JP2001090070A - Constructing method for column and facility for arranging steel frame - Google Patents

Constructing method for column and facility for arranging steel frame

Info

Publication number
JP2001090070A
JP2001090070A JP27167399A JP27167399A JP2001090070A JP 2001090070 A JP2001090070 A JP 2001090070A JP 27167399 A JP27167399 A JP 27167399A JP 27167399 A JP27167399 A JP 27167399A JP 2001090070 A JP2001090070 A JP 2001090070A
Authority
JP
Japan
Prior art keywords
steel frame
erection
gantry
hole
erection piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP27167399A
Other languages
Japanese (ja)
Inventor
Mitsuhiro Naito
充洋 内藤
Shuichi Nagataki
周一 永滝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Kumagai Technos Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Kumagai Technos Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd, Kumagai Technos Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP27167399A priority Critical patent/JP2001090070A/en
Publication of JP2001090070A publication Critical patent/JP2001090070A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide the constructing method for a column, by which a steel frame used for the column can be adjusted directly. SOLUTION: A frame with a hole to be penetrated 20 into which the steel frame is penetrated, and four erection pieces 22 installed around the hole to be penetrated at intervals is mounted on a reference plane 10. The steel frame 18 with the erection pieces in the same number as the erection pieces is hung up, and introduced into a pit hole from the hole to be penetrated of the frame. The erection pieces of the steel frame and the erection pieces of the frame are aligned in the vertical direction, load bearing devices 30 capable of being leveled in the vertical direction are arranged among each erection piece of the frame and each erection piece of the steel frame and the steel frame is lowered, the steel frame is made perpendicular by the load bearing devices, measuring the inclination of the steel frame by an inclinometer 3 installed to the steel frame in the vicinity of the reference plane, and concrete is placed into the pit hole.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、柱の構築方法及び
柱に使用する鉄骨を所定に配置するための設備に関し、
特に建物の地下階部分の柱である構真柱を構築するのに
適する構築方法と、その柱に使用する鉄骨を鉛直に配置
する設備とに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a column and a facility for arranging steel frames used for the column in a predetermined manner.
In particular, the present invention relates to a construction method suitable for constructing a straight pillar, which is a pillar of a basement floor portion of a building, and a facility for vertically arranging a steel frame used for the pillar.

【0002】[0002]

【従来の技術】地上に設置する建て込み架台に4つのレ
ベル調整ジャッキと、ガイド部を水平方向に位置調整す
る複数のジャッキとを備えると共に、構真柱に取り付け
られる建て込みジグを設けた、構真柱の建て込み装置が
提案されている(特許第2556216号公報)。
2. Description of the Related Art A built-in stand mounted on the ground is provided with four level adjusting jacks, a plurality of jacks for adjusting a position of a guide portion in a horizontal direction, and a built-in jig which is attached to a straight pillar. There has been proposed a erected pillar mounting device (Japanese Patent No. 2556216).

【0003】この装置によって構真柱を建て込むべきと
き、レベル調整ジャッキによって建て込み架台を水平に
配置した後、ガイド部の水平方向位置を調整し、建て込
みジグを取り付けた構真柱を前記ガイド部に導き、建て
込みジグのブラケットを建て込み架台のジグ受けジャッ
キに載せる。ジグ受けジャッキによってレベルを微調整
してガイド部を鉛直にし、これによって構真柱を鉛直に
する。
When a erected pillar is to be erected by this apparatus, the erection stand is horizontally arranged by a level adjusting jack, and then the horizontal position of the guide portion is adjusted, and the erected pillar to which the erection jig is attached is mounted. Guide to the guide section and mount the bracket of the built-in jig on the jig receiving jack of the built-in stand. The jig receiving jack finely adjusts the level so that the guide portion is vertical, and thereby the vertical column is vertical.

【0004】[0004]

【発明が解決しようとする課題】前記装置による構真柱
の建て込みでは、構真柱がガイド部を介して建て込み架
台に、いわば間接的に支持される。そのため、構真柱の
鉛直度がガイド部の製作精度によって左右される。加え
て、前記装置では、構真柱のレベル調整や水平方向の位
置調整などのための機器が建て込み架台に設けられ、そ
の機能を建て込み架台に持たせているため、建て込み架
台が大形となっている。
In the installation of a straight pillar by the above apparatus, the straight pillar is indirectly supported on a built-in pedestal via a guide portion. Therefore, the verticality of the straight pillar depends on the manufacturing accuracy of the guide portion. In addition, in the above-mentioned apparatus, devices for adjusting the level of the pillars and adjusting the position in the horizontal direction are provided on the built-in gantry, and the functions of the gantry are provided in the gantry. It has a shape.

【0005】本発明は、柱に用いる鉄骨を直接に調整で
きる、柱の構築方法と、鉄骨配置用設備とを提供する。
[0005] The present invention provides a method for constructing a pillar and a facility for arranging the steel frame, which can directly adjust the steel frame used for the pillar.

【0006】本発明はまた、全体を小型化できる、鉄骨
配置用設備を提供する。
[0006] The present invention also provides a steel frame placement facility that can be downsized as a whole.

【0007】[0007]

【課題を解決するための手段、作用及び効果】本発明
は、基準面から下方へ掘削した杭孔内に柱を構築する方
法である。まず、鉄骨を貫通させる被貫通孔と、この被
貫通孔の周りに間隔をおいて取り付けられた少なくとも
3つのエレクションピースとを有する架台を、前記被貫
通孔が前記杭孔の上方に位置するように前記基準面に設
置する。次いで、前記少なくとも3つのエレクションピ
ースと同数のエレクションピースを有し、これらエレク
ションピースが前記架台のエレクションピースと対応す
るように取り付けられた鉄骨を吊り上げて前記架台の被
貫通孔に貫通させ、前記杭孔内に導く。鉄骨を杭孔内に
導いた後、前記鉄骨のエレクションピースと前記架台の
エレクションピースとを上下方向に整列し、上下方向の
レベル調整可能な荷重支持装置を前記架台の各エレクシ
ョンピースと前記鉄骨の各エレクションピースとの間に
配置して鉄骨を降ろす。そして、前記基準面の近傍で前
記鉄骨に取り付けられた少なくとも1つの傾斜計によっ
て前記鉄骨の傾きを計測しながら前記荷重支持装置によ
って前記鉄骨を鉛直にし、前記杭孔内にコンクリートを
打設する。
SUMMARY OF THE INVENTION The present invention is a method for constructing a pillar in a pile hole excavated downward from a reference plane. First, a pedestal having a through hole through which a steel frame is to penetrate, and at least three erection pieces attached at intervals around the through hole, such that the through hole is located above the pile hole. At the reference plane. Next, the erection piece has the same number of erection pieces as the at least three erection pieces, and the erection pieces lift up a steel frame attached so as to correspond to the erection pieces of the gantry and penetrate through the through-hole of the gantry, and Guide into the hole. After guiding the steel frame into the pile hole, the erection piece of the steel frame and the erection piece of the gantry are vertically aligned, and a load supporting device capable of adjusting the level in the up-down direction is provided for each erection piece of the gantry and the steel frame. Arrange between each erection piece and lower the steel frame. Then, the steel frame is made vertical by the load supporting device while measuring the inclination of the steel frame by at least one inclinometer attached to the steel frame in the vicinity of the reference plane, and concrete is poured into the pile hole.

【0008】鉄骨を荷重支持装置を介して架台に載せる
と、鉄骨の荷重は鉄骨のエレクションピースから荷重支
持装置を経、さらに架台のエレクションピースを経て、
架台に伝わり、ここで受け止められる。この状態で、少
なくとも3個の荷重支持装置を操作してレベルを調整
し、さらに傾斜計によって鉄骨の傾きを計測しながら鉄
骨を鉛直にする。
When the steel frame is placed on the gantry via the load supporting device, the load of the steel frame is transmitted from the erection piece of the steel frame through the load supporting device, further through the erection piece of the gantry,
It is transmitted to the gantry and received here. In this state, the level is adjusted by operating at least three load supporting devices, and the steel frame is made vertical while measuring the inclination of the steel frame using an inclinometer.

【0009】鉄骨は、鉄骨のエレクションピースと架台
のエレクションピースとの間に配置した荷重支持装置に
よって直接に調整されることと、少なくとも3個の荷重
支持装置によって調整されることから、高い精度で鉛直
とされる。その結果、高い鉛直精度の柱を得ることがで
きる。
Since the steel frame is directly adjusted by the load supporting device disposed between the erection piece of the steel frame and the erection piece, and is adjusted by at least three load supporting devices, it is highly accurate. It is vertical. As a result, a column with high vertical accuracy can be obtained.

【0010】荷重支持装置が架台のエレクションピース
に係わっていることと、傾斜計が基準面の近傍で鉄骨に
取り付けられていることから、基準面にいる作業員によ
って荷重支持装置の操作が可能であり、また傾斜計によ
って鉄骨の傾きを計測できる。そのため、杭孔内に入っ
ての危険を伴う計測や調整が不要となり、安全な作業を
保証できる。
Since the load supporting device is related to the erection piece of the gantry and the inclinometer is attached to the steel frame near the reference surface, the operator on the reference surface can operate the load supporting device. Yes, and the inclination of the steel frame can be measured with an inclinometer. Therefore, there is no need for measurement or adjustment involving danger of entering the pile hole, and safe work can be guaranteed.

【0011】少なくとも3個の荷重支持装置と架台とに
よって鉄骨の荷重を受け止めるため、鉄骨の鉛直調整
や、その後のコンクリート打設の際、クレーンによって
鉄骨を吊り下げた状態に保つ必要がなく、クレーンの稼
働率を高めることができる。
Since the load of the steel frame is received by at least three load supporting devices and the gantry, it is not necessary to keep the steel frame suspended by the crane during the vertical adjustment of the steel frame and the subsequent concrete placement. Operating rate can be increased.

【0012】本発明はまた、基準面から下方へ掘削した
杭孔内に柱を構築する方法である。まず、鉄骨を貫通さ
せる被貫通孔と、この被貫通孔の周りに間隔をおいて取
り付けられた少なくとも4つのエレクションピースとを
有する架台を、前記被貫通孔が前記杭孔の上方に位置す
るように前記基準面に設置する。次いで、前記少なくと
も4つのエレクションピースと同数のエレクションピー
スを有し、これらエレクションピースが前記架台のエレ
クションピースと対応するように取り付けられた鉄骨を
吊り上げて前記架台の被貫通孔に貫通させ、前記杭孔内
に導く。鉄骨を杭孔内に導いた後、前記鉄骨のエレクシ
ョンピースと前記架台のエレクションピースとを上下方
向に整列し、上下方向のレベル調整可能、かつ、水平方
向の位置調整可能な荷重支持装置を前記架台の各エレク
ションピースと前記鉄骨の各エレクションピースとの間
に配置して鉄骨を降ろす。その後、前記荷重支持装置に
よって前記鉄骨の水平方向位置を調整する。そして、前
記基準面の近傍で前記鉄骨に取り付けられた少なくとも
1つの傾斜計によって前記鉄骨の傾きを計測しながら前
記荷重支持装置によって前記鉄骨を鉛直にし、前記杭孔
内にコンクリートを打設する。
[0012] The present invention is also a method for constructing a pillar in a pile hole excavated downward from a reference plane. First, a pedestal having a through hole through which a steel frame is to penetrate, and at least four erection pieces attached around the through hole so that the through hole is located above the pile hole. At the reference plane. Then, the erection pieces have the same number as the at least four erection pieces, and these erection pieces lift a steel frame attached so as to correspond to the erection pieces of the gantry and penetrate through the through-holes of the gantry. Guide into the hole. After guiding the steel frame into the pile hole, the erection piece of the steel frame and the erection piece of the gantry are vertically aligned, and the level support in the up and down direction can be adjusted, and the load support device capable of adjusting the position in the horizontal direction can be used. The steel frame is lowered by placing it between each erection piece of the gantry and each erection piece of the steel frame. Then, the horizontal position of the steel frame is adjusted by the load supporting device. Then, the steel frame is made vertical by the load supporting device while measuring the inclination of the steel frame by at least one inclinometer attached to the steel frame in the vicinity of the reference plane, and concrete is poured into the pile hole.

【0013】鉄骨を荷重支持装置を介して架台に載せる
と、鉄骨の荷重は鉄骨のエレクションピースから荷重支
持装置を経、さらに架台のエレクションピースを経て、
架台に伝わり、ここで受け止められる。この状態で、少
なくとも4個の荷重支持装置を操作して鉄骨の水平方向
位置を調整し、鉄骨のレベルを調整し、傾斜計によって
鉄骨の傾きを計測しながら鉄骨を鉛直にする。
When the steel frame is placed on the gantry via the load supporting device, the load of the steel frame passes through the load supporting device from the erection piece of the steel frame, further passes through the erection piece of the gantry,
It is transmitted to the gantry and received here. In this state, the horizontal position of the steel frame is adjusted by operating at least four load supporting devices, the level of the steel frame is adjusted, and the inclination of the steel frame is measured by an inclinometer, thereby making the steel frame vertical.

【0014】鉄骨は、鉄骨のエレクションピースと架台
のエレクションピースとの間に配置した荷重支持装置に
よって直接に調整されることと、少なくとも4個の荷重
支持装置によって調整されることから、高い精度で鉛直
とされる。また、鉄骨の水平方向の位置を正確に決める
ことができる。その結果、水平方向の位置を正確に定め
た高い鉛直精度の柱を得ることができる。
Since the steel frame is directly adjusted by the load supporting device arranged between the erection piece of the steel frame and the erection piece, and is adjusted by at least four load supporting devices, it is highly accurate. It is vertical. In addition, the horizontal position of the steel frame can be accurately determined. As a result, it is possible to obtain a column with a high vertical accuracy in which the position in the horizontal direction is accurately determined.

【0015】荷重支持装置が架台のエレクションピース
に係わっていることと、傾斜計が基準面の近傍で鉄骨に
取り付けられていることから、基準面にいる作業員によ
って荷重支持装置の操作が可能であり、また傾斜計によ
って鉄骨の傾きを計測できる。そのため、杭孔内に入っ
ての危険を伴う計測や調整が不要となり、安全な作業を
保証できる。
Since the load supporting device is related to the erection piece of the gantry and the inclinometer is attached to the steel frame in the vicinity of the reference surface, the operator on the reference surface can operate the load supporting device. Yes, and the inclination of the steel frame can be measured with an inclinometer. Therefore, there is no need for measurement or adjustment involving danger of entering the pile hole, and safe work can be guaranteed.

【0016】少なくとも4個の荷重支持装置と架台とに
よって鉄骨の荷重を受け止めるため、鉄骨の水平方向の
位置調整や鉛直調整、その後のコンクリート打設の際、
クレーンによって鉄骨を吊り下げた状態に保つ必要がな
く、クレーンの稼働率を高めることができる。
In order to receive the load of the steel frame by at least four load supporting devices and the gantry, when the horizontal position adjustment and the vertical adjustment of the steel frame are performed, the concrete
There is no need to keep the steel frame suspended by the crane, and the operating rate of the crane can be increased.

【0017】別の発明では、4つの前記エレクションピ
ースが前記架台に取り付けられている。これらエレクシ
ョンピースは、隣り合って位置する2つのエレクション
ピースの延長線が実質的に90°の角度で交差するよう
に、かつ、互いに対向する部分に位置する2つのエレク
ションピースが実質的に同一平面内に位置するように配
置されている。
In another invention, the four erection pieces are attached to the gantry. These erection pieces are such that the extension lines of two erection pieces located adjacent to each other intersect at an angle of substantially 90 °, and the two erection pieces located at opposing parts are substantially coplanar. It is arranged to be located inside.

【0018】4つのエレクションピースが、いわゆる対
称配置となるため、エレクションピースの取付けが容易
である。また、鉄骨の水平方向の位置調整や鉛直調整が
し易い。
Since the four erection pieces have a so-called symmetrical arrangement, the erection pieces can be easily mounted. In addition, horizontal position adjustment and vertical adjustment of the steel frame can be easily performed.

【0019】さらに別の発明では、2つの前記傾斜計が
前記基準面の近傍で前記鉄骨の実質的に直交する側面に
取り付けられ、前記鉄骨の傾きを計測する。
In still another invention, the two inclinometers are attached to a substantially perpendicular side surface of the steel frame near the reference plane, and measure the inclination of the steel frame.

【0020】傾斜計は当該傾斜計が取り付けられた側面
の鉛直面からの傾きを計測するところ、2つの傾斜計を
鉄骨の実質的に直交する側面に取り付けることによっ
て、鉄骨の鉛直度を完全、かつ、十分に計測できる。
The inclinometer measures the inclination of the side on which the inclinometer is mounted from a vertical plane. By mounting two inclinometers on the substantially orthogonal side of the steel frame, the verticality of the steel frame can be completely and perfectly measured. And it can measure enough.

【0021】さらに別の発明では、前記傾斜計によって
前記鉄骨の傾きを計測しながら前記荷重支持装置によっ
て前記鉄骨を鉛直にすることと、前記杭孔内にコンクリ
ートを打設することとを繰り返す。
[0021] In still another aspect of the present invention, the step of vertically setting the steel frame by the load supporting device while placing the concrete in the pile hole is repeated while measuring the inclination of the steel frame by the inclinometer.

【0022】コンクリートを打設することによって鉄骨
の鉛直度が変わることがあるが、この発明によれば、鉄
骨の傾きを計測しながら鉄骨を鉛直にし、コンクリート
を打設することを繰り返すため、鉄骨は確実に鉛直状態
に維持される。その結果、より鉛直精度の高い柱を得る
ことができる。
Although the verticality of the steel frame may be changed by casting concrete, according to the present invention, the steel frame is repeatedly placed vertically while measuring the inclination of the steel frame, and the concrete casting is repeated. Is surely maintained in a vertical state. As a result, a column with higher vertical accuracy can be obtained.

【0023】さらに別の発明では、前記架台を前記基準
面に設置するに先立って前記杭孔内にケーシングを挿入
し、前記架台を前記基準面に設置するとき、前記架台を
前記ケーシングに固定する。
In still another invention, a casing is inserted into the pile hole prior to installing the gantry on the reference surface, and the gantry is fixed to the casing when the gantry is installed on the reference surface. .

【0024】基準面には架台を支持し、堅固に固定する
ためのコンクリートスラブなどを前もって作っておく必
要があるが、この発明によれば、架台をケーシングによ
って支持できるため、コンクリートスラブなどが不要で
あり、それだけ作業性を高めることができる。一方、ケ
ーシングはコンクリートと共に地中に埋められ、柱の一
部となる。
Although a concrete slab or the like for supporting and firmly fixing the gantry must be prepared in advance on the reference surface, according to the present invention, since the gantry can be supported by the casing, no concrete slab or the like is required. Therefore, workability can be improved accordingly. On the other hand, the casing is buried underground with concrete and becomes part of the pillar.

【0025】本発明はまた、外周面に間隔をおいて取り
付けられた少なくとも3つのエレクションピースを有す
る鉄骨を基準面から下方へ掘削した杭孔内に配置する際
に使用する設備であって、架台と、荷重支持装置とを備
える。前記架台は、前記鉄骨を貫通させる被貫通孔と、
この被貫通孔の周りに間隔をおいた前記少なくとも3つ
のエレクションピースと同数のエレクションピースとを
有し、これらエレクションピースが前記鉄骨のエレクシ
ョンピースと対応するように取り付けられている。そし
て、前記荷重支持装置は、前記架台の各エレクションピ
ースと前記鉄骨の各エレクションピースとの間に配置さ
れ、上下方向のレベル調整可能である。
The present invention also relates to a facility for use in placing a steel frame having at least three erection pieces attached to an outer peripheral surface at intervals in a pile hole excavated downward from a reference plane, comprising: And a load supporting device. The pedestal, a through-hole to penetrate the steel frame,
The at least three erection pieces and the same number of erection pieces are spaced around the through hole, and the erection pieces are attached to correspond to the steel erection pieces. The load support device is disposed between each erection piece of the gantry and each erection piece of the steel frame, and is capable of adjusting a level in a vertical direction.

【0026】鉄骨を架台の被貫通孔を経て杭孔内に導
き、鉄骨のエレクションピースを荷重支持装置に載せる
と、鉄骨の荷重は鉄骨のエレクションピース、荷重支持
装置、さらに架台のエレクションピースを経て架台に伝
えられ、ここで受け止められる。
When the steel frame is guided into the pile hole through the through hole of the gantry and the erection piece of the steel frame is placed on the load supporting device, the load of the steel frame is passed through the erection piece of the steel frame, the load supporting device, and the erection piece of the gantry. It is transmitted to the gantry and received here.

【0027】鉄骨配置用設備が架台と少なくとも3個の
荷重支持装置とからなるところ、架台は鉄骨を貫通させ
て杭孔の周縁に載る大きさであればよく、架台に取り付
けるのは荷重支持装置のためのエレクションピースだけ
であり、荷重支持装置はエレクションピースに載るた
め、設備の全体を可及的に小さくすることが可能であ
り、小型化を図ることができる。また、架台はエレクシ
ョンピースを有するだけであるため、簡単な構造とする
ことができる。
Where the equipment for arranging the steel frame comprises a gantry and at least three load supporting devices, the gantry only needs to be large enough to penetrate the steel frame and to be mounted on the periphery of the pile hole. Since the load supporting device is mounted on the erection piece, the entire equipment can be made as small as possible, and the size can be reduced. In addition, since the gantry only has the erection piece, it can have a simple structure.

【0028】荷重支持装置は鉄骨の荷重を支持すると共
に、少なくとも3個の荷重支持装置によって鉄骨のレベ
ルと鉛直度とを調整できることから、クレーン等によっ
て鉄骨を吊り下げた状態に保つことなく、鉄骨の荷重支
持と、レベル調整と、鉛直調整とを行うことができる。
The load supporting device supports the load of the steel frame, and since the level and the verticality of the steel frame can be adjusted by at least three load supporting devices, the steel frame can be maintained without being suspended by a crane or the like. , Load adjustment, level adjustment, and vertical adjustment.

【0029】別の発明では、前記荷重支持装置はカムア
ームと、座板と、シム板と、ねじ部材とを備える。前記
カムアームは、作用部と、この作用部から横方向へ間隔
をおいた入力部と、前記作用部及び前記入力部から横方
向、かつ、下方向へ間隔をおいた支点部とを有する。前
記カムアームと前記鉄骨のエレクションピースとの間に
配置され、前記鉄骨のエレクションピースと接触する前
記座板は、前記カムアームの作用部と接触する係合部
と、この係合部から横方向へ間隔をおいた、前記カムア
ームの前記入力部に対応する部位に設けられ、上下に貫
通するねじ穴とを有する。前記シム板は、前記カムアー
ムと前記架台のエレクションピースとの間に配置され、
前記カムアームの支点部及び前記架台のエレクションピ
ースと接触する。そして、前記ねじ部材は、前記座板の
ねじ穴にねじ込まれ、前記カムアームの入力部と接触し
て前記カムアームに支持荷重を入力する。
In another aspect, the load supporting device includes a cam arm, a seat plate, a shim plate, and a screw member. The cam arm has an operating portion, an input portion laterally spaced from the operating portion, and a fulcrum portion laterally and downwardly spaced from the operating portion and the input portion. The seat plate, which is disposed between the cam arm and the erection piece of the steel frame and is in contact with the erection piece of the steel frame, has an engaging portion that contacts the working portion of the cam arm and a lateral space from the engaging portion. And a screw hole provided in a portion corresponding to the input portion of the cam arm and penetrating vertically. The shim plate is disposed between the cam arm and the erection piece of the gantry,
It contacts the fulcrum of the cam arm and the erection piece of the gantry. Then, the screw member is screwed into a screw hole of the seat plate, and comes into contact with an input portion of the cam arm to input a support load to the cam arm.

【0030】ねじ部材を座板のねじ穴にねじ込んでねじ
部材の先端をカムアームの入力部に接触させ、ねじ部材
をさらにねじ込むと、カムアームの作用部には、作用部
から支点部までの距離と入力部から支点部までの距離と
の比、つまりアーム比に従って増力された支持荷重が働
く。この支持荷重が鉄骨を支持する。このときの反力
は、架台によって受け止められる。ねじ部材をねじ込む
ことによって鉄骨の押し上げを行い、ねじ部材をねじ戻
すことによって鉄骨の引き下げを行うため、少なくとも
3個の荷重支持装置のねじ部材のねじ込み量を調整する
ことによって鉄骨のレベルと共に鉛直度を調整すること
ができる。
When the screw member is screwed into the screw hole of the seat plate and the tip of the screw member is brought into contact with the input portion of the cam arm, and the screw member is further screwed, the working portion of the cam arm has the distance from the working portion to the fulcrum. A supporting load increased according to the ratio of the distance from the input portion to the fulcrum portion, that is, the arm ratio. This supporting load supports the steel frame. The reaction force at this time is received by the gantry. In order to push up the steel frame by screwing the screw member and to lower the steel frame by unscrewing the screw member, the degree of verticality as well as the level of the steel frame is adjusted by adjusting the screwing amounts of the screw members of at least three load supporting devices. Can be adjusted.

【0031】荷重支持装置のカムアームと、座板と、シ
ム板とを鉄骨のエレクションピースと架台のエレクショ
ンピースとの間に入れ、ねじ部材をねじ込むだけで鉄骨
の荷重を支持できることと、少なくとも3個の荷重支持
装置によって鉄骨のレベルと、鉛直度とを調整できるこ
とから、操作性がよく、簡便である。
The cam arm, the seat plate and the shim plate of the load supporting device are inserted between the erection piece of the steel frame and the erection piece of the gantry, and the load of the steel frame can be supported only by screwing the screw member. Since the level of the steel frame and the verticality can be adjusted by the load supporting device, the operability is good and simple.

【0032】荷重支持装置が4つの部品からなるため安
価であり、アーム比を適当に選定することによって大き
な支持荷重が得られることから、小形化することができ
る。さらに、4つの部品のいずれかが破損したとき、そ
の部品を交換して使用することが可能であり、部品交換
性がよい。
Since the load supporting device is composed of four parts, it is inexpensive, and by appropriately selecting the arm ratio, a large supporting load can be obtained, so that the size can be reduced. Furthermore, when any one of the four parts is damaged, the part can be replaced and used, and the parts can be replaced easily.

【0033】また、カムアームと架台のエレクションピ
ースとの間に差し込むシム板を備えることから、例えば
傾斜面付きのシム板を使用したり、厚みの異なるシム板
を使用したりすることにより、鉄骨のレベル調整の範囲
を広げることができる。
Further, since a shim plate inserted between the cam arm and the erection piece of the gantry is provided, for example, a shim plate having an inclined surface or a shim plate having a different thickness is used, so that the steel frame can be formed. The range of level adjustment can be expanded.

【0034】本発明はまた、外周面に間隔をおいて取り
付けられた少なくとも4つのエレクションピースを有す
る鉄骨を基準面から下方へ掘削した杭孔内に配置する際
に使用する設備であって、架台と、荷重支持装置とを備
える。前記架台は、前記鉄骨を貫通させる被貫通孔と、
この被貫通孔の周りに間隔をおいた前記少なくとも4つ
のエレクションピースと同数のエレクションピースを有
し、これらエレクションピースが前記鉄骨のエレクショ
ンピースと対応するように取り付けられている。そし
て、前記荷重支持装置は、前記架台の各エレクションピ
ースと前記鉄骨の各エレクションピースとの間に配置さ
れ、上下方向のレベル調整可能、かつ、水平方向の位置
調整可能である。
[0034] The present invention also relates to a facility for use in placing a steel frame having at least four erection pieces mounted on an outer peripheral surface at intervals in a pile hole excavated downward from a reference plane, comprising: And a load supporting device. The pedestal, a through-hole to penetrate the steel frame,
There are the same number of erection pieces as the at least four erection pieces spaced around the through hole, and these erection pieces are mounted so as to correspond to the steel erection pieces. The load supporting device is disposed between each erection piece of the gantry and each erection piece of the steel frame, and is capable of adjusting a level in a vertical direction and a position in a horizontal direction.

【0035】前述の設備によって得られる作用及び効果
に加えて、この発明に係る設備では、鉄骨の水平方向の
位置調整ができるため、鉄骨をより正確に杭孔内に配置
することができる。
In addition to the functions and effects obtained by the above-described equipment, the equipment according to the present invention can adjust the horizontal position of the steel frame, so that the steel frame can be more accurately arranged in the pile hole.

【0036】さらに別の発明では、前記荷重支持装置が
カムアームと、座板と、シム板と、ねじ部材とを備える
点で前述の荷重支持装置と同様であり、さらに、前記カ
ムアームと前記座板と前記シム板とを取り囲むフレーム
を備える。このフレームは、前記鉄骨のエレクションピ
ースを挿入可能可能な第1溝と、この第1溝内に挿入さ
れた前記鉄骨のエレクションピースを固定するボルト
と、前記架台のエレクションピースを挿入可能な第2溝
と、この第2溝内に挿入された前記架台のエレクション
ピースの左右の側面に接触可能な少なくとも2つのボル
トとを有する。
According to still another aspect of the present invention, the load supporting device is the same as the above-described load supporting device in that the load supporting device includes a cam arm, a seat plate, a shim plate, and a screw member. And a frame surrounding the shim plate. The frame includes a first groove into which the steel erection piece can be inserted, a bolt for fixing the steel erection piece inserted into the first groove, and a second groove into which the erection piece of the gantry can be inserted. It has a groove and at least two bolts that can be brought into contact with the left and right side surfaces of the erection piece of the gantry inserted into the second groove.

【0037】フレームの第1溝内に挿入された鉄骨のエ
レクションピースをボルトによって固定する。そして、
フレームの第2溝内に挿入された架台のエレクションピ
ースの左右側面に対面しているボルトのうち一方を一方
の側面に向けて所定長さ突出した状態に保ち、他方のボ
ルトを締め付けると、鉄骨は一方の側面が一方のボルト
に突き当たるまで水平方向へ移動する。従って、少なく
とも4個の荷重支持装置のフレームを使用して鉄骨を水
平の2直角方向へ移動することができる。
The steel erection piece inserted into the first groove of the frame is fixed by bolts. And
When one of the bolts facing the left and right sides of the erection piece of the gantry inserted into the second groove of the frame is kept in a state of projecting a predetermined length toward one side, and the other bolt is tightened, a steel frame is formed. Moves horizontally until one side hits one bolt. Thus, the frame can be moved in two horizontal directions at right angles using the frames of at least four load bearing devices.

【0038】[0038]

【発明の実施の形態】柱の構築方法は、断面状態の図1
を参照すると、基準面10から下方へ掘削した杭孔12
内に柱を構築する方法である。ここで、基準面10と
は、例えば、構築すべき柱が地下1階に位置するとき、
地表面であり、構築すべき柱が地下2階に位置すると
き、地下1階のフロア面である。基準面10には適宜、
セメントスラブ14を敷き均す。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A method of constructing a pillar is shown in FIG.
With reference to FIG.
How to build a pillar inside. Here, for example, when the pillar to be constructed is located on the first basement floor,
When the pillar to be constructed is located on the second basement floor, it is the ground surface on the first basement floor. The reference plane 10 is appropriately
The cement slab 14 is spread and leveled.

【0039】柱の構築に際し、杭孔12を掘削し、杭孔
12にケーシング16を挿入し、杭孔12内に鉄筋かご
(図示せず)を挿入するのは、従来と同様である。
In constructing the pillar, the pile hole 12 is excavated, the casing 16 is inserted into the pile hole 12, and a reinforcing cage (not shown) is inserted into the pile hole 12 as in the conventional case.

【0040】本発明では、鉄骨18を貫通させる被貫通
孔20と、被貫通孔20の周りに間隔をおいて取り付け
られた少なくとも3つのエレクションピース22とを有
する架台24を、被貫通孔20が杭孔12の上方で杭孔
12の実質的に中央に位置するように基準面10に設置
する。基準面10に図示のようにコンクリートスラブ1
4があるとき、架台24をコンクリートスラブ14に設
置すればよく、基準面10とはこのような趣旨である。
架台24は適宜に固定することが好ましい。
According to the present invention, the pedestal 24 having the through hole 20 through which the steel frame 18 penetrates and at least three erection pieces 22 attached at intervals around the through hole 20 is formed. It is installed on the reference plane 10 so as to be located substantially at the center of the pile hole 12 above the pile hole 12. Concrete slab 1 on reference surface 10 as shown
When there is 4, the gantry 24 may be installed on the concrete slab 14, and the reference plane 10 has such a purpose.
It is preferable that the gantry 24 is appropriately fixed.

【0041】鉄骨18は、少なくとも3つのエレクショ
ンピース22と同数のエレクションピース26を有す
る。これらエレクションピース26は、架台24のエレ
クションピース22と対応するように、つまり鉄骨18
を正しい位置にもたらしたとき、鉄骨18のエレクショ
ンピース26が架台24のエレクションピース22と上
下方向に整列するように取り付けられている。このよう
に形成された鉄骨18をクレーン(図示せず)から垂下
しているワイヤ28によって吊り上げて架台24の上方
にもたらし、その被貫通孔20に貫通させ、杭孔12内
に導く。
The steel frame 18 has at least three erection pieces 22 and the same number of erection pieces 26. These erection pieces 26 correspond to the erection pieces 22 of the gantry 24, that is, the steel frames 18.
Is brought into a correct position, the erection piece 26 of the steel frame 18 is mounted so as to be vertically aligned with the erection piece 22 of the gantry 24. The steel frame 18 thus formed is lifted by a wire 28 hanging from a crane (not shown), brought above the gantry 24, penetrated through the through hole 20, and guided into the pile hole 12.

【0042】鉄骨18が構真柱となる場合、鉄骨18を
吊り上げるとき、一般に、重心吊りをしている。すなわ
ち、ワイヤ28による2つの吊り上げ点を結ぶ鉛直仮想
面が鉄骨18の重心を通るように吊り上げ点を正しく定
めている(前記特許公報参照)が、本発明では、後述す
る荷重支持装置による鉛直調整が可能であるため、重心
吊りをすることは必ずしも必要ではない。
When the steel frame 18 is a straight pillar, when the steel frame 18 is lifted, the center of gravity is generally suspended. That is, the lifting point is correctly determined so that the vertical virtual plane connecting the two lifting points by the wire 28 passes through the center of gravity of the steel frame 18 (see the above-mentioned patent publication). However, in the present invention, the vertical adjustment by the load support device described later is performed. Therefore, it is not always necessary to suspend the center of gravity.

【0043】鉄骨18を杭孔12内に導いた後、鉄骨1
8のエレクションピース26と架台24のエレクション
ピース22とを上下方向に整列し、上下方向のレベル調
整可能な荷重支持装置30を架台24の各エレクション
ピース22と鉄骨18の各エレクションピース26との
間に配置して鉄骨18を降ろす。
After guiding the steel frame 18 into the pile hole 12, the steel frame 1
8 and the erection piece 22 of the gantry 24 are vertically aligned, and the load support device 30 capable of adjusting the level in the up and down direction is placed between each erection piece 22 of the gantry 24 and each erection piece 26 of the steel frame 18. And the steel frame 18 is lowered.

【0044】鉄骨18が荷重支持装置30に載った後に
は、鉄骨18の荷重は、鉄骨18のエレクションピース
26、荷重支持装置30及び架台24のエレクションピ
ース22を経て架台24に伝わり、架台24及び基準面
10によって受け止められる。従って、鉄骨18をクレ
ーンで吊り上げておくことを要しない。
After the steel frame 18 is placed on the load supporting device 30, the load of the steel frame 18 is transmitted to the gantry 24 via the erection piece 26 of the steel frame 18, the load supporting device 30 and the erection piece 22 of the gantry 24, and the gantry 24 It is received by the reference plane 10. Therefore, it is not necessary to lift the steel frame 18 with a crane.

【0045】鉄骨18を少なくとも3つの荷重支持装置
30によって支持した後、鉄骨18のレベルを荷重支持
装置30によって調整し、さらに基準面10の近傍で鉄
骨18に取り付けられた少なくとも1つの傾斜計32に
よって鉄骨18の傾きを計測しながら少なくとも3つの
荷重支持装置30によって鉄骨18を鉛直にする。ここ
で、基準面10の近傍は、基準面10に居る作業員が特
に不自然な姿勢をすることなく、傾斜計32に接近し、
計測できる範囲とすればよい。
After the steel frame 18 has been supported by the at least three load supporting devices 30, the level of the steel frame 18 is adjusted by the load supporting device 30, and at least one inclinometer 32 attached to the steel frame 18 near the reference plane 10. While the inclination of the steel frame 18 is measured, the steel frame 18 is made vertical by at least three load supporting devices 30. Here, in the vicinity of the reference plane 10, the worker on the reference plane 10 approaches the inclinometer 32 without taking a particularly unnatural posture,
What is necessary is just to set it as the range which can be measured.

【0046】傾斜計32は、例えば、振り子を利用した
サーボ加速度計を使用することができる。これは、振り
子と、振り子の変位を検出する変位検出器と、振り子に
取り付けたコイルと、コイルを囲むマグネットとを有す
る。加速度が加わったとき、振り子が平衡点から動く
と、変位検出器がその変化を信号として出力する。その
出力信号はサーボ増幅器で増幅され、コイルとマグネッ
トが振り子を平衡点に戻すように働く。このとき、コイ
ルに流れる直流電流の大きさは加わった加速度に比例す
るため、その電流を計測することを作動原理とする。こ
のサーボ加速度計を取り付けた鉄骨18が傾斜すると、
振り子が傾こうとして地球重力の分力成分に相当する加
速度が加わる。この加速度をコイルに流れる直流電流と
して計測する。実際には、直流電流から換算された角度
が表示されるため、この角度を傾斜計32から読み取
る。前記サーボ加速度計は、日本航空電子工業株式会社
からMC100L型又はJA-23MA型の商品名で市販されてい
る。鉄骨18の鉛直調整をした後、杭孔12内にトレミ
ー管34を経てコンクリート36を打設し、柱とする。
このとき、杭孔12内に泥水38を満たしておくことが
好ましい。
As the inclinometer 32, for example, a servo accelerometer using a pendulum can be used. It has a pendulum, a displacement detector for detecting the displacement of the pendulum, a coil attached to the pendulum, and a magnet surrounding the coil. When acceleration is applied and the pendulum moves from the equilibrium point, the displacement detector outputs the change as a signal. The output signal is amplified by the servo amplifier, and the coil and the magnet work to return the pendulum to the equilibrium point. At this time, since the magnitude of the DC current flowing through the coil is proportional to the applied acceleration, the operation principle is to measure the current. When the steel frame 18 to which this servo accelerometer is attached tilts,
As the pendulum tilts, an acceleration corresponding to the component force of the earth's gravity is applied. This acceleration is measured as a DC current flowing through the coil. Actually, since the angle converted from the DC current is displayed, this angle is read from the inclinometer 32. The servo accelerometer is commercially available from Japan Aviation Electronics Industry, Ltd. under the trade name of MC100L or JA-23MA. After the vertical adjustment of the steel frame 18, concrete 36 is cast into the pile hole 12 via the tremy tube 34 to form a pillar.
At this time, the muddy water 38 is preferably filled in the pile hole 12.

【0047】基準面10から下方へ掘削した杭孔12内
に柱を構築する別の方法は、再び図1を参照すると、鉄
骨18を貫通させる被貫通孔20と、被貫通孔20の周
りに間隔をおいて取り付けられた少なくとも4つのエレ
クションピース22とを有する架台24を、被貫通孔2
0が杭孔12の上方中央に位置するように基準面10に
設置する。この発明では、鉄骨18を水平方向へ位置調
整するため、エレクションピース22の数量を異ならせ
ている。これは、水平の直交する2方向x、yにおい
て、鉄骨18の位置を調整するには、鉄骨18の一方向
xに位置する少なくとも2箇所と、他方向yに位置する
少なくとも2箇所とのそれぞれで位置を調整することに
よって、容易、かつ、迅速な位置調整ができるとの経験
的事実に基づく。
Another method of constructing a pillar in a pit 12 excavated from the reference plane 10 is shown in FIG. 1 again. A gantry 24 having at least four spaced erection pieces 22 is mounted on a through hole 2.
0 is located on the reference plane 10 such that the 0 is located at the upper center of the pile hole 12. In the present invention, the number of the erection pieces 22 is varied to adjust the position of the steel frame 18 in the horizontal direction. In order to adjust the position of the steel frame 18 in the two horizontal orthogonal directions x and y, at least two positions positioned in one direction x of the steel frame 18 and at least two positions positioned in the other direction y respectively. It is based on the empirical fact that the position can be easily and quickly adjusted by adjusting the position with.

【0048】少なくとも4つのエレクションピース22
と同数のエレクションピース26を有し、これらエレク
ションピース26が架台24のエレクションピース22
と対応するように取り付けられた鉄骨18を吊り上げて
架台24の被貫通孔20に貫通させ、杭孔12内に導
く。
At least four erection pieces 22
Erection pieces 26 of the gantry 24
The steel frame 18 attached so as to correspond to the above is lifted and penetrated through the through hole 20 of the gantry 24 and guided into the pile hole 12.

【0049】その後、鉄骨18のエレクションピース2
6と架台24のエレクションピース22とを上下方向に
整列し、上下方向のレベル調整可能、かつ、水平方向の
位置調整可能な荷重支持装置40(図6及び図7)を架
台24の各エレクションピース22と鉄骨18の各エレ
クションピース26との間に配置して鉄骨18を降ろ
す。
Thereafter, the erection piece 2 of the steel frame 18
6 and the erection piece 22 of the gantry 24 are vertically aligned, and the load support device 40 (FIGS. 6 and 7) capable of adjusting the level in the vertical direction and the position in the horizontal direction is adjusted to each erection piece of the gantry 24. The steel frame 18 is lowered by being arranged between the erection pieces 22 and the erection pieces 26 of the steel frame 18.

【0050】鉄骨18の荷重を少なくとも4つの荷重支
持装置40を経て架台24に伝え、架台24によって受
け止めた後、少なくとも4つの荷重支持装置40によっ
て鉄骨18の水平方向位置を調整する。
The load of the steel frame 18 is transmitted to the gantry 24 via at least four load supporting devices 40, and after being received by the gantry 24, the horizontal position of the steel frame 18 is adjusted by the at least four load supporting devices 40.

【0051】その後、少なくとも4つの荷重支持装置4
0によって鉄骨18のレベルを調整し、基準面10の近
傍で鉄骨18に取り付けられた少なくとも1つの傾斜計
32によって鉄骨18の傾きを計測しながら、少なくと
も4つの荷重支持装置40のうちの3つ又はそれ以上を
使用して鉄骨18を鉛直にする。
Thereafter, at least four load supporting devices 4
0 to adjust the level of the steel frame 18 and measure the tilt of the steel frame 18 by at least one inclinometer 32 attached to the steel frame 18 in the vicinity of the reference plane 10 while three of the at least four load bearing devices 40 are being measured. Or use more to make the steel frame 18 vertical.

【0052】そして、杭孔12内にトレミー管34によ
ってコンクリート26を打設し、柱を構築する。
Then, concrete 26 is poured into the pile hole 12 by the tremy tube 34 to construct a pillar.

【0053】前述の実施例では、鉄骨18の水平方向位
置を調整してから鉄骨18のレベル調整と鉛直調整とを
しているが、これは逆とすることもできる。すなわち、
鉄骨18のレベル調整と鉛直調整とをした後、鉄骨18
の水平位置を調整することもできる。この明細書におい
て、荷重支持装置によって鉄骨の水平方向位置を調整す
ること、荷重支持装置によって鉄骨を鉛直にすることと
あるのは、これらが時系列的に行われることを意味する
のではなく、いずれが先に行われても良いことを意味す
る。
In the above-described embodiment, the level adjustment and the vertical adjustment of the steel frame 18 are performed after the horizontal position of the steel frame 18 is adjusted. However, the order may be reversed. That is,
After the level adjustment and the vertical adjustment of the steel frame 18, the steel frame 18 is adjusted.
The horizontal position can be adjusted. In this specification, to adjust the horizontal position of the steel frame by the load supporting device and to make the steel frame vertical by the load supporting device does not mean that these are performed in time series, This means that either may be performed first.

【0054】柱を構築する別の方法を実施する際、平面
状態の図2に示すように、4つのエレクションピース2
2が架台24に取り付けられること、従って4つのエレ
クションピース26が鉄骨18に取り付けられることが
好ましい。この場合、4つのエレクションピース22
は、隣り合って位置する2つのエレクションピース22
の延長線が実質的に90°の角度で交差するように、か
つ、互いに対向する部分に位置する2つのエレクション
ピース22が実質的に同一平面内に位置するように配置
される。4つのエレクションピース26についても同様
である。
In carrying out another method of constructing a column, four erection pieces 2 are used, as shown in FIG.
Preferably, 2 is attached to the gantry 24 and thus four erection pieces 26 are attached to the steel frame 18. In this case, four erection pieces 22
Are two erection pieces 22 located adjacent to each other.
Are arranged so as to substantially intersect at an angle of 90 °, and the two erection pieces 22 located at portions facing each other are located substantially in the same plane. The same applies to the four erection pieces 26.

【0055】さらに好ましいのは、互いに対向する部分
に位置する2つのエレクションピース22,26を含む
平面Aと、互いに対向する部分に位置する別の2つのエ
レクションピース22,26を含む平面Bとの交点Cの
周りに、4つのエレクションピース22,26が等間隔
で配置されること、すなわち図2の態様となることであ
る。
More preferably, a plane A including two erection pieces 22 and 26 located at a portion facing each other and a plane B including another two erection pieces 22 and 26 located at a portion facing each other. This means that the four erection pieces 22 and 26 are arranged at equal intervals around the intersection C, that is, the mode shown in FIG.

【0056】柱の構築方法を実施する際、2つの傾斜計
32が基準面10の近傍で鉄骨18の実質的に直交する
2つの側面のそれぞれに取り付けられることが好まし
い。鉄骨18が図2に示すように、平面形状が十字状を
呈する、4つの脚からなる中央部分44と、中央部分4
4の各脚に直角な側部分45とからなる場合、互いに直
交する2つの側部分45のそれぞれに2つの傾斜計32
を取り付ける。また、鉄骨18が鋼管からなる場合、直
交する2つの接平面のそれぞれに傾斜計32を取り付け
る。
In practicing the method of constructing a column, two inclinometers 32 are preferably mounted on each of two substantially orthogonal sides of the steel frame 18 near the reference plane 10. As shown in FIG. 2, the steel frame 18 has a cross section in a plane shape, and includes a central portion 44 including four legs and a central portion 4.
4 includes two inclinometers 32 on each of the two side portions 45 orthogonal to each other.
Attach. When the steel frame 18 is made of a steel pipe, the inclinometer 32 is attached to each of two orthogonal tangent planes.

【0057】柱を構築する際、傾斜計32によって鉄骨
18の傾きを計測しながら荷重支持装置30によって鉄
骨18を鉛直にすることと、杭孔12内にコンクリート
36を打設することとを繰り返し、コンクリート36の
打設によって鉄骨18が鉛直からずれるのを防ぐように
する。
When constructing the columns, the load supporting device 30 is used to make the steel frame 18 vertical while the inclination of the steel frame 18 is measured by the inclinometer 32, and the concrete 36 is poured into the pile hole 12 repeatedly. The steel frame 18 is prevented from being displaced from the vertical by placing the concrete 36.

【0058】図示の実施例のように、ケーシング16を
杭孔12内に挿入する場合、架台24を基準面10に設
置するとき、架台24をケーシング16に固定すること
が好ましい。このようにすれば、ケーシング16に架台
24のアンカ機能を持たせることができる。
When the casing 16 is inserted into the pile hole 12 as in the illustrated embodiment, it is preferable that the gantry 24 be fixed to the casing 16 when the gantry 24 is installed on the reference surface 10. In this way, the casing 16 can have the anchoring function of the gantry 24.

【0059】本発明に係る鉄骨配置用設備は、平面状態
を示す図2と、断面状態を示す図3とを参照すると、外
周面に間隔をおいて取り付けられた少なくとも3つのエ
レクションピース26を有する鉄骨18を基準面10か
ら下方へ掘削した杭孔12内に配置する際に使用する設
備であって、架台と、荷重支持装置とを備える。
Referring to FIG. 2 showing a planar state and FIG. 3 showing a cross-sectional state, the equipment for arranging steel frames according to the present invention has at least three erection pieces 26 attached at intervals to the outer peripheral surface. This is equipment used when arranging the steel frame 18 in the pile hole 12 excavated downward from the reference plane 10, and includes a gantry and a load support device.

【0060】架台24は、鉄骨18を貫通させる被貫通
孔20と、被貫通孔20の周りに間隔をおいた前記少な
くとも3つのエレクションピース26と同数のエレクシ
ョンピース22を有し、これらエレクションピース22
が鉄骨のエレクションピース26と対応するように取り
付けられている。
The gantry 24 has a through-hole 20 through which the steel frame 18 penetrates, and the same number of erection pieces 22 as the at least three erection pieces 26 spaced around the through-hole 20.
Are attached so as to correspond to the erection piece 26 made of steel.

【0061】荷重支持装置は、架台24の各エレクショ
ンピース22と鉄骨18の各エレクションピース26と
の間に配置される。荷重支持装置が上下方向のレベル調
整可能である場合、鉄骨18及び架台24はそれぞれ少
なくとも3つのエレクションピース26,22を有し、
荷重支持装置が上下方向のレベル調整可能、かつ、水平
方向の位置調整可能である場合、鉄骨18及び架台24
はそれぞれ少なくとも4つのエレクションピース26,
22を有する。
The load supporting device is disposed between each erection piece 22 of the gantry 24 and each erection piece 26 of the steel frame 18. When the load support device is vertically adjustable, the steel frame 18 and the gantry 24 each have at least three erection pieces 26, 22;
When the load supporting device can adjust the level in the vertical direction and the position in the horizontal direction, the steel frame 18 and the gantry 24 can be adjusted.
Are at least four erection pieces 26,
22.

【0062】上下方向のレベル調整可能な荷重支持装置
30は、側面状態を示す図4及び図5を参照すると、カ
ムアーム50と、座板52と、シム板54と、ねじ部材
56とを備える。
Referring to FIGS. 4 and 5 showing a side view of the load supporting device 30 capable of adjusting the level in the vertical direction, the load supporting device 30 includes a cam arm 50, a seat plate 52, a shim plate 54, and a screw member 56.

【0063】カムアーム50は、作用部58と、この作
用部58から横方向へ間隔をおいた入力部59と、作用
部58及び入力部59から横方向、かつ、下方向へ間隔
をおいた支点部60とを有する。入力部59は作用部5
8の横方向にあるが、これは真横の他、入力部59が作
用部58より上にあっても、逆に下にあってもよい。こ
れに対して、支点部60は作用部58及び入力部59の
横方向で下方向に位置させ、作用部58と、入力部59
と、支点部60とによっててこを形成するようにする。
The cam arm 50 includes an operating portion 58, an input portion 59 laterally spaced from the operating portion 58, and a fulcrum laterally and downwardly spaced from the operating portion 58 and the input portion 59. A part 60. The input unit 59 is the operation unit 5
8, the input portion 59 may be located directly above or below the action portion 58, in addition to being directly beside. On the other hand, the fulcrum part 60 is located below the operation part 58 and the input part 59 in the horizontal direction, and the operation part 58 and the input
And the fulcrum 60 to form a lever.

【0064】図示の実施例では、カムアーム50は構造
用炭素鋼を研削し、焼ならしして次のような形状に作っ
てある。図5に示すように、カムアーム50の作用部5
8は上に向けて凸となった円筒面61を有し、カムアー
ム50の支点部60は下に向けて凸となった円筒面62
を有する。円筒面61及び円筒面62は、それぞれ半径
1、R2の円弧を紙面に垂直な一定の幅にわたって連ね
て形成したものである。半径R1、R2は、同じ大きさで
あってもよく、また異なる大きさであってもよい。
In the illustrated embodiment, the cam arm 50 is formed by grinding and normalizing structural carbon steel into the following shape. As shown in FIG.
8 has a cylindrical surface 61 convex upward, and a fulcrum 60 of the cam arm 50 has a cylindrical surface 62 convex downward.
Having. The cylindrical surface 61 and the cylindrical surface 62 are formed by connecting circular arcs of radii R 1 and R 2 respectively over a certain width perpendicular to the paper surface. The radii R 1 and R 2 may be the same size or may be different sizes.

【0065】例えば、カムアーム50の呼び長さL1を1
20-150 mmに定めるとき、円筒面61,62の中心間距
離L2を10-30 mmに定め、半径R1、R2を20-40 mmに定
めることができる。カムアーム50の紙面に垂直な幅
は、必要支持荷重に基づいて定める。作用部58の円筒
面61は、後述するように、座板の係合部と面接触する
ものであるため、中心角度αが大体100-120°となるよ
うにその範囲を定めることが好ましい。これに対して、
支点部60の円筒面62は、シム板54と線接触し、て
この支点としての機能を果たせばよく、中心角度は数度
とすることができる。カムアーム50の上側では、円筒
面61に傾斜面63を接続し、さらに傾斜面63に水平
面64を接続してある。一方、カムアーム50の下側で
は、円筒面62に2つの傾斜面65,66を接続し、傾
斜面65を円筒面61の延長部分に接続し、傾斜面66
を垂直面67に接続してある。
For example, the nominal length L 1 of the cam arm 50 is set to 1
When deciding to 20-150 mm, defining a center distance L 2 of the cylindrical surface 61, 62 to 10-30 mm, it is possible to determine the radius R 1, R 2 to 20-40 mm. The width of the cam arm 50 perpendicular to the plane of the paper is determined based on the required supporting load. Since the cylindrical surface 61 of the action portion 58 comes into surface contact with the engagement portion of the seat plate as described later, it is preferable to define the range so that the center angle α is approximately 100 to 120 °. On the contrary,
The cylindrical surface 62 of the fulcrum portion 60 may be in line contact with the shim plate 54 to fulfill the function as a fulcrum, and the central angle may be several degrees. Above the cam arm 50, the inclined surface 63 is connected to the cylindrical surface 61, and the horizontal surface 64 is connected to the inclined surface 63. On the other hand, on the lower side of the cam arm 50, the two inclined surfaces 65 and 66 are connected to the cylindrical surface 62, and the inclined surface 65 is connected to an extension of the cylindrical surface 61.
Are connected to a vertical surface 67.

【0066】座板52は、カムアーム50と鉄骨のエレ
クションピース26との間に配置され、エレクションピ
ース26と一部で接触するものであり、カムアーム50
の作用部58と接触する係合部70と、係合部70から
横方向へ間隔をおいて、カムアーム50の入力部59に
対応する部位に設けられた、上下に貫通するねじ穴71
とを有する。座板52のカムアーム50に対面する下側
面は、係合部70以外の部分ではカムアーム50と接触
しない形状とする。
The seat plate 52 is disposed between the cam arm 50 and the erection piece 26 made of steel, and partially contacts the erection piece 26.
And a screw hole 71 penetrating vertically provided at a position corresponding to the input portion 59 of the cam arm 50 at a lateral distance from the engaging portion 70.
And The lower surface of the seat plate 52 facing the cam arm 50 has a shape that does not come into contact with the cam arm 50 at a portion other than the engagement portion 70.

【0067】図示の実施例では、座板52は構造用炭素
鋼を研削して作られており、座板52の係合部70は上
に向けて凹となった円筒面を有する。この円筒面はカム
アーム50の作用部58の円筒面と適合し、ぴったりか
み合う。座板52のエレクションピース26と接触する
部分は、低摩擦係数の表面とすることが好ましい。例え
ば、表面の仕上げ精度を上げたり、ナイロンのような樹
脂板をはめたりすることによって低摩擦係数とする。
In the embodiment shown, the seat plate 52 is made by grinding structural carbon steel, and the engaging portion 70 of the seat plate 52 has a cylindrical surface that is concave upward. This cylindrical surface fits and snugly fits the cylindrical surface of the working part 58 of the cam arm 50. The portion of the seat plate 52 that contacts the erection piece 26 is preferably a surface having a low coefficient of friction. For example, the coefficient of friction is reduced by increasing the finishing accuracy of the surface or by fitting a resin plate such as nylon.

【0068】シム板54は、カムアーム50と架台のエ
レクションピース22との間に配置され、カムアーム5
0の支点部60及びエレクションピース22と接触す
る。シム板54は、図示のように、カムアーム50の支
点部60と接触する面55が傾斜面となるように形成す
る。これによって、レベル調整ができる。
The shim plate 54 is disposed between the cam arm 50 and the erection piece 22 of the gantry.
The fulcrum 60 and the erection piece 22 are in contact with each other. The shim plate 54 is formed such that a surface 55 that contacts the fulcrum 60 of the cam arm 50 is an inclined surface, as shown in the figure. As a result, the level can be adjusted.

【0069】ねじ部材56は、座板52のねじ穴71に
ねじ込まれ、カムアーム50の入力部59と接触してカ
ムアーム50に支持荷重を入力するもので、図示の実施
例では、六角穴付きボルトである。ねじ部材56の先端
又はカムアーム50の入力部59の表面は低摩擦係数で
あることが好ましい。例えば、ねじ部材56の先端を球
面にしたり、入力部59にナイロンのような樹脂板を貼
り付けたりして低摩擦係数とすることができる。
The screw member 56 is screwed into the screw hole 71 of the seat plate 52 and comes into contact with the input portion 59 of the cam arm 50 to input a supporting load to the cam arm 50. In the illustrated embodiment, a hexagon socket head cap screw is used. It is. The tip of the screw member 56 or the surface of the input portion 59 of the cam arm 50 preferably has a low coefficient of friction. For example, the tip of the screw member 56 may be made spherical, or a resin plate such as nylon may be attached to the input portion 59 to have a low friction coefficient.

【0070】荷重支持装置30によって鉄骨を支持すべ
きとき、架台のエレクションピース22上にシム板5
4、カムアーム50及び座板52をこの順で載せ、鉄骨
のエレクションピース26を座板52に載せる。ねじ部
材56の六角穴にラチェット工具74を差し込んでねじ
部材56をねじ込むと、カムアーム50の入力部59が
下方へ押し出され、カムアーム50の作用部58は支点
部60を中心として回転し、上方へ移動する。カムアー
ム50の作用部58の移動に伴い、作用部58の円筒面
61と座板52の係合部70の円筒面とがかみ合ってい
るため、座板52は水平方向へわずかに移動する。鉄骨
の荷重は、ねじ部材56と座板52のねじ穴71との摩
擦によって受け止められる。カムアーム50の作用部5
8の移動と、シム板54の厚みとによってレベルを調整
でき、少なくとも3箇所にある荷重支持装置30それぞ
れのカムアーム50の作用部58の移動によって鉄骨の
鉛直調整ができる。
When the steel frame is to be supported by the load supporting device 30, the shim plate 5 is placed on the erection piece 22 of the gantry.
4. The cam arm 50 and the seat plate 52 are placed in this order, and the steel erection piece 26 is placed on the seat plate 52. When the ratchet tool 74 is inserted into the hexagonal hole of the screw member 56 and the screw member 56 is screwed, the input portion 59 of the cam arm 50 is pushed out downward, and the action portion 58 of the cam arm 50 rotates about the fulcrum 60 and moves upward. Moving. With the movement of the action portion 58 of the cam arm 50, the cylindrical surface 61 of the action portion 58 and the cylindrical surface of the engagement portion 70 of the seat plate 52 are engaged with each other, so that the seat plate 52 slightly moves in the horizontal direction. The load of the steel frame is received by the friction between the screw member 56 and the screw hole 71 of the seat plate 52. Working part 5 of cam arm 50
8 and the thickness of the shim plate 54, the level can be adjusted, and the vertical movement of the steel frame can be adjusted by moving the action portions 58 of the cam arms 50 of at least three load supporting devices 30.

【0071】レベル調整可能、かつ、水平方向の位置調
整可能な荷重支持装置40は、側面状態を示す図6と、
正面状態を示す図7とを参照すると、カムアーム50
と、座板52と、シム板54と、ねじ部材56と、フレ
ーム80とを備える。すなわち、荷重支持装置40は、
荷重支持装置30のカムアーム50、座板52及びシム
板54それぞれの中央部分を取り囲むフレーム80を備
える点で荷重支持装置30と異なっている。
The load supporting device 40 whose level is adjustable and whose position in the horizontal direction is adjustable is shown in FIG.
Referring to FIG. 7 showing the front state, the cam arm 50 is shown.
, A seat plate 52, a shim plate 54, a screw member 56, and a frame 80. That is, the load supporting device 40
The load support device 30 is different from the load support device 30 in that the load support device 30 includes a frame 80 surrounding a central portion of each of the cam arm 50, the seat plate 52, and the shim plate 54.

【0072】フレーム80は細長い環状に形成されてお
り、鉄骨18のエレクションピース26を挿入可能可能
な第1溝82と、第1溝82内に挿入された鉄骨のエレ
クションピース26を固定するボルト84と、架台24
のエレクションピース22を挿入可能な第2溝86と、
第2溝86内に挿入された架台のエレクションピース2
2の左右の側面に接触可能な少なくとも2つのボルト8
8,90とを有する。ボルト84はエレクションピース
26を固定するものであるから、上下に間隔をおいて2
つ設けることが好ましく、フレーム80の一方の側部9
2にねじ込む。これに対して、ボルト88,90はエレ
クションピース22に押し付け、エレクションピース2
6を移動させるものであるから、ボルト90をフレーム
80の一方の側部92に、またボルト88を他方の側部
93にねじ込むようにする。フレーム80は構造用炭素
鋼を鍛造して作ることができる。
The frame 80 is formed in an elongated ring shape, and has a first groove 82 into which the erection piece 26 of the steel frame 18 can be inserted, and a bolt 84 for fixing the erection piece 26 of the steel frame inserted into the first groove 82. And the gantry 24
A second groove 86 into which the erection piece 22 can be inserted;
The erection piece 2 of the gantry inserted into the second groove 86
At least two bolts 8 capable of contacting the left and right side surfaces of the two
8, 90. Since the bolts 84 are for fixing the erection piece 26, the bolts 84 are vertically spaced from each other.
Preferably, one side 9 of the frame 80 is provided.
Screw into 2. On the other hand, the bolts 88 and 90 are pressed against the erection piece 22 and
6 is to be moved, a bolt 90 is screwed into one side 92 of the frame 80 and a bolt 88 is screwed into the other side 93 of the frame 80. The frame 80 can be made by forging structural carbon steel.

【0073】フレーム80の第1溝82と第2溝86と
は連通した1つの溝の形態であるが、第2溝86の方が
第1溝82よりも溝幅が大きい。第1溝82の溝幅は、
エレクションピース26の厚みよりわずかに大きければ
よい。これに対して、第2溝86の溝幅は、第1溝82
の溝幅のほぼ1.5ないし2倍程度の大きさであり、荷重
支持装置30のカムアーム50と、座板52と、シム板
54とが第2溝86内に入る大きさとする。さらに、第
2溝86の2つの溝面87が正面視において第1溝82
から両側へ振り分けられて位置するように形成する。そ
の結果、第1溝82と第2溝86とは、正面形状が凸状
を呈する形態となり、2つの溝面87間の距離の中央が
第1溝82のほぼ中央に対応する。フレーム80の第1
溝82内にエレクションピース26を挿入し、フレーム
80をエレクションピース26に引っ掛けて垂下したと
き、エレクションピース26の下方部分が第2溝86内
へ伸びるように第1溝82の上下長さを定める。
The first groove 82 and the second groove 86 of the frame 80 are in the form of one communicating groove, but the second groove 86 has a larger groove width than the first groove 82. The groove width of the first groove 82 is
What is necessary is just to be slightly larger than the thickness of the erection piece 26. On the other hand, the groove width of the second groove 86 is
And the cam arm 50, the seat plate 52, and the shim plate 54 of the load supporting device 30 enter the second groove 86. Further, the two groove surfaces 87 of the second groove 86 correspond to the first groove 82 in a front view.
From both sides. As a result, the first groove 82 and the second groove 86 have a shape in which the front shape is convex, and the center of the distance between the two groove surfaces 87 substantially corresponds to the center of the first groove 82. First of frame 80
When the erection piece 26 is inserted into the groove 82 and the frame 80 is hung on the erection piece 26 and hangs down, the vertical length of the first groove 82 is determined so that the lower portion of the erection piece 26 extends into the second groove 86. .

【0074】荷重支持装置40を使用して鉄骨を杭孔内
に配置するには次のようにする。まず、図2に示すよう
に、架台24をケーシング16に固定する。図示の架台
24は、平面形状が八角形を呈する孔形成部材100を
中央に有し、その内側が被貫通孔20となっている。4
本の支持部材102が孔形成部材100の1つ置きの辺
部に固着され、さらに4本の補強部材104が隣り合っ
た2本の支持部材102に固着されている。4つのエレ
クションピース22は孔形成部材100の残りの辺部に
固着されている。
The following describes how to place the steel frame in the pile hole using the load supporting device 40. First, the gantry 24 is fixed to the casing 16 as shown in FIG. The illustrated gantry 24 has a hole forming member 100 having an octagonal planar shape in the center, and the inside thereof is a through hole 20. 4
Two support members 102 are fixed to every other side of the hole forming member 100, and four reinforcing members 104 are fixed to two adjacent support members 102. The four erection pieces 22 are fixed to the remaining sides of the hole forming member 100.

【0075】クレーンで吊り上げた鉄骨18を被貫通孔
20から杭孔12内に導き、鉄骨18のエレクションピ
ース26と架台24のエレクションピース22とを図6
及び図7に示すように、上下に整列する。荷重支持装置
40のフレーム80の第1溝82内にエレクションピー
ス26を挿入し、第2溝86内にエレクションピース2
2を挿入する。フレーム80をエレクションピース26
に引っ掛けて垂下し、ボルト84をねじ込んでフレーム
80をエレクションピース26に固定する。その後、カ
ムアーム50と、底板52と、シム板54とをエレクシ
ョンピース26,22間に入れ、クレーンによる吊り上
げを解除する。その結果、鉄骨18の荷重は4つの荷重
支持装置40と架台24とによって受け止められる。
The steel frame 18 lifted by the crane is guided from the through hole 20 into the pile hole 12, and the erection piece 26 of the steel frame 18 and the erection piece 22 of the gantry 24 are connected to each other as shown in FIG.
And as shown in FIG. The erection piece 26 is inserted into the first groove 82 of the frame 80 of the load supporting device 40, and the erection piece 2 is inserted into the second groove 86.
Insert 2. Frame 80 to erection piece 26
And the frame 80 is fixed to the erection piece 26 by screwing the bolt 84. Thereafter, the cam arm 50, the bottom plate 52, and the shim plate 54 are put between the erection pieces 26 and 22, and lifting by the crane is released. As a result, the load of the steel frame 18 is received by the four load supporting devices 40 and the gantry 24.

【0076】図7において、例えば鉄骨のエレクション
ピース26を右方へ移動して位置を調整しようとする場
合、左側のボルト88を緩め、右側のボルト90をねじ
込むと、ボルト90の先端がエレクションピース22に
突き当たり、フレーム80が右方へ移動する。フレーム
80が右方へ移動すると、エレクションピース26がエ
レクションピース22に対して右方へ移動する。このよ
うな調整を図2において対向して位置する2つの荷重支
持装置40で行うことによって、鉄骨18を水平のx方
向へ位置調整できる。さらに、対向して位置する別の2
つの荷重支持装置40によって鉄骨18を水平のy方向
へ位置調整できる。
In FIG. 7, for example, when the steel erection piece 26 is to be moved to the right to adjust the position, the left bolt 88 is loosened and the right bolt 90 is screwed into. 22, the frame 80 moves rightward. When the frame 80 moves rightward, the erection piece 26 moves rightward with respect to the erection piece 22. By performing such an adjustment using the two load supporting devices 40 that are opposed to each other in FIG. 2, the position of the steel frame 18 can be adjusted in the horizontal x direction. In addition, another 2
With the two load supporting devices 40, the position of the steel frame 18 can be adjusted in the horizontal y direction.

【0077】鉄骨18の水平方向の位置調整が完了した
後、ボルト88,90を緩め、ねじ部材56をねじ込ん
でレベル調整と鉛直調整とを行う。全ての調整が完了し
た後、フレーム80の下端部にねじ込んだボルト94を
締め付けて鉄骨18の転倒を防止することが好ましい。
After the horizontal position adjustment of the steel frame 18 is completed, the bolts 88 and 90 are loosened, and the screw member 56 is screwed in to perform level adjustment and vertical adjustment. After all the adjustments are completed, it is preferable to prevent the steel frame 18 from tipping over by tightening a bolt 94 screwed into the lower end of the frame 80.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る柱の構築方法を示す模式図であ
る。
FIG. 1 is a schematic view showing a method for constructing a pillar according to the present invention.

【図2】本発明に係る鉄骨配置用設備の実施例を示す平
面図である。
FIG. 2 is a plan view showing an embodiment of the equipment for arranging steel frames according to the present invention.

【図3】図2の3−3線で切断した断面図である。FIG. 3 is a sectional view taken along line 3-3 in FIG. 2;

【図4】荷重支持装置の実施例を示す側面図である。FIG. 4 is a side view showing an embodiment of the load supporting device.

【図5】荷重支持装置に使用したカムアームの側面図で
ある。
FIG. 5 is a side view of a cam arm used for the load supporting device.

【図6】荷重支持装置の別の実施例を示す側面図であ
る。
FIG. 6 is a side view showing another embodiment of the load supporting device.

【図7】図6に示した荷重支持装置の正面図である。FIG. 7 is a front view of the load supporting device shown in FIG. 6;

【符号の説明】[Explanation of symbols]

10 基準面 12 杭孔 16 ケーシング 18 鉄骨 20 被貫通孔 22,26 エレクションピース 24 架台 30,40 荷重支持装置 32 傾斜計 50 カムアーム 52 座板 54 シム板 56 ねじ部材 80 フレーム REFERENCE SIGNS LIST 10 reference plane 12 pile hole 16 casing 18 steel frame 20 through hole 22, 26 erection piece 24 gantry 30, 40 load support device 32 inclinometer 50 cam arm 52 seat plate 54 shim plate 56 screw member 80 frame

フロントページの続き (72)発明者 永滝 周一 神奈川県横浜市神奈川区富家町1番地1 株式会社熊谷組横浜支店内 Fターム(参考) 2D047 AB04 2D050 AA07 AA11 CA01 CA05 EE04 EE10 EE19 Continued on the front page (72) Inventor Shuichi Nagataki 1 Tomi-cho, Kanagawa-ku, Yokohama-shi, Kanagawa Prefecture F-term (reference) 2D047 AB04 2D050 AA07 AA11 CA01 CA05 EE04 EE10 EE19

Claims (10)

【特許請求の範囲】[Claims] 【請求項1】 基準面から下方へ掘削した杭孔内に柱を
構築する方法であって、 鉄骨を貫通させる被貫通孔と、この被貫通孔の周りに間
隔をおいて取り付けられた少なくとも3つのエレクショ
ンピースとを有する架台を、前記被貫通孔が前記杭孔の
上方に位置するように前記基準面に設置すること、 前記少なくとも3つのエレクションピースと同数のエレ
クションピースを有し、これらエレクションピースが前
記架台のエレクションピースと対応するように取り付け
られた鉄骨を吊り上げて前記架台の被貫通孔に貫通さ
せ、前記杭孔内に導くこと、 前記鉄骨のエレクションピースと前記架台のエレクショ
ンピースとを上下方向に整列し、上下方向のレベル調整
可能な荷重支持装置を前記架台の各エレクションピース
と前記鉄骨の各エレクションピースとの間に配置して鉄
骨を降ろすこと、 前記基準面の近傍で前記鉄骨に取り付けられた少なくと
も1つの傾斜計によって前記鉄骨の傾きを計測しながら
前記荷重支持装置によって前記鉄骨を鉛直にすること、 前記杭孔内にコンクリートを打設することを含む、柱の
構築方法。
1. A method of constructing a pillar in a pile hole excavated downward from a reference plane, comprising: a through-hole for penetrating a steel frame; and at least three holes attached around the through-hole at intervals. Mounting a gantry having two erection pieces on the reference surface such that the penetrated hole is located above the pile hole; and having at least three erection pieces as the number of erection pieces; Lifting a steel frame attached so as to correspond to the erection piece of the gantry, penetrating the pierced hole of the gantry, and guiding it into the pile hole, vertically moving the erection piece of the steel frame and the erection piece of the gantry A load support device that is aligned in the vertical direction and that can adjust the level in the vertical direction is mounted on each of the erection pieces of the gantry and each of the steel frames. Lowering the steel frame by placing the steel frame vertically with the load supporting device while measuring the inclination of the steel frame by at least one inclinometer attached to the steel frame near the reference plane. A method of constructing a pillar, comprising: placing concrete in the pile hole.
【請求項2】 基準面から下方へ掘削した杭孔内に柱を
構築する方法であって、 鉄骨を貫通させる被貫通孔と、この被貫通孔の周りに間
隔をおいて取り付けられた少なくとも4つのエレクショ
ンピースとを有する架台を、前記被貫通孔が前記杭孔の
上方に位置するように前記基準面に設置すること、 前記少なくとも4つのエレクションピースと同数のエレ
クションピースを有し、これらエレクションピースが前
記架台のエレクションピースと対応するように取り付け
られた鉄骨を吊り上げて前記架台の被貫通孔に貫通さ
せ、前記杭孔内に導くこと、 前記鉄骨のエレクションピースと前記架台のエレクショ
ンピースとを上下方向に整列し、上下方向のレベル調整
可能、かつ、水平方向の位置調整可能な荷重支持装置を
前記架台の各エレクションピースと前記鉄骨の各エレク
ションピースとの間に配置して鉄骨を降ろすこと、 前記荷重支持装置によって前記鉄骨の水平方向位置を調
整すること、 前記基準面の近傍で前記鉄骨に取り付けられた少なくと
も1つの傾斜計によって前記鉄骨の傾きを計測しながら
前記荷重支持装置によって前記鉄骨を鉛直にすること、 前記杭孔内にコンクリートを打設することを含む、柱の
構築方法。
2. A method of constructing a pillar in a pile hole excavated downward from a reference plane, comprising: a through-hole for penetrating a steel frame; and at least four holes attached around the through-hole. Mounting a gantry having two erection pieces on the reference surface such that the penetrated hole is located above the pile hole; and having at least four erection pieces and the same number of erection pieces. Lifting a steel frame attached so as to correspond to the erection piece of the gantry, penetrating the pierced hole of the gantry, and guiding it into the pile hole, vertically moving the erection piece of the steel frame and the erection piece of the gantry Erection of the gantry with a load support device that is aligned in the direction, level adjustable in the vertical direction, and position adjustable in the horizontal direction. Disposing a steel frame between a piece and each erection piece of the steel frame, adjusting a horizontal position of the steel frame by the load supporting device, at least one of the steel frames being attached to the steel frame near the reference plane. A method for constructing a column, comprising: verticalizing the steel frame by the load supporting device while measuring the inclination of the steel frame by using two inclinometers; and placing concrete in the pile hole.
【請求項3】 4つの前記エレクションピースが前記架
台に取り付けられており、これらエレクションピース
は、隣り合って位置する2つのエレクションピースの延
長線が実質的に90°の角度で交差するように、かつ、
互いに対向する部分に位置する2つのエレクションピー
スが実質的に同一平面内に位置するように配置された、
請求項2に記載の柱の構築方法。
3. The erection piece is mounted on the gantry, wherein the erection pieces intersect at a substantially 90 ° angle with the extension lines of two adjacent erection pieces. And,
Two erection pieces located at opposing portions are arranged to be substantially in the same plane,
The method for constructing a pillar according to claim 2.
【請求項4】 2つの前記傾斜計が前記基準面の近傍で
前記鉄骨の実質的に直交する側面に取り付けられ、前記
鉄骨の傾きを計測する、請求項1ないし請求項3のいず
れかに記載の柱の構築方法。
4. The inclinometer according to claim 1, wherein two of the inclinometers are mounted on substantially perpendicular side surfaces of the steel frame in the vicinity of the reference plane, and measure the inclination of the steel frame. How to build pillars.
【請求項5】 前記傾斜計によって前記鉄骨の傾きを計
測しながら前記荷重支持装置によって前記鉄骨を鉛直に
することと、前記杭孔内にコンクリートを打設すること
とを繰り返す、請求項4に記載の柱の構築方法。
5. The method according to claim 4, wherein, while the inclination of the steel frame is measured by the inclinometer, the steel frame is vertically set by the load support device and concrete is poured into the pile hole. How to build the pillars described.
【請求項6】 前記架台を前記基準面に設置するに先立
って前記杭孔内にケーシングを挿入し、前記架台を前記
基準面に設置するとき、前記架台を前記ケーシングに固
定する、請求項1ないし請求項3のいずれかに記載の柱
の構築方法。
6. The method according to claim 1, wherein a casing is inserted into the pile hole prior to installing the gantry on the reference surface, and the gantry is fixed to the casing when the gantry is installed on the reference surface. A method for constructing a pillar according to claim 3.
【請求項7】 外周面に間隔をおいて取り付けられた少
なくとも3つのエレクションピースを有する鉄骨を基準
面から下方へ掘削した杭孔内に配置する際に使用する設
備であって、 前記鉄骨を貫通させる被貫通孔と、この被貫通孔の周り
に間隔をおいた前記少なくとも3つのエレクションピー
スと同数のエレクションピースとを有し、これらエレク
ションピースが前記鉄骨のエレクションピースと対応す
るように取り付けられた架台と、 この架台の各エレクションピースと前記鉄骨の各エレク
ションピースとの間に配置され、上下方向のレベル調整
可能な荷重支持装置とを備える、鉄骨配置用設備。
7. A facility for use in arranging a steel frame having at least three erection pieces attached to an outer peripheral surface at intervals in a pile hole excavated downward from a reference plane, wherein the steel frame penetrates the steel frame. And a plurality of erection pieces equal in number to the at least three erection pieces spaced around the pierced hole, and the erection pieces were mounted so as to correspond to the erection pieces of the steel frame. An equipment for arranging a steel frame, comprising: a gantry; and a load supporting device arranged between each erection piece of the gantry and each erection piece of the steel frame and capable of adjusting a vertical level.
【請求項8】 前記荷重支持装置は、 作用部と、この作用部から横方向へ間隔をおいた入力部
と、前記作用部及び前記入力部から横方向、かつ、下方
向へ間隔をおいた支点部とを有するカムアームと、 このカムアームと前記鉄骨のエレクションピースとの間
に配置され、前記鉄骨のエレクションピースと接触する
座板であって前記カムアームの作用部と接触する係合部
と、この係合部から横方向へ間隔をおいた、前記カムア
ームの前記入力部に対応する部位に設けられ、上下に貫
通するねじ穴とを有する座板と、 前記カムアームと前記架台のエレクションピースとの間
に配置され、前記カムアームの支点部及び前記架台のエ
レクションピースと接触するシム板と、 前記座板のねじ穴にねじ込まれ、前記カムアームの入力
部と接触して前記カムアームに支持荷重を入力するねじ
部材とを備える、請求項7に記載の鉄骨配置用設備。
8. The load supporting device according to claim 1, further comprising: an operating part, an input part laterally spaced from the operating part, and a laterally and downwardly spaced part from the operating part and the input part. A cam arm having a fulcrum, an engagement portion disposed between the cam arm and the erection piece of the steel, and a seat plate that contacts the erection piece of the steel, and an engagement portion that contacts an action portion of the cam arm; A seat plate, which is provided at a position corresponding to the input portion of the cam arm and is vertically spaced from the engagement portion and has a screw hole vertically penetrating therethrough, between the cam arm and the erection piece of the gantry; A shim plate that contacts the fulcrum of the cam arm and the erection piece of the gantry, and is screwed into a screw hole of the seat plate, and contacts the input portion of the cam arm to And a screw member for inputting a bearing load on the arm, equipment for steel arrangement according to claim 7.
【請求項9】 外周面に間隔をおいて取り付けられた少
なくとも4つのエレクションピースを有する鉄骨を基準
面から下方へ掘削した杭孔内に配置する際に使用する設
備であって、 前記鉄骨を貫通させる被貫通孔と、この被貫通孔の周り
に間隔をおいた前記少なくとも4つのエレクションピー
スと同数のエレクションピースとを有し、これらエレク
ションピースが前記鉄骨のエレクションピースと対応す
るように取り付けられた架台と、 この架台の各エレクションピースと前記鉄骨の各エレク
ションピースとの間に配置され、上下方向のレベル調整
可能、かつ、水平方向の位置調整可能な荷重支持装置と
を備える、鉄骨配置用設備。
9. A facility for arranging a steel frame having at least four erection pieces attached to an outer peripheral surface at intervals in a pile hole excavated downward from a reference plane, wherein the steel frame penetrates the steel frame. And a plurality of erection pieces equal in number to the at least four erection pieces spaced around the pierced hole. A frame, and a load supporting device disposed between each erection piece of the gantry and each erection piece of the steel frame, and capable of adjusting the level in the vertical direction and adjusting the position in the horizontal direction. .
【請求項10】 前記荷重支持装置は、 作用部と、この作用部から横方向へ間隔をおいた入力部
と、前記作用部及び前記入力部から横方向、かつ、下方
向へ間隔をおいた支点部とを有するカムアームと、 このカムアームと前記鉄骨のエレクションピースとの間
に配置され、前記鉄骨のエレクションピースと接触する
座板であって前記カムアームの作用部と接触する係合部
と、この係合部から横方向へ間隔をおいた、前記カムア
ームの前記入力部に対応する部位に設けられ、上下に貫
通するねじ穴とを有する座板と、 前記カムアームと前記架台のエレクションピースとの間
に配置され、前記カムアームの支点部及び前記架台のエ
レクションピースと接触するシム板と、 前記座板のねじ穴にねじ込まれ、前記カムアームの入力
部と接触して前記カムアームに支持荷重を入力するねじ
部材と、 前記カムアームと前記座板と前記シム板とを取り囲むフ
レームであって前記鉄骨のエレクションピースを挿入可
能可能な第1溝と、この第1溝内に挿入された前記鉄骨
のエレクションピースを固定するボルトと、前記架台の
エレクションピースを挿入可能な第2溝と、この第2溝
内に挿入された前記架台のエレクションピースの左右の
側面に接触可能な少なくとも2つのボルトとを有するフ
レームとを備える、請求項9に記載の鉄骨配置用設備。
10. The load supporting device according to claim 1, further comprising: an operating portion, an input portion laterally spaced from the operating portion, and a laterally and downwardly spaced direction from the operating portion and the input portion. A cam arm having a fulcrum, an engagement portion disposed between the cam arm and the erection piece of the steel, and a seat plate that contacts the erection piece of the steel, and an engagement portion that contacts an action portion of the cam arm; A seat plate, which is provided at a position corresponding to the input portion of the cam arm and is vertically spaced from the engagement portion and has a screw hole vertically penetrating therethrough, between the cam arm and the erection piece of the gantry; A shim plate that contacts the fulcrum of the cam arm and the erection piece of the gantry, and is screwed into a screw hole of the seat plate, and comes into contact with an input portion of the cam arm. A screw member for inputting a support load to the arm, a frame surrounding the cam arm, the seat plate, and the shim plate, the first groove being capable of inserting the erection piece of the steel frame, and being inserted into the first groove. A bolt for fixing the erection piece of the steel frame, a second groove in which the erection piece of the gantry can be inserted, and at least a left and right side surface of the erection piece of the gantry inserted in the second groove. The equipment for steel frame placement according to claim 9, comprising a frame having two bolts.
JP27167399A 1999-09-27 1999-09-27 Constructing method for column and facility for arranging steel frame Withdrawn JP2001090070A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27167399A JP2001090070A (en) 1999-09-27 1999-09-27 Constructing method for column and facility for arranging steel frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27167399A JP2001090070A (en) 1999-09-27 1999-09-27 Constructing method for column and facility for arranging steel frame

Publications (1)

Publication Number Publication Date
JP2001090070A true JP2001090070A (en) 2001-04-03

Family

ID=17503295

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27167399A Withdrawn JP2001090070A (en) 1999-09-27 1999-09-27 Constructing method for column and facility for arranging steel frame

Country Status (1)

Country Link
JP (1) JP2001090070A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758759A (en) * 2017-02-20 2017-05-31 中铁十九局集团第七工程有限公司 A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN108716912A (en) * 2018-04-16 2018-10-30 上海同济检测技术有限公司 Dual axis inclinometer verticality tracking measurement method
JP2022135817A (en) * 2021-03-05 2022-09-15 広州市市政集団有限公司 Excess casting monitoring device for caisson pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758759A (en) * 2017-02-20 2017-05-31 中铁十九局集团第七工程有限公司 A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN108716912A (en) * 2018-04-16 2018-10-30 上海同济检测技术有限公司 Dual axis inclinometer verticality tracking measurement method
CN108716912B (en) * 2018-04-16 2020-07-28 上海同济检测技术有限公司 Perpendicularity tracking and measuring method for double-shaft inclinometer
JP2022135817A (en) * 2021-03-05 2022-09-15 広州市市政集団有限公司 Excess casting monitoring device for caisson pile

Similar Documents

Publication Publication Date Title
CN110219326B (en) Reverse construction method one-column one-pile underwater verticality adjusting construction process
CN205530322U (en) Fixed steel column foot pre -cast screw's construction equipment
US7530176B2 (en) Method and apparatus for monitoring element alignment
CN113482068A (en) Foundation pit support automatic monitoring system
CN112663613A (en) Verticality control device and verticality control method for latticed column
JP2001090070A (en) Constructing method for column and facility for arranging steel frame
JP3732721B2 (en) Tower-like structure leg installation method and equipment used therefor
JP3483522B2 (en) Position adjustment device for steel columns
CN113585079B (en) Method for quickly installing steel structure stand column
CN210049110U (en) Pier adjusting device and pier adjusting system
JP3616895B2 (en) Construction pillar erection device
JPH03295931A (en) Construction method for frame straight pillar
JP4945230B2 (en) Anchor bolt support
JPH0657763A (en) Construction of vertical shaft with center column by solidification of mud slurry
CN107513997A (en) The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis
CN209636882U (en) Underground piling bar column verticality-regulating system
JPH04281916A (en) Base device for construction of main post
CN216194782U (en) Steel pipe column positioning system
CN117449611A (en) Measurement and installation method for large-diameter long-inclined embedded bolt and angle adjusting device
JPH055312A (en) Setting of structural center column
JPH0531631B2 (en)
CN211080336U (en) Fixing device for static load test pile foundation displacement meter
CN1424469A (en) Method and apparatus for controlling verticality of steel pile
CN115219089B (en) Foundation pit monitoring system applied to construction supervision and detection method
CN221147752U (en) Novel water level measuring instrument

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20061205