JP2004076533A - Pile connecting structure - Google Patents
Pile connecting structure Download PDFInfo
- Publication number
- JP2004076533A JP2004076533A JP2002242189A JP2002242189A JP2004076533A JP 2004076533 A JP2004076533 A JP 2004076533A JP 2002242189 A JP2002242189 A JP 2002242189A JP 2002242189 A JP2002242189 A JP 2002242189A JP 2004076533 A JP2004076533 A JP 2004076533A
- Authority
- JP
- Japan
- Prior art keywords
- pile
- bolt
- end plate
- diameter
- head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、コンクリート杭や鋼管杭の接続構造に関し、特に、上杭と下杭を簡単かつ確実に接続することができる作業性の高い杭の接続構造に関するものである。
【0002】
【従来の技術】
従来、上杭と下杭を接続する杭の接続構造としては、上杭と下杭の端板同士を溶接により接続したり、端板の外周部にフランジ継手を突設し、この対設するフランジ継手間をボルト、ナットにて締結する方法が汎用されている。
また、上杭の端部と下杭の端部に、一対の内嵌部と外嵌部を振り分けて設けるとともに、これら内嵌部と外嵌部にそれぞれねじを形成し、内嵌部と外嵌部を螺合接続する方法もある。
【0003】
【発明が解決しようとする課題】
ところで、上記従来の上杭と下杭を接続する接続構造は、それぞれ次のような問題点を有している。
▲1▼溶接による杭の接続構造においては、溶接に時間を要したり、天候によっては施工現場において溶接作業を行うことができなかったり、さらに、溶接の欠陥や溶接部の脆化を防止するためには、所要の設備と熟練した技術者を必要とし、コストがかかったり、技術者が不足がちになる。
▲2▼フランジ継手による接続方法では、継手部分の外径が鋼管杭の外径よりも大きく、鋼管杭の外周面から大きく突出することから、杭を地盤中に埋設する際に大きな貫入抵抗となり、また継手部分に曲げモーメントが作用し、さらに継手部分間には杭の外周に空間が生じてしまい、水平支持力が確保できなくなるおそれがある。
▲3▼上杭の端部と下杭の端部に設けた内嵌部と外嵌部を螺合接続する杭の接続構造は、大径となる内嵌部と外嵌部にねじを形成するための機械加工がコスト高を招き、また、重量物である杭の螺合接続作業は作業性が悪く、多大な手間を要し、さらに、内嵌部と外嵌部に形成したねじが損傷を受けやすく、この場合には、螺合接続作業が困難になる。
【0004】
本発明は、上記従来の杭の接続構造が有する問題点に鑑み、上杭と下杭を簡単かつ確実に接続し、かつ杭径をこの接続部においても大径とならないようにすることができる作業性の高い杭の接続構造を提供することを目的とする。
【0005】
【課題を解決するための手段】
上記目的を達成するため、本発明の杭の接続構造は、上杭と下杭とを各々の端板を介して接続する杭の接続構造において、端板に形成されたボルト穴にボルトを螺合するとともに、相手側の端板のボルトの対向位置に、ボルトの頭部が挿入される大径部と、該大径部と連通しボルト頭部の周方向の移行を許容する大径溝部と、該大径溝部からボルトの軸部を挟むように突設され、移行したボルトの頭部を掛止する鍔部とを形成し、ボルトを相手側端板の大径部に挿入して杭を回転させることにより、ボルト頭部を大径溝部に移行させて端板同士を固定するようにしたことを特徴とする。
【0006】
この杭の接続構造は、端板に形成されたボルト穴にボルトを螺合するとともに、相手側の端板のボルトの対向位置に、ボルトの頭部が挿入される大径部と、該大径部と連通しボルト頭部の周方向の移行を許容する大径溝部と、該大径溝部からボルトの軸部を挟むように突設され、移行したボルトの頭部を掛止する鍔部とを形成し、ボルトを相手側端板の大径部に挿入して杭を回転させることにより、ボルト頭部を大径溝部に移行させて端板同士を固定することから、上杭及び下杭の各端板同士をボルトを介して簡単に固定することができ、これにより、上杭と下杭の接続を迅速かつ安価に行うことができるとともに、杭の外周部に突起物がないことから、杭径を一定として貫入作業に支障なく杭を地盤中に埋設することができる。
また、本発明の杭の接続構造は、鋼管杭とプレストレスコンクリート杭との接続も強固に行うことができ、さらに、杭の接続が簡易かつ短時間に行えることから、杭の施工効率を大幅に向上させることができる。
【0007】
この場合において、前記ボルト穴として緊張用タップ穴を使用することができる。
【0008】
これにより、予めプレストレスコンクリート杭の端板に形成される緊張用タップ穴を利用して加工工程の手数を減じることができる。
【0009】
また、上杭及び下杭の各端板のボルト穴にボルトを螺合するとともに、各端板のボルトの対向位置に大径部と大径溝部と鍔部とを形成し、ボルトを相手側端板の大径部に相互に挿入して杭を回転させることができる。
【0010】
これにより、上杭と下杭の端板を相互にボルトで固定することができ、杭の接続をより強固に行うことができる。
【0011】
また、上杭又は下杭の一方の端板のボルト穴にボルトを螺合するとともに、他方の端板のボルトの対向位置に大径部と大径溝部と鍔部とを形成し、ボルトを相手側端板の大径部に相互に挿入して杭を回転させるようにすることができる。
【0012】
これにより、上杭と下杭の端板同士をボルトを介して簡易に固定することができる。
【0013】
また、ボルト頭部の下面と対向する鍔部の位置の片側に、塑性変形層を形成することができる。
【0014】
これにより、ボルト(ボルト頭部)が、相手側端板の大径部から大径溝部に移行するときに、ボルト頭部の下面が、塑性変形層と接触し、その摩擦抵抗により特定の一方向(ボルトを締め付ける方向)に回転して、ボルトによる締付力を出現させることができる。
【0015】
また、上杭と下杭の各端板に、回転させた位置で一致するキー溝を形成し、該キー溝に回り止めのキー部材を固設することができる。
【0016】
これにより、回転後の位置で上下の杭を固定して杭の逆回転を防止し、大径部からボルトが抜けることを防止することができる。
【0017】
【発明の実施の形態】
以下、本発明の杭の接続構造の実施の形態を図面に基づいて説明する。
【0018】
図1〜図3に、本発明の杭の接続構造の一実施例を示す。
この杭の接続構造は、上杭1と下杭2とを各々の端板3を介して接続するもので、上杭1と下杭2の各端板3に形成された杭を製造する際に使用される緊張用タップ穴4に、例えば、高力ボルト等のボルト5を螺合するとともに、相手側の端板3のボルト5の対向位置に、ボルト5の頭部51が挿入される大径部31と、該大径部31と連通しボルト頭部51の周方向の移行を許容する大径溝部32と、該大径溝部32からボルト5の軸部52を挟むように突設され、移行したボルト5の頭部51を掛止する鍔部33とを形成している。
そして、ボルト5を相手側端板3の大径部31に挿入し、その状態で、例えば上杭1を回転させることにより、ボルト頭部51を大径溝部32に移行させて端板3同士を固定するようにしている。
この場合、ボルト5は、ボルト5を相手側端板3の大径部31に挿入し、そのボルト頭部51を大径溝部32に移行させることができるように、所定長突出した状態に螺合しておくようにする。
【0019】
さらに、ボルト5(ボルト頭部51)が、相手側端板3の大径部31から大径溝部32に移行するときに、ボルト5が締まる方向に自然に回転するように、図1(b’)に示すように、ボルト頭部51の下面と対向する鍔部33の位置の片側に、ポリエチレン樹脂等の合成樹脂やアルミニウム等の金属からなる塑性変形層33aを、塑性変形層33aにボルト頭部51の下面が接触する程度の厚さに形成するようにする。これにより、ボルト5(ボルト頭部51)が、相手側端板3の大径部31から大径溝部32に移行するときに、ボルト頭部51の下面が、塑性変形層33aと接触し、その摩擦抵抗により特定の一方向(ボルト5を締め付ける方向)に回転して、ボルト5による締付力を出現させることができる。
【0020】
また、上杭1と下杭2の各端板3には、回転させた位置で一致するキー溝6が数カ所形成されている。このキー溝6には、回り止めのためのくさび状のキー部材7が打ち込みにより固設されている。
このように、杭1、2の回転後の位置で、上杭端板3のキー溝6と下杭端板3のキー溝6とをキー部材7で結合することにより、杭1、2の逆回転を防止し、大径部31からボルト5が抜けることを防止している。
なお、杭に曲げ力が加わると、キー部材7が抜けることも考えられるため、キー部材7を、図2(c)に示すように、縦型H型のように形成するとともに、キー溝6を同じ形状に形成することもできる。
【0021】
上杭1や下杭2は、プレストレストコンクリート杭等のコンクリート杭からなり、その端部には端板3が配設されている。
端板3には、PC鋼棒8に隣接するように、コンクリート杭にプレストレスをかける際に使用された複数の緊張用タップ穴4が等間隔で形成されており、これらの緊張用タップ穴4には、軸部52が少し出る状態で複数のボルト5が締着されている。
なお、突出する軸部52の長さは、後述する大径溝部32の鍔部33の厚みよりもやや長くなるようにする。
【0022】
これに対し、相手側の端板3のボルト5と対向する位置には、前記した大径部31と大径溝部32、そして、大径溝部32の表側の縁部から突設された鍔部33が形成されている。
大径部31は端板3を貫通するように形成され、また、大径溝部32は、鍔部33を残して大径部31を端板3の周方向に延長するように形成されている。この場合、複数の大径部31において、大径溝部32は同じ方向に延設されている。
なお、本実施例の場合(後述の図4に示す実施例も同様)、平面視して、下杭2に対して上杭1を左回転することにより、上杭1と下杭2を接続することができるが、このほか、後述の図5に示す実施例のように、平面視して、下杭2に対して上杭1を右回転することにより、上杭1と下杭2を接続するようにすることもできる。
上杭1と下杭2を接続するときには、図2〜図3に示すように、複数のボルト5をそれぞれ相手側端板3の大径部31に挿入し、その状態で上杭1を回転させることによって、ボルト頭部51を大径溝部32に移行させ、上杭1と下杭2の端板3同士を固定する。
そして、杭の回転後の位置で、上下の端板3のキー溝6にキー部材7を打ち込むことにより、杭の逆回転を防止し、大径部31からのボルト5の抜けを防止する。
【0023】
一方、図4に示すように、大径部31、大径溝部32及び鍔部33、又はボルト5は、上杭1や下杭2のいずれか一方の端板3にのみ形成することもできる。
すなわち、上杭1又は下杭2の一方の端板3の緊張用タップ穴4にボルト5を螺合するとともに、他方の端板3のボルト5の対向位置に大径部31と大径溝部32と鍔部33とを形成し、ボルト5を相手側端板3の大径部31に挿入して上杭1を回転させるようにする。
なお、大径部31、大径溝部32及び鍔部33を形成する端板3は、作用する曲げや引張力を考慮して、ボルト5側の端板3よりやや厚みを大きくすることが望ましい。
このように、大径部31、大径溝部32及び鍔部33を一方の端板3に、また、ボルト5を他方の端板3に形成することにより、上杭1と下杭2の端板3同士をボルト5を介して簡易に固定することができる。
【0024】
また、本発明の杭の接続構造は、鋼管杭同士、鋼管杭とコンクリート杭の組み合わせにも適用することができる。
すなわち、図5に示すように、筒状に形成された鋼管杭の端部に円環状の端板3を溶接等により固定し、例えば、上杭1の端板3に前記した大径部31、大径溝部32及び鍔部33を形成するとともに、下杭2の円環状の端板3にボルト穴を形成してボルト5を螺合する。
そして、上杭1と下杭2を接続するときには、複数のボルト5を相手側端板3の大径部31に挿入し、その状態で上杭1を回転させることによって、ボルト頭部51を大径溝部32に移行させ、上杭1と下杭2の端板3同士を固定する。
また、杭の回転後の位置で、上下の端板3のキー溝6にキー部材7を打ち込むことにより、杭の逆回転を防止し、大径部31からのボルト5の抜けを防止する。
【0025】
かくして、本実施例の杭の接続構造は、端板3に形成された緊張用タップ穴4にボルト5を螺合するとともに、相手側の端板3のボルト5の対向位置に、ボルト5の頭部51が挿入される大径部31と、該大径部31と連通しボルト頭部51の周方向の移行を許容する大径溝部32と、該大径溝部32からボルト5の軸部52を挟むように突設され、移行したボルト5の頭部51を掛止する鍔部33とを形成し、ボルト5を相手側端板3の大径部31に挿入して杭を回転させることにより、ボルト頭部51を大径溝部32に移行させて端板3同士を固定することから、上杭1及び下杭2の各端板3同士をボルト5を介して簡単に固定することができ、これにより、上杭1と下杭2の接続を迅速かつ安価に行うことができるとともに、杭の外周部に突起物がないことから、杭径を一定として貫入作業に支障なく杭を地盤中に埋設することができる。
そして、上杭1及び下杭2の各端板3の緊張用タップ穴4にボルト5を螺合するとともに、各端板3のボルト5の対向位置に大径部31と大径溝部32と鍔部33とを形成し、ボルト5を相手側端板3の大径部31に相互に挿入して杭を回転させることにより、上杭1と下杭2の端板3を相互にボルト5で固定することができ、杭の接続をより強固に行うことができる。
この場合、ボルト穴として緊張用タップ穴4を使用することにより、予めプレストレスコンクリート杭の端板3に形成される緊張用タップ穴4を利用して加工工程の手数を減じることができる。
また、本発明の杭の接続構造は、鋼管杭とプレストレスコンクリート杭との接続も強固に行うことができ、さらに、杭の接続が簡易かつ短時間に行えることから、杭の施工効率を大幅に向上させることができる。
【0026】
以上、本発明の実施例を説明したが、本発明の杭の接続構造はこの実施例に記載した構成に限定されるものではなく、各実施例に記載した構成を適宜組み合わせたり、端板に鋼材や鋳鉄を適宜使用する等、その趣旨を逸脱しない範囲において適宜その構成を変更することができる。
【0027】
【発明の効果】
本発明の杭の接続構造によれば、端板に形成されたボルト穴にボルトを螺合するとともに、相手側の端板のボルトの対向位置に、ボルトの頭部が挿入される大径部と、該大径部と連通しボルト頭部の周方向の移行を許容する大径溝部と、該大径溝部からボルトの軸部を挟むように突設され、移行したボルトの頭部を掛止する鍔部とを形成し、ボルトを相手側端板の大径部に挿入して杭を回転させることにより、ボルト頭部を大径溝部に移行させて端板同士を固定することから、上杭及び下杭の各端板同士をボルトを介して簡単に固定することができ、これにより、上杭と下杭の接続を迅速かつ安価に行うことができるとともに、杭の外周部に突起物がないことから、杭径を一定として貫入作業に支障なく杭を地盤中に埋設することができる。
また、本発明の杭の接続構造は、鋼管杭とプレストレスコンクリート杭との接続も強固に行うことができ、さらに、杭の接続が簡易かつ短時間に行えることから、杭の施工効率を大幅に向上させることができる。
【0028】
この場合、前記ボルト穴として緊張用タップ穴を使用することにより、予めプレストレスコンクリート杭の端板に形成される緊張用タップ穴を利用して施工の工数を減じることができる。
【0029】
また、上杭及び下杭の各端板のボルト穴にボルトを螺合するとともに、各端板のボルトの対向位置に大径部と大径溝部と鍔部とを形成し、ボルトを相手側端板の大径部に相互に挿入して杭を回転させることにより、上杭と下杭の端板を相互にボルトで固定することができ、杭の接続をより強固に行うことができる。
【0030】
また、上杭又は下杭の一方の端板のボルト穴にボルトを螺合するとともに、他方の端板のボルトの対向位置に大径部と大径溝部と鍔部とを形成し、ボルトを相手側端板の大径部に相互に挿入して杭を回転させるようにすることにより、上杭と下杭の端板同士をボルトを介して簡易に固定することができる。
【0031】
また、ボルト頭部の下面と対向する鍔部の位置の片側に、塑性変形層を形成することにより、ボルト(ボルト頭部)が、相手側端板の大径部から大径溝部に移行するときに、ボルト頭部の下面が、塑性変形層と接触し、その摩擦抵抗により特定の一方向(ボルトを締め付ける方向)に回転して、ボルトによる締付力を出現させることができる。
【0032】
また、上杭と下杭の各端板に、回転させた位置で一致するキー溝を形成し、該キー溝に回り止めのキー部材を固設することにより、回転後の位置で上下の杭を固定して杭の逆回転を防止し、大径部からボルトが抜けることを防止することができる。
【図面の簡単な説明】
【図1】本発明の杭の接続構造の一実施例を示し、(a)は杭の端板の要部拡大平面図、(b)は端板の裏側から見た大径部と大径溝部の正面図、(b’)は塑性変形層を形成した状態を示す端板の裏側から見た大径部と大径溝部の正面図、(c)は杭の要部拡大断面図である。
【図2】同実施例の杭の接続構造の接続工程を示す要部拡大断面図である。
【図3】上杭の端板と下杭の端板をそれぞれ表側から見た正面図である。
【図4】他の実施例の上杭の端板と下杭の端板をそれぞれ表側から見た正面図である。
【図5】鋼管杭の接続構造を示し、(a)は上杭の端板の底面図、(b)は上杭と下杭の接続を示す断面図である。
【符号の説明】
1 上杭
2 下杭
3 端板
31 大径部
32 大径溝部
33 鍔部
33a 塑性変形層
4 緊張用タップ穴
5 ボルト
51 頭部
52 軸部
6 キー溝
7 キー部材
8 PC鋼棒[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a connection structure for a concrete pile or a steel pipe pile, and more particularly to a connection structure for a pile with high workability that can easily and reliably connect an upper pile and a lower pile.
[0002]
[Prior art]
Conventionally, as a connection structure of a pile that connects an upper pile and a lower pile, end plates of the upper pile and the lower pile are connected by welding, or a flange joint is protrudingly provided on an outer peripheral portion of the end plate, and this is installed oppositely. A method of fastening between flange joints with bolts and nuts is widely used.
In addition, a pair of inner fitting portions and outer fitting portions are separately provided at an end of the upper pile and an end portion of the lower pile, and screws are formed in the inner fitting portions and the outer fitting portions, respectively. There is also a method of screwing and connecting the fitting portions.
[0003]
[Problems to be solved by the invention]
By the way, the conventional connection structure for connecting the upper pile and the lower pile has the following problems, respectively.
(1) In the connection structure of piles by welding, welding takes time, welding work cannot be performed at the construction site depending on the weather, and welding defects and weld brittleness are prevented. In order to do so, required equipment and skilled technicians are required, which is costly and tends to be short of technicians.
(2) In the connection method using a flange joint, since the outer diameter of the joint is larger than the outer diameter of the steel pipe pile and protrudes greatly from the outer peripheral surface of the steel pipe pile, a large penetration resistance occurs when the pile is buried in the ground. In addition, a bending moment acts on the joints, and a space is formed between the joints on the outer periphery of the pile, and there is a possibility that the horizontal support force cannot be secured.
(3) The connection structure of the pile, which screw-connects the inner fitting part and the outer fitting part provided at the end of the upper pile and the end of the lower pile, forms a screw at the inner fitting part and the outer fitting part which have a large diameter. In addition, the threading connection of heavy piles is inferior in workability and requires a great deal of labor, and the screws formed in the inner and outer fitting parts are expensive. It is easily damaged, and in this case, the screw connection work becomes difficult.
[0004]
The present invention, in view of the above-mentioned problems of the conventional pile connection structure, can easily and surely connect the upper pile and the lower pile, and can prevent the pile diameter from becoming large even at this connection portion. An object of the present invention is to provide a connection structure for piles with high workability.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, a connection structure for piles according to the present invention is a connection structure for piles in which an upper pile and a lower pile are connected via respective end plates, wherein bolts are screwed into bolt holes formed in the end plates. A large-diameter portion into which the head of the bolt is inserted, and a large-diameter groove communicating with the large-diameter portion and allowing a circumferential transition of the bolt head at the position facing the bolt on the mating end plate. And a flange portion protruding from the large-diameter groove portion so as to sandwich the shaft portion of the bolt, and forming a flange portion for hooking the head of the transferred bolt, and inserting the bolt into the large-diameter portion of the mating end plate. By rotating the pile, the bolt head is shifted to the large-diameter groove to fix the end plates to each other.
[0006]
In this connection structure for a pile, a bolt is screwed into a bolt hole formed in an end plate, and a large-diameter portion into which the head of the bolt is inserted at a position facing the bolt on the mating end plate; A large-diameter groove portion communicating with the diameter portion and allowing the circumferential movement of the bolt head, and a flange portion projecting from the large-diameter groove portion so as to sandwich the bolt shaft portion, and hooking the transferred bolt head portion The bolts are inserted into the large-diameter portion of the mating end plate and the pile is rotated to shift the bolt head to the large-diameter groove and fix the end plates together. Each end plate of the pile can be easily fixed to each other via bolts, so that the connection between the upper pile and the lower pile can be performed quickly and inexpensively, and there is no protrusion on the outer periphery of the pile. Therefore, the pile can be buried in the ground without hindering the penetration work with a constant pile diameter.
Further, the connection structure of the pile according to the present invention can strongly connect the steel pipe pile and the prestressed concrete pile, and furthermore, since the connection of the pile can be performed easily and in a short time, the construction efficiency of the pile is greatly improved. Can be improved.
[0007]
In this case, a tension tap hole can be used as the bolt hole.
[0008]
Thus, the number of working steps can be reduced by using the tension tap holes formed in the end plate of the prestressed concrete pile in advance.
[0009]
In addition, a bolt is screwed into a bolt hole of each end plate of the upper pile and the lower pile, and a large-diameter portion, a large-diameter groove portion, and a flange portion are formed at positions facing the bolts of each end plate. The pile can be rotated by inserting it into the large diameter part of the end plate.
[0010]
Thus, the end plates of the upper pile and the lower pile can be fixed to each other with bolts, and the piles can be connected more firmly.
[0011]
In addition, a bolt is screwed into a bolt hole of one end plate of the upper pile or the lower pile, and a large-diameter portion, a large-diameter groove portion, and a flange portion are formed at positions facing the bolts of the other end plate. The pile can be rotated by inserting it into the large diameter portion of the mating end plate.
[0012]
Thereby, the end plates of the upper pile and the lower pile can be easily fixed via the bolts.
[0013]
Further, a plastically deformable layer can be formed on one side of the position of the flange portion facing the lower surface of the bolt head.
[0014]
As a result, when the bolt (bolt head) moves from the large-diameter portion of the mating end plate to the large-diameter groove, the lower surface of the bolt head comes into contact with the plastically deformable layer, and the specific resistance is determined by the frictional resistance. By rotating in the direction (the direction in which the bolt is tightened), the tightening force of the bolt can be developed.
[0015]
In addition, a key groove corresponding to the rotated position is formed in each end plate of the upper pile and the lower pile, and a key member for preventing rotation is fixed to the key groove.
[0016]
Thereby, the upper and lower piles are fixed at the position after the rotation, thereby preventing the piles from rotating in the reverse direction and preventing the bolts from coming off from the large diameter portion.
[0017]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, an embodiment of a pile connection structure of the present invention will be described with reference to the drawings.
[0018]
1 to 3 show one embodiment of the pile connection structure of the present invention.
This pile connection structure connects the
Then, the
In this case, the
[0019]
Further, when the bolt 5 (bolt head 51) moves from the large-
[0020]
Also, several
In this way, by connecting the
When the bending force is applied to the pile, the
[0021]
The
A plurality of tension tap holes 4 used when prestressing the concrete pile are formed at equal intervals in the
The length of the protruding
[0022]
On the other hand, the large-
The large-
In the case of this embodiment (the same applies to the embodiment shown in FIG. 4 described later), the
When connecting the
By driving the
[0023]
On the other hand, as shown in FIG. 4, the
That is, the
The
By forming the large-
[0024]
Further, the connection structure of piles according to the present invention can be applied to a combination of steel pipe piles or a combination of steel pipe piles and concrete piles.
That is, as shown in FIG. 5, an
When connecting the
Further, by driving the
[0025]
Thus, the connection structure of the pile according to the present embodiment is such that the
Then, a
In this case, by using the
Further, the connection structure of the pile according to the present invention can strongly connect the steel pipe pile and the prestressed concrete pile, and furthermore, since the connection of the pile can be performed easily and in a short time, the construction efficiency of the pile is greatly improved. Can be improved.
[0026]
As mentioned above, although the Example of this invention was described, the connection structure of the pile of this invention is not limited to the structure described in this Example, The structure described in each Example is suitably combined, The configuration can be appropriately changed within a range that does not deviate from the purpose, such as by appropriately using a steel material or cast iron.
[0027]
【The invention's effect】
According to the pile connection structure of the present invention, the bolt is screwed into the bolt hole formed in the end plate, and the large-diameter portion into which the head of the bolt is inserted at a position facing the bolt on the mating end plate. A large-diameter groove communicating with the large-diameter portion and allowing the bolt head to shift in the circumferential direction; and a projecting portion protruding from the large-diameter groove so as to sandwich the bolt shaft, and hooking the transferred bolt head. By forming a flange part to stop, inserting the bolt into the large diameter part of the mating end plate and rotating the pile, the bolt head is shifted to the large diameter groove part and the end plates are fixed, The end plates of the upper pile and the lower pile can be easily fixed to each other via bolts, thereby making it possible to quickly and inexpensively connect the upper pile and the lower pile, and to projecting on the outer periphery of the pile. Since there is no object, the pile can be buried in the ground without hindering the penetration work with a constant pile diameter.
Further, the connection structure of the pile according to the present invention can strongly connect the steel pipe pile and the prestressed concrete pile, and furthermore, since the connection of the pile can be performed easily and in a short time, the construction efficiency of the pile is greatly improved. Can be improved.
[0028]
In this case, by using a tension tap hole as the bolt hole, it is possible to reduce the number of construction steps by using the tension tap hole formed in the end plate of the prestressed concrete pile in advance.
[0029]
In addition, a bolt is screwed into a bolt hole of each end plate of the upper pile and the lower pile, and a large-diameter portion, a large-diameter groove portion, and a flange portion are formed at positions facing the bolts of each end plate. By rotating the pile by mutually inserting it into the large diameter portion of the end plate, the end plates of the upper pile and the lower pile can be fixed to each other with bolts, and the pile can be connected more firmly.
[0030]
In addition, a bolt is screwed into a bolt hole of one end plate of the upper pile or the lower pile, and a large-diameter portion, a large-diameter groove portion, and a flange portion are formed at positions facing the bolts of the other end plate. By rotating the pile by mutually inserting it into the large diameter portion of the mating end plate, the end plates of the upper pile and the lower pile can be easily fixed via bolts.
[0031]
Further, by forming a plastically deformable layer on one side of the position of the flange portion facing the lower surface of the bolt head, the bolt (bolt head) moves from the large-diameter portion of the mating end plate to the large-diameter groove portion. Sometimes, the lower surface of the bolt head comes into contact with the plastically deformable layer and rotates in a specific direction (the direction in which the bolt is tightened) due to its frictional resistance, so that a tightening force by the bolt can appear.
[0032]
Further, a key groove corresponding to the rotated position is formed on each end plate of the upper pile and the lower pile, and a key member for preventing rotation is fixed to the key groove, so that the upper and lower piles are rotated at the rotated position. Can be fixed to prevent reverse rotation of the pile and prevent the bolt from coming off from the large diameter portion.
[Brief description of the drawings]
1A and 1B show an embodiment of a connection structure of a pile according to the present invention, wherein FIG. 1A is an enlarged plan view of a main part of an end plate of the pile, and FIG. 1B is a large diameter portion and a large diameter as viewed from the back side of the end plate. (B ′) is a front view of the large-diameter portion and the large-diameter groove viewed from the back side of the end plate showing a state in which a plastic deformation layer is formed, and (c) is an enlarged cross-sectional view of a main part of the pile. .
FIG. 2 is an enlarged sectional view of a main part showing a connection step of a connection structure of the pile of the embodiment.
FIG. 3 is a front view of the end plate of the upper pile and the end plate of the lower pile as viewed from the front side, respectively.
FIG. 4 is a front view of an end plate of an upper pile and an end plate of a lower pile viewed from the front side according to another embodiment.
5A and 5B show a connection structure of a steel pipe pile, FIG. 5A is a bottom view of an end plate of an upper pile, and FIG. 5B is a cross-sectional view showing a connection between an upper pile and a lower pile.
[Explanation of symbols]
DESCRIPTION OF
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002242189A JP3965572B2 (en) | 2002-08-22 | 2002-08-22 | Pile connection structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002242189A JP3965572B2 (en) | 2002-08-22 | 2002-08-22 | Pile connection structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004076533A true JP2004076533A (en) | 2004-03-11 |
JP3965572B2 JP3965572B2 (en) | 2007-08-29 |
Family
ID=32024458
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002242189A Expired - Fee Related JP3965572B2 (en) | 2002-08-22 | 2002-08-22 | Pile connection structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3965572B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007138522A (en) * | 2005-11-17 | 2007-06-07 | Mitani Sekisan Co Ltd | Connection structure of pile and pc steel bar |
CN102689358A (en) * | 2012-06-21 | 2012-09-26 | 江苏建华管桩有限公司 | Tensioning component and tensioning method of prestressed endless sheet pile and pile including component |
KR102267641B1 (en) * | 2020-07-13 | 2021-06-22 | 피에이치씨탑다운(주) | PHC pile construction method using joint PHC pile and detachable auxiliary pile |
KR102268120B1 (en) * | 2020-07-13 | 2021-06-25 | 피에이치씨탑다운(주) | PHC pile construction method using casing guide and removeable auxiliary pile |
-
2002
- 2002-08-22 JP JP2002242189A patent/JP3965572B2/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007138522A (en) * | 2005-11-17 | 2007-06-07 | Mitani Sekisan Co Ltd | Connection structure of pile and pc steel bar |
CN102689358A (en) * | 2012-06-21 | 2012-09-26 | 江苏建华管桩有限公司 | Tensioning component and tensioning method of prestressed endless sheet pile and pile including component |
CN102689358B (en) * | 2012-06-21 | 2014-07-16 | 江苏建华管桩有限公司 | Tensioning component and tensioning method of prestressed endless sheet pile and pile including component |
KR102267641B1 (en) * | 2020-07-13 | 2021-06-22 | 피에이치씨탑다운(주) | PHC pile construction method using joint PHC pile and detachable auxiliary pile |
KR102268120B1 (en) * | 2020-07-13 | 2021-06-25 | 피에이치씨탑다운(주) | PHC pile construction method using casing guide and removeable auxiliary pile |
Also Published As
Publication number | Publication date |
---|---|
JP3965572B2 (en) | 2007-08-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100835778B1 (en) | Attachable and detachable joint apparatus of concrete pile for foundation work | |
JP4626450B2 (en) | Threaded joint structure of metal pipe | |
US20040047693A1 (en) | Joining structure of pile | |
KR20210066309A (en) | Apparatus for reinforcing the pile head | |
JP5077944B2 (en) | Pile head rebar fittings | |
JP2004076533A (en) | Pile connecting structure | |
JP2006241696A (en) | Joint structure of concrete of foundation or footing to pile head and structure having the joint structure | |
JP4943379B2 (en) | Steel pipe joint structure | |
JP3457304B1 (en) | Connection structure of pile | |
JP2001011871A (en) | Pile head end structure by projecting metal fixture of precast pile | |
JP6233752B2 (en) | Pile head structure | |
JP2011021711A (en) | Steel sheet fastener and steel sheet joining method | |
JP4461153B2 (en) | Pile joint structure | |
JPH1181304A (en) | Connection structure of steel pipe | |
JP3902637B2 (en) | Pile fastening structure and fastener | |
JP2004293035A (en) | Joint structure of steel pipe | |
JP2004162345A (en) | Joining method and joint structure for prefabricated pile and foundation | |
JP2009114727A (en) | Connecting fixture of pile head reinforcing rod | |
JP2019082203A (en) | Fastener, method for repairing sheet pile and method for repairing structure | |
KR102465683B1 (en) | Coupling apparatus for non-welding of pile | |
JP2008248611A (en) | Support fixing structure of shield tunnel | |
JP4239610B2 (en) | Steel pipe joining method | |
JP2005330797A (en) | Anchor bolt holder | |
JP2526356Y2 (en) | Pile connection device | |
EP0633360B1 (en) | Pile coupling for prefabricated pile elements made of concrete |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20050705 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20070405 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070417 |
|
A711 | Notification of change in applicant |
Free format text: JAPANESE INTERMEDIATE CODE: A712 Effective date: 20070423 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070515 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 3965572 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110608 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120608 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120608 Year of fee payment: 5 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120608 Year of fee payment: 5 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120608 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120608 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130608 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130608 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
R360 | Written notification for declining of transfer of rights |
Free format text: JAPANESE INTERMEDIATE CODE: R360 |
|
R370 | Written measure of declining of transfer procedure |
Free format text: JAPANESE INTERMEDIATE CODE: R370 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |