JP2002266434A - Method of constructing cable dome - Google Patents

Method of constructing cable dome

Info

Publication number
JP2002266434A
JP2002266434A JP2001065479A JP2001065479A JP2002266434A JP 2002266434 A JP2002266434 A JP 2002266434A JP 2001065479 A JP2001065479 A JP 2001065479A JP 2001065479 A JP2001065479 A JP 2001065479A JP 2002266434 A JP2002266434 A JP 2002266434A
Authority
JP
Japan
Prior art keywords
ring
cable
dome
roof
inner peripheral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2001065479A
Other languages
Japanese (ja)
Inventor
Hiroshi Shimizu
弘 清水
Makoto Kondo
近藤  誠
Yoichi Iwamoto
洋一 岩本
Masaaki Fukihara
正晃 吹原
Katsuki Totani
克樹 戸谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP2001065479A priority Critical patent/JP2002266434A/en
Publication of JP2002266434A publication Critical patent/JP2002266434A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method of constructing a cable dome eliminating the drawback with a conventional construction method: that it needs a number of timbering members to be installed on the surface of the ground, increasing the costs of materials, labor, and construction work. SOLUTION: The method of constructing a cable dome comprises a process for forming a dome roof on the surface of the ground; a process for erecting outer peripheral timbering members by erecting a small-diameter outer peripheral inner ring and a large-diameter outer peripheral outer ring at each of top ends radially disposed outside an inner peripheral ring; a process for providing a ring connector, with the inner ring rotatably connected to the rear end of the ring connector, and with the separated outer ring fixed to the front end of the ring connector; a process for lifting the dome roof to an erection height by pointing the front end of the ring connector inwards, connecting the outer ring to the inner peripheral ring using a suspension cable, and pointing the front end of the ring connector outward; and a process for connecting the inner peripheral ring to the inner ring by use of a retaining cable, while holding at the erection height the outer ring and the inner peripheral ring which are combined into the shape of an annulus with the divided portions of the outer ring connected to one another.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、球場等の大面積を
有する施設の上方を覆い、雨天等に関わらず内部で競技
等ができる空間を形成するようにしたドーム屋根工法に
係り、特に、トラス状骨組の開閉屋根の外周縁に配設さ
れた内周リングと外周リングから張設されたケーブルを
使用して支持しドーム屋根構造を作製するようにした、
ケーブルドーム施工法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a dome roof method for covering a large area such as a stadium and the like so as to form a space in which a game or the like can be performed inside regardless of rainy weather. The dome-shaped roof structure was supported by using a cable stretched from an inner ring and an outer ring arranged on the outer edge of the truss-shaped opening and closing roof,
Related to the cable dome construction method.

【0002】[0002]

【従来の技術】現在、雨天等に関わらず競技、イベント
等が開催できるように、球場等の大面積の施設(以下グ
ランド面という)の上方を覆い、雨天時においても競技
者、演奏者又は多数の観客が雨に濡れることなく、競技
等に集中できるようにしたドーム屋根の開発が進めら
れ、既に、各地にこのような施設が製作され使用されて
いる。このようなドーム屋根のうち、外周リングと内周
リングとの間に張設されたケーブルにより、グランド面
の上方を覆うようにしたドーム屋根(以下開閉屋根とい
う)を作製することが従来から行われている。
2. Description of the Related Art At present, a large area facility such as a stadium (hereinafter referred to as a ground surface) is covered so that a game or an event can be held regardless of rainy weather. The development of a dome roof that allows many spectators to concentrate on sports and the like without getting wet with rain has been promoted, and such facilities have already been manufactured and used in various places. Among such dome roofs, it has been conventionally practiced to manufacture a dome roof (hereinafter, referred to as an openable roof) that covers the ground surface with a cable stretched between an outer ring and an inner ring. Have been done.

【0003】図6は支保工を用いて開閉屋根をグランド
面の所定の高さに形成し、開閉屋根の外周縁に配設され
た内周リングと球場の外側に配設された外周リングとを
ケーブルで連結し、開閉屋根をグランド面の使用に支障
のない所定高さに支持するようにした従来のケーブルド
ーム施工法の一例を示す図である。このようなケーブル
ドーム施工法は、図6(b)に示す工法フローの手順に
沿って行われている。この工法フロー手順に示すよう
に、ケーブルドーム施工法においては、まず、グランド
面012の開閉屋根01を設ける位置、即ち、開閉屋根
01の骨格を形成するトラス状骨組03が架設されるグ
ランド面012上に支保工を立設する。
[0003] Fig. 6 shows an opening / closing roof formed at a predetermined height above the ground surface by using a shoring, and an inner ring provided on the outer peripheral edge of the opening / closing roof and an outer ring provided outside the stadium. FIG. 2 is a view showing an example of a conventional cable dome construction method in which the open / close roof is supported at a predetermined height that does not hinder the use of the ground surface. Such a cable dome construction method is performed according to the procedure of the construction method flow shown in FIG. As shown in the flow chart of the construction method, in the cable dome construction method, first, the position where the open / close roof 01 of the ground surface 012 is provided, that is, the ground surface 012 where the truss-like frame 03 forming the framework of the open / close roof 01 is erected. A shoring is erected on top.

【0004】即ち、このような開閉屋根01は、内周リ
ング02と内周リング02の周方向に等ピッチに一端が
固着され、他端を内周リング02の略中央に集合させ結
合した数十本のトラス状骨組03と、トラス状骨組03
の上方を被覆する図示省略した被覆材とからなり、しか
も、トラス状骨組03は内周リング02との接合部から
内周リング02の中央部にかけて高くされた円弧状の側
面形状にされ、例えば150kg/m2 〜200kg/
2 の重量のものにされ、開閉屋根01全体の重量は、
直径100mのもので約1200tonの大きさのもの
にされている。
[0004] That is, in such an openable roof 01, one end is fixed at an equal pitch in the circumferential direction of the inner peripheral ring 02 and the inner peripheral ring 02, and the other end is gathered and joined at substantially the center of the inner peripheral ring 02. Ten truss-shaped frames 03 and truss-shaped frames 03
The truss-shaped frame 03 is formed in a circular arc-shaped side surface that is raised from the joint with the inner peripheral ring 02 to the center of the inner peripheral ring 02, for example, 150 kg / m 2 to 200 kg /
are those of the weight of m 2, the weight of the entire opening and closing the roof 01,
It has a diameter of 100 m and a size of about 1200 tons.

【0005】従って、開閉屋根01をグランド面の所定
高さに設置するためには、図6(a)に示すように、内
周リング02下方および内周リング02の内側に等ピッ
チに配設される数十本の各トラス状骨組03の下方に、
これらの重量を支持できる少なくとも3本の支保工04
を設置する必要があり、さらに、円弧状側面形状にされ
ている各トラス状骨組03の下方に正確に配置され立設
される支保工04は、トラス状骨組03を支持する径方
向の位置で異る高さのものにする必要がある。
Therefore, in order to install the open / close roof 01 at a predetermined height on the ground surface, as shown in FIG. Below dozens of truss-like frames 03
At least three supporters 04 capable of supporting these weights
It is necessary to further install, and furthermore, the supporter 04 that is accurately arranged and erected below each truss-shaped frame 03 having an arcuate side shape is provided at a radial position that supports the truss-shaped frame 03. They need to be of different heights.

【0006】また、支保工04は開閉屋根01を支持す
るケーブル05の他端側を結合するための外周リングを
配設するために球場内の外側にも立設する必要がある。
しかも、この球場外に立設する支保工04は、グランド
面012上方に設置される開閉屋根01を支持するため
の2本のケーブル05の各一端を、それぞれ繋着するた
め等ピッチに配置される各トラス状骨組03の延長線外
周上に2本づつ立設するようにしている。
In addition, the supporter 04 needs to be erected outside the stadium in order to arrange an outer peripheral ring for connecting the other end of the cable 05 supporting the open / close roof 01.
In addition, the supporters 04 standing outside the stadium are arranged at equal pitches to connect one ends of the two cables 05 for supporting the open / close roof 01 installed above the ground surface 012. The two truss-shaped frames 03 are erected two by two on the outer circumference of the extension line.

【0007】なお、グランド面012及び球場外に立設
される支保工04は、一体のものではなく、所定長さの
モジュールを積上げて所定の高さにするようにしたもの
で、支保工04の立設に当っては上方に配置されるモジ
ュールをジャッキアップすることにより、その下方にモ
ジュールを挿入していくことにより、一モジュールづつ
ジャッキアップすることにより、所定高さの支保工04
を立設するようにしている。
[0007] The ground surface 012 and the supporter 04 standing outside the baseball stadium are not integrated, but are formed by stacking modules of a predetermined length to a predetermined height. In standing, the modules arranged above are jacked up, the modules are inserted below the jacks, and the modules are jacked up one by one, so that the support 04 having a predetermined height is
Is to be erected.

【0008】このように、支保工04がグランド面01
2上及び球場外に立設された後、グランド面012に立
設された支保工04のうち、最外周に配置されている支
保工04の頂端には、内周リング02を架設すると共
に、球場外に立設された2本の支保工04のうち、内周
側に立設された支保工04(以下内周側支保工という)
の頂端に外周インナーリング06を、また、外周側に立
設された支保工04(以下外周側支保工という)の頂端
に外周アウターリング07からなる外周リングをそれぞ
れ架設する。
As described above, the supporter 04 is connected to the ground surface 01.
After being erected on the ground surface 012 and above the ball ground 012, an inner peripheral ring 02 is erected at the top end of the erection work 04 arranged on the outermost periphery among the erection works 04 erected on the ground surface 012, Of the two supporters 04 standing outside the stadium, the supporter 04 standing on the inner peripheral side (hereinafter referred to as the inner peripheral side supporter)
And an outer peripheral ring made of an outer peripheral ring 07 is installed on the top end of a supporter 04 (hereinafter referred to as an outer peripheral supporter) erected on the outer peripheral side.

【0009】また、外周インナーリング06と外周アウ
ターリング07との間はリングコネクター08で連結さ
れており、予め定められた外周インナーリング06と外
周アウターリング07との高度差を含む相対変位が生じ
ないようにしている。このように、各リング02、0
6、07が各支保工04の頂端に配設された後、開閉屋
根01の架設が行われる。
The outer inner ring 06 and the outer outer ring 07 are connected by a ring connector 08, and a relative displacement including a predetermined height difference between the outer inner ring 06 and the outer outer ring 07 occurs. I try not to. Thus, each ring 02,0
After 6 and 07 are arranged at the top end of each supporter 04, the opening and closing roof 01 is erected.

【0010】なお、内周リング02、外周リングの各支
保工04頂端への架設は、説明の都合上、立設された支
保工04上へ架設する場合について述べたが、上述のよ
うにリング02、06、07がそれぞれ頂端に架設され
モジュール化された各支保工04を順次ジャッキアップ
して所定高さの支保工04を立設することもできる。即
ち、各リング02、06、07の各支保工04頂端への
配設は、地上に近い所に配置されている最上端に配置さ
れるモジュールの頂端に配設され、モジュールのジャッ
キアップと共に各リング02、06、07およびリング
コネクター08を所定高さ迄上昇させるようにすること
もできる。
The inner peripheral ring 02 and the outer peripheral ring are erected on the top end of each shoring 04 for convenience of explanation, but the case of erection on the erected shoring 04 has been described. 02, 06, and 07 are respectively installed at the top ends, and the modularized supporters 04 can be jacked up sequentially to set up the supporters 04 of a predetermined height. That is, the arrangement of each ring 02, 06, 07 at the top end of each supporter 04 is arranged at the top end of the module arranged at the uppermost end arranged close to the ground, and together with the jack-up of the module, The rings 02, 06, 07 and the ring connector 08 can be raised to a predetermined height.

【0011】但し、この場合は各リング02、06、0
7の周方向下方に配置されているモジュールを一斉にジ
ャッキアップして所定の高さにするための不具合、又は
ジャッキアップ力が大きくなる不具合がある反面、高所
での各リング02、06、07の架設作業がなくなり、
安全面の利点、および各リング02、06、07の取り
付け作業が容易になり、取付精度を向上できる利点が得
られる。
However, in this case, each ring 02, 06, 0
There is a problem in that the modules arranged at the lower part in the circumferential direction of jack 7 are simultaneously jacked up to a predetermined height, or there is a problem that the jack-up force is increased, but each ring 02, 06, 07 erection work disappeared,
An advantage in terms of safety and an advantage that mounting work of each of the rings 02, 06, and 07 is facilitated and mounting accuracy can be improved are obtained.

【0012】次に、所定高さに架設された、リング02
への開閉屋根01の架設は、地上のクレーン車09でト
ラス状骨組03を長手方向に切断したトラス状骨組ブロ
ック010を吊り上げて行われる。このため、トラス状
骨組ブロック010の長さは、リング02の中心から放
射状に配置され支保工04の隣接して立設されている支
保工04の頂端に両端が載置できる長さ以上のものにす
ることが好ましいが、クレーン車09の吊り上げ能力に
よっては、隣接して立設された支保工04の間隔より短
い長さに切断したものを吊り上げ、吊り上げ状態で内周
リング02側から順次つなぎ合せて、一端が内周リング
02に結合され、他端が内周リング02の略中央位置で
結合されて、内周リング02の略中央から放射状に架設
された数十本からなるトラス状骨組03による開閉屋根
01を形成することもできる。
Next, the ring 02 erected at a predetermined height is
The truss-like frame block 010 obtained by cutting the truss-like frame 03 in the longitudinal direction is lifted by a crane truck 09 on the ground. For this reason, the length of the truss-shaped frame block 010 is longer than the length at which both ends can be placed on the top end of the supporter 04 radiating from the center of the ring 02 and standing upright next to the supporter 04. However, depending on the lifting capacity of the crane car 09, the crane car 09, which is cut to a length shorter than the interval between the adjacent supporters 04, is lifted, and is sequentially connected from the inner peripheral ring 02 side in the lifting state. In addition, one end is connected to the inner peripheral ring 02, and the other end is connected at a substantially central position of the inner peripheral ring 02, and several tens of truss-like frames are radiated from substantially the center of the inner peripheral ring 02. 03 can also form the open / close roof 01.

【0013】グランド面012上の支保工04頂端へト
ラス状骨組03を架設して開閉屋根01を架設した後、
架設されたトラス状骨組03、内周リンク02等からな
る開閉屋根01を支持するためのケーブル05の架設を
行う。
After the truss-like frame 03 is erected on the top end of the supporter 04 on the ground surface 012 and the open / close roof 01 is erected,
The cable 05 for supporting the open / close roof 01 including the truss-like frame 03, the inner peripheral link 02, and the like is installed.

【0014】このケーブル05の架設は、トラス状骨組
01の一端が結合されている位置の内周リング02にケ
ーブル05の一端を連結すると共に、他端を外周アウタ
ーリング07および外周インナーリング06にそれぞれ
連結するようにした2本のケーブル05で、トラス状骨
組03がその内側に形成されている内周リング02、換
言すれば、開閉屋根01の各々の位置(高さ)に保持す
るようにしている。
The cable 05 is installed by connecting one end of the cable 05 to the inner ring 02 at a position where one end of the truss-like frame 01 is connected, and connecting the other end to the outer outer ring 07 and the outer inner ring 06. The truss-like frame 03 is held at the respective positions (heights) of the inner peripheral ring 02 formed inside the truss-like frame 03, in other words, the openable roof 01, by the two cables 05 which are connected to each other. ing.

【0015】これらのケーブル05のうち、内周リング
02と外周アウターリング07とを連結するケーブル0
5は、略々水平状態か、外周アウターリング07側をや
や高くして架設され開閉屋根01を重量を支持するよう
にしているが、内周リング02と外周インナーリング0
6とを連結するケーブル05は、外周インナーリング0
6側が低くなるように、例えば、内周リング02と外周
インナーリング06との間隔を約50mにした場合、外
周インナーリング06側が10m程度低くなるようにし
て、ケーブル05を架設し、開閉屋根01の吹上げに対
して抵抗する。
Of these cables 05, the cable 0 connecting the inner ring 02 and the outer ring 07
5 is installed in a substantially horizontal state or slightly elevated on the outer ring outer ring 07 side so as to support the weight of the open / close roof 01.
6 is connected to outer peripheral inner ring 0.
For example, when the interval between the inner peripheral ring 02 and the outer peripheral inner ring 06 is set to about 50 m so that the inner peripheral ring 06 is lower, the cable 05 is installed so that the outer peripheral inner ring 06 is lower by about 10 m, and the open / close roof 01 is opened. Resistance to blowing up.

【0016】このために、外周リングの架設時に外周イ
ンナーリング06と外周アウターリング07との間を連
結するようにしているリングコネクター08には、上述
のようにケーブル05の架設を行うことを考慮した傾斜
が設定されて、外周インナーリング06と外周アウター
リング07との頂端を連結するようにしている。逆に言
えば、外周インナーリング06を架設する支保工4(内
周側支保工)と外周アウターリング07を架設する支保
工(外周側支保工)との間には、リングコネクター08
の傾斜が設定できる高低差が設けられている。
For this reason, when the outer ring is installed, the ring connector 08 that connects the outer inner ring 06 and the outer outer ring 07 is connected to the cable 05 as described above. The inclination is set so as to connect the top ends of the outer peripheral inner ring 06 and the outer peripheral outer ring 07. Conversely, a ring connector 08 is provided between the support 4 (the inner support) on which the outer inner ring 06 is installed and the support (the outer support) on which the outer outer ring 07 is installed.
There is provided a height difference that can set the inclination of.

【0017】このように、グランド面012の上方に放
射状のトラス状骨組03が形成され、ケーブル05架設
で行われた後、各ケーブル05の張力調整が行われる。
このケーブル張力調整は、各ケーブル05に設けたロー
ドセル等により各ケーブル05の張力を計測することに
より、外周インナーリング06及び外周アウターリング
07に架設されている各ケーブル05の他端をドラムに
巻回するようにしている図示省略したウインチを駆動し
て、小さい張力のケーブル05はドラムに巻き込み、ま
た、大きい張力のケーブル05は巻き出すことにより、
各々設計で定められたケーブル張力の導入を図るように
している。
As described above, the radial truss-shaped frame 03 is formed above the ground plane 012, and after the cables 05 are erected, the tension of each cable 05 is adjusted.
This cable tension adjustment is performed by measuring the tension of each cable 05 using a load cell or the like provided on each cable 05, and winding the other end of each cable 05 bridged around the outer peripheral inner ring 06 and the outer peripheral ring 07 around a drum. By driving a winch (not shown) that is to be turned, the cable 05 with a small tension is wound around the drum, and the cable 05 with a large tension is unwound,
Each is designed to introduce the cable tension specified in the design.

【0018】逆に、このように設計で定められたケーブ
ル張力の導入を図ることにより、内周リング02、換言
すれば、放射状に配置されたトラス状骨組03等で形成
された開閉屋根01は、設計値通りの高さに、及び姿勢
にされてグランド面012の上方に設置されることにな
る。このように、内周リング02の外周側に一端が連結
された各ケーブル05の張力を導入した後、各ケーブル
05の他端を外周インナーリング06及び外周アウター
リング07に連結した後、外周インナーリング06を支
柱に連結し、支保工04に負荷されている荷重をこの支
柱に移し換える。
Conversely, by introducing the cable tension determined by the design in this way, the open / close roof 01 formed of the inner peripheral ring 02, in other words, the truss-like frame 03 arranged radially, etc. , At a height and a posture as designed, and installed above the ground plane 012. As described above, after the tension of each cable 05 whose one end is connected to the outer peripheral side of the inner peripheral ring 02 is introduced, the other end of each cable 05 is connected to the outer peripheral inner ring 06 and the outer peripheral ring 07, and then the outer peripheral inner ring 07 is connected. The ring 06 is connected to the support, and the load applied to the supporter 04 is transferred to the support.

【0019】この支柱は、図1に示すように球場外の支
保工04(外周側支保工)の外方から内方に向けて傾斜
させ、数本の支保工04毎に設けられた大径の支持柱7
と球場の外壁011の基端部から外方に向けて傾斜させ
て、上端が各支保工04の上端に連結された図示省略し
た小径の支持柱とからなる。また、外周アウターリング
07に負荷される張力は、リングコネクター08を介し
て外周インナーリング06に伝達されるので、このよう
な支柱を設けることなく、外周インナーリング06を支
柱で支持することにより、外周インナーリング06を支
持している支保工04に負荷されている荷重と共に、外
周アウターリング07を支持している支保工04に負荷
される荷重も支柱に負荷させることによりなくすること
ができる。
[0019] The struts from outside are inclined inwardly in 支保 Engineering 04 outside the stadium as shown in FIG. 1 (the outer peripheral side shoring), provided for several of 支保 Engineering 04 diameter Support pillar 7
And a small-diameter support column, not shown, which is inclined outward from the base end of the outer wall 011 of the stadium, and whose upper end is connected to the upper end of each supporter 04. Further, since the tension applied to the outer peripheral outer ring 07 is transmitted to the outer peripheral inner ring 06 via the ring connector 08, by supporting the outer peripheral inner ring 06 with the support without providing such a support, Along with the load applied to the supporter 04 supporting the outer peripheral inner ring 06, the load applied to the supporter 04 supporting the outer peripheral outer ring 07 can be eliminated by applying a load to the column.

【0020】このように、球場外に立設されている支保
工04に負荷される荷重を支柱に移し替えた後、支保工
04を撤去することにより球場の上方には、トラス状骨
組03からなる開閉屋根01を完成させ、その後トラス
状骨組03の上方に軽量スチール、膜材若しくは樹脂板
等からなる軽量の被覆材を密着させて設けることによ
り、開閉屋根01を製作することができる。
As described above, after the load applied to the supporter 04 standing outside the stadium is transferred to the column, the supporter 04 is removed, so that the truss-like frame 03 is placed above the stadium. The open / close roof 01 is completed, and then a light-weight covering material made of lightweight steel, a film material, a resin plate, or the like is provided in close contact with the upper part of the truss-like frame 03, whereby the open / close roof 01 can be manufactured.

【0021】しかしながら、このような工程で製作され
るケーブルドームは、製作工程において多数の支保工を
立設する必要があり、特に、グランド面012上に数十
本のトラス状骨組03の少くとも2倍以上の本数の支保
工を立設しなければならず、多数の支保工が必要とな
り、莫大な資材、労務、工費を要するという不具合があ
る。
However, the cable dome manufactured in such a process requires a large number of supports to be erected in the manufacturing process. In particular, at least a few tens of truss-shaped frames 03 on the ground surface 012 are required. More than twice as many supports need to be erected, requiring a large number of supports, and requiring a huge amount of materials, labor and construction costs.

【0022】また、既設の球場にこのようなケーブルド
ームを架設するときには、既設球場の補強、特に、多数
の支保工04を設置するためのグランド面012の補強
が必要となり、さらには、支保工04の設置により広範
囲にわたりグランド面012が著しく損傷し、その復旧
には多額の費用を必要とし、また、多数の支保工をグラ
ンド面012に立設し、さらには、ケーブルドームの完
成後にはこれら支保工を撤去する必要があり、グランド
面012が長期にわたり使用不能になるという不具合も
ある。
Further, when such a cable dome is erected on an existing ballpark, reinforcement of the existing ballpark, particularly reinforcement of the ground surface 012 for installing a large number of shorings 04, becomes necessary. The installation of No. 04 significantly damaged the ground plane 012 over a wide area and required a large amount of cost to recover it. Also, many supports were erected on the ground plane 012, and after the cable dome was completed, It is necessary to remove the shoring, and there is a problem that the ground plane 012 becomes unusable for a long time.

【0023】また、トラス状骨組03の組立、検査等に
は不安定な状態での高所作業が多くなるため、多大の落
下養生、安全施設を必要とする不具合があった。
In addition, in assembling and inspecting the truss-like frame 03, there are many problems of work at high places in an unstable state, so that there is a problem that a large amount of fall curing and safety facilities are required.

【0024】[0024]

【発明が解決しようとする課題】本発明は、従来のケー
ブルドーム施工法の不具合を解消するためグランド面に
設置する支保工を大巾に減少することができ、莫大な資
材、労務、工費を必要とすることなく、またグランド面
の支保工の減少及び支保工に負荷される荷重の低減もあ
って、グランド面の補強も大がかりのものにする必要が
なく、支保工の設置によるグランド面の損傷も少なく復
旧に要する費用も著しく低減でき、また工期が短縮でき
ることからグランド面の占有期間を短くでき、さらに
は、開閉屋根組立のための高所作業も殆んどなくなり、
作業安全上の装置、施設を殆んど必要としないケーブル
ドーム施工法を提供することを課題とする。
The present invention invention is to solve the above, the failure of conventional cable dome construction methods can be made to decrease by a large margin the 支保 factory to be installed in the ground surface to eliminate, enormous material, labor, the construction cost It is not necessary, and there is also a reduction in the support of the ground surface and a reduction in the load applied to the support.Therefore, it is not necessary to reinforce the ground surface. With little damage, the cost required for restoration can be significantly reduced, and the construction period can be shortened, so that the occupation period of the ground surface can be shortened.
An object of the present invention is to provide a method of constructing a cable dome which requires almost no equipment and facilities for work safety.

【0025】[0025]

【課題を解決するための手段】このため、第1番目の本
発明のケーブルドーム施工法は、次の手段を採用した。
Therefore, the first method of constructing a cable dome according to the present invention employs the following means.

【0026】(1)内周リングの外周に連結したケーブ
ル張力によりグランド面上方所定高さにドーム屋根を架
設するケーブルドーム施工法で、グランド面上で内周リ
ングを組立て、組立てた内周リング内中心からトラス状
骨組を放射状に配置してドーム屋根を形成する工程、
(2)内周リングの外側、具体的にはドーム屋根を形成
する既設球場の外壁の外側に、それぞれが間隔を設けて
放射状に配設され、各頂端に、内周リングより大径にさ
れた外周インナーリングと、外周インナーリングより大
径の外周アウターリングとからなる外周リングを架設す
る支保工をジャッキアップして立設する工程、(3)外
周インナーリングの軸心と直交する鉛直面内で回動でき
るように、基端部が外周インナーリングの外周から突出
された部材に枢着され、又は外周インナーリング外周に
回動自在に連結され、先端部が周方向に分断された外周
アウターリングに固定され、両端が各外周リングに連結
されたリングコネクターを設ける工程、(4)リングコ
ネクターを外周インナーリング外周まわりに回動させ、
先端部を内周リング側に向け、リングコネクターの先端
に連結された外周アウターリングと内周リングとを吊り
ケーブルで連結し、外周アウターリングに一端が連結さ
れて外周アウターリングよりも外側から牽引するように
している、牽引ケーブルに負荷される張力等によりリン
グコネクターを、反対側の内周リング外方向側に回動さ
せ、この回動によるリングコネクターの先端の鉛直面内
の動きにより、グランド面上のドーム屋根を架設高さま
で吊り上げる工程、(5)ドーム屋根を吊り上げ外周側
支保工頂端に載置された外周アウターリングの周方向の
分割部を連結することにより、円環状にされた外周アウ
ターリングと内周リングとを連結した吊りケーブルの張
力により、ドーム屋根を架設高さに保持するとともに、
内周リングと外周インナーリングとの間を風などによる
ドーム屋根の吹上げに対して抵抗する抑えケーブルで連
結する工程、(a)本発明のケーブルドーム施工法は、
上述(1)〜(5)の手段を採用したので、地上で組み
立てられたドーム屋根の吊り上げが、外周支保工頂端に
架設された外周インナーリング外周まわりに回動するリ
ングコネクターの回動で行なうことができ、ドーム屋根
を架設するために立設する支保工の本数を1/10以下
にでき、特に、グランド面に立設する支保工の本数を低
減することができ、資材、労務、工費を大幅に低減でき
るとともに、ドーム屋根の架設期間を短くできる。
(1) A cable dome construction method in which a dome roof is erected at a predetermined height above the ground plane by the tension of the cable connected to the outer circumference of the inner peripheral ring, and the inner peripheral ring is assembled on the ground plane by the cable dome construction method. A process of arranging truss-like frames radially from the inner center to form a dome roof,
(2) Radially arranged at intervals on the outside of the inner ring, specifically on the outer wall of the existing ballpark that forms the dome roof, and each top end has a larger diameter than the inner ring. Jacking up and erecting a supporting structure for erection of an outer ring composed of an outer ring and an outer ring having a larger diameter than the outer ring; (3) a vertical plane perpendicular to the axis of the outer ring; An outer periphery whose base end is pivotally connected to a member protruding from the outer periphery of the outer peripheral inner ring, or is rotatably connected to the outer periphery of the outer peripheral inner ring, and whose distal end is divided in the circumferential direction so that it can rotate inside. Providing a ring connector fixed to the outer ring and having both ends connected to the respective outer peripheral rings; (4) rotating the ring connector around the outer peripheral inner ring outer periphery;
With the distal end facing the inner ring, the outer ring connected to the end of the ring connector and the inner ring are connected by a suspension cable, and one end is connected to the outer ring to pull from the outer ring. The ring connector is turned to the outside of the inner ring on the opposite side by the tension or the like applied to the traction cable, and the movement of the tip of the ring connector in the vertical plane due to the rotation causes the ground to be grounded. (5) Lifting the dome roof on the surface to the erection height, (5) Lifting the dome roof, and connecting the circumferentially divided portions of the outer peripheral ring placed on the top end of the outer peripheral support to form an annular outer periphery With the tension of the suspension cable that connects the outer ring and the inner ring, the dome roof is held at the erected height,
A step of connecting between the inner ring and the outer inner ring with a restraining cable that resists blowing of the dome roof due to wind or the like; (a) the cable dome construction method of the present invention includes:
Since the above-mentioned means (1) to (5) are adopted, the dome roof assembled on the ground is lifted by the rotation of the ring connector that rotates around the outer periphery of the outer peripheral inner ring provided on the top end of the outer peripheral support. Can reduce the number of erections for erecting the dome roof to 1/10 or less. In particular, the number of erections erected on the ground surface can be reduced, and materials, labor, and construction costs can be reduced. And the erection period of the dome roof can be shortened.

【0027】また、ドーム屋根の製作時にグランド面に
立設する支保工の高さは低く、軽量のものにできるの
で、ドーム屋根の製作のためのグランド面の補強が低減
でき、更にはグランド面に生じる損傷を軽微なものにで
き、その復旧に要する費用を大幅に低減することが出来
る。さらに、ドーム屋根の製作が地上で行なわれ、支保
工上の高所でのトラス状骨組の組み立て作業がなくな
り、高所作業が大幅に低減でき高所作業に伴う安全上の
問題を少なくでき、安全確保のために要する費用を低減
できる。
[0027] Further, since the height of the erection on the ground surface at the time of manufacturing the dome roof is low and lightweight, the reinforcement of the ground surface for manufacturing the dome roof can be reduced, and further, the ground surface can be reduced. The damage that occurs in the vehicle can be made small, and the cost required for the recovery can be greatly reduced. In addition, production of the dome roof is carried out on the ground, there is no assembly work of the truss-like skeleton at heights on 支保 engineering, it is possible to reduce the aerial work is safety due to the aerial work can be significantly reduced problem, Costs required for ensuring safety can be reduced.

【0028】また、第2番目の本発明のケーブルドーム
施工法は、次の手段を採用した。
The second method of constructing a cable dome according to the present invention employs the following means.

【0029】(6)前述(1)と同様にドーム屋根を形
成する工程、(7)内周リングの外側に配設され、先端
部に高所に載置された外周アウターリングを固定し基端
部に外周インナーリングを頂端に配置されるモジュール
に固定し、外周アウターリングと外周インナーリングと
の架設高さから定まる傾斜にされたリングコネクターの
基端部を頂端に固定している内周側支保工をジャッキア
ップ等により立設する工程、(8)形成されたドーム屋
根の中央部を貫通させ、頂端部にタワークレーンが設置
された中央支保工を内周リングの中央部にジャッキアッ
プ等により立設する工程、(9)タワークレーンから吊
り下ろした昇降ケーブルの下端部を、ドーム屋根の中央
に設けた中央リング等の周方向数カ所に連結し、昇降ケ
ーブルの巻き上げでドーム屋根を架設高さまで吊り上げ
る工程、(10)吊り上げたドーム屋根を外周アウター
リングと内周リングとの間を連結する吊りケーブルの張
力により架設高さに保持するとともに、内周リングと外
周インナーリングとの間を抑えケーブルで連結する工
程、(b)本発明のケーブルドーム施工法は、上述
(6)〜(10)の手段を採用したので、実施の第1形
態に比較してグランド面上にドーム屋根を設置する高さ
の中央支保工を1本設ける必要があるが、既設球場に設
ける外周支保工の本数は約1/2にでき、さらに低減で
きるので支保工の立設に要する資材、労務、工費をさら
に低減できる。また、グランド面には中央支保工を1本
設けるためのグランド面の補強、及びグランド面に生じ
る損傷は狭い範囲に限られ、それに要する費用及び修復
作業は軽減なものにできる。
(6) A step of forming a dome roof in the same manner as in the above (1), (7) An outer peripheral ring which is disposed outside the inner peripheral ring and is mounted at a high end at a tip end is fixed. An inner circumference in which the outer peripheral inner ring is fixed to the module arranged at the top end at the end, and the base end of the inclined ring connector determined by the height of the outer outer ring and the outer peripheral inner ring is fixed to the top end. Jacking up the side shoring by jacking up, etc. (8) Penetrating the center of the formed dome roof and jacking up the center shoring with the tower crane at the top end to the center of the inner ring (9) Connect the lower end of the lifting cable suspended from the tower crane to several places in the circumferential direction such as the center ring provided at the center of the dome roof, and wind up the lifting cable Lifting the dome roof to the erected height, (10) maintaining the dome roof at the erected height by the tension of a suspension cable connecting the outer peripheral ring and the inner peripheral ring, and maintaining the inner peripheral ring and the outer peripheral ring (B) The cable dome construction method of the present invention employs the above-described means (6) to (10). It is necessary to provide one central supporter at the height to install the dome roof in the area, but the number of outer peripheral supports provided at the existing stadium can be reduced to about 1/2, and it can be further reduced, so the materials required for erecting the supporter , Labor and construction costs can be further reduced. In addition, reinforcement of the ground surface for providing one center support on the ground surface, and damage to the ground surface are limited to a narrow range, and the cost and repair work required for it can be reduced.

【0030】さらに、外周側支保工上での分割された外
周アウターリングの接合作業が不要になり、高所作業を
低減でき安全上の問題を少なくでき、また、これらの作
業に要する装置費用を低減することができる。
Further, the joining work of the divided outer outer ring on the outer peripheral side support work becomes unnecessary, work at high places can be reduced, safety problems can be reduced, and the equipment cost required for these works can be reduced. Can be reduced.

【0031】また、第3番目の本発明のケーブルドーム
施工法は、次の手段を採用した。
The third method of constructing a cable dome according to the present invention employs the following means.

【0032】(11)前述(1)と同様にドーム屋根を
形成する工程、(12)前述(7)と同様に内周側支保
工を立設する工程、(13)グランド面上の内周リング
と立設された内周側支保工頂端に基端部が固定されてい
るリングコネクターの頂端部に固定した外周アウターリ
ングとを吊りケーブルで連結する工程、(14)地上で
組み立てられたドーム屋根の中央部に頂端部を当接させ
て、ドーム屋根を架設高さまでジャッキアップすること
により、中央支保工を内周リングの中央部に立設する工
程、(15)吊り上げたドーム屋根を架設高さに保持す
るとともに、内周リングと外周アウターリングとの間及
び内周リングと外周インナーリングとの間を連結してい
るドーム屋根重量を支持する吊りケーブル及び風などの
吹上げに対して抵抗する抑えケーブルに張力を導入する
工程、(c)本発明のケーブルドーム施工法は、上述
(11)〜(15)の手段を採用したので、実施の第1
形態、第2形態に比較して、ドーム屋根を架設高さへ上
昇させるときのドーム屋根の安定性が吊りケーブル及び
抑えケーブルにより保持でき、特別の装置を必要とする
ことなく、安定したドーム屋根の吊り上げができるよう
になる。
(11) A step of forming a dome roof in the same manner as in (1) above, (12) A step of erecting an inner peripheral side support in the same manner as in (7) above, and (13) an inner periphery on the ground plane. A step of connecting the ring and an outer peripheral ring fixed to the top end of a ring connector whose base end is fixed to the top end of the standing inner peripheral side support with a suspension cable, (14) a dome assembled on the ground The step of erecting the center support at the center of the inner peripheral ring by bringing the top end into contact with the center of the roof and jacking up the dome roof to the erection height. (15) Erecting the suspended dome roof Suspended cables supporting the weight of the dome roof connecting between the inner ring and the outer ring and between the inner ring and the outer ring, Usually Introducing tension to suppress cable, (c) cable dome construction methods of the present invention, described above (11) Since it employs the ~ (15), the first embodiment
As compared with the second embodiment, the stability of the dome roof when the dome roof is raised to the erection height can be held by the suspension cable and the holding cable, and the dome roof is stable without requiring any special device. Can be lifted.

【0033】また、第4番目の本発明のケーブルドーム
施工法は、次の手段を採用した。
The fourth method for constructing a cable dome according to the present invention employs the following means.

【0034】(16)前述(1)と同様にドーム屋根を
形成する工程、(17)前述(7)と同様に内周側支保
工を立設する工程、(18)地上で組み立てられた内周
リングの下方の周方向に等ピッチで配置され、地上で組
み立てられた内周リングの内部にトラス状骨組みを組み
立てたドーム屋根を、架設高さ以上の高さまでジャッキ
アップするリング支保工を立設する工程、(19)吊り
上げたドーム屋根の内周リングと外周インナーリングと
を吊りケーブルで連結及び抑えケーブルで連結する工
程、(20)架設高さ以上に吊り上げたドーム屋根を架
設高さまで降下させて、吊りケーブルに張力を導入し、
吊りケーブルへの張力導入とは別に風などの吹上げに対
して抵抗する抑えケーブルに張力を導入する工程、
(d)本発明のケーブルドーム施工法は、上述(16)
〜(20)の手段を採用したので、実施の第1形態、第
2形態、第3形態に比較して、架設高さ以上に吊り上げ
られたドーム屋根を、架設高さまで降下させて吊りケー
ブルに張力を導入するとともに、吊りケーブルへの張力
導入とは別に、風などの吹上げに対して抵抗する抑えケ
ーブルに張力を導入するようにしたので、吊りケーブル
に導入される張力及び抑えケーブルに導入される張力
が、ドーム屋根を安定して保持できるとともに、強風の
ときでもドーム屋根の吹上に対して抵抗し、グランド面
上に安定的にドーム屋根を架設できる。
(16) A step of forming a dome roof in the same manner as in (1) above, (17) A step of erecting the inner peripheral support in the same manner as in (7) above, and (18) an inner part assembled on the ground. A ring supporter is installed that jacks up the dome roof, which is arranged at equal pitches in the circumferential direction below the circumferential ring and has a truss-like frame assembled inside the inner circumferential ring assembled on the ground, to a height equal to or higher than the installation height. (19) A step of connecting the inner ring and the outer ring of the suspended dome roof with a suspension cable and connecting them with a restraining cable, (20) Lowering the dome roof suspended above the erection height to the erection height To introduce tension into the suspension cable,
The process of introducing tension to the restraining cable, which resists blowing up such as wind, separately from the introduction of tension to the suspension cable,
(D) The cable dome construction method of the present invention is as described in (16) above.
Since the means of (20) to (20) are employed, the dome roof suspended above the erection height is lowered to the erection height to form a suspension cable as compared with the first, second, and third embodiments. In addition to introducing tension into the suspension cable, separately from introducing tension into the suspension cable, tension is introduced into the suppression cable that resists blowing up, such as wind. The applied tension can stably hold the dome roof, resists the blowing of the dome roof even in a strong wind, and stably build the dome roof on the ground surface.

【0035】また、第5番目の本発明のケーブルドーム
施工法は、次の手段を採用した。
The fifth method of constructing a cable dome according to the present invention employs the following means.

【0036】(21)前述(4)、(9)、(14)の
何れかの工程と同様にして、ドーム屋根を架設高さまで
吊り上げる工程が、前述(18)の工程と同様のドーム
屋根を架設高さ以上にまで吊り上げる工程にされ、架設
高さ以上に吊り上げたドーム屋根の内周リングと外周ア
ウターリング及び外周インナーリングとを、前述
(5)、(10)、(15)の何れかの工程と同様にし
て、吊りケーブル及び抑えケーブルで連結し又は張力を
導入した後、前述(20)の工程と同様にして架設高さ
以上から架設高さまで降下させ、ドーム屋根の荷重で生
じる吊りケーブルの張力により、ドーム屋根を架設高さ
に保持するとともに、風などの吹上げに対して抵抗する
抑えケーブルに張力を導入する工程。
(21) In the same manner as in any of the above-mentioned steps (4), (9), and (14), the step of lifting the dome roof to the erection height includes the same dome roof as the step (18). In the step of lifting the dome roof to a height equal to or higher than the erection height, the inner ring, the outer ring, and the outer ring of the dome roof suspended above the erection height may be any one of the above (5), (10), and (15). in the same manner as the step, after introducing the ligated or tension hanging cables and suppressing cable, is lowered until erection height from above (20) of the step and the above construction height in the same manner, hanging occurs in load of the dome roof The process of maintaining the dome roof at the erection height by the tension of the cable, and introducing tension to the restraining cable that resists the blowing up of wind and the like.

【0037】(e)本発明のケーブルドーム施工法は、
上述(21)の手段を採用したので、実施の第1形態、
第2形態、第3形態の作用、効果に加えて、上述(d)
と同様の作用、効果が得られるものにできる。
(E) The cable dome construction method of the present invention
Since the above-mentioned means (21) is adopted, the first embodiment,
In addition to the actions and effects of the second and third embodiments, the above (d)
The same operation and effect as those described above can be obtained.

【0038】[0038]

【発明の実施の形態】以下、本発明のケーブルドーム施
工法の実施の形態を図面にもとづき説明する。なお、図
において図6に示す部材と同一若しくは類似の部材に
は、同一符号を付して詳細説明は省略すると共に、実施
の各形態とも既設のグランド面の上方に開閉屋根を架設
する場合について、説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the method for constructing a cable dome according to the present invention will be described below with reference to the drawings. In the drawings, the same or similar members as those shown in FIG. 6 are denoted by the same reference numerals, and detailed description thereof will be omitted. In each of the embodiments, a case in which an opening / closing roof is installed above an existing ground surface will be described. ,explain.

【0039】図1は本発明のケーブルドーム施工法の実
施の第1形態を示す図で、グランド面012を取り囲み
外周に外壁011を立設すると共に、外壁011の頂端
からグランド面012上方に向けて屋根1を設け、また
グランド面012に向けてスタンド2を形成した既設球
場・既設スタジアム3(以下既設球場という)のグラン
ド面012の上方にトラス状骨組03で開閉屋根01を
設けるようにしたものである。
FIG. 1 is a view showing a first embodiment of a cable dome construction method according to the present invention. An outer wall 011 is provided around an outer periphery of a ground surface 012, and is directed upward from the top end of the outer wall 011 to the ground surface 012. The roof 1 is provided, and the open / close roof 01 is provided with a truss-like frame 03 above the ground surface 012 of an existing stadium / existing stadium 3 (hereinafter referred to as an existing stadium) in which the stand 2 is formed toward the ground surface 012. Things.

【0040】まず、図1(a)に示すようにグランド面
012上で内周リング02を組み立てると共に、外壁0
11の外側には内周側支保工5および外周側支保工4を
立設する。また、この外周側支保工4の頂端には、周方
向に配置されるトラス状骨組03と同数に分割され、こ
の分割部を連結したときには円環状に形成することので
きる外周アウターリング07が設けられ、この分割され
た外周アウターリング07毎に一端が連結され、略屋根
1の張出し量と略同一の長さにされたリングコネクター
内周側支保工5の頂端には、円環状の外周インナーリン
グ06が設けられている。
First, as shown in FIG. 1A, the inner peripheral ring 02 is assembled on the ground surface
An inner support 5 and an outer support 4 are erected outside the outer periphery 11. Further, at the top end of the outer peripheral side support 4, an outer peripheral outer ring 07 which is divided into the same number as the truss-shaped frames 03 arranged in the circumferential direction and which can be formed in an annular shape when these divided portions are connected is provided. One end is connected to each of the divided outer outer rings 07, and a ring connector inner peripheral side support 5 having a length substantially equal to the amount of overhang of the roof 1 is provided at the top end of an annular outer inner ring. A ring 06 is provided.

【0041】外周アウターリング07に一端が連結され
たリングコネクター08は外周インナーリング06に固
定された金具に枢支ピンで他端部が枢着され、鉛直面内
で外周アウターリング07を回動できるようにして、外
周インナーリング06に連結されている。なお、外周イ
ンナーリング06も外周アウターリング07と同様に周
方向に分割して、各分割片を内周側支保工5の頂端に回
動自在に取り付けるようにすれば、リングコネクター0
8の他端側も外周インナーリング06外周に固着取付け
るようにすることができる。
The other end of the ring connector 08, one end of which is connected to the outer peripheral ring 07, is pivotally connected to a bracket fixed to the outer peripheral ring 06 with a pivot pin, and the outer peripheral ring 07 is rotated in a vertical plane. It is connected to the outer peripheral inner ring 06 as much as possible. The outer peripheral inner ring 06 is also divided in the circumferential direction in the same manner as the outer peripheral ring 07, and each divided piece is rotatably attached to the top end of the inner peripheral side support 5.
8 can also be fixedly attached to the outer periphery of the outer peripheral inner ring 06.

【0042】次に、図1(b)に示すように、載置した
外周側支保工4及び外周インナーリング06を頂端に連
結した内周側支保工5を順次ジャッキアップして、外周
アウターリング07の分割片を頂端に各支保工4、5を
構成するモジュールを次ぎ足して、外周側支保工4及び
内周側支保工5の背高を大きくすると共に、外周インナ
ーリング06の外周まわりの鉛直面内で回動できるよう
にした、リングコネクター08の回動が外壁012に邪
魔されない背高にまで内周側支保工5が高くされた時点
で、リングコネクター08を外周インナーリング06外
周まわりに回動させる。
Next, as shown in FIG. 1 (b), the placed outer peripheral support 4 and the inner peripheral support 5 having the outer inner ring 06 connected to the top end are sequentially jacked up to form an outer outer ring. In addition to increasing the height of the outer peripheral side support 4 and the inner peripheral side support 5 by adding a module constituting each of the supports 4 and 5 to the top end of the divided piece 07, the outer periphery of the outer peripheral inner ring 06 is increased. When the inner peripheral side support 5 is raised to a height that does not hinder the rotation of the ring connector 08 from being obstructed by the outer wall 012, the ring connector 08 is rotated around the outer periphery of the inner ring 06. To rotate.

【0043】これにより、リングコネクター08の一端
側に連結され、分割された外周アウターリング07は、
外周インナーリング06の内側、屋根1の上方に位置す
るようになり、外壁011の上方に設けた屋根1に邪魔
されずに吊りケーブル6により、内周リング02と分割
された外周アウターリング07とが連結できるようにな
る。また、外周側支保工4、内周側支保工5の背高を高
める作業と並行して、内周リング02の内部にはトラス
状骨組03を使用して開閉屋根01を形成するようにし
ている。
As a result, the outer peripheral ring 07 connected to one end of the ring connector 08 and divided into
The inner peripheral ring 02 is separated from the inner peripheral ring 02 by the suspension cable 6 without being obstructed by the roof 1 provided above the outer wall 011. Can be connected. Also, in parallel with the operation of increasing the height of the outer peripheral support 4 and the inner peripheral support 5, the open / close roof 01 is formed using a truss-like frame 03 inside the inner peripheral ring 02. I have.

【0044】この開閉屋根01の製作に当っては、内周
リング02の下方に支保工4のモジュールを配置して内
周リング02の高さを若干高くすることにより開閉屋根
01の製作作業を容易にすると共に、より低い位置に配
置された外周アウターリング07でも屋根1と干渉する
ことなく吊りケーブル6で内周リング02と連結するこ
とができるようになる。
In the manufacture of the open / close roof 01, the module of the support 4 is arranged below the inner peripheral ring 02 so that the height of the inner peripheral ring 02 is slightly increased, so that the work of manufacturing the open / close roof 01 can be performed. At the same time, the outer peripheral ring 07 arranged at a lower position can be connected to the inner peripheral ring 02 by the suspension cable 6 without interfering with the roof 1.

【0045】さらに、地上で製作される開閉屋根01の
中央には、数段のモジュールを積み上げて、トラス状骨
組03の一端側を載置できるようにし、作業時の開閉屋
根01の形状を設計値通りに製作し易くしている。
Further, several stages of modules are stacked at the center of the open / close roof 01 manufactured on the ground so that one end of the truss-like frame 03 can be placed thereon, and the shape of the open / close roof 01 during operation is designed. It is easy to manufacture according to value.

【0046】しかしながら、図1(b)より明らかなよ
うに内周リング02の下方および内周リング02の中央
に設置するモジュール(支保工)04は、図6(a)に
示すような高さのものにする必要はなく、低いものでも
良い。
However, as apparent from FIG. 1B, the module (support) 04 installed below the inner peripheral ring 02 and at the center of the inner peripheral ring 02 has a height as shown in FIG. It does not need to be made, but may be low.

【0047】図1(b)の状態で一端が外周アウターリ
ング07の分割片に連結された牽引ケーブル16をウイ
ンチ等を使用して外側へ牽引することにより、図1
(c)に示すように開閉屋根01はグランド面012上
方の所要の高さにリフトアップされ、しかも外周アウタ
ーリング07は再び外周側支保工4頂端に載置される。
この状態で分割されていた外周アウターリング07の分
割部を接合し、内周リング02と外周インナーリング0
6とを連結固定することにより、開閉屋根01は内周リ
ング02と外周アウターリング07とを連結している吊
りケーブル6の張力により所要高さに保持することがで
きる。
In the state shown in FIG. 1 (b), the pulling cable 16 having one end connected to the divided piece of the outer ring 07 is pulled outward by using a winch or the like.
As shown in (c), the open / close roof 01 is lifted up to a required height above the ground surface 012, and the outer peripheral outer ring 07 is again placed on the top end of the outer peripheral support 4.
In this state, the divided portions of the outer ring outer ring 07 that have been split are joined to form the inner ring 02 and the outer ring 0.
6, the open / close roof 01 can be held at a required height by the tension of the suspension cable 6 connecting the inner peripheral ring 02 and the outer peripheral ring 07.

【0048】この後、従来の施工法で述べたように、内
周リング02の周方向に等ピッチに張設された吊りケー
ブル6の張力を調整し、外周インナーリング06まわり
に回動自在にされているリングコネクター08を外周イ
ンナーリング06に固定した後、図1(d)に示すよう
に、外周インナーリング06と内周リング02とを抑え
ケーブル8で連結した後、内周側支保工5で支持されて
いる外周インナーリング06を支持柱7に連結すること
により、外周側支保工4および内周側支保工5で支持さ
れている外周アウターリング07及び外周インナーリン
グ06に負荷されている荷重はこの支持柱7に移し換え
られ、これ迄荷重が負荷されていたこれらの支保工4、
5を撤去することにより、ケーブルドーム屋根を製作す
ることができる。
Thereafter, as described in the conventional construction method, the tension of the suspension cables 6 stretched at equal pitches in the circumferential direction of the inner peripheral ring 02 is adjusted, and the suspension cables 6 are rotatable about the outer peripheral inner ring 06. After fixing the ring connector 08 to the outer peripheral inner ring 06, as shown in FIG. 1D, the outer peripheral inner ring 06 and the inner peripheral ring 02 are connected by the cable 8, and then the inner peripheral side by the outer circumference inner ring 06 which is supported for coupling to the support column 7 by 5, is loaded on the outer peripheral outer ring 07 and the outer inner ring 06 is supported on the outer peripheral side 支保 Engineering 4 and the inner peripheral side 支保 Engineering 5 The existing load is transferred to this support column 7, and these supports 4,
By removing 5, the cable dome roof can be manufactured.

【0049】本実施の形態のケーブルドーム施工法で
は、上述の手段を採用しているが、立設する支保工04
は1/10減となり、しかもグランド面012に設ける
支保工04は短いもので良いため、グランド面012の
損傷を最小限にすることができる。従って、背高の大き
い支保工04のグランド面012への立設が殆んど不要
になり、これに要する資材、労務、工費を少くでき、さ
らにはグランド面012損傷補修に要する費用を大幅に
低減することができる。
In the cable dome construction method of the present embodiment, the above-mentioned means is adopted.
Is reduced by 1/10, and the supporter 04 provided on the ground plane 012 may be short, so that damage to the ground plane 012 can be minimized. Therefore, it is almost unnecessary to erection of the tall supporter 04 on the ground surface 012, and the necessary materials, labor and construction costs can be reduced, and the cost required for repairing the ground surface 012 damage is greatly reduced. Can be reduced.

【0050】また、グランド面012への支保工04の
立設が不要になるので、グランド面012の使用不能期
間を短くできると共に、従来行われていた背高の大きい
支保工04上でのトラス状骨組03の形成のための作業
がなくなり、外周側支保工4での外周アウターリング0
7の接続作業だけで済むため、高所作業を少くでき、安
全上の問題が低減し、安全上必要としていた装置を簡素
なものにすることができる。
Further, since it is not necessary to provide the supporter 04 on the ground plane 012, the period during which the ground plane 012 cannot be used can be shortened. The work for forming the frame-shaped frame 03 is eliminated, and the outer peripheral outer ring 0
Since only the connection work of 7 is required, work at a high place can be reduced, safety problems can be reduced, and a device required for safety can be simplified.

【0051】次に、図2は本発明のケーブルドーム施工
法の実施の第2形態を示す図で、本実施の形態のケーブ
ルドーム施工法では、図2(a)に示すグランド面01
2上で製作された内周リング02の略中央に、図2
(b)に示すように開閉屋根01を設置する高さの背高
にされた中央支保工9を立設し、中央支保工9の頂端に
設置されたタワークレーン10で地上で製作された開閉
屋根01を設置高さまで吊り上げるグランド面012上
方に架設するようにしている。
Next, FIG. 2 shows a second embodiment of the cable dome construction method of the present invention. In the cable dome construction method of the present embodiment, the ground plane 01 shown in FIG.
2 at the approximate center of the inner ring 02 manufactured on FIG.
(B) As shown in (b), a tall central supporter 9 erected to the height at which the opening / closing roof 01 is installed is erected, and an opening / closing manufactured on the ground by a tower crane 10 installed at the top end of the central supporter 9. The roof 01 is erected above the ground plane 012 which is suspended to the installation height.

【0052】また、外周側支保工4の背高は、外周側ア
ウターリング07と外周側インナーリング06とを両端
に連結固定したリングコネクター08が、開閉屋根01
を所定高さに支持、保持するときの傾斜にできる高さに
され、このリングコネクター08の傾斜角を保持したま
ま、換言すれば、リングコネクター08の下端が内周側
支保工5の頂端に固定された状態で、図2(b)に示す
ように、外周インナーリング06を頂端に連結した内周
側支保工5を、ジャッキアップして順次モジュールを次
ぎ足し背高を、開閉屋根01を所定高さにし、吊りケー
ブル6及び抑えケーブル8で支持できる高さにする。
The height of the outer peripheral support 4 is such that a ring connector 08 in which an outer peripheral outer ring 07 and an outer peripheral inner ring 06 are connected and fixed to both ends is provided with an opening / closing roof 01.
Is held at a predetermined height so that it can be inclined when holding and holding the ring connector 08, in other words, the lower end of the ring connector 08 is at the top end of the inner peripheral support 5. In the fixed state, as shown in FIG. 2 (b), the inner peripheral side support 5 connected to the top end with the outer peripheral inner ring 06 is jacked up, modules are sequentially added, and the height is increased. The height is set to a predetermined height so that the suspension cable 6 and the holding cable 8 can support the height.

【0053】一方、内周側支保工5のジャッキアップと
共に内周リング02の中央では中央支保工9が、同様に
ジャッキアップして開閉屋根01を架設する高さにま
で、モジュールを次ぎ足して立設した後、中央支保工9
の頂部に複数のタワークレーン10を設置すると共に、
内周リング02の内側では開閉屋根01の組み立てが行
われる。この地上で組み立てられる開閉屋根01の中央
部には、前述した中央支保工8が通過できる大きさの穴
を設けた中央リングが設けられており、開閉屋根01の
中央から放射状に配置される数十本のトラス状骨組03
の一端は、内周リング02に結合されると共に、他端は
この中央リングに結合されて、トラス状骨組03からな
る開閉屋根01が形成される。
On the other hand, the center supporter 9 at the center of the inner peripheral ring 02 together with the jacking-up of the inner peripheral side supporter 5 adds the module to the same height as the jacking up and the opening and closing roof 01 is erected. After erecting, central support 9
While installing a plurality of tower cranes 10 on the top of
Inside the inner ring 02, the opening and closing roof 01 is assembled. At the center of the roof 01 assembled on the ground, there is provided a center ring provided with a hole large enough to allow the above-described center support 8 to pass therethrough. Ten truss-shaped frames 03
Is connected to the inner ring 02 and the other end is connected to the central ring to form an open / close roof 01 composed of a truss-like frame 03.

【0054】次いで、図2(c)に示すように、タワー
クレーン10から複数本の昇降ケーブル11を吊り降
し、昇降ケーブル11の下端を前述した中央リング等に
連結した後、タワークレーン10を駆動して昇降ケーブ
ル11を巻き込むことにより、地上で製作された内周リ
ング02および開閉屋根01は、一括して架設高さにま
で上昇させることができる。この内周リング02および
開閉屋根01を上昇させるとき、姿勢バランスを保持す
るため内周リング02の周方向から少くとも3本以上の
仮設ケーブル12を吊り下げ、この仮設ケーブル12の
張力を制御することにより開閉屋根01のレベル調整を
行いながら中央支保工9の頂部まで開閉屋根01を上昇
させる。
Next, as shown in FIG. 2 (c), a plurality of lifting cables 11 are suspended from the tower crane 10, and the lower ends of the lifting cables 11 are connected to the above-mentioned center ring or the like. By driving and raising and lowering the cable 11, the inner peripheral ring 02 and the open / close roof 01 manufactured on the ground can be raised to the erected height in a lump. When the inner ring 02 and the opening / closing roof 01 are raised, at least three or more temporary cables 12 are suspended from the circumferential direction of the inner ring 02 to maintain a posture balance, and the tension of the temporary cable 12 is controlled. Thus, the level of the opening and closing roof 01 is raised to the top of the center support 9 while the level of the opening and closing roof 01 is adjusted.

【0055】開閉屋根01が中央支保工9の頂部に達し
た時点で、内周リング02と先に立設された内周側支保
工5の頂端にリングコネクター08を介して固定されて
いる外周アウターリング07とを吊りケーブル6で連結
すると共に、内周リング02と外周インナーリング06
とを抑えケーブル8で連結する。
When the open / close roof 01 reaches the top of the central support 9, the outer periphery fixed to the inner peripheral ring 02 and the top end of the inner peripheral support 5 erected via the ring connector 08. The outer ring 07 is connected with the suspension cable 6, and the inner peripheral ring 02 and the outer peripheral inner ring 06 are connected.
And connect them with the cable 8.

【0056】次いで、内周リング02から等間隔に外方
へ架設された吊りケーブル6、抑えケーブル8の張力調
整を行った後、外周インナーリング06に支持柱7を連
結した後、中央支保工9および内周側支保工5を撤去す
ることにより、図2(d)に示すようにグランド面01
2上の所定の高さ、具体的にはグランド面上で行われる
イベントに支障のない高さに開閉屋根01を設置するこ
とができる。
Next, after adjusting the tension of the suspension cable 6 and the holding cable 8 laid outward at equal intervals from the inner peripheral ring 02, the support column 7 is connected to the outer peripheral inner ring 06, and the center support By removing the inner support 9 and the inner peripheral support 5, as shown in FIG.
2, the roof 01 can be installed at a predetermined height on the ground 2, specifically, a height that does not hinder an event to be performed on the ground surface.

【0057】本実施の形態のケーブルドーム施工法で
は、上述の手段を採用することによりグランド面012
上に開閉屋根01を設置する高さの中央支保工9を1本
設ける必要があるが、外周側支保工4の設置が背高の低
いもので良くなり、実施の第1形態に比べて支保工04
の数をさらに低減できる利点があり、支保工04の立設
に要する資材、労務、工費をさらに少なくすることがで
きる。
In the cable dome construction method of the present embodiment, the ground plane 012 is formed by employing the above-described means.
Although it is necessary to provide one central supporter 9 at the height where the open / close roof 01 is installed, the outer peripheral supporter 4 can be installed with a shorter height, and the supporter can be supported as compared with the first embodiment. Engineering 04
Therefore, the number of materials, labor, and construction costs required for erecting the shoring work 04 can be further reduced.

【0058】また、中央支保工9の立設で損傷したグラ
ンド面012の補修は必要となるものの、補修区画は狭
い範囲に限られ、従来の損傷補修に要する費用を実施の
第1形態と同様に大幅に低減できる。また、施工時間が
短くなるためにグランド面の使用不能期間を短縮化でき
ると共に、トラス状骨組03、外周インナーリング06
が地上で完全なものにできるばかりでなく、実施の第1
形態では施工上の都合から地上では分割して製作し、開
閉屋根01の吊り上げた後、外周側支保工4で連結する
必要のあった外周アウターリング07は地上で完全な形
状に製作できるので、高所作業をより少くすることがで
き、安全対策の面から秀れたものとなる。
Although the ground surface 012 damaged by the erecting of the central support 9 needs to be repaired, the repair section is limited to a narrow area, and the cost required for the conventional damage repair is the same as in the first embodiment. Can be greatly reduced. In addition, since the construction time is shortened, the period during which the ground surface cannot be used can be shortened.
Is not only complete on the ground, but also the first
In the form, it is divided on the ground from the convenience of construction, and it is manufactured separately. After the open / close roof 01 is lifted, the outer peripheral ring 07 which needs to be connected by the outer peripheral support 4 can be manufactured in a complete shape on the ground. The work at high places can be reduced, which is excellent in terms of safety measures.

【0059】さらに、開閉屋根01の吊り上げ時の姿勢
制御がグランド面012上に内周リング02から吊り下
げられている仮設ケーブル12で行え、バランス制御の
ための特別の装置を必要としない利点がある。
Further, the posture control when lifting the open / close roof 01 can be performed by the temporary cable 12 suspended from the inner peripheral ring 02 on the ground plane 012, and there is an advantage that no special device for balance control is required. is there.

【0060】次に、図3は本発明のケーブルドーム施工
法の実施の第3形態を示す図で、開閉屋根01中心部に
立設する中央支保工13のジャッキアップで内周リング
02、開閉屋根01を所定の高さに上昇させると共に、
地上で製作された時点から内周リング02と外周アウタ
ーリング07、外周インナーリング06とそれぞれ連結
している吊りケーブル6、抑えケーブル8によって開閉
屋根01を上昇させるときのバランスを取るようにした
ものである。
Next, FIG. 3 is a diagram showing a third embodiment of the cable dome construction methods of the present invention, the inner peripheral ring 02 with the jack-up of the central 支保 Engineering 13 erected to open and close the roof 01 central opening While raising the roof 01 to a predetermined height,
From the time of production on the ground, the suspension ring 6 connected to the inner ring 02 and the outer ring 07, the outer ring 06 and the suspension cable 6 connected to the outer ring 06, and the holding cable 8 are used to balance the lifting of the open / close roof 01. It is.

【0061】図3(a)に示すように、グランド面01
2上で製作された内周リングの略中央に、図3(b)に
示すように開閉屋根01の形状に合わせた高さの中央支
保工13を立設する。この高さはあまり高いものではな
いので、3個程度のモジュールを積み重ねることにより
形成することができ、この中央支保工13と内周リング
02とに両端を連結することにより、グランド面012
で開閉屋根01を製作する。
As shown in FIG. 3A, the ground plane 01
At the approximate center of the inner peripheral ring manufactured on 2 above, a center supporter 13 having a height corresponding to the shape of the open / close roof 01 is erected as shown in FIG. Since this height is not so high, it can be formed by stacking about three modules, and by connecting both ends to the center support 13 and the inner peripheral ring 02, the ground surface 012 is formed.
To manufacture the open / close roof 01.

【0062】また、外壁011の外側に設ける外周側支
保工4の背高は、実施の第2形態と同様に、外周側アウ
ターリング07と外周側インナーリング06とを連結す
るリングコネクター08が、開閉屋根01を所定高さに
支持、保持するときの傾斜にできる高さにされ、このリ
ングコネクター08の傾斜角を保持したまま、図3
(b)に示すように、外周インナーリング06を頂端に
連結した内周側支保工5を、ジャッキアップして順次モ
ジュールを次ぎ足し背高を、開閉屋根01を所定高さに
したときに吊りケーブル6及び抑えケーブル8で支持で
きる高さにする。
Further, as in the second embodiment, the height of the outer peripheral support 4 provided on the outer side of the outer wall 011 is the same as that of the second embodiment. The opening / closing roof 01 is set to a height that can be inclined when supporting and holding the opening / closing roof 01 at a predetermined height, and while maintaining the inclination angle of the ring connector 08, FIG.
As shown in (b), the inner peripheral side support 5 connected to the top end of the outer peripheral inner ring 06 is jacked up, modules are sequentially added, and the height is raised. The height is set so that it can be supported by the cable 6 and the holding cable 8.

【0063】また、本実施の形態ではグランド面012
上で開閉屋根01が製作されている内周リング02と外
周アウターリング07との間は、吊りケーブル6で連結
されると共に、内周リング02と外周リング06との間
は抑えケーブル8で連結するようにしている。
In this embodiment, the ground plane 012
A suspension cable 6 connects the inner ring 02 and the outer ring 07 on which the open / close roof 01 is manufactured, and a restraining cable 8 connects the inner ring 02 and the outer ring 06. I am trying to do it.

【0064】次いで、中央支保工13をジャッキアップ
して順次モジュールを次ぎ足し、開閉屋根01が架設さ
れるグランド面012上方まで開閉屋根01を上昇させ
る。この開閉屋根01の上昇中のバランスは、屋根1の
先端を迂回して内周リング02と外周インナーリング0
6及び外周アウターリング07とを連結している抑えケ
ーブル8および吊りケーブル6の張力によって取ること
ができる。
Next, the center supporter 13 is jacked up, modules are sequentially added, and the open / close roof 01 is raised to above the ground plane 012 on which the open / close roof 01 is erected. The rising balance of the open / close roof 01 is such that the inner peripheral ring 02 and the outer peripheral inner ring 0
It can be removed by the tension of the holding cable 8 and the suspension cable 6 connecting the outer ring 7 and the outer ring 7.

【0065】また、これらの開閉屋根01の上昇中のバ
ランス制御はケーブル8、6に依らず、実施の第2形態
で示した仮設ケーブル12を設けてバランスを取るよう
にしても良いものである。
The balance control during the raising of the open / close roof 01 may be performed by the provision of the temporary cable 12 shown in the second embodiment, regardless of the cables 8 and 6, so as to achieve balance. .

【0066】このようにして開閉屋根01が所定の高さ
に架設されたとき、図3(c)に示すように、吊りケー
ブル6および抑えケーブル8の長さをウインチで調節す
ることにより、開閉屋根01は中央支保工13による支
持より、吊りケーブル6および抑えケーブル8の張力に
よる支持に移し換えられる。
When the opening / closing roof 01 is erected at a predetermined height in this way, as shown in FIG. 3 (c), the length of the suspension cable 6 and the holding cable 8 is adjusted by the winch, thereby opening and closing the roof. The roof 01 is transferred from being supported by the central supporter 13 to being supported by the tension of the suspension cable 6 and the holding cable 8.

【0067】次いで、ケーブル6、8の支持で無負荷と
なった中央支保工13を撤去すると共に、外周インナー
リング06を支持柱7に連結することにより、無負荷と
なった内周側支保工5を撤去することにより、図3
(d)に示すように、グランド面012上方に開閉屋根
01を完成させることができる。
Next, by removing the central support 13 which has become no load due to the support of the cables 6 and 8, and connecting the outer inner ring 06 to the support column 7, the inner support having no load has become free. 5 by removing
As shown in (d), the openable roof 01 can be completed above the ground surface 012.

【0068】本実施の形態のケーブルドーム施工法で
は、上述の手段を採用することにより、グランド面01
2上に開閉屋根01を設置する高さの中央支保工13を
1本設ける必要があるが、実施の第2形態と同様に外周
側支保工4の設置が背高の低いもので良くなり、実施の
第1形態に比べて支保工04の数を低減できる利点があ
り、支保工04の立設に要する資材、労務、工費をさら
に少なくすることができる。
In the cable dome construction method according to the present embodiment, the ground plane 01
It is necessary to provide one central supporter 13 having a height at which the opening / closing roof 01 is installed on the upper surface 2. However, as in the second embodiment, the outer peripheral supporter 4 can be installed with a shorter height, There is an advantage that the number of the shorings 04 can be reduced as compared with the first embodiment, and the materials, labor, and construction costs required for standing the shorings 04 can be further reduced.

【0069】また、中央支保工13の立設で損傷したグ
ランド面012の補修は必要となるものの、補修区画は
狭い範囲に限られ、従来の損傷補修に要する費用を大幅
に低減できる。
Although repair of the ground plane 012 damaged by the erecting of the central support 13 is necessary, the repair section is limited to a narrow range, and the cost required for the conventional repair can be greatly reduced.

【0070】また、施工時間が短くなるためにグランド
面の使用不能期間を短縮化できると共に、トラス状骨組
03、外周インナーリング06が地上で完全なものにで
きるばかりでなく、外周アウターリング07も実施の第
2形態と同様に地上で完全な円形状のものに製作でき、
高所作業をより少くすることができ、安全対策上秀れた
ものにできる。さらに、開閉屋根01の吊り上げ時の姿
勢制御が、吊りケーブル6および抑えケーブル8又は仮
設ケーブル12で行えるので、特別の装置が不要になる
利点がある。
Further, since the construction time is shortened, the period during which the ground surface cannot be used can be shortened, and not only can the truss-shaped frame 03 and the outer peripheral inner ring 06 be completed completely on the ground, but also the outer peripheral outer ring 07 can be used. Like the second embodiment, it can be made into a completely circular shape on the ground,
Work in high places can be reduced, and safety measures can be improved. Furthermore, since the attitude control when lifting the open / close roof 01 can be performed by the suspension cable 6, the holding cable 8, or the temporary cable 12, there is an advantage that a special device is not required.

【0071】次に、図4は本発明のケーブルドーム施工
法の実施の第4形態を示す図で、内周リング02の下方
に周方向に等ピッチで設置した支保工04のジャッキア
ップで内周リング02、開閉屋根01を架設を行う所定
の高さ以上に上昇させると共に、開閉屋根01の降下に
より所定高さ以上に上昇させた吊りケーブル6、抑えケ
ーブル8の張力を調整することによって、開閉屋根01
をバランス良く架設するようにしたものである。
Next, FIG. 4 is a view showing a fourth embodiment of the cable dome construction method of the present invention. The cable dome is jacked up by a supporter 04 installed at an equal pitch in the circumferential direction below the inner peripheral ring 02. By raising the peripheral ring 02 and the opening / closing roof 01 to a predetermined height or higher for erection, and adjusting the tension of the suspension cable 6 and the holding cable 8 raised to a predetermined height or more by lowering the opening / closing roof 01, Opening / closing roof 01
Are installed in a well-balanced manner.

【0072】図4(a)に示すように、グランド面01
2上で製作された内周リングの略中央に、図4(b)に
示すように開閉屋根01の形状に合わせた高さの中央支
保工14を立設する。この高さはあまり高いものではな
いので、3個程度のモジュールを積み重ねることにより
形成することができ、この中央支保工14と内周リング
02とに両端を連結することにより、グランド面012
で開閉屋根01を製作する。
As shown in FIG. 4A, the ground plane 01
At the approximate center of the inner peripheral ring manufactured on 2 above, a center supporter 14 having a height corresponding to the shape of the open / close roof 01 is erected as shown in FIG. Since this height is not very high, it can be formed by stacking about three modules, and by connecting both ends to the center support 14 and the inner peripheral ring 02, the ground surface 012 is formed.
To manufacture the open / close roof 01.

【0073】また、外壁011の外側に設ける外周側支
保工4の背高は、実施の第2形態、第3形態と同様に外
周側アウターリング07と外周側インナーリング06と
を連結するリングコネクター08が、開閉屋根01を所
定高さに支持、保持するときの傾斜にできる高さにさ
れ、このリングコネクター08の傾斜角を保持したま
ま、図4(b)に示すように、外周インナーリング06
を頂端に連結した内周側支保工5を、ジャッキアップし
て順次モジュールを次ぎ足し、背高を開閉屋根01を2
0〜30mの所定高さにし、吊りケーブル6及び抑えケ
ーブル8で支持できる高さにする。
The height of the outer peripheral support 4 provided on the outer side of the outer wall 011 is the same as that of the second and third embodiments, and a ring connector for connecting the outer peripheral outer ring 07 and the outer peripheral inner ring 06. 08 is set to a height that can be inclined to support and hold the opening / closing roof 01 at a predetermined height, and while maintaining the inclination angle of the ring connector 08, as shown in FIG. 06
Jack is connected to the top end of the inner peripheral support 5 and the modules are added one after the other.
The height is set to a predetermined height of 0 to 30 m so as to be supported by the suspension cable 6 and the holding cable 8.

【0074】次いで、図4(c)に示すように内周リン
グ02の下方周方向にリング支保工15を等ピッチに配
置し、リング支保工15をジャッキアップして順次モジ
ュールを次ぎ足し、開閉屋根01が架設されるグランド
面012上方位置より上方にまで開閉屋根01を上昇さ
せる。この開閉屋根01の上昇中のバランスは、リング
支保工15を一斉にジャッキアップすることによって保
持することができる。この状態で内周リング02と外周
インナーリング06および外周アウターリング07とを
抑えケーブル8および吊りケーブル6で連結する。
Next, as shown in FIG. 4 (c), ring supports 15 are arranged at equal pitches in the lower circumferential direction of the inner peripheral ring 02, the ring supports 15 are jacked up, modules are sequentially added, and opening and closing are performed. The openable roof 01 is raised to a position above the ground surface 012 on which the roof 01 is erected. The balance during the rising of the openable roof 01 can be maintained by simultaneously jacking up the ring supports 15. In this state, the inner peripheral ring 02, the outer peripheral inner ring 06 and the outer peripheral ring 07 are suppressed and connected by the cable 8 and the suspension cable 6.

【0075】この実施例の場合、抑えケーブル8および
吊りケーブル6への張力の導入は控え目にしておき、図
4(d)に示すように開閉屋根01の自重により、開閉
屋根01は点線の高さから実線で示す高さ、即ちグラン
ド面012の使用に好適な高さ、例えば、野球場の場合
約60mの高さに降下して架設されると共にこの降下に
より内周リングの外周、周方向に等ピッチに配置されて
いる吊りケーブル6および抑えケーブル8には、同じ大
きさの張力が導入され、開閉屋根01を安定した姿勢に
して支持することができる。
In the case of this embodiment, the introduction of tension to the holding cable 8 and the suspension cable 6 is modest, and as shown in FIG. Therefore, the height indicated by the solid line, that is, a height suitable for the use of the ground surface 012, for example, in the case of a baseball field, is lowered to a height of about 60 m, and is lowered. The same magnitude of tension is introduced into the suspension cable 6 and the holding cable 8 arranged at equal pitches, and the openable roof 01 can be supported in a stable posture.

【0076】次に、図5は前述した図1に示すケーブル
ドーム施工法の実施の第1形態と同様の施工法により、
地上で製作された開閉屋根01を吊りケーブル6(牽引
ケーブル16)でグランド面012の上方まで吊り上
げ、架設するようにしたものであるが、本実施の形態に
おいては前述した図4に示す実施の第4形態と同様に、
吊りケーブル6で吊り上げる開閉屋根01の高さを架設
位置(高さ)まで吊り上げ、架設高さ以上にまで上昇さ
せた開閉屋根01の自重による降下で、吊りケーブル6
および抑えケーブル8の張力を調整することによって、
開閉屋根01の姿勢とバランス良くして架設できるよう
にしたものである。
Next, FIG. 5 shows a construction similar to the first embodiment of the cable dome construction method shown in FIG.
The open / close roof 01 manufactured on the ground is lifted by the suspension cable 6 (traction cable 16) above the ground plane 012, and is erected. In the present embodiment, the embodiment shown in FIG. As in the fourth embodiment,
The height of the opening / closing roof 01 to be hung by the hanging cable 6 is lifted to the erection position (height), and the height of the opening / closing roof 01 raised to the erection height or more is lowered by its own weight.
And by adjusting the tension of the holding cable 8,
It is designed so that it can be installed with a good balance with the posture of the opening / closing roof 01.

【0077】図5(a)、図5(b)に示すものは、図
1(a)、図1(b)と同様にして施工されるので説明
は省略する。図5(b)の状態から図5(c)に示すよ
うに、架設高さ以上に開閉屋根01がウインチから巻き
出された牽引ケーブル16の張力により、吊りケーブル
6を介して吊り上げられた時点で、内周リング02と外
周インナーリング06との間に抑えケーブル8を張設す
ると共に、外周側支保工4の頂端に載置されている分割
されている外周アウターリング07を連結し円環状の外
周アウターリング07を形成し、また外周インナーリン
グ06のまわりに回動するようにしているリングコネク
ター08を所定の傾斜にした後、開閉屋根01を架設高
さ以上の高さに吊り上げている牽引ケーブル16の張力
を零にする。
The components shown in FIGS. 5A and 5B are constructed in the same manner as in FIGS. 1A and 1B, and will not be described. As shown in FIG. 5 (c) from the state of FIG. 5 (b), when the open / close roof 01 is lifted up via the suspension cable 6 by the tension of the traction cable 16 unwound from the winch at a height higher than the erection height. in the inner periphery while stretched the restraining cable 8 between the ring 02 and the outer inner ring 06, a circle connecting the outer peripheral outer ring 07 which is split is placed on the top end of the outer peripheral side 支保 Engineering 4 cyclic After the outer peripheral ring 07 is formed and the ring connector 08 rotating around the inner peripheral ring 06 is inclined at a predetermined angle, the open / close roof 01 is lifted to a height equal to or higher than the installation height. The tension of the traction cable 16 is reduced to zero.

【0078】これにより、図5(d)の点線で示す如く
架設高さ以上の高さに配置されている開閉屋根01は自
重により、開閉屋根01は点線の高さから実線で示す高
さ、即ちグランド面012の使用に好適な高さに降下し
て架設されると共にこの降下により内周リング02の外
周、周方向に等ピッチに配置されている多数の吊りケー
ブル6および抑えケーブル8には、開閉屋根01の姿勢
を安定したものにする張力が導入され、開閉屋根01を
安定した姿勢にして支持することができる。
As a result, as shown by the dotted line in FIG. 5 (d), the open / close roof 01 arranged at a height equal to or higher than the erection height has its own weight, and the open / close roof 01 has the height indicated by the solid line from the height of the dotted line. In other words, the suspension cable 6 is lowered to a height suitable for the use of the ground surface 012 and is installed. In addition, a tension for stabilizing the posture of the open / close roof 01 is introduced, and the open / close roof 01 can be supported in a stable posture.

【0079】このように、第5形態で説明したように、
吊りケーブル6に所定よりも大きな張力を導入して開閉
屋根01を架設高さ以上にまで吊り上げておき、開閉屋
根01を自重により架設高さにまで降下させて、抑えケ
ーブル8に張力を導入することにより、多数の吊りケー
ブル6および抑えケーブル8に張力を導入し、開閉屋根
01を安定した姿勢にしてケーブルにより支持すること
は、タワークレーン10を使用して開閉屋根01を吊り
上げるようにした実施の第2形態、又は中央支保工13
をジャッキアップすることにより、開閉屋根01をグラ
ンド面012上の架設高さまで吊り上げるようにした実
施の第3形態にも適用することができるものである。
As described above, as described in the fifth embodiment,
A tension higher than a predetermined value is introduced into the suspension cable 6 to lift the opening / closing roof 01 to a height equal to or higher than the erection height, and the opening / closing roof 01 is lowered to the erection height by its own weight to introduce tension to the holding cable 8. In this way, tension is introduced into a large number of the suspension cables 6 and the holding cables 8 so that the opening / closing roof 01 is supported in a stable posture by the cables, and the tower crane 10 is used to lift the opening / closing roof 01. 2nd form, or central supporter 13
, The open / close roof 01 can be lifted up to the erected height on the ground plane 012 by jacking up the third embodiment.

【0080】即ち、実施の第2形態においては、中央支
保工9を開閉屋根01の架設高さよりも高くして、その
上方にタワークレーン10を設置することにより、この
施工法が可能になり、実施の第3形態においては中央支
保工13を開閉屋根01の架設高さ以上にすることによ
り、同様の施工法が可能になり、架設高さ以上の高さに
架設した開閉屋根01をグランド面012の使用に好適
な高さにまで降下させて架設すると共に、この降下時の
開閉屋根01の重量により、内周リング02の外周周方
向に等ピッチに配置されている多数の吊りケーブル6お
よび抑えケーブル8には、開閉屋根01の姿勢を安定し
たものにできる張力が導入でき、ケーブル6、8により
開閉屋根01を安定した姿勢に保持できるものにするこ
とができる。
That is, in the second embodiment, this construction method can be performed by setting the center support 9 higher than the height of the erection roof 01 and installing the tower crane 10 above it. In the third embodiment, a similar construction method becomes possible by setting the central supporter 13 to have a height equal to or higher than the erection height of the opening / closing roof 01, and the opening / closing roof 01 erected at a height equal to or higher than the erection height is grounded. 012 is lowered to a height suitable for use, and the number of suspension cables 6 arranged at equal pitches in the outer circumferential direction of the inner peripheral ring 02 and A tension that can stabilize the attitude of the open / close roof 01 can be introduced into the holding cable 8, and the cables 6 and 8 can maintain the open / close roof 01 in a stable attitude.

【0081】[0081]

【発明の効果】以上説明したように、本発明のケーブル
ドーム施工法は、グランド面上で内周リングを組立て、
組立てた内周リング内中心からトラス状骨組を放射状に
配置してドーム屋根を形成する工程、内周リングの外側
にそれぞれが間隔を設けて放射状に配設し、各頂端へ内
周リングより大径の外周インナーリング、外周インナー
リングより大径の外周アウターリングからなる外周リン
グを架設する外周側支保工を立設する工程、外周インナ
ーリング外周に回動自在に連結され、先端部に分断され
た外周アウターリングが固定され、両端を各外周リング
に連結したリングコネクターを設ける工程、リングコネ
クターを外周インナーリングまわりに回動させ、先端部
を内周リング側に向け外周アウターリングと内周リング
とを吊りケーブルで連結し、外周アウターリングに連結
されている牽引ケーブルによりリングコネクターを内周
リング外方向側に回動させ、この回動によりグランド面
上のドーム屋根を架設高さまで吊り上げる工程、ドーム
屋根を吊り上げ外周側支保工頂端に載置された外周アウ
ターリング周方向分割部を連結した円環状の外周アウタ
ーリングと内周リングとを吊りケーブルにより、ドーム
屋根を架設高さに保持し、内周リングと外周インナーリ
ングとを抑えケーブルで連結する工程とからなるものに
した。
As described above, according to the cable dome construction method of the present invention, the inner peripheral ring is assembled on the ground surface,
A process of arranging truss-shaped frames radially from the center of the assembled inner peripheral ring to form a dome roof, arranging them radially outside the inner peripheral ring with a space between each, and each top end being larger than the inner peripheral ring. A step of erecting an outer peripheral side support for installing an outer peripheral ring composed of an outer peripheral inner ring having a diameter and an outer peripheral ring having a larger diameter than the outer peripheral inner ring, which is rotatably connected to the outer peripheral inner ring outer periphery and is divided into a tip portion. The outer outer ring is fixed and the ring connector is connected to each outer ring at both ends.The ring connector is rotated around the outer inner ring, and the outer peripheral ring and the inner ring are turned with their tips toward the inner ring. Is connected to the outer ring with the pulling cable connected to the outer ring. Moving the dome roof on the ground surface to the erected height by this rotation, lifting the dome roof, and connecting the outer circumferential outer ring placed at the top end of the outer circumferential support to the circumferential outer ring. And a step of holding the dome roof at the erection height with a hanging cable and suspending the inner ring and the outer ring with a cable to connect the inner ring with the inner ring.

【0082】これにより、立設する支保工の本数を1/
10以下にでき、資材、労務、工費をでき、ドーム屋根
の架設期間を短くできる。また、グランド面の支保工の
高さを低く軽量のものにでき、グランド面の補強が不要
になりグランド面に生じる損傷を軽微なものにできる。
さらに、ドーム屋根の製作が地上ででき、支保工上での
トラス状骨組の組み立て作業がなくなり、高所作業を低
減でき安全上の問題を少なくでき、これらに要する費用
を低減できる。
As a result, the number of shoring works to be erected is reduced by 1 /
It can be reduced to 10 or less, and materials, labor and construction costs can be reduced, and the dome roof construction period can be shortened. In addition, the height of the support of the ground surface can be reduced and the weight can be reduced, so that reinforcement of the ground surface is not required, and damage to the ground surface can be reduced.
Further, the dome roof can be manufactured on the ground, and the work of assembling the truss-like frame on the shoring work can be eliminated, work at heights can be reduced, safety problems can be reduced, and costs required for these can be reduced.

【0083】また、本発明のケーブルドーム施工法は、
前述と同様にドーム屋根を形成する工程、内周リングの
外側に配設され、先端部に外周アウターリングを固定し
基端部に外周インナーリングを固定し、所定の傾斜にさ
れたリングコネクターの基端部を頂端に固定した内周側
支保工を立設する工程、ドーム屋根の中央部を貫通し頂
端部にタワークレーンを設置した中央支保工を内周リン
グ中央に立設する工程、タワークレーンから吊り下ろし
た昇降ケーブルの下端部をドーム屋根の中央に連結し、
昇降ケーブルの巻き上げドーム屋根を架設高さに吊り上
げる工程、吊り上げたドーム屋根を外周アウターリング
と内周リングとに連結した吊りケーブルにより架設高さ
に保持し、内周リングと外周インナーリングとを抑えケ
ーブルで連結する工程とからなるものとした。
The cable dome construction method of the present invention comprises:
The process of forming the dome roof in the same manner as described above, arranged outside the inner peripheral ring, fixing the outer peripheral ring at the distal end and fixing the outer peripheral ring at the base end, and the ring connector with a predetermined inclination The process of erecting the inner peripheral support with the base end fixed to the top end, the process of erecting the central support with the tower crane installed at the top end through the center of the dome roof, the tower Connect the lower end of the lifting cable suspended from the crane to the center of the dome roof,
The process of hoisting the hoisting dome roof of the elevating cable to the erection height, holding the dome roof at the erection height by the hanging cable connected to the outer ring and the inner ring, and suppressing the inner ring and the outer ring Connecting with a cable.

【0084】これにより、グランド面上にドーム屋根を
架設する中央支保工を1本設ける必要があるが、外周支
保工の本数を約1/2にできるので資材、労務、工費を
さらに低減できる。また、グランド面には中央支保工を
1本設けるグランド面の補強、グランド面に生じる損傷
修復に要する費用、作業は軽微なものにできる。さら
に、分割された外周アウターリングの接合作業が不要に
なり、高所作業を低減でき安全上の問題が少なくなり、
これらのための装置費用を低減できる。
As a result, it is necessary to provide one central supporter for erection of the dome roof on the ground surface. However, the number of outer peripheral supports can be reduced to about 1 /, so that materials, labor and construction costs can be further reduced. In addition, the cost and work required for reinforcing the ground surface and repairing the damage generated on the ground surface by providing one central supporter on the ground surface can be reduced. Furthermore, the joining work of the divided outer outer ring is not required, the work at high places can be reduced, and the safety problem is reduced,
Equipment costs for these can be reduced.

【0085】また、本発明のケーブルドーム施工法は、
前述と同様にドーム屋根を形成する工程、前述と同様に
内周側支保工を立設する工程、グランド面上の内周リン
グと立設された内周側支保工頂端のリングコネクターの
頂端部に固定した外周アウターリングとを吊りケーブル
で連結する工程、組み立てたドーム屋根中央部に当接さ
せ、架設高さまで上昇させる中央支保工を内周リング中
央部に立設する工程、吊り上げたドーム屋根を架設高さ
に保持し、風などのドーム屋根の吹上に対して抵抗する
内周リングと外周アウターリング及び内周リングと外周
インナーリングを連結している吊りケーブル及び抑えケ
ーブルに張力を導入する工程とからなるものとした。
The cable dome construction method of the present invention
The process of forming the dome roof as described above, the process of erecting the inner peripheral support in the same manner as described above, the inner peripheral ring on the ground surface and the top end of the ring connector at the top of the inner peripheral support that is erected Connecting the outer ring fixed to the outer ring with a suspension cable, abutting the center of the assembled dome roof and raising the center support to the erection height at the center of the inner ring, erecting the dome roof At the erection height, and introduce tension to the suspension cable and holding cable connecting the inner and outer rings and the inner and outer rings that resist the dome roof from blowing up wind. Process.

【0086】これにより、ドーム屋根を架設高さへ上昇
させるときの安定性が吊りケーブル及び抑えケーブルに
より保持でき、特別の装置を必要とせず安定したドーム
屋根の吊り上げができる。
Thus, the stability when the dome roof is raised to the erection height can be held by the suspension cable and the holding cable, and the dome roof can be stably lifted without requiring any special device.

【0087】また、本発明のケーブルドーム施工法は、
前述と同様にドーム屋根を形成する工程、前述と同様に
内周側支保工を立設する工程、組み立てた内周リング下
方周方向に配置され、内周リング内に組み立てたドーム
屋根を、架設高さ以上に上昇させるリング支保工を立設
する工程、吊り上げたドーム屋根の内周リングと外周ア
ウターリング及び外周インナーリングとを吊りケーブル
及び抑えケーブルで連結する工程、架設高さ以上に吊り
上げたドーム屋根を架設高さまで降下させ吊りケーブル
に張力を導入し、抑えケーブルには別にドーム屋根の吹
上に対して抵抗する張力を導入する工程とからなるもの
とした。
The cable dome construction method of the present invention is as follows.
A process of forming a dome roof as described above, a process of erecting the inner peripheral side support as described above, and a dome roof which is disposed in a circumferential direction below the assembled inner ring and is assembled in the inner ring, The process of erecting a ring support that rises above the height, the process of connecting the inner ring of the dome roof, the outer outer ring and the outer inner ring of the dome roof with a suspension cable and a restraining cable, The step of lowering the dome roof to the erection height and introducing tension to the suspension cable, and separately introducing tension to the holding cable that resists the blowing of the dome roof.

【0088】これにより、実施の第1形態、第2形態、
第3形態に比較し、架設高さ以上に吊り上げられたドー
ム屋根を、架設高さまで降下させて吊りケーブルに張力
を導入でき、抑えケーブルには別に吹上に対して抵抗す
る張力を導入したので、吊りケーブル及び抑えケーブル
に導入される張力により、ドーム屋根を安定して保持で
き、ドーム屋根の吹上に対して抵抗し安定なドーム屋根
を架設できる。
Thus, the first embodiment, the second embodiment,
As compared to the third form, the dome roof suspended above the erection height can be lowered to the erection height and tension can be introduced into the suspension cable, and the tension that separately resists blow-up is introduced into the holding cable, The dome roof can be stably held by the tension introduced into the suspension cable and the hold-down cable, and a stable dome roof can be erected by resisting the blowing of the dome roof.

【0089】また、本発明のケーブルドーム施工法は、
前述した何れかの工程によりドーム屋根を架設高さまで
吊り上げる工程が、前述ドーム屋根を架設高さ以上にま
で吊り上げる工程にされ、架設高さ以上に吊り上げたド
ーム屋根の内周リングと外周アウターリング及び外周イ
ンターリングとを前述の工程と同様にして、吊りケーブ
ル及び抑えケーブルで連結し又は張力を導入した後、前
述の工程と同様にして架設高さ以上から架設高さまで降
下させ、ドーム屋根の荷重で生じる吊りケーブルの張力
で、ドーム屋根を架設高さに保持し、抑えケーブルにド
ーム屋根吹上に対して抵抗する張力を導入する工程とか
らなるものとした。
Further, the cable dome construction method of the present invention is as follows.
The step of lifting the dome roof to the erection height by any of the above-described steps is the step of lifting the dome roof to the erection height or higher, and the inner peripheral ring and the outer peripheral ring of the dome roof that is raised above the erection height and After connecting the outer inter-ring with the suspension cable and holding cable or introducing tension in the same manner as in the above process, lower the dome roof from the height above the erection height in the same manner as in the above process, and load the dome roof. And the step of holding the dome roof at the erection height by the tension of the suspension cable generated in the above, and introducing a tension to the holding cable that resists the blowing of the dome roof.

【0090】これにより、前述した作用、効果に加え
て、吊りケーブル及び抑えケーブルに導入される張力に
より、ドーム屋根を安定して保持でき、ドーム屋根の吹
上に対して抵抗し安定なドーム屋根を架設できる上述と
同様の作用、効果が得られる。
As a result, in addition to the above-described functions and effects, the dome roof can be stably held by the tension introduced into the suspension cable and the holding cable, and a stable dome roof can be provided which resists the blowing of the dome roof. The same operation and effect as described above that can be installed can be obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のケーブルドーム施工法の実施の第1形
態を示すフロー図、
FIG. 1 is a flowchart showing a first embodiment of a cable dome construction method of the present invention;

【図2】本発明のケーブルドーム施工法の実施の第2形
態を示すフロー図、
FIG. 2 is a flowchart showing a second embodiment of the cable dome construction method of the present invention,

【図3】本発明のケーブルドーム施工法の実施の第3形
態を示すフロー図、
FIG. 3 is a flowchart showing a third embodiment of the cable dome construction method of the present invention;

【図4】本発明のケーブルドーム施工法の実施の第4形
態を示すフロー図、
FIG. 4 is a flowchart showing a fourth embodiment of the cable dome construction method of the present invention;

【図5】本発明のケーブルドーム施工法の実施の第5形
態を示すフロー図、
FIG. 5 is a flowchart showing a fifth embodiment of the cable dome construction method of the present invention;

【図6】従来のケーブルドーム施工法の実施の形態を示
す図で、図6(a)はドーム屋根としての開閉屋根施工
時を示す断面図、図6(b)は施工のフローを示す図で
ある。
6A and 6B are diagrams showing an embodiment of a conventional cable dome construction method, in which FIG. 6A is a cross-sectional view showing a dome roof when opening and closing a roof, and FIG. 6B is a view showing a construction flow. It is.

【符号の説明】[Explanation of symbols]

1 屋根 2 スタンド 3 既設球場 4 外周側支保工 5 内周側支保工 6 吊りケーブル 7 支持柱 8 抑えケーブル 9 中央支保工 10 タワークレーン 11 昇降ケーブル 12 仮設ケーブル 13 中央支保工 14 中央支保工 15 リング支保工 16 牽引ケーブル 01 開閉屋根 02 内周リング 03 トラス状骨組 04 支保工 05 ケーブル 06 外周インナーリング 07 外周アウターリング 08 リングコネクター 09 クレーン車 010 トラス状骨組ブロック 011 外壁 012 グランド面 DESCRIPTION OF SYMBOLS 1 Roof 2 Stand 3 Existing ballpark 4 Outer side support 5 Inner side support 6 Suspension cable 7 Support column 8 Suppression cable 9 Central support 10 Tower crane 11 Elevating cable 12 Temporary cable 13 Central support 14 Central support 15 Ring Shoring 16 Towing cable 01 Opening / closing roof 02 Inner ring 03 Trussed frame 04 Shoring 05 Cable 06 Outer inner ring 07 Outer outer ring 08 Ring connector 09 Crane truck 010 Trussed frame block 011 Outer wall 012 Ground plane

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岩本 洋一 兵庫県高砂市荒井町新浜2丁目1番1号 三菱重工業株式会社高砂研究所内 (72)発明者 吹原 正晃 神戸市兵庫区和田崎町一丁目1番1号 三 菱重工業株式会社神戸造船所内 (72)発明者 戸谷 克樹 神戸市兵庫区和田崎町一丁目1番1号 三 菱重工業株式会社神戸造船所内 Fターム(参考) 2E174 AA01 BA05 DA02 DA08 DA18 DA24  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Yoichi Iwamoto 2-1-1 Shinhama, Arai-machi, Takasago City, Hyogo Prefecture Inside the Takasago Research Laboratory, Mitsubishi Heavy Industries, Ltd. (72) Inventor Masaaki Fukihara 1-1-1, Wadazakicho, Hyogo-ku, Kobe-shi No. 1 In the Kobe Shipyard of Mitsubishi Heavy Industries, Ltd. (72) Inventor Katsuki Toya 1-1-1, Wadazakicho, Hyogo-ku, Kobe F-term in Kobe Shipyard, Mitsubishi Heavy Industries, Ltd. 2E174 AA01 BA05 DA02 DA08 DA18 DA24

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 内周リング、前記内周リングの内部に放
射状に配置されたトラス状骨組とからなるドーム屋根
を、前記内周リングの外周に連結したケーブルによりグ
ランド面上方に架設するケーブルドーム施工法におい
て、前記グランド面上で前記ドーム屋根を形成する工程
と、前記内周リングの外側に離隔して配設され各頂端に
外周リングを架設する支保工を立設する工程と、一方の
前記外周リングの軸心と直交する鉛直面内で回動し、両
端が各外周リングに連結されたリングコネクターを設け
る工程と、前記リングコネクターを前記内周リング側に
回動させ、前記リングコネクターの一端に連結された前
記外周リングと前記内周リングとを吊りケーブルで連結
し、前記リングコネクターを外方向に回動させ前記ドー
ム屋根を架設高さまで吊り上げる工程と、吊り上げた前
記ドーム屋根を前記吊りケーブルの張力により架設高さ
に保持する工程とからなることを特徴とするケーブルド
ーム施工法。
1. A cable dome in which a dome roof comprising an inner peripheral ring and a truss-like frame radially arranged inside the inner peripheral ring is erected above a ground plane by a cable connected to an outer periphery of the inner peripheral ring. In the construction method, a step of forming the dome roof on the ground surface, and a step of erecting a shoring that is disposed outside the inner peripheral ring and is erected at each top end to install an outer peripheral ring, Providing a ring connector that rotates in a vertical plane perpendicular to the axis of the outer peripheral ring and has both ends connected to the outer peripheral rings; and rotating the ring connector toward the inner peripheral ring, the ring connector The outer ring and the inner ring connected to one end are connected by a suspension cable, and the ring connector is pivoted outward to suspend the dome roof to an installation height. A cable dome construction method, comprising: a step of lifting the dome roof; and a step of holding the suspended dome roof at an erected height by tension of the suspension cable.
【請求項2】 内周リング、前記内周リングの内部に放
射状に配置されたトラス状骨組とからなるドーム屋根
を、前記内周リングの外周に連結したケーブルによりグ
ランド面上方に架設するケーブルドーム施工法におい
て、前記グランド面上で前記ドーム屋根を形成する工程
と、前記内周リングの外側に配設され頂端に外周リング
を架設する支保工を立設する工程と、頂端部にタワーク
レーンが設置され、前記ドーム屋根の中央部を貫通させ
た中央支保工を前記内周リングの中央部に立設する工程
と、前記タワークレーンから吊り下ろした昇降ケーブル
の下端部を前記ドーム屋根の中央部に連結し、前記ドー
ム屋根を架設高さまで吊り上げる工程と、吊り上げた前
記ドーム屋根を前記外周リングと前記内周リングとに連
結した吊りケーブルの張力により架設高さに保持する工
程とからなることを特徴とするケーブルドーム施工法。
2. A cable dome in which a dome roof comprising an inner peripheral ring and a truss-like frame radially arranged inside the inner peripheral ring is erected above a ground plane by a cable connected to an outer periphery of the inner peripheral ring. In the construction method, a step of forming the dome roof on the ground surface, a step of erecting a support provided outside the inner peripheral ring and erection of an outer peripheral ring at a top end, and a tower crane at a top end A step of erecting a center support installed at the center of the inner peripheral ring and penetrating the center of the dome roof; and And lifting the dome roof to the erection height, and tensioning a suspension cable connecting the lifted dome roof to the outer ring and the inner ring. A method for constructing a cable dome, comprising the step of maintaining the erection height by force.
【請求項3】 内周リング、前記内周リングの内部に放
射状に配置されたトラス状骨組とからなるドーム屋根
を、前記内周リングの外周に連結したケーブルによりグ
ランド面上方に架設するケーブルドーム施工法におい
て、前記グランド面上で前記ドーム屋根を形成する工程
と、前記内周リングの外側に配設され頂端に外周リング
を架設する支保工を立設する工程と、前記グランド面上
に配置されている前記内周リングと立設された前記支保
工上に配設された前記外周リングとを吊りケーブルで連
結する工程と、前記ドーム屋根を架設高さまでジャッキ
アップする中央支保工を前記内周リングの中央部に立設
する工程と、吊り上げた前記ドーム屋根を前記吊りケー
ブルの張力により架設高さに保持する工程とからなるこ
とを特徴とするケーブルドーム施工法。
3. A cable dome in which a dome roof comprising an inner peripheral ring and a truss-like frame radially arranged inside the inner peripheral ring is erected above a ground plane by a cable connected to an outer periphery of the inner peripheral ring. In the construction method, a step of forming the dome roof on the ground plane, a step of erecting a supporter provided outside the inner peripheral ring and erection of an outer peripheral ring at a top end, and disposed on the ground plane. Connecting a hanging cable between the inner ring and the outer ring provided on the upright support, and a central support for jacking up the dome roof to a erection height. A cable comprising a step of erecting the dome roof at the center of the peripheral ring, and a step of holding the suspended dome roof at the erected height by tension of the suspension cable. Dome construction method.
【請求項4】 内周リング、前記内周リングの内部に放
射状に配置されたトラス状骨組とからなるドーム屋根
を、前記内周リングの外周に連結したケーブルによりグ
ランド面上方に架設するケーブルドーム施工法におい
て、前記グランド面上で前記ドーム屋根を形成する工程
と、前記内周リングの外側に配設され頂端に外周リング
を架設する外周支保工を立設する工程と、前記内周リン
グの下方周方向に等ピッチで配置され、前記ドーム屋根
を架設高さ以上にまでジャッキアップするリング支保工
を立設する工程と、吊り上げた前記ドーム屋根の前記内
周リングと前記外周リングとを吊りケーブルで連結する
工程と、架設高さ以上に上昇させた前記ドーム屋根を架
設高さまで降下させ、前記吊りケーブルに張力を導入す
る工程とからなることを特徴とするケーブルドーム施工
法。
4. A cable dome in which a dome roof comprising an inner peripheral ring and a truss-like frame radially arranged inside the inner peripheral ring is erected above a ground plane by a cable connected to an outer periphery of the inner peripheral ring. In the construction method, a step of forming the dome roof on the ground surface, a step of erection of an outer peripheral supporter provided outside the inner peripheral ring and erection of an outer peripheral ring at a top end thereof, and Erecting a ring supporter that is arranged at equal pitches in the lower circumferential direction and jacks up the dome roof to a height equal to or higher than the erection height, and suspends the inner ring and the outer ring of the lifted dome roof. A cable connecting step, and a step of lowering the dome roof raised above the erection height to the erection height and introducing tension to the suspension cable. Characteristic cable dome construction method.
【請求項5】 前記ドーム屋根を架設高さまで吊り上げ
る工程が、前記ドーム屋根を架設高さ以上にまで吊り上
げる工程にされ、架設高さ以上に吊り上げた前記ドーム
屋根の前記内周リングと前記外周リングとを吊りケーブ
ル及び抑えケーブルで連結した後、架設高さ以上から架
設高さまで降下させたときの前記ドーム屋根の荷重によ
り生じる前記吊りケーブル及び抑えケーブルの張力によ
り、前記ドーム屋根を架設高さに保持する工程とからな
ることを特徴とする請求項1ないし請求項3の何れかの
ケーブルドーム施工法。
5. The step of hoisting the dome roof to the erection height, wherein the step of hoisting the dome roof to a height higher than the erection height, wherein the inner peripheral ring and the outer peripheral ring of the dome roof suspended above the erection height After connecting the dome roof with the suspension cable and the holding cable, the tension of the suspension cable and the holding cable caused by the load on the dome roof when the dome roof is lowered from the erection height or higher to the erection height. 4. The method according to claim 1, further comprising the step of holding.
JP2001065479A 2001-03-08 2001-03-08 Method of constructing cable dome Pending JP2002266434A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001065479A JP2002266434A (en) 2001-03-08 2001-03-08 Method of constructing cable dome

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001065479A JP2002266434A (en) 2001-03-08 2001-03-08 Method of constructing cable dome

Publications (1)

Publication Number Publication Date
JP2002266434A true JP2002266434A (en) 2002-09-18

Family

ID=18924117

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001065479A Pending JP2002266434A (en) 2001-03-08 2001-03-08 Method of constructing cable dome

Country Status (1)

Country Link
JP (1) JP2002266434A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007071097A (en) * 2005-09-07 2007-03-22 Takenaka Komuten Co Ltd Construction method of wind power generation tower
RU2464387C2 (en) * 2010-09-02 2012-10-20 Сергей Михайлович Анпилов Method to manufacture large-span covers of hangar, large-span cover of hangar (versions)
CN104420656A (en) * 2013-08-29 2015-03-18 上海宝冶集团有限公司 Traction tension forming mounting method of spherical rib annular type cable dome structure
JP2017172204A (en) * 2016-03-24 2017-09-28 大成建設株式会社 Roof structure
CN107246153A (en) * 2017-06-14 2017-10-13 东南大学 A kind of non-stand construction method of annular Suo Cheng networks
CN109057362A (en) * 2018-09-05 2018-12-21 北京奇力建通工程技术有限公司 A kind of Suo Cheng network rope system traction tensioning integral construction method and equipment
CN111101600A (en) * 2019-11-20 2020-05-05 北京市建筑工程研究院有限责任公司 Construction method of double-oblique-arch hyperbolic paraboloid cable net structure with limited construction space

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007071097A (en) * 2005-09-07 2007-03-22 Takenaka Komuten Co Ltd Construction method of wind power generation tower
JP4701047B2 (en) * 2005-09-07 2011-06-15 株式会社竹中工務店 Wind power tower construction method
RU2464387C2 (en) * 2010-09-02 2012-10-20 Сергей Михайлович Анпилов Method to manufacture large-span covers of hangar, large-span cover of hangar (versions)
CN104420656A (en) * 2013-08-29 2015-03-18 上海宝冶集团有限公司 Traction tension forming mounting method of spherical rib annular type cable dome structure
JP2017172204A (en) * 2016-03-24 2017-09-28 大成建設株式会社 Roof structure
CN107246153A (en) * 2017-06-14 2017-10-13 东南大学 A kind of non-stand construction method of annular Suo Cheng networks
CN109057362A (en) * 2018-09-05 2018-12-21 北京奇力建通工程技术有限公司 A kind of Suo Cheng network rope system traction tensioning integral construction method and equipment
CN109057362B (en) * 2018-09-05 2021-06-22 北京奇力建通工程技术有限公司 Cable-supported grid structure cable system traction and tensioning integrated construction method and equipment
CN111101600A (en) * 2019-11-20 2020-05-05 北京市建筑工程研究院有限责任公司 Construction method of double-oblique-arch hyperbolic paraboloid cable net structure with limited construction space
CN111101600B (en) * 2019-11-20 2021-04-02 北京市建筑工程研究院有限责任公司 Construction method of double-oblique-arch hyperbolic paraboloid cable net structure with limited construction space

Similar Documents

Publication Publication Date Title
CA2735625C (en) Method of building a hybrid tower for a wind generator
US7192252B2 (en) Safety device for a wind turbine
CN107090932A (en) Large span thin-walled planar based on stiffness ring beam encircles the construction method of truss
CN109236012B (en) Method for hoisting power transmission line T-shaped guyed tower
JP2009113922A (en) Construction method for tower structure and crane for construction
US4953720A (en) Crane and method for using crane
CN111455871A (en) Segmental vertical rotation structure for arch rib of steel box arch bridge and construction method
JP2002266434A (en) Method of constructing cable dome
JP2002147340A (en) Installing method of windmill generator and windmill generator
JPH0245274Y2 (en)
JPH10195826A (en) Bridge construction method and device thereof
JP3516056B2 (en) Rotary lift-up construction method for dome roof
JP2000204792A (en) Frame for assembly and/or maintenance for tower-shaped building, and assembly and/or maintenance method for tower-shaped building
JP2579715B2 (en) External tower crane
JPH0718743A (en) Construction method for large span domelike roof
JP2946074B2 (en) Large roof erection method
JP3242775B2 (en) Installation method of vertical container
CN110552542A (en) Construction method of conical building structure
JP3328790B2 (en) High-rise building assembly method
JP4571760B2 (en) Building construction method
JPH09256535A (en) Constructing method of dome type roof
JP3506022B2 (en) How to build a dome roof
JPH0617544A (en) Automatic reinforcing device of beam loaded with weight in temporarily installed machine
JPH07150771A (en) Installation structure for frame of cover body for external curing
JP2004059321A (en) Climbing crane and its climbing method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040527

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050622

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060516

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060919