JPH0531631B2 - - Google Patents
Info
- Publication number
- JPH0531631B2 JPH0531631B2 JP27076085A JP27076085A JPH0531631B2 JP H0531631 B2 JPH0531631 B2 JP H0531631B2 JP 27076085 A JP27076085 A JP 27076085A JP 27076085 A JP27076085 A JP 27076085A JP H0531631 B2 JPH0531631 B2 JP H0531631B2
- Authority
- JP
- Japan
- Prior art keywords
- steel column
- cylinder
- frame
- guide
- guide cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 51
- 239000010959 steel Substances 0.000 claims description 51
- 238000009412 basement excavation Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 2
- 238000010276 construction Methods 0.000 description 10
- 238000000034 method Methods 0.000 description 7
- 238000003780 insertion Methods 0.000 description 4
- 230000037431 insertion Effects 0.000 description 4
- 239000000725 suspension Substances 0.000 description 2
- 230000008602 contraction Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は鉄骨柱の建込み方法及びその装置に関
する。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method and apparatus for erecting a steel column.
(従来の技術)
従来、建造物を構築する際に、地下部の逆打工
法の一環として行われる鉄骨柱の建込み方法とし
ては、建込み装置を設置してからこの装置で鉄骨
柱を支持しつつ建て込み、その後コンクリートを
打設する方法であつた。また建込み装置として、
建込み架台に鉄骨柱を支承する支持装置を設け、
上記鉄骨柱を鉛直調整する調整手段を設けている
ものがある。(Conventional technology) Conventionally, when constructing a building, the method of erecting steel columns as part of the reverse construction method for underground areas involves installing erecting equipment and then supporting the steel columns with this equipment. The method was to build the building while doing so, and then pour concrete. Also, as construction equipment,
A support device is installed on the erection frame to support the steel column,
Some are equipped with adjustment means for vertically adjusting the steel columns.
(発明が解決しようとする問題点)
従来の建込み方法によると、鉄骨柱を挿入して
から、柱の内側等からコンクリート打設用のトレ
ミー管などを挿入するため、その内側等に挿入空
間がない場合には施工ができない不都合があつ
た。そして鉄骨柱が地表に突出する場合は、建込
み装置や作業足場が高くなり、コンクリート打設
が面倒となり、例えばミキサ車による直打ちがで
きず、しかも鉄骨柱の下方が長くなる分だけ曲が
りやすくなるなど、建込み精度上問題があり、反
対に鉄骨柱の頭部が地表より下方にある場合に
は、同形の鉄骨柱を継ぎ足ししないと、建込み架
台に支持できないため、継ぎ足しの必要があり、
作業上工程数が増す欠点があつた。また従来の建
込み装置によると、鉄骨柱を直接支承し、鉄骨柱
心調整をするので、柱の建込みやその調整に時間
を要し、作業能率が悪かつた。(Problems to be Solved by the Invention) According to the conventional construction method, a steel column is inserted and then a tremie pipe for concrete pouring is inserted from inside the column, so an insertion space is created inside the column. There was an inconvenience that construction could not be carried out without it. If the steel columns protrude above the ground, the construction equipment and work scaffolding will be higher, making concrete pouring more troublesome. For example, direct pouring with a mixer truck is not possible, and the longer the lower part of the steel columns, the more likely they are to bend. On the other hand, if the head of the steel column is below the ground level, it cannot be supported on the erection frame unless a steel column of the same shape is added, so it is necessary to add another steel column. ,
The disadvantage was that the number of work steps increased. Further, according to the conventional erecting equipment, since the steel column is directly supported and the steel column center is adjusted, it takes time to erect the column and adjust it, resulting in poor work efficiency.
本発明の目的は、建込み作業を容易かつ能率的
に行うことであり、他の目的は建込み精度の向上
を図ることにある。 An object of the present invention is to perform erection work easily and efficiently, and another object is to improve the accuracy of erection.
(問題点を解決するための手段)
本発明の建込み方法は、地盤中に縦穴を掘削
し、掘削後縦穴内に建込み架台で支持したガイド
筒体を挿入し、この筒体の内空を利用して縦穴内
に所定レベルまでコンクリートを打設し、打設
後、鉛直調整した上記ガイド筒体内に、この筒体
を案内として一端部を吊持した鉄骨柱を挿入し、
他端部側を上記コンクリートに挿入することであ
る。(Means for Solving the Problems) The erection method of the present invention involves excavating a vertical hole in the ground, inserting a guide cylinder supported by a erection frame into the vertical hole after excavation, and Concrete is poured into the vertical hole to a predetermined level using the concrete, and after pouring, a steel column with one end suspended is inserted into the vertically adjusted guide cylinder using the cylinder as a guide.
The other end is inserted into the concrete.
また本発明の建込み装置は、上記建込み方法を
実施するためのもので、建込み架台と、この建込
み架台に支持しかつこの架台から垂設しており、
内面に鉄骨柱を案内するガイドを設けてあるガイ
ド筒体と、このガイド筒体に設けた筒体の鉛直調
整手段と、ガイド筒体の鉛直度を測定する測定手
段と、上記鉄骨柱を吊持する吊持手段とを具備す
るものである。 Further, the erection device of the present invention is for carrying out the above-mentioned erection method, and includes a erection frame, supported by the erection frame and suspended from the erection frame,
A guide cylinder provided with a guide for guiding a steel column on its inner surface, a vertical adjustment means for the cylinder provided on the guide cylinder, a measuring means for measuring the verticality of the guide cylinder, and a means for suspending the steel column. and a suspension means for holding the device.
(作用)
縦穴内にガイド筒体を挿入設置してコンクリー
トを打設しから、鉄骨柱を建込む。鉄骨柱は吊持
ち手段で吊持ちするため、柱鉄骨の上端部が地表
より突出しているか、又は下方に位置しているか
とは関係なく建込み架台の高さを常に一定するこ
とができる。鉄骨柱はガイド筒体の内面に設けて
あるガイドにより案内される。鉄骨柱の鉛直度は
コンクリートが固化して、鉄骨柱が十分固定され
るまで測定手段により管理可能である。鉄骨柱の
芯出しは直接行なわず、鉛直修正されたガイド筒
体を通じて芯調整される。(Operation) A guide cylinder is inserted into the vertical hole, concrete is poured, and the steel column is erected. Since the steel column is suspended by a suspension means, the height of the erected frame can always be kept constant regardless of whether the upper end of the steel column protrudes from the ground surface or is located below. The steel column is guided by a guide provided on the inner surface of the guide cylinder. The verticality of the steel column can be controlled by measuring means until the concrete hardens and the steel column is sufficiently fixed. The centering of the steel columns is not performed directly, but is adjusted through a guide cylinder whose verticality has been corrected.
(実施例)
以下本発明の実施例を図面を参照して説明す
る。(Example) Examples of the present invention will be described below with reference to the drawings.
まず、鉄骨柱の建込み装置を説明し、ついで建
込み方法を説明する。 First, the equipment for erecting steel columns will be explained, and then the erecting method will be explained.
第1,2図において、建込み架台1が地上に縦
穴Gaを臨む位置に設置してある。建込み架台1
は平面四角形で、各脚部1aは架台ベース2上に
ボルト3で固定してある。建込み架台1には4台
のレベル調整のためのジヤツキ4が設けてあり、
各ジヤツキで水平台枠1bの水平レベルを調整す
る。 In Figures 1 and 2, a built-in frame 1 is installed on the ground at a position facing the vertical hole Ga. Built-in frame 1
has a rectangular planar shape, and each leg portion 1a is fixed onto a gantry base 2 with bolts 3. The built-in frame 1 is equipped with four jacks 4 for level adjustment.
Each jack adjusts the horizontal level of the horizontal underframe 1b.
建込み架台1の中心には、平面四角形状の建込
みガイド筒体5が挿入設置してあり、筒体の上端
に水平に取りつけた支持枠5aが架台の台枠1b
上に載置してある。ガイド筒体5の中心は8本の
調整ボルト6により建込み柱位置の中心に合わせ
ることができる。ガイド筒体5の内面の上下に
は、第1〜3図に示すように鉄骨柱Pを筒体内に
挿入案内する上部ガイドレール7及び下部ガイド
レール8が上下方向に敷設してある。上下各ガイ
ドレールは、1対のチヤンネル7a,8aを所定
間隔を置いて背中合せにして、一方のフランジを
筒体5の内面にねじで固着している。鉄骨柱Pの
図示の例では十字状であるため、この形状に合う
ようにガイドレール7,8を筒体各面の内面の所
定位置に配置してある。鉄骨柱Pのブラケツト
B,Baが第2,3図に示すように、ガイドレー
ル7,8のチヤンネル間に位置し、保持されてい
る。またガイド筒体5の下部外周には第1,3図
に示すように筒体の直角四方向に水平ジヤツキ9
がブラケツト9aにより取り付けてある。このジ
ヤツキのラム9bの先端には調整アーム9cが軸
ピンを中心として揺動可能に取り付けてある。各
アーム9cはガイド筒体5外周に取り付けたブラ
ケツト9dに軸9eを中心として揺動可能に取り
付けてある。ラム9bの伸縮により、アーム9c
が軸9eを中心として揺動し、縦穴Baのスタン
ドパイプS内面に押圧的に当接可能である。ジヤ
ツキ9のストロークを調整することにより、ガイ
ド筒体5を第3図X,Y両方向の位置・調整がで
きて、筒体の鉛直度の修正が可能となる。ジヤツ
キ9の作動は地上に設置してある油圧ポンプ10
を操作して行われる。 A construction guide cylinder 5 having a rectangular planar shape is inserted into the center of the construction frame 1, and a support frame 5a attached horizontally to the upper end of the cylinder supports the frame 1b of the frame.
It is placed above. The center of the guide cylinder 5 can be aligned with the center of the erected pillar position using eight adjustment bolts 6. As shown in FIGS. 1 to 3, an upper guide rail 7 and a lower guide rail 8 are installed in the vertical direction on the inner surface of the guide cylinder 5 to guide the insertion of the steel column P into the cylinder. Each of the upper and lower guide rails has a pair of channels 7a and 8a placed back to back at a predetermined interval, and one flange is fixed to the inner surface of the cylindrical body 5 with a screw. Since the illustrated example of the steel column P has a cross shape, guide rails 7 and 8 are arranged at predetermined positions on the inner surface of each surface of the cylinder to match this shape. As shown in FIGS. 2 and 3, the brackets B and Ba of the steel column P are positioned and held between the channels of the guide rails 7 and 8. In addition, on the outer periphery of the lower part of the guide cylinder 5, there are horizontal jacks 9 in four directions perpendicular to the cylinder as shown in FIGS. 1 and 3.
is attached by a bracket 9a. An adjustment arm 9c is attached to the tip of the ram 9b of this jack so as to be able to swing around a shaft pin. Each arm 9c is attached to a bracket 9d attached to the outer periphery of the guide cylinder 5 so as to be swingable about an axis 9e. Due to the expansion and contraction of the ram 9b, the arm 9c
swings around the shaft 9e and can press against the inner surface of the stand pipe S of the vertical hole Ba. By adjusting the stroke of the jack 9, the guide cylinder 5 can be positioned and adjusted in both the X and Y directions in FIG. 3, and the verticality of the cylinder can be corrected. The jack 9 is operated by a hydraulic pump 10 installed on the ground.
This is done by operating.
ガイド筒体5の鉛直度の測定は、第1図に示す
ように筒体の外周に取り付けた傾斜計11と、地
上に設置してある傾斜測定器12により行う。 The verticality of the guide cylinder 5 is measured using an inclinometer 11 attached to the outer periphery of the cylinder and an inclinometer 12 installed on the ground, as shown in FIG.
鉄骨柱Pの上端は、ワイヤ12の下端に取り付
けた吊金具14により吊持ちしてある。 The upper end of the steel column P is suspended by a hanging fitting 14 attached to the lower end of the wire 12.
15はガイド筒体の支持枠5a上に設置したジ
ヤツキであつて、このジヤツキは上部ブラケツト
Bを介して鉄骨柱Pの高さ位置を調整可能であ
る。 Reference numeral 15 denotes a jack installed on the support frame 5a of the guide cylinder, and this jack can adjust the height position of the steel column P via the upper bracket B.
次に鉄骨柱の建込み方法を説明する。 Next, we will explain how to erect steel columns.
第4図に示すように地盤中にスタンドパイプS
を圧入してから、リバース掘削機等の掘削機によ
り縦穴Gaを掘削し、掘削後この縦穴内に鉄筋か
ご(図示せず)を挿入設置する。そして縦穴Ga
を臨む地上に建込み架台1を設置し、ジヤツキ4
により台枠1bのレベルを調整する。 As shown in Figure 4, stand pipe S is placed in the ground.
After press-fitting, a vertical hole Ga is excavated using an excavator such as a reverse excavator, and after excavation, a reinforcing bar cage (not shown) is inserted and installed in this vertical hole. And vertical hole Ga
Install the built-in frame 1 on the ground facing the
The level of the underframe 1b is adjusted by.
建込み架台1を設置した後、第5図に示すよう
に建込みガイド筒体5を架台の中心に沿つて上方
から挿入し、筒体の上端の支持枠5aを架台の台
枠1b上に載置支持する。そして建込み架台1上
に設けた調整ボルト6により、直角四方向の位置
をトランシツト等で測定して調整し、架台の中心
にガイド筒体5の支持枠5aの心を合わせる。そ
して筒体5の下部の水平ジヤツキ9を油圧ポンプ
10を操作して、ストロークを調整して、アーム
9cをスタンドパイプSの内壁面に押圧させなが
ら、筒体の鉛直度を調整する。この筒体の鉛直度
は傾斜計11と傾斜測定器12とで測定する。鉛
直度を修正してからガイド筒体5を固定する。 After installing the erection frame 1, as shown in FIG. 5, insert the erection guide cylinder 5 from above along the center of the frame, and place the support frame 5a at the upper end of the cylinder onto the underframe 1b of the frame. Place and support. Then, the positions in the four right-angled directions are measured and adjusted using a transit or the like using adjustment bolts 6 provided on the erection frame 1, and the center of the support frame 5a of the guide cylinder 5 is aligned with the center of the frame. Then, the stroke of the horizontal jack 9 at the bottom of the cylinder 5 is adjusted by operating the hydraulic pump 10, and the verticality of the cylinder is adjusted while pressing the arm 9c against the inner wall surface of the stand pipe S. The verticality of this cylindrical body is measured by an inclinometer 11 and an inclinometer 12. After correcting the verticality, the guide cylinder 5 is fixed.
ガイド筒体5の挿入設置が完了した後、このガ
イド筒体内にトレミー管を挿入して、地上のミキ
サ車からコンクリートを縦穴Ga内に所定のレベ
ルまで打設する。 After the insertion and installation of the guide cylinder 5 is completed, a tremie pipe is inserted into the guide cylinder, and concrete is poured from a ground mixer truck into the vertical hole Ga to a predetermined level.
打設を終了し、トレミー管を引抜いてから、鉄
骨柱Pをクレーンのワイヤ13下端の吊金具14
で吊持して、筒体の上方から上部ガイドレール
7、下部ガイドレール8に沿つて筒体内に静かに
挿入する(第1図)。挿入された鉄骨柱Pは支持
枠5a上のジヤツキ15により高さ、位置を調整
して、固定する。 After completing the pouring and pulling out the tremie pipe, attach the steel column P to the hanging fitting 14 at the lower end of the wire 13 of the crane.
, and gently insert it into the cylinder from above along the upper guide rail 7 and lower guide rail 8 (Fig. 1). The inserted steel column P is fixed in height and position by the jacks 15 on the support frame 5a.
鉄骨柱Pを建込み、コンクリートが固化するま
で、傾斜測定器12で鉛直度を管理し、必要に応
じてガイド筒体5の鉛直の微調整をし、コンクリ
ート固化後、縦穴Gaの上部を砂利などを埋め戻
し後に建込み架台1とガイド筒体5とを撤去す
る。 The steel column P is erected, and the verticality is controlled using the inclination measuring device 12 until the concrete hardens.The verticality of the guide cylinder 5 is finely adjusted as necessary.After the concrete hardens, the upper part of the vertical hole Ga is covered with gravel. After backfilling, etc., the built-in frame 1 and guide cylinder 5 are removed.
上記建込み装置において、ガイドレール7,8
を固定するボルトの取付孔をルーズホールにし
て、その位置を変更できるようにすれば、種々の
形状の鉄骨柱に対応できる。例えば第6図に示す
鉄骨柱Pの場合には、左右の例えば下部ガイドレ
ール8,8を図面下方に移動させることにより、
この柱を円滑に案内できる。また鉄骨柱のガイド
の構成は上例に限定されるものではなく、そして
ガイドを筒体側のみでなく、鉄骨柱側にも設けて
もよく、また鉄骨柱側にのみに設けたものであつ
てもよい。 In the above construction equipment, the guide rails 7, 8
By making the mounting hole for the bolt that fixes it a loose hole so that its position can be changed, it can be used with steel columns of various shapes. For example, in the case of the steel column P shown in FIG. 6, by moving the left and right lower guide rails 8, 8 downward in the drawing,
This pillar can be guided smoothly. Further, the structure of the guide for the steel column is not limited to the above example, and the guide may be provided not only on the cylinder side but also on the steel column side, or it may be provided only on the steel column side. Good too.
(発明の効果)
本発明の建込み方法によれば、鉄骨柱の建込み
前にコンクリートを打設し、鉄骨柱を吊持ちする
ことにより、従来のように鉄骨柱の内側等にトレ
ミー管を挿入する空間がない場合でも、建込みが
でき、鉄骨柱頭部が地表より下にある場合でも、
鉄骨柱を継ぎ足す必要はなく、柱頭部が地表より
上方に突出している場合でも、作業足場が高くな
ることはなく、コンクリート打設がしやすく、建
込み作業の能率がよくなり、精度よく建込むこと
ができる。また本発明の建込み装置によれば、鉄
骨柱を建込み装置で支持せず、芯調整されたガイ
ド筒体で鉄骨柱の鉛直度が出るため柱の建込みが
単純となり、建込み調整に手間がかからず、微調
整ができて建込み精度がよくなり、ガイドにより
迅速な建込みができる。(Effects of the Invention) According to the erection method of the present invention, by pouring concrete before erection of a steel column and suspending the steel column, tremie pipes are installed inside the steel column as in the past. Even if there is no space for insertion, it can be built and the steel column head is below ground level.
There is no need to add steel columns, and even if the column heads protrude above the ground, the work scaffolding will not be high, making it easier to pour concrete, improving the efficiency of construction work, and ensuring accurate construction. can be included. Furthermore, according to the erection device of the present invention, the steel column is not supported by the erection device, and the verticality of the steel column is determined by the core-adjusted guide cylinder, which simplifies the erection of the column and makes it easier to adjust the erection. It does not require much effort, allows for fine adjustments, improves the accuracy of erection, and allows for quick erection due to the guide.
第1図は使用状態を示す縦断面図、第2図は第
1図−線断面図、第3図は第1図−線断
面図、第4図はスタンドパイプを縦穴に設置した
状態を示す断面図、第5図は建込み装置を設置し
た状態を示す断面図、第6図はガイドレールの位
置を変更した例を示す断面図である。
1……建込み架台、5……ガイド筒体、7,8
……ガイド、9……鉛直調整手段、11,12…
…鉛直度測定手段、13,14……吊持ち手段、
Ga……縦穴、P……鉄骨柱。
Figure 1 is a vertical cross-sectional view showing the state of use, Figure 2 is a cross-sectional view taken along the line shown in Figure 1, Figure 3 is a cross-sectional view taken along the line shown in Figure 1, and Figure 4 shows the standpipe installed in the vertical hole. 5 is a sectional view showing a state in which the erection device is installed, and FIG. 6 is a sectional view showing an example in which the position of the guide rail is changed. 1... Built-in frame, 5... Guide cylinder, 7, 8
... Guide, 9 ... Vertical adjustment means, 11, 12 ...
...Verticality measuring means, 13, 14... Hanging means,
Ga... Vertical hole, P... Steel column.
Claims (1)
で支持したガイド筒体を挿入し、この筒体の内空
を利用して縦穴内に所定レベルまでコンクリート
を打設し、打設後、鉛直調整した上記ガイド筒体
内に、この筒体を案内として一端部を吊持した鉄
骨柱を挿入し、他端部側を上記コンクリートに埋
入することを特徴とする鉄骨柱の建込み方法。 2 建込み架台と、 この建込み架台に支持しかつ架台から垂設して
おり、内面に鉄骨柱を案内するガイドを設けてあ
るガイド筒体と、 このガイド筒体に設けた筒体の鉛直調整手段
と、上記ガイド筒体の鉛直度を測定する測定手段
と、 上記鉄骨柱を吊持する吊持手段と を具備する鉄骨柱の建込み装置。[Claims] 1. A vertical hole is excavated in the ground, and after the excavation, a guide cylinder supported by a frame is inserted into the vertical hole, and concrete is poured into the vertical hole to a predetermined level using the inner space of this cylinder. After installation and pouring, a steel column with one end suspended is inserted into the vertically adjusted guide cylinder using the cylinder as a guide, and the other end is embedded in the concrete. How to erect steel columns. 2. A built-in frame, a guide cylinder supported by the built-in frame and suspended from the frame, and provided with a guide for guiding the steel column on its inner surface, and a vertical axis of the cylinder provided on this guide cylinder. A steel column erection device comprising: an adjusting means, a measuring means for measuring the verticality of the guide cylinder, and a suspending means for suspending the steel column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27076085A JPS62133255A (en) | 1985-12-03 | 1985-12-03 | Method and apparatus for building steel bar pillar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP27076085A JPS62133255A (en) | 1985-12-03 | 1985-12-03 | Method and apparatus for building steel bar pillar |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS62133255A JPS62133255A (en) | 1987-06-16 |
JPH0531631B2 true JPH0531631B2 (en) | 1993-05-13 |
Family
ID=17490605
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP27076085A Granted JPS62133255A (en) | 1985-12-03 | 1985-12-03 | Method and apparatus for building steel bar pillar |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS62133255A (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05112936A (en) * | 1991-10-24 | 1993-05-07 | Toukan Kiso Kogyo Kk | Structural center column centering template |
JP3750042B2 (en) * | 1998-06-15 | 2006-03-01 | 清水建設株式会社 | Construction pillar erection device |
JP3914821B2 (en) * | 2002-05-30 | 2007-05-16 | 株式会社奥村組 | Rebar position adjustment jig |
JP7275793B2 (en) * | 2019-04-12 | 2023-05-18 | 株式会社大林組 | Position adjusting device and method for adjusting position of structural column |
JP7277743B2 (en) * | 2019-07-05 | 2023-05-19 | ジャパンパイル株式会社 | Prefabricated pile holding device and foundation pile construction method |
-
1985
- 1985-12-03 JP JP27076085A patent/JPS62133255A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS62133255A (en) | 1987-06-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2005090116A (en) | Method for erecting steel frame column and positioning frame body used for it | |
CN106759943A (en) | A kind of pre-assembled Anchor Bolts in Steel Column Bases structure | |
JPH0531631B2 (en) | ||
JPH08120673A (en) | Accurate erection method and equipment for steel frame column under ground surface of reverse construction method | |
JP2747566B2 (en) | Construction method of straight pillar | |
JPH09203041A (en) | Structural center column erection method and guide pipe used therefor | |
JPH0849235A (en) | Inclination adjusting device in construction method for building up permanent substractural column | |
JP2556215B2 (en) | Construction method | |
JP3750042B2 (en) | Construction pillar erection device | |
JPH07122273B2 (en) | Structure pillar built-in stand | |
JP2567631Y2 (en) | Level adjuster for steel foundation beams | |
JP2556216B2 (en) | Construction pillar installation jig | |
JPH10317391A (en) | Foundation structure for steel tower and method for constructing the same | |
JP3731975B2 (en) | Method and apparatus for positioning a steel pipe column when installing a plug-in type steel pipe column | |
JP3030374B2 (en) | Construction method and equipment for trussed pillar | |
JPH1161812A (en) | Plumbing device of steel column | |
JPH08209718A (en) | Erection and adjustment device for structural center column | |
CN215053235U (en) | Lattice column mounting device for reverse construction method | |
CN215053064U (en) | Lattice column verticality correction device | |
CN217150251U (en) | Digital verticality adjusting system for reverse steel stand column | |
JPH04281916A (en) | Base device for construction of main post | |
CN2342021Y (en) | Steel pillar lifting and placing device for foundation piles | |
CN115977141A (en) | Construction method suitable for connecting top middle plate of reverse construction structure with enclosure structure | |
JPH08284180A (en) | Embedment work method for foundation bolt | |
JPH0649976B2 (en) | How to build a true pillar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
EXPY | Cancellation because of completion of term |