JP2002312022A - System, method and program for managing process of parts delivery, recording medium with recorded program for managing progress of parts delivery and parts management system - Google Patents

System, method and program for managing process of parts delivery, recording medium with recorded program for managing progress of parts delivery and parts management system

Info

Publication number
JP2002312022A
JP2002312022A JP2001117438A JP2001117438A JP2002312022A JP 2002312022 A JP2002312022 A JP 2002312022A JP 2001117438 A JP2001117438 A JP 2001117438A JP 2001117438 A JP2001117438 A JP 2001117438A JP 2002312022 A JP2002312022 A JP 2002312022A
Authority
JP
Japan
Prior art keywords
parts
delivery
model
status
progress management
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001117438A
Other languages
Japanese (ja)
Other versions
JP3640900B2 (en
Inventor
Shuji Tanabe
修司 田辺
Kiyoshi Sato
清 佐藤
Ryoichi Kokusho
良一 国生
Kazuto Tamura
和人 田村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sharp Corp
Original Assignee
Sharp Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sharp Corp filed Critical Sharp Corp
Priority to JP2001117438A priority Critical patent/JP3640900B2/en
Publication of JP2002312022A publication Critical patent/JP2002312022A/en
Application granted granted Critical
Publication of JP3640900B2 publication Critical patent/JP3640900B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

PROBLEM TO BE SOLVED: To suppress the increase of a burden for managing inventories and lowering of production efficiency of machine models. SOLUTION: A system 3 for managing progress of parts delivery is formed by including a data storing part 11 to record production plan data for a scheduled model to produce, a control part 27 for displaying the progress of the parts delivery to determine availability of each part for every model at the point of time before the scheduled delivery data of each part and to confirm the ordering status of each part for every model, based on the data recorded in the data storing part 11, and a progress managing terminal unit 34 to display the result obtained by the control part 27 for displaying the progress of the parts delivery. A manager can grasp the tendency of a bottleneck in the production of the model in advance by determining the availability ad confirming the ordering status before the scheduled delivery data of the component parts. As a result, it becomes possible to suitably cope with the bottleneck in the production.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、生産を予定してい
る機種(製品)を構成する部品の納入進度を管理する部
品管理システムにおいて、日々納入される部品の在庫を
過剰に増やすことなく、機種の生産隘路にも適切に対応
できる部品納入進度管理システム、部品納入進度管理方
法、部品納入進度管理プログラム、部品納入進度管理プ
ログラムを記録した記録媒体および部品管理システムに
関するものである。
BACKGROUND OF THE INVENTION The present invention relates to a parts management system for managing the progress of the delivery of parts constituting a model (product) to be produced, without excessively increasing the inventory of parts delivered daily. The present invention relates to a component delivery progress management system, a component delivery progress management method, a component delivery progress management program, a recording medium storing a component delivery progress management program, and a component management system capable of appropriately coping with a production bottleneck of a model.

【0002】[0002]

【従来の技術】従来から、生産計画に基づく機種の生産
にあたり、当該機種を構成する部品の納入進度の管理が
行われている。従来の部品納入進度管理の一例について
説明すれば以下の通りである。
2. Description of the Related Art Conventionally, in the production of a model based on a production plan, management of the progress of delivery of parts constituting the model has been performed. An example of the conventional component delivery progress management will be described below.

【0003】まず、機種の生産予定日から手番だけ遡っ
た日に部品の納期を指定する。なお、上記の手番とは、
納入した部品の検査や生産前の準備(前加工)のために
必要な日数のことである。そして、納期当日に、その日
の部品の納入予定数と納入実績数とに基づいて当該部品
の納入状況を把握し、その納入状況に基づいて機種の生
産が隘路となるかを判断する。
[0003] First, a delivery date of a part is specified on a date as far back as the turn from the planned production date of the model. In addition, the above-mentioned turn is
This is the number of days required for inspection of delivered parts and preparation before production (pre-processing). Then, on the day of delivery, the delivery status of the part is grasped based on the scheduled number of parts delivered and the number of actual deliveries on that day, and it is determined whether the production of the model becomes a bottleneck based on the delivery status.

【0004】ここで、機種の生産が隘路とはならないと
判断したときは問題はないが、機種の生産が隘路となる
と判断したときは、上記機種の生産日程を調整する。つ
まり、生産隘路となる機種についてのみその生産を遅ら
すか、あるいは、生産が前倒しできる機種があれば、そ
の機種の生産と生産隘路となる機種の生産とを入れ替え
る。
Here, there is no problem when it is determined that the production of the model does not become a bottleneck, but when it is determined that the production of the model becomes a bottleneck, the production schedule of the model is adjusted. In other words, the production is delayed only for the model that becomes a production bottleneck, or if there is a model whose production can be brought forward, the production of the model is replaced with the production of the model that becomes the production bottleneck.

【0005】[0005]

【発明が解決しようとする課題】ところで、ある機種に
ついて一度立てた生産計画を変更するというのは、他の
機種の生産にも影響を及ぼすと共に、上記機種の販売店
への配送も遅れることとなり、販売店に迷惑をかける。
そのため、生産計画の変更は、なるべくなら避けたいも
のである。
However, changing the production plan once established for a certain model affects the production of other models and delays the delivery of the above models to a store. Trouble retailers.
Therefore, it is desirable to avoid changing the production plan if possible.

【0006】そこで、このような機種の生産隘路を未然
に防止する方法として、例えば、手番を長めに設定し、
納期と生産予定日との間に、部品の納入遅れをカバーで
きる期間を確保することが考えられる。
Therefore, as a method of preventing such a production bottleneck of a model, for example, by setting a longer turn,
It is conceivable to secure a period between the delivery date and the scheduled production date to cover the delay in parts delivery.

【0007】しかし、各部品について、納期と生産予定
日との間が必要以上に長くなると、部品が早めに納入さ
れることによって、部品全体での在庫数が多くなってし
まう。部品倉庫の収容量には限度があり、また、在庫部
品の管理負担も増加するので、部品の在庫数が過剰に増
加するのは好ましくはない。
[0007] However, if the time between the delivery date and the scheduled production date becomes longer than necessary for each part, the parts are delivered early and the stock quantity of the whole part increases. Since the storage capacity of the parts warehouse is limited and the management burden of the stock parts increases, it is not preferable that the stock quantity of the parts excessively increases.

【0008】また、機種の生産計画を仕方なく変更する
場合でも、従来は、機種の生産計画を変更するか否かを
納期当日で判断していたので、変更した生産計画に基づ
く生産ラインの稼働(部品の検査や生産前の準備を含
む)が、生産計画の変更の検討に要した時間だけ納期当
日から遅れることになる。つまり、変更した生産計画に
基づいて実際に生産ラインが稼働するのは、納期当日か
ら最低でも半日後、あるいは一日後となる。その結果、
納期当日から最低でも半日は生産ラインを遊ばす結果と
なり、機種の生産を効率よく行うことができない。
Further, even when the production plan of the model is changed without help, conventionally, whether or not to change the production plan of the model is determined on the delivery date, so that the production line is operated based on the changed production plan. (Including inspection of parts and preparations before production) will be delayed from the delivery date by the time required for considering changes in the production plan. That is, the actual operation of the production line based on the changed production plan is at least half a day or one day after the delivery date. as a result,
At least half a day from the date of delivery, the production line will be idle, resulting in inefficient production of models.

【0009】本発明は、上記の問題点を解決するために
なされたもので、その目的は、機種の生産隘路の傾向を
部品の納期よりも前に把握し、その結果に基づいて部品
の納入進度を管理することにより、在庫の管理負担の増
大および機種の生産効率の低下を抑制することができる
部品納入進度管理システム、部品納入進度管理方法、部
品納入進度管理プログラム、部品納入進度管理プログラ
ムを記録した記録媒体および部品管理システムを提供す
ることにある。
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object of the present invention is to grasp the tendency of a production bottleneck of a model before the delivery date of a part and to deliver the part based on the result. A component delivery progress management system, a component delivery progress management method, a component delivery progress management program, and a component delivery progress management program that can control the increase in inventory management burden and the decrease in model production efficiency by managing the progress An object of the present invention is to provide a recorded recording medium and a parts management system.

【0010】[0010]

【課題を解決するための手段】本発明に係る部品納入進
度管理システムは、上記の課題を解決するために、生産
を予定している機種を構成する各部品の納入進度を管理
する部品納入進度管理システムであって、上記機種の生
産計画情報と、上記機種を構成する各部品に関する情報
とを記憶する記憶手段と、上記記憶手段に記憶された情
報に基づいて、上記各部品の納入予定日よりも前の時点
で、上記各部品の品揃え状況を上記機種ごとに判断する
と共に、上記各部品の発注状況を上記機種ごとに確認す
る制御手段と、上記制御手段にて得られる結果を表示す
る表示手段とを備えていることを特徴としている。
SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, a parts delivery progress management system according to the present invention manages the delivery progress of each component constituting a model to be produced. A management system, comprising: storage means for storing production plan information of the model and information on each part constituting the model; and a scheduled delivery date of each part based on the information stored in the storage means. Prior to this, the control means for judging the assortment status of each part for each model and confirming the order status of each part for each model, and displaying the results obtained by the control means And display means for displaying the information.

【0011】また、本発明に係る部品納入進度管理方法
は、上記の課題を解決するために、生産を予定している
機種を構成する各部品の納入進度を管理する部品納入進
度管理方法であって、(記憶手段に記憶されている)上
記機種の生産計画情報と、上記機種を構成する各部品に
関する情報とに基づいて、上記各部品の納入予定日より
も前の時点で、制御手段が上記各部品の品揃え状況を上
記機種ごとに判断すると共に、上記各部品の発注状況を
上記機種ごとに確認するステップと、上記制御手段にて
得られる結果を表示手段が表示するステップとを有して
いることを特徴としている。
In order to solve the above-mentioned problems, a part delivery progress management method according to the present invention is a part delivery progress management method for managing the delivery progress of each component constituting a model to be produced. Then, based on the production plan information of the model (stored in the storage means) and the information on each of the components constituting the model, at a point before the scheduled delivery date of each of the parts, the control means A step of judging the assortment status of each part for each model, confirming the order status of each part for each model, and displaying a result obtained by the control means on a display means. It is characterized by doing.

【0012】上記の構成によれば、生産を予定している
機種の生産計画情報と、上記機種を構成する各部品に関
する情報とが記憶手段に記憶されている。上記の生産計
画情報としては、例えば、機種の日別生産計画数(生産
予定日ごとの生産予定数)がある。また、上記の部品に
関する情報としては、例えば、上記機種とその構成部品
との対応関係、各部品の納入予定日、納入予定数、納入
実績数、在庫数、発注員数、上記各部品の納入の督促を
支援する情報がある。なお、上記支援情報としては、例
えば、各部品の取引先およびその担当者、注文番号(注
番)、伝票番号(伝番)がある。
According to the above configuration, the storage means stores the production plan information of the model whose production is scheduled and the information on each component constituting the model. The above-mentioned production plan information includes, for example, the number of daily production plans of the models (the number of planned productions per planned production date). In addition, information on the above-mentioned parts includes, for example, the correspondence between the above-mentioned model and its component parts, the scheduled delivery date and the scheduled delivery number of each part, the actual delivery quantity, the number of stocks, the number of orderers, and the delivery of each of the above parts. There is information to support dunning. The support information includes, for example, a supplier of each part and its person in charge, an order number (note number), and a slip number (number).

【0013】制御手段は、記憶手段に記憶されたこれら
の情報に基づいて、機種を構成する各部品の品揃え状況
を機種ごとに判断すると共に、各部品の発注状況を機種
ごとに確認する。この制御手段にて得られる結果は、表
示手段に表示される。
Based on the information stored in the storage means, the control means determines the assortment status of each component constituting the model for each model, and confirms the order status of each component for each model. The result obtained by this control means is displayed on the display means.

【0014】このとき、制御手段は、品揃え状況の判断
および発注状況の確認を、各部品の納入予定日よりも前
に行うので、例えば、部品の納入に携わる担当者の上司
である管理者や生産計画を企画する生産企画部の人(以
下、管理者に統一して記載する)が、表示手段に表示さ
れた結果を見たときに、各部品を用いて生産される機種
の生産が隘路となりそうかどうかという生産隘路の傾向
を、部品の納入予定日よりも前に把握することができ
る。この結果、機種の生産隘路が発生しそうと判断すれ
ば、納入予定日までに部品を納入するような督促を取引
先に行ったり、生産計画の変更(生産隘路となりそうな
機種の生産と、先に生産可能な機種の生産を入れ替え
る)を行うなどの適切な対応をとることができる。
[0014] At this time, the control means judges the assortment status and confirms the order status before the scheduled delivery date of each part. For example, the manager, who is the supervisor of the person in charge of the delivery of the component, When a person in the Production Planning Department who plans a production plan or a production planning department (hereinafter referred to as the “manager”) sees the results displayed on the display means, The tendency of the production bottleneck to be a bottleneck can be grasped before the scheduled delivery date of parts. As a result, if it is determined that a bottleneck in the production of the model is likely to occur, the supplier will be urged to deliver the parts by the scheduled delivery date, or the production plan will be changed (the production (Replace the production of models that can be produced at any time).

【0015】ここで、部品の納入の督促を行う場合は、
部品の納入予定日よりも前に督促できるので、元々の納
入予定日自体が変動することがない。したがって、従来
のように納入予定日と生産予定日との間が長期にならな
いので、在庫が長期にわたって過剰になるということが
なく、在庫の管理負担の増大を抑制することができる。
Here, in order to urge the delivery of parts,
Since the dunning can be performed before the scheduled delivery date of the parts, the original scheduled delivery date itself does not change. Therefore, since the time between the scheduled delivery date and the scheduled production date does not become long as in the related art, the stock does not become excessive for a long time, and an increase in stock management load can be suppressed.

【0016】また、生産計画を変更する場合は、生産計
画を変更するかどうかの検討を、生産隘路となる機種の
構成部品の納入予定日よりも前に行うことができるの
で、その検討を納入予定日よりも前に終えることができ
れば、上記納入予定日から直ちに、生産計画変更後の機
種の生産のための生産ライン(検査、準備を含む)を稼
働させることが可能となる。つまり、元々の納入予定日
と、生産計画変更後の機種の生産ラインの稼働開始日と
の間にタイムラグが生じることがない。この結果、機種
の生産効率の低下を抑制することができる。
In the case where the production plan is changed, it is possible to consider whether or not to change the production plan before the scheduled delivery date of the component parts of the model that will be a production bottleneck. If it can be completed before the scheduled date, the production line (including inspection and preparation) for the production of the model after the change of the production plan can be operated immediately from the scheduled delivery date. That is, there is no time lag between the original scheduled delivery date and the operation start date of the production line of the model after the change of the production plan. As a result, a decrease in the production efficiency of the model can be suppressed.

【0017】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記各部品の在庫数
と、上記各部品の納入予定日における納入予定数とに基
づいて、上記各部品の欠品状況を判断する欠品状況判断
手段をさらに備え、上記制御手段は、上記機種を構成す
る部品の総数と、欠品と判断された部品の数とに基づい
て、上記各部品の品揃え状況を上記機種ごとに判断する
ことを特徴としている。
[0017] In order to solve the above-mentioned problems, the parts delivery progress management system according to the present invention is based on the number of parts in stock and the number of parts to be delivered at the scheduled delivery date of each part. Further comprising a shortage status judging means for judging the shortage status of the parts, wherein the control means is configured to determine the number of parts of each of the parts based on the total number of parts constituting the model and the number of parts determined to be missing. It is characterized in that the alignment status is determined for each model.

【0018】上記の構成によれば、欠品状況判断手段に
よって、各部品の欠品状況が判断される。例えば、ある
部品について、在庫数が納入予定日における納入予定数
に達していなければ、上記部品は欠品であると判断さ
れ、逆に、在庫数が納入予定数に達していれば、上記部
品は欠品ではないと判断される。
According to the above arrangement, the missing part status of each part is determined by the missing part determining means. For example, if the stock quantity of a certain part does not reach the scheduled delivery date on the scheduled delivery date, the part is determined to be out of stock. Conversely, if the stock quantity has reached the planned delivery quantity, the part Is not a missing item.

【0019】そして、制御手段により、上記機種を構成
する部品の総数と、欠品と判断された部品の数とに基づ
いて、上記各部品の品揃え状況が上記機種ごとに判断さ
れる。例えば、上記機種を構成する部品の総数に対す
る、欠品と判断された部品の数の割合に基づいて、品揃
え状況が上記機種ごとに判断される。
The control means determines the assortment status of each of the parts based on the total number of parts constituting the above-mentioned parts and the number of parts determined to be missing. For example, the assortment status is determined for each model based on the ratio of the number of parts determined to be missing to the total number of parts constituting the model.

【0020】このように、欠品状況判断手段の判断結果
を品揃え状況の判断に利用するので、制御手段が各部品
の品揃え状況を機種ごとに的確に判断することができ
る。
As described above, since the judgment result of the out-of-stock state judging means is used for judging the assortment state, the control means can accurately judge the assortment state of each component for each model.

【0021】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記品揃え状況の判
断対象となる機種を指定する品揃え機種指定手段をさら
に備え、上記制御手段は、上記品揃え機種指定手段によ
って指定された機種を構成する各部品の品揃え状況を判
断することを特徴としている。
In order to solve the above problems, the parts delivery progress management system according to the present invention further comprises an assortment model designating means for designating a model for which the assortment status is to be determined. It is characterized in that the assortment status of each component constituting the model designated by the assortment model designation means is determined.

【0022】上記の構成によれば、品揃え機種指定手段
によって指定された機種に対して、その機種を構成する
各部品の品揃え状況が制御手段により判断される。した
がって、管理者は、品揃え機種指定手段を操作すること
によって、品揃え状況を見る機種を自由に選択すること
ができ、管理者の意図する機種についての各部品の品揃
え状況を表示手段にて把握することができる。
According to the above arrangement, for the model designated by the assortment model designation means, the assortment status of each component constituting the model is judged by the control means. Therefore, by operating the assortment model designation means, the administrator can freely select a model whose assortment status is to be viewed, and display the assortment status of each part for the model intended by the administrator on the display means. Can understand.

【0023】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記制御手段は、上
記品揃え機種指定手段によって指定された機種を構成す
る各部品の納入予定の有無および在庫の有無とに基づい
て、上記各部品の品揃え状況を判断することを特徴とし
ている。
In order to solve the above-mentioned problems, the parts delivery progress management system according to the present invention is characterized in that the control means determines whether or not each part constituting the model designated by the assortment model designation means is scheduled to be delivered. It is characterized in that the assortment status of each of the above components is determined based on the presence or absence of stock.

【0024】上記の構成によれば、制御手段は、指定さ
れた機種についての各部品の品揃え状況を判断する際
に、各部品の納入予定の有無と、在庫の有無とに基づい
て各部品の品揃え状況を判断するので、その判断を的確
に行うことができる。
According to the above arrangement, the control means, when judging the assortment status of each part for the designated model, determines whether each part is scheduled to be delivered and whether or not each part is in stock. Since the product selection status is determined, the determination can be made accurately.

【0025】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記制御手段は、上
記機種を構成する各部品の在庫数、納入予定数、上記機
種の生産予定数および各部品の発注員数に基づいて上記
各部品が欠品となるか否か(上記各部品の発注が適正か
否か)を判断すると共に、その欠品部品(発注漏れ部
品)の有無に基づいて機種としての発注状況を確認する
ことを特徴としている。
In order to solve the above-mentioned problems, in the parts delivery progress management system according to the present invention, the control means includes: a stock quantity, a scheduled delivery quantity, a planned production quantity of each of the parts constituting the model; Based on the number of parts ordered, it is determined whether or not each of the above parts is missing (whether or not the order of each of the above parts is appropriate). It is characterized by checking the order status as a model.

【0026】上記の構成によれば、制御手段により、機
種を構成する各部品が欠品となるか否か(各部品の発注
が適正か否か)が判断される。この判断は、例えば、上
記機種を構成する各部品の在庫数と納入予定数との和
と、上記機種の生産予定数と各部品の発注員数との積と
の大小を比較することにより行われる。そして、制御手
段により、欠品部品(発注漏れ部品)の有無に基づいて
機種としての発注状況が確認される。これにより、制御
手段が各部品の発注状況を機種ごとに的確に確認するこ
とができる。
According to the above arrangement, the control means determines whether or not each part constituting the model is out of stock (whether or not the order of each part is appropriate). This determination is made, for example, by comparing the sum of the stock number and the scheduled delivery number of each part constituting the above model with the product of the planned production number of the above model and the number of orderers for each part. . Then, the control unit confirms the order status of the model based on the presence or absence of the missing parts (parts not ordered). Thus, the control means can accurately confirm the order status of each part for each model.

【0027】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記発注状況の確認
対象となる機種を指定する発注機種指定手段をさらに備
え、上記制御手段は、上記発注機種指定手段によって指
定された機種を構成する各部品の発注状況を確認するこ
とを特徴としている。
In order to solve the above-mentioned problems, the parts delivery progress management system according to the present invention further comprises order model designation means for designating a model to be checked for the order status. It is characterized in that the order status of each component constituting the model designated by the model designation means is confirmed.

【0028】上記の構成によれば、発注機種指定手段に
よって指定された機種に対して、その機種を構成する各
部品の発注状況が制御手段により確認される。したがっ
て、管理者は、発注機種指定手段を操作することによっ
て、発注状況を見る機種を自由に選択することができ、
管理者の意図する機種についての各部品の発注状況を表
示手段にて把握することができる。
According to the above arrangement, for the model designated by the order model designation means, the ordering status of each component constituting the model is confirmed by the control means. Therefore, the administrator can freely select a model whose order status is to be checked by operating the order model designation means.
The order status of each part for the model intended by the administrator can be grasped by the display means.

【0029】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記制御手段は、上
記発注機種指定手段によって指定された機種を構成する
各部品の在庫数、納入予定数、上記機種の生産予定数お
よび各部品の発注員数に基づいて、上記各部品の発注状
況を確認することを特徴としている。
In order to solve the above problems, the parts delivery progress management system according to the present invention, wherein the control means comprises: a stock quantity and a scheduled delivery quantity of each component constituting the model designated by the ordered model designation means. It is characterized in that the order status of each of the above-mentioned parts is confirmed based on the planned production number of the above-mentioned model and the number of orders for each part.

【0030】上記の構成によれば、制御手段は、指定さ
れた機種についての各部品の発注状況を確認する際に、
各部品の在庫数、納入予定数、上記機種の生産予定数お
よび各部品の発注員数に基づいて各部品の発注状況を確
認するので、その確認を的確に行うことができる。
[0030] According to the above configuration, the control means, when confirming the order status of each part for the designated model,
Since the order status of each part is confirmed based on the stock quantity of each part, the scheduled delivery number, the planned production number of the above-described model, and the number of orderers for each part, the confirmation can be performed accurately.

【0031】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記制御手段は、上
記各部品の品揃え状況の判断結果および上記各部品の発
注状況の確認結果に応じた色を各機種ごとまたは各部品
ごとに設定し、上記表示手段は、上記制御手段にて得ら
れる結果を、上記設定色にて表示することを特徴として
いる。
In order to solve the above-mentioned problems, the parts delivery progress management system according to the present invention is characterized in that the control means responds to a judgment result of an assortment status of each part and a confirmation result of an order status of each part. The display color is set for each model or each component, and the display means displays the result obtained by the control means in the set color.

【0032】上記の構成によれば、制御手段にて得られ
る結果、つまり、各部品の品揃え状況の判断結果および
各部品の発注状況の確認結果が、それらの結果に応じた
色で表示手段に表示される。これにより、表示手段を見
る管理者は、機種ごとまたは部品ごとの品揃え状況およ
び発注状況を、一目で見て容易に把握することができ
る。
According to the above arrangement, the result obtained by the control means, that is, the result of determining the assortment status of each part and the result of confirming the order status of each part are displayed in a color corresponding to the result. Will be displayed. Thereby, the administrator who looks at the display means can easily grasp at a glance the assortment status and the order status for each model or each component.

【0033】本発明に係る部品納入進度管理システム
は、上記の課題を解決するために、上記制御手段は、上
記各部品の納入の督促を支援する情報を上記表示手段に
表示させることを特徴としている。
In order to solve the above-mentioned problem, the parts delivery progress management system according to the present invention is characterized in that the control means displays on the display means information for prompting the delivery of the parts. I have.

【0034】上記各部品の納入の督促を支援する情報と
しては、上述したように、例えば、各部品の取引先およ
びその担当者、注文番号(注番)、伝票番号(伝番)が
ある。制御手段は、このような支援情報を表示手段に表
示するので、例えば管理者や部品担当者は、表示手段に
表示された支援情報に基づいて、部品の納入の取引先へ
の督促を的確に行うことができる。
As described above, the information for supporting the reminder of the delivery of each part includes, for example, the business partner and the person in charge of each part, the order number (note number), and the slip number (number). Since the control means displays such support information on the display means, for example, the manager or the parts clerk can appropriately urge the supplier to deliver the parts based on the support information displayed on the display means. It can be carried out.

【0035】本発明に係る部品納入進度管理プログラム
は、上記の課題を解決するために、生産を予定している
機種を構成する各部品の納入進度を管理する部品納入進
度管理システムにおける部品納入進度管理プログラムで
あって、上記機種の生産計画情報と、上記機種を構成す
る各部品に関する情報とに基づいて、上記各部品の納入
予定日よりも前の時点で、上記各部品の品揃え状況を上
記機種ごとに判断すると共に、上記各部品の発注状況を
上記機種ごとに確認する手段と、上記品揃え状況の判断
結果および上記発注状況の確認結果を表示する手段とし
てコンピュータを機能させるためのプログラムであるこ
とを特徴としている。
In order to solve the above-mentioned problems, a parts delivery progress management program according to the present invention provides a parts delivery progress management system for managing the delivery progress of each component constituting a model to be produced. A management program that, based on the production plan information of the above-mentioned model and the information on each of the parts constituting the above-mentioned model, determines the assortment status of each of the above-mentioned parts at a time before the scheduled delivery date of the above-mentioned parts A program for causing a computer to function as means for judging for each model and checking the order status of each part for each model, and for displaying the judgment result of the assortment status and the confirmation result of the order status It is characterized by being.

【0036】上記の部品納入進度管理プログラムをコン
ピュータが実行することにより、本発明の部品納入進度
管理方法を実現することが可能となる。
When the computer executes the above-described component delivery progress management program, the component delivery progress management method of the present invention can be realized.

【0037】本発明に係る部品納入進度管理プログラム
を記録した記録媒体は、上記の課題を解決するために、
上述した本発明の部品納入進度管理プログラムをコンピ
ュータにて読み取り可能に記録してなることを特徴とし
ている。
According to the present invention, there is provided a recording medium on which a component delivery progress management program is recorded.
The above-described parts delivery progress management program of the present invention is characterized in that it is recorded so as to be readable by a computer.

【0038】上記の構成によれば、記録媒体に記録され
ている部品納入進度管理プログラムをコンピュータが読
み取って実行することにより、本発明の部品納入進度管
理方法を実現することが可能となる。
According to the above configuration, the computer can read and execute the component delivery progress management program recorded on the recording medium, thereby realizing the component delivery progress management method of the present invention.

【0039】本発明に係る部品管理システムは、上記の
課題を解決するために、上述した本発明の部品納入進度
管理システムと、生産を予定している機種を構成する各
部品を発注する部品発注システムと、発注された各部品
を手配する受注者側システムとが通信回線を介して互い
に接続されてなることを特徴としている。
In order to solve the above-mentioned problems, a parts management system according to the present invention includes a parts delivery progress management system according to the present invention described above and a parts ordering system for ordering each part constituting a model to be produced. The system and an order receiving side system for arranging ordered parts are connected to each other via a communication line.

【0040】上記の構成によれば、部品発注システムに
て生産予定機種の構成部品が発注されると、上記発注を
受けて受注者側システムは、生産ラインに供給する部品
を手配する。
According to the above configuration, when a component of a model to be produced is ordered by the component ordering system, the order receiving side system receives the order and arranges a component to be supplied to the production line.

【0041】ここで、部品発注システムと受注者側シス
テムと部品納入進度管理システムとが通信回線を介して
接続されているので、部品納入進度管理システムは、部
品発注システムにて得られる情報(例えば部品の発注情
報)や、受注者側システムにて得られる情報(例えば1
次業者から2次加工業者への部品の支給情報)を電子デ
ータで受信し、受信した情報を即座に部品の納入管理に
反映させることが可能となる。その結果、管理者および
担当者は、部品に関する情報をリアルタイムに把握する
ことが可能となる。
Here, since the parts ordering system, the order receiving side system, and the parts delivery progress management system are connected via the communication line, the parts delivery progress management system obtains information (for example, (Part ordering information) and information (for example, 1
(Part supply information from the subcontractor to the secondary processing subcontractor) is received as electronic data, and the received information can be immediately reflected in the delivery management of the part. As a result, the manager and the person in charge can grasp the information on the parts in real time.

【0042】なお、本発明に係る部品納入進度管理方法
は、上記各部品の在庫数と、上記各部品の納入予定日に
おける納入予定数とに基づいて、(欠品状況判断手段
が)上記各部品の欠品状況を判断するステップと、上記
機種を構成する部品の総数と、欠品と判断された部品の
数とに基づいて、(制御手段が)上記各部品の品揃え状
況を上記機種ごとに判断するステップとを有していても
よい。
The method for managing the progress of parts delivery according to the present invention is based on the stock quantity of each part and the scheduled delivery number of each part on the scheduled delivery date. Based on the step of determining the missing parts status of the parts, the total number of parts constituting the model, and the number of the parts determined to be missing, the control unit determines the assortment status of each of the parts by the model. And a step of determining each time.

【0043】また、本発明に係る部品納入進度管理方法
は、(品揃え機種指定手段によって)指定された機種を
構成する各部品の品揃え状況を(制御手段が)判断する
ステップを有していてもよい。
Further, the component delivery progress management method according to the present invention has a step of (by the control means) judging the assortment status of each component constituting the designated model (by the assortment model designation means). You may.

【0044】また、本発明に係る部品納入進度管理方法
は、(上記品揃え機種指定手段によって)指定された機
種を構成する各部品の納入予定の有無および在庫の有無
とに基づいて、(制御手段が)上記各部品の品揃え状況
を判断するステップを有していてもよい。
Further, the component delivery progress management method according to the present invention is based on (control by the above-mentioned assortment model designation means) whether or not each component constituting the designated model is scheduled to be delivered and whether or not it is in stock. The means may have a step of judging an assortment status of each of the parts.

【0045】また、本発明に係る部品納入進度管理方法
は、(制御手段が)上記機種を構成する各部品の在庫
数、納入予定数、上記機種の生産予定数および各部品の
発注員数に基づいて上記各部品が欠品となるか否かを判
断すると共に、その欠品部品の有無に基づいて機種とし
ての発注状況を確認するステップを有していてもよい。
Further, the component delivery progress management method according to the present invention is characterized in that the control means (based on the number of stocks, the number of parts to be delivered, the number of parts to be produced of the above-mentioned type, and the number of orderers for each part). The method may further include a step of determining whether or not each of the above-mentioned parts is out of stock, and checking the order status as a model based on the presence or absence of the out-of-stock parts.

【0046】また、本発明に係る部品納入進度管理方法
は、(発注機種指定手段によって)指定された機種を構
成する各部品の発注状況を(制御手段が)確認するステ
ップを有していてもよい。
Further, the component delivery progress management method according to the present invention may include a step of (by the control means) confirming the order status of each component constituting the designated model (by the order model designation means). Good.

【0047】また、本発明に係る部品納入進度管理方法
は、(上記発注機種指定手段によって)指定された機種
を構成する各部品の在庫数、納入予定数、上記機種の生
産予定数および各部品の発注員数に基づいて、(制御手
段が)上記各部品の発注状況を確認するステップを有し
ていてもよい。
Further, the parts delivery progress management method according to the present invention comprises the following steps: the number of parts, the number of parts to be delivered, the number of parts to be produced, and the number of parts; (Control means) may confirm the order status of each of the parts based on the number of order members.

【0048】また、本発明に係る部品納入進度管理方法
は、(制御手段が)上記各部品の品揃え状況の判断結果
および上記各部品の発注状況の確認結果に応じた色を各
機種ごとまたは各部品ごとに設定するステップと、上記
判断結果および上記確認結果(上記制御手段にて得られ
る結果)を、(表示手段が)上記設定色にて表示するス
テップとを有していてもよい。
Further, the component delivery progress management method according to the present invention is characterized in that the control means (by the control means) assigns a color corresponding to the judgment result of the assortment status of each component and the confirmation result of the order status of each component for each model or The method may include a step of setting for each component and a step of displaying the judgment result and the confirmation result (the result obtained by the control means) in the set color (by the display means).

【0049】また、本発明に係る部品納入進度管理方法
は、(制御手段が)上記各部品の納入の督促を支援する
情報を表示手段に表示させるステップを有していてもよ
い。
Further, the component delivery progress management method according to the present invention may include a step of causing the display means to display information for assisting the prompting of the delivery of each component (by the control means).

【0050】また、本発明に係る部品納入進度管理プロ
グラムは、上記した各手段としてコンピュータを機能さ
せるためのプログラムであってもよい。
The component delivery progress management program according to the present invention may be a program for causing a computer to function as each of the above-described means.

【0051】また、本発明に係る部品納入進度管理プロ
グラムを記録した記録媒体は、上記部品納入進度管理プ
ログラムををコンピュータにて読み取り可能に記録して
なる構成であってもよい。
Further, the recording medium on which the component delivery progress management program according to the present invention is recorded may have a configuration in which the component delivery progress management program is recorded so as to be readable by a computer.

【0052】[0052]

【発明の実施の形態】本発明の実施の一形態について、
図面に基づいて説明すれば以下の通りである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described.
The following is a description based on the drawings.

【0053】本発明は、生産計画に基づいて生産される
機種を構成する部品の納入進度を管理する際に、部品の
納入予定日(納期)よりも前の時点で、部品の品揃えお
よび発注確認を行い、これによって機種の生産が隘路と
なるかどうかの傾向をつかみ、その結果に基づいて部品
の納入の督促を業者に行ったり、生産計画を変更するな
どの適切な対応を行う点に特徴がある。以下、この点を
踏まえて、まず、本発明の部品管理システムのシステム
構成について説明する。
According to the present invention, when managing the progress of delivery of parts constituting a model to be produced based on a production plan, assortment and ordering of parts before a scheduled delivery date (delivery date) of the parts. In order to determine whether or not the production of the model will be a bottleneck, and to take appropriate measures such as urging the supplier to deliver parts based on the results and changing the production plan based on the results There are features. Hereinafter, based on this point, the system configuration of the parts management system of the present invention will be described first.

【0054】(1.システム構成)図2は、本実施形態
に係る部品管理システムの概略の構成を示している。部
品管理システムは、部品発注システム1と、部品検収シ
ステム2と、部品納入進度管理システム3と、受注者側
システム4とで構成されている。なお、部品発注システ
ム1と、部品検収システム2と、部品納入進度管理シス
テム3とは、一体的に構成することが可能である。部品
納入進度管理システム3は、部品発注システム1、部品
検収システム2および受注者側システム4と、インター
ネットなどの通信回線5を介して互いに通信可能に接続
されており、電子データによる情報交換(EDI;Elec
tronic Data Interchange )が可能となっている。
(1. System Configuration) FIG. 2 shows a schematic configuration of a component management system according to the present embodiment. The parts management system includes a parts ordering system 1, a parts inspection system 2, a parts delivery progress management system 3, and a contractor system 4. The parts ordering system 1, the parts inspection system 2, and the parts delivery progress management system 3 can be integrally configured. The parts delivery progress management system 3 is communicably connected to a parts ordering system 1, a parts inspection system 2, and a supplier system 4 via a communication line 5 such as the Internet. ; Elec
tronic Data Interchange) is possible.

【0055】部品発注システム1は、生産計画/製品構
成表6をもとに作成される部品フォーキャスト7に基づ
いて、生産を計画した製品の構成部品の業者(受注者側
システム4)への発注を行うシステムである。したがっ
て、部品発注システム1からは、部品の注文情報や納期
情報が受注者側システム4に送信される。
The part ordering system 1 sends a component (a contractor system 4) of a component of a product planned to be produced based on a part forecast 7 created based on a production plan / product configuration table 6. This is a system for placing orders. Therefore, the part ordering system 1 transmits order information and delivery date information of parts to the orderer system 4.

【0056】ここで、生産計画/製品構成表6とは、生
産企画部が作成した機種(製品)の生産計画、および、
生産を計画した製品とその構成部品との対応関係を示す
構成表のことである。また、部品フォーキャスト7と
は、現在から例えば3か月後までの生産計画に基づき、
各生産予定日において生産に必要な部品の所要量(必要
日(納入予定日)、必要数量(納入予定数))を示すも
のであり、部品フォーキャスト情報として受注者側シス
テム4に提示されることになる。
Here, the production plan / product composition table 6 refers to a production plan of a model (product) created by the production planning department, and
This is a composition table showing the correspondence between products planned for production and their components. In addition, the part forecast 7 is based on a production plan from the present to three months later, for example.
It indicates the required quantity (necessary date (scheduled delivery date), required quantity (scheduled delivery number)) of parts required for production at each scheduled production date, and is presented to the contractor-side system 4 as part forecast information. Will be.

【0057】また、部品発注システム1からの上記注文
情報には、予約注文と確定注文との2種類の情報があ
る。予約注文とは、確定注文の前に注文の予定を提示す
るものであり、部品の手配に必要な時間(以下、調達リ
ードタイム(L/T)とも称する)だけ、当該部品が必
要となる生産予定日から遡って発行される。一方、確定
注文とは、予約注文の範囲内で行われ、必要日時間近に
なって実際の必要数量および納期が指定されて発行され
るものである。
The order information from the parts ordering system 1 includes two types of information: a reservation order and a confirmed order. A pre-order is a process of presenting an order schedule before a firm order, and a production in which the part is required only for the time required for arranging the part (hereinafter, also referred to as procurement lead time (L / T)). Issued retroactively from the scheduled date. On the other hand, the firm order is placed within the range of the reserved order, and is issued with the actual required quantity and delivery date specified near the required date and time.

【0058】したがって、本システムにおいては、部品
の注文を行うにあたり、フォーキャスト(所要量計
画)、予約注文、確定注文の3段階注文方式が採られて
いる。
Therefore, in order to order parts, the present system employs a three-stage order system of forecast (requirement planning), reservation order, and confirmed order.

【0059】また、部品発注システム1は、部品の発注
情報や、発注した部品を用いて生産される製品の生産日
程、部品の納期情報などを部品納入進度管理システム3
に送信する。これにより、部品納入進度管理システム3
は、そのような情報を用いて部品の納入進度を管理する
ことが可能となる。
The part ordering system 1 also stores part ordering information, production schedules of products produced using the ordered parts, parts delivery date information, and the like.
Send to As a result, the parts delivery progress management system 3
It is possible to manage the progress of parts delivery using such information.

【0060】部品検収システム2は、部品発注システム
1からの発注に基づき、受注者側システム4から生産ラ
インに供給される部品を検収する。部品検収システム2
での検収の結果は、検収実績として部品納入進度管理シ
ステム3に送信される。また、検収した部品を用いて生
産ラインにて生産した機種の生産実績も、部品納入進度
管理システム3に送信される。
The parts inspection system 2 inspects the parts supplied to the production line from the contractor system 4 based on the order from the parts ordering system 1. Parts inspection system 2
Is sent to the parts delivery progress management system 3 as the inspection result. Further, the production results of the models produced on the production line using the inspected components are also transmitted to the component delivery progress management system 3.

【0061】部品納入進度管理システム3は、部品発注
システム1、部品検収システム2および受注者側システ
ム4から送信される情報に基づいて、生産予定の機種を
構成する部品の納入進度を管理するシステムであり、本
発明の最も特徴的な部分である。なお、部品納入進度管
理システム3の詳細については後述する。
The parts delivery progress management system 3 manages the delivery progress of the parts constituting the model to be produced based on information transmitted from the parts ordering system 1, the parts inspection system 2, and the orderer system 4. Which is the most characteristic part of the present invention. The details of the component delivery progress management system 3 will be described later.

【0062】受注者側システム4は、部品発注システム
1からの発注に基づいて部品を手配し、部品検収システ
ム2に供給するシステムであり、国内パーツメーカシス
テム、海外パーツメーカシステム、JIT(Just In Ti
me)基地システム、2次加工業者システムなどで構成さ
れている。
The contractor-side system 4 is a system for arranging parts based on the order from the parts ordering system 1 and supplying the parts to the parts inspection system 2, and includes a domestic parts maker system, an overseas parts maker system, and JIT (Just In). Ti
me) It consists of a base system, a secondary processor system and the like.

【0063】ここで、上記のJIT基地システムは、預
託した業者の倉庫であり、倉庫内に保管された部品をす
ぐに生産ラインに供給したり、2次加工業者システムに
支給することができるような場所に設けられている。よ
って、このJIT基地システムには、例えば遠隔地のパ
ーツメーカから供給される部品や、機種の生産によく用
いられる部品などが主に保管される。
The JIT base system described above is a warehouse of a contractor, so that parts stored in the warehouse can be immediately supplied to a production line or supplied to a secondary processor system. It is provided in a place. Therefore, the JIT base system mainly stores, for example, parts supplied from a remote parts maker, parts frequently used for model production, and the like.

【0064】このJIT基地システムでは、部品を必要
量だけ出庫した都度、検収が行われ、部品の検収情報や
支給情報が部品納入進度管理システム3に送信される。
また、JIT基地システムが国内パーツメーカシステム
から入庫した部品の入庫情報も、部品納入進度管理シス
テム3に送信される。
In this JIT base system, every time a required quantity of parts is delivered, inspection is performed, and inspection information and supply information of the parts are transmitted to the part delivery progress management system 3.
In addition, the storage information of the parts received by the JIT base system from the domestic parts maker system is also transmitted to the parts delivery progress management system 3.

【0065】受注者側システム4が国内パーツメーカシ
ステムで構成される場合、当該システムからは、部品の
出荷情報(2次加工業者への出荷(直送)も含む)が部
品納入進度管理システム3に送信される。また、受注者
側システム4が2次加工業者システムで構成される場
合、当該システムには、上記したフォーキャスト情報や
注文情報が送信されるようになっている。
When the orderer-side system 4 is composed of a domestic parts maker system, the parts delivery information (including the shipment (direct delivery) to the secondary processor) is sent from the system to the parts delivery progress management system 3. Sent. Further, when the contractor-side system 4 is constituted by a secondary processor system, the above-mentioned forecast information and order information are transmitted to the system.

【0066】ここで、2次加工業者システムは、国内パ
ーツメーカシステムやJIT基地システムなどから搬送
される部品を組み立てて組品をつくるシステムである。
2次加工業者システムにて組み立てられた組品は、部品
検収システム2を介して生産ラインに搬送される。
Here, the secondary processor system is a system for assembling parts conveyed from a domestic part maker system, a JIT base system, or the like to form an assembly.
The assembled product assembled by the secondary processor system is transferred to the production line via the parts inspection system 2.

【0067】なお、説明の便宜上、国内パーツメーカシ
ステムなどから2次加工業者システムに搬送される部品
を『支給部品』と称することとし、その搬送を『支給』
と称することにする。また、国内パーツメーカシステム
などから直接生産ラインに搬送される部品、あるいは、
2次加工業者システムから生産ラインに搬送される部品
を『供給部品』と称することとし、その搬送を『供給』
と称することにする。つまり、『供給部品』と言えば、
納入後すぐに生産ラインで使用する部品を指し、『支給
部品』と言えば、『供給部品』が組品である場合に、そ
の組品を構成する部品を指す。以下、『供給部品』と
『支給部品』、『供給』と『支給』とは区別することに
する。
For convenience of explanation, the parts to be transferred from the domestic parts maker system or the like to the secondary processing system are referred to as “supplied parts”, and the transfer is referred to as “supplied”.
I will call it. Also, parts transferred directly to the production line from a domestic parts maker system, or
Parts transferred from the secondary processor system to the production line are referred to as "supply parts", and the transfer is referred to as "supply".
I will call it. In other words, speaking of "supplied parts"
Refers to parts used on the production line immediately after delivery, and "supplied parts" refers to parts that make up the assembled parts when the "supplied parts" are assembled. Hereinafter, "supply parts" and "supply parts" and "supply" and "supply" will be distinguished.

【0068】受注者側システム4が海外パーツメーカで
構成されている場合、受注者側システム4から供給され
る部品は、輸入通関8を介して部品検収システム2に供
給される。また、この場合は、部品の出港予定(ET
D;Estimate Time of Departure)および着港予定(E
TA;Estimate Time of Arrival)に関する情報が、W
WW(World Wide Web)ブラウザにより部品納入進度管
理システム3に送信される。
When the contractor-side system 4 is composed of an overseas parts maker, the parts supplied from the contractor-side system 4 are supplied to the parts inspection system 2 via the import customs clearance 8. In this case, the part is scheduled to leave (ET
D; Estimate Time of Departure and scheduled arrival (E)
Information on TA: Estimate Time of Arrival
It is transmitted to the parts delivery progress management system 3 by a WW (World Wide Web) browser.

【0069】ここで、図3は、部品発注処理および部品
検収処理の概要を示している。これらについて説明する
と、受注者側システム4のJIT基地システムからは、
部品の入庫データが部品発注システム1のホストコンピ
ュータに送信される。上記ホストコンピュータは、部品
フォーキャスト情報7に基づいて部品の注文書を作成
し、協力会社(例えば受注者側システム4の2次加工業
者システムや国外パーツメーカシステム)に送信する。
FIG. 3 shows an outline of the parts ordering processing and the parts inspection processing. To explain these, from the JIT base system of the contractor system 4,
The storage data of the parts is transmitted to the host computer of the parts ordering system 1. The host computer creates an order form for the part based on the part forecast information 7 and transmits the order to a cooperating company (for example, a secondary processing system of the contractor system 4 or a foreign parts maker system).

【0070】受注者側システム4は、注文のあった部品
にEIAJ(日本電子機械工業会)の規格に準拠した納
品書を付け、当該部品を部品検収システム2に出荷す
る。部品検収システム2は、上記納品書に付加されてい
るバーコードをハンディーターミナル(携帯端末)で読
み取り、出荷された部品の検収を行う。検収の結果は、
直接あるいは部品発注システム1のホストコンピュータ
を介して部品納入進度管理システム3に供給される。
The order receiving side system 4 attaches a delivery note conforming to EIAJ (Electronic Manufacturers Association of Japan) standards to the ordered parts and ships the parts to the parts inspection system 2. The parts inspection system 2 reads the barcode added to the delivery note with a handy terminal (portable terminal) and inspects the shipped parts. The result of the inspection is
It is supplied to the parts delivery progress management system 3 directly or via the host computer of the parts ordering system 1.

【0071】一方、受注者側システム4では、当該部品
のEIAJ納品書の情報およびETA情報(輸入部品の
とき)が直送部品の納品実績としてコンピュータに入力
され、これらの情報がWWWブラウザにより本社インタ
ーネットサーバへ送信される。そして、これらの情報
は、当該サーバから部品発注システム1のホストコンピ
ュータを介して部品納入進度管理システム3に送信され
る。
On the other hand, in the contractor-side system 4, the information of the EIAJ delivery note and the ETA information (for imported parts) of the parts are input to the computer as the delivery results of the directly sent parts, and the information is sent to the head office Internet by a WWW browser. Sent to server. These pieces of information are transmitted from the server to the component delivery progress management system 3 via the host computer of the component ordering system 1.

【0072】図2に示すように、部品発注システム1と
部品検収システム2と部品納入進度管理システム3と受
注者側システム4とが通信回線5を介して接続されてい
ることで、例えば、部品発注システム1にて得られる部
品の発注情報、部品検収システム2での検収実績、受注
者側システム4における1次業者から2次加工業者シス
テムに支給される部品の支給実績が、通信回線5を介し
て電子データとして部品納入進度管理システム3に送信
される。
As shown in FIG. 2, the parts ordering system 1, the parts inspection system 2, the parts delivery progress management system 3, and the contractor system 4 are connected via the communication line 5, so that, for example, The ordering information of parts obtained by the ordering system 1, the results of inspection by the parts inspection system 2, and the results of parts supply from the primary contractor to the secondary processing system in the supplier system 4 are transmitted through the communication line 5. The electronic data is transmitted to the component delivery progress management system 3 as electronic data.

【0073】これにより、部品納入進度管理システム3
は、部品の納入管理に上記電子データを直ぐに利用する
ことが可能となる。その結果、管理者および担当者は、
部品の納入管理における最新情報を把握することができ
る。また、これにより、納入部品の隘路の発生をできる
だけ抑え、生産遅延の発生をできるだけ抑えることも可
能となる。また、納入部品が輸入部品の場合は、ETA
情報が部品納入進度管理システム3に送信されるので、
部品の納入進度管理の精度を向上させることができる。
Thus, the part delivery progress management system 3
Enables the electronic data to be used immediately for parts delivery management. As a result, administrators and
The latest information on parts delivery management can be grasped. This also makes it possible to minimize the occurrence of bottlenecks in delivered parts and to minimize the production delay. If the delivered parts are imported parts, ETA
Since the information is transmitted to the parts delivery progress management system 3,
It is possible to improve the accuracy of managing the progress of parts delivery.

【0074】(2.部品納入進度管理システムの構成)
次に、部品納入進度管理システム3の詳細について説明
する。部品納入進度管理システム3は、生産計画に基づ
いて生産される機種を構成する部品の納入進度を管理す
るシステムであり、図1に示すように、データ記憶部1
1(記憶手段)と、納入進度管理処理部21と、通信部
31と、出力部32と、入力部33と、進度管理端末装
置34(表示手段、品揃え機種指定手段、発注機種指定
手段)とを備えている。
(2. Configuration of Component Delivery Progress Management System)
Next, details of the parts delivery progress management system 3 will be described. The parts delivery progress management system 3 is a system that manages the delivery progress of the parts that make up the model produced based on the production plan, and as shown in FIG.
1 (storage means), delivery progress management processing section 21, communication section 31, output section 32, input section 33, progress management terminal device 34 (display means, assortment model designation means, order model designation means) And

【0075】通信部31は、納入進度管理処理部21に
おいて処理された情報を通信回線を介して進度管理端末
装置34に送信するためのインターフェースである。
The communication section 31 is an interface for transmitting the information processed in the delivery progress management processing section 21 to the progress management terminal device 34 via a communication line.

【0076】出力部32は、納入進度管理処理部21に
て得られる後述する各種テーブルや、L/Tなどの部品
管理に必要な情報を出力するものであり、例えばPC
(Personal Computer )のモニタやプリンタで構成され
る。この出力部32を扱うのは、部品担当者のみとなっ
ている。
The output section 32 outputs various tables, which will be described later, obtained by the delivery progress management processing section 21 and information necessary for parts management such as L / T.
(Personal Computer) monitor and printer. Only the person in charge of parts handles this output unit 32.

【0077】入力部33は、各種情報を入力するための
ものであり、キーボードやマウスなどによって構成され
ている。担当者は、この入力部33を介して、出力部3
2に表示させる画面の切り替えなどを行うことが可能と
なっている。
The input section 33 is for inputting various information, and is constituted by a keyboard, a mouse and the like. The person in charge can output to the output unit 3 via the input unit 33.
For example, it is possible to switch the screen to be displayed on the display 2.

【0078】進度管理端末装置34は、後述する納入進
度管理処理部21において処理された情報を表示するも
のであり、例えばPCで構成されている。部品の納入進
度を直接管理している担当者、その担当者の上司である
管理者、および、生産企画部の部長などは、進度管理端
末装置34に表示される画面を見ることで、部品の納入
進度を把握することができる。
The progress management terminal device 34 displays information processed in the delivery progress management processing unit 21 described later, and is composed of, for example, a PC. The person in charge of directly managing the progress of parts delivery, the manager who is the supervisor of the person in charge, and the manager of the production planning department, etc., see the screen displayed on the progress management terminal device 34, The progress of delivery can be grasped.

【0079】また、進度管理端末装置34は、管理者や
生産企画部(以下、管理者に統一して記載する)が納入
進度管理処理部21に対する処理を指示する際にも用い
られる。つまり、進度管理端末装置34は、納入進度管
理処理部21の後述する部品納入進度表示制御部27で
の品揃え状況の判断対象となる機種を指定したり、発注
状況の確認対象となる機種を指定する場合にも用いられ
る。
The progress management terminal device 34 is also used when a manager or a production planning department (hereinafter, referred to as a manager) instructs the delivery progress management processing unit 21 to perform processing. In other words, the progress management terminal device 34 designates a model for which the component delivery progress display control unit 27 of the delivery progress management processing unit 21, which will be described later, determines the assortment status, and specifies a model for which the order status is to be confirmed. Also used when specifying.

【0080】また、進度管理端末装置34は、部品納入
進度管理システム3以外に、例えば受注者側システム4
にも設置されており、受注者側システム4でも部品の納
入進度を把握することが可能となっている。
Further, in addition to the parts delivery progress management system 3, the progress management terminal device 34 includes, for example, an orderer side system 4.
The order receiving party system 4 can also grasp the progress of parts delivery.

【0081】次に、データ記憶部11について説明す
る。データ記憶部11は、部品納入進度管理システム3
が部品の納入進度を管理するのに必要な情報を記憶する
ものであり、生産計画(日程)マスター12、部品別適
用機種マスター13、納入予実マスター14、注残マス
ター15、在庫マスター16、取引先マスター17およ
び担当者マスター18で構成されている。
Next, the data storage unit 11 will be described. The data storage unit 11 stores the parts delivery progress management system 3
Stores information necessary to manage the progress of parts delivery, and includes a production plan (schedule) master 12, an applicable model master 13 for each part, a delivery forecast master 14, a backlog master 15, an inventory master 16, and a transaction. It is composed of a destination master 17 and a person in charge master 18.

【0082】ここで、図4は、上記の各マスターに記憶
されている情報の一覧を示している。なお、同図中の左
欄の項目の情報のうち、各マスターに記憶される情報を
○印で示している。以下、この図4を参照しながら、各
マスターについて説明する。
FIG. 4 shows a list of information stored in each master. The information stored in each master among the information of the items in the left column in FIG. Hereinafter, each master will be described with reference to FIG.

【0083】生産計画マスター12は、機種の生産計画
に関する情報を記憶している。具体的には、生産計画マ
スター12は、生産を計画した事業部、機種の生産月、
機種が試作であるか量産であるかの区分、生産を予定し
ている機種の製品コード、生産部門(工程)、生産実績
数、日別生産計画数(生産予定日ごとの生産予定数)に
関する情報を記憶している。
The production plan master 12 stores information relating to the production plan of the model. Specifically, the production planning master 12 includes a business unit planning production, a production month of a model,
Classification of whether the model is a prototype or mass production, product code of the model to be produced, production department (process), number of actual productions, daily production plan number (planned number of production for each planned production date) Information is stored.

【0084】部品別適用機種マスター13は、各部品
と、各部品が適用される機種との対応関係を各部品ごと
に把握するための情報を記憶している。具体的には、部
品別適用機種マスター13は、事業部、生産月、区分
(試作/量産)、品種、製品コード、部品の納入場所、
部品コード、次工程に関する情報を記憶している。
The applicable model master 13 for each part stores information for grasping the correspondence between each part and the model to which each part is applied for each part. More specifically, the applicable model master 13 for each part includes a business unit, a production month, a division (prototype / mass production), a kind, a product code, a part delivery location,
The part code and information on the next process are stored.

【0085】上記の次工程の情報とは、納入対象となる
部品が次にどの工程に搬送されるのかを示す情報であ
り、例えば、各工程に対応する数桁の数字を含んで表さ
れる。ここで、支給部品の次工程情報には、上記の数字
の末尾にさらにアルファベットを付ける一方、供給部品
の次工程情報には上記のアルファベットを付けないよう
にすることで、次工程情報を参照すれば、供給部品であ
るか支給部品であるかを判断することが可能となる。
The information on the next process is information indicating to which process the component to be delivered is to be transported next, and includes, for example, several digits corresponding to each process. . Here, in the next process information of the supplied parts, an alphabet is further added to the end of the above number, while the next process information of the supplied parts is not appended with the alphabet, so that the next process information can be referred to. For example, it is possible to determine whether the component is a supplied component or a supplied component.

【0086】納入予実マスター14は、部品の納入予定
と納入実績とを把握するための情報を記憶している。具
体的には、納入予実マスター14は、事業部、生産月、
品種、納入場所、部品コード、部品名称、予約注文およ
び確定注文の注文番号(以下、注番と記載する)、L/
T(調達リードタイム)、生産予定日の何日前(実質稼
働日分)に納品が必要かを示す手番(加工)、取引先コ
ード、次工程、総発注数、部品(供給部品を含む)の納
入予定日、納入予定数、納入実績数、最新納期、支給部
品の支給日、支給予定数、支給実績数、単価、預託部品
倉庫納入(預託部品として倉庫に納入されている部品か
否か)に関する情報を記憶している。なお、上記の最新
納期とは、生産日程の変更のシュミレーションを行った
ときに、最終的に決定される部品の最新納期のことであ
る。
The delivery forecast master 14 stores information for ascertaining the delivery schedule and delivery results of parts. Specifically, the delivery forecast master 14 is divided into the division, the production month,
Product type, delivery location, part code, part name, order numbers for reservation and firm orders (hereinafter referred to as note numbers), L /
T (procurement lead time), turn (processing) indicating how many days before the scheduled production date (effective working day) delivery is required, supplier code, next process, total order quantity, parts (including supply parts) Scheduled delivery date, scheduled delivery number, actual delivery number, latest delivery date, supply date of supplied parts, scheduled supply number, actual supply number, unit price, delivery of consigned parts warehouse (whether parts are delivered to the warehouse as consigned parts ) Is stored. Note that the latest delivery date is the latest delivery date of parts that is finally determined when a simulation of a change in the production schedule is performed.

【0087】注残マスター15は、基本的には、納入予
実マスター14の記憶内容とほぼ同じ内容を記憶してい
る。具体的には、注残マスター15は、事業部、生産
月、品種、製品コード、部品コード、部品が組品の場合
の親部品を示す親部品コード、部品名称、注番、伝票番
号(以下、伝番と記載する)、L/T、手番(加工)、
発注員数、取引先コード、次工程、資材部担当者名(コ
ード番号)、部品管理担当者名(コード番号)、総発注
数、納入予定日、納入予定数、納入実績数、最新納期、
発注済納入残数、支給日、支給予定数、支給実績数、直
送支給、ETD・ETA日付、預託部品倉庫納入に関す
る情報を記憶している。
The backlog master 15 basically stores almost the same contents as the stored contents of the delivery forecast master 14. Specifically, the backlog master 15 includes a business unit, a production month, a product type, a product code, a part code, a parent part code indicating a parent part when the part is an assembled part, a part name, a note number, and a slip number (hereinafter, referred to as a part number). , A number), L / T, turn (processing),
Number of orderer, supplier code, next process, name of material department staff (code number), name of parts manager (code number), total order quantity, expected delivery date, expected delivery number, actual delivery number, latest delivery date,
Stores information on the number of ordered deliveries remaining, the payment date, the planned number of payments, the number of actual payments, the direct delivery, the ETD / ETA date, and the delivery of the consigned parts warehouse.

【0088】なお、上記の直送支給とは、国内パーツメ
ーカシステムから2次加工業者システムに支給される部
品であるか否かを示す情報である。
The direct delivery is information indicating whether or not the part is supplied from the domestic parts maker system to the secondary processing system.

【0089】また、上記の発注員数とは、1個の機種を
生産するのに必要な構成部品の数を指す。例えば、図5
に示すように、機種Aが部品Bおよび部品Cからなって
おり、部品Bがさらに部品Dと部品Eとからなり、部品
Eがさらに部品Fと部品Gとからなっているものとす
る。そして、機種Aまたは親部品を生産するのに必要な
子部品の数を、同図の括弧内の数字で示す。つまり、同
図は、機種Aを生産するのに、部品Bが1個、部品Cが
1個必要であり、部品Bを生産するのに部品Dが1個、
部品Eが2個必要であり、部品Eを生産するのに部品F
が1個、部品Gが2個必要であることを示す。この場
合、例えば部品Gの発注員数、つまり、1個の機種Aを
生産するのに必要な部品Gの数は4となる。
The number of order members indicates the number of components necessary to produce one model. For example, FIG.
As shown in the figure, it is assumed that the model A is composed of the parts B and C, the part B is further composed of the parts D and E, and the part E is further composed of the parts F and G. The number in parentheses in the figure indicates the number of child parts required to produce the model A or the parent part. That is, in the figure, one part B and one part C are required to produce the model A, and one part D is required to produce the part B.
Two parts E are required, and the parts F
Indicates that one component and two components G are required. In this case, for example, the number of parts G ordered, that is, the number of parts G required to produce one model A is four.

【0090】在庫マスター16は、工場の部品の在庫を
把握するための情報を記憶している。具体的には、在庫
マスター16は、事業部、生産月、品種、納入場所、部
品コード、次工程、部品管理担当者名、工場内の部品の
在庫数(前日・現在)、単価に関する情報を記憶してい
る。
The stock master 16 stores information for grasping the stock of parts at the factory. Specifically, the inventory master 16 stores information on the division, the production month, the product type, the delivery location, the part code, the next process, the name of the parts manager, the number of parts in the factory (the previous day / present), and the unit price. I remember.

【0091】取引先マスター17は、部品の取引先を把
握するための情報を記憶している。具体的には、取引先
マスター17は、事業部、取引先コード、業者(取引
先)名称)、窓口担当者名、TEL番号、資材部担当者
名、部品管理担当者名に関する情報を記憶している。な
お、取引先マスター17は、資材部担当者名として、コ
ード番号とそれに対応する担当者名とを両方記憶してい
る。
[0091] The supplier master 17 stores information for grasping the parts supplier. Specifically, the supplier master 17 stores information on the business division, supplier code, supplier (supplier name), contact person name, TEL number, material department person name, and parts management person name. ing. Note that the supplier master 17 stores both the code number and the corresponding person name as the material part person name.

【0092】担当者マスター18は、部品の納入を管理
している担当者を把握するための情報を記憶している。
具体的には、担当者マスター18は、事業部、生産部門
(工程)、部品管理担当者名に関する情報を記憶してい
る。なお、担当者マスター18は、部品管理担当者名と
して、コード番号とそれに対応する担当者名とを両方記
憶している。
The person in charge master 18 stores information for grasping the person in charge who manages the delivery of parts.
Specifically, the person in charge master 18 stores information on the business division, the production department (process), and the name of the person in charge of parts management. The person in charge master 18 stores both the code number and the person in charge corresponding to the code number as the part management person in charge.

【0093】次に、納入進度管理処理部21について説
明する。
Next, the delivery progress management processing section 21 will be described.

【0094】納入進度管理処理部21は、データ記憶部
11に記憶されている情報に基づいて、部品の納入進度
を管理するものであり、図1に示すように、機種別構成
部品展開部22、部品別納入予定実績比較部23、隘路
判断部24(欠品状況判断手段)、出力要求別仕訳部2
5、発注内容確認部26および制御手段としての部品納
入進度表示制御部(以下、単に制御部と記載する)27
で構成されている。
The delivery progress management processing section 21 manages the delivery progress of parts based on the information stored in the data storage section 11, and as shown in FIG. , Parts-by-part delivery schedule comparison section 23, bottleneck determination section 24 (out-of-stock state determination means), output request-specific journaling section
5. Order confirmation unit 26 and a part delivery progress display control unit (hereinafter simply referred to as a control unit) 27 as a control means
It is composed of

【0095】機種別構成部品展開部22は、生産計画マ
スター12および部品別適用機種マスター13に記憶さ
れている情報に基づいて、生産計画のある機種(当日以
降の12日間に生産計画のある機種)の生産に使用され
る部品を把握し、部品別適用機種テーブルを作成する。
具体的には以下の通りである。
The model-specific component expanding section 22 is configured to execute a model with a production plan (models with a production plan for 12 days from that day) based on the information stored in the production plan master 12 and the applicable model master 13 for each part. ) Grasp the parts used in the production and create a table of applicable models for each part.
Specifically, it is as follows.

【0096】図6は、生産計画マスター12および部品
別適用機種マスター13に記憶されている情報の一例を
示している。この場合、機種別構成部品展開部22は、
まず、生産計画マスター12に記憶されている情報の中
から、生産計画にある機種の製品コード(A1AU123456)
を抽出し、その製品コードに対応する部品コード(CPA1
234567890 )に関する情報を部品別適用機種マスター1
3から抽出する。そして、機種別構成部品展開部22
は、同図に示すように、上記製品コードと上記部品コー
ドに関する情報とを対応付ける部品別適用機種テーブル
を作成する。このような部品別適用機種テーブルを作成
することにより、生産予定の機種とその構成部品との関
連性を生産予定日ごとに管理することができる。
FIG. 6 shows an example of information stored in the production plan master 12 and the applied model master 13 for each part. In this case, the model-specific component expanding unit 22
First, from the information stored in the production plan master 12, the product code of the model in the production plan (A1AU123456)
Is extracted and the part code (CPA1
234567890) Applicable model master by component
Extract from 3. Then, the model-specific component developing unit 22
Creates a part-by-part applicable model table that associates the product code with information on the part code, as shown in FIG. By creating such a part-by-part applicable model table, it is possible to manage the relationship between the model to be produced and its component parts for each scheduled production date.

【0097】部品別納入予定実績比較部23は、機種別
構成部品展開部22にて作成した部品別適用機種テーブ
ルと、納入予実マスター14および在庫マスター16に
記憶されている情報とに基づいて、生産計画にある機種
の生産に用いられる部品の納入予定と納入実績との対比
テーブル(納入予定・実績テーブル)を作成する。具体
的には、以下の通りである。
The part-by-part delivery schedule comparison section 23 is based on the part-by-part application model table created by the model-specific component development section 22 and the information stored in the delivery forecast master 14 and the stock master 16. Create a comparison table (delivery schedule / result table) between the delivery schedule and delivery results of the parts used for the production of the models in the production plan. Specifically, it is as follows.

【0098】図7は、機種別構成部品展開部22にて作
成した部品別適用機種テーブル(図6と同じテーブル)
と、納入予実マスター14に記憶されている情報の一例
を示している。この場合、部品別納入予定実績比較部2
3は、部品別適用機種テーブルの中の部品コード(CPA1
234567890 )をもとにして、納入予実マスター14の中
から、当該部品コードに対応する部品の納入予定日、納
入予定数、納入実績数などを抽出し、同図に示す納入予
定・実績対比テーブルを作成する。
FIG. 7 shows a part-by-part applicable model table created by the model-specific component developing unit 22 (the same table as in FIG. 6).
And an example of information stored in the delivery forecast master 14. In this case, the parts delivery schedule comparison part 2
3 is the part code (CPA1
234567890), the scheduled delivery date, scheduled delivery number, delivery actual number, etc. of the part corresponding to the part code are extracted from the delivery forecast master 14 and the delivery schedule / actual comparison table shown in FIG. Create

【0099】次に、在庫マスター16の記憶内容が例え
ば図8に示す内容であるとすると、部品別納入予定実績
比較部23は、上記納入予定・実績対比テーブルにおけ
る部品コードに対応する在庫数を在庫マスター16より
抽出し、抽出した在庫数を上記納入予定・実績対比テー
ブルに書き込み、同図に示す納入予定・実績テーブルを
最終的に決定する。
Next, assuming that the storage contents of the inventory master 16 are, for example, the contents shown in FIG. 8, the part-by-part delivery schedule / actual comparison section 23 calculates the inventory quantity corresponding to the part code in the delivery schedule / actual comparison table. It is extracted from the stock master 16 and the extracted stock quantity is written in the above-mentioned delivery schedule / actual comparison table, and the delivery schedule / actual table shown in FIG.

【0100】つまり、最終的には、部品別適用機種テー
ブルにおける製品コード(生産予定の機種名)と、納入
予定・実績テーブルに記憶された情報のうち、上記製品
コードに対応する部品コードの部品に関する情報と、上
記部品の在庫数の情報とを足し合わせたものが、納入予
定・実績テーブルとなる。
That is, finally, the product code (model name to be produced) in the applicable model table for each part and the part of the part code corresponding to the product code in the information stored in the delivery schedule / actual table. The sum of the information on the parts and the information on the number of parts in stock constitutes a delivery schedule / actual table.

【0101】なお、同図の納入予定・実績テーブルで
は、部品コードを1つしか挙げていないが、これは説明
を簡略化するためである。機種の生産は、通常、複数の
部品を用いて行われるため、実際には複数の部品コード
が存在している。
Note that, in the delivery schedule / result table of FIG. 10, only one component code is listed, but this is for the sake of simplicity. Since the production of a model is usually performed using a plurality of parts, there are actually a plurality of part codes.

【0102】隘路判断部24は、部品別納入予定実績比
較部23にて作成した納入予定・実績テーブルと、生産
計画マスター12および納入予実マスター14に記憶さ
れている情報とに基づいて、機種を構成する部品の欠品
状況を判断する。以下、この点について、より具体的に
説明する。
The bottleneck judging unit 24 determines the model based on the delivery schedule / actual table created by the part-by-part delivery schedule / actual comparison unit 23 and the information stored in the production plan master 12 and the delivery forecast master 14. Determine the missing parts status of the constituent parts. Hereinafter, this point will be described more specifically.

【0103】隘路判断部24は、まず、上記納入予定・
実績テーブルにおける製品コード(機種名)と生産月と
を把握し、生産計画マスター12に記憶されている情報
の中から、上記製品コードと上記生産月とから特定され
る生産予定機種の内容を把握する。
The bottleneck judging section 24 firstly checks the delivery schedule
The product code (model name) and the production month in the performance table are grasped, and from the information stored in the production plan master 12, the contents of the planned production model specified by the product code and the production month are grasped. I do.

【0104】ここで、図9は、5月11日現在における
納入予定・実績テーブルと、このテーブルの中の製品コ
ードおよび生産月に基づいて生産計画マスター12から
抽出した情報とを示している。同図の日別生産計画数か
ら、5月11日に生産予定の機種が100台、5月12
日に生産予定の機種が100台あることがわかる。
FIG. 9 shows a delivery schedule / actual table as of May 11, and information extracted from the production plan master 12 based on the product code and the production month in this table. Based on the number of daily production plans shown in the figure, 100 units scheduled to be produced on May 11th, May 12th
It can be seen that there are 100 models scheduled to be produced each day.

【0105】次に、隘路判断部24は、納入予定・実績
テーブルの中の手番を見る。同図では、手番は1となっ
ており、このことから、生産予定日の1日前に部品の納
入が必要であることが把握される。
Next, the bottleneck judging section 24 looks at the turn in the delivery schedule / results table. In the figure, the turn number is 1, which indicates that it is necessary to deliver parts one day before the scheduled production date.

【0106】次に、隘路判断部24は、納入予定・実績
テーブルの中の納入予定数および納入実績数を見る。こ
のとき、上記手番が1であることから、隘路判断部24
は、納入予定日が生産予定日より1日前の納入予定数お
よび納入実績数を見ることになる。
Next, the bottleneck judging unit 24 checks the number of scheduled deliveries and the number of actual deliveries in the delivery schedule / actual table. At this time, since the turn is 1, the bottleneck determination unit 24
Means the number of scheduled deliveries and the number of actual deliveries where the scheduled delivery date is one day before the scheduled production date.

【0107】同図では、5月11日の生産予定日より1
日前の5月10日における部品の納入予定数、納入実績
数はそれぞれ100、100となっており、納入実績数
が納入予定数を下回っていない。したがって、この場
合、隘路判断部24は、5月11日に生産予定の機種に
ついては、部品の納入実績数が生産計画を満足している
(隘路ではない)と判断したことになる。
[0107] In the figure, 1 day from the scheduled production date on May 11th.
The scheduled number of parts delivered and the number of actual deliveries on May 10 of the previous day are 100 and 100, respectively, and the number of actual deliveries is not less than the expected number of deliveries. Therefore, in this case, the bottleneck determination unit 24 has determined that, for the model scheduled to be produced on May 11, the number of delivered parts satisfies the production plan (not a bottleneck).

【0108】一方、5月12日の生産予定日より1日前
の5月11日現在における部品の納入予定数、納入実績
数はそれぞれ100、90となっており、納入されるべ
き部品の数が10個不足している。このとき、部品の現
在の在庫が5個であるので、最終的には部品の不足分は
5個となる。この場合、隘路判断部24は、5月12日
に生産予定の機種については、部品の納入実績数が生産
計画を満足していない(隘路である)と判断する。
On the other hand, the scheduled number of parts delivered and the number of actual parts delivered as of May 11, one day before the scheduled production date of May 12, are 100 and 90, respectively. 10 are missing. At this time, since the current stock of the component is five, the shortage of the component eventually becomes five. In this case, the bottleneck determination unit 24 determines that the actual number of parts delivered does not satisfy the production plan for the model scheduled to be produced on May 12 (it is a bottleneck).

【0109】隘路判断部24は、このような判断を、5
月11日以降の12日間に生産予定のある機種の構成部
品の全てについて判断する。ただし、納入予定日は将来
であるので、隘路判断の当日以外の納入予定日の部品に
ついては、その納入予定日における納入実績数はゼロと
みなす。
The bottleneck determination unit 24 determines such a determination as 5
Judgment is made for all components of a model that is scheduled to be produced for 12 days from the 11th of the month. However, since the scheduled delivery date is in the future, the number of delivered parts on the scheduled delivery date other than the day of the bottleneck determination is regarded as zero.

【0110】このように、隘路判断部24は、生産予定
の機種の構成部品の納入予定日における納入予定数、納
入実績数、在庫数に基づいて、部品の欠品状況を判断す
るようになっている。特に、納入予定日が将来の場合
は、隘路判断部24は、上記機種を構成する各部品の在
庫数と、上記各部品の納入予定日における納入予定数と
に基づいて、上記各部品の欠品状況を判断するものと言
える。
As described above, the bottleneck judging section 24 judges the stockout status of parts based on the scheduled delivery number, actual delivery quantity, and stock quantity on the scheduled delivery date of the component parts of the model to be produced. ing. In particular, when the scheduled delivery date is in the future, the bottleneck determination unit 24 determines whether or not each component is missing based on the stock quantity of each component constituting the model and the scheduled delivery number of each of the components at the scheduled delivery date. It can be said that the product status is determined.

【0111】また、隘路判断部24は、上記した欠品状
況の判断結果に応じて、納入実績数の欄の表示色を納入
予定日ごとに設定するようになっている。つまり、隘路
判断部24は、所定の納入予定日に部品の欠品がないと
判断した場合は、上記納入予定日における納入実績数の
欄の表示色を例えば青色(色コード)に設定する。一
方、隘路判断部24は、所定の納入予定日に部品の欠品
があると判断した場合は、上記納入予定日における納入
実績数の欄の表示色を例えば警告色である赤色(色コー
ド)に設定する。図10は、このような表示色の設定前
と設定後とにおける納入予定・実績テーブルをそれぞれ
示している。
Further, the bottleneck judging section 24 sets the display color of the column of the number of delivery results for each scheduled delivery date in accordance with the result of the above-mentioned shortage status determination. That is, when the bottleneck determination unit 24 determines that there is no missing parts on the predetermined scheduled delivery date, the display color of the column of the number of actual deliveries on the scheduled delivery date is set to, for example, blue (color code). On the other hand, when the bottleneck determination unit 24 determines that there is a missing part on the predetermined scheduled delivery date, the display color of the delivery result number column on the scheduled delivery date is, for example, a warning color of red (color code). Set to. FIG. 10 shows the delivery schedule / result table before and after setting such display colors, respectively.

【0112】このように、隘路判断部24が上記テーブ
ルにおける納入実績数の欄の表示色を設定しておくこと
で、上記テーブルに基づいて作成される後述する各種表
示画面の納入実績数の欄が上記表示色にて表示される。
これにより、上記画面を見る管理者にとって、部品の納
入進度(機種の生産の隘路が発生しそうか否か)の把握
が容易になる。なお、以降では、表示色の設定された納
入予定・実績テーブルを用いることにする。
As described above, the bottleneck determination unit 24 sets the display color of the delivery result number column in the above table, so that the delivery result number column of various display screens, which will be described later, is created based on the table. Are displayed in the above display colors.
This makes it easier for an administrator who views the screen to grasp the progress of parts delivery (whether or not a bottleneck in model production is likely to occur). In the following, a scheduled delivery / result table in which display colors are set will be used.

【0113】出力要求別仕訳部25は、上記した表示色
設定後の納入予定・実績テーブルと、注残マスター1
5、取引先マスター17および担当者マスター18に記
憶された情報とに基づいて、納入部品の取引先と担当者
とを把握するための取引先・担当者テーブルを作成す
る。
The output request-specific journal unit 25 includes a delivery schedule / actual table after the display color setting described above and a back order master 1
5. Based on the information stored in the customer master 17 and the person in charge master 18, a customer / person table for comprehending the customer and the person in charge of the delivered parts is created.

【0114】具体的には、出力要求別仕訳部25は、ま
ず、図11に示す取引・担当コード設定テーブルを作成
する。このテーブルは、隘路判断部24にて表示色設定
後の納入予定・実績テーブルの部品コードをもとにし
て、注残マスター15から上記部品コードに対応する資
材部担当者名(取引先コード)および部品管理担当者名
(担当者コード)を少なくとも抽出することで作成され
る。
More specifically, the output request-specific journal unit 25 first creates a transaction / charge code setting table shown in FIG. This table is based on the part codes of the delivery schedule / results table after the display colors are set by the bottleneck determining part 24, and the name of the person in charge of the material department corresponding to the part codes from the back order master 15 (supplier code) It is created by extracting at least the name of the person in charge of parts management (person in charge code).

【0115】次に、出力要求別仕訳部25は、図12に
示すように、取引・担当コード設定テーブルの資材部担
当者名のコード番号および部品管理担当者名のコード番
号をもとにして、取引先マスター17から、上記資材部
担当者名のコード番号と対応する取引先担当者を抽出す
ると共に、担当者マスター18から、上記部品管理担当
者名のコード番号と対応する担当者名を抽出する。そし
て、出力要求別仕訳部25は、取引・担当コード設定テ
ーブルの資材部担当者名のコード番号および部品管理担
当者名のコード番号を、それぞれ対応する担当者名に置
き換えた取引先・担当者テーブルを作成する。なお、こ
のテーブルは、資材部担当者の担当者名に対応する業者
名称、窓口担当者名、TEL番号も含んでいる。
Next, as shown in FIG. 12, the output request-specific journalizing section 25 uses the code number of the person in charge of the material department and the code number of the person in charge of parts management in the transaction / charge code setting table. From the supplier master 17, the contact person corresponding to the code number of the material department contact name is extracted, and the contact person name corresponding to the code number of the part management contact name is extracted from the contact master 18. Extract. Then, the output request-specific journal unit 25 replaces the code number of the person in charge of the material department and the code number of the person in charge of parts management in the transaction and charge code setting table with the corresponding person in charge. Create a table. This table also includes a trader name, a contact person name, and a TEL number corresponding to the name of the person in charge of the material department.

【0116】したがって、取引先・担当者テーブルを参
照すれば、納入部品の取引先と、その部品を管理する担
当者とを直ちに把握することが可能となる。
Therefore, by referring to the supplier / contact table, it is possible to immediately grasp the supplier of the delivered part and the responsible person who manages the part.

【0117】発注内容確認部26は、部品別納入予定実
績比較部23にて作成された納入予定・実績テーブル
と、注残マスター15および在庫マスター16に記憶さ
れた情報とに基づいて、部品発注の確認用のテーブルを
作成する。
The order content confirming section 26 performs a part ordering process based on the delivery schedule / actual table created by the part-by-part delivery schedule / actual comparison section 23 and the information stored in the back-order master 15 and the stock master 16. Create a table for confirmation.

