JP2007072747A - Production schedule preparation method, production schedule preparation device and program - Google Patents

Production schedule preparation method, production schedule preparation device and program Download PDF

Info

Publication number
JP2007072747A
JP2007072747A JP2005258889A JP2005258889A JP2007072747A JP 2007072747 A JP2007072747 A JP 2007072747A JP 2005258889 A JP2005258889 A JP 2005258889A JP 2005258889 A JP2005258889 A JP 2005258889A JP 2007072747 A JP2007072747 A JP 2007072747A
Authority
JP
Japan
Prior art keywords
resource
resources
job
dummy
production plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005258889A
Other languages
Japanese (ja)
Other versions
JP4648136B2 (en
Inventor
Nobuyuki Odera
信行 大寺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2005258889A priority Critical patent/JP4648136B2/en
Publication of JP2007072747A publication Critical patent/JP2007072747A/en
Application granted granted Critical
Publication of JP4648136B2 publication Critical patent/JP4648136B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method or the like for preparing an efficient production schedule by allocating resources to the jobs of a plurality of orders on the basis of a resource operation calendar. <P>SOLUTION: Order information is registered in an order instruction table 10, product information is registered in a product master 11, step information is registered in a process master 12, the information of normal resources and dummy resources is registered in a resource master 20, the information of the operation time of the normal resources and the dummy resources is registered in the resource operation calendar 21, result information is registered in a result information table 22, and the schedule date and time are initialized (S1 and S2). The order is obtained from the order instruction table 10, is developed into the job to be executed from the product master 11, the step master 12 and the resource master 20, and is registered in a non-allocated job list 13 (S3). On the basis of the logic that allocation to the job of a certain order is possible = it is within the operation time of main resources, it is within the operation time of sub resources and also it is within the operation time of dummy resources, the processing of allocating the normal resources and the dummy resources to the job is executed (S4-S9). <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成方法及び生産計画作成装置、並びにプログラムに関する。   In one or more orders, the present invention allocates resources that can be allocated to a job based on a resource operation calendar to produce all the jobs that are processes necessary to manufacture a product of the order. The present invention relates to a production plan creation method, a production plan creation device, and a program for creating a plan.

従来から、製造業において多工程から構成される生産プロセスにおいては、複数のオーダーを生産するのに、複数のオーダーと当該オーダーの製品を製造するのに必要な工程との組み合わせであるジョブを資源稼動カレンダーに基づきスケジューリングして作成する生産計画が重要である。   Traditionally, in a manufacturing process consisting of multiple processes in the manufacturing industry, a job that is a combination of multiple orders and the processes necessary to manufacture the products of that order is a resource to produce multiple orders. A production plan that is scheduled based on an operating calendar is important.

例えば、従来技術として、要員に関する情報と、設備(資源)に関する情報と、工程に関する情報と、オーダーに関する情報とを参照し、オーダー毎にオーダーに対応した中間体の内のいずれかを得るための工程であるシリーズに基づき、スケジューリング時の割付単位に対応するロット毎のジョブを生成し、ジョブの割付可能な設備、生産能力および必要な要員を取得してジョブをカレンダー(資源稼動カレンダー)に割り付ける生産工程スケジューラという技術が特許文献1に開示されている。   For example, as a prior art, referring to information on personnel, information on equipment (resources), information on processes, and information on orders, to obtain any of the intermediates corresponding to the orders for each order Based on the series of processes, a job for each lot corresponding to the allocation unit at the time of scheduling is generated, the equipment, the production capacity, and the necessary personnel that can be allocated to the job are acquired, and the job is allocated to a calendar (resource operation calendar). A technique called a production process scheduler is disclosed in Patent Document 1.

また、部品、工程、機械、治具に関する固有の情報と、機械(資源)毎の稼動時間タイプに関する情報と、割付の制約条件に関する情報とを参照し、納期優先ルールと稼働率優先ルールを適用して、部品の製造指示を分解した各ジョブを機械毎にカレンダー(資源稼動カレンダー)にしたがって割り付けるジョブショップスケジューリングエキスパートシステムという技術が特許文献2に開示されている。   In addition, refer to specific information on parts, processes, machines, and jigs, information on operating time types for each machine (resource), and information on allocation constraints, and apply delivery priority rules and operating rate priority rules Patent Document 2 discloses a technique called a job shop scheduling expert system that assigns each job obtained by disassembling parts manufacturing instructions according to a calendar (resource operation calendar) for each machine.

特開平11−66181号公報JP-A-11-66181 特開平5−174030号公報JP-A-5-174030

ここで、従来技術において、スケジューリングの結果、あるオーダーが納期遅れとなることが判った場合、通常、計画担当者は資源稼動カレンダーを操作して、納期遅れの解消を図る。具体的には、納期遅れの発生するオーダーのジョブ(どのジョブとは特定できないが、現実の制約を勘案した上で、最も効果的に納期遅れを解消できると思われるジョブを選択する。)で使用する資源(人、設備等)の稼働時間を増やし(例えば、資源が人であれば残業あるいは休日出勤を設定し、資源が設備であれば稼動時間の延長あるいは休日の稼動時間を設定する)、或いは/且つ、資源量を増やす(例えば、資源が人であれば人数、資源が設備であれば台数等を増やす)ように資源稼動カレンダーを変更する。そして、変更した資源稼動カレンダーに基づいてジョブに資源を割り付けなおすことにより、遅れの発生したオーダーにおいては、延長された稼働時間と増強された資源量により、より早期に工程は完了し、納期遅れを解消する可能性がある。ここで、可能性があるとしたのは、優先度に基づいたジョブへの資源の割付において、他のオーダーのジョブの優先度が高い場合に、納期遅れの発生するオーダーのジョブに資源が割り付けない場合があるからである。   Here, in the prior art, when it is found as a result of scheduling that an order is delayed in delivery, the planner usually operates the resource operation calendar to eliminate the delay in delivery. Specifically, in the job of the order where the delivery date is delayed (which job cannot be identified, select the job that is considered to be able to resolve the delivery date most effectively in consideration of actual restrictions). Increase the working hours of the resources (people, equipment, etc.) to be used (for example, if the resources are people, set overtime or holiday work, and if the resources are equipment, set up the working hours or set the working hours on holidays) Alternatively, and / or change the resource operation calendar so as to increase the amount of resources (for example, increase the number of people if the resource is a person, increase the number of resources if the resource is equipment). Then, by reallocating resources to jobs based on the changed resource operation calendar, in the case of delayed orders, the process is completed earlier due to the extended operation time and the increased amount of resources. May be eliminated. Here, there is a possibility that when resources are assigned to jobs based on priorities, resources are assigned to jobs in the order where delivery is delayed if the job priority of other orders is high. Because there may be no.

その一方で、資源稼動カレンダーは、人や設備などの資源の資源名、稼働時間、資源量の情報が含まれており、全てのオーダーについて平等に適用されるため、納期遅れの発生するオーダーのジョブだけでなく、稼働時間が延長され、或いは/且つ、資源量が増強された資源を使用する納期遅れが発生していない他の全てのオーダーのジョブにも当該資源が割り付けられ、完成日時が早まる場合がある。即ち、本来稼動する必要のなかった資源も稼動することになり、生産計画に無駄が生じる。   On the other hand, the resource operation calendar contains resource name, operation time, and resource amount information for resources such as people and equipment, and is applied equally to all orders. Not only jobs, but also resources of all other orders that have a longer working time and / or use resources with an increased amount of resources and that have not been delayed in delivery are assigned to these resources. It may be early. That is, resources that were not originally required to operate are also operated, resulting in wasteful production planning.

本発明は、上記問題点に鑑みてなされたものであり、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて生産計画を作成する際に、無駄のない生産計画を作成することができる生産計画作成方法及び生産計画作成装置、並びにプログラムを提供するものである。   The present invention has been made in view of the above problems, and in one or more orders, for all jobs that are processes necessary to manufacture products of the order, based on the resource operation calendar, The present invention provides a production plan creation method, a production plan creation apparatus, and a program that can create a production plan without waste when creating a production plan by allocating resources that can be assigned to the job.

課題を解決するための手段及び効果Means and effects for solving the problems

上記課題を解決するために、第一の発明に係る生産計画作成装置は、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成装置であって、全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を資源として登録する資源登録手段と、前記通常資源の稼働時間及び前記ダミー資源の稼働時間を資源稼動カレンダーに設定する資源稼動カレンダー登録手段と、前記資源稼動カレンダーに基づいて、前記ジョブの内の前記通常資源及び前記ダミー資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記通常資源及び前記ダミー資源を割り付けるジョブ割り付け手段と、を備えることを特徴とする。   In order to solve the above-described problem, the production plan creation device according to the first invention operates resources for all jobs that are necessary for manufacturing a product of the order in one or more orders. A production plan creation device that creates a production plan by allocating resources that can be assigned to the job based on a calendar. It is a normal resource that can be applied to all orders, and an order-specific dummy that can be applied to a specific order. Resource registration means for registering resources as resources, resource operation calendar registration means for setting the operation time of the normal resource and the operation time of the dummy resource in a resource operation calendar, and the job based on the resource operation calendar The unallocated jobs to which the normal resources and the dummy resources are not allocated are selected in order by a predetermined allocation algorithm, and allocated. A job assignment means for assigning the normal resources and the dummy resource available, characterized in that it comprises a.

第一の発明に係る生産計画作成方法は、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成方法であって、全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を資源として登録する資源登録ステップと、前記通常資源の稼働時間及び前記ダミー資源の稼働時間を資源稼動カレンダーに設定する資源稼動カレンダー登録ステップと、前記資源稼動カレンダーに基づいて、前記ジョブの内の前記通常資源及び前記ダミー資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記通常資源及び前記ダミー資源を割り付けるジョブ割り付けステップと、を備えることを特徴とする。   In one or more orders, the production plan creation method according to the first aspect of the invention assigns all jobs, which are processes necessary for manufacturing the products of the order, to the jobs based on the resource operation calendar. A production plan creation method that allocates possible resources and creates a production plan, and registers normal resources applicable to all orders and order-specific dummy resources applicable to specific orders as resources. A resource registration step; a resource operation calendar registration step for setting an operation time of the normal resource and an operation time of the dummy resource in a resource operation calendar; and the normal resource in the job and the job based on the resource operation calendar The non-allocated jobs to which no dummy resources are allocated are selected in order using a predetermined allocation algorithm, and the normal resources that can be allocated are selected. And characterized in that it and a job assignment step of allocating said dummy resource.

第一の発明に係るプログラムは、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成するためのプログラムであって、全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を資源として登録する資源登録ステップ、前記通常資源の稼働時間及び前記ダミー資源の稼働時間を資源稼動カレンダーに設定する資源稼動カレンダー登録ステップ、前記資源稼動カレンダーに基づいて、前記ジョブの内の前記通常資源及び前記ダミー資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記通常資源及び前記ダミー資源を割り付けるジョブ割り付けステップ、をコンピュータに実行させることを特徴とする。   In one or more orders, the program according to the first invention is a resource that can be allocated to a job based on a resource operation calendar for all jobs that are processes required to manufacture a product of the order. A resource registration step for registering as a resource a normal resource that can be applied to all orders and an order-specific dummy resource that can be applied to a specific order. A resource operation calendar registration step for setting an operation time of the normal resource and an operation time of the dummy resource in a resource operation calendar, and the normal resource and the dummy resource in the job are not allocated based on the resource operation calendar The unallocated jobs are selected in order by a predetermined allocation algorithm, and the normal resources that can be allocated and the Characterized in that to execute the job assignment step of allocating Me resources to the computer.

これによると、資源として、全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を設けたことにより、オーダー毎に資源稼動カレンダーの稼働時間をコントロールが可能となる。尚、通常資源は、実在する設備や人であるが、ダミー資源は、実在する設備や人ではない。即ち、特定のオーダーに適用可能なオーダー固有のダミー資源を設けたことによる、資源稼動カレンダーに基づいたジョブに通常資源及びダミー資源を割り付ける条件は下記の通りとなる。
条件1:ある通常資源又はダミー資源が割付可能=ジョブが必要とする稼働時間が通常資源又はダミー資源にあり、且つ、ジョブが必要とする資源量が通常資源又はダミー資源にある。
条件2:ジョブに必要な通常資源及びダミー資源が共に割付可能である。
以上の条件により、あるオーダーのジョブに割付可能な通常資源及びダミー資源の時間は、通常資源の稼働時間且つダミー資源の稼働時間になる。従って、資源稼動カレンダーにおいて、稼働時間の操作をしたい通常資源については、その稼働時間を最大限に稼動可能な状態とすることにより、ダミー資源の稼働時間の設定が支配的になり、ダミー資源の稼働時間の設定を調整することでオーダーのジョブを割付可能な時間をコントロールすることが可能になり、適切に納期遅れを解消することができ、無駄のない生産計画を作成することができる。尚、所定の割付アルゴリズムは、従来技術の割付アルゴリズムを適用するものとし、例えば、オーダー毎に設定した工程優先度による優先順位計画アルゴリズム等である。
According to this, normal resources that can be applied to all orders and dummy resources specific to orders that can be applied to specific orders are provided as resources, so that the operation time of the resource operation calendar can be controlled for each order. It becomes possible. Note that the normal resource is an existing facility or person, but the dummy resource is not an actual facility or person. That is, the conditions for allocating the normal resource and the dummy resource to the job based on the resource operation calendar by providing the order-specific dummy resource applicable to the specific order are as follows.
Condition 1: A certain normal resource or dummy resource can be allocated = the operation time required by the job is in the normal resource or dummy resource, and the resource amount required by the job is in the normal resource or dummy resource.
Condition 2: Both normal resources and dummy resources necessary for a job can be allocated.
Due to the above conditions, the time of the normal resource and the dummy resource that can be assigned to a job of an order becomes the operation time of the normal resource and the operation time of the dummy resource. Therefore, in the resource operation calendar, setting the operation time of the dummy resource becomes dominant by setting the operation time to the maximum operation state for the normal resource for which the operation time is desired. By adjusting the setting of the operation time, it becomes possible to control the time for which the job of the order can be allocated, the delivery time delay can be properly eliminated, and a production plan without waste can be created. Note that the predetermined allocation algorithm is a conventional allocation algorithm, such as a priority planning algorithm based on process priority set for each order.

ここで、第一の発明に係る生産計画作成装置は、前記資源登録手段で登録するダミー資源が、その一部または全部が特定のオーダーの特定のジョブに割付可能であって良い。   Here, in the production plan creation device according to the first invention, a part or all of the dummy resources registered by the resource registration means may be assignable to a specific job of a specific order.

第一の発明に係る生産計画作成方法は、前記資源登録ステップで登録するダミー資源が、その一部または全部が特定のオーダーの特定のジョブに割付可能であって良い。   In the production plan creation method according to the first invention, a part or all of the dummy resources registered in the resource registration step may be assigned to a specific job of a specific order.

第一の発明に係るプログラムは、記資源登録ステップで登録するダミー資源が、その一部または全部が特定のオーダーの特定のジョブに割付可能であって良い。   In the program according to the first aspect, a part or all of the dummy resources registered in the resource registration step may be assignable to a specific job in a specific order.

これによると、特定のオーダーに適用可能なオーダー固有のダミー資源の一部または全部を、特定のオーダーの稼働時間を操作したい特定のジョブに割付可能とすることにより、納期遅れを発生する特定のオーダーに対して確実にダミー資源が割り付けられるようになるため、より適切に納期遅れを解消することができ、無駄のない生産計画を作成することができる。   According to this, a part or all of the order-specific dummy resources that can be applied to a specific order can be assigned to a specific job that wants to operate the operating time of a specific order. Since dummy resources can be reliably assigned to orders, delays in delivery can be more appropriately eliminated, and a production plan without waste can be created.

また、第二の発明に係る生産計画作成装置は、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成装置であって、前記ジョブに割付可能な資源を登録する資源登録手段と、前記資源の稼働時間と適用可能な対象オーダーとを資源稼動カレンダーに設定する資源稼動カレンダー登録手段と、前記資源稼動カレンダーに基づいて、前記ジョブの内の前記資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記資源を割り付けるジョブ割り付け手段と、を備えることを特徴とする。   In addition, the production plan creation device according to the second aspect of the present invention, for one or more orders, for all jobs that are processes necessary to manufacture a product of the order, based on the resource operation calendar, A production plan creation device for creating a production plan by allocating resources that can be allocated to the resource, resource registration means for registering resources that can be allocated to the job, operating time of the resources, and applicable target orders Resource operation calendar registration means to be set in the resource operation calendar, and based on the resource operation calendar, unallocated jobs that are not allocated the resource among the jobs are sequentially selected by a predetermined allocation algorithm, and can be allocated Job allocating means for allocating resources.

第二の発明に係る生産計画作成方法は、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成方法であって、前記ジョブに割付可能な資源を登録する資源登録ステップと、前記資源の稼働時間と適用可能な対象オーダーとを資源稼動カレンダーに設定する資源稼動カレンダー登録ステップと、前記資源稼動カレンダーに基づいて、前記ジョブの内の前記資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記資源を割り付けるジョブ割り付けステップと、を備えることを特徴とする。   In one or more orders, the production plan creation method according to the second aspect of the invention assigns to all jobs that are processes necessary to manufacture products of the order based on the resource operation calendar. A production plan creation method for allocating possible resources and creating a production plan, wherein a resource registration step for registering resources that can be allocated to the job, resource operation time and applicable target orders A resource operation calendar registration step to be set in a calendar, and based on the resource operation calendar, unallocated jobs that have not been allocated the resource among the jobs are sequentially selected by a predetermined allocation algorithm, and the resources that can be allocated are selected. An allocating job allocating step.

第二の発明に係るプログラムは、1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成するためのプログラムであって、前記ジョブに割付可能な資源を登録する資源登録ステップ、前記資源の稼働時間と適用可能な対象オーダーとを資源稼動カレンダーに設定する資源稼動カレンダー登録ステップ、前記資源稼動カレンダーに基づいて、前記ジョブの内の前記資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記資源を割り付けるジョブ割り付けステップ、をコンピュータに実行させることを特徴とする。   In one or more orders, the program according to the second invention is a resource that can be allocated to a job based on a resource operation calendar for all jobs that are processes required to manufacture a product of the order. A resource registration step for registering resources that can be allocated to the job, and a resource for setting the resource operation time and applicable target order in a resource operation calendar An operation calendar registration step, based on the resource operation calendar, an unallocated job that has not been allocated the resource among the jobs is sequentially selected by a predetermined allocation algorithm, and a job allocation step that allocates the resources that can be allocated, The computer is executed.

これによると、資源稼動カレンダーの設定項目に適用可能な対象オーダーが加えられることにより、ジョブに資源を割り付ける際に、対象オーダーに設定された特定のオーダーにおいてのみ稼働時間の設定が有効になり、ジョブへの資源の割付の制御(割付可能/不可能の制御)が可能になるため、適切に納期遅れを解消することができ、無駄のない生産計画を作成することができる。尚、所定の割付アルゴリズムは、従来技術の割付アルゴリズムを適用するものとし、例えば、オーダー毎に設定した工程優先度による優先順位計画アルゴリズム等である。   According to this, the applicable order is added to the setting item of the resource operation calendar, so when assigning resources to jobs, the operation time setting is effective only for the specific order set in the target order, Since it is possible to control the allocation of resources to jobs (control to enable / disable allocation), it is possible to properly eliminate delays in delivery and create a production plan without waste. Note that the predetermined allocation algorithm is a conventional allocation algorithm, such as a priority planning algorithm based on process priority set for each order.

ここで、第一の発明又は第二の発明に係る生産計画作成装置は、前記資源稼動カレンダー登録手段が、前記資源の資源量を更に資源稼動カレンダーに設定して良い。   Here, in the production plan creation device according to the first invention or the second invention, the resource operation calendar registration means may further set the resource amount of the resource in the resource operation calendar.

第一の発明又は第二の発明に係る生産計画作成方法は、前記資源稼動カレンダー登録ステップが、前記資源の資源量を更に資源稼動カレンダーに設定して良い。   In the production plan creation method according to the first invention or the second invention, the resource operation calendar registration step may further set the resource amount of the resource in the resource operation calendar.

第一の発明又は第二の発明に係るプログラムは、前記資源稼動カレンダー登録ステップが、前記資源の資源量を更に資源稼動カレンダーに設定して良い。   In the program according to the first invention or the second invention, the resource operation calendar registration step may further set the resource amount of the resource in the resource operation calendar.

これによると、資源稼動カレンダーの設定項目に資源量が加えられることにより、資源量を変えることができる資源についても対応することが可能になる。   According to this, by adding the resource amount to the setting item of the resource operation calendar, it becomes possible to cope with the resource that can change the resource amount.

尚、第一の発明又は第二の発明に係るプログラムは、CD−ROM(Compact Disc Read Only Memory)、DVD(Digital Versatile Disk)などのリムーバブル型記録媒体やハードディスクなどの固定型記録媒体に記録して配布可能である他、有線又は無線の電気通信手段によってインターネットなどの通信ネットワークを介して配布可能である。   The program according to the first or second invention is recorded on a removable recording medium such as a CD-ROM (Compact Disc Read Only Memory) or DVD (Digital Versatile Disk) or a fixed recording medium such as a hard disk. In addition to the distribution method, it can be distributed via a communication network such as the Internet by wired or wireless telecommunication means.

以下、図面を参照しつつ、本発明である生産計画作成方法及び生産計画作成装置、並びにプログラムを実施するための最良の形態について、具体的な一例に即して説明する。   The best mode for carrying out the production plan creation method, production plan creation apparatus, and program according to the present invention will be described below with reference to a specific example with reference to the drawings.

本実施形態では、加工機、作業者、治工具などの資源を用いて、複数工程を経て完成する生産ラインを対象とする。ここで、製品の工程数は製品の種類により異なり、各工程で必要となる資源はあらかじめ決まっており、場合によっては代替可能な資源が複数ある。   In the present embodiment, a production line that is completed through a plurality of processes using resources such as a processing machine, an operator, and a tool is targeted. Here, the number of product processes varies depending on the type of product, and the resources required in each process are determined in advance, and there are a plurality of substitutable resources depending on circumstances.

[第一の実施形態]
まず、第一の実施形態に係る生産計画スケジューラ(生産計画装置)について、図1に基づいて説明する。図1は、第一の実施形態に係る生産計画スケジューラのブロック図である。図1に示すように生産計画スケジューラ1は、オーダー指示テーブル10と、製品マスタ11と、工程マスタ12と、未割付ジョブリスト13と、資源マスタ(資源登録手段)20と、資源稼動カレンダー(資源稼動カレンダー登録手段)21と、実績情報テーブル22と、資源割付部(ジョブ割付手段)2と、割付情報テーブル3と、割付対象ジョブテーブル4と、を備えている。生産は外部から与えられるオーダー指示に従って開始される。生産計画スケジューラ1は、与えられるオーダー指示を達成するために、製品の全工程の開始時刻及び終了時刻と、工程に使用する資源のリストからなる生産計画を作成するためのものである。
[First embodiment]
First, a production plan scheduler (production plan apparatus) according to the first embodiment will be described with reference to FIG. FIG. 1 is a block diagram of a production plan scheduler according to the first embodiment. As shown in FIG. 1, the production plan scheduler 1 includes an order instruction table 10, a product master 11, a process master 12, an unassigned job list 13, a resource master (resource registration means) 20, a resource operation calendar (resources). An operation calendar registration unit) 21, a performance information table 22, a resource allocation unit (job allocation unit) 2, an allocation information table 3, and an allocation target job table 4 are provided. Production is started according to order instructions given from the outside. The production plan scheduler 1 is for creating a production plan including a start time and an end time of all processes of a product and a list of resources used for the process in order to achieve a given order instruction.

オーダーテーブル10は、外部から与えられるオーダー指示に基づいて、生産すべき製品の数量と納期が指定されるものである。   The order table 10 designates the quantity and delivery date of products to be produced based on order instructions given from the outside.

製品マスタ11は、生産計画スケジューラ1が対象とする製品名及び製品を完成するための工程の連なりが登録されるものである。   In the product master 11, a product name and a series of processes for completing the product targeted by the production plan scheduler 1 are registered.

工程マスタ12は、製品の各工程情報が登録されるものである。ここで、工程情報とは、ある加工品を完成するために実施する工程の連なりに関する情報で、各工程に関して使用する資源、使用する資源の割合、工程に必要な時間等の情報が含まれる。   The process master 12 is for registering each process information of a product. Here, the process information is information related to a series of processes performed to complete a certain processed product, and includes information such as resources used for each process, a ratio of resources used, and a time required for the process.

資源マスタ(資源登録手段)20は、通常資源及びダミー資源の資源名、資源コード、資源の能力が登録されるものである。   The resource master (resource registration means) 20 is for registering the resource names, resource codes, and resource capabilities of normal resources and dummy resources.

資源稼動カレンダー(資源稼動カレンダー登録手段)21は、通常資源及びダミー資源の稼動可能な時間である稼動時間が登録されるものである。   The resource operation calendar (resource operation calendar registering means) 21 registers an operation time that is an operation time of the normal resource and the dummy resource.

実績情報テーブル22は、すでに生産計画に従って実施されたジョブの着手時刻、完了時刻、進捗率など、実測された実績情報が外部から登録されるものである。この実績情報は、生産計画開始時に読み込まれ、これを初期状態として生産計画を開始する。尚、全くの初期状態では、実績情報テーブル22は空であり、生産ラインがジョブを実行する都度、実績情報は増加する。   The actual result information table 22 is used to register actually measured actual result information such as the start time, completion time, and progress rate of a job that has already been performed according to the production plan. The actual information is read at the start of the production plan, and the production plan is started with this as the initial state. In a completely initial state, the record information table 22 is empty, and record information increases each time a production line executes a job.

未割付ジョブリスト13は、新たに生産計画を開始すると、オーダーテーブル10に含まれている生産すべき製品について、製品マスタ11と工程マスタ12を元にして実施すべきジョブを求め、既に生産ラインが生産を開始しており、実績情報に登録されているジョブを除外したものを保存するためのものである。尚、ジョブとは、生産ラインに存在する製品の工程を特定する呼び名である。   The unallocated job list 13 obtains a job to be executed based on the product master 11 and the process master 12 for a product to be produced included in the order table 10 when a production plan is newly started. Has started production, and saves jobs that have been excluded from jobs registered in the performance information. A job is a name for identifying a process of a product existing on a production line.

資源割付部(ジョブ割付手段)2は、未割付ジョブリスト13に含まれるジョブ群に割付アルゴリズムを適用し、資源稼動カレンダー21及び実績情報テーブル22に基づいて、ジョブへの通常資源及びダミー資源の割付を試行する。ここで、割付アルゴリズムは、オーダーに設定した優先順位に基づく優先順位計画を行う。即ち、割付アルゴリズムは、未割付ジョブリスト13から割付可能なジョブを割付対象ジョブとして抽出して割付対象ジョブテーブル4に保存し、割付対象ジョブテーブル4に保存した割付対象ジョブからオーダーに設定した優先順位に基づいて、通常資源及びダミー資源を割り付けるジョブを選択する。ジョブに通常資源及びダミー資源が割り付けられると、割付情報テーブル3に保存されるとともに、割付対象ジョブテーブル4が更新される。   The resource allocation unit (job allocation means) 2 applies an allocation algorithm to the job group included in the unallocated job list 13, and based on the resource operation calendar 21 and the result information table 22, the normal resource and dummy resource of the job are allocated. Attempt allocation. Here, the allocation algorithm performs a priority plan based on the priority set in the order. In other words, the allocation algorithm extracts jobs that can be allocated from the unallocated job list 13 as allocation target jobs, stores them in the allocation target job table 4, and sets priority from the allocation target jobs stored in the allocation target job table 4 to the order. Based on the rank, a job to which normal resources and dummy resources are allocated is selected. When a normal resource and a dummy resource are allocated to a job, the job is stored in the allocation information table 3 and the allocation target job table 4 is updated.

割付情報テーブル3は、ジョブ毎に割り付けた通常資源及びダミー資源と、開始日時及び終了日時を含む割付情報からなり、これは生産計画そのものである。尚、割付情報テーブル3は、図示しない出力用インタフェースを介して、生産計画スケジューラ1外部の出力装置(ディスプレイ、ハードディスク、またはプリンタ等)にて読み出しが可能である。尚、出力用インタフェースは、出力装置(ディスプレイ、ハードディスク、またはプリンタ等)に出力するためのデータ変換や通信を行うプログラム又はハードウェアである。   The allocation information table 3 includes allocation information including normal resources and dummy resources allocated for each job, start date and time, and end date and time, which is a production plan itself. The allocation information table 3 can be read by an output device (display, hard disk, printer, etc.) outside the production plan scheduler 1 via an output interface (not shown). Note that the output interface is a program or hardware that performs data conversion and communication for output to an output device (display, hard disk, printer, or the like).

次に、第一の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理の手順について、具体例を用いて図2に基づいて、説明する。図2は、第一の実施形態に係る生産計画スケジューラを用い生産計画作成方法の処理の手順について説明したフローチャートである。尚、以下で説明する第一の実施形態に係る生産計画作成方法の処理は、コンピュータにおいても同様に、プログラムとしてCPUにより読み出して実行することができる。また、このプログラムは、CD−ROMやFD、DVDなどのリムーバブルな記憶媒体に記録しておくことにより、様々なコンピュータの記憶装置にインストールすることが可能である。   Next, the processing procedure of the production plan creation method using the production plan scheduler according to the first embodiment will be described based on FIG. 2 using a specific example. FIG. 2 is a flowchart illustrating the processing procedure of the production plan creation method using the production plan scheduler according to the first embodiment. The process of the production plan creation method according to the first embodiment described below can be read and executed by the CPU as a program in the computer as well. Further, this program can be installed in various computer storage devices by recording it in a removable storage medium such as a CD-ROM, FD, or DVD.

図2に示すように、まず、オーダー指示テーブル10、製品マスタ11、工程マスタ12、資源マスタ20、資源稼動カレンダー21、実績情報テーブル22、に事前にデータを登録及び設定しておく(ステップS1:資源登録ステップ、資源稼動カレンダー登録ステップ)。   As shown in FIG. 2, first, data is registered and set in advance in the order instruction table 10, the product master 11, the process master 12, the resource master 20, the resource operation calendar 21, and the result information table 22 (step S1). : Resource registration step, resource operation calendar registration step).

第一の実施形態におけるオーダー指示テーブル10の具体例を、下記の表1に示す。表1のオーダー指示テーブル10では、オーダー1〜4の4つのオーダーが外部から指示されていることを示す。表1のオーダー指示テーブル10において、オーダー1がオーダーコード「P01」で、製品名が「製品1」であり、優先度が「4」であることを示す。優先度は1〜4で4が最も高い。また、オーダー1は、納期が「2005/4/4 12:00」であり、他のオーダーよりも2日早い設定となっている。   A specific example of the order instruction table 10 in the first embodiment is shown in Table 1 below. The order instruction table 10 of Table 1 indicates that four orders 1 to 4 are instructed from the outside. In the order instruction table 10 of Table 1, the order 1 is the order code “P01”, the product name is “product 1”, and the priority is “4”. The priority is 1-4 and 4 is the highest. Order 1 has a delivery date of “2005/4/4 12:00” and is set two days earlier than other orders.

Figure 2007072747
Figure 2007072747

第一の実施形態における製品マスタ11の具体例を、下記の表2に示す。表2の製品マスタ11において、製品1は、製品コードが「S1」、製品名が「ケース」、工程数が「4」、1工程目の名称が「工程1−1」、2工程目の名称が「工程1−2」、3工程目の名称が「工程1−3」、4工程目の名称が「工程1−4」であることを示す。第一の実施形態では、工程1、工程2、工程3、工程4の順に実施しなければならないことを示している。   Specific examples of the product master 11 in the first embodiment are shown in Table 2 below. In the product master 11 of Table 2, the product 1 has the product code “S1”, the product name “case”, the number of processes “4”, the first process name “process 1-1”, the second process The name is “Step 1-2”, the name of the third step is “Step 1-3”, and the name of the fourth step is “Step 1-4”. In 1st embodiment, it has shown that it must implement in order of the process 1, the process 2, the process 3, and the process 4. FIG.

Figure 2007072747
Figure 2007072747

第一の実施形態における工程マスタ12の具体例を、下記の表3に示す。表3の工程マスタ12において、工程1−1は、工程コードが「K11」、主資源が「設備1」、副資源が「作業者1」、工程時間が「3時間」であることを示す。   Specific examples of the process master 12 in the first embodiment are shown in Table 3 below. In the process master 12 of Table 3, process 1-1 indicates that the process code is “K11”, the main resource is “facility 1”, the sub resource is “worker 1”, and the process time is “3 hours”. .

Figure 2007072747
Figure 2007072747

第一の実施形態における資源マスタ20の具体例を、下記の表4に示す。表4の資源マスタ20において、主資源である設備1〜3、副資源である作業者1〜3、ダミー資源としてダミー1〜4が登録されることを示す。また、表4の資源マスタ20において、設備1は、資源コード「R01」であることを示す。尚、設備1〜3及び作業者1〜3は通常資源であり、ダミー1〜4はそれぞれオーダー1〜4のダミー資源となる。   Specific examples of the resource master 20 in the first embodiment are shown in Table 4 below. In resource master 20 of Table 4, it shows that facilities 1-3 which are main resources, workers 1-3 which are subresources, and dummy 1-4 are registered as dummy resources. Further, in the resource master 20 of Table 4, the facility 1 indicates the resource code “R01”. The facilities 1 to 3 and the workers 1 to 3 are normal resources, and the dummy 1 to 4 are dummy resources of orders 1 to 4, respectively.

Figure 2007072747
Figure 2007072747

第一の実施形態における通常時の資源稼動カレンダー21の具体例を、下記の表5に示す。表5に示す資源稼動カレンダー21において、通常資源である設備1〜3及び作業者1〜3については毎日(日曜日から土曜日まで)24時間を稼動時間とする。また、ダミー資源であるダミー1〜4は、月曜日から金曜日までの9:00〜12:00及び13:00〜17:00を稼働時間とする。第一の実施形態においては、「あるオーダーのジョブに割付可能=(主資源の稼働時間内)かつ(副資源の稼動時間内)かつ(ダミー資源の稼動時間内)」というロジックに基づくため、ダミー資源が実際の各オーダーに属するジョブへの割り付きをコントロールすることになる。   Specific examples of the normal resource operation calendar 21 in the first embodiment are shown in Table 5 below. In the resource operation calendar 21 shown in Table 5, for the facilities 1 to 3 and the workers 1 to 3 which are normal resources, 24 hours every day (from Sunday to Saturday) is set as the operation time. The dummy resources 1 to 4, which are dummy resources, have an operation time of 9:00 to 12:00 and 13:00 to 17:00 from Monday to Friday. In the first embodiment, since it is based on the logic that “assignment to a job of an order = (within the operating time of the main resource) and (within the operating time of the secondary resource) and (within the operating time of the dummy resource)”, The dummy resource controls the allocation to jobs belonging to each actual order.

Figure 2007072747
Figure 2007072747

尚、第一の実施形態における実績情報テーブル22は、どの通常資源及びダミー資源にも何も割りついておらず、全くの初期状態として空とする。   In addition, the performance information table 22 in the first embodiment is empty as a completely initial state because nothing is assigned to any normal resource and dummy resource.

そして、生産計画スケジューラ1は、計画日時の初期化を実行する(ステップS2)。具体的には、計画日時を計画開始時刻に設定する。第一の実施形態では、2005/4/1 9:00からジョブを割り付ける(計画開始時刻)ものとして、計画日時に設定する。   The production plan scheduler 1 then initializes the plan date and time (step S2). Specifically, the plan date and time is set as the plan start time. In the first embodiment, the job is assigned from 2005/4/1 9:00 (plan start time), and the plan date is set.

次に、オーダー指示テーブル10に基づいて、生産すべき製品名を求め、製品マスタ11、工程マスタ12及び資源マスタ20から実施すべきジョブに展開する。そして、未割付ジョブリスト13に登録する(ステップS3)。これが未割付ジョブリスト13の初期状態となる。第一の実施形態における未割付ジョブリスト13の具体例を、下記の表6に示す。   Next, based on the order instruction table 10, a product name to be produced is obtained and developed from the product master 11, the process master 12, and the resource master 20 into jobs to be executed. Then, it is registered in the unallocated job list 13 (step S3). This is the initial state of the unallocated job list 13. A specific example of the unallocated job list 13 in the first embodiment is shown in Table 6 below.

Figure 2007072747
Figure 2007072747

以下、ジョブへの通常資源及びダミー資源の割付の処理を行う(ステップS4〜ステップS9:ジョブ割付ステップ)。まず、工程順に実施しなければならない制約より、未割付ジョブリスト13のジョブの中から割付対象ジョブを全て抽出し、割付対象ジョブテーブル4に登録する(ステップS4)。初回であるので、第一の実施形態においては、割付対象ジョブは、各オーダーの1工程目となり、下記の表7に割付対象ジョブテーブル4の具体例を示す。   Hereinafter, the process of assigning the normal resource and the dummy resource to the job is performed (step S4 to step S9: job assignment step). First, all assignment target jobs are extracted from the jobs in the unassigned job list 13 due to restrictions that must be performed in the order of processes, and registered in the assignment target job table 4 (step S4). Since this is the first time, in the first embodiment, the allocation target job is the first step of each order, and Table 7 below shows a specific example of the allocation target job table 4.

Figure 2007072747
Figure 2007072747

次に、割付対象ジョブテーブル4に割付対象ジョブが登録されているかどうかを判断する(ステップS5)。ここで、割付対象ジョブテーブル4に割付対象ジョブが登録されていない場合は(ステップS5:NO)、全てのジョブに通常資源及びダミー資源が割り付けられたものとして、処理を終了する。   Next, it is determined whether or not an allocation target job is registered in the allocation target job table 4 (step S5). Here, when the allocation target job is not registered in the allocation target job table 4 (step S5: NO), it is assumed that the normal resource and the dummy resource are allocated to all the jobs, and the process ends.

一方、割付対象ジョブテーブル4に割付対象ジョブが登録されている場合は(ステップS5:YES)、評価値に基づき、通常資源及びダミー資源を割り付けるジョブを決定し、割付情報テーブルに登録する(ステップS6)。ここで、「あるオーダーのジョブに割付可能=(主資源の稼働時間内)かつ(副資源の稼動時間内)かつ(ダミー資源の稼動時間内)」というロジックに基づいて、ジョブへの通常資源及びダミー資源の割り付けが行われる。第一の実施形態では、割付対象ジョブに含まれる主資源は、設備1,2,3となる。まず、設備1を使用する割付対象ジョブについて調べる。この設備1に対する割付対象ジョブは、P01−K11とP02−K11の2つである。これらに対して、割付の評価値を求める。評価値は、下記の式に従って求めるものとする。
評価値=優先度
そして、評価値が高い割付対象ジョブが、通常資源及びダミー資源が割り付けられるジョブとして選択される。設備1では、評価値が4であるP01−K11が選択される。計画時刻2005/4/1 9:00の時点で主資源である設備1、副資源である作業者1、ダミー資源であるダミー1に割付はなく、稼働時間も満足しているため、このジョブに、主資源として設備1、副資源として作業者1、ダミー資源としてダミー1が9:00−12:00の期間割り付けられる。この情報は、割付情報テーブル3に記入される。尚、同じ主資源である設備1を使用するもう一つのジョブP02−K11は、計画時刻2005/4/1 9:00の時点では割り付けることができない。そして、割付対象ジョブテーブル4と未割付ジョブリスト13を更新する(ステップS7)。即ち、通常資源及びダミー資源及びダミー資源が割り付けられたジョブを割付対象ジョブテーブル4及び未割付ジョブリスト13から削除する。
On the other hand, when the allocation target job is registered in the allocation target job table 4 (step S5: YES), the job to allocate the normal resource and the dummy resource is determined based on the evaluation value, and is registered in the allocation information table (step S5). S6). Here, based on the logic that “assignment to a job of an order = (within the operation time of the main resource) and (within the operation time of the secondary resource) and (within the operation time of the dummy resource)”, the normal resource to the job And dummy resources are allocated. In the first embodiment, the main resources included in the allocation target job are facilities 1, 2, and 3. First, the allocation target job that uses the facility 1 is examined. There are two assignment target jobs for the equipment 1, P01-K11 and P02-K11. For these, the evaluation value of allocation is obtained. The evaluation value shall be obtained according to the following formula.
Evaluation value = priority An allocation target job having a high evaluation value is selected as a job to which normal resources and dummy resources are allocated. In the facility 1, P01-K11 having an evaluation value of 4 is selected. At the planned time of 2005/4/1 9:00, there is no assignment for the equipment 1 that is the main resource, the worker 1 that is the secondary resource, and the dummy 1 that is the dummy resource. In addition, the facility 1 as the main resource, the worker 1 as the sub-resource, and the dummy 1 as the dummy resource are allocated for a period of 9:00 to 12:00. This information is entered in the allocation information table 3. Note that another job P02-K11 that uses the equipment 1 that is the same main resource cannot be assigned at the planned time 2005/4/1 9:00. Then, the allocation target job table 4 and the unallocated job list 13 are updated (step S7). That is, the job to which the normal resource, the dummy resource, and the dummy resource are allocated is deleted from the allocation target job table 4 and the unallocated job list 13.

次に、他の通常資源及びダミー資源を割り付けるジョブがあるかどうかが判断され(ステップS8)、他の通常資源及びダミー資源を割り付けるジョブがある場合は(ステップS8:YES)、ステップS6にもどる。第一の実施形態では、上述の1つ目の主資源である設備1と同様にして、2つ目の主資源である設備2、設備3についても処理され、P03−K21に主資源として設備2、副資源として作業者2、ダミー資源としてダミー3が9:00−10:00の期間に、P04−K31に主資源として設備3、副資源として作業者3、ダミー資源としてダミー4が9:00−11:00の期間に割り付けられ、割付対象ジョブテーブル4と未割付ジョブリスト13を更新する(ステップS6〜S7)。そして、他の通常資源及びダミー資源を割り付けるジョブがなくなると(ステップS8:NO)、ステップS9に進む。尚、第一の実施形態において、表7では、通常資源及びダミー資源が割り付けられたジョブP01−K11、P03−K21、P04−K31を網掛けで表示している。また、以上の処理によりジョブP01−K11、P03−K21、P04−K31に通常資源及びダミー資源が割り付けられて、更新された割付対象ジョブテーブル4は、下記の表8に示す通りとなる。   Next, it is determined whether there is a job for allocating other normal resources and dummy resources (step S8). If there is a job for allocating other normal resources and dummy resources (step S8: YES), the process returns to step S6. . In the first embodiment, the second main resource, equipment 2 and equipment 3, are processed in the same manner as the above-mentioned first main resource, equipment 1, and the equipment is used as the main resource in P03-K21. 2. Worker 2 as a secondary resource, dummy 3 as a dummy resource during a period from 9:00 to 10:00, equipment 3 as a main resource, worker 3 as a secondary resource, dummy 4 as a dummy resource 9 during P04-K31 0:11 to 11:00, the allocation target job table 4 and the unallocated job list 13 are updated (steps S6 to S7). Then, when there is no job to allocate other normal resources and dummy resources (step S8: NO), the process proceeds to step S9. In the first embodiment, in Table 7, the jobs P01-K11, P03-K21, and P04-K31 to which the normal resource and the dummy resource are allocated are displayed by shading. In addition, the normal resource and the dummy resource are allocated to the jobs P01-K11, P03-K21, and P04-K31 by the above processing, and the updated allocation target job table 4 is as shown in Table 8 below.

Figure 2007072747
Figure 2007072747

そして、通常資源及びダミー資源が割り付いたジョブの内、最も早く通常資源及びダミー資源を解放する日時に計画日時を設定する(ステップS9)。第一の実施形態では、通常資源及びダミー資源が割り付いたジョブP01−K11、P03−K21、P04−K31の中でも最も早く処理が完了するジョブであるP03−K21の完了日時である2005/4/1 10:00に計画日時が設定される。   Then, the planned date and time is set to the date and time when the normal resource and dummy resource are released earliest among the jobs to which the normal resource and dummy resource are assigned (step S9). In the first embodiment, 2005/4 is the completion date and time of P03-K21, which is the job that completes the earliest among the jobs P01-K11, P03-K21, and P04-K31 to which normal resources and dummy resources are allocated. / 1 The planned date and time is set at 10:00.

次に、ステップS4に戻り、工程順に実施しなければならない制約より、未割付ジョブリスト13のジョブの中から割付対象ジョブを全て抽出し、割付対象ジョブを全て抽出し、割付対象ジョブテーブル4に登録する(ステップS4)。第一の実施形態では、オーダー3の1工程目であるP03−K21が終了したので、オーダー3の2工程目であるP03−K22が割付対象ジョブテーブル4に登録される。第一の実施形態における2回目割付前の割付対象ジョブテーブル4の具体例を下記の表9に示す。   Next, returning to step S4, due to restrictions that must be performed in the order of processes, all allocation target jobs are extracted from the jobs in the unallocated job list 13, all allocation target jobs are extracted, and the allocation target job table 4 is extracted. Register (step S4). In the first embodiment, P03-K21, which is the first step of order 3, is completed, so P03-K22, which is the second step of order 3, is registered in the allocation target job table 4. A specific example of the allocation target job table 4 before the second allocation in the first embodiment is shown in Table 9 below.

Figure 2007072747
Figure 2007072747

そして、割付対象ジョブテーブル4に登録されているジョブに通常資源及びダミー資源を割り付ける(ステップS6〜S8)。第一の実施形態では、主資源である設備2がジョブに割りついていない状態となるが、設備2を使用するジョブがないため、割り付けるジョブがなく、ステップS9に進む。尚、割り付けるジョブがないため、2回目割付後の割付対象ジョブテーブル4に登録されている割付対象ジョブは表9のまま変化しない。   Then, normal resources and dummy resources are allocated to the jobs registered in the allocation target job table 4 (steps S6 to S8). In the first embodiment, the facility 2 as the main resource is not assigned to a job. However, since there is no job that uses the facility 2, there is no job to be assigned, and the process proceeds to step S9. Since there are no jobs to be allocated, the allocation target jobs registered in the allocation target job table 4 after the second allocation remain unchanged from Table 9.

次に、通常資源及びダミー資源が割り付いたジョブの内、最も早く通常資源及びダミー資源を解放する日時に計画日時を設定する(ステップS9)。第一の実施形態では、P03−K21以外の通常資源及びダミー資源が割り付いたジョブP01−K11、P04−K31の中でも最も早く処理が完了するジョブであるP04−K31の完了日時である2005/4/1 11:00に計画日時が設定される。   Next, the planned date and time is set to the date and time at which the normal resource and dummy resource are released earliest among the jobs to which the normal resource and dummy resource are assigned (step S9). In the first embodiment, the completion date and time of P04-K31, which is the job that completes the earliest job among jobs P01-K11 and P04-K31 to which normal resources and dummy resources other than P03-K21 are allocated, is 2005 /. The planned date and time is set to 4/1 11:00.

次に、ステップS4に戻り、工程順に実施しなければならない制約より、未割付ジョブリスト13のジョブの中から割付対象ジョブを全て抽出し、割付対象ジョブを全て抽出し、割付対象ジョブテーブル4に登録する(ステップS4)。第一の実施形態では、オーダー4の1工程目であるP04−K31が終了したので、オーダー4の2工程目であるP04−K32が割付対象ジョブテーブル4に登録される。第一の実施形態における3回目割付前の割付対象ジョブテーブル4の具体例を下記の表10に示す。   Next, returning to step S4, due to restrictions that must be performed in the order of processes, all allocation target jobs are extracted from the jobs in the unallocated job list 13, all allocation target jobs are extracted, and the allocation target job table 4 is extracted. Register (step S4). In the first embodiment, P04-K31, which is the first process of order 4, is completed, so P04-K32, which is the second process of order 4, is registered in the allocation target job table 4. A specific example of the allocation target job table 4 before the third allocation in the first embodiment is shown in Table 10 below.

Figure 2007072747
Figure 2007072747

そして、割付対象ジョブテーブル4に登録されているジョブに通常資源及びダミー資源を割り付ける(ステップS6〜S8)。第一の実施形態では、主資源である設備2及び設備3がジョブに割りついていない状態となる。従って、設備3を使用するジョブP03−K22に主資源として設備3、副資源として作業者3、ダミー資源としてダミー3を11:00−12:00、13:00−14:00の期間に割り付け、割付対象ジョブテーブル4と未割付ジョブリスト13を更新する。また、設備2を使用するジョブがないため、割り付けるジョブがない。尚、第一の実施形態において、表10では、通常資源及びダミー資源が割り付けられたジョブP03−K22を網掛けで表示している。また、3回目割付後の更新された割付対象ジョブテーブル4を下記の表11に示す。   Then, normal resources and dummy resources are allocated to the jobs registered in the allocation target job table 4 (steps S6 to S8). In the first embodiment, the equipment 2 and equipment 3 that are main resources are not assigned to jobs. Therefore, the job P03-K22 that uses the equipment 3 is assigned the equipment 3 as the main resource, the worker 3 as the sub-resource, and the dummy 3 as the dummy resource for the period of 11: 00-12: 00, 13: 00-14: 00. The allocation target job table 4 and the unallocated job list 13 are updated. In addition, since there is no job that uses the equipment 2, there is no job to be assigned. In the first embodiment, in Table 10, jobs P03-K22 to which normal resources and dummy resources are allocated are displayed by shading. The updated assignment target job table 4 after the third assignment is shown in Table 11 below.

Figure 2007072747
Figure 2007072747

次に、通常資源及びダミー資源が割り付いたジョブの内、最も早く通常資源及びダミー資源を解放する日時に計画日時を設定する(ステップS9)。第一の実施形態では、P03−K21、P04−K31以外の通常資源及びダミー資源が割り付いたジョブP01−K11、P03−K22の中でも最も早く処理が完了するジョブであるP01−K11の完了日時である2005/4/1 12:00に計画日時が設定される。   Next, the planned date and time is set to the date and time at which the normal resource and dummy resource are released earliest among the jobs to which the normal resource and dummy resource are assigned (step S9). In the first embodiment, the completion date and time of P01-K11, which is the job that completes the earliest among the jobs P01-K11 and P03-K22 to which normal resources and dummy resources other than P03-K21 and P04-K31 are assigned. The planned date and time is set to 2005/4/1 12:00.

次に、ステップS4に戻り、工程順に実施しなければならない制約より、未割付ジョブリスト13のジョブの中から割付対象ジョブを全て抽出し、割付対象ジョブを全て抽出し、割付対象ジョブテーブル4に登録する(ステップS4)。第一の実施形態では、オーダー1の1工程目であるP01−K11が終了したので、オーダー1の2工程目であるP01−K12が割付対象ジョブテーブル4に登録される。第一の実施形態における4回目割付前の割付対象ジョブテーブル4の具体例を下記の表12に示す。   Next, returning to step S4, due to restrictions that must be performed in the order of processes, all allocation target jobs are extracted from the jobs in the unallocated job list 13, all allocation target jobs are extracted, and the allocation target job table 4 is extracted. Register (step S4). In the first embodiment, P01-K11, which is the first process of order 1, is completed, so P01-K12, which is the second process of order 1, is registered in the allocation target job table 4. A specific example of the allocation target job table 4 before the fourth allocation in the first embodiment is shown in Table 12 below.

Figure 2007072747
Figure 2007072747

そして、割付対象ジョブテーブル4に登録されているジョブに通常資源及びダミー資源を割り付ける(ステップS6〜S8)。第一の実施形態では、主資源である設備1、設備2がジョブに割りついていない状態となる。設備1を使用する割付対象ジョブの中で最も評価値が高いP01−K12が割付候補としてあがるが、副資源である作業者1が稼働時間外となるため、割付が行われない。また、設備2を使用するジョブがないため、割り付けるジョブがなく、ステップS9に進む。尚、割り付けるジョブがないため、4回目割付後の割付対象ジョブテーブル4に登録されている割付対象ジョブは表12のまま変化しない。   Then, normal resources and dummy resources are allocated to the jobs registered in the allocation target job table 4 (steps S6 to S8). In the first embodiment, the equipment 1 and equipment 2 that are main resources are not assigned to jobs. P01-K12 having the highest evaluation value among the allocation target jobs that use the facility 1 is listed as an allocation candidate, but the allocation is not performed because the worker 1 as a secondary resource is out of operation time. Further, since there is no job that uses the equipment 2, there is no job to be allocated, and the process proceeds to step S9. Since there are no jobs to be allocated, the allocation target jobs registered in the allocation target job table 4 after the fourth allocation remain unchanged from Table 12.

次に、前回(4回目)割付時に割付対象ジョブテーブル4の中に割付候補となる割付対象ジョブがあったため、資源稼動カレンダー21の最も早い主資源及び副資源及びダミー資源の稼動開始時間に計画日時を設定する(ステップS9)。第一の実施形態では、副資源の稼動開始時間である2005/4/1 13:00に計画日時が設定される。   Next, since there is an allocation target job that is an allocation candidate in the allocation target job table 4 at the time of the previous allocation (fourth time), the operation start time of the primary resource, the secondary resource, and the dummy resource in the resource operation calendar 21 is planned. Date and time are set (step S9). In the first embodiment, the planned date and time is set to 2005/4/1 13:00, which is the operation start time of the secondary resource.

次に、ステップS4に戻り、工程順に実施しなければならない制約より、未割付ジョブリスト13のジョブの中から割付対象ジョブを全て抽出し、割付対象ジョブを全て抽出し、割付対象ジョブテーブル4に登録する(ステップS4)。第一の実施形態では、計画日時に処理が終了するジョブがないために、割付対象ジョブテーブル4は4回目割付後と同じであり、下記の表13に示す通りとなる。   Next, returning to step S4, due to restrictions that must be performed in the order of processes, all allocation target jobs are extracted from the jobs in the unallocated job list 13, all allocation target jobs are extracted, and the allocation target job table 4 is extracted. Register (step S4). In the first embodiment, since there is no job whose processing ends at the scheduled date and time, the allocation target job table 4 is the same as that after the fourth allocation, and is as shown in Table 13 below.

Figure 2007072747
Figure 2007072747

そして、割付対象ジョブテーブル4に登録されているジョブに通常資源及びダミー資源を割り付ける(ステップS6〜S8)。第一の実施形態では、主資源である設備1及び設備2がジョブに割りついていない状態となる。従って、設備1を使用するジョブP01−K12に主資源として設備1、副資源として作業者1、ダミー資源としてダミー1を13:00−16:00の期間に割り付け、割付対象ジョブテーブル4と未割付ジョブリスト13を更新する。一方、割付対象ジョブテーブル4に登録されている他の割付対象ジョブP02−K11及びP04−K32は、評価値がP01−K12よりも低いため割り付けられない。また、設備2を使用するジョブがないため、割り付けるジョブがない。尚、第一の実施形態において、表13では、通常資源及びダミー資源が割り付けられたジョブP01−K12を網掛けで表示している。ここで、5回目割付後の更新された割付対象ジョブテーブル4及び5回目割付後の割付情報テーブル3の具体例を、それぞれ下記の表14及び表15に示す。   Then, normal resources and dummy resources are allocated to the jobs registered in the allocation target job table 4 (steps S6 to S8). In the first embodiment, the equipment 1 and equipment 2 that are main resources are not assigned to jobs. Accordingly, the job P01-K12 that uses the facility 1 is assigned the facility 1 as the main resource, the worker 1 as the sub-resource, and the dummy 1 as the dummy resource during the period 13: 00-16: 00 The allocated job list 13 is updated. On the other hand, the other allocation target jobs P02-K11 and P04-K32 registered in the allocation target job table 4 are not allocated because their evaluation values are lower than those of P01-K12. In addition, since there is no job that uses the equipment 2, there is no job to be assigned. In the first embodiment, in Table 13, the jobs P01-K12 to which the normal resources and the dummy resources are allocated are displayed by shading. Specific examples of the updated allocation target job table 4 after the fifth allocation and the allocation information table 3 after the fifth allocation are shown in Tables 14 and 15 below, respectively.

Figure 2007072747
Figure 2007072747

Figure 2007072747
Figure 2007072747

以下、同様にして未割付ジョブリスト13及び割付対象ジョブテーブル4に割付対象ジョブがなくなるまで(ステップS5:NO)、ステップS4〜ステップS9までの処理が行われる。   In the same manner, the processes from step S4 to step S9 are performed until there are no more allocation target jobs in the unallocated job list 13 and the allocation target job table 4 (step S5: NO).

尚、以上の処理により求められた割付情報テーブル3(生産計画)に基づいて実際に生産が行われた結果を示す実績情報テーブル22の具体例を下記の表16に示す。   Table 16 below shows a specific example of the result information table 22 showing the result of actual production based on the allocation information table 3 (production plan) obtained by the above processing.

Figure 2007072747
Figure 2007072747

また、以上の処理により最終的に求められた割付情報テーブル3(生産計画)に基づくジョブの割り付け結果を示すガントチャートを図3に示す。図3及び後述する図4〜図8では、上部にオーダー毎のジョブの割り付け状況を示し、下部に通常資源及びダミー資源毎のジョブへの割り付け状況を示す。また、1つ1つの長方形が1つのジョブを示し、長方形内の左端にある数字はオーダーの番号を示している。尚、ジョブは開始日時から終了日時までを長方形として表しており、場合によっては通常資源またはダミー資源の稼働時間外も含んで表現しているが、ジョブは通常資源またはダミー資源の稼働時間外は処理が行われない。また、三角印がオーダーの納期を示す。オーダー1は2時間納期から遅れており、他のオーダーは納期内に完了していることがわかる。   FIG. 3 shows a Gantt chart showing job assignment results based on the assignment information table 3 (production plan) finally obtained by the above processing. In FIG. 3 and FIGS. 4 to 8 described later, the job allocation status for each order is shown in the upper part, and the job allocation status for each normal resource and dummy resource is shown in the lower part. Each rectangle indicates one job, and the number at the left end in the rectangle indicates the order number. The job is represented as a rectangle from the start date and time to the end date and time. In some cases, the job is also included outside the normal resource or dummy resource operation time. Processing is not performed. A triangle indicates the delivery date of the order. It can be seen that Order 1 is delayed from the delivery time of 2 hours, and the other orders are completed within the delivery date.

ここで、オーダー1が納期遅れとならないように対応した資源稼動カレンダー21の具体例を表17に示す。表17は、上述の納期遅れを発生する資源稼動カレンダー21の具体例である表5に対して、ダミー1のみに2005/4/2 9:00−12:00、13:00−17:00を稼働時間として加えている。   Here, a specific example of the resource operation calendar 21 corresponding to order 1 not to be delayed in delivery is shown in Table 17. Table 17 shows only a dummy 1 for 2005/4/2 9: 00-12: 00, 13: 00-17: 00, compared to Table 5 which is a specific example of the resource operation calendar 21 that causes the above-described delivery delay. Is added as the operating time.

Figure 2007072747
Figure 2007072747

この表17に示す資源稼動カレンダー21を用いて、上述した図2に示す第一の実施形態に係る生産計画スケジューラ1を用いた生産計画作成方法の処理を行い最終的に求められた割付情報テーブル3(生産計画)に基づくジョブの割り付け結果を示すガントチャートを図4に示す。図4に示すように、オーダー1に関わるジョブのみが2005/4/2に割り付けられており、他のオーダーについては、2005/4/2に割り付けられることはない。この結果、オーダー1は、2005/4/2 15:00に完成し、納期遅れを解消していることがわかる。尚、表17に示す資源稼動カレンダー21において、ダミー1のみに2005/4/2 13:00−17:00の稼働時間を削除することにより、図4に示す2005/4/2 13:00−15:00に割り付けられているジョブP01−K14が2005/4/4 9:00−11:00に割り付けられることになり、オーダー1は、2005/4/4 11:00に完成し、設備3及び作業者3が2005/4/2の午後に稼動及び出勤しなくても、納期遅れを解消することがわかる。   Using the resource operation calendar 21 shown in Table 17, the allocation information table finally obtained by performing the process of the production plan creation method using the production plan scheduler 1 according to the first embodiment shown in FIG. 2 described above. FIG. 4 shows a Gantt chart showing job allocation results based on 3 (production plan). As shown in FIG. 4, only jobs related to order 1 are assigned to 2005/4/2, and other orders are not assigned to 2005/4/2. As a result, it can be seen that Order 1 is completed at 2005/4/2 15:00, and the delivery delay is eliminated. In addition, in the resource operation calendar 21 shown in Table 17, the operation time of 2005/4/2 13: 00-17: 00 is deleted only for the dummy 1, so that 2005/4/2 13: 00- shown in FIG. Job P01-K14 assigned to 15:00 will be assigned to 2005/4/4 9: 00-111: 00, order 1 will be completed at 2005/4/4 11:00, equipment 3 And even if the worker 3 does not work and work in the afternoon of 2005/4/2, it can be seen that the delivery delay is eliminated.

