JP2006200205A - Concrete utility pole and method of reinforcing the same - Google Patents

Concrete utility pole and method of reinforcing the same Download PDF

Info

Publication number
JP2006200205A
JP2006200205A JP2005012502A JP2005012502A JP2006200205A JP 2006200205 A JP2006200205 A JP 2006200205A JP 2005012502 A JP2005012502 A JP 2005012502A JP 2005012502 A JP2005012502 A JP 2005012502A JP 2006200205 A JP2006200205 A JP 2006200205A
Authority
JP
Japan
Prior art keywords
reinforcing
concrete
pole
telephone pole
utility pole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005012502A
Other languages
Japanese (ja)
Inventor
Toshifumi Kawasaki
俊史 河崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Teijin Ltd
Original Assignee
Teijin Techno Products Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Teijin Techno Products Ltd filed Critical Teijin Techno Products Ltd
Priority to JP2005012502A priority Critical patent/JP2006200205A/en
Publication of JP2006200205A publication Critical patent/JP2006200205A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method of reinforcing a concrete utility pole capable of achieving a remarkable reduction in construction time and cost, having high safety for operation, capable of providing sufficient strength by a simple method, and not affected by construction environment. <P>SOLUTION: When the concrete utility pole is reinforced by a reinforcing material, the reinforcing material is inserted into an opening part formed in the utility pole. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、コンクリート製電信柱及びその補強方法に関するものである。   The present invention relates to a concrete telephone pole and a reinforcing method thereof.

コンクリート製電信柱等のコンクリート柱が劣化した場合には、通常新たなコンクリート柱への立て替えが行なわれている。
これに対し、経年変化等を考慮して見込まれた耐用年数に達するまで所定の基準を満たしている電信柱については、補強材等による補強を行うことにより延命策を講じる場合もある。その例として、例えば特開2003−314085号公報に開示される如く、劣化部外周にアラミド繊維製シートを巻き付け、樹脂で固めることにより補強を行う方法などが知られている。
When concrete poles such as concrete telegraph poles deteriorate, they are usually replaced with new concrete pillars.
On the other hand, for telegraph poles that satisfy a predetermined standard until the expected service life is reached in consideration of aging, etc., life-prolonging measures may be taken by reinforcing them with reinforcing materials. For example, as disclosed in Japanese Patent Application Laid-Open No. 2003-314085, for example, a method is known in which an aramid fiber sheet is wound around the periphery of a deteriorated portion and is reinforced by hardening with a resin.

上述した従来技術のうち、立て替えによる場合は、劣化した電柱を除去した後新品を立設するまでの間、仮の電信柱が必要となる上、これらの電信柱を仮設しておくための仮設用地が必要となり、電柱立て替えのコストがかさむ上、撤去した電柱を廃棄物として処理するための手間がかかるという問題があった。
さらに、立て替えによる場合は、施工を開始するまでに、地権者や電力会杜との事前の折衝が必要であり、電柱1本の立て替えに1週間程度の時間が必要であった。
Among the above-mentioned conventional techniques, in the case of re-installation, temporary telephone poles are required until a new one is erected after removing the deteriorated telephone poles, and a temporary installation for temporarily setting these telephone poles. There is a problem that land is required, which increases the cost of replacing the utility pole, and takes time to dispose of the removed utility pole as waste.
In addition, in the case of relocation, it was necessary to negotiate in advance with the landowner and the electric power association before the start of construction, and it took about 1 week to replace one utility pole.

一方、アラミド繊維製シートによる補強方法は、立て替えによる方法に比べて施工時間とコストが改善できるが、それでも1本あたり半日程度の施工時間を要する上、施工環境に制約を受けることがあった。
特開2003−314085号公報
On the other hand, the reinforcement method using an aramid fiber sheet can improve the construction time and cost as compared with the method using the replacement, but it still requires a construction time of about half a day per one and is restricted by the construction environment.
Japanese Patent Laid-Open No. 2003-314085

本発明は、上述の課題を解決するものであり、大幅な施工時間の短縮とコストの削減が達成できると同時に、作業の安全性が高く、簡易な方法でかつ充分な強度を得ることが可能である上、施工環境の影響を受けないコンクリート製電信柱の補強方法を提供することを目的とする。   The present invention solves the above-described problems, and can achieve a significant reduction in construction time and cost, while at the same time providing high work safety and a sufficient strength with a simple method. In addition, an object of the present invention is to provide a method for reinforcing a concrete telephone pole that is not affected by the construction environment.

かくして本発明によれば、補強材により補強されたコンクリート製電信柱であって、該補強材が該電信柱に設けられた開口部から該電信柱内部へ挿入されたものであることを特徴とするコンクリート製電信柱、及びコンクリート製電信柱を補強材にて補強するに際し、該補強材を電信柱に設けられた開口部から電信柱内部へ挿入することを特徴とするコンクリート製電信柱の補強方法が提供される。   Thus, according to the present invention, a concrete telephone pole reinforced by a reinforcing material, wherein the reinforcing material is inserted into the inside of the telephone pole from an opening provided in the telephone pole. A concrete telegraph pole to be reinforced, and when reinforcing the concrete telegraph pole with a reinforcing material, the reinforcement is inserted into the telegraph pole from an opening provided in the telegraph pole. A method is provided.

本発明によれば、大幅な施工時間の短縮とコストの削減が達成できると同時に、作業の安全性が高く、簡易な方法でかつ充分な強度を得ることが可能である上、施工環境の影響を受けないコンクリート製電信柱の補強方法が提供されるので、電柱立て替えやアラミド繊維製シートによる補強方法に比べて施工時間とコストが大きく改善できる。   According to the present invention, it is possible to achieve a significant reduction in construction time and cost, and at the same time, work safety is high, it is possible to obtain a sufficient strength with a simple method, and the influence of the construction environment. Since a method for reinforcing a concrete telephone pole that is not subject to the problem is provided, the construction time and cost can be greatly improved as compared with a method for reinforcing a telephone pole and a method using an aramid fiber sheet.

以下、本発明を図面に基づいて説明する。図1は、本発明のコンクリート製電信柱の一実施態様を示す縦断面図及び横断面図である。通常コンクリート製電信柱1は、上端に向かって若干細くなる略円筒形をなしており、複数の鉄筋とその鉄筋の間に充填されたコンクリートから成る外周部11、および外周部11の内側に、本発明で示した方法により補強を行う前には何も充填されていない中空部13を備えている。外周部11の厚み(肉厚)は、電信柱1の横断面直径の1/8程度である。   Hereinafter, the present invention will be described with reference to the drawings. FIG. 1 is a longitudinal sectional view and a transverse sectional view showing one embodiment of a concrete telephone pole of the present invention. Normally, the concrete telephone pole 1 made of concrete has a substantially cylindrical shape that becomes slightly narrower toward the upper end, and a plurality of reinforcing bars and an outer peripheral part 11 made of concrete filled between the reinforcing bars, and an inner side of the outer peripheral part 11, Before the reinforcement is performed by the method shown in the present invention, a hollow portion 13 which is not filled with anything is provided. The thickness (wall thickness) of the outer peripheral part 11 is about 1/8 of the cross-sectional diameter of the telephone pole 1.

電信柱1の根入長(埋設深度)は、柱長のおよそ1/6程度である。地際から所定の高さのところには、アースを設置するためのアース用穴3が備えられている。一例として、コンクリート製電信柱の場合には、立設時に地際から1800mm程度の位置にアース用穴3が備わるように設計されている。   The penetration length (embedding depth) of the telegraph pole 1 is about 1/6 of the pole length. A ground hole 3 for installing a ground is provided at a predetermined height from the ground. As an example, in the case of a concrete telephone pole, it is designed so that the grounding hole 3 is provided at a position of about 1800 mm from the ground when standing.

外周部11のコンクリートの亀裂およびそのコンクリート内部の鉄筋の破断により生じる劣化部9は、経年変化、立設場所の状況等様々な条件が複合的に重なって生じる。劣化部9は、図1に示すように比較的地際に近い場所に生じやすく、このためアース用穴3は劣化部9よりも上部に設置されていることが多い。   The deteriorated portion 9 caused by cracks in the concrete at the outer peripheral portion 11 and the breakage of the reinforcing bars inside the concrete is caused by a combination of various conditions such as secular change and the situation of the standing place. As shown in FIG. 1, the deteriorated portion 9 is likely to be generated at a location relatively close to the ground. For this reason, the grounding hole 3 is often installed above the deteriorated portion 9.

図2は、上記のような電信柱の具体的な補強方法の作業工程を表すフローチャートである。先ずステップS1で、電信柱にアース用穴が具備されている場合には、アース用穴の表面に取り付けられたカバーを取り外し、これを開口部とする(ステップS3)。他方、電信柱にアース用穴3が存在しない場合は、コアドリル等を用いて足場ボルト取付部等に穴をあけ、適宜開口部を設ける(ステップS5)。
尚、以下の各ステップについては、アース用穴から補強材を注入する場合につき説明するが、足場ボルト取付部に穴をあけた場合も全く同じである。
FIG. 2 is a flowchart showing a work process of a concrete reinforcing method for a telephone pole as described above. First, in step S1, if the telephone pole is provided with a grounding hole, the cover attached to the surface of the grounding hole is removed, and this is used as an opening (step S3). On the other hand, when the grounding hole 3 does not exist in the telephone pole, a hole is drilled in the scaffolding bolt mounting portion using a core drill or the like, and an opening is appropriately provided (step S5).
The following steps will be described with respect to the case where the reinforcing material is injected from the ground hole, but the same applies when the hole is drilled in the scaffold bolt mounting portion.

次のステップでは、補強後に図1のモルタル充填部5の支柱となる、アラミド繊維強化樹脂材料製鉄筋代替材料(補強材)7a、7b、…を数本、アース用穴3から中空部13に挿入する(ステップS7)。この際使用される鉄筋代替材料7a、7b、…は、中空部13最下部からアース用穴3に達する程度の長さを有する(ステップS7)。   In the next step, after reinforcement, several aramid fiber reinforced resin material reinforcing steel substitutes (reinforcing materials) 7a, 7b,... Which become the support of the mortar filling portion 5 in FIG. Insert (step S7). The reinforcing steel substitute materials 7a, 7b,... Used at this time have a length that reaches the grounding hole 3 from the lowermost portion of the hollow portion 13 (step S7).

上記方法により、鉄筋代替材料を挿入した後、砂、セメント、および水を適宜混合して生成したモルタルを、図3に示すように、モルタルポンプ21によりアース用穴3付近まで充填する(ステップS9)。そして、モルタル充填を行った後、アース用穴カバーを再び装着し、劣化部9の表面を防水塗料等により処理する(ステップS11)。なお、以上説明した補強方法においては、モルタルを充填する前に、中空部13の最下部付近に砂を充填させておいてもよい。   After inserting the reinforcing bar substitute material by the above method, the mortar produced by appropriately mixing sand, cement, and water is filled to the vicinity of the grounding hole 3 by the mortar pump 21 as shown in FIG. 3 (step S9). ). Then, after filling with mortar, the ground hole cover is mounted again, and the surface of the deteriorated portion 9 is treated with a waterproof paint or the like (step S11). In the reinforcing method described above, sand may be filled in the vicinity of the lowermost portion of the hollow portion 13 before filling with mortar.

かくして補強されたコンクリート製電信柱の最下部からアース用穴3に達する部分には、図1に示す如く、補強材としてアラミド繊維強化樹脂材料からなる複数の鉄筋代替材料7a、7b、…が挿入され、さらにセメントと砂を水で練り上げて混合したモルタルが充填されている。   As shown in FIG. 1, a plurality of reinforcing bar replacement materials 7a, 7b,... Made of aramid fiber reinforced resin material are inserted into the portion reaching the grounding hole 3 from the lowermost part of the concrete telephone pole reinforced in this way. Furthermore, it is filled with mortar in which cement and sand are kneaded with water and mixed.

また、アース用穴3より上部に出来た劣化部を補強する場合には、上述した補強方法によりモルタル充填を行った後、例えば、劣化部付近の外部から補強を行うといった別の補強方法を併用することにより補強を行うことが好ましい。   In addition, when reinforcing the deteriorated part formed above the ground hole 3, after the mortar filling by the above-described reinforcing method, for example, another reinforcing method such as reinforcing from the outside near the deteriorated part is used in combination. It is preferable to reinforce.

以下、0.1mm程度のひび割れを21箇所有し、立設後10年を経過したコンクリート製電信柱(以後、単に電柱と呼ぶ)の補強における、強度確認試験の例を挙げて本発明の構成および効果をさらに詳細に説明する。   Hereinafter, the structure of the present invention will be described with reference to an example of a strength confirmation test in reinforcement of a concrete telephone pole (hereinafter simply referred to as a power pole) having 21 cracks of about 0.1 mm and 10 years after standing. The effect will be described in more detail.

[実施例1]
補強の対象とした電柱は、総重量700kg、柱長16000mmで、直径400mm、肉厚50mmの中空略円筒形をなしている。外周部のコンクリート内には、支柱として10本の鉄筋が配筋され、最下部が地際から2500mmの位置に埋設されている。また、アース用穴3は、地際から1800mm程度上部に位置しており、縦60mm、横30mmの楕円形をなしている。そして、該電柱は立設後10年を経過したものであり、0.1mm程度のひび割れを21箇所有している。
[Example 1]
The utility pole to be reinforced has a total weight of 700 kg, a pillar length of 16000 mm, a hollow substantially cylindrical shape with a diameter of 400 mm and a wall thickness of 50 mm. Ten reinforcing bars are arranged as pillars in the outer peripheral concrete, and the lowermost part is embedded at a position of 2500 mm from the ground. The grounding hole 3 is located about 1800 mm above the ground and has an elliptical shape of 60 mm in length and 30 mm in width. And this electric pole has passed 10 years after standing, and has 21 cracks of about 0.1 mm.

上記電柱に、図2に示す方法により、コポリパラフェニレン・3、4’−オキシジフェニレン・テレフタラミド繊維(帝人テクノプロダクツ(株)製「テクノーラ」)に、特開平3−103561号公報に開示の方法によりエポキシアクリレート樹脂を含浸させて得た鉄筋代替材料を挿入した後、200lのモルタルをアース用穴3に達する位置まで充填して補強を行った。尚、上記モルタルは、砂:セメント:水の比を3:1:2として混合したものである。
上記の補強に際しては、充填されたモルタルが硬化するのに約1週間を要するため、補強後2週間放置した後、強度確認試験を行った。
As disclosed in JP-A-3-103561, copolyparaphenylene 3,4′-oxydiphenylene terephthalamide fiber (“Technola” manufactured by Teijin Techno Products Co., Ltd.) is applied to the above utility pole by the method shown in FIG. After inserting the reinforcing steel substitute material obtained by impregnating the epoxy acrylate resin by the method, 200 l of mortar was filled up to the position reaching the ground hole 3 for reinforcement. The mortar is a mixture of sand: cement: water at a ratio of 3: 1: 2.
In the above-mentioned reinforcement, since it takes about one week for the filled mortar to harden, it was left for two weeks after the reinforcement, and then a strength confirmation test was performed.

図4は強度確認試験の概要を示すための模式図であり、先ず電柱1を水平に配置し、立設時の電柱最下部から4000mm(立設時、地際から15mm上部)の位置に、外周部11のコンクリート内に配筋された鉄筋のうちの1本をサンダで切断した劣化部9を作成した後、立設時に埋設される部分(電柱の最下部から2500mm)を固定装置により固定した。固定装置は、固定台31、33と、各固定台にジャッキによりそれぞれ締結された枕材31a、31bおよび33a、33bとから構成されている。   FIG. 4 is a schematic diagram for showing an outline of the strength confirmation test. First, the utility pole 1 is horizontally arranged, and at a position of 4000 mm from the lowest part of the utility pole at the time of standing (at the time of standing, 15 mm from the ground) After creating the deteriorated part 9 by cutting one of the reinforcing bars arranged in the concrete of the outer peripheral part 11 with sander, the part embedded at the time of standing (2500 mm from the lowest part of the utility pole) is fixed with a fixing device did. The fixing device is composed of fixing bases 31 and 33 and pillow materials 31a and 31b and 33a and 33b fastened to the fixing bases by jacks.

強度の測定は、固定されていない方の端部(立設時の上端)から250mmの位置を荷重点とし、電柱の中心軸になるべく直角となる方向に、一定の速度で試験荷重に達するまで荷重を加えた。その後、荷重の方向を180度回転して、再び試験荷重に達するまで荷重を加えた。以上の操作の後、いずれかの方向で電柱が破壊するまで荷重を加え続け、そのときまでに荷重計の示した最大荷重を破壊荷重とし、この最大荷重の値を強度とした。   The strength is measured until the test load is reached at a constant speed in a direction as perpendicular as possible to the center axis of the utility pole, with the load point at a position 250 mm from the end that is not fixed (upper end when standing). A load was applied. Thereafter, the direction of the load was rotated 180 degrees, and the load was applied until the test load was reached again. After the above operation, the load was continuously applied until the utility pole broke in either direction, and the maximum load indicated by the load meter was taken as the breaking load until that time, and the value of this maximum load was taken as the strength.

上記の方法で補強された電柱の強度は、試験荷重を7.00kNとし、下向きに荷重を加え続けていった場合、17.79kNであり、新品の電柱を同条件で測定した場合の15〜16kNと比べて遜色のない値であった。   The strength of the utility pole reinforced by the above method is 17.79 kN when the test load is 7.00 kN and the load is continuously applied downward, and is 15 to 15 when a new utility pole is measured under the same conditions. Compared to 16 kN, the value was not inferior.

また、本発明の方法によれば、施工時間は電柱1本当たり約2時間であり、従来の立て替えやアラミド繊維製シートによる補強方法に比べて工期を格段に短縮することが可能である上、施工コストが1本あたり10万円以下で済むため、立て替えによる方法の1/3、アラミド繊維製シートによる補強方法の1/2程度にコストを削減することができる。
さらに、電柱の開口部を介して補強作業を行なうため、作業の安全性が高く、立て替えの場合のように撤去した電柱の処理に手間がかかることもない。
In addition, according to the method of the present invention, the construction time is about 2 hours per utility pole, and the construction period can be significantly shortened compared to the conventional method of reinforcement or reinforcement by an aramid fiber sheet, Since the construction cost is 100,000 yen or less per one piece, the cost can be reduced to about 1/3 of the method by the replacement and about 1/2 of the reinforcing method by the aramid fiber sheet.
Further, since the reinforcement work is performed through the opening of the utility pole, the safety of the work is high, and it does not take time to process the removed utility pole as in the case of replacement.

本発明のコンクリート製電信柱の補強方法は、大幅な施工時間の短縮とコストの削減が達成できると同時に、作業の安全性が高く、簡易な方法でかつ充分な強度を得ることが可能である上、施工環境の影響を受けないので、電柱立て替えやアラミド繊維製シートによる補強方法に比べて施工時間とコストが大きく改善できる。   The method for reinforcing concrete telegraph poles according to the present invention can achieve a significant reduction in construction time and cost, and at the same time, the work safety is high, and it is possible to obtain sufficient strength with a simple method. In addition, since it is not affected by the construction environment, construction time and cost can be greatly improved as compared with a method of reinforcing a power pole or a reinforcement method using an aramid fiber sheet.

本発明のコンクリート製電信柱の一実施態様を示す縦断面図及び横断面図である。It is the longitudinal cross-sectional view and cross-sectional view which show one embodiment of the concrete telephone poles of this invention. 本発明の電信柱の補強方法の作業工程を表すフローチャートである。It is a flowchart showing the work process of the reinforcement method of the telephone pole of this invention. 本発明のコンクリート製電信柱の補強方法の一実施態様を示す断面図である。It is sectional drawing which shows one embodiment of the reinforcement method of the concrete telephone pole of this invention. 本発明のコンクリート製電信柱の強度確認試験の概要を示すための模式図である。It is a schematic diagram for showing the outline | summary of the strength confirmation test of the concrete telephone pole of this invention.

符号の説明Explanation of symbols

1 コンクリート製電信柱
3 アース用穴(開口部)
5 モルタル充填部
7a、7b、7c 鉄筋代替材料
9 劣化部
11 外周部
13 中空部
21 モルタルポンプ
31、33 固定台
31a、31b、33a、33b 枕材
1 Concrete telephone pole 3 Ground hole (opening)
5 Mortar filling part 7a, 7b, 7c Steel bar substitute material 9 Deteriorating part 11 Outer part 13 Hollow part 21 Mortar pump 31, 33 Fixing base 31a, 31b, 33a, 33b Pillow material

Claims (4)

補強材により補強されたコンクリート製電信柱であって、該補強材が該電信柱に設けられた開口部から該電信柱内部へ挿入されたものであることを特徴とするコンクリート製電信柱。   A concrete telephone pole reinforced with a reinforcing material, wherein the reinforcing material is inserted into an inside of the telephone pole from an opening provided in the telephone pole. 補強材が、複数の鉄筋代替材料およびモルタルから成る補強材である請求項1記載のコンクリート製電信柱。   The concrete telephone pole according to claim 1, wherein the reinforcing material is a reinforcing material made of a plurality of reinforcing bar substitute materials and mortar. 鉄筋代替材料が、アラミド繊維強化樹脂材料である請求項1又は2記載のコンクリート製電信柱。   The concrete telephone pole according to claim 1 or 2, wherein the reinforcing steel substitute material is an aramid fiber reinforced resin material. コンクリート製電信柱を補強材にて補強するに際し、該補強材を電信柱に設けられた開口部から電信柱内部へ挿入することを特徴とするコンクリート製電信柱の補強方法。   A method for reinforcing a concrete telephone pole, comprising: inserting a reinforcing material into an inside of a telephone pole from an opening provided in the telephone pole when the concrete telephone pole is reinforced with a reinforcing material.
JP2005012502A 2005-01-20 2005-01-20 Concrete utility pole and method of reinforcing the same Pending JP2006200205A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005012502A JP2006200205A (en) 2005-01-20 2005-01-20 Concrete utility pole and method of reinforcing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005012502A JP2006200205A (en) 2005-01-20 2005-01-20 Concrete utility pole and method of reinforcing the same

Publications (1)

Publication Number Publication Date
JP2006200205A true JP2006200205A (en) 2006-08-03

Family

ID=36958446

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005012502A Pending JP2006200205A (en) 2005-01-20 2005-01-20 Concrete utility pole and method of reinforcing the same

Country Status (1)

Country Link
JP (1) JP2006200205A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010047985A (en) * 2008-08-21 2010-03-04 Hiroyasu Minayoshi Reinforcing body for hollow pole and reinforcing method for the hollow pole by use of the reinforcing body
JP2012127134A (en) * 2010-12-16 2012-07-05 Nippon Concrete Ind Co Ltd Reinforcement material and reinforcement method of concrete column body

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004092376A (en) * 2002-02-15 2004-03-25 Ntt Infranet Co Ltd Reinforcement method for concrete utility pole, reinforced concrete utility pole and reinforcement suspending jig for concrete utility pole

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004092376A (en) * 2002-02-15 2004-03-25 Ntt Infranet Co Ltd Reinforcement method for concrete utility pole, reinforced concrete utility pole and reinforcement suspending jig for concrete utility pole

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010047985A (en) * 2008-08-21 2010-03-04 Hiroyasu Minayoshi Reinforcing body for hollow pole and reinforcing method for the hollow pole by use of the reinforcing body
JP2012127134A (en) * 2010-12-16 2012-07-05 Nippon Concrete Ind Co Ltd Reinforcement material and reinforcement method of concrete column body

Similar Documents

Publication Publication Date Title
JP2007162448A (en) Reinforcing method and reinforcing structure for columnar structure
JP6259807B2 (en) Road bridge guard fence and its installation method
JP2016160690A (en) Road bridge protection fence and its installation method
CN106013211A (en) Foundation bolt group fixing structure and construction method thereof
JP4389237B1 (en) Pressure receiving device for anchor method and anchor method
JP3786938B2 (en) Reinforcement method for concrete structures
JP2006316585A (en) Anticorrosive reinforcing method of steel pipe column
KR20100014193A (en) Concrete pile
JP6399680B2 (en) Caisson with cutable temporary wall for shield excavation
JP2006200205A (en) Concrete utility pole and method of reinforcing the same
JP4999617B2 (en) Reinforcement method for concrete structures
JP4420697B2 (en) Standing structure of steel pipe columns
JP2003166352A (en) Method for reinforcing concrete column, and reinforced concrete column
KR100540928B1 (en) method for manufacturing anchor bolt carrying out and an anchor bolt
JPH1018424A (en) Root wrapping reinforcing structure of column base of steel post or the like
JP5367115B2 (en) Reinforcement method for concrete structures
JP5534861B2 (en) PC well and bridge construction method
KR20110095538A (en) Method for head setting of micro-pile and apparatus for the same
JP6345328B1 (en) Original position building method and original position structure
KR101273375B1 (en) PHC pile head cutting work and reinforced concrete structure for jointing scaffolding structural steel and construction method therof
JP2011184956A (en) Cap for grouting hole cap
JP2010281181A (en) Foundation structure of cylindrical storage tank
KR20020089029A (en) Reinforced Method of Head in a Prestressed Spun High Strength Concrete Pile
JP6403394B2 (en) Anchor bolt construction method
JP2004150251A (en) Replacement of corroded deteriorated handrail by reuse of existing driving anchor material, and its construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20071120

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20091105

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091110

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100316