JP2019040345A - Process management device and method - Google Patents

Process management device and method Download PDF

Info

Publication number
JP2019040345A
JP2019040345A JP2017161236A JP2017161236A JP2019040345A JP 2019040345 A JP2019040345 A JP 2019040345A JP 2017161236 A JP2017161236 A JP 2017161236A JP 2017161236 A JP2017161236 A JP 2017161236A JP 2019040345 A JP2019040345 A JP 2019040345A
Authority
JP
Japan
Prior art keywords
time
job
date
progress
delivery date
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017161236A
Other languages
Japanese (ja)
Other versions
JP6811693B2 (en
Inventor
梅田 豊裕
Toyohiro Umeda
豊裕 梅田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP2017161236A priority Critical patent/JP6811693B2/en
Publication of JP2019040345A publication Critical patent/JP2019040345A/en
Application granted granted Critical
Publication of JP6811693B2 publication Critical patent/JP6811693B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

To further, appropriately manage a progress state of actual manufacturing.SOLUTION: A process management device for managing progress states of a plurality of jobs in a factory for manufacturing a plurality of different products in parallel by processing a plurality of raw materials as respective jobs in a plurality of prescribed processes in a prescribed order includes: a first process due date calculation part for calculating a limit process due date; a prior load time calculation part for calculating a prior load time; a second process due date calculation part for calculating a process due date on a bottleneck process basis; a prior load reference time calculation part for calculating a prior load reference time; and a progress level calculation part for calculating a relative position of a determination date on a time base with respect to the prior load reference time, the process due date on the bottleneck process basis, and the limit process due date, and calculating a progress level corresponding to the relative position in a process in which the jobs arrive on the prescribed determination date, in each job.SELECTED DRAWING: Figure 1

Description

本発明は、製品の製造工程における進捗状況を管理する工程管理装置および方法に関する。   The present invention relates to a process management apparatus and method for managing progress in a product manufacturing process.

従来、金属素材の生産工場等において、複数の設備で素材を処理する工程を経て納期及び製造手順の異なる多品種の製品が並行して生産される多品種生産システムが普及している。多品種生産システムにおいて、ある工程における複数の素材に対する処理における各進捗状況にムラがあると、素材毎のリードタイムにばらつきが出るため、製造する製品の納期管理が難しくなる。また、素材に対する処理の進捗状況のムラにより全体的なリードタイムが延びると、設備の稼働率低下にも繋がる。このため、多品種生産システムでは、それぞれの素材に対する処理の進捗状況を好適に管理する工程管理装置の構築が重要となっている。   2. Description of the Related Art Conventionally, a multi-product production system in which multi-product products with different delivery dates and different manufacturing procedures are produced in parallel through a process of processing a material with a plurality of facilities in a metal material production factory or the like has become widespread. In a multi-product production system, if there is unevenness in the progress of processing for a plurality of materials in a certain process, the lead time for each material will vary, making it difficult to manage the delivery date of the product to be manufactured. In addition, if the overall lead time is extended due to unevenness in the progress of processing on the material, the operating rate of the equipment is also reduced. For this reason, in a multi-product production system, it is important to construct a process management apparatus that suitably manages the progress of processing for each material.

特許文献1に記載の技術では、製品を生産するための複数の工程の進捗情報または進捗予定情報を記憶し、進捗情報または進捗予定情報を表示装置にて表示し、進捗情報または進捗予定情報を入力情報によって更新している。これによって、製品の生産計画の適正化が可能となり、かつ実際の製品の生産作業の進捗を適切に管理することが可能となっている。   In the technique described in Patent Document 1, progress information or progress schedule information of a plurality of processes for producing a product is stored, progress information or progress schedule information is displayed on a display device, and the progress information or progress schedule information is displayed. Updated with input information. This makes it possible to optimize the product production plan and to appropriately manage the progress of the actual product production work.

特開2011−90595号公報JP 2011-90595 A

しかしながら、上記特許文献1に記載の技術に対し、実際の生産の進捗状況を更に適切に管理することができるように、改善が求められている。   However, there is a demand for improvement with respect to the technique described in Patent Document 1 so that the actual progress of production can be managed more appropriately.

本発明は、上記問題を解決するもので、実際の生産の進捗状況を更に適切に管理することができる工程管理装置および方法を提供することを目的とする。   The present invention solves the above-described problems, and an object thereof is to provide a process management apparatus and method that can more appropriately manage the actual production progress.

本発明の第1態様は、
複数の素材をそれぞれジョブとして所定の複数工程において所定の順番で処理することにより複数の異なる製品を並行して生産する工場における複数の前記ジョブの進捗状況を管理する工程管理装置であって、
前記ジョブ毎に、最終工程での出荷納期を起点とし、上流工程に対して第1工程まで順に標準工程間リードタイムずつ遡った時刻を、それぞれ、前記出荷納期に間に合うために最も遅く処理完了可能な限界工程納期として算出する第1工程納期計算部と、
前記ジョブ毎に、各工程において計算対象ジョブの前記限界工程納期よりも早い前記限界工程納期を持つ前記計算対象ジョブ以外の他ジョブの前記工程における標準処理時間に関連する関連時間の合計を先行負荷時間として算出する先行負荷時間計算部と、
前記ジョブ毎に、前記計算対象ジョブの各工程において、所定の基準日時に前記先行負荷時間を加算した時刻と前記限界工程納期との時間差をそれぞれ算出し、前記時間差のうち最小値を抽出し、前記計算対象ジョブの各工程において、前記限界工程納期から前記最小値遡った時刻をそれぞれボトルネック工程基準での工程納期として算出する第2工程納期計算部と、
前記ジョブ毎に、第1工程においては、前記基準日時に前記先行負荷時間を加算した時刻を先行負荷基準時刻として算出し、第N(Nは2以上かつ前記計算対象ジョブの工程数以下の整数)工程においては、第(N−1)工程の先行負荷基準時刻に第(N−1)工程から第N工程までの標準工程間リードタイムを加算した時刻と、前記基準日時に第N工程における前記先行負荷時間を加算した時刻とのうち遅い方を先行負荷基準時刻として算出する先行負荷基準時刻計算部と、
前記ジョブ毎に、所定の判定日時に前記ジョブが到着している工程において、前記先行負荷基準時刻と前記ボトルネック工程基準での工程納期と前記限界工程納期とに対する、時間軸上における前記判定日時の相対位置を算出し、前記相対位置に応じた進捗レベルを算出する進捗レベル計算部と、
を備えるものである。
The first aspect of the present invention is:
A process management apparatus that manages the progress of a plurality of jobs in a factory that produces a plurality of different products in parallel by processing a plurality of materials as jobs in a predetermined order in a plurality of processes,
For each job, starting from the delivery date of the final process, the time that goes back by the lead time between the standard processes in order to the first process with respect to the upstream process can be completed most recently in order to meet the delivery date of delivery. A first process delivery date calculation unit for calculating a critical process delivery time;
For each job, a preload is added to the total related time related to the standard processing time in the process of other jobs other than the calculation target job having the limit process delivery time earlier than the limit process delivery time of the calculation target job in each process. A preload time calculation unit to calculate as time,
For each job, in each process of the calculation target job, calculate a time difference between the time when the preceding load time is added to a predetermined reference date and the limit process delivery time, and extract a minimum value among the time differences, In each process of the calculation target job, a second process delivery date calculation unit that calculates a time that is traced back from the minimum process delivery date as the process delivery date on the bottleneck process basis,
For each job, in the first step, a time obtained by adding the preceding load time to the reference date and time is calculated as a preceding load reference time, and an Nth (N is an integer not less than 2 and not more than the number of steps of the calculation target job) ) In the process, the time obtained by adding the standard inter-process lead time from the (N-1) process to the Nth process to the preceding load reference time of the (N-1) process, and the reference date and time in the Nth process. A preceding load reference time calculation unit that calculates a later one of the times obtained by adding the preceding load times as a preceding load reference time;
In the process in which the job arrives at a predetermined determination date for each job, the determination date on the time axis with respect to the preceding load reference time, the process delivery date based on the bottleneck process criteria, and the limit process delivery date A progress level calculation unit that calculates a relative position of the target and calculates a progress level according to the relative position;
Is provided.

本発明の第2態様は、
複数の素材をそれぞれジョブとして所定の複数工程において所定の順番で処理することにより複数の異なる製品を並行して生産する工場における複数の前記ジョブの進捗状況を管理する工程管理方法であって、
前記ジョブ毎に、最終工程での出荷納期を起点とし、上流工程に対して第1工程まで順に標準工程間リードタイムずつ遡った時刻を、それぞれ、前記出荷納期に間に合うために最も遅く処理完了可能な限界工程納期として算出する第1工程納期計算ステップと、
前記ジョブ毎に、各工程において計算対象ジョブの前記限界工程納期よりも早い前記限界工程納期を持つ前記計算対象ジョブ以外の他ジョブの前記工程における標準処理時間に関連する関連時間の合計を先行負荷時間として算出する先行負荷時間計算ステップと、
前記ジョブ毎に、前記計算対象ジョブの各工程において、所定の基準日時に前記先行負荷時間を加算した時刻と前記限界工程納期との時間差をそれぞれ算出し、前記時間差のうち最小値を抽出し、前記計算対象ジョブの各工程において、前記限界工程納期から前記最小値遡った時刻をそれぞれボトルネック工程基準での工程納期として算出する第2工程納期計算ステップと、
前記ジョブ毎に、第1工程においては、前記基準日時に前記先行負荷時間を加算した時刻を先行負荷基準時刻として算出し、第N(Nは2以上かつ前記ジョブの工程数以下の整数)工程においては、第(N−1)工程の先行負荷基準時刻に第(N−1)工程から第N工程までの標準工程間リードタイムを加算した時刻と、前記基準日時に第N工程における前記先行負荷時間を加算した時刻とのうち遅い方を先行負荷基準時刻として算出する先行負荷基準時刻計算ステップと、
前記ジョブ毎に、所定の判定日時に前記ジョブが到着している工程において、前記先行負荷基準時刻と前記ボトルネック工程基準での工程納期と前記限界工程納期とに対する、時間軸上における前記判定日時の相対位置を算出し、前記相対位置に応じた進捗レベルを算出する進捗レベル計算ステップと、
を備えるものである。
The second aspect of the present invention is:
A process management method for managing the progress of a plurality of jobs in a factory that produces a plurality of different products in parallel by processing a plurality of materials as jobs in a predetermined order in a predetermined plurality of steps,
For each job, starting from the delivery date of the final process, the time that has been traced back to the first process by the lead time between the standard processes in order from the upstream process can be completed most recently to meet the delivery date of delivery. A first process delivery date calculation step for calculating a critical process delivery time;
For each job, a preload is added to the total related time related to the standard processing time in the process of other jobs other than the calculation target job having the limit process delivery time earlier than the limit process delivery time of the calculation target job in each process. A preload time calculation step to calculate as time,
For each job, in each process of the calculation target job, calculate a time difference between the time when the preceding load time is added to a predetermined reference date and the limit process delivery time, and extract a minimum value among the time differences, In each process of the calculation target job, a second process delivery date calculation step for calculating a time that is traced back from the minimum process delivery date as the process delivery date on the bottleneck process basis,
For each job, in the first step, a time obtained by adding the preceding load time to the reference date and time is calculated as a preceding load reference time, and the Nth (N is an integer not less than 2 and not more than the number of steps of the job) step , The time obtained by adding the lead time between standard processes from the (N-1) process to the Nth process to the preceding load reference time of the (N-1) process, and the preceding in the Nth process at the reference date and time. A preceding load reference time calculating step for calculating a later one of the times obtained by adding the load times as a preceding load reference time;
In the process in which the job arrives at a predetermined determination date for each job, the determination date on the time axis with respect to the preceding load reference time, the process delivery date based on the bottleneck process criteria, and the limit process delivery date A progress level calculating step of calculating a relative position of the target and calculating a progress level according to the relative position;
Is provided.

上記第1態様又は上記第2態様では、ジョブ毎に、各工程において計算対象ジョブの限界工程納期よりも早い限界工程納期を持つ計算対象ジョブ以外の他ジョブの工程における処理時間に関連する関連時間の合計が、先行負荷時間として算出される。ジョブ毎に、計算対象ジョブの各工程において、基準日時に先行負荷時間を加算した時刻と限界工程納期との時間差がそれぞれ算出され、算出された時間差のうち最小値が抽出され、計算対象ジョブの各工程において、限界工程納期から最小値遡った時刻が、それぞれボトルネック工程基準での工程納期として算出される。   In the first aspect or the second aspect, for each job, a related time related to a processing time in a process of a job other than the calculation target job having a limit process delivery time earlier than the limit process delivery time of the calculation target job in each process. Is calculated as the preceding load time. For each job, in each process of the calculation target job, a time difference between the time obtained by adding the preceding load time to the reference date and the limit process delivery time is calculated, and the minimum value is extracted from the calculated time differences. In each process, the time that goes back the minimum value from the limit process delivery date is calculated as the process delivery date on the basis of the bottleneck process.

基準日時に先行負荷時間を加算した時刻と限界工程納期との時間差が最小値の工程ということは、計算対象ジョブの限界工程納期よりも早い限界工程納期を持つ計算対象ジョブ以外の他ジョブの処理が完了した時点から、計算対象ジョブの限界工程納期までの余裕時間が、最も少ない工程ということを意味する。よって、上記時間差が最小値の工程は、限界工程納期を遵守するのが最も困難な工程であるということができる。そこで、上記時間差が最小値の工程は、ボトルネック工程と称される。   The process with the minimum time difference between the time obtained by adding the preceding load time to the standard date and time and the limit process delivery date is the processing of jobs other than the calculation target job that has a limit process delivery time earlier than the limit process delivery date of the calculation target job. This means that the process has the shortest margin time from the completion of the process to the limit process delivery date of the job to be calculated. Therefore, it can be said that the process with the minimum time difference is the most difficult process to comply with the limit process delivery date. Therefore, the process having the minimum time difference is referred to as a bottleneck process.

このボトルネック工程基準での工程納期は、標準工程間リードタイムでジョブが全工程を流れた場合に、ボトルネック工程において、計算対象ジョブより限界工程納期が早い他のジョブが全て処理された直後に、計算対象ジョブに対する処理を開始できる最も遅いタイミングとなる。したがって、ジョブに対する処理をボトルネック工程基準での工程納期より早く開始した場合には、その後、標準工程間リードタイムで処理した時に、ボトルネック工程において、限界工程納期が計算対象ジョブより早い他のジョブに対する処理が終了するのを待つ可能性が高くなる。一般に、納期の早いジョブに対する処理を優先して開始するからである。その結果、上記第1態様又は上記第2態様によれば、他のジョブとの関係で決まるボトルネック工程の負荷状況を考慮した上で、どのタイミングまでに各ジョブを処理するべきかの目安を得ることができる。   The process delivery date based on this bottleneck process standard is that immediately after all other jobs whose marginal process delivery time is earlier than the job to be calculated are processed in the bottleneck process when the job flows through all processes with the lead time between standard processes. In addition, it is the latest timing at which processing for the calculation target job can be started. Therefore, if processing for a job starts earlier than the process delivery date based on the bottleneck process standard, then when processing with the lead time between standard processes, the limit process delivery time in the bottleneck process is earlier than that of the job to be calculated. There is a higher possibility of waiting for the processing for the job to end. This is because, in general, processing for a job with a quick delivery date is preferentially started. As a result, according to the first aspect or the second aspect, after considering the load situation of the bottleneck process determined by the relationship with other jobs, an indication of at which timing each job should be processed Can be obtained.

また、上記第1態様又は上記第2態様では、ジョブ毎に、第1工程においては、所定の基準日時に先行負荷時間を加算した時刻が先行負荷基準時刻として算出される。第N(Nは2以上かつジョブの工程数以下の整数)工程においては、第(N−1)工程の先行負荷基準時刻に第(N−1)工程から第N工程までの標準工程間リードタイムを加算した時刻と、基準日時に第N工程における先行負荷時間を加算した時刻とのうち遅い方が、先行負荷基準時刻として算出される。   In the first mode or the second mode, for each job, in the first step, a time obtained by adding the preceding load time to a predetermined reference date and time is calculated as the preceding load reference time. In the Nth step (N is an integer equal to or larger than 2 and equal to or less than the number of job steps), lead between standard steps from the (N-1) th step to the Nth step at the preceding load reference time of the (N-1) th step. The later of the time obtained by adding the time and the time obtained by adding the preceding load time in the Nth step to the reference date and time is calculated as the preceding load reference time.

この先行負荷基準時刻は、全工程において、計算対象ジョブより限界工程納期が早い他のジョブに対する処理が全て完了した後に、計算対象ジョブに対する処理を開始するとした場合の最も早いタイミングである。すなわち、先行負荷基準時刻より早く計算対象ジョブに対する処理を開始した場合には、計算対象ジョブより限界工程納期が早い他のジョブが後回しになる可能性がある。その結果、他のジョブの納期遅れを引き起こす可能性がある。   The preceding load reference time is the earliest timing when processing for the calculation target job is started after all processing for other jobs whose limit process delivery date is earlier than that of the calculation target job is completed in all processes. In other words, when processing for a calculation target job is started earlier than the preceding load reference time, there is a possibility that another job whose limit process delivery date is earlier than that of the calculation target job will be postponed. As a result, there is a possibility of delaying delivery of other jobs.

また、上記第1態様又は上記第2態様では、ジョブ毎に、所定の判定日時に計算対象ジョブが到着している工程において、先行負荷基準時刻とボトルネック工程基準での工程納期と限界工程納期とに対する、時間軸上における判定日時の相対位置が算出され、相対位置に応じた進捗レベルが算出される。したがって、上記第1態様又は上記第2態様によれば、限界工程納期のみを用いて進捗レベルを算出するのに比べて、より細かい区分で進捗レベルを算出することができる。その結果、実際の生産の進捗状況を更に適切に管理することができる。   Moreover, in the said 1st aspect or the said 2nd aspect, in the process for which the calculation object job has arrived at the predetermined determination date for each job, the process delivery date and the limit process delivery date based on the preceding load reference time and the bottleneck process reference The relative position of the determination date and time on the time axis is calculated, and the progress level corresponding to the relative position is calculated. Therefore, according to the first aspect or the second aspect, it is possible to calculate the progress level in a finer section as compared to calculating the progress level using only the limit process delivery date. As a result, the actual production progress can be managed more appropriately.

上記第1態様において、例えば、前記進捗レベル計算部は、処理の緊急度を表す指標である複数のレベルに区分して前記進捗レベルを算出してもよい。前記複数のレベルは、前記処理の緊急度が高くなる順に、第1レベルから第4レベルを含んでもよい。前記進捗レベル計算部は、算出する前記進捗レベルを、前記判定日時が前記先行負荷基準時刻以前のときは、前記第1レベルとし、前記判定日時が前記先行負荷基準時刻以降であって、かつ前記ボトルネック工程基準での工程納期以前のときは、前記第2レベルとし、前記判定日時が前記ボトルネック工程基準での工程納期以降であって、かつ前記限界工程納期以前のときは、前記第3レベルとし、前記判定日時が前記限界工程納期以降のときは、前記第4レベルとしてもよい。   In the first aspect, for example, the progress level calculation unit may calculate the progress level by classifying the progress level into a plurality of levels that are indices indicating the urgency of the process. The plurality of levels may include a first level to a fourth level in order of increasing urgency of the process. The progress level calculation unit sets the progress level to be calculated as the first level when the determination date is before the preceding load reference time, the determination date is after the preceding load reference time, and When it is before the process delivery date based on the bottleneck process standard, the second level is set. When the determination date is after the process delivery date based on the bottleneck process standard and before the limit process delivery date, the third level is set. When the determination date is after the critical process delivery date, the fourth level may be set.

先行負荷基準時刻より早く計算対象ジョブに対する処理を開始した場合には、計算対象ジョブより限界工程納期が早い他のジョブが後回しになる可能性がある。その結果、他のジョブの納期遅れを引き起こす可能性がある。そこで、本態様では、算出する進捗レベルは、判定日時が先行負荷基準時刻以前のときは、処理の緊急度が最も低い第1レベルとされる。したがって、本態様によれば、処理の緊急度が最も低いため、処理の開始が最も弱く促されることになり、計算対象ジョブより限界工程納期が早い他のジョブの納期遅れを引き起こす可能性を低くすることができる。   When the process for the calculation target job is started earlier than the preceding load reference time, there is a possibility that another job whose limit process delivery date is earlier than that of the calculation target job is postponed. As a result, there is a possibility of delaying delivery of other jobs. Therefore, in this aspect, the calculated progress level is the first level with the lowest urgency of the process when the determination date and time is before the preceding load reference time. Therefore, according to this aspect, since the urgency of the process is the lowest, the start of the process is urged to be weakest, and the possibility of causing a delay in the delivery of another job whose marginal process delivery date is earlier than the calculation target job is reduced. can do.

ジョブに対する処理をボトルネック工程基準での工程納期より早く開始した場合には、その後、標準工程間リードタイムで処理した時に、ボトルネック工程において、限界工程納期が計算対象ジョブより早い他のジョブに対する処理が終了するのを待つ可能性が高くなる。そこで、本態様では、算出する進捗レベルは、判定日時が先行負荷基準時刻以降であって、かつボトルネック工程基準での工程納期以前のときは、処理の緊急度が第1レベルより高いが第3レベルより低い第2レベルとされる。したがって、本態様によれば、処理の緊急度が比較的低いため、処理の開始が比較的弱く促されることになり、ボトルネック工程において、限界工程納期が計算対象ジョブより早い他のジョブに対する処理が終了するのを待つ可能性が高くなるのを抑制することができる。   If processing for a job starts earlier than the process delivery date based on the bottleneck process standard, then when processing is performed with the lead time between standard processes, the bottleneck process will process other jobs whose marginal process delivery time is earlier than the calculation target job. There is a higher possibility of waiting for the processing to end. Therefore, in this aspect, when the determination date is after the preceding load reference time and before the process delivery date based on the bottleneck process reference, the urgency level of the process is higher than the first level. The second level is lower than the third level. Therefore, according to this aspect, since the degree of urgency of the process is relatively low, the start of the process is urged relatively weakly. In the bottleneck process, the process for another job whose limit process delivery time is earlier than the calculation target job. It is possible to suppress the possibility of waiting for completion of.

ボトルネック工程基準での工程納期は、標準工程間リードタイムでジョブが全工程を流れた場合に、ボトルネック工程において、計算対象ジョブより限界工程納期が早い他のジョブが全て処理された直後に、つまり不要な空き時間を発生させずに、計算対象ジョブに対する処理を開始できる最も遅いタイミングとなる。そこで、本態様では、算出する進捗レベルは、判定日時がボトルネック工程基準での工程納期以降であって、かつ限界工程納期以前のときは、処理の緊急度が第2レベルより高いが第4レベルより低い第3レベルとされる。したがって、本態様によれば、処理の緊急度が比較的高いため、処理の開始が比較的強く促されることになり、ボトルネック工程において、計算対象ジョブより限界工程納期が早い他のジョブが全て処理された後、あまり大きな空き時間を発生させることなく、計算対象ジョブに対する処理を開始することができる。   The process delivery date based on the bottleneck process standard is that the job flows through all processes with the standard inter-process lead time, and immediately after all other jobs that have a limit process delivery time earlier than the calculation target job are processed in the bottleneck process. That is, it is the latest timing at which the processing for the calculation target job can be started without generating unnecessary idle time. Therefore, in this aspect, when the determination date is after the process delivery date based on the bottleneck process standard and before the limit process delivery date, the urgency level of the process is higher than the second level. The third level is lower than the level. Therefore, according to this aspect, since the urgency of the process is relatively high, the start of the process is urged relatively strongly, and in the bottleneck process, all other jobs whose limit process delivery time is earlier than the calculation target job are all After the processing, the processing for the calculation target job can be started without causing a very large free time.

限界工程納期以降に処理を開始すると、標準工程間リードタイムでジョブが全工程を流れた場合に、出荷納期に遅れることになる。そこで、本態様では、算出する進捗レベルは、判定日時が限界工程納期以降のときは、処理の緊急度が最も高い第4レベルとされる。したがって、本態様によれば、処理の緊急度が最も高いため、処理の開始が最も強く促されることになり、出荷納期に対する遅れを少なくすることが可能になる。   When processing is started after the limit process delivery date, if the job flows through all processes with the standard inter-process lead time, the delivery date will be delayed. Therefore, in this aspect, the calculated progress level is the fourth level with the highest urgency of the process when the determination date is after the limit process delivery date. Therefore, according to this aspect, since the urgency of the process is the highest, the start of the process is most strongly urged, and the delay with respect to the delivery date can be reduced.

上記第1態様において、例えば、前記ジョブ毎に、前記判定日時に前記ジョブが到着している工程である到着工程を記憶する進捗データ記憶部と、前記ジョブ毎に、前記限界工程納期と、前記ボトルネック工程基準での工程納期と、前記先行負荷基準時刻とを記憶する管理基準記憶部と、をさらに備えてもよい。前記第1工程納期計算部は、前記ジョブ毎に、算出した前記限界工程納期を前記管理基準記憶部に保存してもよい。前記第2工程納期計算部は、前記ジョブ毎に、算出した前記ボトルネック工程基準での工程納期を前記管理基準記憶部に保存してもよい。前記先行負荷基準時刻計算部は、前記ジョブ毎に、算出した前記先行負荷基準時刻を前記管理基準記憶部に保存してもよい。前記進捗レベル計算部は、前記ジョブ毎に、前記到着工程を前記進捗データ記憶部から読み出し、読み出した前記到着工程に対応する前記限界工程納期と、前記ボトルネック工程基準での工程納期と、前記先行負荷基準時刻とを前記管理基準記憶部から読み出して、前記到着工程における前記進捗レベルを算出してもよい。   In the first aspect, for example, for each job, a progress data storage unit that stores an arrival process that is a process in which the job has arrived at the determination date, and for each job, the limit process delivery date, You may further provide the management reference | standard storage part which memorize | stores the process delivery date by a bottleneck process reference | standard, and the said preceding load reference | standard time. The first process delivery date calculation unit may store the calculated limit process delivery date for each job in the management reference storage unit. The second process delivery date calculation unit may store the calculated process delivery date based on the bottleneck process standard in the management standard storage unit for each job. The preceding load reference time calculation unit may store the calculated preceding load reference time in the management reference storage unit for each job. The progress level calculation unit reads, for each job, the arrival process from the progress data storage unit, the limit process delivery date corresponding to the read arrival process, the process delivery date based on the bottleneck process standard, The advance load reference time may be read from the management reference storage unit, and the progress level in the arrival process may be calculated.

本態様では、ジョブ毎に、到着工程が読み出され、読み出された到着工程に対応する限界工程納期と、ボトルネック工程基準での工程納期と、先行負荷基準時刻とが読み出されて、到着工程における進捗レベルが算出される。したがって、本態様によれば、判定日時にジョブに対する処理中の工程における進捗レベルを算出することが可能になる。   In this aspect, for each job, the arrival process is read, the limit process delivery time corresponding to the read arrival process, the process delivery time on the bottleneck process basis, and the preceding load reference time are read, The progress level in the arrival process is calculated. Therefore, according to this aspect, it is possible to calculate the progress level in the process being processed for the job at the determination date and time.

上記第1態様において、例えば、前記ジョブ毎に、前記ジョブが第1工程に到着した到着日時を起点とし、下流工程に対して最終工程まで順に前記標準工程間リードタイムずつ経過した時刻を、それぞれ、最も早く処理が完了可能な最早完成基準時刻として算出する最早完成基準時刻計算部を更に備えてもよい。前記複数のレベルは、前記処理の緊急度が前記第1レベルより低い第0レベルを更に含んでもよい。前記進捗レベル計算部は、前記ジョブ毎に、前記判定日時に前記ジョブが到着している工程において、更に、前記最早完成基準時刻に対する、時間軸上における前記判定日時の相対位置を算出し、前記相対位置に応じた前記進捗レベルを算出してもよい。前記進捗レベル計算部は、前記進捗レベルを、前記判定日時が、前記先行負荷基準時刻以前のうちで、前記最早完成基準時刻以降のときを前記第1レベルとし、前記最早完成基準時刻以前のときを前記第0レベルとしてもよい。   In the first aspect, for example, for each job, the time when the standard process lead time elapses in order from the arrival date and time when the job arrived at the first process to the final process with respect to the downstream process, An earliest completion reference time calculation unit that calculates the earliest completion reference time at which processing can be completed earliest may be further provided. The plurality of levels may further include a 0th level in which the urgency level of the processing is lower than the first level. The progress level calculation unit further calculates a relative position of the determination date and time on the time axis with respect to the earliest completion reference time in the process in which the job arrives at the determination date and time for each job, The progress level corresponding to the relative position may be calculated. The progress level calculation unit sets the progress level as the first level when the determination date and time is after the earliest completion reference time before the preceding load reference time, and before the earliest completion reference time. May be the 0th level.

最早完成基準時刻は、ジョブの第1工程への到着時期を起点とし、下流工程に対して最終工程まで順に標準工程間リードタイムずつ経過した時刻である。このため、最早完成基準時刻より早く計算対象ジョブに対する処理を開始する必要性は全く無い。そこで、本態様では、算出する進捗レベルは、判定日時が最早完成基準時刻以前のときは、処理の緊急度が第1レベルより低い第0レベルとされる。したがって、本態様によれば、最早完成基準時刻以前のときは処理の緊急度が最も低いため、処理の開始が最も弱く促されることになり、計算対象ジョブより限界工程納期が早い他のジョブの納期遅れを引き起こす可能性を低くすることができる。   The earliest completion reference time is the time at which the lead time between standard processes has passed in order from the downstream process to the final process starting from the arrival time of the job at the first process. For this reason, there is no need to start processing for the calculation target job earlier than the earliest completion reference time. Therefore, in this aspect, the calculated progress level is set to the 0th level in which the urgency level of the process is lower than the 1st level when the determination date is earlier than the earliest completion reference time. Therefore, according to this aspect, since the urgency of the process is the lowest before the earliest completion reference time, the start of the process is urged to be weakest, and other jobs whose marginal process delivery time is earlier than the calculation target job. The possibility of causing a delay in delivery can be reduced.

上記第1態様において、例えば、前記ジョブ毎に、前記判定日時に前記ジョブが到着している工程において、進捗度合いを表す進捗指数を算出する進捗指数計算部を更に備えてもよい。前記進捗指数計算部は、前記判定日時が前記最早完成基準時刻のときは、前記進捗指数を所定の第1基準指数とし、前記判定日時が前記先行負荷基準時刻のときは、前記進捗指数を前記第1基準指数より大きい所定の第2基準指数とし、前記判定日時が前記ボトルネック工程基準での工程納期のときは、前記進捗指数を前記第2基準指数より大きい所定の第3基準指数とし、前記判定日時が前記限界工程納期のときは、前記進捗指数を前記第3基準指数より大きい所定の第4基準指数とし、前記判定日時が前記最早完成基準時刻と前記先行負荷基準時刻との間のときは、前記進捗指数を前記第1基準指数と前記第2基準指数とで線形補間した第1補間値とし、前記判定日時が前記先行負荷基準時刻と前記ボトルネック工程基準での工程納期との間のときは、前記進捗指数を前記第2基準指数と前記第3基準指数とで線形補間した第2補間値とし、前記判定日時が前記ボトルネック工程基準での工程納期と前記限界工程納期との間のときは、前記進捗指数を前記第3基準指数と前記第4基準指数とで線形補間した第3補間値としてもよい。   In the first aspect, for example, a progress index calculation unit that calculates a progress index indicating a progress degree may be further provided for each job in a process in which the job arrives at the determination date and time. The progress index calculation unit sets the progress index as a predetermined first reference index when the determination date is the earliest completion reference time, and sets the progress index when the determination date is the preceding load reference time. A predetermined second reference index greater than the first reference index, and when the determination date and time is a process delivery date based on the bottleneck process reference, the progress index is a predetermined third reference index greater than the second reference index; When the determination date / time is the critical process delivery date, the progress index is set to a predetermined fourth reference index larger than the third reference index, and the determination date / time is between the earliest completion reference time and the preceding load reference time. When the progress index is a first interpolation value obtained by linearly interpolating the first reference index and the second reference index, the determination date and time is the preceding load reference time and the process delivery date based on the bottleneck process reference. In the meantime, the progress index is set to a second interpolation value obtained by linear interpolation with the second reference index and the third reference index, and the determination date and time is a process delivery date based on the bottleneck process criteria and the limit process delivery date. When the interval is between, the progress index may be a third interpolation value obtained by linear interpolation between the third reference index and the fourth reference index.

本態様では、進捗レベルが第1レベルのときの進捗指数は、第1補間値とされ、進捗レベルが第2レベルのときの進捗指数は、第2補間値とされ、進捗レベルが第3レベルのときの進捗指数は、第3補間値とされる。このため、同じ進捗レベルであっても、判定日時の基準指数に対する相対位置に依存して、進捗指数が異なる値となる。したがって、本態様によれば、より詳細に、進捗度合いを把握することができる。   In this aspect, the progress index when the progress level is the first level is the first interpolation value, the progress index when the progress level is the second level is the second interpolation value, and the progress level is the third level. The progress index at this time is the third interpolation value. For this reason, even if the progress level is the same, the progress index becomes a different value depending on the relative position of the determination date and time with respect to the reference index. Therefore, according to this aspect, the degree of progress can be grasped in more detail.

上記第1態様において、例えば、情報を表示する表示部と、前記ジョブ毎に、前記進捗レベルを前記表示部に表示する表示制御部と、をさらに備えてもよい。   The first aspect may further include, for example, a display unit that displays information, and a display control unit that displays the progress level on the display unit for each job.

本態様では、ジョブ毎に、進捗レベルが表示部に表示される。したがって、本態様によれば、ジョブ毎の進捗レベルを容易に把握することができる。   In this aspect, the progress level is displayed on the display unit for each job. Therefore, according to this aspect, the progress level for each job can be easily grasped.

上記第1態様において、例えば、予め設定された、前記工程で用いられる設備の稼働率を前記工程毎に記憶する稼働率記憶部と、前記ジョブ毎に、前記各工程での処理に要する標準処理時間を記憶するジョブデータ記憶部と、をさらに備えてもよい。前記先行負荷時間計算部は、計算対象工程で用いられる設備の稼働率を前記稼働率記憶部から読み出し、計算対象工程での処理に要する前記標準処理時間を前記ジョブデータ記憶部から読み出し、前記標準処理時間を前記稼働率で除算した時間を前記関連時間として用いてもよい。   In the first aspect, for example, a preset operation rate storage unit that stores an operation rate of equipment used in the step for each step, and a standard process required for processing in each step for each job. And a job data storage unit for storing time. The preceding load time calculation unit reads the operation rate of equipment used in the calculation target process from the operation rate storage unit, reads the standard processing time required for processing in the calculation target process from the job data storage unit, and A time obtained by dividing the processing time by the operating rate may be used as the related time.

本態様では、計算対象工程で用いられる設備の稼働率が読み出され、計算対象工程での処理に要する標準処理時間が読み出されて、標準処理時間を稼働率で除算した時間が関連時間として用いられる。したがって、本態様によれば、設備の稼働率を考慮することによって、実際の稼働状況に適合する先行負荷時間を算出することができる。   In this aspect, the operating rate of the equipment used in the calculation target process is read, the standard processing time required for processing in the calculation target step is read, and the time obtained by dividing the standard processing time by the operating rate is the related time. Used. Therefore, according to this aspect, it is possible to calculate the preload time suitable for the actual operation status by considering the operation rate of the equipment.

本発明によれば、ジョブ毎に、所定の判定日時に計算対象ジョブが到着している工程において、先行負荷基準時刻とボトルネック工程基準での工程納期と限界工程納期とに対する、時間軸上における判定日時の相対位置が算出され、相対位置に応じた進捗レベルが算出されるため、限界工程納期のみを用いて進捗レベルを算出するのに比べて、より細かい区分で進捗レベルを算出することができる。その結果、実際の生産の進捗状況を更に適切に管理することができる。   According to the present invention, for each job, in the process in which the calculation target job has arrived at the predetermined determination date and time, the process delivery date and the limit process delivery date based on the preceding load reference time, the bottleneck process reference, on the time axis Since the relative position of the determination date and time is calculated and the progress level corresponding to the relative position is calculated, it is possible to calculate the progress level in finer categories than when calculating the progress level using only the limit process delivery date. it can. As a result, the actual production progress can be managed more appropriately.

第1実施形態の工程管理装置の構成例を概略的に示すブロック図である。It is a block diagram showing roughly an example of composition of a process management device of a 1st embodiment. 限界工程納期を概略的に示すタイミングチャートである。It is a timing chart which shows a limit process delivery date roughly. 先行負荷時間を概略的に示すタイミングチャートである。It is a timing chart which shows a prior load time roughly. 工程納期余裕時間を概略的に示すタイミングチャートである。It is a timing chart which shows process delivery time margin time roughly. ボトルネック工程基準での工程納期を概略的に示すタイミングチャートである。It is a timing chart which shows roughly the process delivery date by a bottleneck process standard. 先行負荷基準時刻を概略的に示すタイミングチャートである。It is a timing chart which shows a preceding load standard time roughly. 第1実施形態における進捗レベルの表示例を概略的に示す図である。It is a figure which shows roughly the example of a display of the progress level in 1st Embodiment. 第1工程納期計算部、先行負荷時間計算部、第2工程納期計算部、先行負荷基準時刻計算部による第1実施形態の動作を概略的に示すフローチャートである。It is a flowchart which shows schematically operation | movement of 1st Embodiment by a 1st process delivery date calculation part, a preceding load time calculation part, a 2nd process delivery date calculation part, and a preceding load reference time calculation part. 第1工程納期計算部、先行負荷時間計算部、第2工程納期計算部、先行負荷基準時刻計算部による第1実施形態の動作を概略的に示すフローチャートである。It is a flowchart which shows schematically operation | movement of 1st Embodiment by a 1st process delivery date calculation part, a preceding load time calculation part, a 2nd process delivery date calculation part, and a preceding load reference time calculation part. 第1工程納期計算部、先行負荷時間計算部、第2工程納期計算部、先行負荷基準時刻計算部による第1実施形態の動作を概略的に示すフローチャートである。It is a flowchart which shows schematically operation | movement of 1st Embodiment by a 1st process delivery date calculation part, a preceding load time calculation part, a 2nd process delivery date calculation part, and a preceding load reference time calculation part. 進捗レベル計算部、表示制御部の動作を概略的に示すフローチャートである。It is a flowchart which shows roughly operation | movement of a progress level calculation part and a display control part. ジョブにおける限界工程納期、ボトルネック工程基準での工程納期、先行負荷基準時刻を概略的に示すタイミングチャートである。6 is a timing chart schematically showing a limit process delivery date, a process delivery date based on a bottleneck process standard, and a preceding load reference time in a job. 図12と異なるジョブにおける限界工程納期、ボトルネック工程基準での工程納期、先行負荷基準時刻を概略的に示すタイミングチャートである。13 is a timing chart schematically showing a limit process delivery date, a process delivery date based on a bottleneck process basis, and a preceding load reference time in a job different from FIG. 12. 図12のジョブと図13のジョブとの進捗レベルを概略的に示すタイミングチャートである。14 is a timing chart schematically showing progress levels of the job of FIG. 12 and the job of FIG. 第2実施形態の工程管理装置の構成例を概略的に示すブロック図である。It is a block diagram which shows roughly the structural example of the process management apparatus of 2nd Embodiment. 最早完成基準時刻を概略的に示すタイミングチャートである。It is a timing chart which shows the earliest completion reference time roughly. 第2実施形態における進捗レベルの表示例を概略的に示す図である。It is a figure which shows roughly the example of a display of the progress level in 2nd Embodiment. 第2実施形態における進捗指数の表示例を概略的に示す図である。It is a figure which shows roughly the example of a display of the progress index in 2nd Embodiment. 進捗レベルが同じである2つのジョブの進捗指数を概略的に示すタイミングチャートである。It is a timing chart which shows roughly the progress index of two jobs with the same progress level. 第1工程納期計算部、先行負荷時間計算部、第2工程納期計算部、先行負荷基準時刻計算部、最早完成基準時刻計算部による第2実施形態の動作を概略的に示すフローチャートである。It is a flowchart which shows schematically operation | movement of 2nd Embodiment by a 1st process delivery date calculation part, a preceding load time calculation part, a 2nd process delivery date calculation part, a preceding load reference time calculation part, and the earliest completion reference time calculation part. 第1工程納期計算部、先行負荷時間計算部、第2工程納期計算部、先行負荷基準時刻計算部、最早完成基準時刻計算部による第2実施形態の動作を概略的に示すフローチャートである。It is a flowchart which shows schematically operation | movement of 2nd Embodiment by a 1st process delivery date calculation part, a preceding load time calculation part, a 2nd process delivery date calculation part, a preceding load reference time calculation part, and the earliest completion reference time calculation part. 進捗レベル計算部、表示制御部、進捗指数計算部による第2実施形態の動作を概略的に示すフローチャートである。It is a flowchart which shows roughly operation | movement of 2nd Embodiment by a progress level calculation part, a display control part, and a progress index | exponent calculation part.

(本発明の基礎となった知見)
図2は、本発明の第1実施形態における第1工程納期計算部151(後述の図1)によって算出されるジョブJBの限界工程納期を概略的に示すタイミングチャートである。図2を用いて、まず、本発明の基礎となった知見が説明される。
(Knowledge that became the basis of the present invention)
FIG. 2 is a timing chart schematically showing the limit process delivery date of the job JB calculated by the first process delivery date calculation unit 151 (FIG. 1 described later) in the first embodiment of the present invention. The knowledge that is the basis of the present invention will be described first with reference to FIG.

金属素材の生産工場等においては、複数の素材をそれぞれジョブとして所定の複数工程において所定の順番で処理することにより複数の異なる製品が並行して生産される。本実施形態では、第1工程納期計算部151は、例えば図2に示されるように、ジョブJBの出荷納期DTを起点として、最終工程(図2では設備8)から標準工程間リードタイムSLTずつ上流工程に向かって遡ることによって、各工程(設備7〜設備1)において処理を完了すべき期限を表す限界工程納期PDTを、限界工程納期PD7〜PD1として算出する。本実施形態では、第1工程納期計算部151は、ジョブ毎に、限界工程納期PDTを算出する。   In a metal material production factory or the like, a plurality of different products are produced in parallel by processing a plurality of materials as jobs in a predetermined order in predetermined steps. In the present embodiment, as shown in FIG. 2, for example, the first process delivery date calculation unit 151 starts from the delivery delivery date DT of the job JB, starting from the final process (equipment 8 in FIG. 2) from the standard process lead time SLT. By going back to the upstream process, the limit process delivery date PDT indicating the time limit for completing the process in each process (equipment 7 to equipment 1) is calculated as the limit process delivery date PD7 to PD1. In the present embodiment, the first process delivery date calculation unit 151 calculates a limit process delivery date PDT for each job.

工程間リードタイムは、連続する2つの工程における処理終了時刻の時間差である。すなわち、工程間リードタイムは、前工程の処理終了時刻から次工程の処理終了時刻までの時間である。標準工程間リードタイムSLTは、前後の工程の組合せ単位で、過去の工程間リードタイムの実績値から予め算出された平均値又は中央値である。標準工程間リードタイムSLTは、工程間リードタイム記憶部142(後述の図1)に記憶されている。   The inter-process lead time is a time difference between processing end times in two consecutive processes. That is, the inter-process lead time is the time from the process end time of the previous process to the process end time of the next process. The standard inter-process lead time SLT is an average value or median value calculated in advance from the past actual inter-process lead time in units of combinations of the preceding and following processes. The standard inter-process lead time SLT is stored in the inter-process lead time storage unit 142 (FIG. 1 described later).

各工程における処理終了時刻が限界工程納期より遅れると、ジョブが標準工程間リードタイムSLTで流れる場合には、そのジョブは出荷納期に間に合わないことになる。そこで、従来、この限界工程納期PD1〜PD7までに、設備1〜7での処理がそれぞれ完了するように、進捗状況が管理されていた。例えば、限界工程納期までの余裕日数を指標としておき、余裕日数が一定値以下になると、対象となるジョブに警告を出力するようにして、途中工程で生産の遅れが発生しないように管理する方法が一般に知られている。あるいは、工程納期までの余裕日数が短い作業から優先的に処理するように製造手順を指示する方法も、よく知られている。しかしながら、限界工程納期のみによる管理では、以下の問題がある。   If the processing end time in each process is delayed from the limit process delivery date, if the job flows with the standard inter-process lead time SLT, the job will not be in time for the delivery delivery date. Therefore, in the past, the progress has been managed so that the processes in the facilities 1 to 7 are completed by the critical process delivery times PD1 to PD7. For example, the number of days left until the critical process delivery date is used as an index, and if the number of days left is less than a certain value, a warning is output to the target job so that production delays do not occur in the middle of the process. Is generally known. Alternatively, a method of instructing a manufacturing procedure so as to preferentially process an operation with a short allowance time until the process delivery date is well known. However, the management based only on the critical process delivery date has the following problems.

(X)工程における処理を開始すべき目安がない:
限界工程納期に対して遅れないという安全面を考慮し過ぎると、各工程の処理開始時刻を早くし過ぎることになるため、仕掛品が増えてしまう。逆に、工程納期に処理が終了するように、ぎりぎりに処理開始時刻を設定すると、特に上流工程における遅延が下流工程に伝搬して、出荷納期に遅れる可能性が生じる。
(X) There is no guideline to start processing in the process:
If the safety aspect of not delaying the limit process delivery time is considered too much, the processing start time of each process will be too early, and the work in process will increase. Conversely, if the process start time is set at the last minute so that the process is completed at the process delivery date, the delay in the upstream process may be propagated to the downstream process, and the delivery date may be delayed.

(Y)他のジョブへの影響が分からない:
限界工程納期に対して遅れないという安全面を考慮して、各工程の処理開始時刻を早くし過ぎると、限界工程納期が早い他のジョブの処理が後回しになる。その結果、後回しになったジョブが出荷納期に遅れる可能性が高くなる。しかし、この可能性の度合いを考慮するのが困難である。
(Y) I don't know the impact on other jobs:
If the process start time of each process is set too early in consideration of the safety aspect that it is not delayed with respect to the limit process delivery date, processing of other jobs with earlier limit process delivery times will be delayed. As a result, there is a high possibility that the postponed job will be delayed in the delivery date. However, it is difficult to consider the degree of this possibility.

(Z)設備負荷を考慮した管理が困難である:
設備負荷の高いボトルネック設備が途中にある場合、ボトルネック設備より上流工程ではジョブを限界工程納期より早く処理できたとしても、そのジョブがボトルネック設備の前で待機することになると、仕掛量が増える原因となる。ジョブにより工程の順序が異なるジョブショップ型の場合、負荷の高い設備を通るジョブと、負荷の低い設備しか通らないジョブとでは、限界工程納期が同じでも限界工程納期に対する余裕時間が異なるはずである。ところが、この余裕時間の差異を判断することが困難である。
(Z) Management taking into account equipment load is difficult:
If there is a bottleneck equipment with a high equipment load in the middle, even if the process upstream of the bottleneck equipment can process the job earlier than the limit process delivery date, if the job waits in front of the bottleneck equipment, Will increase. In the case of a job shop type in which the order of processes differs depending on the job, a job that passes through a high load facility and a job that passes through only a low load facility should have different margin times for the limit process delivery date even if the limit process delivery date is the same. . However, it is difficult to determine this difference in margin time.

そこで、本発明者は、上述の問題点を解決する以下の項目を狙いとして、本開示の技術を想到した。すなわち、
(A)工程での処理を開始するタイミングの目安となる指標を提供する。
(B)進捗管理において管理対象として着目している対象ジョブの処理タイミングが、納期遵守という観点から、他のジョブに影響する可能性の高低を判断可能にする。
(C)設備の負荷状況に応じて、進捗管理の目安となる基準を修正可能にする。
(D)ジョブによって利用する設備及び順序が異なるジョブショップ型の場合でも、ジョブによって異なる設備の負荷状況を考慮した進捗管理を可能にする。
Therefore, the present inventor has conceived the technique of the present disclosure with the aim of the following items that solve the above-described problems. That is,
(A) An index serving as a guideline for starting the process in the process is provided.
(B) It is possible to determine whether the processing timing of a target job that is focused as a management target in progress management is likely to affect other jobs from the viewpoint of observing the delivery date.
(C) It is possible to modify a standard as a guide for progress management in accordance with the load status of the equipment.
(D) Even in the case of a job shop type in which equipment and order used by a job are different, it is possible to perform progress management in consideration of the load status of equipment that differs depending on the job.

(実施の形態)
以下、本発明の実施の形態について、図面を参照しながら説明する。なお、各図面において、同じ構成要素には同じ符号が用いられ、詳細な説明は、適宜、省略される。
(Embodiment)
Hereinafter, embodiments of the present invention will be described with reference to the drawings. In the drawings, the same components are denoted by the same reference numerals, and detailed description thereof is omitted as appropriate.

(構成)
図1は、第1実施形態における工程管理装置100の構成例を概略的に示すブロック図である。図1に示されるように、第1実施形態における工程管理装置100は、ディスプレイ110、入力部120、メモリ130、記憶装置140、及び中央演算処理装置(CPU)150を備える。
(Constitution)
FIG. 1 is a block diagram schematically showing a configuration example of a process management apparatus 100 in the first embodiment. As shown in FIG. 1, the process management apparatus 100 according to the first embodiment includes a display 110, an input unit 120, a memory 130, a storage device 140, and a central processing unit (CPU) 150.

第1実施形態における工程管理装置100は、複数の素材をジョブとして複数の工程(設備)で処理して複数の受注製品を並行して生産する、例えばジョブショップ型で多品種生産の工場において、各素材に対する処理の進捗状況を管理する。各受注製品は、受注製品ごとに予め定められた工程の順で素材が工程に対応する設備により処理されることによって生産される。   The process management apparatus 100 according to the first embodiment processes a plurality of materials as jobs in a plurality of processes (equipment) and produces a plurality of ordered products in parallel. For example, in a job shop type multi-product production factory, Manage the progress of processing for each material. Each ordered product is produced by processing the material by equipment corresponding to the process in the order of the process predetermined for each ordered product.

ディスプレイ110(表示部の一例に相当)は、例えば液晶ディスプレイパネルを含む。ディスプレイ110は、CPU150により制御されて、後述のように、ジョブ毎に、工程における進捗レベルを表示する。なお、ディスプレイ110は、液晶ディスプレイパネルに限られない。ディスプレイ110は、有機EL(electroluminescence)パネルなどの他のパネルを含んでもよい。   The display 110 (corresponding to an example of a display unit) includes, for example, a liquid crystal display panel. The display 110 is controlled by the CPU 150 and displays the progress level in the process for each job as will be described later. The display 110 is not limited to a liquid crystal display panel. The display 110 may include other panels such as an organic EL (electroluminescence) panel.

入力部120は、例えばマウス又はキーボードを含む。入力部120は、ユーザにより操作されると、その操作内容を示す操作信号をCPU150に出力する。なお、ディスプレイ110がタッチパネル式ディスプレイの場合には、マウス又はキーボードに代えて、タッチパネル式ディスプレイが入力部120を兼用してもよい。   The input unit 120 includes, for example, a mouse or a keyboard. When operated by the user, the input unit 120 outputs an operation signal indicating the operation content to the CPU 150. When the display 110 is a touch panel display, the touch panel display may also serve as the input unit 120 instead of the mouse or the keyboard.

メモリ130は、例えば半導体メモリ等により構成される。メモリ130は、例えばリードオンリーメモリ(ROM)、ランダムアクセスメモリ(RAM)、電気的に消去書き換え可能なROM(EEPROM)などを含む。メモリ130のROMは、CPU150を動作させる本実施形態の制御プログラムを記憶する。   The memory 130 is configured by, for example, a semiconductor memory. The memory 130 includes, for example, a read only memory (ROM), a random access memory (RAM), an electrically erasable / rewritable ROM (EEPROM), and the like. The ROM of the memory 130 stores the control program of this embodiment that causes the CPU 150 to operate.

CPU150は、年月日時をカウントする時計機能を有する。CPU150は、メモリ130に記憶された本実施形態の制御プログラムにしたがって動作することによって、第1工程納期計算部151、先行負荷時間計算部152、第2工程納期計算部153、先行負荷基準時刻計算部154、進捗レベル計算部155、表示制御部156の機能を有する。CPU150の各機能は、後述される。   The CPU 150 has a clock function that counts the date and time. The CPU 150 operates in accordance with the control program of the present embodiment stored in the memory 130, whereby the first process delivery date calculation unit 151, the preceding load time calculation unit 152, the second process delivery date calculation unit 153, and the preceding load reference time calculation. Unit 154, progress level calculation unit 155, and display control unit 156. Each function of the CPU 150 will be described later.

記憶装置140は、例えばハードディスク又は半導体メモリ等により構成される。記憶装置140は、ジョブデータ記憶部141、工程間リードタイム記憶部142、稼働率記憶部143、管理基準記憶部144、進捗データ記憶部145を含む。各記憶部141〜145は、互いに別の媒体で構成されてもよい。代替的に、各記憶部141〜145は、記憶領域が分けられた一つの媒体で構成されてもよい。   The storage device 140 is configured by, for example, a hard disk or a semiconductor memory. The storage device 140 includes a job data storage unit 141, an inter-process lead time storage unit 142, an operation rate storage unit 143, a management reference storage unit 144, and a progress data storage unit 145. Each of the storage units 141 to 145 may be composed of different media. Alternatively, each of the storage units 141 to 145 may be configured by one medium in which the storage area is divided.

ジョブデータ記憶部141は、ジョブ毎に、使用する設備の順番(つまり通過する工程の順番)、各設備での標準処理時間、出荷納期、現時点での進捗状況(どの工程まで進んでいるか)を予め記憶している。各設備での標準処理時間は、過去の同じ製品を同じ工程で処理したときの実績値の平均値又は中央値を用いてもよい。現時点の進捗状況は、各工程の処理終了時刻で表してもよい。すなわち、各工程の処理終了時刻が記載されていれば、その工程は処理済みであることを表し、処理終了時刻が記載されていなければ、その工程は未処理であることを表す。   The job data storage unit 141 indicates, for each job, the order of equipment to be used (that is, the order of the passing process), the standard processing time in each equipment, the delivery date of delivery, and the current progress status (which process has been advanced). Pre-stored. As the standard processing time in each facility, an average value or a median value of actual values when the same product in the past is processed in the same process may be used. The current progress status may be represented by the processing end time of each process. That is, if the process end time of each process is described, it indicates that the process has been processed, and if the process end time is not described, it indicates that the process has not been processed.

工程間リードタイム記憶部142は、ジョブ毎に、前後の工程の組合せにおける標準工程間リードタイムSLT(図2)を予め記憶する。工程間リードタイム記憶部142は、例えば図2に示されるジョブについては、設備1から設備2、設備2から設備3、・・・、設備6から設備7の、それぞれの標準工程間リードタイムSLTを予め記憶する。例えば、設備1で処理された後、次に設備2で処理されたときの工程間リードタイムの過去の実績値が集積され、その実績値の平均値又は中央値が予め算出されている。そして、実績値の平均値又は中央値が、設備1から設備2への標準工程間リードタイムSLTとして、工程間リードタイム記憶部142に格納される。   The inter-process lead time storage unit 142 stores in advance a standard inter-process lead time SLT (FIG. 2) in a combination of preceding and succeeding processes for each job. The inter-process lead time storage unit 142, for example, for the job shown in FIG. 2, each standard inter-process lead time SLT from the equipment 1 to the equipment 2, the equipment 2 to the equipment 3,. Is stored in advance. For example, past actual values of inter-process lead times when processed by the facility 1 and then processed by the facility 2 are accumulated, and an average value or median value of the actual values is calculated in advance. Then, the average value or median value of the actual values is stored in the inter-process lead time storage unit 142 as the standard inter-process lead time SLT from the equipment 1 to the equipment 2.

稼働率記憶部143は、設備毎に、標準的な稼働率を予め記憶する。稼働率は、1日24時間のなかで、ジョブの処理に費やすことができる最大時間の比率である。例えばメンテナンスの時間及び作業者の休憩時間には設備を動かせないため、稼働率は100%未満である。稼働率記憶部143は、例えば図2では、設備1の稼働率が50%、設備2の稼働率が80%等のように、設備毎に標準的に設定された稼働率を記憶する。   The operating rate storage unit 143 stores a standard operating rate in advance for each facility. The operating rate is the ratio of the maximum time that can be spent on job processing within 24 hours per day. For example, the operation rate is less than 100% because the equipment cannot be moved during the maintenance time and the break time of the worker. For example, in FIG. 2, the operation rate storage unit 143 stores the operation rate set for each facility in a standard manner such that the operation rate of the facility 1 is 50% and the operation rate of the facility 2 is 80%.

管理基準記憶部144は、後述のように、第1工程納期計算部151、第2工程納期計算部153、先行負荷基準時刻計算部154の計算結果を記憶する。進捗データ記憶部145は、現在日時における各ジョブの進捗状況、つまり各ジョブがどの設備で処理中であるかを記憶する。   As will be described later, the management criterion storage unit 144 stores the calculation results of the first process delivery date calculation unit 151, the second process delivery date calculation unit 153, and the preceding load reference time calculation unit 154. The progress data storage unit 145 stores the progress status of each job at the current date and time, that is, which equipment is processing each job.

第1工程納期計算部151は、上述のように、ジョブ毎に、その出荷納期を起点として、最終工程から標準工程間リードタイムずつ上流工程に向かって遡ることによって、各工程において処理を完了すべき期限を表す工程納期を算出する。ある工程においてジョブに対する処理終了時刻が上記算出された工程納期より遅れると、そのジョブは、出荷納期に間に合わなくなる。したがって、上記算出された工程納期は、限界工程納期と称される。第1工程納期計算部151は、ジョブ毎に、算出した各工程の限界工程納期を管理基準記憶部144に保存する。   As described above, the first process delivery date calculation unit 151 completes the process in each process by going back to the upstream process from the final process by the lead time between the standard processes starting from the delivery delivery date for each job as described above. The process delivery date representing the deadline is calculated. If the processing end time for a job in a certain process is delayed from the calculated process delivery date, the job will not be in time for the delivery date. Therefore, the calculated process delivery date is referred to as a limit process delivery date. The first process delivery date calculation unit 151 stores the calculated limit process delivery date of each process in the management reference storage unit 144 for each job.

図3は、先行負荷時間計算部152によって算出される先行負荷時間を概略的に示すタイミングチャートである。先行負荷時間計算部152は、ジョブ毎に、各工程の先行負荷時間を算出する。先行負荷時間は、計算対象工程において、計算対象ジョブの限界工程納期よりも早い限界工程納期を持つ他のジョブの計算対象工程における標準処理時間を稼働率で除算した実働処理時間(関連時間の一例に相当)の合計時間である。   FIG. 3 is a timing chart schematically showing the preceding load time calculated by the preceding load time calculating unit 152. The preceding load time calculation unit 152 calculates the preceding load time for each process for each job. The preceding load time is the actual processing time (an example of the related time) obtained by dividing the standard processing time in the calculation target process of another job with a limit process delivery time earlier than the limit process delivery date of the calculation target job by the operation rate. Equivalent time).

例えば図3において、ジョブJBの設備4における限界工程納期PD4は、3月14日である。先行負荷時間計算部152は、設備4における限界工程納期が3月14日より早いジョブJB以外の他ジョブであって、設備4で未処理のジョブに対する設備4における標準処理時間をジョブデータ記憶部141から読み出す。先行負荷時間計算部152は、設備4の稼働率を稼働率記憶部143から読み出す。先行負荷時間計算部152は、設備4における各ジョブに対する標準処理時間をそれぞれ設備4の稼働率で除算した実働処理時間の合計時間を算出する。この合計時間(図3の例では9.8日)が、設備4の先行負荷時間PLTである。   For example, in FIG. 3, the limit process delivery date PD4 in the equipment 4 of the job JB is March 14th. The prior load time calculation unit 152 is a job data storage unit that calculates the standard processing time in the facility 4 for jobs other than the job JB whose deadline for the limit process in the facility 4 is earlier than March 14 and is unprocessed in the facility 4 141 to read. The preceding load time calculation unit 152 reads the operation rate of the equipment 4 from the operation rate storage unit 143. The preceding load time calculation unit 152 calculates a total time of actual processing times obtained by dividing the standard processing time for each job in the facility 4 by the operation rate of the facility 4. This total time (9.8 days in the example of FIG. 3) is the preceding load time PLT of the equipment 4.

先行負荷時間計算部152は、ジョブJBの各工程(図3では設備1〜8)について、先行負荷時間を算出する。先行負荷時間計算部152は、さらに、ジョブJB以外の他のジョブを計算対象ジョブとして、各工程における先行負荷時間を算出する。その結果、先行負荷時間計算部152は、全ジョブ毎に、かつジョブが通過する工程毎に、先行負荷時間を算出する。   The preceding load time calculation unit 152 calculates the preceding load time for each process of the job JB (equipment 1 to 8 in FIG. 3). The preceding load time calculation unit 152 further calculates a preceding load time in each process using a job other than the job JB as a calculation target job. As a result, the preceding load time calculation unit 152 calculates the preceding load time for every job and for each process through which the job passes.

例えば設備4の先行負荷時間PLTは、計算対象ジョブ(図3ではジョブJB)より先に設備4で処理すべきジョブに対する標準処理時間/稼働率の合計時間である。したがって、先行負荷時間PLTより後でジョブJBに対する処理を開始すれば、他のジョブに対する処理を妨害しないであろうと考えられる。   For example, the preceding load time PLT of the facility 4 is the total time of standard processing time / operation rate for jobs to be processed by the facility 4 prior to the calculation target job (job JB in FIG. 3). Therefore, it is considered that if processing for job JB is started after the preceding load time PLT, processing for other jobs will not be disturbed.

図4は、第2工程納期計算部153によって算出される工程納期余裕時間を概略的に示すタイミングチャートである。図5は、第2工程納期計算部153によって算出されるボトルネック工程基準での工程納期を概略的に示すタイミングチャートである。   FIG. 4 is a timing chart schematically showing the process delivery time margin calculated by the second process delivery time calculation unit 153. FIG. 5 is a timing chart schematically showing the process delivery date based on the bottleneck process criterion calculated by the second process delivery date calculation unit 153.

第2工程納期計算部153は、基準日時SDTに先行負荷時間PLTを加算した時刻と限界工程納期との時間差を工程納期余裕時間DMTとして算出する。例えば図4において、上述のように、設備4の先行負荷時間PLTは9.8日であり、限界工程納期PD4は、3月14日である。また、基準日時SDTは、例えば、現在日時であり、図4では3月1日0時0分である。したがって、設備4の工程納期余裕時間DMTは、3.2日である。この工程納期余裕時間DMTの間に処理を開始すれば、自分自身のジョブ(計算対象ジョブ、図4ではジョブJB)より限界工程納期が早い他のジョブに対する処理に悪影響を与えず、しかも、自分自身のジョブ(計算対象ジョブ、図4ではジョブJB)も限界工程納期に遅れることがないという利点がある。   The second process delivery date calculation unit 153 calculates the time difference between the time obtained by adding the preceding load time PLT to the reference date and time SDT and the limit process delivery time as the process delivery margin time DMT. For example, in FIG. 4, as described above, the preceding load time PLT of the equipment 4 is 9.8 days, and the limit process delivery date PD4 is March 14. Further, the reference date and time SDT is, for example, the current date and time, and is 0:00 on March 1 in FIG. Therefore, the process delivery time allowance time DMT of the equipment 4 is 3.2 days. If processing is started during this process delivery margin time DMT, it will not adversely affect the processing of other jobs whose marginal process delivery is earlier than their own job (job to be calculated, job JB in FIG. 4). There is an advantage that its own job (job to be calculated, job JB in FIG. 4) is not delayed by the limit process delivery date.

第2工程納期計算部153は、設備1〜8の工程納期余裕時間DMTを比較して、最小値である最小工程納期余裕時間DMTminを抽出する。図4の例では、設備6の工程納期余裕時間DMTは2.2日であり、これが最小工程納期余裕時間DMTminになっている。この最小工程納期余裕時間DMTminとなる工程(図4では設備6)は、以下、「ボトルネック工程」と称される。   The second process delivery time calculation unit 153 compares the process delivery time allowance times DMT of the facilities 1 to 8 and extracts the minimum process delivery time allowance time DMTmin that is the minimum value. In the example of FIG. 4, the process delivery allowance time DMT of the facility 6 is 2.2 days, which is the minimum process delivery allowance time DMTmin. Hereinafter, the process (equipment 6 in FIG. 4) having the minimum process delivery margin time DMTmin is referred to as a “bottleneck process”.

第2工程納期計算部153は、全ての工程(図5では、設備1〜8)において、限界工程納期PDTから最小工程納期余裕時間DMTminを減算した納期を、ボトルネック工程基準での工程納期BNTとして算出する。第2工程納期計算部153は、ジョブ毎に、各工程におけるボトルネック工程基準での工程納期BNTを算出する。第2工程納期計算部153は、算出したボトルネック工程基準での工程納期BNTを管理基準記憶部144に保存する。   The second process delivery date calculation unit 153 calculates a delivery date obtained by subtracting the minimum process delivery time margin DMTmin from the limit process delivery date PDT in all processes (in FIG. 5, equipment 1 to 8). Calculate as The second process delivery date calculation unit 153 calculates a process delivery date BNT based on the bottleneck process standard in each process for each job. The second process delivery date calculation unit 153 stores the calculated process delivery date BNT based on the bottleneck process standard in the management standard storage unit 144.

ボトルネック工程基準での工程納期BNTは、自分自身のジョブ(計算対象ジョブ、図5ではジョブJB)より限界工程納期PDTが早い全ての工程(ボトルネック工程を含む)におけるジョブに対する処理に悪影響を与えず、かつ、全工程をジョブが標準工程間リードタイムで処理される場合に、ボトルネック工程でジョブの待ち時間(不要な設備の空き時間)を生じさせない最も遅いタイミングと言うことができる。すなわち、ボトルネック工程より上流工程において、ボトルネック工程基準での工程納期BNTより遅くジョブに対する処理が開始されると、ボトルネック工程において、ジョブの到着を待つために設備に空き時間が発生する可能性が高くなるとともに、限界工程納期PDTに対する余裕時間が短くなる。   The process delivery date BNT based on the bottleneck process standard has an adverse effect on the processing for jobs in all processes (including the bottleneck process) whose marginal process delivery date PDT is earlier than its own job (job to be calculated, job JB in FIG. 5). When all jobs are processed with the standard inter-process lead time, it can be said that it is the latest timing that does not cause a job waiting time (unnecessary equipment idle time) in the bottleneck process. In other words, in the upstream process from the bottleneck process, if processing for a job is started later than the process delivery time BNT based on the bottleneck process standard, the bottleneck process may have idle time for waiting for the arrival of the job. And the margin time for the limit process delivery date PDT is shortened.

図6は、先行負荷基準時刻計算部154によって算出される先行負荷基準時刻を概略的に示すタイミングチャートである。例えば図6において、先行負荷基準時刻計算部154は、第1工程(設備1)では、基準日時SDTに先行負荷時間PLTを加算した時刻TP1を第1工程の先行負荷基準時刻TPとして算出する。   FIG. 6 is a timing chart schematically showing the preceding load reference time calculated by the preceding load reference time calculation unit 154. For example, in FIG. 6, in the first process (facility 1), the preceding load reference time calculation unit 154 calculates time TP1 obtained by adding the preceding load time PLT to the reference date and time SDT as the preceding load reference time TP of the first process.

第2工程(設備2)では、先行負荷基準時刻計算部154は、第1工程の先行負荷基準時刻TPに標準工程間リードタイムSLTを加算した時刻TP21と、基準日時SDTに第2工程の先行負荷時間PLTを加算した時刻TP22とを比較して、遅い方の時刻TP22を第2工程の先行負荷基準時刻TPとして算出する。   In the second process (facility 2), the preceding load reference time calculation unit 154 precedes the second process by the time TP21 obtained by adding the inter-process lead time SLT to the preceding load reference time TP of the first process and the reference date and time SDT. The later time TP22 is calculated as the preceding load reference time TP of the second step by comparing with the time TP22 to which the load time PLT is added.

第N工程(Nは2以上かつ計算対象ジョブの工程数以下の整数)では、先行負荷基準時刻計算部154は、第(N−1)工程の先行負荷基準時刻に標準工程間リードタイムSLTを加算した時刻と、基準日時SDTに第N工程での先行負荷時間PLTを加算した時刻とを比較して、遅い方の時刻を第N工程の先行負荷基準時刻TPとして算出する。   In the Nth process (N is an integer not less than 2 and not more than the number of processes of the calculation target job), the preceding load reference time calculation unit 154 sets the standard inter-process lead time SLT at the preceding load reference time of the (N-1) process. The added time and the time obtained by adding the preceding load time PLT in the Nth step to the reference date and time SDT are calculated, and the later time is calculated as the preceding load reference time TP in the Nth step.

先行負荷基準時刻計算部154は、ジョブ毎に、各工程における先行負荷基準時刻を算出する。先行負荷基準時刻計算部154は、算出した先行負荷基準時刻TPを管理基準記憶部144に保存する。この先行負荷基準時刻TPは、自分自身のジョブより限界工程納期が早い他の全てのジョブに対して悪影響を与えない、最も早い処理タイミングと言うことができる。   The preceding load reference time calculation unit 154 calculates the preceding load reference time in each process for each job. The preceding load reference time calculation unit 154 stores the calculated preceding load reference time TP in the management reference storage unit 144. The preceding load reference time TP can be said to be the earliest processing timing that does not adversely affect all other jobs whose deadline for deadline process is earlier than their own job.

なお、先行負荷基準時刻計算部154は、この時刻の比較を、第N工程が最終工程(図6では設備8)になるまで行ってもよいが、第N工程がボトルネック工程になるまでで終了してもよい。なぜなら、ボトルネック工程以降は、一律に、第(N−1)工程の先行負荷基準時刻に標準工程間リードタイムSLTを加算した時刻の方が、基準日時SDTに第N工程での先行負荷時間PLTを加算した時刻より遅いからである。なお、この先行負荷基準時刻TPは、ボトルネック工程以降では、図6に示されるように、ボトルネック工程基準での工程納期BNTに一致する。   The preceding load reference time calculation unit 154 may compare this time until the Nth process becomes the final process (equipment 8 in FIG. 6), but until the Nth process becomes the bottleneck process. You may end. This is because, after the bottleneck process, the time obtained by adding the inter-standard process lead time SLT to the preceding load reference time of the (N-1) th process is equal to the preceding load time in the Nth process on the reference date and time SDT. This is because it is later than the time when PLT is added. The preceding load reference time TP coincides with the process delivery date BNT based on the bottleneck process reference after the bottleneck process, as shown in FIG.

上述の第1工程納期計算部151、先行負荷時間計算部152、第2工程納期計算部153、先行負荷基準時刻計算部154による計算は、事前に、例えば現在(計算開始日)から1箇月先までの受注製品について行われる。一方、次に説明される進捗レベル計算部155、表示制御部156の動作は、受注製品の製造中に、進捗状況を調べるために行われる。   The calculation by the first process delivery date calculation unit 151, the preceding load time calculation unit 152, the second process delivery date calculation unit 153, and the preceding load reference time calculation unit 154 is performed in advance, for example, one month ahead from the current (calculation start date). It will be done for up to order products. On the other hand, the operations of the progress level calculation unit 155 and the display control unit 156 described below are performed in order to check the progress status during manufacturing of the ordered product.

図7は、進捗レベル計算部155によって算出され、表示制御部156によってディスプレイ110に表示される、進捗レベルの表示例を概略的に示す図である。   FIG. 7 is a diagram schematically showing a display example of the progress level calculated by the progress level calculation unit 155 and displayed on the display 110 by the display control unit 156.

進捗レベル計算部155は、例えば、入力部120を用いて進捗レベルの評価をユーザにより指示されると、CPU150から判定日時として現在日時を取得する。進捗レベル計算部155は、進捗データ記憶部145から、現在日時において各ジョブがどの工程(設備)に到着しているかという各ジョブの進捗状況を読み出す。進捗レベル計算部155は、読み出した各ジョブについて、到着している到着工程の限界工程納期PDT、ボトルネック工程基準での工程納期BNT、先行負荷基準時刻TPを管理基準記憶部144から読み出す。   For example, when the user instructs the progress level calculation unit 155 to evaluate the progress level using the input unit 120, the progress level calculation unit 155 acquires the current date and time as the determination date and time from the CPU 150. The progress level calculation unit 155 reads from the progress data storage unit 145 the progress status of each job, which process (equipment) each job has reached at the current date and time. The progress level calculation unit 155 reads, for each read job, the limit process delivery date PDT of the arrival process that has arrived, the process delivery date BNT based on the bottleneck process standard, and the preceding load reference time TP from the management standard storage unit 144.

進捗レベル計算部155は、限界工程納期PDTと、ボトルネック工程基準での工程納期BNTと、先行負荷基準時刻TPとに対する、時間軸上における現在日時(判定日時)の相対位置を算出する。進捗レベル計算部155は、算出した相対位置に応じて、以下のように4段階として進捗レベルを算出する。   The progress level calculation unit 155 calculates the relative position of the current date and time (determination date) on the time axis with respect to the limit process delivery date PDT, the process delivery date BNT based on the bottleneck process criteria, and the preceding load reference time TP. The progress level calculation unit 155 calculates the progress level in four steps as follows according to the calculated relative position.

すなわち、進捗レベル計算部155は、現在日時が先行負荷基準時刻TP以前であれば、進捗レベルを、急ぐ必要が無いことを表すレベルLV1(第1レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が、先行負荷基準時刻TP以降であってボトルネック工程基準での工程納期BNT以前であれば、進捗レベルを、処理可能であることを表すレベルLV2(第2レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が、ボトルネック工程基準での工程納期BNT以降であって限界工程納期PDT以前であれば、進捗レベルを、早目に処理すべきであることを表すレベルLV3(第3レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が限界工程納期PDT以降であれば、進捗レベルを、急いで処理すべきであることを表すレベルLV4(第4レベルの一例に相当)とする。   In other words, if the current date is before the preceding load reference time TP, the progress level calculation unit 155 sets the progress level to a level LV1 (corresponding to an example of the first level) indicating that there is no need to rush. If the current date and time is after the preceding load reference time TP and before the process delivery date BNT based on the bottleneck process reference, the progress level calculation unit 155 indicates the level LV2 (second Equivalent to an example of a level). The progress level calculation unit 155 indicates that if the current date and time is after the process delivery date BNT based on the bottleneck process criteria and before the limit process delivery date PDT, the progress level should be processed earlier LV3 (Corresponding to an example of the third level). If the current date and time is after the limit process delivery date PDT, the progress level calculation unit 155 sets the progress level to level LV4 (corresponding to an example of the fourth level) indicating that it should be processed quickly.

図7は、計算対象ジョブJBが設備3に到着しており、現在日時が3月10日である例を示す。図7では、現在日時が先行負荷基準時刻TP以降であってボトルネック工程基準での工程納期BNT以前である。したがって、進捗レベル計算部155は、ジョブJBの設備3における進捗レベルを、処理可能であることを表すレベルLV2とする。   FIG. 7 shows an example in which the calculation target job JB has arrived at the facility 3 and the current date is March 10th. In FIG. 7, the current date and time is after the preceding load reference time TP and before the process delivery date BNT on the bottleneck process basis. Therefore, the progress level calculation unit 155 sets the progress level in the equipment 3 of the job JB to a level LV2 that represents that processing is possible.

表示制御部156は、ジョブ毎に、進捗レベル計算部155によって算出された進捗レベルをディスプレイ110に表示する。表示制御部156は、例えば図7をディスプレイ110に表示する。ディスプレイ110に表示された図7の画面を見ることによって、ユーザは、ジョブJBの設備3における進捗レベルが、レベルLV2であると理解する。   The display control unit 156 displays the progress level calculated by the progress level calculation unit 155 on the display 110 for each job. The display control unit 156 displays, for example, FIG. By viewing the screen of FIG. 7 displayed on the display 110, the user understands that the progress level in the equipment 3 of the job JB is the level LV2.

(動作)
図8〜図10は、図1に示される工程管理装置100の第1工程納期計算部151、先行負荷時間計算部152、第2工程納期計算部153、先行負荷基準時刻計算部154による第1実施形態の動作を概略的に示すフローチャートである。例えば、入力部120を用いてユーザにより指示されると、図8の動作が開始される。
(Operation)
8 to 10 show the first process due date calculation unit 151, the preceding load time calculation unit 152, the second process delivery date calculation unit 153, and the preceding load reference time calculation unit 154 of the process management apparatus 100 shown in FIG. It is a flowchart which shows the operation | movement of embodiment roughly. For example, when instructed by the user using the input unit 120, the operation of FIG. 8 is started.

図8のステップS800において、第1工程納期計算部151は、計算対象ジョブとして、最初のジョブを設定する。ステップS805において、第1工程納期計算部151は、設定されたジョブの出荷納期をジョブデータ記憶部141から取得し、設定されたジョブにおける全ての工程間における標準工程間リードタイムを工程間リードタイム記憶部142から取得する。ステップS810において、第1工程納期計算部151は、設定されたジョブにおける全ての工程の限界工程納期PDTを算出する。第1工程納期計算部151は、算出した全ての工程の限界工程納期PDTを、設定されたジョブに対応付けて、管理基準記憶部144に保存する。   In step S800 of FIG. 8, the first process delivery date calculation unit 151 sets the first job as the calculation target job. In step S805, the first process delivery date calculation unit 151 acquires the delivery date of the set job from the job data storage unit 141, and calculates the standard inter-process lead time between all processes in the set job as the inter-process lead time. Obtained from the storage unit 142. In step S810, the first process delivery date calculation unit 151 calculates the limit process delivery date PDT of all the processes in the set job. The first process delivery date calculation unit 151 stores the calculated limit process delivery dates PDT of all processes in the management reference storage unit 144 in association with the set jobs.

ステップS815において、第1工程納期計算部151は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS815でNO)、処理は、ステップS820に進む。ステップS820において、第1工程納期計算部151は、計算対象ジョブとして、次のジョブを設定する。その後、処理はステップS805に戻って、以上のステップが繰り返される。一方、全てのジョブについて終了していれば(ステップS815でYES)、処理はステップS825に進む。   In step S815, the first process delivery date calculation unit 151 determines whether or not all jobs have been completed. If all jobs have not been completed (NO in step S815), the process proceeds to step S820. In step S820, the first process delivery date calculation unit 151 sets the next job as a calculation target job. Thereafter, the process returns to step S805, and the above steps are repeated. On the other hand, if all jobs have been completed (YES in step S815), the process proceeds to step S825.

ステップS825において、先行負荷時間計算部152は、計算対象ジョブとして、最初のジョブを設定する。ステップS830において、先行負荷時間計算部152は、設定されたジョブにおける、計算対象工程として最初の工程を設定する。ステップS835において、先行負荷時間計算部152は、設定された工程(計算対象工程)において、設定されたジョブ(計算対象ジョブ)の限界工程納期より早い限界工程納期を持つ他のジョブを、管理基準記憶部144から取得する。   In step S825, the preceding load time calculation unit 152 sets the first job as the calculation target job. In step S830, the preceding load time calculation unit 152 sets the first process as the calculation target process in the set job. In step S <b> 835, the preceding load time calculation unit 152 manages, in the set process (calculation target process), another job having a limit process delivery time earlier than the limit process delivery date of the set job (calculation target job). Obtained from the storage unit 144.

ステップS840において、先行負荷時間計算部152は、設定された工程に用いられる設備の稼働率を稼働率記憶部143から取得する。先行負荷時間計算部152は、ステップS835で取得した他のジョブの、設定された工程における各標準処理時間をジョブデータ記憶部141から取得する。先行負荷時間計算部152は、各標準処理時間/稼働率の合計時間を先行負荷時間として算出する。先行負荷時間計算部152は、算出した先行負荷時間を、計算対象ジョブ及び計算対象工程に対応付けて、管理基準記憶部144に保存する。   In step S840, the preceding load time calculation unit 152 acquires the operation rate of the equipment used for the set process from the operation rate storage unit 143. The preceding load time calculation unit 152 acquires, from the job data storage unit 141, each standard processing time in the set process of the other job acquired in step S835. The preceding load time calculation unit 152 calculates the total time of each standard processing time / operation rate as the preceding load time. The preceding load time calculation unit 152 stores the calculated preceding load time in the management reference storage unit 144 in association with the calculation target job and the calculation target process.

ステップS845において、先行負荷時間計算部152は、全ての工程について終了したか否かを判定する。全ての工程について終了していなければ(ステップS845でNO)、処理は、ステップS850に進む。ステップS850において、先行負荷時間計算部152は、計算対象工程として、次の工程を設定する。その後、処理はステップS835に戻って、以上のステップが繰り返される。   In step S845, the preceding load time calculation unit 152 determines whether or not all the processes have been completed. If all the processes have not been completed (NO in step S845), the process proceeds to step S850. In step S850, the preceding load time calculation unit 152 sets the next process as a calculation target process. Thereafter, the process returns to step S835, and the above steps are repeated.

一方、全ての工程について終了していれば(ステップS845でYES)、処理はステップS855に進む。ステップS855において、先行負荷時間計算部152は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS855でNO)、処理は、ステップS860に進む。ステップS860において、先行負荷時間計算部152は、計算対象ジョブとして、次のジョブを設定する。その後、処理はステップS830に戻って、以上のステップが繰り返される。一方、全てのジョブについて終了していれば(ステップS855でYES)、処理は、図9のステップS900に進む。   On the other hand, if all processes have been completed (YES in step S845), the process proceeds to step S855. In step S855, the preceding load time calculation unit 152 determines whether all jobs have been completed. If all jobs have not been completed (NO in step S855), the process proceeds to step S860. In step S860, the preceding load time calculation unit 152 sets the next job as the calculation target job. Thereafter, the process returns to step S830, and the above steps are repeated. On the other hand, if all jobs have been completed (YES in step S855), the process proceeds to step S900 in FIG.

ステップS900において、第2工程納期計算部153は、基準日時を設定する。基準日時は、上述のように、現在日時でもよい。第2工程納期計算部153は、例えば入力部120を用いてユーザによって指示された基準日時を設定してもよい。ステップS905において、第2工程納期計算部153は、計算対象ジョブとして、最初のジョブを設定する。ステップS910において、第2工程納期計算部153は、全工程について、基準日時に先行負荷時間を加算した時刻と限界工程納期との時間差を算出する。第2工程納期計算部153は、算出した時間差のうち最小値をメモリ130のRAMに保存する。ステップS915において、第2工程納期計算部153は、全工程について、メモリ130のRAMに保存した最小値を用いて、ボトルネック工程基準での工程納期を算出する。第2工程納期計算部153は、ボトルネック工程基準での工程納期を、計算対象ジョブに対応付けて、管理基準記憶部144に保存する。   In step S900, the second process delivery date calculation unit 153 sets a reference date and time. The reference date and time may be the current date and time as described above. The second process delivery date calculation unit 153 may set a reference date and time instructed by the user using the input unit 120, for example. In step S905, the second process delivery date calculation unit 153 sets the first job as the calculation target job. In step S910, the second process delivery date calculation unit 153 calculates the time difference between the time obtained by adding the preceding load time to the reference date and the limit process delivery date for all processes. The second process delivery date calculation unit 153 stores the minimum value of the calculated time difference in the RAM of the memory 130. In step S <b> 915, the second process delivery date calculation unit 153 calculates a process delivery date based on the bottleneck process standard using the minimum value stored in the RAM of the memory 130 for all processes. The second process delivery date calculation unit 153 stores the process delivery date based on the bottleneck process standard in the management standard storage unit 144 in association with the calculation target job.

ステップS920において、第2工程納期計算部153は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS920でNO)、処理は、ステップS925に進む。ステップS925において、第2工程納期計算部153は、計算対象ジョブとして、次のジョブを設定する。その後、処理はステップS910に戻って、以上のステップが繰り返される。一方、全てのジョブについて終了していれば(ステップS920でYES)、処理は図10のステップS1005に進む。   In step S920, the second process delivery date calculation unit 153 determines whether or not all jobs have been completed. If all jobs have not been completed (NO in step S920), the process proceeds to step S925. In step S925, the second process delivery date calculation unit 153 sets the next job as the calculation target job. Thereafter, the process returns to step S910, and the above steps are repeated. On the other hand, if all jobs have been completed (YES in step S920), the process proceeds to step S1005 in FIG.

ステップS1005において、先行負荷基準時刻計算部154は、計算対象ジョブJとして、最初のジョブを設定する。ステップS1010において、先行負荷基準時刻計算部154は、計算対象ジョブの第1工程の先行負荷時間を管理基準記憶部144から取得する。先行負荷基準時刻計算部154は、基準日時に第1工程の先行負荷時間を加算した時刻を、第1工程の先行負荷基準時刻として、計算対象ジョブに対応付けて、管理基準記憶部144に保存する。ステップS1020において、先行負荷基準時刻計算部154は、第N工程として工程の順番をカウントするカウント値Nに「2」を設定する。   In step S1005, the preceding load reference time calculation unit 154 sets the first job as the calculation target job J. In step S <b> 1010, the preceding load reference time calculation unit 154 acquires the preceding load time of the first step of the calculation target job from the management reference storage unit 144. The preceding load reference time calculation unit 154 stores, in the management reference storage unit 144, the time obtained by adding the preceding load time of the first process to the reference date and time as the preceding load reference time of the first process in association with the calculation target job. To do. In step S1020, the preceding load reference time calculation unit 154 sets “2” to the count value N that counts the order of the steps as the Nth step.

ステップS1025において、先行負荷基準時刻計算部154は、計算対象ジョブJの第(N−1)工程の先行負荷基準時刻を管理基準記憶部144から取得する。先行負荷基準時刻計算部154は、第(N−1)工程から第N工程までの標準工程間リードタイムを工程間リードタイム記憶部142から取得する。先行負荷基準時刻計算部154は、第(N−1)工程の先行負荷基準時刻に第(N−1)工程から第N工程までの標準工程間リードタイムを加算した時刻を算出し、算出した時刻を第1時刻としてメモリ130のRAMに保存する。   In step S <b> 1025, the preceding load reference time calculation unit 154 acquires the preceding load reference time of the (N−1) -th process of the calculation target job J from the management reference storage unit 144. The preceding load reference time calculation unit 154 acquires the standard inter-process lead time from the (N−1) -th process to the N-th process from the inter-process lead time storage unit 142. The preceding load reference time calculation unit 154 calculates a time obtained by adding the standard inter-process lead time from the (N-1) process to the Nth process to the preceding load reference time of the (N-1) process. The time is stored in the RAM of the memory 130 as the first time.

ステップS1030において、先行負荷基準時刻計算部154は、計算対象ジョブの第N工程の先行負荷時間を管理基準記憶部144から取得する。先行負荷基準時刻計算部154は、基準日時に第N工程の先行負荷時間を加算した時刻を算出し、算出した時刻を第2時刻としてメモリ130のRAMに保存する。ステップS1035において、先行負荷基準時刻計算部154は、メモリ130のRAMに保存された第1時刻と第2時刻とを比較し、遅い方を第N工程の先行負荷基準時刻として、計算対象ジョブJに対応付けて、管理基準記憶部144に保存する。   In step S1030, the preceding load reference time calculation unit 154 acquires the preceding load time of the Nth step of the calculation target job from the management reference storage unit 144. The preceding load reference time calculation unit 154 calculates a time obtained by adding the preceding load time of the Nth process to the reference date and time, and stores the calculated time in the RAM of the memory 130 as the second time. In step S1035, the preceding load reference time calculation unit 154 compares the first time stored in the RAM of the memory 130 with the second time, and sets the later one as the preceding load reference time of the Nth step, and the calculation target job J Are stored in the management reference storage unit 144 in association with

ステップS1040において、先行負荷基準時刻計算部154は、工程の順番のカウント値Nが計算対象ジョブJの最終工程M(J)になったか否かを判定する。カウント値Nが計算対象ジョブJの最終工程M(J)になっていなければ(ステップS1040でNO)、処理はステップS1045に進む。一方、カウント値Nが計算対象ジョブJの最終工程M(J)になっていれば(ステップS1040でYES)、処理はステップS1050に進む。   In step S <b> 1040, the preceding load reference time calculation unit 154 determines whether or not the process order count value N has reached the final process M (J) of the calculation target job J. If the count value N is not the final process M (J) of the calculation target job J (NO in step S1040), the process proceeds to step S1045. On the other hand, if the count value N is the final process M (J) of the calculation target job J (YES in step S1040), the process proceeds to step S1050.

ステップS1045において、先行負荷基準時刻計算部154は、工程の順番のカウント値Nを1だけインクリメントする。その後、処理はステップS1025に進み、以上のステップが繰り返される。ステップS1050において、先行負荷基準時刻計算部154は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS1050でNO)、処理は、ステップS1055に進む。ステップS1055において、先行負荷基準時刻計算部154は、計算対象ジョブJとして、次のジョブを設定する。その後、処理はステップS1010に戻って、以上のステップが繰り返される。一方、全てのジョブについて終了していれば(ステップS1050でYES)、図10の処理は終了する。   In step S <b> 1045, the preceding load reference time calculation unit 154 increments the process order count value N by one. Thereafter, the process proceeds to step S1025, and the above steps are repeated. In step S1050, the preceding load reference time calculation unit 154 determines whether all jobs have been completed. If all jobs have not been completed (NO in step S1050), the process proceeds to step S1055. In step S <b> 1055, the preceding load reference time calculation unit 154 sets the next job as the calculation target job J. Thereafter, the process returns to step S1010, and the above steps are repeated. On the other hand, if all jobs have been completed (YES in step S1050), the processing in FIG. 10 ends.

本実施形態において、ステップS800〜S820は、第1工程納期計算ステップの一例に相当し、ステップS825〜S860は、先行負荷時間計算ステップの一例に相当し、ステップS900〜S925は、第2工程納期計算ステップの一例に相当し、ステップS1005〜S1055は、先行負荷基準時刻計算ステップの一例に相当する。   In this embodiment, steps S800 to S820 correspond to an example of a first process delivery time calculation step, steps S825 to S860 correspond to an example of a preceding load time calculation step, and steps S900 to S925 correspond to a second process delivery time calculation step. Steps S1005 to S1055 correspond to an example of a calculation step, and steps S1005 to S1055 correspond to an example of a preceding load reference time calculation step.

図11は、図1に示される工程管理装置100の進捗レベル計算部155、表示制御部156の動作を概略的に示すフローチャートである。例えば、入力部120を用いて進捗レベルの表示が指示されると、図11の動作が開始される。   FIG. 11 is a flowchart schematically showing operations of the progress level calculation unit 155 and the display control unit 156 of the process management apparatus 100 shown in FIG. For example, when the display of the progress level is instructed using the input unit 120, the operation of FIG. 11 is started.

ステップS1100において、進捗レベル計算部155は、判定日時を設定する。進捗レベル計算部155は、現在日時をCPU150から取得して、判定日時として現在日時を設定してもよい。代替的に、進捗レベル計算部155は、判定日時として将来の日時を設定してもよい。ステップS1105において、進捗レベル計算部155は、計算対象ジョブとして、最初のジョブを設定する。ステップS1110において、進捗レベル計算部155は、設定されたジョブの進捗状況、つまり設定されたジョブが到着している工程(設備)を進捗データ記憶部145から取得する。   In step S1100, the progress level calculation unit 155 sets a determination date and time. The progress level calculation unit 155 may acquire the current date and time from the CPU 150 and set the current date and time as the determination date and time. Alternatively, the progress level calculation unit 155 may set a future date and time as the determination date and time. In step S1105, the progress level calculation unit 155 sets the first job as the calculation target job. In step S1110, the progress level calculation unit 155 acquires the progress status of the set job, that is, the process (equipment) where the set job has arrived from the progress data storage unit 145.

ステップS1115において、進捗レベル計算部155は、設定されたジョブが到着している工程(設備)の先行負荷基準時刻と、ボトルネック工程基準での工程納期と、限界工程納期とを、管理基準記憶部144から取得する。ステップS1120において、進捗レベル計算部155は、先行負荷基準時刻と、ボトルネック工程基準での工程納期と、限界工程納期とに対する、時間軸上における判定日時の相対位置を算出する。ステップS1125において、進捗レベル計算部155は、算出した相対位置に基づき進捗レベルを算出し、算出した進捗レベルをメモリ130のRAMに保存する。   In step S1115, the progress level calculation unit 155 stores the management standard storage of the preceding load reference time of the process (equipment) in which the set job has arrived, the process delivery date based on the bottleneck process criteria, and the limit process delivery date. From the unit 144. In step S1120, the progress level calculation unit 155 calculates the relative position of the determination date and time on the time axis with respect to the preceding load reference time, the process delivery date based on the bottleneck process criteria, and the limit process delivery date. In step S <b> 1125, the progress level calculation unit 155 calculates a progress level based on the calculated relative position, and stores the calculated progress level in the RAM of the memory 130.

ステップS1130において、進捗レベル計算部155は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS1130でNO)、処理は、ステップS1135に進む。ステップS1135において、進捗レベル計算部155は、計算対象ジョブとして、次のジョブを設定する。その後、処理はステップS1110に戻って、以上のステップが繰り返される。   In step S1130, the progress level calculation unit 155 determines whether or not all jobs have been completed. If all the jobs have not been completed (NO in step S1130), the process proceeds to step S1135. In step S1135, the progress level calculation unit 155 sets the next job as a calculation target job. Thereafter, the process returns to step S1110, and the above steps are repeated.

一方、全てのジョブについて終了していれば(ステップS1130でYES)、処理はステップS1140に進む。ステップS1140において、表示制御部156は、ジョブ毎に進捗レベルをディスプレイ110に表示する。その後、図11の処理は終了する。本実施形態において、ステップS1100〜S1135は、進捗レベル計算ステップの一例に相当する。   On the other hand, if all the jobs have been completed (YES in step S1130), the process proceeds to step S1140. In step S1140, the display control unit 156 displays the progress level on the display 110 for each job. Thereafter, the process of FIG. 11 ends. In the present embodiment, steps S1100 to S1135 correspond to an example of a progress level calculation step.

(進捗レベルの具体例)
2つのジョブのある工程における限界工程納期が同じであっても、その後の通過工程が異なると、進捗レベル計算部155によって算出される進捗レベルの異なるケースが、図12〜図14を用いて説明される。
(Specific examples of progress levels)
Even if the marginal process delivery time in a process of two jobs is the same, the case where the progress level calculated by the progress level calculation unit 155 differs when the subsequent passing process is different will be described with reference to FIGS. Is done.

図12は、設備1,3,4,6,8を通過するジョブJB1における限界工程納期PDT、ボトルネック工程基準での工程納期BNT、先行負荷基準時刻TPを概略的に示すタイミングチャートである。図13は、設備1,2,3,5,7,8を通過するジョブJB2における限界工程納期PDT、ボトルネック工程基準での工程納期BNT、先行負荷基準時刻TPを概略的に示すタイミングチャートである。図14は、ジョブJB1(図12)とジョブJB2(図13)との進捗レベルを概略的に示すタイミングチャートである。   FIG. 12 is a timing chart schematically showing the limit process delivery date PDT, the process delivery date BNT based on the bottleneck process reference, and the preceding load reference time TP in the job JB1 passing through the facilities 1, 3, 4, 6, and 8. FIG. 13 is a timing chart schematically showing the limit process delivery date PDT, the process delivery date BNT based on the bottleneck process reference, and the preceding load reference time TP in the job JB2 passing through the facilities 1, 2, 3, 5, 7, and 8. is there. FIG. 14 is a timing chart schematically showing progress levels of the job JB1 (FIG. 12) and the job JB2 (FIG. 13).

図12、図13に示されるように、ジョブJB1とジョブJB2とは、通過する工程が互いに異なるため、ジョブショップ型の生産工程になっている。また、図12、図13から分かるように、設備3における限界工程納期PDTは、ジョブJB1及びジョブJB2ともに3月13日で、同じになっている。なお、基準日時SDTは、ジョブJB1(図12)及びジョブJB2(図13)の両方とも、3月1日0時0分になっている。   As shown in FIG. 12 and FIG. 13, the job JB1 and the job JB2 are job shop type production processes because the passing processes are different from each other. As can be seen from FIGS. 12 and 13, the limit process delivery date PDT in the facility 3 is the same on March 13 for both the job JB1 and the job JB2. The reference date and time SDT is 0:00 on March 1 for both job JB1 (FIG. 12) and job JB2 (FIG. 13).

図12において、基準日時SDTに先行負荷時間PLTを加算した時刻と限界工程納期PDTとの時間差である工程納期余裕時間のうち最小値の最小工程納期余裕時間DMTminを持つ工程は、先行負荷時間PLTが最も長い設備6である。したがって、設備6がボトルネック工程となる。   In FIG. 12, the process having the minimum process delivery margin time DMTmin among the process delivery margin time, which is the time difference between the time obtained by adding the preceding load time PLT to the reference date and time SDT and the limit process delivery time PDT, Is the longest facility 6. Therefore, the facility 6 becomes a bottleneck process.

一方、図13に示されるジョブJB2は、設備6を通過しない。図13において、基準日時SDTに先行負荷時間PLTを加算した時刻と限界工程納期PDTとの時間差である工程納期余裕時間のうち最小値の最小工程納期余裕時間DMTminを持つ工程は、設備7である。したがって、設備7がボトルネック工程となる。   On the other hand, the job JB2 shown in FIG. In FIG. 13, a process having a minimum process delivery margin time DMTmin of the minimum value among the process delivery margin times which are the time difference between the time obtained by adding the preceding load time PLT to the reference date and time SDT and the limit process delivery date PDT is the equipment 7. . Therefore, the facility 7 becomes a bottleneck process.

図12、図13から分かるように、最小工程納期余裕時間DMTminは、ジョブJB1(図12)より、ジョブJB2(図13)の方が長い。したがって、ジョブJB1(図12)における設備3のボトルネック工程基準での工程納期BNTは、3月11日であるのに対して、ジョブJB2(図13)における設備3のボトルネック工程基準での工程納期BNTは、3月9日であり、ジョブJB1に対して2日早くなっている。   As can be seen from FIGS. 12 and 13, the minimum process delivery time margin DMTmin is longer for job JB2 (FIG. 13) than for job JB1 (FIG. 12). Therefore, the process delivery time BNT based on the bottleneck process standard for the equipment 3 in the job JB1 (FIG. 12) is March 11, whereas the process delivery time BNT based on the bottleneck process standard for the equipment 3 in the job JB2 (FIG. 13). The process delivery date BNT is March 9, which is two days earlier than the job JB1.

図14において、判定日時は、3月10日に設定されている。ジョブJB1のボトルネック工程基準での工程納期BNTは、3月11日である。このため、判定日時(3月10日)の時点で、ジョブJB1が設備3まで進捗していた場合には、進捗レベル計算部155は、算出する進捗レベルを、処理可能であることを表すレベルLV2とする。よって、判定日時の時点(つまりボトルネック工程基準での工程納期BNTより早い時点)でジョブJB1に対する設備3における処理が開始されると、標準工程間リードタイムで処理が進んだ場合、ボトルネック工程(設備6)で待機する可能性があることが分かる。   In FIG. 14, the determination date and time is set to March 10. The process delivery date BNT based on the bottleneck process standard of job JB1 is March 11. Therefore, when the job JB1 has progressed to the facility 3 at the determination date (March 10), the progress level calculation unit 155 indicates that the calculated progress level can be processed. Let it be LV2. Therefore, when processing in the facility 3 for the job JB1 is started at the time of determination date (that is, earlier than the process delivery date BNT based on the bottleneck process standard), if the process proceeds with the standard inter-process lead time, the bottleneck process It turns out that there is a possibility of waiting at (facility 6).

一方、ジョブJB2のボトルネック工程基準での工程納期BNTは、3月9日である。このため、判定日時(3月10日)の時点で、ジョブJB2が設備3まで進捗していた場合には、進捗レベル計算部155は、算出する進捗レベルを、早目に処理すべきであることを表すレベルLV3とする。よって、判定日時の時点(つまりボトルネック工程基準での工程納期BNTより遅い時点)でジョブJB2に対する設備3における処理が開始されると、標準工程間リードタイムで処理が進んだ場合、ボトルネック工程(設備7)で待機する可能性が低く、早目に処理して出荷できる可能性があることが分かる。   On the other hand, the process delivery date BNT based on the bottleneck process standard of job JB2 is March 9. For this reason, when the job JB2 has progressed to the facility 3 at the determination date (March 10), the progress level calculation unit 155 should process the calculated progress level early. It is assumed that the level is LV3. Therefore, when the processing in the equipment 3 for the job JB2 is started at the time of the determination date (that is, the time later than the process delivery date BNT based on the bottleneck process standard), if the process proceeds with the standard inter-process lead time, the bottleneck process It is found that there is a low possibility of waiting at (facility 7), and there is a possibility that it can be processed and shipped early.

このように、本実施形態によれば、限界工程納期が同じであっても、進捗レベルに対して、異なる評価を行うことが可能になっている。   Thus, according to this embodiment, even if the limit process delivery date is the same, it is possible to perform different evaluations on the progress level.

(効果)
以上説明されたように、第1実施形態では、限界工程納期による自分自身のジョブの出荷納期のみを考慮した工程管理ではなくて、それに加えて、設備に対する負荷、他のジョブへの影響を総合的に考慮した工程管理が可能となっている。すなわち、進捗レベル計算部155は、ジョブの進捗状況を、限界工程納期のみによる2段階ではなくて、4段階で評価している。
(effect)
As described above, in the first embodiment, not only process management considering only the delivery date of one's own job by the limit process delivery date, but also the load on the equipment and the influence on other jobs are integrated. Process management that takes into account this is possible. In other words, the progress level calculation unit 155 evaluates the progress of the job in four stages instead of only two stages based on the limit process delivery date.

第1実施形態では、ジョブ毎に、通過する全ての工程において、自分自身のジョブ(計算対象ジョブ)よりも限界工程納期が早い他のジョブの当該工程での標準処理時間/稼働率を合計して先行負荷時間が算出される。基準日時に先行負荷時間を加算した時刻と、限界工程納期との時間差が最小値の工程が各ジョブのボトルネック工程と称される。この最小値の時間差が全ての工程で確保されるように、ボトルネック工程基準での工程納期が算出される。   In the first embodiment, for each job, the standard processing time / operating rate in the relevant process of other jobs whose marginal process delivery time is earlier than their own job (calculation target job) is summed up in all the processes that pass. Thus, the preload time is calculated. The process in which the time difference between the time obtained by adding the preceding load time to the reference date and time and the limit process delivery date is the minimum value is referred to as the bottleneck process of each job. The process delivery time on the basis of the bottleneck process is calculated so that this minimum time difference is ensured in all processes.

このボトルネック工程基準での工程納期は、標準工程間リードタイムでジョブが全工程を流れた場合に、ボトルネック工程において、自分自身のジョブ(計算対象ジョブ)より限界工程納期が早い他のジョブが全て処理された直後に(つまり不要な空き時間を発生させずに)、自分自身のジョブに対する処理を開始できる最も遅いタイミングとなる。   The process delivery date based on this bottleneck process standard is that when the job flows through all processes with the standard inter-process lead time, other jobs that have a limit process delivery time earlier than their own job (calculation target job) in the bottleneck process Immediately after all are processed (that is, without generating unnecessary idle time), it is the latest timing at which the processing for the own job can be started.

したがって、ボトルネック工程の上流工程において、ジョブに対する処理をボトルネック工程基準での工程納期より早く開始した場合には、その後、標準工程間リードタイムで処理した時に、ボトルネック工程において、限界工程納期が自分自身のジョブ(計算対象ジョブ)より早い他のジョブに対する処理が終了するのを待つ可能性が高くなる。一般に、納期の早いジョブに対する処理を優先して開始するからである。その結果、ボトルネック工程基準での工程納期を用いることによって、他のジョブとの関係で決まるボトルネック工程の負荷状況を考慮した上で、どのタイミングまでに各ジョブを処理するべきかの目安を得ることができる。   Therefore, in the upstream process of the bottleneck process, if the processing for the job starts earlier than the process delivery date based on the bottleneck process standard, then the limit process delivery time will be Is more likely to wait for the completion of processing for another job earlier than its own job (job to be calculated). This is because, in general, processing for a job with a quick delivery date is preferentially started. As a result, by using the process delivery date based on the bottleneck process standard, the load status of the bottleneck process determined by the relationship with other jobs is taken into consideration, and an indication of when each job should be processed Can be obtained.

また、第1実施形態では、ジョブの第1工程では、基準時刻に先行負荷時間を加算した時刻が先行負荷基準時刻として算出される。また、その後の第N工程(Nは2以上かつジョブの工程数以下の整数)では、標準工程間リードタイムで決まる時刻と、先行負荷時間の終了時刻とのうち、遅い方の時刻が先行負荷基準時刻として算出される。   In the first embodiment, in the first step of the job, a time obtained by adding the preceding load time to the reference time is calculated as the preceding load reference time. In the subsequent Nth process (N is an integer of 2 or more and the number of job processes or less), the later of the time determined by the lead time between standard processes and the end time of the preceding load time is the preceding load. Calculated as the reference time.

この先行負荷基準時刻は、全工程において、自分自身のジョブ(計算対象ジョブ)より限界工程納期が早い他のジョブに対する処理が全て完了した後に、自分自身のジョブ(計算対象ジョブ)に対する処理を開始するとした場合の最も早いタイミングである。すなわち、先行負荷基準時刻より早く自分自身のジョブ(計算対象ジョブ)に対する処理を開始した場合には、自分自身のジョブ(計算対象ジョブ)より限界工程納期が早い他のジョブが後回しになって、他のジョブの納期遅れを引き起こす可能性がある。このように、先行負荷基準時刻を用いることによって、他のジョブに対する影響を考慮することができる。   This preload reference time starts processing for one's own job (calculation target job) after all the processing for other jobs whose marginal process delivery time is earlier than their own job (calculation target job) is completed in all processes. If so, it is the earliest timing. In other words, when processing for one's own job (calculation target job) is started earlier than the preceding load reference time, another job whose limit process delivery time is earlier than its own job (calculation target job) is postponed, It may cause delays in the delivery of other jobs. In this way, the influence on other jobs can be taken into account by using the preceding load reference time.

また、第1実施形態では、ジョブに対する処理を開始して、受注製品の製造を開始した後に、判定日時の時点でジョブに対する処理中の工程において、先行負荷基準時刻と、ボトルネック工程基準での工程納期と、限界工程納期とに対する、判定日時の時間軸上における相対的な位置関係によって進捗レベルが区別され、その進捗レベルがジョブ毎にディスプレイ110に表示される。   In the first embodiment, after starting the processing for the job and starting manufacturing the ordered product, in the process that is being processed for the job at the determination date and time, the prior load reference time and the bottleneck process reference The progress level is distinguished by the relative positional relationship on the time axis of the determination date with respect to the process delivery date and the limit process delivery date, and the progress level is displayed on the display 110 for each job.

そして、第1実施形態では、判定日時が、
(A)先行負荷基準時刻以前、
(B)先行負荷基準時刻からボトルネック工程基準での工程納期までの間、
(C)ボトルネック工程基準での工程納期から限界工程納期までの間、
(D)限界工程納期以降、
の4段階で区別されている。これによって、同じ設備まで進捗したジョブごとの優先度を限界工程納期のみで設定された基準よりも細かい区分で評価できる。
In the first embodiment, the determination date is
(A) Before the preceding load reference time,
(B) From the preceding load reference time to the process delivery date based on the bottleneck process reference,
(C) From the process delivery date to the limit process delivery date based on the bottleneck process standard,
(D) After the critical process delivery date,
Are distinguished in four stages. As a result, the priority of each job that has progressed to the same equipment can be evaluated in a finer category than the standard set only by the limit process delivery date.

さらに、ジョブによって異なるボトルネック工程又はボトルネック工程以外の他の工程の負荷状況が、上記(A)〜(D)の基準に反映されている。このため、製品の種類によって、利用する設備又は順序が異なるジョブショップ型の生産工程に対しても、第1実施形態を容易に適用することができる。   Furthermore, the load status of the bottleneck process or the process other than the bottleneck process, which differs depending on the job, is reflected in the above criteria (A) to (D). For this reason, the first embodiment can be easily applied to a job shop type production process that uses different equipment or order depending on the type of product.

次に、第2実施形態における工程管理装置が、第1実施形態と異なる点を中心に説明される。第2実施形態の工程管理装置は、第1実施形態と同様に、複数の素材をジョブとして複数の工程(設備)で処理して複数の受注製品を並行して生産する、例えばジョブショップ型で多品種生産の工場において、各素材に対する処理の進捗状況を管理する。各受注製品は、受注製品ごとに予め定められた工程の順で素材が工程に対応する設備により処理されることによって生産される。   Next, the process management apparatus in the second embodiment will be described focusing on differences from the first embodiment. As in the first embodiment, the process management apparatus according to the second embodiment processes a plurality of materials as jobs in a plurality of processes (equipment) and produces a plurality of ordered products in parallel. For example, a job shop type Manages the progress of processing for each material in a multi-product production factory. Each ordered product is produced by processing the material by equipment corresponding to the process in the order of the process predetermined for each ordered product.

(構成)
図15は、第2実施形態における工程管理装置100の構成例を概略的に示すブロック図である。図15に示されるように、第2実施形態における工程管理装置100は、ディスプレイ110、入力部120、メモリ130、記憶装置140、及びCPU150を備える。
(Constitution)
FIG. 15 is a block diagram schematically showing a configuration example of the process management apparatus 100 in the second embodiment. As shown in FIG. 15, the process management apparatus 100 in the second embodiment includes a display 110, an input unit 120, a memory 130, a storage device 140, and a CPU 150.

メモリ130のROMは、CPU150を動作させる第2実施形態の制御プログラムを記憶する。CPU150は、年月日時をカウントする時計機能を有する。CPU150は、メモリ130に記憶された第2実施形態の制御プログラムにしたがって動作することによって、第1工程納期計算部151、先行負荷時間計算部152、第2工程納期計算部153、先行負荷基準時刻計算部154、進捗レベル計算部155、表示制御部156、最早完成基準時刻計算部157、進捗指数計算部158の機能を有する。最早完成基準時刻計算部157、進捗指数計算部158の各機能は、後述される。   The ROM of the memory 130 stores the control program according to the second embodiment that causes the CPU 150 to operate. The CPU 150 has a clock function that counts the date and time. The CPU 150 operates in accordance with the control program of the second embodiment stored in the memory 130, so that the first process delivery date calculation unit 151, the preceding load time calculation unit 152, the second process delivery date calculation unit 153, and the preceding load reference time It has functions of a calculation unit 154, a progress level calculation unit 155, a display control unit 156, an earliest completion reference time calculation unit 157, and a progress index calculation unit 158. The functions of the earliest completion reference time calculation unit 157 and the progress index calculation unit 158 will be described later.

ジョブデータ記憶部141は、更に、ジョブ毎に、最初の工程(つまり第1工程)に素材(ジョブ)が到着した到着日時(つまり第1工程にジョブが投入された投入日時)を予め記憶している。管理基準記憶部144は、更に、最早完成基準時刻計算部157の計算結果を記憶する。   The job data storage unit 141 further stores in advance the arrival date and time when the material (job) arrives at the first process (that is, the first process) for each job (that is, the date and time when the job was submitted to the first process). ing. The management reference storage unit 144 further stores the calculation result of the earliest completion reference time calculation unit 157.

図16は、最早完成基準時刻計算部157によって算出される最早完成基準時刻を概略的に示すタイミングチャートである。最早完成基準時刻計算部157は、ジョブ毎に、最初の工程(つまり第1工程)に素材(ジョブ)が到着した到着日時ATを起点とし、下流工程に対して最終工程まで順に標準工程間リードタイムSLTずつ経過した時刻を、それぞれ、最も早く処理が完了可能な最早完成基準時刻FTとして算出する。言い換えると、最早完成基準時刻計算部157は、工程納期とは関係なく、ジョブの第1工程への到着日時ATから直ぐに処理を開始し、以降の工程を標準工程間リードタイムSLTで処理した場合の各工程の処理終了時刻を、それぞれ、最早完成基準時刻FTとして算出する。最早完成基準時刻計算部157は、算出した最早完成基準時刻FTを管理基準記憶部144に保存する。   FIG. 16 is a timing chart schematically showing the earliest completion reference time calculated by the earliest completion reference time calculation unit 157. The earliest completion reference time calculation unit 157 reads, for each job, the standard inter-process lead in order from the downstream process to the final process starting from the arrival date and time AT when the material (job) arrives at the first process (that is, the first process). The time when each time SLT has elapsed is calculated as the earliest completion reference time FT at which processing can be completed earliest. In other words, the earliest completion reference time calculation unit 157 starts processing immediately from the arrival date and time AT of the job to the first process regardless of the process delivery date, and processes subsequent processes with the standard inter-process lead time SLT. The process end time of each process is calculated as the earliest completion reference time FT. The earliest completion reference time calculation unit 157 stores the calculated earliest completion reference time FT in the management reference storage unit 144.

図16において、一番右に示される限界工程納期PDTと、一番左に示される最早完成基準時刻FTとは、両方とも工程毎に標準工程間リードタイムSLTずつ経過しているので、互いに同じ形状のラインになっている。   In FIG. 16, the limit process delivery date PDT shown on the right and the earliest completion reference time FT shown on the left are both the same because the standard inter-process lead time SLT has elapsed for each process. It is a shape line.

第1工程納期計算部151、先行負荷時間計算部152、第2工程納期計算部153、先行負荷基準時刻計算部154、最早完成基準時刻計算部157による計算は、事前に、例えば現在(計算開始日)から1箇月先までの受注製品について行われる。一方、進捗レベル計算部155、表示制御部156、進捗指数計算部158の動作は、受注製品の製造中に、進捗状況を調べるために行われる。   The calculation by the first process delivery date calculation unit 151, the preceding load time calculation unit 152, the second process delivery date calculation unit 153, the preceding load reference time calculation unit 154, and the earliest completion reference time calculation unit 157 is performed in advance, for example, the present (calculation start) From 1 day to 1 month ahead. On the other hand, the operations of the progress level calculation unit 155, the display control unit 156, and the progress index calculation unit 158 are performed to check the progress status during the manufacture of the ordered product.

図17は、第2実施形態において、進捗レベル計算部155によって算出され、表示制御部156によってディスプレイ110に表示される、進捗レベルの表示例を概略的に示す図である。   FIG. 17 is a diagram schematically showing a display example of the progress level calculated by the progress level calculation unit 155 and displayed on the display 110 by the display control unit 156 in the second embodiment.

第2実施形態の進捗レベル計算部155は、例えば、入力部120を用いて進捗レベルの評価をユーザにより指示されると、CPU150から判定日時として現在日時を取得する。進捗レベル計算部155は、進捗データ記憶部145から、現在日時において各ジョブがどの工程(設備)に到着しているかという各ジョブの進捗状況を読み出す。進捗レベル計算部155は、読み出した各ジョブについて、到着している到着工程の限界工程納期PDT、ボトルネック工程基準での工程納期BNT、先行負荷基準時刻TP、最早完成基準時刻FTを管理基準記憶部144から読み出す。   The progress level calculation unit 155 of the second embodiment acquires the current date and time as the determination date and time from the CPU 150 when, for example, the user instructs the evaluation of the progress level using the input unit 120. The progress level calculation unit 155 reads from the progress data storage unit 145 the progress status of each job, which process (equipment) each job has reached at the current date and time. The progress level calculation unit 155 stores, for each read job, the limit process delivery date PDT of the arriving process that has arrived, the process delivery date BNT based on the bottleneck process standard, the preceding load reference time TP, and the earliest completion reference time FT. Read from the unit 144.

進捗レベル計算部155は、限界工程納期PDTと、ボトルネック工程基準での工程納期BNTと、先行負荷基準時刻TPと、最早完成基準時刻FTとに対する、時間軸上における現在日時(判定日時)の相対位置を算出する。進捗レベル計算部155は、算出した相対位置に応じて、第2実施形態では以下のように5段階として進捗レベルを算出する。   The progress level calculation unit 155 stores the current date and time (determination date) on the time axis with respect to the limit process delivery date PDT, the process delivery date BNT on the bottleneck process basis, the preceding load reference time TP, and the earliest completion reference time FT. The relative position is calculated. In accordance with the calculated relative position, the progress level calculation unit 155 calculates the progress level in five steps as follows in the second embodiment.

すなわち、進捗レベル計算部155は、現在日時が最早完成基準時刻FT以前であれば、処理を停止すべきことを表すレベルLV0(第0レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が、最早完成基準時刻FT以降であって先行負荷基準時刻TP以前であれば、進捗レベルを、急ぐ必要が無いことを表すレベルLV1(第1レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が、先行負荷基準時刻TP以降であってボトルネック工程基準での工程納期BNT以前であれば、進捗レベルを、処理可能であることを表すレベルLV2(第2レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が、ボトルネック工程基準での工程納期BNT以降であって限界工程納期PDT以前であれば、進捗レベルを、早目に処理すべきであることを表すレベルLV3(第3レベルの一例に相当)とする。進捗レベル計算部155は、現在日時が限界工程納期PDT以降であれば、進捗レベルを、急いで処理すべきであることを表すレベルLV4(第4レベルの一例に相当)とする。   That is, if the current date is before the earliest completion reference time FT, the progress level calculation unit 155 sets the level LV0 (corresponding to an example of the 0th level) indicating that the process should be stopped. If the current date and time is after the earliest completion reference time FT and before the preceding load reference time TP, the progress level calculation unit 155 indicates the level LV1 (as an example of the first level) indicating that there is no need to rush. Equivalent). If the current date and time is after the preceding load reference time TP and before the process delivery date BNT based on the bottleneck process reference, the progress level calculation unit 155 indicates the level LV2 (second Equivalent to an example of a level). The progress level calculation unit 155 indicates that if the current date and time is after the process delivery date BNT based on the bottleneck process criteria and before the limit process delivery date PDT, the progress level should be processed earlier LV3 (Corresponding to an example of the third level). If the current date and time is after the limit process delivery date PDT, the progress level calculation unit 155 sets the progress level to level LV4 (corresponding to an example of the fourth level) indicating that it should be processed quickly.

図17は、第1実施形態の図7と同様に、計算対象ジョブJBが設備3に到着しており、現在日時が3月10日である例を示す。図17では、現在日時が先行負荷基準時刻TP以降であってボトルネック工程基準での工程納期BNT以前である。したがって、進捗レベル計算部155は、ジョブJBの設備3における進捗レベルを、処理可能であることを表すレベルLV2とする。   FIG. 17 illustrates an example in which the calculation target job JB has arrived at the facility 3 and the current date and time is March 10 as in FIG. 7 of the first embodiment. In FIG. 17, the current date and time is after the preceding load reference time TP and before the process delivery date BNT based on the bottleneck process reference. Therefore, the progress level calculation unit 155 sets the progress level in the equipment 3 of the job JB to a level LV2 that represents that processing is possible.

表示制御部156は、ジョブ毎に、進捗レベル計算部155によって算出された進捗レベルをディスプレイ110に表示する。表示制御部156は、例えば図17をディスプレイ110に表示する。ディスプレイ110に表示された図17の画面を見ることによって、ユーザは、ジョブJBの設備3における進捗レベルが、レベルLV2であると理解する。   The display control unit 156 displays the progress level calculated by the progress level calculation unit 155 on the display 110 for each job. For example, the display control unit 156 displays FIG. 17 on the display 110. By viewing the screen of FIG. 17 displayed on the display 110, the user understands that the progress level of the equipment 3 of the job JB is the level LV2.

図18は、進捗指数計算部158によって算出され、表示制御部156によってディスプレイ110に表示される、進捗指数の表示例を概略的に示す図である。   FIG. 18 is a diagram schematically illustrating a display example of the progress index calculated by the progress index calculation unit 158 and displayed on the display 110 by the display control unit 156.

進捗指数の算出に用いられる基準指数は、予め定められた、進捗レベルの境界における進捗指数である。言い換えると、基準指数は、それぞれ予め定められた、最早完成基準時刻FT、先行負荷基準時刻TP、ボトルネック工程基準での工程納期BNT、限界工程納期PDTにおける進捗指数である。これらの予め定められた各基準指数は、例えば第2実施形態の制御プログラムの一部として、メモリ130のROMに保存されている。   The reference index used to calculate the progress index is a progress index at a boundary between progress levels, which is determined in advance. In other words, the reference index is a progress index at the earliest completion reference time FT, the preceding load reference time TP, the process delivery time BNT based on the bottleneck process reference, and the limit process delivery time PDT, which are respectively determined in advance. Each of these predetermined reference indices is stored in the ROM of the memory 130 as a part of the control program of the second embodiment, for example.

図18の例では、レベルLV0とレベルLV1との境界(最早完成基準時刻FT)の基準指数は「0」に定められている(第1基準指数の一例に相当)。また、レベルLV1とレベルLV2との境界(先行負荷基準時刻TP)の基準指数は「10」に定められている(第2基準指数の一例に相当)。また、レベルLV2とレベルLV3との境界(ボトルネック工程基準での工程納期BNT)の基準指数は「20」に定められている(第3基準指数の一例に相当)。また、レベルLV3とレベルLV4との境界(限界工程納期PDT)の基準指数は「30」に定められている(第4基準指数の一例に相当)。   In the example of FIG. 18, the reference index at the boundary between the level LV0 and the level LV1 (earliest completion reference time FT) is set to “0” (corresponding to an example of the first reference index). The reference index at the boundary between the level LV1 and the level LV2 (preceding load reference time TP) is set to “10” (corresponding to an example of the second reference index). Further, the reference index of the boundary between the level LV2 and the level LV3 (process delivery date BNT based on the bottleneck process reference) is set to “20” (corresponding to an example of the third reference index). Further, the reference index of the boundary between the level LV3 and the level LV4 (limit process delivery date PDT) is set to “30” (corresponding to an example of the fourth reference index).

進捗指数計算部158は、基準指数と基準指数との間の進捗指数を、2つの基準指数の線形補間によって算出する。進捗指数計算部158は、算出した基準指数をメモリ130のRAMに保存する。図18の例では、基準指数が「20」であるレベルLV2とレベルLV3との境界は4月10日になっており、基準指数が「30」であるレベルLV3とレベルLV4との境界は4月20になっている。したがって、進捗指数計算部158は、判定日時(現在日時)である4月16日の進捗指数を、基準指数「20」と基準指数「30」との線形補間によって、進捗指数「26」と算出する。   The progress index calculator 158 calculates a progress index between the reference index and the reference index by linear interpolation of the two reference indexes. The progress index calculation unit 158 stores the calculated reference index in the RAM of the memory 130. In the example of FIG. 18, the boundary between the level LV2 and the level LV3 with the reference index “20” is April 10, and the boundary between the level LV3 and the level LV4 with the reference index “30” is 4. The month is 20th. Therefore, the progress index calculation unit 158 calculates the progress index of April 16, which is the determination date (current date), as the progress index “26” by linear interpolation between the reference index “20” and the reference index “30”. To do.

なお、基準指数は、図18の例に限られない。基準指数と基準指数との間の進捗指数が線形補間によって適切に算出されるように、2つの基準指数の間に差異が設けられていればよい。   The reference index is not limited to the example of FIG. It is sufficient that a difference is provided between the two reference indexes so that the progress index between the reference index and the progress index is appropriately calculated by linear interpolation.

(進捗指数の具体例)
2つのジョブのある工程における進捗レベルが同じであっても、進捗指数計算部158によって算出される進捗指数の異なるケースが、図19を用いて説明される。
(Specific example of progress index)
A case where the progress index calculated by the progress index calculation unit 158 is different even when the progress levels in a certain process of two jobs are the same will be described with reference to FIG.

図19は、進捗レベルが同じレベルLV3であるジョブJB3,JB4の進捗指数を概略的に示すタイミングチャートである。図19において、最早完成基準時刻FTは、ジョブJB3,JB4ともに同じ3月3日であり、限界工程納期PDTは、ジョブJB3,JB4ともに同じ3月13日である。また、判定日時である3月10日には、ジョブJB3,JB4ともに設備3まで進捗しており、進捗レベルは、同じレベルLV3である。   FIG. 19 is a timing chart schematically showing progress indexes of jobs JB3 and JB4 having the same progress level LV3. In FIG. 19, the earliest completion reference time FT is the same March 3 for both jobs JB3 and JB4, and the limit process delivery date PDT is the same March 13 for both jobs JB3 and JB4. On March 10, which is the determination date, both the jobs JB3 and JB4 have progressed to the facility 3, and the progress level is the same level LV3.

一方、ジョブJB3の進捗指数は「22」、ジョブJB4の進捗指数は「25」になっている。すなわち、限界工程納期PDT及び進捗レベルが同じであっても、ジョブJB4の方を優先すべきであることが分かる。これは,ジョブJB4の方が、ボトルネック工程基準での工程納期BNTからの遅れが相対的に大きく,ボトルネック工程に対する処理を早く進める必要性が高いためである。   On the other hand, the progress index of job JB3 is “22”, and the progress index of job JB4 is “25”. That is, it can be understood that the job JB4 should be prioritized even if the limit process delivery date PDT and the progress level are the same. This is because the job JB4 has a relatively large delay from the process delivery date BNT based on the bottleneck process standard, and it is highly necessary to advance the process for the bottleneck process earlier.

(動作)
図20、図21は、図15に示される工程管理装置100の第1工程納期計算部151、先行負荷時間計算部152、第2工程納期計算部153、先行負荷基準時刻計算部154、最早完成基準時刻計算部157による第2実施形態の動作を概略的に示すフローチャートである。なお、第2実施形態でも、第1実施形態と同様に、第1工程納期計算部151、先行負荷時間計算部152により図8の動作が行われ、第2工程納期計算部153により図9の動作が行われる。第2実施形態でも、第1実施形態と同様に、例えば、入力部120を用いてユーザにより指示されると、図8の動作が開始される。
(Operation)
20 and 21 show the first process delivery date calculation unit 151, the preceding load time calculation unit 152, the second process delivery date calculation unit 153, the preceding load reference time calculation unit 154, and the earliest completion of the process management apparatus 100 shown in FIG. 7 is a flowchart schematically showing the operation of the second embodiment by a reference time calculation unit 157. In the second embodiment, as in the first embodiment, the operation shown in FIG. 8 is performed by the first process delivery date calculation unit 151 and the preceding load time calculation unit 152, and the second process delivery date calculation unit 153 performs the operation shown in FIG. Operation is performed. In the second embodiment, as in the first embodiment, for example, when an instruction is given by the user using the input unit 120, the operation of FIG. 8 is started.

第2実施形態において、図9のステップS920でYESになると、処理は、図20のステップS1005に進む。図20のステップS1005〜S1055は、図10のステップS1005〜S1055と同じである。図20のステップS1050において、全てのジョブについて終了すると(ステップS1050でYES)、処理は図21のステップS2100に進む。   In the second embodiment, if “YES” is determined in the step S920 in FIG. 9, the process proceeds to a step S1005 in FIG. Steps S1005 to S1055 in FIG. 20 are the same as steps S1005 to S1055 in FIG. In step S1050 in FIG. 20, when all the jobs are completed (YES in step S1050), the process proceeds to step S2100 in FIG.

図21のステップS2100において、最早完成基準時刻計算部157は、計算対象ジョブとして、最初のジョブを設定する。ステップS2105において、最早完成基準時刻計算部157は、設定されたジョブの第1工程への到着日時をジョブデータ記憶部141から取得する。ステップS2110において、最早完成基準時刻計算部157は、設定されたジョブにおける全ての工程間における標準工程間リードタイムを工程間リードタイム記憶部142から取得する。   In step S2100 of FIG. 21, the earliest completion reference time calculation unit 157 sets the first job as the calculation target job. In step S2105, the earliest completion reference time calculation unit 157 acquires the arrival date and time of the set job at the first step from the job data storage unit 141. In step S2110, the earliest completion reference time calculation unit 157 acquires the standard inter-process lead time between all processes in the set job from the inter-process lead time storage unit 142.

ステップS2115において、最早完成基準時刻計算部157は、設定されたジョブにおける第2工程以降の全ての工程について最早完成基準時刻FTを算出する。最早完成基準時刻計算部157は、算出した全ての工程の最早完成基準時刻FTを、設定されたジョブに対応付けて、管理基準記憶部144に保存する。   In step S2115, the earliest completion reference time calculation unit 157 calculates the earliest completion reference time FT for all processes after the second process in the set job. The earliest completion reference time calculation unit 157 stores the calculated earliest completion reference times FT of all processes in the management reference storage unit 144 in association with the set job.

ステップS2120において、最早完成基準時刻計算部157は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS2120でNO)、処理は、ステップS2125に進む。ステップS2125において、最早完成基準時刻計算部157は、計算対象ジョブとして、次のジョブを設定する。その後、処理はステップS2105に戻って、以上のステップが繰り返される。一方、全てのジョブについて終了していれば(ステップS2120でYES)、処理は終了する。   In step S2120, the earliest completion reference time calculation unit 157 determines whether or not all jobs have been completed. If all jobs have not been completed (NO in step S2120), the process proceeds to step S2125. In step S2125, the earliest completion reference time calculation unit 157 sets the next job as a calculation target job. Thereafter, the process returns to step S2105, and the above steps are repeated. On the other hand, if all jobs have been completed (YES in step S2120), the process ends.

図22は、図15に示される工程管理装置100の進捗レベル計算部155、表示制御部156、進捗指数計算部158による第2実施形態の動作を概略的に示すフローチャートである。例えば、入力部120を用いて進捗レベル及び進捗指数の表示が指示されると、図22の動作が開始される。   FIG. 22 is a flowchart schematically showing the operation of the second embodiment by the progress level calculation unit 155, the display control unit 156, and the progress index calculation unit 158 of the process management apparatus 100 shown in FIG. For example, when the display of the progress level and the progress index is instructed using the input unit 120, the operation of FIG. 22 is started.

図22のステップS1100〜S1110は、図11のステップS1100〜S1110と同じである。ステップS1110に続くステップS2200において、進捗レベル計算部155は、設定されたジョブが到着している工程(設備)の最早完成基準時刻と、先行負荷基準時刻と、ボトルネック工程基準での工程納期と、限界工程納期とを、管理基準記憶部144から取得する。   Steps S1100 to S1110 in FIG. 22 are the same as steps S1100 to S1110 in FIG. In step S2200 following step S1110, the progress level calculation unit 155 determines the earliest completion reference time of the process (equipment) where the set job has arrived, the preceding load reference time, the process delivery date based on the bottleneck process reference, The limit process delivery date is acquired from the management reference storage unit 144.

ステップS2205において、進捗レベル計算部155は、最早完成基準時刻と、先行負荷基準時刻と、ボトルネック工程基準での工程納期と、限界工程納期とに対する、時間軸上における判定日時の相対位置を算出する。ステップS2210において、進捗レベル計算部155は、算出した相対位置に基づき進捗レベルを算出し、算出した進捗レベルをメモリ130のRAMに保存する。ステップS2215において、進捗指数計算部158は、進捗指数を算出し、算出した進捗指数をメモリ130のRAMに保存する。   In step S2205, the progress level calculation unit 155 calculates the relative position of the determination date and time on the time axis with respect to the earliest completion reference time, the preceding load reference time, the process delivery date based on the bottleneck process criteria, and the limit process delivery date. To do. In step S <b> 2210, the progress level calculation unit 155 calculates the progress level based on the calculated relative position, and stores the calculated progress level in the RAM of the memory 130. In step S2215, the progress index calculation unit 158 calculates a progress index and stores the calculated progress index in the RAM of the memory 130.

ステップS2220において、進捗レベル計算部155は、全てのジョブについて終了したか否かを判定する。全てのジョブについて終了していなければ(ステップS2220でNO)、処理は、ステップS2225に進む。ステップS2225において、進捗レベル計算部155は、計算対象ジョブとして、次のジョブを設定する。その後、処理はステップS1110に戻って、以上のステップが繰り返される。   In step S2220, progress level calculation unit 155 determines whether or not all jobs have been completed. If all the jobs have not been completed (NO in step S2220), the process proceeds to step S2225. In step S2225, the progress level calculation unit 155 sets the next job as a calculation target job. Thereafter, the process returns to step S1110, and the above steps are repeated.

一方、全てのジョブについて終了していれば(ステップS2220でYES)、処理はステップS2210に進む。ステップS2210において、表示制御部156は、ジョブ毎に、進捗レベル及び進捗指数をディスプレイ110に表示する。その後、図22の処理は終了する。   On the other hand, if all the jobs have been completed (YES in step S2220), the process proceeds to step S2210. In step S2210, the display control unit 156 displays a progress level and a progress index on the display 110 for each job. Thereafter, the process of FIG. 22 ends.

(効果)
以上説明されたように、第2実施形態では、最早完成基準時刻計算部157は、第1工程へのジョブの到着日時(投入日時)を起点とし、標準工程間リードタイムSLTを加算した時刻を第2工程の処理終了時刻として算出し、これを最終工程まで繰り返すことによって決まる各工程の処理終了時刻を、最早完成基準時刻FTとして算出する。
(effect)
As described above, in the second embodiment, the earliest completion reference time calculation unit 157 uses the arrival date and time (input date and time) of the job to the first process as a starting point, and the time obtained by adding the standard inter-process lead time SLT. The process end time of the second process is calculated, and the process end time of each process determined by repeating this process until the final process is calculated as the earliest completion reference time FT.

言い換えると、最早完成基準時刻は、到着日時(投入日時)から直ぐに処理を開始し、その後は、工程納期とは関係なく標準工程間リードタイムで生産を進めた場合(つまり最早で完成させて出荷する場合)の基準時刻となる。この場合において、標準工程間リードタイムも最短時間に設定すると、最早完成基準時刻は、特急で生産する場合の基準時刻を意味することになる。   In other words, the earliest completion reference time starts processing immediately from the arrival date and time (input date and time), and after that, when the production is advanced with the lead time between standard processes regardless of the process delivery date (that is, completed and shipped as soon as possible) The reference time of In this case, if the lead time between the standard processes is also set to the shortest time, the earliest completion reference time means the reference time for production on the express.

このように、第2実施形態によれば、工程納期とは関係なく、優先的に処理を進めた場合の処理のタイミング(基準時刻)に対して,工程納期を守るための処理のタイミング(基準時刻)の余裕度合を判断することができる。このため、工程納期を順守することの難しさを把握することができる。   As described above, according to the second embodiment, the process timing (reference) for keeping the process delivery date with respect to the process timing (reference time) when the process is preferentially advanced regardless of the process delivery date. Time) can be determined. For this reason, it is possible to grasp the difficulty of complying with the process delivery date.

(変形された実施形態)
(1)上記第1、第2実施形態では、先行負荷時間計算部152は、標準処理時間を稼働率で除算した実働処理時間の合計時間を先行負荷時間としているが、これに限られない。先行負荷時間計算部152は、稼働率で除算せずに、標準処理時間の合計時間を先行負荷時間としてもよい。この場合には、稼働率記憶部143(図1)を備えなくてもよい。
(Modified embodiment)
(1) In the first and second embodiments, the preceding load time calculation unit 152 uses the total time of the actual processing time obtained by dividing the standard processing time by the operating rate as the preceding load time, but is not limited thereto. The preceding load time calculation unit 152 may use the total time of the standard processing times as the preceding load time without dividing by the operation rate. In this case, the operation rate storage unit 143 (FIG. 1) may not be provided.

(2)上記第1実施形態では、表示制御部156は、進捗レベル計算部155によって算出された進捗レベルを、図7に示されるような表示形態でディスプレイ110に表示しているが、これに限られない。表示制御部156は、例えば、計算対象のジョブ及び工程(設備)と、進捗レベルとが対応づけられた表形式でディスプレイ110に表示してもよい。   (2) In the first embodiment, the display control unit 156 displays the progress level calculated by the progress level calculation unit 155 on the display 110 in a display form as shown in FIG. Not limited. For example, the display control unit 156 may display the calculation target job and process (equipment) on the display 110 in a table format in which the progress level is associated.

同様に、上記第2実施形態では、表示制御部156は、進捗レベル計算部155によって算出された進捗レベルと、進捗指数計算部158によって算出された進捗指数とを、図18に示されるような表示形態でディスプレイ110に表示しているが、これに限られない。表示制御部156は、例えば、計算対象のジョブ及び工程(設備)と、進捗レベルと、進捗指数とが対応づけられた表形式でディスプレイ110に表示してもよい。   Similarly, in the second embodiment, the display control unit 156 displays the progress level calculated by the progress level calculation unit 155 and the progress index calculated by the progress index calculation unit 158 as shown in FIG. Although it is displayed on the display 110 in a display form, it is not limited to this. For example, the display control unit 156 may display the display 110 in a table format in which jobs and processes (equipment) to be calculated, a progress level, and a progress index are associated with each other.

100 工程管理装置
110 ディスプレイ
141 ジョブデータ記憶部
143 稼働率記憶部
144 管理基準記憶部
145 進捗データ記憶部
150 CPU
151 第1工程納期計算部
152 先行負荷時間計算部
153 第2工程納期計算部
154 先行負荷基準時刻計算部
155 進捗レベル計算部
156 表示制御部
157 最早完成基準時刻計算部
158 進捗指数計算部
DESCRIPTION OF SYMBOLS 100 Process management apparatus 110 Display 141 Job data memory | storage part 143 Operation rate memory | storage part 144 Management reference | standard storage part 145 Progress data memory | storage part 150 CPU
151 First Process Delivery Time Calculation Unit 152 Advance Load Time Calculation Unit 153 2nd Process Delivery Time Calculation Unit 154 Advance Load Reference Time Calculation Unit 155 Progress Level Calculation Unit 156 Display Control Unit 157 Earlier Completion Reference Time Calculation Unit 158 Progress Index Calculation Unit

Claims (8)

複数の素材をそれぞれジョブとして所定の複数工程において所定の順番で処理することにより複数の異なる製品を並行して生産する工場における複数の前記ジョブの進捗状況を管理する工程管理装置であって、
前記ジョブ毎に、最終工程での出荷納期を起点とし、上流工程に対して第1工程まで順に標準工程間リードタイムずつ遡った時刻を、それぞれ、前記出荷納期に間に合うために最も遅く処理完了可能な限界工程納期として算出する第1工程納期計算部と、
前記ジョブ毎に、各工程において計算対象ジョブの前記限界工程納期よりも早い前記限界工程納期を持つ前記計算対象ジョブ以外の他ジョブの前記工程における標準処理時間に関連する関連時間の合計を先行負荷時間として算出する先行負荷時間計算部と、
前記ジョブ毎に、前記計算対象ジョブの各工程において、所定の基準日時に前記先行負荷時間を加算した時刻と前記限界工程納期との時間差をそれぞれ算出し、前記時間差のうち最小値を抽出し、前記計算対象ジョブの各工程において、前記限界工程納期から前記最小値遡った時刻をそれぞれボトルネック工程基準での工程納期として算出する第2工程納期計算部と、
前記ジョブ毎に、第1工程においては、前記基準日時に前記先行負荷時間を加算した時刻を先行負荷基準時刻として算出し、第N(Nは2以上かつ前記計算対象ジョブの工程数以下の整数)工程においては、第(N−1)工程の先行負荷基準時刻に第(N−1)工程から第N工程までの標準工程間リードタイムを加算した時刻と、前記基準日時に第N工程における前記先行負荷時間を加算した時刻とのうち遅い方を先行負荷基準時刻として算出する先行負荷基準時刻計算部と、
前記ジョブ毎に、所定の判定日時に前記ジョブが到着している工程において、前記先行負荷基準時刻と前記ボトルネック工程基準での工程納期と前記限界工程納期とに対する、時間軸上における前記判定日時の相対位置を算出し、前記相対位置に応じた進捗レベルを算出する進捗レベル計算部と、
を備える工程管理装置。
A process management apparatus that manages the progress of a plurality of jobs in a factory that produces a plurality of different products in parallel by processing a plurality of materials as jobs in a predetermined order in a plurality of processes,
For each job, starting from the delivery date of the final process, the time that has been traced back to the first process by the lead time between the standard processes in order from the upstream process can be completed most recently to meet the delivery date of delivery. A first process delivery date calculation unit for calculating a critical process delivery time;
For each job, a preload is added to the total related time related to the standard processing time in the process of other jobs other than the calculation target job having the limit process delivery time earlier than the limit process delivery time of the calculation target job in each process. A preload time calculation unit to calculate as time,
For each job, in each process of the calculation target job, calculate a time difference between the time when the preceding load time is added to a predetermined reference date and the limit process delivery time, and extract a minimum value among the time differences, In each process of the calculation target job, a second process delivery date calculation unit that calculates a time that is traced back from the minimum process delivery date as the process delivery date on the bottleneck process basis,
For each job, in the first step, a time obtained by adding the preceding load time to the reference date and time is calculated as a preceding load reference time, and an Nth (N is an integer not less than 2 and not more than the number of steps of the calculation target job) ) In the process, the time obtained by adding the standard inter-process lead time from the (N-1) process to the Nth process to the preceding load reference time of the (N-1) process, and the reference date and time in the Nth process. A preceding load reference time calculation unit that calculates a later one of the times obtained by adding the preceding load times as a preceding load reference time;
In the process in which the job arrives at a predetermined determination date for each job, the determination date on the time axis with respect to the preceding load reference time, the process delivery date based on the bottleneck process criteria, and the limit process delivery date A progress level calculation unit that calculates a relative position of the target and calculates a progress level according to the relative position;
A process management apparatus comprising:
前記進捗レベル計算部は、処理の緊急度を表す指標である複数のレベルに区分して前記進捗レベルを算出し、
前記複数のレベルは、前記処理の緊急度が高くなる順に、第1レベルから第4レベルを含み、
前記進捗レベル計算部は、算出する前記進捗レベルを、前記判定日時が前記先行負荷基準時刻以前のときは、前記第1レベルとし、前記判定日時が前記先行負荷基準時刻以降であって、かつ前記ボトルネック工程基準での工程納期以前のときは、前記第2レベルとし、前記判定日時が前記ボトルネック工程基準での工程納期以降であって、かつ前記限界工程納期以前のときは、前記第3レベルとし、前記判定日時が前記限界工程納期以降のときは、前記第4レベルとする、
請求項1に記載の工程管理装置。
The progress level calculation unit calculates the progress level by dividing it into a plurality of levels that are indices indicating the urgency of processing,
The plurality of levels include a first level to a fourth level in order of increasing urgency of the processing,
The progress level calculation unit sets the progress level to be calculated as the first level when the determination date is before the preceding load reference time, the determination date is after the preceding load reference time, and When it is before the process delivery date based on the bottleneck process standard, the second level is set. When the determination date is after the process delivery date based on the bottleneck process standard and before the limit process delivery date, the third level is set. And when the determination date and time is after the critical process delivery date, the fourth level,
The process management apparatus according to claim 1.
前記ジョブ毎に、前記判定日時に前記ジョブが到着している工程である到着工程を記憶する進捗データ記憶部と、
前記ジョブ毎に、前記限界工程納期と、前記ボトルネック工程基準での工程納期と、前記先行負荷基準時刻とを記憶する管理基準記憶部と、をさらに備え、
前記第1工程納期計算部は、前記ジョブ毎に、算出した前記限界工程納期を前記管理基準記憶部に保存し、
前記第2工程納期計算部は、前記ジョブ毎に、算出した前記ボトルネック工程基準での工程納期を前記管理基準記憶部に保存し、
前記先行負荷基準時刻計算部は、前記ジョブ毎に、算出した前記先行負荷基準時刻を前記管理基準記憶部に保存し、
前記進捗レベル計算部は、前記ジョブ毎に、前記到着工程を前記進捗データ記憶部から読み出し、読み出した前記到着工程に対応する前記限界工程納期と、前記ボトルネック工程基準での工程納期と、前記先行負荷基準時刻とを前記管理基準記憶部から読み出して、前記到着工程における前記進捗レベルを算出する、
請求項1又は2に記載の工程管理装置。
For each job, a progress data storage unit that stores an arrival process that is a process in which the job arrives at the determination date and time,
For each of the jobs, a management criterion storage unit that stores the marginal process delivery date, the process delivery date based on the bottleneck process criteria, and the preceding load reference time is further provided.
The first process delivery date calculation unit stores the calculated limit process delivery date in the management reference storage unit for each job,
The second process delivery date calculation unit stores, for each job, the calculated process delivery date based on the bottleneck process standard in the management standard storage unit,
The preceding load reference time calculation unit stores the calculated preceding load reference time in the management reference storage unit for each job,
The progress level calculation unit reads, for each job, the arrival process from the progress data storage unit, the limit process delivery date corresponding to the read arrival process, the process delivery date based on the bottleneck process standard, Read the preceding load reference time from the management reference storage unit, and calculate the progress level in the arrival process,
The process management apparatus according to claim 1.
前記ジョブ毎に、前記ジョブが第1工程に到着した到着日時を起点とし、下流工程に対して最終工程まで順に前記標準工程間リードタイムずつ経過した時刻を、それぞれ、最も早く処理が完了可能な最早完成基準時刻として算出する最早完成基準時刻計算部を更に備え、
前記複数のレベルは、前記処理の緊急度が前記第1レベルより低い第0レベルを更に含み、
前記進捗レベル計算部は、前記ジョブ毎に、前記判定日時に前記ジョブが到着している工程において、更に、前記最早完成基準時刻に対する、時間軸上における前記判定日時の相対位置を算出し、前記相対位置に応じた前記進捗レベルを算出し、
前記進捗レベル計算部は、前記進捗レベルを、前記判定日時が、前記先行負荷基準時刻以前のうちで、前記最早完成基準時刻以降のときを前記第1レベルとし、前記最早完成基準時刻以前のときを前記第0レベルとする、
請求項2に記載の工程管理装置。
For each job, the time at which the standard process lead time elapses in order from the downstream process to the final process, starting from the arrival date and time when the job arrived at the first process, can be completed earliest. It further includes an earliest completion reference time calculation unit that calculates the earliest completion reference time.
The plurality of levels further includes a 0th level in which the urgency level of the processing is lower than the first level,
The progress level calculation unit further calculates a relative position of the determination date and time on the time axis with respect to the earliest completion reference time in the process in which the job arrives at the determination date and time for each job, Calculate the progress level according to the relative position,
The progress level calculation unit sets the progress level as the first level when the determination date and time is after the earliest completion reference time before the preceding load reference time, and before the earliest completion reference time. Is the 0th level,
The process management apparatus according to claim 2.
前記ジョブ毎に、前記判定日時に前記ジョブが到着している工程において、進捗度合いを表す進捗指数を算出する進捗指数計算部を更に備え、
前記進捗指数計算部は、
前記判定日時が前記最早完成基準時刻のときは、前記進捗指数を所定の第1基準指数とし、
前記判定日時が前記先行負荷基準時刻のときは、前記進捗指数を前記第1基準指数より大きい所定の第2基準指数とし、
前記判定日時が前記ボトルネック工程基準での工程納期のときは、前記進捗指数を前記第2基準指数より大きい所定の第3基準指数とし、
前記判定日時が前記限界工程納期のときは、前記進捗指数を前記第3基準指数より大きい所定の第4基準指数とし、
前記判定日時が前記最早完成基準時刻と前記先行負荷基準時刻との間のときは、前記進捗指数を前記第1基準指数と前記第2基準指数とで線形補間した第1補間値とし、
前記判定日時が前記先行負荷基準時刻と前記ボトルネック工程基準での工程納期との間のときは、前記進捗指数を前記第2基準指数と前記第3基準指数とで線形補間した第2補間値とし、
前記判定日時が前記ボトルネック工程基準での工程納期と前記限界工程納期との間のときは、前記進捗指数を前記第3基準指数と前記第4基準指数とで線形補間した第3補間値とする、
請求項4に記載の工程管理装置。
A progress index calculation unit that calculates a progress index representing the degree of progress in the process where the job arrives at the determination date and time for each job,
The progress index calculator is
When the determination date and time is the earliest completion reference time, the progress index is a predetermined first reference index,
When the determination date and time is the preceding load reference time, the progress index is a predetermined second reference index larger than the first reference index,
When the determination date and time is a process delivery date based on the bottleneck process standard, the progress index is a predetermined third standard index greater than the second standard index,
When the determination date and time is the critical process delivery date, the progress index is set as a predetermined fourth reference index larger than the third reference index,
When the determination date is between the earliest completion reference time and the preceding load reference time, the progress index is a first interpolation value obtained by linear interpolation between the first reference index and the second reference index,
A second interpolation value obtained by linearly interpolating the progress index with the second reference index and the third reference index when the determination date / time is between the preceding load reference time and the process delivery date based on the bottleneck process reference age,
A third interpolation value obtained by linearly interpolating the progress index with the third reference index and the fourth reference index when the determination date is between the process delivery date and the limit process delivery date based on the bottleneck process criterion; To
The process management apparatus according to claim 4.
情報を表示する表示部と、
前記ジョブ毎に、前記進捗レベルを前記表示部に表示する表示制御部と、
をさらに備える請求項1〜5のいずれか1項に記載の工程管理装置。
A display for displaying information;
A display control unit for displaying the progress level on the display unit for each job;
The process management apparatus according to any one of claims 1 to 5, further comprising:
予め設定された、前記工程で用いられる設備の稼働率を前記工程毎に記憶する稼働率記憶部と、
前記ジョブ毎に、前記各工程での処理に要する標準処理時間を記憶するジョブデータ記憶部と、をさらに備え、
前記先行負荷時間計算部は、計算対象工程で用いられる設備の稼働率を前記稼働率記憶部から読み出し、計算対象工程での処理に要する前記標準処理時間を前記ジョブデータ記憶部から読み出し、前記標準処理時間を前記稼働率で除算した時間を前記関連時間として用いる、
請求項1〜6のいずれか1項に記載の工程管理装置。
An operation rate storage unit that stores the operation rate of equipment used in the process set in advance for each process,
A job data storage unit for storing a standard processing time required for processing in each step for each job;
The preceding load time calculation unit reads the operation rate of equipment used in the calculation target process from the operation rate storage unit, reads the standard processing time required for processing in the calculation target process from the job data storage unit, and The time obtained by dividing the processing time by the operating rate is used as the related time.
The process management apparatus of any one of Claims 1-6.
複数の素材をそれぞれジョブとして所定の複数工程において所定の順番で処理することにより複数の異なる製品を並行して生産する工場における複数の前記ジョブの進捗状況を管理する工程管理方法であって、
前記ジョブ毎に、最終工程での出荷納期を起点とし、上流工程に対して第1工程まで順に標準工程間リードタイムずつ遡った時刻を、それぞれ、前記出荷納期に間に合うために最も遅く処理完了可能な限界工程納期として算出する第1工程納期計算ステップと、
前記ジョブ毎に、各工程において計算対象ジョブの前記限界工程納期よりも早い前記限界工程納期を持つ前記計算対象ジョブ以外の他ジョブの前記工程における標準処理時間に関連する関連時間の合計を先行負荷時間として算出する先行負荷時間計算ステップと、
前記ジョブ毎に、前記計算対象ジョブの各工程において、所定の基準日時に前記先行負荷時間を加算した時刻と前記限界工程納期との時間差をそれぞれ算出し、前記時間差のうち最小値を抽出し、前記計算対象ジョブの各工程において、前記限界工程納期から前記最小値遡った時刻をそれぞれボトルネック工程基準での工程納期として算出する第2工程納期計算ステップと、
前記ジョブ毎に、第1工程においては、前記基準日時に前記先行負荷時間を加算した時刻を先行負荷基準時刻として算出し、第N(Nは2以上かつ前記ジョブの工程数以下の整数)工程においては、第(N−1)工程の先行負荷基準時刻に第(N−1)工程から第N工程までの標準工程間リードタイムを加算した時刻と、前記基準日時に第N工程における前記先行負荷時間を加算した時刻とのうち遅い方を先行負荷基準時刻として算出する先行負荷基準時刻計算ステップと、
前記ジョブ毎に、所定の判定日時に前記ジョブが到着している工程において、前記先行負荷基準時刻と前記ボトルネック工程基準での工程納期と前記限界工程納期とに対する、時間軸上における前記判定日時の相対位置を算出し、前記相対位置に応じた進捗レベルを算出する進捗レベル計算ステップと、
を備える工程管理方法。
A process management method for managing the progress of a plurality of jobs in a factory that produces a plurality of different products in parallel by processing a plurality of materials as jobs in a predetermined order in a predetermined plurality of steps,
For each job, starting from the delivery date of the final process, the time that has been traced back to the first process by the lead time between the standard processes in order from the upstream process can be completed most recently to meet the delivery date of delivery. A first process delivery date calculation step for calculating a critical process delivery time;
For each job, a preload is added to the total related time related to the standard processing time in the process of other jobs other than the calculation target job having the limit process delivery time earlier than the limit process delivery time of the calculation target job in each process. A preload time calculation step to calculate as time,
For each job, in each process of the calculation target job, calculate a time difference between the time when the preceding load time is added to a predetermined reference date and the limit process delivery time, and extract a minimum value among the time differences, In each process of the calculation target job, a second process delivery date calculation step for calculating a time that is traced back from the minimum process delivery date as the process delivery date on the bottleneck process basis,
For each job, in the first step, a time obtained by adding the preceding load time to the reference date and time is calculated as a preceding load reference time, and the Nth (N is an integer not less than 2 and not more than the number of steps of the job) step , The time obtained by adding the lead time between standard processes from the (N-1) process to the Nth process to the preceding load reference time of the (N-1) process, and the preceding in the Nth process at the reference date and time. A preceding load reference time calculating step for calculating a later one of the times obtained by adding the load times as a preceding load reference time;
In the process in which the job arrives at a predetermined determination date for each job, the determination date on the time axis with respect to the preceding load reference time, the process delivery date based on the bottleneck process criteria, and the limit process delivery date A progress level calculating step of calculating a relative position of the target and calculating a progress level according to the relative position;
A process management method comprising:
JP2017161236A 2017-08-24 2017-08-24 Process control equipment and method Active JP6811693B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017161236A JP6811693B2 (en) 2017-08-24 2017-08-24 Process control equipment and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017161236A JP6811693B2 (en) 2017-08-24 2017-08-24 Process control equipment and method

Publications (2)

Publication Number Publication Date
JP2019040345A true JP2019040345A (en) 2019-03-14
JP6811693B2 JP6811693B2 (en) 2021-01-13

Family

ID=65726531

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017161236A Active JP6811693B2 (en) 2017-08-24 2017-08-24 Process control equipment and method

Country Status (1)

Country Link
JP (1) JP6811693B2 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63298665A (en) * 1987-05-29 1988-12-06 Kanebo Ltd Production planning device
JPH08215994A (en) * 1995-02-10 1996-08-27 Nippondenso Co Ltd Scheduler support system and method therof
JPH10307862A (en) * 1997-05-06 1998-11-17 Kubota Corp Method for preparing production plan
JP2003058228A (en) * 2001-08-15 2003-02-28 Fujitsu Ten Ltd Product progress management method and device
JP2004030199A (en) * 2002-06-25 2004-01-29 Jfe Steel Kk System and method for creating production plan
JP2009157871A (en) * 2007-12-28 2009-07-16 Panasonic Corp Production management method
JP2010020665A (en) * 2008-07-14 2010-01-28 Seiko Epson Corp Production management method, production management system, and production management program

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63298665A (en) * 1987-05-29 1988-12-06 Kanebo Ltd Production planning device
JPH08215994A (en) * 1995-02-10 1996-08-27 Nippondenso Co Ltd Scheduler support system and method therof
JPH10307862A (en) * 1997-05-06 1998-11-17 Kubota Corp Method for preparing production plan
JP2003058228A (en) * 2001-08-15 2003-02-28 Fujitsu Ten Ltd Product progress management method and device
JP2004030199A (en) * 2002-06-25 2004-01-29 Jfe Steel Kk System and method for creating production plan
JP2009157871A (en) * 2007-12-28 2009-07-16 Panasonic Corp Production management method
JP2010020665A (en) * 2008-07-14 2010-01-28 Seiko Epson Corp Production management method, production management system, and production management program

Also Published As

Publication number Publication date
JP6811693B2 (en) 2021-01-13

Similar Documents

Publication Publication Date Title
JP6677743B2 (en) Data processing method and device
WO2012032827A1 (en) Production schedule creating method and apparatus therefor
WO2008060861A2 (en) Method and system for analyzing schedule trends
JP2015005085A (en) Scheduling method and scheduling device
JP2019040345A (en) Process management device and method
JP2015075868A (en) Schedule display device, method and program
JP6570775B1 (en) Process determination support device, process determination support method, process determination support program, and storage medium
US20160033961A1 (en) Production Control Support Apparatus and Production Control Support Method
JP6214835B2 (en) Work guidance assignment system and work guidance assignment method
JP2010257383A (en) Scheduling method, scheduling program, and scheduling system
JP2010262426A (en) Method, program and device for preparing production plan
CN109074053A (en) Product puts into plan device, product investment ways to draw up the plan and product and puts into scheduling program
JP2011096108A (en) System and program for supporting decision making for change of production plan
JP6729703B2 (en) Information presenting method, device, and program
JP2015109056A (en) Production plan creation method, production plan creation program, and production plan creation device
JP2011175354A (en) Priority determination device
JP2017027412A (en) Display information control program, method and device
JP2017072927A (en) Schedule correction support device and method
JP2006155011A (en) Production schedule planning device, and production schedule planning method
JP6729330B2 (en) Manufacturing term prediction device, manufacturing term prediction method, and computer program
JP6691496B2 (en) Start rule changing device and production control system
CN106156000A (en) Searching method based on intersection algorithm and search system
JP4757883B2 (en) Mold life prediction result calculation apparatus and life prediction result calculation program
JP7420257B2 (en) Solving system, solving method, and solving program
JP5984686B2 (en) Information processing apparatus and program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190930

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201012

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20201117

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20201215

R150 Certificate of patent or registration of utility model

Ref document number: 6811693

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150