JP2001248176A - Earth retaining method - Google Patents

Earth retaining method

Info

Publication number
JP2001248176A
JP2001248176A JP2000058887A JP2000058887A JP2001248176A JP 2001248176 A JP2001248176 A JP 2001248176A JP 2000058887 A JP2000058887 A JP 2000058887A JP 2000058887 A JP2000058887 A JP 2000058887A JP 2001248176 A JP2001248176 A JP 2001248176A
Authority
JP
Japan
Prior art keywords
excavation
earth
retaining
struts
walls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2000058887A
Other languages
Japanese (ja)
Other versions
JP3776280B2 (en
Inventor
Koichi Tanaka
耕一 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2000058887A priority Critical patent/JP3776280B2/en
Publication of JP2001248176A publication Critical patent/JP2001248176A/en
Application granted granted Critical
Publication of JP3776280B2 publication Critical patent/JP3776280B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To achieve rational earth retaining work by constructing earth- retaining walls, struts, and intermediate columns within subsoil prior to excavation, in contrast to a conventional method which erects the struts while digging the ground, so that the vertical fulcrums of the earth-retaining walls become clear even in weak subsoil, resulting in a minimized displacement of the earth- retaining walls and cross-sectional forces during excavation. SOLUTION: Using an excavating machine for constructing underground continuous walls, excavation is carried out to a predetermined depth as channeled walls are held by a stabilizing solution, and a reinforcing cage 6 is inserted. Then concrete is placed to construct portions serving as the earth- retaining walls 1, the struts 4 and the intermediate columns 5. Excavation and removal of the struts or nearby unnecessary portions are repeated to complete installation of floors.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地下構造物の構築
方法としての山留め工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a mountain retaining method as a method for constructing an underground structure.

【0002】[0002]

【従来の技術】通常の山留め工法は、山留め壁を施工
し、さらに切梁・アンカー等の支保工を架設して掘削を
行う。
2. Description of the Related Art In a conventional shoring method, a shoring wall is constructed, and excavation is performed by erection of supports such as cutting beams and anchors.

【0003】[0003]

【発明が解決しようとする課題】この切梁・アンカー等
の支保工は、掘削を行いながら順次架設するため、図6
に示すように、山留め壁1の変位・曲げモーメントが累
積してしまう。
Since the support of the beam, anchor, etc., is to be erected sequentially while excavating, FIG.
As shown in (1), the displacement and bending moment of the retaining wall 1 are accumulated.

【0004】特に軟弱地盤が厚く堆積する場合には、地
中部で過大な変位・断面力が生じ、山留め壁1に補強を
行った事例もある。このような軟弱地盤で、しかも周囲
に家屋等2の近接重要構造物が存在する場合には、図7
に示すように山留め壁1の変位を防止する地盤改良によ
る先行地中梁3が必要となり、工費、工期の増大を招い
てしまう。
[0004] In particular, when the soft ground is thickly deposited, an excessive displacement / cross-sectional force is generated in the underground portion, and in some cases, the retaining wall 1 is reinforced. In the case of such a soft ground and a nearby important structure such as a house 2 exists around the soft ground, FIG.
As shown in (1), the preceding underground beam 3 is required to improve the ground to prevent the displacement of the retaining wall 1, which leads to an increase in construction cost and construction period.

【0005】本発明の目的は前記従来例の不都合を解消
し、山留め壁の発生変位・断面力を最小限に抑えなが
ら、掘削を行うことができる山留め工法を提供すること
にある。
An object of the present invention is to solve the disadvantages of the prior art and to provide a digging method capable of digging while minimizing the displacement and sectional force of the gusset wall.

【0006】[0006]

【課題を解決するための手段】本発明は前記目的を達成
するため、地中連続壁施工用の掘削機を使用して所定深
度まで掘削し、鉄筋かごを挿入し、コンクリートを打設
して、山留め壁、切梁、または/および中間柱となる部
分を施工し、掘削、先行切梁の不要部分の撤去を繰り返
し、床付けを完了すること、および、山留め壁、切梁、
または/および中間柱となる鉄筋かごの継手部鉄筋は重
ね継手で連続させること、または、山留め壁、不要部分
撤去後の切梁、中間柱は本設構造物として利用すること
を要旨とするものである。
According to the present invention, in order to attain the above object, an excavator for constructing an underground continuous wall is used to excavate to a predetermined depth, a reinforcing steel cage is inserted, and concrete is cast. Constructing the part that will become the retaining wall, the girder, and / or the intermediate column, repeatedly excavating, removing unnecessary parts of the preceding girder, and completing the flooring;
The main point is that the reinforcing bars of the reinforcing bar cage to be used as intermediate pillars are connected continuously by lap joints, or the retaining walls, cut beams after removal of unnecessary parts, and intermediate pillars are used as permanent structures. It is.

