JP2007198100A - Caisson method combined with guide hole construction method for constructing underground structure - Google Patents
Caisson method combined with guide hole construction method for constructing underground structure Download PDFInfo
- Publication number
- JP2007198100A JP2007198100A JP2006041592A JP2006041592A JP2007198100A JP 2007198100 A JP2007198100 A JP 2007198100A JP 2006041592 A JP2006041592 A JP 2006041592A JP 2006041592 A JP2006041592 A JP 2006041592A JP 2007198100 A JP2007198100 A JP 2007198100A
- Authority
- JP
- Japan
- Prior art keywords
- construction method
- underground
- guide hole
- wall
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
本発明は、地下室を築造する際に山止めを必要とせず、予めの開削(掘削)をしないで、地下構造物の壁部分を先行して地上に築造し、内部を掘削しながら自重にて沈下させていく工事工法である。従来の開削工法に比べ、掘削土量が大幅に少なく、その分の工事費用が大幅に軽減できる利点があり、地下構造物本体の外側の土部を殆ど掘らないので、地山(元の土部)をいためる事がなく、地震時の揺れによる衝撃を和らげる効果もあり、工事範囲も少なくできる。
従来の潜函工法では、本体の沈下の際、傾いたり、位置のずれ、過沈下をきたす事が殆どであった。これを解決した地下構造物築造用ガイドホール工法併用潜函工事工法である。The present invention does not require a mountain stop when constructing a basement, does not perform excavation (excavation) in advance, constructs the wall portion of the underground structure on the ground first, and excavates the inside by its own weight It is a construction method that will sink. Compared to the conventional open-cut method, there is an advantage that the excavated soil volume is significantly smaller and the construction cost can be greatly reduced, and the soil outside the underground structure body is hardly dug. Part of the construction), and the effect of mitigating the shock caused by the shaking at the time of the earthquake is reduced.
In the conventional submersion method, when the main body sinks, it is mostly tilted, misaligned, or excessively subsidized. This is a submersible construction method combined with a guide hole construction method for building underground structures.
従来の潜函工法は、構造物の主たる壁を、地上に築造し壁の内側を重機による掘削と人力による補助的掘削と構造物の自重、及び掘削と合わせて構造物を下方向へ引っ張り込む事で地下の設置位置へ誘導沈埋せしめる工法が大半であるが、沈埋の過程での傾きや過沈下現象が発生することが殆どであった。修正は危険を伴う人力による方法がとられており、正確な位置への誘導が難しい現状がある。
このため、多少の傾きや過沈下での利用可能な防火用水槽や貯留水槽などに使われている工法である。In the conventional submersible construction method, the main wall of the structure is built on the ground, and the inside of the wall is pulled down by a heavy machine, auxiliary excavation by human power, the weight of the structure, and excavation. In most cases, however, the method of guided submergence to the underground installation position has caused tilting or excessive subsidence during the submergence process. The correction is performed by a dangerous human power method, and it is difficult to guide to an accurate position.
For this reason, it is a construction method that is used for fire prevention water tanks and storage water tanks that can be used when there is a slight inclination or excessive subsidence.
従来の潜函工事工法に於ける傾き、過沈下などの精度の悪さの欠陥を改良し、在来開削工法による地下構造物の築造に匹敵する精度を保つため、ガイドホール工法を併用することで解決することを課題とした。In order to improve the deficiencies of inaccuracy such as tilt and oversink in the conventional submersible construction method, and to maintain the accuracy comparable to the construction of underground structures by the conventional open-cut method, it is solved by using the guide hole method together The task was to do.
地震時に地盤により発生する液状化現象の抑制効果を解決することを課題とした。The problem was to solve the effect of suppressing liquefaction caused by the ground during an earthquake.
本発明は、上記課題を解決するために、対象構造物の設置予定場所の壁の中心に沿って、図1及び図2の様にアースドリル様のドリル掘削機械にて適応のホール(穴)を沈下定位置より、地下部の縦方向の長さより2メートル以上程垂直に深く掘り、この穴に砂利などの粒状の固形物を充填した後、地下部分本体壁を築造し、築造壁の内側の土部を図3から図5の様に掘削し、地下部分構造物の自重により地下定位置まで沈下させることで解決される。尚且つガイドホールの穴の直径は、構造物の壁の厚さより広くあけ、ガイドホール同士の位置の間隔は隣接のホールが崩れない程度に保ちドリル様に掘削を施し、掘削が終了した後、当該ホールに砂利など粒状の固形物を充填し、完了の後、構築地下構造物の壁の低位置を確定するための捨てコンクリートを打設し、位置を印し、当該構造物の壁を築造し、これを所望の位置まで沈埋、傾き及び過沈下を防止せしめることを可能とすることで解決される。In order to solve the above-mentioned problems, the present invention provides a hole (hole) that can be adapted to the earth drill-like drilling machine as shown in FIGS. 1 and 2 along the center of the wall of the place where the target structure is to be installed. After digging deeply about 2 meters or more vertically from the vertical length of the underground part from the settling position, and filling this hole with granular solids such as gravel, build the underground part main body wall, inside the building wall This is solved by excavating the soil part of Fig. 3 to Fig. 5 and sinking it to the fixed position by the weight of the underground partial structure. In addition, the diameter of the hole of the guide hole is wider than the thickness of the wall of the structure, the distance between the positions of the guide holes is maintained so that the adjacent holes do not collapse, and drilling is performed like a drill. Fill the hall with granular solids such as gravel, and after completion, place abandoned concrete to determine the low position of the wall of the built underground structure, mark the position, and build the wall of the structure This can be solved by making it possible to prevent subsidence, inclination and oversinking to a desired position.
上記に付随し、対象構造物の外壁外側に沿って、沈下途中の際の傾き防止のためH鋼などのガイドレールを垂直に打ち込んでおき、対象構造物が沈下するとき、これに沿ってスムーズに埋設せしめる事でも、課題が解決される。Along with the above, along the outside of the outer wall of the target structure, a guide rail such as H steel is driven vertically to prevent tilting in the middle of subsidence, and when the target structure sinks smoothly along this The problem can also be solved by embedding it in the wall.
本発明の地下構造物築造用ガイドホール工法併用潜函工事工法にて施工すると、在来の開削工法に比べ掘削土量が大幅に減少し、これに伴い残土処分の量も減少し、工事費が比例して大幅に軽減される。また、地下部完了後の埋め戻しは、隙間の充填程度で済み、在来工事での埋め戻しの大量の土砂が不用になり、これにかかる工事費用が限りなく減少させることが可能となった。在来開削工法では、あるべき地山(本来の土壌)を削りとり、埋め戻しをしても地山の状態と同様の土壌にするのは不可能であり、地震の揺れの際、地山と埋め戻し土が分離別れ現象を生じ、ぶつかり合う危険性が発生する。その結果、地震の衝撃が大きくなる可能性が大で、建築構造物への衝撃が増す事になる。本発明のガイドホール工法併用潜函工事工法では、埋め戻しを殆ど必要としないため地震時の揺れに対して揺れを一体化出来るため、在来工法にて築造した構造物より、揺れに対して問題が減少することを可能とした。及びガイドホールに充填してある砂利などの固形物は、水を透すため、液状化を減少させる効果もあり課題が解決される。The construction of the underground structure construction submersible construction method of the present invention significantly reduces the amount of excavated soil compared to the conventional open-cut method, which also reduces the amount of residual soil disposal and construction costs. Proportionally reduced significantly. In addition, the refilling after the completion of the underground part can be done only by filling the gap, and a large amount of earth and sand in the conventional work becomes unnecessary, and the construction cost related to this can be reduced as much as possible. . With the conventional open-cut method, it is impossible to make the soil similar to the state of the natural ground even if the natural ground (original soil) should be shaved and backfilled. As a result, the backfilling soil is separated and a danger of collision occurs. As a result, there is a high possibility that the impact of the earthquake will be large, and the impact on the building structure will increase. In the submersible construction method combined with the guide hole method of the present invention, since there is almost no need for backfilling, it is possible to integrate the shaking against the shaking at the time of earthquake, so there is a problem with shaking than the structure built by the conventional construction method. Made it possible to decrease. In addition, since solids such as gravel filled in the guide hole are permeable to water, there is an effect of reducing liquefaction and the problem is solved.
本発明の地下構造物築造用ガイドホール工法併用潜函工事工法は、開削工事を必要としないため工事範囲が少なくてすみ、隣地との間隔を許される限り少なくすることが可能である。大規模な土留(山止め)工事が不要なため工事費が大幅に軽減され、当該工法により、従来工法の欠点であった傾き、過沈下を解消させることが可能となった。山止め工事に使用する大型重機を必要とせず、また余掘りも不要のため狭い敷地に地下室の築造を可能とし、理論的には許容範囲で、地下100メートル以上の場所に構造物を築造せしめることが可能である。駐車場を地下に築造する費用と地上部に構築する費用とは余り開きがなく工事を遂行できることが可能となったことで、地上部では不要な構造物を地下に、安価で築造可能なため、利用範囲を拡大できる産業的価値をもった工法であり、利用範囲は広い。The submerged construction method combined with the guide hole construction method for constructing an underground structure according to the present invention does not require excavation work, so the construction range is small, and the distance from the adjacent land can be reduced as much as possible. The construction cost has been greatly reduced because large-scale earth retaining (climbing) work is not required, and it has become possible to eliminate the tilt and oversink that were the disadvantages of the conventional method. It does not require large heavy machinery used for mountain-clamping work and does not require extra digging, so it is possible to build a basement in a narrow site, and theoretically allow a structure to be built in a place more than 100 meters below the ground. It is possible. The cost of building a parking lot underground and the cost of building it above the ground can be done without much opening, so it is possible to build unnecessary structures underground at a low cost. It is a construction method with industrial value that can expand the range of use, and the range of use is wide.
以下に本発明にかかる地下構造物築造用ガイドホール工法併用潜函工事工法の好適な実施形態を添付図面を参照して詳述する。図1はAの本体壁の位置にBのガイドホールを施す位置関係を示したもので図2はその断面図で状況を示したものである。ガイドホールには掘削時に崩れやすい小粒砂利などを充填しておく。Preferred embodiments of a submerged construction method combined with a guide hole construction method for building an underground structure according to the present invention will be described below in detail with reference to the accompanying drawings. FIG. 1 shows a positional relationship in which a guide hole B is provided at the position of the main body wall A, and FIG. 2 shows the situation in a sectional view thereof. Fill the guide hole with small gravel that is easy to collapse during excavation.
地下構造物築造用ガイドホール工法併用潜函工事工法の沈下及び沈埋設工程について説明する。図6から図8は従来の潜函工法の状況を示したもので、図7は沈下途中に傾きが生じ、左右に傾きながら沈下する時、本体と地盤との間に大きく隙間が発生する状況を示したものである。図8はDの過沈下が生じた場合の状況を示したものである。The subsidence and subsidence process of the submerged construction method combined with the guidehole method for building underground structures will be explained. FIGS. 6 to 8 show the situation of the conventional submersible construction method. FIG. 7 shows a situation in which a large gap is generated between the main body and the ground when tilting occurs while sinking and when sinking while tilting left and right. It is shown. FIG. 8 shows the situation when excessive subsidence of D occurs.
地下構造物築造用ガイドホール工法併用潜函工事工法では、上記のような現象を解決した図3から図5である。図3はガイドホール施工後に本体壁を築造し、壁内部の掘削第一段階で、掘削の進行に伴い、充填してある砂利等が崩れる様子を示し、図4は掘削、沈下中間状況で、ガイドホールの砂利がほぼ均等に崩れ、本体壁が均等及び垂直に沈下している状況を示し、図5は掘削が完了し、本体壁が定位置に着地した状況である。このようにガイドホールを施行し砂利などを充填しておくことで、掘削及び本体壁の沈下埋設がスムーズに出来、従来の単なる自重のみで沈下させる工法に比べ、精度が格段に改善させることを目的とした地下構造物築造用ガイドホール工法併用潜函工事工法の形態である。In the submerged construction method combined with the guide hole construction method for building an underground structure, FIG. 3 to FIG. 5 solve the above phenomenon. Fig. 3 shows the construction of the main wall after the construction of the guide hole, and shows how the gravel that has been filled collapses as the excavation progresses in the first stage of excavation inside the wall. FIG. 5 shows a situation in which the gravel of the guide hole collapses almost evenly and the main body wall sinks evenly and vertically, and FIG. 5 shows the situation where excavation has been completed and the main body wall has landed in place. By enforcing guide holes and filling gravel etc. in this way, excavation and subsidence of the wall of the main body can be performed smoothly, and accuracy can be improved significantly compared to the conventional method of subsidizing only by its own weight. It is a form of submerged construction method combined with guide hole construction method for underground structure construction.
A 築造構造物本体壁
B ガイドホール
C 充填砂利等
D 本体壁過沈下部分
E 傾き方向矢印
F 地山(地盤)A building structure body wall
B Guide hole
C Filling gravel, etc.
D Body wall oversink
E Inclination direction arrow
F Ground (ground)
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006041592A JP2007198100A (en) | 2006-01-23 | 2006-01-23 | Caisson method combined with guide hole construction method for constructing underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006041592A JP2007198100A (en) | 2006-01-23 | 2006-01-23 | Caisson method combined with guide hole construction method for constructing underground structure |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2007198100A true JP2007198100A (en) | 2007-08-09 |
Family
ID=38452966
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006041592A Pending JP2007198100A (en) | 2006-01-23 | 2006-01-23 | Caisson method combined with guide hole construction method for constructing underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2007198100A (en) |
-
2006
- 2006-01-23 JP JP2006041592A patent/JP2007198100A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104612143B (en) | Composite pile constructed in drilled hole structure under a kind of solution cavity/soil cave geological conditions | |
CN104264688A (en) | Manual hole digging non-uniform pile support construction technology | |
CN110735600B (en) | Mechanical pore-forming pile construction process for karst geology | |
KR20130081971A (en) | Precast concrete wall and method for constructing underground permanent wall using the precast concrete wall | |
JP5882143B2 (en) | Anti-floating pile for underground structures and anti-floating method for underground structures | |
CN103726495A (en) | Offshore deep foundation pit supporting structure and construction method thereof | |
JP2017186783A (en) | Construction method of continuous underground wall | |
CN110735432A (en) | Method for clearing pile foundation and controlling parameters in shield tunneling machine over-invasion limit tunnel range | |
CN109339079A (en) | A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum | |
CN107653878A (en) | Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction | |
JP2003206539A (en) | Temporary closing construction method | |
JP6806465B2 (en) | Construction method of foundation structure | |
KR20100035349A (en) | Construction method of retaining wall using cast-in-place pile | |
CN101481913A (en) | Construction method of rock-socketed underground continuous wall punching slot section | |
CN116756940A (en) | Push pipe engineering design and construction method based on stress performances of different geological environments | |
JP3967473B2 (en) | Construction method of underground structure | |
CN207538090U (en) | A kind of externally reinforced structure of Urban underground Tunnel | |
JP4485006B2 (en) | Construction method for underground structures | |
JP2008184889A (en) | Caisson construction method combined with guide hole method for constructing underground structure | |
JPH08184058A (en) | Landslide protection construction | |
JP5157814B2 (en) | Installation method of ready-made piles | |
CN110144903B (en) | Construction method for foundation pit support in air defense cavity | |
JP6259271B2 (en) | Caisson installation method and underground column body group | |
JP2007198100A (en) | Caisson method combined with guide hole construction method for constructing underground structure | |
KR20110087175A (en) | From first of all excavation reclamation methodof phc pickets will improve and the method will be able to the method |