JP2003019709A - Base concrete board, tank supporting equipment and its installation method - Google Patents

Base concrete board, tank supporting equipment and its installation method

Info

Publication number
JP2003019709A
JP2003019709A JP2001207584A JP2001207584A JP2003019709A JP 2003019709 A JP2003019709 A JP 2003019709A JP 2001207584 A JP2001207584 A JP 2001207584A JP 2001207584 A JP2001207584 A JP 2001207584A JP 2003019709 A JP2003019709 A JP 2003019709A
Authority
JP
Japan
Prior art keywords
concrete
tank
foundation
basic
foundation concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001207584A
Other languages
Japanese (ja)
Other versions
JP4690590B2 (en
Inventor
Koji Niwayama
宏治 庭山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TATSUMI SANGYO KK
Original Assignee
TATSUMI SANGYO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TATSUMI SANGYO KK filed Critical TATSUMI SANGYO KK
Priority to JP2001207584A priority Critical patent/JP4690590B2/en
Publication of JP2003019709A publication Critical patent/JP2003019709A/en
Application granted granted Critical
Publication of JP4690590B2 publication Critical patent/JP4690590B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a base concrete board capable of being adapted to a supporting object having various dimensions while deterioration in strength caused by poor temperature control or laying or banding together of reinforcing bars is prevented and shortening of a construction working process and prevention of a danger are achieved. SOLUTION: The base concrete board is prefabricated in a plant. A horizontal reinforcement 12 and a vertical reinforcement 13 are arranged inside a concrete base body 11. A part of the horizontal reinforcement 12 is extended in a specific direction, and projected from at least one side surface of the concrete base body 11 to form a connecting projected part 15.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、浄化槽等のタンク
を支持する場合に用いられる基礎コンクリート板、タン
ク支持設備及びその設置方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a basic concrete plate used for supporting a tank such as a septic tank, a tank supporting facility, and a method of installing the same.

【0002】[0002]

【従来の技術】例えば、浄化槽を地中に設置する場合、
従来は、掘削用建設機械を用いて、地面に浄化槽の大き
さに合わせた穴を掘り、所定の大きさ及び深さの穴を掘
削した後、生コンクリート打設工事を行なう。生コンク
リート打設工事においては、まず、掘削された穴の底部
に砕石を敷きつめ、次に型枠を設置し、次に鉄筋を格子
状に敷設する。敷設された鉄筋は、交差部分で結束す
る。この後、型枠内に生コンクリートを打設する。
2. Description of the Related Art For example, when a septic tank is installed underground,
Conventionally, a construction machine for excavation is used to dig a hole in the ground according to the size of a septic tank, and a hole having a predetermined size and depth is excavated, and then a fresh concrete placing work is performed. In concrete pouring work, first, crushed stones are laid on the bottom of the excavated hole, then a formwork is installed, and then reinforcing bars are laid in a grid pattern. The laid rebar is tied at the intersection. After this, ready-mixed concrete is placed in the formwork.

【0003】生コンクリート打設工事が終了した後、必
要な養生期間をとり、その後、基礎コンクリートの上に
浄化槽を設置し、次にその周りを埋め戻す。
After completion of the pouring of the ready-mixed concrete, a necessary curing period is taken, after which a septic tank is installed on the basic concrete, and then the surrounding area is backfilled.

【0004】上述した従来工法の一つの問題点は、生コ
ンクリートが温度管理の不可能な外気温の影響を直接に
受け、コンクリート強度が変動することである。例え
ば、冬期には、生コンクリートの凍結により強度が劣化
する。
One of the problems of the above-mentioned conventional construction method is that the fresh concrete is directly affected by the outside temperature whose temperature cannot be controlled, and the concrete strength fluctuates. For example, in winter, the strength of raw concrete deteriorates due to freezing of fresh concrete.

【0005】従来工法のもう一つの問題点は、鉄筋の敷
設及び結束を現場で行なうために、敷設及び結束の作業
を均一に実行することが困難であること、しかも、土壁
のむき出した穴の内部において鉄筋を敷設し、かつ、結
束する必要があるため、鉄筋の汚れ、さびを生じ易いこ
とである。これらは、基礎コンクリートの強度低下を惹
起する。
Another problem with the conventional method is that it is difficult to uniformly perform the work of laying and bundling because the work of laying and bundling the reinforcing bars is performed on site, and that the holes in the soil wall are exposed. Since it is necessary to lay the reinforcing bars inside and to bind them together, the reinforcing bars are likely to become dirty and rusted. These cause a decrease in strength of the basic concrete.

【0006】従来工法の更にもう一つの問題点は、強度
確保のため、最低72時間の養生期間を確保しなければ
ならないことである。このことは、掘削された穴を数日
間も放置しなければならないことを意味し、工事期間が
長くなると共に、作業員は勿論、工事現場周辺の住民に
とっても危険である。
Still another problem with the conventional method is that a curing period of at least 72 hours must be secured in order to secure strength. This means that the excavated hole must be left for several days, which lengthens the construction period and is dangerous not only for the workers but also for the residents around the construction site.

【0007】また、従来工法においても、工事前に予
め、基礎コンクリート部を、別に製造しておく方法が考
えられていたが、連結部のない一枚構造の規格物であっ
た。その結果、タンク支持設備の大型化に比例して、基
礎コンクリート部の運搬及び設置工事に多くの費用と労
力を要し経済上の不利益が大きかった。また同時に、一
枚構造の規格物であるため、様々な寸法を有する浄化槽
に対応することができず、使用条件が限られており、実
用性にも乏しかった。
Further, in the conventional construction method as well, a method of separately manufacturing the basic concrete portion before construction has been considered, but the standard construction has a single-piece structure without connecting portions. As a result, in proportion to the increase in the size of the tank supporting equipment, much cost and labor were required for the transportation and installation work of the foundation concrete part, which was a great economic disadvantage. At the same time, since it is a standard product with a single sheet structure, it cannot be applied to septic tanks having various sizes, the usage conditions are limited, and the practicality is poor.

【0008】別の従来技術として、複数枚の基礎コンク
リート板を、連結金具で連結して、基礎コンクリート部
を形成する技術も知られている。しかしながら、複数枚
の基礎コンクリート板を連結金具で連結して行く構造で
は、連結金具による連結部分に隙間、揺動を生じるた
め、機械的強度が不足する。
As another conventional technique, there is known a technique of forming a basic concrete portion by connecting a plurality of basic concrete plates with connecting metal fittings. However, in a structure in which a plurality of foundation concrete plates are connected by connecting metal fittings, mechanical strength is insufficient because gaps and rocking occur in the connecting portions of the connecting metal fittings.

【0009】[0009]

【発明が解決しようとする課題】本発明の課題は、タン
ク支持設備が大型化しても、その土台たる基礎コンクリ
ート部建造に係る資材の運搬及び設置工事に必要とされ
る労力を削減し得る基礎コンクリート板、この基礎コン
クリート板を用いたタンク支持設備及びその設置方法を
提供することである。
SUMMARY OF THE INVENTION An object of the present invention is to provide a foundation capable of reducing the labor required for the transportation and installation work of the materials related to the construction of the foundation concrete part, which is the base of the equipment, even if the tank supporting equipment becomes large in size. It is to provide a concrete board, a tank supporting equipment using the basic concrete board, and an installation method thereof.

【0010】本発明の別の課題は、様々な寸法を有する
タンクに適合しうる基礎コンクリート板、この基礎コン
クリート板を用いたタンク支持設備及びその設置方法を
提供することである。
Another object of the present invention is to provide a basic concrete plate which can be adapted to tanks having various sizes, a tank supporting equipment using the basic concrete plate, and a method of installing the same.

【0011】本発明のもう一つの課題は、基礎コンクリ
ート板を構成する生コンクリートの温度管理を、気温の
変動による影響を受けることなく実行でき、従って、温
度管理不良による強度劣化を生じることのない、高品質
の基礎コンクリート板、この基礎コンクリート板を用い
たタンク支持設備及びその設置方法を提供することであ
る。
Another object of the present invention is to control the temperature of ready-mixed concrete constituting a foundation concrete plate without being affected by fluctuations in air temperature, and therefore to prevent strength deterioration due to poor temperature control. To provide a high-quality base concrete plate, a tank support facility using this base concrete plate, and an installation method thereof.

【0012】本発明の更にもう一つの課題は、鉄筋の敷
設及び連結を均一できると共に、鉄筋の汚れ、さびを生
じることがなく、従って、所定の強度を有する基礎コン
クリート部を形成し得る基礎コンクリート板、この基礎
コンクリート板を用いたタンク支持設備及びその設置方
法を提供することである。
Still another object of the present invention is to provide a basic concrete which enables uniform laying and connection of the reinforcing bar, does not cause dirt and rust on the reinforcing bar, and therefore can form a basic concrete portion having a predetermined strength. To provide a board, a tank supporting equipment using the foundation concrete board, and a method of installing the tank supporting equipment.

【0013】本発明の更にもう一つの課題は、現場にお
いて、基礎コンクリート部の養生期間が不要であり、工
事期間の短縮化及び危険防止に有効な基礎コンクリート
板、この基礎コンクリート板を用いたタンク支持設備及
びその設置方法を提供することである。
Yet another object of the present invention is to provide a foundation concrete plate which does not require a curing period for the foundation concrete portion on site and is effective for shortening the construction period and preventing danger, and a tank using this foundation concrete plate. It is to provide a supporting facility and a method of installing the supporting facility.

【0014】[0014]

【課題を解決するための手段】上述した課題を解決する
ため、本発明に係る基礎コンクリート板は、コンクリー
ト基体と、鉄筋とを含む。前記コンクリート基体は、所
定の厚みを有する平板状であり、前記鉄筋は、前記コン
クリート基体内部に設けられ、一部が前記基礎コンクリ
ート板の少なくとも一側面から突出している。また、前
記基礎コンクリート板は、予め、工場で製造される。
In order to solve the above-mentioned problems, the basic concrete board according to the present invention includes a concrete base and a reinforcing bar. The concrete base is a flat plate having a predetermined thickness, the reinforcing bars are provided inside the concrete base, and a part of the reinforcing bar projects from at least one side surface of the basic concrete plate. The basic concrete board is manufactured in advance in a factory.

【0015】上述したように、本発明に係る基礎コンク
リート板は、コンクリート基体内部に鉄筋が設けられて
いるから、鉄筋による機械的補強効果が得られ、機械的
強度の高い基礎コンクリート板が得られる。
As described above, in the basic concrete plate according to the present invention, since the reinforcing bars are provided inside the concrete substrate, the mechanical reinforcing effect of the reinforcing bars can be obtained, and the basic concrete plate having high mechanical strength can be obtained. .

【0016】しかも、鉄筋は、一部が基礎コンクリート
板の少なくとも一側面から突出しているから、突出して
いる部分を連結用突出部とし、複数の基礎コンクリート
板を、連結用突出部のある少なくとも1側面で組み合わ
せることができる。従って、個々の基礎コンクリート板
自体は小型に抑えられ、運搬及び設置工事に要する労力
を削減することができる。
Moreover, since the reinforcing bar partially projects from at least one side surface of the basic concrete plate, the projecting portion is used as a connecting projecting portion, and the plurality of basic concrete plates have at least one connecting projecting portion. Can be combined on the sides. Therefore, the individual concrete foundation plates themselves can be kept small, and the labor required for transportation and installation work can be reduced.

【0017】更に、本発明に係る基礎コンクリート板
は、予め、工場において製造されたものであるので、基
礎コンクリート板を構成する生コンクリートの温度管理
を、工場の管理された設備で確実に実行できる。すなわ
ち、屋外での敷設工事において、外気温の変動による影
響を受けることがなくなり、温度管理不良による強度劣
化を回避し、高品質の基礎コンクリート板を得ることが
できる。
Further, since the basic concrete plate according to the present invention is manufactured in advance in a factory, the temperature control of the ready-mixed concrete forming the basic concrete plate can be surely executed by the facility controlled by the factory. . That is, it is possible to obtain a high-quality basic concrete plate by avoiding the influence of the fluctuation of the outside temperature in the outdoor laying work, avoiding the strength deterioration due to poor temperature control.

【0018】また、鉄筋の敷設と、連結及び連結用突出
部の設定も、工場で実行できるので、鉄筋を均一に敷設
し、確実に連結できる。連結の手段として、溶接も採用
できるから、鉄筋編成の機械的強度も増大できる。同様
に、連結用突出部として機能する鉄筋を延長し、如何な
る寸法に設定するか、その加工工程も確実に実行し得
る。しかも、こられの作業は環境の良好な工場内で実行
できるので、鉄筋及び連結用突出部の汚れ、さびを生じ
ることもなくなる。このため、所定の強度を有する基礎
コンクリート板を形成し得る。
Further, the laying of the reinforcing bars and the setting of the connection and the connecting projections can be carried out in the factory, so that the reinforcing bars can be laid evenly and reliably connected. Since welding can also be used as a connecting means, the mechanical strength of the reinforcing bar formation can be increased. Similarly, it is possible to extend the reinforcing bars functioning as the connecting protrusions and to set the dimensions of the reinforcing bars so that the processing step can be surely executed. Moreover, since these operations can be performed in a factory with a good environment, the reinforcing bars and the connecting projections will not be soiled or rusted. Therefore, a basic concrete plate having a predetermined strength can be formed.

【0019】上述した基礎コンクリート板は、タンク支
持設備に用いられる。タンク支持設備は、基礎コンクリ
ート部と、架台と、タンクとを含む。前記基礎コンクリ
ート部は、前記基礎コンクリート板の複数枚を、前記突
出部で連結して設けられたものである。前記架台は、前
記基礎コンクリート部上に設けられる。前記タンクは、
前記架台に載せられる。
The above-mentioned foundation concrete plate is used for tank supporting equipment. The tank support facility includes a foundation concrete part, a pedestal, and a tank. The basic concrete portion is provided by connecting a plurality of the basic concrete plates with the projecting portion. The pedestal is provided on the basic concrete portion. The tank is
It is mounted on the mount.

【0020】ここで、本発明に係る基礎コンクリート板
は、コンクリート基体と、鉄筋とを含み、鉄筋の一部は
基礎コンクリート板の少なくとも一側面から突出してい
るから、突出部を連結することで、複数の基礎コンクリ
ート板を確実に、且、容易に連結することが可能とな
る。よって、タンク支持設備が大型化しても、その土台
たる基礎コンクリート部の設置工事に必要とされる労力
は、より小型である基礎コンクリート板の取り扱いに要
する労力に削減することができる。そして、上述のよう
に、基礎コンクリート板に連結可能構造を設けること
で、個々のタンク寸法に適合するよう、基礎コンクリー
ト部の面積を、設置現場で容易に調節することができ
る。この結果、様々な寸法を有するタンク、例えば浄化
槽に広く使用可能となり、作業効率を向上させ、施工コ
ストを削減することができる。
Here, the basic concrete plate according to the present invention includes a concrete base and a reinforcing bar, and since a part of the reinforcing bar projects from at least one side surface of the basic concrete plate, by connecting the projecting portions, It is possible to reliably and easily connect a plurality of foundation concrete plates. Therefore, even if the tank supporting equipment becomes large in size, the labor required for the installation work of the foundation concrete portion as the base can be reduced to the labor required for handling the smaller foundation concrete plate. Then, as described above, by providing the foundation concrete plate with the connectable structure, the area of the foundation concrete portion can be easily adjusted at the installation site so as to match the individual tank dimensions. As a result, it can be widely used in tanks having various sizes, for example, septic tanks, and work efficiency can be improved and construction costs can be reduced.

【0021】また、本発明においては、一枚構造の規格
物たる基礎コンクリート部ではなく、より小型の基礎コ
ンクリート板を用いることができるので、工事資材の軽
量化を図り、運搬、操作を容易化できる。
Further, in the present invention, since a smaller basic concrete plate can be used instead of the standard concrete part having a one-piece structure, it is possible to reduce the weight of construction materials and facilitate transportation and operation. it can.

【0022】さらに、本発明に係る基礎コンクリート板
は、予め、工場において製造されるから、現場での生コ
ンクリート打設工事が不要となる。
Further, since the basic concrete board according to the present invention is manufactured in advance in a factory, it is not necessary to put ready-mixed concrete on site.

【0023】本発明に係るタンク支持設備の設置方法
は、第1の工程と、第2の工程と、第3の工程とを含
む。前記第1の工程は、前記基礎コンクリート板の複数
枚を、予め、工場で製造しておき、それを現場で、前記
突出部を相対向して、整地した設置面に配置する。前記
第2の工程は、前記基礎コンクリート板の間隙で、各突
出部を所定の方法で連結し、且、架橋コンクリート部で
補強して一体化構造とする。前記第3の工程は、前記第
2の工程後において、前記架橋コンクリート部を避け
て、前記架台を配置し、その上にタンクを載せる。
The method for installing the tank support equipment according to the present invention includes a first step, a second step, and a third step. In the first step, a plurality of the basic concrete plates are manufactured in advance in a factory, and the projecting portions are opposed to each other and arranged on a grounded installation surface in the field. In the second step, the projecting portions are connected by a predetermined method in the gap between the foundation concrete plates, and are reinforced by the bridged concrete portion to form an integrated structure. In the third step, after the second step, the bridge is placed while avoiding the bridged concrete portion, and the tank is placed on it.

【0024】基礎コンクリート板は、工場で既に完成し
ており、現場では、地中に掘られた穴の底部に、タンク
に対応した寸法で、基礎コンクリート板を複数枚組み合
わせて設置し、次に、各基礎コンクリート板間の相対向
する突出部を連結し、連結部をコンクリートで架橋する
だけでよい。このため、通常、基礎コンクリート部に対
して要求される、養生期間が不要になり、工事期間の短
縮化及び危険防止にきわめて顕著な効果を奏する。
The foundation concrete plate has already been completed at the factory, and at the site, a plurality of foundation concrete plates are installed at the bottom of the hole dug in the ground with a size corresponding to the tank, and then installed. It suffices to connect opposite projecting portions between the respective foundation concrete plates and bridge the connecting portions with concrete. Therefore, the curing period, which is usually required for the basic concrete portion, becomes unnecessary, and the construction period can be shortened and danger can be prevented significantly.

【0025】タンクを設置するには、連結に係る架橋コ
ンクリート部を避けて架台を設置し、その上にタンクを
載置する。従って、タンクの荷重が架橋コンクリート部
に直接に加わるのを回避し、タンクを早期に設置するこ
とが可能になる。
In order to install the tank, a pedestal is installed while avoiding the bridged concrete portion related to the connection, and the tank is placed on it. Therefore, the load of the tank can be avoided from being directly applied to the bridged concrete portion, and the tank can be installed early.

【0026】本発明の更に具体的な特徴及び利点は、図
面を参照して更に具体的に説明する。
More specific features and advantages of the present invention will be more specifically described with reference to the drawings.

【0027】[0027]

【発明の実施の形態】図1は、本発明に係る基礎コンク
リート板を、部分的に破断して示す斜視図である。図2
は、図1に示す2−2線に沿った断面図である。図3
は、図1及び図2に示す基礎コンクリート板に含まれる
鉄筋と、連結との配置構造に関する平面図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is a partially cutaway perspective view of a foundation concrete board according to the present invention. Figure 2
FIG. 2 is a sectional view taken along line 2-2 shown in FIG. 1. Figure 3
FIG. 3 is a plan view of a layout structure of reinforcing bars included in the foundation concrete plates shown in FIGS. 1 and 2 and a connection.

【0028】図示された基礎コンクリート板は、予め、
工場において製造されたものである。コンクリート基体
11の内部には、必要な本数及びピッチで、横鉄筋12
及び縦鉄筋13が、例えば格子状に配置され、且、重層
構造をなしている。横鉄筋12と、縦鉄筋13との各交
差点は、連結14されている。連結手段としては、通
常、溶接または線材による結束を用いる。
The illustrated foundation concrete board is
It is manufactured in a factory. Inside the concrete substrate 11, the horizontal reinforcing bars 12 are arranged in the required number and pitch.
The vertical reinforcing bars 13 are arranged in a grid pattern, for example, and have a multilayer structure. Each intersection of the horizontal reinforcing bar 12 and the vertical reinforcing bar 13 is connected to each other. As the connecting means, welding or binding by a wire is usually used.

【0029】横鉄筋12の一部は、所定の方向に延長さ
れ、コンクリート基体11の少なくとも一側面から突出
し、連結用突出部15を形成している。
A part of the horizontal reinforcing bar 12 is extended in a predetermined direction and protrudes from at least one side surface of the concrete substrate 11 to form a connecting protrusion 15.

【0030】上述したように、本発明に係る基礎コンク
リート板において、横鉄筋12の一部が、所定の方向に
延長され、コンクリート基体11の少なくとも一側面か
ら突出し、連結用突出部15を形成しているから、連結
用突出部15で、複数枚の基礎コンクリート板を組み合
わせることができる。従って、個々の基礎コンクリート
板自体は小型に抑えられ、運搬及び設置工事に要する労
力を削減する事ができる。
As described above, in the basic concrete plate according to the present invention, a part of the horizontal reinforcing bar 12 is extended in a predetermined direction and protrudes from at least one side surface of the concrete base body 11 to form the connecting projection 15. Therefore, it is possible to combine a plurality of foundation concrete plates with the connecting projection 15. Therefore, the individual foundation concrete plates themselves can be kept small, and the labor required for transportation and installation work can be reduced.

【0031】しかも、本発明に係る基礎コンクリート板
は、予め、工場において製造されたものであるので、基
礎コンクリート板を構成する生コンクリートの温度管理
を、工場の管理された設備で確実に実行できる。すなわ
ち、屋外での敷設工事において、外気温の変動による影
響を受けることがなくなり、温度管理不良による強度劣
化を回避し、高品質の基礎コンクリート板を得ることが
できる。
Moreover, since the basic concrete board according to the present invention is manufactured in advance in a factory, the temperature control of the ready-mixed concrete constituting the basic concrete board can be surely executed by the facility controlled by the factory. . That is, it is possible to obtain a high-quality basic concrete plate by avoiding the influence of the fluctuation of the outside temperature in the outdoor laying work, avoiding the strength deterioration due to poor temperature control.

【0032】また、横鉄筋12、縦鉄筋13の敷設と、
連結14及び連結用突出部15の設定も、工場で実行で
きるので、横鉄筋12、縦鉄筋13を均一に敷設し、確
実に連結できる。連結14の手段として、溶接も採用で
きるから、鉄筋編成の機械的強度も増大できる。同様
に、連結用突出部15として機能する横鉄筋12を延長
し、如何なる寸法に設定するか、その加工工程も確実に
実行し得る。しかも、こられの作業は環境の良好な工場
内で実行できるので、横鉄筋12、縦鉄筋13及び連結
用突出部15の汚れ、さびを生じることもなくなる。こ
のため、所定の強度を有する基礎コンクリート板を形成
し得る。
The laying of the horizontal reinforcing bar 12 and the vertical reinforcing bar 13,
Since the connection 14 and the connecting protrusion 15 can be set in the factory, the horizontal reinforcing bars 12 and the vertical reinforcing bars 13 can be evenly laid and reliably connected. Welding can also be used as the means for the connection 14, so that the mechanical strength of the reinforcing bar formation can be increased. Similarly, the horizontal reinforcing bars 12 functioning as the connecting protrusions 15 can be extended and the dimensions of the horizontal reinforcing bars 12 can be set, and the processing step thereof can be executed reliably. Moreover, since these operations can be carried out in a factory with a good environment, the horizontal reinforcing bars 12, the vertical reinforcing bars 13 and the connecting projections 15 do not become dirty or rusted. Therefore, a basic concrete plate having a predetermined strength can be formed.

【0033】図1乃至図3における、横鉄筋12及び縦
鉄筋13の本数やピッチ及び配置形状は、例示であっ
て、鉄筋としての必要な強度が確保できれば、図示する
数量より多くても少なくても良いし、配置形状も格子状
でなくとも良い。
The numbers, pitches, and arrangement shapes of the horizontal reinforcing bars 12 and the vertical reinforcing bars 13 in FIGS. 1 to 3 are merely examples, and if the necessary strength as the reinforcing bars can be secured, the number may be larger or smaller than the illustrated quantity. The arrangement shape may not be a grid shape.

【0034】同様に、前記連結14により組み合わされ
た鉄筋の重層構造についても、図2には二重構造として
明示されているが、鉄筋としての必要な強度が確保で
き、コンクリート基体11の少なくとも一側面から、横
鉄筋12または縦鉄筋13の一部を突出させ、有効に機
能する連結用突出部15が形成できれば、重なり数は多
くとも少なくともよい。
Similarly, the laminated structure of the reinforcing bars combined by the connection 14 is clearly shown as a double structure in FIG. 2, but the necessary strength as a reinforcing bar can be ensured and at least one of the concrete bases 11 can be secured. The number of overlaps may be at least as long as a part of the horizontal reinforcing bar 12 or the vertical reinforcing bar 13 can be projected from the side surface to form the connecting projection 15 that functions effectively.

【0035】図4は、本発明に係るタンク支持設備を地
中に設けた場合の斜視図である。図5は、図4に示すタ
ンク支持設備の正面図である。図6は、図4または図5
に示すタンク支持設備の側面図である。図7は、図4乃
至図6に示すタンク支持設備を上部から見た平面図であ
る。
FIG. 4 is a perspective view of the tank support equipment according to the present invention provided in the ground. FIG. 5 is a front view of the tank support facility shown in FIG. FIG. 6 corresponds to FIG. 4 or FIG.
It is a side view of the tank support equipment shown in FIG. FIG. 7 is a plan view of the tank supporting equipment shown in FIGS. 4 to 6 as viewed from above.

【0036】図示されたタンク支持設備は、基礎コンク
リート部17と、架台50と、タンク40とを含む。基
礎コンクリート部17は、図1乃至図3で示した複数の
基礎コンクリート板10を、連結用突出部15で連結し
て設けられたものである。連結された突出部15は、架
橋コンクリート部16で補強され、一体化構造となって
いる。架台50は、基礎コンクリート部17上に設けら
れ、タンク40は、架台50に載せられる。また、図4
乃至図7では、本発明に係るタンク支持設備は、穴20
の底部21に、整地のため敷きつめた砕石30上に設け
られている。図示はされていないが、砕石30の表面に
モルタルを塗り、水平度の高い設置面を構成することが
できる。
The illustrated tank support facility includes a foundation concrete portion 17, a pedestal 50, and a tank 40. The basic concrete portion 17 is provided by connecting the plurality of basic concrete plates 10 shown in FIGS. 1 to 3 with the connecting projections 15. The connected protruding portion 15 is reinforced by the bridged concrete portion 16 and has an integrated structure. The gantry 50 is provided on the foundation concrete portion 17, and the tank 40 is placed on the gantry 50. Also, FIG.
7 to 7, the tank supporting equipment according to the present invention has a hole 20
Is provided on the bottom portion 21 of the crushed stone 30 laid for leveling. Although not shown, mortar can be applied to the surface of the crushed stone 30 to form a highly level installation surface.

【0037】図4乃至図7に図示されたタンク支持設備
は、穴20の底部21に、整地のため敷きつめた砕石3
0上に設けられているが、これはタンク40が浄化槽で
ある場合、通常の設置場所を想定した例示である。従っ
て、設置場所が、例えば地表面か、地中かでタンク支持
設備自体の性能に差異は生じない。同様に、砕石30
は、整地し、地盤強化のため敷設されるものであるか
ら、砕石30を敷設すべき必要性の無い地盤の強固な場
所に、本発明に係るタンク支持設備を設置する場合は、
必ずしも必須の構成要素とは言えない。
The tank supporting equipment shown in FIGS. 4 to 7 has a crushed stone 3 laid on the bottom 21 of the hole 20 for leveling.
However, when the tank 40 is a septic tank, this is an example assuming a normal installation place. Therefore, there is no difference in the performance of the tank supporting equipment itself depending on whether the installation location is on the ground surface or in the ground. Similarly, crushed stone 30
Is to be laid for leveling and strengthening the ground, so when installing the tank support equipment according to the present invention in a strong place of the ground where there is no need to lay the crushed stone 30,
Not necessarily an essential component.

【0038】タンク支持装置に用いられている基礎コン
クリート板10は、図1乃至図3を参照して説明したよ
うに、コンクリート基体と、鉄筋とを含み、鉄筋の一部
は基礎コンクリート板の少なくとも一側面から突出して
いるから、突出部15を連結することで、複数の基礎コ
ンクリート板10を確実に、且、容易に連結することが
可能となる。よって、タンク支持設備が大型化しても、
その土台たる基礎コンクリート部17の設置工事に必要
とされる労力は、より小型である基礎コンクリート板1
0の取り扱いに要する労力に削減することができる。そ
して、上述のように、基礎コンクリート板10に連結可
能構造を設けることで、個々のタンク寸法に適合するよ
う、基礎コンクリート部17の面積を、設置現場で容易
に調節することができる。この結果、様々な寸法を有す
るタンク、例えば浄化槽に広く使用可能となり、作業効
率を向上させ、施工コストを削減することができる。
As described with reference to FIGS. 1 to 3, the basic concrete plate 10 used in the tank supporting device includes a concrete base and a reinforcing bar, and a part of the reinforcing bar is at least the basic concrete plate. Since it projects from one side surface, it is possible to reliably and easily connect the plurality of foundation concrete plates 10 by connecting the protruding portions 15. Therefore, even if the tank support equipment becomes large,
The labor required for the installation work of the foundation concrete part 17 which is the base is smaller than the basic concrete board 1
The labor required for handling 0 can be reduced. Then, as described above, by providing the connectable structure to the base concrete plate 10, the area of the base concrete portion 17 can be easily adjusted at the installation site so as to match the individual tank dimensions. As a result, it can be widely used in tanks having various sizes, for example, septic tanks, and work efficiency can be improved and construction costs can be reduced.

【0039】また、本発明においては、一枚構造の規格
物たる基礎コンクリート部17ではなく、より小型の基
礎コンクリート板10を用いることができるので、工事
資材の軽量化に成功し、運搬が容易となる。
Further, in the present invention, since a smaller basic concrete plate 10 can be used instead of the standard concrete part 17 having a single-piece structure, the construction material can be successfully reduced in weight and can be easily transported. Becomes

【0040】さらに、本発明に係る基礎コンクリート板
10は、予め、工場において製造されるから、現場での
生コンクリート打設工事が不要となる。しかも、基礎コ
ンクリート板10を構成する生コンクリートの温度管理
を、工場の管理された設備で、確実に実行できる。この
ため、気温の変動による影響を受ず、温度管理不良によ
る強度劣化を回避して、高品質の基礎コンクリート板1
0を実現することができる。
Further, since the basic concrete board 10 according to the present invention is manufactured in advance in a factory, it is not necessary to put ready-mixed concrete on site. Moreover, the temperature control of the ready-mixed concrete forming the basic concrete board 10 can be surely executed by the facility controlled by the factory. Therefore, it is not affected by temperature fluctuations, avoids strength deterioration due to poor temperature control, and is a high-quality basic concrete board 1
0 can be realized.

【0041】また、基礎コンクリート板10の内部構造
となる鉄筋の敷設及び連結も、基礎コンクリート板10
の製造と同時に、工場で実行できるので、鉄筋を均一に
敷設し、連結できる。しかも、連結手段として溶接等も
採用できるから、鉄筋編成の機械的強度を増大できる。
これらの作業は、環境の良好な工場内で実行できるの
で、鉄筋の汚れ、さびを生じることもなく、所定の強度
を有する基礎コンクリー板を形成し得る。
Further, the laying and connection of the reinforcing bars, which are the internal structure of the basic concrete board 10, are also performed by the basic concrete board 10.
Since it can be performed in the factory at the same time as the manufacturing of, the reinforcing bars can be laid evenly and connected. Moreover, since welding or the like can be adopted as the connecting means, the mechanical strength of the reinforcing bar formation can be increased.
Since these operations can be carried out in a factory with a good environment, it is possible to form a basic concrete plate having a predetermined strength without causing stains and rust on the reinforcing bars.

【0042】次に、図4乃至図7に図示したタンク支持
装置の設置方法について説明する。図8は、本発明に係
る基礎コンクリート板が設置される穴の斜視図である。
上述した基礎コンクリート板10を用いて、浄化槽等タ
ンクを地中に埋設する場合、図8に示すように、設置箇
所に、掘削機等を用いて、穴20を掘っておく。穴20
は、底面21を含み、施工を容易にするため、通常、後
に設置されるタンクよりも、少し大きくなるように形成
される。
Next, a method of installing the tank support device shown in FIGS. 4 to 7 will be described. FIG. 8: is a perspective view of the hole in which the foundation concrete board which concerns on this invention is installed.
When a tank such as a septic tank is buried in the ground using the above-mentioned basic concrete plate 10, as shown in FIG. 8, a hole 20 is dug at an installation site using an excavator or the like. Hole 20
Includes a bottom surface 21 and is usually formed to be slightly larger than a tank to be installed later in order to facilitate construction.

【0043】図9は、図8で示す穴の底面に、砕石を敷
きつめ、基礎コンクリート板を組み合わせて設置する工
程を示す分解構造図である。図10は図9に示す工程完
了後、連結用突出部を、連結した状態を示す斜視図であ
る。図11は、図10の側面図である。
FIG. 9 is an exploded structural view showing a process of laying crushed stones on the bottom surface of the hole shown in FIG. 8 and installing a foundation concrete plate in combination. FIG. 10 is a perspective view showing a state in which the connecting protrusions are connected after the step shown in FIG. 9 is completed. FIG. 11 is a side view of FIG.

【0044】図9に示すように、地中に掘られた穴20
の底部21には、通常、地盤強化のため、砕石30が均
等に敷きつめられる。図示はされていないが、砕石30
の表面にモルタルを塗り、水平度の高い設置面を構成す
ることができる。そして、基礎コンクリート板10を、
連結用突出部15を対向させつつ、矢印Zで示す如く入
れ、図10、図11に示すように、穴20の底部21上
に設置する。基礎コンクリート板10は、製造工場か
ら、運搬車によって搬送される。そして、クレーン車等
を用いて、穴20の底部21に設置される。
As shown in FIG. 9, a hole 20 dug in the ground
Crushed stones 30 are usually spread evenly on the bottom portion 21 of the ground for strengthening the ground. Although not shown, crushed stone 30
Mortar can be applied to the surface of the to form a highly level installation surface. Then, the foundation concrete plate 10
The connecting projections 15 are opposed to each other and are inserted as shown by an arrow Z, and are installed on the bottom portion 21 of the hole 20 as shown in FIGS. The basic concrete plate 10 is transported by a transport vehicle from the manufacturing plant. Then, it is installed on the bottom portion 21 of the hole 20 by using a crane truck or the like.

【0045】先行技術では、穴20の掘削作業工程の後
は、生コンクリート打設工事を行なっていた。すなわ
ち、まず、掘削された穴の底部に砕石を敷きつめ、型枠
を設置し、鉄筋を格子状に敷設する。次に、敷設された
鉄筋を、交差部分で連結して後、型枠内に生コンクリー
トを打設する。そして、生コンクリート打設工事が終了
した後、適宜必要なコンクリート養生期間をとり、その
後、基礎コンクリートの上に浄化槽を設置し、最後にそ
の周りを埋め戻すという作業工程を経る事となる。
In the prior art, after the step of excavating the hole 20, the ready-mixed concrete placing work was performed. That is, first, crushed stones are spread over the bottom of the excavated hole, a formwork is installed, and the reinforcing bars are laid in a grid pattern. Next, the laid reinforcing bars are connected at intersections, and then ready-mixed concrete is placed in the formwork. Then, after the completion of the ready-mixed concrete placing work, a necessary concrete curing period is taken, after which a septic tank is installed on the basic concrete, and finally the surrounding work is backfilled.

【0046】これに対して、本発明に係るタンク支持設
備の基礎コンクリート部17は、前記従来の基礎コンク
リートより小型の基礎コンクリート板10を、予め工場
で製造し、これを設置現場に運搬して組み合わせること
によって作製する。
On the other hand, in the basic concrete part 17 of the tank supporting equipment according to the present invention, the basic concrete plate 10 which is smaller than the conventional basic concrete is manufactured in advance in the factory and is transported to the installation site. It is made by combining them.

【0047】工場製造により、品質面では、屋外作業で
の温度管理不良による基礎コンクリート板10の強度劣
化を防止し、鉄筋に汚れ、さびを生じることもなく、所
定の強度を確保でき、施工経済面では、小型である事か
ら運搬及び設置工事が容易であること、現場での基礎コ
ンクリート全体に要する養生期間が不要となることで、
工事期間の短縮化及び危険防止に関し有効である基礎コ
ンクリート板10を実現している。
In terms of quality, the strength of the basic concrete plate 10 can be prevented from being deteriorated due to poor temperature control in outdoor work by the factory manufacturing, and the predetermined strength can be secured without causing the reinforcing bars to be soiled or rusted. In terms of size, because it is small, it is easy to carry and install, and the curing period required for the entire basic concrete on site is unnecessary,
A basic concrete board 10 that is effective for shortening the construction period and preventing danger is realized.

【0048】図12は、図10及び図11で示す工程に
続いて、隣接する2つの基礎コンクリート板の間隙にコ
ンクリートを補充し、架橋した状態を示す斜視図であ
る。図13は、図12の側面図である。
FIG. 12 is a perspective view showing a state in which, following the steps shown in FIGS. 10 and 11, concrete is replenished and bridged in the gap between two adjacent concrete foundation plates. FIG. 13 is a side view of FIG.

【0049】図12及び図13を参照するに、隣接する
2つの基礎コンクリート板10は、連結14により、互
いに連結された連結用突出部15を、架橋コンクリート
部16により補強することで、一体化構造となり、基礎
コンクリート部17を形成する。
Referring to FIGS. 12 and 13, two adjacent concrete foundation plates 10 are integrated by reinforcing the connecting projection 15 connected to each other by the connection 14 with the bridge concrete part 16. It becomes a structure and forms the foundation concrete part 17.

【0050】基礎コンクリート板10を穴20の底面2
1上に設置した後、隣接する2つの基礎コンクリート板
10において、相対向する連結用突出部15を、まず、
図10及び図11で示したように連結14により連結
し、次に、残った間隙部分にコンクリートを補充して、
架橋コンクリート部16を構成する。別々の存在であっ
た基礎コンクリート部10は、架橋コンクリート部16
により、一体化され、基礎コンクリート部17を構成す
ることになる。この点、架橋コンクリート部16にの
み、生コンクリートを打設すれば足りる事から、コンク
リートの養生期間は従来より大幅に短縮することができ
る。また、行政規定上の建築基準を満たす一体化構造と
して所定の基準をクリアすることができ、基礎コンクリ
ート部17の強度の点に関しても建造上の不都合はな
い。
The base concrete plate 10 is placed on the bottom surface 2 of the hole 20.
First, after installing on 1, the adjacent connecting concrete projections 10 in the two adjacent concrete concrete plates 10
As shown in FIGS. 10 and 11, they are connected by the connection 14, and then the remaining gap is filled with concrete,
The crosslinked concrete portion 16 is configured. The foundation concrete part 10 which was a separate entity is a bridge concrete part 16
By this, they are integrated to form the basic concrete portion 17. In this respect, since it is sufficient to pour ready-mixed concrete only into the cross-linked concrete portion 16, the curing period of concrete can be significantly shortened as compared with the conventional case. Further, it is possible to meet a predetermined standard as an integrated structure that meets the architectural standard under the administrative regulations, and there is no inconvenience in construction in terms of strength of the basic concrete portion 17.

【0051】図14は、本発明に係る基礎コンクリート
部上に、浄化槽等のタンクを設置するステップを示す分
解構造図である。図14において、穴20の内部に配置
された基礎コンクリート部17の上に架台50を設置
し、架台50上にタンク40を載せる。
FIG. 14 is an exploded structural view showing a step of installing a tank such as a septic tank on the basic concrete portion according to the present invention. In FIG. 14, the gantry 50 is installed on the foundation concrete portion 17 arranged inside the hole 20, and the tank 40 is placed on the gantry 50.

【0052】図15は、架台上にタンクを載せた後の状
態を示す斜視図である。タンク40の設置は、例えば、
クレーン車等を用いて実行され、設置後タンク40の周
りは、埋め戻される。
FIG. 15 is a perspective view showing a state after the tank is placed on the mount. The tank 40 is installed, for example,
This is executed using a crane vehicle or the like, and the area around the tank 40 is backfilled after installation.

【0053】ここで、基礎コンクリート板10は、工場
で既に完成しており、現場では、前記所定の手順で設置
し、間隙部に架橋コンクリート部16を設けて、基礎コ
ンクリート部17を形成し、次に、基礎コンクリート部
17の上に架台50を設け、架台50上にタンク40を
載せるだけでよい。従って、架橋コンクリート部16の
養生期間経過前でも、架橋コンクリート部16を避けて
架台50を設置し、タンク40を支持すれば、速やかに
タンク40を埋め戻すことが可能である。このため、基
礎コンクリート部17に関するコンクリート養生期間は
不要となり、工事期間の短縮化及び危険防止にきわめて
顕著な効果を奏する。
Here, the basic concrete plate 10 has already been completed in the factory, and at the site, it is installed by the above-mentioned predetermined procedure, the bridge concrete part 16 is provided in the gap, and the basic concrete part 17 is formed. Next, the pedestal 50 may be provided on the foundation concrete portion 17, and the tank 40 may be placed on the pedestal 50. Therefore, even before the curing period of the bridged concrete portion 16 elapses, if the pedestal 50 is installed so as to avoid the bridged concrete portion 16 and the tank 40 is supported, the tank 40 can be quickly backfilled. For this reason, the concrete curing period for the basic concrete portion 17 is not necessary, and the construction period is shortened and the danger is very remarkable.

【0054】架台50は、架橋コンクリート部16を避
けて基礎コンクリート部17上に設けられる。この配置
によれば、架橋コンクリート部16の養生期間前でも、
タンク40を載せることが可能であり、速やかに工事を
終了する事ができる。架台50の寸法や、形状、設置場
所及び設置数は例示に過ぎず、例えば、架橋コンクリー
ト部16に負担が係らず、安定した設置方法であれば、
架台50を1つだけ適当な場所に設置するだけでもよ
い。
The pedestal 50 is provided on the foundation concrete part 17 while avoiding the bridged concrete part 16. According to this arrangement, even before the curing period of the bridged concrete part 16,
It is possible to mount the tank 40, and the construction can be completed promptly. The size, shape, installation location, and number of installations of the gantry 50 are merely examples, and, for example, if the installation method is stable without burdening the bridged concrete section 16,
It is also possible to install only one gantry 50 at an appropriate place.

【0055】図16は、本発明に係る基礎コンクリート
板の別の実施例を部分的に破断して示す斜視図である。
図17は、図16に示す17ー17線に沿った断面図で
ある。図18は、図16または図17に示す基礎コンク
リート板に含まれる鉄筋及び連結の配置構造を示す平面
図である。図において、図1乃至図3に現れた構成部分
と同一の構成部分については、同一の参照符号を付し、
重複説明は省略する。
FIG. 16 is a partially cutaway perspective view showing another embodiment of the foundation concrete board according to the present invention.
FIG. 17 is a sectional view taken along line 17-17 shown in FIG. FIG. 18 is a plan view showing an arrangement structure of reinforcing bars and connections included in the foundation concrete plate shown in FIG. 16 or FIG. In the figure, the same components as those shown in FIGS. 1 to 3 are designated by the same reference numerals,
A duplicate description will be omitted.

【0056】図示実施例では、横鉄筋12は、コンクリ
ート基体11の内部に設けられ、一部がコンクリート基
体11の2側面から突出している。
In the illustrated embodiment, the horizontal reinforcing bars 12 are provided inside the concrete base body 11, and a part thereof projects from two side surfaces of the concrete base body 11.

【0057】図示はされていないが、横鉄筋12を、コ
ンクリート基体11の他の残りの側面からも突出させた
構造を採用することもできる。すなわち、縦鉄筋13を
矢印Yで示す方向の両端に延長して連結用突出部15を
設けてもよいし、基礎コンクリート部に必要とされる長
さ及び幅寸法の面積次第では、矢印X及びYで示す任意
の方向に、横鉄筋12及び縦鉄筋13を伸長して、連結
用突出部15を設けることができる。
Although not shown, it is also possible to employ a structure in which the horizontal reinforcing bar 12 is also projected from the other remaining side surface of the concrete base 11. That is, the vertical reinforcing bars 13 may be extended to both ends in the direction indicated by the arrow Y to provide the connecting protrusions 15, or the arrow X and the arrow depending on the area of the length and width dimensions required for the basic concrete portion. The horizontal reinforcing bar 12 and the vertical reinforcing bar 13 can be extended in any direction indicated by Y to provide the connecting protrusion 15.

【0058】図19は図1乃至図3に示した基礎コンク
リート板と、図16乃至図18に示した基礎コンクリー
ト板を用いたタンク支持設備の斜視図、図20は図19
に示したタンク支持装置の正面図、図21は図19及び
図20に示したタンク支持設備の側面図、図22は図1
9乃至図21に示したタンク支持設備の平面図である。
図において、図4乃至図7に現れた構成部分と同一の構
成部分については、同一の参照符号を付し、重複説明は
省略する。図19乃至図22に図示されたタンク支持設
備の特徴は、連結用突出部15と架橋コンクリート部1
6とが、二箇所設けられている点にある。すなわち、図
19乃至図22は、図1乃至図3に図示された基礎コン
クリート板10と、図16乃至図18に図示された基礎
コンクリート板10とを組み合わせて、様々な寸法を有
するタンク40に適合し、広く使用可能なタンク支持設
備を提供しうることを示す具体例である。
FIG. 19 is a perspective view of a tank supporting facility using the foundation concrete plates shown in FIGS. 1 to 3 and the foundation concrete plates shown in FIGS. 16 to 18, and FIG.
21 is a front view of the tank supporting apparatus shown in FIG. 21, FIG. 21 is a side view of the tank supporting equipment shown in FIGS. 19 and 20, and FIG.
FIG. 22 is a plan view of the tank support facility shown in FIGS. 9 to 21.
In the figure, the same components as those shown in FIGS. 4 to 7 are designated by the same reference numerals, and the duplicate description will be omitted. The features of the tank supporting equipment shown in FIGS. 19 to 22 are that the connecting projection 15 and the bridge concrete part 1 are connected.
6 and 2 are provided at two places. That is, FIGS. 19 to 22 show a combination of the basic concrete plate 10 shown in FIGS. 1 to 3 and the basic concrete plate 10 shown in FIGS. 16 to 18 to form a tank 40 having various sizes. 3 is a concrete example showing that the tank supporting equipment can be adapted and can be widely used.

【0059】図16乃至図22に示した実施例の場合
も、図1乃至図7に示した実施例と同様の作用効果が得
られることは自明である。また、図示は省略するが、図
19乃至図22に図示したタンク支持設備も、図8乃至
図15に図示した設置方法を適用できる。
It is obvious that in the case of the embodiment shown in FIGS. 16 to 22, the same operational effect as that of the embodiment shown in FIGS. 1 to 7 can be obtained. Although illustration is omitted, the installation method illustrated in FIGS. 8 to 15 can be applied to the tank support equipment illustrated in FIGS. 19 to 22.

【0060】[0060]

【発明の効果】以上述べたように、本発明によれば次の
ような効果が得られる。 (a)タンク支持設備が大型化しても、その土台たる基
礎コンクリート部建造に係る資材の運搬及び工事に必要
とされる労力を削減し得る基礎コンクリート板、この基
礎コンクリート板を用いたタンク支持設備及びその設置
方法を提供できる。 (b)基礎コンクリート板が連結構造を有する事で、様
々な寸法を有するタンクに適合しうる基礎コンクリート
部、この基礎コンクリート板を用いたタンク支持設備及
びその設置方法を提供できる。 (c)基礎コンクリート板を構成する生コンクリートの
温度管理を、気温の変動による影響を受けることなく実
行でき、従って、温度管理不良による強度劣化を生じる
ことのない、高品質の基礎コンクリート板、この基礎コ
ンクリート板を用いたタンク支持設備及びその設置方法
を提供できる。 (d)鉄筋の敷設及び連結を均一できると共に、鉄筋の
汚れ、さびを生じることがなく、従って、所定の強度を
有する基礎コンクリートを形成し得る基礎コンクリート
板、この基礎コンクリート板を用いたタンク支持設備及
びその設置方法を提供できる。 (e)現場において、基礎コンクリート部の養生期間が
不要であり、工事期間の短縮化及び危険防止に有効な基
礎コンクリート板、この基礎コンクリート板を用いたタ
ンク支持設備及びその設置方法を提供できる。
As described above, according to the present invention, the following effects can be obtained. (A) A basic concrete board that can reduce the labor required for the transportation and construction of materials related to the construction of the basic concrete part, which is the base of the tank supporting equipment, even if the tank supporting equipment becomes large, and the tank supporting equipment using the basic concrete board And its installation method can be provided. (B) Since the basic concrete plate has a connection structure, it is possible to provide a basic concrete part that can be adapted to tanks having various sizes, a tank support facility using this basic concrete plate, and an installation method thereof. (C) The temperature control of the ready-mixed concrete constituting the basic concrete plate can be executed without being affected by the fluctuation of the air temperature, and therefore, the high-quality basic concrete plate, which does not cause the strength deterioration due to the poor temperature control, A tank support facility using a basic concrete plate and a method for installing the same can be provided. (D) Reinforcing bars can be evenly laid and connected, and the reinforcing bars can be prevented from being soiled or rusted. Therefore, a basic concrete plate capable of forming a basic concrete having a predetermined strength, and a tank support using the basic concrete plate. It is possible to provide equipment and a method of installing the equipment. (E) On-site, it is possible to provide a foundation concrete plate that does not require a curing period for the foundation concrete portion and is effective for shortening the construction period and preventing danger, a tank support facility using this foundation concrete plate, and an installation method thereof.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る基礎コンクリート板を、部分的に
破断して示す斜視図である。
FIG. 1 is a perspective view showing a partially broken base concrete plate according to the present invention.

【図2】図1に示す2−2線に沿った断面図である。2 is a cross-sectional view taken along line 2-2 shown in FIG.

【図3】本発明に係る基礎コンクリート板に含まれる、
鉄筋及び連結の配置構造に関する平面図である。
FIG. 3 is included in a foundation concrete plate according to the present invention,
It is a top view regarding the arrangement structure of a reinforcement and a connection.

【図4】本発明に係るタンク支持設備について、設置さ
れた状態を示す斜視図である。
FIG. 4 is a perspective view showing the installed state of the tank supporting equipment according to the present invention.

【図5】図4に図示したタンク支持設備の正面図であ
る。
FIG. 5 is a front view of the tank support facility shown in FIG.

【図6】図4及び図5に図示したタンク支持設備の側面
図である。
6 is a side view of the tank support facility illustrated in FIGS. 4 and 5. FIG.

【図7】図4乃至図6に図示したタンク支持設備を上部
から見た平面図である。
FIG. 7 is a plan view of the tank support facility shown in FIGS. 4 to 6 as viewed from above.

【図8】本発明に係る基礎コンクリート板と、タンク支
持設備の設置方法に関し、基礎コンクリート板が設置さ
れる穴の斜視図である。
FIG. 8 is a perspective view of a hole in which the foundation concrete plate is installed, regarding the foundation concrete plate and the method for installing the tank support facility according to the present invention.

【図9】図8に図示した穴の底面に、砕石を敷きつめ、
基礎コンクリート板を組み合わせて設置する工程を示す
分解構造図である。
9: Crushed stones are laid on the bottom of the hole shown in FIG.
It is a disassembled structural drawing which shows the process of installing a foundation concrete board in combination.

【図10】本発明に係る基礎コンクリート板と、タンク
支持設備の設置方法に関し、図9記載の工程完了後、連
結用突出部を、連結した状態を示す斜視図である。
FIG. 10 is a perspective view showing a state in which the connecting projections are connected after the step described in FIG. 9 is completed, regarding the method for installing the foundation concrete plate and the tank support equipment according to the present invention.

【図11】図10に図示した基礎コンクリート板の側面
図である。
11 is a side view of the foundation concrete plate shown in FIG.

【図12】本発明に係る基礎コンクリート板と、タンク
支持設備の設置方法に関し、図10及び図11記載の工
程に続いて、基礎コンクリート板の間隙をコンクリート
で補充し、架橋した状態を示す斜視図である。
FIG. 12 is a perspective view showing a state in which the base concrete plate according to the present invention and the method for installing the tank support equipment are filled with concrete and bridged, following the steps shown in FIGS. 10 and 11. It is a figure.

【図13】図12に図示した基礎コンクリート部の側面
図である。
FIG. 13 is a side view of the foundation concrete portion illustrated in FIG.

【図14】本発明に係る基礎コンクリート板と、タンク
支持設備の設置方法に関し、基礎コンクリート部上に、
タンクを設置する場合の構成を示す、分解構造図であ
る。
FIG. 14 relates to a method of installing a foundation concrete plate and a tank support facility according to the present invention, and
FIG. 3 is an exploded structural view showing a configuration when a tank is installed.

【図15】本発明に係る基礎コンクリート板と、タンク
支持設備の設置方法に関し、タンク支持設備を設置した
状態を示す斜視図である。
FIG. 15 is a perspective view showing a state in which the tank supporting equipment is installed, regarding the foundation concrete board and the method for installing the tank supporting equipment according to the present invention.

【図16】本発明に係る基礎コンクリート板の別の実施
例について、部分的に破断して示す斜視図である。
FIG. 16 is a partially cutaway perspective view showing another embodiment of the foundation concrete plate according to the present invention.

【図17】図16の17ー17線に沿った断面図であ
る。
17 is a sectional view taken along line 17-17 of FIG.

【図18】図16及び図17に図示した基礎コンクリー
ト板に関し、鉄筋及び連結の配置構造を示す平面図であ
る。
FIG. 18 is a plan view showing an arrangement structure of reinforcing bars and connections of the foundation concrete plates shown in FIGS. 16 and 17;

【図19】本発明に係る基礎コンクリート板の別の実施
例をもちいたタンク支持装置の斜視図である。
FIG. 19 is a perspective view of a tank supporting device using another embodiment of the foundation concrete plate according to the present invention.

【図20】図19に図示したタンク支持装置の正面図で
ある。
20 is a front view of the tank support device shown in FIG.

【図21】図19及び図20に図示したタンク支持装置
の側面図である。
FIG. 21 is a side view of the tank support device shown in FIGS. 19 and 20.

【図22】図19乃至図21に図示したタンク支持装置
を上部から見た平面図である。
FIG. 22 is a plan view of the tank supporting device shown in FIGS. 19 to 21 as viewed from above.

【符号の説明】[Explanation of symbols]

10 基礎コンクリート板 11 コンクリート基体 12 横鉄筋 13 縦鉄筋 14 連結 15 連結用突出部 16 架橋コンクリート部 17 基礎コンクリート部 20 穴 21 底部 30 砕石 40 タンク 50 架台 10 Foundation concrete plate 11 Concrete base 12 horizontal rebar 13 Vertical rebar 14 connection 15 Connecting protrusion 16 Cross-linked concrete section 17 Foundation concrete section 20 holes 21 bottom 30 crushed stone 40 tanks 50 mounts

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート基体と、鉄筋とを含み、予
め、工場で製造される基礎コンクリート板であって、 前記コンクリート基体は、所定の厚みを有する平板状で
あり、 前記鉄筋は、前記コンクリート基体内部に設けられ、一
部が前記コンクリート基体の少なくとも一側面から突出
している基礎コンクリート板。
1. A basic concrete board, which includes a concrete base and a reinforcing bar and is manufactured in advance in a factory, wherein the concrete base is a flat plate having a predetermined thickness, and the reinforcing bar is the concrete base. A foundation concrete plate which is provided inside and a part of which protrudes from at least one side surface of the concrete substrate.
【請求項2】 基礎コンクリート部と、架台と、タンク
とを含むタンク支持設備であって、 前記基礎コンクリート部は、請求項1に記載された基礎
コンクリート板の複数を、前記突出部で連結して設けら
れたものであり、 前記架台は、前記基礎コンクリート部上に設けられ、 前記タンクは、前記架台に載せられるタンク支持設備。
2. A tank support facility including a foundation concrete portion, a gantry, and a tank, wherein the foundation concrete portion connects a plurality of the foundation concrete plates according to claim 1 with the projecting portion. The tank support facility is provided on the foundation concrete part, and the tank is mounted on the platform.
【請求項3】 第1の工程と、第2の工程と、第3の工
程とを含むタンク支持設備の設置方法であって、 前記第1の工程では、請求項1に記載された基礎コンク
リート板の複数枚を、前記突出部を相対向して配置し、 前記第2の工程では、前記基礎コンクリート板の間隙
で、各突出部を連結し、且、前記間隙を架橋コンクリー
ト部で補強して一体化構造とし、 前記第3の工程では、前記架橋コンクリート部を避け
て、前記架台を配置し、その上にタンクを載せるタンク
支持設備の設置方法。
3. A method of installing tank support equipment, comprising: a first step, a second step, and a third step, wherein in the first step, the foundation concrete according to claim 1. A plurality of plates are arranged so that the protrusions face each other, and in the second step, the protrusions are connected by the gaps of the foundation concrete plate, and the gaps are reinforced by the bridged concrete portions. In the third step, the tank supporting facility is installed by arranging the gantry while avoiding the bridged concrete portion and placing the tank on the gantry in the third step.
JP2001207584A 2001-07-09 2001-07-09 Foundation concrete board, tank support equipment and installation method Expired - Lifetime JP4690590B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001207584A JP4690590B2 (en) 2001-07-09 2001-07-09 Foundation concrete board, tank support equipment and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001207584A JP4690590B2 (en) 2001-07-09 2001-07-09 Foundation concrete board, tank support equipment and installation method

Publications (2)

Publication Number Publication Date
JP2003019709A true JP2003019709A (en) 2003-01-21
JP4690590B2 JP4690590B2 (en) 2011-06-01

Family

ID=19043545

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001207584A Expired - Lifetime JP4690590B2 (en) 2001-07-09 2001-07-09 Foundation concrete board, tank support equipment and installation method

Country Status (1)

Country Link
JP (1) JP4690590B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007198716A (en) * 2006-01-30 2007-08-09 Denso Corp Hot water storage tank unit and hot water storage type water heater
CN108331001A (en) * 2018-01-30 2018-07-27 山西大学 A kind of prefabricated assembled box foundation of subregion assembling

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54155214A (en) * 1978-05-29 1979-12-07 Nihon Cement Production of concrete plate equipped with reinforcing member for joints
JPS60251082A (en) * 1984-05-17 1985-12-11 株式会社 東京タツノ Underground tank
JPH08326067A (en) * 1995-05-31 1996-12-10 Tokiko Yuki Kk Fixing device for underground tank
JP2000336820A (en) * 1999-06-01 2000-12-05 Kyokuto Corp Joint structure of joint part of precast floor slab

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS54155214A (en) * 1978-05-29 1979-12-07 Nihon Cement Production of concrete plate equipped with reinforcing member for joints
JPS60251082A (en) * 1984-05-17 1985-12-11 株式会社 東京タツノ Underground tank
JPH08326067A (en) * 1995-05-31 1996-12-10 Tokiko Yuki Kk Fixing device for underground tank
JP2000336820A (en) * 1999-06-01 2000-12-05 Kyokuto Corp Joint structure of joint part of precast floor slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007198716A (en) * 2006-01-30 2007-08-09 Denso Corp Hot water storage tank unit and hot water storage type water heater
CN108331001A (en) * 2018-01-30 2018-07-27 山西大学 A kind of prefabricated assembled box foundation of subregion assembling

Also Published As

Publication number Publication date
JP4690590B2 (en) 2011-06-01

Similar Documents

Publication Publication Date Title
KR100926140B1 (en) Structure for using precast members and construction method thereof
US20060248847A1 (en) Method for providing a pad to support heavy equipment
JP2003019709A (en) Base concrete board, tank supporting equipment and its installation method
KR100462236B1 (en) panel for external underground wall of building, structure and construction method using the same
JPH09195438A (en) Precast concrete plate and reinforcing structure of building
JPH10219708A (en) Precast concrete block for continuous footing and continuous footing method by use thereof
GB2147635A (en) Foundation for suspended floors
JP7455931B1 (en) Precast board manufacturing method and precast board
JP4966617B2 (en) Rebuilding unit building
JP3729890B2 (en) Single-sided precast concrete underground beam and its components
JPH11350500A (en) Foundation structure of building and foundation work method
JPH09273205A (en) Rain water storage tank
JPH10195852A (en) Construction method for porous pipeline for c.c.box
JPH06167003A (en) Road curb stone forming method
KR200266585Y1 (en) panel for external underground wall of building and external underground wall- structure using the same
JP3677834B2 (en) Structure of connecting part of reinforced concrete basement building unit
JPH06330529A (en) Mounting method of cast-in-place concrete strip footing and precast concrete wall slab
AU750020B3 (en) A load bearing building panel
JP2829717B2 (en) Construction method of installation foundation for heavy objects
JP4102498B2 (en) Method for manufacturing concrete structure and method for carrying the same
JPH05287761A (en) Building construction member and construction method of structure using the same
JP3009298B2 (en) Method of manufacturing PCa slab
JPH09137699A (en) Method for holding reinforcing bar of invert concrete
JPH1161855A (en) Process for constructing underground space
JP2001214459A (en) Method for constructing retaining wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080507

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100121

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100127

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100325

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110209

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110218

R150 Certificate of patent or registration of utility model

Ref document number: 4690590

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140225

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term