【0007】請求項1記載の本発明によれば、従来のよ
うに掘下げながら切梁を架設していく場合とは相違し
て、掘削前に、山留め壁と切梁、中間柱を地盤中に構築
するので、軟弱地盤中においても、山留め壁の鉛直方向
の支点が明確となる。その結果、掘削時の山留め壁変位
・断面力が最小限に抑えられ、合理的な山留め工とな
る。
According to the first aspect of the present invention, unlike the conventional case where a cutting beam is erected while digging down, the excavation wall, the cutting beam, and the intermediate column are placed in the ground before excavation. Since it is constructed, the fulcrum in the vertical direction of the retaining wall becomes clear even in soft ground. As a result, the displacement and section force of the retaining wall during excavation are minimized, and a reasonable retaining operation is achieved.

【0008】また、このように鉛直方向の支点が明確に
なっているため、事前に山留め架構に生じる断面力を把
握できる。
Further, since the fulcrum in the vertical direction is clearly defined as described above, it is possible to grasp in advance the sectional force generated in the retaining structure.

【0009】請求項2記載の本発明によれば、前記作用
に加えて、山留め壁、切梁、中間柱は、水平方向に鉄筋
に重ね継手を用いることで、曲げモーメントに対しても
抵抗可能な部材とすることができる。
According to the second aspect of the present invention, in addition to the above-mentioned effects, the retaining wall, the cut beam, and the intermediate column can also resist the bending moment by using the lap joint in the reinforcing bar in the horizontal direction. Member.

【0010】請求項3記載の本発明によれば、山留め
壁、不要部分撤去後の切梁、中間柱はこれを本設として
利用することで施工の合理化を図ることができ、さら
に、切梁、中間柱は剛性の高い鉄筋コンクリート造であ
るため、仮設桟橋の支持杭、主桁等に併用可能である。
[0010] According to the third aspect of the present invention, the mountain retaining wall, the cut beam after removing the unnecessary portion, and the intermediate pillar can be used as a permanent construction to streamline the construction. Since the intermediate pillar is made of reinforced concrete with high rigidity, it can be used for supporting piles and main girder of temporary piers.

【0011】[0011]

【発明の実施の形態】以下、本発明の実施の形態を詳細
に説明する。図1は本発明の山留め工法の1実施形態を
示す平面図、図2は同上縦断側面図で、図中1は山留め
壁、4は切梁、5は中間柱を示す。
Embodiments of the present invention will be described below in detail. FIG. 1 is a plan view showing an embodiment of a mountain retaining method according to the present invention, and FIG. 2 is a vertical sectional side view of the same, in which 1 is a retaining wall, 4 is a cut beam, and 5 is an intermediate column.

【0012】本発明は中間柱5はある場合とない場合が
あるが、これら、山留め壁1、切梁4、中間柱5は地中
連続壁施工用の掘削機を使用して、溝壁を安定液で保持
しながら所定深度まで掘削し、図5に示すように鉄筋か
ご6を挿入し、コンクリートをトレミー管等を用いて打
設して、または、ポンプ打設で施工する。
According to the present invention, the intermediate column 5 may or may not be provided. However, the retaining wall 1, the cutting beam 4, and the intermediate column 5 are formed by using an excavator for constructing an underground continuous wall. Excavation is performed to a predetermined depth while maintaining the stable liquid, and a reinforcing cage 6 is inserted as shown in FIG. 5, and concrete is cast using a tremy tube or the like, or is pumped.

【0013】また、これら山留め壁1、切梁4、中間柱
5となる鉄筋かご6は必要箇所を鉄筋同士の重ね継手10
で連続させる。その場合、中間柱5は切梁4との関係
で、上下段で適宜間隔で平面十字形になるように鉄筋を
組み、十字形の各先端部が継手となる。
The reinforcing cage 6 serving as the retaining wall 1, the cutting beam 4, and the intermediate column 5 is provided with necessary portions at the lap joint 10 of the reinforcing bars.
To continue. In this case, the intermediate pillars 5 are assembled with reinforcing bars so as to form a plane cruciform at appropriate intervals in the upper and lower tiers in relation to the cutting beam 4, and each end of the cruciform becomes a joint.

【0014】鉄筋かご6相互の継手部の施工方法と防護
対策については図示は省略するが、側鋼板と継手防護プ
レートを用いたり、キャンパスシートと継手防護ボック
スを用いたりする。
Although the illustration of the construction method and protective measures of the joint between the reinforcing bars 6 is omitted, a side steel plate and a joint protective plate or a campus sheet and a joint protective box are used.

【0015】この場合の施工順序は山留め壁1、切梁
4、中間柱5のいずれを先行させるものでもよい。ま
た、切梁4は鉛直方向において中間部分の不要部分αに
は鉄筋を挿入せず、かつ、鉄板7等で囲繞してこの部分
にはコンクリートが回り込まないようにして後で撤去し
やすいようにしておくこともできる。
In this case, the construction order may be such that any one of the retaining wall 1, the cutting beam 4, and the intermediate column 5 precedes. In addition, the reinforcing bar is not inserted into the unnecessary portion α of the intermediate portion in the vertical direction, and is surrounded by an iron plate 7 or the like so that concrete does not go around in this portion so that it can be easily removed later. You can keep it.

【0016】このように事前に山留め壁1、切梁4、中
間柱5となる部分を施工し、図3に示すように内部掘削
を行う。この内部掘削にともない、先行して施工した切
梁4またはその近傍の不要部分αの撤去を行う。なお、
鉄板7等で囲繞しないような場合でもブレーカー等でコ
ンクリートまたは鉄筋コンクリートを破壊・除去でき
る。
In this way, the portions to be the retaining wall 1, the cutting beam 4, and the intermediate column 5 are constructed in advance, and the internal excavation is performed as shown in FIG. Along with this internal excavation, the cutting beam 4 previously constructed or the unnecessary portion α in the vicinity thereof is removed. In addition,
Even in the case where the concrete or the reinforced concrete is not surrounded by the iron plate 7 or the like, the concrete or the reinforced concrete can be destroyed and removed by the breaker or the like.

【0017】さらに、掘削機の設置等に使用する掘削時
の仮設桟橋8はこれを切梁4上に主桁を渡し、架設する
ことができる。切梁4、中間柱5が仮設桟橋8の支持
杭、主桁等に併用可能なことによる。
Further, a temporary pier 8 used for excavator installation or the like during excavation can be erected by passing a main girder on the cutting beam 4. This is because the cutting beams 4 and the intermediate pillars 5 can be used together with the support piles, the main girder and the like of the temporary pier 8.

【0018】前記のごとく、掘削および切梁4またはそ
の近傍の不要部分αの撤去を繰り返し、図4に示すよう
に床付けが完了する。図4中、9は床付け面を示す。
As described above, the excavation and the removal of the unnecessary portion α in the vicinity of the cutting beam 4 or the vicinity thereof are repeated, and the flooring is completed as shown in FIG. In FIG. 4, reference numeral 9 denotes a flooring surface.

【0019】また、このようにして施工した、山留め壁
1、不要部分撤去後の切梁4、中間柱5は剛性の高い鉄
筋コンクリート(RC)構造であり、これらを本設構造
物の躯体として利用することもできる。
Further, the retaining wall 1, the beam 4 after removing unnecessary parts, and the intermediate pillar 5 constructed in this manner are reinforced concrete (RC) structures having high rigidity, and these are used as the frame of the main structure. You can also.

【0020】[0020]

【発明の効果】以上述べたように本発明の山留め工法
は、従来のように掘下げながら切梁を架設していく場合
とは相違して、掘削前に、山留め壁と切梁、中間柱を地
盤中に構築するので、軟弱地盤中においても、山留め壁
の鉛直方向の支点が明確となり、その結果、掘削時の山
留め壁変位・断面力が最小限に抑えられ、合理的な山留
め工となるものである。
As described above, the mountain retaining method according to the present invention is different from the conventional method in which a cutting beam is erected while digging down, and before the excavation, the retaining wall, the cutting beam, and the intermediate pillar are connected. Because it is built in the ground, the vertical fulcrum of the retaining wall becomes clear even in soft ground, and as a result, displacement and cross-sectional force of the retaining wall during excavation are minimized, making it a reasonable retaining work Things.

【0021】また、このように鉛直方向の支点が明確に
なっているため、事前に山留め架構に生じる断面力を把
握できる。
Further, since the fulcrum in the vertical direction is clear as described above, it is possible to grasp in advance the sectional force generated in the mountain retaining frame.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の山留め工法の1実施形態を示す平面図
である。
FIG. 1 is a plan view showing an embodiment of a mountain retaining method according to the present invention.

【図2】本発明の山留め工法の1実施形態を示す縦断側
面図である。
FIG. 2 is a longitudinal sectional side view showing one embodiment of the mountain retaining method of the present invention.

【図3】本発明の山留め工法の1実施形態を示す第2工
程の縦断側面図である。
FIG. 3 is a vertical sectional side view of a second step showing one embodiment of the mountain retaining method of the present invention.

【図4】本発明の山留め工法の1実施形態を示す第3工
程の縦断側面図である。
FIG. 4 is a vertical sectional side view of a third step showing one embodiment of the mountain retaining method of the present invention.

【図5】本発明の山留め工法の1実施形態を示す配筋状
況の側面図である。
FIG. 5 is a side view of a bar arrangement state showing one embodiment of the mountain retaining method of the present invention.

【図6】山留め工の説明図である。FIG. 6 is an explanatory view of a mountain retaining work.

【図7】先行地中梁を設けた場合の山留め工の説明図で
ある。
FIG. 7 is an explanatory diagram of a mountain retaining work when a preceding underground beam is provided.

【符号の説明】[Explanation of symbols]

1…山留め壁 2…家屋等 3…先行地中梁 4…切梁 5…中間柱 6…鉄筋かご 7…鉄板 8…仮設桟橋 9…床付け面 10…重ね継手 α…不要部分 DESCRIPTION OF SYMBOLS 1 ... Mountain retaining wall 2 ... House etc. 3 ... Preceding underground beam 4 ... Cut-off beam 5 ... Intermediate pillar 6 ... Reinforced basket 7 ... Iron plate 8 ... Temporary pier 9 ... Flooring surface 10 ... Lap joint alpha ... Unnecessary part

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 地中連続壁施工用の掘削機を使用して所
定深度まで掘削し、鉄筋かごを挿入し、コンクリートを
打設して、山留め壁、切梁、または/および中間柱とな
る部分を施工し、掘削、先行切梁の不要部分の撤去を繰
り返し、床付けを完了することを特徴とした山留め工
法。
1. Excavating to a predetermined depth using an excavator for underground continuous wall construction, inserting a reinforced cage, casting concrete, and forming a retaining wall, a cut beam, and / or an intermediate column. A mountain retaining method characterized by repeating the construction of a part, excavation, and removal of unnecessary parts of the preceding girder to complete flooring.
【請求項2】 山留め壁、切梁、または/および中間柱
となる鉄筋かごの継手部鉄筋は重ね継手で連続させる請
求項1記載の山留め工法。
2. The method according to claim 1, wherein the reinforcing bars of the reinforcing cages serving as the retaining wall, the cut beam, and / or the intermediate column are connected by a lap joint.
【請求項3】 山留め壁、不要部分撤去後の切梁、中間
柱は本設構造物として利用する請求項1または請求項2
記載の山留め工法。
3. The mountain retaining wall, the cut beam after removing unnecessary parts, and the intermediate pillar are used as a permanent structure.
The retaining method described.
JP2000058887A 2000-03-03 2000-03-03 Mountain fastening method Expired - Fee Related JP3776280B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000058887A JP3776280B2 (en) 2000-03-03 2000-03-03 Mountain fastening method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000058887A JP3776280B2 (en) 2000-03-03 2000-03-03 Mountain fastening method

Publications (2)

Publication Number Publication Date
JP2001248176A true JP2001248176A (en) 2001-09-14
JP3776280B2 JP3776280B2 (en) 2006-05-17

Family

ID=18579417

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000058887A Expired - Fee Related JP3776280B2 (en) 2000-03-03 2000-03-03 Mountain fastening method

Country Status (1)

Country Link
JP (1) JP3776280B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103993603A (en) * 2014-05-30 2014-08-20 中冶沈勘工程技术有限公司 Top-down construction method for anchor rod and rotary jet grouting back cover deep foundation pit without precipitation operation
CN113832987A (en) * 2021-10-28 2021-12-24 中船勘察设计研究院有限公司 Reinforcing process of steel lattice stand column in reverse construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103993603A (en) * 2014-05-30 2014-08-20 中冶沈勘工程技术有限公司 Top-down construction method for anchor rod and rotary jet grouting back cover deep foundation pit without precipitation operation
CN113832987A (en) * 2021-10-28 2021-12-24 中船勘察设计研究院有限公司 Reinforcing process of steel lattice stand column in reverse construction method

Also Published As

Publication number Publication date
JP3776280B2 (en) 2006-05-17

Similar Documents

Publication Publication Date Title
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP2868651B2 (en) Earth retaining method above existing underground structure
JPH0684690B2 (en) Building basement extension method
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JP2005002671A (en) Underpinning method and viaduct
JP2001248176A (en) Earth retaining method
JPH1077644A (en) Earthquake resisting pile foundation construction method
JPH0721196B2 (en) Reverse construction method of underground structure
JP3109038B2 (en) Underground skeleton structure and construction method
JP3700119B2 (en) Pillar construction method
JPH07138972A (en) Construction method for underground skeleton
JP3567387B2 (en) How to build an underground skeleton
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JPH101957A (en) Underground construction method for building
JPH04185816A (en) Construction of beam in underground wall
JPH08291526A (en) Construction method for underground structure
JP6851180B2 (en) How to rebuild the building
JPH10159094A (en) Timbering structure of earth retaining wall
JPH04368519A (en) Anchor retaining wall
JP2001336164A (en) Working platform for constructing underground structure and constructing method thereof
JP2002061213A (en) Inverted construction method
JPH0447021A (en) Construction method for sheathing guide pile
JPS5921831A (en) Reverse placement work

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050829

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050906

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051101

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060221

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060222

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120303

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees