JPH055312A - Setting of structural center column - Google Patents

Setting of structural center column

Info

Publication number
JPH055312A
JPH055312A JP3158282A JP15828291A JPH055312A JP H055312 A JPH055312 A JP H055312A JP 3158282 A JP3158282 A JP 3158282A JP 15828291 A JP15828291 A JP 15828291A JP H055312 A JPH055312 A JP H055312A
Authority
JP
Japan
Prior art keywords
true
column
pillar
jig
guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3158282A
Other languages
Japanese (ja)
Other versions
JP2556215B2 (en
Inventor
Tomoyoshi Yamamoto
知由 山本
Takahide Mizoguchi
隆英 溝口
Keiji Himi
恵二 氷見
Akiomi Konishi
昭臣 小西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP3158282A priority Critical patent/JP2556215B2/en
Publication of JPH055312A publication Critical patent/JPH055312A/en
Application granted granted Critical
Publication of JP2556215B2 publication Critical patent/JP2556215B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Foundations (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To set a structural center column to be provided on a pile constructed at job-site with high accuracy in a short time prior to the excavation of underground stair. CONSTITUTION:A setting base 10 having a guide 11 on its center is set on the ground's surface above a pile 50 constructed at the job site, and the horizon of the base 10 is adjusted by a level-regulating jack 20. Even for the guide 11, two directions crossing within the horizon and distortion are finely adjusted. A setting tool 30 is connected to the upside of a structural center column 1 by high-strength bolts, and the hanger tool on the upper end of the tool 30 is hung down through roller shackles to hang it up by the gravity center of the column 1. It is inserted into the guide 11 of the base 10 from the lower end of the column 1, and the guide rail 33 is vertically guided by the guide 11 of the base 10 and set in the concrete above the pile 50.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は建物の地下工事をいわゆ
る逆打工法で行う場合において、建物地下階部分の掘削
に先立ち現場築造杭上に建込まれる構真柱の建込方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of erection of a construction pillar to be erected on a site construction pile before excavation of a basement floor of a building when the underground construction of the building is carried out by a so-called reverse driving method. is there.

【0002】[0002]

【従来の技術】いわゆる逆打工法においては、通常、地
上1階の床・梁コンクリート打設後、地下掘削を行い、
地下1階の床・梁コンクリートを打設し、順次地下2
階、地下3階の順で地下掘削、床・梁工事を行う。その
ため、掘削時に上階の床・梁荷重を受けるための構真柱
と称する鉄骨柱を設ける。
2. Description of the Related Art In the so-called reverse driving method, usually, after placing the floor and beam concrete on the first floor above ground, excavating underground,
The floor and beam concrete on the 1st basement floor were placed, and the basement 2
Underground excavation and floor / beam construction will be performed in the order of the first floor and the third basement. Therefore, a steel frame column called a structural column will be installed to receive the floor and beam loads on the upper floor during excavation.

【0003】この場合、構真柱の建込精度は非常に重要
である。すなわち、構真柱は上階の荷重(1階、地下1
階、地下2階、……、及び地上鉄骨工事等が開始される
と、鉄骨重量、床コンクリート重量等)を受けるため、
図25に示すように傾斜すると予想外の曲げモーメント
が加わり、危険となる。また、図26に示すように鉄骨
鉄筋コンクリート柱を構成する構真柱が傾斜すると、柱
型内に納まらなくなるか、または柱の鉄筋が納まらなく
なり、図26(c) のように構真柱が鉄筋に当たったり、
図26(d) のように柱型から出てしまうことになる。
In this case, the installation accuracy of the true column is very important. In other words, the true pillar is the load on the upper floor (1st floor, 1 underground)
Floors, 2nd basement floors, etc., and when steel structures above ground are started, the weight of steel frames, floor concrete, etc.) will be received.
If it is inclined as shown in FIG. 25, an unexpected bending moment is applied, which is dangerous. Also, as shown in FIG. 26, when the true-columns that make up the steel-reinforced concrete columns are inclined, they do not fit inside the column mold or the rebars of the columns do not fit, and the true-columns are reinforced as shown in FIG. 26 (c). Hit
As shown in FIG. 26 (d), it comes out of the pillar shape.

【0004】従来の構真柱の建込方法としては、構真柱
頂部の位置確保のため、現場築造杭の施工に用いた杭掘
削架台上にH形鋼を井桁に組み、トランシットで芯墨を
出し、その墨を基準に構真柱をセットするのが一般的で
ある。
As a conventional method of erection of the true structure pillar, in order to secure the position of the top portion of the true structure pillar, H-section steel is assembled on the pile excavation base used for construction of the on-site built pile in the cross girder, and the core ink is made with the transit. It is common to set the true pillar based on the ink.

【0005】また、構真柱の傾斜に対しては杭掘削時の
ケーシングに反力をとり、できるだけ下部にジャッキを
設けて構真柱を横方向に押して移動させている。
Further, with respect to the inclination of the true column, a reaction force is applied to the casing during pile excavation, and a jack is provided as low as possible to push the true column laterally to move it.

【0006】[0006]

【発明が解決しようとする課題】しかし、上述した建込
方法ではH形鋼の井桁の中に構真柱を挿入する際、クリ
アランスがあり、かつ挿入時に構真柱がH形鋼とせるた
めに誤差が出る。
However, in the above-mentioned erection method, there is a clearance when the structural column is inserted into the H-shaped steel well girder, and the structural column can be made into the H-shaped steel at the time of insertion. There is an error in.

【0007】また、井桁のH形鋼を基準となるX,Y方
向に直角または平行とする作業が煩雑であり、このこと
により構真柱にねじれが生じる。
Further, the work of setting the H-shaped steel of the cross girder at right angles or parallel to the X and Y directions, which is the reference, is complicated, and this causes twisting of the true column.

【0008】さらに、従来は構真柱の施工にも杭掘削架
台をそのまま使用しているため、構真柱の建込みを完了
した後、コンクリートが硬化するまで杭掘削架台を外す
ことができず、転用の効率が悪い。
Furthermore, since the pile excavation base is used as it is for the construction of the construction pillar, the pile excavation base cannot be removed until the concrete is hardened after the construction of the construction pillar is completed. , Conversion efficiency is poor.

【0009】傾斜の修正に関しては、ケーシング長が短
い場合、傾斜を完全に修正することは困難である。ま
た、杭掘削に用いられる孔壁安定のための泥水中で構真
柱の傾斜を確認することが困難である。
Regarding the correction of the inclination, it is difficult to completely correct the inclination when the casing length is short. Moreover, it is difficult to confirm the inclination of the true column in the muddy water for stabilizing the hole wall used for pile excavation.

【0010】本発明は従来技術における上述のような問
題点の解消を図ったものである。
The present invention is intended to solve the above-mentioned problems in the prior art.

【0011】[0011]

【課題を解決するための手段】本発明の構真柱建込方法
は以下の工程を有するものである。なお、これらの工程
は一部並行作業となったり、作業手順を入れ換えること
もあり得る。
The method of constructing a true column according to the present invention has the following steps. It should be noted that some of these steps may be performed in parallel or the work procedure may be changed.

【0012】(a) 構真柱を垂直方向に案内するための
ガイド部を形成した構真柱建込架台を構真柱建込位置上
に設置する工程。 (b) 前記構真柱建込架台のガイド部の位置を調整する
工程。 (c) 構真柱を重心で吊り上げるための構真柱建込治具
を前記構真柱の上端に取付ける工程。 (d) 構真柱を前記構真柱建込治具を介して揚重装置で
垂直に吊り上げ、下端先端部から前記構真柱建込架台の
前記ガイド部に挿入する工程。 (e) 前記構真柱建込治具を前記構真柱建込架台のガイ
ド部に沿って垂直に案内し、前記構真柱下端を現場築造
杭の未硬化コンクリート中の所定深さまで建込む工程。
(A) A step of installing a true-column mounting frame having guide portions for guiding the true-column in the vertical direction on the true-column mounting position. (b) A step of adjusting the position of the guide portion of the structure pillar mounting frame. (c) A step of attaching a true-column mounting jig for lifting the true-column to the center of gravity to the upper end of the true-column. (d) A step of vertically hoisting the true column by means of a lifting device via the true column erection jig, and inserting it from the lower end to the guide portion of the true column erection stand. (e) Vertically guide the above-mentioned structure pillar mounting jig along the guide portion of the above-mentioned structure pillar mounting base, and erect the lower end of the structure pillar to a predetermined depth in the uncured concrete of the site construction pile Process.

【0013】構真柱建込架台ガイド部は精度を確保する
ため、水平面内で微調整できる構造が望ましい。
In order to ensure accuracy, it is desirable that the structure-supporting gantry pedestal guide part be capable of fine adjustment in the horizontal plane.

【0014】また、構真柱建込治具に治具本体に沿っ
て、鉛直面を形成するガイドレール部を設け、構真柱建
込架台のガイド部に設けたガイドローラーと当接させな
がら、建込むようにすれば、高精度の建込みをスムーズ
に行うことができる。
Further, a guide rail portion that forms a vertical surface is provided along the jig main body in the true-column mounting jig, and while contacting with a guide roller provided in the guide portion of the true-column mounting base. If it is installed, high-accuracy installation can be performed smoothly.

【0015】構真柱を所定深さまで建込んだ状態でさら
に微調整するためには、建込治具本体の上部側面に複数
の受けブラケットを設け、構真柱建込架台上に設置した
鉛直方向のジャッキに支持させ、これらを調整する方法
を用いることができる。
In order to make further fine adjustment in a state where the true pillar is built up to a predetermined depth, a plurality of receiving brackets are provided on the upper side surface of the building jig main body, and a vertical bracket installed on the true pillar mounting frame is installed. It is possible to use a method in which the directional jacks are supported and these are adjusted.

【0016】[0016]

【実施例】次に、図示した実施例について説明する。EXAMPLES Next, the illustrated examples will be described.

【0017】図1は本発明の概要を示したもので、建込
架台10及び建込治具30を用いて、構真柱1を現場築
造杭50上部に垂直に建込んで行く様子を示している。
FIG. 1 shows an outline of the present invention, showing a state in which a construction post 1 and a construction jig 30 are used to vertically erection a true construction column 1 on top of a field construction pile 50. ing.

【0018】建込架台10は構真柱建込位置の地表に設
置され、中央部に構真柱1を垂直方向に案内するための
ガイド部11が形成されている。建込架台10はレベル
調整ジャッキ(油圧ジャッキ)20等で水平の調整を行
い、また後述するようにガイド部11についても水平面
内における直交する2方向及びねじれ等に対する回転の
微調整ができるようにしてある。
The built-in pedestal 10 is installed on the ground surface at the position where the structured pillars are built, and a guide portion 11 for guiding the structured pillars 1 in the vertical direction is formed in the central portion. The built-in pedestal 10 is horizontally adjusted by a level adjustment jack (hydraulic jack) 20 and the like, and as will be described later, the guide portion 11 is also made to be capable of fine adjustment of rotation in two directions orthogonal to each other in a horizontal plane and twist. There is.

【0019】建込治具30は治具本体を構真柱1の上部
に高力ボルト等で連結し、建込治具30上端の吊治具部
をローラーシャックル等を介して揚重機で吊り上げるこ
とにより、構真柱1を重心で吊り上げることができるよ
うにしたものである。構真柱1の建込みに際しては、構
真柱1を建込治具30を介して吊り上げ、構真柱1の下
端から建込架台10のガイド部11に挿入する。例えば
構真柱1の断面が矩形の場合には、建込治具本体に構真
柱1と外径が同一または相似な断面を有するものを用
い、治具本体の外周面をガイドレール部として、建込架
台10のガイド部11で垂直に案内する。構真柱1の断
面が矩形以外、例えば円形断面や、H形断面、十字断
面、その他の場合には構真柱1の重心に合わせて、構真
柱1の断面を決定し、4隅に角形パイプあるいはアング
ル等でガイドレール部を設けることにより、外周部が略
矩形断面となるようにし、建込架台10のガイド部11
に合わせる。
As for the installation jig 30, the jig main body is connected to the upper part of the false column 1 by a high-strength bolt or the like, and the hanging jig portion at the upper end of the installation jig 30 is lifted by a lifting machine via a roller shackle or the like. As a result, the true column 1 can be hoisted at the center of gravity. At the time of erection of the true construction pillar 1, the true construction pillar 1 is lifted up through the construction jig 30 and inserted into the guide portion 11 of the construction stand 10 from the lower end of the true construction pillar 1. For example, when the cross section of the true pillar 1 is rectangular, the built-in jig main body having a cross section having the same or similar outer diameter as the true true pillar 1 is used, and the outer peripheral surface of the jig main body is used as the guide rail portion. The guide portion 11 of the built-in frame 10 guides vertically. If the cross section of the true pillar 1 is other than rectangular, for example, a circular cross section, an H-shaped cross section, a cross section, or otherwise, the cross section of the true pillar 1 is determined according to the center of gravity of the true pillar 1, and the four corners are determined. By providing the guide rail portion with a square pipe or an angle, the outer peripheral portion has a substantially rectangular cross section, and the guide portion 11 of the erection stand 10 is provided.
To match.

【0020】図2〜図4は構真柱建込架台10の一実施
例を示したもので、構真柱建込架台10のセットから構
真柱1の建込みまでの、作業手順の一例を挙げると以下
のようになる。
FIGS. 2 to 4 show an embodiment of the mounting stand 10 for the true-column structure. An example of the work procedure from the setting of the mounting stand 10 for the true-column structure to the installation of the true-column structure 1. The following is an example.

【0021】(1) 地表のアスファルトコンクリート上
に設けた墨に合わせて建込架台10をセットする。
(1) The built-in frame 10 is set in accordance with the black ink provided on the asphalt concrete on the ground surface.

【0022】(2) 4箇所のレベル調整ジャッキ20に
より建込架台10を水平にセットする。
(2) The built-in frame 10 is set horizontally by the four level adjustment jacks 20.

【0023】(3) 地表のアスファルトコンクリート上
に設けた芯墨を下げ振り等で下部ゲージ18まで上げ、
ゲージの数値を読み取る。
(3) Raise the core ink provided on the asphalt concrete on the surface of the ground to the lower gauge 18 by swinging it down, etc.
Read the value on the gauge.

【0024】(4) 下部ゲージ18の数値と同じ数値を
上部ゲージ19に移す(上部ゲージと下部ゲージとは建
込架台が垂直であれば、ゲージ数値が同一となるように
しておく)。
(4) The same numerical value as the lower gauge 18 is transferred to the upper gauge 19 (the upper gauge and the lower gauge have the same gauge value if the built-in stand is vertical).

【0025】(5) 建込架台10中央のガイド部11に
芯出し定規をセットする(ガイド部の形状、寸法に合わ
せた略矩形の定規であり、ガイド部にはめ込んで水平面
内の調整に利用する)。
(5) A centering ruler is set on the guide part 11 in the center of the built-in frame 10 (a substantially rectangular ruler that matches the shape and size of the guide part, and is fitted into the guide part to be used for adjustment in the horizontal plane. To).

【0026】(6) 対向する上部ゲージ19間に水糸を
張る(この水糸が通り芯に平行となり、構真柱の芯を示
す)。
(6) A water thread is stretched between the opposed upper gauges 19 (this water thread is parallel to the passing core and indicates the core of the true column).

【0027】(7) 建込架台はX,Y方向各々300m
m、ねじれ8°以内については、水平面内に配した複数
の油圧ジャッキ13で微調整可能となっている。油圧ジ
ャッキ13で、前述した水糸に合わせてX,Y方向及び
ねじれを調整し、芯出し定規に合わせる。以上で芯出し
作業が完了する。
(7) The built-in frame is 300m in each of the X and Y directions.
Within the range of m and twist of 8 °, fine adjustment is possible with a plurality of hydraulic jacks 13 arranged in the horizontal plane. The hydraulic jack 13 adjusts the X and Y directions and the twist in accordance with the water thread described above, and adjusts the centering ruler. This completes the centering work.

【0028】(8) 芯出し定規を外す。(8) Remove the centering ruler.

【0029】(9) 建込時に構真柱1がガイド部11の
ガイドローラー12に当たってずれることを防止するた
め、ガイドローラー12は上げておく。
(9) The guide roller 12 is raised in order to prevent the false column 1 from hitting the guide roller 12 of the guide portion 11 and shifting when it is installed.

【0030】(10) 構真柱1を建込む。(10) Build the true pillar 1.

【0031】(11) 構真柱1上部の建込治具30が建込
架台10位置に来た時点で、ガイドローラー12を元に
戻す。
(11) The guide roller 12 is returned to the original position when the installation jig 30 on the upper part of the true column 1 reaches the position of the installation stand 10.

【0032】(12) 構真柱1上部の建込治具30をガイ
ドローラー12でガイドしながら、構真柱1を挿入す
る。
(12) While inserting the construction jig 30 above the structure column 1 with the guide roller 12, the structure column 1 is inserted.

【0033】(13) 建込治具30に設けたブラケット3
8を建込架台10に設けた治具受けジャッキ25上にセ
ットし、正規のレベルまで治具受けジャッキ25で微調
整する。
(13) Bracket 3 provided on the installation jig 30
8 is set on the jig receiving jack 25 provided on the building base 10 and finely adjusted by the jig receiving jack 25 to a regular level.

【0034】以上の操作により構真柱1は位置、レベル
とも正しく簡易にセットできる。
By the above operation, the true post 1 can be set correctly and easily in both position and level.

【0035】図5〜図15は構真柱建込治具30の実施
例を示したものである。
FIGS. 5 to 15 show an embodiment of the true-column mounting jig 30.

【0036】図5〜図8に示した実施例は構真柱1が各
先端にフランジ部を有する十字断面柱の場合である。
The embodiment shown in FIGS. 5 to 8 is a case where the true column 1 is a cross-section column having a flange portion at each tip.

【0037】構真柱建込治具30は大きく分けて、吊治
具部、建込治具本体、ガイドレール部の3つの部分から
なる。
The true column erection jig 30 is roughly divided into three parts, that is, a hanging jig part, an erection jig body, and a guide rail part.

【0038】吊治具部は建込治具30本体の上部に設け
られ、構真柱1の傾きをなくすため、計算によって重心
を求め、重心が吊中心となるように吊孔31を設ける。
また、構真柱1を吊った状態での垂直性を確保するた
め、例えば図20に示すようにローラーシッャクル40
を用いるとよい。ローラーシャックル40を用いること
で、図21(a) に示すように吊り上げたときに構真柱1
が傾いても、重心を吊中心としているため、図21(b)
に示すようにローラーシャックル40部分の回転により
垂直になる。
The hanging jig portion is provided above the main body of the erection jig 30, and in order to eliminate the inclination of the true column 1, the center of gravity is calculated and the hanging hole 31 is provided so that the center of gravity is the hanging center.
Further, in order to ensure the verticality in the state where the true column 1 is hung, for example, as shown in FIG.
Should be used. By using the roller shackle 40, as shown in FIG.
Since the center of gravity is the center of suspension even when the
The roller shackle 40 is rotated to be vertical as shown in FIG.

【0039】建込治具本体に関し、従来、構真柱の上部
に取り付けるタイプの建込治具は仮設であることから、
精度及び構真柱との取合部を容易に考えていたが、構真
柱1の自重で垂直性を保つためには建込治具30にも構
真柱1と同程度の精度が必要であるのみならず、構真柱
1との取合部(継手部)も完全に一体化できるものでな
ければならない。このため、本実施例では構真柱との取
合部に4箇所のエレクションピース36を設け、各々複
数本の高力ボルト37で接合する形式としている。ま
た、建込治具本体の上部側面には、構真柱1を所定深度
まで建込んだ状態で、建込架台10に対し治具受けジャ
ッキ25を介して垂直に支持させる(図2参照)ための
複数のブラケット38を設けている。
With respect to the main body of the installation jig, conventionally, the installation jig of the type to be attached to the upper part of the false column is temporary,
Although it was easy to consider the accuracy and the joint with the true-structured pillar, in order to maintain the verticality by the self-weight of the true-structured pillar 1, the erection jig 30 needs to have the same accuracy as the true-structured pillar 1. Not only the above, but also the joint (joint) with the structural column 1 must be able to be completely integrated. For this reason, in the present embodiment, four erection pieces 36 are provided at the joint with the true column and are joined by a plurality of high-strength bolts 37. Further, on the upper side surface of the installation jig main body, the installation column 10 is vertically supported via the jig receiving jack 25 in a state of being installed up to a predetermined depth (see FIG. 2). A plurality of brackets 38 are provided for this purpose.

【0040】ガイドレール部33は正確に設置された建
込架台の中央部に正しく構真柱1をセットするために設
けられ、このガイドレール部33を建込架台ガイド部の
ガイドローラー12(図3参照)に当てて構真柱1を挿
入して行く。なお、ガイドローラー部は起倒式になって
おり、構真柱先端から挿入して行く時点では上向きに立
て、構真柱1との干渉を避け、所定深さまで建込んだ状
態で倒し、建込治具30のガイドレール部33に当接さ
せる。
The guide rail portion 33 is provided in order to correctly set the true column 1 in the center portion of the installation frame installed correctly, and this guide rail portion 33 is used to guide the guide roller 12 (see FIG. 3) and insert the true column 1. In addition, the guide roller part is upside down, and when it is inserted from the tip of the structure column, it stands upright, avoiding interference with the structure column 1 and tilting it up to a predetermined depth, The guide rail portion 33 of the inserting jig 30 is brought into contact with the guide rail portion 33.

【0041】対向するガイドレール部33の外面寸法を
数種類に統一することにより、多数ある構真柱サイズを
整理し、建込架台についても数種類のガイド部またはガ
イドレール部を用意すればよいことになる。
By unifying the outer surface dimensions of the guide rail portions 33 facing each other into several types, it is possible to organize a large number of true column sizes and prepare several types of guide portions or guide rail portions for the mounting base. Become.

【0042】ガイドレール部33の長さは構真柱1の先
端が杭コンクリート天端に到達する直前に建込架台のガ
イドローラーで拘束されるように決定する(杭コンクリ
ートの抵抗で先端が移動し、構真柱が傾くのを防ぐた
め)。また、ガイドレール部33は杭コンクリートが固
まった後、取り外すが、上述のように長さを決定する
と、ガイドレール部33先端は地表面より約2m程度と
なる。そのため、地表面上での作業で簡単に取り外せ、
かつ精度が確保できる方法として、例えば図22に示す
ような納まりが考えられる。すなわち、ガイドレール部
33の先端にピン34を設け、構真柱1側の受プレート
5にピン用の孔6をあけ、その孔6にピン34を差し込
み固定する。
The length of the guide rail portion 33 is determined so that it is constrained by the guide roller of the building frame immediately before the tip of the true column 1 reaches the top of the pile concrete (the tip moves due to the resistance of the pile concrete). However, to prevent the true pillar from tilting). Further, the guide rail portion 33 is removed after the pile concrete has hardened, but when the length is determined as described above, the tip of the guide rail portion 33 becomes about 2 m from the ground surface. Therefore, it can be easily removed by working on the ground surface,
In addition, as a method for ensuring the accuracy, for example, the accommodation as shown in FIG. 22 can be considered. That is, a pin 34 is provided at the tip of the guide rail portion 33, a hole 6 for a pin is opened in the receiving plate 5 on the side of the false column 1, and the pin 34 is inserted and fixed in the hole 6.

【0043】図9〜図12に示した実施例は構真柱1が
円形断面の鋼管柱の場合である。本実施例ではガイドレ
ール部33が矩形をなすよう丸鋼管からなる建込治具本
体30の外側に4本の角パイプをガイドレール部33と
して配置している。ガイドレール部33の長さや先端部
の構造は上述した十字断面柱の場合と同様に考えること
ができる。
The embodiment shown in FIGS. 9 to 12 is a case where the true column 1 is a steel pipe column having a circular cross section. In this embodiment, four square pipes are arranged as guide rail portions 33 on the outside of the installation jig body 30 made of a round steel pipe so that the guide rail portions 33 form a rectangle. The length of the guide rail portion 33 and the structure of the tip portion can be considered as in the case of the cross-section column described above.

【0044】図13〜図16に示した実施例は構真柱1
が角形断面の鋼管柱の場合である。本実施例では建込治
具本体30に外径が鋼管柱と同寸法の角形鋼管を用い、
角形鋼管柱外周面と連続する外周面をガイドレール部3
3’として利用している。図16はその場合の建込架台
のガイドローラー12との当接部分を示している。
The embodiment shown in FIGS. 13 to 16 is a true pillar 1
Is the case of a steel pipe column with a rectangular cross section. In this embodiment, a square steel pipe having the same outer diameter as the steel pipe column is used for the installation jig body 30,
The outer peripheral surface that is continuous with the outer peripheral surface of the rectangular steel pipe column is used as the guide rail portion 3.
It is used as 3 '. FIG. 16 shows a contact portion of the built-in stand with the guide roller 12 in that case.

【0045】図17〜図19に示した実施例は構真柱1
がI形鋼1aとこれと直交するT形鋼1bとで構成さ
れ、これに梁受け部2が付いた形状の場合である。構真
柱30も同様にI形鋼30aとこれと直交するT形鋼3
0bとで構成しているが、フランジ幅、板厚等は小さく
てもよい。この場合も梁受け部2等を含めて重心を計算
し、重心吊りを行う。
The embodiment shown in FIG. 17 to FIG.
Is composed of an I-shaped steel 1a and a T-shaped steel 1b orthogonal to the I-shaped steel 1a, and a beam receiving portion 2 is attached to this. Similarly, the structural true column 30 has an I-shaped steel 30a and a T-shaped steel 3 orthogonal to the I-shaped steel 30a.
0b, but the flange width, plate thickness, etc. may be small. Also in this case, the center of gravity including the beam receiving portion 2 and the like is calculated and the center of gravity is suspended.

【0046】図23は全体工程のフローチャートであ
り、現場築造杭作業(掘削→1次スライム処理→孔壁測
定→鉄筋籠建込み→2次スライム処理→コンクリート打
設)終了後、直ちに構真柱建込架台をセットする。
FIG. 23 is a flow chart of the whole process. Immediately after the completion of on-site construction pile work (excavation → primary slime treatment → hole wall measurement → reinforcement basket construction → secondary slime treatment → concrete placement) Set the built-in stand.

【0047】図24(a) 〜(g) は図23の現場築造杭作
業後の工程に相当する。
24 (a) to 24 (g) correspond to the steps after the on-site construction pile work of FIG.

【0048】図24(a) は構真柱建込架台10のセット
の様子を示したもので、例えば以下の手順で行う。作業
地盤確認→構真柱芯確認(アスファルトコンクリート上
の墨)→架台芯セット(架台4隅で合わせる)→レベル
調整(架台取付け水準器を用い、各レベル調整ジャッキ
の高さを調整)→架台芯ずれの調整(架台定規を用い
る)→構真柱芯位置部分調整確認(測定結果による位置
調整)→構真柱レベル確認。
FIG. 24 (a) shows a state in which the true column built-in gantry 10 is set. For example, the procedure is as follows. Check work ground → Check true column core (ink on asphalt concrete) → Stand core set (match at the four corners of the stand) → Level adjustment (adjust the height of each level adjustment jack using the level level attached to the stand) → Stand Adjustment of misalignment (using a pedestal ruler) → Confirmation of core position adjustment of the true column (position adjustment based on measurement results) → Level check of true column.

【0049】図24(b) は構真柱1の建込みの様子を示
したもので、例えば以下の手順で行う。構真柱芯及び方
向確認→構真柱レベル確認→構真柱建込み(クローラー
クレーン2台共吊り)→吊上げ移動→芯位置に吊込み
(クローラークレーン1台)→構真柱架台挿入(吊下げ
→先端コンクリート中へ挿入)→構真柱セット、レベル
調整、方向確認。
FIG. 24 (b) shows a state in which the true post 1 is built, and is carried out by the following procedure, for example. Check the true column core and direction → Check the true column level → Build the true column (suspend with two crawler cranes) → Lifting movement → Suspend at the core position (1 crawler crane) → Insert the true column stand (hang) Lowering → Inserting into the tip concrete) → Structural column setting, level adjustment, direction confirmation.

【0050】図24(c) は架台10の撤去の様子を示し
たもので、例えば以下の手順で行う。杭コンクリート養
生→構真柱頭部仮固定→位置確認固定→架台撤去→定規
撤去→構真柱レベル、芯位置確認。
FIG. 24 (c) shows a state in which the gantry 10 is removed. The procedure is as follows, for example. Pile concrete curing → Temporary fixing of structural column head → Fixing position confirmation → Removing the cradle → Removing ruler → Confirming the structural column level and core position.

【0051】図24(d) は1次埋戻しの様子を示したも
ので、杭掘削用の泥水(安定液)を回収し、再生砕石5
4等で所定高さまで埋戻す。
FIG. 24 (d) shows the state of primary backfilling, in which muddy water (stabilizing liquid) for pile excavation is collected and recycled crushed stone 5
Backfill to the prescribed height with 4 etc.

【0052】図24(e) はケーシング51の撤去の様子
を示したもので、頭部固定金物等を撤去した後、杭建込
み用のケーシング51を引抜く。
FIG. 24 (e) shows a state of removing the casing 51. After removing the head fixing hardware and the like, the casing 51 for pile construction is pulled out.

【0053】図24(f) は構真柱建込治具10の撤去の
様子を示したもので、構真柱建込治具10を構真柱1頭
部から取外し、さらに構真柱頭部の位置を確認する。
FIG. 24 (f) shows a state in which the true-column mounting jig 10 is removed. The true-column mounting jig 10 is removed from one true-column head, and the true-column head is further removed. Check the position of.

【0054】図24(g) は2次埋戻しの様子を示したも
ので、砕石55等をGLレベルまで埋戻す。
FIG. 24 (g) shows a state of secondary backfilling, in which the crushed stones 55 and the like are backfilled to the GL level.

【0055】構真柱建込架台は前述のように水平、X,
Y方向及びねじれが簡易に微調整できるようになってい
る。一方、構真柱の形状は図5〜図19に示したもの以
外も含めて各種あり、サイズも分かれているが、構真柱
建込治具により建込架台部においては全て角形形状に置
き換え、X,Y方向及びねじれを管理する。
As described above, the structure-mounted post is horizontal, X,
The Y direction and the twist can be easily finely adjusted. On the other hand, there are various shapes of the true structure pillars, including those other than those shown in FIGS. , X, Y directions and twist.

【0056】構真柱は精度良く製造、ジョイントしたも
のを構真柱建込治具を使用して重心で吊ることで、自ず
と垂直となり、建込架台のガイド部で垂直に案内し、現
場築造杭の未硬化のコンクリート中に精度よく建込むこ
とができる。
The structure columns are manufactured and jointed with high precision, and by using the structure column erection jig to hang them at the center of gravity, they automatically become vertical, and they are vertically guided by the guides of the pedestal mount to build on-site. It can be accurately built in the uncured concrete of the pile.

【0057】[0057]

【発明の効果】構真柱は現場築造杭のコンクリート打設
後、短時間に建込みを完了させないと、コンクリートが
硬化し、挿入不可能となるが、本発明の建込方法を用い
ることにより、構真柱をコンクリートが十分流動性を有
する時間内に高精度で建込むことができる。
[Effects of the Invention] The structure columns cannot be inserted unless the construction is completed within a short time after the concrete is cast on the site-constructed piles. However, by using the construction method of the present invention, the concrete cannot be inserted. , It is possible to build a true column with high accuracy within the time when the concrete has sufficient fluidity.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の概要を示す鉛直断面図である。FIG. 1 is a vertical sectional view showing an outline of the present invention.

【図2】構真柱建込架台の一実施例を示す正面図であ
る。
FIG. 2 is a front view showing an embodiment of a true pillar built-in gantry.

【図3】構真柱建込架台の一実施例を示す平面図であ
る。
FIG. 3 is a plan view showing an embodiment of a true-column mounting frame.

【図4】構真柱建込架台の一実施例を示す側面図であ
る。
FIG. 4 is a side view showing an embodiment of a true-column mounting frame.

【図5】構真柱建込治具の一実施例を示す正面図であ
る。
FIG. 5 is a front view showing an embodiment of a true-column mounting jig.

【図6】図5のA−A断面図である。6 is a cross-sectional view taken along the line AA of FIG.

【図7】図5のB−B断面図である。7 is a sectional view taken along line BB of FIG.

【図8】構真柱と構真柱建込治具の継手の配置を示す水
平断面図である。
FIG. 8 is a horizontal cross-sectional view showing an arrangement of joints of a true-column and a true-column-installing jig.

【図9】構真柱建込治具の他の実施例を示す正面図であ
る。
FIG. 9 is a front view showing another embodiment of the true-column mounting jig.

【図10】図9のC−C断面図である。10 is a cross-sectional view taken along line CC of FIG.

【図11】図9のD−D断面図である。11 is a cross-sectional view taken along the line DD of FIG.

【図12】図9のE−E断面図である。12 is a sectional view taken along line EE of FIG.

【図13】構真柱建込治具のさらに他の実施例を示す正
面図である。
FIG. 13 is a front view showing yet another embodiment of a true-column mounting jig.

【図14】図13のF−F断面図である。FIG. 14 is a sectional view taken along line FF of FIG.

【図15】図13のG−G断面図である。15 is a sectional view taken along line GG of FIG.

【図16】構真柱建込治具と構真柱建込架台のガイドロ
ーラー部との当接部分を示す水平断面図である。
FIG. 16 is a horizontal cross-sectional view showing a contact portion between a true-column mounting jig and a guide roller portion of the true-column mounting base.

【図17】構真柱建込治具のさらに他の実施例(上端吊
治具部は省略)を示す正面図である。
FIG. 17 is a front view showing still another embodiment of the true-column mounting jig (the upper end hanging jig portion is omitted).

【図18】図17のH−H断面図である。18 is a sectional view taken along line HH of FIG.

【図19】構真柱と構真柱建込治具の継手の配置を示す
水平断面図である。
FIG. 19 is a horizontal cross-sectional view showing an arrangement of joints of a true-column and a true-column-installing jig.

【図20】構真柱建込治具の上端吊治具部の構造を示し
たもので、(a) は正面図、(b) は側面図である。
20A and 20B show a structure of an upper end lifting jig portion of a true-column mounting jig, wherein FIG. 20A is a front view and FIG. 20B is a side view.

【図21】(a) 、(b) はローラーシャックルの作用を説
明するための図である。
21 (a) and 21 (b) are views for explaining the action of the roller shackle.

【図22】構真柱建込治具のガイドレール部先端の納ま
りを示す斜視図である。
FIG. 22 is a perspective view showing the accommodation of the tip of the guide rail portion of the true-column mounting jig.

【図23】構真柱建込みの全体工程のフローチャートで
ある。
FIG. 23 is a flowchart of the entire process of building a true pillar.

【図24】(a) 〜(g) は現場築造杭作業後の構真柱建込
み作業を示す鉛直断面図である。
24 (a) to (g) are vertical cross-sectional views showing the work of constructing the true post after the work of constructing piles on site.

【図25】構真柱の垂直確保の必要性を説明するための
鉛直断面図である。
FIG. 25 is a vertical cross-sectional view for explaining the necessity of vertically ensuring the true columns.

【図26】構真柱の垂直確保の必要性を説明するための
図であり、(a) は鉛直断面図、(b) は構真柱が正確に建
込まれた場合の水平断面図、(c) 及び(d) は構真柱に傾
斜が生じた場合の水平断面図である。
[Fig. 26] Fig. 26 is a diagram for explaining the necessity of vertically securing the true pillar, (a) is a vertical sectional view, (b) is a horizontal sectional view when the true pillar is correctly installed, (c) and (d) are horizontal cross-sectional views when the true column is inclined.

【符号の説明】[Explanation of symbols]

1…構真柱、2…梁受け部、5…受けプレート、6…
孔、10…構真柱建込架台、11…ガイド部、12…ガ
イドローラー、13…油圧ジャッキ、18…下部ゲー
ジ、19…上部ゲージ、20…レベル調整ジャッキ、2
5…治具受けジャッキ、30…構真柱建込治具、31…
吊孔、33,33’…ガイドレール部、34…ピン、3
6…エレクションピース、37…高力ボルト、38…ブ
ラケット、40…ローラーシャックル、50…現場築造
杭、51…ケーシング、52…杭天端、53…杭余盛り
天端、54,55…砕石、
DESCRIPTION OF SYMBOLS 1 ... Structural pillar, 2 ... Beam receiving part, 5 ... Receiving plate, 6 ...
Holes, 10 ... Structured pillar installation frame, 11 ... Guide part, 12 ... Guide roller, 13 ... Hydraulic jack, 18 ... Lower gauge, 19 ... Upper gauge, 20 ... Level adjustment jack, 2
5 ... Jig receiving jack, 30 ... Construction pillar construction jig, 31 ...
Hanging hole, 33, 33 '... Guide rail part, 34 ... Pin, 3
6 ... Erection piece, 37 ... High-strength bolt, 38 ... Bracket, 40 ... Roller shackle, 50 ... On-site built pile, 51 ... Casing, 52 ... Pile top, 53 ... Pile surplus top, 54, 55 ... Crushed stone,

フロントページの続き (72)発明者 小西 昭臣 東京都港区元赤坂一丁目3番8号 鹿島建 設株式会社東京支店内Continuation of the front page (72) Inventor Akomi Konishi 1-3-8 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. Tokyo Branch

Claims (1)

【特許請求の範囲】 【請求項1】 現場築造杭のコンクリート打設後、建物
の地下階部分の掘削に先立ち、主として建物の地下階部
分の柱を構成する構真柱を前記現場築造杭上に垂直に建
込む構真柱の建込方法において、(a) 前記構真柱を垂
直方向に案内するためのガイド部を形成した構真柱建込
架台を構真柱建込位置上に設置する工程、(b) 前記構
真柱建込架台のガイド部の位置を調整する工程、(c)
前記構真柱を重心で吊り上げるための構真柱建込治具を
前記構真柱の上端に取付ける工程、(d) 前記構真柱を
前記構真柱建込治具を介して揚重装置で垂直に吊り上
げ、下端先端部から前記構真柱建込架台の前記ガイド部
に挿入する工程、及び、(e) 前記構真柱建込治具を前
記構真柱建込架台のガイド部に沿って垂直に案内し、前
記構真柱下端を前記現場築造杭の未硬化コンクリート中
の所定深さまで建込む工程を有することを特徴とする構
真柱建込方法。 【請求項2】 現場築造杭のコンクリート打設後、建物
の地下階部分の掘削に先立ち、主として建物の地下階部
分の柱を構成する構真柱を前記現場築造杭上に垂直に建
込む構真柱の建込方法において、(a) 前記構真柱を垂
直方向に案内するためのガイド部を形成した構真柱建込
架台を構真柱建込位置上に設置する工程、(b) 前記構
真柱建込架台のガイド部の位置を調整する工程、(c)
前記構真柱を重心で吊り上げるための構真柱建込治具を
前記構真柱の上端に取付ける工程、(d) 前記構真柱を
前記構真柱建込治具を介して揚重装置で垂直に吊り上
げ、下端先端部から前記構真柱建込架台の前記ガイド部
に挿入する工程、(e) 前記構真柱建込治具を前記構真
柱建込架台のガイド部に沿って垂直に案内し、前記構真
柱下端を前記現場築造杭の未硬化コンクリート中の所定
深さまで建込むとともに、前記建込治具本体の上部側面
に設けた複数の受けブラケットをそれぞれ前記構真柱建
込架台上に設置した鉛直方向のジャッキに支持させる工
程、及び、(f) 前記受けブラケットを支持する鉛直方
向のジャッキの高さを調整し、前記構真柱建込治具及び
前記構真柱の垂直を調整する工程、を有することを特徴
とする構真柱建込方法。 【請求項3】 前記構真柱建込治具には該構真柱建込治
具本体に沿って、建込治具本体の外周部に鉛直面を形成
するガイドレール部が形成されており、前記構真柱建込
架台の前記ガイド部には、前記構真柱建込治具を垂直に
案内するに際し、前記構真柱建込治具の前記ガイドレー
ル部に当接するガイドローラーが設けられている請求項
1または2記載の構真柱建込方法。 【請求項4】 前記ガイド部は前記構真柱建込架台に対
し、水平面内の直交する2方向の移動及び水平面内の回
転が可能である請求項1、2または3記載の構真柱建込
方法。
[Claims] [Claim 1] Prior to excavation of the basement of the building after concrete placement of the site-constructed pile, the true pillars mainly constituting the pillars of the basement of the building are installed on the site-constructed pile. In the method of erection of the vertical columns to be erected vertically in (a), (a) installing the gantry column pedestal having the guide portion for vertically guiding the gantry columns on the gantry column erected position. Step (b) adjusting the position of the guide portion of the above-mentioned structure column built-in gantry, (c)
A step of attaching a trueness column building jig for lifting the trueness column at the center of gravity, to the upper end of the trueness column, (d) a lifting device for the trueness column through the trueness column building jig Vertically, and inserting from the lower end to the guide section of the true-column mounting base, and (e) the true-column mounting jig to the guide section of the true-column mounting frame. A method of erection of a true-post pillar, comprising a step of vertically guiding along the bottom of the true-post pillar to a predetermined depth in the uncured concrete of the on-site built pile. 2. A structure in which a true pillar, which mainly constitutes a pillar of a basement of a building, is vertically installed on the basement of the building after excavating the basement of the building after the concrete has been laid on the site. In the method of erection of true pillar, (a) a step of installing a true stanchion built-in gantry having a guide portion for guiding the true true pillar in a vertical direction on a true true pillar built-in position, (b) A step of adjusting the position of the guide portion of the above-mentioned structure-based pillar mounting frame, (c)
A step of attaching a trueness column building jig for lifting the trueness column at the center of gravity, to the upper end of the trueness column, (d) a lifting device for the trueness column through the trueness column building jig Vertically, and the step of inserting from the lower end to the guide portion of the true-column mounting frame, (e) along the guide portion of the true-column mounting frame of the true-column mounting jig. Guide vertically and erect the lower end of the structure pillar to a predetermined depth in the uncured concrete of the on-site built pile, and install a plurality of receiving brackets provided on the upper side surface of the building jig main body, respectively. Supporting the vertical jack installed on the building base, and (f) adjusting the height of the vertical jack supporting the receiving bracket to adjust the height of the vertical pillar mounting jig and the vertical shaft. A method of constructing a true pillar, comprising the step of adjusting the verticality of the pillar. 3. A guide rail portion, which forms a vertical plane on the outer peripheral portion of the installation jig main body, is formed on the installation post main jig along the installation main body of the installation true pillar. A guide roller is provided in the guide portion of the true-column mounting jig, which comes into contact with the guide rail portion of the true-column mounting jig when vertically guiding the true-column mounting jig. 3. The method of erection of a true pillar according to claim 1 or 2. 4. The true pillar construction according to claim 1, 2 or 3, wherein the guide portion is movable in two directions orthogonal to each other in the horizontal plane and rotatable in the horizontal plane with respect to the true pillar built-in gantry. Included method.
JP3158282A 1991-06-28 1991-06-28 Construction method Expired - Lifetime JP2556215B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3158282A JP2556215B2 (en) 1991-06-28 1991-06-28 Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3158282A JP2556215B2 (en) 1991-06-28 1991-06-28 Construction method

Publications (2)

Publication Number Publication Date
JPH055312A true JPH055312A (en) 1993-01-14
JP2556215B2 JP2556215B2 (en) 1996-11-20

Family

ID=15668194

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3158282A Expired - Lifetime JP2556215B2 (en) 1991-06-28 1991-06-28 Construction method

Country Status (1)

Country Link
JP (1) JP2556215B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0815426A (en) * 1994-06-30 1996-01-19 Nec Corp Terrain alteration extracting device using interference type synthetic aperture radar
JP2013122149A (en) * 2011-12-12 2013-06-20 Ohbayashi Corp Column construction method
JP2014020022A (en) * 2012-07-12 2014-02-03 Taisei Corp Under-ground piled column assembly method
JP2018165431A (en) * 2017-03-28 2018-10-25 大成建設株式会社 Construction method of cast-in-place pile and foundation
CN115492403A (en) * 2022-10-09 2022-12-20 浙江省一建建设集团有限公司 Combined type precise positioning construction device for tower footing steel latticed column

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5719418A (en) * 1980-07-07 1982-02-01 Takahashi Kogyo Kk Constructing process of column to preset position in counter-piling process for column
JPS58218515A (en) * 1982-06-09 1983-12-19 Takenaka Komuten Co Ltd Method and apparatus for erecting structural center pillar at reverse-casting time
JP3011757U (en) * 1994-04-06 1995-06-06 長正 長野 Electric bicycle charger
JP3021442U (en) * 1995-08-07 1996-02-20 日発販売株式会社 toolbox

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5719418A (en) * 1980-07-07 1982-02-01 Takahashi Kogyo Kk Constructing process of column to preset position in counter-piling process for column
JPS58218515A (en) * 1982-06-09 1983-12-19 Takenaka Komuten Co Ltd Method and apparatus for erecting structural center pillar at reverse-casting time
JP3011757U (en) * 1994-04-06 1995-06-06 長正 長野 Electric bicycle charger
JP3021442U (en) * 1995-08-07 1996-02-20 日発販売株式会社 toolbox

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0815426A (en) * 1994-06-30 1996-01-19 Nec Corp Terrain alteration extracting device using interference type synthetic aperture radar
JP2013122149A (en) * 2011-12-12 2013-06-20 Ohbayashi Corp Column construction method
JP2014020022A (en) * 2012-07-12 2014-02-03 Taisei Corp Under-ground piled column assembly method
JP2018165431A (en) * 2017-03-28 2018-10-25 大成建設株式会社 Construction method of cast-in-place pile and foundation
CN115492403A (en) * 2022-10-09 2022-12-20 浙江省一建建设集团有限公司 Combined type precise positioning construction device for tower footing steel latticed column

Also Published As

Publication number Publication date
JP2556215B2 (en) 1996-11-20

Similar Documents

Publication Publication Date Title
CN113605390B (en) Accurate positioning structure for pile connection and construction method
CN112900450A (en) Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN113638417B (en) Pile connection accurate positioning pouring system and construction method
CN110016938B (en) Positioning and verticality adjusting device for rectangular lattice column of reverse construction method foundation pit
CN111945714B (en) Steel sleeve guiding method combined with steel upright column inserting construction method
CN105951747A (en) Construction method for embedding latticed column through reverse building method
CN112663613A (en) Verticality control device and verticality control method for latticed column
CN111472353A (en) Reverse construction method steel pipe upright pile construction casing device and construction method thereof
JP2005090116A (en) Method for erecting steel frame column and positioning frame body used for it
JP2556215B2 (en) Construction method
JPH055391A (en) Structural stud erection holder
CN216920302U (en) Pre-buried steel column transfers system of hanging down
JP2556216B2 (en) Construction pillar installation jig
CN215053235U (en) Lattice column mounting device for reverse construction method
CN113356185B (en) Assembled underground station steel pipe column and accurate installation method thereof
CN115898047A (en) Pre-buried formula rag bolt locator
CN214116620U (en) Adjustable support for accurate positioning of permanent double-steel-pipe column
CN113684826A (en) Reverse construction method steel pipe upright pile construction casing device and construction method thereof
JPH03295931A (en) Construction method for frame straight pillar
CN113718814A (en) Pile foundation construction method and bridge pier construction method
JPH0531631B2 (en)
CN110872843B (en) Construction method for controlling verticality of foundation pit section steel lattice column
JPH1161812A (en) Plumbing device of steel column
JP2799778B2 (en) Construction method of steel tube concrete pillar
JP7364105B2 (en) Position adjustment device and method for adjusting the position of the structure pillar

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19960716

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110905

Year of fee payment: 15

EXPY Cancellation because of completion of term