JP2002173926A - Revetment lining - Google Patents

Revetment lining

Info

Publication number
JP2002173926A
JP2002173926A JP2000374393A JP2000374393A JP2002173926A JP 2002173926 A JP2002173926 A JP 2002173926A JP 2000374393 A JP2000374393 A JP 2000374393A JP 2000374393 A JP2000374393 A JP 2000374393A JP 2002173926 A JP2002173926 A JP 2002173926A
Authority
JP
Japan
Prior art keywords
mat
bolts
mats
stone
revetment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000374393A
Other languages
Japanese (ja)
Inventor
Junichiro Saito
順一郎 斎藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TOYO KOSAN KK
Original Assignee
TOYO KOSAN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TOYO KOSAN KK filed Critical TOYO KOSAN KK
Priority to JP2000374393A priority Critical patent/JP2002173926A/en
Publication of JP2002173926A publication Critical patent/JP2002173926A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a metal fitting for mutually connecting mats laid and juxtaposed on a face of slope by adhering stone masses on an upper surface. SOLUTION: The mats stuck with the stone masses are closely laid and juxtaposed on the face of slope, and mutual peripheral edge parts of the adjacent mats are connected at an almost specific interval by a connecting metal fitting 3. The connecting metal fitting 3 has a pair of upper and lower slender sandwiching plates 5 and 6, two bolts 7 are implanted at an interval in the lower side sandwiching plate 5, and a hole 8 for passing these bolts is bored in the upper side sandwiching plate 6. The tip of the bolts 7 is pointed in a conical shape so as to be capable of piercing through the mats 1. The peripheral edge parts 1a of the mutually adjacent mats 1 are superposed, the sandwiching plate 5 with the bolts is applied to under these parts, and the two bolts 7 are pierced from below the mats 1. Thus, the sandwiching plate 6 having the hole 8 is passed through the bolts 7 appearing on the mats 1, and a nut 9 is threadedly engaged with and fastened to the respective bolts 7.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、河川や海岸の堤
防を覆って、洗掘や崩壊を防ぐための護岸覆工に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a revetment lining for covering a river or coastal dike to prevent scouring or collapse.

【0002】[0002]

【従来の技術】以前の護岸工事は、表面をコンクリート
ですっかり覆ってしまって生態系を分断してしまうもの
がほとんどであったが、最近は、自然をできるだけ保全
するために、コンクリートを使わずに、自然石や木材を
主体とする工事に変わりつつある。例えば、河川の法面
にまず吸出し防止マットを敷き、その上に鉄線かご(ふ
とんかご)や木製の枠体を置き、その中に玉石を詰め
る。しかし、このような方法では、現場で石詰めしなけ
ればならないので、工期が長く、工事費も高いものにつ
く。また、設置した金網や鉄線かごが表に現れるので、
自然の景観を損う。
2. Description of the Related Art In the past, revetment works were almost completely covered with concrete and cut off ecosystems. At the same time, construction is changing to mainly natural stone and wood. For example, a draft prevention mat is first laid on the slope of a river, and an iron wire basket (futon basket) or a wooden frame is placed on top of the mat, and cobblestone is stuffed into it. However, such a method requires stuffing stones at the site, so that the construction period is long and the construction cost is high. Also, the wire mesh and iron wire basket that you have set up will appear on the table,
Impair the natural landscape.

【0003】そこで、本特許出願人は先の特許出願(特
開平11−256546号公報)で、透水性のマットの
上面に、底を平坦に形成した石塊を密に接着し、これを
法面に敷き詰める護岸覆工を提案した。このものでは、
マットを敷くだけで護岸工事を行うことができ、石塊は
不定形のものを使用すれば、自然に近い景観が得られ
る。しかし、隣のマット同士を連結するために紐を用い
るようにしたが、この構造では施工がたいへん面倒であ
った。
[0003] In view of this, the present applicant filed a prior patent application (Japanese Patent Application Laid-Open No. H11-256546) to closely adhere a stone block having a flat bottom to the upper surface of a water-permeable mat, We proposed seawall lining to cover the surface. In this one,
The revetment work can be performed simply by laying a mat, and if the stone blocks are of irregular shape, a landscape close to nature can be obtained. However, strings are used to connect adjacent mats, but this construction is very troublesome.

【0004】[0004]

【発明が解決しようとする課題】この発明は、上面に石
塊を接着したマットの施工性を改善することを主な課題
とする。
SUMMARY OF THE INVENTION It is a main object of the present invention to improve the workability of a mat having a stone mass adhered to an upper surface.

【0005】[0005]

【課題を解決するための手段】石塊を接着したマットを
地面に敷き詰めた後、マットの間に隙間ができないよう
マットの周縁部同士を連結するが、この発明では、その
結合手段を、マットを挟む上下2枚の細長い挟持板と、
下側の挟持板に間隔をあけて植設され、マットを突き通
すように先端が尖っている複数本のボルトと、上側の挟
持板に設けた孔から突出するボルトに螺合緊締するナッ
トから構成する(請求項1)。このものでは、隣同士の
マットの縁部を重ね合わせ、下からボルトを突き通し、
ボルトに挟持板を挿通した後、ナットを螺合緊締する。
こうすることで、隣同士のマットが上下の挟持板の間に
は挟持され、互いにずれることがない。特に、ボルトの
先を尖らせてあるので、マットに孔をあけるまでもな
く、ボルトの先をマットに当てて、力を加えれば、簡単
にボルトをマットに突き通すことができるので、作業性
が優れる。ボルトの尖った先端は、そのままでは危険な
ので、ナットを締め終わってから、切断工具を使って切
り落とす。
After the mat to which the stone blocks are adhered is laid on the ground, the peripheries of the mats are connected to each other so that there is no gap between the mats. An upper and lower two elongated holding plates sandwiching the
Consists of a plurality of bolts that are planted at intervals on the lower holding plate and have sharp tips to penetrate the mat, and nuts that are screwed and tightened to bolts protruding from the holes provided in the upper holding plate (Claim 1). In this one, the edges of the mats next to each other are overlapped, bolts are pierced from below,
After inserting the holding plate through the bolt, the nut is screwed tight.
By doing so, the adjacent mats are sandwiched between the upper and lower sandwiching plates, and do not shift from each other. In particular, the point of the bolt is sharpened, so you can easily penetrate the mat by applying the force by applying the tip of the bolt to the mat without making a hole in the mat. Excellent. The sharp point of the bolt is dangerous as it is, so after tightening the nut, cut it off with a cutting tool.

【0006】2枚の該挟持板は、横断面で見たとき、山
型に形成すれば(請求項2)、マット同士をさらに確実
に挟持し、相互にずれることがない。また、2枚のうち
の少なくとも1枚の挟持板の対向面に凸部を形成しても
(請求項3)、同様の効果が得られる。
When the two holding plates are formed in a mountain shape when viewed in a transverse cross section (claim 2), the mats are more securely held between the mats and do not shift from each other. The same effect can be obtained even if a convex portion is formed on the facing surface of at least one of the two holding plates (claim 3).

【0007】マットを地面に固定するために、後部が逆
U字形に折曲され、杭の先端および後端が尖っている杭
を用いる(請求項4)。このような杭は、鉄筋などに用
いられている鋼棒を曲げ加工して安価に作ることがで
き、しかも、杭の後部がU字に曲がっていて、後端は尖
っているので、後端がマットに突き刺さり、マットがし
っかりと地面に固定され、めくれあがることがない。
In order to fix the mat to the ground, use is made of a pile whose rear part is bent in an inverted U-shape and whose tip and rear end are pointed. Such piles can be made inexpensively by bending steel rods used for steel bars, etc. In addition, the rear end of the pile is bent in a U shape and the rear end is sharp, so the rear end Penetrates the mat, the mat is firmly fixed to the ground, and does not turn up.

【0008】ところで、マットの上に接着する石塊は、
従来、天然石(例えば、花崗岩、安山岩、玄武岩)を用
いているが、このように直径が数十センチもある天然石
は安価には手に入らない。また、大量の天然石を採掘す
るとなると、少なからず自然破壊を招くことになる。そ
こで、本特許出願人は天然石と同等のものを人工的に作
ることを試みて成功した。原料は、ニッケル、マンガン
など鉱物の溶融精錬の際に溶融金属から分離してその上
に浮かぶ溶融スラグである。この溶融スラグを炉の外に
取り出し、大気中でゆっくり冷やし、鉱物を結晶化させ
る。結晶化には、特に1000℃から800℃の温度領域が重
要であり、この領域を2〜4時間位の長い時間をかけて
通過させるようにする。こうしてできる岩石を所望の大
きさに割って、石材として使用する。また、溶融スラグ
を型(モールド)に入れて徐冷すれば、底が平らのもの
など所望の形状の石材が得られ、加工コストが軽減され
る。こうして得られる石材は、天然石と成分、強度等が
ほとんど同じあり、天然石と区別なく使用することがで
きる。
[0008] By the way, the stone mass adhered on the mat is
Conventionally, natural stones (eg, granite, andesite, and basalt) are used, but such natural stones having a diameter of several tens of centimeters are not available at low cost. In addition, mining a large amount of natural stone will cause considerable destruction of nature. Thus, the present applicant has succeeded in artificially producing a natural stone equivalent. The raw material is a molten slag which is separated from the molten metal and floated on the molten metal during the refining of minerals such as nickel and manganese. The molten slag is taken out of the furnace and cooled slowly in the atmosphere to crystallize the mineral. For crystallization, a temperature range of 1000 ° C. to 800 ° C. is particularly important, and the material is allowed to pass through this range over a long time of about 2 to 4 hours. The resulting rock is divided into desired sizes and used as stone. In addition, if the molten slag is put into a mold and gradually cooled, a stone having a desired shape such as a flat bottom is obtained, and the processing cost is reduced. The stone thus obtained has almost the same components, strength and the like as natural stone, and can be used without distinction from natural stone.

【0009】溶融スラグは、ゴミ(産業廃棄物や家庭ゴ
ミ)を焼却処理したときに出る焼却灰を溶融して無害化
するときにも得られる。焼却灰は、ダイオキシンや重金
属等有害物質が含まれており、そのままでは捨てられな
い厄介者である。この焼却灰を塩基度調整剤(ドロマイ
ト、石灰石、貝殻など)および還元剤(粉状コークス)
と共に電気炉に入れて、1400〜1500℃前後の高温で還元
溶融する。こうすると、焼却灰は液状化しマグマのよう
な状態になり、灰の中に含まれているダイオキシン等の
有害物質は高温に晒されて分解気化し回収処理される。
また、焼却灰の中の重金属類(カドミウム、鉛、六価ク
ロム等)は、スラグと分離して炉底の溶融メタル中に溶
解し回収される。こうして、無害化された溶融スラグが
得られる。この溶融スラグでも、上述と同様に、徐冷し
て石材とすることができる。
[0009] Molten slag is also obtained when incinerated ash produced when incinerating waste (industrial waste and household waste) is melted and rendered harmless. Incinerated ash contains harmful substances such as dioxins and heavy metals, and is a troublesome person that cannot be discarded as it is. This incinerated ash is used as a basicity adjusting agent (dolomite, limestone, shell, etc.) and a reducing agent (powder coke)
Together with an electric furnace to reduce and melt at a high temperature of about 1400 to 1500 ° C. As a result, the incinerated ash liquefies and becomes a magma-like state, and harmful substances such as dioxin contained in the ash are exposed to high temperatures, decomposed and vaporized, and collected.
Heavy metals (cadmium, lead, hexavalent chromium, etc.) in the incineration ash are separated from the slag and dissolved in the molten metal at the bottom of the furnace to be recovered. Thus, the detoxified molten slag is obtained. This molten slag can also be gradually cooled to a stone material as described above.

【0010】要するに、マットの上面に接着する石塊
は、溶融スラグを炉の外に取り出して徐冷することで得
られる人工石を用いることができる(請求項5)。この
ような人工石を用いれば、天然石の採掘のために自然破
壊を招くことがなく、また、量産化すれば、コスト的に
も天然石に太刀打ちできる可能性がある。さらに、溶融
スラグの原料にゴミ焼却灰を用いるようにすれば、廃棄
物の有効活用が図れ、一挙両得である。
[0010] In short, an artificial stone obtained by taking molten slag out of a furnace and slowly cooling it can be used as the stone mass to be adhered to the upper surface of the mat (claim 5). The use of such artificial stones does not cause natural destruction due to mining of natural stones, and if mass-produced, there is a possibility that natural stones can compete with natural stones. Furthermore, if refuse incineration ash is used as the raw material of the molten slag, effective use of waste can be achieved, and both advantages are obtained.

【0011】[0011]

【発明の実施の形態】図1に示すように、上面に石塊2
を接着するマット1は、補強ネットを上に、ポリエステ
ル不織布を下にして張り合わせたものであり、ポリエス
テル不織布の目は、土はほとんど通過できないが、水分
は通過できるような粗さになっており、補強ネットは、
延びの少ない材料、例えばアラミド繊維やポリエステル
繊維などで作られている。マット1の周縁部1aは、約1
0cm幅で折り返し、縫い止めて補強する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIG.
The mat 1 for bonding is made by bonding a reinforcing net on top and a polyester non-woven fabric below. The eyes of the polyester non-woven fabric are so rough that soil can hardly pass through but moisture can pass through. , The reinforcement net,
It is made of a low elongation material such as aramid fiber or polyester fiber. The periphery 1a of the mat 1 is approximately 1
Fold it back at 0cm width, sew it and reinforce it.

【0012】マット1に接着する石塊2は、直径が15〜
50cm前後の自然石(玉石をはじめ、割石、野面石など)
をカッタで二分したものであり、そのカット面(平面)
2aに接着剤を塗ってマット1に貼り付ける。石塊2
は、天然石ではなく、上述のように溶融スラグを徐冷し
た人工石でもよい。石塊2は周縁部1aを残してマット
全面にほぼ密に貼り付ける。
The stone mass 2 adhered to the mat 1 has a diameter of 15 to
Natural stones of around 50cm (including cobblestone, split stone, field stone, etc.)
Is cut in half by a cutter, and its cut surface (plane)
2a is coated with an adhesive and attached to the mat 1. Stone block 2
Instead of natural stone, artificial stone obtained by gradually cooling molten slag as described above may be used. The stone blocks 2 are stuck almost densely over the entire surface of the mat except for the peripheral portion 1a.

【0013】なお、1枚のマット1は縦横2.0×1.5mの
大きさであり、石塊2を張り付けたときの重量は300〜1
500kgほどになる。運搬はパレットに載せて行う。
Each mat 1 has a size of 2.0 × 1.5 m in length and width, and a weight of 300 to 1 when the stone mass 2 is attached.
It will be about 500kg. Transport is carried on pallets.

【0014】このように、石塊を貼り付けたマットを図
2に示すように、法面に隙間なく敷き並べ、隣のマット
の周縁部同士をほぼ一定間隔を置いて連結金具3で連結
する。連結金具3は、図3に示すように、上下一対の細
長い挟持板5、6を有し、下側の挟持板5には、間隔を
あけて2本のボルト7が植設されており、上側の挟持板
6には、これらボルトが通る孔8があいている。ボルト
7の先端は、マット1を突き通すことができるよう円錐
状に尖っている。
As shown in FIG. 2, the mat on which the stone blocks are stuck is laid out on the slope without any gaps, and the peripheral edges of the adjacent mats are connected with the connecting fitting 3 at substantially constant intervals. . As shown in FIG. 3, the connection fitting 3 has a pair of upper and lower elongate holding plates 5, 6, and two bolts 7 are planted on the lower holding plate 5 at intervals. The upper holding plate 6 has a hole 8 through which these bolts pass. The tip of the bolt 7 is pointed in a conical shape so that the mat 1 can be penetrated.

【0015】連結金具3の使い方は、図4に示すよう
に、相隣接するマット1の周縁部1aを重ね合わせ、そ
の下にボルト付の挟持板5をあてがい、2本のボルト7
をマット1の下から突き通す。こうして、マット1の上
に現れたボルト7に、孔8のあいた挟持板6を通し、各
ボルト7にナット9を螺合して締め付ける。こうするこ
とで、2枚のマットは、上下の挟持板5、6の間にしっ
かりと挟み込まれ連結される。マットの挟み込みをより
確実にするために、2枚の挟持板5、6は単なる平板で
はなく、図示のように山型断面に形成するとよい。ま
た、挟持板の対向面に間隔を存して小さな凸部10を形
成しても効果がある。なお、ボルト7は、先端が尖って
いて危険なので、ナット9を締め終わったら、ナットの
先に突き出ている部分を、カッター工具を用いて切り取
る(図4鎖線)。このように先を切り落とすと、その部
分でボルトのねじ山が潰れるので、ナットの脱落を防止
する効果もある。
As shown in FIG. 4, the connecting bracket 3 is used in such a manner that the peripheral edges 1a of adjacent mats 1 are overlapped, and a clamping plate 5 with bolts is applied thereunder, and two bolts 7 are provided.
Through the bottom of the mat 1. In this way, the bolts 7 appearing on the mat 1 are passed through the holding plate 6 with the holes 8, and the nuts 9 are screwed into the bolts 7 and fastened. In this way, the two mats are firmly sandwiched between the upper and lower sandwiching plates 5 and 6 and connected. In order to more reliably hold the mat, the two holding plates 5 and 6 are not merely flat plates but may be formed in a mountain-shaped cross section as shown in the figure. It is also effective to form small projections 10 at intervals on the opposing surface of the holding plate. Since the bolt 7 has a sharp pointed tip and is dangerous, when the nut 9 has been tightened, the protruding portion of the nut is cut off using a cutter tool (dotted line in FIG. 4). If the tip is cut off in this way, the thread of the bolt is crushed at that portion, and there is also an effect of preventing the nut from falling off.

【0016】次いで、マット1を地面に固定するために
要所要所に杭11を打つ。図5に示すように、杭11は
先端が尖った金属製の棒であり、後部はU字型11aに
折曲しており、後端も先端同様尖っている。このような
杭を、マットの周縁部1aを貫くように地中に打ち込
む。杭は、その後端もマットを貫いて地中に入るまで、
打ち込む。こうして、マットは、杭の後部U字型部11
aでしっかり抑えられるので、マットが地面からめくれ
あがることがない。杭の本数は、マット1枚当たり、1.
5〜2本位でよい。
Next, a stake 11 is struck at a required position to fix the mat 1 to the ground. As shown in FIG. 5, the stake 11 is a metal rod with a sharp pointed tip, the rear part is bent into a U-shape 11a, and the rear end is sharpened like the tip. Such a pile is driven into the ground so as to penetrate the periphery 1a of the mat. Until the stake goes into the ground through the mat at the rear end,
Drive in. In this way, the mat is connected to the rear U-shaped part 11 of the pile.
The mat does not turn up from the ground because it is firmly held down by a. The number of piles is 1.
5 or 2 is fine.

【0017】図7は、このようにしてマットを施工した
護岸を示す。なお、水辺では、マットの上に間詰の砂利
を敷き、石塊と石塊の間の隙間をこの砂利で埋めるよう
にする。こうすれば、一つ一つの石塊2が動きにくくな
り、全体として流れに対し強度が増す。特に河床部では
洗掘に備えて、マットの上に充分厚く寄せ石12を敷
く。水辺より上にはマット上に覆土をし、さらに好まし
くは植栽を施す。植物の根はマットを通ってその下にま
で延びるので、マットが地面に強固に固定される。法面
肩部では、マットに充分な量の覆土13を被せ、マット
がめくりあがらないようにする。
FIG. 7 shows the revetment on which the mat is constructed in this manner. At the waterside, shingled gravel is laid on the mat, and the gap between the stone blocks is filled with the gravel. This makes it difficult for the individual stone blocks 2 to move, and increases the strength against the flow as a whole. In particular, in the riverbed portion, a parquet stone 12 is laid sufficiently thick on the mat in preparation for scouring. Above the waterside, cover the soil on a mat, and more preferably plant. The roots of the plant extend through and beneath the mat, so that the mat is firmly fixed to the ground. At the slope shoulder, a sufficient amount of cover soil 13 is placed on the mat so that the mat does not turn over.

【0018】このような護岸では、石塊2が、杭によっ
て地面に固定されたマット1に接着されており、流水に
洗われても、石塊は押し流されることなく、法面や河床
を洗掘から保護する。石塊の間に詰めた砂利も、石塊に
支えられ、押し流されることはない。他方、マット1
は、石塊2の間から土が吸し出されるのを防止する。マ
ットの上を植栽で覆った場合、植栽の根がマット1の目
を通過して、土の中にまで伸び、マットを法面に強固に
固定するので、一層強固な護岸となる。
In such a revetment, the stone blocks 2 are adhered to the mat 1 fixed to the ground by piles, and even if washed by running water, the stone blocks are not washed away and the slopes and riverbeds are washed. Protect from digging. The gravel packed between the blocks is also supported by the blocks and is not washed away. On the other hand, mat 1
Prevents the soil from being sucked out from between the stone blocks 2. When the mat is covered with the planting, the roots of the planting pass through the eyes of the mat 1 and extend into the soil, and the mat is firmly fixed to the slope, so that the seawall is further strengthened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 石塊を接着したマットの要部斜視図である。FIG. 1 is a perspective view of a main part of a mat to which a stone block is adhered.

【図2】 マットの施工状態を平面および断面で示した
ものである。
FIG. 2 is a plan view and a cross-sectional view illustrating a construction state of a mat.

【図3】 接続金具の斜視図である。FIG. 3 is a perspective view of a connection fitting.

【図4】 接続金具の使用状態断面図である。FIG. 4 is a sectional view of a use state of the connection fitting.

【図5】 杭の立面図である。FIG. 5 is an elevation view of a pile.

【図6】 護岸覆工の施工状態を示す断面図である。FIG. 6 is a cross-sectional view showing a construction state of revetment lining.

【符号の説明】[Explanation of symbols]

1 マット 2 石塊 3 連結金具(結合手段) 5 下部挟持板 6 上部挟持板 7 ボルト 8 孔 9 ナット 10 凸部 11 杭(固定手段) 11a 杭のU字部 DESCRIPTION OF SYMBOLS 1 Mat 2 Stone block 3 Connection metal fitting (connection means) 5 Lower holding plate 6 Upper holding plate 7 Bolt 8 Hole 9 Nut 10 Convex part 11 Pile (fixing means) 11a U-shaped part of pile

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 上面に石塊を接着したマットと、地面に
敷き詰められた該マットの周縁部同士を結合する手段
と、該マットを地面に固定する手段を備えた護岸覆工に
おいて、該結合手段が、該マットを挟む上下2枚の細長
い挟持板と、下側の該挟持板に間隔をあけて植設され、
該マットを突き通すように先端が尖っている複数本のボ
ルトと、上側の該挟持板に設けた孔から突出する該ボル
トに螺合緊締するナットから成ることを特徴とする護岸
覆工。
1. A revetment lining comprising a mat having a stone mass adhered to an upper surface thereof, means for joining peripheral edges of the mat laid on the ground, and means for fixing the mat to the ground. Means are implanted in the upper and lower two elongated holding plates sandwiching the mat and the lower holding plate at intervals.
A seawall lining, comprising: a plurality of bolts, each having a sharp tip so as to penetrate the mat, and a nut screwed into the bolt protruding from a hole provided in the upper holding plate.
【請求項2】 2枚の該挟持板が、横断面で見たとき、
山型をなしている請求項1に記載の護岸覆工。
2. When the two holding plates are viewed in cross section,
The revetment lining according to claim 1, wherein the revetment has a mountain shape.
【請求項3】 2枚のうちの少なくとも1枚の該挟持板
の対向面に凸部を形成した請求項1に記載の護岸覆工。
3. The revetment lining according to claim 1, wherein a convex portion is formed on an opposing surface of at least one of the two holding plates.
【請求項4】 該固定手段が杭で構成され、該杭は、後
部が逆U字形に折曲され、先端だけでなく後端も尖って
いる請求項1に記載の護岸覆工。
4. The seawall lining according to claim 1, wherein the fixing means is constituted by a pile, and the pile is bent in an inverted U-shape, and not only the front end but also the rear end is pointed.
【請求項5】 該石塊が溶融スラグを炉の外に取り出し
て徐冷した人工石から成る請求項1に記載の護岸覆工。
5. The revetment lining according to claim 1, wherein said mass of stone is made of artificial stone which has been taken out of a furnace and gradually cooled.
JP2000374393A 2000-12-08 2000-12-08 Revetment lining Pending JP2002173926A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000374393A JP2002173926A (en) 2000-12-08 2000-12-08 Revetment lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000374393A JP2002173926A (en) 2000-12-08 2000-12-08 Revetment lining

Publications (1)

Publication Number Publication Date
JP2002173926A true JP2002173926A (en) 2002-06-21

Family

ID=18843591

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000374393A Pending JP2002173926A (en) 2000-12-08 2000-12-08 Revetment lining

Country Status (1)

Country Link
JP (1) JP2002173926A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011056505A (en) * 2010-10-15 2011-03-24 Shibata Industrial Co Ltd Impervious sheet structure
JP2011518268A (en) * 2008-04-22 2011-06-23 アントン カナンド, Flood, coastal or puddle protection device and method
CN108193643A (en) * 2018-02-06 2018-06-22 国合凯希水体修复江苏有限公司 A kind of channel revetment device
KR20180096939A (en) * 2017-02-22 2018-08-30 영원산업개발 주식회사 A connector of a mat using of coconut and the establishment method using it
KR20200022152A (en) * 2018-08-22 2020-03-03 김희운 Stone net ecology weir having structure functional

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011518268A (en) * 2008-04-22 2011-06-23 アントン カナンド, Flood, coastal or puddle protection device and method
JP2011056505A (en) * 2010-10-15 2011-03-24 Shibata Industrial Co Ltd Impervious sheet structure
KR20180096939A (en) * 2017-02-22 2018-08-30 영원산업개발 주식회사 A connector of a mat using of coconut and the establishment method using it
KR101984534B1 (en) * 2017-02-22 2019-05-31 영원산업개발 주식회사 A connector of a mat using of coconut and the establishment method using it
CN108193643A (en) * 2018-02-06 2018-06-22 国合凯希水体修复江苏有限公司 A kind of channel revetment device
KR20200022152A (en) * 2018-08-22 2020-03-03 김희운 Stone net ecology weir having structure functional
KR102299844B1 (en) * 2018-08-22 2021-09-07 김희운 Stone net ecology weir having structure functional

Similar Documents

Publication Publication Date Title
JP5235793B2 (en) Protective net construction method for falling rocks, etc.
US4804293A (en) Flexible layer structure for protecting earthworks, bed walls and for delimiting embedding layers
Theisen The role of geosynthetics in erosion and sediment control: An overview
US11117075B2 (en) Composite filter sock anchors, compost filter sock assemblies and method of forming same
JP2002173926A (en) Revetment lining
JP3083250B2 (en) Slope reinforcement and greening
JP3086874U (en) Revetment lining
CN108396752A (en) A kind of assembled side slope protection flexible net and its construction method
CN109898528A (en) A kind of high slope piling strtucture and constructing operation method
JP2002309582A (en) Protective structure for face of slope, wall face, waterside face or the like
JP2001011838A (en) Greening method
CN110234813A (en) Barricade with reinforced earth
JP3081829U (en) Stairs and steps unit
CN110089303A (en) One kind moving spliced mining junkyard and temporarily plants raw repair module and its construction method
CN203583437U (en) Pile-net dinas dam mudflat enclosure hydraulic structure
JP4372632B2 (en) Slope greening method
JPH10280360A (en) Mat having mass bodies arranged in connected state
JP3053376U (en) Seawall
JP2021032026A (en) Revetment structure, and construction method of the same
JP2007224507A (en) Slope greening method
JPH09324428A (en) Gabion bag
JP2001008547A (en) Vegetation mat and its production
CN218861469U (en) Stable protection structure for river and pond side slope
KR100641583B1 (en) The method of building the reinforced earth wall
JPH09285772A (en) Treating plant for waste

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040721

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040806

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20041215