JP2000336626A - Method of constructing offshore structure - Google Patents

Method of constructing offshore structure

Info

Publication number
JP2000336626A
JP2000336626A JP11153618A JP15361899A JP2000336626A JP 2000336626 A JP2000336626 A JP 2000336626A JP 11153618 A JP11153618 A JP 11153618A JP 15361899 A JP15361899 A JP 15361899A JP 2000336626 A JP2000336626 A JP 2000336626A
Authority
JP
Japan
Prior art keywords
blocks
slab
pile
floor panel
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11153618A
Other languages
Japanese (ja)
Other versions
JP3582701B2 (en
Inventor
Nozomi Shinohara
原 望 篠
Yuichi Yoshino
野 雄 一 芳
Kazuo Kokubu
分 和 雄 國
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP15361899A priority Critical patent/JP3582701B2/en
Publication of JP2000336626A publication Critical patent/JP2000336626A/en
Application granted granted Critical
Publication of JP3582701B2 publication Critical patent/JP3582701B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method of constructing an offshore structure capable of shortening the construction period and reducing the construction cost by forming an offshore structure having a wide area like a landing area requiring the widest area in an offshore air port of large floor panel blocks and the piled foundation. SOLUTION: This method of constructing an offshore structure is formed of a process for manufacturing a floor panel for constructing an offshore structure while dividing it into blocks 2 and carrying the blocks loaded on a carrying ship 14 to the construction field and for setting the blocks between the foundation pile placing carrier chip 22 and the constructed floor panel block 2A, a process for placing foundation piles 9 into the floor panel blocks 2 through previously set pile placing holes 3, a process for cutting the pile heads for alignment and for connecting the floor panel blocks and the foundation piles 9 to each other with temporary fixing caps and for filling the mortar between the foundation piles 9 and the floor panel blocks 2, a process for bonding both the floor panel blocks to each other while welding the steel beams to each other and placing the floor panel concrete, and a process for paving the joint part of the floor panel blocks 2.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明が属する技術分野】本発明は、海上構造物の構築
方法に関し、特に、海上空港の中で最も広い面積を必要
とする離着陸地域の構築に実施して好適な海上構造物の
構築方法に関す。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a marine structure, and more particularly to a method of constructing a marine structure suitable for constructing a take-off and landing area requiring the largest area among marine airports. about.

【0002】[0002]

【従来の技術】海上空港を構築するには、従来は埋立工
法によっていた。しかし、埋立工法による場合は、工期
が長期化し、又、工事費がかさむものである。
2. Description of the Related Art In order to construct a marine airport, a conventional landfill method has been used. However, when using the landfill method, the construction period is prolonged, and the construction cost is increased.

【0003】特に、海上空港の中で最も広い面積を必要
とする離着陸地域の構築は、工期の長期化、工事費の増
大が問題となっている。
In particular, the construction of a take-off and landing area that requires the largest area among marine airports has a problem of prolonging the construction period and increasing construction costs.

【0004】一部に、床版をブロック化し、床版ブロッ
クと杭基礎とにより、海上構造物を構築する方法が提案
されているが、従来の方法は、岸壁を起点とし岸壁から
海上構造物を順次構築して行くものであり、岸壁から遠
く離れた海上に空港の離着陸地域のように、広い面積の
海上構造物を構築するには採用できないものである。
[0004] A method has been proposed in which a floor slab is partially blocked and a marine structure is constructed by using a floor slab block and a pile foundation. It cannot be used to build a large-area marine structure, such as an airport take-off and landing area, far away from the quay.

【0005】[0005]

【発明が解決しようとする課題】従って、本発明は、海
上空港の中で最も広い面積を必要とする離着陸地域のよ
うな広い面積の海上構造物を、大型床版ブロックと杭基
礎により構築し、工期の短縮と工費の低減を図ることの
できる海上構造物の構築方法を提供することを目的とす
るものである。
SUMMARY OF THE INVENTION Accordingly, the present invention is to construct a large-area marine structure such as a take-off and landing area requiring the largest area of a marine airport by using a large floor slab block and a pile foundation. It is an object of the present invention to provide a method of constructing a marine structure capable of shortening the construction period and reducing the construction cost.

【0006】[0006]

【課題を解決するための手段】本発明によれば、海上構
造物を構築する床版をブロックに分割して製作し、基礎
杭打設台船と施工済み床版ブロックとの間にセットする
工程と、床版ブロックに予め設けた杭打設孔を通して基
礎杭を打設する工程と、床版ブロックと基礎杭を連結す
る工程と、から成っている。
According to the present invention, a slab for constructing a marine structure is divided into blocks and manufactured, and is set between a foundation pile driving barge and a completed slab block. The method comprises the steps of: driving a foundation pile through a pile driving hole provided in advance in the floor slab; and connecting the floor slab to the foundation pile.

【0007】かかる海上構造物構築方法は、海上空港の
中で最も広い面積を必要とする離着陸地域の構築に実施
して好適なものである。
The method for constructing a marine structure is suitable for constructing a take-off and landing area requiring the largest area among marine airports.

【0008】海上構造物を構築する床版をブロックに分
割し、運搬船に搭載して現地まで曵航し、基礎杭打設台
船と施工済み床版ブロックとの間にセットし、床版ブロ
ックに予め設けた杭打設孔を通して基礎杭を打設して、
海上空港の離着陸地域のような広い面積の海上構造物を
構築することより、工期の短縮と工費の低減を図ること
ができる。
A slab for constructing a marine structure is divided into blocks, mounted on a carrier, towed to the site, and set between a foundation pile driving barge and the installed slab block, and a slab block is provided. Pile the foundation pile through the pile driving hole provided in advance,
By constructing a large-area marine structure such as a take-off and landing area at a marine airport, it is possible to shorten the construction period and reduce construction costs.

【0009】[0009]

【発明の実施の形態】本発明にしたがい海上空港におけ
る離着陸地域を構築する場合を例に挙げ、本発明の実施
例を説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described by taking as an example a case where a take-off and landing area at a marine airport is constructed according to the present invention.

【0010】図1乃至図3は、海上空港の離着陸地域の
構造を示し、図1において、離着陸地域1は、長さ4,
224m、幅490mのものであり、図2に示す長さ1
32m、幅17.5mの床版ブロック(床版パネル)2
を、長さ方向32枚、幅方向28枚、計896枚を連結
して成るものであり、床版パネル2は、図3に示すよう
に、海底盤8下に打設された鋼管杭9により支持されて
いる。
FIGS. 1 to 3 show the structure of a take-off and landing area of a marine airport. In FIG.
224 m, width 490 m, length 1 shown in FIG.
32 m wide, 17.5 m wide slab block (slab panel) 2
Are connected in a total length of 896, 32 in the length direction and 28 in the width direction. The slab panel 2 is composed of steel pipe piles 9 cast under the seabed 8, as shown in FIG. Supported by

【0011】次に、海上空港の離着陸地域を構築する行
程を、床版パネルの積込み、床版パネルの運搬、床版パ
ネルの設置・基礎杭打設、基礎杭と床版パネルの結合、
床版パネル相互の結合の順に説明する。
Next, the steps of constructing the take-off and landing area of the sea airport include loading slab panels, transporting slab panels, installing slab panels, setting foundation piles, connecting foundation piles and slab panels,
Description will be made in the order of connection between the floor panels.

【0012】図4乃至図5は、床版ブロック(床版パネ
ル)の積込み状況を示し、岸壁10上で製作された(工
場製作)床版パネル2の下面に、エアキャスタ11を設
置し、岸壁の支承台基礎杭12で支持された海底支承台
13上に着底された床版パネル運搬船14まで、岸壁1
0上のウインチ18により引き込む。引き込み後はエア
キャスタ11は回収する。
FIGS. 4 and 5 show the loading status of the floor slab blocks (floor panels). An air caster 11 is installed on the lower surface of the (factory-made) floor slab 2 manufactured on the quay 10. The quay 1 up to the floor slab panel carrier 14 settled on the seabed support 13 supported by the pier support base 12
Pull in by winch 18 above zero. After being pulled in, the air casters 11 are collected.

【0013】床版パネル運搬船14には、リフティング
ジャッキ16(図10)により昇降されるリフティング
ビーム15が設けられている。また、床版パネル運搬船
14は、係留ウインチ17を備えており、岸壁10の運
搬船接岸面には防舷材19が設置されている。
The floor slab panel carrier 14 is provided with a lifting beam 15 which is raised and lowered by a lifting jack 16 (FIG. 10). Further, the floor slab panel carrier 14 is provided with a mooring winch 17, and fenders 19 are installed on the berth 10 on the carrier berthing surface.

【0014】図6は、エアキャスタ11の作動原理を示
し、キャスタバック(トーラスバック)11aに加圧エ
アを供給して膨張させ、支持バッド11bと床面14a
との間の圧力室14bに加圧エアを供給させて床版パネ
ル2を浮上させる。
FIG. 6 shows the operating principle of the air caster 11, in which pressurized air is supplied to a caster bag (torus bag) 11a to expand the caster bag 11a, and a support pad 11b and a floor surface 14a.
And pressurized air is supplied to the pressure chamber 14b between the first and second floors to float the floor panel 2.

【0015】図7乃至図9は、床版パネルの運搬状況を
示し、床版パネル運搬船14は、床版パネル2の積込み
が完了すると、浮力調整後工場岸壁から曵出し、図7に
示すように、建設地点まで曵き船20で曵航する。その
際、床版パネル運搬船14の回りには警戒船21を配置
する。
FIGS. 7 to 9 show the state of transport of the slab panels. When the loading of the slab panels 2 is completed, the slab panel carrier 14 withdraws from the factory quay after adjusting the buoyancy, as shown in FIG. At that time, the ship is towed by the towing boat 20 to the construction site. At that time, a guard ship 21 is arranged around the floor slab panel carrier 14.

【0016】建設地点では床版パネル運搬船14を、図
8及び図9に示すように、セップと称せられる基礎杭打
設台船22と施工済み床版ブロック2A(これには、施
工済み旅客ターミナル護岸も含む)の間に係留する。図
8における矢印は、床版パネル運搬船14の引込み方向
を示す。
At the construction site, the slab panel carrier 14 is, as shown in FIGS. 8 and 9, a base pile setting barge 22 called CEP and an installed slab block 2A (including an installed passenger terminal). (Including revetment). The arrow in FIG. 8 indicates the retraction direction of the floor slab panel carrier 14.

【0017】図10乃至図13は、床版パネルの設置・
基礎杭打設状況を示し、図10において、基礎杭打設台
船22をジャッキダウンし、床版パネル運搬船14のリ
フティングジャッキ15、16により床版パネル2を持
ち上げ(左図)、施工済み床版ブロック2Aと基礎杭打
設台船22のパネル受けアーム23より床版パネル2を
仮受けし(中央図)、床版パネル運搬船14を引き出す
(右図)。
FIGS. 10 to 13 show installation of floor slab panels.
In FIG. 10, the foundation pile driving situation is shown. In FIG. 10, the foundation pile driving barge 22 is jacked down, and the floor slab panels 2 are lifted by the lifting jacks 15 and 16 of the floor slab panel carrier 14 (left figure). The slab panel 2 is temporarily received from the slab block 2A and the panel receiving arm 23 of the foundation pile driving barge 22 (center view), and the slab panel carrier 14 is pulled out (right figure).

【0018】図11及び図12において、床版パネル2
を仮受けし、基礎杭打設台船22のジャッキング操作に
より、床版パネル2のレベル調整が完了した状態で、杭
運搬台船24を基礎杭打設台船22の舷側に係留し、基
礎杭打設台船22上を移動するクレーン走行架台25に
搭載されたクローラークレーン26により、基礎杭とな
る鋼管杭9を床版パネル2の杭打設孔3を通して立込
む。
In FIG. 11 and FIG.
In the state where the level adjustment of the floor slab panel 2 is completed by the jacking operation of the foundation pile driving barge 22, the pile carrier barge 24 is moored to the side of the foundation pile driving barge 22, By a crawler crane 26 mounted on a crane traveling stand 25 moving on the foundation pile driving barge 22, the steel pipe pile 9 serving as the foundation pile stands up through the pile driving hole 3 of the floor panel 2.

【0019】基礎杭打設台船22には油圧ハンマーパワ
ーユニット27が設けられており、また床版パネル2上
には別のクレーン28が設けられている。
A hydraulic hammer power unit 27 is provided on the foundation pile driving barge 22, and another crane 28 is provided on the floor panel 2.

【0020】図13において、鋼管杭9の建込みが完了
したら、クローラクレーン26により、油圧ハンマ29
を杭頭にセットして所定深度まで打設する。
In FIG. 13, when the steel pipe pile 9 is completely erected, the crawler crane 26 moves the hydraulic hammer 29
Is set on the pile head and driven to the specified depth.

【0021】図14乃至図16は、基礎杭と床版パネル
の結合を示し、基礎杭(鋼管杭)9の打設が完了した
ら、杭頭を所定高さに切り揃えて、仮固定キャップ30
を床版パネル2の杭打設孔3に挿入し杭頭にセットす
る。
FIGS. 14 to 16 show the connection between the foundation pile and the floor slab panel. When the foundation pile (steel pipe pile) 9 is completed, the pile head is trimmed to a predetermined height and the temporary fixing cap 30 is set.
Is inserted into the pile driving hole 3 of the floor panel 2 and set on the pile head.

【0022】次に、仮固定キャップ30を矢印で示す方
向に回転させて、キャップ側テーパつば30aと杭打設
孔側キャップストッパ4を噛み合わせて、床版パネル2
の荷重を基礎杭9に受けさせる。
Next, the temporary fixing cap 30 is rotated in the direction shown by the arrow to engage the cap-side tapered collar 30a with the pile driving hole-side cap stopper 4, and the floor slab panel 2
Is received by the foundation pile 9.

【0023】その後、杭打設孔下端のチューブ31にモ
ルタルを注入して底蓋を形成したのち、基礎杭9の外周
と杭打設孔3の内周との間にモルタル32を充填し固定
する。
Thereafter, mortar is poured into the tube 31 at the lower end of the pile driving hole to form a bottom cover, and then the mortar 32 is filled and fixed between the outer periphery of the foundation pile 9 and the inner periphery of the pile driving hole 3. I do.

【0024】なお、基礎杭9の外周と杭打設孔3の内周
には予め鉄筋33を溶接しておき、モルタル32の付着
が充分とれるようにしておく。
A reinforcing bar 33 is previously welded to the outer periphery of the foundation pile 9 and the inner periphery of the pile driving hole 3 so that the mortar 32 can be sufficiently adhered.

【0025】図17及び図18は、床版パネルの接合を
示し、床版を構成するプレキャストコンクリート版5、
5Aを受けている鋼製桁7、7Aの溶接34と、向かい
合うプレキャストコンクリート版5、5Aの外縁枠間に
コンクリート35を打設することにより行う。
FIG. 17 and FIG. 18 show the joining of the slab panels, and the precast concrete slabs 5 constituting the slab are shown in FIGS.
This is performed by placing concrete 35 between the welding 34 of the steel girders 7, 7A receiving the 5A and the outer frame of the facing precast concrete plates 5, 5A.

【0026】なお、図17において、右側は既設側であ
り、左側は新設側であり、既設側桁7Aにノックピン3
7を取付け、新設側桁7の孔にノックピン37を差込ん
で、床版パネルを仮受けした時点でパネルの位置のズレ
が発生しないよう鋼製桁同士が連結される。
In FIG. 17, the right side is the existing side, and the left side is the new side.
The steel girders are connected to each other so that when the floor panel is temporarily received by inserting the knock pin 37 into the hole of the new side girders 7 and the panel slab is not misaligned.

【0027】図17において、コンクリートを現場打設
する際には底蓋38を設置し、またプレキャストコンク
リート版5、5Aの鉄筋6と現場打設コンクリート35
の鉄筋36とを接合する。
In FIG. 17, a bottom cover 38 is installed when concrete is cast in place, and the reinforcing steel 6 of the precast concrete slabs 5 and 5A and the cast-in-place concrete 35 are used.
To the reinforcing bar 36.

【0028】[0028]

【発明の効果】本発明は、海上構造物を構築する床版を
大型ブロックに分割し、運搬船に搭載して現地まで曵航
し、基礎杭打設台船と施工済み床版ブロックとの間にセ
ットし、床版ブロックに予め設けた杭打設孔を通して基
礎杭を打設して、海上構造物を構築するものであるの
で、海上空港の離着陸地域のような広い面積の海上構造
物を、従来工法に比べ短期間で、且つ、低コストで構築
することができるものである。
According to the present invention, a floor slab for constructing a marine structure is divided into large blocks, mounted on a carrier, and towed to the site. And laying a foundation pile through a pile driving hole provided in advance on the floor slab block to construct a marine structure, so a marine structure with a large area such as a take-off and landing area of a marine airport It can be constructed in a shorter time and at lower cost than the conventional method.

【図面の簡単な説明】[Brief description of the drawings]

【図1】空港の離着陸地域の平面図。FIG. 1 is a plan view of a take-off and landing area of an airport.

【図2】床版パネルの平面図。FIG. 2 is a plan view of a floor panel.

【図3】図2の拡大A矢示図。FIG. 3 is an enlarged view of an arrow A in FIG. 2;

【図4】床版パネルの積込み状況を示す図。FIG. 4 is a view showing a loading state of floor slab panels.

【図5】図4の拡大A矢示図。FIG. 5 is an enlarged view of an arrow A in FIG. 4;

【図6】エアキャスタの作動原理図。FIG. 6 is an operation principle diagram of an air caster.

【図7】床版パネルを積んだ運搬船を曵き船で曵航する
状態を示す図。
FIG. 7 is a diagram showing a state in which a carrier on which floor slab panels are loaded is towed by a towing boat.

【図8】床版パネルを積んだ運搬船を基礎杭打設台船と
施工済み床版ブロックとの間に係留した平面図。
FIG. 8 is a plan view of a carrier loaded with floor slab panels moored between a foundation pile driving barge and a completed floor slab block.

【図9】図8の拡大A矢示図。FIG. 9 is an enlarged view of an arrow A in FIG. 8;

【図10】床版パネルの設置順序を示す正面図。FIG. 10 is a front view showing the installation order of floor slab panels.

【図11】基礎杭建込み状況を示す正面図。FIG. 11 is a front view showing a foundation pile construction situation.

【図12】基礎杭建込み状況を示す平面図。FIG. 12 is a plan view showing a foundation pile construction situation.

【図13】基礎杭打設状況を示す正面図。FIG. 13 is a front view showing a foundation pile driving situation.

【図14】仮固定キャップにより基礎杭と床版パネルを
結合した平面図。
FIG. 14 is a plan view in which a foundation pile and a floor slab panel are connected by a temporary fixing cap.

【図15】仮固定キャップにより基礎杭と床版パネルを
結合した側断面図。
FIG. 15 is a side sectional view in which a foundation pile and a floor slab panel are joined by a temporary fixing cap.

【図16】キャップ側テーパつばと杭打設孔側テーパス
トッパとが噛み合う状態を示す説明図。
FIG. 16 is an explanatory view showing a state in which a cap side tapered collar and a pile driving hole side tapered stopper are engaged with each other.

【図17】床版パネルの接合における溶接状況を示す断
面図。
FIG. 17 is a cross-sectional view showing a welding situation in joining the floor slab panels.

【図18】床版パネルの接合におけるコンクリート打設
状況を示す断面図。
FIG. 18 is a cross-sectional view showing a concrete casting situation in joining the floor slab panels.

【符号の説明】[Explanation of symbols]

1・・・空港の離着陸地域 2・・・床版パネル 3・・・杭打設孔 4・・・杭打設孔側テーパストッパ 5・・・プレキャストコンクリート版 6・・・鉄筋 7・・・鋼製桁 8・・・海底盤 9・・・鋼管杭 10・・・岸壁 11・・・エアキャスタ 12・・・支承台基礎杭 13・・・海底支承台 14・・・床版パネル運搬船 15・・・リフティングビーム 16・・・リフティングジャッキ 17・・・係留ウインチ 18・・・岸壁上ウインチ 19・・・防舷材 20・・・曵船 21・・・警戒船 22・・・基礎杭打設台船 23・・・パネル受けアーム 24・・・杭台船 25・・・クレーン走行架台 26・・・クローラクレーン 27・・・油圧ハンマーパワーユニット 28・・・クレーン 29・・・油圧ハンマ 30・・・仮固定キャップ 31・・・チューブ 32・・・モルタル 33・・・鉄筋 34・・・溶接 35・・・打設コンクリート 36・・・鉄筋 37・・・ノックピン 38・・・底蓋 DESCRIPTION OF SYMBOLS 1 ... take-off and landing area of airport 2 ... floor panel 3 ... pile driving hole 4 ... pile driving hole side taper stopper 5 ... precast concrete plate 6 ... rebar 7 ... Steel girder 8 ・ ・ ・ Seabed bed 9 ・ ・ ・ Steel pipe pile 10 ・ ・ ・ Wharf 11 ・ ・ ・ Air caster 12 ・ ・ ・ Support base foundation pile 13 ・ ・ ・ Sea bottom support base 14 ・ ・ ・ Floor panel carrier 15 ... Lifting beam 16 ... Lifting jack 17 ... Mooring winch 18 ... Wharf winch 19 ... Fender 20 ... Towing boat 21 ... Watching boat 22 ... Foundation pile driving Setting boat 23 ・ ・ ・ Panel receiving arm 24 ・ ・ ・ Pile boat 25 ・ ・ ・ Crane traveling stand 26 ・ ・ ・ Crawler crane 27 ・ ・ ・ Hydraulic hammer power unit 28 ・ ・ ・ Crane 29 ・ ・ ・ Hydraulic hammer 30 ・..Temporary fixed cap 31 ... tube 32 ... mortar 33 ... reinforcing steel 34 ... welding 35 ... punch set concrete 36 ... reinforcing steel 37 ... knock pin 38 ... bottom cover

───────────────────────────────────────────────────── フロントページの続き (72)発明者 芳 野 雄 一 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 國 分 和 雄 東京都千代田区四番町9−6四番町プラザ 1001 ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Yuichi Yoshino Kashima Construction Co., Ltd. 1-2-7 Moto-Akasaka, Minato-ku, Tokyo (72) Inventor Kazuo Kokubu Yonbancho, Chiyoda-ku, Tokyo 9-6 Yonbancho Plaza 1001

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 海上構造物を構築する床版をブロックに
分割して製作し、基礎杭打設台船と施工済み床版ブロッ
クとの間にセットする工程と、床版ブロックに予め設け
た杭打設孔を通して基礎杭を打設する工程と、床版ブロ
ックと基礎杭を連結する工程と、から成ることを特徴と
する海上構造物構築方法。
A slab for constructing a marine structure is divided into blocks, manufactured and set between a foundation pile driving barge and a completed slab block, and provided on the slab block in advance. A method for constructing a marine structure, comprising: a step of driving a foundation pile through a pile driving hole; and a step of connecting a floor slab and a foundation pile.
【請求項2】 海上構造物を構築する床版をブロックに
分割して製作し、運搬船に搭載して現地まで曵航し、基
礎杭打設台船と施工済み床版ブロックとの間にセットす
る工程と、床版ブロックに予め設けた杭打設孔を通して
基礎杭を打設する工程と、杭頭を切り揃えて仮固定キャ
ップで床版ブロックと基礎杭を連結した後、基礎杭と床
版ブロックとの間にモルタルを注入し固定する工程と、
床版ブロック同士のジョイントを鋼製桁の溶接接合と床
版コンクリートの打設により行う工程と、床版ブロック
のジョイントが完了した部分から、引き続き舗装を行う
工程と、から成ることを特徴とする海上構造物構築方
法。
2. A floor slab for constructing a marine structure is divided into blocks and manufactured, mounted on a carrier and towed to the site, and set between a foundation pile driving barge and the completed floor slab block. And the step of placing the foundation pile through the pile setting holes provided in the floor slab, and cutting the pile heads and connecting the floor slab and foundation pile with the temporary fixing cap. A step of injecting and fixing mortar between the plate block,
A step of jointing the slab blocks with each other by welding a steel girder and placing slab concrete; and a step of continuously paving from a joint where the slab blocks are completed. Offshore structure construction method.
【請求項3】 基礎杭打設台船上を移動するクレーン走
行架台に搭載されたクローラークレーンにより、基礎杭
の建込み及び打設を行うことを特徴とする請求項2に記
載の海上構造物構築方法。
3. The construction of a marine structure according to claim 2, wherein the foundation pile is erected and set by a crawler crane mounted on a crane traveling platform that moves on the base pile setting gantry. Method.
【請求項4】 床版ブロックの杭打設孔側のテーパスト
ッパと仮固定キャップ側のテーパつばを噛み合わせて、
床版ブロックと基礎杭を連結することを特徴とする請求
項2及び3に記載の海上構造物構築方法。
4. A taper stopper on the pile driving hole side of the floor slab block and a taper collar on the temporary fixing cap side are engaged with each other,
The method for constructing a marine structure according to claim 2 or 3, wherein the floor slab and the foundation pile are connected.
【請求項5】 海上構造物が、空港の離着陸地域である
ことを特徴とする請求項2乃至4に記載の海上構造物構
築方法。
5. The offshore structure construction method according to claim 2, wherein the offshore structure is a take-off and landing area of an airport.
JP15361899A 1999-06-01 1999-06-01 Offshore structure construction method Expired - Lifetime JP3582701B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15361899A JP3582701B2 (en) 1999-06-01 1999-06-01 Offshore structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15361899A JP3582701B2 (en) 1999-06-01 1999-06-01 Offshore structure construction method

Publications (2)

Publication Number Publication Date
JP2000336626A true JP2000336626A (en) 2000-12-05
JP3582701B2 JP3582701B2 (en) 2004-10-27

Family

ID=15566440

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15361899A Expired - Lifetime JP3582701B2 (en) 1999-06-01 1999-06-01 Offshore structure construction method

Country Status (1)

Country Link
JP (1) JP3582701B2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505675A (en) * 2011-10-11 2012-06-20 中国石油天然气集团公司 Ashore prefabricated island-landing construction method for top facilities of offshore isolated artificial island
CN102587342A (en) * 2012-03-02 2012-07-18 中国水电顾问集团华东勘测设计研究院 Buoyancy type mounting method for offshore boosting station
CN104612120A (en) * 2014-12-15 2015-05-13 中铁上海工程局集团有限公司 Integrated construction method related to in-water steel pipe pile establishing platform
CN105568948A (en) * 2016-02-26 2016-05-11 福建省新能海上风电研发中心有限公司 Multifunctional self-elevating platform used for offshore pile foundation localization guiding and exploration and working method of platform
CN106555390A (en) * 2015-09-25 2017-04-05 上海勘测设计研究院有限公司 The jacket-type location structure of catheterostat piling under water
CN110042819A (en) * 2019-04-16 2019-07-23 中国电建集团华东勘测设计研究院有限公司 A kind of marine converter station for flexible HVDC transmission system
CN113602518A (en) * 2021-06-30 2021-11-05 珠海天晴航空航天科技有限公司 Landing device for unmanned aerial vehicle to land on sea surface boat
CN114032944A (en) * 2021-10-26 2022-02-11 中交第三航务工程局有限公司宁波分公司 Offshore wind power high-rise pile cap construction method and system

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895034B (en) * 2014-03-06 2017-01-25 天津市海王星海上工程技术股份有限公司 Installation method for suction pile bottom hull type self-lifting platform

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505675A (en) * 2011-10-11 2012-06-20 中国石油天然气集团公司 Ashore prefabricated island-landing construction method for top facilities of offshore isolated artificial island
CN102587342A (en) * 2012-03-02 2012-07-18 中国水电顾问集团华东勘测设计研究院 Buoyancy type mounting method for offshore boosting station
CN104612120A (en) * 2014-12-15 2015-05-13 中铁上海工程局集团有限公司 Integrated construction method related to in-water steel pipe pile establishing platform
CN104612120B (en) * 2014-12-15 2016-08-17 中铁上海工程局集团有限公司 A kind of integral construction method setting up platform about steel-pipe pile in water
CN106555390A (en) * 2015-09-25 2017-04-05 上海勘测设计研究院有限公司 The jacket-type location structure of catheterostat piling under water
CN106555390B (en) * 2015-09-25 2019-02-15 上海勘测设计研究院有限公司 Underwater jacket piling jacket-type location structure
CN105568948A (en) * 2016-02-26 2016-05-11 福建省新能海上风电研发中心有限公司 Multifunctional self-elevating platform used for offshore pile foundation localization guiding and exploration and working method of platform
CN110042819A (en) * 2019-04-16 2019-07-23 中国电建集团华东勘测设计研究院有限公司 A kind of marine converter station for flexible HVDC transmission system
CN110042819B (en) * 2019-04-16 2021-06-01 中国电建集团华东勘测设计研究院有限公司 Offshore converter station for flexible direct current transmission system
CN113602518A (en) * 2021-06-30 2021-11-05 珠海天晴航空航天科技有限公司 Landing device for unmanned aerial vehicle to land on sea surface boat
CN114032944A (en) * 2021-10-26 2022-02-11 中交第三航务工程局有限公司宁波分公司 Offshore wind power high-rise pile cap construction method and system

Also Published As

Publication number Publication date
JP3582701B2 (en) 2004-10-27

Similar Documents

Publication Publication Date Title
CN104018436B (en) Prefabricated box culvert system and its installation method
CN109356210B (en) Pile foundation building inclination correction pile interception underpinning limiting structure and construction method thereof
JP5830423B2 (en) Pile type offshore structure construction method and pile type offshore structure
CN103485360A (en) Steel platform tower crane foundation and construction method thereof
WO2023184679A1 (en) Large-span space special-shaped arch rib flying-swallow type basket steel box arch bridge and rapid construction method
CN211815986U (en) High-pile beamless plate wharf structure
JP3582701B2 (en) Offshore structure construction method
WO2023020356A1 (en) Caisson quay and construction method therefor
KR101474554B1 (en) harbor structures construction equipment and it's construction method
CN114000459B (en) Method for erecting platform for high-pile wharf cast-in-place pile construction
JPH1054037A (en) Coffering method and steel structural body therefor
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
CN116677003A (en) Construction process of offshore bridge high-pile cap
CN217325062U (en) Assembling sliding support of large-tonnage steel cross beam of cable-stayed bridge cable tower
JP2002364004A (en) Installation method for underwater foundation
CN115432552A (en) Hanging bracket and construction method of assembly type high-pile wharf using same
CN115491986A (en) Construction system suitable for trestle and construction method thereof
JP3463604B2 (en) Dolphin construction method
CN111593702B (en) Upgrading and reforming method and upgrading and reforming structure for wharf
JP2874573B2 (en) Rail foundation and its repair method
JP3335804B2 (en) Bridge construction method
CN115492141B (en) Steel suspended box cofferdam structure, bottom plate thereof and construction method
CN217621305U (en) Structure foundation for prefabricating immersed tube by factory method
JP2632795B2 (en) How to build artificial ground
CN217678548U (en) Transition section structure of trestle and dam body

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040722

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040722

R150 Certificate of patent or registration of utility model

Ref document number: 3582701

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130806

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160806

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term