JP2003223536A - Method and program for sorting group operation - Google Patents

Method and program for sorting group operation

Info

Publication number
JP2003223536A
JP2003223536A JP2002282411A JP2002282411A JP2003223536A JP 2003223536 A JP2003223536 A JP 2003223536A JP 2002282411 A JP2002282411 A JP 2002282411A JP 2002282411 A JP2002282411 A JP 2002282411A JP 2003223536 A JP2003223536 A JP 2003223536A
Authority
JP
Japan
Prior art keywords
work
group
construction
time
sorting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2002282411A
Other languages
Japanese (ja)
Other versions
JP4430289B2 (en
Inventor
Ryuichi Hishinuma
隆一 菱沼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ASAHI TSUSHIN KK
Original Assignee
ASAHI TSUSHIN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ASAHI TSUSHIN KK filed Critical ASAHI TSUSHIN KK
Priority to JP2002282411A priority Critical patent/JP4430289B2/en
Publication of JP2003223536A publication Critical patent/JP2003223536A/en
Application granted granted Critical
Publication of JP4430289B2 publication Critical patent/JP4430289B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

<P>PROBLEM TO BE SOLVED: To automatically and efficiently create, using a computer program, an operation journal in making a plurality of operation groups share telephone installation work or the like. <P>SOLUTION: This method includes acquiring operation issue data including at least the operation site and operation starting time zone of each of a plurality of operations to be completed within a specified period (S1); accepting the designation of the plurality of operation groups which should share the plurality of operations (S2); creating a plurality of operation sorting plans for the operation issues to be shared by the operation groups and their order, based on the operating time which each operation group requires to complete the operation issue for which each group is responsible (S3); and displaying the plurality of operation sorting plans created on a display in such a manner that either of the plans can be selected. These processes are implemented by computers. <P>COPYRIGHT: (C)2003,JPO

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は班別作業仕分け方法
および班別作業仕分けプログラムに関し、より詳しく
は、各種電話工事やパソコン・コピー機・ファクシミリ
機等のOA機器の修理等の作業を複数の作業班に分担し
て行わせる際の作業仕分け表をコンピュータを利用して
自動的且つ効率的に作成するための方法およびプログラ
ムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a work sorting method for each group and a work sorting program for each group, and more specifically, it performs a plurality of works such as various telephone works and repair of office automation equipment such as personal computers, copiers, and facsimile machines. The present invention relates to a method and a program for automatically and efficiently creating a work sorting table when a work group shares the work with a computer.

【0002】[0002]

【従来の技術】電話工事を例として説明すると、電話や
営業窓口または法人営業等によって受けた工事依頼を、
電話工事の請負会社に振り分け、各請負会社毎のカスタ
ム端末にオーダー情報としてデータ送信する。各請負会
社は、通常、遅くとも工事日の前々日までにオーダー情
報を受け取る。このようにして、各請負会社のカスタム
端末には、同一の工事日が指定された複数のオーダー情
報が蓄積される。
[Prior Art] Taking telephone construction as an example, a construction request received by telephone, sales counter or corporate sales
It is distributed to the contracting companies for telephone construction, and data is transmitted as order information to the custom terminal of each contracting company. Each contractor usually receives order information at least two days before the construction date. In this way, a plurality of order information in which the same construction date is designated is stored in the custom terminal of each contracting company.

【0003】オーダー情報を受けた各請負会社では、工
事日の前日に、当該工事日が指定された複数のオーダー
情報をカスタム端末からプリンタで紙出力し、すべての
オーダーについて一件毎にその工事に必要な工具や材料
等を確認し、工事予約時間・工事場所(ユーザの住所)
・工事内容等を考慮して、作業仕分け表(班別持出表と
も呼ばれる)を作成する。作業仕分け表は作業班毎に作
成され、工事場所・工事内容・工事開始予定時刻・工事
終了予定時刻等が工事順に記載されている。工事当日、
各作業班は、上記作業仕分け表によって自班に割り当て
られたオーダーを確認しながら、指定順に工事を行う。
Each contracting company that received the order information outputs a plurality of order information on the day before the construction day from a custom terminal to a printer, and outputs the construction information for each order for each order. Check the tools and materials needed for the construction, construction reservation time and construction place (user's address)
-Create a work sorting table (also called a group-specific carry-out table) in consideration of the work content. The work sorting table is created for each work group, and the work place, the work content, the scheduled start time of the work, the scheduled finish time of the work, etc. are described in the order of the work. On the day of construction,
Each work group performs construction in the designated order while confirming the orders assigned to it by the work sorting table.

【0004】[0004]

【発明が解決しようとする課題】従来は上記作業仕分け
表の作成を手作業で行っていたが、熟練者でも長時間を
要するものであった。その一つの要因は、作業班によっ
てスキルレベルが異なり、同じ工事であっても作業班の
スキルレベルないしそれに伴う作業スピードレベルに応
じて工事の所要時間が異なることにあった。
Conventionally, the above-mentioned work sorting table is manually created, but it takes a long time even for a skilled person. One of the reasons is that the skill level differs depending on the work group, and even for the same work, the time required for the work varies depending on the skill level of the work group or the work speed level accompanying it.

【0005】[0005]

【課題を解決するための手段】そこで本発明は、従来技
術における上記問題を解決し、電話工事等を複数の作業
班に分担して行わせる際の作業仕分け表をコンピュータ
システムを利用して自動的且つ効率的に作成することを
目的とする。
SUMMARY OF THE INVENTION Therefore, the present invention solves the above problems in the prior art and automatically uses a computer system for a work sorting table when telephone work and the like are shared among a plurality of work groups. The objective is to create it efficiently and efficiently.

【0006】この目的を達成するため、本発明による班
別作業仕分け方法は、(a)特定の期間内に完了させる
べき複数の作業の各々についてその作業場所および作業
開始時間帯を少なくとも含む作業案件データを取得し、
(b)これら複数の作業を分担すべき複数の作業班の指
定を受け、(c)各作業班の現在地と、作業案件データ
中の各作業案件の作業場所および作業開始時間帯と、各
作業班が各担当作業案件に要する作業時間とから、各作
業班が担当すべき作業案件およびその作業順についての
作業仕分け案を複数通り作成し、(d)作成された複数
通りの作業仕分け案のいずれかを選択可能にディスプレ
イ表示する、各処理をコンピュータに実行させることを
特徴とする(請求項1)。
To achieve this object, the method for sorting work by group according to the present invention is: (a) a work project including at least a work place and a work start time zone for each of a plurality of works to be completed within a specific period. Get the data,
(B) The designation of a plurality of work groups to share these plurality of works, (c) the current location of each work group, the work location and work start time zone of each work case in the work case data, and each work From the work time required for each work group to be in charge of each group, a plurality of work classification plans for each work group to be in charge of each work group and its work order are created, and (d) of the created plural work classification plans. It is characterized in that a computer is caused to execute each processing for displaying any one of them on a display (claim 1).

【0007】本発明の一つの好適な実施形態によれば、
前記(c)の処理において、(c−1)作業開始時間帯
の条件を満たす作業案件のうち、所定の優先順位による
最優先の作業班の出発地から最も近いと判断される作業
場所の作業案件を選択して当該最優先作業班の第1作業
案件とし、作業班の優先順位にしたがって順次同様にし
て既選択の作業案件を除く作業案件のうち各作業班の出
発地から最も近いと判断される作業場所の作業案件を各
作業班の第1作業案件とし、(c−2)このようにして
決定された第1作業案件のうち最も早く作業を終了する
と判断される作業班から、既選択の作業案件を除く作業
案件のうち当該作業班の第1作業案件の作業場所から最
も近いと判断される作業場所の作業案件を選択して当該
作業班の第二作業案件とし、順次同様にして第1作業案
件の作業終了順に各作業班の第二作業案件を選択し、
(c−3)順次同様にして全作業案件を各作業班に振り
分けることによって第1の作業仕分け案を作成し、(c
−4)作業班の優先順位を変えて上記(c−1)および
その後の(c−2)ないし(c−3)の各処理を実行し
て複数通りの作業仕分け案を作成する(請求項2)。
According to one preferred embodiment of the invention,
In the processing of (c), among the work cases that satisfy the condition of (c-1) work start time zone, the work in the work place that is determined to be the closest from the departure place of the work team with the highest priority according to a predetermined priority order. Select a project to be the first work project of the highest priority work group, and in the same manner, according to the priority of the work group, it is judged that it is the closest to the departure point of each work group among the work projects excluding the already selected work project. The work case of the work place to be set is defined as the first work case of each work group, and (c-2) from the work group determined to finish the work earliest among the first work cases determined in this way, Of the work cases other than the selected work case, the work case of the work place that is judged to be closest to the work place of the first work case of the work group is selected and set as the second work case of the work group, and in the same manner. In order of work completion of the first work case Select the second work projects of the working group,
(C-3) In the same manner, the first work classification plan is created by allocating all work cases to each work group in the same manner.
-4) The priority of the work group is changed and the above-mentioned (c-1) and the subsequent processes (c-2) to (c-3) are executed to create a plurality of work sorting plans (claims). 2).

【0008】前記(c)の処理において用いる作業時間
は、各作業班が要した作業時間の実績を作業種別毎に記
録した作業スキルデータベースに基づいて予測すること
ができる(請求項3)。あるいは、作業種別毎の標準作
業時間を数値化した標準作業時間データベースと、作業
班毎の作業スピードレベルを数値化した作業スピードレ
ベルデータベースとを作成し、前記(c)の処理におい
て、各作業班が担当する作業案件の作業種別についての
標準作業時間を標準作業時間データベースから読み出す
とともに、当該作業班の作業スピードレベルを作業スピ
ードレベルデータベースから読み出し、これらを乗じて
各作業班が担当する作業案件に要する作業時間を算出す
るようにしてもよい(請求項4)。
The work time used in the process (c) can be predicted based on a work skill database in which the actual work time required by each work group is recorded for each work type (claim 3). Alternatively, a standard work time database that quantifies the standard work time for each work type and a work speed level database that quantifies the work speed level for each work group are created, and in the processing of (c), each work group is created. The standard work time for the work type of the work item in charge of is read from the standard work time database, the work speed level of the work group is read from the work speed level database, and these are multiplied to obtain the work item that each work group is in charge of. The required work time may be calculated (claim 4).

【0009】本発明の別の好適な実施形態によれば、前
記(d)の処理において、複数通りに作成された作業仕
分け案の各々について、最も遅く全作業案件の作業を終
了する作業班の当該作業終了時刻を予測してディスプレ
イ表示する(請求項5)。
According to another preferred embodiment of the present invention, in the processing of (d), for each of the work sorting plans created in a plurality of ways, the work group that finishes the work of all work projects latest The work end time is predicted and displayed on the display (Claim 5).

【0010】本発明のさらに別の好適な実施形態によれ
ば、現在時刻が作業開始時間帯の中にあり且つその作業
場所が当該作業班の現在地に最も近い作業案件であって
も、現在地から作業場所への移動所要時間を考慮すると
作業開始時刻が作業開始時間帯を越えてしまう場合に、
前記(d)の処理において、その作業案件を当該作業班
が担当する場合には作業開始時間帯の条件を満たさない
ことをディスプレイ表示する(請求項6)。前記(d)
の処理において作業開始時間帯の条件を満たさないもの
として表示された作業案件については、当該作業案件を
他の作業班に移管させた場合の作業開始予定時刻を、各
作業班に組み込まれている各作業案件の場所およびそれ
らの作業終了予定時刻に基づいて算出し、さらに、その
場合の作業終了予定時刻を各作業班が要する作業時間に
基づいて算出して、各作業班に移管可能であるか否かを
ディスプレイ表示することができる(請求項7)。ま
た、当該作業案件を他の作業班に移管させるべきことの
指示を受けて、この作業移管を実行して、作業移管後の
作業仕分け案をディスプレイ表示することができる(請
求項8)。
According to still another preferred embodiment of the present invention, even if the present time is within the work start time zone and the work place is the closest to the present position of the work group, Considering the time required to move to the work place, if the work start time exceeds the work start time zone,
In the process of (d), when the work group is in charge of the work case, it is displayed on the display that the condition of the work start time zone is not satisfied (claim 6). (D)
For the work items displayed as not satisfying the conditions of the work start time zone in the process of 1., the work start scheduled time when the work item is transferred to another work group is incorporated in each work group. It is possible to transfer to each work group by calculating it based on the location of each work case and the scheduled work end time, and further calculating the scheduled work end time in that case based on the work time required by each work group. Whether or not it can be displayed on the display (Claim 7). Further, upon receiving an instruction to transfer the work item to another work group, this work transfer is executed, and the work sorting plan after the work transfer can be displayed on the display (claim 8).

【0011】前記(d)の処理後に選択された作業仕分
け案は、これを班別の作業工程表にしてプリンタ出力可
能とすることが好ましい(請求項9)。
It is preferable that the work sorting plan selected after the process of (d) is made into a work process table for each group and can be output to a printer (claim 9).

【0012】前記(a)における特定の期間とは、たと
えば、一日のうちの特定の時間帯である(請求項1
0)。
The specific period in (a) is, for example, a specific time zone of the day (claim 1).
0).

【0013】本発明は、また、請求項1ないし10のい
ずれか記載の班別作業仕分け方法における各処理をコン
ピュータに実行させるための班別作業仕分けプログラム
を提供するものである。
The present invention also provides a group-based work sorting program for causing a computer to execute each process in the group-based work sorting method according to any one of claims 1 to 10.

【0014】[0014]

【発明の実施の形態】図1は本発明が適用される電話工
事管理システムの概要を示すブロック図であり、各作業
班の車両10には、GPSセンサ12、中央処理装置
(CPU)13、ディスプレイ14、プリンタ15等を
備えたナビゲーションシステム11が搭載されている。
1 is a block diagram showing an outline of a telephone construction management system to which the present invention is applied. A vehicle 10 of each work group has a GPS sensor 12, a central processing unit (CPU) 13, A navigation system 11 including a display 14, a printer 15 and the like is mounted.

【0015】GPSセンサ12は人工衛星から送られる
測位信号をアンテナ16で受信して車両10の絶対位置
を検出する。より正確な車両位置検出のために、所定の
基地局から送信される測位誤差に対する補正信号を受信
して位置補正するD−GPS(ディファレンシャルGP
S)を使用したり、方位センサ(地磁気センサ、ジャイ
ロセンサ、車輪センサ等)、距離センサ、ビーコン受信
装置等を併用してもよい。
The GPS sensor 12 receives the positioning signal sent from the artificial satellite by the antenna 16 and detects the absolute position of the vehicle 10. For more accurate vehicle position detection, a D-GPS (Differential GP) that receives a correction signal for a positioning error transmitted from a predetermined base station and corrects the position.
S) may be used, or an orientation sensor (geomagnetic sensor, gyro sensor, wheel sensor, etc.), distance sensor, beacon receiving device, etc. may be used together.

【0016】CPU13はGPSセンサ12その他の測
位センサからの検出信号を受けて、車両10の現在地を
特定し、この現在地をディスプレイ14のマップ上に表
示するとともに、所定のインターバル(たとえば5分間
隔)でアンテナ17からセンターコンピュータ20に送
信する。
The CPU 13 receives the detection signals from the GPS sensor 12 and other positioning sensors, specifies the current position of the vehicle 10, displays this current position on the map of the display 14, and also at a predetermined interval (for example, every 5 minutes). Is transmitted from the antenna 17 to the center computer 20.

【0017】工事請負会社のセンターコンピュータ20
には、中央処理装置(CPU)21、メモリ22、ディ
スプレイ23、プリンタ24等が備えられている。管理
センター20では、アンテナ25を介して車両10の現
在地データを受信すると、これをCPU21で解析処理
して、ディスプレイ23上に表示する。
Center computer 20 of the construction contractor
A central processing unit (CPU) 21, a memory 22, a display 23, a printer 24 and the like are provided in the computer. When the management center 20 receives the current position data of the vehicle 10 via the antenna 25, the CPU 21 analyzes the current position data and displays it on the display 23.

【0018】また、CPU21とデータ送受信可能に接
続されたメモリ22には、工事種別毎の標準作業時間を
経験的・統計的に定義した標準作業時間データベース2
21と、作業班毎の作業スピードレベルを経験的・統計
的に定義した作業スピードレベルデータベース222
と、当該工事請負会社が管轄する地区およびその周辺地
区の道路地図をディスプレイ23上に表示するための道
路地図データベース223とが格納されている。
In the memory 22 connected to the CPU 21 so that data can be transmitted and received, the standard work time database 2 in which the standard work time for each construction type is empirically and statistically defined
21 and a work speed level database 222 that empirically and statistically defines the work speed level of each work group.
And a road map database 223 for displaying a road map of the area under its control and the surrounding area on the display 23.

【0019】図2は標準作業時間データベース221の
一例を示すデータテーブルであり、一般電話回線におけ
る作業種別を特定するコード番号と、各コード番号によ
って特定される作業種別とに対応して、その作業種別の
標準工程時間が数値化して示されている。このデータテ
ーブルによれば、「内入」作業の標準工程時間を「1」
として、たとえば「内出」作業の標準工程時間は「3」
とされているから「内入」作業の3倍の時間を要し、
「公衆変更」作業の標準工程時間は「5」とされている
から「内入」作業の5倍の時間を要する。不要化した作
業種別の削除、新たな作業種別の加入、既存の作業種別
の標準工程時間の変更等があったときは、それに応じて
データベース221の更新が行われ、図2に示すデータ
テーブル中の「更新日時」の欄に表示される(図2では
表示省略)。なお、標準工程時間の単位は任意に設定で
きるが、図2のデータテーブルでは標準工程時間「1」
の作業を後述の作業レベル「1」の作業班が工事する場
合には80分を要するものとして定義されている。
FIG. 2 is a data table showing an example of the standard work time database 221. The work corresponding to the code number for specifying the work type in the general telephone line and the work type specified by each code number are shown. The standard process time of each type is shown numerically. According to this data table, the standard process time for "inside entry" work is "1".
As an example, the standard process time for "in-house" work is "3"
Because it is said that it takes three times as long as the time of “incoming” work,
Since the standard process time of the "public change" work is "5", it takes five times as long as the "internal entry" work. When the unnecessary work type is deleted, a new work type is added, or the standard process time of an existing work type is changed, the database 221 is updated accordingly, and the data table shown in FIG. It is displayed in the column of "update date and time" (display is omitted in FIG. 2). The unit of the standard process time can be set arbitrarily, but in the data table of FIG. 2, the standard process time is “1”.
It is defined that 80 minutes are required when the work group of the work level “1” described later constructs the work of (1).

【0020】図2のデータテーブルに表示された各作業
種別の具体的な工事内容を概説すると次の通りである。
The concrete construction contents of each work type displayed in the data table of FIG. 2 are outlined below.

【0021】「内入」=加入者電話回線の電話番号の変
更を伴わない移転における新設置場所の工事 「内出」=加入者電話回線の電話番号の変更を伴わない
移転における旧設置場所の工事 「外入」=加入者電話回線の電話番号の変更を伴う移転
における新設置場所の工事 「外出」=加入者電話回線の電話番号の変更を伴う移転
における旧設置場所の工事 「復活」=加入者電話回線の権利を休止させていたもの
を復活させる工事 「休止」=加入者電話回線を止めて権利を留保させる工
事 「付」=加入者電話回線を再び利用できるようにする工
事 「去」=加入者電話回線の配線等を撤去する工事 「転込」=加入者電話回線を転用(アナログからデジタ
ルへの回線変更等)する工事 「加除」=加入者電話回線を除去する工事 「端設」=端末機器を設置する工事 「端廃」=端末機器を取り外す工事 「端変」=端末機器を交換する工事 「ビジ設」=ビジネスホンを設置する工事 「ビジ廃」=ビジネスホンを廃止する工事 「ビジ変」=ビジネスホンを交換する工事 「N設」=キャッチホン等のサービスを新設する工事 「A設」=電話番号移転通知サービスを新設する工事 「臨込」=臨時電話回線を設置する工事 「臨廃」=臨時電話回線を廃止する工事 「滅損」=事故で不通となった加入者電話回線の配線等
を取り外す工事 「復旧」=事故で不通となった加入者電話回線を利用で
きるようにする工事 「引込移」=屋外の電話引込線を移転する工事 「新込」=新規加入者電話回線を新設する工事 「優設」=優先回線(公衆電話用回線)を利用できるよ
うにする工事 「公衆変更」=公衆電話機の移転または電話機種変更設
置工事 「専用」=専用回線を新設する工事
"Domestic entry" = construction of new installation site for relocation without changing telephone number of subscriber telephone line "In-house" = construction of old installation site for relocation without changing telephone number of subscriber telephone line Construction "Outside" = Construction of a new installation site for relocation with a change in the telephone number of the subscriber's telephone line "Outside" = Construction of old installation site for relocation with a change in the telephone number of the subscriber's telephone line "Resurrection" = Construction to restore the subscriber's telephone line rights that have been suspended "Pause" = Construction to suspend the subscriber telephone line and retain the rights "Attach" = Construction to make the subscriber telephone line available again ”= Construction to remove the wiring of the subscriber's telephone line“ Transfer ”= Construction to convert the subscriber's telephone line (change from analog to digital, etc.)“ Addition ”= Construction to remove the subscriber's telephone line Setting "= Setting terminal equipment Work to be done "End of life" = Work to remove the terminal device "End of life" = Work to replace the terminal device "Visible" = Work to install a business phone "Business abandoned" = Work to abolish the business phone "Business strange" = Business phone Construction to be replaced "N" = Construction to newly establish a service such as call waiting "A" = Construction to newly establish a telephone number transfer notification service "Extra" = Construction to install a temporary telephone line "Extinction" = Temporary telephone line "Disintegration" = work to remove the wiring of the subscriber's telephone line that was interrupted due to the accident "Recovery" = construction to allow the use of the subscriber's telephone line that was interrupted due to the accident "Relocation" = Construction for relocating the telephone service line outside the building "New integration" = Construction for newly establishing a new subscriber telephone line "Excellent" = Construction for enabling the use of priority lines (public telephone lines) "Public change" = Public telephone Move to Construction of new phone models change installation work "only" = leased line

【0022】図3は作業スピードレベルデータベース2
22の一例を示すデータテーブルであり、作業班を特定
するコード番号と、各コード番号によって特定される作
業班(この実施形態では一人が一つの作業班を構成する
ので作業班イコール作業者である)の名前とに対応し
て、その作業班の作業レベルが数値化して示されてい
る。このデータテーブルによれば、たとえばコード01
の作業班の作業スピードレベルは「1.1」であるか
ら、図2の標準作業時間データベースに示す各作業の標
準工程時間を乗じて、「内入」作業には「1.1」の作
業時間(=88分)を要し、「内出」作業には「3.
3」の作業時間(=264分)を要し、「公衆変更」作
業には「5.5」の作業時間(=440分)を要するこ
とが分かる。同様にして、コード02の作業班の作業ス
ピードレベルは「0.6」であるから、図2の標準作業
時間データベースに示す各作業の標準工程時間を乗じ
て、「内入」作業は「0.6」の作業時間(=48分)
で済み、「内出」作業は「1.8」の作業時間(=14
4分)で済み、「公衆変更」作業は「3」の作業時間
(=240分)で済むことが分かる。すなわち、この図
3に示す作業スピードレベルデータテーブルにおける
「作業レベル」の数値が小さければ小さいほど熟練作業
者であって作業スピードが速いことを意味している。
FIG. 3 shows a work speed level database 2
22 is a data table showing an example of a work group 22 and a code number for identifying a work group, and a work group specified by each code number (in this embodiment, one work group constitutes one work group, and thus is a work group equal worker). ), The work level of the work group is quantified and shown. According to this data table, for example, code 01
Since the work speed level of the work group of “1.1” is “1.1”, the standard process time of each work shown in the standard work time database of FIG. It takes time (= 88 minutes) and "3.
It can be seen that the work time of "3" (= 264 minutes) is required, and the work of "public change" requires the work time of "5.5" (= 440 minutes). Similarly, since the work speed level of the work group of code 02 is "0.6", the standard process time of each work shown in the standard work time database of FIG. Working time of 6 "(= 48 minutes)
The work time of “1.8” is for “in-house” work (= 14
It can be seen that it takes only 4 minutes) and the work of "public change" can be done in the work time of "3" (= 240 minutes). That is, the smaller the value of the "work level" in the work speed level data table shown in FIG. 3, the faster the worker is and the faster the work speed is.

【0023】図3の作業スピードレベルデータテーブル
には、併せて、一般電話回線以外の特殊回線の工事が可
能である(「1」)か不可能である(「0」)かが各作
業班毎に示されている。このデータテーブルによれば、
コード01の作業班は一般電話回線工事のほか、「P
C」(ISDN64電話回線工事にて所定の端末機器を
購入したユーザを対象にパソコン等のインターネットお
よびメールの設定を行う工事)、「公衆」(公衆電話の
設置工事)および「専用」(専用回線の設置・廃止工
事)の各作業を行うことができるが、「ビジネスホン」
(ビジネスユーザ向け多機能電話機の設置工事)および
「ホームテレホン」(一般ユーザ向け多機能電話機の設
置工事)の各作業を担当することはできない。コード0
2の作業班はすべての作業を行う能力がある。
In the work speed level data table shown in FIG. 3, it is also possible for each work group whether construction of special lines other than general telephone lines is possible ("1") or impossible ("0"). It is shown for each. According to this data table
In addition to general telephone line construction, the code 01 work group
"C" (work to set up Internet and mail for personal computers etc. for users who have purchased the specified terminal equipment in ISDN64 telephone line construction), "public" (public telephone installation work) and "dedicated" (dedicated line) Can be carried out (installation / abolition work)
It is not possible to take charge of each work (installation work of multi-function phone for business users) and "home telephone" (installation work of multi-function phone for general users). Code 0
The second work group is capable of doing all the work.

【0024】図3の作業スピードレベルデータテーブル
に格納されたデータに変更があったときや、作業班の追
加・削除等があったときは、それに応じてデータベース
222の更新が行われ、図3のデータテーブル中の「更
新日時」の欄に表示される(図3では表示省略)。
When the data stored in the work speed level data table of FIG. 3 is changed, or when a work group is added or deleted, the database 222 is updated accordingly, and FIG. It is displayed in the column of “update date and time” in the data table of (not shown in FIG. 3).

【0025】さらにCPU21は、工事発注元から当該
工事請負会社に受注した工事の工事種別、工事場所、工
事日、ユーザ指定の工事時間帯(この実施形態では、午
前9時〜12時、午後1時〜3時、午後1時〜5時の3
通りの時間帯に工事が開始されるべきことをユーザ指定
可能としている)等を含むオーダー情報を工事発注元か
ら直接受信し、またはこれを受信した端末からのデータ
送信あるいは手入力によって取り込み、工事日および一
定の工事エリア毎にリストにしてオーダーファイルを作
成して、メモリ22のオーダーファイル格納部224に
格納する。
Further, the CPU 21 has the construction type of the construction ordered from the construction contractor to the construction contractor, the construction place, the construction date, and the construction time zone designated by the user (in this embodiment, 9:00 am to 12:00 am, 1 pm). 3am from 1pm to 3pm, 1pm to 5pm
The user can specify that the construction should be started in the specified time zone), etc., and directly receive the order information from the construction ordering source, or the data received from the terminal that received this or the manual input, and the construction An order file is created as a list for each day and a certain construction area, and stored in the order file storage unit 224 of the memory 22.

【0026】図4は特定の工事日に特定の工事エリア
(ここでは神奈川県横須賀地区)で行うべき工事のオー
ダーファイルをオーダーファイル格納部224から読み
出してディスプレイ表示したものであり、受注工事を特
定するオーダー番号、工事場所の電話番号(局番以下省
略して表示)、工事種別、工事に要すると思われる標準
的な工事時間(図2の標準作業時間データベースに示す
各作業の標準工程時間に対応している)、ユーザにより
指定された工事時間帯、ユーザによる班指定の有無、工
事対象の電話回線が一般回線であるか特殊回線のいずれ
かであるかを示すスキル要素、工事対象電話回線の契約
者名(表示省略)およびその設置場所(町以下の表示省
略)等が一覧表示形式で表示されている。この例では、
いずれの工事についても班指定がなく、またすべての工
事が一般回線を対象とするもの(スキル要素なし)とし
て示されているが、これらを必要に応じて変更する場合
はこのディスプレイ画面において入力する。
FIG. 4 shows an order file for a construction to be performed in a specific construction area (here, Yokosuka district, Kanagawa prefecture) on a specific construction day, which is read from the order file storage section 224 and displayed on the display. Order number, telephone number of the construction site (displayed as abbreviated below the station number), type of construction, standard construction time considered to be required for construction (corresponding to the standard process time of each work shown in the standard work time database in Fig. 2) , The construction time zone specified by the user, whether or not the group is specified by the user, the skill element indicating whether the telephone line targeted for construction is a general line or a special line, the telephone line targeted for construction The name of the contractor (not shown) and its location (not shown below the town) are displayed in list format. In this example,
There is no group designation for any construction, and all construction is shown as for general lines (no skill element), but if you change these as necessary, enter on this display screen. .

【0027】CPU21は、請け負った工事を複数の作
業班に分担して行わせる際の作業仕分け表を作成する。
作業仕分け表の作成作業は、オーダーファイルにリスト
表示された特定の工事日に特定の工事エリアで行うべき
工事を、標準作業時間データベース221および作業ス
ピードレベルデータベース222を参照して、当該工事
日に稼働可能な複数の作業班に振り分けるものであっ
て、当該工事日に請け負った全工事をその日のうちに
(好ましくは遅くとも午後5時半位までに)完了させる
こと、および、各工事についてユーザ指定の工事時間帯
の中で作業開始することの条件を満足させることを原則
とする。
The CPU 21 creates a work sorting table when the contracted work is shared among a plurality of work groups.
For the work of creating the work sorting table, the work to be performed in the particular work area on the particular work day listed in the order file is referred to by referring to the standard work time database 221 and the work speed level database 222. Allocate to multiple work groups that can operate, and complete all the construction contracted on the construction day within that day (preferably by 5:30 pm at the latest), and user-designated for each construction As a general rule, the conditions for starting work within the construction time zone of

【0028】以下、図4のオーダーファイルリストに示
される全23件の工事案件を特定の日に横須賀地区で行
うべき場合に、参照すべき標準作業時間データベース2
21および作業スピードレベルデータベース222がそ
れぞれ図2および図3に示されるようなデータテーブル
として作成されているものとして、図5のフローチャー
トを参照して、作業仕分け表作成処理の詳細を説明す
る。通常の場合、この作業は工事日の前日に行う。
In the following, the standard work time database 2 to be referred to when all 23 construction projects shown in the order file list of FIG. 4 should be carried out in the Yokosuka area on a specific day.
21 and the work speed level database 222 are created as data tables as shown in FIGS. 2 and 3, respectively, the details of the work sorting table creation process will be described with reference to the flowchart of FIG. Normally, this work is done the day before the construction day.

【0029】まず、工事日当日のオーダーファイルリス
トをコンピュータ20のディスプレイ23に表示させる
ことによって当日のオーダーデータを取得する(S
1)。前述のように、当日オーダーファイルリストが表
示されたディスプレイ画面(図4)において班指定やス
キル要素等の作業条件を変更することができ、また、当
日行うべき工事案件に追加があった場合には当該工事案
件を追加することができる。
First, the order file list for the construction day is displayed on the display 23 of the computer 20 to obtain the order data for the day (S).
1). As mentioned above, work conditions such as group designation and skill elements can be changed on the display screen (Fig. 4) displaying the order file list on the day, and when there is an addition to the construction project to be done on the day. Can add the construction project.

【0030】次に、該オーダーファイルリストのディス
プレイ画面において所要のキー操作を行う(たとえば同
画面に現れる図示しない「次へ」キーのクリック)と、
ディスプレイ表示が、当該工事請負会社に所属する全作
業班の一覧表示(図6)に切り替わり、このディスプレ
イ画面において当日の工事を分担すべき作業班を指定す
る(S2)。説明を簡略化するため、ここではコード番
号34,37および45の3つの作業班が当日横須賀地
区で稼動可能であるものとし、これら3つの作業班の
「配車」欄にチェック「レ」を入れた後、「次へ」キー
(図示せず)をクリックする。
Next, when a required key operation is performed on the display screen of the order file list (for example, clicking a "next" key (not shown) appearing on the screen),
The display is switched to the list display of all work groups belonging to the construction contractor (FIG. 6), and the work groups to which the work of the day is to be assigned are designated on this display screen (S2). In order to simplify the explanation, it is assumed here that three work groups with code numbers 34, 37, and 45 can operate in the Yokosuka area on the day, and a check mark "Re" is entered in the "Vehicle allocation" column of these three work groups. After that, click the “Next” key (not shown).

【0031】S1およびS2によって作業仕分け処理の
対象となる工事案件およびそれら工事案件を担当する作
業班が確定するので、これを受けたCPU21は、仕分
け表作成プログラム225を起動させて、複数通りの作
業仕分け表を作成する(S3)。仕分け表作成プログラ
ム225は、図2の標準作業時間データテーブルおよび
図3の作業スピードレベルデータテーブルを参照して、
S1で取得した全23件の工事案件をS2で指定された
3つの作業班に振り分ける処理を実行するものである
が、その際の具体的処理工程を図14および図15のフ
ローチャートを参照して以下説明する。
By S1 and S2, the construction items to be subjected to the work sorting process and the work teams in charge of those construction items are determined. Therefore, the CPU 21 having received this, activates the sorting table creation program 225 to execute a plurality of types. A work sorting table is created (S3). The sorting table creation program 225 refers to the standard work time data table of FIG. 2 and the work speed level data table of FIG.
The process of allocating all the 23 construction projects acquired in S1 to the three work groups specified in S2 is executed, and the specific processing steps at that time will be described with reference to the flowcharts of FIGS. 14 and 15. This will be described below.

【0032】まず、各作業班について当日最初に担当す
べき工事案件(午前第1案件)を選択する処理工程が図
14のフローチャートに示されており、図4のオーダー
ファイルの全23件の工事案件のうち午前中の工事時間
帯が指定されているものを抽出し(S11)、それら工
事案件の中で、S2で指定された作業班のうちで所定の
優先順位が第1位である作業班を処理対象に設定し(S
12)、その出発地(車庫または営業所)から最も近い
場所にある工事案件を抽出する(S13)。優先順位を
決定する基準は任意であるが、ここではコード番号順と
しているので、S12では午前中の指定工事案件のうち
コード番号が最も小さい34班を選択して、その出発地
に最も近い工事案件をS13で抽出する。
First, the processing steps for selecting the construction project (first project in the morning) to be in charge of the day for each work group are shown in the flowchart of FIG. 14, and all 23 constructions of the order file of FIG. 4 are constructed. The work for which the construction time zone in the morning is designated is extracted (S11), and the work with the predetermined priority is the first among the work groups designated in S2 among the construction works. Set the group as the processing target (S
12), the construction project located closest to the departure place (garage or sales office) is extracted (S13). Although the criteria for determining the priority is arbitrary, the order is the code number here, so in S12, the 34 teams with the smallest code number are selected from the designated construction projects in the morning, and the construction closest to the departure site is selected. The case is extracted in S13.

【0033】なお、S13における「最も近い」工事場
所の抽出に際しては所定の判断基準を採用するものと
し、たとえば、オーダーファイル中の契約者住所(すな
わち工事場所)を参照して、出発地から直線距離で最短
の数ヶ所の工事場所を選択し、これら数ヶ所の工事場所
について、メモリ22の道路地図データベース223か
ら読み出した横須賀地区の道路地図を参照して34班の
車庫からの実際の移動距離を算定して、該移動距離が最
短である工事案件を「最も近い」工事案件とみなすこと
ができる。VICS(道路交通情報通信システム)から
の渋滞情報を参照して、移動所要時間が最短である工事
案件を「最も近い」工事案件とみなしてもよい。あるい
は、作業班によっては工事エリア内の特定の局エリア
(同一電話局番のエリア)や特定の大規模ビルでの作業
を得意にするような場合もあるので、そのような作業班
については、担当する工事案件を特定の局エリアや特定
の大規模ビル等に限定し、その中から「最も近い」工事
場所を抽出するようにしてもよいし、午前第1案件につ
いては当該特定局エリアやビル等の中から抽出し、以降
の案件については局エリア等にこだわらずに最短移動距
離や最短移動時間の工事場所のものを抽出するようにし
てもよい。
It should be noted that when extracting the "closest" construction site in S13, a predetermined judgment criterion is adopted, and for example, referring to the contractor address (that is, the construction site) in the order file, a straight line from the departure place is used. Select the shortest several construction sites in terms of distance, and refer to the Yokosuka district road map read from the road map database 223 of the memory 22 for these several construction sites, and the actual movement distance from the garage of 34 teams. And the construction project with the shortest moving distance can be regarded as the “closest” construction project. By referring to the traffic congestion information from VICS (Road Traffic Information and Communication System), the construction case with the shortest required travel time may be regarded as the “closest” construction case. Alternatively, some working groups may be good at working in a specific office area (area with the same telephone number) or a large building in the construction area. The construction projects to be carried out may be limited to a specific station area or a specific large-scale building, and the “closest” construction site may be extracted from them. For the first project in the morning, the specific station area or building concerned may be extracted. It is also possible to extract from the above, and for the subsequent projects, regardless of the station area or the like, those of the construction site having the shortest movement distance or the shortest movement time may be extracted.

【0034】また、車庫(または工事場所)から(次
の)工事場所への移動に要する時間は、移動距離と任意
に定める車速(たとえば毎時10km)との関係から算
出することができる。道路が渋滞している場合は通常よ
りも多くの移動時間を要することになるが、特定のエリ
アにおいては曜日や時間帯との関係で渋滞の有無や程度
を予測することが一般に可能であるので、これらの関係
から統計的に作成した日時別の平均車速や平均移動時間
のデータベースを参照することによって、移動所要時間
を高精度に予測することが可能となる。
The time required to move from the garage (or construction site) to the (next) construction site can be calculated from the relationship between the travel distance and an arbitrarily determined vehicle speed (for example, 10 km / h). If the road is congested, it will take more travel time than usual, but it is generally possible to predict the presence or extent of congestion in a specific area in relation to the day of the week and the time of day. By referring to the database of average vehicle speed and average travel time by date and time statistically created from these relationships, it becomes possible to predict the required travel time with high accuracy.

【0035】次に、S13で抽出した工事案件のオーダ
ーファイルを参照して、班指定およびスキル要素の条件
を満たしているか否かを確認する(S14)。満たして
いない場合(S14:No)はS18で工事案件の再抽
出を行うが、図4のオーダーファイルでは全工事案件に
ついて班指定がなく、スキル要素の指定もない(S1
4:Yes)ことから、この工事案件を34班の午前第
1案件として選択するとともに、その作業終了時刻を予
測する(S15)。たとえば、34班の出発地から最も
近いものとしてNo.17の工事案件が34班の午前第
1案件として選択されたと仮定すると、この工事案件の
工事種別は「内入」であって(図4参照)その標準作業
時間は「1」であり(図2参照)、34班の作業スピー
ドレベルは「0.5」である(図3参照)から、この工
事には「1」×「0.5」=「0.5」=40分を要す
るものと予測できる。したがって、34班が9時からこ
の工事案件の作業を開始すると、その作業終了予定時刻
は9時40分となる(図7参照)。
Next, referring to the order file of the construction project extracted in S13, it is confirmed whether or not the conditions of group designation and skill element are satisfied (S14). If not satisfied (S14: No), the construction project is re-extracted in S18, but in the order file of FIG. 4, no group is designated for all construction projects and no skill element is designated (S1).
4: Yes), the construction project is selected as the first project in the morning of the 34th group, and the work end time is predicted (S15). For example, No. 34 is the closest to the departure point of the 34th team. Assuming that the 17 construction projects were selected as the 1st project in the morning of the 34th group, the construction type of this construction project is "inside" (see Fig. 4), and the standard work time is "1" (Fig. 2), the working speed level of 34 teams is "0.5" (see Fig. 3), so this construction requires "1" x "0.5" = "0.5" = 40 minutes. Can be predicted. Therefore, when the 34th group starts work on this construction project from 9:00, the scheduled work end time is 9:40 (see FIG. 7).

【0036】次に、S16で全作業班について午前第1
案件を選択したか否かを判定する。ここでは34班につ
いて午前第1案件を選択しただけである(S16:N
o)ので、次の処理対象すなわち次にコード番号が小さ
い37班に処理対象を移して(S17)、同様にS14
およびS15の処理を行い、37班の午前第1案件を選
択してその作業終了時刻を予測する。次いで、45班を
対象として同様に処理を行って45班の午前第1案件を
選択してその作業終了時刻を予測する。37班および4
5班についての午前第1案件は、既に選択された工事案
件を除く工事案件の中から選択されることは言うまでも
なく、さらにこれら作業班について工事種別・スキル要
素や工事場所(局エリアや大規模ビル等)等の条件指定
がある場合にはそれらも勘案した上で、その時点で選択
可能な工事案件の中から午前第1案件を選択する。本事
例では、37班の午前第1案件としてNo.21の工事
案件(その作業終了予定時刻は9時24分)が選択さ
れ、45班の午前第1案件としてNo.19の工事案件
(その作業終了予定時刻は10時28分)が選択されて
いる(図8および図9参照)。なお、各作業班がそれぞ
れ午前第1案件の工事場所に9時に到着するよう、前述
の移動所要時間に基づいて各作業班の車庫出発時刻が定
められる。
Next, in S16, the first morning of all work groups
Determine whether the item is selected. Here, only the first case in the morning is selected for 34 teams (S16: N).
o), the processing target is moved to the next processing target, that is, the 37th group having the next smallest code number (S17), and similarly S14.
Then, the processing of S15 is performed, and the first case in the morning of group 37 is selected and the work end time is predicted. Next, the same processing is performed for the 45th team, the morning first case of the 45th team is selected, and the work end time is predicted. 37 teams and 4
Needless to say, the first project in the morning for Group 5 is selected from the construction projects excluding the already selected construction projects. Furthermore, regarding these work groups, the construction type / skill elements and construction location (bureau area and large scale If conditions such as buildings are specified, the first project in the morning is selected from the construction projects that can be selected at that time after considering them. In this example, No. 1 was selected as the first morning project of 37th group. No. 21 construction project (scheduled work end time is 9:24) was selected and No. 1 was selected as the first project in the morning of 45 teams. Nineteen construction projects (scheduled work end time is 10:28) are selected (see FIGS. 8 and 9). In addition, the garage departure time of each work group is determined based on the above-mentioned required travel time so that each work group arrives at the construction site of the first project at 9:00.

【0037】このようにして全ての作業班について午前
第1案件を選択する(S16:Yes)。
In this way, the first case in the morning is selected for all the work groups (S16: Yes).

【0038】各作業班がその後に担当すべき工事案件
(午前第2案件以降)を選択する処理工程が図15のフ
ローチャートに示されており、午前第2案件の選択処理
について説明すると、S16で選択された各作業班の午
前第1案件の作業終了予定時刻が最先である作業班を抽
出して(S19)、その現在地すなわち午前第1案件の
工事場所から最も近い場所にある工事案件を抽出する
(S20)。本事例では37班が最も早く午前第1案件
の作業を終了する(午前9時24分,図8参照)から、
S19では37班が処理対象に設定される。S20にお
ける「最も近い」工事案件の抽出はS13に関して既述
したと同様にして判断することができる。
The process steps for each work group to select the construction project (the second project after the morning) to be in charge thereafter are shown in the flowchart of FIG. 15, and the selection process for the second project in the morning will be described. The work group having the earliest scheduled work end time of the selected first work group in the first work group is extracted (S19), and the construction project located closest to the current location, that is, the construction site of the first work in the morning is extracted. Extract (S20). In this example, the 37th group finishes the work of the first item in the morning (9:24 am, see Fig. 8),
In S19, 37 teams are set as the processing target. The extraction of the “closest” construction project in S20 can be determined in the same manner as described above with respect to S13.

【0039】次いで、S20で抽出した工事案件を当該
作業班が行うべき午前第2案件として選択してよいか否
かをS21で判定し、不可であればS26で次に近い工
事案件を抽出してS21の判定処理を繰り返す。S21
についてはS14に関して既述したと同様であり、S2
6についてはS18に関して既述したと同様であるの
で、説明を省略する。
Then, it is determined in S21 whether or not the construction project extracted in S20 may be selected as the second morning project to be carried out by the work group. If not, the next closest construction project is extracted in S26. Then, the determination process of S21 is repeated. S21
Is similar to that already described for S14, and S2
Since item 6 is the same as that already described for step S18, the description thereof is omitted.

【0040】S21で抽出した工事案件が班指定および
スキル要素の条件を満たしていることが確認された場合
(S21:Yes)、当該工事案件について指定された
工事時間帯に当該作業班が間に合うか否かを、その直前
の工事案件の作業終了予定時刻およびそこから次の工事
案件(S20またはS26で抽出した工事案件)の工事
場所までの移動時間に基づいて判定し(S22)、この
工事案件を当該作業班(37班)の午前第2案件として
選択してその作業終了時刻を予測する(S23)。
When it is confirmed that the construction project extracted in S21 satisfies the conditions of group designation and skill element (S21: Yes), whether the work group is in time for the construction time zone designated for the construction project. Whether or not it is determined based on the scheduled work completion time of the immediately preceding construction project and the moving time from there to the construction site of the next construction project (construction project extracted in S20 or S26) (S22). Is selected as the second morning project of the work group (37 group) and the work end time is predicted (S23).

【0041】なお、S22における判定結果は工事案件
の選択処理(作業仕分け表作成処理)自体には影響を与
えないが、後述するように班毎の作業工程をディスプレ
イ表示する際に指定工事時間帯に間に合う工事案件(●
印)と間に合わない工事案件(○印)とを区別して表示
するために必要である。作業仕分け表作成処理において
指定工事時間帯に間に合わない工事事件を排除しない理
由は、これを排除してしまうと、図5のS1で取得した
すべての工事案件をその日のうちに完了できなくなって
しまう恐れがあるためである。このため、指定工事時間
帯に間に合うか否かを問わずにその日のうちに行わなけ
ればならない全工事案件をひとまず各作業班に振り分け
ておき、その後、指定工事時間帯に間に合わないと判定
された工事案件について、後述するような作業移管や作
業班追加等の補完処理によって指定工事時間帯に間に合
うように調整している。
Although the determination result in S22 does not affect the construction process selection process (work sorting table creation process) itself, as will be described later, when the work process of each group is displayed on the display, the designated construction time period is displayed. Construction projects in time for (●
It is necessary to distinguish and display the construction project (marked with ○) and the construction project that is not in time. The reason for not excluding construction cases that are not in time for the designated construction time zone in the work sorting table creation process is that if this is excluded, all construction projects acquired in S1 of FIG. 5 cannot be completed within that day. This is because there is a fear. Therefore, regardless of whether it is in time for the designated construction time, all the construction projects that must be done on that day are assigned to each work group for the time being, and then it was determined that it was not in time for the designated construction time With respect to construction projects, adjustments are made in time for the designated construction time by supplementary processing such as transfer of work and addition of work groups as described below.

【0042】以上のようにして作業終了時刻順にその作
業班について次に担当すべき工事案件を選択し、午前中
の工事時間帯が指定された工事案件をすべて選択した
(いずれかの作業班に割り振った)とき(S24:Ye
s)に処理を終了する。
As described above, the construction project to be in charge of the work group is selected next in order of the work end time, and all the construction projects for which the construction time zone in the morning is designated are selected (to any of the work groups). Allocation) (S24: Ye
The process ends in s).

【0043】本事例ではまず37班の午前第2案件とし
てNo.10の工事案件が選択されてその作業終了時刻
が10時01分と予測され、次に34班の午前第2案件
としてNo.13の工事案件が選択されてその作業終了
時刻が10時36分と予測され、最後に45班の午前第
2案件としてNo.07の工事案件が選択されてその作
業終了時刻が12時14分と予測されている(図7〜図
9参照)。
In this example, No. 1 was selected as the second morning project of 37 teams. Construction work No. 10 was selected, and the work end time was predicted to be 10:01. The construction project of No. 13 is selected, and the work end time is predicted to be 10:36, and finally No. 13 as the second project in the morning of 45 teams. The construction project No. 07 is selected and the work end time is predicted to be 12:14 (see FIGS. 7 to 9).

【0044】午前第3案件以降の選択処理もS20〜S
28と同様に行われるものであって、本事例では午前第
2案件の作業終了予定は37班、34班、45班の順な
のでこの順にS22およびS23の条件判定を行い、3
7班の午前第3案件としてNo.09の工事案件が選択
されてその作業終了時刻が11時35分と予測され、3
4班の午前第3案件としてNo.04の工事案件が選択
されるてその作業終了時刻が12時01分と予測され、
最後に37班の午前第4案件としてNo.05の工事案
件が選択されてその作業終了時刻が13時22分と予測
される。なお、45班の午前第2案件の作業終了予定時
刻(12時14分)よりも37班の午前第3案件の作業
終了予定時刻(11時35分)の方が早いので、No.
04の工事案件選択後のS25では37班が抽出され
る。また、45班の午前第2案件の作業終了予定時刻は
既に12時を過ぎており、午前指定の工事案件に間に合
わないことが明らかであるので、午前第3案件の選択は
行われない(以上図7〜図9参照)。これで午前中の工
事時間帯が指定された全工事案件が選択された(S2
4:Yes)ので、図15のフローチャートによる処理
を終了する。
The selection process after the third item in the morning is also S20 to S.
This is done in the same way as 28, and in this case the work completion schedule for the 2nd case in the morning is 37 teams, 34 teams, 45 teams in that order, so the conditions of S22 and S23 are determined in this order, and 3
No. 3 as the 3rd morning project of Group 7 The construction project No. 09 was selected, and the work end time is predicted to be 11:35, and 3
No. 3 as the 3rd morning project of Group 4 The construction project No. 04 is selected and the work end time is predicted to be 12: 01,
Finally, No. 4 as the 4th morning project of group 37. The construction item of 05 is selected, and the work end time is predicted to be 13:22. Since the scheduled work end time (11:35) of the third project in the 37th morning of group 37 is earlier than the scheduled work finish time (12:14) of the second project in the 45th group, No.
In S25 after the selection of the construction project in 04, 37 teams are extracted. Also, the scheduled end time of the 2nd morning project of group 45 is already past 12:00, and it is clear that it will not be in time for the designated construction project in the morning, so the 3rd morning project is not selected (above) 7 to 9). This selects all the construction projects with the designated construction time zone in the morning (S2
4: Yes), and thus the process according to the flowchart of FIG. 15 ends.

【0045】各作業班が午後に担当すべき工事案件の選
択処理も既述した午前中の場合と略同様に行われる。す
なわち、午後の工事時間帯が指定されているもの(この
例では午後1時〜3時の工事時間帯および午後1時〜5
時の工事時間帯の2通りがあるが、前者を優先する)の
中から、また各作業班について工事種別・スキル要素・
工事場所等の条件指定があるときはそれらの条件を満た
さない工事案件を除外した上で、午前中最後の工事案件
の作業終了予定時刻が早い作業班の順に午後第1案件を
選択する。本事例では午前中の工事案件を終了するのが
34班、45班、37班の順であるので、この順にまず
午後第1案件を選択し、以下午前中の場合と同様にして
午後第2案件以降を選択する。このようにして、No.
08,No.06,No.16,No.14,No.2
3,No.18が34班の午後第1ないし第6案件とし
て選択され、No.12,No.11,No.15,N
o.20,No.22が37班の午後第1ないし第6案
件として選択され、No.03,No.01,No.0
2が45班の午後第1ないし第3案件として選択される
(図7〜図9参照)。
The selection process of the construction project that each work group should be in charge of in the afternoon is performed in substantially the same manner as in the morning. That is, a construction time zone in the afternoon is designated (in this example, the construction time zone from 1:00 pm to 3:00 pm and 1:00 pm to 5 pm)
There are two types of construction hours at the time, but the former is given priority), and for each work group, construction type, skill element,
When conditions such as the construction site are specified, the construction projects that do not meet those conditions are excluded, and the first project in the afternoon is selected in the order of the work group with the earliest scheduled work end time of the last construction project in the morning. In this example, the construction projects in the morning will be completed in the order of 34th group, 45th group, and 37th group. Therefore, in this order, the first project in the afternoon is selected first, and the second session in the afternoon is performed in the same manner as in the morning. Select after Item. In this way, the No.
08, No. 06, No. 16, No. 14, No. Two
3, No. No. 18 was selected as the 1st to 6th case in the afternoon of the 34th group, and No. 18 was selected. 12, No. 11, No. 15, N
o. 20, No. No. 22 was selected as the 1st to 6th case of the 37th group in the afternoon, and No. 22 was selected. 03, No. 01, No. 0
2 is selected as the 1st to 3rd case in the afternoon of 45 teams (see FIGS. 7 to 9).

【0046】なお、最初の工事案件(午前第1案件)を
除く各工事案件の作業開始予測時刻については、既述し
たようにしてその直前の工事場所からの移動距離等に基
づいて移動所要時間を予測し、該直前の工事案件の作業
終了予定時刻から移動所要時間を経過した時刻としてい
る。たとえば34班が午前第1案件の作業を終了するの
は9時40分と予測されており、ここから午前第2案件
場所までの移動所要時間は16分とされているので、午
前第2案件の作業開始予定時刻は9時56分となってい
る。そして、この工事案件の工事種別は「新込」であっ
て(図4参照)その標準作業時間は「1」であり(図2
参照)、コード番号34の作業班の作業スピードレベル
は「0.5」である(図3参照)から、この工事には
「1」×「0.5」=「0.5」=40分を要するもの
と予測できるので、その作業終了予定時刻は10時36
分となる(図7参照)。
As for the estimated work start time of each construction project except the first construction project (first project in the morning), the required travel time is based on the travel distance from the construction site immediately before that as described above. Is predicted, and the time required for movement has elapsed from the scheduled work completion time of the immediately preceding construction project. For example, it is predicted that the 34th group will finish the work on the 1st case in the morning at 9:40, and the time required to move from here to the location of the 2nd case in the morning is 16 minutes. The scheduled work start time is 9:56. The construction type of this construction project is “new” (see FIG. 4), and the standard work time is “1” (FIG. 2).
Since the work speed level of the work group of code number 34 is "0.5" (see Fig. 3), "1" x "0.5" = "0.5" = 40 minutes for this work. Since it can be predicted that this will require,
Minutes (see FIG. 7).

【0047】午後第1案件の作業開始時刻(図7〜図9
における「計画」欄に記載)について、34班および4
5班は午前最後の工事案件の作業終了予定時刻が比較的
早く、その工事場所から午後第1案件の工事場所への移
動所要時間を考慮しても午後第1案件を13時に作業開
始することが可能である(図7,図9参照)が、37班
については午前最後の工事案件の作業終了予定時刻が既
に13時を超えており、これに午後第1案件の工事場所
までの移動所要時間がさらに加わるため、午後第1案件
の作業開始予定時刻が13時33分となっている(図8
参照)。
Work start time for the first case in the afternoon (FIGS. 7 to 9)
34) and 4)
Team 5 has a relatively early scheduled work end time for the last construction project in the morning, and should start work on the first project at 13:00 pm considering the time required to move from the construction site to the construction site for the first project in the afternoon. It is possible (see Figures 7 and 9), but for Team 37, the scheduled work end time for the last construction project in the morning has already exceeded 13:00, and this requires moving to the construction site for the first project in the afternoon. Due to the additional time, the scheduled work start time for the 1st case in the afternoon is 13:33 (Fig. 8
reference).

【0048】以上のようにして、図7〜図9に示す班毎
作業工程一覧をセットにした作業仕分けの第1案が作成
される。これらの班毎作業工程一覧はディスプレイ14
の道路地図上に表示して確認することができる。
As described above, the first proposal for work sorting is created with the work process list for each group shown in FIGS. 7 to 9 as a set. A list of work processes for each group is displayed on the display 14.
You can check it by displaying it on the road map.

【0049】この第1案による作業仕分けによると、3
7班の午前中最後の工事案件である午前第4案件(N
o.05)および午後最後の工事案件である午後第6案
件(No.22)は、ユーザ指定の工事時間帯に作業を
開始することができない。すなわち、午前第4案件の作
業開始予定時刻は12時02分であり、この工事におい
てユーザから指定を受けている工事時間帯(9時〜12
時)に作業を開始することができないことを示している
(図8参照)。ちなみに、37班の午前第3案件(N
o.09)の作業終了予定時刻は11時35分であり、
この時点では午前9時〜12時の指定工事時間帯を経過
してはいない(S23:No)ので、午前第4案件とし
てNo.05が選択された(S24)が、午前第3案件
から午前第4案件への移動中にこの工事時間帯を経過し
てしまったものである。同様に、この37班の午後第6
案件の作業開始予定時刻は17時02分であり、この工
事においてユーザから指定を受けている工事時間帯(1
3時〜17時)に作業を開始することができないことを
示している。図8の班毎作業工程一覧をディスプレイ表
示したときには、これら工事案件の欄が反転表示または
他とは異なる色表示等によって他の工事案件(ユーザ指
定の工事時間帯に作業開始可能なもの)とは区別して表
示される。
According to the work sorting according to the first plan, 3
The 4th morning project (N), which is the last construction project in the morning of Group 7
o. 05) and the 6th afternoon project (No. 22), which is the last construction project in the afternoon, cannot start work in the construction time zone designated by the user. That is, the scheduled work start time for the 4th case in the morning is 12:02, and the construction time zone (9:00 to 12) specified by the user in this construction.
It indicates that the work cannot be started at the time (see FIG. 8). By the way, the third project in the morning of group 37 (N
o. The scheduled work end time of 09) is 11:35,
At this point, the designated construction time zone from 9:00 am to 12:00 has not elapsed (S23: No), so No. 4 is selected as the fourth case in the morning. 05 is selected (S24), but this construction time period has passed during the movement from the third item in the morning to the fourth item in the morning. Similarly, the 6th afternoon of this 37th team
The scheduled work start time for the project is 17:02, and the construction time zone (1
It indicates that the work cannot be started from 3:00 to 17:00). When the work process list for each group in FIG. 8 is displayed on the display, the fields of these construction projects are highlighted or displayed in a different color from other construction projects (work can be started in the construction time zone specified by the user). Are displayed separately.

【0050】第1案による作業仕分けは図10に示すよ
うにディスプレイ表示される。上述のように、この第1
の作業仕分け案によると、37班の午前最後の工事案件
と午後最後の工事案件がユーザ指定の工事時間帯に作業
開始することができないので、図10のディスプレイ画
面においてもこれらの工事案件欄が他とは区別して表示
される。図10では、ユーザ指定の工事時間帯に作業開
始可能な工事案件を●印で、同工事時間帯に作業開始で
きないものを○印で示している。また、班毎作業工程一
覧(図7〜図9)には各作業班の午前および午後の作業
終了予定時刻が併せて表示されている。
The work sorting according to the first plan is displayed on the display as shown in FIG. As mentioned above, this first
According to the work classification plan of No. 37, since the last construction project in the morning of the 37th group and the last construction project in the afternoon cannot be started in the construction time zone designated by the user, these construction project columns are also displayed in the display screen of FIG. It is displayed separately from the others. In FIG. 10, the work items that can start work in the work time zone designated by the user are indicated by ●, and those that cannot be started in the work time zone are indicated by ○. Further, in the work process list for each group (FIGS. 7 to 9), scheduled work end times in the morning and afternoon of each work group are also displayed.

【0051】次いで、S12における優先順位を変えて
行うことによって作業仕分けの別案を作成する(S
3)。S12における優先順位をランダムに設定するこ
とによって多数の作業仕分け案を作成するようにしても
よいが、本事例では、S12における優先順位を37
班、45班、34班の適用順にしてS13〜S15およ
び以降の処理を行い、次には45班、34班、37班の
適用順にしてS13〜S15および以降の処理を行うこ
とにより、合計3通りの作業仕分け案を作成している。
このようにして作成された第2案および第3案による作
業仕分け表を図10と同様にしてディスプレイ表示した
のが図11および図12である。これら第2および第3
の作業仕分け案によれば、いずれの作業班についてもユ
ーザ指定の工事時間帯に作業を開始することができ、且
つ、当日予定されている全23件の工事案件を滞りなく
消化することができるものとなっている。
Next, another work sorting plan is created by changing the priority order in S12 (S12).
3). Although a large number of work sorting plans may be created by randomly setting the priority order in S12, in this example, the priority order in S12 is 37.
By performing S13 to S15 and subsequent processing in the application order of the group, 45 group, and 34 group, and then performing S13 to S15 and subsequent processing in the application order of 45 group, 34 group, and 37 group, There are three types of work sorting plans.
FIGS. 11 and 12 show the display of the work sorting tables according to the second and third plans created in this way, similar to FIG. These second and third
According to the work sorting plan of No. 2, it is possible to start the work for any work group in the construction time zone specified by the user, and it is possible to smoothly complete all the 23 construction projects scheduled on the day. It has become a thing.

【0052】これら3通りの作業仕分け案をS3で作成
した後、CPU21は、各作業仕分け案において最も遅
く作業が終了する作業班の作業終了予定時刻を一覧にし
てディスプレイ23に出力する(S4,図13)。この
ディスプレイ画面においていずれかの作業終了予定時刻
をダブルクリックすると、各案における作業仕分け表
(図10〜図12参照)を示すディスプレイ画面に移行
し、ここで特定の作業班を指定すると当該作業班の班毎
作業工程一覧(図7〜図9参照)を示すディスプレイ画
面に移行し、ここから所定の操作で地図画面(図示せ
ず)に移行できるようになっている。
After creating these three types of work classification plans in S3, the CPU 21 outputs a list of the scheduled work completion times of the work groups whose work is the latest in each work classification plan to the display 23 (S4). (Fig. 13). If you double-click any scheduled work end time on this display screen, the screen will move to the display screen showing the work sorting table (see FIGS. 10 to 12) for each plan, and if you specify a specific work group here, the work group concerned will be displayed. The display screen showing the list of work steps for each group (see FIGS. 7 to 9) can be displayed, and the map screen (not shown) can be displayed from here by a predetermined operation.

【0053】実際のコンピュータ20の操作では、S1
で全23件の工事を特定するとともにS2でこれら工事
を分担すべき作業班を特定した後に、作業仕分け案の作
成を促す所要のキー操作を行うと、図13に示すような
作業終了予定時刻一覧を示すディスプレイ画面が現れ
る。図13に示す例では、第1〜第3の作業仕分け案に
よる作業終了予定時刻は17時27分、17時15分お
よび17時35分であり、この中で全作業班の作業を最
も早く終えるのは第2案であるので、第2案を第1候補
としてその詳細を確認すると、その作業仕分け表(図1
2)を示すディスプレイ画面となり、いずれの作業班に
も作業遅れが生じないことが確認されるので、この第2
案を最終的に作業仕分けとして選択して(S5)、作業
仕分けの処理を終了する。この実施形態では、図12の
ような作業仕分け表を参照して作業遅れの有無を確認し
た後に、コンピュータ操作者による入力を待ってS5で
最終案の確定を行うようにしているが、作業終了予定時
刻が最も早いことと、いずれの作業班にも作業遅れを生
じないことの2つの条件が満たされた場合には、CPU
21が自動的に当該案を選定するようなプログラムにし
てもよい。
In the actual operation of the computer 20, S1
When all the 23 works are specified in step S2 and the work group to which these works are to be assigned are specified in step S2, and the required key operation that prompts the creation of the work sorting plan is performed, the scheduled work end time shown in FIG. A display screen showing a list appears. In the example shown in FIG. 13, the scheduled work end times according to the first to third work sorting plans are 17:27, 17:15, and 17:35, among which the work of all work groups is the earliest. The second plan is to be completed, so if you check the details of the second plan as the first candidate, the work sorting table (Fig. 1) will be displayed.
The display screen shown in 2) is displayed, and it is confirmed that no work delay will occur in any work group.
The plan is finally selected as the work sorting (S5), and the work sorting processing is ended. In this embodiment, after confirming the presence or absence of work delay by referring to the work sorting table as shown in FIG. 12, the final plan is confirmed in S5 after waiting for the input by the computer operator. If two conditions are satisfied: the earliest scheduled time and no work delay in any work group, the CPU is
The program may be such that 21 automatically selects the plan.

【0054】最終的に確定した作業仕分けにおける班毎
作業工程一覧(第1案についての図7ないし図9に示さ
れるものに対応するもの)は、プリンタ24によりプリ
ントアウトして班別持出表として各作業班に手渡し、ま
たは各作業班の車両10に送信してディスプレイ14表
示および/またはプリンタ15出力することができる。
The work process list for each group in the finally decided work sorting (corresponding to the one shown in FIGS. 7 to 9 for the first plan) is printed out by the printer 24 and brought out by group. Can be handed to each work group or transmitted to the vehicle 10 of each work group and displayed on the display 14 and / or output to the printer 15.

【0055】以上に各作業仕分け案の作成要領について
具体的に説明したが、実際の処理では、複数通りに作成
された作業仕分け案のいずれにおいても少なくとも一の
作業班で作業遅れが生じてしまうことがある。以下、こ
のような場合の補完的処理について説明する。
Although the procedure for creating each work classification plan has been specifically described above, in the actual processing, at least one work group causes a work delay in any of the plurality of work classification plans created. Sometimes. Hereinafter, complementary processing in such a case will be described.

【0056】たとえば、前記説明における図13の作業
終了予定時刻一覧が図16のようになり、この中で作業
終了予定時刻が最も早い第11案を第1候補としてその
詳細を確認したときに、当該第11案による班毎作業工
程一覧が図17のように表示されたものとする。34班
の午前第3案件、42班の午前第3案件および午前第4
案件、ならびに43班の午前第4案件の欄に○印が付さ
れており、この案ではこれらの工事案件を指定工事時間
帯に作業開始することができないことが示されている。
このような場合、図16の作業終了予定時刻一覧の表示
画面に戻って、次に作業が早く終わる作業仕分け案を順
次選択してその作業仕分け表を画面表示させ、それらの
中で各作業班に全く作業遅れが生じないものがあれば、
その作業仕分け案を最終的に選択することが可能である
が、実際にはすべての作業仕分け案においていずれかの
作業班に作業遅れが生じていたり、各作業班に全く作業
遅れが生じない案によると作業終了時刻が極端に遅くな
ってしまう場合があり得る。このような場合には、作業
終了時刻が最も早い第11案について、作業遅れが生ず
る各工事案件を他の作業班に移管することの可否を検討
する。
For example, the scheduled work end time list of FIG. 13 in the above description is as shown in FIG. 16, and when the eleventh plan with the earliest scheduled work end time is the first candidate and its details are confirmed, It is assumed that the work process list for each group according to the 11th plan is displayed as shown in FIG. 34th group 3rd morning, 42nd group 3rd morning and 4th morning
A circle is attached to the case and the field of the fourth morning case of the 43rd group, and this proposal indicates that these construction cases cannot be started in the designated construction time zone.
In such a case, returning to the display screen of the scheduled work end time list of FIG. 16, the work sorting plan for which the work is finished sooner is sequentially selected, and the work sorting table is displayed on the screen. If there is no work delay in
It is possible to finally select the work classification plan, but in reality, all work classification plans have a work delay in one work group or no work delay in each work group. According to the report, the work end time may be extremely delayed. In such a case, with regard to the 11th plan, which has the earliest work end time, the possibility of transferring each construction project that causes a work delay to another work group is examined.

【0057】一例として、42班の午前第3案件につい
ての作業移管の手順について説明する。図17の作業仕
分け表において○印が付された当該工事案件の欄をダブ
ルクリックすると、ディスプレイ23の余白部分に、そ
の工事案件の詳細とともに作業開始予定時刻および作業
終了予定時刻等の工事明細表示画面が現れる(図1
8)。この表示画面により、当該工事案件の作業開始予
定時刻が12時15分であり、ユーザ指定の工事時間帯
である9時〜12時には間に合わないことが確認でき
る。
As an example, the procedure of work transfer for the morning third case of group 42 will be described. By double-clicking the column of the relevant construction item marked with a circle in the work sorting table of FIG. 17, the details of the construction item are displayed in the margin of the display 23 along with the construction details such as the scheduled work start time and scheduled work end time. The screen appears (Fig. 1
8). From this display screen, it is possible to confirm that the scheduled work start time of the construction project is 12:15, and that it will not be in time for the construction time zone designated by the user from 9:00 to 12:00.

【0058】ここで、この工事案件について他の作業班
に移管することを促す所要の操作(たとえばディスプレ
イ画面中に表示される「作業移管」キーのクリックおよ
びその確認後の「OK」キーのクリック)を行うと、こ
の工事案件を他の作業班が担当した場合の作業開始予定
時刻を、各作業班の午前中に組み込まれている各工事案
件の場所およびそれらの作業終了予定時刻に基づいて算
出し、さらに、その場合の作業終了予定時刻を各作業班
の作業スピードレベル(図3参照)および当該工事案件
の作業種別の標準作業時間(図2参照)に基づいて算出
して、図20に示すような作業移管選択画面にしてディ
スプレイ表示する。この画面において★印は作業移管し
ても移管後の作業班で作業遅れが生じないことを示して
おり、☆印は作業移管後の作業班で作業遅れが生じてし
まうことを示している。また、当初予定されていた午前
中の工事案件が追加されることによって午後の工事案件
に作業遅れが生じてしまう場合があり、これが午後の工
事案件が図17では●であったものが図19では○印に
変わってしまうことで示されている。
Here, a required operation for promoting the transfer of this construction project to another work group (for example, clicking the "work transfer" key displayed on the display screen and clicking the "OK" key after confirmation thereof). ), The scheduled work start time when another work group is in charge of this construction project is based on the location of each work project incorporated in the morning of each work group and the scheduled work end time. 20 is calculated based on the work speed level of each work group (see FIG. 3) and the standard work time of the work type of the construction project (see FIG. 2). A work transfer selection screen such as that shown in is displayed on the display. In this screen, a star indicates that the work group will not be delayed even if the work is transferred, and a star indicates that the work group will be delayed after the work is transferred. In addition, the work project in the morning may be delayed due to the addition of the initially planned work project in the morning. This is shown in FIG. Then, it is shown by changing to a circle.

【0059】図19の作業移管選択画面から、たとえば
31班には当初の作業仕分け案(図17)では午前中に
2つの工事案件が組み込まれていたが、この作業班の午
前第3案件として、42班の午前第3案件を移管させて
も当該工事案件のユーザ指定の工事時間帯に間に合い、
且つ、この作業移管を行っても午後の所定の工事案件を
すべて予定通りに消化することができ、午前および午後
の作業終了予定時刻もほぼ問題のないものであることが
分かる。ここで、31班の午前第3案件の★印をダブル
クリックする等によって作業移管の実行を促すと、図2
0に示すような作業移管後の作業仕分け表がディスプレ
イ表示される。図17との対比から、移管元の42班に
ついては午前中の工事案件欄において午前第3案件が削
除されて午後第4案件が午前第3案件に繰り上がり、こ
れに伴って午前および午後の作業終了予定時刻が早くな
っており、また、移管先の31班については午前中の工
事案件欄において午前第3案件が追加され、これに伴っ
て午前および午後の作業終了予定時刻が遅くなっている
ことが分かる。
From the work transfer selection screen of FIG. 19, for example, in the 31st group, two construction projects were incorporated in the morning in the original work sorting plan (FIG. 17). , Even if the 42nd group's 3rd morning project is transferred, it will be in time for the user-specified construction time zone of the relevant construction project,
Moreover, it can be seen that even if this work transfer is performed, all the predetermined construction projects in the afternoon can be completed as scheduled, and the scheduled work end times in the morning and the afternoon are almost no problem. Here, if the transfer of work is urged by double-clicking on the ★ mark of the 3rd AM project in the 31st group,
The work sorting table after the work transfer as shown in 0 is displayed on the display. From the comparison with Fig. 17, for team 42 of the transfer source, the third project in the morning was deleted in the construction project column in the morning, and the fourth project in the afternoon moved to the third project in the morning. The scheduled work end time is earlier, and the third project in the morning is added to the transfer destination 31st group, and the scheduled work end time in the morning and afternoon is delayed accordingly. I know that

【0060】以上に説明したような作業移管処理を、図
17の作業仕分け表において作業遅れを示す○印が付さ
れた各工事案件について順次行ってゆく。すなわち、4
2班の午前第3案件を31班の午前第3案件に作業移管
させても、なお3つの工事案件がユーザ指定の工事時間
帯に間に合わない(図20)ので、これら3つの工事案
件についての作業移管処理を順次行う。
The work transfer processing as described above is sequentially carried out for each construction item marked with a circle indicating the work delay in the work sorting table of FIG. Ie 4
Even if the 3rd morning project of the 2nd group is transferred to the 3rd morning project of the 31st group, the 3 construction projects are still not in time for the construction time specified by the user (Fig. 20). Work transfer processing is performed sequentially.

【0061】このような作業移管処理によっても必ずし
も全工事案件を首尾良く移管させることができるとは限
らない。幾つかの作業移管処理後に図21のような作業
仕分け表が作成されたとする。図17においては4つの
工事案件が○印であったのが、そのうち3つの工事案件
については他の作業班に移管させることができたが、3
5班の午前第3案件だけが他の作業班にうまく移管させ
ることができずに○印のままで残っている。図21の作
業仕分け表においてこの○印の欄をダブルクリック等に
より該当する工事明細を表示させる(図22)と、この
午前第3案件の作業開始予定時刻は12時01分であっ
て、ユーザ指定工事時間帯に僅か1分の遅れであること
が分かる。この程度の遅れは許容範囲の遅れとみなすこ
とができるので、図21の作業仕分け案を最終的に採用
する。
Even with such work transfer processing, it is not always possible to transfer all the construction projects successfully. It is assumed that a work sorting table as shown in FIG. 21 is created after some work transfer processing. In Fig. 17, four construction projects were marked with a circle, but three construction projects could be transferred to another work group, but 3
Only the third project in the morning of group 5 could not be successfully transferred to other work groups, and it remains as a circle. When the corresponding work details are displayed by double-clicking the box marked with ○ in the work sorting table of FIG. 21 (FIG. 22), the scheduled work start time for this third AM project is 12: 1 and the user It can be seen that it is only 1 minute behind the designated construction time. Since a delay of this extent can be regarded as an allowable delay, the work sorting plan of FIG. 21 is finally adopted.

【0062】複数通りに作成された作業仕分け案のいず
れにおいても、作業移管処理後もなお複数の工事案件の
作業遅れが解消しない場合や、その作業開始の遅れが許
容範囲を超えるような場合は、当初予定の作業班では全
部の工事案件を処理できないことを意味しているので、
作業班を追加して既述した作業仕分け処理をやり直す。
当該未決の○印の工事案件が少数である場合は、単にこ
れらの工事案件を追加した作業班に担当させるようにし
てもよい。
In any of the work sorting plans created in a plurality of cases, when the work delay of a plurality of construction projects cannot be eliminated even after the work transfer processing, or the work start delay exceeds the allowable range, Since it means that the initially planned work group cannot process all construction projects,
Add a work group and redo the work sorting process described above.
When the number of undecided construction projects marked with a circle is small, the work teams who have added these construction projects may simply be in charge.

【0063】なお、作業移管は必ずしも移管先の午前ま
たは午後の最終案件として組み込まれるものとは限ら
ず、移管対象の工事案件の指定工事時間帯と移管先の作
業班の各工事案件の作業終了予定時刻およびその工事場
所との関係によっては、午前または午後の途中の工事案
件に組み込まれることもある。たとえば図19の作業移
管選択画面において、36班または38班に作業移管さ
せるときは午前第3案件に組み込まれ、当初案の午前第
3案件が午前第4案件に繰り下げられている。
The work transfer is not always incorporated as the final project in the morning or afternoon of the transfer destination, and the designated construction time period of the transfer target construction project and the completion of the work of each construction project of the transfer destination work group. Depending on the scheduled time and the relationship with the construction site, it may be included in a construction project during the morning or afternoon. For example, in the work transfer selection screen of FIG. 19, when the work is transferred to the 36th group or the 38th group, the work is incorporated into the 3rd morning project, and the 3rd morning project is put back to the 4th morning project.

【0064】作業移管の処理について説明したが、図5
のフローチャートにおいてS1で工事日当日のオーダー
データを取得した後、S5で作業仕分け案のいずれかを
最終的に確定するまでの間にオーダーの追加が必要とな
った場合も、作業移管の場合と同様にして当該追加オー
ダーを各作業班に担当させることの可否について確認す
ることができる。たとえば、図17,図20,図21に
示すような作業仕分け表を表示したディスプレイ画面に
おいて図示しない「作業追加」キーをクリックすること
によって図18に示すような工事明細表示画面が現れる
ので、この画面において指定工事時間帯、工事場所の電
話番号、工事種別、回線契約者名、設置場所等の必要デ
ータを入力する。あるいは追加オーダーを工事発注元か
ら直接受信し、またはこれを受信した端末からのデータ
送信または手入力によって取り込んで図18に示すよう
な工事明細表示画面として表示させてもよい。当該追加
オーダを各作業班に担当させた場合の結果は図19の作
業移管選択画面と同様に示される追加オーダー仕分け選
択画面がディスプレイ表示され、この中で最適と認めら
れる作業班の工事案件欄の★印をダブルクリックする等
によって追加オーダーの仕分け処理が実行される。ある
いは、当該追加オーダーの工事場所に最も近い(前述の
判断基準による)既登録工事案件を探し出して、その工
事案件を担当する作業班が次に担当すべき工事案件とし
て割り込ませた上で、図5のフローチャートのS3で作
業仕分け案を作成してもよい。
Although the work transfer processing has been described, FIG.
In the flow chart of Fig. 2, even if it is necessary to add an order after obtaining the order data for the construction day on S1 and finally confirming one of the work sorting plans in S5, In the same manner, it is possible to confirm whether each work group can take charge of the additional order. For example, by clicking a "work addition" key (not shown) on the display screen displaying the work sorting table as shown in FIGS. 17, 20, and 21, a construction detail display screen as shown in FIG. 18 appears. On the screen, enter the required data such as designated construction time zone, construction site telephone number, construction type, line contractor name, and installation location. Alternatively, the additional order may be received directly from the construction ordering source, or may be received by data transmission or manual input from the terminal that has received the additional order and displayed as a construction detail display screen as shown in FIG. The result of assigning the additional order to each work group is the same as the work transfer selection screen of FIG. 19, and the additional order sorting selection screen is displayed. By double-clicking the mark of *, etc., the sorting process of the additional order is executed. Alternatively, the registered construction project closest to the construction site of the additional order (according to the above-mentioned criteria) is searched for, and the work team in charge of the construction project interrupts it as the next construction project to be in charge, and then A work sorting plan may be created in S3 of the flowchart of FIG.

【0065】なお、ユーザ指定の工事時間帯に間に合わ
ない(工事時間帯の間に当該工事場所に到着しないため
に作業開始することができない)場合の作業移管処理に
ついて既述したが、当日のオーダーファイルリスト(図
4参照)に含まれる工事案件数が相対的に少ない場合に
は、前述の要領で各作業班に工事案件を振り分けていく
と、ある工事案件についてはその指定工事時間帯の前に
当該工事場所に到着してしまうことがあり得る。この場
合には、このままで作業仕分け処理をひとまず終了さ
せ、作成した各案の作業仕分け表(図17参照)におい
て当該早着の工事案件を他の工事案件(指定工事時間帯
の条件を満たすもの(●印)および指定工事時間帯に間
に合わないもの(○印))とは識別可能に表示する。こ
のような早着の工事案件が多く生ずるような場合は、当
日に行うべき工事案件数や工事内容に対して稼動作業班
数が多すぎることを意味しているので、稼動作業班数を
削減(図5のフローチャートのS2で削減後の作業班数
を再設定)した上で再度仕分け処理を実行することがで
きる。
It should be noted that the work transfer processing in the case where the construction time zone designated by the user is not in time (the work cannot be started during the construction time zone because the construction site has not arrived) has already been described. When the number of construction projects included in the file list (see Fig. 4) is relatively small, the work projects are distributed to each work group as described above. May arrive at the construction site. In this case, the work sorting process is terminated as it is, and in the work sorting table (see FIG. 17) of each draft created, the early-arriving construction project is replaced with another construction project (that satisfies the conditions of the designated construction time zone). (● mark) and those that do not meet the designated construction time (○ mark) will be displayed in a distinguishable manner. If many such early-arriving construction projects occur, it means that the number of operating work groups is too large for the number of construction projects and work contents to be done on the day, so the number of operating work groups should be reduced. (The number of work groups after reduction is reset in S2 of the flowchart of FIG. 5) and then the sorting process can be executed again.

【0066】本発明の幾つかの実施形態について図面を
参照して詳述したが、本発明はこれに限定されるもので
はなく、特許請求の範囲の各請求項に記載される発明の
範囲内において広く変形態様を取り得る。たとえば、以
上の説明では、作業種別毎の標準作業時間を数値化した
標準作業時間データベース221と、作業班毎の作業ス
ピードレベルを数値化した作業スピードレベルデータベ
ース222をあらかじめ作成してセンターコンピュータ
20のメモリ22に格納しておき、作業仕分け表作成処
理において、各作業班が担当する作業案件の作業種別に
ついての標準作業時間を標準作業時間データベースから
読み出すとともに、当該作業班の作業スピードレベルを
作業スピードレベルデータベースから読み出し、これら
を乗じて各作業班が担当する作業案件に要する作業時間
を算出するようにしたが、この具体的手法に限定される
ものではない。たとえば、各作業班が要した作業時間の
実績を作業種別毎に記録した作業スキルデータベースを
センターコンピュータ20のメモリ22に格納してお
き、これを参照して各作業班が担当する作業案件に要す
る作業時間を予測するようにしてもよい。作業班が作業
案件を担当する毎にその作業時間実績を取り入れること
により、徐々に信頼性の高い作業スキルデータベースに
更新され、より正確な作業時間予測が可能になる。
Although some embodiments of the present invention have been described in detail with reference to the drawings, the present invention is not limited thereto, but is within the scope of the invention described in each claim of the claims. Can be widely modified. For example, in the above description, the standard work time database 221 that quantifies the standard work time for each work type and the work speed level database 222 that quantifies the work speed level for each work group are created in advance and stored in the center computer 20. It is stored in the memory 22, and in the work sorting table creation process, the standard work time for the work type of the work case in charge of each work group is read from the standard work time database, and the work speed level of the work group is set to the work speed. Although the work time is read from the level database and is multiplied by these to calculate the work time required for the work case in charge of each work group, the present invention is not limited to this specific method. For example, a work skill database in which the results of the work time required by each work group are recorded for each work type is stored in the memory 22 of the center computer 20, and the work cases required by each work group are referred to with reference to this. The working time may be predicted. Each time the work team takes charge of a work item, by incorporating the work time results, the work skill database is gradually updated to be highly reliable, and more accurate work time prediction becomes possible.

【0067】また、以上の説明では各作業案件を一つず
つ作業仕分けするものとしているが、たとえば電話工事
においては複数の工事案件が互いに関連性を持つために
同一作業班が一括して処理すべき場合(同一住所での電
話回線新設工事、旧住所から新住所への電話移設工事
等)があり、このような場合には仕分け処理(図5のフ
ローチャートのS3)上は複数の関連オーダーを一括し
て扱うことが好ましい。
Further, in the above description, each work case is classified as work one by one, but, for example, in telephone construction, since a plurality of construction cases are related to each other, they are collectively processed by the same work group. There are cases where it should be done (new construction of telephone lines at the same address, telephone relocation work from the old address to the new address, etc.). In such cases, multiple related orders should be placed on the sorting process (S3 in the flowchart of FIG. 5). It is preferable to handle them collectively.

【0068】[0068]

【発明の効果】以上に説明したように、本発明によれ
ば、電話工事等を複数の作業班に分担して行わせる際の
作業仕分け表をコンピュータシステムを利用して自動的
且つ効率的に作成することができるという効果がある。
As described above, according to the present invention, a work sorting table when telephone work or the like is divided among a plurality of work groups is performed automatically and efficiently by using a computer system. It has the effect that it can be created.

【0069】また、本発明では複数通りの作業仕分け案
を作成するので、各案において最も遅く作業を終了する
作業班の作業終了予定時刻または各案における各作業班
の作業遅れの有無を参照していずれかの案を選択するこ
とができる。
Further, in the present invention, since a plurality of types of work sorting plans are created, the work end scheduled time of the work group that finishes the work latest in each plan or the presence or absence of work delay of each work group in each plan is referred to. You can choose one of these options.

【0070】また、作成した作業仕分け案においていず
れかの作業班の担当作業案件に作業遅れが生ずる場合に
は、当該作業案件を他の作業班に移管させることが可能
であり、この作業移管処理によって作業仕分け案をさら
に適正化することができる。
Further, when a work delay occurs in the work item in charge of any work group in the created work sorting plan, the work item can be transferred to another work group, and this work transfer processing is performed. This makes it possible to further optimize the work sorting plan.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明が適用される電話工事管理システムの概
要を示すブロック図である。
FIG. 1 is a block diagram showing an outline of a telephone construction management system to which the present invention is applied.

【図2】標準作業時間データベースの一例を示すデータ
テーブルである。
FIG. 2 is a data table showing an example of a standard work time database.

【図3】作業スピードレベルデータベースの一例を示す
データテーブルである。
FIG. 3 is a data table showing an example of a work speed level database.

【図4】特定の工事日に特定の工事エリア(神奈川県横
須賀地区)で行うべき工事のオーダーファイルをオーダ
ーファイル格納部から読み出してディスプレイ表示した
図である。
FIG. 4 is a diagram in which an order file for construction to be performed in a specific construction area (Yokosuka district, Kanagawa prefecture) on a specific construction day is read from the order file storage unit and displayed on the display.

【図5】本発明による作業仕分け表作成処理を示すフロ
ーチャートである。
FIG. 5 is a flowchart showing a work sorting table creation process according to the present invention.

【図6】単純化した適用事例において工事請負会社に所
属する全作業班を一覧表示した表である。
FIG. 6 is a table showing a list of all work groups belonging to a construction contractor in a simplified application example.

【図7】同事例において図14および図15のフローチ
ャートに示される処理工程およびその後の処理工程を経
て作案された一の作業班の作業工程一覧をディスプレイ
表示した図である。
FIG. 7 is a diagram showing a display of a work process list of one work group designed through the process steps shown in the flowcharts of FIGS. 14 and 15 and the subsequent process steps in the same case.

【図8】同事例において同処理工程を経て作案された他
の作業班の作業工程一覧をディスプレイ表示した図であ
る。
FIG. 8 is a diagram showing a display of a work process list of another work group, which has been devised through the same treatment process in the same case.

【図9】同事例において同処理工程を経て作案された他
の作業班の作業工程一覧をディスプレイ表示した図であ
る。
FIG. 9 is a diagram showing a display of a work process list of another work group, which has been designed through the same process in the same case.

【図10】図7〜図9の班毎作業工程一覧のセットとし
て作案された作業仕分けの第1案をディスプレイ表示し
た図である。
FIG. 10 is a diagram in which a first plan of work sorting, which is designed as a set of work process lists for each group in FIGS. 7 to 9, is displayed on a display.

【図11】作業仕分けの第2案をディスプレイ表示した
図である。
FIG. 11 is a diagram in which a second proposal of work sorting is displayed on a display.

【図12】作業仕分けの第3案をディスプレイ表示した
図である。
FIG. 12 is a diagram in which a third plan of work sorting is displayed on a display.

【図13】図10〜図12に示す各作業仕分け案におい
て最も遅く作業が終了する作業班の作業終了予定時刻を
ディスプレイ表示した図である。
FIG. 13 is a diagram in which a scheduled work end time of a work group, which finishes work latest in each work sorting plan shown in FIGS. 10 to 12, is displayed on a display.

【図14】図5のフローチャートにおけるS3のステッ
プを実行するための具体的処理として、各作業班につい
て当日最初に担当すべき工事案件(午前第1案件)を選
択する処理工程を示すフローチャートである。
FIG. 14 is a flowchart showing a processing step of selecting a construction project (first morning project) to be first in charge for each work group as a specific process for executing step S3 in the flowchart of FIG. .

【図15】図14のフローチャートに示される処理工程
の後、各作業班について次に担当すべき工事案件(午前
第2案件以降)を選択する処理工程を示すフローチャー
トである。
FIG. 15 is a flowchart showing a processing step of selecting a construction project (the second project after the second morning) to be in charge for each work group after the processing steps shown in the flowchart of FIG.

【図16】より実際的な適用事例において作成された各
作業仕分け案において最も遅く作業が終了する作業班の
作業終了予定時刻をディスプレイ表示した図である。
FIG. 16 is a diagram in which the scheduled work end time of the work group, which finishes the work latest in each work sorting plan created in a more practical application example, is displayed on the display.

【図17】図16で最も作業終了予定時刻の早い作業仕
分け案をディスプレイ表示した図である。
FIG. 17 is a diagram in which a work sorting plan with the earliest scheduled work end time in FIG. 16 is displayed on the display.

【図18】図17で作業遅れが生じている工事案件につ
いてその工事明細をディスプレイ表示した図である。
FIG. 18 is a diagram in which the construction details of the construction project in which the work delay has occurred in FIG. 17 are displayed on the display.

【図19】図18に示された工事案件を他の作業班に移
管させたときの処理結果をディスプレイ表示した作業移
管選択画面の図である。
FIG. 19 is a diagram of a work transfer selection screen displaying a processing result when the construction project shown in FIG. 18 is transferred to another work group.

【図20】図19の作業移管選択画面から作業遅れを生
じない一の場合を選択したときの作業移管後の作業仕分
け案をディスプレイ表示した図である。
FIG. 20 is a diagram in which the work sorting plan after the work transfer is displayed on the display when the one case in which the work is not delayed is selected from the work transfer selection screen of FIG. 19;

【図21】同様の作業移管処理を繰り返し行った後の作
業仕分け案をディスプレイ表示した図である。
FIG. 21 is a diagram showing a display of a work sorting plan after repeating the same work transfer process.

【図22】図21の表中で作業遅れが生じている工事案
件についてその工事明細をディスプレイ表示した図であ
る。
FIG. 22 is a diagram in which the construction details of a construction project in which a work delay occurs in the table of FIG. 21 are displayed on a display.

【符号の説明】[Explanation of symbols]

10 作業班の車両 11 カーナビシステム 12 GPSセンサ 13 CPU 14 ディスプレイ 15 プリンタ 16 GPSアンテナ 17 アンテナ 20 センターコンピュータ 21 CPU 22 メモリ 221 標準作業時間データベース 222 作業スピードレベルデータベース 223 道路地図データベース 224 オーダーファイル格納部 225 仕分け表作成プログラム 23 ディスプレイ 24 プリンタ 25 アンテナ Vehicle of 10 working groups 11 Car navigation system 12 GPS sensor 13 CPU 14 display 15 Printer 16 GPS antenna 17 antenna 20 Center computer 21 CPU 22 memory 221 Standard Working Time Database 222 Work speed level database 223 Road Map Database 224 Order file storage 225 Sorting table creation program 23 Display 24 printers 25 antenna

Claims (11)

【特許請求の範囲】[Claims] 【請求項1】(a)特定の期間内に完了させるべき複数
の作業の各々についてその作業場所および作業開始時間
帯を少なくとも含む作業案件データを取得し、(b)こ
れら複数の作業を分担すべき複数の作業班の指定を受
け、(c)各作業班の現在地と、作業案件データ中の各
作業案件の作業場所および作業開始時間帯と、各作業班
が各担当作業案件に要する作業時間とから、各作業班が
担当すべき作業案件およびその作業順についての作業仕
分け案を複数通り作成し、(d)作成された複数通りの
作業仕分け案のいずれかを選択可能にディスプレイ表示
する、各処理をコンピュータに実行させることを特徴と
する班別作業仕分け方法。
1. A work item data including at least a work place and a work start time zone is acquired for each of a plurality of works to be completed within a specific period, and (b) the work is shared. (C) the current location of each work group, the work place and work start time zone of each work case in the work case data, and the work time required by each work group for each work case in charge From the above, a plurality of work assortment plans for work cases and work orders to be handled by each work group are created, and (d) any one of the plurality of created work assortment plans is selectably displayed. A method for sorting work by group, which is characterized by causing a computer to execute each process.
【請求項2】前記(c)の処理において、(c−1)作
業開始時間帯の条件を満たす作業案件のうち、所定の優
先順位による最優先の作業班の出発地から最も近いと判
断される作業場所の作業案件を選択して当該最優先作業
班の第1作業案件とし、作業班の優先順位にしたがって
順次同様にして既選択の作業案件を除く作業案件のうち
各作業班の出発地から最も近いと判断される作業場所の
作業案件を各作業班の第1作業案件とし、(c−2)こ
のようにして決定された第1作業案件のうち最も早く作
業を終了すると判断される作業班から、既選択の作業案
件を除く作業案件のうち当該作業班の第1作業案件の作
業場所から最も近いと判断される作業場所の作業案件を
選択して当該作業班の第二作業案件とし、順次同様にし
て第1作業案件の作業終了順に各作業班の第二作業案件
を選択し、(c−3)順次同様にして全作業案件を各作
業班に振り分けることによって第1の作業仕分け案を作
成し、(c−4)作業班の優先順位を変えて上記(c−
1)およびその後の(c−2)ないし(c−3)の各処
理を実行して複数通りの作業仕分け案を作成することを
特徴とする、請求項1記載の班別作業仕分け方法。
2. In the processing of (c), it is determined that the work item satisfying the condition of (c-1) work start time zone is closest to the departure place of the highest priority work group according to a predetermined priority order. The work item of the work place to be selected is set as the first work item of the highest priority work group, and in the same manner, according to the priority of the work group, the departure place of each work group among the work items excluding the already selected work item The work case of the work place that is determined to be closest to the work group is set as the first work case of each work group, and (c-2) it is determined that the work is completed earliest among the first work cases determined in this way. From the work group, among the work cases excluding the already selected work case, select the work case in the work place that is determined to be closest to the work place of the first work case in the work group, and select the second work case in the work group. And, in the same way, for the first work case The second work item of each work group is selected in the order of completion of the work, and (c-3) in the same manner, the first work sorting plan is created by allocating all work items to each work group, (c-4). By changing the priority of the work group, the above (c-
2. The method for sorting work by group according to claim 1, wherein a plurality of types of work sorting plans are created by executing the processing 1) and the subsequent processings (c-2) to (c-3).
【請求項3】前記(c)の処理において用いる作業時間
は、各作業班が要した作業時間の実績を作業種別毎に記
録した作業スキルデータベースに基づいて予測すること
を特徴とする、請求項1または2記載の班別作業仕分け
方法。
3. The work time used in the process (c) is estimated based on a work skill database in which the actual work time required by each work group is recorded for each work type. The work sorting method according to section 1 or 2.
【請求項4】作業種別毎の標準作業時間を数値化した標
準作業時間データベースと、作業班毎の作業スピードレ
ベルを数値化した作業スピードレベルデータベースとを
作成し、前記(c)の処理において、各作業班が担当す
る作業案件の作業種別についての標準作業時間を標準作
業時間データベースから読み出すとともに、当該作業班
の作業スピードレベルを作業スピードレベルデータベー
スから読み出し、これらを乗じて各作業班が担当する作
業案件に要する作業時間を算出することを特徴とする、
請求項1または2記載の班別作業仕分け方法。
4. A standard work time database in which the standard work time for each work type is quantified, and a work speed level database in which the work speed level for each work group is quantified are created, and in the process of (c), The standard work time for the work type of the work item that each work group is in charge is read from the standard work time database, the work speed level of the work group is read from the work speed level database, and each work group is in charge by multiplying these. Characterized by calculating the work time required for the work item,
The method for sorting work by group according to claim 1.
【請求項5】前記(d)の処理において、複数通りに作
成された作業仕分け案の各々について、最も遅く全作業
案件の作業を終了する作業班の当該作業終了時刻を予測
してディスプレイ表示することを特徴とする、請求項1
ないし4のいずれか記載の班別作業仕分け方法。
5. In the processing of (d) above, for each of the work sorting plans created in a plurality of ways, the work end time of the work group that finishes the work of all work projects latest is predicted and displayed. Claim 1 characterized by the above.
The work sorting method according to any one of 1 to 4 above.
【請求項6】現在時刻が作業開始時間帯の中にあり且つ
その作業場所が当該作業班の現在地に最も近い作業案件
であっても、現在地から作業場所への移動所要時間を考
慮すると作業開始時刻が作業開始時間帯を越えてしまう
場合に、前記(d)の処理において、その作業案件を当
該作業班が担当する場合には作業開始時間帯の条件を満
たさないことをディスプレイ表示することを特徴とす
る、請求項1ないし5のいずれか記載の班別作業仕分け
方法。
6. Even if the present time is within the work start time zone and the work place is the closest work item to the present position of the work group, the work is started considering the time required to move from the present position to the work place. When the time exceeds the work start time zone, in the process of (d), when the work group is in charge of the work case, it is displayed on the display that the condition of the work start time zone is not satisfied. A method for sorting work by group according to any one of claims 1 to 5.
【請求項7】前記(d)の処理において作業開始時間帯
の条件を満たさないものとして表示された作業案件につ
いて、当該作業案件を他の作業班に移管させた場合の作
業開始予定時刻を、各作業班に組み込まれている各作業
案件の場所およびそれらの作業終了予定時刻に基づいて
算出し、さらに、その場合の作業終了予定時刻を各作業
班が要する作業時間に基づいて算出して、各作業班に移
管可能であるか否かをディスプレイ表示することを特徴
とする、請求項6記載の班別作業仕分け方法。
7. The work start scheduled time when the work case is transferred to another work group for the work case displayed as not satisfying the condition of the work start time zone in the processing of (d), Calculated based on the location of each work case incorporated in each work group and their scheduled work end time, and in addition, calculate the scheduled work end time in that case based on the work time required by each work group, 7. The work sorting method for each group according to claim 6, further comprising displaying on a display whether or not the work can be transferred to each work group.
【請求項8】当該作業案件を他の作業班に移管させるべ
きことの指示を受けて、この作業移管を実行して、作業
移管後の作業仕分け案をディスプレイ表示することを特
徴とする、請求項7記載の班別作業仕分け方法。
8. A method for receiving the instruction to transfer the work item to another work group, executing the work transfer, and displaying the work sorting plan after the work transfer on the display. Item-classified work sorting method according to item 7.
【請求項9】前記(d)の処理後に選択された作業仕分
け案を班別の作業工程表にしてプリンタ出力可能とする
ことを特徴とする、請求項1ないし8のいずれか記載の
班別作業仕分け方法。
9. The group classification according to claim 1, wherein the work classification plan selected after the process of (d) is made into a group-specific work process table and can be output to a printer. Work sorting method.
【請求項10】前記(a)における特定の期間が一日の
うちの特定の時間帯であることを特徴とする、請求項1
ないし9のいずれか記載の班別作業仕分け方法。
10. The specific period in (a) above is a specific time zone of the day, and
A method for sorting work by group according to any one of 1 to 9.
【請求項11】請求項1ないし10のいずれか記載の班
別作業仕分け方法における各処理をコンピュータに実行
させるための班別作業仕分けプログラム。
11. A group-based work sorting program for causing a computer to execute each process in the group-based work sorting method according to any one of claims 1 to 10.
JP2002282411A 2001-11-21 2002-09-27 Work sorting system by group Expired - Fee Related JP4430289B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002282411A JP4430289B2 (en) 2001-11-21 2002-09-27 Work sorting system by group

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2001356703 2001-11-21
JP2001-356703 2001-11-21
JP2002282411A JP4430289B2 (en) 2001-11-21 2002-09-27 Work sorting system by group

Publications (2)

Publication Number Publication Date
JP2003223536A true JP2003223536A (en) 2003-08-08
JP4430289B2 JP4430289B2 (en) 2010-03-10

Family

ID=27759182

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002282411A Expired - Fee Related JP4430289B2 (en) 2001-11-21 2002-09-27 Work sorting system by group

Country Status (1)

Country Link
JP (1) JP4430289B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110363409A (en) * 2019-06-28 2019-10-22 北京银企融合技术开发有限公司 A kind of team's configuration method based on output capacity, apparatus and system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63310068A (en) * 1987-06-11 1988-12-19 Toshiba Corp Decided assignment changing system
JPH05108649A (en) * 1991-10-16 1993-04-30 Kobe Steel Ltd Production/physical distribution schedule generating device
JPH05120295A (en) * 1991-10-24 1993-05-18 Toshiba Corp Allocation possibility judgement device
JPH05150985A (en) * 1991-03-07 1993-06-18 Hitachi Ltd Problem solving method
JPH07210606A (en) * 1994-01-24 1995-08-11 Sekisui Chem Co Ltd Scheduling system
JPH07234997A (en) * 1993-12-27 1995-09-05 Hitachi Eng Co Ltd Method/system for planning car allocation
JPH09330359A (en) * 1996-06-12 1997-12-22 Hitachi Ltd Work schedule alteration management system
JPH10105611A (en) * 1996-09-30 1998-04-24 Mitsubishi Electric Corp Nursing visit scheduling system
JPH10261122A (en) * 1997-03-18 1998-09-29 Sumitomo Wiring Syst Ltd Work distribution optimization method
WO2001013276A1 (en) * 1999-08-12 2001-02-22 General Electric Company Methods and apparatus for scheduling

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63310068A (en) * 1987-06-11 1988-12-19 Toshiba Corp Decided assignment changing system
JPH05150985A (en) * 1991-03-07 1993-06-18 Hitachi Ltd Problem solving method
JPH05108649A (en) * 1991-10-16 1993-04-30 Kobe Steel Ltd Production/physical distribution schedule generating device
JPH05120295A (en) * 1991-10-24 1993-05-18 Toshiba Corp Allocation possibility judgement device
JPH07234997A (en) * 1993-12-27 1995-09-05 Hitachi Eng Co Ltd Method/system for planning car allocation
JPH07210606A (en) * 1994-01-24 1995-08-11 Sekisui Chem Co Ltd Scheduling system
JPH09330359A (en) * 1996-06-12 1997-12-22 Hitachi Ltd Work schedule alteration management system
JPH10105611A (en) * 1996-09-30 1998-04-24 Mitsubishi Electric Corp Nursing visit scheduling system
JPH10261122A (en) * 1997-03-18 1998-09-29 Sumitomo Wiring Syst Ltd Work distribution optimization method
WO2001013276A1 (en) * 1999-08-12 2001-02-22 General Electric Company Methods and apparatus for scheduling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110363409A (en) * 2019-06-28 2019-10-22 北京银企融合技术开发有限公司 A kind of team's configuration method based on output capacity, apparatus and system

Also Published As

Publication number Publication date
JP4430289B2 (en) 2010-03-10

Similar Documents

Publication Publication Date Title
JP5308621B2 (en) Map data distribution system
CN101501452A (en) Map update data supplying apparatus, version table, map data updating syste and map update data supplying method
JP2005158046A (en) Worker-in-charge command system and worker-in-charge command method
JP2007249952A (en) Vehicle operation information processing method and vehicle operation information processing system
JP2002312550A (en) Method for assigning work to workers
EP1708131A1 (en) Worker-in-charge command system and worker-in-charge command method
CN107563584B (en) Information processing apparatus and information processing method
EP1443402A1 (en) Information control system, server for information control system, and information terminal for information control system
JP5078965B2 (en) Work classification correction system by group
JP5355491B2 (en) Work site work management system
JP2004139584A (en) Route search device, route search method and route search program
JP2004178454A (en) Construction business integration management system and method
JP2003223536A (en) Method and program for sorting group operation
JP4430294B2 (en) Work classification correction system by group according to work progress
JP5057864B2 (en) Automatic business distribution system and automatic business distribution method
JP4385101B2 (en) Work completion system by listening survey
JP2006178940A (en) Refuse collection calendar creation device, refuse collection calendar creation software, refuse collection calendar information creation system and information terminal device
JP2820340B2 (en) Touring work sequence decision management system
JP2008186382A (en) System and program for determining work propriety
JP3381037B2 (en) Construction by-product reuse information management system
JP2005055964A (en) Schedule management device, operating method of schedule management device, schedule management program and computer-readable recording medium to which schedule management program is recorded
JP2007257311A (en) Wide-range business management device and method
JP2005128772A (en) Schedule control device and program
JP2005284937A (en) Print order allocation apparatus, program for use in the same, and print order allocation system
JP6399104B2 (en) Itinerary display program, itinerary display method, and itinerary display device

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20040507

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20040507

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060530

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060728

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20061121

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070419

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20081112

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20090416

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20090416

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090928

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091217

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121225

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4430289

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121225

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121225

Year of fee payment: 3

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121225

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121225

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131225

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131225

Year of fee payment: 4

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131225

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees