CN104420656A - Traction tension forming mounting method of spherical rib annular type cable dome structure - Google Patents

Traction tension forming mounting method of spherical rib annular type cable dome structure Download PDF

Info

Publication number
CN104420656A
CN104420656A CN201310382531.7A CN201310382531A CN104420656A CN 104420656 A CN104420656 A CN 104420656A CN 201310382531 A CN201310382531 A CN 201310382531A CN 104420656 A CN104420656 A CN 104420656A
Authority
CN
China
Prior art keywords
rope
ring
cable
frock
traction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310382531.7A
Other languages
Chinese (zh)
Inventor
陈辉
赵荣耀
李旻
遇瑞
刘洪亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201310382531.7A priority Critical patent/CN104420656A/en
Publication of CN104420656A publication Critical patent/CN104420656A/en
Pending legal-status Critical Current

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention relates to construction mounting of a cable dome, in particular to a construction mounting method of the cable dome structure with glass bearing secondary cable net. Traction equipment and a tool cable are arranged at the corresponding position of the periphery slightly higher than an outer pressing ring of a cable dome and are connected with an outer ring ridge cable and an inner pulling ring component, the inner pulling ring and the outer ring ridge cable are evenly and synchronously pulled, and secondary cable nets, ring cables, supporting rod, inclined cables and the like are expanded and mounted while pulling lifting is carried out. When the ring cable on the outmost portion is away from the ground, mounting is completed; the outer ring ridge cable and an inner pulling ring tool are pulled synchronously until the outer ring ridge cable, the inclined cables and the secondary cable nets are connected in place, and final forming is achieved by stretching and drawing the inclined cable on the outmost ring. A large amount of arithmetical operation is not needed, and plenty of supporting tower trusses are eliminated.

Description

A kind of spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method
Technical field
The present invention relates to cable dome structure construction and installation, particularly relate to the cable dome structure construction installation method with glass support time rope net.
Background technology
Cable dome is made up of draw ring and outer press ring in notochord, oblique cord, strop, depression bar and necessity, belongs to the full tension structure system of prestressing force self-balancing, and it is the high structural system of a kind of reasonable stress, structure efficiency.Cable dome must pass through stretch-draw, sets up necessary prestressing force in the structure, just has the larger rigidity of structure, with bearing load and maintenance shape.More cable dome structure manufacturing process is adopted mainly to comprise geometric method installation, stretch-draw notochord manufacturing process etc. at present both at home and abroad, all need to carry out complicated mathematical operation and adopt a large amount of supporting tower frames just can complete installation, finally causing that difficulty of construction strengthens, the construction period compared with long, construction operation security risk is large.
Summary of the invention
The present invention is intended to the above-mentioned defect solving prior art, provides a kind of spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method.The present invention does not need to carry out a large amount of mathematical operations, eliminates a large amount of support tower yet.
For solving the problem, a kind of spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method of the present invention, described spherical rib-ring-shaped cable dome structure is with glass support time rope net, and it comprises:
1st step: install pulling equipment, traction tension operation platform on outer press ring beam, install lifting means in the position a little more than outer-ring beam;
2nd step: draw ring and notochord net in installation near the ground, installs between draw ring and promotes frock rope in Cable dome external pressure ring beam and ground, installs traction frock rope between outer press ring beam and ground outer shroud notochord;
3rd step: alternately promote and traction frock rope, mounting stay, strop, oblique cord and glass support time rope net, completes the assembling of rope leverage successively, strictly controls guy cable length and cord clip position in process, totally guarantees that rope leverage is in " ω " shape;
4th step: within draw ring to promote frock rope be main, with traction frock rope, whole rope leverage is promoted traction to high-altitude;
5th step: no longer promote close to during level when lifting frock rope and horizontal plane angle are less than 5 °, only draw outer notochord, make the rope head of outer notochord close to support lug;
6th step: draw the most outer shroud radial cable of outer notochord and glass support and be connected with support lug in place, remove and promote frock rope and traction frock rope;
7th step: by rope head adjusting device, suitably lengthen outer shroud oblique cord (12), draws the spreading frock rope of outer oblique cord, the upper rope head of outer oblique cord is connected with support lug, then removes spreading frock rope;
8th step: synchronous grading tension outer shroud oblique cord, force in control cable and position shape, based on force in control cable, make structure stretch-draw forming.
Described one spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method; It is characterized in that, it also comprises: the 9th step: adopt drag-line dynamometer to check outer shroud notochord and the radial cable force of glass support, carry out secondary mend stretch-draw for being caused the drag-line not reaching designing requirement by construction error.
Described one spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method, it is characterized in that, what described traction tension operation platform comprised that centre leaves a blank holds concurrently as the base of upper people's platform, base side is provided with two columns, diagonal member is provided with: column top also has inverted L shape suspended end, is provided with safety rope bottom suspended end and between column between column top and the base other end.
Described one spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method, described lifting frock rope is steel strand, and nominal Fracture Force is greater than 260kN; One end is provided with earth anchor and is pinned on interior draw ring otic placode, and promote the cylinder that frock is an open upper end lower end perforate, inside be provided with the centre-hole jack controlled by Boosting pumping station, openend is provided with an anchor ear and is fixed on traction tension operation platform, and described lifting frock rope is through the hole and the centre-hole jack that promote frock.
The present invention arranges pulling equipment according at the periphery correspondence position a little more than Cable dome outer press ring, frock rope, with outer shroud notochord, interior draw ring component is connected, draw ring and outer shroud notochord in even sync pulling, time rope net is installed in the expansion of traction enhancement limit, limit, each ring strop, strut, oblique cord etc., install after most outer shroud strop leaves ground, sync pulling outer shroud notochord, interior draw ring frock rope is until outer shroud notochord, oblique cord and secondary rope net connect in place, finally be shaped by the most outer shroud oblique cord of staged stretched, finally carry out cable force monitoring, to the hypodynamic outer shroud oblique cord of the stretch-draw caused by construction error, glass support rope carries out benefit stretch-draw.The present invention does not need to carry out a large amount of mathematical operations, eliminates a large amount of support tower yet, by the most outer shroud oblique cord of stretch-draw, is structural entity Tension Forming.Make the installation difficulty of Cable dome, stretch-draw difficulty significantly reduces, installation on ground construction can security risk reduce.The present invention installs for cable dome structure and has a wide range of applications.
Accompanying drawing explanation
Below in conjunction with accompanying drawing to further instruction of the present invention:
Fig. 1 is the 1st, 2 step schematic diagrames;
Fig. 2 is the 3rd step schematic diagram;
Fig. 3 is that 4-5 walks schematic diagram;
Fig. 4 is the 6th step schematic diagram;
Fig. 5 is the 7th step schematic diagram;
Fig. 6 is the 8th step schematic diagram;
Fig. 7 is that the operating platform schematic diagram that rises is drawn in described traction;
Fig. 8 is described lifting frock rope and promotes frock schematic diagram.
Detailed description of the invention
As shown in figs 1 to 6, in figure, 17 is ground, a kind of spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method, and described spherical rib-ring-shaped cable dome structure is with glass support time rope net, and it comprises:
1st step: install pulling equipment, traction tension operation platform 18 on outer press ring beam 13, install lifting means in the position a little more than outer-ring beam;
2nd step: draw ring 1 and notochord net 2,3,4 in installation near the ground, installs between draw ring 1 and promotes frock rope 14 in Cable dome external pressure ring beam 13 and ground, installs traction frock rope 15 between outer press ring beam 13 and ground outer shroud notochord 4;
3rd step: alternately promote and traction frock rope, mounting stay 6,8 successively, strop 10,11, oblique cord 5,7,12 and glass support time rope net 9, complete the assembling of rope leverage, strict control guy cable length and cord clip position in process, totally guarantee that rope leverage is in " ω " shape;
4th step: within draw ring to promote frock rope 14 be main, with traction frock rope 15, whole rope leverage is promoted traction to high-altitude;
5th step: no longer promote close to during level when lifting frock rope 14 is less than 5 ° with horizontal plane angle, only draw outer notochord 4, make the rope head of outer notochord 4 close to support lug 13;
6th step: draw the most outer shroud radial cable 9 of outer notochord 4 and glass support and be connected in place with support lug 13, remove and promote frock rope 14 and traction frock rope 15;
7th step: by rope head adjusting device, suitably lengthen outer shroud oblique cord 12, draws the spreading frock rope 16 of outer oblique cord, the upper rope head of outer oblique cord 12 is connected with support lug 13, then removes spreading frock rope 16;
8th step: synchronous grading tension outer shroud oblique cord 12, force in control cable and position shape, based on force in control cable, make structure stretch-draw forming.
9th step: adopt drag-line dynamometer to check outer shroud notochord 4 and glass support radial cable 9 Suo Li, carries out secondary for being caused the drag-line not reaching designing requirement by construction error and mends stretch-draw.
Described traction tension operation platform 18 comprises the base 181 of middle reserved drag-line and traction, tensioning equipment passage, base side is provided with two columns 182, diagonal member 183 is provided with: column top also has inverted L shape suspended end 184, is provided with safety rope 185 bottom suspended end and between column between column top and the base other end.
Described lifting frock rope 14 is steel strand, and nominal Fracture Force is greater than 260kN; One end is provided with earth anchor 141 and is pinned on interior draw ring otic placode 142, and promote the cylinder that frock 19 is an open upper end lower end perforate, inside be provided with the centre-hole jack 20 controlled by Boosting pumping station 21, openend is provided with an anchor ear 192 and is fixed on traction tension operation platform, and described lifting frock rope is through the hole and the centre-hole jack that promote frock.

Claims (4)

1. a spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method, described spherical rib-ring-shaped cable dome structure is with glass support time rope net, and it is characterized in that, it comprises:
1st step: install pulling equipment, traction tension operation platform on outer press ring beam (13), install lifting means in the position a little more than outer-ring beam;
2nd step: draw ring (1) and notochord net (2,3,4) in installation near the ground, install between draw ring (1) in Cable dome external pressure ring beam (13) and ground and promote frock rope (14), between outer press ring beam (13) and ground outer shroud notochord (4), traction frock rope (15) is installed;
3rd step: alternately promote and traction frock rope, mounting stay (6,8), strop (10 successively, 11), oblique cord (5,7,12) and glass support time rope net (9), complete the assembling of rope leverage, strict control guy cable length and cord clip position in process, totally guarantee that rope leverage is in " ω " shape;
4th step: within draw ring to promote frock rope (14) be main, with traction frock rope (15), whole rope leverage is promoted traction to high-altitude;
5th step: no longer promote close to during level when lifting frock rope (14) and horizontal plane angle are less than 5 °, only draw outer notochord (4), make the rope head of outer notochord (4) close to support lug (13);
6th step: draw the most outer shroud radial cable (9) of outer notochord (4) and glass support and be connected in place with support lug (13), remove and promote frock rope (14) and draw frock rope (15);
7th step: by rope head adjusting device, suitably lengthen outer shroud oblique cord (12), draws the spreading frock rope (16) of outer oblique cord, the upper rope head of outer oblique cord (12) is connected with support lug (13), then removes spreading frock rope (16);
8th step: synchronous grading tension outer shroud oblique cord (12), force in control cable and position shape, based on force in control cable, make structure stretch-draw forming.
2. one according to claim 1 spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method; It is characterized in that, it also comprises: the 9th step: adopt drag-line dynamometer to check outer shroud notochord (4) and glass support radial cable (9) Suo Li, carries out secondary mend stretch-draw for being caused the drag-line not reaching designing requirement by construction error.
3. one according to claim 1 spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method, it is characterized in that, what described traction tension operation platform comprised that centre leaves a blank holds concurrently as the base of upper people's platform, base side is provided with two columns, diagonal member is provided with: column top also has inverted L shape suspended end, is provided with safety rope bottom suspended end and between column between column top and the base other end.
4. one according to claim 1 spherical rib-ring-shaped cable dome structure traction stretch-draw forming mounting method, it is characterized in that, described lifting frock rope is steel strand, and nominal Fracture Force is greater than 260kN; One end is provided with earth anchor and is pinned on interior draw ring otic placode, and promote the cylinder that frock is an open upper end lower end perforate, inside be provided with the centre-hole jack controlled by Boosting pumping station, openend is provided with an anchor ear and is fixed on traction tension operation platform, and described lifting frock rope is through the hole and the centre-hole jack that promote frock.
CN201310382531.7A 2013-08-29 2013-08-29 Traction tension forming mounting method of spherical rib annular type cable dome structure Pending CN104420656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310382531.7A CN104420656A (en) 2013-08-29 2013-08-29 Traction tension forming mounting method of spherical rib annular type cable dome structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310382531.7A CN104420656A (en) 2013-08-29 2013-08-29 Traction tension forming mounting method of spherical rib annular type cable dome structure

Publications (1)

Publication Number Publication Date
CN104420656A true CN104420656A (en) 2015-03-18

Family

ID=52970711

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310382531.7A Pending CN104420656A (en) 2013-08-29 2013-08-29 Traction tension forming mounting method of spherical rib annular type cable dome structure

Country Status (1)

Country Link
CN (1) CN104420656A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013812A (en) * 2016-05-18 2016-10-12 东南大学 Support-free overhead zip line construction method of two-way single-layer cable net structure
CN107034992A (en) * 2017-06-07 2017-08-11 山东建筑大学 A kind of band winds up the Geiger dome structure and construction forming method of stiffening ring bar
CN107806205A (en) * 2017-09-20 2018-03-16 中国核工业华兴建设有限公司 A kind of mounting structure and installation method of unlined steel dome
CN109057362A (en) * 2018-09-05 2018-12-21 北京奇力建通工程技术有限公司 A kind of Suo Cheng network rope system traction tensioning integral construction method and equipment
CN113417368A (en) * 2021-06-07 2021-09-21 中建深圳装饰有限公司 High-space large-span fold-line-shaped cable membrane structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS646429A (en) * 1987-03-16 1989-01-11 Takenaka Komuten Co Construction of cable dome
JPH06101274A (en) * 1992-09-17 1994-04-12 Kumagai Gumi Co Ltd Method of constructing roof of cable dome
JP2002266434A (en) * 2001-03-08 2002-09-18 Mitsubishi Heavy Ind Ltd Method of constructing cable dome
CN101413291A (en) * 2008-11-12 2009-04-22 东南大学 Cable sky dome tower frame raising cable rod accumulation mounting method
CN102400560A (en) * 2011-08-03 2012-04-04 浙江东宸建设控股集团有限公司 Method for forming and mounting spherical-rib annular cable dome structure by stretching ridge cable once
CN102251616B (en) * 2011-05-03 2012-11-28 东南大学 Secondary cable net cable dome structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS646429A (en) * 1987-03-16 1989-01-11 Takenaka Komuten Co Construction of cable dome
JPH06101274A (en) * 1992-09-17 1994-04-12 Kumagai Gumi Co Ltd Method of constructing roof of cable dome
JP2002266434A (en) * 2001-03-08 2002-09-18 Mitsubishi Heavy Ind Ltd Method of constructing cable dome
CN101413291A (en) * 2008-11-12 2009-04-22 东南大学 Cable sky dome tower frame raising cable rod accumulation mounting method
CN102251616B (en) * 2011-05-03 2012-11-28 东南大学 Secondary cable net cable dome structure
CN102400560A (en) * 2011-08-03 2012-04-04 浙江东宸建设控股集团有限公司 Method for forming and mounting spherical-rib annular cable dome structure by stretching ridge cable once

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郭正兴,罗斌,杨杰,朱颖曾,仇荣根,陈骥赢: "刚性屋面索穹顶施工关键技术研究及工程应用", 《施工技术》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013812A (en) * 2016-05-18 2016-10-12 东南大学 Support-free overhead zip line construction method of two-way single-layer cable net structure
CN107034992A (en) * 2017-06-07 2017-08-11 山东建筑大学 A kind of band winds up the Geiger dome structure and construction forming method of stiffening ring bar
CN107034992B (en) * 2017-06-07 2019-10-18 山东建筑大学 A kind of band winds up the Geiger dome structure and construction forming method of stiffening ring bar
CN107806205A (en) * 2017-09-20 2018-03-16 中国核工业华兴建设有限公司 A kind of mounting structure and installation method of unlined steel dome
CN109057362A (en) * 2018-09-05 2018-12-21 北京奇力建通工程技术有限公司 A kind of Suo Cheng network rope system traction tensioning integral construction method and equipment
CN109057362B (en) * 2018-09-05 2021-06-22 北京奇力建通工程技术有限公司 Cable-supported grid structure cable system traction and tensioning integrated construction method and equipment
CN113417368A (en) * 2021-06-07 2021-09-21 中建深圳装饰有限公司 High-space large-span fold-line-shaped cable membrane structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN104420656A (en) Traction tension forming mounting method of spherical rib annular type cable dome structure
CN103615064B (en) A kind of Cable dome and installation method thereof
CN103321416B (en) Construction method for prestress of cable-stayed grid structure
CN104234200B (en) A kind of suspen-shell structure rope leverage is by ring lifting installation method
CN105401714A (en) Attachment type lifting scaffold and lifting method
CN103669885A (en) Segmental hoisting process of ultra-large-span steel truss
CN202882185U (en) Ribbed-type rigid grid cable dome
CN101845912A (en) Segmental-body assembly type emergency communication tower
CN101413291B (en) Accumulation mounting method for cable sky dome tower frame raising cable rod
CN113622576B (en) Swivel construction method for structural space of steel cover shed roof of ultra-large stadium
CN208899886U (en) Cantilever frame platform
CN104746883A (en) Construction method for three-crane lifting installation used for bow-shaped space truss
CN102251483A (en) Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN103266799B (en) Mast and installation technology thereof
CN104532850B (en) Foundation pit support system
CN109826082B (en) Construction method for installing decorative structure in multi-tower combined space of cable-stayed bridge
CN105672665A (en) Installation method for large-span double-layer cylindrical surface net shell
CN205100531U (en) Lift scaffold support body assembly
CN105016220B (en) A kind of pole guide support adding device
CN204216536U (en) A kind of high pressure suspension circuit sagging prevention device
CN102912989A (en) Installation method for steel reticulated shell and cable dome combined structure
CN104947953B (en) A kind of 10kV transmission line cement poles replacing options and the interim bar of replacing
CN107795185A (en) Chimney reinforces pylon high-altitude installation node security construction method
CN105417422B (en) A kind of packaged type independence derrick mast hoisting device and its hanging method
CN207700824U (en) A kind of body of rod draws high device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150318

RJ01 Rejection of invention patent application after publication