【0118】より具体的には、発注内容確認部26は、
図13に示すように、上記納入予定・実績テーブルにあ
る部品コードをもとにして、注残マスター15および在
庫マスター16から上記部品コードの情報を抽出し、こ
れらをまとめたテーブルを作成する。以下では、このテ
ーブルを注残・在庫・納入予実テーブルと称することに
する。
More specifically, the order content confirmation unit 26
As shown in FIG. 13, information on the part codes is extracted from the back-order master 15 and the stock master 16 based on the part codes in the delivery schedule / actual table, and a table summarizing these is created. Hereinafter, this table is referred to as a back-order / stock / delivery forecast actual table.

【0119】制御部27は、主に、データ記憶部11に
記憶された情報に基づいて、生産予定の機種を構成する
各部品の納入予定日よりも前の時点で、上記各部品の品
揃え状況を上記機種ごとに判断すると共に、上記各部品
の発注状況を上記機種ごとに確認する機能を有してい
る。制御部27にて得られる結果は、通信部31を介し
て進度管理端末装置34に送信され、進度管理端末装置
34に表示される。
The control unit 27 mainly performs the product assortment of the parts based on the information stored in the data storage unit 11 before the scheduled delivery date of the parts constituting the model to be produced. It has a function of judging the situation for each model and confirming the order status of each part for each model. The result obtained by the control unit 27 is transmitted to the progress management terminal device 34 via the communication unit 31 and displayed on the progress management terminal device 34.

【0120】(3.動作)次に、部品納入進度管理シス
テム3における動作について説明する。まず、本システ
ムにおけるおおまかな流れは以下の通りである。図14
に示すように、S1にて、処理を行う者が、管理者(例
えば部品担当者の上司、機種の生産計画を企画する生産
企画部)であれば、制御部27により、品揃え管理(S
2)と発注確認(S3)とが順に行われる。一方、S1
にて、処理を行う者が部品を扱う担当者であれば、制御
部27により、部品の納入進度管理(S4)が行われ
る。S3およびS4の後、続けて処理を行う場合には
(S5にてYes)、S1以降の処理を繰り返し、続け
て処理を行わない場合には(S5にてNo)、そのまま
処理を終了する。
(3. Operation) Next, the operation of the parts delivery progress management system 3 will be described. First, the general flow of this system is as follows. FIG.
As shown in (1), if the person who performs the process in S1 is a manager (for example, a supervisor in charge of parts, a production planning department that plans a production plan of a model), the control unit 27 performs an assortment management (S
2) and order confirmation (S3) are sequentially performed. On the other hand, S1
If the person who performs the process is a person who handles parts, the control unit 27 manages the progress of parts delivery (S4). After S3 and S4, if the process is to be continued (Yes in S5), the process after S1 is repeated, and if not to be continued (No in S5), the process is terminated.

【0121】以下、上記の品揃え管理、発注確認、部品
納入進度管理のそれぞれの処理について説明する。
Hereinafter, each processing of the above-mentioned assortment management, order confirmation, and part delivery progress management will be described.

【0122】(3−1.品揃え管理)品揃え管理は、日
々のラインへ部品を供給するために、在庫品及び納入予
定品で、どこまでの生産が可能か、いつ、どのよう
に生産できるか、変更が可能か、を事前に把握するこ
とを目的としている。このため、本システムにおける品
揃え管理は、図15に示すように、部品の品揃え状況を
機種別に管理するための品揃え状況機種別管理(S1
1)と、各機種を構成する部品ごとの品揃え状況を管理
するための品揃え状況部品別管理(S12)とで構成さ
れている。
(3-1. Assortment management) In the assortment management, in order to supply parts to a daily line, inventory and to-be-delivered products can be produced to what extent, when, and how. The purpose is to know in advance whether or not changes are possible. For this reason, assortment management in this system, as shown in FIG. 15, assortment status model-specific management (S1) for managing the assortment status of parts by model
1) and assortment status component management (S12) for managing the assortment status of each component constituting each model.

【0123】(3−1−1.品揃え状況機種別管理)品
揃え状況機種別管理は、管理者が進度管理端末装置34
を介して『品揃え状況機種別一覧表』の出力要求を行う
ことで開始され、制御部27が、生産予定にある機種を
構成する部品の総数と、隘路判断部24にて欠品と判断
された部品の数とに基づいて、上記各部品の品揃え状況
を上記機種ごとに判断する。そして、制御部27は、そ
の判断結果として、図16に示す『品揃え状況機種別一
覧表』を作成し、進度管理端末装置34に送信する。こ
の『品揃え状況機種別一覧表』の作成の手法は、以下の
通りである。
(3-1-1. Assortment status model-specific management) The assortment status model-specific management is performed by the manager of the progress management terminal device 34.
Is started by making a request for output of the “list of assortment status models” through the control unit 27. The control unit 27 determines the total number of parts constituting the model to be produced and determines that the bottleneck determination unit 24 is out of stock. The assortment status of each component is determined for each model based on the number of components thus determined. Then, as a result of the determination, the control unit 27 creates an “assortment status model-specific list” shown in FIG. 16 and transmits it to the progress management terminal device 34. The method of creating this “list of assortment status models” is as follows.

【0124】まず、『品揃え状況機種別一覧表』の出力
要求があれば、制御部27は、納入進度管理処理部21
の隘路判断部24が作成した納入予定・実績テーブルの
中から、品揃え管理を行う日を含めてその日以降の所定
期間(5日間)に生産予定のある機種の納入予定・実績
テーブルを取り込む。なお、上記の出力要求は、生産部
門および品種をそれぞれ指定することで行われる。
First, if there is a request to output the “list of assortment status models”, the control unit 27
From the delivery schedule / results table created by the bottleneck determination unit 24, a delivery schedule / results table of a model that is scheduled to be produced for a predetermined period (five days) after that date, including the date on which the assortment is managed, is fetched. The above output request is made by designating the production department and the product type, respectively.

【0125】ここで、制御部27は、上記機種として、
図16に示す5種類の機種(SEIHIN1〜SEIHIN 5)の納
入予定・実績テーブルを取り込んだものとする。なお、
ここでの説明の理解がしやすいように、SEIHIN 2、SEIH
IN 4をそれぞれ構成する部品の手番は全て1とする。し
たがって、SEIHIN 2、SEIHIN 4については、構成部品の
納入予定日は、5月13日、5月14日、5月17日の
生産予定日に対して1日前の5月12日、5月13日、
5月14日(実質稼働日)となる。そして、現時点
(『品揃え状況機種別一覧表』の出力要求があった時
点)は、同図より5月11日であるため、SEIHIN 2、SE
IHIN 4については、制御部27は、部品の納入予定日よ
りも前に品揃え状況の判断を行うことになる。
Here, the control unit 27 has the following
It is assumed that the delivery schedule / results table of the five types (SEIHIN1 to SEIHIN5) shown in FIG. 16 has been imported. In addition,
To make the explanation here easier to understand, SEIHIN 2, SEIH
The turn of each component constituting IN 4 is all 1. Therefore, regarding SEIHIN 2 and SEIHIN 4, the scheduled delivery date of the component parts is May 12, May 13, one day before the scheduled production date of May 13, May 14, May 17, and May 17. Day,
May 14 (effective working day). Since the current time (when an output request for the “list of assortment statuses by model” is made) is May 11 in the figure, SEIHIN 2, SE
For IHIN4, the control unit 27 determines the assortment status before the scheduled delivery date of the parts.

【0126】一方、生産予定日が5月11日、5月12
日であるSEIHIN 1、SEIHIN 3、SEIHIN 5については、構
成部品の納入予定日は、少なくとも5月11日よりも前
ということになる。しかし、これらの機種の品揃えにつ
いては、既に、構成部品の納入予定日よりも前に判断さ
れている点を断っておく。これらの機種が挙がっている
のは、処理日以降の5日間に生産予定があるからにほか
ならない。
On the other hand, when the scheduled production date is May 11, May 12,
For SEIHIN 1, SEIHIN 3, and SEIHIN 5, which are days, the scheduled delivery date of the component parts is at least before May 11. However, it should be noted that the lineup of these models has already been determined before the scheduled delivery date of the component parts. The only reason these models are listed is that they will be produced five days after the processing date.

【0127】ここで、隘路判断部24は、既に、機種を
構成する各部品ごとに、納入予定日における納入予定数
と納入実績数と在庫数とに基づいて、部品が欠品となる
かどうかを判断しており、その結果を納入予定・実績テ
ーブルに警告色(コード)として反映している。
Here, the bottleneck judging section 24 determines whether or not a part is missing on the basis of the expected number of deliveries, the actual number of deliveries, and the number of stocks on the scheduled delivery date for each part constituting the model. And the result is reflected as a warning color (code) in the delivery schedule / results table.

【0128】そこで、制御部27は、処理日以降の5日
間に生産予定のある機種の各部品ごとの納入予定・実績
テーブルに基づいて、機種の生産が隘路となりそうか否
かを各部品の納入予定日よりも前に判断する。具体的に
は、制御部27は、欠品部品(警告色コードが赤の部
品)の数が構成部品全体の数に対してどれだけの割合で
存在するかを機種ごとに求めることで、機種の生産が隘
路となりそうか否かを各部品の納入予定日よりも前に判
断する。そして、制御部27は、その割合に応じて表示
色を設定する。
Therefore, the control unit 27 determines whether or not the production of the model is likely to become a bottleneck based on the delivery schedule / results table for each component of the model which is scheduled to be produced in five days after the processing date. Judge before the scheduled delivery date. Specifically, the control unit 27 obtains, for each model, the ratio of the number of missing parts (parts with the warning color code of red) to the total number of constituent parts, and Judgment is made before the scheduled delivery date of each part to determine whether production of the parts is likely to be a bottleneck. Then, the control unit 27 sets the display color according to the ratio.

【0129】例えば、制御部27は、上記割合が0%で
ある場合には、工場および預託在庫で機種の生産可能と
判断し、表示色として『紫』を、上記割合が0%よりも
大きく5%未満である場合には、表示色として『青』
を、上記割合が5%以上10%未満である場合には、表
示色として『黄』を、上記割合が10%以上である場合
には、表示色として『赤』を設定する。
For example, if the above ratio is 0%, the control unit 27 determines that the model can be produced from the factory and the consigned stock, and displays “purple” as the display color and the above ratio is larger than 0%. If it is less than 5%, the display color is "blue".
When the above ratio is 5% or more and less than 10%, “yellow” is set as the display color, and when the above ratio is 10% or more, “red” is set as the display color.

【0130】そして、図16に示すように、制御部27
が、生産予定日および機種と、設定した上記表示色とを
対応付けることで、『品揃え状況機種別一覧表』が完成
する。同図からは、例えば、5月11日時点で、5月1
4日に生産予定の機種(SEIHIN2 、SEIHIN4 )および5
月17日に生産予定の機種(SEIHIN4 )について、欠品
部品数が全構成部品数に対して10%以上あり、当該機
種の生産が隘路になりそうであることがわかる。
Then, as shown in FIG.
However, by associating the planned production date and model with the set display color, the "sorting status model list" is completed. From the figure, for example, as of May 11, May 1
Models to be produced on the 4th (SEIHIN2, SEIHIN4) and 5
With regard to the model (SEIHIN4) scheduled to be produced on March 17, the number of missing parts is 10% or more of the total number of components, indicating that the production of the model is likely to become a bottleneck.

【0131】制御部27がこのようにして作成した『品
揃え状況機種別一覧表』を進度管理端末装置34に送信
し、管理者がこの『品揃え状況機種別一覧表』を進度管
理端末装置34で見ることで、管理者は、現時点より5
日後までに生産予定にある機種の部品の品揃え状況の全
体像を機種ごとに把握することができる。また、生産予
定日ごとに部品の品揃え状況を機種ごとにカラー表示す
ることで、管理者はその品揃え状況を瞬時に判断でき
る。なお、この表の作成過程において、部品検収システ
ム2からの検収実績および受注側システム4からの支給
実績はリアルに取り込まれている。
The control section 27 transmits the "list of assortment status models" created in this way to the progress management terminal device 34, and the administrator stores the "list of assortment status models" in the progress management terminal device. Looking at at 34, the administrator is now 5
It is possible to grasp the overall picture of the assortment status of parts of the models scheduled to be produced by a later date for each model. In addition, by displaying the assortment status of parts for each model by color for each planned production date, the manager can instantly judge the assortment status. In the process of creating this table, the actual results of the inspection from the parts inspection system 2 and the actual results of the supply from the order receiving system 4 are taken in realistically.

【0132】(3−1−2.品揃え状況部品別管理)管
理者は、進度管理端末装置34に表示される『品揃え状
況機種別一覧表』を見て、品揃え状況をさらに確認した
い機種がある場合には、上記機種についての『品揃え状
況部品別一覧表』の出力要求を進度管理端末装置34を
介して行う。この場合、制御部27は、進度管理端末装
置34によって指定された機種を構成する各部品の品揃
え状況を判断する。そして、制御部27は、その判断結
果として、図17に示す『品揃え状況部品別一覧表』を
作成し、進度管理端末装置34に送信する。この『品揃
え状況部品別一覧表』の作成の手法は、以下の通りであ
る。
(3-1-2. Management of Assortment Status Parts by Component) The administrator wants to further confirm the assortment status by looking at the “assortment status machine type list” displayed on the progress management terminal device 34. If there is a model, an output request for the “list of assortment status parts” for the above model is made via the progress management terminal device 34. In this case, the control unit 27 determines the assortment status of each component constituting the model designated by the progress management terminal device 34. Then, as a result of the determination, the control unit 27 creates a “list of assortment status parts” shown in FIG. 17 and transmits the list to the progress management terminal device 34. The method of creating this “list of assortment status parts” is as follows.

【0133】まず、管理者が、図16にて表示されてい
る機種(例えばSEIHIN 3)、生産部門および生産月をそ
れぞれを指定して、『品揃え状況部品別一覧表』の出力
要求を行うと、制御部27は、納入進度管理処理部21
の隘路判断部24が作成した納入予定・実績テーブルの
中から、品揃え管理を行う日を含めてその日以降の所定
期間(5日間)に生産予定のある機種の納入予定・実績
テーブルを取り込む。また、制御部27は、出力要求別
仕訳部25の作成した取引先・担当者テーブルも取り込
む。
First, the administrator designates the model (for example, SEIHIN 3), the production department, and the production month displayed in FIG. 16 and makes an output request for the “list of assortment status parts”. And the control unit 27, the delivery progress management processing unit 21
From the delivery schedule / results table created by the bottleneck determination unit 24, a delivery schedule / results table of a model that is scheduled to be produced for a predetermined period (five days) after that date, including the date on which the assortment is managed, is fetched. The control unit 27 also takes in the business partner / person in charge table created by the output request-specific journalizing unit 25.

【0134】次に、制御部27は、各部品ごとの納入予
定・実績テーブルおよび取引先・担当者テーブルに基づ
いて、生産予定の機種を構成する部品(部品コード)を
把握すると共に、当該部品に関する情報を把握する。上
記部品に関する情報としては、例えば、部品名称、注
番、L/T、手番、預託部品倉庫納入、支給部品に関す
る情報、担当者、次工程、納入予定日、納入予定数、納
入実績数、在庫数に関する情報である。
Next, the control unit 27 grasps the parts (part codes) constituting the model to be produced based on the delivery schedule / actual table and the supplier / person contact table for each part, Get information about The information on the above parts includes, for example, part name, order number, L / T, hand number, delivery to a consigned parts warehouse, information on supplied parts, person in charge, next process, scheduled delivery date, scheduled delivery number, delivery result number, This is information on the stock quantity.

【0135】ここで、機種(SEIHIN 3)を構成する部品
が、図17に示すように6種類(品名1〜6)あったと
する。この場合、品名1〜3の部品の手番は同図より1
であることから、機種(SEIHIN 3)の生産予定日が5月
12日に対して、品名1〜3の部品の納入予定日は5月
11日となる。一方、品名4〜6の部品の手番は2であ
ることから、機種(SEIHIN 3)の生産予定日が5月14
日以降に対して、品名4〜6の部品の納入予定日は5月
12日以降となる。
Here, it is assumed that there are six types (product names 1 to 6) of parts constituting the model (SEIHIN 3) as shown in FIG. In this case, the turn of the parts having the product names 1 to 3 is 1 as shown in FIG.
Therefore, the scheduled production date of the model (SEIHIN 3) is May 12, and the scheduled delivery date of the parts having the product names 1 to 3 is May 11. On the other hand, since the turn of the parts with product names 4 to 6 is 2, the planned production date of the model (SEIHIN 3) is May 14
The scheduled delivery date of the parts with product names 4 to 6 is May 12 or later.

【0136】したがって、制御部27は、品名4〜6の
部品については、5月11日現在で、5月12日の納入
予定日よりも前に、各部品の品揃え状況を判断すること
になる。なお、品名1〜3の部品については、制御部2
7は、5月11日の納入予定日よりも前に、既に品揃え
状況を判断していることを先に断っておく。
Accordingly, the control unit 27 determines the assortment status of the parts 4-6 as of May 11, before the scheduled delivery date of May 12. Become. Note that the control unit 2
No. 7 refuse earlier that the assortment status has already been determined before the scheduled delivery date of May 11.

【0137】次に、制御部27は、上記部品に関する情
報に基づいて、部品の品揃え状況を判断する。具体的に
は、品揃え状況を判断する日が部品の納期当日にあたっ
ている場合には、制御部27は、その納期当日の部品の
納入予定数と在庫数との和が機種の生産に必要な数(所
要数)に達しているか否かを判断する。なお、上記の所
要数とは、具体的には、日別生産計画数と発注員数との
積で表されるものである。一方、品揃え状況を判断する
日が部品の納期よりも前である場合には、制御部27
は、将来に部品の納入予定があるか、工場に部品の在庫
があるか、預託倉庫(JIT基地システム)に部品の在
庫があるかだけを判断する。なお、この場合、部品の数
(納入予定数や在庫数)は問題とはしない。
Next, the control unit 27 determines the assortment status of the parts based on the information on the parts. More specifically, if the date for determining the assortment status falls on the day of delivery of the part, the control unit 27 determines that the sum of the planned number of parts to be delivered and the number of stock on the day of delivery is necessary for the production of the model. It is determined whether or not the number (required number) has been reached. Note that the required number is specifically expressed as a product of the number of daily production plans and the number of orders. On the other hand, if the date for determining the assortment status is earlier than the delivery date of the part, the control unit 27
Determines only whether parts are scheduled to be delivered in the future, whether parts are in stock at a factory, or whether parts are in stock in a depository warehouse (JIT base system). In this case, the number of parts (planned delivery number or stock number) does not matter.

【0138】次に、制御部27は、上記各結果に応じて
表示色を設定する。例えば、制御部27は、部品の納入
予定数と在庫数との和が所要数に達していない場合に
は、表示色として『赤』を、部品の在庫がある場合(部
品の在庫数が所要数に達している場合)には、表示色と
して『青』を、部品の納入予定がある場合には、表示色
として『黄』を設定する。
Next, the control unit 27 sets a display color according to each of the above results. For example, when the sum of the planned number of parts to be delivered and the number of inventories does not reach the required number, the control unit 27 displays “red” as the display color, If the number has been reached, "blue" is set as the display color, and if there is a scheduled delivery of parts, "yellow" is set as the display color.

【0139】そして、図17に示すように、制御部27
が、生産予定日および部品と、設定した表示色とを対応
付けることで、『品揃え状況部品別一覧表』が完成す
る。なお、表中の『過不足』の欄の数字は、納期当日
(同図では5月11日)における(在庫数−所要数)を
示している。また、図中、生産日程欄の、の色は、
それぞれ図16における色に対応していることを示して
いる。
Then, as shown in FIG.
However, by associating the planned production date and parts with the set display colors, the “list of assortment status parts” is completed. The number in the column of "excess or deficiency" in the table indicates (the number of stocks minus the required number) on the day of delivery (May 11 in the figure). In the figure, the color of the production schedule column is
It is shown that each corresponds to the color in FIG.

【0140】また、制御部27は、各部品に関する情報
(上記した部品名称、担当者などの情報)も併せて『品
揃え状況部品別一覧表』に取り入れている。このとき、
表中の『預託』は、在庫が預託倉庫にあるか否かを、
『支給』は、支給部品の有無を示している。また、表中
の『注番』では、確定注文の注文番号を省略している。
The control section 27 also incorporates information on each part (information on the above-mentioned part names, persons in charge, etc.) into the “List of parts assortment status parts”. At this time,
"Consignment" in the table indicates whether the inventory is in the depository warehouse,
“Supply” indicates whether or not there is a supply component. Further, the order number of the confirmed order is omitted in “Note number” in the table.

【0141】制御部27がこのようにして作成した『品
揃え状況部品別一覧表』を進度管理端末装置34に送信
し、管理者がこの『品揃え状況部品別一覧表』を進度管
理端末装置34で見ることで、管理者は、誰の担当部品
が未納になっているかを、納期よりも前の段階で確実に
把握することができ、この段階でその担当者へ注意、指
導を与えることができる。
The control section 27 transmits the "list of assortment status parts" created in this way to the progress management terminal device 34, and the administrator sends the "list of assortment status components" to the progress management terminal device. By seeing at 34, the manager can surely grasp who is responsible for the parts that have not been delivered before the delivery date, and give attention and guidance to the responsible personnel at this stage. Can be.

【0142】上記した『品揃え状況部品別一覧表』は、
特に、『品揃え状況機種別一覧表』にて品揃え状況が良
好でない機種(品揃え状況が例えば『赤』で表示されて
いる機種)が確認された場合に、当該機種を構成する部
品の品揃え状況を把握する際に用いられる。
The “list of assortment status parts” described above is
In particular, when a model with an unsatisfactory assortment status (for example, a model whose assortment status is displayed in "red") is confirmed in the "assortment status model list", the parts constituting the model are identified. It is used when grasping the assortment status.

【0143】(3−2.発注確認)発注確認は、生産企
画部が作成した倉入日程(案)に基づき、本番日程(生
産日程)とは別に、計画機種の生産が可能か、納期
の詰めが必要な部品は何か、いつの納期に変更が必要
か、を管理者が事前に把握することを目的としている。
このため、本システムにおける発注確認は、図18に示
すように、部品の発注を機種別に確認するための機種別
発注確認(S21)と、隘路部品発注確認(S22)
と、隘路部品の詳細確認(S23)と、支給部品の納期
確認(S24)とで構成されている。
(3-2. Order Confirmation) The order confirmation is based on the warehouse entry schedule (draft) prepared by the production planning department, separately from the production schedule (production schedule), whether production of the planned model is possible or not. The purpose is for the manager to know in advance what parts need to be packed and when the delivery date needs to be changed.
For this reason, as shown in FIG. 18, the order confirmation in the present system includes the order confirmation by model (S21) for confirming the order of parts by model and the order confirmation of bottleneck parts (S22).
And detailed confirmation of bottleneck parts (S23) and confirmation of delivery date of supplied parts (S24).

【0144】(3−2−1.機種別発注確認)機種別発
注確認は、管理者が進度管理端末装置34を介して『発
注状況機種別一覧表』の出力要求を行うことで開始され
る。このような出力要求があれば、制御部27は、生産
予定の機種を構成する各部品の在庫数、納入予定数、上
記機種の生産予定数および各部品の発注員数に基づいて
上記各部品が欠品となるか否かを判断すると共に、その
欠品部品の有無に基づいて機種としての発注状況を確認
する。そして、制御部27は、その確認結果として、図
19に示す『発注状況機種別一覧表』を作成し、進度管
理端末装置34に送信する。この『発注状況機種別一覧
表』の作成の手法は、以下の通りである。なお、ここで
は、部品の調達リードタイムが1週間以上を対象とす
る。また、上記の出力要求は、生産部門および品種をそ
れぞれ指定することで行われるが、未指定であっても構
わない。
(3-2-1. Model-specific order confirmation) Model-specific order confirmation is started when the administrator issues an output request for “order status model list” through the progress management terminal device 34. . If there is such an output request, the control unit 27 determines whether each of the parts is based on the number of stocks, the number of parts to be delivered, the number of parts to be produced of the above-mentioned model, and the number of orders for each part constituting the model to be produced. It is determined whether or not there is a missing part, and the order status as a model is confirmed based on the presence or absence of the missing part. Then, as a result of the confirmation, the control unit 27 creates an “order status model list” shown in FIG. 19 and transmits it to the progress management terminal device 34. The method of creating the “order status model list” is as follows. Here, it is assumed that the procurement lead time of parts is one week or more. Further, the above output request is made by designating the production department and the product type, respectively, but may be unspecified.

【0145】まず、制御部27は、生産計画マスター1
2における生産計画に基づいて、発注確認を行う日以降
12日間に生産が予定されている機種(製品コード)と
日別生産計画数とを把握すると共に、発注内容確認部2
6にて作成した注残・在庫・納入予実テーブルに基づい
て、上記機種を構成する部品に関する情報を把握する。
上記部品に関する情報とは、例えば、注番、在庫数、発
注員数および納入予定数である。
First, the control unit 27 controls the production planning master 1
2, the model (product code) scheduled to be produced for 12 days after the date of order confirmation and the number of daily production plans are grasped.
Based on the back-order / stock / delivery forecast table created in step 6, information on the parts making up the model is grasped.
The information on the parts is, for example, the order number, the number of stocks, the number of orderers, and the number of scheduled deliveries.

【0146】なお、上記機種としては、図19に示すよ
うに、機種(SEIHIN 1〜SEIHIN 6)があるものとする。
また、ここでの説明の理解がしやすいように、SEIHIN
2、SEIHIN 4、SEIHIN 6をそれぞれ構成する部品の手番
は全て1とする。したがって、SEIHIN 2、SEIHIN 4、SE
IHIN 6については、構成部品の納入予定日は、5月13
日以降の生産予定日に対して1日前の5月12日以降と
なる。そして、現時点(『発注状況機種別一覧表』の出
力要求があった時点)は、同図より5月11日であるた
め、生産予定日が5月13日以降のSEIHIN 2、SEIHIN
4、SEIHIN 6については、制御部27は、部品の納入予
定日よりも前に発注状況の確認を行うことになる。
As shown in FIG. 19, it is assumed that the models include models (SEIHIN 1 to SEIHIN 6).
Also, to make the explanation here easy to understand, SEIHIN
2. The turn numbers of the components constituting SEIHIN 4 and SEIHIN 6 are all 1. Therefore, SEIHIN 2, SEIHIN 4, SE
For IHIN 6, the scheduled delivery date of the components is May 13
On or after May 12, one day before the scheduled production date. The current time (when the output of the “order status model list” is requested) is May 11 in the figure, so the scheduled production date is SEIHIN 2 and SEIHIN after May 13th.
4. Regarding SEIHIN 6, the control unit 27 checks the order status before the scheduled delivery date of the parts.

【0147】一方、生産予定日が5月11日、5月12
日であるSEIHIN 1、SEIHIN 3、SEIHIN 5については、構
成部品の納入予定日は、少なくとも5月11日よりも前
ということになる。しかし、これらの機種の発注状況に
ついては、既に、構成部品の納入予定日よりも前に確認
されている点を断っておく。これらの機種が挙がってい
るのは、処理日以降の12日間に生産予定があるからに
ほかならない。
On the other hand, when the scheduled production date is May 11, May 12,
For SEIHIN 1, SEIHIN 3, and SEIHIN 5, which are days, the scheduled delivery date of the component parts is at least before May 11. However, it should be noted that the order status of these models has already been confirmed before the scheduled delivery date of the component parts. The only reason these models are listed is that they are scheduled to be produced 12 days after the processing date.

【0148】次に、制御部27は、日別生産計画数と発
注員数とに基づいて上記機種を構成する部品の必要数を
判断し、機種ごとおよび生産予定日ごとに、対応する部
品の発注状況を以下のようにして把握する。なお、上記
の必要数は、日別生産計画数と発注員数との積で表され
る。
Next, the control unit 27 determines the required number of parts constituting the above model based on the daily production plan number and the number of orderers, and orders the corresponding part for each model and each scheduled production date. Understand the situation as follows. The above required number is represented by the product of the number of daily production plans and the number of ordering personnel.

【0149】制御部27は、ある部品についての在庫数
と納入予定数との和が上記必要数以上となる場合は、当
該部品は欠品とならず、取引先への部品納入の督促また
は納期調整は不要であると判断する。一方、制御部27
は、在庫数と納入予定数との和が上記必要数未満である
場合は、当該部品は欠品となり、部品納入の督促または
納期調整が必要であると判断する。ここで、上記の納期
調整とは、例えば生産計画の変更を意味する。
When the sum of the stock quantity and the scheduled delivery quantity of a certain part is equal to or greater than the required number, the control unit 27 does not run out of the part and urges the delivery of the part to the customer or the delivery date. It is determined that no adjustment is necessary. On the other hand, the control unit 27
If the sum of the stock quantity and the scheduled delivery quantity is less than the required number, it is determined that the part is out of stock, and that it is necessary to urge the delivery of parts or adjust the delivery date. Here, the delivery date adjustment means, for example, a change in a production plan.

【0150】次に、制御部27は、部品の各発注状況に
対応する表示色を設定する。より具体的には、欠品とな
る部品が少なくとも1つあり、当該部品の発注がフォー
キャストによるものである場合には、制御部27は、当
該部品を用いて生産される機種についての発注状況の表
示色を例えば『赤』に設定する。また、欠品となる部品
が少なくとも1つあり、当該部品の発注が確定注文また
は予約注文によるものである場合には、制御部27は、
納入予定の調整が必要と判断し、当該部品を用いて生産
される機種についての発注状況の表示色を例えば『橙』
に設定する。また、欠品となる部品が一つもない場合
は、制御部27は、当該部品を用いて生産される機種に
ついての発注状況の表示色を例えば『緑』に設定する。
Next, the control section 27 sets a display color corresponding to each order status of parts. More specifically, when there is at least one part to be out of stock and the order of the part is made by forecast, the control unit 27 determines whether the order status of the model produced using the part is Is set to, for example, "red". If there is at least one part that is missing and the order for the part is a firm order or a pre-order, the control unit 27
Judging that the delivery schedule needs to be adjusted, the color of the order status for models produced using the parts is changed to "Orange", for example.
Set to. If there is no missing part, the control unit 27 sets the display color of the order status for the model produced using the part to, for example, “green”.

【0151】そして、制御部27は、図19に示すよう
に、機種および生産予定日と、設定された色で部品の発
注状況とを対応付け、『発注状況機種別一覧表』が完成
する。
Then, as shown in FIG. 19, the control unit 27 associates the model and the planned production date with the order status of the parts in the set color, and completes the “order status model list”.

【0152】制御部27がこのようにして作成した『発
注状況機種別一覧表』を進度管理端末装置34に送信
し、管理者がこの『発注状況機種別一覧表』を進度管理
端末装置34で見ることで、管理者は、現時点より12
日後までの間に生産予定のある機種の部品の発注状況の
全体像を把握することができる。また、生産順序に基づ
き発注状況をカラー表示することで、管理者は部品の発
注状況を瞬時に判断できる。なお、この表の作成過程に
おいて、検収実績及び支給実績はリアルに取り込まれて
いる。
The control unit 27 transmits the “order status model type list” created in this way to the progress management terminal device 34, and the administrator uses the progress status terminal device 34 to send the “order status model type list” to the progress management terminal device 34. Looking at it, the administrator is now 12
It is possible to grasp the overall picture of the order status of the parts of the model scheduled to be produced by the end of the day. Further, by displaying the order status in color based on the production order, the manager can instantly determine the order status of the parts. In the process of creating this table, the actual results of inspection and payment are taken in realistically.

【0153】(3−2−2.隘路部品発注確認)ところ
で、機種別の部品の発注状況が、常に、図19に示すよ
うな良好な状態であれば問題はない。しかし、例えば、
生産計画の変更により、機種の生産が前倒しとなること
によって、部品の発注状況に変化が生じる場合がある。
例えば、図20は、生産計画の変更によって、機種(SE
IHIN 3)の生産が5月19日および5月20日に前倒し
となり、当該機種を構成する部品の発注状況が変化した
場合の『発注状況機種別一覧表』を示している。この場
合には、管理者は、その機種の構成部品(機種の生産隘
路を生じさせるような隘路部品)の発注状況についての
詳細を把握する必要がある。
(3-2-2. Confirmation of Bottleneck Parts Ordering) By the way, if the ordering status of the parts for each model is always in a good state as shown in FIG. 19, there is no problem. But, for example,
A change in the production plan may lead to a change in the ordering status of parts due to an earlier production of the model.
For example, FIG. 20 shows that the model (SE
The “Order Status Model List” when the production of IHIN 3) is brought forward on May 19 and May 20 and the order status of the parts constituting the model changes. In this case, the administrator needs to grasp the details of the ordering status of the component parts of the model (bottle parts that cause a production bottleneck of the model).

【0154】そこで、管理者が進度管理端末装置34を
介して『隘路部品発注状況一覧表』の出力要求を行う
と、制御部27は、進度管理端末装置34によって指定
された機種を構成する各部品の発注状況を確認する。さ
らに詳しくは、制御部27は、進度管理端末装置34に
よって指定された機種を構成する各部品の在庫数、納入
予定数、上記機種の生産予定数および各部品の発注員数
に基づいて、上記各部品の発注状況を確認する。そし
て、制御部27は、その確認結果として、図21に示す
『隘路部品発注状況一覧表』を作成し、進度管理端末装
置34に送信する。この『隘路部品発注状況一覧表』の
作成の手法は、以下の通りである。
Then, when the administrator issues an output request for the “bottle bottle part order status list” via the progress management terminal device 34, the control unit 27 Check the order status of parts. More specifically, the control unit 27 performs the above-described operations on the basis of the inventory quantity, the scheduled delivery quantity, the planned production quantity of the model, and the number of orderers for each component constituting the model designated by the progress management terminal device 34. Check the order status of parts. Then, as a result of the confirmation, the control unit 27 creates a “bottle bottle part order status list” shown in FIG. 21 and transmits it to the progress management terminal device 34. The method of creating this “bottle parts order status list” is as follows.

【0155】まず、管理者が、図20において部品の発
注状況が赤色となっている機種(SEIHIN 3)、生産部門
および生産月をそれぞれ指定して、進度管理端末装置3
4を介して上記の出力要求を行うと、制御部27は、生
産計画マスター12における生産計画に基づいて、発注
確認を行う日以降12日間に生産が予定されている機種
(製品コード)と日別生産計画数とを把握すると共に、
発注内容確認部26にて作成した注残・在庫・納入予実
テーブルに基づいて、上記機種を構成する部品に関する
情報を把握する。上記部品に関する情報とは、例えば、
注番、在庫数、発注員数および納入予定数である。
First, the manager designates the model (SEIHIN 3), production department and production month for which the order status of parts is red in FIG.
When the above output request is made via the control unit 4, the control unit 27 determines, based on the production plan in the production plan master 12, the model (product code) and the model (product code) scheduled to be produced for 12 days after the order confirmation date. While grasping the number of different production plans,
Based on the back-order / stock / delivery forecast table created by the order content confirmation unit 26, information on the parts making up the model is grasped. The information on the parts is, for example,
The order number, the number of stocks, the number of orderers, and the number of delivery schedules.

【0156】また、制御部27は、出力要求別仕訳部2
5の作成した取引先・担当者テーブルに基づいて、生産
予定の機種を構成する部品に関する情報を把握する。上
記部品に関する情報としては、例えば、部品名称、注
番、L/T、手番、預託部品倉庫納入、支給部品に関す
る情報、担当者、次工程、納入予定日、納入予定数、納
入実績数、在庫数に関する情報である。
The control unit 27 also controls the output request-specific journalizing unit 2.
Based on the supplier / person-in-charge table created in step 5, information on parts constituting a model to be produced is grasped. The information on the above parts includes, for example, part name, order number, L / T, hand number, delivery to a consigned parts warehouse, information on supplied parts, person in charge, next process, scheduled delivery date, scheduled delivery number, delivery result number, This is information on the stock quantity.

【0157】なお、生産予定機種(SEIHIN 3)の構成部
品としては、図21に示すように、品名1および品名2
の部品が挙がっている。ここで、これらの部品の手番は
2なので、5月12日の生産予定に対する各部品の納入
予定日は5月10日であり、5月19日、5月20日の
生産予定に対する各部品の納入予定日は5月17日、5
月18日である。したがって、制御部27は、5月17
日、5月18日の納入予定日よりも前に、品名1および
品名2の部品の発注状況を確認することになる。なお、
5月10日に納入予定であった部品については、その納
入予定日よりも前に既に部品の発注確認は行われている
ものとする。
The components of the model to be produced (SEIHIN 3) include a product name 1 and a product name 2 as shown in FIG.
Parts are listed. Here, since the turn of these parts is 2, the scheduled delivery date of each part with respect to the production schedule on May 12 is May 10, and each part with respect to the production schedule on May 19 and May 20. Scheduled delivery date is May 17, 5
March 18. Therefore, the control unit 27 may
Before the scheduled delivery date of May 18th, the order status of the parts having the product name 1 and the product name 2 will be confirmed. In addition,
For parts scheduled to be delivered on May 10, it is assumed that part order confirmation has already been performed before the scheduled delivery date.

【0158】次に、制御部27は、日別生産計画数と発
注員数とに基づいて、機種別発注確認の場合と同様に、
上記機種を構成する部品の必要数を判断し、生産予定日
ごとに、対応する部品の発注状況を以下のようにして把
握する。
Next, the control unit 27, based on the number of daily production plans and the number of orderers, performs the same as in the case of order confirmation by model,
The required number of parts constituting the above model is determined, and the order status of the corresponding parts is grasped for each scheduled production date as follows.

【0159】制御部27は、ある部品についての在庫数
と納入予定数との和が上記必要数以上となる場合は、当
該部品は欠品とならず、取引先への部品納入の督促また
は納期調整は不要であると判断する。一方、制御部27
は、在庫数と納入予定数との和が上記必要数未満である
場合は、当該部品は欠品となり、部品納入の督促または
納期調整が必要であると判断する。ここで、上記の納期
調整とは、例えば生産計画の変更を意味する。
When the sum of the stock quantity and the scheduled delivery quantity of a part is equal to or greater than the required number, the control unit 27 does not run out of the part and prompts for the delivery of the part to the customer or the delivery date. It is determined that no adjustment is necessary. On the other hand, the control unit 27
If the sum of the stock quantity and the scheduled delivery quantity is less than the required number, it is determined that the part is out of stock, and that it is necessary to urge the delivery of parts or adjust the delivery date. Here, the delivery date adjustment means, for example, a change in a production plan.

【0160】次に、制御部27は、部品の各発注状況に
対応する表示色を設定する。より具体的には、欠品とな
る部品が少なくとも1つあり、当該部品の発注がフォー
キャストによるものである場合には、制御部27は、当
該部品の発注状況の表示色を例えば『赤』に設定する。
また、欠品となる部品が少なくとも1つあり、当該部品
の発注が確定注文または予約注文によるものである場合
には、制御部27は、当該部品の発注状況の表示色を例
えば『橙』に設定する。また、欠品となる部品が一つも
ない場合は、制御部27は、当該部品の発注状況の表示
色を例えば『緑』に設定する。
Next, the control unit 27 sets a display color corresponding to each order status of parts. More specifically, when there is at least one part that is out of stock and the order for the part is a forecast, the control unit 27 sets the display color of the order status of the part to “red”, for example. Set to.
If there is at least one part that is missing, and the order of the part is a confirmed order or a pre-order, the control unit 27 changes the display color of the order status of the part to, for example, “orange”. Set. If there is no missing part, the control unit 27 sets the display color of the order status of the part to “green”, for example.

【0161】そして、制御部27は、図21に示すよう
に、発注状況の表示色として『赤』または『橙』を含む
部品のみを抽出し、生産予定日および各部品と、設定さ
れた表示色とを対応付け、『隘路部品発注状況一覧表』
が完成する。このとき、制御部27は、各部品に関する
情報(上記した部品名称、担当者などの情報)も併せて
『隘路部品発注状況一覧表』に取り入れている。
Then, as shown in FIG. 21, the control unit 27 extracts only the parts including "red" or "orange" as the display color of the order status, and sets the planned production date and each part together with the set display. Correspond to the color, "List of bottle parts order status"
Is completed. At this time, the control unit 27 also incorporates information on each component (the above-mentioned component name, information on the person in charge, etc.) into the “bottle part order status list”.

【0162】制御部27がこのようにして作成した『隘
路部品発注状況一覧表』を進度管理端末装置34に送信
し、管理者がこの『隘路部品発注状況一覧表』を進度管
理端末装置34で見ることで、管理者は、現時点より1
2日後までの間に生産隘路を生じさせるような部品の発
注状況の詳細を把握することができる。また、生産順序
に基づき隘路部品の発注状況をカラー表示することで、
管理者は隘路部品の発注状況を瞬時に判断できる。
The control section 27 transmits the “bottle parts order status list” created in this way to the progress management terminal device 34, and the administrator uses the progress bottle terminal orders status table at the progress management terminal device 34. By looking, the administrator is 1
It is possible to grasp details of the ordering status of parts that may cause a production bottleneck within two days. In addition, by displaying the order status of bottleneck parts in color based on the production order,
The manager can instantly determine the order status of bottleneck parts.

【0163】また、管理者はこのカラー表示を見て、納
期調整がさらに可能な範囲であるかを判断し、各担当者
へ指示を出すことができる。さらなる納期調整不可と判
断したときは、管理者は直ちに生産企画部のマスタース
ケジューラーへ連絡し、倉入日程の調整を依頼すること
になる。
The administrator can see the color display to determine whether the delivery date can be further adjusted, and issue an instruction to each person in charge. If it is determined that further delivery date adjustment is not possible, the manager immediately contacts the master scheduler of the production planning department and requests adjustment of the warehouse entry schedule.

【0164】(3−2−3.隘路部品詳細確認)ところ
で、上記したように生産計画が前倒し変更になった場合
には、納期調整により注文部品の納期が前進するため、
隘路部品についての納期調整の詳細を取引先に確認して
もらう必要がある。そのため、管理者が進度管理端末装
置34を介して『隘路部品詳細表』の出力要求を行う
と、制御部27は、図22に示す『隘路部品詳細表』を
作成し、進度管理端末装置34に送信する。これによ
り、管理者は、『隘路部品詳細表』に基づいて、隘路部
品の納期調整について取引先に確認することが可能とな
る。この『隘路部品詳細表』の作成の手法は、以下の通
りである。
(3-2-3. Confirmation of Bottleneck Parts Details) As described above, if the production plan is changed ahead of schedule, the delivery date of the ordered parts is advanced by the delivery date adjustment.
It is necessary to have the supplier confirm the details of the delivery date adjustment for bottleneck parts. Therefore, when the administrator issues an output request for the “bottle parts detail table” via the progress management terminal device 34, the controller 27 creates the “bottle parts details table” shown in FIG. Send to Thereby, the administrator can confirm with the supplier about the delivery date adjustment of the bottleneck parts based on the “bottleneck parts detail table”. The method of creating the “bottle part detail table” is as follows.

【0165】まず、管理者が、進度管理端末装置34を
介して『隘路部品詳細表』の出力要求を行うと、制御部
27は、生産計画マスター12における生産計画(変更
後)と、出力要求仕訳部25の取引者・担当者テーブル
と、発注内容確認部26の注残・在庫・納入予実テーブ
ルとを取り込む。そして、管理者が、隘路部品および取
引先を進度管理端末装置34を介して指定すると、制御
部27は、指定された隘路部品の生産予定日を当週から
3週後までの範囲で抽出する。
First, when the administrator makes an output request for the “bottle part detail table” via the progress management terminal device 34, the control unit 27 sets the production plan (after the change) in the production plan master 12 and the output request. The transaction / contact person table of the journalizing unit 25 and the back-order / stock / delivery forecast table of the order confirmation unit 26 are fetched. Then, when the manager specifies the bottleneck part and the business partner via the progress management terminal device 34, the control unit 27 extracts the scheduled production date of the specified bottleneck part from the current week to three weeks later. .

【0166】次に、制御部27は、生産計画と注残・在
庫・納入予実テーブルとに基づいて、隘路部品の納入の
必要日と必要数とを計算する。具体的には、制御部27
は、生産予定日から手番だけ遡った日を隘路部品の納入
必要日とし、日別生産計画数と発注員数との積を、隘路
部品の納入必要数とする。そして、制御部27は、図2
2に示すように、上記納入必要日および納入必要数を含
む、上記隘路部品に関する必要事項を生産予定日ごとに
まとめた『隘路部品詳細表』を完成させる。
Next, the control unit 27 calculates the required date and the required number of delivery of bottleneck parts based on the production plan and the back-order / stock / delivery forecast table. Specifically, the control unit 27
Is the date required for delivery of the bottleneck part, which is the date preceding the scheduled production date by the turn, and the product of the daily production plan number and the number of orderers is the required number of bottleneck part delivery. Then, the control unit 27
As shown in FIG. 2, a "bottle parts detail table" is prepared, which summarizes the necessary items related to the bottle parts, including the required delivery date and the required number, for each scheduled production date.

【0167】管理者は、このような『隘路部品詳細表』
に基づいて、隘路部品についての納期調整の詳細を取引
先に確認する。そして、納期変更について取引先の了解
が得られれば、管理者は、納期調整がOKであると判断
する。そして、管理者は、納期調整を行った場合には、
図22中の調整結果欄の数字を0から1に変更する。す
ると、制御部27は、図20で示した『発注状況機種別
一覧表』と、図21で示した『隘路部品発注状況一覧
表』とにおいて、『橙』の色表示を『緑』へと変更す
る。なお、このとき、管理者が気付いたことがあれば、
そのことを『隘路部品詳細表』の備考欄に入力し、誰が
見ても分かるようにする。
[0167] The administrator can use such a "detailed bottle parts table".
The details of the delivery date adjustment for bottleneck parts are confirmed with the supplier based on the. Then, if the business partner's consent is obtained for the change of the delivery date, the manager determines that the delivery date adjustment is OK. And, when the manager adjusts the delivery date,
The number in the adjustment result column in FIG. 22 is changed from 0 to 1. Then, the control unit 27 changes the color display of “orange” to “green” in the “order status model list” shown in FIG. 20 and the “bottle part order status list” shown in FIG. change. At this time, if the administrator has noticed,
This is entered in the remarks column of the “Detailed Parts List” so that anyone can see it.

【0168】(3−2−4.支給部品納期確認)ところ
で、隘路部品が組品(供給部品、親部品)であれば、そ
の組品を構成する支給部品についても納期調整が必要と
なる。この場合、管理者が進度管理端末装置34を介し
て『支給部品納期情報一覧表』の出力要求を行うと、制
御部27は、図23(a)に示す『支給部品納期情報一
覧表』を作成し、進度管理端末装置34に送信する。こ
れにより、管理者は、上記の『支給部品納期情報一覧
表』に基づいて、隘路部品が組品である場合に、納期調
整が必要な支給部品がどれだけあるかを把握することが
できると共に、親部品の納期調整結果に基づいて、支給
部品の納期調整を行うことが可能となる。この『支給部
品納期情報一覧表』の作成の手法は、以下の通りであ
る。
(3-2-4. Confirmation of Delivery Date of Supplied Parts) If the bottleneck part is an assembly (supply part, parent part), it is necessary to adjust the delivery date of the supplied parts constituting the assembly. In this case, when the administrator issues an output request for the “supplied part delivery date information list” via the progress management terminal device 34, the control unit 27 displays the “supplied part delivery date information list” shown in FIG. It is created and transmitted to the progress management terminal device 34. Thereby, based on the “supplied parts delivery date information table”, the administrator can grasp how many supplied parts need to be adjusted for delivery when bottleneck parts are assembled. In addition, it is possible to adjust the delivery date of the supplied component based on the delivery date adjustment result of the parent component. The method of creating the “supplied parts delivery date information list” is as follows.

【0169】まず、管理者が、進度管理端末装置34を
介して『支給部品納期情報一覧表』の出力要求を行う
と、制御部27は、隘路判断部24の納入予定・実績テ
ーブルと、出力要求仕訳部25の取引者・担当者テーブ
ルと、発注内容確認部26の注残・在庫・納入予実テー
ブルとを取り込む。そして、管理者が、進度管理端末装
置34を介して、供給部品(親部品)の部品コードを指
定すると、制御部27は、注残・在庫・納入予実テーブ
ルに基づいて、指定された親部品コードが同一となる部
品コード(支給部品)に関する情報を抽出する。そし
て、制御部27は、過去1週間(実質稼働日である5日
間)と、今後の3週間(15日)分の注番と納入予定数
とを少なくとも抽出し、図23(a)に示す『支給部品
納期情報一覧表』を完成させる。
First, when the manager makes an output request for the “supplied parts delivery date information list” via the progress management terminal device 34, the control section 27 sends the delivery schedule / actual table of the bottleneck determination section 24 and the output. The transaction / contact person table of the request journalizing section 25 and the back-order / stock / delivery forecast table of the order confirmation section 26 are fetched. Then, when the administrator specifies the part code of the supplied part (parent part) via the progress management terminal device 34, the control unit 27 executes the designated parent part based on the back-order / stock / delivery forecast table. Information on a part code (supplied part) having the same code is extracted. Then, the control unit 27 extracts at least a note number and a scheduled delivery number for the past one week (five days, which is the actual working day) and for the next three weeks (15 days), and shows them in FIG. Completion of "supplied parts delivery date information list".

【0170】なお、表中の同一枠内に2段で記載されて
いる部分においては、上段が注番で下段が納入予定数を
示している。また、既に納入済みとなる支給部品(納入
実績数が納入予定数に達した支給部品)については、制
御部27は、納入予定日の欄を青色で表示するようにす
る。
[0170] In the portions described in two rows in the same frame in the table, the upper row indicates the order number, and the lower row indicates the scheduled delivery number. In addition, for a supplied part that has already been delivered (a supplied part whose delivered result number has reached the scheduled delivery number), the control unit 27 displays the expected delivery date column in blue.

【0171】管理者は、図23(a)に示す『支給部品
納期情報一覧表』において、供給部品(親部品)の納期
変更内容を見て、納期が前進した日数だけ支給部品の納
期調整を行う。この結果、図23(b)に示す『支給部
品納期情報一覧表』が完成する。
In the “supplied part delivery date information list” shown in FIG. 23A, the administrator looks at the contents of the change in the delivery date of the supplied part (parent part) and adjusts the delivery date of the supplied part by the number of days the delivery date has advanced. Do. As a result, the “supplied part delivery date information list” shown in FIG. 23B is completed.

【0172】なお、親部品の最新納期は、倉入れ日程
(生産計画)の変更のシュミレーションにより決定され
るものであり、親部品の当初納期と変更後の納期との差
が、支給部品の納期を前進させる日数となる。同図
(b)では、親部品の納期が2日前進したことに伴い、
この親部品に対応する全ての支給部品の納期を2日前進
させている。
The latest delivery date of the parent part is determined by a simulation of a change in the storage schedule (production plan), and the difference between the original delivery date of the parent part and the changed delivery date is the delivery date of the supplied part. Is the number of days to move forward. In the same figure (b), the delivery date of the parent part has advanced two days,
The delivery date of all supplied parts corresponding to this parent part is advanced by two days.

【0173】(3−3.納入進度管理)上述した品揃え
管理および発注確認は、主として管理職が活用するもの
であるが、(進度管理)担当者は、さらに部品の発注の
詳細および納入指示内容に基づき、日々の隘路防止を行
うことが重要である。そこで、担当者は納入進度管理を
毎日行うことになる。この納入進度管理は、図24に示
すように、納入状況部品別管理(S31)と、納入状況
詳細管理(S32)と、納入状況担当者別管理(S3
3)と、未納入部品詳細管理(S34)と、部品詳細管
理(S35)と、督促リスト管理(S36)とで構成さ
れている。
(3-3. Delivery Progress Management) The above-described assortment management and order confirmation are mainly used by managers. It is important to prevent daily bottlenecks based on the content. Therefore, the person in charge manages the delivery progress every day. As shown in FIG. 24, the delivery progress management includes delivery status component management (S31), delivery status detail management (S32), and delivery status clerk management (S3).
3), detailed management of undelivered parts (S34), detailed part management (S35), and dunning list management (S36).

【0174】なお、上述した品揃え管理および発注確認
により、機種の生産隘路を事前に防止することが可能と
なるはずであるが、このような品揃え管理および発注確
認を行ってもなお、機種の生産計画の変更等により、部
品の納入遅れによって機種の生産隘路が生じることもあ
る。そこで、以下では、このような特殊な場合も含め
て、上記各処理について説明する。
It should be noted that the above-described assortment management and order confirmation should make it possible to prevent the production bottleneck of the model in advance, but even if such assortment management and order confirmation are performed, Due to changes in the production plan, delays in parts delivery may cause a production bottleneck for the model. Therefore, hereinafter, the respective processes will be described including such special cases.

【0175】(3−3−1.納入状況部品別管理)ま
ず、担当者が、進度管理端末装置34を介して『支供給
部品の納入状況一覧表』の出力要求を行うと、制御部2
7は、隘路判断部24の納入予定・実績テーブルと、出
力要求仕訳部25の取引者・担当者テーブルと、発注内
容確認部26の注残・在庫・納入予実テーブルとを取り
込む。なお、上記の出力要求は、生産部門、機種、生産
月をそれぞれ設定することで行われる。
(3-3-1. Management of Delivery Status Parts) First, when the person in charge makes an output request of “delivery status list of supplied parts” via the progress management terminal device 34, the control unit 2
7 fetches a delivery schedule / results table of the bottleneck determination unit 24, a trader / person table of the output request journalizing unit 25, and a back-order / stock / delivery forecast table of the order confirmation unit 26. The above output request is made by setting the production department, model, and production month, respectively.

【0176】そして、制御部27は、上記各テーブルの
うち、処理日(上記の出力要求があった日)を含めて以
降3日間と、処理日よりも前の7日間に対応する部分だ
けを抽出する。
Then, the control unit 27 determines only the portions corresponding to the following three days including the processing date (the date of the output request) and the seven days before the processing date in each of the tables. Extract.

【0177】次に、制御部27は、部品の総発注数と、
納入予定の累計数と、過不足数とを算出する。ここで、
上記総発注数は、処理日も含めて以降3日間の間に生産
計画のある機種(製品コード)に対して発注された部品
の発注数の総計である。また、上記の納入予定の累計数
は、指定機種を構成する部品(供給部品、支給部品)の
処理日までの納入予定数の累計である。また、上記の過
不足数は、処理日における納入予定数と納入実績数との
差である。
Next, the control unit 27 determines the total number of parts ordered,
Calculate the cumulative number of delivery schedules and the number of excess and deficiency. here,
The total number of orders is the total number of parts ordered for a model (product code) having a production plan for the next three days including the processing date. The above-mentioned cumulative number of scheduled deliveries is the total number of scheduled deliveries of parts (supplied parts, supplied parts) constituting the designated model until the processing date. The above-mentioned excess / deficiency number is the difference between the scheduled delivery number and the actual delivery number on the processing day.

【0178】続いて、制御部27は、抽出した各テーブ
ルに含まれる情報、部品の総発注数、納入予定の累計数
および過不足数に基づいて、各納入予定日ごとの部品の
納入状況を異なる色に対応させる。より具体的には以下
の通りである。
Subsequently, the control unit 27 determines the delivery status of the parts for each scheduled delivery date based on the information included in the extracted tables, the total number of ordered parts, the cumulative number of scheduled deliveries, and the number of excess / deficiency. Correspond to different colors. More specifically, it is as follows.

【0179】制御部27は、納入予定日における納入実
績数がその日の納入予定数に満たない場合には、納入状
況としては、納入遅れを示す『赤(大物部品はピン
ク)』を設定する。また、制御部27は、処理日以降で
納入予定・実績テーブルに納入予定がある場合には納入
状況として『黄』を設定する。
If the actual number of deliveries on the scheduled delivery date is less than the expected number of deliveries on that day, the control unit 27 sets the delivery status to "red (large component is pink)" indicating delivery delay. Further, if there is a delivery schedule in the delivery schedule / actual table after the processing date, the control unit 27 sets “yellow” as the delivery status.

【0180】制御部27は、納入予定・実績テーブルに
おいて供給部品の納入実績がある場合には、納入状況と
しては、工場に納入済みであることを示す『青』を設定
する。また、制御部27は、納入予定・実績テーブルに
おいて支給部品の納入実績がある場合には、倉庫(JI
T基地システム)に納入済みであることを示す『橙』を
設定する。
If there is a delivery record of the supplied part in the delivery schedule / result table, the control section 27 sets the delivery status to “blue” indicating that the delivery has been completed to the factory. In addition, if there is a delivery record of the supplied part in the delivery schedule / result table, the control unit 27 checks the warehouse (JI).
Set "orange" to indicate that the product has already been delivered to the T base system).

【0181】制御部27は、直送部品の納入予定・実績
テーブルにおいて、支給日における支給実績数が支給予
定数だけある場合には、直送済みであることを示す『水
色』を設定する。また、制御部27は、直送部品以外の
部品の納入予定・実績テーブルで、支給日における支給
実績数が支給予定数だけある場合には、支給完了である
ことを示す『紺』を設定する。
In the delivery schedule / results table of the direct delivery parts, if the number of actual deliveries on the supply date is the same as the expected number of deliveries, the control unit 27 sets “light blue” indicating that direct delivery has been completed. Further, the control unit 27 sets “dark blue” indicating that the supply is completed when the number of actual supplies on the supply date is the same as the expected number of supplies in the delivery schedule / result table of the parts other than the direct delivery parts.

【0182】制御部27は、ETD日(出港予定日)が
取得できた場合には、納入状況としては『薄い緑』を設
定する。また、制御部27は、ETA日(着港予定日)
が到来すれば、納入状況としては『緑』を設定する。
When the ETD date (scheduled departure date) can be obtained, the control unit 27 sets “pale green” as the delivery status. In addition, the control unit 27 sets the ETA date (scheduled arrival date).
Is set, the delivery status is set to "green".

【0183】このようにして、部品の納入状況を異なる
色に対応させると、制御部27は、指定された機種を構
成する各部品と、設定された色とを対応付け、図25に
示す『支供給部品の納入状況一覧表』が完成する。この
とき、制御部27は、各部品に関する情報のうち必要な
ものについては『支供給部品の納入状況一覧表』に取り
入れている。
As described above, when the delivery status of the parts is made to correspond to different colors, the control unit 27 associates each part constituting the designated model with the set color, and sets “1” shown in FIG. List of delivery status of supporting parts ”is completed. At this time, the control unit 27 incorporates necessary information out of the parts into the “supply part delivery status list”.

【0184】なお、この表中、『有』は、支給部品があ
ること、つまり、部品が供給部品であることを示し、
『支』は、部品が支給部品(一旦工場に入る部品)であ
ることを示し、『直』は、部品が直送部品(2次加工業
者に直接行く部品)であることを示す。
In this table, “Yes” indicates that there is a supplied part, that is, the part is a supplied part.
“Support” indicates that the component is a supplied component (a component that once enters a factory), and “Direct” indicates that the component is a direct-feed component (a component that directly goes to a secondary processing company).

【0185】なお、確定注文後に、生産日程の変更によ
り機種の生産が将来の方向にずれる場合でも、製品在庫
を発生させないようにするため、当初の納入予定日は変
えない。したがって、この場合でも、制御部27は、当
初の納入予定日のままで部品の納入状況を判断し、色表
示を行うことになる。
Even if the production schedule changes in the future due to a change in the production schedule after the firm order, the original scheduled delivery date is not changed so as not to generate product inventory. Therefore, even in this case, the control unit 27 determines the delivery status of the parts with the original scheduled delivery date and performs color display.

【0186】制御部27がこのようにして作成した『支
供給部品の納入状況一覧表』を進度管理端末装置34に
送信し、担当者がこの『支供給部品の納入状況一覧表』
を進度管理端末装置34で見ることで、担当者は、現時
点(処理日)での部品の納入遅れの有無を把握すること
ができる。
The control section 27 sends the “supply part delivery status list” created in this way to the progress management terminal device 34, and the person in charge sends this “supply part delivery status list”.
By using the progress management terminal device 34, the person in charge can grasp the presence or absence of the component delivery delay at the present time (the processing date).

【0187】(3−3−2.納入状況詳細管理)上記し
た納入状況部品別管理で、部品の納入遅延が分かると、
次に、担当者は、納入遅延となる部品がどの程度あるの
かを把握することが必要となる。このため、担当者が、
進度管理端末装置34を介して『支供給部品の納入状況
詳細表』の出力要求を行うと、制御部27は、図26に
示す『支供給部品の納入状況詳細表』を作成し、進度管
理端末装置34に送信するようになっている。
(3-3-2. Detailed management of delivery status) In the above-described management of delivery status parts, if the delivery delay of parts is found,
Next, it is necessary for the person in charge to grasp how many parts are delayed in delivery. For this reason,
When an output request for a “supply part delivery status detail table” is made via the progress management terminal device 34, the control unit 27 creates a “supply part delivery status detail table” shown in FIG. The data is transmitted to the terminal device 34.

【0188】この『支供給部品の納入状況詳細表』の作
成の手法については、図25の『支供給部品の納入状況
一覧表』の作成後、納入状況の色表示欄を、具体的な納
入予定数と納入実績数とに置き換えることで完成され
る。なお、納入遅れがある場合(納入実績数が納入予定
数に達していない場合)は、納入予定数および納入実績
数が『赤』をバックに表示される。
The method of creating the “supply part delivery status detail table” is as follows. After the “supply part delivery status list” in FIG. 25 is created, the delivery status color display column is changed to a specific delivery status. It is completed by replacing the planned number with the actual number of deliveries. When there is a delivery delay (when the number of actual deliveries has not reached the number of expected deliveries), the number of expected deliveries and the number of actual deliveries are displayed with "red" in the background.

【0189】制御部27がこのようにして作成した『支
供給部品の納入状況詳細表』を進度管理端末装置34に
送信し、担当者がこの『支供給部品の納入状況詳細表』
を進度管理端末装置34で見ることで、担当者は、納入
遅延となる部品がどの程度あるのかを把握することがで
きる。
The control unit 27 transmits the “delivered supply part detailed table” thus created to the progress management terminal device 34, and the person in charge sends this “delivered part detailed delivery table”.
Can be grasped by the progress management terminal device 34, and the person in charge can grasp how many parts are delayed in delivery.

【0190】(3−3−3.納入状況担当者別管理)担
当者は、図26で示した『支供給部品の納入状況詳細
表』の中から、自分の担当部品だけを抜粋したい場合が
ある。この場合、担当者が、自分の担当者コードのイニ
シャル(MY)を指定して、進度管理端末装置34を介
して『支供給部品の納入状況担当者別一覧表』の出力要
求を行うと、制御部27は、図26で示した『支供給部
品の納入状況詳細表』の中から、指定担当者に対応する
部品だけを抜粋し、図27に示すような『支供給部品の
納入状況担当者別一覧表』を作成する。
(3-3-3. Management by Delivery Person in Charge) In some cases, the person in charge wants to extract only his / her part from the “Detailed Delivery Status Table of Supply Parts” shown in FIG. is there. In this case, when the person in charge designates the initial (MY) of his / her person's code and makes an output request of the “supplied parts delivery status by person in charge” via the progress management terminal device 34, The control unit 27 extracts only the parts corresponding to the designated person from the “Delivery status of supply parts” shown in FIG. Create an individual list.

【0191】制御部27がこのようにして作成した『支
供給部品の納入状況担当者別一覧表』を進度管理端末装
置34に送信し、担当者がこの『支供給部品の納入状況
担当者別一覧表』を進度管理端末装置34で見ること
で、担当者は、自分の担当となる部品についてだけ、そ
の納入遅延を把握するとができる。
The control section 27 transmits the “list of sub-supplied parts delivery status by person in charge” created in this way to the progress management terminal device 34, and the in-charge person instructs the “sub-supplied part delivery status by person in charge” By viewing the “List” on the progress management terminal device 34, the person in charge can grasp the delivery delay of only the parts to be in charge of himself / herself.

【0192】(3−3−4.未納入部品詳細管理)担当
者は、図27で示した『支供給部品の納入状況担当者別
一覧表』の中から、自分の担当部品のうち、未納入部品
だけを抜粋したい場合がある。この場合、担当者が、
『支供給部品の納入状況担当者別一覧表』の中の『督
促』ボタンをクリックすると、制御部27は、未納入部
品だけを抜粋した、図28に示す『未納入部品詳細一覧
表』を作成し、進度管理端末装置34に送信する。
(3-3-4. Detailed management of undelivered parts) The person in charge, out of the “list of sub-supplied parts delivery status by person in charge” shown in FIG. There are times when you want to extract only delivered parts. In this case,
When the "Dunning" button is clicked in the "List of sub-supplied parts delivery status by person in charge", the control unit 27 displays the "Undelivered parts detailed list" shown in FIG. It is created and transmitted to the progress management terminal device 34.

【0193】これにより、担当者はこの『未納入部品詳
細一覧表』を進度管理端末装置34で見ることで、担当
者は、未納入部品についてのみ、その納入遅延を把握す
るとができる。
Thus, the person in charge can see the “detailed list of undelivered parts” on the progress management terminal device 34, so that the person in charge can grasp the delivery delay of only undelivered parts.

【0194】(3−3−5.部品詳細管理)上記のよう
に、未納入部品が確認されると、担当者は、その未納入
部品について、取引先に納入の督促を行う必要がある。
(3-3-5. Detailed Component Management) As described above, when an undelivered part is confirmed, the person in charge needs to urge the supplier to deliver the undelivered part.

【0195】そこで、担当者が進度管理端末装置34を
介して『部品管理詳細表(督促用)』の出力要求を行う
と、制御部27は、図29に示す『部品管理詳細表(督
促用)』を作成し、進度管理端末装置34に送信するよ
うになっている。この『部品管理詳細表(督促用)』の
作成の手法については、以下の通りである。
Then, when the person in charge makes an output request for the “parts management details table (for dunning)” via the progress management terminal device 34, the control unit 27 returns to the “parts management details table (for dunning)” shown in FIG. )] Is created and transmitted to the progress management terminal device 34. The method of creating the “parts management detailed table (for dunning)” is as follows.

【0196】まず、担当者から上記の出力要求がある
と、制御部27は、隘路判断部24の納入予定・実績テ
ーブルと、出力要求別仕訳部25の取引先・担当者テー
ブルと、発注内容確認部26の注残・在庫・納入予実テ
ーブルとを取り込む。なお、上記の出力要求は、機種
(製品コード)、生産月、部品(部品コード)を指定す
ることで行われる。
First, when there is the above-mentioned output request from the person in charge, the control unit 27 sets the delivery schedule / actual table of the bottleneck judgment unit 24, the supplier / person table of the output request-specific journalizing unit 25, and the order contents. The back-order / stock / delivery forecast actual table of the confirmation unit 26 is fetched. The above output request is made by designating a model (product code), a production month, and a part (part code).

【0197】そして、制御部27は、指定された部品の
納入予定・実績テーブルと、取引先・担当者テーブル
と、注残・在庫・納入予実テーブルとを抽出する。その
後、制御部27は、指定部品の納入予定日別に、納入予
定数、納入実績数、差異数(納入予定数−納入実績
数)、注番、伝番、指定(部品を午前中に納入するのか
午後に納入するのかの指定)などをまとめ、合わせて取
引先の情報も含めて、図29に示す『部品管理詳細表
(督促用)』を完成させる。
Then, the control unit 27 extracts a delivery schedule / actual table, a supplier / person table, and a back-order / stock / delivery forecast table of the designated part. After that, the control unit 27 separates the number of scheduled deliveries, the number of actual deliveries, the number of differences (the expected number of deliveries-the number of actual deliveries), the order number, the transfer number, and the designation (parts are delivered in the morning) by the scheduled delivery date of the designated parts "Department management detailed table (for dunning)" shown in FIG. 29 is also completed, including information on business partners.

【0198】なお、通常は、特殊な部品(大物部品キャ
ビネット等)を除き、部品を午前中に納入することとし
ている。
Normally, parts are to be delivered in the morning except for special parts (such as large parts cabinets).

【0199】制御部27がこのようにして作成した『部
品管理詳細表(督促用)』を進度管理端末装置34に送
信し、担当者がこの『部品管理詳細表(督促用)』を進
度管理端末装置34で見ることで、担当者は、この『部
品管理詳細表(督促用)』に基づいて、部品の納入の督
促を取引先に行うことになる。担当者は、取引先に電話
をかけて未納入部品について督促すると、督促において
確認した結果を、『部品管理詳細表(督促用)』の備考
欄にその旨をメモし、誰が見ても分かるようにする。
The control unit 27 transmits the “parts management details table (for dunning)” created in this way to the progress management terminal device 34, and the person in charge manages the “parts management details table (for dunning)”. By looking at the terminal device 34, the person in charge urges the supplier to deliver the parts based on the “parts management detailed table (for dunning)”. When the person in charge calls the business partner and reminder the undelivered parts, the result confirmed in the reminder is noted in the remarks column of the "parts management detailed table (for dunning)", and anyone can see it To do.

【0200】(3−3−6.督促リスト管理)上述のよ
うな納入進度管理で部品の納入遅れに対処していくが、
納期当日でも未納入の部品については、納期当日に最終
的に未納入部品となったリスト(督促リスト)を出力
し、担当者がこの督促リストに基づいて、再度、未納入
部品について督促を行い、必ず生産に間に合わせるよう
に納品の確約をとることが必要とされる。
(3-3-6. Dunning List Management) The delivery progress management as described above deals with the delivery delay of parts.
For parts that have not been delivered even on the day of delivery, a list (dunning list) that finally became undelivered parts on the day of delivery is output, and the person in charge reminds the undelivered parts again based on this dunning list. However, it is necessary to ensure delivery in time for production.

【0201】そこで、担当者が進度管理端末装置34を
介して『督促リスト』の出力要求を行うと、制御部27
は、図30に示す『督促リスト』を作成し、進度管理端
末装置34に送信するようになっている。この『督促リ
スト』の作成の手法については、以下の通りである。
Then, when the person in charge makes an output request for the “reminder list” through the progress management terminal device 34, the controller 27
Creates a “dunning list” shown in FIG. 30 and transmits it to the progress management terminal device 34. The method of creating the “Dunning list” is as follows.

【0202】まず、担当者から上記の出力要求がある
と、制御部27は、隘路判断部24の納入予定・実績テ
ーブルと、発注内容確認部26の注残・在庫・納入予実
テーブルとを取り込む。なお、上記の出力要求では、担
当者(担当者コード)も指定される。
First, when there is the above-mentioned output request from the person in charge, the control unit 27 fetches the delivery schedule / actual table of the bottleneck judging unit 24 and the back-order / stock / delivery actual table of the order content confirming unit 26. . In the output request, a person in charge (person in charge code) is also specified.

【0203】そして、制御部27は、指定された担当者
の部品で、処理日(上記出力要求があった日)以降に納
入予定があり、かつ、処理日の前日までの納入予定に対
して納入遅れとなっている部品に関する情報を、上記各
テーブルから抽出する。その後、制御部27は、各部品
ごとに、次工程、取引先、注番、総発注数、納入予定累
計、総実績数、不足数、最終納入日、納入予定数を把握
し、これらの内容を盛り込んだ『督促リスト』を完成さ
せる。
Then, the control unit 27 determines whether the parts to be delivered by the designated person in charge are scheduled to be delivered after the processing date (the date of the output request) and are scheduled to be delivered up to the day before the processing day. Information on parts that are delayed in delivery is extracted from each of the above tables. After that, the control unit 27 grasps the next process, the business partner, the order number, the total number of orders, the total number of scheduled deliveries, the total number of actual deliveries, the number of shortfalls, the final delivery date, and the number of scheduled deliveries for each part. Complete the "Dunning List" that includes

【0204】ここで、上記総発注数は、所定期間内にお
いて発注された部品の発注数の総計である。また、上記
の納入予定累計は、最終納入日までの所定期間内におけ
る部品の納入予定数の累計である。また、総実績数は、
上記所定期間内における部品の納入実績数の累計であ
る。また、上記の不足数は、上記所定期間内における納
入予定数と納入実績数との差である。
Here, the total number of orders is the total number of parts ordered within a predetermined period. The above-mentioned total scheduled delivery is the total number of scheduled delivery of parts within a predetermined period until the final delivery date. Also, the total number of achievements is
This is a cumulative total of the number of parts delivered within the predetermined period. The above-mentioned shortage number is a difference between the scheduled number of deliveries and the actual number of deliveries within the above-mentioned predetermined period.

【0205】制御部27がこのようにして作成した『督
促リスト』を進度管理端末装置34に送信し、担当者が
この『督促リスト』を進度管理端末装置34で見て、部
品の納入の督促を再度取引先に行うことになる。このよ
うな『督促リスト』を制御部27が作成することによ
り、担当者は、取引先へ督促すべき未納入部品を容易に
把握することができる。担当者は、督促において確認し
た結果を、図29の『部品管理詳細表(督促用)』の備
考欄にメモし、誰が見ても分かるようにする。
The control unit 27 transmits the “reminder list” created in this way to the progress management terminal device 34, and the person in charge looks at the “reminder list” on the progress management terminal device 34, and reminds of the delivery of parts. Is performed again to the business partner. By creating such a “dunning list” by the control unit 27, the person in charge can easily grasp the undelivered parts to be dunned to the business partner. The person in charge makes a note of the result confirmed in the dunning in the remarks column of the “parts management detailed table (for dunning)” in FIG. 29 so that anyone can see it.

【0206】(4.効果)以上のように、本発明は、生
産を予定している機種の生産計画情報と、上記機種を構
成する各部品に関する情報とをデータ記憶部11に記憶
させておき、S2およびS3で示したように、制御部2
7が、データ記憶部11に記憶されている情報に基づい
て、上記各部品の納入予定日よりも前の時点で、上記各
部品の品揃え状況を上記機種ごとに判断すると共に、上
記各部品の発注状況を上記機種ごとに確認する構成であ
る。制御部27にて得られる結果(品揃え状況の判断結
果および発注状況の確認結果)は、進度管理端末装置3
4に送信され、進度管理端末装置34にて表示される。
(4. Effects) As described above, according to the present invention, the data storage unit 11 stores the production plan information of the model scheduled to be produced and the information on each component constituting the model. , S2 and S3, the control unit 2
7 determines, based on the information stored in the data storage unit 11, the assortment status of each of the parts for each of the models at a time before the scheduled delivery date of each of the parts, and This is a configuration for checking the order status of each model. The result obtained by the control unit 27 (the determination result of the assortment status and the confirmation result of the order status) is the progress management terminal device 3.
4 and displayed on the progress management terminal device 34.

【0207】これにより、例えば、管理者は、進度管理
端末装置34に表示される品揃え状況および発注状況に
基づいて、機種の生産が隘路となりそうかどうかという
生産隘路の傾向を、部品の納入予定日よりも前に把握す
ることができる。この結果、機種の生産隘路が発生しそ
うと判断すれば、例えば、部品の納入の督促を取引先に
行うことができる。
Thus, for example, based on the assortment status and order status displayed on the progress management terminal device 34, the administrator can determine the tendency of the production bottleneck, which indicates whether the production of the model is likely to be a bottleneck, based on the delivery of parts. It can be grasped before the scheduled date. As a result, if it is determined that a production bottleneck of the model is likely to occur, for example, the supplier can be urged to deliver parts.

【0208】この場合、部品の納入予定日よりも前に督
促できるので、元々の納入予定日自体は変動しない。し
たがって、従来のように納入予定日と生産予定日との間
が長期になるというようなことがなく、在庫が長期にわ
たって過剰になるということはない。これにより、在庫
の管理負担が増大することはない。
In this case, since the dunning can be performed before the scheduled delivery date of the parts, the original scheduled delivery date itself does not change. Therefore, unlike the conventional case, the time between the scheduled delivery date and the scheduled production date does not become long, and the inventory does not become excessive for a long time. This does not increase the inventory management burden.

【0209】また、品揃え状況および発注状況に基づい
て、機種の生産隘路が発生しそうと判断すれば、機種の
生産計画を変更することも可能である。この場合は、生
産計画を変更するかどうかの検討を、生産隘路となる機
種の構成部品の納入予定日よりも前に行うことができる
ので、その検討を上記納入予定日当日よりも前に終える
ことができれば、上記納入予定日当日から直ちに、生産
計画変更後の機種の生産のための生産ライン(検査、準
備を含む)を稼働させることが可能となる。つまり、元
々の納入予定日当日と、生産計画変更後の機種の生産ラ
インの稼働開始日との間にタイムラグが生じることがな
い。この結果、機種の生産を効率よく行うことができ
る。
[0209] If it is determined that a production bottleneck of a model is likely to occur based on the assortment status and order status, the production plan of the model can be changed. In this case, the study on whether to change the production plan can be made before the scheduled delivery date of the component parts of the model that will be the bottleneck in the production, and the study is completed before the scheduled delivery date. If possible, the production line (including inspection and preparation) for the production of the model after the change of the production plan can be operated immediately from the scheduled delivery date. That is, there is no time lag between the original scheduled delivery date and the operation start date of the production line of the model after the change of the production plan. As a result, model production can be performed efficiently.

【0210】なお、本発明は、上記各部品の納入予定日
よりも前に、品揃え状況の判断および発注状況の確認の
両者を行ってはじめて意味がある。つまり、各部品の品
揃えを判断しただけでは、機種の生産に必要な数だけ各
部品の発注がなされているのかわからない。また、各部
品の発注が適切になされていても、品揃えを把握できて
いなければ、在庫品および納入予定品で、どこまでの生
産が可能かを把握することができない。したがって、品
揃え状況の判断と発注確認とのうち、どちらか一方のみ
では、機種の生産隘路の傾向をつかむことはできない。
[0210] The present invention is meaningful only when both the determination of the assortment status and the confirmation of the order status are performed before the scheduled delivery date of each component. In other words, it is not possible to judge whether the order of each part is sufficient for the production of the model just by determining the assortment of each part. Further, even if the order of each part is properly made, if the product lineup is not grasped, it is not possible to grasp how much production is possible with the stock product and the scheduled delivery product. Therefore, the tendency of the production bottleneck of the model cannot be grasped by only one of the judgment of the product assortment status and the order confirmation.

【0211】また、本発明は、制御部27が、上記各部
品の品揃え状況の判断結果および上記各部品の発注状況
の確認結果に応じた色を各機種ごとまたは各部品ごとに
設定し、進度管理端末装置34が、制御部27にて得ら
れる結果を、上記設定色にて表示する構成である。これ
により、管理者は、進度管理端末装置34に表示される
結果を、容易にかつ的確に把握することができる。
Further, according to the present invention, the control unit 27 sets a color for each model or each component according to the result of determining the assortment status of each component and the result of checking the order status of each component, The progress management terminal device 34 is configured to display the result obtained by the control unit 27 in the set color. Thus, the administrator can easily and accurately grasp the result displayed on the progress management terminal device 34.

【0212】また、図21に示した『隘路部品発注状況
一覧表』は、倉入日程の入替え(生産計画の前倒し)に
より隘路となる部品(赤色および橙色表示部品)を表示
するものである。また、図29に示した『部品管理詳細
表(督促用)』は、部品の納入の督促を取引先に行うた
めのものである。つまり、これらの表は、問題部品(機
種の生産隘路を引き起こす部品)の納品督促を支援する
アクション情報(支援情報)を含むものである。本発明
では、制御部27がこのようなアクション情報を進度管
理端末装置34に表示させることにより、例えば管理者
や部品担当者は、進度管理端末装置34に表示されたア
クション情報に基づいて、部品の納入の取引先への督促
を的確に行うことができる。
The "bottle parts order status list" shown in FIG. 21 displays parts (red and orange display parts) that become bottlenecks due to replacement of the warehouse entry schedule (earlier production plan). The “parts management detailed table (for dunning)” shown in FIG. 29 is for performing dunning of the delivery of parts to the business partner. In other words, these tables include action information (support information) that assists in prompting the delivery of problem parts (parts that cause a production bottleneck of the model). In the present invention, the control unit 27 causes the progress management terminal device 34 to display such action information, so that, for example, the manager or the component person in charge can manage the component based on the action information displayed on the progress management terminal device 34. The dunning to the business partner of the delivery can be performed accurately.

【0213】(5.部品納入進度管理プログラムおよび
記録媒体)以上で説明した部品納入進度管理システム3
での処理は、プログラムで実現することが可能である。
このプログラムはコンピュータで読み取り可能な記録媒
体に格納されている。本発明では、この記録媒体とし
て、データ記憶部11であってもよいし、部品納入進度
管理システム3で処理が行われるために必要な図示して
いないメモリ(例えばROMそのもの)であってもよい
し、また図示していないが外部記憶装置としてプログラ
ム読み取り装置が設けられ、そこに記録媒体を挿入する
ことで読み取り可能なプログラムメディアであってもよ
い。
(5. Parts Delivery Progress Management Program and Recording Medium) The parts delivery progress management system 3 described above
Can be realized by a program.
This program is stored in a computer-readable recording medium. In the present invention, the recording medium may be the data storage unit 11 or a memory (not shown) (not shown) required for the parts delivery progress management system 3 to perform processing. Although not shown, a program reading device may be provided as an external storage device, and may be a program medium readable by inserting a recording medium therein.

【0214】上記いずれの場合においても、格納されて
いるプログラムはマイクロプロセッサ(図示せず)のア
クセスにより実行される構成であってもよいし、格納さ
れているプログラムを読み出し、読み出したプログラム
を図示されていないプログラム記憶エリアにダウンロー
ドすることにより、そのプログラムが実行される構成で
あってもよい。この場合、ダウンロード用のプログラム
は予め本体装置に格納されているものとする。
In any of the above cases, the stored program may be configured to be executed by accessing a microprocessor (not shown), or the stored program may be read and the read program may be read. The program may be executed by downloading it to a program storage area that is not executed. In this case, it is assumed that the download program is stored in the main device in advance.

【0215】ここで、上記プログラムメディアは、本体
と分離可能に構成される記録媒体であり、磁気テープや
カセットテープ等のテープ系、フロッピー(登録商標)
ディスクやハードディスク等の磁気ディスクやCD−R
OM/MO/MD/DVD等の光ディスクのディスク
系、ICカード(メモリカードを含む)/光カード等の
カード系、あるいはマスクROM、EPROM、EEP
ROM、フラッシュROM等による半導体メモリを含め
た固定的にプログラムを担持する媒体であってもよい。
Here, the program medium is a recording medium configured to be separable from the main body, and is a tape system such as a magnetic tape or a cassette tape, a floppy (registered trademark).
Magnetic disk and CD-R such as disk and hard disk
Disk system of optical disk such as OM / MO / MD / DVD, card system such as IC card (including memory card) / optical card, or mask ROM, EPROM, EEP
A fixed medium including a semiconductor memory such as a ROM or a flash ROM may be a medium that carries a program.

【0216】また、本発明においては、インターネット
を含む通信ネットワークと接続可能なシステム構成であ
ることから、通信ネットワークからプログラムをダウン
ロードするように流動的にプログラムを担持する媒体で
あってもよい。なお、このように通信ネットワークから
プログラムをダウンロードする場合には、そのダウンロ
ード用プログラムは予め本体装置に格納しておくか、あ
るいは別な記録媒体からインストールされるものであっ
てもよい。
Further, in the present invention, since the system configuration can be connected to a communication network including the Internet, the medium may be a medium that carries the program fluidly so that the program is downloaded from the communication network. When the program is downloaded from the communication network, the download program may be stored in the main device in advance or may be installed from another recording medium.

【0217】なお、記録媒体に格納されている内容とし
てはプログラムに限定されず、データであってもよい。
The contents stored on the recording medium are not limited to programs, but may be data.

【0218】(6.補足)以上で説明した本発明の部品
納入進度管理システム、部品納入進度管理方法、部品納
入進度管理プログラムを記録した記録媒体および部品管
理システムは、以下のように表現することもできる。
(6. Supplement) The component delivery progress management system, the component delivery progress management method, the recording medium on which the component delivery progress management program is recorded, and the component management system of the present invention described above are expressed as follows. Can also.

【0219】本発明の部品納入進度管理システムは、生
産計画機種の生産予定に対する機種の構成部品の品揃え
状況(納入状況)を表示する品揃え状況(納入状況)表
示手段と、生産隘路となる機種に対して、生産予定日別
に生産に必要な部品の隘路状況を警告の色別で表示する
警告色別表示手段と、指定納期への納品に対する督促業
務を支援するアクション情報を表示するアクション情報
表示手段とを備えた構成である。
The parts delivery progress management system of the present invention is an assortment status (delivery status) display means for displaying the assortment status (delivery status) of the component parts of the model with respect to the production plan of the production plan model, and a production bottleneck. Warning color display means that displays the bottleneck situation of parts required for production in different colors by warning colors for each model production date, and action information that displays action information that supports the dunning operation for delivery to the specified delivery date And a display unit.

【0220】また、本発明の部品納入進度管理システム
は、上記した部品納入進度管理システムにおいて、上記
品揃え状況表示手段は、生産予定機種の生産予定日に対
する、構成部品の納入状況の自動判断と、警告の色別表
示とを行う構成である。
Further, in the parts delivery progress management system of the present invention, in the above-mentioned parts delivery progress management system, the assortment status display means automatically determines the delivery status of the component parts with respect to the planned production date of the model to be produced. , And a warning by color.

【0221】また、本発明の部品納入進度管理システム
は、上記品揃え状況の自動把握と警告色別表示を納入部
品の実績把握を元に行い、生産予定機種の生産隘路の把
握に基づいて、構成部品の督促必要部品の絞込み、納入
業者へのアクション情報の提供、および、業務体制(例
えば管理者、生産企画部)に合わせた情報の提供を行う
構成である。
Further, the parts delivery progress management system of the present invention performs the above-mentioned automatic grasp of the assortment status and warning color display based on the grasp of the actual results of the delivered parts, and based on the grasp of the production bottleneck of the model to be produced. This configuration narrows down dunning-required parts of component parts, provides action information to suppliers, and provides information tailored to the business system (for example, manager, production planning department).

【0222】また、本発明の部品納入進度管理方法は、
生産計画機種の生産予定に対する、製品の構成部品の品
揃え状況(納入状況)を表示するステップと、生産隘路
となる機種に対して、生産予定日別に、生産に必要な部
品の隘路状況を警告色別に表示するステップと、指定納
期への納品に対する督促業務を支援するアクション情報
を表示するステップとを有している。
Also, the method for managing the progress of parts delivery according to the present invention
A step to display the assortment status (delivery status) of product components with respect to the production schedule of the production plan model, and warn the bottleneck status of the parts required for production by the planned production date for the production bottleneck model It has a step of displaying by color and a step of displaying action information that supports a dunning operation for delivery to a designated delivery date.

【0223】上記の構成によれば、生産予定機種の本日
以降12日後までの生産予定に対し、部品の品揃え状況
を警告色別表示することによって、管理職は、生産の予
定に対する部品の確保、および納入予定の全体を瞬時に
把握でき、次のアクションが迅速になる。すなわち生産
の隘路を未然に防止することが可能となる。よって、実
質的な日々の隘路部品の撲滅と、長期的に見た部品枠の
確保ができる。
According to the above-described configuration, for the production schedule of the model to be produced from today to twelve days later, the assortment status of the parts is displayed by the warning color, so that the manager can secure the parts with respect to the production schedule. , And the entire delivery schedule can be grasped instantly, and the next action can be performed quickly. That is, it is possible to prevent bottlenecks in production. Therefore, it is possible to substantially eliminate bottleneck parts on a daily basis and secure a parts frame in a long term.

【0224】さらに、生産の予定機種の品揃えと機種構
成部品の納入状況とを関連付けて管理できるように、機
種別構成部品展開部が、注文発行時の機種別構成部品の
構成情報(例えば確定注文番号)を部品別適用機種テー
ブルとして持つことにより、機種の隘路から具体的な部
品の隘路を把握することができる。これにより、部品の
隘路がその部品を使用して生産される機種の生産計画に
与える影響を判断することが可能となる。その結果、部
品の隘路の状況に応じた対応策を打てるなど、次に適切
なアクションを行うことが可能となる。
Further, the model-specific component developing unit expands the model-specific component configuration information at the time of order issuance (for example, confirms) so that the assortment of planned models to be produced and the delivery status of the model components can be managed in association with each other. (Order number) as a part-based application model table, it is possible to grasp the specific bottleneck of the part from the bottleneck of the model. Thus, it is possible to determine the influence of the bottleneck of a part on the production plan of a model manufactured using the part. As a result, it is possible to take an appropriate action next, such as taking a countermeasure according to the situation of the bottleneck of parts.

【0225】また、生産の追加および生産の順番の変更
の要求に対しても、上記影響の判断が瞬時に可能である
ので、市場に密着した生産計画の策定を容易に行うこと
ができる。
In addition, the above-mentioned influence can be determined instantaneously in response to a request for adding a production and changing the production order, so that a production plan closely related to the market can be easily formulated.

【0226】つまり、月間の生産ラインの能力(設備・
人員)を考えた場合、大幅な追加生産はできないが、市
場の動向(売れ筋商品(機種)の売り上げ状況)によ
り、生産の順序を入れ替えたり、計画台数を増加したり
する必要が生じる場合がある。この場合、従来では、人
海戦術の対応を強いられていたが、本発明によれば、隘
路部品の、変更後の生産計画への影響を迅速に判断する
ことができるので、市場の動向に応じた対応策を容易に
打てる効果がある。
That is, the monthly production line capacity (equipment /
), Significant additional production is not possible, but depending on market trends (sales status of hot-selling products (models)), it may be necessary to change the order of production or increase the planned number of units . In this case, conventionally, the response of the human naval tactic was forced. However, according to the present invention, it is possible to quickly determine the influence of the bottleneck parts on the production plan after the change, so There is an effect that a corresponding countermeasure can be easily taken.

【0227】また、本発明の部品納入進度管理システム
は、さらに、上記機種別構成部品情報を持つ手段(部品
別適用機種テーブル)に、次工程の情報(製造担当と機
種別の構成部品展開連番)を付与する構成である。
Further, the parts delivery progress management system of the present invention further stores information on the next process (manufacturer and component-specific component development No.).

【0228】納入部品は、直接生産工程に供給される部
品(供給部品)と、一旦、2次加工業者に支給される部
品(支給部品)とに分類される。次工程情報を機種別構
成部品情報に付与することで、供給部品の中でも、一旦
2次加工業者に支給され、加工後生産ラインに供給され
る部品の納入情報が機種別構成部品情報にリアルに反映
される。これにより、2次加工先の状況を、部品管理担
当レベルで容易に把握することができる。
The delivered parts are classified into parts directly supplied to the production process (supplied parts) and parts temporarily supplied to the secondary processor (supplied parts). By adding the next process information to the model-specific component information, the delivery information of the parts that are once supplied to the secondary processing company and supplied to the production line after processing among the supplied parts are realistically included in the model-specific component information. Will be reflected. As a result, the status of the secondary machining destination can be easily grasped at the part management charge level.

【0229】さらに、部品の隘路が発生した場合、督促
に必要な内容を進度管理担当者別に表示させることで、
その表示画面を見ながら、経験の薄い人でも容易に督促
業務ができる。なお、上記の督促に必要な内容とは、部
品に関する情報であって、例えば、資材部担当者、管理
担当者、製造担当業者名、窓口担当者、TEL番号等が
ある。
Further, when a bottleneck occurs in the parts, the contents required for the dunning are displayed for each of the progress managers.
While looking at the display screen, even the inexperienced person can easily perform the dunning operation. The contents required for the dunning are information on parts, and include, for example, a material department manager, a manager, a manufacturer, a contact person, and a TEL number.

【0230】さらに、督促確認結果(業者と交渉した今
後の対応策情報)を督促確認情報に付与することによ
り、部品管理担当者以外の人(管理職、生産企画部の生
産計画作成者等)が今後の部品の納入予定計画を容易に
理解でき、必要な対策に対して迅速に対応することが可
能となる。
Further, by attaching the result of the dunning confirmation (information on future countermeasures negotiated with the trader) to the dunning confirmation information, a person other than the person in charge of parts management (a manager, a production plan creator of the production planning department, etc.) Can easily understand the planned delivery schedule of future parts, and can quickly respond to necessary measures.

【0231】また、本発明の部品管理システムは、上述
したいずれかの部品納入進度管理システムと、当該部品
納入進度管理システムに通信回線を介して接続される業
者用検収確認・督促内容表示装置とを有している構成で
ある。
Further, the parts management system of the present invention includes any one of the above-described parts delivery progress management systems, and an acceptance confirmation / reminder content display device for a trader connected to the parts delivery progress management system via a communication line. It is the structure which has.

【0232】上記の構成によれば、直送部品(2次加工
先に1次業者より直接部品が納品される部品)の納入状
況を、部品納入進度管理システムが通信回線を介して業
者用検収確認・督促内容表示装置から受領することがで
きる。これにより、1次業者から2次加工業者に直接納
品される部品の納入状況を部品納入進度管理システムに
てリアルに把握することができる。その結果、相手先の
ラインを止めることのないように、2次加工業者に支給
される部品に対する管理を、部品納入進度管理システム
が責任を持って行うことができる。
According to the above configuration, the delivery status of the directly sent parts (parts to which the parts are directly delivered from the primary supplier to the secondary processing destination) is checked by the parts delivery progress management system through the communication line for the acceptance of the supplier. -It can be received from the dunning content display device. As a result, the delivery status of components directly delivered from the primary supplier to the secondary processor can be grasped realistically by the component delivery progress management system. As a result, the component delivery progress management system can manage the components supplied to the secondary processing company with responsibility so as not to stop the partner line.

【0233】本発明の部品納入進度管理プログラムを記
録したコンピュータ読み取り可能な記録媒体は、上記の
各手段をコンピュータに実現させて、上記部品納入進度
管理システムを動作させる部品納入進度管理プログラム
を記録したコンピュータ読み取り可能な記録媒体であ
る。
[0233] The computer-readable recording medium that records the component delivery progress management program of the present invention stores the component delivery progress management program that causes the above-described units to be realized by a computer and operates the component delivery progress management system. It is a computer-readable recording medium.

【0234】上記構成により、上記記録媒体から読み出
された部品納入進度管理プログラムによって、上記部品
納入進度管理システムおよび部品納入進度管理方法を実
現することができる。
According to the above configuration, the component delivery progress management system and the component delivery progress management method can be realized by the component delivery progress management program read from the recording medium.

【0235】[0235]

【発明の効果】本発明に係る部品納入進度管理システム
は、以上のように、生産を予定している機種を構成する
各部品の納入進度を管理する部品納入進度管理システム
であって、上記機種の生産計画情報と、上記機種を構成
する各部品に関する情報とを記憶する記憶手段と、上記
記憶手段に記憶された情報に基づいて、上記各部品の納
入予定日よりも前の時点で、上記各部品の品揃え状況を
上記機種ごとに判断すると共に、上記各部品の発注状況
を上記機種ごとに確認する制御手段と、上記制御手段に
て得られる結果を表示する表示手段とを備えている構成
である。
As described above, the component delivery progress management system according to the present invention is a component delivery progress management system for managing the delivery progress of each component constituting a model to be produced. Storage means for storing the production plan information and information on each part constituting the model, and based on the information stored in the storage means, at a time prior to the scheduled delivery date of each part, Control means for judging the assortment status of each part for each model and checking the order status of each part for each model, and display means for displaying the result obtained by the control means Configuration.

【0236】また、本発明に係る部品納入進度管理方法
は、以上のように、生産を予定している機種を構成する
各部品の納入進度を管理する部品納入進度管理方法であ
って、(記憶手段に記憶されている)上記機種の生産計
画情報と、上記機種を構成する各部品に関する情報とに
基づいて、上記各部品の納入予定日よりも前の時点で、
制御手段が上記各部品の品揃え状況を上記機種ごとに判
断すると共に、上記各部品の発注状況を上記機種ごとに
確認するステップと、上記制御手段にて得られる結果を
表示手段が表示するステップとを有している構成であ
る。
The component delivery progress management method according to the present invention, as described above, is a component delivery progress management method for managing the delivery progress of each component constituting a model to be produced. Based on the production plan information of the above-mentioned model (stored in the means) and the information on each of the parts constituting the above-mentioned model, at a time before the scheduled delivery date of each of the above-mentioned parts,
A control means for judging an assortment status of each part for each model, and confirming an order status of each component for each model; and a display means for displaying a result obtained by the control means. This is a configuration having

【0237】それゆえ、制御手段は、品揃え状況の判断
および発注状況の確認を、各部品の納入予定日よりも前
に行うので、管理者が、表示手段に表示された結果を見
たときに、各部品を用いて生産される機種の生産が隘路
となりそうかどうかという生産隘路の傾向を、部品の納
入予定日よりも前に把握することができる。この結果、
機種の生産隘路が発生しそうと判断すれば、納入予定日
までに部品を納入するような督促を取引先に行ったり、
生産計画の変更を行うなどの適切な対応をとることがで
きる。
Therefore, the control means judges the assortment status and confirms the order status before the scheduled delivery date of each part. Therefore, when the administrator sees the result displayed on the display means, Further, it is possible to grasp the tendency of the production bottleneck as to whether or not the production of a model produced using each part is likely to become a bottleneck before the scheduled delivery date of the part. As a result,
If it is determined that there will be a bottleneck in the production of the model, the supplier will be urged to deliver parts by the scheduled delivery date,
Appropriate measures such as changing the production plan can be taken.

【0238】ここで、部品の納入の督促を行う場合は、
部品の納入予定日よりも前に督促できるので、元々の納
入予定日自体が変動することがない。したがって、従来
のように納入予定日と生産予定日との間が長期にならな
いので、在庫が長期にわたって過剰になるということが
なく、在庫の管理負担の増大を抑制することができる。
Here, in order to urge the delivery of parts,
Since the dunning can be performed before the scheduled delivery date of the parts, the original scheduled delivery date itself does not change. Therefore, since the time between the scheduled delivery date and the scheduled production date does not become long as in the related art, the stock does not become excessive for a long time, and an increase in stock management load can be suppressed.

【0239】また、生産計画を変更する場合は、生産計
画を変更するかどうかの検討を、生産隘路となる機種の
構成部品の納入予定日よりも前に行うことができるの
で、その検討を納入予定日よりも前に終えることができ
れば、上記納入予定日から直ちに、生産計画変更後の機
種の生産のための生産ライン(検査、準備を含む)を稼
働させることが可能となる。つまり、元々の納入予定日
と、生産計画変更後の機種の生産ラインの稼働開始日と
の間にタイムラグが生じることがない。この結果、機種
の生産効率の低下を抑制することができるという効果を
奏する。
When the production plan is to be changed, whether or not the production plan is to be changed can be examined before the scheduled delivery date of the components of the model that will be the production bottleneck. If it can be completed before the scheduled date, the production line (including inspection and preparation) for the production of the model after the change of the production plan can be operated immediately from the scheduled delivery date. That is, there is no time lag between the original scheduled delivery date and the operation start date of the production line of the model after the change of the production plan. As a result, there is an effect that a decrease in the production efficiency of the model can be suppressed.

【0240】本発明に係る部品納入進度管理システム
は、以上のように、上記各部品の在庫数と、上記各部品
の納入予定日における納入予定数とに基づいて、上記各
部品の欠品状況を判断する欠品状況判断手段をさらに備
え、上記制御手段は、上記機種を構成する部品の総数
と、欠品と判断された部品の数とに基づいて、上記各部
品の品揃え状況を上記機種ごとに判断する構成である。
As described above, the parts-delivering-progress management system according to the present invention uses the stock-out status of each part based on the stock quantity of each part and the planned number of parts to be delivered on the scheduled delivery date. The controller further includes a part-out state determining unit that determines the part-sorting state of each part based on the total number of parts constituting the model and the number of parts determined to be out of stock. In this configuration, the judgment is made for each model.

【0241】それゆえ、欠品状況判断手段の判断結果を
品揃え状況の判断に利用するので、制御手段が各部品の
品揃え状況を機種ごとに的確に判断することができると
いう効果を奏する。
[0241] Therefore, since the judgment result of the out-of-stock condition judging means is used for judging the assortment status, there is an effect that the control means can accurately judge the assortment status of each part for each model.

【0242】本発明に係る部品納入進度管理システム
は、以上のように、上記品揃え状況の判断対象となる機
種を指定する品揃え機種指定手段をさらに備え、上記制
御手段は、上記品揃え機種指定手段によって指定された
機種を構成する各部品の品揃え状況を判断する構成であ
る。
As described above, the parts delivery progress management system according to the present invention further includes an assortment model designation means for designating a model to be determined for the assortment status, and the control means includes the assortment model. This is a configuration in which the assortment status of each component constituting the model designated by the designation means is determined.

【0243】それゆえ、管理者は、品揃え機種指定手段
を操作することによって、品揃え状況を見る機種を自由
に選択することができ、管理者の意図する機種について
の各部品の品揃え状況を表示手段にて把握することがで
きるという効果を奏する。
Therefore, the manager can freely select a model whose viewing status is to be checked by operating the assortment model designating means. Can be grasped by the display means.

【0244】本発明に係る部品納入進度管理システム
は、以上のように、上記制御手段は、上記品揃え機種指
定手段によって指定された機種を構成する各部品の納入
予定の有無および在庫の有無とに基づいて、上記各部品
の品揃え状況を判断する構成である。
As described above, in the parts delivery progress management system according to the present invention, the control means determines whether or not each component constituting the model designated by the assortment model designation means is scheduled to be delivered and whether or not the parts are in stock. Is configured to determine the assortment status of each of the above components based on

【0245】それゆえ、制御手段は、各部品の品揃え状
況を的確に行うことができるという効果を奏する。
Therefore, the control means has an effect that the assortment status of each part can be accurately performed.

【0246】本発明に係る部品納入進度管理システム
は、以上のように、上記制御手段は、上記機種を構成す
る各部品の在庫数、納入予定数、上記機種の生産予定数
および各部品の発注員数に基づいて上記各部品が欠品と
なるか否か(上記各部品の発注が適正か否か)を判断す
ると共に、その欠品部品(発注漏れ部品)の有無に基づ
いて機種としての発注状況を確認する構成である。
As described above, in the parts delivery progress management system according to the present invention, the control means controls the number of parts, the number of parts to be delivered, the number of parts to be produced of the above-mentioned model, and the order of each part constituting the above-mentioned model. Based on the number of members, it is determined whether or not each of the above-mentioned parts is missing (whether or not the order of each of the above-mentioned parts is appropriate). This is a configuration for checking the status.

【0247】それゆえ、制御手段は、各部品の発注状況
を機種ごとに的確に確認することができるという効果を
奏する。
Therefore, the control means has an effect that the order status of each part can be accurately confirmed for each model.

【0248】本発明に係る部品納入進度管理システム
は、以上のように、上記発注状況の確認対象となる機種
を指定する発注機種指定手段をさらに備え、上記制御手
段は、上記発注機種指定手段によって指定された機種を
構成する各部品の発注状況を確認する構成である。
As described above, the parts delivery progress management system according to the present invention further comprises order model designation means for designating a model whose order status is to be confirmed, and the control means is controlled by the order model designation means. This is a configuration in which the order status of each part constituting the specified model is confirmed.

【0249】それゆえ、管理者は、発注機種指定手段を
操作することによって、発注状況を見る機種を自由に選
択することができ、管理者の意図する機種についての各
部品の発注状況を表示手段にて把握することができると
いう効果を奏する。
Therefore, the administrator can freely select a model whose order status is to be viewed by operating the order model specifying means, and display the order status of each part for the model intended by the administrator. This has the effect of being able to be grasped.

【0250】本発明に係る部品納入進度管理システム
は、以上のように、上記制御手段は、上記発注機種指定
手段によって指定された機種を構成する各部品の在庫
数、納入予定数、上記機種の生産予定数および各部品の
発注員数に基づいて、上記各部品の発注状況を確認する
構成である。
As described above, in the parts delivery progress management system according to the present invention, the control means controls the inventory quantity, the scheduled delivery quantity, and the number of parts constituting the model designated by the ordered model designation means. In this configuration, the order status of each component is confirmed based on the planned production quantity and the number of orderers for each component.

【0251】それゆえ、制御手段は、指定された機種に
ついての各部品の発注状況を的確に確認することができ
るという効果を奏する。
Therefore, the control means has an effect that the order status of each part for the designated model can be accurately confirmed.

【0252】本発明に係る部品納入進度管理システム
は、以上のように、上記制御手段は、上記各部品の品揃
え状況の判断結果および上記各部品の発注状況の確認結
果に応じた色を各機種ごとまたは各部品ごとに設定し、
上記表示手段は、上記制御手段にて得られる結果を、上
記設定色にて表示する構成である。
As described above, in the parts delivery progress management system according to the present invention, the control means sets the colors according to the result of the judgment on the assortment status of the respective parts and the result of the confirmation of the order status of the respective parts. Set for each model or each part,
The display means is configured to display the result obtained by the control means in the set color.

【0253】それゆえ、表示手段を見る管理者は、機種
ごとまたは部品ごとの品揃え状況および発注状況を、一
目で見て容易に把握することができるという効果を奏す
る。
Therefore, the manager who looks at the display means can easily grasp the assortment status and the order status for each model or each component at a glance.

【0254】本発明に係る部品納入進度管理システム
は、以上のように、上記制御手段は、上記各部品の納入
の督促を支援する情報を上記表示手段に表示させる構成
である。
As described above, the parts delivery progress management system according to the present invention is configured such that the control means causes the display means to display information for assisting the prompting of the delivery of each part.

【0255】それゆえ、管理者や部品担当者は、表示手
段に表示された支援情報に基づいて、部品の納入の取引
先への督促を的確に行うことができるという効果を奏す
る。
[0255] Therefore, there is an effect that the manager and the parts manager can appropriately prompt the supplier for the delivery of the parts based on the support information displayed on the display means.

【0256】本発明に係る部品納入進度管理プログラム
は、以上のように、生産を予定している機種を構成する
各部品の納入進度を管理する部品納入進度管理システム
における部品納入進度管理プログラムであって、上記機
種の生産計画情報と、上記機種を構成する各部品に関す
る情報とに基づいて、上記各部品の納入予定日よりも前
の時点で、上記各部品の品揃え状況を上記機種ごとに判
断すると共に、上記各部品の発注状況を上記機種ごとに
確認する手段と、上記品揃え状況の判断結果および上記
発注状況の確認結果を表示する手段としてコンピュータ
を機能させるためのプログラムである構成である。
As described above, the component delivery progress management program according to the present invention is a component delivery progress management program in a component delivery progress management system for managing the delivery progress of each component constituting a model to be produced. Based on the production plan information of the above-mentioned model and the information on each of the parts constituting the above-mentioned model, the assortment status of each of the above-mentioned parts at each time before the scheduled delivery date of each of the above-mentioned parts is described for each of the above-mentioned models. It is a program for causing a computer to function as means for determining and checking the ordering status of each part for each model, and for displaying the result of determining the assortment status and the result of checking the ordering status. is there.

【0257】それゆえ、上記の部品納入進度管理プログ
ラムをコンピュータが実行することにより、本発明の部
品納入進度管理方法を実現することが可能となるという
効果を奏する。
Therefore, when the computer executes the above-described component delivery progress management program, it is possible to realize the component delivery progress management method of the present invention.

【0258】本発明に係る部品納入進度管理プログラム
を記録した記録媒体は、以上のように、上述した本発明
の部品納入進度管理プログラムをコンピュータにて読み
取り可能に記録してなる構成である。
As described above, the recording medium storing the component delivery progress management program according to the present invention has a configuration in which the above-described component delivery progress management program of the present invention is recorded so as to be readable by a computer.

【0259】それゆえ、記録媒体に記録されている部品
納入進度管理プログラムをコンピュータが読み取って実
行することにより、本発明の部品納入進度管理方法を実
現することが可能となるという効果を奏する。
Therefore, by reading and executing the component delivery progress management program recorded on the recording medium by the computer, it is possible to realize the component delivery progress management method of the present invention.

【0260】本発明に係る部品管理システムは、以上の
ように、上述した本発明の部品納入進度管理システム
と、生産を予定している機種を構成する各部品を発注す
る部品発注システムと、発注された各部品を手配する受
注者側システムとが通信回線を介して互いに接続されて
なる構成である。
As described above, the parts management system according to the present invention comprises a parts delivery progress management system according to the present invention, a parts ordering system for ordering each part constituting a model to be produced, and an ordering system. And a contractor-side system for arranging the respective parts are connected to each other via a communication line.

【0261】それゆえ、部品納入進度管理システムは、
部品発注システムにて得られる情報(例えば部品の発注
情報)や、受注者側システムにて得られる情報(例えば
1次業者から2次加工業者への部品の支給情報)を電子
データで受信し、受信した情報を即座に部品の納入管理
に反映させることが可能となる。その結果、管理者およ
び担当者は、部品に関する情報をリアルタイムに把握す
ることが可能となるという効果を奏する。
Therefore, the parts delivery progress management system
Receiving information (for example, part ordering information) obtained by the part ordering system and information (for example, part supply information from the primary trader to the secondary processing trader) obtained by the orderer system as electronic data; The received information can be immediately reflected in the delivery management of parts. As a result, there is an effect that the manager and the person in charge can grasp the information on the parts in real time.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の一形態に係る部品管理システム
を構成する部品納入進度管理システムの概略の構成を示
す説明図である。
FIG. 1 is an explanatory diagram showing a schematic configuration of a component delivery progress management system constituting a component management system according to an embodiment of the present invention.

【図2】上記部品管理システムの概略の構成を示す説明
図である。
FIG. 2 is an explanatory diagram showing a schematic configuration of the component management system.

【図3】上記部品管理システムにおける部品発注処理お
よび部品検収処理の流れを示す説明図である。
FIG. 3 is an explanatory diagram showing a flow of a component ordering process and a component acceptance process in the component management system.

【図4】上記部品納入進度管理システムのデータ記憶部
を構成する各マスターに記憶されている情報の一覧を示
す説明図である。
FIG. 4 is an explanatory diagram showing a list of information stored in each master constituting a data storage unit of the component delivery progress management system.

【図5】生産予定の機種の部品構成を示すと共に、各部
品の発注員数を示す説明図である。
FIG. 5 is an explanatory diagram showing a component configuration of a model to be produced and showing the number of orders for each component.

【図6】上記データ記憶部の生産計画マスターおよび部
品別適用機種マスターに記憶されている情報と、これら
の情報に基づいて上記部品納入進度管理システムの納入
進度管理処理部の機種別構成部品展開部が作成する部品
別適用機種テーブルの情報とを示す説明図である。
FIG. 6 shows information stored in a production planning master and a part-by-part applicable model master in the data storage unit and, based on the information, a component-specific component development of a delivery progress management processing unit of the component delivery progress management system. FIG. 9 is an explanatory diagram showing information of a part-by-part applied model table created by a unit.

【図7】上記部品別適用機種テーブルの情報と、上記デ
ータ記憶部の納入予定・実績マスターに記憶されている
情報とを示すと共に、これらの情報に基づいて、上記納
入進度管理処理部の部品別納入予定実績比較部が作成す
る納入予定・実績対比テーブルの情報を示す説明図であ
る。
FIG. 7 shows information of the applicable model table for each part and information stored in a delivery schedule / actual master in the data storage unit, and based on these information, a part of the delivery progress management processing unit. It is explanatory drawing which shows the information of the delivery schedule / results comparison table which a separate delivery schedule results comparison part creates.

【図8】上記データ記憶部の在庫マスターに記憶されて
いる情報を示すと共に、上記情報と上記納入予定・実績
対比テーブルの情報とに基づいて上記部品別納入予定実
績比較部が作成する納入予定・実績テーブルの情報を示
す説明図である。
FIG. 8 shows information stored in an inventory master of the data storage unit, and a delivery schedule created by the part-by-part delivery schedule / actual comparison unit based on the information and the information of the delivery schedule / actual comparison table. -It is explanatory drawing which shows the information of a performance table.

【図9】上記生産計画マスターに記憶されている情報
と、上記納入予定・実績テーブルの情報とを示す説明図
である。
FIG. 9 is an explanatory diagram showing information stored in the production plan master and information of the delivery schedule / actual table.

【図10】警告色の設定前後における上記納入予定・実
績テーブルの情報を示す説明図である。
FIG. 10 is an explanatory diagram showing information of the delivery schedule / actual table before and after setting a warning color.

【図11】上記納入予定・実績テーブルの情報と、上記
データ記憶部の注残マスターに記憶されている情報と、
これらの情報に基づいて上記納入進度管理処理部の出力
要求別仕訳部が作成する取引・担当コード設定テーブル
の情報とを示す説明図である。
FIG. 11 shows information of the delivery schedule / actual table, information stored in a back order master of the data storage unit,
It is an explanatory view showing information of a transaction and charge code setting table created by the output request-specific journaling unit of the delivery progress management processing unit based on these information.

【図12】上記取引・担当コード設定テーブルの情報
と、上記データ記憶部の取引先マスターおよび担当者マ
スターに記憶されている情報と、これらの情報に基づい
て上記出力要求別仕訳部が作成する取引先・担当者テー
ブルの情報とを示す説明図である。
FIG. 12 shows the information in the transaction / charge code setting table, the information stored in the supplier master and the person in charge master in the data storage unit, and the output request-specific journal unit creates based on the information. It is explanatory drawing which shows the information of a business partner / person in charge table.

【図13】上記納入進度管理処理部の発注内容確認部が
作成する注残・在庫・納入予実テーブルの情報を示す説
明図である。
FIG. 13 is an explanatory diagram showing information of a back order / stock / delivery forecast actual table created by an order content confirmation unit of the delivery progress management processing unit.

【図14】上記部品納入進度管理システムにおける動作
のおおまかな流れを示すフローチャートである。
FIG. 14 is a flowchart showing a general flow of an operation in the component delivery progress management system.

【図15】上記部品納入進度管理システムにおける品揃
え管理の流れを示すフローチャートである。
FIG. 15 is a flowchart showing a flow of assortment management in the component delivery progress management system.

【図16】上記納入進度管理処理部の納入進度表示制御
部(以下、単に制御部と記載する)が作成する『品揃え
状況機種別一覧表』の内容を示す説明図である。
FIG. 16 is an explanatory diagram showing the contents of an “assortment status machine type list” created by a delivery progress display control unit (hereinafter simply referred to as a control unit) of the delivery progress management processing unit.

【図17】上記制御部が作成する『品揃え状況部品別一
覧表』の内容を示す説明図である。
FIG. 17 is an explanatory diagram showing the contents of a “list of assortment status parts” created by the control unit.

【図18】上記部品納入進度管理システムにおける発注
確認の流れを示すフローチャートである。
FIG. 18 is a flowchart showing a flow of order confirmation in the component delivery progress management system.

【図19】上記制御部が作成する『発注状況機種別一覧
表』の内容を示す説明図である。
FIG. 19 is an explanatory diagram showing the contents of an “ordering status model list” created by the control unit.

【図20】生産計画の変更によって、機種を構成する部
品の発注状況が変化した場合に、上記制御部が作成する
『発注状況機種別一覧表』の内容を示す説明図である。
FIG. 20 is an explanatory diagram showing the contents of an “ordering status model list” created by the control unit when the ordering status of parts constituting a model changes due to a change in a production plan.

【図21】上記制御部が作成する『隘路部品発注状況一
覧表』の内容を示す説明図である。
FIG. 21 is an explanatory diagram showing the contents of a “bottle part order status list” created by the control unit.

【図22】上記制御部が作成する『隘路部品詳細表』の
内容を示す説明図である。
FIG. 22 is an explanatory diagram showing the contents of a “bottle part detail table” created by the control unit.

【図23】(a)は、納期調整を行う前に上記制御部が
作成する『支給部品納期情報一覧表』の内容を示す説明
図である。(b)は、納期調整を行った後に上記制御部
が作成する『支給部品納期情報一覧表』の内容を示す説
明図である。
FIG. 23A is an explanatory diagram showing the contents of a “supplied part delivery date information list” created by the control unit before delivery date adjustment is performed. (B) is an explanatory view showing the contents of a "supplied part delivery date information list" created by the control unit after the delivery date is adjusted.

【図24】上記部品納入進度管理システムにおける納入
進度管理の流れを示すフローチャートである。
FIG. 24 is a flowchart showing a flow of delivery progress management in the component delivery progress management system.

【図25】上記制御部が作成する『支供給部品の納入状
況一覧表』の内容を示す説明図である。
FIG. 25 is an explanatory view showing the contents of a “supply part delivery status list” created by the control unit.

【図26】上記制御部が作成する『支供給部品の納入状
況詳細表』の内容を示す説明図である。
FIG. 26 is an explanatory diagram showing the contents of a “supply part delivery status detailed table” created by the control unit.

【図27】上記制御部が作成する『支供給部品の納入状
況担当者別一覧表』の内容を示す説明図である。
FIG. 27 is an explanatory diagram showing the contents of a “list of subsupply parts delivery status persons in charge” created by the control unit.

【図28】上記制御部が作成する『未納入部品詳細一覧
表』の内容を示す説明図である。
FIG. 28 is an explanatory diagram showing the contents of a “non-delivery part detail list” created by the control unit.

【図29】上記制御部が作成する『部品管理詳細表(督
促用)』の内容を示す説明図である。
FIG. 29 is an explanatory diagram showing the contents of a “parts management detailed table (for dunning)” created by the control unit.

【図30】上記制御部が作成する『督促リスト』の内容
を示す説明図である。
FIG. 30 is an explanatory diagram showing the contents of a “dunning list” created by the control unit.

【符号の説明】[Explanation of symbols]

1 部品発注システム 3 部品納入進度管理システム 4 受注者側システム 5 通信回線 11 データ記憶部(記憶手段) 24 隘路判断部(欠品状況判断手段) 27 部品納入進度表示制御部(制御手段) 34 進度管理端末装置(表示手段、品揃え機種指定
手段、発注機種指定手段)
Reference Signs List 1 parts ordering system 3 parts delivery progress management system 4 contractor system 5 communication line 11 data storage unit (storage means) 24 bottleneck determination unit (out-of-stock status determination means) 27 parts delivery progress display control unit (control means) 34 progress Management terminal device (display means, assortment model designation means, order model designation means)

フロントページの続き (72)発明者 国生 良一 大阪府大阪市阿倍野区長池町22番22号 シ ャープ株式会社内 (72)発明者 田村 和人 大阪府大阪市阿倍野区長池町22番22号 シ ャープ株式会社内 Fターム(参考) 3C100 AA03 AA29 AA36 AA38 BB02 BB04 BB33 BB36 BB38 BB39 CC03 CC11 Continued on the front page (72) Inventor Ryoichi Kunio 22-22 Nagaike-cho, Abeno-ku, Osaka-shi, Osaka Inside (72) Inventor Kazuto Tamura 22-22 Nagaike-cho, Abeno-ku, Osaka-shi, Osaka F term (reference) 3C100 AA03 AA29 AA36 AA38 BB02 BB04 BB33 BB36 BB38 BB39 CC03 CC11

Claims (13)

【特許請求の範囲】[Claims] 【請求項1】生産を予定している機種を構成する各部品
の納入進度を管理する部品納入進度管理システムであっ
て、 上記機種の生産計画情報と、上記機種を構成する各部品
に関する情報とを記憶する記憶手段と、 上記記憶手段に記憶された情報に基づいて、上記各部品
の納入予定日よりも前の時点で、上記各部品の品揃え状
況を上記機種ごとに判断すると共に、上記各部品の発注
状況を上記機種ごとに確認する制御手段と、 上記制御手段にて得られる結果を表示する表示手段とを
備えていることを特徴とする部品納入進度管理システ
ム。
1. A parts delivery progress management system for managing the delivery progress of each component constituting a model scheduled to be produced, comprising: production plan information of the model; information on each component constituting the model; Storage means for storing the information, and based on the information stored in the storage means, at a point in time prior to the scheduled delivery date of each part, determine the assortment status of each part for each model, and A parts delivery progress management system comprising: control means for confirming the order status of each part for each of the models; and display means for displaying a result obtained by the control means.
【請求項2】上記各部品の在庫数と、上記各部品の納入
予定日における納入予定数とに基づいて、上記各部品の
欠品状況を判断する欠品状況判断手段をさらに備え、 上記制御手段は、上記機種を構成する部品の総数と、欠
品と判断された部品の数とに基づいて、上記各部品の品
揃え状況を上記機種ごとに判断することを特徴とする請
求項1に記載の部品納入進度管理システム。
2. The control device according to claim 1, further comprising a shortage status judging means for judging a shortage status of each of the parts based on a stock quantity of each of the parts and a scheduled delivery number of each of the parts on a scheduled delivery date. 2. The apparatus according to claim 1, wherein the means determines an assortment status of each of the parts for each of the models based on a total number of parts constituting the models and a number of parts determined to be missing. The described component delivery progress management system.
【請求項3】上記品揃え状況の判断対象となる機種を指
定する品揃え機種指定手段をさらに備え、 上記制御手段は、上記品揃え機種指定手段によって指定
された機種を構成する各部品の品揃え状況を判断するこ
とを特徴とする請求項2に記載の部品納入進度管理シス
テム。
3. An assortment model designating means for designating a model for which the assortment status is to be determined, wherein the control means comprises a product of each component constituting the model designated by the assortment model designating means. The part delivery progress management system according to claim 2, wherein the alignment status is determined.
【請求項4】上記制御手段は、上記品揃え機種指定手段
によって指定された機種を構成する各部品の納入予定の
有無および在庫の有無とに基づいて、上記各部品の品揃
え状況を判断することを特徴とする請求項3に記載の部
品納入進度管理システム。
4. The control means judges the assortment status of each part based on whether or not each part constituting the model designated by the assortment model designation means is scheduled to be delivered and whether or not there is a stock. The component delivery progress management system according to claim 3, wherein:
【請求項5】上記制御手段は、上記機種を構成する各部
品の在庫数、納入予定数、上記機種の生産予定数および
各部品の発注員数に基づいて上記各部品が欠品となるか
否かを判断すると共に、その欠品部品の有無に基づいて
機種としての発注状況を確認することを特徴とする請求
項1ないし4のいずれかに記載の部品納入進度管理シス
テム。
5. The control means according to claim 1, wherein said parts are out of stock on the basis of the number of stocks, the number of parts to be delivered, the number of parts to be produced of said part, and the number of orders for said parts. The parts delivery progress management system according to any one of claims 1 to 4, further comprising determining whether or not the part is missing and checking the order status as a model based on the presence or absence of the missing parts.
【請求項6】上記発注状況の確認対象となる機種を指定
する発注機種指定手段をさらに備え、 上記制御手段は、上記発注機種指定手段によって指定さ
れた機種を構成する各部品の発注状況を確認することを
特徴とする請求項5に記載の部品納入進度管理システ
ム。
6. An order model designating means for designating a model for which the order status is to be confirmed, wherein the control means confirms the order status of each component constituting the model designated by the order model designating means. The component delivery progress management system according to claim 5, wherein
【請求項7】上記制御手段は、上記発注機種指定手段に
よって指定された機種を構成する各部品の在庫数、納入
予定数、上記機種の生産予定数および各部品の発注員数
に基づいて、上記各部品の発注状況を確認することを特
徴とする請求項6に記載の部品納入進度管理システム。
7. The control means, based on the stock quantity, the scheduled delivery quantity, the planned production quantity of each of the parts constituting the model designated by the ordered model designation means, and the number of orders for each part, The parts delivery progress management system according to claim 6, wherein an order status of each part is confirmed.
【請求項8】上記制御手段は、上記各部品の品揃え状況
の判断結果および上記各部品の発注状況の確認結果に応
じた色を各機種ごとまたは各部品ごとに設定し、 上記表示手段は、上記制御手段にて得られる結果を、上
記設定色にて表示することを特徴とする請求項1ないし
7のいずれかに記載の部品納入進度管理システム。
8. The control means sets a color for each model or each component according to the result of the determination of the assortment status of each of the parts and the result of the confirmation of the order status of each of the components. 8. The component delivery progress management system according to claim 1, wherein a result obtained by said control means is displayed in said set color.
【請求項9】上記制御手段は、上記各部品の納入の督促
を支援する情報を上記表示手段に表示させることを特徴
とする請求項1ないし8のいずれかに記載の部品納入進
度管理システム。
9. The parts delivery progress management system according to claim 1, wherein said control means causes said display means to display information for assisting in demanding delivery of said parts.
【請求項10】生産を予定している機種を構成する各部
品の納入進度を管理する部品納入進度管理方法であっ
て、 上記機種の生産計画情報と、上記機種を構成する各部品
に関する情報とに基づいて、上記各部品の納入予定日よ
りも前の時点で、制御手段が上記各部品の品揃え状況を
上記機種ごとに判断すると共に、上記各部品の発注状況
を上記機種ごとに確認するステップと、 上記制御手段にて得られる結果を表示手段が表示するス
テップとを有していることを特徴とする部品納入進度管
理方法。
10. A parts delivery progress management method for managing the delivery progress of each part constituting a model scheduled to be produced, comprising: a production plan information of said model, information on each part constituting said model. Based on the above, at a point before the scheduled delivery date of each of the parts, the control means determines the assortment status of each of the parts for each of the models and checks the order status of each of the parts for each of the models. A component delivery progress management method, comprising: a step; and a step in which a display means displays a result obtained by the control means.
【請求項11】生産を予定している機種を構成する各部
品の納入進度を管理する部品納入進度管理システムにお
ける部品納入進度管理プログラムであって、 上記機種の生産計画情報と、上記機種を構成する各部品
に関する情報とに基づいて、上記各部品の納入予定日よ
りも前の時点で、上記各部品の品揃え状況を上記機種ご
とに判断すると共に、上記各部品の発注状況を上記機種
ごとに確認する手段と、 上記品揃え状況の判断結果および上記発注状況の確認結
果を表示する手段としてコンピュータを機能させるため
のプログラムであることを特徴とする部品納入進度管理
プログラム。
11. A parts delivery progress management program in a parts delivery progress management system for managing the delivery progress of each component constituting a model scheduled to be produced, comprising: production plan information of the model; Prior to the scheduled delivery date of each of the above parts, the product assortment status of each of the above parts is determined for each of the above models based on the information on each of the above parts. And a program for causing a computer to function as means for displaying the determination result of the assortment status and the confirmation result of the order status.
【請求項12】請求項11に記載の部品納入進度管理プ
ログラムをコンピュータにて読み取り可能に記録してな
ることを特徴とする部品納入進度管理プログラムを記録
した記録媒体。
12. A recording medium on which a component delivery progress management program according to claim 11 is recorded so as to be readable by a computer.
【請求項13】請求項1ないし9のいずれかに記載の部
品納入進度管理システムと、 上記機種を構成する各部品を発注する部品発注システム
と、 発注された部品を手配する受注者側システムとが通信回
線を介して互いに接続されてなることを特徴とする部品
管理システム。
13. A parts delivery progress management system according to any one of claims 1 to 9, a parts ordering system for ordering each part constituting said model, and a contractor side system for arranging ordered parts. Are connected to each other via a communication line.
JP2001117438A 2001-04-16 2001-04-16 Component management system, component management method, component management program, and recording medium recording component management program Expired - Fee Related JP3640900B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001117438A JP3640900B2 (en) 2001-04-16 2001-04-16 Component management system, component management method, component management program, and recording medium recording component management program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001117438A JP3640900B2 (en) 2001-04-16 2001-04-16 Component management system, component management method, component management program, and recording medium recording component management program

Publications (2)

Publication Number Publication Date
JP2002312022A true JP2002312022A (en) 2002-10-25
JP3640900B2 JP3640900B2 (en) 2005-04-20

Family

ID=18967991

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001117438A Expired - Fee Related JP3640900B2 (en) 2001-04-16 2001-04-16 Component management system, component management method, component management program, and recording medium recording component management program

Country Status (1)

Country Link
JP (1) JP3640900B2 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006065852A (en) * 2004-07-29 2006-03-09 Sharp Corp System, method and program for parts management, and recording medium with the program recorded thereon
JP2009151578A (en) * 2007-12-21 2009-07-09 Hitachi Ltd Forecast management system
JP2010061317A (en) * 2008-09-02 2010-03-18 Hitachi Ltd Forecast management system and program thereof
JP2010176407A (en) * 2009-01-29 2010-08-12 Hitachi Ltd Forecast management device and its program
JP2011034186A (en) * 2009-07-30 2011-02-17 Yoichiro Kojima Production management system
JP2015057681A (en) * 2013-08-15 2015-03-26 株式会社インプット Sales support system having healthcare function
JP6273622B1 (en) * 2016-09-23 2018-02-07 充広 藤田 ΔtLot control method product management system, ΔtLot control method product management program, and ΔtLot control method information processing program
CN114881618A (en) * 2022-07-06 2022-08-09 小米汽车科技有限公司 Vehicle production data processing method and device and storage medium
WO2023068052A1 (en) 2021-10-19 2023-04-27 カシオ計算機株式会社 Inventory management method, program, and inventory management device

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020057341A (en) * 2018-09-28 2020-04-09 フジキンソフト株式会社 Production management device and production management method

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006065852A (en) * 2004-07-29 2006-03-09 Sharp Corp System, method and program for parts management, and recording medium with the program recorded thereon
JP2009151578A (en) * 2007-12-21 2009-07-09 Hitachi Ltd Forecast management system
JP2010061317A (en) * 2008-09-02 2010-03-18 Hitachi Ltd Forecast management system and program thereof
JP2010176407A (en) * 2009-01-29 2010-08-12 Hitachi Ltd Forecast management device and its program
JP2011034186A (en) * 2009-07-30 2011-02-17 Yoichiro Kojima Production management system
JP2015057681A (en) * 2013-08-15 2015-03-26 株式会社インプット Sales support system having healthcare function
JP6273622B1 (en) * 2016-09-23 2018-02-07 充広 藤田 ΔtLot control method product management system, ΔtLot control method product management program, and ΔtLot control method information processing program
JP2018049578A (en) * 2016-09-23 2018-03-29 充広 藤田 ΔtLot CONTROL METHOD ARTICLE MANAGEMENT SYSTEM, ΔtLot CONTROL METHOD ARTICLE MANAGEMENT PROGRAM AND ΔtLot CONTROL METHOD INFORMATION PROCESSING PROGRAM
WO2023068052A1 (en) 2021-10-19 2023-04-27 カシオ計算機株式会社 Inventory management method, program, and inventory management device
CN114881618A (en) * 2022-07-06 2022-08-09 小米汽车科技有限公司 Vehicle production data processing method and device and storage medium
CN114881618B (en) * 2022-07-06 2024-09-06 小米汽车科技有限公司 Vehicle production data processing method, device and storage medium

Also Published As

Publication number Publication date
JP3640900B2 (en) 2005-04-20

Similar Documents

Publication Publication Date Title
US7024382B2 (en) System and method for managing retail and wholesale operations
JP5032131B2 (en) Estimated time of arrival (ETA) system and method
US6324437B1 (en) System and method for managing the alteration of garments
JP3982168B2 (en) Purchasing management system, purchasing management method, and purchasing management program
US6876895B2 (en) Order assembly production system and method
US8190497B2 (en) Handheld scanner device with display location database
US20030106039A1 (en) Computer-implemented system and method for project development
US20020156694A1 (en) System and method for customized build-to-order assembly
US20060212323A1 (en) Production management system
US9785895B1 (en) System and method for providing handheld field force data gathering automation in a big box retail environment
Chen et al. A case study in the design of BTO/CTO shop floor control system
JP2002024350A (en) Retail store managing system
JPH06214996A (en) Production management method
JP2002312022A (en) System, method and program for managing process of parts delivery, recording medium with recorded program for managing progress of parts delivery and parts management system
JP2007323680A (en) Management decision support system
JP5145547B2 (en) Multi-variety low-volume electronic equipment production support system and multi-product low-volume electronic equipment production support program
TWI242734B (en) Method for ordering and facilitating the collection items
JP2002063440A (en) Order issuing apparatus, order issuing system, method for issuing order, order issuing program and computer readable recording medium having order issuing program recorded thereon
JP2005215817A (en) System for estimating computer system construction
JP2003216844A (en) Apparatus and method for managing production preparation
JP5199795B2 (en) Forecast management system and program
CN115660618B (en) Maintenance flow optimization method based on corrugated paper equipment and related equipment
JPH06332912A (en) Work managing system
JP2001117983A (en) Cost managing device and recording medium
JP2003345969A (en) Supporting system and method for business operation

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040830

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040907

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20041108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050118

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050119

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080128

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090128

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100128

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110128

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120128

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130128

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees