JP2003058228A - Product progress management method and device - Google Patents

Product progress management method and device

Info

Publication number
JP2003058228A
JP2003058228A JP2001246610A JP2001246610A JP2003058228A JP 2003058228 A JP2003058228 A JP 2003058228A JP 2001246610 A JP2001246610 A JP 2001246610A JP 2001246610 A JP2001246610 A JP 2001246610A JP 2003058228 A JP2003058228 A JP 2003058228A
Authority
JP
Japan
Prior art keywords
production
time
delivery
progress
allowance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2001246610A
Other languages
Japanese (ja)
Inventor
Kazutaka Yamaguchi
和隆 山口
Teru Sawada
輝 沢田
Kazuhiro Kobayashi
和弘 小林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Denso Ten Ltd
Original Assignee
Denso Ten Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Denso Ten Ltd filed Critical Denso Ten Ltd
Priority to JP2001246610A priority Critical patent/JP2003058228A/en
Publication of JP2003058228A publication Critical patent/JP2003058228A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To shorten manufacture lead time and to manufacture production objects matched with delivery time. SOLUTION: At the time of manufacturing the production objects along the flow of a plurality of processes indicated in (a), in order to manufacture them in a just-in-time manner so as to be just in time for the delivery time, not only feed time is controlled but also a delivery margin after feed is controlled. When only the feed time is controlled, as indicated in (b), feed is performed with a time margin so as not to generate objects which do not make the delivery time and stock in process equivalent to the time margin is generated when production is smoothly completed. As indicated in (c), when progress management based on a delivery margin is performed among the respective processes, the manufacture lead time is shortened while keeping an appropriate delivery margin.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、「かんばん納入方
式契約」などに基づき、生産日程計画によらない生産指
示で生産の投入制御が行われる生産工場で、全体的な生
産進度管理を行うための生産進度管理方法および装置に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is intended for overall production progress management in a production factory in which production input control is performed based on a "kanban delivery system contract" or the like according to a production instruction that does not depend on a production schedule. The present invention relates to a production progress management method and device.

【0002】[0002]

【従来の技術】従来から、「かんばん方式」と呼ばれる
生産管理手法が、「必要なものを必要な時に、必要な量
だけ生産する」ジャストインタイム(Just In Time)の
概念実現のために、各種生産工場に導入されている。看
板方式に関する先行技術は、たとえば特開平3−142
666号公報などに開示されている。この先行技術に
は、部品工場と組立工場との間で、組立工場で組立てる
製品の需要変動等で部品需要が変動するとき、組立工場
で使用した部品を必ずしも直ぐ部品工場に注文しない発
注形態をとるように、ジャストインタイムの概念を修正
する考え方が示されている。組立工場で使用した部品を
次に使用するまでに時間があくような場合には、使用し
た部品を直ぐに発注してしまうと、完成された部品が納
入されて、次に組立に使用するまでに保管しておく必要
が生じ、仕掛り品を貯めないというジャストインタイム
の考え方に反してしまうからである。
2. Description of the Related Art Conventionally, in order to realize the concept of Just In Time, a production management method called "Kanban system""produces what is needed, when it is needed and in the required amount". It has been installed in various production plants. The prior art relating to the signboard system is disclosed in, for example, Japanese Patent Laid-Open No. 3-142.
It is disclosed in Japanese Patent No. 666. This prior art has an ordering form in which the parts used in the assembly factory are not necessarily immediately ordered to the parts factory when the demand for the parts assembled in the assembly factory fluctuates between the parts factory and the assembly factory. As is the case, the idea of modifying the just-in-time concept is presented. If it takes time to use the parts used in the assembly plant next time, if you order the used parts immediately, the completed parts will be delivered and you will be able to use them for the next assembly. This is because it is necessary to keep it, which violates the just-in-time concept of not storing work-in-process.

【0003】生産工場で、実質的にジャストインタイム
の考え方を実践するためには、種々に変動する生産計画
に対して、きめ細かに対応し、納期を厳守して効率よく
生産を進めなければならなくなってきている。納期を考
慮した現実的な生産計画を作成することに関する先行技
術は、たとえば特開2000−254838号公報など
に開示されている。この先行技術では、製品の生産要求
であるオーダー毎に、投入予定時刻と納期との間に通過
工程を割り付け、オーダー毎の納期に対する投入予定時
刻の余裕に応じて通過工程での待ち時間を調整するよう
にしている。
In order to substantially practice the just-in-time concept in a production factory, it is necessary to respond to various fluctuating production plans in detail and strictly adhere to the delivery date for efficient production. It's gone. Prior art relating to creating a realistic production plan in consideration of delivery date is disclosed in, for example, Japanese Patent Laid-Open No. 2000-254838. In this prior art, a passing process is allocated between a scheduled input time and a delivery date for each order that is a product production request, and the waiting time in the passing process is adjusted according to the margin of the scheduled input time with respect to the delivery date for each order. I am trying to do it.

【0004】[0004]

【発明が解決しようとする課題】生産工場では、一般に
複数の工程を経て生産対象品の生産が行われる。多種少
量生産品が多いようなときには、生産単位が比較的小さ
くなり、段取替えなどの生産準備に要する時間が多くな
って、生産効率が低下する。さらに、生産に支障が生じ
る可能性も高くなる。個々の工程などに障害が生じて
も、全体として納期を守ることができるようにするため
には、生産工程への投入は、納期に対して一定の日数を
見込んで余裕を保たせて行い、生産現場のスキルに期待
して納期の確保を図っているのが現状である。したがっ
て、現状のジャストインタイムでの生産は、生産対象品
を造り始める投入時期の制御に留まり、しかも納期を守
るために余裕が多くなり、投入時点から納期までの製造
リードタイムが長くなったり、生産現場での調整で製造
リードタイムがばらついてしまっている。
In a production factory, a product to be produced is generally produced through a plurality of steps. When there are many types of small-lot production products, the production unit becomes relatively small, the time required for production preparation such as setup change becomes long, and the production efficiency decreases. Furthermore, there is a high possibility that production will be hindered. Even if failures occur in individual processes, etc., in order to be able to keep the delivery date as a whole, input into the production process with a certain number of days for the delivery date, keeping a margin, The current situation is to ensure delivery time by expecting the skills of the production site. Therefore, the current just-in-time production is limited to the control of the input time to start the production of the product, and there is more room to keep the delivery time, and the manufacturing lead time from the input time to the delivery time becomes longer, The manufacturing lead time has fluctuated due to adjustments at the production site.

【0005】本発明の目的は、製造リードタイムを短縮
し、納期に合わせて生産対象品を製造することができる
生産進度管理方法および装置を提供することである。
An object of the present invention is to provide a production progress management method and apparatus capable of shortening the manufacturing lead time and manufacturing an object product to be produced in accordance with a delivery date.

【0006】[0006]

【課題を解決するための手段】本発明は、複数の工程で
順次生産を行う工場で、要求された製造納期を満たすた
めの生産進度管理方法において、各工程での先行または
遅れを、要求された製造納期に対する絶対的な納期余裕
度として評価し、納期余裕度に基づいて、生産対象品の
最適投入時期および各工程での生産優先度を調整するこ
とを特徴とする生産進度管理方法である。
SUMMARY OF THE INVENTION The present invention is a factory that sequentially manufactures a plurality of processes, and in a production progress management method for satisfying a required production deadline, advance or delay in each process is required. The production progress management method is characterized in that it is evaluated as an absolute delivery margin with respect to the production delivery deadline, and the optimal input timing of the product to be produced and the production priority in each process are adjusted based on the delivery deadline. .

【0007】本発明に従えば、順次生産を行う複数の工
程で、各工程毎に、先行または遅れを、要求された製造
納期に対する絶対的な納期余裕度として評価し、納期余
裕度に基づいて生産対象品の最適投入時期および各工程
での生産優先度を調整するので、各工程での生産を適正
な余裕度で行うことができ、工程間や生産対象品間の調
整で納期を守る余地があり、しかも過度の余裕度で、製
造リードタイムを延長して仕掛りを増やすような事態を
避けることができる。
According to the present invention, in a plurality of processes for sequentially producing, the advance or delay is evaluated for each process as an absolute delivery time margin with respect to the required delivery time, and based on the delivery time margin. Since the optimum input timing of the product to be produced and the production priority in each process are adjusted, it is possible to perform production in each process with an appropriate margin, and there is room to protect the delivery date by adjusting between processes and products to be produced. In addition, it is possible to avoid a situation where the manufacturing lead time is extended and work in progress is increased with an excessive margin.

【0008】また本発明で、前記納期余裕度は、予め定
める時期毎に再計算し、前記各工程での生産優先度は、
再計算された納期余裕度に基づいて、精度を高めるよう
に補正することを特徴とする。
In the present invention, the delivery allowance is recalculated at each predetermined time, and the production priority in each process is
It is characterized in that the correction is performed so as to improve the accuracy based on the recalculated delivery time allowance.

【0009】本発明に従えば、生産対象品が生産に投入
された後でも、予め定める時間や生産数などの一定時期
毎に納期余裕度が再計算され、再計算された納期余裕度
に基づいて各工程での生産優先度の精度が高められる。
これによって、生産の実状に合わせて各工程での納期余
裕度に基づく生産が行われ、複数の生産対象品を順次生
産するような場合でも、全体として納期を守るように生
産進度の管理を行うことができる。
According to the present invention, even after the product to be produced is put into production, the delivery allowance is recalculated at regular intervals such as a predetermined time and the number of products to be produced, and based on the recalculated delivery allowance. The accuracy of the production priority in each process is improved.
As a result, the production is performed based on the delivery margin in each process according to the actual situation of production, and even when a plurality of products to be produced are sequentially produced, the production progress is managed to keep the delivery date as a whole. be able to.

【0010】また本発明で、前記納期余裕度は、先行度
と遅延度との両側から判断し、予め定める適正な範囲に
調整することを特徴とする。
Further, the present invention is characterized in that the delivery allowance is determined from both sides of the leading degree and the delay degree, and is adjusted to an appropriate predetermined range.

【0011】本発明に従えば、納期余裕度が先行側に大
きくなりすぎて製造リードタイムが長くなってしまう事
態と、納期余裕度が遅延側に小さくなりすぎて、納期を
守ることができなくなる事態とを、納期余裕度を適正な
範囲に調整して、避けることができる。
According to the present invention, the delivery time margin becomes too large on the leading side and the manufacturing lead time becomes long, and the delivery time margin becomes too small on the delay side, making it impossible to keep the delivery time. You can avoid the situation by adjusting the delivery margin to an appropriate range.

【0012】また本発明で、前記納期余裕度は、前記各
工程毎に、製造納期として指定される時刻までの保有時
間から、不就業時間および計画的ライン停止時間を含む
生産ライン停止時間を差引いた保有工数で、該保有工数
から、該工程以降での生産に必要となる残必要生産時間
として想定される生産ライン効率、および段取替えを含
む生産準備時間を加えた生産必要時間と、製造完了時点
から顧客への供給までに必要な一定の余裕時間とを差引
いた余裕工数を、除算して算出することを特徴とする。
Further, in the present invention, the delivery time margin is obtained by subtracting the production line stop time including the non-working time and the planned line stop time from the holding time up to the time designated as the manufacturing delivery time for each of the processes. In addition to the required man-hours, the required production time including the production line efficiency estimated from the remaining man-hours as the remaining required production time required for the production after the process, and the production preparation time including the setup change, and the production completion It is characterized in that it is calculated by dividing the spare man-hours obtained by subtracting a certain spare time required from the point of time until the supply to the customer.

【0013】本発明に従えば、各生産対象品について、
各工程毎に余裕工数を保有工数で除算して納期余裕度を
算出する。保有工数は、製造納期として指定される時刻
までの保有時間から、不就業時間および計画的ライン停
止時間を含む生産ライン停止時間を差引いた時間であ
り、余裕工数は、保有工数から、該工程以降での生産に
必要となる残必要生産時間として想定される生産ライン
効率、および段取替えを含む生産準備時間を加えた生産
必要時間と、製造完了時点から顧客への供給までに必要
な一定の余裕時間とを差引いた時間である。納期余裕度
は割合として算出されるので、適正な範囲を割合として
評価することができ、各工程での余裕度を、工程毎の必
要時間の大きさによらずに評価することができる。
According to the present invention, for each product to be produced,
The delivery man-hours are calculated by dividing the man-hours for each process by the man-hours owned. The number of man-hours held is the time obtained by subtracting the production line stop time including non-working time and planned line stop time from the holding time until the time specified as the manufacturing delivery date. Production line efficiency, which is assumed to be the remaining production time required for production at the factory, and production preparation time including production preparation time including setup changes, and a certain margin required from the completion of production to the supply to customers. It is the time minus the time. Since the delivery allowance is calculated as a ratio, an appropriate range can be evaluated as a ratio, and the allowance in each process can be evaluated regardless of the amount of time required for each process.

