JP2007138702A - Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel - Google Patents

Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel Download PDF

Info

Publication number
JP2007138702A
JP2007138702A JP2007005822A JP2007005822A JP2007138702A JP 2007138702 A JP2007138702 A JP 2007138702A JP 2007005822 A JP2007005822 A JP 2007005822A JP 2007005822 A JP2007005822 A JP 2007005822A JP 2007138702 A JP2007138702 A JP 2007138702A
Authority
JP
Japan
Prior art keywords
cylinder
work
working cylinder
outer shell
cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007005822A
Other languages
Japanese (ja)
Inventor
Kunie Yuguchi
國榮 湯口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DAINICHI CONSULTANT Inc
Original Assignee
DAINICHI CONSULTANT Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DAINICHI CONSULTANT Inc filed Critical DAINICHI CONSULTANT Inc
Priority to JP2007005822A priority Critical patent/JP2007138702A/en
Publication of JP2007138702A publication Critical patent/JP2007138702A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To store a clod of the earth formed by cutting the natural ground into a cylindrical shape by only the thickness of a blade by a rigid and steel working cylinder having a double structure into an inner side working cylinder, transfer the clod of the earth backward together with a vessel to remove the clod of the earth in the cross section, and apply a countermeasure construction method from this space to excavate while retracting all the cross sections. <P>SOLUTION: This tunnel excavation device is a two-story mobile arch center provided with five working cylinders and connecting an excavation part having a cutting blade 17 at its tip with a working cylinder jacking part provided with a working cylinder machine chamber case body 54 at the rearmost end. A hydraulic jack 60 using a supporting column of the arch center as a reaction force member is arranged to close the cylinder by a working cylinder closing door case body 64 having a mud absorbing pump 65 and incorporating a mud collecting tank 66. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は油圧ジャッキで推進できる移動セントル架台に、鋼製の中空で外側と内側がぴったりあった筒状の2重構造の作業筒を複数基搭載し、外側作業筒内部に掘削動力伝達ロッドを有し、これにより外側作業筒最先端円周部を分割し、独立して回転可能な切削刃を装着した掘削部を駆動し、地山土塊を円周状に繰り抜くと同時に、作業筒全体を油圧ジャッキで推進させ、内側作業筒内に土塊を収容する。
又掘削部直後に設置した土塊切断装置により地山から直角に切り離し、内側作業筒を後方へ移送する事により地山の中抜き掘削を行なうものである。
In the present invention, a moving center barrel that can be propelled by a hydraulic jack is mounted with a plurality of hollow cylindrical steel work tubes that are tight on the outside and inside, and an excavation power transmission rod is provided inside the outside work tube. It has an outer work cylinder, which divides the most peripheral part of the outer work cylinder, drives the excavation part equipped with a cutting blade that can be rotated independently, and pulls out the natural soil block at the same time. Is propelled with a hydraulic jack, and the soil block is accommodated in the inner working cylinder.
Moreover, it cuts off from a natural ground at right angles with the lump cutting apparatus installed immediately after the excavation part, and excavates a natural ground by moving an inner work cylinder back.

この作業により確保された外側作業筒空間から十分なる対策工法を施し、中抜きされ脆弱になった地山断面を、バックホー等の掘削機の最大効率姿勢を発揮する後退姿勢で作業筒と共に後退しながら、全断面を整形掘削するトンネルの掘削工法に関する。 By taking sufficient countermeasures from the outer work cylinder space secured by this work, the ground section that has been cut out and weakened is retreated with the work cylinder in a retreating posture that demonstrates the maximum efficiency posture of an excavator such as a backhoe. However, the present invention relates to a tunnel excavation method for shaping and excavating the entire cross section.

トンネル掘削は地山を外側からトンネル軸に沿い奥に向かって、切羽面を片押しで掘削を進めると共に、掘削に伴う大きな地山圧力に対しては、鋼製支保工、ロックボルト等の補助工法により対処している。 Tunnel excavation proceeds from the outside to the back along the tunnel axis by pushing the face face in one direction, and for large ground pressure due to excavation, it is supported by steel support, rock bolts, etc. It is dealt with by the construction method.

軟弱地質における切羽の崩壊等の対処については、様々な対策が必要となるが施工が切羽前面からしか出来ないため、作業の方向性や作業のスペースが限定され、非効率で冗長的な作業となりしばしば難航することがある。
是らに対処するため事前調査に基づく、様々な地質に対応した地盤改良法、凍結法等の対策工法を実施しトンネルを完成させている。
また、大型トンネルボーリングマシン(以下TBM)等によって、全断面の掘削と同時にコンクリート覆工を実施し、トンネルを完成させている。
Various measures are required to deal with the collapse of the face in soft geology, but the construction can only be done from the front of the face, so the work direction and work space are limited, making it inefficient and redundant work. Often difficult.
To cope with this problem, the tunnel has been completed by implementing countermeasures such as ground improvement methods and freezing methods corresponding to various geological features based on preliminary surveys.
In addition, the tunnel is completed by excavating the entire cross-section with a large tunnel boring machine (hereinafter referred to as TBM) and carrying out concrete lining.

従来のトンネル掘削は、地形、地質、地下水位等の条件に応じ、選択された掘削方式により実施され、各種の補助工法や地盤の改良等の対策工法が併用されると共に、条件によっては大型TBMが経済的であるため採用されている。   Conventional tunnel excavation is carried out according to the selected excavation method according to the conditions such as topography, geology, groundwater level, etc., and various auxiliary construction methods and countermeasure construction methods such as ground improvement are used together. Is adopted because it is economical.

しかしながら、自然条件が全て把握されている訳でなく、時として異常な偏圧や出水等による予期せぬ事態に遭遇することが多々あり、先線の地質条件把握のための事前調査や、これに基づく対策工法の確定は不可欠な課題である。   However, not all natural conditions are known, and sometimes unexpected situations such as abnormal bias pressure or flooding often occur. It is an indispensable task to establish a countermeasure method based on the above.

また、この対策工法の施工にあたっては刃口からの片押し作業のため、作業の方向性や作業空間の確保、安全性、確実性の確認等が大きな課題である。 In addition, the construction of this countermeasure construction method involves one-side pressing work from the blade edge, so that the direction of work, securing of work space, confirmation of safety and certainty, etc. are major issues.

TBMの採用の場合は、全断面を切削刃で切削し、泥土を後方へ排出している。
このため切削に強大な馬力を要し、反力による地山へ及ぼす影響が大きく、TBMの挙動の制御が複雑となり設備が大型化、複雑化している。
又全断面の切削のため排泥量が多く、その処理に多額の費用を要する等TBM採用に当たっては、地質条件、設備規模の決定、経済性が大きな課題である。
In the case of adopting TBM, the entire cross section is cut with a cutting blade, and the mud is discharged backward.
For this reason, a powerful horsepower is required for cutting, and the influence of the reaction force on the natural ground is large, the control of the behavior of the TBM is complicated, and the equipment is enlarged and complicated.
In addition, geological conditions, determination of equipment scale, and economics are major issues when adopting TBM.

上記目的を達成するために、トンネルの法線縦横断計画に合致した施工基面に、基礎台座の形状に合わせ掘削した溝に、埋めるように基礎台座を埋設し、大きな荷重、反力に抵抗できるように定着する。
この基礎台座に移動セントルを、ガイドベアリング等で移動し、据付ると共に固定ボルトで固着し掘削を開始する。
In order to achieve the above purpose, the foundation pedestal is buried on the construction base that matches the normal vertical crossing plan of the tunnel in the groove excavated according to the shape of the foundation pedestal to resist large loads and reaction forces. Establish as possible.
The moving centle is moved to the foundation pedestal by a guide bearing or the like and installed, and fixed by a fixing bolt to start excavation.

掘削の主体である作業筒は、鋼製で中空の筒状とし、筒の外鈑と内鈑を、軸方向及び円周方向に一定間隔に補強腹鈑で補強し、機械作業が十分可能な空間を確保し、互いにぴったり合った外殻と内殻に分けた2重の構造とする。
外殻作業筒は、外鈑と内鈑との空間に、推進機械室の駆動モーターからの駆動力を伝達する伝達ロッドを、軸方向に一定間隔に配置された2枚一組の補強腹鈑の間に配置し、これに直角に交わる円周方向補強腹鈑に取付けたベアリングを介して固定する。
The work cylinder, which is the main body of excavation, is made of steel and has a hollow cylindrical shape, and the outer and inner flanges of the cylinder are reinforced with reinforcing bellows at regular intervals in the axial direction and the circumferential direction so that machine work can be performed sufficiently. Space is secured and the structure is divided into an outer shell and an inner shell that fit closely together.
The outer shell cylinder is a set of two reinforced bellows in which a transmission rod for transmitting the driving force from the drive motor of the propulsion machine room is arranged in the space between the outer casing and the inner casing at regular intervals in the axial direction. And fixed through a bearing attached to a circumferential reinforcement prone to intersect at right angles to this.

伝達ロッドと伝達ロッドの間に、先端切削部で切削された岩砕、泥土を後方へ移送する排泥管を設置する。
また、内殻作業筒の移動を容易にするため、荷重のかかる断面下半分の軸方向補強腹鈑の上部に、内殻作業筒に接するよう棒状のベアリングを設置する。
Between the transmission rod and the transmission rod, a sludge pipe that transfers rocks and mud cut at the tip cutting part to the rear is installed.
Further, in order to facilitate the movement of the inner shell working cylinder, a rod-shaped bearing is installed on the upper part of the axially reinforced bellows in the lower half of the cross section where the load is applied so as to contact the inner shell working cylinder.

内殻作業筒は、切取られた土塊を収容し、後方へ移送するための容器であり土塊の重量に耐えられる様、軸及び円周方向補強腹鈑により十分に補強する。   The inner shell cylinder is a container for storing and transferring the cut chunk of soil, and is sufficiently reinforced with a shaft and a circumferential reinforcing bellow so as to withstand the weight of the chunk.

外殻作業筒の先端円周部の外鈑と内鈑を偶数正多角形に分割、整形した切削刃支持鈑に支えられ、切削刃回転軸を介して独立して回転可能な切削刃を装着した切削部を設ける。
そして油圧ジャッキの推進力により、鏡面の土塊に押付け外殻作業筒の円周を包含した多角形を刃厚分だけ繰り抜くように切削し、繰り抜かれた円筒形土塊部を切削と同時に推進力により、内殻作業筒内部に収納する。
The outer edge and inner edge of the outer circumference of the outer shell work cylinder are divided into even regular polygons, supported by a shaped cutting blade support rod, and equipped with a cutting blade that can rotate independently via the cutting blade rotating shaft A cut portion is provided.
Then, with the thrust of the hydraulic jack, the polygon including the circumference of the pressing outer shell cylinder is cut to the mirror surface lump so as to be pulled out by the blade thickness. Thus, it is housed inside the inner shell work cylinder.

土塊の切削を行う切削刃の回転力は、動力伝達ロッドの回転力を,駆動力伝達歯車で直角に変換し、駆動力伝達遊星歯車を介して、刃先に歯形を刻んだ切削刃に伝達され土塊の切削を行なう。 The rotational force of the cutting blade that cuts the clot is converted to a rotational force of the power transmission rod by a driving force transmission gear at a right angle, and is transmitted to the cutting blade whose tooth shape is carved through the driving force transmission planetary gear. Cut the clot.

これらの動力伝達機構を保護するため,機構の空間を補強スペーサーで埋め、切削刃支持鈑に締付けボルトで固定し、強固に一体化する。 In order to protect these power transmission mechanisms, the space of the mechanism is filled with a reinforcing spacer, fixed to the cutting blade support rod with a fastening bolt, and firmly integrated.

切削部の直後には地山から繰り抜いた土塊を直角に切離すため、ワイヤソーによる切取り装置を設ける。
切取り装置は掘削部の直後に、円周方向補強腹鈑で区切った設置空間を設け、留め金具を兼ねたシャーピンで定着されたワイヤソーを収納する。
Immediately after the cutting section, a wire saw cutting device is provided in order to cut off the soil block pulled out from the natural ground at a right angle.
The cutting device is provided immediately after the excavation part with an installation space separated by a circumferential reinforcing prong, and stores a wire saw fixed with a shear pin that also serves as a fastener.

使用に際しては、ワイヤソー駆動モーターの駆動力により、ワイヤソーが回転する事により、シャーピンを破断、そして更に土塊を直角に切断する。
切断の進行によりワイヤソーが弛んで余った部分を遊ばせる収容部が必要であり、巻き取るための弛取装置を設ける。
In use, when the wire saw is rotated by the driving force of the wire saw drive motor, the shear pin is broken and the earth lump is cut at a right angle.
An accommodating portion that allows the wire saw to loosen due to the progress of cutting is required, and a loosening device for winding is provided.

弛取装置は、固定滑車と移動滑車を複数個、向い合せに組合せ、この間に本体ワイヤソーを抱き込んだ伸縮可能な櫛状部を主構造とし、この挙動を制御するため装置を誘導レールに納める。
この装置の端部から巻取用ワイヤーを伸ばし、一定の張力を超えるとON,OFF出来るバネスイッチ持った巻取用プテッピングモーターに繋ぎ、櫛状部の間隔を広げこの部分に駆動しながら余分なワイヤソーを収納する。
一度切断を終えた場合は、土塊を排除し、ワイヤソーを設置し直す。
The loosening device is composed of a fixed pulley and multiple movable pulleys facing each other, and a telescopic comb-like part that embeds the body wire saw between them is the main structure, and the device is housed on a guide rail to control this behavior. .
While extending the winding wire from the end of this device and connecting it to a winding stepping motor with a spring switch that can be turned on and off when a certain tension is exceeded, widen the interval of the comb-shaped part while driving to this part Store extra wire saws.
Once you have finished cutting, remove the clod and re-install the wire saw.

作業筒の坑口側最後尾には推進機械室を設け、トンネルの掘削、作業筒の推進、後退を行なう動力を発生させる。
推進機械室は移動セントル作業架台の鋼製支柱間に合わせ方形の筺体とし、剛性を高め、外殻作業筒と一体化するための補強スチッフナーで筺体と剛結する。
その4隅に駆動モーターを設置し、また左右の架台支柱と接する側の、補強スチッフナーと補強スチッフナー間に、着脱出来る取付ボルトを介して、推進(又は後退)用の油圧ジャッキを設置し、反力部材と連結する。
A propulsion machine room is provided at the tail end of the work cylinder side to generate power for excavating the tunnel, propelling and retreating the work cylinder.
The propulsion machine room is a rectangular housing that fits between the steel columns of the moving center work stand, and is rigidly connected to the housing with a reinforcing stiffener to increase rigidity and integrate with the outer shell work cylinder.
Drive motors are installed at the four corners, and hydraulic jacks for propulsion (or retraction) are installed between the reinforcement stiffeners on the side that comes into contact with the left and right gantry pillars, between the reinforcement stiffeners and detachable mounting bolts. Connect with force member.

上記の油圧ジャッキの反力部材として、作業架台の支柱間を軸方向に反力伝達スチフナーで連結し剛性高め、これに着脱出来る取付ボルトを介して油圧ジャッキの頭部(又は端部)を取付け、架台全体で大きな反力に抵抗させる。   As the reaction force member of the above hydraulic jack, the column of the work platform is connected with the reaction force transmission stiffener in the axial direction to increase the rigidity, and the head (or end) of the hydraulic jack is attached via a mounting bolt that can be attached to and detached from this , Resist the great reaction force throughout the gantry.

推進機械室の坑口側端部には、取付金具で中空の方形筺体の閉鎖扉を設ける。
閉鎖扉の内部には、吸泥ポンプを内蔵した集泥槽を設置し、この中に取付ヘッドで繋いだ排泥管を導入する。
また動力伝達ロッドの中心部を貫通する高圧水供給管に対して、取付ヘッドで繋ぎ高圧水を供給する。
推進(後退)動力の制御、切削刃の回転、高圧水の供給、集泥槽からの排泥はすべて、扉に設置された操作盤の操作により行なう。
これらの電動力、高圧水道、排泥は架台支柱に付随して設置した給電、給水、排泥施設により供給または排出する。
At the end of the propulsion machine room on the wellhead side, a hollow rectangular enclosure closure door is provided with a mounting bracket.
A mud collection tank with a built-in mud pump is installed inside the closed door, and a mud pipe connected by a mounting head is introduced into this tank.
Moreover, it connects with an attachment head with respect to the high pressure water supply pipe which penetrates the center part of a power transmission rod, and supplies high pressure water.
Control of propulsion (retreat) power, rotation of the cutting blade, supply of high-pressure water, and drainage from the mud collection tank are all performed by operating the operation panel installed on the door.
These electric power, high-pressure water supply, and waste mud are supplied or discharged by the power supply, water supply, and mud discharge facilities installed along with the support column.

基礎台座の上に置かれる移動セントルは、ガイドベアリング等で移動出来、定着ボルトで台座に固定出来る作業架台とする。
移動セントルは上部と下部の作業フロアーの2階建とし、土塊等の大きな荷重に耐えるようH型鋼の支柱、縦梁桁、横梁桁、アーチリブで構成し、外周をスキンプレートで覆い、各階は梁桁に鋼床鈑を架設した剛性の大きな作業架台とする。
The moving center placed on the base pedestal shall be a work platform that can be moved with guide bearings and fixed to the pedestal with fixing bolts.
The moving center is composed of two floors, the upper and lower working floors. It is composed of H-shaped steel columns, vertical beam girders, cross beam girders, and arch ribs to withstand heavy loads such as dirt, and the outer periphery is covered with skin plates. A rigid work platform with a steel floor erected in the girder.

上部作業フロア‐の中央部坑口側一区画には、上部作業フロアーへのアプローチとしての重量用昇降エレベーターを設置する。
各階の作業筒装填区画レーンにボールベアリングで左右前後に移動可能で定着ボルトで固定出来、作業筒の安定と縦移動を容易にするための作業筒誘導受けレールを敷設する。
A lifting elevator for weight as an approach to the upper work floor will be installed in a section of the upper work floor at the central wellhead side.
The work tube loading section lane on each floor can be moved back and forth with ball bearings and fixed with fixing bolts, and a work tube guide receiving rail is installed to facilitate stable and vertical movement of the work tube.

最大推進長の1行程推進を完了し、内殻作業筒を後方へ移送するために、下部作業架台の直後まで引き込み線を敷設し、下部作業フロアーの高さに合わせた作業筒移送貨車に作業筒受けレールを介して積込み、トンネル外の土塊処理区画へ移送する。   To complete the one-stroke propulsion of the maximum propulsion length and transfer the inner shell work cylinder to the rear, a lead-in line is laid immediately after the lower work platform, and work is performed on the work cylinder transfer wagon that matches the height of the lower work floor. It is loaded via the tube receiving rail and transferred to the mass processing section outside the tunnel.

土捨場における排土のために、移送された内殻作業筒を、直径で2葉に分解して排土したり、組立のため円周方向補強腹鈑に複数の分解継手を設け、ボルトにより着脱出来る構造とする。   For removal of soil at the dump site, the transferred inner shell cylinder is disassembled into two leaves with a diameter, and multiple disassembly joints are provided on the circumferential reinforcing bellows for assembly. The structure should be removable.

内殻作業筒排出後の外殻作業筒内で、地山及び鏡面へのロックボルトの打設、各種注入工事等の対策工法を実施出来る様ロックボルト打設機、各種注入機、ロードカッター、バックホー等を自走で搬入し、作業足場が固定出来る構造とする。 In the outer shell work cylinder after the inner shell work cylinder is discharged, a lock bolt driving machine, various injection machines, load cutter, A structure that can carry the backhoe etc. by itself and fix the work platform.

また、ロックボルトの打設や各種注入工法、凍結工法等の対策工法作業が作業筒全体に亘る場合に対応するため、外殻作業筒にはロックボルト打設を念頭に置き、ネジコミ式の多目的作業孔を設ける。 Also, in order to deal with the case where the work of countermeasures such as the installation of lock bolts, various injection methods, freezing methods, etc. covers the entire work cylinder, the outer shell work cylinder is designed with a lock bolt in mind, and is a multi-purpose screw-comb type. A working hole is provided.

多目的作業孔は、一定間隔で多数必要であるため断面の脆弱化を招く、これを防ぐため多目的作業孔周辺には外殻作業筒の外鈑,内鈑に添接した補強鈑を設ける。 Since a large number of multipurpose work holes are required at regular intervals, the cross section is weakened. In order to prevent this, the outer shell of the outer shell work cylinder and the reinforcing rod attached to the inner shell are provided around the multipurpose work hole.

対策工法を完了した作業筒においては、作業筒を後退させながら、中抜きして脆くなった鏡面土塊をロードカッターによる突き崩し、整形掘削、バックホーによる掘削土の集積、積込み作業、クレーンによる鋼製支保工や基礎台座の組立等目的の作業を実施する。 For work cylinders that have completed the countermeasures, retreat the work cylinder, break the mirrored blob that has become fragile by cutting out with a load cutter, shape excavation, accumulation of excavated soil by backhoe, loading work, steel making by crane Carry out tasks such as support work and assembly of foundation pedestals.

本発明は以上説明したとおり構成されているので、以下のような効果を発揮する。
本発明における作業筒は、前述の小断面で2重構造の堅固な鋼製の筒状で、掘削部と推進機械部の2本を連結した構造を基本とし、掘削部先端には独立して回転し切削できる切削部を設けており、従来のシールド掘削機の様に大きな地山圧力に抗して自ら回転し筒全体面積を掘削するのでなく、作業筒円周を包含した正多角形の刃厚分だけ円周状に切削するのみであるため、地山に余分な影響を与えず、力を作用点に集中させ最小仕事で最大効果を達成でき飛躍的な省力化が図れる。
Since the present invention is configured as described above, the following effects are exhibited.
The working cylinder in the present invention is a solid steel cylinder having a small cross section and a double structure, and has a structure in which two excavation parts and a propulsion machine part are connected to each other. It has a cutting part that can rotate and cut, and it does not rotate itself against large ground pressure like a conventional shield excavator and excavates the entire area of the cylinder, but instead of a regular polygon that includes the circumference of the work cylinder Since only the blade thickness is cut in a circumferential shape, the maximum effect can be achieved with the minimum work by concentrating the force on the working point without excessively affecting the natural ground, and dramatic labor savings can be achieved.

円筒形に切削した土塊はそのまま内殻作業筒に収納し、一定長毎に土塊切断装置で切離され、坑外の土塊処理区画へ移送、解体されるため、岩石の場合1.5倍にものぼる掘削土の体積変化率を最小限に止め、掘削及び残土処理コストの削減、作業スペースの最小化を図り、効率的な作業を実施出来る。   The lump cut into a cylindrical shape is stored in the inner shell cylinder as it is, separated by a lump cutting device at regular intervals, transferred to the lump processing section outside the mine, and dismantled. The volume change rate of the excavated soil can be minimized, the excavation and remaining soil processing costs can be reduced, the work space can be minimized, and efficient work can be carried out.

内殻作業筒に収納された土塊は,先線の地質サンプルであり、トンネル断面の全体に亘って詳細な地質データ−が得られ、想定される事態に対するあらゆる危険性を察知し、迅速に対策工法の検討、決定でき、安全で施工基面が構造的に確保された作業筒内から、機械施工を主体にした対策工法を実施し、地山を早期に安定させる事が出来る。
このように、トンネル工事の省エネルギー化、省人化、工場化が促進されトンネル施工運営における安全性の向上、効率的、経済的で恒常的な進捗を図れる効果がある。
The clot stored in the inner shell cylinder is a geological sample of the front line, and detailed geological data can be obtained over the entire tunnel cross section. The construction method can be examined and determined, and the construction method can be implemented from the inside of the work cylinder, which is safe and the construction base surface is structurally secured.
In this way, energy saving, manpower saving, and factoryization of tunnel construction are promoted, and there is an effect that safety can be improved in tunnel construction management and efficient, economical and constant progress can be achieved.

移動セントルに装着した作業筒の推進用油圧ポンプの作動により、作業筒が推進し掘削部を鏡面に押し付けると同時に、駆動モーターの回転力が、駆動力伝達ロッドを介し、回転切削刃を回転させる。
このとき、駆動力伝達ロッドの中心部に設けられた、高圧水管から高圧水を鏡面土塊に噴射し、切削のきっかけを作ると共に、切削刃の潤滑を促し、鏡面土塊を内殻作業筒の形状を包含した刃形どおりに切削するため、推進と同時に鏡面土塊が内殻作業筒に順次収納される。
By operating the hydraulic pump for propelling the work cylinder attached to the moving center, the work cylinder propels and presses the excavation part against the mirror surface, and at the same time, the rotational force of the drive motor rotates the rotary cutting blade via the drive force transmission rod. .
At this time, high-pressure water is sprayed from the high-pressure water pipe provided at the center of the driving force transmission rod to the mirror clot, creating a trigger for cutting and promoting the lubrication of the cutting blade. In order to cut according to the shape of the blade including the mirror, the specular soil is sequentially stored in the inner shell work cylinder simultaneously with the propulsion.

切削汚泥は、切削刃の互に向い合う方向の回転力により呼び込まれ、隣り合う切削刃の間に設置された排泥管付近に導かれる。そして吸引ポンプの吸引力により集泥槽に集められ、総排泥管から排水溝へさらに坑外の沈殿池ヘ排出される。   The cutting sludge is attracted by the rotational force of the cutting blades facing each other and guided to the vicinity of the drainage pipe installed between the adjacent cutting blades. Then, it is collected in the mud collection tank by the suction force of the suction pump, and discharged from the total mud pipe to the drainage ditch and further to the settling basin outside the mine.

各作業筒を推進し最大長まで推進出来た作業筒から、土塊切取り装置により鏡面土塊から切り離し土塊を収納し、重い内殻作業筒を受けレール、昇降エレベーター等を介して慎重に内殻作業筒運搬貨車に積込み、坑外へ送出する事で鏡面土塊が中抜きされ、掘削作業空間が確保される。 From each work cylinder that has been propelled to the maximum length by propelling each work cylinder, it is separated from the specular lump by a lump cutting device, and the clot is stored, and a heavy inner shell work cylinder is received through the rail, elevator, etc. By loading it into a transport wagon and sending it out of the mine, the specular clot is removed and the excavation work space is secured.

作業架台に装填された作業筒は、夫々独立して作動できる。
各作業筒の掘削速度は、遭遇する地質に左右され差異が生じるが、先に推進を終え、内殻作業筒の送出を完了した作業筒から作業計画に沿って、各作業車を作業筒内へ自走で搬入させ、所定の位置に固定しロックボルトの打設、各種注入工事等、必要な対策工法を施工出来、掘削区間の安全性が早期に確保出来る。
The work cylinders loaded on the work platform can operate independently.
The excavation speed of each work cylinder depends on the geology encountered, and there are differences, but each work vehicle is moved into the work cylinder according to the work plan from the work cylinder that has been propelled first and the inner shell work cylinder has been sent out. It is possible to carry it in by self-propelled, fix it at a predetermined position, and implement necessary countermeasures such as placing a lock bolt and various injection works, and secure the safety of the excavation section at an early stage.

内殻作業筒の送出を完了し、対策工法を完了した区間については、作業計画に従って、上部フロア‐作業筒の後退を優先させ、作業筒全体を後退させながらスペースを確保し、先ず下部作業フロアーにバックホーによる掘削土の集積、積込み、ベルトコンベアーによる排送作業ルートを確保する。
そして上部作業フロアーから中抜きして脆くなった土塊を、効率的な後退姿勢での整形掘削が施工できるバックホー、ロードカッター等により突き崩し、後退により確保された下部階の空洞スペースへ、掘削土を自由落下させ掘削を進める。
断面の整形掘削を終了させた区間については、クレーン等による鋼製支保工の設置や基礎台座の組立等、一連の目的の作業工程を機械化され効率的で、想定できる恒常的な進捗速度で作業が遂行される。
For the section where the delivery of the inner cylinder was completed and the countermeasure method was completed, according to the work plan, priority was given to retreating the upper floor-work cylinder, ensuring space while retreating the entire work cylinder, and first the lower work floor In addition, the excavation soil will be collected and loaded by the backhoe and discharged by the belt conveyor.
The clot that has become brittle due to being hollowed out from the upper work floor is crushed by a backhoe, road cutter, etc. that can be shaped and excavated in an efficient receding posture, and excavated soil into the hollow space of the lower floor secured by retreating. Free fall and proceed with excavation.
For sections where cross-section excavation has been completed, a series of objective work processes, such as installation of steel supports using cranes and assembly of foundation pedestals, are mechanized, and work is performed at a constant progress rate that can be assumed. Is carried out.

作業筒の推進と後退は、機械室側面補強スチフナーと反力を得るためのH型鋼支柱間の補強スチフナーを結合するよう、互い違いに着脱可能な取付けボルトを介して、シリンダーヘッド又はピストンヘッドを取付け、油圧ポンプの伸長又は収縮の推力により駆動する。
そしてピストンの働長分毎に、取付けボルトを着脱し匍匐して前後進出来る。
The cylinder head or piston head is mounted via staggered removable mounting bolts to connect the machine room side reinforcement stiffener and the reinforcement stiffener between the H-shaped steel columns to obtain the reaction force. It is driven by the thrust of expansion or contraction of the hydraulic pump.
And for every working length of the piston, it can move forward and backward by attaching and detaching the mounting bolt.

実施例について図面を参照して説明すると、図1において、は標準的なトンネルの横断図を示している。   The embodiment will be described with reference to the drawings, in which FIG. 1 shows a cross section of a standard tunnel.

図2に示す実施例では、掘削装置の本体である移動セントルの横断図であり、2階建てで、5本の作業筒を装着している。
そして、大きな荷重のかかる2階の作業筒については、直下にH型鋼支柱7を配して荷重を支えている。
移動セントルの骨格は縦横の桁梁とH型鋼支柱7、アーチリブ6を剛結し、周囲を覆工コンクリート打設の為、数センチ上下に可動出来るスキンプレート5で覆い水密性と剛性を高めている。
In the embodiment shown in FIG. 2, it is a cross-sectional view of a moving centle which is the main body of the excavator, and is two stories and is equipped with five work cylinders.
And about the work cylinder of the 2nd floor where a big load is applied, the H-shaped steel support | pillar 7 is distribute | arranged directly under and the load is supported.
The moving centle skeleton is rigidly connected with vertical and horizontal girders, H-shaped steel pillars 7 and arch ribs 6, and the surrounding is covered with a skin plate 5 that can be moved up and down by several centimeters to improve water tightness and rigidity. Yes.

図3に示す実施例は、作業筒の配置図であり、対策工法の施工事例として、ロックボルト14の施工位置の概念を示している。   The embodiment shown in FIG. 3 is a layout diagram of work cylinders and shows the concept of the construction position of the lock bolt 14 as a construction example of the countermeasure construction method.

図4に示す実施例は、作業筒の断面図であり、中空の筒状で互いに接する外殻作業筒9と内殻作業筒10の2重構造を示している。
外殻作業筒外版33と外殻作業筒内鈑31の先端部を八分割し、二組が対になってハの字状に向い合い、外殻作業筒9の円周を包含し正八角形に整形した切削刃支持鈑20で、4段に積層された切削刃17を切削刃回転軸19を介して貫くように束ね、下部切削刃保護版23と切削刃締付けボルト24で固定している。
C−C断面部の作業筒は大きな荷重を支える必要性から、縦横断方向に一定の間隔で2枚一組の外殻作業筒腹鈑32,内殻作業筒腹鈑29で補強しており、この空間に駆動力伝達ロッド25および排泥管36を配置している。
又、外殻作業筒腹鈑32に内殻作業筒10に接するよう移動用ベアリング34を設ける。
B−B断面部については駆動力が、駆動力伝達ロッド25に刻まれた伝達ロッド先端歯車37により駆動力伝達遊星歯車26に伝達され、回転方向が90度変換されている。
A−A断面部については駆動力伝達遊星歯車26の回転力が切削刃17の刃先に刻まれた歯形を介して、切削刃17に伝達されている。
The embodiment shown in FIG. 4 is a cross-sectional view of a work cylinder and shows a double structure of an outer shell work cylinder 9 and an inner shell work cylinder 10 which are in a hollow cylindrical shape and are in contact with each other.
The front end portion of the outer shell working cylinder outer plate 33 and the outer shell working cylinder inner collar 31 are divided into eight, and two pairs face each other in a letter C shape and include the circumference of the outer shell working cylinder 9 The cutting blade support rod 20 shaped into a square shape is used to bundle the cutting blades 17 stacked in four stages so as to penetrate through the cutting blade rotating shaft 19, and are fixed by the lower cutting blade protection plate 23 and the cutting blade clamping bolt 24. Yes.
The work cylinder of the C-C cross section is reinforced with a pair of outer shell work cylinder 32 and inner shell work cylinder 29 at regular intervals in the longitudinal and transverse direction because it is necessary to support a large load. The driving force transmission rod 25 and the mud pipe 36 are disposed in this space.
Further, a moving bearing 34 is provided on the outer shell working cylinder prone pad 32 so as to contact the inner shell working cylinder 10.
Regarding the BB cross section, the driving force is transmitted to the driving force transmission planetary gear 26 by the transmission rod tip gear 37 carved in the driving force transmission rod 25, and the rotation direction is converted by 90 degrees.
With respect to the AA cross section, the rotational force of the driving force transmission planetary gear 26 is transmitted to the cutting blade 17 via a tooth profile carved on the cutting edge of the cutting blade 17.

図5に示す実施例は先端切削部の断面図であり、外殻作業筒9の先端部を外殻作業筒外鈑33と外殻作業筒内鈑31で切削刃17を包むように整形した切削刃支持鈑20で挟み、切削刃回転軸19で貫き、切削刃ベアリング21で回転を円滑にすると共に切削刃支持スペーサー22で間隔を保持し、上部、下部切削刃保護鈑23で切削刃締め付けボルト24を介して着脱出来るよう固定している。 The embodiment shown in FIG. 5 is a cross-sectional view of the tip cutting part, in which the tip of the outer shell working cylinder 9 is shaped so as to wrap the cutting blade 17 with the outer shell working cylinder outer rod 33 and the outer shell working cylinder inner rod 31. The blade is clamped by the blade support rod 20, penetrated by the cutting blade rotating shaft 19, smoothed by the cutting blade bearing 21 and kept at a distance by the cutting blade support spacer 22, and the cutting blade clamping bolt by the upper and lower cutting blade protection rods 23. 24 is fixed so that it can be attached and detached.

図6に示す実施例は先端切削部側面図であり、中心に高圧水管35を持ち、先端に伝達ロッド先端歯車37を刻んだ駆動力伝達ロッド25により、駆動力が駆動力伝達遊星歯車26を介して切削刃17に伝達されており、これら一連の切削機構を保護するため、切削刃支持版固定スペーサー49を噛ませ切削刃支持版20に切削刃支持版取付ボルト46で固定している。
又、切削刃支持版固定スペーサー49と外殻作業筒腹版38との間に、土塊切取装置を設け、2基のワイヤーソー駆動モーター39でワイヤーソーを駆動し、固定滑車42と移動滑車41を複数個向い合せに組合せ、この間に本体ワイヤソーを抱き込んだ、伸縮可能な櫛状部を主構造とした巻取り装置設けており、この挙動を制御するためワイヤーソー弛取誘導レール44に納めている。
その櫛状部の端部から巻取り用ワイヤ伸ばし、一定の張力を超えるとON,OFF出来るバネスイッチ持ったワイヤーソー弛取モーター43に繋ぎ、櫛状部の間隔を広げこの部分に余分なワイヤソーを収納する。
一度切断を終えた場合は、土塊を排除し、ワイヤソーを設置し直す・
The embodiment shown in FIG. 6 is a side view of the tip cutting part, and the driving force is transmitted to the driving force transmission planetary gear 26 by the driving force transmission rod 25 having a high pressure water pipe 35 at the center and a transmission rod tip gear 37 at the tip. In order to protect these series of cutting mechanisms, a cutting blade support plate fixing spacer 49 is bitten and fixed to the cutting blade support plate 20 with a cutting blade support plate mounting bolt 46.
Further, a lump cutting device is provided between the cutting blade support plate fixing spacer 49 and the outer shell work cylinder belly plate 38, and the wire saw is driven by two wire saw drive motors 39, and the fixed pulley 42 and the movable pulley 41 are provided. A winding device with a comb-shaped part that can be expanded and contracted, with the main body wire saw held between them, is provided in the main structure, and is placed in the wire saw loosening guide rail 44 to control this behavior. ing.
The wire for winding is extended from the end of the comb-like part and connected to a wire saw loosening motor 43 having a spring switch that can be turned ON / OFF when a certain tension is exceeded, and the space between the comb-like parts is widened to an extra wire saw. Storing.
Once you have finished cutting, remove the clod and re-install the wire saw.

図7に示す実施例は、作業筒駆動機械室横断図であり、作業筒機械室筺体54は剛性を高めるため外殻作業筒9と一体化するための筺体補剛スチッフナー55で筺体と連結する。
その4隅に切削の機動力を発生する駆動モーター50を設置し、また左右の架台支柱と接する側の隣り合う筺体補剛スチッフナー55との間に、着脱出来る油圧ジャッキ取付ボルト59を介して、推進(又は後退)用の作業筒油圧ジャッキ60を設置する。
油圧ジャッキ60の反力部材として、H形鋼支柱7の間を3枚一組の反力伝達スチフナー56で連結し剛性高め、この間に着脱出来る油圧ジャッキ取付ボルト59を介して油圧ジャッキの頭部(又は端部)を取付け、架台全体で大きな反力に抵抗させる。
また、各階の梁桁に作業筒鋼床版桁58を連結し、作業筒の荷重を支えると共に、作業筒の移動の為移動用ベアリング34を持った作業筒誘導受レール57を設け移動の円滑を図っている。
The embodiment shown in FIG. 7 is a cross-sectional view of the work cylinder drive machine room, and the work cylinder machine room housing 54 is connected to the housing by a housing stiffening stiffener 55 for integration with the outer shell work tube 9 in order to increase rigidity. .
A drive motor 50 for generating cutting mobility is installed at the four corners, and between the adjacent frame stiffener stiffeners 55 on the side in contact with the left and right gantry columns, via a detachable hydraulic jack mounting bolt 59, A work cylinder hydraulic jack 60 for propulsion (or retreat) is installed.
As the reaction force member of the hydraulic jack 60, the H-shaped steel struts 7 are connected by a set of three reaction force transmission stiffeners 56 to increase the rigidity, and the head of the hydraulic jack is attached via a hydraulic jack mounting bolt 59 that can be attached and detached between them. Attach (or end) and resist a large reaction force on the whole frame.
In addition, a work cylinder steel slab girder 58 is connected to the beam girder on each floor to support the load of the work cylinder, and a work cylinder guide receiving rail 57 having a moving bearing 34 for moving the work cylinder is provided for smooth movement. I am trying.

図8に示す実施事例は、作業筒閉鎖扉断面図であり、作業筒機械室筺体54の最後尾に閉鎖扉取付金具61を介して開閉でき、閉鎖扉ハンドル85で閉鎖できるよう取付、作業フロアーの水密性を図るとともに、外殻作業筒9に収納された高圧水管35への高圧水の供給、集泥菅から汚泥の収集のため、吸泥ポンプ65を持った集泥槽66を備え、総排泥管63から排水溝4へ排出している。
図9の実施事例は作業筒閉鎖扉のD−D断面図であり、扉開閉に伴う接続の破断に適応できるよう、フレキシブルホースと連結した集泥菅取付ヘッド68および高圧水取付ヘッド69を介して外殻作業筒9と接続している。
外部からの電力、高圧水道供給、コンピューター等への信号線もこの扉から供給する。
The working example shown in FIG. 8 is a cross-sectional view of a work cylinder closing door, which can be opened and closed at the rearmost end of the work cylinder machine chamber housing 54 via a closing door mounting bracket 61 and can be closed with a closing door handle 85. In addition, a mud collection tank 66 having a mud pump 65 is provided for supplying high pressure water to the high pressure water pipe 35 accommodated in the outer shell work cylinder 9 and collecting sludge from the mud collection tank. It is discharged from the total mud pipe 63 to the drainage groove 4.
9 is a cross-sectional view taken along the line DD of the work cylinder closing door, and is provided with a mud drainage attachment head 68 and a high-pressure water attachment head 69 connected to a flexible hose so that it can be adapted to breakage of the connection accompanying opening and closing of the door. The outer shell work cylinder 9 is connected.
Electric power from outside, high-pressure water supply, and signal lines to computers are also supplied from this door.

図10の実施例は作業筒閉鎖扉の立体図である。 The embodiment of FIG. 10 is a three-dimensional view of a work cylinder closing door.

図11の実施例は作業筒の立体図である。
作業筒最後尾には、作業筒機械室筺体54を備え、駆動モーター50の動力を駆動力伝達歯車51、伝達ロッド後部歯車52を介し、駆動力伝達ロッド25に伝達されている。
また、3枚一組の筺体補剛スチフナー55と、反力伝達スチフナー56の間を油圧ジャッキ60で、油圧ジャッキ取付ボルト59を介して連結している。
運転作業部と切削作業部の境界には作業筒支持環状受枠70で作業筒を支持し作業筒隔離壁71で地山と隔離しており、先端の切削刃17を正八角形の回転切削刃支持版20で支えている。
The embodiment of FIG. 11 is a three-dimensional view of a work cylinder.
A work cylinder machine room housing 54 is provided at the end of the work cylinder, and the power of the drive motor 50 is transmitted to the drive force transmission rod 25 via the drive force transmission gear 51 and the transmission rod rear gear 52.
Further, a set of three frame stiffeners 55 and the reaction force transmission stiffener 56 are connected by a hydraulic jack 60 via a hydraulic jack mounting bolt 59.
A work cylinder is supported by a work cylinder support annular receiving frame 70 at the boundary between the operation work section and the cutting work section, and is isolated from a natural ground by a work cylinder isolation wall 71, and the cutting blade 17 at the tip is supported by a regular octagonal rotary cutting blade. It is supported by the plate 20.

図12の実施例は作業筒先進後退全断面掘削工法の全体概要図である。 The embodiment of FIG. 12 is an overall schematic diagram of the work cylinder advanced retreat full-section excavation method.

図13の実施例は、作業筒先進後退全断面掘削工法の作業工程図である。 The embodiment of FIG. 13 is a work process diagram of the work cylinder advanced retreat full-section excavation method.

図14の実施例は、多用途作業孔の立体図である。
連続した削孔で構造が弱体化するため多用途作業孔支持版87を添接し、これに削孔しネジ状の多用途作業孔蓋86で内側から閉じている。
The embodiment of FIG. 14 is a three-dimensional view of a versatile work hole.
Since the structure is weakened by continuous drilling, a multipurpose work hole support plate 87 is attached, and holes are drilled in this and closed from the inside with a screw-shaped multipurpose work hole lid 86.

図15の実施は作業筒構造立体図である。 内殻作業筒の端部には、内殻作業筒連結環90を配し、中空の筒内には軸方向に内殻作業筒腹版29とこれに直角に交わる円周方向に作業筒円周腹版38を配し、分割線92で2葉に分割、組立てるため、作業筒円周腹版38の間に分解・組立継手ロッド96嵌込み、固定ボルト97で連結している。
また、外殻作業筒の端部には、外殻作業筒連結環93を設け、駆動力伝達ロッド25の連結、排泥管の接続のため、連結カップリング94を配しこれを締付ける連結カップリング締付孔95を備えている。
15 is a three-dimensional view of the work cylinder structure. An inner shell working cylinder connecting ring 90 is arranged at the end of the inner shell working cylinder, and the inner cylinder working cylinder belly plate 29 is axially disposed in the hollow cylinder, and the working cylinder circle is formed in a circumferential direction perpendicular to this. In order to divide and assemble the peripheral plate 38 into two leaves at the dividing line 92, the disassembly / assembly joint rod 96 is fitted between the work tube peripheral plate 38 and connected by a fixing bolt 97.
Further, an outer shell working cylinder coupling ring 93 is provided at the end of the outer shell working cylinder, and a coupling cup 94 is disposed and tightened for coupling the driving force transmission rod 25 and the sludge pipe. A ring tightening hole 95 is provided.

トンネル地山が有用な岩石の場合は、一定規模の切出寸法を持つため、素材としての高付加価値化が図れる。 In the case of rocks where the tunnel ground is useful, it has a certain cut-out size, so it can increase the added value as a material.

本発明の主体である移動セントルは、二階建ての強固な鋼構造の架台であり、地山に挿入される作業筒も堅固で機能的な設計が可能であるため、坑内作業の安全性の向上はもとより、機械化による作業のオートメーション化の促進され、トンネル建設コストの削減が図れる。 The moving center that is the subject of the present invention is a two-story solid steel structure mount, and the work cylinder inserted into the natural ground can be designed firmly and functionally, improving the safety of underground work Besides, automation of work by mechanization is promoted, and tunnel construction cost can be reduced.

トンネルの標準横断図である。It is a standard cross section of a tunnel. 移動セントル断面図である。FIG. ロックボルト施工概念図である。It is a rock bolt construction conceptual diagram. 作業筒断面図である。It is work cylinder sectional drawing. 先端切削部縦断面図である。It is a front-end | tip cutting part longitudinal cross-sectional view. 先端切削部側面図である。It is a front end cutting part side view. 作業筒駆動機械室横断図である。It is a work cylinder drive machine room cross section. 作業筒閉鎖扉断面図である。It is sectional drawing of a work cylinder closing door. 作業筒閉鎖扉D−D断面図である。It is work cylinder closing door DD sectional drawing. 作業筒閉鎖扉立体図である。It is a three-dimensional view of a work cylinder closing door. 作業筒全体立体図である。FIG. 作業筒先進後退全断面掘削工法全体概要図である。It is a work cylinder advanced retreating whole section excavation method whole outline figure. 作業筒先進後退全断面掘削工法模式図である。 。It is a work cylinder advanced retreat full section excavation method schematic diagram. . 作業筒構造立体図であるFIG. 多用途作業孔立体図である。FIG.

符号の説明Explanation of symbols

0 建築限界線
1 歩道部
2 路肩部
3 車道部
4 排水溝
5 スキンプレート
6 セントルアーチリブ
7 H型鋼支柱
8 上部床版梁桁
9 外殻作業筒
10 内殻作業筒
11 駆動モーター収納部
12 下部床版梁桁
13 基礎台座
14 ロックボルト
15 ロックボルト施工線
16 ロックボルト打込位置
17 切削刃
18 上部切削刃保護鈑
19 切削刃回転軸
20 切削刃支持鈑
21 切削刃ベアリング
22 切削刃支持スペーサー
23 下部切削刃保護鈑
24 切削刃締付ボルト
25 駆動力伝達ロッド
26 駆動力伝達遊星歯車
27 遊星歯車回転軸
28 内殻作業筒内鈑
29 内殻作業筒腹鈑
30 内殻作業筒外鈑
31 外殻作業筒内鈑
32 外殻作業筒腹鈑
33 外殻作業筒外鈑
34 移動用ベアリング
35 高圧水管
36 排泥管
37 伝達ロッド先端歯車
38 外殻作業筒円周腹鈑
39 ワイヤソー駆動モーター
40 ワイヤソー繰出・引込口
41 移動滑車
42 固定滑車
43 ワイヤソー弛取モーター
44 ワイヤソー弛取誘導レール
45 ワイヤソー弛取装置
46 切削刃支持版取付ボルト
47 ワイヤソー収納部
48 ワイヤソーシャーピン
49 切削刃支持鈑固定スペーサー
50 駆動モーター
51 駆動力伝達歯車
52 伝達ロッド後部歯車
53 駆動モーター回転軸
54 作業筒機械室筐体
55 筐体補剛スチフナー
56 反力伝達スチフナー
57 作業筒誘導受レール
58 作業筒鋼床版桁
59 油圧ジャッキ取付ボルト
60 油圧ジャッキ(推進・後退)
61 閉鎖扉取付金具
62 閉鎖扉筐体
63 総排泥管
64 高圧水供給管
65 吸泥ポンプ
66 集泥槽
67 集泥管
68 集泥管取付ヘッド
69 高圧水管取付ヘッド
70 作業筒支持環状受枠
71 作業筒隔離壁
72 H型鋼製支保工
73 羽口止アンカー
74 羽口止ロックボルト
75 鏡面
76 ロックボルト打設機
77 断面整形掘削機
78 バックホー
79 重量物昇降機
80 上部フロア−
81 ベルトコンベア−
82 土砂運搬車
83 作業筒運搬車
84 引込線レール
85 閉鎖扉ハンドル
86 多用途作業孔蓋
87 多用途作業孔蓋支持鈑
88 止めネジ
89 覆工コンクリート
90 内殻作業筒連結環
91 内殻作業筒連結ボルト孔
92 分割線
93 外殻作業筒連結環
94 連結カップリング
95 連結カップリング締付孔
96 分解・組立継手ロッド
97 固定ボルト







0 Building limit line 1 Sidewalk
2 shoulder
3 Roadway
4 Drainage channel
5 Skin plate
6 Centar Arch Rib
7 H-shaped steel column
8 Upper floor slab beam girder
9 Outer shell cylinder
10 Inner shell cylinder
11 Drive motor storage
12 Lower floor slab beam 13 Base pedestal 14 Rock bolt 15 Lock bolt installation line 16 Lock bolt driving position 17 Cutting blade 18 Upper cutting blade protection rod 19 Cutting blade rotating shaft 20 Cutting blade support rod 21 Cutting blade bearing
DESCRIPTION OF SYMBOLS 22 Cutting blade support spacer 23 Lower cutting blade protection rod 24 Cutting blade clamping bolt 25 Driving force transmission rod 26 Driving force transmission planetary gear 27 Planetary gear rotating shaft 28 Inner shell working cylinder inner rod 29 Inner shell working cylinder stomach rod 30 Inner shell Work tube outer rod 31 Outer shell work tube inner rod 32 Outer shell work tube inner rod 33 Outer shell work tube outer rod 34 Moving bearing
35 High pressure water pipe
36 Drainage pipe 37 Transmission rod tip gear
38 outer shell work cylinder circumferential belly 39 wire saw drive motor 40 wire saw feeding / retracting port 41 moving pulley 42 fixed pulley 43 wire saw loosening motor 44 wire saw loosening guide rail 45 wire saw loosening device 46 cutting blade support plate mounting bolt 47 wire saw Storage portion 48 Wire saw shear pin 49 Cutting blade support rod fixing spacer 50 Drive motor 51 Drive force transmission gear 52 Transmission rod rear gear 53 Drive motor rotating shaft 54 Work cylinder machine room housing 55 Housing stiffening stiffener 56 Reaction force transmission stiffener 57 Work Cylinder guide receiving rail 58 Work cylinder steel floor girder 59 Hydraulic jack mounting bolt 60 Hydraulic jack (promotion / retraction)
61 Closing door mounting bracket 62 Closing door casing 63 Total mud pipe 64 High pressure water supply pipe
65 Mud pump
66 Mud collection tank 67 Mud collection pipe 68 Mud collection pipe mounting head 69 High-pressure water pipe mounting head 70 Work tube support annular receiving frame 71 Work tube isolation wall 72 H-type steel support 73 Feather stop anchor 74 Feather stop lock bolt 75 Mirror surface 76 Rock bolt driving machine 77 Cross-section shaping excavator
78 Backhoe
79 Heavy lifting equipment
80 Upper floor
81 Belt conveyor
82 Sediment transporter
83 Work tube carrier 84 Service line rail 85 Closing door handle
86 Multipurpose work hole lid
87 Multipurpose work hole lid support rod 88 Set screw 89 Clay concrete
90 Inner shell cylinder connection ring
91 Inner shell work cylinder connection bolt hole
92 dividing line
93 Outer shell connection ring
94 Coupling coupling
95 Connection coupling tightening hole
96 Disassembly / Assembly Joint Rod
97 Fixing bolt







Claims (5)

外殻作業筒内部に駆動力伝達ロッドを持ち、これを介し先端掘削部を駆動し、内殻作業筒に掘削土塊を収容出来る2重構造の作業筒 A double-structured work cylinder that has a driving force transmission rod inside the outer shell work cylinder, drives the tip excavation section via this rod, and can hold the excavated soil mass in the inner shell work cylinder 外殻作業筒の先端全円周を、偶数正多角形に分割し、その辺に沿って独立して回転出来る切削刃を持った切削部を有する外殻作業筒。 An outer shell working cylinder having a cutting portion having a cutting blade that can divide the entire circumference of the tip of the outer shell working cylinder into even regular polygons and independently rotate along the sides thereof. 切削部の直後に土塊をワイヤーソーで切断する為の、向合った櫛状のワイヤーソー弛取器を備えた土塊切断装置を有する外殻作業筒。 An outer shell working cylinder having an earth lump cutting device provided with a facing comb-shaped wire saw loosening device for cutting an earth lump with a wire saw immediately after a cutting portion. 外殻作業筒にネジ状の多用途作業孔を有する外殻作業筒。 An outer shell cylinder having a screw-like multipurpose work hole in the outer shell cylinder. 請求項1、2、3および4を有する作業筒を備えた掘削装置によるトンネルの作業筒先進全断面後退掘削工法。 A tunnel working cylinder advanced full-section receding excavation method by a drilling device provided with a working cylinder having claims 1, 2, 3 and 4.
JP2007005822A 2007-01-15 2007-01-15 Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel Pending JP2007138702A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007005822A JP2007138702A (en) 2007-01-15 2007-01-15 Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007005822A JP2007138702A (en) 2007-01-15 2007-01-15 Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2005335265A Division JP4070143B2 (en) 2005-11-21 2005-11-21 Double-structure work tunnel and tunnel work cylinder advanced full-section receding excavation method

Publications (1)

Publication Number Publication Date
JP2007138702A true JP2007138702A (en) 2007-06-07

Family

ID=38201903

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007005822A Pending JP2007138702A (en) 2007-01-15 2007-01-15 Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel

Country Status (1)

Country Link
JP (1) JP2007138702A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233747A (en) * 2013-04-24 2013-08-07 上海隧道工程股份有限公司 Pre-drilling launcher
CN103410522A (en) * 2013-08-27 2013-11-27 中铁十三局集团第四工程有限公司 Continuous close-range underpass railway bridge construction method employing shallow tunneling method
CN106050130A (en) * 2016-06-30 2016-10-26 浙江海聚科技有限公司 Advance drilling method
CN110965585A (en) * 2019-12-25 2020-04-07 中铁建设集团市政工程有限公司 Multi-multi-arch rectangular tunnel arch division construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103233747A (en) * 2013-04-24 2013-08-07 上海隧道工程股份有限公司 Pre-drilling launcher
CN103410522A (en) * 2013-08-27 2013-11-27 中铁十三局集团第四工程有限公司 Continuous close-range underpass railway bridge construction method employing shallow tunneling method
CN106050130A (en) * 2016-06-30 2016-10-26 浙江海聚科技有限公司 Advance drilling method
CN110965585A (en) * 2019-12-25 2020-04-07 中铁建设集团市政工程有限公司 Multi-multi-arch rectangular tunnel arch division construction method

Similar Documents

Publication Publication Date Title
WO2018082714A1 (en) Shield tunneling machine for tunnel connecting passageway and connecting passageway tunneling method thereof
US20230193758A1 (en) Tunnelling shield
JP2023113780A (en) Method and system for constructing underground tunnel
JP4070143B2 (en) Double-structure work tunnel and tunnel work cylinder advanced full-section receding excavation method
CN110529136A (en) Municipal blow-off line pipe jacking construction method
JP4181980B2 (en) Tunnel construction method
JP2007138702A (en) Excavation construction method for forward advance of working cylinder and retraction of all cross sections in tunnel
WO2001023711A1 (en) Ground reinforcing method
JPH06235296A (en) Self-advancing type tunnel excavator
JP3874095B2 (en) Wellhead formation method and shield machine when reaching shield machine
JP2002266598A (en) Shield tunneling method, large-sectional tunnel, method for constructing the same, and shield machine
CN114754194A (en) Storage tank top pipe installation device and construction method thereof
KR101237749B1 (en) Propulsion unit head that is used in shield method
KR100977212B1 (en) Horizontal ring type rotary drill system and method using the same
JP2596802B2 (en) Ring cut excavator
JP4731463B2 (en) Tunnel excavator and tunnel excavation method
JP4731464B2 (en) Tunnel excavator and tunnel excavation method
JP4334954B2 (en) Method and apparatus for widening underground space
JPH06100080B2 (en) Large-section tunnel construction method and ground solidification column construction device
CN118187888A (en) Shield cutter head cleaning method
JP2604623B2 (en) Ring cut excavator
JP2003214091A (en) Tunnel boring machine
JPH09144475A (en) Excavator
JP2014156691A (en) Tunnel construction method
JPH0730672B2 (en) Reconstruction method of existing underdrain