JP2007002411A - Track construction method - Google Patents

Track construction method Download PDF

Info

Publication number
JP2007002411A
JP2007002411A JP2005180096A JP2005180096A JP2007002411A JP 2007002411 A JP2007002411 A JP 2007002411A JP 2005180096 A JP2005180096 A JP 2005180096A JP 2005180096 A JP2005180096 A JP 2005180096A JP 2007002411 A JP2007002411 A JP 2007002411A
Authority
JP
Japan
Prior art keywords
girder
steel
track
permanent
girders
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2005180096A
Other languages
Japanese (ja)
Other versions
JP4846278B2 (en
Inventor
Yoshio Koizumi
儀生 小泉
Kiyoshi Masuda
潔 増田
Fumihiko Nakamura
中村  文彦
Toshio Ochi
敏夫 越智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2005180096A priority Critical patent/JP4846278B2/en
Publication of JP2007002411A publication Critical patent/JP2007002411A/en
Application granted granted Critical
Publication of JP4846278B2 publication Critical patent/JP4846278B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a track construction method for easily switching a support from steel girders to permanent girder. <P>SOLUTION: The track construction method is for use in switching the temporary support of a track 1 which is set up by temporarily supporting sleepers 3 having rails 2, 2 mounted thereon by the steel girders 4, 4, etc., to the support by the permanent girders 5. By the method, a plurality of mounts 7 each having an elastic bearing 6 with the upper surface separated from the lower surface of each steel girder 4, are arranged under the steel girders 4 at intervals in a steel girder 4 extending direction. Then concrete is placed at least on the periphery of each steel girder 4 around the mount 7 to form a preceding girder 5a, a temporary beam 10 of each steel girder 4 is removed, and the permanent girder 5 is supported by the mount section 7 via the elastic bearing 6. Then, concrete is further placed around the steel girder 4 where the temporary beam 10 has been set, and thus the construction of the permanent girders 5 is completed. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、軌道の高架工事や振動抑制工事などをおこなう際に、一時的に鋼桁上に敷設した軌道を、本設桁による支持に切替える軌道の施工方法に関するものである。   The present invention relates to a track construction method for switching a track temporarily laid on a steel girder to support by a main girder when performing an elevated track construction or vibration suppression construction.

従来、鉄道の軌道の下に地下道、駅舎、地下街などを構築する際に、本設桁を構築する場所の隣接地に設けられた鋼桁によって軌道を一時的に支持させ、本設桁の完成後に軌道の切替えをおこなう方法が知られている(特許文献1など参照)。   Conventionally, when constructing underpasses, station buildings, underground shopping streets, etc. under the railroad track, the track is temporarily supported by a steel girder provided adjacent to the place where the permanent girder is constructed, and the permanent girder is completed. A method of switching the trajectory later is known (see Patent Document 1).

この方法では、一時的に軌道を支持させた鋼桁は本設桁への切替え時に撤去し、本設桁上にはバラスト等を敷き詰めて、その上に軌道を敷設する作業をおこなっていた。   In this method, the steel girder that temporarily supported the track was removed at the time of switching to the main girder, and the work was carried out by laying ballast or the like on the main girder and laying the track on it.

また、特許文献2,3には、レール上を鉄道車両が走行することによって発生する振動が、軌道を支持する構造物に伝達されないようにする防振構造が開示されている。
特開昭50−94713号公報 特開平8−311801号公報 特開平8−311802号公報
Patent Documents 2 and 3 disclose vibration-proof structures that prevent vibrations generated when a rail vehicle travels on a rail from being transmitted to a structure that supports the track.
JP 50-94713 A Japanese Patent Laid-Open No. 8-31801 JP-A-8-31802

しかしながら前記した軌道の施工方法では、工事中に使用した鋼桁を撤去する撤去作業が必要となる上に、撤去作業時の切断などによって破損した鋼桁は再利用することができず廃棄処分がされていた。   However, the above-mentioned track construction method requires a removal work to remove the steel girder used during the construction, and the steel girder damaged by cutting during the removal work cannot be reused and discarded. It had been.

そこで、本発明は、鋼桁から本設桁への切り替えを容易におこなうことができる軌道の施工方法を提供することを目的としている。   Then, this invention aims at providing the construction method of the track | orbit which can perform switching from a steel girder to a permanent girder easily.

前記目的を達成するために、本発明は、レールを載置させる枕木が鋼桁によって一時的に支持されている軌道を、本設桁による支持に切替える軌道の施工方法において、前記鋼桁の下面と離隔する上面が形成された弾性支承部を備えた台座部を前記鋼桁の延伸方向に間隔を置いて複数設け、少なくとも前記台座部周辺の前記鋼桁の周囲にコンクリートを打設して前記本設桁の一部を形成し、前記鋼桁の仮支持部を撤去して前記本設桁を前記台座部に前記弾性支承部を介して支持させ、前記仮支持部が設置されていた前記鋼桁の周囲にコンクリートを打設して前記本設桁を完成させる軌道の施工方法であることを特徴とする。   To achieve the above object, the present invention provides a track construction method for switching a track on which a sleeper on which a rail is placed is temporarily supported by a steel girder to support by a main girder, A plurality of pedestal portions each having an elastic bearing portion formed with an upper surface spaced apart from each other at intervals in the extending direction of the steel girder, and at least concrete is placed around the steel girder around the pedestal portion, Forming a part of a permanent girder, removing the temporary support part of the steel girder and supporting the permanent girder on the pedestal part via the elastic support part, the temporary support part was installed The track construction method is characterized in that concrete is cast around a steel girder to complete the main girder.

ここで、前記台座部には、前記弾性支承部を設置した底板から立設させた壁によって前記本設桁の側面に対向させる凹部を形成し、前記本設桁の側面には該凹部に収容させる突起部を設けることができる。   Here, the pedestal portion is formed with a recess facing the side surface of the permanent girder by a wall erected from the bottom plate on which the elastic support portion is installed, and the side surface of the permanent girder is accommodated in the concave portion. Protruding portions can be provided.

このように構成された本発明の軌道の施工方法は、軌道を仮支持させていた鋼桁の周囲にコンクリートを打設して本設桁を構築し、その本設桁は弾性支承部を介して構造物に支持させる。   The track construction method of the present invention configured as described above is to construct a permanent girder by placing concrete around a steel girder that has temporarily supported the track, and the permanent girder is interposed through an elastic bearing. To support the structure.

このため、鋼桁を撤去する必要がない上に、弾性支承部によって本設桁が支持されるので振動減衰効果が大きい。   For this reason, it is not necessary to remove the steel girder, and since the main girder is supported by the elastic bearing portion, the vibration damping effect is great.

また、前記台座部に設けられた凹部に前記本設桁に設けた前記突起部を係合させることによって、前記本設桁の延伸方向及び横断方向にずれが発生することを防ぐことができる。   Further, by engaging the protrusion provided on the permanent beam with the concave portion provided on the pedestal, it is possible to prevent a deviation in the extending direction and the transverse direction of the permanent beam.

以下、本発明の最良の実施の形態について図面を参照して説明する。   The best mode for carrying out the present invention will be described below with reference to the drawings.

図6は、本実施の形態の軌道の施工方法によって構築された本設桁5上に軌道1を敷設した状態の平面図である。   FIG. 6 is a plan view of a state in which the track 1 is laid on the main beam 5 constructed by the track construction method of the present embodiment.

まず、本実施の形態の軌道1の構成から説明すると、この軌道1は、図1に示すように並行に敷設される2本のレール2,2と、そのレール2,2を載置させるために図6に示すようにレール2,2の延伸方向に間隔をおいて設置される弾性枕木としての枕木3,・・・と、その枕木3にレール2,2を固定させる締結具2a,・・・とによって主に構成されている。   First, the configuration of the track 1 according to the present embodiment will be described. The track 1 is for placing two rails 2 and 2 laid in parallel and the rails 2 and 2 as shown in FIG. As shown in FIG. 6, the sleepers 3,... As elastic sleepers installed at intervals in the extending direction of the rails 2, 2, and the fasteners 2a for fixing the rails 2, 2 to the sleeper 3.・ ・ Mainly composed of

この軌道1は、工事中は鋼桁4,・・・によって支持され、工事後は本設桁5によって支持される。   The track 1 is supported by steel girders 4... During construction and is supported by the main girder 5 after construction.

また、この鋼桁4は、H型鋼材などの鋼材からなり、本設桁5は鋼桁4の周囲にコンクリートを打設することによって形成される。   The steel girder 4 is made of a steel material such as an H-shaped steel material, and the main girder 5 is formed by placing concrete around the steel girder 4.

さらに、この鋼桁4,・・・は、図2に示すように軌道1の延伸方向に間隔を置いて複数設けられた仮支持部としての仮設梁部10,10によって支持される。   Further, as shown in FIG. 2, the steel girders 4,... Are supported by temporary beam portions 10, 10 serving as temporary support portions that are provided at intervals in the extending direction of the track 1.

この仮設梁部10は、H型鋼材などから形成される部材であって、図3に示すように軌道1の延伸直交方向に間隔置いて立設されたH型鋼材製の仮設柱部11,11の上端面間に架け渡される。   The temporary beam portion 10 is a member formed of H-type steel material or the like, and as shown in FIG. 3, as shown in FIG. 11 is bridged between the upper end surfaces.

また、工事後の軌道1を支持する本設桁5は、図1に示すように台座部7,7を介して鉄筋コンクリートなどによって構築された梁部9によって支持される。   Further, the permanent girder 5 that supports the track 1 after the construction is supported by a beam portion 9 constructed of reinforced concrete or the like via pedestal portions 7 and 7, as shown in FIG.

この梁部9の上面に設置される台座部7,7は、図1に示すように断面視L字型に形成されており、一対が向かい合わせになって設置されている。   The pedestal portions 7 and 7 installed on the upper surface of the beam portion 9 are formed in an L shape in cross section as shown in FIG. 1, and a pair is installed facing each other.

この台座部7は、梁部9の上面に当接させる板状の底板7aと、その底板7aの一方の端部から立設された側壁7bと、図2に示すようにその側壁7bの両側に設けられた控え壁7c,7cとによって主に構成される。   The pedestal portion 7 includes a plate-like bottom plate 7a to be brought into contact with the upper surface of the beam portion 9, side walls 7b erected from one end of the bottom plate 7a, and both sides of the side walls 7b as shown in FIG. It is mainly comprised by the retaining walls 7c and 7c provided in this.

この台座部7は、梁部9の上面に型枠を組み立てて鉄筋コンクリートで直接構築することもできるが、工場などによって予め製作したものを設置するものであってもよい。   The pedestal portion 7 can be directly constructed of reinforced concrete by assembling a formwork on the upper surface of the beam portion 9, but may be installed in advance by a factory or the like.

この底板7aの上面には、防振ゴム、圧縮コイルバネ、板バネなどの弾性材によって例えば矩形に形成された弾性支承部6が図2に示すように2個設置され、この弾性支承部6,・・・上に本設桁5は載置される。   On the upper surface of the bottom plate 7a, for example, two elastic support portions 6 formed in a rectangular shape by an elastic material such as an anti-vibration rubber, a compression coil spring, and a leaf spring are installed as shown in FIG. ... the main girder 5 is placed on the top.

また、図2及び図5に示すように、側壁7b及び控え壁7c,7cによって形成される凹部7dには、本設桁5の側面から軌道1の延伸直交方向に突出させた突起部5bが収容される。   Further, as shown in FIGS. 2 and 5, in the concave portion 7 d formed by the side wall 7 b and the retaining walls 7 c and 7 c, a protruding portion 5 b that protrudes from the side surface of the main girder 5 in the extending orthogonal direction of the track 1. Be contained.

さらに、この突起部5dの側面と、側壁7b及び控え壁7c,7cとの間には、ゴム等の緩衝材8を介在させてこれらの部材が直接、接触し合わないようにする。   Further, a cushioning material 8 such as rubber is interposed between the side surface of the protruding portion 5d and the side wall 7b and the retaining walls 7c, 7c so that these members do not come into direct contact with each other.

次に、本実施の形態の軌道の施工方法について説明する。   Next, the track construction method of the present embodiment will be described.

図2は、鋼桁4,・・・を支持させる仮設梁部10,10と、本設桁5を支持させる梁部9,9の両方が配設されている状態の平面図を示したものであり、この前段階として梁部9,9が構築されていない状態が存在する。   FIG. 2 is a plan view showing a state where both the temporary beam portions 10 and 10 for supporting the steel girders 4... And the beam portions 9 and 9 for supporting the main beam 5 are arranged. In this previous stage, there is a state in which the beam portions 9 are not constructed.

図2のような状態になるには、まず仮設柱部11,11と仮設梁部10とによって図3(図2のA−A線断面図)に示すように門型の支持構造物を構築し、その上に並行に鋼桁4,・・・を並べる。   In order to be in the state as shown in FIG. 2, first, a portal-type support structure is constructed by the temporary column parts 11, 11 and the temporary beam part 10 as shown in FIG. 3 (cross-sectional view taken along line AA in FIG. 2) The steel girders 4, ... are arranged in parallel on it.

そして、鋼桁4,・・・の延伸方向に間隔を置いて設置される枕木3,・・・は、鋼桁4,・・・に連結部4aを介して固定する。   And the sleepers 3, ... installed at intervals in the extending direction of the steel girders 4, ... are fixed to the steel girders 4, ... via the connecting portion 4a.

さらに、枕木3,・・・の上には、鋼桁4,・・・の延伸方向と同一方向に向けたレール2,2を載置し、枕木3,・・・に締結具2a,・・・を介して固定する。   Furthermore, on the sleepers 3,..., Rails 2 and 2 are placed in the same direction as the extending direction of the steel girders 4,.・ Fix through.

このようにして敷設された軌道1は、この時点では鋼桁4,・・・によって支持されており、他の部分に軌道1の荷重は作用していないので、図2に示す位置に鉄筋コンクリート製の梁部9,9を構築することができる。   The track 1 laid in this way is supported by the steel girders 4,... At this time, and the load of the track 1 does not act on other parts. The beam portions 9 and 9 can be constructed.

この梁部9は、図6に示すように軌道1の延伸方向に間隔を置いて設けられ、その両端は本設柱部12,12によって下方から支持されると共に、縦桁部13,・・・によって他の梁部9との間が連結される。   As shown in FIG. 6, the beam portions 9 are provided at intervals in the extending direction of the track 1, and both ends thereof are supported from below by the main column portions 12, 12, and the vertical beam portions 13,. The other beam 9 is connected by

そして、この梁部9の上面には、図4(図2のB−B線断面図)に示すように、一対の台座部7,7が向かい合わせとなるように設置される。   And as shown in FIG. 4 (BB sectional drawing of FIG. 2), a pair of base parts 7 and 7 are installed in the upper surface of this beam part 9 so that it may face each other.

この台座部7の底板7aに取り付けられた弾性支承部6の上面は、鋼桁4の下面と離隔するような位置関係となっており、この段階では鋼桁4,・・・・と台座部7,7は接続されておらず鋼桁4,・・・の荷重が台座部7,7側に作用することはない。   The upper surface of the elastic support portion 6 attached to the bottom plate 7a of the pedestal portion 7 is in a positional relationship so as to be separated from the lower surface of the steel girder 4. At this stage, the pedestal portion and the steel girder 4,. 7 and 7 are not connected and the load of the steel girders 4... Does not act on the pedestals 7 and 7 side.

次に、仮設梁部10,10と鋼桁4,・・・が当接して仮支持されている部分を除いた鋼桁4,・・・の周囲にコンクリートを打設して、図5に示すように本設桁5の一部を形成する先行桁部5aを構築する。   Next, concrete is placed around the steel beams 4,... Excluding the portion where the temporary beam portions 10, 10 and the steel beams 4,. As shown, a leading digit portion 5a that forms part of the permanent girder 5 is constructed.

この先行桁部5aは、図1(図5のC−C線断面図)に示すように台座部7,7上に設けられる突起部5b,5bを含む本設桁5の一部であって、鋼桁4,・・・及び連結部4aが露出しないようにコンクリートを打設して形成される。   This leading girder 5a is a part of the main girder 5 including projections 5b and 5b provided on the pedestals 7 and 7, as shown in FIG. The steel girders 4,... And the connecting portion 4a are formed by placing concrete so as not to be exposed.

このようにして先行桁部5a,・・・を形成すると、図5に示したように仮設梁部10,10の周囲だけ鋼桁4,・・・が露出した状態になると共に、図1に示すように台座部7,7上では、先行桁部5aの下面が弾性支承部6,6の上面に当接又は近接する位置まで形成される。   When the leading beam portions 5a,... Are formed in this way, the steel beams 4,... Are exposed only around the temporary beam portions 10, 10, as shown in FIG. As shown, on the pedestal portions 7, 7, the lower surface of the leading beam portion 5 a is formed to a position where it abuts or approaches the upper surfaces of the elastic support portions 6, 6.

但し、この状態では、まだ先行桁部5a,・・・は鋼桁4,・・・に吊られている状態であるため、軌道1は鋼桁4,・・・が仮設梁部10,10に支持されることによって支持されている。   However, in this state, the preceding girder portions 5a,... Are still suspended from the steel girders 4,. It is supported by being supported by.

そこで、図6に示すように仮設梁部10,10を撤去すると、先行桁部5a,・・・が台座部7,・・・の弾性支承部6,・・・上に載置され、支持部材が仮設梁部10,10から本設の梁部9,9に切り替わることになる。   Therefore, when the temporary beam portions 10 and 10 are removed as shown in FIG. 6, the leading beam portions 5a,... Are placed on and supported by the elastic support portions 6,. The member is switched from the temporary beam portions 10 and 10 to the main beam portions 9 and 9.

そして、仮設梁部10,10を撤去することによって露出した鋼桁4,・・・の周囲にコンクリートを打設して後行桁部5c,・・・を構築し、本設桁部5全体を完成させる。   Then, concrete is cast around the steel girders 4,... Exposed by removing the temporary beam parts 10, 10 to construct the following girders 5c,. To complete.

次に、本実施の形態の軌道の施工方法の作用について説明する。   Next, the operation of the track construction method of the present embodiment will be described.

このように構成された本発明の軌道の施工方法は、軌道1を仮支持させていた鋼桁4,・・・の周囲にコンクリートを打設して本設桁5を構築し、その本設桁5は弾性支承部6,・・・を介して本設用に設けられた梁部9,9に支持させる。   The track construction method of the present invention configured as described above is to construct a permanent girder 5 by placing concrete around the steel girders 4,. The girder 5 is supported by the beam portions 9, 9 provided for the main installation through the elastic support portions 6,.

このため、工事中に一時的な仮設として使用した鋼桁4,・・・を撤去する必要がない上に、弾性支承部6,・・・によって本設桁5が支持されるようになるので振動減衰効果が大きく、軌道1の支持構造を防振構造として、鉄道車両通過によって発生する振動が隣接するビルなどの他の構造物に伝播することを抑えることができる。   For this reason, it is not necessary to remove the steel girders 4,... Used as temporary temporary during construction, and the main girders 5 are supported by the elastic bearing parts 6,. The vibration damping effect is great, and the support structure of the track 1 is used as an anti-vibration structure, so that it is possible to suppress the vibration generated by passing through the railway vehicle from propagating to other structures such as adjacent buildings.

また、鋼桁4,・・・を切断して撤去することがないので、破損して再利用できないような廃棄物が発生しない。   In addition, since the steel girders 4,... Are not cut and removed, there is no waste that is broken and cannot be reused.

さらに、台座部7,7に設けられた凹部7d,7dに本設桁5の側面に設けた突起部5b,5bを係合させることによって、本設桁5の延伸方向及び横断方向にずれが発生することを防ぐことができる。   Further, by engaging the projections 5b, 5b provided on the side surface of the permanent girder 5 with the recesses 7d, 7d provided in the pedestal parts 7, 7, there is a shift in the extending direction and the transverse direction of the permanent girder 5. It can be prevented from occurring.

また、弾性支承部6,・・・による支持構造とすることで、バラストを敷設する必要がなくなり維持管理が容易になる。   In addition, the support structure by the elastic support portions 6,... Eliminates the need for laying ballast and facilitates maintenance.

以上、図面を参照して、本発明の最良の実施の形態を詳述してきたが、具体的な構成は、この実施の形態に限らず、本発明の要旨を逸脱しない程度の設計的変更は、本発明に含まれる。   Although the best embodiment of the present invention has been described in detail with reference to the drawings, the specific configuration is not limited to this embodiment, and design changes that do not depart from the gist of the present invention are possible. Are included in the present invention.

例えば、前記した実施の形態では、仮設梁部10が設置されている鋼桁4,・・・の周辺を除いた他の部分を先行桁部5aとして先に構築したが、これに限定されるものではなく、少なくとも台座部7,7上に位置する鋼桁4,・・・の周囲に先行してコンクリートを打設して先行桁部5aを構築すれば、残りの部分は後行桁部5cとして構築することができる。   For example, in the above-described embodiment, the other part excluding the periphery of the steel girders 4,... Where the temporary beam part 10 is installed is first constructed as the preceding girder part 5a. If the preceding girder part 5a is constructed by placing concrete in advance around the steel girders 4,... Positioned at least on the pedestal parts 7, 7, the remaining part is the trailing girder part. It can be constructed as 5c.

また、前記実施の形態では、仮設梁部10及び梁部9を設けた高架上の軌道1の架け替えについて説明したが、これに限定されるものではなく、地下道などを構築するために軌道1の下方を掘削するような場合にも本発明を適用することができる。   In the above embodiment, the replacement of the track 1 on the elevated structure provided with the temporary beam portion 10 and the beam portion 9 has been described. However, the present invention is not limited to this, and the track 1 is used to construct an underpass or the like. The present invention can also be applied to the case of excavating the lower part of the machine.

さらに、前記実施の形態では4本の鋼桁4,・・・によって軌道1を支持させたが、これに限定されるものではなく、鋼桁4の本数及び形状は任意に設定することができる。   Furthermore, in the said embodiment, although the track | orbit 1 was supported by the four steel girders 4, ..., it is not limited to this, The number and shape of the steel girders 4 can be set arbitrarily. .

また、枕木3として弾性枕木を使用したが、これに限定されるものではなく、コンクリート枕木や木製枕木などであってもよい。   Moreover, although the elastic sleeper was used as the sleeper 3, it is not limited to this, A concrete sleeper, a wooden sleeper, etc. may be sufficient.

本発明の最良の実施の形態の軌道を支持させる本設桁の構成を説明する断面図(図5のC−C線断面図)である。It is sectional drawing explaining the structure of the permanent girder which supports the track | orbit of the best embodiment of this invention (CC sectional view taken on the line of FIG. 5). 本発明の最良の実施の形態の軌道の施工方法の手順を説明する平面図である。It is a top view explaining the procedure of the construction method of the track | orbit of the best embodiment of this invention. 図2のA−A線断面図である。It is the sectional view on the AA line of FIG. 図2のB−B線断面図である。FIG. 3 is a sectional view taken along line BB in FIG. 2. 本発明の最良の実施の形態の軌道の施工方法の手順を説明する平面図である。It is a top view explaining the procedure of the construction method of the track | orbit of the best embodiment of this invention. 本発明の最良の実施の形態の軌道の施工方法によって構築された軌道の構成を説明する平面図である。It is a top view explaining the structure of the track | orbit constructed | assembled by the track construction method of the best embodiment of this invention.

符号の説明Explanation of symbols

1 軌道
2 レール
3 枕木
4 鋼桁
5 本設桁
5b 突起部
6 弾性支承部
7 台座部
7a 底板
7b 側壁(壁)
7c 控え壁(壁)
7d 凹部
10 仮設梁部(仮支持部)
1 Track 2 Rail 3 Sleeper 4 Steel Girder 5 Permanent Girder 5b Protrusion 6 Elastic Bearing 7 Base 7a Bottom Plate 7b Side Wall (Wall)
7c Reservation wall (wall)
7d Concave portion 10 Temporary beam portion (temporary support portion)

Claims (2)

レールを載置させる枕木が鋼桁によって一時的に支持されている軌道を、本設桁による支持に切替える軌道の施工方法において、
前記鋼桁の下面と離隔する上面が形成された弾性支承部を備えた台座部を前記鋼桁の延伸方向に間隔を置いて複数設け、少なくとも前記台座部周辺の前記鋼桁の周囲にコンクリートを打設して前記本設桁の一部を形成し、前記鋼桁の仮支持部を撤去して前記本設桁を前記台座部に前記弾性支承部を介して支持させ、前記仮支持部が設置されていた前記鋼桁の周囲にコンクリートを打設して前記本設桁を完成させることを特徴とする軌道の施工方法。
In the track construction method of switching the track on which the sleepers on which the rail is placed are temporarily supported by the steel girders to the support by the main girders,
A plurality of pedestal portions each having an elastic bearing portion formed with an upper surface spaced apart from the lower surface of the steel girder are provided at intervals in the extending direction of the steel girder, and concrete is provided around at least the steel girder around the pedestal portion. Forming a part of the permanent girder, removing the temporary support part of the steel girder, and supporting the permanent girder on the pedestal part via the elastic support part; A track construction method, wherein concrete is placed around the steel girders that have been installed to complete the main girders.
前記台座部には、前記弾性支承部を設置した底板から立設させた壁によって前記本設桁の側面に対向させる凹部を形成し、前記本設桁の側面には該凹部に収容させる突起部を設けたことを特徴とする請求項1に記載の軌道の施工方法。   The pedestal is formed with a recess facing the side surface of the permanent girder by a wall erected from the bottom plate on which the elastic support portion is installed, and a protrusion that is accommodated in the concave portion on the side surface of the permanent girder The track construction method according to claim 1, wherein:
JP2005180096A 2005-06-21 2005-06-21 Track construction method Expired - Fee Related JP4846278B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005180096A JP4846278B2 (en) 2005-06-21 2005-06-21 Track construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005180096A JP4846278B2 (en) 2005-06-21 2005-06-21 Track construction method

Publications (2)

Publication Number Publication Date
JP2007002411A true JP2007002411A (en) 2007-01-11
JP4846278B2 JP4846278B2 (en) 2011-12-28

Family

ID=37688273

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005180096A Expired - Fee Related JP4846278B2 (en) 2005-06-21 2005-06-21 Track construction method

Country Status (1)

Country Link
JP (1) JP4846278B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008303568A (en) * 2007-06-06 2008-12-18 Shimizu Corp Method of implementing vibration isolation of existing track
JP2015124476A (en) * 2013-12-25 2015-07-06 鹿島建設株式会社 Construction girder and erection method of construction girder

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56142955A (en) * 1980-04-09 1981-11-07 Kajima Corp Slab construction incorporating beam with temporalily
JP2002194704A (en) * 2000-12-26 2002-07-10 Taisei Corp Method for constructing girder
JP2003027404A (en) * 2001-07-19 2003-01-29 East Japan Railway Co Method for constructing under-track structure
JP2003082603A (en) * 2001-09-12 2003-03-19 East Japan Railway Co Construction method for structure under rail track

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56142955A (en) * 1980-04-09 1981-11-07 Kajima Corp Slab construction incorporating beam with temporalily
JP2002194704A (en) * 2000-12-26 2002-07-10 Taisei Corp Method for constructing girder
JP2003027404A (en) * 2001-07-19 2003-01-29 East Japan Railway Co Method for constructing under-track structure
JP2003082603A (en) * 2001-09-12 2003-03-19 East Japan Railway Co Construction method for structure under rail track

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008303568A (en) * 2007-06-06 2008-12-18 Shimizu Corp Method of implementing vibration isolation of existing track
JP2015124476A (en) * 2013-12-25 2015-07-06 鹿島建設株式会社 Construction girder and erection method of construction girder

Also Published As

Publication number Publication date
JP4846278B2 (en) 2011-12-28

Similar Documents

Publication Publication Date Title
JP5824424B2 (en) Track slab restraint structure, restraint jig, and method for forming race slab restraint structure
JP3728657B2 (en) Railway bridge replacement method
JP2008303567A (en) Vibration-isolating ballast track
JP4846278B2 (en) Track construction method
JP2009235729A (en) Reinforcement structure of viaduct connection
KR20160117923A (en) Slab track structure of steel-framed reinforced concrete structure (src) for railway bridge, and construction method for the same
JP2006214269A (en) Erected girder
JP4858850B2 (en) Installation method for vibration-proof track of existing track
JP2008127900A (en) Concrete track slab
KR101670587B1 (en) Railway track using Z-shaped precast concrete slab panel
JP2007170044A (en) Steel floor slab reinforcing structure and existing steel floor slab reinforcing method
JP2004324287A (en) Structure and method for laying floating ladder track on steel bridge
JP6754219B2 (en) Floor slab joint structure and floor slab renewal method
KR102122610B1 (en) Concrete track construction method that can be used suitably for a rapid improvement of ballast track, and concrete slab support device and railway building device for the same
JP3788774B2 (en) Railroad track structure and railroad track construction method
KR20170138704A (en) Combination type embedded rail track
JP2004324245A (en) Floating ladder sleeper, floating ladder track, and laying method therefor
JP7473296B2 (en) Invert and invert construction method
JP2861219B2 (en) Bridge deck repair steel slab and its mounting method
KR101160187B1 (en) Precast integrated track girder and it&#39;s manufacture and construction method for railway bridge
JP6905709B2 (en) Deck renewal method, deck joint structure and road bridge
JP6740846B2 (en) Floor slab replacement structure and floor slab replacement construction method
KR101653559B1 (en) Method of repairing railway
KR20200048155A (en) Vibration Absorption Type Vertical Wall Strcture
JP3665909B2 (en) Bridge reconstruction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080215

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100113

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110222

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110331

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111004

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111012

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20171021

Year of fee payment: 6

R150 Certificate of patent or registration of utility model

Ref document number: 4846278

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees