JP2001336286A - Skeleton execution module in lamination method - Google Patents

Skeleton execution module in lamination method

Info

Publication number
JP2001336286A
JP2001336286A JP2000158563A JP2000158563A JP2001336286A JP 2001336286 A JP2001336286 A JP 2001336286A JP 2000158563 A JP2000158563 A JP 2000158563A JP 2000158563 A JP2000158563 A JP 2000158563A JP 2001336286 A JP2001336286 A JP 2001336286A
Authority
JP
Japan
Prior art keywords
beams
construction
skeleton
crane
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000158563A
Other languages
Japanese (ja)
Inventor
Shinobu Yamazaki
忍 山崎
Hikari Furuguchi
光 古口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2000158563A priority Critical patent/JP2001336286A/en
Publication of JP2001336286A publication Critical patent/JP2001336286A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a skeleton execution module capable of rationalizing the fitting work of a horizontal member with a horizontal shifting device dedicated in a divided execution area and shortening an execution cycle with the load reduction of a large crane in the skeleton construction work. SOLUTION: This skeleton execution module of a frame structure has a conveying means used for installing the horizontal member in a size of nearly the whole of the divided execution area. A frame 1 comprises a plurality of parallel upper beams 11 and required lines of auxiliary beams 12 provided between the upper beams to integrally connect the upper beams 11. A shifting means comprises an overhead traveling crane 13 traveling horizontally and vertically in the plane of the execution area supported by the upper beams 11. Mast sections 14 wholly installed on steel frame girders 2 or the like are provided below the end sections of the upper beams 11. A weight can be moved in the lump by the crane to the next execution area according to the skeleton execution of a floor.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、大型鉄骨造の積
層工法における躯体構築作業を対象とする躯体施工用モ
ジュールに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a skeleton building module for a skeleton building operation in a large steel frame laminating method.

【0002】[0002]

【発明が解決しようとする課題】柱、大梁、小梁、デッ
キプレートなどの組立てに続いて床コンクリートを打設
して、1フロアーづつ躯体を固めながら上方へと施工を
伸ばしてゆく積層工法では、1フロアー以上の落差がな
い環境下で、しかも確りしたコンクリート床からアプロ
ーチできるため、鉄骨建方作業の安全性の向上、溶接作
業等の能率向上を始めメリットは多い。
The laminating method in which the concrete is cast after the assembling of pillars, girders, small beams, deck plates, etc., and then the construction is extended upward while solidifying the frame by floor. In the environment where there is no drop of more than one floor and the approach can be made from the concrete floor, there are many merits such as improvement of the safety of the steel frame construction work and improvement of the efficiency of the welding work and the like.

【0003】しかしながら、鉄骨建方を先行する施工法
に比べると、溶接やコンクリート打設など天候に左右さ
れ易い工程が躯体構築工程上、非常にクリチカルとな
り、工程の圧縮調整が難しい欠点がある。このような積
層工法における課題の解決手段の1つとして、出来る限
り水平方向部材をユニット化し、コンクリート打設まで
の鉄骨建方サイクルを圧縮する方法が考えられる。しか
し、ユニット化にはかなりの広さの仮組ヤードが必要と
なり、敷地余裕のない建設現場では実施困難な場合が多
く、その採用にも制限を受けるという新たな課題を有す
る。
[0003] However, compared to the construction method that precedes the steel-frame construction method, a process that is easily influenced by the weather, such as welding or concrete casting, is very critical in the frame building process, and there is a disadvantage that it is difficult to adjust the compression of the process. As one of the means for solving the problem in such a laminating method, a method of uniting the horizontal members as much as possible and compressing the steel frame construction cycle until concrete placement is conceivable. However, unitization requires a considerably large temporary assembly yard, which is often difficult to implement on construction sites where there is not enough room, and there is a new problem in that its adoption is also restricted.

【0004】この発明の目的は、小梁やデッキプレート
等の水平部材のユニット化によらず、施工エリア内専用
の水平移送デバイスによる水平部材の取付作業の合理化
と、躯体構築作業での大型クレーンの負荷低減とによる
施工のサイクル短縮とを可能となし、これらにより上記
積層工法における上記課題を解決することができる新た
な躯体施工用モジュールを提供することにある。
An object of the present invention is not to unitize a horizontal member such as a small beam or a deck plate, but to rationalize an operation of mounting a horizontal member by a dedicated horizontal transfer device in a construction area and a large crane for a frame building operation. Another object of the present invention is to provide a new module for constructing a skeleton, which makes it possible to shorten the construction cycle by reducing the load on the structure, and to solve the above-mentioned problems in the above-mentioned laminating method.

【0005】[0005]

【課題を解決するための手段】上記目的によるこの発明
は、積層工法により建築する建物平面を、所要数の同形
の施工エリアに区分し、その1施工エリアの略全体に及
ぶ大きさで小梁、デッキプレート等の小部材の取付けに
使用する搬送手段を具備し、1フロアーの躯体施工に合
わせて次の施工エリアへの一括移動がクレーンなどによ
り可能なフレーム構造の躯体施工用モジュールであつ
て、複数列の並行な上部ビームと、上部ビーム間に設け
られて上部ビームを一体に接合する所要数列の補助ビー
ムとから構成された上記フレームと、上部ビームに支持
されて施工エリアの面内を縦横に走行する天井走行クレ
ーンと、各上部ビームの端部下側に設けられて全体を鉄
骨大梁又は鉄骨柱の仮設ブラケット等に設置するマスト
部とからなるというものである。
SUMMARY OF THE INVENTION The present invention according to the above object divides a building plane constructed by a laminating method into a required number of construction areas having the same shape, and has a small beam having a size covering substantially the whole of one construction area. A frame construction module having a transport means used for mounting small members such as deck plates and the like, and which can be collectively moved to the next construction area by a crane or the like in accordance with the framework construction on one floor. A plurality of parallel upper beams, the above-mentioned frame composed of a required number of auxiliary beams provided between the upper beams and integrally joining the upper beams, and in the plane of the construction area supported by the upper beams. It consists of an overhead traveling crane that travels vertically and horizontally, and a mast that is provided below the end of each upper beam and that is installed entirely on a steel beam or a temporary bracket of a steel column. Than it is.

【0006】このような構成の躯体施工用モジュールで
は、下記効果を期待することができる。 施工エリア全体を網羅した水平移送デバイスが提供
されるので、小部材の取付け、まくばり、敷設などの作
業が大幅に省力化され、配員の削減、施工エリアの作業
時間の短縮が期待できる。
The following effects can be expected from the skeleton-constructing module having such a configuration. Since a horizontal transfer device that covers the entire construction area is provided, work such as installation, rolling, and laying of small members can be greatly reduced, personnel can be reduced, and work time in the construction area can be reduced.

【0007】 垂直(荷揚げ)揚重と水平(取付け、
まくばり、敷設等)、搬送が分離できるので大型クレー
ンの負荷を低減でき、他の重作業での大型クレーンの活
用が可能となる。
[0007] Vertical (unloading) lifting and horizontal (mounting,
(Swing, laying, etc.) and transportation can be separated, so the load on the large crane can be reduced, and the large crane can be used for other heavy work.

【0008】 施工エリア内専用の移送デバイスが供
給されることで取付け手順の変更やトラブルが発生して
も対応しやすく、大型クレーンの稼働や全体工程への影
響抑制効果も期待できる。
[0008] By supplying a dedicated transfer device in the construction area, it is easy to respond to a change in the installation procedure or a trouble, and an effect of suppressing the operation of a large crane and the entire process can be expected.

【0009】 移送デバイスが架空式となるので、施
工エリア内に持ち込んだ床上走行のハンドリング装置
(たとえばフォークリフト)などで小部材のハンドリン
グ作業を行う場合に比べて、コンクリートスラブへの強
度的配慮や床段差、開口対応などが不要となる。床上を
資材仮置きヤードとして有効活用できるとともに、狭い
エリアで作業員とハンドリング装置が交錯することもな
いので安全上のメリットも期待できる。
[0009] Since the transfer device is of an imaginary type, compared with the case of handling small members using a handling device (for example, a forklift) for traveling on the floor brought into the construction area, consideration is given to the strength of the concrete slab and the floor. Steps, openings and the like are not required. The floor can be used effectively as a temporary material storage yard, and safety benefits can be expected because workers and handling equipment do not intersect in a small area.

【0010】 大スパンに対応できる簡易搬送設備付
きの作業モジュールとして汎用性があり、不使用時の他
用途への転用も可能である。たとえば、地上においては
鉄筋先組みやPC加工ヤードを始めとするサイトファク
トリーの作業設備そのものとして利用できる。そのよう
な場合には、開閉式の雨養生、風養生を付加して地上に
設置することで作業能率や作業環境の改善に一層の効果
を期待でき、場合によっては、マスト部下面ローラなど
の移動デバイスを具備させることで移動式とすることも
可能である。
It is versatile as a work module with simple transport equipment that can handle large spans, and can be diverted to other uses when not in use. For example, on the ground, it can be used as the work equipment of a site factory such as a rebar pre-assembly or a PC processing yard. In such a case, it is possible to expect a further effect on the improvement of work efficiency and work environment by installing on the ground by adding a rain-curing and wind-curing that can be opened and closed. A mobile device can be provided by providing a mobile device.

【0011】[0011]

【発明の実施の形態】図中1は、1施工エリアの略全体
に及ぶ大きさの躯体施工用モジュールのフレームで、等
間隔に配置した3列の上部ビーム11,11と、それら
上部ビーム11,11の両端部間及び中間部間に配設さ
れて、上部ビーム11,11を一体に接合する4列の補
助ビーム12,12とからなる。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS In the drawing, reference numeral 1 denotes a frame for a frame construction module having a size substantially covering the entire construction area. Three rows of upper beams 11, 11 arranged at equal intervals, and the upper beams 11 , 11 are arranged between both ends and between the intermediate portions, and are composed of four rows of auxiliary beams 12, 12 for integrally joining the upper beams 11, 11.

【0012】13は施工エリアの面内を縦横に走行する
天井走行クレーン、14はフレーム全体を鉄骨大梁又は
鉄骨柱の仮設ブラケット等に設置するマスト部で、各上
部ビーム11,11の端部下側に設けられている。
Reference numeral 13 denotes an overhead traveling crane that travels vertically and horizontally in the plane of the construction area. Reference numeral 14 denotes a mast for installing the entire frame on a steel beam or a temporary bracket of a steel column. It is provided in.

【0013】上記上部ビーム11及び補助ビーム12と
マスト部14の各部材は、現場で簡単に組み払しできる
軽量の立体トラス材を用いて構成されている。また上部
ビーム11,11に支持される上記天井走行クレーン1
3は、搬送対象となる部材が軽量であることと、1フロ
アー分の揚程があればよいことから、巻き上げのみを動
力化し、横行、走行についてはすべて手動で簡便に資材
移送ができる簡易の懸垂型天井クレーン(以下ライトク
レーン)を採用し、上部ビーム11,11の複数の上弦
材から吊りチェーンあるいはワイヤロープとターンバッ
クルなどで構成した高さ調整自在な吊り材15,15を
介して、適当なピッチで懸垂支持してある。
The members of the upper beam 11, the auxiliary beam 12, and the mast portion 14 are made of a lightweight three-dimensional truss material that can be easily assembled and disassembled on site. The overhead traveling crane 1 supported by the upper beams 11, 11
No. 3 is a simple suspension which can be used only for hoisting because only the material to be conveyed is light and the lift for one floor is sufficient. A type overhead crane (hereinafter referred to as a light crane) is used, and a plurality of upper chords of the upper beams 11, 11 can be appropriately adjusted via suspension chains 15, wire ropes, turnbuckles, and other height-adjustable suspension members 15, 15. Suspended at a great pitch.

【0014】このような吊り材15,15では高さ調整
が可能なことから、上部ビーム11,11に垂直方向の
撓みが生じても、簡単に走行レール13aのレベル出し
が可能となる。また吊り材15の下方端末はレール上部
に取付けられて、図では省略しているが、全方向に首振
り可能なボールジョイントを組み込んだジョイント金物
に接続される。
Since the height of the hanging members 15 can be adjusted, even if the upper beams 11 are bent in the vertical direction, the level of the traveling rail 13a can be easily set. The lower end of the suspension member 15 is attached to the upper part of the rail, and is connected to a joint fitting incorporating a ball joint that can swing in all directions, although not shown in the drawing.

【0015】図に示す実施形態では、上部ビーム11,
11の下面に走行レール13aが懸垂により配置してい
る。各走行レール13a内にはレールに沿って走行可能
な低摺動な走行サドル(図示せず)が挿入され、この走
行サドルは連結して1本の剛体化された横行レール13
bに連結される。このとき走行サドル下部と横行レール
13bの上面間には上記と同様なボールジョイントを組
み込んだジョイント金物が挿入されている。横行レール
13bには横行トロリー13cが挿入され、その下方に
は例えば490kg吊りの電動チェーンブロック等の揚
貨装置が懸垂される。
In the embodiment shown in the figures, the upper beams 11,
A traveling rail 13 a is suspended from the lower surface of the vehicle 11. A low-sliding traveling saddle (not shown) that can travel along the rail is inserted into each traveling rail 13a, and this traveling saddle is connected to one rigidized transverse rail 13.
b. At this time, a joint fitting incorporating a ball joint similar to the above is inserted between the lower portion of the traveling saddle and the upper surface of the traversing rail 13b. A trolley 13c is inserted into the traverse rail 13b, and a lifting device such as an electric chain block suspended from, for example, 490 kg is suspended below the trolley 13c.

【0016】上記構成によるライトクレーンは、従来の
天井走行クレーンと異なり、レールなどの設置精度がそ
れほど要求されず、上部ビーム11,11が若干量弾性
変形しても吊り材15,15やレール等が部材レベルで
姿勢を変えられるので支障なく作業出来ることを最大の
特徴としている。
Unlike the conventional overhead traveling crane, the light crane having the above configuration does not require much installation accuracy of rails and the like, and even if the upper beams 11, 11 are slightly elastically deformed, the suspension members 15, 15, the rails, etc. The greatest feature is that the work can be performed without any trouble because the posture can be changed at the member level.

【0017】上部ビーム11,11及び補助ビーム1
2,12により構成されたフレーム1を支える上記マス
ト部14,14は、その下面に躯体として先行設置され
た大梁鉄骨2の上部フランジの上面に荷重伝達するブラ
ケット(図は省略)を具備している。このブラケットと
大梁鉄骨2の上部フランジ間はクランプやピンなどで簡
易に接合できる構造にすると共に、地震や風による水平
力によりモジュール全体が移動又は落下しないように大
梁鉄骨2又は四周の柱3にずれ止めができる金物を合わ
せて装備している。
Upper beam 11, 11 and auxiliary beam 1
The mast portions 14, 14 supporting the frame 1 constituted by the frames 2, 12 are provided with brackets (not shown) for transmitting a load to the upper surface of the upper flange of the girder steel beam 2 previously installed as a frame on the lower surface thereof. I have. The structure between the bracket and the upper flange of the girder steel frame 2 is such that it can be easily joined with a clamp or a pin. Equipped with hardware that can prevent slippage.

【0018】このような構成の躯体施工用モジュールを
用いて、積層工法により躯体を構築するシーケンスを図
3以下に示す。なお、この説明では躯体施工用モジュー
ルを大梁鉄骨2に設置しているが、その設置の仕方は鉄
骨柱の仮設ブラケットの場合でも変わるところがないの
で、重複説明を避けるため仮設ブラケットについては省
略する。
A sequence for constructing a skeleton by the laminating method using the skeleton building module having such a configuration is shown in FIG. 3 and thereafter. In this description, the skeleton building module is installed on the girder steel frame 2. However, since the manner of installation does not change even in the case of a temporary bracket of a steel column, the temporary bracket is omitted to avoid redundant description.

【0019】図3は適用する建物の斜視である。この建
物5では、構造の複雑なコア部分を先行構築し、周囲の
ウイング部を8工区の施工エリアに分けて順に施工する
ケースを考える。各施工エリアの平面形状は図4に示す
ような矩形で全て同形であり、N階の施工は鉄骨から始
まり、大型クレーン4により柱3、大梁鉄骨2の建方を
行う。
FIG. 3 is a perspective view of a building to which the present invention is applied. In this building 5, a case is considered in which a complicated core part of the structure is pre-constructed, and the surrounding wings are divided into eight construction areas and constructed in order. The construction shape of each construction area is a rectangle as shown in FIG. 4, and all constructions are the same. The construction on the Nth floor starts with a steel frame, and a large crane 4 constructs the columns 3 and the girders 2.

【0020】鉄骨建方作業者は次の施工エリアに移動す
るが、鉄骨完了の施工エリアでは小梁及びデッキプレー
トの敷設作業が行われる。このときに図5に示すよう
に、躯体施工用モジュールを既設の大梁鉄骨2の上に大
型クレーン4で吊り込んで簡易設置する。設置後に上記
ライトクレーンを使用して、小梁6及びデッキプレート
7の取付け等の作業を行う。重量がやや重い部材或いは
長尺デッキプレート等の吊り込みは、2台のライトクレ
ーンの相番で行うことができる。またこれらの作業は積
層工法の特徴であるコンクリートの床上作業となり、小
型の高所作業車を利用すれば、安全かつ効率よくこれら
の作業が行える。
The steel frame construction worker moves to the next construction area, but in the construction area where the steel frame is completed, the work of laying small beams and deck plates is performed. At this time, as shown in FIG. 5, the skeleton building module is suspended by a large crane 4 on the existing girder steel frame 2 and is simply installed. After the installation, the light beam crane is used to perform operations such as mounting the small beams 6 and the deck plate 7. Suspension of a slightly heavy member or a long deck plate can be performed using two light cranes. In addition, these operations are performed on a concrete floor, which is a feature of the laminating method, and these operations can be performed safely and efficiently by using a small aerial work vehicle.

【0021】一方、この間に大型クレーン4は小部材の
まとめ揚げを行えばよく、1施工エリアの荷揚げは短時
間で完了して、他の部位の揚重作業に引当ることが可能
となる。また床鉄筋のまくばりにも省力化が期待でき
る。
On the other hand, the large crane 4 only has to carry out the unloading of the small members during this time, and the unloading of one construction area is completed in a short time, and it becomes possible to use it for the lifting work of other parts. Labor savings can also be expected in the roll-up of floor reinforcement.

【0022】小梁6及びデッキプレート7の施工が完了
したならば、躯体施工用モジュールジュールを大型クレ
ーン4で吊り上げて、次の隣の施工エリアに一括移動
し、大梁鉄骨2の上方に盛替えて使用する。盛替作業も
フレーム1及びマスト部4、ライトの全てがユニット化
されていることに加え、ライトクレーン自体に寸法上の
フレキビリティがあるため、盛替え時の設置位置精度や
全体の変形をそれほど気にしなくともよいので、極めて
短時間の作業で済むことになる。
When the construction of the beams 6 and the deck plates 7 is completed, the module joules for frame construction are lifted by the large crane 4 and moved collectively to the next construction area, and are relocated to the upper part of the steel beams 2. To use. In addition to the uniting of the frame 1, the mast section 4, and the light, the light crane itself has dimensional flexibility, so the installation position accuracy and overall deformation during the refilling are not so much. Since the user does not need to worry, the work can be performed in a very short time.

【0023】このように、この発明の躯体施工用モジュ
ールでは、施工エリア全体を網羅した水平移送デバイス
が提供されるので、小梁6やデッキプレート7等の小部
材にかかわる施工作業が大幅に省力化され、施工エリア
での作業時間の改善や大型クレーンの負荷低減による他
の重作業での活用が可能となり、施工手順の変更やトラ
ブルの発生にも対応できることから、大型クレーンの稼
働や全体工程への影響抑制効果も期待できるとともに、
施工エリア内での移送デバイスが架空式となるので、コ
ンクリートスラブへの強度的配慮や床段差、開口などの
対応手段も不要となる。
As described above, in the module for building a skeleton according to the present invention, since the horizontal transfer device covering the entire construction area is provided, the construction work relating to the small members such as the small beams 6 and the deck plates 7 is greatly saved. It can be used for other heavy work by improving the working time in the construction area and reducing the load on the large crane, and it can respond to changes in the construction procedure and occurrence of troubles, so the operation of the large crane and the entire process Can be expected to have an effect on
Since the transfer device in the construction area is of an imaginary type, there is no need to consider the strength of the concrete slab and to take measures such as steps on the floor and openings.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 この発明に係わる積層工法における躯体施工
用モジュールの1実施形態の略示平面図である。
FIG. 1 is a schematic plan view of one embodiment of a module for building a frame in a laminating method according to the present invention.

【図2】 同上の側面図である。FIG. 2 is a side view of the same.

【図3】 この発明の躯体施工用モジュールを採用した
積層工法による建物の略示斜視図である。
FIG. 3 is a schematic perspective view of a building by a laminating method employing the frame building module of the present invention.

【図4】 施工エリアと躯体施工用モジュールの略示斜
視図である。
FIG. 4 is a schematic perspective view of a construction area and a skeleton construction module.

【図5】 1施工エリアにおける躯体施工用モジュール
の設置状態と施工状態とを示す略示斜視図である。
FIG. 5 is a schematic perspective view showing an installation state and a construction state of a skeleton construction module in one construction area.

【符号の説明】[Explanation of symbols]

1 躯体施工用モジュールのフレーム 2 大梁鉄骨 3 柱 4 大型クレーン 5 建物 6 小梁 7 デッキプレート 11 上部ビーム 12 補助フレーム 13 天井走行クレーン(ライトクレーン) 14 マスト部 DESCRIPTION OF SYMBOLS 1 Frame of building construction module 2 Steel girder 3 Pillar 4 Large crane 5 Building 6 Small beam 7 Deck plate 11 Upper beam 12 Auxiliary frame 13 Overhead traveling crane (light crane) 14 Mast part

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 積層工法により建築する建物平面を、所
要数の同形の施工エリアに区分し、その1施工エリアの
略全体に及ぶ大きさで小梁、デッキプレート等の小部材
の取付けに使用する搬送手段を具備し、1フロアーの躯
体施工に合わせて次の施工エリアへの一括移動がクレー
ンなどにより可能なフレーム構造の躯体施工用モジュー
ルであつて、 複数列の並行な上部ビームと、上部ビーム間に設けられ
て上部ビームを一体に接合する所要数列の補助ビームと
から構成された上記フレームと、上部ビームに支持され
て施工エリアの面内を縦横に走行する天井走行クレーン
と、各上部ビームの端部下側に設けられて全体を鉄骨大
梁又は鉄骨柱の仮設ブラケット等に設置するマスト部と
からなることを特徴とする積層工法における躯体施工用
モジュール。
1. A building surface to be constructed by a laminating method is divided into a required number of construction areas of the same shape, and is used for mounting small members such as small beams, deck plates, etc. in a size covering substantially the entire construction area. A frame construction module with a frame structure that can be moved to the next construction area at the same time as the construction of one floor by using a crane. The above-mentioned frame composed of a required number of rows of auxiliary beams provided between the beams and integrally joining the upper beams, an overhead traveling crane supported by the upper beams and traveling vertically and horizontally in the plane of the construction area, and each upper part A mast part provided below the end of the beam and entirely installed on a steel girder or a temporary bracket of a steel column, etc. Lumpur.
JP2000158563A 2000-05-29 2000-05-29 Skeleton execution module in lamination method Pending JP2001336286A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000158563A JP2001336286A (en) 2000-05-29 2000-05-29 Skeleton execution module in lamination method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000158563A JP2001336286A (en) 2000-05-29 2000-05-29 Skeleton execution module in lamination method

Publications (1)

Publication Number Publication Date
JP2001336286A true JP2001336286A (en) 2001-12-07

Family

ID=18663021

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000158563A Pending JP2001336286A (en) 2000-05-29 2000-05-29 Skeleton execution module in lamination method

Country Status (1)

Country Link
JP (1) JP2001336286A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113978751A (en) * 2021-11-12 2022-01-28 中航西安飞机工业集团股份有限公司 Modular reconfigurable tool frame structure and reconfiguration method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113978751A (en) * 2021-11-12 2022-01-28 中航西安飞机工业集团股份有限公司 Modular reconfigurable tool frame structure and reconfiguration method

Similar Documents

Publication Publication Date Title
JP2000045231A (en) Erection method for arch bridge
JP2001336286A (en) Skeleton execution module in lamination method
JPH06272389A (en) Temporary unloading stage
JP2017031657A (en) Ceiling crane support device and load receiving member
JPH10131508A (en) Material transport device of temporarily set curing body
CN115162823B (en) Assembling method of pinnacle steel member
JP3032052U (en) Construction equipment for pier reinforcement work
CN105084229B (en) Roof crane and application to roof-midspan longitudinal steel beam hoisting
JP3100574B2 (en) Suspended scaffold and its erection method
CN215331380U (en) Rail type suspension platform
JP4303400B2 (en) Overhead crane built into a framework scaffold
JPH0513862Y2 (en)
JP4445366B2 (en) Reinforcement method for tower crane mount
CN113863684B (en) Construction method of stepped double-layer steel truss
CN211714320U (en) Roof structure of tubular high-rise building
JP2017172262A (en) Construction method of building
JP3035139B2 (en) Floor slab construction method for multi-story buildings
JP3847029B2 (en) Box-type building
WO2021024382A1 (en) Modular transport modules, plant structure, and method for constructing plant structure
CN105110203A (en) Roof crane and application thereof in hoisting roof side-span longitudinal steel beams
JP2690822B2 (en) Steel construction method for low-rise buildings
JP2001146837A (en) Working path bridged over construction elevator
CN114310744A (en) Lower frame assembly point positioning device
JP2536347B2 (en) Building construction method using traveling crane
JPH11125014A (en) Construction method of building

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050428

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050517

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20051004