【0014】また本発明は、予め設定される初期生産単
位を、最小生産可能単位まで段階的に分割して、前記製
造納期に対する前記納期余裕度を向上させることを特徴
とする。
Further, the present invention is characterized in that the preset initial production unit is stepwise divided into minimum producible units to improve the delivery margin with respect to the production delivery date.

【0015】本発明に従えば、予め設定される初期生産
単位であるロットの大きさを、生産可能な最小単位であ
る最小生産可能単位にまで段階的に分割するので、納期
を早めるように、生産優先度を制御することが可能にな
る。
According to the present invention, the size of a lot, which is a preset initial production unit, is divided step by step into the minimum producible unit which is the minimum producible unit, so that the delivery date can be expedited. It becomes possible to control the production priority.

【0016】また本発明は、複数の生産対象品につい
て、前記複数の工程で順次生産を行う生産順序シーケン
スを、前後する生産対象品の同一性を段取替えに必要な
作業因子によって評価し、前記生産優先度の調整を、段
取替え時間を含む生産準備時間を最小化するように行う
ことを特徴とする。
Further, according to the present invention, a production sequence sequence in which a plurality of production target products are sequentially produced in the plurality of steps is evaluated by the work factors necessary for setup change to determine the identity of the production target products before and after the production sequence sequence. The production priority is adjusted so that the production preparation time including the setup change time is minimized.

【0017】本発明に従えば、前後する生産対象品につ
いて、複数の工程で順次生産を行う生産順序シーケンス
を、前後する生産対象品の同一性を段取替えに必要な作
業因子によって評価し、生産優先度の調整を、段取替え
時間を含む生産準備時間を最小化するように行う。生産
対象品の同一性を評価した生産優先度の調整を行うの
で、段取替え時間を含む生産準備時間を容易に最小化す
ることができる。
According to the present invention, a production sequence sequence in which sequential production is carried out in a plurality of steps is performed for a product to be produced before and after, and the identity of the product to be produced before and after is evaluated by a work factor required for setup change to produce the product. The priority is adjusted so as to minimize the production preparation time including the setup change time. Since the production priority is adjusted by evaluating the identity of the product to be produced, the production preparation time including the setup change time can be easily minimized.

【0018】また本発明は、稼働時間帯が長い工程から
短い工程へ移行する際の途中仕掛り量を、稼働時間帯が
短い工程の操業開始時点で最大とし、操業終了時点で最
小となるように、仕掛り量制御を行うことを特徴とす
る。
Further, according to the present invention, the amount of in-process products in transition from a process having a long operating time zone to a process having a short operating time zone is maximized at the start of the operation of the process having a short operating time zone and minimized at the end of the operation. In addition, the in-process amount control is performed.

【0019】本発明に従えば、1日16時間勤務による
工程から8時間勤務による工程など、稼働時間帯が長い
工程から短い工程へ移行する際の途中仕掛り量を、稼働
時間帯が短い工程の操業開始時点で最大とし、操業終了
時点で最小となるように、仕掛り量制御を行うので、高
額設備の投資回収などを図るために稼働時間帯が長い工
程が混じっていても、納期余裕度を適正に保って生産を
行うことができる。
According to the present invention, the amount of work in progress when a process having a long operating time period shifts to a process having a short operating time period, such as a process operating from 16 hours a day to a process operating from 8 hours a day. The amount of work-in-process is controlled so that it is maximized at the start of the operation and minimized at the end of the operation, so even if there are processes with long operating hours mixed in order to recover the investment of expensive equipment, It is possible to maintain the proper production.

【0020】さらに本発明は、複数の工程で順次生産を
行う工場で、要求された製造納期を満たすための生産進
度管理を行うために使用する装置であって、各工程での
先行または遅れを、要求された製造納期に対する絶対的
な納期余裕度として評価する納期余裕度評価手段と、納
期余裕度に基づいて、生産対象品の最適投入時期および
各工程での生産優先度を調整して、進度予測を行う進度
予測手段と、表示画面上の一つの軸を経過時間軸とし、
他の軸を工程順方向として、経過時間軸上に現在時刻を
表す基準点を設定し、時間軸上で該基準点よりも過去側
に、進度の実績を表示し、時間軸上で該基準点よりも未
来側に、現在時刻までの進度実測に基づいて、進度予測
手段で予測される進度予測を表示する進度表示手段とを
含むことを特徴とする生産進度管理装置である。
Furthermore, the present invention is an apparatus used for controlling the production progress in order to meet the required production deadline in a factory which sequentially manufactures in a plurality of processes, and the advance or delay in each process By adjusting the delivery time margin evaluation means that evaluates as an absolute delivery time margin against the required manufacturing delivery time and the optimal input time of the product to be produced and the production priority in each process based on the delivery time margin, A progress predicting means for predicting progress and one axis on the display screen as an elapsed time axis,
Set the reference point that represents the current time on the elapsed time axis with the other axis as the process forward direction, display the progress record on the past side of the reference point on the time axis, and display the progress on the time axis. The production progress management device is characterized in that it includes a progress display unit for displaying a progress prediction predicted by the progress prediction unit on the future side of the point based on the progress measurement up to the present time.

【0021】本発明に従えば、複数の工程で順次生産を
行う工場で、要求された製造納期を満たすための生産進
度管理を行うために使用する生産進度管理装置は、納期
余裕度評価手段と、進度予測手段と、進度表示手段とを
含む。納期余裕度評価手段は、各工程での先行または遅
れを、要求された製造納期に対する絶対的な納期余裕度
として評価する。進度予測手段は、納期余裕度に基づい
て、生産対象品の最適投入時期および各工程での生産優
先度を調整して、進度予測を行う。進度表示手段は、表
示画面上の一つの軸を経過時間軸とし、他の軸を工程順
方向として、経過時間軸上に現在時刻を表す基準点を設
定し、時間軸上で該基準点よりも過去側に、進度の実績
を表示し、時間軸上で該基準点よりも未来側に、現在時
刻までの進度実測に基づいて、進度予測手段で予測され
る進度予測を表示する。進度予測手段の表示画面で、現
在時刻を基準に、時間軸の過去側では進度の実績が表示
され、時間軸の未来側では予測進度が表示されるので、
進度の管理を行うための判りやすい表示を行うことがで
きる。表示を見ながら、納期余裕度についての総合的な
判断を行い、製造リードタイムを短縮する方向に、管理
の精度を高めることができる。
According to the present invention, the production progress management device used for performing the production progress management for satisfying the required production delivery time in a factory that sequentially produces in a plurality of processes is a delivery time allowance evaluating means. , A progress predicting means and a progress displaying means. The delivery time allowance evaluation means evaluates the lead or delay in each process as an absolute delivery time allowance with respect to the requested production delivery time. The progress prediction means adjusts the optimum input timing of the product to be produced and the production priority in each process based on the delivery margin, and performs the progress prediction. The progress display means sets one axis on the display screen as the elapsed time axis and the other axis as the process forward direction, and sets a reference point representing the current time on the elapsed time axis, and sets the reference point from the reference point on the time axis. Also displays the progress record on the past side, and displays the progress prediction predicted by the progress prediction unit on the time axis on the future side of the reference point based on the progress measurement up to the current time. On the display screen of the progress predicting means, the past progress on the time axis is displayed on the basis of the current time, and the progress progress is displayed on the future side on the time axis.
An easy-to-understand display for managing the progress can be displayed. It is possible to improve the management accuracy in the direction of shortening the manufacturing lead time by making a comprehensive judgment on the delivery margin while looking at the display.

【0022】また本発明は、前記複数の工程に対して、
製造納期が指定される複数の生産対象品についての必要
生産準備時間および必要生産時間を算出する時間算出手
段と、該複数の生産対象品について、前記進度予測手段
で予測される進度予測に基づいて、予想生産開始時刻お
よび予測生産終了時刻を算出する時刻算出手段と、時間
算出手段によって算出される必要生産準備時間および必
要生産時間、時刻算出手段によって算出される予想生産
開始時刻および予測生産終了時刻、ならびに、前記納期
余裕度評価手段によって評価される納期余裕度の現在状
態を含む詳細値を、生産対象品の生産順序とともに表示
して、生産指示を行う生産指示手段とをさらに含むこと
を特徴とする。
Further, the present invention is directed to the plurality of steps,
A time calculating means for calculating the required production preparation time and the required production time for a plurality of production target products for which a production delivery date is designated, and based on the progress prediction predicted by the progress prediction means for the plurality of production target products. A time calculation means for calculating the expected production start time and the estimated production end time, a required production preparation time and a required production time calculated by the time calculation means, and an estimated production start time and an estimated production end time calculated by the time calculation means And a production instruction means for displaying a detailed value including the current state of the delivery time margin evaluated by the delivery time margin evaluation means together with the production order of the products to be produced, and giving a production instruction. And

【0023】本発明に従えば、生産指示手段は、複数の
工程に対し、必要生産準備時間および必要生産時間と、
予想生産開始時刻および予測生産終了時刻と、納期余裕
度の現在状態を含む詳細値を、生産対象品の生産順序と
ともに表示して、生産指示を行うので、複数の生産対象
品をそれぞれ納期に間に合せて投入する管理を容易に行
うことができる。
According to the present invention, the production instructing means provides the required production preparation time and the required production time for a plurality of processes,
The estimated production start time and estimated production end time, and detailed values including the current state of the delivery allowance are displayed together with the production order of the products to be produced, and the production instruction is given. It is possible to easily carry out the management in accordance with.

【0024】また本発明で、前記生産指示手段は、前記
納期余裕度評価手段によって評価される納期余裕度に基
づいて、納期余裕度が適正値よりも小さい生産対象品に
対しては、事前に必要となる準備作業を抽出し、先行す
る生産指示を与える生産対象品についての指示順序の間
に割込み作業として作業指示を行うことを特徴とする。
Further, according to the present invention, the production instructing means may preliminarily check, based on the delivery time allowance evaluated by the delivery time allowance evaluating means, for a product to be produced whose delivery time allowance is smaller than an appropriate value. It is characterized in that necessary preparatory work is extracted, and a work instruction is given as an interrupt work during an instruction sequence for a production target product to which a preceding production instruction is given.

【0025】本発明に従えば、納期余裕度が小さい生産
対象品に対して、事前に準備作業を行うので、納期遅れ
が生じないように生産を行うことができる。
According to the present invention, since preparatory work is performed in advance for a product to be produced having a small delivery allowance, production can be performed without delay in delivery.

【0026】また本発明で、前記進度表示手段は、前記
納期余裕度を前記工程毎に、予め定める図形の大きさで
表示することを特徴とする。
Further, in the invention, it is preferable that the progress display means displays the delivery allowance in a predetermined size of a graphic for each of the steps.

【0027】本発明に従えば、納期余裕度が工程毎に予
め定める図形、たとえば円や正方形などの大きさで表示
されるので、進度表示手段から納期余裕度を容易に読取
ることができる。
According to the present invention, the delivery allowance is displayed in the shape predetermined for each process, for example, the size of a circle or a square, so that the delivery allowance can be easily read from the progress display means.

【0028】また本発明で、前記進度表示手段は、前記
納期余裕度の段階を予め色の変化に対応付けておき、前
記納期余裕度評価手段によって評価される納期余裕度を
前記工程毎に、該色で表示することを特徴とする。
In the present invention, the progress display means associates the stage of the delivery time allowance with the color change in advance, and the delivery time allowance evaluated by the delivery time allowance evaluating means is set for each of the steps. It is characterized by displaying in the color.

【0029】本発明に従えば、納期余裕度が段階的に、
予め定める色の変化で表示されるので、進度表示手段か
ら納期余裕度を容易に読取ることができる。
According to the present invention, the delivery allowance is stepwise,
Since it is displayed with a predetermined color change, the delivery margin can be easily read from the progress display means.

【0030】また本発明で、前記進度表示手段は、前記
納期余裕度評価手段によって評価される納期余裕度が無
くなり、前記要求される製造納期が満たされないと予測
される工程に対して、納期余裕度を予め定める色で表示
することを特徴とする。
Further, in the present invention, the progress display means is provided with a delivery time margin for a process in which the delivery time margin evaluated by the delivery time margin evaluation means is exhausted and the required manufacturing delivery time is not satisfied. The feature is that the degree is displayed in a predetermined color.

【0031】本発明に従えば、納期余裕度が予め定める
色で表示されると、納期余裕度が無くなり、要求される
製造納期が満たされないと予測される工程であることが
判りやすく表示され、対策の必要性を認識させる警告と
することができる。
According to the present invention, when the delivery time allowance is displayed in a predetermined color, the delivery time allowance is exhausted, and it is displayed in an easy-to-understand manner as a process in which it is predicted that the required production delivery time will not be met. It can be a warning to recognize the necessity of measures.

【0032】また本発明で、前記進度表示手段は、前記
納期余裕度評価手段によって評価される納期余裕度が無
くなり、前記要求される製造納期が満たされないと予測
される工程に対して、納期余裕度を時間的に変化する形
態で表示することを特徴とする。
Further, according to the present invention, the progress display means is provided with a delivery time margin for a process in which the delivery time margin evaluated by the delivery time margin evaluation means is exhausted and the required manufacturing delivery time is not satisfied. The feature is that the degree is displayed in a form that changes with time.

【0033】本発明に従えば、納期余裕度が時間的に変
化する形態、たとえば点滅などで表示されると、納期余
裕度が無くなり、要求される製造納期が満たされないと
予測される工程であることが判りやすく表示され、対策
の必要性を認識させる警告とすることができる。
According to the present invention, when the delivery margin is displayed in a form that changes with time, such as blinking, it is predicted that the delivery margin will be exhausted and the required manufacturing delivery deadline will not be met. It can be displayed in an easy-to-understand manner and can be used as a warning to recognize the necessity of measures.

【0034】また本発明で、前記進度表示手段は、各生
産対象品について、前記複数の工程のうちの最初の工程
に投入する時点で前記進度予測手段によって予測される
進度と、予め定める一定時間毎に集計される実績値との
差を、該一定時間毎の変遷状態として表示する機能を備
えることを特徴とする。
Further, in the present invention, the progress display means, for each product to be produced, the progress predicted by the progress prediction means at the time of introducing the product into the first step of the plurality of steps, and a predetermined constant time. It is characterized in that it has a function of displaying a difference from the actual value summed up for each as a transitional state for each fixed time.

【0035】本発明に従えば、各生産対象品について、
投入時点での生産完了予測値と、一定時間毎に集計され
ていく実績値との差を、一定時間毎の変遷状態として表
示するので、工程の進度の変遷状態を判りやすく閲覧す
ることが可能になる。
According to the present invention, for each product to be produced,
Since the difference between the predicted value of production completion at the time of input and the actual value that is aggregated at fixed time intervals is displayed as the transition status at fixed time intervals, it is possible to browse the transition status of the process progress in an easy-to-understand manner. become.

【0036】また本発明で、前記進度表示手段は、前記
時間軸上で前記基準点を過去側にシフトすることによっ
て、過去の実績データを表示する機能を備えることを特
徴とする。
Further, according to the present invention, the progress display means is provided with a function of displaying past performance data by shifting the reference point to the past side on the time axis.

【0037】本発明に従えば、進度表示手段で過去の実
績データを閲覧し、進度の実績を容易に把握することが
可能になる。
According to the present invention, it is possible to browse past performance data by the progress display means and easily grasp the progress performance.

【0038】また本発明で、前記進度表示手段は、前記
時間軸上で前記基準点を未来側にシフトすることによっ
て、未来の投入予定および生産シミュレーション結果を
表示する機能を備えることを特徴とする。
Further, in the present invention, the progress display means is provided with a function of displaying a future supply schedule and a production simulation result by shifting the reference point to the future side on the time axis. .

【0039】本発明に従えば、進度表示手段で未来の投
入予定および生産シミュレーション結果を閲覧可能とな
り、進度の予測を容易に把握することが可能になる。
According to the present invention, it is possible to browse future supply schedules and production simulation results by the progress display means, and it is possible to easily grasp the progress prediction.

【0040】[0040]

【発明の実施の形態】図1は、本発明の実施の一形態で
ある生産進度管理方法の基本的な考え方を示す。図1
(a)に示すように、生産対象品が複数の工程を順次経
て、納期時刻に間に合うように生産する必要がある場
合、現状では間に合わない事態を避けるため、図1
(b)に示すように、納期に対して一定の日数を見込ん
で投入し、あとは現場スキルで制御している。このた
め、たとえば2日で完成するリードタイムが2日の生産
対象品であっても、1日の余裕を見込んでリードタイム
3日として投入している。生産が順調に進めば、納期に
対して1日早く生産が完了し、1日は在庫状態となって
しまう。なお、本実施形態では、電子機器の生産を例と
して説明するけれども、本発明の考え方はどのような生
産対象品にも適用することができる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows a basic concept of a production progress management method according to an embodiment of the present invention. Figure 1
As shown in (a), when it is necessary to produce the product to be produced in sequence through a plurality of processes in time to meet the delivery time, in order to avoid the situation which is not in time, the situation shown in FIG.
As shown in (b), a certain number of days is expected for the delivery date, and the input is made. For this reason, for example, even if the product to be produced has a lead time of 2 days, which is completed in 2 days, the lead time is set to 3 days in anticipation of an extra day. If production goes smoothly, production will be completed one day earlier than the delivery date and inventory will be left for one day. It should be noted that although the production of the electronic device is described as an example in the present embodiment, the idea of the present invention can be applied to any product to be produced.

【0041】本実施形態では、図1(c)に示すよう
に、適正な余裕を見込んだ理想工程を設定して生産対象
品を投入し、途中の工程では次工程以降の納期余裕度を
予測評価し、理想時刻に近づくようにフィードバック制
御する。納期余裕度は、理想工程よりも進めば大きくな
り、遅れれば小さくなる。納期余裕度が小さくなるとき
は、他の生産対象品で納期余裕度が大きいものよりも優
先度を高めて工程に投入し、進度の遅れを補正する。納
期余裕度が大きくなるときは、他の生産対象品で納期余
裕度が小さいものを優先して工程に投入し、複数の生産
対象品が全体的に納期を満たすように調整する。
In the present embodiment, as shown in FIG. 1 (c), an ideal process with an appropriate allowance is set and a product to be produced is introduced, and in the middle of the process, the delivery margin after the next process is predicted. Evaluate and perform feedback control so that it approaches the ideal time. The delivery allowance becomes larger if it goes beyond the ideal process and becomes smaller if it goes behind. When the delivery allowance becomes smaller, the priority of the other production target products having a larger delivery allowance is given to the process, and the progress is corrected. When the delivery allowance becomes large, other products to be produced, which have a small delivery allowance, are preferentially put into the process, and adjustments are made so that the plurality of products to be produced satisfy the delivery as a whole.

【0042】納期余裕度は、たとえば5段階で評価す
る。最も遅れている段階を「1」、最も進んでいる段階
を「5」として、中間の「3」の段階に留まるようにフ
ィードバック制御する。もし、途中で納期余裕度が
「2」以下になると、進度が遅れ始めていると判断し、
次工程に優先的に投入して進度を早める。途中で納期余
裕度が「4」以上になると、進度が進み始めていると判
断し、次工程では他の生産対象品を優先して投入して進
度を遅らせることを可能と判断する。
The delivery allowance is evaluated in, for example, five levels. Feedback control is performed so that the stage that is most delayed is "1" and the stage that is most advanced is "5" so as to stay in the intermediate stage "3". If the delivery margin becomes "2" or less on the way, it is judged that the progress is starting to be delayed,
Priority is given to the next process to accelerate the progress. When the delivery allowance becomes "4" or more in the middle, it is determined that the progress is starting to progress, and it is possible to delay the progress by prioritizing the introduction of other products to be produced in the next process.

【0043】図2は、生産工場で生産対象品が流れる形
態の例を示す。図2は(a)は、組立工程など、専用化
された工程の形態を示す。組立工程などでは、複数の工
程がラインを構成し、投入順が完成順と一致する。この
ような専用化された工程では、最終工程での完成品に対
応する「かんばん」を先頭工程に戻せば、ジャストイン
タイムでの生産が可能となる。図2(b)は、マシン工
程のようなセル生産方式の形態を示す。各種自動化され
た生産装置を用いるマシン工程で、特に、多種少量生産
を行うような場合は、各工程の稼働率を上げるため、複
数種類の生産対象品を混在して生産する。このため、投
入順と完成順とは必ずしも一致しない。現状の「かんば
ん」方式では、セル生産方式に対し、最終工程で生産完
了したら先頭工程に「かんばん」を戻してつくり始める
投入指示を行うだけである。本発明は、工程間の進度を
調整することができるので、図2(a)に示すような専
用化された工程ばかりではなく、図2(b)に示すよう
なセル生産方式にも充分に適用することができる。図2
(b)でも、特定の生産対象品について考えれば、図1
(a)に示すような一連の工程で順次生産されていると
考えることができるからである。
FIG. 2 shows an example of the form in which the products to be produced flow in the production factory. FIG. 2A shows a form of a dedicated process such as an assembling process. In the assembly process and the like, a plurality of processes form a line, and the order of input matches the order of completion. In such a dedicated process, just returning the "Kanban" corresponding to the finished product in the final process to the first process enables just-in-time production. FIG. 2B shows a form of a cell production system such as a machine process. In a machine process using various automated production devices, particularly in the case of performing a variety of small-volume production, a plurality of types of production target products are mixed and produced in order to increase the operation rate of each process. Therefore, the input order and the completion order do not always match. In the current “Kanban” method, the cell production method is simply instructed to put back the “Kanban” in the first step after the completion of production in the final step and start manufacturing. Since the present invention can adjust the progress between processes, it is not only applicable to the dedicated process as shown in FIG. 2 (a) but also to the cell production system as shown in FIG. 2 (b). Can be applied. Figure 2
Even in (b), considering a specific product to be produced,
This is because it can be considered that the products are sequentially manufactured in the series of steps shown in (a).

【0044】「かんばん」などの生産指示単位には、製
造完了納期が、日、時刻の単位で記載される。この納期
時刻から起算して、現在の生産途中状態での納期余裕度
を、残生産必要時間、工程生産余裕度などから一定時間
毎、または生産実績の変化毎に再評価を行う。生産優先
度、生産単位、最適仕掛り量などを検出して、進度補正
を行い、納期時刻までの生産過程において一定の納期余
裕度を維持しながら、生産制御を行う。また、生産が確
定し、監視対象となっている工程群の先頭工程に投入さ
れた生産対象品についていは、最終製造完了場面までを
予測し、生産開始予測時刻、各時点での納期余裕度を含
めて、進度制御状態を管理するためのモニタ画面が提供
される。この納期余裕度を、生産計画に依存しない絶対
的な先行/遅れ度の評価尺度として、生産制御の起点と
する。これによって、生産日程計画が存在しない「かん
ばん納入方式契約」に基づく後補充方式主体の生産工場
でも、全体的な生産進度管理を可能にすることができ
る。
In the production instruction unit such as "Kanban", the production completion delivery date is described in units of day and time. Starting from this delivery time, the delivery allowance in the current state of intermediate production is re-evaluated at regular time intervals based on the remaining production required time, the process production allowance, etc., or every time the production results change. Production priority, production unit, optimal work-in-progress amount, etc. are detected, the progress is corrected, and production control is performed while maintaining a certain delivery margin during the production process up to the delivery time. In addition, for products to be produced that have been finalized and have been put into the first process of the monitored process group, the final production completion scene is predicted, and the estimated production start time and the delivery margin at each point A monitor screen for managing the progress control state is provided. This delivery time margin is used as the starting point of production control, as an absolute evaluation scale of advance / delay that does not depend on the production plan. As a result, it is possible to manage the entire production progress even in a production factory mainly based on the post-replenishment system based on the “Kanban delivery system contract” for which no production schedule plan exists.

【0045】すなわち、本実施形態は、順次生産を行う
複数の工程で、各工程毎に、先行または遅れを、要求さ
れた製造納期に対する絶対的な納期余裕度として評価
し、納期余裕度に基づいて生産対象品の最適投入時期お
よび各工程での生産優先度を調整するので、各工程での
生産を適正な余裕度で行うことができ、工程間や生産対
象品間の調整で納期を守る余地があり、しかも過度の余
裕度で、製造リードタイムを延長して仕掛りを増やすよ
うな事態を避けることができる。
That is, in the present embodiment, the advance or delay is evaluated as the absolute delivery time margin with respect to the required production delivery time for each process in a plurality of production steps, and based on the delivery time allowance. By adjusting the optimal input timing of production target products and the production priority in each process, it is possible to carry out production in each process with an appropriate margin, and the delivery date is protected by adjustment between processes and production target products. It is possible to avoid the situation where the manufacturing lead time is extended and the number of work in process is increased with a room and an excessive margin.

【0046】また本実施形態では、納期余裕度は、予め
定める時期毎に再計算し、各工程での生産優先度は、再
計算された納期余裕度に基づいて、精度を高めるように
補正する。したがって、生産対象品が生産に投入された
後でも、予め定める時間や生産数などの一定時期毎に納
期余裕度が再計算され、再計算された納期余裕度に基づ
いて各工程での生産優先度の精度が高められる。これに
よって、生産の実状に合わせて各工程での納期余裕度に
基づく生産が行われ、複数の生産対象品を順次生産する
ような場合でも、全体として納期を守るように生産進度
の管理を行うことができる。
Further, in this embodiment, the delivery allowance is recalculated at each predetermined time, and the production priority in each process is corrected so as to improve the accuracy based on the recalculated delivery allowance. . Therefore, even after the product to be produced has been put into production, the delivery time allowance is recalculated at regular intervals such as the predetermined time and the number of productions, and the production priority in each process is prioritized based on the recalculated delivery time allowance. The degree of precision is improved. As a result, the production is performed based on the delivery margin in each process according to the actual situation of production, and even when a plurality of products to be produced are sequentially produced, the production progress is managed to keep the delivery date as a whole. be able to.

【0047】また納期余裕度は、先行度と遅延度との両
側から判断し、予め定める適正な範囲に調整する。これ
によって、納期余裕度が先行側に大きくなりすぎ、製造
リードタイムが長くなって、在庫が多くなってしまう事
態と、納期余裕度が遅延側に小さくなりすぎて、納期を
守ることができなくなってしまう事態とを、避けること
ができる。
The delivery allowance is determined from both sides of the leading degree and the delay degree, and adjusted within a predetermined appropriate range. Due to this, the delivery margin becomes too large on the leading side, the manufacturing lead time becomes long, and the inventory increases, and the delivery margin becomes too small on the delay side, making it impossible to keep the delivery date. It is possible to avoid the situation that happens.

【0048】図3は、図1の実施形態の生産進度管理方
法を実行するために必要な装置構成の例を示す。複数の
工程には、工程側端末装置1,2,3,4,…がそれぞ
れ設置され、管理側端末装置10からの生産指示を受
け、生産対象品の生産を進め、実績を順次管理側端末装
置10に報告する。工程側端末装置1,2,3,4,…
および管理側端末装置10は、それぞれコンピュータ装
置であり、予め設定されるプログラムに従って、生産進
度管理のための処理を行う。
FIG. 3 shows an example of a device configuration necessary for executing the production progress management method of the embodiment shown in FIG. Process side terminal devices 1, 2, 3, 4, ... Are respectively installed in a plurality of processes, receive a production instruction from the management side terminal device 10 and proceed with the production of the product to be produced, and the results are sequentially managed by the management side terminal. Report to device 10. Process side terminal devices 1, 2, 3, 4, ...
The management side terminal device 10 and the management side terminal device 10 are computer devices, respectively, and perform processing for production progress management according to a preset program.

【0049】管理側端末装置10は、プログラム動作に
よって、納期余裕度評価手段11、進度予測手段12、
進度表示手段13、時間算出手段14、時刻算出手段1
5および生産指示手段16として機能する。工程側端末
装置1,2,3,4,…と管理側端末装置10との間
は、LAN(Local Area Network)20を介して、情報
通信可能に接続されている。管理側端末装置10の生産
指示手段16は、LAN20を介して生産指示を各工程
側端末装置1,2,3,4,…に与える。各工程側端末
装置1,2,3,4,…からの生産実績データは、LA
N10を介して管理側端末装置10に集められる。
The management-side terminal device 10 executes the program operation to determine the due date margin evaluation means 11, the progress prediction means 12,
Progress indicator 13, time calculator 14, time calculator 1
5 and the production instruction means 16. The process side terminal devices 1, 2, 3, 4, ... And the management side terminal device 10 are connected via a LAN (Local Area Network) 20 so that information communication is possible. The production instruction means 16 of the management side terminal device 10 gives a production instruction to each process side terminal device 1, 2, 3, 4, ... Via the LAN 20. The production performance data from each process side terminal device 1, 2, 3, 4, ...
It is collected in the management side terminal device 10 via N10.

【0050】時間算出手段14は、複数の工程に対し
て、製造納期が指定される複数の生産対象品についての
必要生産準備時間および必要生産時間を算出する。時刻
算出手段15は、複数の生産対象品について、進度予測
手段12で予測される進度予測に基づいて、予想生産開
始時刻および予測生産終了時刻を算出する。生産指示手
段16は、複数の工程に対し、必要生産準備時間および
必要生産時間と、予想生産開始時刻および予測生産終了
時刻と、納期余裕度の現在状態を含む詳細値を、生産対
象品の生産順序とともに表示して、生産指示を行うの
で、複数の生産対象品をそれぞれ納期に間に合せて投入
する管理を容易に行うことができる。
The time calculating means 14 calculates the required production preparation time and the required production time for a plurality of production target products for which the manufacturing deadlines are designated, for a plurality of processes. The time calculation means 15 calculates the predicted production start time and the predicted production end time for the plurality of production target products based on the progress prediction predicted by the progress prediction means 12. The production instructing means 16 produces the detailed values including the required production preparation time and the required production time, the estimated production start time and the estimated production end time, and the present state of the delivery schedule margin for the plurality of processes, in order to produce the production target product. Since it is displayed together with the order and the production instruction is given, it is possible to easily carry out the management of putting a plurality of products to be produced in time for each delivery date.

【0051】本実施形態の生産進度管理では、本来「か
んばん方式」で前提にしているような、毎日、比較的安
定な生産量を生産している生産対象品ばかりではなく、
生産量の変動が大きい生産対象品をも有効に管理するこ
とを目標としている。近年、多品種少量生産化が進み、
生産量の変動は大きくなってきており、そのような変動
に対応して有効な生産進度管理を行うことが課題となっ
ているからである。また、量産が安定して行われるよう
な生産対象品でも、量産に先立つ試作や、量産を終了し
て生産を収束する時期の生産では、生産量の変動は大き
くなる。
In the production progress management of the present embodiment, not only the production target products that produce a relatively stable production amount every day as originally assumed in the "Kanban system" but also
The goal is to effectively manage the products that are subject to large fluctuations in production. In recent years, high-mix, low-volume production has progressed,
This is because the fluctuation of the production amount is increasing, and it is a subject to effectively manage the production progress in response to such fluctuation. Further, even for a product to be produced for which mass production is performed stably, the fluctuation of the production amount becomes large in the trial production before the mass production or the production when the mass production is finished and the production is converged.

【0052】図4は、毎日安定に量産する毎日生産品
と、生産量の変動が大きい間欠生産品とで、現状の製造
リードタイムを測定した結果の例を示す。間欠生産品で
は、製造リードタイムは広い範囲に分布しているので、
長時間側の部分を短時間側に移行させるように改善すれ
ばよいことが判る。
FIG. 4 shows an example of the result of measuring the current manufacturing lead time for the daily production product that is stably mass-produced every day and the intermittent production product in which the production amount varies greatly. With intermittent products, the manufacturing lead time is distributed over a wide range, so
It can be seen that it suffices to improve so that the part on the long side shifts to the short side.

【0053】図5は、勤務形態の違いが仕掛在庫量の変
動に及す影響を示す。一般に、自動機などを設置してい
るマシン工程などでは、高額の設備投資を回収するため
に、設備の稼働時間を長くして、他の工程と勤務形態が
異なることがある。すなわち、複数の作業シフトを作業
者が交代して設備を稼働させ、1日の不就業時間を短く
している。設備によっては、24時間連続稼働させる場
合もある。本実施形態では、たとえば1日2交代である
2直で勤務するマシン工程では、1直で勤務する基板工
程や組立工程で不就業時間となっている時間帯にも生産
を行い、1直の生産開始時に仕掛在庫量が最大Maxと
なり、1直の生産終了時に仕掛在庫量が最小Minとな
るような管理を行う。このような管理は、従来の「かん
ばん」の流通量で管理する手法では適切に行うことがで
きない。現在の仕掛量を常に監視して制御する必要があ
る。
FIG. 5 shows the influence of the difference in work style on the fluctuation of the in-process inventory quantity. Generally, in a machine process or the like in which an automatic machine or the like is installed, in order to recover a large amount of capital investment, the operating time of the facility may be lengthened and the work form may differ from other processes. That is, the workers take turns to operate the equipment by changing a plurality of work shifts to shorten the non-working time per day. Depending on the equipment, it may be operated continuously for 24 hours. In the present embodiment, for example, in a machine process that works in two shifts, which is two shifts per day, production is performed even during a non-working time in a board process or an assembly process that works in one shift. Management is performed such that the in-process inventory amount becomes the maximum Max at the start of production and the in-process inventory amount becomes the minimum Min at the end of the production immediately after. Such management cannot be appropriately performed by the conventional method of managing the distribution amount of “Kanban”. It is necessary to constantly monitor and control the current work in progress.

【0054】たとえば、1日16時間勤務による2直の
工程から8時間勤務による1直の工程など、稼働時間帯
が長い工程から短い工程へ移行する際の途中仕掛り量
を、稼働時間帯が短い工程の操業開始時点で最大とし、
操業終了時点で最小となるように、仕掛り量制御を行う
ことによって、高額設備の投資回収などを図るために稼
働時間帯が長い工程が混じっていても、納期余裕度を適
正に保って生産を行うことができる。
For example, the amount of work in progress when a process having a long operating time shifts from a process having a long operating time to a process having a short operating time, such as a process of two shifts working 16 hours a day to a process of one shift working eight hours Maximum at the start of operation in a short process,
By controlling the amount of work in progress so that it becomes the minimum at the end of operation, even if there are processes with long operating hours mixed in order to recover the investment of high-priced equipment etc. It can be performed.

【0055】図6は、本実施形態で「かんばん」を利用
して、工程間での生産進度を管理する考え方を示す。各
工程で、左側の立体の大きさは生産能力を示し、右側の
立体の大きさは必要な仕掛在庫量を示す。ただし、本実
施形態での「かんばん」は、図3の生産指示手段16か
らLAN20を介して各工程側端末装置1,2,3,
4,…に与えられる電子的な指令である。図6(a)
は、各工程で同等の工程サイクルタイムで生産が行わ
れ、理想の後補充方式が適用される場合を示す。各工程
で生産が終了した分だけ「かんばん」を先行する工程に
戻し、次の生産に必要な生産対象品を受取るようにすれ
ばよい。図6(b)は、工程サイクルタイムに差がある
場合であり、サイクルタイムが長い8分の工程の次の3
分の工程では、仕掛在庫を多くしておく必要がある。図
6(c)は、稼働時間差がある場合であり、2直の工程
の後の1直の工程では、仕掛在庫を多くしておく必要が
ある。図6(d)は製造ロット差が有る場合であり、製
造ロットが小さい工程では、仕掛在庫を多くしておく必
要がある。
FIG. 6 shows the concept of managing the production progress between processes by using "kanban" in this embodiment. In each process, the size of the solid on the left side shows the production capacity, and the size of the solid on the right side shows the required in-process inventory amount. However, the “Kanban” in this embodiment is the process-side terminal devices 1, 2, 3, from the production instruction means 16 of FIG.
It is an electronic command given to 4, .... Figure 6 (a)
Shows the case where the production is performed at the same process cycle time in each process and the ideal post-replenishment method is applied. It is sufficient to return the "Kanban" to the preceding process by the amount of production completed in each process and receive the product to be produced for the next production. FIG. 6B shows the case where there is a difference in the process cycle time, and the following 3 steps of the process with a long cycle time of 8 minutes are performed.
In the minute step, it is necessary to keep a large amount of in-process inventory. FIG. 6C shows a case where there is a difference in operating time, and it is necessary to increase the in-process inventory in the first shift process after the second shift process. FIG. 6D shows the case where there is a difference in the production lot, and it is necessary to increase the in-process inventory in the process in which the production lot is small.

【0056】図7および図8は、図3の進度表示手段1
3に表示される進捗管理モニタ画面の例を示す。横方向
のX軸を時間軸とし、時間軸上の中央付近に現在時刻に
相当する基準点をとる。基準点よりも過去側には進度の
実績データを表示し、未来側には進度の予測を表示す
る。縦方向のY軸は、工程の流れを示し、各工程では、
生産対象品毎に時間の割当てを帯状の時間区分として表
示する。図7では、特定の生産対象品についての時間区
分を、工程間を曲線で結ぶことによって、得られる生産
進捗曲線を表示している状態を示す。
7 and 8 show the progress indicator 1 of FIG.
3 shows an example of the progress management monitor screen displayed in 3. The horizontal X-axis is used as a time axis, and a reference point corresponding to the current time is set near the center on the time axis. Progress data is displayed on the past side of the reference point, and progress prediction is displayed on the future side. The vertical Y axis shows the flow of the process, and in each process,
The allocation of time for each product to be produced is displayed as a strip of time. FIG. 7 shows a state in which a production progress curve obtained by connecting the time divisions of a specific production target product with a curve is displayed.

【0057】すなわち、進度表示手段13は、表示画面
上の一つの軸であるX軸を経過時間軸とし、他の軸であ
るY軸を工程順方向として、経過時間軸上に現在時刻を
表す基準点を設定し、時間軸上で該基準点よりも過去側
に、進度の実績を表示し、時間軸上で該基準点よりも未
来側に、現在時刻までの進度実測に基づいて、進度予測
手段で予測される進度予測を表示する。進度予測手段の
表示画面で、現在時刻を基準に、時間軸の過去側では進
度の実績が表示され、時間軸の未来側では予測進度が表
示されるので、進度の管理を行うための判りやすい表示
を行うことができる。表示を見ながら、納期余裕度につ
いての総合的な判断を行い、製造リードタイムを短縮す
る方向に、管理の精度を高めることができる。
That is, the progress display means 13 represents the present time on the elapsed time axis with the X axis, which is one axis on the display screen, as the elapsed time axis and the other axis, the Y axis, as the process forward direction. Set a reference point, display the progress record on the time axis in the past of the reference point, and display the progress record on the time axis in the future of the reference point, based on the progress measurement up to the current time. The progress prediction predicted by the prediction means is displayed. On the display screen of the progress predicting means, the actual progress is displayed on the past side of the time axis and the predicted progress is displayed on the future side of the time axis based on the current time, which is easy to understand for managing the progress. The display can be done. It is possible to improve the management accuracy in the direction of shortening the manufacturing lead time by making a comprehensive judgment on the delivery margin while looking at the display.

【0058】図8は、図7の生産進捗曲線と理想曲線と
を示し、生産進捗曲線に対しては納期余裕度も示す。理
想曲線は、生産対象品を先頭の工程に投入する際に予測
した曲線であり、生産進捗曲線は実績と、実績に基づく
予測とを組合わせて得られる。
FIG. 8 shows the production progress curve and the ideal curve of FIG. 7, and also shows the delivery margin for the production progress curve. The ideal curve is a curve predicted when the product to be produced is put into the first step, and the production progress curve is obtained by combining the actual results and the prediction based on the actual results.

【0059】進度表示手段13では、各生産対象品につ
いて、複数の工程のうちの最初の工程に投入する時点で
前記進度予測手段によって予測される進度と、予め定め
る一定時間毎に集計される実績値との差を、該一定時間
毎の変遷状態として表示する機能を備える。各生産対象
品について、投入時点での生産完了予測値と、一定時間
毎に集計されていく実績値との差を、一定時間毎の変遷
状態として表示するので、工程の進度の変遷状態を判り
やすく閲覧することが可能になる。
In the progress display means 13, for each product to be produced, the progress predicted by the progress prediction means at the time of inputting into the first step of the plurality of steps, and the record of totaling at a predetermined fixed time. It is provided with a function of displaying a difference from the value as a transitional state for each fixed time. For each production target product, the difference between the predicted production completion value at the time of input and the actual value that is aggregated at fixed time intervals is displayed as a transitional status at fixed time intervals, so the progress status of the process can be known. It becomes possible to browse easily.

【0060】また進度表示手段は、時間軸上で基準点を
過去側にシフトすることによって、過去の実績データを
表示する機能を備える。進度表示手段13で過去の実績
データを閲覧し、進度の実績を容易に把握することが可
能になる。
Further, the progress display means has a function of displaying past performance data by shifting the reference point to the past side on the time axis. It is possible to browse past performance data on the progress display means 13 and easily grasp the progress performance.

【0061】また進度表示手段13は、時間軸上で基準
点を未来側にシフトすることによって、未来の投入予定
および生産シミュレーション結果を表示する機能を備え
る。進度表示手段13で未来の投入予定および生産シミ
ュレーション結果を閲覧可能となり、進度の予測を容易
に把握することが可能になる。
Further, the progress display means 13 has a function of displaying the future supply schedule and production simulation result by shifting the reference point to the future side on the time axis. The progress display means 13 makes it possible to browse future injection schedules and production simulation results, and it is possible to easily grasp the progress prediction.

【0062】なお、「R工程」は、電子機器の両面配線
基板に対し、裏面側への表面実装部品のリフロー方式の
半田付けによる実装工程を示す。「F工程」は、両面配
線基板に対する表面側への実装工程を示す。「P工程」
は、ボンドチップ工程を示す。「縦」は、接続リードが
一方に出ている縦型部品の取付工程を示す。「横」は、
接続リードが両側に出ている横型部品の取付工程を示
す。
The "R process" indicates a mounting process by soldering the surface mounting component to the back surface side of the electronic device on the back side by reflow soldering. “F process” indicates a mounting process on the front surface side of the double-sided wiring board. "P process"
Shows a bond chip process. “Vertical” indicates a process of attaching a vertical component in which a connecting lead is provided on one side. "Horizontal" is
The process of attaching a horizontal component with connection leads on both sides is shown.

【0063】図9は、図7および図8に示すようなモニ
タ画面を利用して進度管理を手順を示す。ステップs0
から手順を開始し、ステップs1では納期時刻を決定す
る。ステップs2では、納期時刻に間に合うような各工
程での投入指示計画を立てる。ステップs3では、各工
程での納期余裕度を評価する。ステップs4では、納期
に間に合わない欠品が発生するか否かを判断し、発生す
ると判断されるときは、ステップs5でアラームによる
警告を与える。アラームに応じて、ステップs6で投入
指示計画が修正されると、ステップs3に戻る。
FIG. 9 shows the procedure of progress management using the monitor screens shown in FIGS. 7 and 8. Step s0
The procedure is started from, and the delivery time is determined in step s1. At step s2, an input instruction plan for each process is made in time for the delivery time. In step s3, the delivery allowance in each process is evaluated. At step s4, it is judged whether or not a shortage of goods which is not in time for delivery occurs, and when it is judged that there is a shortage, a warning by an alarm is given at step s5. When the closing instruction plan is corrected in step s6 according to the alarm, the process returns to step s3.

【0064】ステップs4で欠品発生がないと判断され
るときは、ステップs7で仕掛在庫が削減可能か否かを
判断する。リードタイムが長く、削減可能と判断される
ときは、ステップs8で投入指示計画を補正し、ステッ
プs3に戻る。ステップs7で仕掛在庫の削減が可能で
ないと判断されるときは、ステップs9で投入指示計画
に従った投入指示を各工程に与える。この投入指示は、
前述の理想曲線に相当する。
If it is determined in step s4 that there is no shortage, it is determined in step s7 whether the in-process inventory can be reduced. When it is determined that the lead time is long and the lead time can be reduced, the closing instruction plan is corrected in step s8, and the process returns to step s3. When it is determined in step s7 that it is not possible to reduce the in-process inventory, in step s9, an input instruction according to the input instruction plan is given to each process. This input instruction is
It corresponds to the above-mentioned ideal curve.

【0065】生産対象品が投入されると、ステップs1
0で、生産実績の監視が行われる。ステップs11で
は、投入された生産対象品について、全工程での生産が
完了しているか否かを判断する。完了していないと判断
されるときは、ステップs12で、生産実績に基づき、
残っている工程での余裕度の評価が行われる。ステップ
s13では余裕度に基づいて、計画の投入指示の補正が
必要か否かを判断する。補正が必要と判断されるとき
は、ステップs14で余裕度が適正な値となるように調
整する進度補正が行われ、ステップs10に戻る。ステ
ップs13で、投入指示の補正が不要と判断されるとき
は、補正を行わずにステップs10に戻る。ステップs
11で全行程の生産が完了していると判断されるとき
は、ステップs15で手順を終了する。
When the product to be produced is input, step s1
At 0, the production performance is monitored. In step s11, it is determined whether or not the production target product that has been input is completed in all the processes. When it is determined that the process is not completed, in step s12, based on the production results,
The margin is evaluated in the remaining steps. In step s13, it is determined whether or not it is necessary to correct the plan input instruction based on the margin. When it is determined that the correction is necessary, the progress correction for adjusting the margin to an appropriate value is performed in step s14, and the process returns to step s10. When it is determined in step s13 that the correction of the closing instruction is unnecessary, the correction is not performed and the process returns to step s10. Step s
When it is determined in 11 that the production of the entire process is completed, the procedure ends in step s15.

【0066】図9の手順では、ステップs1からステッ
プs6までの第1の段階で、納期決定および余裕評価に
よる現状値の把握と分析とを行い、納期に間に合わない
ような事態を避ける監視モードの制御を行っている。ス
テップs7およびステップs8の第2の段階では、余裕
が過大で仕掛り在庫が以上に増大するのを補正する補正
制御モードを行う。ステップs9からステップs13ま
での第3の段階では、最適な投入状態でリードタイムが
短縮されるような投入制御モードが行われる。
In the procedure of FIG. 9, in the first stage from step s1 to step s6, the present value is grasped and analyzed by the delivery date determination and the margin evaluation, and the monitoring mode in which the situation that the delivery date cannot be met is avoided. We are in control. In the second stage of step s7 and step s8, a correction control mode for correcting the excessive increase in the in-process inventory due to the excessive margin is performed. In the third stage from step s9 to step s13, a closing control mode is performed in which the lead time is shortened in the optimum closing state.

【0067】図10は、図9に示す3段階の手順を適用
して、適正な納期余裕度の制御を行う例を示す。まず納
期時刻を決定し、監視モードで投入指示を作成する。納
期に間に合わない欠品が生じる場合を除外し、仕掛りを
1日から0日に短縮する補正制御モードを実行した後、
投入制御モードを実行して、リードタイム1.5日を実
現することができる。
FIG. 10 shows an example in which the three-stage procedure shown in FIG. 9 is applied to control an appropriate delivery margin. First, the delivery time is determined, and the closing instruction is created in the monitoring mode. After executing the correction control mode that shortens the work in process from 1 day to 0 days, excluding the case where out-of-stock items that are not in time for delivery occur
A lead time of 1.5 days can be realized by executing the closing control mode.

【0068】なお、進度表示手段13は、納期余裕度を
工程毎に、予め定める図形の大きさ、たとえば円や正方
形などの大きさで表示させることができる。これによっ
て、進度表示手段13から納期余裕度を容易に読取るこ
とができる。
The progress display means 13 can display the delivery allowance for each process in a predetermined graphic size, for example, a size of a circle or a square. As a result, the delivery allowance can be easily read from the progress display unit 13.

【0069】また、進度表示手段13では、納期余裕度
の段階を予め色の変化に対応付けておき、納期余裕度評
価手段11によって評価される納期余裕度を工程毎に、
色の変化で表示することもできる。納期余裕度が段階的
に、予め定める色の変化で表示されれば、進度表示手段
13から納期余裕度を容易に読取ることができる。
In the progress display means 13, the stage of the delivery time allowance is associated with the color change in advance, and the delivery time allowance evaluated by the delivery time allowance evaluating means 11 is set for each process.
It can also be displayed by changing the color. If the delivery allowance is displayed stepwise with a predetermined color change, the delivery allowance can be easily read from the progress display unit 13.

【0070】また進度表示手段13は、納期余裕度評価
手段11によって評価される納期余裕度が無くなり、要
求される製造納期が満たされないと予測される工程に対
して、納期余裕度を予め定める色、たとえば赤色で表示
することもできる。納期余裕度が予め定める色で表示さ
れると、納期余裕度が無くなり、要求される製造納期が
満たされないと予測される工程であることが判りやすく
表示され、対策の必要性を認識させる警告とすることが
できる。
Further, the progress display means 13 is a color for predetermining a delivery time allowance for a process in which the delivery time allowance evaluated by the delivery time allowance evaluating means 11 is exhausted and the required manufacturing delivery time is not satisfied. It can also be displayed in red, for example. When the delivery time allowance is displayed in a predetermined color, the delivery time allowance is exhausted, and it is displayed in an easy-to-understand manner as a process in which it is predicted that the required manufacturing delivery time will not be met, and a warning is displayed to recognize the necessity of countermeasures. can do.

【0071】また進度表示手段13は、納期余裕度評価
手段11によって評価される納期余裕度が無くなり、要
求される製造納期が満たされないと予測される工程に対
して、納期余裕度を時間的に変化する点滅などの形態で
表示することもできる。納期余裕度が時間的に変化する
形態、たとえば点滅などで表示されると、納期余裕度が
無くなり、要求される製造納期が満たされないと予測さ
れる工程であることが判りやすくなる。
Further, the progress display means 13 temporally sets the delivery time allowance for the process in which the delivery time allowance evaluated by the delivery time allowance evaluating means 11 is exhausted and the required manufacturing delivery time is not satisfied. It can also be displayed in the form of changing blinking. When the delivery allowance is displayed in a form that changes with time, for example, by blinking, the delivery allowance disappears, and it is easy to understand that this is a process in which it is predicted that the required manufacturing delivery cannot be met.

【0072】図11は、特定の工程について、緊急品の
生産を割当てる考え方を示す。納期余裕度が小さい生産
対象品は、優先度のレベルであるLV値が1となり、す
でに指示されている投入順序に割込んで投入される。こ
れによって、図10に示すような進度予測で、余裕度が
小さくなった工程についての補正を行い、適正な余裕度
に回復させるための生産指示を行うことができる。
FIG. 11 shows the concept of allocating the production of emergency products for a specific process. The production target product having a small delivery allowance has an LV value of 1, which is a priority level, and is interrupted and injected in the instructing order. As a result, with the progress prediction as shown in FIG. 10, it is possible to perform the correction for the process in which the margin becomes small and to give the production instruction for recovering to the proper margin.

【0073】このような生産指示は、納期余裕度評価手
段11によって評価される納期余裕度に基づいて、納期
余裕度が適正値よりも小さい生産対象品に対しては、事
前に必要となる準備作業を抽出し、先行する生産指示を
与える生産対象品についての指示順序の間への割込みと
して行われる。納期余裕度が小さい生産対象品に対し
て、事前に準備作業を行うので、納期遅れが生じないよ
うに生産を行うことができる。
Based on the delivery allowance evaluated by the delivery allowance evaluation means 11, such a production instruction is required in advance for a product to be produced with a delivery allowance smaller than an appropriate value. It is done as an interrupt into the ordering sequence for the product to be produced that extracts the work and gives the preceding production instruction. Since preparation work is performed in advance for a product to be produced that has a small delivery allowance, it is possible to perform production without delay in delivery.

【0074】図12は、図10に示すような納期余裕度
の制御を行うためのアルゴリズム構成要素を示す。アル
ゴリズムの主要な構成要素は、次のように評価される。
まず、投入指示のスケジューリングは、起点となる該当
かんばんの前工程完了実績または予測を明確にする必要
がある。前工程完了予想時刻は、次の(1)式で算出す
ることができる。 前工程完了予想時刻=前工程開始予想時刻+前工程の必要生産時間 …(1)
FIG. 12 shows algorithm components for controlling the delivery allowance as shown in FIG. The main components of the algorithm are evaluated as follows.
First, in the scheduling of the input instruction, it is necessary to clarify the previous process completion record or forecast of the relevant kanban that is the starting point. The estimated time of completion of the previous process can be calculated by the following equation (1). Expected time to complete the previous process = Expected time to start the previous process + Required production time for the previous process (1)

【0075】たとえば、前工程のサイクルタイムが3分
で、生産数が24のときには、3×24=72(分)が
前工程の必要生産時間となる。
For example, when the cycle time of the pre-process is 3 minutes and the number of productions is 24, 3 × 24 = 72 (minutes) is the necessary production time of the pre-process.

【0076】次に納期に対する緊急度合を、かんばん、
またはマガジン収容数あたりで定量的に表す納期余裕度
を、次の(2)式に従って算出する。 納期余裕度=(納期時刻までの保有工数 −最終工程までの必要生産時間 −納期時刻までの予備時間 −不就業時間) ÷(納期時刻までの保有工数−不就業時間) …(2)
Next, the urgency of the delivery date, Kanban,
Alternatively, the delivery allowance, which is quantitatively expressed per the number of magazines accommodated, is calculated according to the following equation (2). Delivery time margin = (Man-hours held by delivery time-Required production time until final process-Preparatory time by delivery time-Nonworking time) ÷ (Man-hours held by delivery time-Unworking time) (2)

【0077】たとえば、納期は出荷用のトラック便の出
発時刻に設定され、出荷便時刻までの保有工数が20時
間、出荷前予備時間が2時間、不就業時間が5時間であ
るとする。必要サイクルタイムが4分で、24台生産
し、標準稼働率が80%であるときには、必要生産時間
は4×24÷0.8=120(分)=2(時間)とな
る。したがって、納期余裕度は、(20−9)÷(20
−5)=0.73=73(%)となる。
For example, it is assumed that the delivery date is set to the departure time of a truck for shipping, the number of man-hours held by the shipping time is 20 hours, the pre-shipment spare time is 2 hours, and the non-working time is 5 hours. When the required cycle time is 4 minutes, 24 units are produced, and the standard operation rate is 80%, the required production time is 4 × 24 ÷ 0.8 = 120 (minutes) = 2 (hours). Therefore, the delivery margin is (20-9) ÷ (20
-5) = 0.73 = 73 (%).

【0078】すなわち、納期余裕度は、各工程毎に、製
造納期として指定される時刻までの保有時間から、不就
業時間および計画的ライン停止時間を含む生産ライン停
止時間を差引いた保有工数によって、その保有工数から
その工程以降での生産に必要となる残必要生産時間とし
て想定される生産ライン効率、および段取替えを含む生
産準備時間を加えた生産必要時間と、製造完了時点から
顧客への供給までに必要な一定の余裕時間とを差引いた
余裕工数を、除算して算出する。納期余裕度は割合とし
て算出されるので、各工程での余裕度を、工程毎の必要
時間の大きさによらずに評価することができる。
In other words, the delivery time allowance is calculated by holding man-hours obtained by subtracting the production line stop time including the non-working time and the planned line stop time from the holding time up to the time designated as the manufacturing delivery time for each process. Production line efficiency that is assumed as the remaining production time required for production after that process from the number of man-hours held, and production preparation time including production preparation time including setup change, and supply to customers from the time production is completed It is calculated by dividing the man-hours that are obtained by subtracting a certain margin time required up to. Since the delivery allowance is calculated as a ratio, the allowance in each process can be evaluated regardless of the size of the required time for each process.

【0079】納期余裕度は、百分率表示での緊急度変換
テーブルとして示すように、たとえば5段階の緊急度に
変換することができる。この緊急度は、図1や図10に
示すような5段階の納期余裕度と同等である。また、図
11に示すように、緊急品として割込みを行う際の評価
尺度となるレベルLVに対応している。
The delivery date allowance can be converted into, for example, five levels of urgency, as shown by the urgency conversion table in percentage display. This urgency level is equivalent to the five levels of delivery allowance as shown in FIGS. Further, as shown in FIG. 11, it corresponds to the level LV that is an evaluation scale when interrupting as an emergency item.

【0080】次に次工程の稼働時間帯に対する調整可能
度合として、かんばん、またはマガジン収容数あたりの
調整余裕度を次の(3)式に従って算出する。調整余裕
度は、順序調整やロット形成での調整可能度合を定量的
に表す。 調整余裕度=(次工程生産可能時刻までの余裕工数−不就業時間) ÷事項底での必要生産時間 …(3)
Next, as the degree of adjustment with respect to the operating time zone of the next process, the adjustment allowance per kanban or the number of magazines accommodated is calculated according to the following equation (3). The adjustment allowance quantitatively represents the degree of adjustability in order adjustment and lot formation. Adjustment allowance = (margin man-hours until next process production available time-non-working time) / required production time at item bottom (3)

【0081】調整余裕度が大きいときは、予め設定され
る初期生産単位であるロットの大きさを、生産可能な最
小単位である最小生産可能単位にまで段階的に分割し
て、納期を早めるように、生産優先度を制御することが
可能になる。
When the adjustment allowance is large, the size of a lot, which is a preset initial production unit, is divided into the minimum producible unit, which is the minimum producible unit, in stages, so that the delivery date is expedited. Moreover, it becomes possible to control the production priority.

【0082】次に、生産負荷時間の精度向上のために、
標準段取替え時間を、次の(4)式に従って計算する。 段取替時間=部品交換時間 +基板幅調整時間 +メタルマスク交換時間 +プログラム切換時間 +初品確認時間 −外段取時間 …(4)
Next, in order to improve the accuracy of the production load time,
The standard setup change time is calculated according to the following equation (4). Setup change time = Parts exchange time + Substrate width adjustment time + Metal mask exchange time + Program switching time + Initial product confirmation time-External setup time (4)

【0083】前後する生産対象品について、複数の工程
で順次生産を行う生産順序シーケンスを、前後する生産
対象品の同一性を段取替えに必要な作業因子によって評
価し、生産優先度の調整を、段取替え時間を含む生産準
備時間を最小化するように行う。生産対象品の同一性を
評価した生産優先度の調整を行うので、段取替え時間を
含む生産準備時間を容易に最小化することができる。
The production sequence sequence in which the production target products before and after are sequentially produced in a plurality of processes is evaluated by the work factor necessary for the setup change to determine the identity of the production target products before and after, and the production priority is adjusted by The production preparation time including the setup change time should be minimized. Since the production priority is adjusted by evaluating the identity of the product to be produced, the production preparation time including the setup change time can be easily minimized.

【0084】また本発明で、前記進度表示手段は、前記
納期余裕度を前記工程毎に、予め定める図形の大きさで
表示することを特徴とする。
Further, in the invention, it is preferable that the progress display means displays the delivery allowance with a predetermined size of a figure for each of the steps.

【0085】図13および図14は、納期余裕度および
調整余裕度の計算結果の例をそれぞれ示す。これらの計
算結果を用いて、生産開始時刻の動的再計算を行うこと
ができる。
13 and 14 show examples of calculation results of the delivery margin and the adjustment margin, respectively. Using these calculation results, it is possible to dynamically recalculate the production start time.

【0086】[0086]

【発明の効果】以上のように本発明によれば、順次生産
を行う複数の工程で、要求された製造納期に対する絶対
的な納期余裕度に基づいて生産対象品の最適投入時期お
よび各工程での生産優先度を調整するので、各工程での
生産を適正な余裕度で行うことができ、総合的に製造リ
ードタイムを短縮することができる。
As described above, according to the present invention, in a plurality of processes in which production is sequentially performed, the optimum input time of the product to be produced and each process are determined based on the absolute delivery time margin with respect to the required production delivery time. Since the production priority is adjusted, the production in each process can be performed with an appropriate margin, and the manufacturing lead time can be shortened overall.

【0087】また本発明によれば、生産対象品が生産に
投入された後でも、予め定める時間や生産数などの一定
時期毎に納期余裕度が再計算され、生産の実状に合わせ
て各工程での納期余裕度に基づく生産が行われ、複数の
生産対象品を順次生産するような場合でも、全体として
納期を守り、かつ製造リードタイムを短縮することがで
きるように生産進度の管理を行うことができる。
Further, according to the present invention, even after the product to be produced is put into production, the delivery allowance is recalculated at regular intervals such as a predetermined time and the number of productions, and each process is adjusted according to the actual situation of production. Even if the production is performed based on the delivery time margin in the case of multiple production target products in sequence, the production progress is managed so that the delivery time can be kept as a whole and the manufacturing lead time can be shortened. be able to.

【0088】また本発明によれば、納期余裕度を適正な
範囲に調整し、納期を満たす範囲で製造リードタイムを
短縮することができる。
Further, according to the present invention, it is possible to adjust the delivery time allowance within an appropriate range and shorten the manufacturing lead time within the range where the delivery time is satisfied.

【0089】また本発明によれば、各生産対象品につい
て、各工程毎に余裕工数を保有工数で除算して納期余裕
度を割合として算出し、適正な範囲か否かを、工程毎の
必要時間の大きさによらずに評価することができる。
Further, according to the present invention, for each product to be produced, the spare man-hour for each process is divided by the possessed man-hour to calculate the delivery time allowance as a ratio, and it is necessary to determine whether it is within an appropriate range for each process. It can be evaluated regardless of the amount of time.

【0090】また本発明によれば、初期生産単位である
ロットの大きさを、生産可能な最小単位である最小生産
可能単位にまで段階的に分割して、納期を早めるよう
に、生産優先度を制御することができる。
Further, according to the present invention, the size of a lot, which is an initial production unit, is divided into the minimum producible unit which is the minimum producible unit step by step, and the production priority is set so that the delivery date is accelerated. Can be controlled.

【0091】また本発明によれば、前後する生産対象品
の同一性を段取替えに必要な作業因子によって評価し、
生産対象品の同一性を評価した生産優先度の調整を行う
ので、段取替え時間を含む生産準備時間を容易に最小化
することができる。
Further, according to the present invention, the identity of the products to be produced before and after is evaluated by the work factor necessary for the setup change,
Since the production priority is adjusted by evaluating the identity of the product to be produced, the production preparation time including the setup change time can be easily minimized.

【0092】また本発明によれば、稼働時間帯が長い工
程から短い工程へ移行する際の途中仕掛り量を、稼働時
間帯が短い工程の操業開始時点で最大とし、操業終了時
点で最小となるように、仕掛り量制御を行うので、稼働
時間帯が長い工程が混じっていても、納期余裕度を適正
に保って生産を行うことができる。
Further, according to the present invention, the amount of in-process products in transition from a process having a long operating time zone to a process having a short operating time zone is maximized at the start of operation of the process having a short operation time zone and minimized at the end of operation. As described above, since the amount of work-in-progress is controlled, even if there are processes with long operating hours, production can be performed with an appropriate delivery margin.

【0093】さらに本発明によれば、進度予測手段の表
示画面で、現在時刻を基準に、時間軸の過去側では進度
の実績が表示され、時間軸の未来側では予測進度が表示
されるので、表示を見ながら、納期余裕度についての総
合的な判断を行い、製造リードタイムを短縮する方向
に、管理の精度を高めることができる。
Further, according to the present invention, on the display screen of the progress predicting means, the progress progress is displayed on the past side of the time axis and the predicted progress is displayed on the future side of the time axis with reference to the present time. , It is possible to improve the management accuracy in the direction of shortening the manufacturing lead time by making a comprehensive judgment on the delivery margin while looking at the display.

【0094】また本発明によれば、複数の工程に対し、
必要生産準備時間および必要生産時間と、予想生産開始
時刻および予測生産終了時刻と、納期余裕度の現在状態
を含む詳細値を、生産対象品の生産順序とともに表示し
て、生産指示を行うので、複数の生産対象品をそれぞれ
納期に間に合せて投入する管理を容易に行うことができ
る。
Further, according to the present invention, for a plurality of steps,
The required production preparation time and required production time, the estimated production start time and estimated production end time, and the detailed value including the current state of the delivery allowance are displayed together with the production order of the products to be produced, and the production instruction is given. It is possible to easily perform management to put a plurality of products to be produced in time for each delivery date.

【0095】また本発明によれば、納期余裕度が小さい
生産対象品に対しては、事前に準備作業を行い、納期遅
れが生じないように生産を行うことができる。
Further, according to the present invention, it is possible to perform a preparatory work in advance for a product to be produced with a small delivery allowance so that production can be performed without delay in delivery.

【0096】また本発明によれば、納期余裕度を、工程
毎に、予め定める図形、たとえば円や正方形などの大き
さで表示し、納期余裕度を容易に読取り可能にすること
ができる。
Further, according to the present invention, the delivery allowance can be displayed for each process in a predetermined figure, for example, the size of a circle or a square, so that the delivery allowance can be easily read.

【0097】また本発明によれば、納期余裕度を予め定
める色の変化で段階的に表示するので、進度表示手段か
ら納期余裕度を容易に読取り可能にすることができる。
Further, according to the present invention, since the delivery allowance is displayed stepwise by the change in the predetermined color, the delivery allowance can be easily read from the progress display means.

【0098】また本発明によれば、納期余裕度が無くな
り、要求される製造納期が満たされないと予測される工
程を予め定める色で表示し、対策の必要性を認識させる
ように警告することができる。
Further, according to the present invention, it is possible to display a process in which a margin of delivery date is exhausted and a required production delivery date is not satisfied in a predetermined color, and to warn the user to recognize the necessity of countermeasure. it can.

【0099】また本発明によれば、納期余裕度が無くな
り、要求される製造納期が満たされないと予測される工
程を、点滅などで表示し、対策の必要性を認識させるよ
うに警告することができる。
Further, according to the present invention, it is possible to display a process, which is predicted to be out of the delivery time allowance and the required manufacturing delivery time is not satisfied, by blinking or the like to warn the user to recognize the necessity of the countermeasure. it can.

【0100】また本発明によれば、進度予測手段で、各
生産対象品について、投入時点での生産完了予測値と、
一定時間毎に集計されていく実績値との差を、一定時間
毎の変遷状態として表示して、工程の進度の変遷状態を
判りやす位状態で、閲覧可能にすることができる。
Further, according to the present invention, the progress predicting means, for each product to be produced, the predicted production completion value at the time of introduction,
It is possible to display the difference from the actual value that is aggregated at regular intervals as a transitional state at regular intervals so that the transitional state of the progress of the process can be easily viewed.

【0101】また本発明によれば、進度表示手段で過去
の実績データを閲覧可能にすることができる。
Further, according to the present invention, the past performance data can be browsed by the progress display means.

【0102】また本発明によれば、進度表示手段で未来
の投入予定および生産シミュレーション結果を閲覧可能
にすることができる。
Further, according to the present invention, it is possible to view the future production schedule and production simulation result by the progress display means.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施の一形態である生産進度管理方法
の概略的な考え方を示すグラフである。
FIG. 1 is a graph showing a schematic concept of a production progress management method according to an embodiment of the present invention.

【図2】本発明で生産進度管理の対象となる工程の形態
を示す図である。
FIG. 2 is a diagram showing a form of a process targeted for production progress management in the present invention.

【図3】図1の生産進度管理方法を実行するための装置
の構成を示すブロック図である。
FIG. 3 is a block diagram showing a configuration of an apparatus for executing the production progress management method of FIG.

【図4】本発明で、毎日生産品と間欠生産品とで、製造
リードタイムを改善すべき対象を示すグラフである。
FIG. 4 is a graph showing targets for which the manufacturing lead time should be improved in the daily production product and the intermittent production product according to the present invention.

【図5】本発明で、勤務形態の違いを仕掛在庫量の変化
に反映させる考え方を示す図である。
FIG. 5 is a diagram showing a concept of reflecting a difference in work style in a change in work-in-process inventory according to the present invention.

【図6】本発明の進度管理を行う工程形態の例を示す図
である。
FIG. 6 is a diagram showing an example of a process form for performing progress management of the present invention.

【図7】図3の進度表示手段13に生産進捗曲線を表示
させている表示画面の例を示す図である。
7 is a diagram showing an example of a display screen displaying a production progress curve on a progress display means 13 of FIG.

【図8】図3の進度表示手段13に生産進捗曲線、理想
曲線、および納期余裕度を表示させている表示画面の例
を示す図である。
8 is a diagram showing an example of a display screen displaying a production progress curve, an ideal curve, and a delivery deadline on the progress display means 13 of FIG.

【図9】本発明で、進度管理を行う概略的な手順を示す
フローチャートである。
FIG. 9 is a flowchart showing a schematic procedure for performing progress management in the present invention.

【図10】図9の手順に従う進度管理の例を示す図であ
る。
10 is a diagram showing an example of progress management according to the procedure of FIG.

【図11】本発明の進度管理で、緊急品に対する工程へ
の割込みを示す図である。
FIG. 11 is a diagram showing interruption of a process for an emergency item in the progress management of the present invention.

【図12】本発明で進度管理を行うためのアルゴリズム
構成要素を示す図である。
FIG. 12 is a diagram showing algorithm components for performing progress management in the present invention.

【図13】図12のアルゴリズム構成要素を用いて納期
余裕度を計算した結果の例を示すグラフである。
FIG. 13 is a graph showing an example of a result of calculating a delivery allowance using the algorithm components of FIG.

【図14】図12のアルゴリズム構成要素を用いて調整
余裕度を計算した結果の例を示すグラフである。
FIG. 14 is a graph showing an example of a result of calculating an adjustment allowance using the algorithm components of FIG.

【符号の説明】[Explanation of symbols]

1,2,3,4,… 工程側端末装置 10 管理側端末装置 11 納期余裕度評価手段 12 進度予測手段 13 進度表示手段 14 時間算出手段 15 時刻算出手段 16 生産指示手段 20 LAN 1, 2, 3, 4, ... Process side terminal device 10 Management side terminal device 11 Delivery time margin evaluation means 12 Progress prediction means 13 Progress display means 14 hours calculation means 15 Time calculation means 16 Production instruction means 20 LAN

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小林 和弘 兵庫県神戸市兵庫区御所通1丁目2番28号 富士通テン株式会社内 Fターム(参考) 3C100 AA03 AA05 AA18 AA23 AA24 AA29 AA32 BB04 BB14 BB15 BB31 CC02 DD15    ─────────────────────────────────────────────────── ─── Continued front page    (72) Inventor Kazuhiro Kobayashi             1-228 Goshodori, Hyogo-ku, Kobe-shi, Hyogo               Within Fujitsu Ten Limited F term (reference) 3C100 AA03 AA05 AA18 AA23 AA24                       AA29 AA32 BB04 BB14 BB15                       BB31 CC02 DD15

Claims (17)

【特許請求の範囲】[Claims] 【請求項1】 複数の工程で順次生産を行う工場で、要
求された製造納期を満たすための生産進度管理方法にお
いて、 各工程での先行または遅れを、要求された製造納期に対
する絶対的な納期余裕度として評価し、 納期余裕度に基づいて、生産対象品の最適投入時期およ
び各工程での生産優先度を調整することを特徴とする生
産進度管理方法。
1. In a production progress management method for satisfying a required production delivery date in a factory that sequentially manufactures in a plurality of processes, the lead or delay in each process is an absolute delivery date with respect to the required production delivery date. A production progress management method characterized by evaluating the margin as a margin, and adjusting the optimum input timing of production target products and the production priority in each process based on the delivery margin.
【請求項2】 前記納期余裕度は、予め定める時期毎に
再計算し、 前記各工程での生産優先度は、再計算された納期余裕度
に基づいて、精度を高めるように補正することを特徴と
する請求項1記載の生産進度管理方法。
2. The delivery margin is recalculated at each predetermined time, and the production priority in each process is corrected so as to improve accuracy based on the recalculated delivery margin. The production progress management method according to claim 1, which is characterized in that.
【請求項3】 前記納期余裕度は、先行度と遅延度との
両側から判断し、予め定める適正な範囲に調整すること
を特徴とする請求項1または2記載の生産進度管理方
法。
3. The production progress management method according to claim 1, wherein the delivery allowance is judged from both sides of the advancement and the delay and adjusted within a predetermined appropriate range.
【請求項4】 前記納期余裕度は、前記各工程毎に、 製造納期として指定される時刻までの保有時間から、不
就業時間および計画的ライン停止時間を含む生産ライン
停止時間を差引いた保有工数で、 該保有工数から、該工程以降での生産に必要となる残必
要生産時間として想定される生産ライン効率、および段
取替えを含む生産準備時間を加えた生産必要時間と、製
造完了時点から顧客への供給までに必要な一定の余裕時
間とを差引いた余裕工数を、 除算して算出することを特徴とする請求項1〜3のいず
れかに記載の生産進度管理方法。
4. The delivery time allowance is the number of man-hours held for each of the processes, which is obtained by subtracting the production line stop time including non-working time and planned line stop time from the holding time until the time specified as the manufacturing delivery time. Then, from the man-hours held, the production line efficiency estimated as the remaining production time required for the production after the process, and the production required time including the production preparation time including the setup change, The production progress management method according to any one of claims 1 to 3, wherein the man-hours obtained by subtracting a certain allowance time required for supplying to the product are calculated by division.
【請求項5】 予め設定される初期生産単位を、最小生
産可能単位まで段階的に分割して、前記製造納期に対す
る前記納期余裕度を向上させることを特徴とする請求項
1〜4のいずれかに記載の生産進度管理方法。
5. The preset initial production unit is divided step by step to a minimum producible unit to improve the delivery margin with respect to the production delivery date. The production progress management method described in.
【請求項6】 複数の生産対象品について、前記複数の
工程で順次生産を行う生産順序シーケンスを、前後する
生産対象品の同一性を段取替えに必要な作業因子によっ
て評価し、 前記生産優先度の調整を、段取替え時間を含む生産準備
時間を最小化するように行うことを特徴とする請求項1
〜5のいずれかに記載の生産進度管理方法。
6. The production priority sequence in which a plurality of production target products are sequentially produced in the plurality of processes is evaluated by the work factor required for setup change to determine the identity of the preceding and following production target products, and the production priority is set. 2. The adjustment is performed so as to minimize the production preparation time including the setup change time.
5. The production progress management method according to any one of 5 to 5.
【請求項7】 稼働時間帯が長い工程から短い工程へ移
行する際の途中仕掛り量を、稼働時間帯が短い工程の操
業開始時点で最大とし、操業終了時点で最小となるよう
に、仕掛り量制御を行うことを特徴とする請求項1〜6
のいずれかに記載の生産進度管理方法。
7. The work-in-process is set so that the amount of in-process products during the transition from a process having a long operating time zone to a process having a short operating time zone is maximized at the start of operation of the process having a short operation time zone and minimized at the end of operation. The amount control is performed, and the amount control is performed.
The production progress management method described in any one of.
【請求項8】 複数の工程で順次生産を行う工場で、要
求された製造納期を満たすための生産進度管理を行うた
めに使用する装置であって、 各工程での先行または遅れを、要求された製造納期に対
する絶対的な納期余裕度として評価する納期余裕度評価
手段と、 納期余裕度に基づいて、生産対象品の最適投入時期およ
び各工程での生産優先度を調整して、進度予測を行う進
度予測手段と、 表示画面上の一つの軸を経過時間軸とし、他の軸を工程
順方向として、経過時間軸上に現在時刻を表す基準点を
設定し、時間軸上で該基準点よりも過去側に、進度の実
績を表示し、時間軸上で該基準点よりも未来側に、現在
時刻までの進度実測に基づいて、進度予測手段で予測さ
れる進度予測を表示する進度表示手段とを含むことを特
徴とする生産進度管理装置。
8. A device used to control the production progress to meet a required production deadline in a factory that sequentially manufactures in a plurality of processes, and is required to lead or delay each process. The delivery time margin evaluation means that evaluates the delivery time as an absolute delivery time margin, and based on the delivery time margin, the optimal input time of the product to be produced and the production priority in each process are adjusted to predict the progress. The progress predicting means to be performed and one axis on the display screen as the elapsed time axis, the other axis as the process forward direction, and a reference point representing the current time is set on the elapsed time axis, and the reference point is set on the time axis. The progress display that displays the progress record on the past side and displays the progress prediction predicted by the progress prediction unit on the time axis on the future side of the reference point based on the progress measurement up to the current time. Production progress tube characterized by including means Processing equipment.
【請求項9】 前記複数の工程に対して、製造納期が指
定される複数の生産対象品についての必要生産準備時間
および必要生産時間を算出する時間算出手段と、 該複数の生産対象品について、前記進度予測手段で予測
される進度予測に基づいて、予想生産開始時刻および予
測生産終了時刻を算出する時刻算出手段と、 時間算出手段によって算出される必要生産準備時間およ
び必要生産時間、時刻算出手段によって算出される予想
生産開始時刻および予測生産終了時刻、ならびに、前記
納期余裕度評価手段によって評価される納期余裕度の現
在状態を含む詳細値を、生産対象品の生産順序とともに
表示して、生産指示を行う生産指示手段とをさらに含む
ことを特徴とする請求項8記載の生産進度管理装置。
9. A time calculating means for calculating a required production preparation time and a required production time for a plurality of production target products whose production delivery dates are designated for the plurality of processes, and a plurality of production target products, A time calculation means for calculating an expected production start time and an estimated production end time based on the progress prediction predicted by the progress prediction means, and a necessary production preparation time and a required production time, time calculation means calculated by the time calculation means. The estimated production start time and the estimated production end time calculated by the above, and detailed values including the current state of the delivery schedule margin evaluated by the delivery schedule margin evaluation means are displayed together with the production order of the product to be produced, 9. The production progress management device according to claim 8, further comprising production instruction means for giving an instruction.
【請求項10】 前記生産指示手段は、前記納期余裕度
評価手段によって評価される納期余裕度に基づいて、納
期余裕度が適正値よりも小さい生産対象品に対しては、
事前に必要となる準備作業を抽出し、先行する生産指示
を与える生産対象品についての指示順序の間に割込み作
業として作業指示を行うことを特徴とする請求項9記載
の生産進度管理装置。
10. The production instructing means, on the basis of the delivery time allowance evaluated by the delivery time allowance evaluating means, for the production target product having the delivery time allowance smaller than an appropriate value,
10. The production progress management apparatus according to claim 9, wherein a necessary preparatory work is extracted in advance, and a work instruction is given as an interrupt work during an instruction sequence for a product to be produced which gives a preceding production instruction.
【請求項11】 前記進度表示手段は、前記納期余裕度
を前記工程毎に、予め定める図形の大きさで表示するこ
とを特徴とする請求項8〜10のいずれかに記載の生産
進度管理装置。
11. The production progress management device according to claim 8, wherein the progress display means displays the delivery allowance in each of the steps in a size of a predetermined graphic. .
【請求項12】 前記進度表示手段は、前記納期余裕度
の段階を予め色の変化に対応付けておき、前記納期余裕
度評価手段によって評価される納期余裕度を前記工程毎
に、該色で表示することを特徴とする請求項8〜11の
いずれかに記載の生産進度管理装置。
12. The progress display means associates the stage of the delivery time allowance with a change in color in advance, and the delivery time allowance evaluated by the delivery time allowance evaluating means is indicated by the color for each step. It displays, The production progress management apparatus in any one of Claims 8-11.
【請求項13】 前記進度表示手段は、前記納期余裕度
評価手段によって評価される納期余裕度が無くなり、前
記要求される製造納期が満たされないと予測される工程
に対して、納期余裕度を予め定める色で表示することを
特徴とする請求項11または12記載の生産進度管理装
置。
13. The progress display means preliminarily sets a delivery time allowance for a process in which the delivery time allowance evaluated by the delivery time allowance evaluating means is exhausted and the required manufacturing delivery time is not satisfied. 13. The production progress management device according to claim 11 or 12, wherein the production progress management device is displayed in a defined color.
【請求項14】 前記進度表示手段は、前記納期余裕度
評価手段によって評価される納期余裕度が無くなり、前
記要求される製造納期が満たされないと予測される工程
に対して、納期余裕度を時間的に変化する形態で表示す
ることを特徴とする請求項11〜13のいずれかに記載
の生産進度管理装置。
14. The progress display means sets a delivery time allowance as a time for a process in which the delivery time allowance evaluated by the delivery time allowance evaluation means is exhausted and the required manufacturing delivery time is not satisfied. 14. The production progress management apparatus according to claim 11, wherein the production progress management apparatus displays the production progress management apparatus.
【請求項15】 前記進度表示手段は、各生産対象品に
ついて、前記複数の工程のうちの最初の工程に投入する
時点で前記進度予測手段によって予測される進度と、予
め定める一定時間毎に集計される実績値との差を、該一
定時間毎の変遷状態として表示する機能を備えることを
特徴とする請求項8〜14のいずれかに記載の生産進度
管理装置。
15. The progress display means collects, for each product to be produced, the progress predicted by the progress prediction means at the time when the product is put into the first step of the plurality of steps and a predetermined time interval. 15. The production progress management device according to claim 8, further comprising a function of displaying a difference from the actual result value as a transitional state for each fixed time.
【請求項16】 前記進度表示手段は、前記時間軸上で
前記基準点を過去側にシフトすることによって、過去の
実績データを表示する機能を備えることを特徴とする請
求項8〜15のいずれかに記載の生産進度管理装置。
16. The progress display means has a function of displaying past performance data by shifting the reference point to the past side on the time axis. The production progress management device described in Crab.
【請求項17】 前記進度表示手段は、前記時間軸上で
前記基準点を未来側にシフトすることによって、未来の
投入予定および生産シミュレーション結果を表示する機
能を備えることを特徴とする請求項8〜16のいずれか
に記載の生産進度管理装置。
17. The progress display means has a function of displaying a future supply schedule and a production simulation result by shifting the reference point to the future side on the time axis. The production progress management device according to any one of 1 to 16.
JP2001246610A 2001-08-15 2001-08-15 Product progress management method and device Withdrawn JP2003058228A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001246610A JP2003058228A (en) 2001-08-15 2001-08-15 Product progress management method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001246610A JP2003058228A (en) 2001-08-15 2001-08-15 Product progress management method and device

Publications (1)

Publication Number Publication Date
JP2003058228A true JP2003058228A (en) 2003-02-28

Family

ID=19076120

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001246610A Withdrawn JP2003058228A (en) 2001-08-15 2001-08-15 Product progress management method and device

Country Status (1)

Country Link
JP (1) JP2003058228A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005148940A (en) * 2003-11-12 2005-06-09 Kawasaki Microelectronics Kk Scheduling device
JP2006163676A (en) * 2004-12-06 2006-06-22 Hitachi Medical Corp Method of analyzing medical appliance operation efficiency and system for supporting operation planning
JP2011511385A (en) * 2008-02-07 2011-04-07 アヴラハム ワイ ゴールドラット インスティテュート、リミテッド パートナーシップ Method and system for determining the relative priority of work in progress and narrowing down process improvement targets
JP2013008218A (en) * 2011-06-24 2013-01-10 Mitsubishi Electric Corp Inventory balance management support system
JP2013063585A (en) * 2011-09-16 2013-04-11 Murata Machinery Ltd Filament winding device
JP2015005002A (en) * 2013-06-19 2015-01-08 株式会社神戸製鋼所 Operation support system of in-process material storage facility
JP2015118446A (en) * 2013-12-17 2015-06-25 株式会社神戸製鋼所 Operation information offering system
JP2017207977A (en) * 2016-05-19 2017-11-24 株式会社神戸製鋼所 Production schedule determination apparatus and production schedule determination method
JP2019040345A (en) * 2017-08-24 2019-03-14 株式会社神戸製鋼所 Process management device and method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005148940A (en) * 2003-11-12 2005-06-09 Kawasaki Microelectronics Kk Scheduling device
JP2006163676A (en) * 2004-12-06 2006-06-22 Hitachi Medical Corp Method of analyzing medical appliance operation efficiency and system for supporting operation planning
JP2011511385A (en) * 2008-02-07 2011-04-07 アヴラハム ワイ ゴールドラット インスティテュート、リミテッド パートナーシップ Method and system for determining the relative priority of work in progress and narrowing down process improvement targets
JP2013008218A (en) * 2011-06-24 2013-01-10 Mitsubishi Electric Corp Inventory balance management support system
JP2013063585A (en) * 2011-09-16 2013-04-11 Murata Machinery Ltd Filament winding device
JP2015005002A (en) * 2013-06-19 2015-01-08 株式会社神戸製鋼所 Operation support system of in-process material storage facility
JP2015118446A (en) * 2013-12-17 2015-06-25 株式会社神戸製鋼所 Operation information offering system
JP2017207977A (en) * 2016-05-19 2017-11-24 株式会社神戸製鋼所 Production schedule determination apparatus and production schedule determination method
JP2019040345A (en) * 2017-08-24 2019-03-14 株式会社神戸製鋼所 Process management device and method

Similar Documents

Publication Publication Date Title
US5818716A (en) Dynamic lot dispatching required turn rate factory control system and method of operation thereof
US5991732A (en) Strategical-tactical logistic system
US5841659A (en) Production plan generating method and apparatus
US9836042B2 (en) Electronic component mounting system and equipment unit management method for electronic component mounting system
JPH11235648A (en) Manufacturing plan control device, manufacturing plan controlling method and storage medium recorded with manufacturing plan control program capable of reading by computer
Bokhorst et al. Lean production control at a high-variety, low-volume parts manufacturer
US20160048127A1 (en) Component arrangement determination method
JP2003058228A (en) Product progress management method and device
Chen The order fulfillment planning problem considering multi-site order allocation and single-site shop floor scheduling
US8027857B2 (en) Rough-cut manufacturing operations for use in planning
JP2007079663A (en) Production operation planning apparatus and production operation plan evaluation apparatus
JPH08212261A (en) Starting plan forming device
JP2004075321A (en) Stock management method and stock management program
JPH10229293A (en) Part mounting program forming method
JP2008140015A (en) Part delivery instruction system, part delivery instruction method, and part delivery instruction program
US9880548B2 (en) Electronic component mounting system and component management method for electronic component mounting system
JP4760125B2 (en) Maintenance quantity batch calculation system for discontinued parts and maintenance parts
JP2002091536A (en) Managing method for integrated manufacture of steel product, scheduling device and storage medium
JP4902616B2 (en) Loss cost optimization system, loss cost optimization method, and loss cost optimization program
JP3195385B2 (en) Production planning system and production planning method
US6970756B2 (en) Computer-assisted pull flow production management method
JP3983061B2 (en) production management system
JP2798299B2 (en) Inventory simulation system
JPH1011502A (en) Production plan evaluation system
JPH08264998A (en) Production control system

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20081104