly to 1st Embodiment in the intermediate part extended perpendicularly | vertically at the time of installation.

≪第3実施形態≫
次に、本発明に係る第3実施形態について図7および図8を参照しながら説明する。なお、第1実施形態と重複する手順についての説明は省略し、第1実施形態と異なる点についてのみ説明する。また、第1実施形態と同一の部材には同一の符号を付している。
<< Third Embodiment >>
Next, a third embodiment according to the present invention will be described with reference to FIGS. In addition, description about the procedure which overlaps with 1st Embodiment is abbreviate | omitted, and only a different point from 1st Embodiment is demonstrated. The same members as those in the first embodiment are denoted by the same reference numerals.

本実施形態で第1実施形態と異なる点は、張設ブロック21の設置位置および形状である。第1実施形態の張設ブロック16は、外周柱2の上端部、即ち外周柱2における上梁5との接合部に設置されている。これは、ケーブル17の引張荷重が外周柱2に作用するため、上梁5との接合から離れた位置に張設ブロック16が設置されると、ケーブル17の引張力が外周柱に大きな曲げモーメントとして作用するからである。一方、張設ブロック16は、ケーブル17のライズを大きくする観点からは可能な限り高い位置に設けられることが望まれる。そのため、第1実施形態では、外周柱2に曲げ応力が作用しないようにし且つケーブル17のライズを確保するためには、中間柱3の頭部3aを長く(束を大きく)する必要があった。   The present embodiment is different from the first embodiment in the installation position and shape of the tension block 21. The tension block 16 of the first embodiment is installed at the upper end portion of the outer peripheral column 2, that is, at the joint portion with the upper beam 5 in the outer peripheral column 2. This is because, since the tensile load of the cable 17 acts on the outer peripheral column 2, if the tension block 16 is installed at a position away from the joint with the upper beam 5, the tensile force of the cable 17 causes a large bending moment on the outer peripheral column. Because it acts as. On the other hand, from the viewpoint of increasing the rise of the cable 17, it is desirable that the tension block 16 be provided at a position as high as possible. Therefore, in the first embodiment, in order to prevent bending stress from acting on the outer peripheral column 2 and to ensure the rise of the cable 17, it is necessary to lengthen the head 3a of the intermediate column 3 (make the bundle larger). .

そこで、本実施形態では、張設ブロック21を外周柱2における上梁5との接合部よりも高い位置に設けている。これにより、中間柱3の頭部3aを短く(束を小さく)する或いは、ケーブル引張力に対する梁の曲げ応力低減量を大きくすることができる。そして、外周柱2の上方に延出するように設けられた張設ブロック21は、ケーブル17の引張力に耐え得るように、ケーブル17の延在方向に長い形状とされ、外周柱2から張り出した部位が上梁5に荷重を伝達するようになっている。   Therefore, in this embodiment, the extending block 21 is provided at a position higher than the joint portion of the outer peripheral column 2 with the upper beam 5. Thereby, the head 3a of the intermediate column 3 can be shortened (the bundle is reduced), or the bending stress reduction amount of the beam with respect to the cable pulling force can be increased. The extending block 21 provided so as to extend above the outer peripheral column 2 has a long shape in the extending direction of the cable 17 so as to withstand the tensile force of the cable 17 and extends from the outer peripheral column 2. The part that transmits the load is transmitted to the upper beam 5.

また、図8に示すように、中間柱3を挟むように配置された2本のケーブル17は、中間柱3間では平行に延在し、中間柱3と外周柱2との間では、平面視で外周柱2に向かって開くように延在している。これにより、2本のケーブル17は、上梁5に対して上下方向の曲げ応力を低減するだけでなく、水平方向のたわみを抑制するようになっている。   In addition, as shown in FIG. 8, the two cables 17 arranged so as to sandwich the intermediate pillar 3 extend in parallel between the intermediate pillars 3, and are flat between the intermediate pillar 3 and the outer peripheral pillar 2. It extends so as to open toward the outer peripheral column 2 in view. Thereby, the two cables 17 not only reduce the bending stress in the vertical direction with respect to the upper beam 5 but also suppress the deflection in the horizontal direction.

以上で具体的実施形態についての説明を終えるが、本発明はこれらの実施形態に限定されるものではない。例えば、上記実施形態では、2階建ての既存建物について本発明を適用したが、1階建てや3階建て以上の既存建物についても適用可能である。なお、既存建物が3階建て以上であり、2階よりも上の中間梁およびスラブを全て撤去するとともに、中間柱も全階にわたって撤去する場合には、以下のような撤去方法を採ればよい。即ち、中間柱3が撤去される梁(上梁5、中間梁4)ごとに、被支持ブロック13と張設ブロック16または21とを設けてケーブル17を架設する。そして、仮支持架台14または仮支持ピース18を設けて中間柱3を支持させ、ケーブル17に被支持ブロック13を支持させた状態で中間柱3における被支持ブロック13よりも下側の部位を撤去する作業を、上層階から下層階へ向けて繰り返し行う。このように、上層階から順に中間柱を撤去することで、荷重迂回手段を、第1実施形態に示した被支持ブロック13の直下の中間梁4に荷重を伝達する仮支持架台14、または第2実施形態に示した中間柱3における被支持ブロック13が設けられた部位よりも下側の部位に荷重を伝達する仮支持ピース18のような簡易な構成とし、2階よりも上の中間梁4およびスラブ6の全て、および全階にわたる中間柱3を撤去することができる。また、複数層の梁を有する既存建物において、1層おきに梁を撤去したり、3層ごとに2層ずつ梁を撤去したりする形態等も可能である。   This is the end of the description of specific embodiments, but the present invention is not limited to these embodiments. For example, in the above-described embodiment, the present invention is applied to an existing building having two floors. However, the present invention can also be applied to an existing building having one or three floors. In addition, when the existing building is more than 3 stories and all intermediate beams and slabs above the 2nd floor are removed, and the intermediate pillars are also removed on all floors, the following removal method may be adopted. . That is, for each beam (upper beam 5 and intermediate beam 4) from which the intermediate column 3 is removed, the supported block 13 and the extending block 16 or 21 are provided and the cable 17 is installed. Then, the temporary support base 14 or the temporary support piece 18 is provided to support the intermediate column 3, and the portion below the supported block 13 in the intermediate column 3 is removed in a state where the supported block 13 is supported by the cable 17. Repeat the work from the upper floor to the lower floor. In this way, by removing the intermediate pillars in order from the upper floor, the load bypass means can be used as the temporary support base 14 for transmitting the load to the intermediate beam 4 directly below the supported block 13 shown in the first embodiment, or The intermediate beam above the second floor has a simple configuration such as a temporary support piece 18 that transmits a load to a portion below the portion where the supported block 13 is provided in the intermediate pillar 3 shown in the second embodiment. 4 and all of the slabs 6 and the intermediate pillar 3 over the entire floor can be removed. Further, in an existing building having a plurality of layers of beams, it is possible to remove the beams every other layer, or to remove the beams by every two layers.

また、上記実施形態では、一断面に2本の中間柱がある既存建物について本発明を適用したが、中間柱が1本または3本以上ある既存建物についても当然に適用可能である。なお、中間柱が一断面に複数本ある既存建物にあっては、全ての中間柱を撤去する形態も可能であるが、そのうちの数本のみを撤去する形態、例えば、2本あるうちの1本のみ撤去する形態や、5本あるうち、中央の1本を残して他の4本を撤去する形態等も可能である。この場合、撤去する中間柱に隣接する中間柱が本発明で云う外側柱に相当する。更に、上記実施形態では、中間柱を撤去する方法に関し、既存建物の一断面について説明したが、中間柱3が複数列ある場合には、各列に対して上記手順で作業を施せばよい。また、上記実施形態は、ケーブルを1方向にのみ張設する形態であるが、ケーブルを直交する2方向に張設することも可能である。   Moreover, in the said embodiment, although this invention was applied to the existing building which has two intermediate pillars in one cross section, naturally it is applicable also to the existing building which has one or more intermediate pillars. In the case of an existing building having a plurality of intermediate pillars in one section, it is possible to remove all the intermediate pillars. However, only a few of them are removed, for example, one of the two. A form in which only one book is removed or a form in which the other four are removed while leaving one in the center is also possible. In this case, the intermediate column adjacent to the intermediate column to be removed corresponds to the outer column in the present invention. Furthermore, although the said embodiment demonstrated the cross section of the existing building regarding the method of removing an intermediate pillar, when the intermediate pillar 3 has two or more rows, what is necessary is just to work in the said procedure with respect to each row. Moreover, although the said embodiment is a form which stretches a cable only to 1 direction, it is also possible to stretch a cable to 2 directions orthogonal.

また、上記実施形態では、荷重迂回手段として仮支持架台14または18を設置し、中間柱3の荷重を迂回させた後に中間柱3を切断したが、荷重迂回手段を設けることなく直ちにケーブル17で中間柱を支持し、被支持ブロック13よりも下方に伝達する荷重を十分小さくした上で中間柱3を切断してもよい。この場合にも、中間柱3における被支持ブロック13が設けられた位置よりも下方の位置に歪み計を設置する等して切断部の残留応力を推定するとよい。   In the above embodiment, the temporary support base 14 or 18 is installed as a load bypassing means, and the intermediate pillar 3 is cut after the load of the intermediate pillar 3 is bypassed. The intermediate column 3 may be cut after supporting the intermediate column and sufficiently reducing the load transmitted below the supported block 13. Also in this case, the residual stress of the cut portion may be estimated by installing a strain gauge at a position below the position where the supported block 13 is provided in the intermediate column 3.

また、上記実施形態では、ラーメン構造を有する鉄骨造の既存建物に本発明を適用したが、鉄筋コンクリート造または鉄骨鉄筋コンクリート造の既存建物についても適用可能である。これら変更の他、被支持手段や張設手段の具体的形状等、本発明の趣旨を逸脱しない範囲であれば適宜変更可能である。   Moreover, in the said embodiment, although this invention was applied to the existing building of the steel structure which has a ramen structure, it is applicable also to the existing building of a reinforced concrete structure or a steel frame reinforced concrete structure. In addition to these changes, the specific shapes of the supported means and the tensioning means can be appropriately changed as long as they do not depart from the spirit of the present invention.

1 既存建物
2 外周柱(外側柱)
3 中間柱
3a 頭部
4 中間梁
5 上梁
6 スラブ
11 仮柱
12 補強部材
13 被支持ブロック
14 仮支持架台(荷重迂回手段)
15 油圧ジャッキ
16 張設ブロック
17 ケーブル
18 仮支持ピース(荷重迂回手段)
21 張設ブロック
G 地盤
1 Existing building 2 Perimeter column (outside column)
3 Intermediate column 3a Head 4 Intermediate beam 5 Upper beam 6 Slab 11 Temporary column 12 Reinforcement member 13 Supported block 14 Temporary support frame (load bypass means)
15 Hydraulic jack 16 Tension block 17 Cable 18 Temporary support piece (load bypass means)
21 Tension Block G Ground

Claims (4)

中間柱と、該中間柱を平面視で挟む位置に配置され、それぞれ梁によって該中間柱と連結された一対の外側柱とを有する既存建物において、前記中間柱を撤去する改造方法であって、
前記中間柱における前記梁との接合部よりも低い位置にケーブルによる支持に供される被支持手段を設けるステップと、
前記一対の外側柱における前記被支持手段よりも高い位置にケーブルを張設するための張設手段をそれぞれ設けるステップと、
前記被支持手段を通るように前記一対の張設手段間にケーブルを架設するステップと、
前記張設手段に前記ケーブルを緊張状態で保持させ、該ケーブルに前記被支持手段を支持させるステップと、
前記ケーブルに前記被支持手段を支持させた状態で前記中間柱における前記被支持手段よりも下側の部位を撤去するステップと
を有することを特徴とする既存建物の改造方法。
In an existing building having an intermediate pillar and a pair of outer pillars arranged at positions sandwiching the intermediate pillar in plan view and connected to the intermediate pillar by beams, respectively, a modification method for removing the intermediate pillar,
Providing a supported means to be supported by a cable at a position lower than the joint with the beam in the intermediate column;
Providing a tensioning means for tensioning a cable at a position higher than the supported means in the pair of outer pillars;
Laying a cable between the pair of stretching means so as to pass through the supported means;
Causing the tensioning means to hold the cable in a tension state, and allowing the cable to support the supported means;
A method of remodeling an existing building, comprising a step of removing a portion of the intermediate pillar below the supported means in a state where the supported means is supported by the cable.
前記中間柱における前記被支持手段設置部位に荷重迂回手段を設けるステップと、
前記荷重迂回手段に、前記被支持手段設置部位に伝達する伝達荷重を迂回させるステップと、
前記荷重迂回手段に前記伝達荷重を迂回させた状態で、或いは前記荷重迂回手段に前記伝達荷重を迂回させつつ、前記被支持手段の下端近傍で前記中間柱を切断するステップとを、
前記ケーブルに前記被支持手段を支持させるステップの前に更に有することを特徴とする、請求項1に記載の既存建物の改造方法。
Providing a load bypass means at the supported means installation site in the intermediate column;
Diverting the load to be transmitted to the supported means installation site to the load bypass means;
Cutting the intermediate column in the vicinity of the lower end of the supported means while the load bypassing means bypasses the transmission load, or while the load bypassing means bypasses the transmission load;
The method for remodeling an existing building according to claim 1, further comprising a step of supporting the supported means on the cable.
前記張設手段を前記外側柱における前記梁との接合部よりも高い位置に設けたことを特徴とする、請求項1または請求項2に記載の既存建物の改造方法。   The method for remodeling an existing building according to claim 1, wherein the extension means is provided at a position higher than a joint portion of the outer column with the beam. 前記既存建物は、複数層の梁を有する多層建物であり、
前記ケーブルに前記被支持手段を支持させる前に、前記中間柱における前記被支持手段よりも低い位置に接合する梁の前記一対の外側柱に対する縁を切るステップと、
前記ケーブルに前記被支持手段を支持させた後に、前記一対の外側柱に対する縁が切られた梁を撤去するステップと
を更に有することを特徴とする、請求項1〜請求項3のいずれか一項に記載の既存建物の改造方法。
The existing building is a multi-layered building having a plurality of layers of beams,
Before supporting the supported means on the cable, cutting the edge of the beam that joins the intermediate pillar at a position lower than the supported means with respect to the pair of outer pillars;
The method further comprises a step of removing a beam having a cut edge with respect to the pair of outer pillars after the supported means is supported by the cable. Remodeling method of existing building as described in section.
JP2009189484A 2009-08-18 2009-08-18 Remodeling existing building Active JP5503223B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009189484A JP5503223B2 (en) 2009-08-18 2009-08-18 Remodeling existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009189484A JP5503223B2 (en) 2009-08-18 2009-08-18 Remodeling existing building

Publications (2)

Publication Number Publication Date
JP2011038381A true JP2011038381A (en) 2011-02-24
JP5503223B2 JP5503223B2 (en) 2014-05-28

Family

ID=43766407

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009189484A Active JP5503223B2 (en) 2009-08-18 2009-08-18 Remodeling existing building

Country Status (1)

Country Link
JP (1) JP5503223B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2525089C1 (en) * 2013-01-29 2014-08-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Казанский государственный архитектурно-строительный университет" КГАСУ Device to reinforce beam structures
JP2016050474A (en) * 2014-08-29 2016-04-11 鹿島建設株式会社 Reinforcement Frame
JP2018071289A (en) * 2016-11-02 2018-05-10 株式会社竹中工務店 Renovation method
JP2019070289A (en) * 2017-10-11 2019-05-09 株式会社竹中工務店 Repair method of existing structure
JP2021032040A (en) * 2019-08-29 2021-03-01 鹿島建設株式会社 Earthquake resistant reinforcement structure
CN115263013A (en) * 2022-07-19 2022-11-01 中冶检测认证有限公司 Industrial plant joist column cutting method and industrial plant joist structure
JP7363522B2 (en) 2020-01-27 2023-10-18 積水ハウス株式会社 beam reinforcement structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002106178A (en) * 2000-10-03 2002-04-10 Takenaka Komuten Co Ltd Building reconstructing method
JP2005232937A (en) * 2004-02-23 2005-09-02 Sumitomo Forestry Co Ltd Beam reinforcing structure and method of wooden building
JP3878900B2 (en) * 2002-10-10 2007-02-07 株式会社竹中工務店 Remodeling method to remove pillar of existing building
JP2007270546A (en) * 2006-03-31 2007-10-18 Nippon Steel Corp Building reinforcing structure and reinforcing method using shape memory alloy
JP2011006972A (en) * 2009-06-27 2011-01-13 Sumitomo Forestry Co Ltd Method of reinforcing beam in wooden building

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002106178A (en) * 2000-10-03 2002-04-10 Takenaka Komuten Co Ltd Building reconstructing method
JP3878900B2 (en) * 2002-10-10 2007-02-07 株式会社竹中工務店 Remodeling method to remove pillar of existing building
JP2005232937A (en) * 2004-02-23 2005-09-02 Sumitomo Forestry Co Ltd Beam reinforcing structure and method of wooden building
JP2007270546A (en) * 2006-03-31 2007-10-18 Nippon Steel Corp Building reinforcing structure and reinforcing method using shape memory alloy
JP2011006972A (en) * 2009-06-27 2011-01-13 Sumitomo Forestry Co Ltd Method of reinforcing beam in wooden building

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2525089C1 (en) * 2013-01-29 2014-08-10 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Казанский государственный архитектурно-строительный университет" КГАСУ Device to reinforce beam structures
JP2016050474A (en) * 2014-08-29 2016-04-11 鹿島建設株式会社 Reinforcement Frame
JP2018071289A (en) * 2016-11-02 2018-05-10 株式会社竹中工務店 Renovation method
JP2019070289A (en) * 2017-10-11 2019-05-09 株式会社竹中工務店 Repair method of existing structure
JP7020046B2 (en) 2017-10-11 2022-02-16 株式会社竹中工務店 How to repair existing structures
JP2021032040A (en) * 2019-08-29 2021-03-01 鹿島建設株式会社 Earthquake resistant reinforcement structure
JP7211915B2 (en) 2019-08-29 2023-01-24 鹿島建設株式会社 Seismic reinforcement structure
JP7363522B2 (en) 2020-01-27 2023-10-18 積水ハウス株式会社 beam reinforcement structure
CN115263013A (en) * 2022-07-19 2022-11-01 中冶检测认证有限公司 Industrial plant joist column cutting method and industrial plant joist structure
CN115263013B (en) * 2022-07-19 2024-03-01 中冶检测认证有限公司 Joist column cutting method and joist structure for industrial factory building

Also Published As

Publication number Publication date
JP5503223B2 (en) 2014-05-28

Similar Documents

Publication Publication Date Title
JP5503223B2 (en) Remodeling existing building
JP2007077630A (en) Continuous girder using precast main-girder segment, and its erection method
JP6111922B2 (en) Column base reinforcement method and apparatus
JP6147621B2 (en) Tower crane support structure and tower crane equipment
JP5192251B2 (en) Tower crane support structure and construction method thereof
JP7009724B2 (en) Column-beam frame repair method and repair column-beam frame
JP5131121B2 (en) Seismic reinforcement structure for columns and seismic reinforcement method
JP4996370B2 (en) Frame assembly method and building frame
JP5191191B2 (en) Extension construction method of extension building
JP6228836B2 (en) Reverse winding method
JP5017887B2 (en) Tower crane support structure, tower crane support method
JP2010255374A (en) Demolition method for skyscraper building
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JP6320242B2 (en) How to install temporary pillars
JP5645548B2 (en) Dismantling method, jack structure
JP4504747B2 (en) Building construction method using tower crane
JP7169765B2 (en) How to build structures
JP2018096163A (en) Method of constructing building
JP6529241B2 (en) Building foundation structure and construction method of building foundation structure
JP6752006B2 (en) Fixed structure of building unit and unit building
JP6504824B2 (en) Construction method of damping structure
JP6192286B2 (en) Evacuation building
JP2016017291A (en) Demolition method and demolition system
JP2019027279A (en) Vibration control structure
JP5502657B2 (en) Dismantling method, load transmission structure

Legal Events

Date Code Title Description
RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20110810

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120313

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130611

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130806

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140311

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140314

R150 Certificate of patent or registration of utility model

Ref document number: 5503223

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250