JP2003313890A - Construction method of underground structure - Google Patents

Construction method of underground structure

Info

Publication number
JP2003313890A
JP2003313890A JP2002120584A JP2002120584A JP2003313890A JP 2003313890 A JP2003313890 A JP 2003313890A JP 2002120584 A JP2002120584 A JP 2002120584A JP 2002120584 A JP2002120584 A JP 2002120584A JP 2003313890 A JP2003313890 A JP 2003313890A
Authority
JP
Japan
Prior art keywords
underground structure
constructing
slab concrete
underground
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002120584A
Other languages
Japanese (ja)
Other versions
JP4031284B2 (en
Inventor
Tadahiro Fukumoto
忠浩 福本
Taku Hirai
卓 平井
Nobutomo Mori
森  信智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Doboku Co Ltd
Original Assignee
Takenaka Doboku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Doboku Co Ltd filed Critical Takenaka Doboku Co Ltd
Priority to JP2002120584A priority Critical patent/JP4031284B2/en
Publication of JP2003313890A publication Critical patent/JP2003313890A/en
Application granted granted Critical
Publication of JP4031284B2 publication Critical patent/JP4031284B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method favorable for the construction of a long underground structure such as an underground road, a channel or a tunnel, or a non-long underground tank while eliminating the waste of material and labor required for the construction of the underground structure by using the improved ground improved by a deep mixing method, as it is as a structural main body. <P>SOLUTION: This construction method comprises a step of improving the ground for constructing the underground structure, into a range of bearing internal and external force working on the underground structure, by a deep mixing method, a step of excavating the improved ground down to the depth position of a slab bottom plate to construct slab concrete, and a step of using the slab concrete as a strut after the slab concrete manifests required strength, to excavate the improved ground below by a space portion equivalent to the underground structure and finishing the internal wall, floor, and the like of this space to complete the underground structure. <P>COPYRIGHT: (C)2004,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、地下に道路、水
路、トンネル等の所謂長尺地下構造物又は非長尺の地下
タンク等を構築する工法の技術分野に属し、更に云え
ば、深層混合処理工法により地盤改良した改良地盤を構
造主体に利用する地下構造物の構築工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technical field of a construction method for constructing a so-called long underground structure such as a road, a waterway, a tunnel or a non-long underground tank underground, and more specifically, a deep mixing method. The present invention relates to a construction method for an underground structure that uses mainly the improved ground improved by the treatment method.

【0002】[0002]

【従来の技術】従来、トンネルに用いられるボックスカ
ルバート等の地下構造物を構築する場合には、図5に例
示したように、先ず山留めbを構築し、地盤の掘削と共
に切梁cを仮設して掘削を進め、掘削完了後に掘削底部
dに地下構造物aを構築する山留め切梁工法が一般的に
実施されている。
2. Description of the Related Art Conventionally, in the case of constructing an underground structure such as a box culvert used for a tunnel, as shown in FIG. 5, a mountain retaining b is first constructed, and a girder c is temporarily installed together with excavation of the ground. The excavation work is generally carried out by constructing the underground structure a on the excavation bottom part d after completion of the excavation.

【0003】特殊な例として、地下階を先行して構築し
切梁に利用しながら地盤の掘削を進める逆打ち工法も実
施されている。
As a special example, there is also practiced a reverse construction method in which a basement floor is constructed in advance and used as a girder to excavate the ground.

【0004】また、地盤の液状化や沈下対策、地下水対
策などの必要がある場合には、地盤を予め広く地盤改良
した上で、その改良地盤について、構造物の地下部分に
必要な掘削を行い、構造物の建築を進めるオープンカッ
ト工法(特開平6−73722号公報)も実施されてい
る。
When it is necessary to take countermeasures against liquefaction and subsidence of the ground, countermeasures against groundwater, etc., the ground is broadly improved in advance, and then the improved ground is subjected to necessary excavation in the underground part of the structure. The open-cut construction method (Japanese Patent Laid-Open No. 6-73722) for promoting the construction of structures has also been implemented.

【0005】[0005]

【本発明が解決しようとする課題】しかしながら、上記
山留め切梁工法は、山留めbや切梁c等の仮設部材を多
く必要とする上に、地下構造物aを独立して構築するの
でコストが嵩み工期が長びく欠点がある。
However, the above-mentioned mountain retaining beam construction method requires a large number of temporary members such as mountain retaining b and beam c, and the underground structure a is constructed independently, so that the cost is low. It is bulky and takes a long time to construct.

【0006】上記した逆打ち工法は、仮設部材の使用を
軽減できる利点はあるものの、居住空間を有する建物の
構築を主目的として実施するものであり、道路や水路、
トンネル等の所謂長尺地下構造物の構築には適さない。
Although the above-mentioned reverse construction method has an advantage that the use of temporary members can be reduced, it is carried out mainly for the purpose of constructing a building having a living space.
It is not suitable for the construction of so-called long underground structures such as tunnels.

【0007】更に、上記オープンカット工法も、仮設部
材の使用を軽減できる利点はあるものの、改良地盤は山
留めあるいは止水壁として利用するものでしかなく、構
造物は改良地盤上へ独立して構築するから、無駄が多
い。
Further, although the above open cut method also has an advantage that the use of temporary members can be reduced, the improved ground is only used as a mountain retaining or a water blocking wall, and the structure is independently constructed on the improved ground. Therefore, there is a lot of waste.

【0008】本発明の目的は、深層混合処理工法により
地盤改良した改良地盤をそっくり構造主体に利用するこ
とで、地下構造物の構築に要する資材や労力の無駄を省
き、コストを軽減でき、地下道路、水路、トンネル等の
所謂長尺地下構造物或いは非長尺の地下タンク等の構築
に好適な構築工法を提供することにある。
[0008] The object of the present invention is to use the improved ground improved by the deep-mixing processing method as a structural main body so that the waste of materials and labor required for constructing an underground structure can be saved and the cost can be reduced. An object of the present invention is to provide a construction method suitable for constructing so-called long underground structures such as roads, waterways, and tunnels, or non-long underground tanks.

【0009】[0009]

【課題を解決するための手段】上述の課題を解決するた
めの手段として、請求項1に記載した発明に係る地下構
造物の構築工法は、地下構造物を構築する地盤を同地下
構造物へ働く内外力を負担可能な範囲まで深層混合処理
工法により地盤改良する段階と、改良地盤をスラブ底盤
の深さ位置まで掘削し、スラブコンクリートを構築する
段階と、前記スラブコンクリートが所要の強度を発現し
た後に、これを切梁に利用して下方の改良地盤を地下構
造物に相当する空間分だけ掘削を進め、同空間の内壁、
床などの仕上げを行って地下構造物を完成する段階と、
から成ることを特徴とする。
[Means for Solving the Problems] As a means for solving the above-mentioned problems, the construction method for an underground structure according to the invention described in claim 1 is a method for constructing a ground for constructing an underground structure into the same underground structure. The step of improving the ground by the deep-mixing method to the extent that the working internal and external forces can be borne, the step of excavating the improved ground to the depth of the slab bottom to construct the slab concrete, and the slab concrete exhibiting the required strength. After that, using this as a truss, the improved ground below is excavated by the space equivalent to the underground structure, and the inner wall of the space,
The stage of finishing the underground structure by finishing the floor etc.,
It is characterized by consisting of.

【0010】請求項2に記載した発明は、請求項1に記
載した地下構造物の構築工法において、深層混合処理工
法により地盤改良した改良地盤をスラブ底盤の深さ位置
まで掘削する工程に先行して、スラブコンクリートを支
持するのに適切な部位にH鋼等の柱心材を建て込み、し
かる後にスラブコンクリートを構築して前記柱心材によ
って支持させ、次いで前記スラブコンクリートの下方の
改良地盤の掘削を進め、掘削した空間の内壁、床などの
仕上げを行うことを特徴とする。
The invention described in claim 2 is the method for constructing an underground structure according to claim 1, which is prior to the step of excavating the improved ground improved by the deep mixing method to the depth position of the slab floor. Then, a column core material such as H steel is erected at an appropriate portion for supporting the slab concrete, and then the slab concrete is constructed and supported by the column core material, and then the excavation of the improved ground below the slab concrete is performed. It is characterized by advancing and finishing the inner wall and floor of the excavated space.

【0011】[0011]

【発明の実施形態、及び実施例】図1は、請求項1に記
載した発明に係る地下構造物の構築工法の実施形態を示
している。この構築工法は、図1の紙面と垂直方向に長
いトンネルや地下道路、水路などの所謂長尺地下構造物
又は非長尺の地下タンクなどを構築する場合に好適に実
施される。
Embodiments and Examples of the Invention FIG. 1 shows an embodiment of a method for constructing an underground structure according to the invention described in claim 1. This construction method is suitably carried out when constructing a so-called long underground structure such as a tunnel, an underground road, a waterway, or a non-long underground tank that is long in the direction perpendicular to the plane of FIG.

【0012】この構築工法の実施要領は、先ず図1Aに
示したように、地下構造物Aを構築する地盤1を、同地
下構造物Aへ働く内外力(土圧、地下水圧及び鉛直荷重
など)を負担可能な範囲(水平方向及び深さ方向の範
囲)まで深層混合処理工法により地盤改良する。
As shown in FIG. 1A, the construction method is as follows. First, as shown in FIG. 1A, the ground 1 for constructing the underground structure A is subjected to internal and external forces (earth pressure, groundwater pressure, vertical load, etc.) acting on the underground structure A. ) To the extent that it can bear (range in the horizontal direction and the depth direction) by the deep layer mixing method.

【0013】ここでいう深層混合処理工法は既に公知、
周知の技術なので、具体的に図示して説明することは省
略するが、要するに、プラントで硬化材(安定材)をス
ラリー状に作り、これをスラリーポンプで処理機に圧送
し、上述した改良範囲の軟弱地盤の全面にわたり、処理
機で掘削土と硬化材スラリーとを均一に撹拌混合させ、
軟弱土を所定の強度が得られるように大深度まで地盤改
良を行う工法である。但し、前記の内容に限定されるも
のではない。
The deep layer mixing processing method here is already known,
Since this is a well-known technique, a detailed illustration and description thereof will be omitted, but in short, a hardening material (stabilizer) is made into a slurry in a plant, and this is pumped to a processing machine by a slurry pump, and the above-mentioned improvement range Using a processing machine, stir and mix excavated soil and hardener slurry uniformly over the entire soft ground of
This is a method for improving the soil to a large depth so that the soft soil can have a predetermined strength. However, the content is not limited to the above.

【0014】上記内外力を負担可能な地盤改良の範囲を
言い換えると、力学的に地下構造物として成り立つ範囲
をいう。例えば平面領域は、少なくとも構築予定の地下
構造物Aの外周に、内外力を負担するのに必要な壁厚H
を加えた領域である。深度領域は、少なくとも構築予定
の地下構造物Aの深度に、同地下構造物Aを支持するの
に必要な底厚さDを加えた深度とする。
In other words, the range of ground improvement that can bear the above-mentioned internal and external forces is the range that is mechanically established as an underground structure. For example, the plane area has a wall thickness H required to bear internal and external forces at least on the outer circumference of the underground structure A to be constructed.
It is the area where is added. The depth region is at least the depth of the underground structure A to be built, plus the bottom thickness D required to support the underground structure A.

【0015】前記深層混合処理工法によって地盤改良を
所定範囲まで施工すると、次には、図1Bに示したよう
に、その改良地盤1を、スラブ底盤の深さ位置D、即
ち構築予定の地下構造物Aの天井レベルまでを掘削す
る。つづいて、図1Cに示したように、掘削底部に、ス
ラブコンクリート2を打設して構築する。但し、後に続
く改良地盤1の更なる掘削その他の作業の準備として、
前記スラブコンクリート2に開口部を形成しておくのが
好ましい。
When the ground improvement is carried out to a predetermined range by the deep layer mixing treatment method, next, as shown in FIG. 1B, the improved ground 1 is moved to the depth position D 1 of the slab bottom, that is, the underground to be constructed. Excavate to the ceiling level of structure A. Subsequently, as shown in FIG. 1C, the slab concrete 2 is placed on the bottom of the excavation to build the concrete. However, in preparation for further excavation and other work of the improved ground 1 that follows,
It is preferable to form an opening in the slab concrete 2.

【0016】前記スラブコンクリート2は、それより下
方の改良地盤1の掘削を進める際に切梁に利用するの
で、構築予定の地下構造物Aを平面的に見て十分に覆う
程度の広さで、且つ掘削部の側壁4に作用する土圧、地
下水圧などに対して十分な強度を発揮するように構築す
る。
Since the slab concrete 2 is used as a girder when the excavation of the improved ground 1 below the slab concrete 2 is carried out, the slab concrete 2 should be large enough to cover the underground structure A to be constructed in plan view. In addition, it is constructed so as to exert sufficient strength against earth pressure, groundwater pressure, etc. acting on the side wall 4 of the excavated portion.

【0017】前記スラブコンクリート2が前記強度を発
現した後に、これを切梁に利用して、図1D、Eに示し
たように、下方の改良地盤1を地下構造物Aに相当する
空間分だけ掘削する。そして、図1Fに示したように、
完成した空間の側壁(内壁)3と底壁(床)5にショッ
トクリート(吹付け)等の仕上げ6を行い、更にスラブ
コンクリート2の上方の掘削部8を埋め戻して地下構造
物Aの構築を完了する。
After the slab concrete 2 develops the strength, the slab concrete 2 is utilized as a cutting beam, and as shown in FIGS. 1D and 1E, the improved ground 1 at the lower portion corresponds to the space corresponding to the underground structure A. Excavate. Then, as shown in FIG. 1F,
Finishing 6 such as shotcrete (spraying) on the side wall (inner wall) 3 and bottom wall (floor) 5 of the completed space, and further backfilling the excavated portion 8 above the slab concrete 2 to build an underground structure A. To complete.

【0018】上記したように、本発明に係る地下構造物
の構築工法は、深層混合処理工法により地盤改良した改
良地盤1をそっくり構造主体に利用するので、改めて地
下構造物Aを構築する資材や労力の無駄を省き、コスト
を軽減できるのである。
As described above, in the method for constructing an underground structure according to the present invention, since the improved ground 1 improved by the deep mixing method is used mainly for the structure, the material for constructing the underground structure A is It is possible to save labor and reduce costs.

【0019】図2と図3は、請求項1に記載した発明に
係る地下構造物の構築工法の異なる実施形態を示してい
る。この実施形態は、所謂露天式の地下道路(高速道路
等)や水路等の長尺地下構造物を構築する場合に好適に
実施される。
2 and 3 show different embodiments of the method for constructing an underground structure according to the invention described in claim 1. This embodiment is preferably implemented when constructing a long underground structure such as a so-called open-air underground road (highway or the like) or a waterway.

【0020】この地下構造物の構築工法もやはり、先ず
は深層混合処理工法により、地下構造物Bを構築する地
盤11を、同地下構造物Bへ働く内外力(土圧、地下水
圧及び鉛直荷重など)を負担可能な範囲(水平方向及び
深さ方向の範囲)まで地盤改良する(図3A)。
In this construction method for an underground structure as well, first, by the deep mixing method, the ground 11 for constructing the underground structure B is subjected to internal and external forces (earth pressure, groundwater pressure and vertical load) acting on the underground structure B. Etc.) to the extent that it can bear (horizontal direction and depth direction range) ground improvement (Fig. 3A).

【0021】次に、前記改良地盤11をスラブ底盤の深
さ位置D、即ち構築予定の地下構造物Bの天井レベル
まで掘削し、同掘削底部にスラブコンクリート12を構
築する(図3B)。
Next, the improved ground 11 is excavated to the depth position D X of the slab bottom, that is, the ceiling level of the underground structure B to be constructed, and the slab concrete 12 is constructed at the bottom of the excavation (FIG. 3B).

【0022】本実施形態の特徴は、スラブコンクリート
12を地面レベル(G.L)に構築することである。よ
ってスラブコンクリート12は、地下構造物Bが地下道
路の場合には、その道路上を横断する橋としての役割を
期待することもできる。よって、スラブコンクリート1
2は、地下構造物Bの上面の全面に構築する場合のほ
か、後の切梁としての役割を失わない程度の間隔をあけ
て構築することもできる(図2)。したがって、前記の
間隔部分は、改良地盤を掘削する場合の開口として利用
することができる。
A feature of this embodiment is that the slab concrete 12 is constructed at the ground level (GL). Therefore, when the underground structure B is an underground road, the slab concrete 12 can be expected to function as a bridge that crosses the road. Therefore, slab concrete 1
No. 2 can be constructed not only when it is built on the entire upper surface of the underground structure B, but also at intervals such that it does not lose its role as a post beam (Fig. 2). Therefore, the above-mentioned interval portion can be used as an opening when excavating the improved ground.

【0023】前記スラブコンクリート12が強度を発現
した後に、これを切梁に利用して、図3C、Dに示した
ように、下方の改良地盤11を地下構造物Bに相当する
空間分だけ掘削し、改良地盤11をそのまま側壁13と
底壁15に利用した地下構造物Bを構築する。そして、
図3Eに示したように、完成した空間の側壁13と底壁
15にショットクリート(吹付け)等の仕上げ16を行
って地下構造物Aの構築を完成する。
After the slab concrete 12 develops its strength, it is used as a cross beam to excavate the improved ground 11 below by a space corresponding to the underground structure B, as shown in FIGS. 3C and 3D. Then, the improved ground 11 is used as it is for the side wall 13 and the bottom wall 15 to construct an underground structure B. And
As shown in FIG. 3E, finishing 16 such as shotcrete (spraying) is performed on the side wall 13 and the bottom wall 15 of the completed space to complete the construction of the underground structure A.

【0024】したがって、本発明に係る地下構造物の構
築工法によると、上記図1に基づいて説明した地下構造
物Aの構築工法の作用効果と略同様の作用効果を奏す
る。即ち、深層混合処理工法により地盤改良した改良地
盤11をそっくり構造主体に利用するので、改めて地下
構造物Bを構築する資材や労力の無駄を省き、コストを
軽減できるのである。
Therefore, according to the method for constructing an underground structure according to the present invention, the same operational effect as that of the method for constructing an underground structure A described with reference to FIG. 1 can be obtained. That is, since the improved ground 11 improved by the deep layer mixing method is used mainly for the structure, waste of materials and labor for constructing the underground structure B again can be omitted, and the cost can be reduced.

【0025】図4A〜Dは、請求項2に記載した発明に
係る地下構造物の構築工法の実施形態を示している。こ
れは地下構造物Cが大規模でスラブコンクリートを支持
する支柱が必要な場合に好適な構築工法である。
4A to 4D show an embodiment of a method for constructing an underground structure according to the invention described in claim 2. This is a suitable construction method when the underground structure C has a large scale and a pillar for supporting the slab concrete is required.

【0026】本発明の場合は、深層混合処理工法により
地盤改良した改良地盤21をスラブ底盤の深さ位置まで
掘削する工程に先行して、スラブコンクリート22を支
持するのに適切な部位(図示例では、平面的に見て断面
の略中央位置)にH鋼等の柱心材7を建て込む。しかる
後にスラブコンクリート22を構築し、これを前記柱心
材7によって支持させる。次いで前記スラブコンクリー
ト22の下方の改良地盤21の掘削を進め、掘削した空
間の内壁23、床25などの仕上げ及び柱心材7の仕上
げ等を行うことを特徴とする(請求項2記載の発明)。
In the case of the present invention, prior to the step of excavating the improved ground 21 improved by the deep layer mixing processing method to the depth position of the slab bottom, an area suitable for supporting the slab concrete 22 (illustrated example) Then, the column core material 7 of H steel or the like is built in at a substantially central position of the cross section when viewed in plan. After that, the slab concrete 22 is constructed and supported by the pillar core material 7. Next, the excavation of the improved ground 21 below the slab concrete 22 is advanced to finish the inner wall 23, the floor 25 and the like of the excavated space and the pillar core material 7 (the invention according to claim 2). .

【0027】この地下構造物Cの構築工法は、構築する
スラブコンクリート22の支点間が長く、柱心材7を設
けなくてはならない場合などに好適に実施される。柱心
材7を設けたことにより、スラブコンクリート22の支
持力を確保できるので、下方の改良地盤21を安定して
掘削することができ、地下構造物自体の安定性も得られ
るのである。
This construction method of the underground structure C is preferably carried out when the slab concrete 22 to be constructed has a long fulcrum and the column core material 7 must be provided. Since the supporting force of the slab concrete 22 can be secured by providing the pillar core material 7, the improved ground 21 below can be stably excavated, and the stability of the underground structure itself can also be obtained.

【0028】以上に実施形態を図面に基づいて説明した
が、本発明は、図示例の実施形態の限りではなく、その
技術的思想を逸脱しない範囲において、当業者が通常に
行う設計変更、応用のバリエーションの範囲を含むこと
を念のために言及する。
Although the embodiments have been described above with reference to the drawings, the present invention is not limited to the embodiments shown in the drawings, and the design changes and applications that a person skilled in the art normally makes within the scope not departing from the technical idea thereof. Note that it includes a range of variations of.

【0029】[0029]

【本発明の奏する効果】請求項1、2に記載した発明に
係る地下構造物の構築工法によれば、下記する効果を奏
する。 1)深層混合処理工法により地盤改良した改良地盤をそ
っくり構造主体に利用するので、改めて地下構造物を構
築する資材や労力の無駄を省き、コスト削減に寄与する
ことは勿論、耐震性能に優れた所謂長尺地下構造物の構
築を可能にする。 2)地下構造物を構築する地盤を先行して地盤改良する
ため、液状化対策、軟弱地盤対策が不要である。 3)スラブコンクリートが切梁的な役割を果たすので、
支保工、山留め工を必要とせず、改良地盤の壁厚は自立
山留めとして用いる場合より薄くでき、経済的である。 4)上部工事を行う場合には、スラブコンクリート構築
後に上部工事が可能となり、よって全体工期の短縮を図
ることができる。 5)埋め戻し作業を行う場合には、掘削残土をコンクリ
ートスラブ設置が終了した箇所へ埋め戻すことができ、
残土処理の簡略化を図ることができる。 6)スラブコンクリートを橋などに利用することもでき
る。 7)掘削幅が広く、スラブコンクリート支点間が長い場
合でも柱心材を設けることにより安定して地下構造物の
構築を行い得る。
[Effects of the Present Invention] According to the construction method for an underground structure according to the present invention, the following effects can be obtained. 1) The improved ground, which has been improved by the deep-mixing method, is used for the structure as a whole. Therefore, it is possible to save the waste of materials and labor for constructing the underground structure again, contribute to cost reduction, and of course, it has excellent seismic performance. It enables the construction of so-called long underground structures. 2) Since the ground for constructing an underground structure is improved first, it is not necessary to take measures against liquefaction and soft ground. 3) Since slab concrete plays the role of a cutting beam,
It does not require support work or earth retaining work and the wall thickness of the improved ground can be made thinner than when using it as a self-supporting earth retaining structure, which is economical. 4) When performing superstructure work, superstructure work can be performed after slab concrete construction, thus shortening the overall construction period. 5) When carrying out backfilling work, the excavated soil can be backfilled to the place where the concrete slab installation has been completed.
It is possible to simplify the treatment of residual soil. 6) Slab concrete can also be used for bridges. 7) Even if the excavation width is wide and the slab concrete fulcrums are long, it is possible to stably construct the underground structure by providing the pillar core material.

【図面の簡単な説明】[Brief description of drawings]

【図1】A〜Fは、請求項1に記載した発明に係る地下
構造物の構築工法の実施形態を段階的に示した説明図で
ある。
1A to 1F are explanatory views showing, step by step, an embodiment of a method for constructing an underground structure according to the invention described in claim 1.

【図2】請求項1に記載した発明に係る地下構造物の構
築工法の異なる実施形態を示した斜視図である。
FIG. 2 is a perspective view showing a different embodiment of a method for constructing an underground structure according to the invention described in claim 1.

【図3】A〜Eは、請求項1に記載した発明に係る地下
構造物の構築工法の実施形態を段階的に示した説明図で
ある。
3A to 3E are explanatory views showing an embodiment of a method for constructing an underground structure according to the invention described in claim 1 step by step.

【図4】A〜Dは、請求項2に記載した発明に係る地下
構造物の構築工法を段階的に示した説明図である。
4A to 4D are explanatory views showing stepwise a construction method of an underground structure according to the invention described in claim 2.

【図5】従来技術を示した立面図である。FIG. 5 is an elevational view showing the prior art.

【符号の説明】[Explanation of symbols]

A、B、C 地下構造物 1、11、21 地盤 2、12、22 スラブコンクリート 3、13 地下構造物の側壁 4、14 掘削部の側壁 5、15 地下構造物の底壁 6、16 仕上げ 7 掘削部 8 柱心材 A, B, C underground structure 1, 11, 21 ground 2,12,22 Slab concrete 3, 13 Side wall of underground structure 4,14 Side wall of excavation part 5,15 Bottom wall of underground structure 6, 16 finish 7 excavation section 8 pillar heartwood

───────────────────────────────────────────────────── フロントページの続き (72)発明者 森 信智 東京都中央区銀座八丁目21番1号 株式会 社竹中土木内 Fターム(参考) 2D047 AB04    ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Norito Mori             8-21-21 Ginza, Chuo-ku, Tokyo Stock market             Takenaka engineering works F-term (reference) 2D047 AB04

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】地下構造物を構築する地盤を同地下構造物
へ働く内外力を負担可能な範囲まで深層混合処理工法に
より地盤改良する段階と、 改良地盤をスラブ底盤の深さ位置まで掘削し、スラブコ
ンクリートを構築する段階と、 前記スラブコンクリートが所要の強度を発現した後に、
これを切梁に利用して下方の改良地盤を地下構造物に相
当する空間分だけ掘削を進め、同空間の内壁、床などの
仕上げを行って地下構造物を完成する段階と、から成る
ことを特徴とする地下構造物の構築工法。
1. A step of improving the ground for constructing an underground structure by a deep-mixing method to the extent that the internal and external forces acting on the underground structure can be borne, and excavating the improved ground to the depth of the slab floor. A step of constructing a slab concrete, and after the slab concrete develops a required strength,
Utilizing this as a truss, the improved ground below is excavated for the space equivalent to the underground structure, and the inner wall and floor of the space are finished to complete the underground structure. Construction method for underground structures.
【請求項2】深層混合処理工法により地盤改良した改良
地盤をスラブ底盤の深さ位置まで掘削する工程に先行し
て、スラブコンクリートを支持するのに適切な部位にH
鋼等の柱心材を建て込み、しかる後にスラブコンクリー
トを構築して前記柱心材によって支持させ、次いで前記
スラブコンクリートの下方の改良地盤の掘削を進め、掘
削した空間の内壁、床などの仕上げを行うことを特徴と
する、請求項1に記載した地下構造物の構築工法。
2. Prior to the step of excavating the improved ground, which has been improved by the deep mixing method, to the depth of the slab bottom, H at an appropriate site for supporting the slab concrete.
After constructing pillar core material such as steel, and then constructing slab concrete to be supported by the pillar core material, then proceed with excavation of the improved ground below the slab concrete, and finish the inner wall of the excavated space, floor, etc. The method for constructing an underground structure according to claim 1, wherein:
JP2002120584A 2002-04-23 2002-04-23 Construction method for underground structures Expired - Lifetime JP4031284B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002120584A JP4031284B2 (en) 2002-04-23 2002-04-23 Construction method for underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002120584A JP4031284B2 (en) 2002-04-23 2002-04-23 Construction method for underground structures

Publications (2)

Publication Number Publication Date
JP2003313890A true JP2003313890A (en) 2003-11-06
JP4031284B2 JP4031284B2 (en) 2008-01-09

Family

ID=29536768

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002120584A Expired - Lifetime JP4031284B2 (en) 2002-04-23 2002-04-23 Construction method for underground structures

Country Status (1)

Country Link
JP (1) JP4031284B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018017104A (en) * 2016-07-29 2018-02-01 大成建設株式会社 Composite body of earth structure and concrete structure and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6192220A (en) * 1984-10-09 1986-05-10 Tobishima Kensetsu Kk Method of building underground structure using ground improving agent
JPH0673722A (en) * 1992-07-10 1994-03-15 Takenaka Komuten Co Ltd For open-cutting weak ground by deep soil stabilization by chemical method
JPH10183651A (en) * 1996-12-27 1998-07-14 Ohbayashi Corp Construction method for structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6192220A (en) * 1984-10-09 1986-05-10 Tobishima Kensetsu Kk Method of building underground structure using ground improving agent
JPH0673722A (en) * 1992-07-10 1994-03-15 Takenaka Komuten Co Ltd For open-cutting weak ground by deep soil stabilization by chemical method
JPH10183651A (en) * 1996-12-27 1998-07-14 Ohbayashi Corp Construction method for structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018017104A (en) * 2016-07-29 2018-02-01 大成建設株式会社 Composite body of earth structure and concrete structure and construction method thereof

Also Published As

Publication number Publication date
JP4031284B2 (en) 2008-01-09

Similar Documents

Publication Publication Date Title
CN108868778B (en) Non-excavation construction method for large underground structure
CN102182325B (en) Storey adding method for existing building basement with frame structure and independent foundation
KR100313720B1 (en) Composite Underground Structure Construction Method
US20020071725A1 (en) Earth support and permanent structural foundation wall
JP2007308995A (en) Under path and construction method for the same
CN113235613B (en) Method for excavating and supporting newly-built foundation pit by utilizing adjacent existing guard piles
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JP2001032673A (en) Tunnel work execution method
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
CN105986830B (en) The tunneling method of construction of roadside strip underground garage
CN113202106B (en) Deep foundation pit excavation method
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JP2005002671A (en) Underpinning method and viaduct
JP2001271365A (en) Construction method for underground structure
JP2000291398A (en) Underground structure and construction method therefor
JP2003313890A (en) Construction method of underground structure
JPH0559728A (en) Sheathing work above underground structure
JPH0953237A (en) Pit and constructing method of basement utilizing the pit
JPH0415878B2 (en)
JPH07139300A (en) Method for constructing underground construction
CN117211302B (en) Assembled steel-concrete guide wall and construction method thereof
KR100663108B1 (en) Method for Constructing an Underground Structure Using Up-down Method
CN216193926U (en) Construction site trestle structure
RU2235165C2 (en) Method of old bridge reconstruction

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050331

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070322

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070403

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070601

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071002

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071018

R150 Certificate of patent or registration of utility model

Ref document number: 4031284

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101026

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101026

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111026

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111026

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121026

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121026

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131026

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term