CN107513997A - The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis - Google Patents

The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis Download PDF

Info

Publication number
CN107513997A
CN107513997A CN201710661078.1A CN201710661078A CN107513997A CN 107513997 A CN107513997 A CN 107513997A CN 201710661078 A CN201710661078 A CN 201710661078A CN 107513997 A CN107513997 A CN 107513997A
Authority
CN
China
Prior art keywords
steel pipe
laser
perpendicularity
reading
imaginary axis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710661078.1A
Other languages
Chinese (zh)
Inventor
马跃强
刘龙
成炜
施春锋
施贵宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN201710661078.1A priority Critical patent/CN107513997A/en
Publication of CN107513997A publication Critical patent/CN107513997A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds

Abstract

The invention provides a kind of construction method that steel pipe perpendicularity is quickly adjusted using imaginary axis, laser inclinometer and light target is arranged on outer wall of steel pipe, steel pipe positions when being in horizontality to laser rays;Then it is in steel pipe under horizontality and laser inclinometer stable reading state, it is assumed that steel pipe home position has the imaginary axis of an absolute upright, and laser inclinometer reading is reset to the perpendicularity for making its reading represent imaginary axis;After steel pipe hangs in drilling, the reading according to laser inclinometer carries out steel pipe perpendicularity adjustment.The construction method laser inclinometer and light target are easy for installation, level, which loads laser rays accuracy of alignment, does not influence the final perpendicularity of steel pipe, solve the problems, such as that the deflection deformation caused by steel pipe is horizontal positioned and laser rays accuracy of alignment deficiency cause measurement accumulated error, in addition, the reading of laser inclinometer is demarcated as to the perpendicularity of imaginary axis, the difficulty of steel pipe perpendicularity adjustment is reduced, difficulty of construction can be substantially reduced, improves efficiency of construction.

Description

The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis
Technical field
The present invention relates to a kind of construction method that steel pipe perpendicularity is quickly adjusted using imaginary axis, belong to building construction technology Field.
Background technology
In reverse construction, vertical applied force structure is frequently with one pile for one column form, the i.e. concrete-pile by bottom and position Steel column in concrete-pile top is formed, after underground structure completion, knot of the steel column external wrapping concrete as basement Structure post.The degree control of steel pipe is the key of construction technology, and structure vertical support system bearing capacity and Stability Analysis of Structures The important leverage of property.Therefore, it is necessary to strictly control positioning and the perpendicularity of steel column, the additional curved of steel column otherwise can be increased Square, so as to cause the unstable failure under design section, this requires that steel column perpendicularity reaches 1/600 even more high.
General vertical adjustment method is to set laser inclinometer respectively at steel pipe head end and tail end center in Practical Project And light target, during by laser rays directive light target cross searching, laser rays measures axle as steel pipe centre of form axle, then with measuring instrument Reading is according to progress steel pipe perpendicularity adjustment.Certain amount of deflection, lifting steel pipes and lower section under horizontality be present to brill in steel pipe Carried out in hole under vertical state, make to measure axle under steel pipe vertical state and centre of form axle has therebetween deviation, influence The perpendicularity of steel pipe.Moreover, needing to adjust steel column centre of form axle repeatedly in work progress, there is systematic error synergistic effect The problems such as subjective uncertain factor significantly and in manual operation increases accidental error, efficiency is very low.
The content of the invention
In being constructed for one pile for one column, laser inclinometer Laser Measuring dead axle and steel existing for existing adjusting verticality of steel column method Tubular mandrel exists and needs to adjust centre of form axle in deviation, construction repeatedly, systematic error superposition be present, by man's activity is big, efficiency Low problem, the invention provides a kind of construction method that steel pipe perpendicularity is quickly adjusted using imaginary axis, by laser inclinometer It is arranged on light target on outer wall of steel pipe, steel pipe positions when being in horizontality to laser rays;Then it is in level in steel pipe Under state and laser inclinometer stable reading state, it is assumed that home position has the void of absolute upright to steel pipe in this case Intend axle, laser inclinometer reading is reset to the perpendicularity for making its reading represent imaginary axis;After steel pipe hangs in drilling, according to laser The reading of inclinometer carries out steel pipe perpendicularity adjustment.The construction method laser inclinometer and light target are easy for installation, and level loads sharp Light accuracy of alignment does not influence the final perpendicularity of steel pipe, solves deflection deformation and laser rays pair caused by steel pipe is horizontal positioned Middle precision deficiency causes the problem of measurement accumulated error, in addition, the reading of laser inclinometer is demarcated as to the perpendicularity of imaginary axis, The difficulty of steel pipe perpendicularity adjustment is reduced, difficulty of construction can be substantially reduced, improves efficiency of construction.
To solve above technical problem, the present invention includes following technical scheme:
A kind of construction method that steel pipe perpendicularity is quickly adjusted using imaginary axis, is comprised the following steps:
S1. steel pipe is horizontal positioned, the fixed laser inclinometer on the outer wall of the head end of the steel pipe, and in the steel pipe Light target is fixed on tail end outer wall, adjusts the pedestal of the laser inclinometer, makes the laser transmitter projects of the laser inclinometer Laser rays be radiated at the light target center, then remove the light target;
S2. the steel pipe is sling vertically with loop wheel machine, treats that the steel pipe is suspended under gravity and laser inclinometer is read Assume that steel pipe center has the imaginary axis of an absolute upright after number keeps stable more than 1min, under this state, by the laser The reading of inclinometer returns 0, and now the laser inclinometer reading represents the perpendicularity of the imaginary axis;
S3. the steel pipe is hung in drilling, and hydraulic pressure vertical adjustment disk is installed on the ground at the top of the drilling, and it is described To be rigidly connected between the calibrated mount and the steel pipe of hydraulic pressure vertical adjustment disk, vertical thousand be arranged on the hydraulic pressure vertical adjustment disk are utilized Jin top and level jack adjust the steel pipe head end, the reading of the laser inclinometer is leveled off to 0;
S4., concrete discharging pipe and casting concrete are set in the steel pipe, after concrete reaches design strength, torn open Except the laser inclinometer and the hydraulic pressure vertical adjustment disk.
Preferably, in step S1, the fixed form of the laser inclinometer is to be welded on the outer wall of the steel pipe head end Substrate one, bolt hole being provided with the substrate one, L-type connecting plate one being fixed with bolt on the substrate one, the L-type connects Laser hole is provided with fishplate bar one, the laser inclinometer is fixed on the L-type connecting plate one by pedestal, the laser hair Laser hole described in emitter face.
Preferably, in step S1, the fixed form of the light target is the welding substrate on the outer wall of the steel pipe tail end Two, bolt hole is provided with the substrate two, and L-type connecting plate two, the L-type connecting plate are fixed with bolt on the substrate two The light target is fixed on two, the vertical range of cross searching to the outer wall of steel pipe of the light target is equal to the laser hole to institute State the vertical range of outer wall of steel pipe.
Preferably, the steel pipe head end outer wall both sides are symmetrically arranged with hanger, and in step S2, the lifting rope of loop wheel machine, which is suspended on, to be hung On ear.
Preferably, in step S3, the soil body first below the hydraulic pressure vertical adjustment disk carries out reinforcing and forms back-up coat, and sets Put pre-buried iron plate.
Preferably, the hydraulic pressure vertical adjustment disk includes locating rack and calibrated mount, and the locating rack is fixed on the back-up coat The pre-buried iron plate on, the calibrated mount is supported in the pre-buried iron plate on the back-up coat by four vertical jack On, the calibrated mount is fixed on the locating rack by four level jacks in the horizontal direction, among the calibrated mount There is through hole, the steel pipe is fixed in the through hole.
Preferably, the laser inclinometer reading is X-Y axle readings, is provided between the locating rack and the calibrated mount 4 level jacks, one pair of which are located at X-direction, and another pair is located at Y direction, in step S3, pass through regulation first A pair of level jacks of X-direction make X-axis reading become zero, and the level for then adjusting another pair Y direction is very heavy Top makes Y-axis reading become zero.
Preferably, in step S4, during pouring the concrete, the reading of the laser inclinometer is monitored all the time, Reading is kept to become zero..
The present invention is allowed to compared with prior art, have the following advantages that and actively imitate due to using above technical scheme Fruit:
(1) laser inclinometer and light target are arranged on outer wall of steel pipe, light target has versatility, and light target fixation is not managed The influence of wall machining accuracy, while laser inclinometer nor affects on construction operation in steel pipe;
(2) light target is only used for substantially adjusting the direction of laser inclinometer, and therefore, laser rays only needs substantially to put down with the steel pipe centre of form Row, greatly reduce the difficulty of laser rays centering;
(3) after loop wheel machine suspends steel pipe in midair, more than 1 minute indeclinable situation is kept in laser inclinometer reading, it is assumed that this During state there is the imaginary axis of an absolute upright in steel pipe center, and laser inclinometer reading is zeroed, later laser inclinometer Reading can represent the gradient of the imaginary axis, ensure that laser inclinometer reading more levels off to zero, and imaginary axis gets over convergence absolute upright, Steel pipe perpendicularity is higher;
(4) laser inclinometer reading includes X-Y axle readings, by the level jack of hydraulic pressure vertical adjustment disk be arranged to X-direction, Each two of Y direction, X-axis, Y-axis reading can be adjusted respectively, simplify perpendicularity adjustment difficulty.
Brief description of the drawings
Fig. 1 is the flow for the construction method that steel pipe perpendicularity is quickly adjusted using imaginary axis that one embodiment of the invention provides Block diagram;
Fig. 2 is the schematic diagram of the penstock installation laser inclinometer that one embodiment of the invention provides and light target;
Fig. 3 is the light target structural representation that one embodiment of the invention provides;
Fig. 4 is the schematic diagram that the loop wheel machine that one embodiment of the invention provides slings steel pipe vertically;
Fig. 5 is the hydraulic pressure vertical adjustment dish structure schematic diagram that one embodiment of the invention provides;
Fig. 6 is the top view of the hydraulic pressure vertical adjustment disk in Fig. 5;
Fig. 7 is the schematic diagram for pouring pile foundation concrete that one embodiment of the invention provides.
Label is as follows in figure:
Steel pipe 100;Imaginary axis 101;Hanger 102;Head end 110;Tail end 120;Laser inclinometer 200;Laser rays 201;Base Plate 1;L-type connecting plate 1;Laser hole 221;Substrate 2 230;L-type connecting plate 2 240;Light target 250;Cross searching 251;Loop wheel machine 310;Casing 320;Back-up coat 330;Concrete discharging pipe 340;Hydraulic pressure vertical adjustment disk 400;Locating rack 410;Calibrated mount 420;Vertical jack 430;Level jack 440.
Embodiment
Steel pipe perpendicularity is quickly adjusted using imaginary axis to provided by the invention below in conjunction with the drawings and specific embodiments Construction method is described in further detail.With reference to following explanation and claims, advantages and features of the invention will become apparent from. It should be noted that accompanying drawing uses using very simplified form and non-accurately ratio, only to convenience, lucidly aid in Illustrate the purpose of the embodiment of the present invention.
Referring to Fig. 1, Fig. 1 is the FB(flow block) of the present embodiment, Fig. 2-7 is work progress figure.Below in conjunction with Fig. 1 to figure 7 pairs of main points of the invention are described further.
The construction method of the perpendicularity of steel pipe 100 is quickly adjusted using imaginary axis 101, is comprised the following steps:
S1. as shown in Fig. 2 steel pipe 100 is horizontal positioned, the fixed laser inclinometer on the outer wall of the head end 110 of steel pipe 100 200, and light target 250 is fixed on the outer wall of tail end 120 of steel pipe 100, the pedestal of adjustment laser inclinometer 200, make laser deviational survey The laser rays 201 of the laser transmitter projects of instrument 200 is radiated at the center of light target 250, then removes light target 250.
Wherein, the fixed form of laser inclinometer 200 is the welding substrate 1 on the outer wall of the head end 110 of steel pipe 100, Bolt hole is provided with substrate 1, L-type connecting plate 1, L-type connecting plate 1 are fixed with bolt on substrate 1 On be provided with laser hole 221, laser inclinometer 200 is fixed on L-type connecting plate 1, generating laser face laser hole 221。
Wherein, the fixed form of light target 250 is the welding substrate 2 230 on the outer wall of the tail end 120 of steel pipe 100, substrate two Bolt hole is provided with 230, L-type connecting plate 2 240 is fixed with bolt on substrate 2 230, is fixed on L-type connecting plate 2 240 Light target 250, the vertical range of the cross searching 251 of light target 250 to the outer wall of steel pipe 100 are equal to laser hole 221 to the outer wall of steel pipe 100 Vertical range.Ensureing simultaneously, laser hole 221 is substantially parallel with the centre of form axle of steel pipe 100 with the line of the cross searching 251 of light target 250, So generally laser rays is only needed to be radiated at light target 250, because of the foundation that laser rays 201 works not as later stage vertical adjustment, therefore not Construction in later period precision is influenceed, this greatly reduces the difficulty of the centering of laser rays 201.
In the present embodiment, light target 250 is act as:Make the laser rays 201 of laser inclinometer 200 substantially with steel pipe 100 It is parallel, prevent that angle is excessive between laser inclinometer 200 and steel pipe 100, influences measurement accuracy.Therefore, it is in water in steel pipe 100 During level state, ensure that laser rays 201 is in the immediate vicinity of light target 250 and can meet to require, then dismountable light target 250.
Traditional laser inclinometer 200 and the mounting means of light target 250 are to distinguish laser inclinometer 200 and light target 250 On the central axis of the head end 110 of steel pipe 100 and tail end 120, have as a drawback that:(1) light target 250 may be only available for spy The steel pipe 100 of fixed-caliber, compatibility is poor;And light target 250 by steel pipe 100 process and the mouth of pipe at cutting accuracy influenceed, because processing The shortcomings that scale error often leads to be difficult to be nested into the mouth of pipe or fix loosely;(2) laser inclinometer 200 is located in steel pipe 100 At the heart, grouting, plasma discharge, concreting operation in steel pipe 100 are influenceed.
In the present embodiment, laser inclinometer 200 and light target 250 are arranged on the outer wall of steel pipe 100, had the following advantages that: (1) light target 250 has a versatility, and light target 250 is installed and do not influenceed by tube wall machining accuracy;(2) laser inclinometer 200 is not yet Influence construction operation in steel pipe 100.In addition, in the present embodiment, light target 250 is only used for substantially adjusting the side of laser inclinometer 200 To therefore, laser rays 201 only needs substantially parallel with the centre of form of steel pipe 100, greatly reduces the difficulty of the centering of laser rays 201.
S2. as shown in figure 3, being sling steel pipe 100 vertically with loop wheel machine 310, treat steel pipe 100 under gravity in vertical Assume that the center of steel pipe 100 has an eradication pair after state and the reading of laser inclinometer 200 keep stable more than 1min, under this state Vertical imaginary axis 101, the reading of laser inclinometer 200 is zeroed, now the reading of laser inclinometer 200 represents imaginary axis 101 Perpendicularity.
Wherein, both sides are symmetrically arranged with a pair of hangers 102, the lifting rope suspension of loop wheel machine 310 on the outer wall of 100 head end of steel pipe 110 On hanger 102.Steel pipe 100 is in vertical state, and the reading of laser inclinometer 200 is kept after stablizing more than 1min, now steel pipe 100 it is believed that in the steel pipe 100 by the absolute upright state of horizontal force, not represented with imaginary axis 101 under this state Absolute upright axle, after the reading of laser inclinometer 200 is reset, then the reading of laser inclinometer 200 can represent hanging down for imaginary axis 101 Straight degree.
S3. steel pipe 100 is hung in drilling, and hydraulic pressure vertical adjustment disk 400 is installed on the ground at the top of drilling, and hydraulic pressure is adjusted It is vertical very heavy on hydraulic pressure vertical adjustment disk 400 using being arranged to be rigidly connected between the calibrated mount 420 and steel pipe 100 of vertical disk 400 Top 430 and level jack 440 adjust the head end 110 of steel pipe 100, the reading of laser inclinometer 200 is leveled off to 0.Generally, drill Upper end is provided with casing 320, and steel pipe 100 is inserted in casing 320 by hydraulic pressure vertical adjustment disk 400.
The reading of wherein laser inclinometer 200 levels off to 0, refers to its reading closer to 0, perpendicularity precision is higher, reads Number needs to meet [0, m], wherein, the laser inclinometer 200 corresponding to maximum deflection difference value that m is allowed by the perpendicularity of steel pipe 100 Reading.
Steel pipe 100 insertion drilling in, perpendicularity can slightly deviation, it is necessary to be adjusted to the perpendicularity of steel pipe 100.Adjustment The perpendicularity of steel pipe 100, hydraulic pressure vertical adjustment disk 400 can be used.First, by near hydraulic pressure vertical adjustment disk 400 to be installed around drilling The soil body is reinforced, and forms back-up coat 330, and pre-buried iron plate is set in back-up coat 330, then installs hydraulic pressure vertical adjustment disk 400.
Wherein, hydraulic pressure vertical adjustment disk 400 includes locating rack 410 and calibrated mount 420, and locating rack 410 is rigidly connected in back-up coat On pre-buried iron plate on 330, calibrated mount 420 is supported in the pre-buried iron plate on back-up coat 330 by four vertical jack 430 On, calibrated mount 420 is fixed on locating rack 410 by four level jacks 440 in the horizontal direction, among calibrated mount 420 There is through hole, steel pipe 100 is fixed in through-holes.Wherein vertical jack 430 can make calibrated mount 420 be in horizontal tilt degree, horizontal Jack 440 can adjust the horizontal displacement of calibrated mount 420, adjust the position of the head end 110 of steel pipe 100 within the specific limits, so as to Adjust the perpendicularity of steel pipe 100.
Wherein, the reading of laser inclinometer 200 is X-Y axle readings, and 4 water are provided between locating rack 410 and calibrated mount 420 Flat jack 440, one pair of which are located at X-direction, and another pair is located at Y direction, in step S3, first by adjusting a pair of water Flat jack 440 makes X-axis reading be zeroed, and then adjusting another pair level jack 440 makes Y-axis reading be zeroed.
S4., concrete discharging pipe 340 and casting concrete are set in steel pipe 100, after concrete reaches design strength, Remove laser inclinometer 200 and hydraulic pressure vertical adjustment disk 400.
Wherein, during casting concrete, the reading of laser inclinometer 200 is monitored all the time, keeps reading to level off to zero.
In summary, the construction method provided by the invention for quickly adjusting the perpendicularity of steel pipe 100 using imaginary axis 101 has Following advantage:(1) laser inclinometer 200 and light target 250 being arranged on the outer wall of steel pipe 100, light target 250 has versatility, and Light target 250 is fixed not to be influenceed by tube wall machining accuracy, while laser inclinometer 200 nor affects on construction operation in steel pipe 100; (2) light target 250 is only used for substantially adjusting the direction of laser inclinometer 200, therefore, laser rays 201 only need substantially with the shape of steel pipe 100 The heart is parallel, greatly reduces the difficulty of the centering of laser rays 201;(3) after loop wheel machine 310 suspends steel pipe 100 in midair, in laser deviational survey The reading of instrument 200 keeps more than 1 minute indeclinable situation, it is assumed that the center of steel pipe 100 is in the presence of absolute upright during this state Imaginary axis 101, and the reading of laser inclinometer 200 is zeroed, the later reading of laser inclinometer 200 can represent the imaginary axis 101 Gradient, ensure that the reading of laser inclinometer 200 more levels off to zero, imaginary axis 101 gets over convergence absolute upright, the perpendicularity of steel pipe 100 It is higher;(4) reading of laser inclinometer 200 includes X-Y axle readings, and the level jack 440 of hydraulic pressure vertical adjustment disk 400 is arranged into X Each two of direction of principal axis, Y direction, can adjust X-axis respectively, Y-axis reading becomes zero, simplify perpendicularity adjustment work difficulty.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Scope.

Claims (8)

1. a kind of construction method that steel pipe perpendicularity is quickly adjusted using imaginary axis, it is characterised in that comprise the following steps:
S1. steel pipe is horizontal positioned, the fixed laser inclinometer on the outer wall of the head end of the steel pipe, and in the tail end of the steel pipe Light target is fixed on outer wall, adjusts the pedestal of the laser inclinometer, make the laser inclinometer laser transmitter projects swash Light is radiated at the light target center, then removes the light target;
S2. the steel pipe is sling vertically with loop wheel machine, treats that the steel pipe is suspended under gravity and laser inclinometer reading is protected Keep steady after determining more than 1min, assume that steel pipe center has the imaginary axis of an absolute upright under this state, by the laser deviational survey The reading of instrument returns 0, and now the laser inclinometer reading represents the perpendicularity of the imaginary axis;
S3. the steel pipe is hung in drilling, and hydraulic pressure vertical adjustment disk is installed on the ground at the top of the drilling, and the hydraulic pressure To be rigidly connected between the calibrated mount of vertical adjustment disk and the steel pipe, the vertical jack being arranged on the hydraulic pressure vertical adjustment disk is utilized The steel pipe head end is adjusted with level jack, the reading of the laser inclinometer is leveled off to 0;
S4., concrete discharging pipe and casting concrete are set in the steel pipe, after concrete reaches design strength, remove institute State laser inclinometer and the hydraulic pressure vertical adjustment disk.
2. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 1, it is characterised in that step In S1, the fixed form of the laser inclinometer is the welding substrate one on the outer wall of the steel pipe head end, on the substrate one Bolt hole is provided with, L-type connecting plate one is fixed with bolt on the substrate one, laser is provided with the L-type connecting plate one Hole, the laser inclinometer are fixed on the L-type connecting plate one by pedestal, laser described in the generating laser face Hole.
3. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 2, it is characterised in that step In S1, the fixed form of the light target is the welding substrate two on the outer wall of the steel pipe tail end, is provided with the substrate two Bolt hole, L-type connecting plate two is fixed with bolt on the substrate two, the light target is fixed on the L-type connecting plate two, it is described The vertical range of the cross searching of light target to the outer wall of steel pipe is equal to the laser hole to the vertical range of the outer wall of steel pipe.
4. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 1, it is characterised in that described Steel pipe head end outer wall both sides are symmetrically arranged with hanger, and in step S2, the lifting rope of loop wheel machine is suspended on hanger.
5. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 1, it is characterised in that step In S3, the soil body first below the hydraulic pressure vertical adjustment disk carries out reinforcing and forms back-up coat, and sets pre-buried iron plate.
6. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 5, it is characterised in that described Hydraulic pressure vertical adjustment disk includes locating rack and calibrated mount, and the locating rack is fixed on the pre-buried iron plate on the back-up coat, institute State calibrated mount to be supported on the pre-buried iron plate on the back-up coat by four vertical jack, the calibrated mount is in level Side is fixed on the locating rack upwardly through four level jacks, has through hole among the calibrated mount, the steel pipe is fixed In the through hole.
7. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 1, it is characterised in that described Laser inclinometer reading is X-Y axle readings, and 4 level jacks are provided between the locating rack and the calibrated mount, One pair of which is located at X-direction, and another pair is located at Y direction, in step S3, first by adjusting described in a pair of X-direction Level jack makes X-axis reading become zero, and then adjusting the level jack of another pair Y direction makes Y-axis reading become zero.
8. the construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis as claimed in claim 1, it is characterised in that step In S4, during pouring the concrete, the reading of the laser inclinometer is monitored all the time, keep reading to become zero.
CN201710661078.1A 2017-08-04 2017-08-04 The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis Pending CN107513997A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710661078.1A CN107513997A (en) 2017-08-04 2017-08-04 The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710661078.1A CN107513997A (en) 2017-08-04 2017-08-04 The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis

Publications (1)

Publication Number Publication Date
CN107513997A true CN107513997A (en) 2017-12-26

Family

ID=60722883

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710661078.1A Pending CN107513997A (en) 2017-08-04 2017-08-04 The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis

Country Status (1)

Country Link
CN (1) CN107513997A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110219326A (en) * 2019-05-23 2019-09-10 海天建设集团有限公司 The underwater vertical adjustment construction technology of inverse method one-column one-pile
CN110593258A (en) * 2019-10-15 2019-12-20 广东省建筑工程集团有限公司 Existing building pile foundation steel sleeve pile reinforcing construction method and reinforcing structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011117803A (en) * 2009-12-02 2011-06-16 Ohbayashi Corp Method for measuring build-in error of steel pipe, and steel pipe
CN104499485A (en) * 2014-12-08 2015-04-08 上海建工集团股份有限公司 One-column one-pile full-automatic hydraulic verticality adjusting system and method
CN206279566U (en) * 2016-11-16 2017-06-27 上海建工二建集团有限公司 Inverse method one-column one-pile duplex displaced type overall process measuring system
CN106958244A (en) * 2017-04-27 2017-07-18 中铁隧道集团四处有限公司 The installation and locating method of ultra-deep and large diameter steel pipe column

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011117803A (en) * 2009-12-02 2011-06-16 Ohbayashi Corp Method for measuring build-in error of steel pipe, and steel pipe
CN104499485A (en) * 2014-12-08 2015-04-08 上海建工集团股份有限公司 One-column one-pile full-automatic hydraulic verticality adjusting system and method
CN206279566U (en) * 2016-11-16 2017-06-27 上海建工二建集团有限公司 Inverse method one-column one-pile duplex displaced type overall process measuring system
CN106958244A (en) * 2017-04-27 2017-07-18 中铁隧道集团四处有限公司 The installation and locating method of ultra-deep and large diameter steel pipe column

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110219326A (en) * 2019-05-23 2019-09-10 海天建设集团有限公司 The underwater vertical adjustment construction technology of inverse method one-column one-pile
CN110593258A (en) * 2019-10-15 2019-12-20 广东省建筑工程集团有限公司 Existing building pile foundation steel sleeve pile reinforcing construction method and reinforcing structure
CN110593258B (en) * 2019-10-15 2023-09-15 广东省建筑工程集团有限公司 Reinforcing construction method and reinforcing structure for steel sleeve pile of existing building pile foundation

Similar Documents

Publication Publication Date Title
CN205296874U (en) Information -based construction monitor positioning device of stake integration
CN113605390B (en) Accurate positioning structure for pile connection and construction method
CN104264902B (en) Structure for connecting concrete filled steel tubular column with pile foundation
CN206110202U (en) Pile foundation static load detection device
WO2020133972A1 (en) High-precision automatic positioning and verticality adjustment system for ultra-long steel column by reverse construction method and construction method
CN111254920B (en) Reverse-operation-process concrete-filled steel tube column installation construction method and reverse-operation-process concrete-filled steel tube column construction structure
CN114541652B (en) Construction method of V-shaped steel column
CN106958244B (en) The installation and locating method of ultra-deep and large diameter steel pipe column
CN111962505A (en) Double-pile-casing positioning structure of collimation pile, double-pile-casing device, collimation pile and construction method
CN107513997A (en) The construction method of steel pipe perpendicularity is quickly adjusted using imaginary axis
CN113280721A (en) Pile core positioning device and pile core positioning method
CN113638417A (en) Pile connection accurate positioning pouring system and construction method
CN112663613A (en) Verticality control device and verticality control method for latticed column
CN111719607A (en) Method and device for accurately positioning and adjusting verticality of steel pipe column
CN215105558U (en) Pile core positioning device
CN109972847A (en) A kind of positioning of structural column, plumbing device
CN208280128U (en) Operating platform for cast-in-situ bored pile more piece steel reinforcement cage straight thread abutting joint
CN217078739U (en) Self-adaptive balanced placing platform structure for underground continuous wall reinforcement cage
CN216920302U (en) Pre-buried steel column transfers system of hanging down
CN213267538U (en) Leading hole platform for U-shaped sandstone riverbed steel trestle on shoal
CN209368828U (en) Reverse construction erection of steel pipe column control device
CN115030137B (en) Underground diaphragm wall reinforcement cage positioning and adjusting device and construction method thereof
JP2556215B2 (en) Construction method
CN217053055U (en) Positioning tool for head section steel pipe of cable tower
CN218970017U (en) Flexible connection device for reverse construction steel pipe column and reinforcement cage

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171226

WD01 Invention patent application deemed withdrawn after publication