即ち、第一の実施形態に係る生産計画スケジューラ1を用いた生産計画作成方法の処理を行い最終的に求められた図4に示す生産計画は、従来技術と比較して下記のことがわかる。例えば、表18にしめす従来技術の資源稼動カレンダーを用いて、従来技術による生産計画スケジューラを用いた生産計画作成方法の処理を行い最終的に求められた生産計画に基づくジョブの割り付け結果を示すガントチャートを図7に示す。ここで、従来技術による生産計画スケジューラを用いた生産計画作成方法では、オーダーに設定した優先順位に基づく優先順位計画による割付アルゴリズムを用いて、資源稼動カレンダー及び実績情報テーブルに基づいて、未割付ジョブリストに含まれるジョブ群への資源の割付を試行する。表18に示す従来技術の資源稼動カレンダーは、表5に示す第一の実施形態に係る資源稼動カレンダーに対応しており、図7では、図3に示すガントチャートと同様に、オーダー1が2時間納期から遅れており、他のオーダーは納期内に完了していることがわかる。   That is, it can be seen that the production plan shown in FIG. 4 finally obtained by performing the process of the production plan creation method using the production plan scheduler 1 according to the first embodiment is as follows in comparison with the prior art. For example, using a resource operation calendar of the prior art shown in Table 18, processing of a production plan creation method using a production plan scheduler according to the prior art, and a Gantt showing a job allocation result based on the finally obtained production plan A chart is shown in FIG. Here, in the production plan creation method using the production plan scheduler according to the prior art, an unallocated job based on the resource operation calendar and the result information table using an allocation algorithm based on a priority plan based on the priority set in the order. Attempts to allocate resources to the jobs included in the list. The resource operation calendar of the prior art shown in Table 18 corresponds to the resource operation calendar according to the first embodiment shown in Table 5, and in FIG. 7, as in the Gantt chart shown in FIG. You can see that other orders have been completed within the due date because they are behind the due date.

Figure 2007072747
Figure 2007072747

ここで、オーダー1が納期遅れとならないように対応した従来技術の資源稼動カレンダーの具体例を表19に示す。表19は、上述の納期遅れを発生する従来技術の資源稼動カレンダーの具体例である表18に対して、全ての資源に2005/4/2を稼働日として加えている。   Here, a specific example of the resource operation calendar of the prior art corresponding to the order 1 not to be delayed in delivery is shown in Table 19. Table 19 adds 2005/4/2 to all resources as working days, compared to Table 18 which is a specific example of the resource working calendar of the prior art that causes the above-mentioned delay in delivery date.

Figure 2007072747
Figure 2007072747

表19にしめす従来技術の資源稼動カレンダーを用いて、従来技術による生産計画スケジューラを用いた生産計画作成方法の処理を行い最終的に求められた生産計画に基づくジョブの割り付け結果を示すガントチャートを図8に示す。図8に示すように、オーダー1は2005/4/2 15:00に完成し、納期遅れを解消していることがわかる。しかしながら、他のオーダーは、納期よりもさらに早く完了し、オーダー1以外のオーダーにかかわる作業者1が本来作業する必要がないのに出勤している。従って、第一の実施形態に係る生産計画スケジューラ1を用いた生産計画作成方法の処理を行い最終的に求められた図4に示す生産計画では作業者1を無駄に出勤することを解消していることがわかる。   Table 19 shows a Gantt chart showing job allocation results based on the production plan finally obtained by processing the production plan creation method using the production plan scheduler according to the conventional technology using the resource operation calendar of the conventional technology shown in Table 19. As shown in FIG. As shown in FIG. 8, it can be seen that Order 1 was completed at 2005/4/2 15:00 and the delivery delay was resolved. However, the other orders are completed even earlier than the delivery date, and the worker 1 who is involved in an order other than the order 1 does not have to work originally, but is working. Therefore, the production plan shown in FIG. 4 finally obtained by performing the process of the production plan creation method using the production plan scheduler 1 according to the first embodiment eliminates the wasteful attendance of the worker 1. I understand that.

[第二の実施形態]
次に、第二の実施形態に係る生産計画スケジューラ(生産計画装置)について説明する。第二の実施形態に係る生産計画スケジューラの構成は、第一の実施形態にかかる生産計画スケジューラの構成と同じであり、図1に基づいて説明する。図1に示すように生産計画スケジューラ1は、オーダー指示テーブル10と、製品マスタ11と、工程マスタ12と、未割付ジョブリスト13と、資源マスタ(資源登録手段)20と、資源稼動カレンダー(資源稼動カレンダー登録手段)21と、実績情報テーブル22と、資源割付部(ジョブ割付手段)2と、割付情報テーブル3と、割付対象ジョブテーブル4と、を備えている。生産は外部から与えられるオーダー指示に従って開始される。生産計画スケジューラ1は、与えられるオーダー指示を達成するために、製品の全工程の開始時刻及び終了時刻と、工程に使用する資源のリストからなる生産計画を作成するためのものである。
[Second Embodiment]
Next, a production plan scheduler (production plan apparatus) according to the second embodiment will be described. The configuration of the production plan scheduler according to the second embodiment is the same as the configuration of the production plan scheduler according to the first embodiment, and will be described with reference to FIG. As shown in FIG. 1, the production plan scheduler 1 includes an order instruction table 10, a product master 11, a process master 12, an unassigned job list 13, a resource master (resource registration means) 20, a resource operation calendar (resources). An operation calendar registration unit) 21, a performance information table 22, a resource allocation unit (job allocation unit) 2, an allocation information table 3, and an allocation target job table 4 are provided. Production is started according to order instructions given from the outside. The production plan scheduler 1 is for creating a production plan including a start time and an end time of all processes of a product and a list of resources used for the process in order to achieve a given order instruction.

オーダー指示テーブル10、製品マスタ11、工程マスタ12、未割付ジョブリスト13、実績情報テーブル22は、第一の実施形態に係る生産計画スケジューラ1のオーダー指示テーブル10、製品マスタ11、工程マスタ12、未割付ジョブリスト13、実績情報テーブル22と同じであり、その説明を省略する。   The order instruction table 10, the product master 11, the process master 12, the unassigned job list 13, and the result information table 22 are the order instruction table 10, the product master 11, the process master 12, and the production plan scheduler 1 according to the first embodiment. This is the same as the unallocated job list 13 and the result information table 22, and a description thereof will be omitted.

資源マスタ(資源登録手段)20は、資源の資源名、資源コード、資源の能力が登録されるものである。   The resource master (resource registration means) 20 registers the resource name, resource code, and resource capability of the resource.

資源稼動カレンダー(資源稼動カレンダー登録手段)21は、資源の稼動可能な時間である稼動時間と適用可能な対象オーダーとが登録されるものである。   The resource operation calendar (resource operation calendar registering means) 21 is for registering an operation time that is a resource operation time and an applicable target order.

資源割付部(ジョブ割付手段)2は、未割付ジョブリスト13に含まれるジョブ群に割付アルゴリズムを適用し、資源稼動カレンダー21及び実績情報テーブル22に基づいて、ジョブへの資源の割付を試行する。ここで、割付アルゴリズムは、オーダーに設定した優先順位に基づく優先順位計画を行う。即ち、割付アルゴリズムは、未割付ジョブリスト13から割付可能なジョブを割付対象ジョブとして抽出して割付対象ジョブテーブル4に保存し、割付対象ジョブテーブル4に保存した割付対象ジョブからオーダーに設定した優先順位に基づいて、資源を割り付けるジョブを選択する。ジョブに資源が割り付けられると、割付情報テーブル3に保存されるとともに、割付対象ジョブテーブル4が更新される。   The resource allocation unit (job allocation means) 2 applies an allocation algorithm to the job group included in the unallocated job list 13 and tries to allocate resources to the job based on the resource operation calendar 21 and the result information table 22. . Here, the allocation algorithm performs a priority plan based on the priority set in the order. In other words, the allocation algorithm extracts jobs that can be allocated from the unallocated job list 13 as allocation target jobs, stores them in the allocation target job table 4, and sets priority from the allocation target jobs stored in the allocation target job table 4 to the order. Select a job to allocate resources based on rank. When resources are allocated to the job, the job is stored in the allocation information table 3 and the allocation target job table 4 is updated.

割付情報テーブル3は、ジョブ毎に割り付けた資源と、開始日時及び終了日時を含む割付情報からなり、これは生産計画そのものである。尚、割付情報テーブル3は、図示しない出力用インタフェースを介して、生産計画スケジューラ1外部の出力装置(ディスプレイ、ハードディスク、またはプリンタ等)にて読み出しが可能である。尚、出力用インタフェースは、出力装置(ディスプレイ、ハードディスク、またはプリンタ等)に出力するためのデータ変換や通信を行うプログラム又はハードウェアである。   The allocation information table 3 includes allocation information including resources allocated for each job, start date and time, and end date and time, which is a production plan itself. The allocation information table 3 can be read by an output device (display, hard disk, printer, etc.) outside the production plan scheduler 1 via an output interface (not shown). Note that the output interface is a program or hardware that performs data conversion and communication for output to an output device (display, hard disk, printer, or the like).

次に、第二の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理の手順について、具体例を用いて説明する。第二の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理の手順は、第一の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理の手順と同様であり、図2に基づいて説明する。尚、以下で説明する第二の実施形態に係る生産計画作成方法の処理は、コンピュータにおいても同様に、プログラムとしてCPUにより読み出して実行することができる。また、このプログラムは、CD−ROMやFD、DVDなどのリムーバブルな記憶媒体に記録しておくことにより、様々なコンピュータの記憶装置にインストールすることが可能である。   Next, the processing procedure of the production plan creation method using the production plan scheduler according to the second embodiment will be described using a specific example. The process procedure of the production plan creation method using the production plan scheduler according to the second embodiment is the same as the process procedure of the production plan creation method using the production plan scheduler according to the first embodiment. 2 will be described. The process of the production plan creation method according to the second embodiment described below can be read and executed by the CPU as a program in the computer as well. Further, this program can be installed in various computer storage devices by recording it in a removable storage medium such as a CD-ROM, FD, or DVD.

図2に示すように、まず、オーダー指示テーブル10、製品マスタ11、工程マスタ12、資源マスタ20、資源稼動カレンダー21、実績情報テーブル22、に事前にデータを登録及び設定しておく(ステップS1:資源登録ステップ、資源稼動カレンダー登録ステップ)。   As shown in FIG. 2, first, data is registered and set in advance in the order instruction table 10, the product master 11, the process master 12, the resource master 20, the resource operation calendar 21, and the result information table 22 (step S1). : Resource registration step, resource operation calendar registration step).

第二の実施形態におけるオーダー指示テーブル10、製品マスタ11、工程マスタ12の具体例は、第一の実施形態と同じであり、それぞれ上述した表1〜表3と同じである。   Specific examples of the order instruction table 10, the product master 11, and the process master 12 in the second embodiment are the same as those in the first embodiment, and are the same as those in Tables 1 to 3, respectively.

第二の実施形態における資源マスタ20の具体例を、下記の表20に示す。表20の資源マスタ20において、主資源である設備1〜3、副資源である作業者1〜3が登録されることを示す。また、表10の資源マスタ20において、設備1は、資源コード「R01」であることを示す。尚、設備1〜3及び作業者1〜3は通常資源となる。   A specific example of the resource master 20 in the second embodiment is shown in Table 20 below. In the resource master 20 of Table 20, it shows that the equipment 1-3 which are main resources, and the workers 1-3 which are subresources are registered. In addition, in the resource master 20 of Table 10, the facility 1 indicates the resource code “R01”. In addition, the equipment 1-3 and the workers 1-3 become a normal resource.

Figure 2007072747
Figure 2007072747

第二の実施形態における通常時の資源稼動カレンダー21の具体例を、下記の表21に示す。表21に示す資源稼動カレンダー21において、設備1〜3については、毎日(日曜日から土曜日まで)24時間を稼動時間とし、対象オーダーをすべて(all)とする。また、作業者1〜3は、月曜日から金曜日までの9:00〜12:00及び13:00〜17:00を稼働時間とし、対象オーダーをすべて(all)とする。第二の実施形態においては、「あるオーダーのジョブに割付可能=(主資源の稼働時間内)かつ(副資源の稼動時間内)かつ(主資源の対象オーダー)かつ(副資源の対象オーダー)」というロジックに基づくため、資源の対象オーダーが実際の各オーダーに属するジョブの割り付きをコントロールすることになる。   Specific examples of the normal resource operation calendar 21 in the second embodiment are shown in Table 21 below. In the resource operation calendar 21 shown in Table 21, regarding the facilities 1 to 3, 24 hours every day (from Sunday to Saturday) is set as the operation time, and all target orders are set to (all). In addition, workers 1 to 3 use 9:00 to 12:00 and 13:00 to 17:00 from Monday to Friday as operating hours, and set all target orders to (all). In the second embodiment, “assignment to a job of an order = (within the operation time of the main resource) and (within the operation time of the sub resource) and (the target order of the main resource) and (the target order of the sub resource) Therefore, the allocation of jobs belonging to each actual order is controlled by the target order of the resource.

Figure 2007072747
Figure 2007072747

尚、第二の実施形態における実績情報テーブル22は、どの資源にも何も割りついておらず、全くの初期状態として空とする。   Note that the performance information table 22 in the second embodiment has nothing assigned to any resource, and is empty as a completely initial state.

そして、生産計画スケジューラ1は、計画日時の初期化を実行する(ステップS2)。具体的には、計画日時を計画開始時刻に設定する。第二の実施形態では、2005/4/1 9:00からジョブを割り付ける(計画開始時刻)ものとして、計画日時に設定する。   The production plan scheduler 1 then initializes the plan date and time (step S2). Specifically, the plan date and time is set as the plan start time. In the second embodiment, the job is assigned from 2005/4/1 9:00 (plan start time), and the plan date and time are set.

次に、オーダー指示テーブル10に基づいて、生産すべき製品名を求め、製品マスタ11、工程マスタ12及び資源マスタ20から実施すべきジョブに展開する。そして、未割付ジョブリスト13に登録する(ステップS3)。これが未割付ジョブリスト13の初期状態となる。第二の実施形態における未割付ジョブリスト13の具体例を、下記の表22に示す。   Next, based on the order instruction table 10, a product name to be produced is obtained and developed from the product master 11, the process master 12, and the resource master 20 into jobs to be executed. Then, it is registered in the unallocated job list 13 (step S3). This is the initial state of the unallocated job list 13. A specific example of the unallocated job list 13 in the second embodiment is shown in Table 22 below.

Figure 2007072747
Figure 2007072747

そして、第一の実施形態と同様にして未割付ジョブリスト13及び割付対象ジョブテーブル4に割付対象ジョブがなくなるまで(ステップS5:NO)、ステップS4〜ステップS9(ジョブ割付ステップ)までの処理が行われる。尚、第二の実施形態では、ステップS6において、「あるオーダーのジョブに割付可能=(主資源の稼働時間内)かつ(副資源の稼動時間内)かつ(主資源の対象オーダー)かつ(副資源の対象オーダー)」というロジックに基づいて、ジョブへの資源の割り付けが行われる。   Then, similarly to the first embodiment, the processes from step S4 to step S9 (job allocation step) are performed until there are no allocation target jobs in the unallocated job list 13 and the allocation target job table 4 (step S5: NO). Done. In the second embodiment, in step S6, “assignment to a job of a certain order = (within the operation time of the main resource) and (within the operation time of the sub resource) and (the target order of the main resource) and ( The resource is assigned to the job based on the logic of “resource target order)”.

尚、以上の処理により、資源を割り付けるジョブの状況を示す割付対象ジョブテーブル4の経過の具体例を下記の表23に示す。   The following table 23 shows a specific example of the process of the allocation target job table 4 indicating the status of jobs to which resources are allocated by the above processing.

Figure 2007072747
Figure 2007072747

また、以上の処理により最終的に求められた割付情報テーブル3(生産計画)に基づくジョブの割り付け結果を示すガントチャートを図5に示す。図5に示すように、オーダー1は2時間納期から遅れており、他のオーダーは納期内に完了していることがわかる。   FIG. 5 shows a Gantt chart showing job assignment results based on the assignment information table 3 (production plan) finally obtained by the above processing. As shown in FIG. 5, it can be seen that Order 1 is delayed from the two-hour delivery date, and the other orders are completed within the delivery date.

ここで、オーダー1が納期遅れとならないように対応した資源稼動カレンダー21の具体例を表24に示す。表24は、上述の納期遅れを発生する資源稼動カレンダー21の具体例である表21に対して、作業者2のみに2005/4/2 9:00−12:00、13:00−17:00を稼働時間として加え、その対象オーダーをオーダー1(P01)のみとしている。   Here, a specific example of the resource operation calendar 21 corresponding to the order 1 not to be delayed in delivery is shown in Table 24. Table 24 shows only the worker 2 2005/4/2 9: 00-12: 00, 13: 00-17: Table 21 which is a specific example of the resource operation calendar 21 that causes the above-described delivery delay. 00 is added as the operating time, and the target order is only order 1 (P01).

Figure 2007072747
Figure 2007072747

この表24に示す資源稼動カレンダー21を用いて、上述した図2に示す第二の実施形態に係る生産計画スケジューラ1を用いた生産計画作成方法の処理を行い最終的に求められた割付情報テーブル3(生産計画)に基づくジョブの割り付け結果を示すガントチャートを図6に示す。図6に示すように、作業者2のオーダー1に関わるジョブのみが2005/4/2に割り付けられており、他のオーダーについては、2005/4/2に割り付けられることはない。この結果、オーダー1は、2005/4/4 11:00に完成し、納期遅れを解消していることがわかる。また、従来技術と比較して、第二の実施形態に係る生産計画スケジューラ1を用いた生産計画作成方法の処理を行い最終的に求められた図6に示す生産計画では作業者1及び作業者3を無駄に出勤することを解消していることがわかる。   Using the resource operation calendar 21 shown in Table 24, the allocation information table finally obtained by performing the process of the production plan creation method using the production plan scheduler 1 according to the second embodiment shown in FIG. FIG. 6 shows a Gantt chart showing job allocation results based on 3 (production plan). As shown in FIG. 6, only jobs related to the order 1 of the worker 2 are assigned to 2005/4/2, and other orders are not assigned to 2005/4/2. As a result, Order 1 is completed at 2005/4/4 11:00, and it can be seen that the delivery delay has been eliminated. Compared with the prior art, in the production plan shown in FIG. 6 which is finally obtained by processing the production plan creation method using the production plan scheduler 1 according to the second embodiment, the worker 1 and the worker It can be seen that 3 has been eliminated from wasting work.

このように、第一の実施形態の生産計画作成方法及び生産計画作成装置、並びにプログラムによれば、資源マスタ20に登録する資源として、通常資源及び特定のオーダーのジョブに割付可能なオーダー固有のダミー資源を設けたことにより、資源割付部2においてジョブに資源を割り付ける際に、通常資源の稼働時間且つダミー資源の稼働時間にジョブに割り付けることが可能となり、ダミー資源の稼働時間の設定を調整することでオーダーに関する割付可能な時間をコントロールすることが可能になり、適切に納期遅れを解消することができ、無駄のない生産計画を作成することができる。   As described above, according to the production plan creation method, the production plan creation device, and the program of the first embodiment, as resources to be registered in the resource master 20, it is possible to assign to a normal resource and a specific order job that can be assigned to a specific order job. By providing a dummy resource, when allocating resources to a job in the resource allocation unit 2, it is possible to allocate the job to the normal resource operation time and the dummy resource operation time, and adjust the dummy resource operation time settings. By doing so, it becomes possible to control the time that can be allocated with respect to the order, it is possible to appropriately resolve the delivery delay, and it is possible to create a production plan without waste.

また、第二の実施形態の生産計画作成方法及び生産計画作成装置、並びにプログラムによれば、資源稼動カレンダー21の設定項目に適用可能な対象オーダーが加えられることにより、資源割付部2においてジョブに資源を割り付ける際に、対象オーダーに設定された特定のオーダーにおいてのみ稼働時間の設定が有効になり、ジョブへの資源の割付の制御(割付可能/不可能の制御)が可能になるため、適切に納期遅れを解消することができ、無駄のない生産計画を作成することができる。   Further, according to the production plan creation method, production plan creation apparatus, and program of the second embodiment, a target order that can be applied to the setting items of the resource operation calendar 21 is added to the job in the resource allocation unit 2. When assigning resources, the operating time setting is effective only for the specific order set in the target order, and it is possible to control the assignment of resources to jobs (control of assignability / impossibility), so it is appropriate In addition, the delay in delivery can be eliminated, and a production plan without waste can be created.

以上、本発明の好適な実施の形態について説明したが、本発明は、前記実施の形態に限定されるものではなく、特許請求の範囲に記載した限りにおいてさまざまな変更が可能なものである。   The preferred embodiments of the present invention have been described above. However, the present invention is not limited to the above-described embodiments, and various modifications can be made as long as they are described in the claims.

第一の実施形態において、資源マスタ20に登録したダミー資源の一部または全部について、特定のオーダーの特定のジョブに対して割付可能にしても良い。これにより、オーダーの各ジョブの内、稼働時間を操作したいジョブにダミー資源を割付可能にすることにより、納期遅れを発生する特定のオーダーに対して確実にダミー資源が割り付けられるようになるため、より適切に納期遅れを解消することができ、無駄のない生産計画を作成することができる。   In the first embodiment, part or all of the dummy resources registered in the resource master 20 may be assigned to a specific job in a specific order. As a result, dummy resources can be assigned to specific orders that cause delays in delivery by making it possible to assign dummy resources to jobs whose operating time is to be manipulated among the jobs in the order. It is possible to eliminate delays in delivery more appropriately and to create a production plan without waste.

また、第一の実施形態及び第二の実施形態において、資源稼動カレンダー21について、更に資源の資源量を設定しても良い。これにより、資源量を変えることができる資源についても対応することが可能になる。   In the first embodiment and the second embodiment, the resource amount of the resource may be set for the resource operation calendar 21. As a result, it is possible to deal with resources that can change the amount of resources.

第一の実施形態及び第二の実施形態に係る生産計画作成装置のブロック図である。It is a block diagram of a production plan creation device according to the first embodiment and the second embodiment. 第一の実施形態及び第二の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理の手順について説明したフローチャートである。It is the flowchart explaining the procedure of the process of the production plan preparation method using the production plan scheduler which concerns on 1st embodiment and 2nd embodiment. 通常時の資源稼動カレンダーに基づき第一の実施形態及び第二の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理を行い最終的に求められた生産計画を示すガントチャートである。It is a Gantt chart which shows the production plan finally obtained by processing the production plan creation method using the production plan scheduler according to the first embodiment and the second embodiment based on the normal resource operation calendar. 納期遅れ対策時の資源稼動カレンダーに基づき第一の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理を行い最終的に求められた生産計画を示すガントチャートである。It is a Gantt chart which shows the production plan finally obtained by processing the production plan creation method using the production plan scheduler according to the first embodiment on the basis of the resource operation calendar at the time of delaying delivery. 通常時の資源稼動カレンダーに基づき第二の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理を行い最終的に求められた生産計画を示すガントチャートである。It is a Gantt chart which shows the production plan finally obtained by processing the production plan creation method using the production plan scheduler according to the second embodiment based on the normal resource operation calendar. 納期遅れ対策時の資源稼動カレンダーに基づき第二の実施形態に係る生産計画スケジューラを用いた生産計画作成方法の処理を行い最終的に求められた生産計画を示すガントチャートである。It is a Gantt chart which shows the production plan finally obtained by processing the production plan creation method using the production plan scheduler according to the second embodiment on the basis of the resource operation calendar at the time of delaying delivery date. 通常時の資源稼動カレンダーに基づき従来技術の生産計画スケジューラを用いて求められた生産計画を示すガントチャートである。It is a Gantt chart which shows the production plan calculated | required using the production plan scheduler of the prior art based on the resource operation calendar at the normal time. 納期遅れ対策時の資源稼動カレンダーに基づき従来技術の生産計画スケジューラを用いて求められた生産計画を示すガントチャートである。It is a Gantt chart which shows the production plan calculated | required using the production plan scheduler of the prior art based on the resource operation calendar at the time of a delay in delivery date.

符号の説明Explanation of symbols

1 生産計画スケジューラ(生産計画作成装置)
2 資源割付部(ジョブ割付手段)
3 割付情報テーブル
4 割付対象ジョブテーブル
10 オーダーテーブル
11 製品マスタ
12 工程マスタ
13 未割付ジョブリスト
20 資源マスタ(資源登録手段)
21 資源稼動カレンダー(資源稼動カレンダー登録手段)
22 実績情報テーブル
S1 資源登録ステップ、資源稼動カレンダー登録ステップ
S4〜S9 ジョブ割付ステップ
1 Production plan scheduler (production plan creation device)
2 Resource allocation section (Job allocation means)
3 Allocation information table 4 Job table to be allocated 10 Order table 11 Product master 12 Process master 13 Unallocated job list 20 Resource master (resource registration means)
21 Resource operation calendar (resource operation calendar registration means)
22 Performance information table S1 Resource registration step, Resource operation calendar registration step S4 to S9 Job allocation step

Claims (12)

1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成装置であって、
全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を資源として登録する資源登録手段と、
前記通常資源の稼働時間及び前記ダミー資源の稼働時間を資源稼動カレンダーに設定する資源稼動カレンダー登録手段と、
前記資源稼動カレンダーに基づいて、前記ジョブの内の前記通常資源及び前記ダミー資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記通常資源及び前記ダミー資源を割り付けるジョブ割り付け手段と、
を備えることを特徴とする生産計画作成装置。
For one or more orders, create a production plan by assigning resources that can be assigned to the job, based on the resource operation calendar, for all jobs that are processes required to manufacture the product of the order. A production plan creation device,
Resource registration means for registering normal resources applicable to all orders and order-specific dummy resources applicable to specific orders as resources,
Resource operation calendar registration means for setting the operation time of the normal resource and the operation time of the dummy resource in a resource operation calendar;
Based on the resource operation calendar, unassigned jobs to which the normal resources and the dummy resources are not assigned are sequentially selected by a predetermined assignment algorithm, and the assignable normal resources and the dummy resources are assigned. Job allocation means,
A production plan creation device comprising:
前記資源登録手段で登録するダミー資源は、その一部または全部が特定のオーダーの特定のジョブに割付可能であることを特徴とする請求項1に記載の生産計画作成装置。   2. The production plan creation device according to claim 1, wherein a part or all of the dummy resources registered by the resource registration means can be assigned to a specific job of a specific order. 1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成装置であって、
前記ジョブに割付可能な資源を登録する資源登録手段と、
前記資源の稼働時間と適用可能な対象オーダーとを資源稼動カレンダーに設定する資源稼動カレンダー登録手段と、
前記資源稼動カレンダーに基づいて、前記ジョブの内の前記資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記資源を割り付けるジョブ割り付け手段と、
を備えることを特徴とする生産計画作成装置。
For one or more orders, create a production plan by assigning resources that can be assigned to the job, based on the resource operation calendar, for all jobs that are processes required to manufacture the product of the order. A production plan creation device,
Resource registration means for registering resources that can be allocated to the job;
Resource operation calendar registration means for setting the resource operation time and applicable target orders in a resource operation calendar;
Based on the resource operation calendar, unallocated jobs that have not been allocated the resource among the jobs are sequentially selected by a predetermined allocation algorithm, and job allocation means for allocating the resources that can be allocated;
A production plan creation device comprising:
前記資源稼動カレンダー登録手段は、前記資源の資源量を更に資源稼動カレンダーに設定することを特徴とする請求項1〜3のいずれか一項に記載の生産計画作成装置。   The production schedule creation device according to any one of claims 1 to 3, wherein the resource operation calendar registration unit further sets a resource amount of the resource in a resource operation calendar. 1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成方法であって、
全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を資源として登録する資源登録ステップと、
前記通常資源の稼働時間及び前記ダミー資源の稼働時間を資源稼動カレンダーに設定する資源稼動カレンダー登録ステップと、
前記資源稼動カレンダーに基づいて、前記ジョブの内の前記通常資源及び前記ダミー資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記通常資源及び前記ダミー資源を割り付けるジョブ割り付けステップと、
を備えることを特徴とする生産計画作成方法。
For one or more orders, create a production plan by assigning resources that can be assigned to the job, based on the resource operation calendar, for all jobs that are processes required to manufacture the product of the order. A production plan creation method comprising:
A resource registration step of registering as a resource a normal resource applicable to all orders and an order-specific dummy resource applicable to a specific order;
A resource operation calendar registration step for setting an operation time of the normal resource and an operation time of the dummy resource in a resource operation calendar;
Based on the resource operation calendar, unassigned jobs to which the normal resources and the dummy resources are not assigned are sequentially selected by a predetermined assignment algorithm, and the assignable normal resources and the dummy resources are assigned. Job assignment step;
A production plan creation method characterized by comprising:
前記資源登録ステップで登録するダミー資源は、その一部または全部が特定のオーダーの特定のジョブに割付可能であることを特徴とする請求項5に記載の生産計画作成方法。   6. The production plan creation method according to claim 5, wherein a part or all of the dummy resources registered in the resource registration step can be assigned to a specific job of a specific order. 1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成する生産計画作成方法であって、
前記ジョブに割付可能な資源を登録する資源登録ステップと、
前記資源の稼働時間と適用可能な対象オーダーとを資源稼動カレンダーに設定する資源稼動カレンダー登録ステップと、
前記資源稼動カレンダーに基づいて、前記ジョブの内の前記資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記資源を割り付けるジョブ割り付けステップと、
を備えることを特徴とする生産計画作成方法。
For one or more orders, create a production plan by assigning resources that can be assigned to the job, based on the resource operation calendar, for all jobs that are processes required to manufacture the product of the order. A production plan creation method comprising:
A resource registration step of registering resources that can be allocated to the job;
A resource operation calendar registration step for setting an operation time of the resource and an applicable target order in a resource operation calendar;
Based on the resource operation calendar, unallocated jobs that have not been allocated the resource among the jobs are sequentially selected by a predetermined allocation algorithm, and a job allocation step of allocating the resources that can be allocated;
A production plan creation method characterized by comprising:
前記資源稼動カレンダー登録ステップは、前記資源の資源量を更に資源稼動カレンダーに設定することを特徴とする請求項5〜7のいずれか一項に記載の生産計画作成方法。   The production schedule creation method according to any one of claims 5 to 7, wherein the resource operation calendar registration step further sets a resource amount of the resource in a resource operation calendar. 1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成するためのプログラムであって、
全てのオーダーに適用可能な通常資源と、特定のオーダーに適用可能なオーダー固有のダミー資源と、を資源として登録する資源登録ステップ、
前記通常資源の稼働時間及び前記ダミー資源の稼働時間を資源稼動カレンダーに設定する資源稼動カレンダー登録ステップ、
前記資源稼動カレンダーに基づいて、前記ジョブの内の前記通常資源及び前記ダミー資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記通常資源及び前記ダミー資源を割り付けるジョブ割り付けステップ、
をコンピュータに実行させるためのプログラム。
For one or more orders, create a production plan by assigning resources that can be assigned to the job, based on the resource operation calendar, for all jobs that are processes required to manufacture the product of the order. A program for
A resource registration step for registering normal resources applicable to all orders and order-specific dummy resources applicable to a specific order as resources;
Resource operation calendar registration step for setting the operation time of the normal resource and the operation time of the dummy resource in a resource operation calendar;
Based on the resource operation calendar, unassigned jobs to which the normal resources and the dummy resources are not assigned are sequentially selected by a predetermined assignment algorithm, and the assignable normal resources and the dummy resources are assigned. Job allocation step,
A program that causes a computer to execute.
前記資源登録ステップで登録するダミー資源は、その一部または全部が特定のオーダーの特定のジョブに割付可能であることを特徴とする請求項9に記載のプログラム。   The program according to claim 9, wherein a part or all of the dummy resources registered in the resource registration step can be allocated to a specific job of a specific order. 1つ以上のオーダーにおいて、当該オーダーの製品を製造するのに必要な工程である全てのジョブに対して、資源稼動カレンダーに基づき、当該ジョブに割付可能な資源を割り付けて、生産計画を作成するためのプログラムであって、
前記ジョブに割付可能な資源を登録する資源登録ステップ、
前記資源の稼働時間と適用可能な対象オーダーとを資源稼動カレンダーに設定する資源稼動カレンダー登録ステップ、
前記資源稼動カレンダーに基づいて、前記ジョブの内の前記資源を割り付けていない未割付ジョブを所定の割付アルゴリズムにより順番に選択し、割付可能な前記資源を割り付けるジョブ割り付けステップ、
をコンピュータに実行させるためのプログラム。
For one or more orders, create a production plan by assigning resources that can be assigned to the job, based on the resource operation calendar, for all jobs that are processes required to manufacture the product of the order. A program for
A resource registration step of registering resources that can be allocated to the job;
A resource operation calendar registration step for setting the operation time of the resource and applicable target orders in a resource operation calendar;
A job allocation step of selecting, based on the resource operation calendar, unallocated jobs that have not been allocated the resources of the jobs in order by a predetermined allocation algorithm, and allocating the resources that can be allocated;
A program that causes a computer to execute.
前記資源稼動カレンダー登録ステップは、前記資源の資源量を更に資源稼動カレンダーに設定することを特徴とする請求項9〜11のいずれか一項に記載のプログラム。   The program according to any one of claims 9 to 11, wherein the resource operation calendar registration step further sets a resource amount of the resource in a resource operation calendar.
JP2005258889A 2005-09-07 2005-09-07 Production plan creation method, production plan creation device, and program Expired - Fee Related JP4648136B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005258889A JP4648136B2 (en) 2005-09-07 2005-09-07 Production plan creation method, production plan creation device, and program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005258889A JP4648136B2 (en) 2005-09-07 2005-09-07 Production plan creation method, production plan creation device, and program

Publications (2)

Publication Number Publication Date
JP2007072747A true JP2007072747A (en) 2007-03-22
JP4648136B2 JP4648136B2 (en) 2011-03-09

Family

ID=37934130

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005258889A Expired - Fee Related JP4648136B2 (en) 2005-09-07 2005-09-07 Production plan creation method, production plan creation device, and program

Country Status (1)

Country Link
JP (1) JP4648136B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012093865A (en) * 2010-10-26 2012-05-17 Sumitomo Forestry Co Ltd Production schedule computation method and production schedule computing device
JP2013069119A (en) * 2011-09-22 2013-04-18 Kobe Steel Ltd Scheduling method, scheduling program, and scheduling device
CN111260322A (en) * 2020-01-16 2020-06-09 襄阳航泰动力机器厂 Discrete manufacturing industry work order scheduling improvement method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000040099A (en) * 1998-07-23 2000-02-08 Toshiba Corp Device and method for preparing schedule, selecting method for job and recording medium recording software of schedule preparation
JP2005216074A (en) * 2004-01-30 2005-08-11 Jfe Steel Kk Production plan preparation system, production plan preparation method and program

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000040099A (en) * 1998-07-23 2000-02-08 Toshiba Corp Device and method for preparing schedule, selecting method for job and recording medium recording software of schedule preparation
JP2005216074A (en) * 2004-01-30 2005-08-11 Jfe Steel Kk Production plan preparation system, production plan preparation method and program

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012093865A (en) * 2010-10-26 2012-05-17 Sumitomo Forestry Co Ltd Production schedule computation method and production schedule computing device
JP2013069119A (en) * 2011-09-22 2013-04-18 Kobe Steel Ltd Scheduling method, scheduling program, and scheduling device
CN111260322A (en) * 2020-01-16 2020-06-09 襄阳航泰动力机器厂 Discrete manufacturing industry work order scheduling improvement method

Also Published As

Publication number Publication date
JP4648136B2 (en) 2011-03-09

Similar Documents

Publication Publication Date Title
JP5657189B2 (en) Schedule correction apparatus, schedule correction program, and schedule correction method
Lambrecht et al. ACLIPS: A capacity and lead time integrated procedure for scheduling
US8775229B1 (en) Method of correcting a project schedule
WO2019142225A1 (en) Display control device, program, and display control method
US7356376B1 (en) Work when ready load balancing using critical dates
JP4880827B2 (en) Production scheduling method, program for causing computer to execute production scheduling method, and computer-readable recording medium recording program for causing computer to execute production scheduling method
JP4648136B2 (en) Production plan creation method, production plan creation device, and program
JP5234818B2 (en) Production plan creation method, production plan creation program, and production plan creation device
JP2007213141A (en) Personnel distribution system, personnel distribution method, personnel distribution program, and recording medium with the program recorded thereon
JP5653333B2 (en) Schedule creation method, schedule creation program, and schedule creation device
JP2011100318A (en) Work process control device, work process control method, and program
JP2006202082A (en) Production line management system, production line management program, recording medium, and method for managing production line
JP4319026B2 (en) Schedule creation method, schedule creation system, and program
JP2006146530A (en) Scheduling support system
JP2003006393A (en) Scheduling device and its method
JP2020013313A (en) Shift plan data creation program
JP2010262361A (en) Business management system
JP2001092883A (en) Working manpower assignment supporting device and recording medium storing program
JP2005182685A (en) Production planning method and program
JP2004145814A (en) Scheduling method and program
JPH1086044A (en) Worker&#39;s discretion utilization schedule planning method and device therefor
WO2024042766A1 (en) Progress management system, production execution system, and progress management method
JP4658525B2 (en) Production planning program
JP4350637B2 (en) Manufacturing plan adjustment system, manufacturing plan adjustment program, and manufacturing plan adjustment method
WO2023176846A1 (en) Production planning device, production planning method, and program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070928

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100405

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100810

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101005

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20101207

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20101209

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131217

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees