JP2000144762A - Foundation forming method for building - Google Patents

Foundation forming method for building

Info

Publication number
JP2000144762A
JP2000144762A JP10314543A JP31454398A JP2000144762A JP 2000144762 A JP2000144762 A JP 2000144762A JP 10314543 A JP10314543 A JP 10314543A JP 31454398 A JP31454398 A JP 31454398A JP 2000144762 A JP2000144762 A JP 2000144762A
Authority
JP
Japan
Prior art keywords
foundation
underground beam
pile
forming
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10314543A
Other languages
Japanese (ja)
Inventor
Shuichi Nagataki
周一 永滝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP10314543A priority Critical patent/JP2000144762A/en
Publication of JP2000144762A publication Critical patent/JP2000144762A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To permit to easily carry out the pile foundation forming work, inground beam forming work, or to easily and accurately perform excavation work for foundation forming portion and also to enhance the positional accuracy for the foundation. SOLUTION: By using the pile main bars 2x, which is provided in the pile foundation forming portion, as the main bars for a column, concrete is placed in the pile foundation forming portion without providing a base reinforcement at the bottom portion of the pile foundation forming portion. Then, concrete is placed in the inground beam forming portion and the foundation of the building is formed in a state where the inground beam body structure is held and retained in such a manner that the bottom of the inground beam body structure distributed in the inground beam forming portion is separated oppositely from the bottom surface of the inground beam forming portion.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、建築物の杭基礎
部などの基礎の作成方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of forming a foundation such as a pile foundation of a building.

【0002】[0002]

【従来の技術】従来の、例えば、杭基礎部及びこの杭基
礎部と連続する地中梁部とから成る建築物の基礎を作成
する場合の施工工程を、図9〜図14に基づいて説明す
る。まず、建築物の基礎を構成する杭及び地中梁の位置
を出す。次に、図9に示すように、複数の杭位置に、杭
打機で場所打コンクリート杭2を作成する。これはよく
知られているように、杭打機で地盤中に穴2sをあけ、
その中に杭主筋2aを配置してコンクリートを打設する
ことによって作成される。尚、穴2sの上部は埋め戻し
2fされる。また、この場合、杭頭2tの品質を保つた
め、杭頭部分においてコンクリートを余盛し、後述する
ように、この余盛コンクリート部分2bをはつるように
している。次に、図10,図13に示すように、杭基礎
部のフーチング部及びこのフーチング部と連続する地中
梁部を形成する位置の地盤を掘削して、フーチング部形
成部分3及び地中梁部形成部分4を形成する。そして、
上述したように、杭頭の余盛コンクリート部分2bをは
つり、フーチング部形成部分3及び地中梁部形成部分4
の底面に薄いコンクリート層5(捨てコンクリート)を
設ける(図11,図13参照)。フーチング部形成部分
3の底面に設けた薄いコンクリート層5の上にはフーチ
ング部及び柱形状の墨出しが行われ、地中梁部形成部分
4の底面に設けた薄いコンクリート層5の上には地中梁
部の墨出しが行われる。次に、フーチング部形成部分3
においては、図12に示すように、上記薄いコンクリー
ト層5の上にベース配筋6を設けて、杭頭2tの杭主筋
2aに柱配筋7を取り付け、かつ、フーチング部の墨に
合わせて、ベース配筋6の周囲を囲むように型枠8を設
置する。また、地中梁部形成部分4においても、図14
に示すように、上記薄いコンクリート層5の上に地中梁
鉄筋受架台9(または足場)を設置してこの地中梁鉄筋
受架台9を利用して、地中梁構体10を配筋して組み立
てる。そして、組み立てた地中梁構体10の両側に、地
中梁部の墨に合わせて型枠を設置する。尚、図14中、
11は仮設通路、12は仮設昇降階段であり、これら
は、地中梁構体10の組立て作業用の仮設物である。そ
して、上記各型枠内にコンクリートを流し込んで、杭基
礎部のフーチング部と地中梁部とを作成する。その後、
各型枠を撤去,あるいは組み付けたまま、完成したフー
チング部の周囲及び地中梁部の両側に土砂を埋戻す。最
後に、地盤表面上に薄いコンクリート層や砂利層などを
設けて、その上に配筋した後、床(土間)コンクリート
を打設する。
2. Description of the Related Art A conventional construction process for forming a foundation of a building including, for example, a pile foundation and an underground beam continuous with the pile foundation will be described with reference to FIGS. I do. First, the positions of the piles and underground beams that constitute the foundation of the building are determined. Next, as shown in FIG. 9, the cast-in-place concrete pile 2 is created at a plurality of pile positions by a pile driver. This is, as is well known, drilling a hole 2s in the ground with a pile driver,
It is created by placing the main reinforcing bar 2a therein and casting concrete. The upper portion of the hole 2s is backfilled 2f. Further, in this case, in order to maintain the quality of the pile head 2t, concrete is laid at the pile head portion, and as will be described later, the extra concrete portion 2b is attached. Next, as shown in FIG. 10 and FIG. 13, the footing portion of the pile foundation portion and the ground at the position where the underground beam portion continuous with the footing portion is formed are excavated, and the footing portion forming portion 3 and the underground beam are excavated. The part forming part 4 is formed. And
As described above, the excess concrete portion 2b of the pile head is removed, and the footing portion forming portion 3 and the underground beam portion forming portion 4 are removed.
A thin concrete layer 5 (abandoned concrete) is provided on the bottom surface (see FIGS. 11 and 13). On the thin concrete layer 5 provided on the bottom surface of the footing portion forming portion 3, the footing portion and the columnar ink-out are performed, and on the thin concrete layer 5 provided on the bottom surface of the underground beam portion forming portion 4. Marking of the underground beam is performed. Next, the footing portion forming portion 3
In FIG. 12, as shown in FIG. 12, a base reinforcing bar 6 is provided on the thin concrete layer 5, a column reinforcing bar 7 is attached to a pile main reinforcing bar 2a of a pile head 2t, and in accordance with black ink of a footing portion. Then, the formwork 8 is installed so as to surround the periphery of the base reinforcing bar 6. Also, in the underground beam forming part 4, FIG.
As shown in FIG. 7, an underground beam reinforcing bar 9 (or a scaffold) is installed on the thin concrete layer 5 and the underground beam structure 10 is arranged using the underground beam reinforcing bar 9. And assemble. Then, form frames are installed on both sides of the assembled underground beam structure 10 in accordance with the ink of the underground beam portion. In FIG. 14,
Reference numeral 11 denotes a temporary passage, and reference numeral 12 denotes a temporary elevating stair. These are temporary objects for assembling the underground beam structure 10. And concrete is poured into each of the above-mentioned formwork, and a footing part and an underground beam part of a pile foundation part are created. afterwards,
While removing or assembling each formwork, backfill the soil around the completed footing and on both sides of the underground beam. Finally, a thin concrete layer or a gravel layer is provided on the ground surface, and reinforcement is arranged thereon, and then floor (soil) concrete is poured.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、上述し
た従来の建築物の基礎の作成方法によれば、杭基礎形成
部分のフーチング部形成部分において、底部にベース配
筋を設けなくてはならず、また、地中梁部形成部分にお
いて、底部に薄いコンクリート層を予め設けると共に、
地中梁鉄筋受架台,仮設通路,仮設昇降階段などを仮設
して地中梁の組立てなどを行わなければならず、作業が
煩雑であった。また、従来は、建築物の建築位置の周囲
に、ある基準を決め、この基準より杭の中心位置やフー
チング部形成部分,地中梁部形成部分の位置を、糸など
を張って出している。しかし、地盤1上には墨を打てな
いので、フーチング部形成部分,地中梁部形成部分など
の基礎形成部分の掘削作業を正確に行うことができなか
った。また、地盤1上には墨を打てず、また、上記糸
は、実際の杭打時やフーチング部,地中梁部の施工時に
は撤去されたり、位置が狂う場合があるので、実際の杭
基礎や地中梁の施工にあたっては、適時上記基準より、
杭の中心位置やフーチング,地中梁など基礎の位置を確
認しながら作業を進めなければならず、確認の際ごとの
誤差が出る可能性があった。よって、上記課題ととも
に、基礎形成部分の掘削作業を正確に行うことができ
ず、基礎を設ける位置の位置精度を高めることが困難で
あるという課題があった。
However, according to the above-mentioned conventional method of forming a foundation for a building, a base reinforcing bar must be provided at the bottom in the footing portion forming portion of the pile foundation forming portion. In addition, in the underground beam part formation part, while providing a thin concrete layer at the bottom in advance,
The underground beams have to be temporarily assembled to assemble the underground beams by temporarily installing underground beam reinforcing bars, temporary passages, temporary elevating stairs, and the like, and the work is complicated. Conventionally, a certain standard is determined around the construction position of a building, and the center position of the pile, the position of the footing portion forming portion, and the position of the underground beam portion forming portion are drawn out with a thread or the like based on this standard. . However, since black ink cannot be applied on the ground 1, excavation work of a foundation forming part such as a footing part forming part and an underground beam part forming part could not be performed accurately. In addition, black ink is not applied on the ground 1, and the above-mentioned yarn may be removed or misaligned at the time of actual pile driving or construction of the footing portion or the underground beam portion. When constructing foundations and underground beams,
The work had to be performed while checking the center position of the pile, the footing, and the position of the foundation such as the underground beam, and there was a possibility that an error would occur at each check. Therefore, in addition to the above-mentioned problem, there has been a problem that the excavation work of the foundation forming portion cannot be performed accurately, and it is difficult to improve the positional accuracy of the position where the foundation is provided.

【0004】本願発明は上述した課題を解消するために
なされたもので、杭基礎部作成作業や地中梁部作成作業
を簡単に行えるようにすることを目的とする。また、上
記目的とともに、基礎形成部分の掘削作業を正確に簡単
に行うことができ、かつ、基礎を設ける位置の位置精度
を高めることができるようにすることを目的とする。
[0004] The present invention has been made to solve the above-mentioned problems, and an object of the present invention is to make it possible to easily perform a pile foundation portion forming operation and an underground beam portion forming operation. Another object of the present invention is to enable the excavation work of a foundation forming part to be performed accurately and easily, and to increase the positional accuracy of a position where a foundation is provided.

【0005】[0005]

【課題を解決するための手段】本願発明の請求項1に係
る建築物の基礎の作成方法は、地盤を掘削して、建築物
の基礎としての杭基礎部及び地中梁部を形成するための
杭基礎部形成部分及びこの杭基礎部形成部分と連続する
地中梁部形成部分を形成し、これら杭基礎部形成部分及
び地中梁部形成部分にコンクリートを打設して建築物の
基礎を作成する方法において、上記杭基礎部形成部分に
設けられる杭主筋を柱の主筋として用いることにより、
上記杭基礎部形成部分の底部にベース配筋を設けずに、
当該杭基礎部形成部分にコンクリートを打設するととも
に、上記地中梁部形成部分に配設される地中梁構体の底
部が上記地中梁成形部分の底面より離反するように、当
該地中梁構体を、上記地盤表面被覆層を介して吊下げる
ようにした状態で、当該地中梁形成部分にコンクリート
を打設して建築物の基礎を作成するようにした。請求項
2の発明は、地盤を掘削して、建築物の基礎としての杭
基礎部を形成するための杭基礎部形成部分を形成し、こ
の杭基礎部形成部分にコンクリートを打設して建築物の
基礎を作成する方法において、上記地中梁部形成部分に
配設される地中梁構体の底部が上記地中梁成形部分の底
面より離反するように、当該地中梁構体を、上記地盤表
面被覆層を介して吊下げるようにした状態で、当該地中
梁形成部分にコンクリートを打設して建築物の基礎を作
成するようにした。請求項3の発明は、地盤を掘削し
て、建築物の基礎としての杭基礎部を形成するための杭
基礎部形成部分を形成し、この杭基礎部形成部分にコン
クリートを打設して建築物の基礎を作成する方法におい
て、上記杭基礎部形成部分に設けられる杭主筋を柱の主
筋として用いることにより、上記杭基礎部形成部分の底
部にベース配筋を設けずに、当該杭基礎部形成部分にコ
ンクリートを打設して建築物の基礎を作成するようにし
た。請求項4の発明は、請求項1,2,3において、上
記杭基礎部形成部分や地中梁部形成部分は、杭基礎部形
成部分や地中梁部形成部分に対応する地盤表面を除いた
地盤表面上に予めコンクリートなどによる地盤表面被覆
層を設けた後に、当該地盤表面被覆層が設けられていな
い部分の地盤を掘削して形成するようにしたものであ
る。請求項5の発明は、上記請求項4において、少なく
とも上記杭基礎形成部分、地中梁形成部分に対応する部
分の地盤を改良した後に、上記杭基礎形成部分、地中梁
形成部分を形成するようにした。
According to a first aspect of the present invention, there is provided a method for forming a foundation of a building, comprising the steps of: excavating a ground to form a pile foundation and an underground beam as a foundation of the building. The pile foundation formation part and the underground beam formation part which is continuous with this pile foundation part formation part are formed, and concrete is poured into these pile foundation part formation part and the underground beam formation part, In the method of creating, by using the pile main reinforcement provided in the pile foundation portion forming part as the main reinforcement of the column,
Without providing base reinforcement at the bottom of the pile foundation part,
The concrete is poured into the pile foundation portion forming portion, and the underground beam structure disposed in the underground beam portion forming portion is separated from the underground beam forming portion so that the bottom of the underground beam structure is separated from the bottom surface of the underground beam forming portion. In a state where the beam structure was suspended via the ground surface covering layer, concrete was poured into the underground beam forming portion to form the foundation of the building. According to the second aspect of the present invention, a foundation is formed by excavating the ground to form a pile foundation forming part for forming a pile foundation as a foundation of a building, and casting concrete into the pile foundation forming part. In the method of creating a foundation for an object, the underground beam structure is disposed such that a bottom of the underground beam structure disposed in the underground beam portion forming portion is separated from a bottom surface of the underground beam forming portion. In a state of being suspended through the ground surface coating layer, concrete was poured into the underground beam forming portion to form a foundation of the building. According to a third aspect of the present invention, a foundation is formed by excavating the ground to form a pile foundation portion for forming a pile foundation portion as a foundation of a building, and casting concrete into the pile foundation portion forming portion. In the method of creating a foundation for a product, by using a pile main reinforcement provided in the pile foundation portion forming part as a main reinforcement of a column, a base reinforcement is not provided at the bottom of the pile foundation part forming part, and the pile foundation part is not provided. Concrete was poured into the formation and the foundation of the building was created. According to a fourth aspect of the present invention, in the first, second, and third aspects, the pile foundation portion forming portion and the underground beam portion forming portion exclude the ground surface corresponding to the pile foundation portion forming portion and the underground beam portion forming portion. After a ground surface coating layer made of concrete or the like is provided on the ground surface in advance, the ground where the ground surface coating layer is not provided is excavated to form the ground. According to a fifth aspect of the present invention, in the fourth aspect, the pile foundation forming portion and the underground beam forming portion are formed after at least the ground corresponding to the pile foundation forming portion and the underground beam forming portion is improved. I did it.

【0006】[0006]

【発明の実施の形態】・実施の形態1 以下、図1ないし図8に基づいて本発明の実施の形態1
による建築物の基礎の作成方法を詳説する。尚、図11
〜図14の従来技術で説明した構成部分と同一部分は同
一符号を付している。
BEST MODE FOR CARRYING OUT THE INVENTION Embodiment 1 Hereinafter, Embodiment 1 of the present invention will be described with reference to FIGS.
The method of making the foundation of a building by using is explained in detail. Note that FIG.
The same components as those described in the related art of FIG. 14 to FIG. 14 are denoted by the same reference numerals.

【0007】まず、建築物を立てる地盤1において、建
築物の基礎としての杭基礎部及び地中梁部を形成するた
めの杭基礎部形成部分及びこの杭基礎部形成部分と連続
する地中梁部形成部分に対応する地盤表面を除いた地盤
表面にコンクリート(捨てコンクリート)を打設して地
盤表面被覆層を設ける。具体的には、図1に示すよう
に、まず、建築物を立てる地盤1全体を、打設するコン
クリートの厚さ分だけ数十mm掘削(根切)する。尚、
この場合、地盤1に自立性があれば地盤改良を行う必要
がないが、自立性がない地盤1の場合は予め地盤全体の
地盤改良を行っておく(地盤改良とは、例えば、地盤面
を転圧して地盤を硬くしたり、セメント系,石灰系の材
料を地盤の土と混ぜ合わせて地盤を硬くしたりすること
をいう)。例えば、地盤1が「関東ローム層」であれ
ば、地盤改良を行う必要がない場合が多い。そして、杭
及び地中梁の位置を出す。この位置出しは、ある基準を
決め、この基準より杭の中心位置やフーチング部形成部
分及び地中梁部形成部分の位置を、糸などを張って出
す。上記位置出しは、数十mm掘削した地盤表面1A上
において、杭が設けられる中心位置の周囲に杭径D1よ
り大きい径D2をとってフーチング部形成部分の位置出
しを行い、この位置に基づいて型枠8Aを設置する。ま
た、地中梁が設置される位置の両側に地中梁の巾W1よ
り大きい巾W2をとって地中梁部形成部分の位置出しを
行い、この位置に基づいて型枠8Bを設置する(従っ
て、最終的には、径D2のフーチング部,巾W2の地中
梁部が作成されることになる)。上記のように型枠8
A,8Bを設置した後に、図2に示すように、型枠8
A,8Bの外側にコンクリートを打設して、地盤表面被
覆層13を設ける。即ち、建築物を立てる地盤1全体を
均等に若干掘削した後、この掘削後の地盤表面1Aにお
いて、図2に示すように、杭基礎部形成部分及びこの杭
基礎部形成部分と連続する地中梁部形成部分に対応する
地盤表面1A部分を区画するように型枠8A,8Bを設
置して、上記杭基礎部形成部分及び地中梁部形成部分に
対応する地盤表面を除いた地盤表面1A上にコンクリー
トを打設して地盤表面被覆層13を設ける。上記地盤表
面被覆層13を設けた後は、基準線Xを当該地盤表面被
覆層13の上に移す。つまり、上記ある基準より計測し
て図2に示すように上記杭基礎部形成部分及び地中梁部
形成部分の近くの地盤表面被覆層13の上に基準線Xを
墨出しする。そして、以後、実際の杭基礎や地中梁の施
工作業は、上記地盤表面被覆層13の上に打った基準線
Xに基づいて位置を確認しながら行う。また、基準線X
により、柱,壁位置の墨出しも行う。
First, in a ground 1 on which a building is to be erected, a pile foundation portion for forming a pile foundation portion and an underground beam portion as a foundation of the building, and an underground beam continuous with the pile foundation portion forming portion Concrete (abandoned concrete) is cast on the ground surface excluding the ground surface corresponding to the part forming portion to provide a ground surface coating layer. Specifically, as shown in FIG. 1, first, the entire ground 1 on which a building is to be erected is excavated (root cut) by several tens of mm by the thickness of the concrete to be cast. still,
In this case, if the ground 1 has independence, it is not necessary to perform the ground improvement. However, if the ground 1 has no independence, the ground improvement of the entire ground is performed in advance. Rolling to harden the ground, or mixing cement-based or lime-based materials with the ground soil to harden the ground.) For example, if the ground 1 is the “Kanto loam layer”, it is often unnecessary to perform ground improvement. Then, the positions of the pile and the underground beam are determined. For this positioning, a certain reference is determined, and the center position of the pile, the position of the footing portion forming portion, and the position of the underground beam portion forming portion are drawn out with a thread or the like based on this reference. The above-mentioned positioning is performed on the ground surface 1A excavated by several tens of millimeters, by taking a diameter D2 larger than the pile diameter D1 around the center position where the pile is provided, to position the footing portion forming portion, and based on this position. The mold 8A is set. Further, the width W2 of the underground beam is larger than the width W1 of the underground beam on both sides of the position where the underground beam is installed, the underground beam portion forming portion is located, and the formwork 8B is installed based on this position ( Therefore, finally, a footing portion having a diameter D2 and an underground beam portion having a width W2 are created. Form 8 as described above
After installing the A and 8B, as shown in FIG.
Concrete is cast outside of A and 8B to provide a ground surface coating layer 13. That is, after slightly excavating the entire ground 1 on which the building is to be erected, on the ground surface 1A after the excavation, as shown in FIG. Formwork 8A, 8B is installed so as to divide the ground surface 1A corresponding to the beam forming portion, and the ground surface 1A excluding the ground surface corresponding to the pile foundation forming portion and the underground beam forming portion. A ground surface covering layer 13 is provided by casting concrete on the top. After providing the ground surface coating layer 13, the reference line X is moved onto the ground surface coating layer 13. That is, as shown in FIG. 2, the reference line X is measured on the ground surface covering layer 13 near the pile foundation portion forming portion and the underground beam portion forming portion as measured from a certain reference. Thereafter, the actual construction work of the pile foundation and the underground beam is performed while confirming the position based on the reference line X struck on the ground surface covering layer 13. Also, the reference line X
In this way, blackout of pillar and wall positions is also performed.

【0008】次に、図3,図5に示すように、地盤表面
被覆層13が設けられていない部分の地盤を、地盤表面
被覆層13に沿って、アースオーガーなどの杭打機30
およびバックホーなどの掘削機40で地盤を地盤表面1
Aに対してほぼ垂直に掘削することにより、杭基礎部形
成部分23や地中梁部形成部分24を形成する。
Next, as shown in FIGS. 3 and 5, a portion of the ground where the ground surface covering layer 13 is not provided is moved along the ground surface covering layer 13 along with a piling machine 30 such as an earth auger.
And the ground with the excavator 40 such as a backhoe
By excavating substantially perpendicular to A, a pile foundation portion forming portion 23 and an underground beam portion forming portion 24 are formed.

【0009】手順としては、まず、図3に示すように、
杭打機30で杭基礎部形成部分23を形成する。この場
合、まず、径D2のドリルで掘削してフーチング部形成
部分23Bを形成し、その後、基準線Xに基づいて杭位
置を再確認した後、径D1のドリルに換えて杭形成部分
23Aを形成する。次に、図4に示すように、杭基礎部
形成部分23の杭形成部分23A内に、複数の杭主筋2
x(鉄筋)を帯筋(フープ筋)で巻いて作成した杭構体
を配置し、コンクリートを打設して杭2を形成する(杭
頭処理する場合は、杭主筋2xを継ぐ場合がある)。
尚、杭形成部分23Aにコンクリートを打設する場合、
杭形成部分23Aとフーチング部形成部分23Bとの境
できっちりとコンクリートの打設を止めるのは困難であ
るし、また、必然性もないので、フーチング部形成部分
23Bの底面にも薄いコンクリート層5(捨てコンクリ
ート)が打設されるようにする。尚、杭頭2tの余盛コ
ンクリートは行わない(泥水を使用する場合は、バキュ
ームなどで杭頭コンクリートを除去する)。さらに、フ
ーチング部形成部分23Bの内側面地肌23sから乾い
た土砂等がくずれて底面に溜まっても、この土砂等がフ
ーチング部形成部分23Bに打設するコンクリートと混
ざらないように、フーチング部形成部分23Bの内面
(内側面,底面の両方あるいは少なくとも内側面)側に
は、フーチング部形成部分23Bの内面とフーチング部
形成部分23Bに打設されるコンクリートとの縁を切る
ための縁切り材14としてのシートなどを取り付けてお
く。
As a procedure, first, as shown in FIG.
The pile base forming part 23 is formed by the pile driving machine 30. In this case, first, a footing portion forming portion 23B is formed by drilling with a drill having a diameter D2, and then the pile position is reconfirmed based on the reference line X. Then, the pile forming portion 23A is replaced with a drill having a diameter D1. Form. Next, as shown in FIG. 4, a plurality of pile main reinforcements 2 are provided in the pile formation portion 23 </ b> A of the pile foundation portion formation portion 23.
A pile structure formed by winding x (rebar) with a band (hoop) is placed, and concrete is cast to form a pile 2 (in the case of pile head processing, the main pile 2x may be joined). .
In addition, when casting concrete in the pile formation part 23A,
It is difficult to stop the casting of concrete at the boundary between the pile forming portion 23A and the footing portion forming portion 23B, and since there is no necessity, the thin concrete layer 5 ( (Abandoned concrete). In addition, the extra concrete of the pile head 2t is not performed (when muddy water is used, the pile head concrete is removed by vacuum or the like). Furthermore, even if dry soil and the like are dislodged from the inner surface ground 23s of the footing portion forming portion 23B and accumulate on the bottom surface, the footing portion forming portion does not mix with the concrete poured into the footing portion forming portion 23B. On the inner surface (both the inner side surface and the bottom surface or at least the inner side surface) side of 23B, as an edge cutting member 14 for cutting the edge between the inner surface of the footing portion forming portion 23B and the concrete cast into the footing portion forming portion 23B. Attach a sheet, etc.

【0010】次に、図5に示すように、掘削機40で地
中梁部形成部分24を形成した後、図6に示すように、
予め地中梁主筋10a,帯筋10bで組んでおいた地組
の地中梁構体10A(例えば、現場内や現場の近くで直
接、地面の上で主筋,帯筋を組んで作成した地中梁)
を、形成した地中梁部形成部分24内に設置する。この
場合、図7に詳細を示すように、地中梁部形成部分3の
上縁両側にスペーサ15,15を介して掛け渡した支持
用鉄筋16(カンザシ筋)で、地組の地中梁構体10A
の底が地中梁部形成部分24の底面より離れるように地
組の地中梁構体10Aを吊架する。尚、上記同様の縁切
り材14としてのシートなどを地中梁部形成部分24の
内面側に取り付けておく。この縁切り材14は、上記型
枠8Bをそのまま付けている場合は、型枠8Bに木材8
bなどで釘止めすればよいし、型枠8Bをはずしている
場合は、コンクリート釘などで止めればよい。
Next, as shown in FIG. 5, after forming an underground beam forming portion 24 with an excavator 40, as shown in FIG.
An underground girder structure 10A of a ground structure previously assembled with the underground beam main reinforcement 10a and the stirrup 10b (for example, an underground beam created by assembling the main reinforcement and the stirrup directly on the ground at or near the site) Beam)
Is installed in the formed underground beam portion forming portion 24. In this case, as shown in detail in FIG. 7, the underground beams of the ground structure are supported by supporting reinforcing bars 16 (Kansashi bars) which are bridged on both sides of the upper edge of the underground beam portion forming portion 3 via spacers 15, 15. Structure 10A
The underground beam structure 10A of the ground is suspended so that the bottom of the underground beam portion is separated from the bottom surface of the underground beam portion forming portion 24. In addition, a sheet or the like as the edge cutting member 14 similar to the above is attached to the inner surface side of the underground beam portion forming portion 24. When the above-mentioned formwork 8B is attached as it is, the trimming material 14 is attached to the wood 8 by the formwork 8B.
It may be nailed with b or the like, or when the form 8B is removed, it may be nailed with concrete nails or the like.

【0011】その後、図4のように、杭頭2tより突出
する杭主筋2xに帯筋2y(フープ筋)を巻く。この
時、ベース配筋は行わない。そして、RC柱を立てる場
合は、杭主筋2xの上端に本来の柱筋(図示せず)の下
端を突き合わせて溶接などで接続しておく。即ち、構造
上、杭頭2t部分を基礎及び柱として考えて、杭主筋2
xを直接に柱筋につなぐようにして、杭主筋2xが柱筋
を兼ねるように構成している。つまり、杭頭2tに植設
した杭主筋2xそのものを柱の主筋として用いるように
する。尚、鉄骨柱を立てる場合は、アンカーボルト2z
(図8)が地盤表面被覆層13より上に長く突出するよ
う配設しておく。
Thereafter, as shown in FIG. 4, a band 2y (hoop) is wound around the main pile 2x projecting from the pile head 2t. At this time, base reinforcement is not performed. When the RC column is to be erected, the lower end of the original column bar (not shown) is abutted to the upper end of the main pile bar 2x and connected by welding or the like. That is, structurally, the pile head 2t is considered as a foundation and a pillar, and the pile main reinforcement 2
x is directly connected to the column bar, so that the main pile bar 2x also serves as the column bar. That is, the main pile 2x planted at the pile head 2t is used as the main reinforcement of the pillar. When standing a steel column, use anchor bolts 2z
(FIG. 8) is disposed so as to protrude longer than the ground surface coating layer 13.

【0012】以上の工程が終了したら、図8に示すよう
に、地中梁構体10Aの主筋10a同士を鉄筋10cで
接続する。この場合、地中梁構体10Aの主筋10aと
これをつなぐ鉄筋10cは、継ぎ手部材10dを用いた
り、重ね継手,溶接,圧接などで接続する。尚、鉄筋1
0cと杭主筋2xは接続しない。
When the above steps are completed, as shown in FIG. 8, the main reinforcing bars 10a of the underground beam structure 10A are connected to each other by the reinforcing bars 10c. In this case, the main reinforcing bar 10a of the underground beam structure 10A and the reinforcing bar 10c connecting the main reinforcing bar 10a are connected by using a joint member 10d or by lap joint, welding, pressure welding, or the like. In addition, rebar 1
0c and the main pile 2x are not connected.

【0013】その後、地盤表面被覆層13の上に配筋
(土間配筋)して、フーチング部形成部分23B内及び
地中梁部形成部分24内にコンクリートを打設すること
により、フーチング部及び地中梁部が形成され、杭基礎
部及び地中梁部とから成る基礎が作成されることにな
る。最後に、床(土間)コンクリートを打設する(尚、
フーチング部,地中梁部,及び床(土間)のコンクリー
トを同時に打設するようにしてもよい)。
Thereafter, concrete is laid in the footing portion forming portion 23B and the underground beam portion forming portion 24 by arranging reinforcing bars (soil arranging) on the ground surface covering layer 13, thereby forming the footing portion and the ground. An underground beam is formed, and a foundation consisting of a pile foundation and an underground beam is created. Finally, cast concrete on the floor (soil) (note that
The concrete of the footing part, the underground beam part, and the floor (soil) may be simultaneously poured.

【0014】上記実施の形態1によれば、以下のような
効果が得られる。 (1)フーチング部の配筋において、杭主筋2xそのも
のを柱筋として用いるようにしているので、ベース配筋
を設ける必要が無くなる。つまり、従来は、杭主筋2a
とは別に柱配筋7を設けているので、この柱配筋7のか
かる荷重を受けるためにベース配筋を設けているが、実
施の形態1では、本来の柱筋にかかる荷重を、この柱筋
に接続されて柱筋として機能する杭主筋2xが直接受け
るので、ベース配筋を設ける必要が無くなる。従って、
フーチング部の配筋において、従来と比べて大幅に施工
手間を削減できる。 (2)地中梁部の作成においては、予め形成した地組の
地中梁構体10Aを、地組の地中梁構体10Aの底が地
中梁部形成部分24の底面より離れるように支持用鉄筋
16(カンザシ筋)で吊架するだけなので、従来のよう
に、地中梁鉄筋受架台(または足場),仮設通路,仮設
昇降階段を設置する必要がなく、地中梁部形成部分24
の底面にコンクリート(捨てコンクリート)を打つ必要
も無い。従って、地中梁部の作成において、従来と比べ
て大幅に施工手間を削減できる。 (3)杭基礎形成部分23のフーチング部形成部分23
Bや地中梁形成部分24など基礎形成部分の掘削作業
は、地盤表面被覆層13が設けられていない部分の地盤
を地盤表面被覆層13に沿って地盤表面1Aに対してほ
ぼ垂直に掘削するだけなので、簡単に正確に行える。ま
た、形成される杭基礎部形成部分23のフーチング部形
成部分23B及び地中梁部形成部分24など基礎形成部
分がそのまま型枠として機能し、埋戻し作業を行わなく
てもよいので、従来と比べて作業が簡単になる。尚、こ
の場合、自立性がある地盤1であれば、地盤改良せずと
も、フーチング部形成部分23B及び地中梁部形成部分
24など基礎形成部分をそのまま型枠として機能させる
ことができる。また、自立性がない地盤1であっても、
予め地盤全体の地盤改良を行っておくことにより、フー
チング部形成部分23B及び地中梁部形成部分24など
基礎形成部分をそのまま型枠として機能させることが可
能となる。 (4)地盤表面被覆層13の上に基準線Xを移すことが
でき、この移した基準線Xに基づいて、以後、杭の中心
位置やフーチング,地中梁の位置を正確に確認しながら
施工が行えるので、従来と比べて、杭やフーチング,地
中梁など基礎を設ける位置の位置精度を高くできる。ま
た、基準線Xに基づいて、地中梁主筋10aの位置が杭
主筋2xと干渉しないように地中梁構体10Aの位置を
予め決めることができるので、従来のように、ある基準
に基づいて何回も地中梁構体10Aの位置を決め直さな
ければならないようなことがなくなる。また同様に、基
準線Xに基づいて、柱,壁位置の確認を正確に行えるの
で、柱,壁位置の位置精度も高くできる。 (5)フーチング部形成部分23B及び地中梁部形成部
分24の内面側に縁切り材14を設けた後に、コンクリ
ートを打設するようにしているので、フーチング部形成
部分23B及び地中梁部形成部分24に打設するコンク
リートと土砂が混ざることがなくなるため、品質の良い
フーチング部及び地中梁部を作成できる。
According to the first embodiment, the following effects can be obtained. (1) Since the main reinforcing bar 2x itself is used as a column bar in the reinforcing bar of the footing portion, it is not necessary to provide a base reinforcing bar. That is, conventionally, the pile main reinforcement 2a
Since the column reinforcing bar 7 is provided separately, the base reinforcing bar is provided to receive the load applied by the column reinforcing bar 7. However, in the first embodiment, the load applied to the original column reinforcing bar is Since the pile main bar 2x that is connected to the column bar and functions as a column bar is directly received, there is no need to provide a base bar arrangement. Therefore,
In the arrangement of the footing portion, the labor required for the construction can be greatly reduced as compared with the conventional case. (2) In creating the underground beam, support the preformed underground beam structure 10A so that the bottom of the underground beam structure 10A of the ground is separated from the bottom of the underground beam forming portion 24. Since it is only suspended by the reinforcing bar 16 (Kansashi bar), there is no need to install an underground beam reinforcing stand (or a scaffold), a temporary passage, and a temporary up-and-down staircase as in the related art.
There is no need to hit concrete on the bottom of the building. Therefore, in the creation of the underground beam part, the construction labor can be greatly reduced as compared with the related art. (3) Footing part forming part 23 of pile foundation forming part 23
In the excavation work of the foundation forming portion such as the B or the underground beam forming portion 24, the ground in the portion where the ground surface covering layer 13 is not provided is excavated substantially perpendicularly to the ground surface 1A along the ground surface covering layer 13. It is easy and accurate. In addition, the foundation forming portions such as the footing portion forming portion 23B and the underground beam forming portion 24 of the formed pile foundation portion forming portion 23 function as a formwork as they are, and it is not necessary to perform backfilling work. The work becomes easier. In this case, if the ground 1 has autonomy, the foundation forming portion such as the footing portion forming portion 23B and the underground beam portion forming portion 24 can function as a mold without any improvement of the ground. Also, even if the ground 1 has no independence,
By previously performing the ground improvement of the entire ground, it is possible to make the foundation forming parts such as the footing part forming part 23B and the underground beam part forming part 24 function as they are as the formwork. (4) The reference line X can be moved onto the ground surface covering layer 13, and thereafter, based on the transferred reference line X, the center position of the pile, the footing, and the position of the underground beam are accurately confirmed. Since the construction can be performed, the positional accuracy of the foundation, such as a pile, a footing, or an underground beam, can be improved as compared with the conventional method. Further, the position of the underground beam structure 10A can be determined in advance based on the reference line X so that the position of the underground beam main bar 10a does not interfere with the pile main bar 2x. There is no need to repeatedly determine the position of the underground beam structure 10A. Similarly, since the positions of the columns and walls can be accurately confirmed based on the reference line X, the positional accuracy of the positions of the columns and walls can be increased. (5) Since the edge cutting material 14 is provided on the inner surface side of the footing portion forming portion 23B and the underground beam portion forming portion 24, concrete is cast, so that the footing portion forming portion 23B and the underground beam portion forming. Since concrete and earth and sand to be poured into the portion 24 do not mix, a high-quality footing portion and underground beam portion can be created.

【0015】尚、実施の形態1では、予め地盤表面被覆
層を設ける方法について説明したが、地盤表面被覆層を
設けない場合でも、基礎としての杭基礎部,地中梁部の
作成作業を容易にできる。また、地盤表面被覆層を設け
ないで、杭基礎部のフーチング部の作成においては、従
来のようにベース配筋,柱配筋を設置して作成し、地中
梁部の作成においてのみ、地中梁部形成部分に配設され
る地中梁構体の底部が地中梁成形部分の底面より離反す
るように、地中梁構体を、地盤表面被覆層を介して吊下
げるようにした状態で、地中梁部形成部分にコンクリー
トを打設する方法を行っても、従来と比べて、地中梁部
の作成を容易にできる。また、上記とは逆に、地盤表面
被覆層を設けないで、杭基礎部のフーチング部の作成に
おいてのみ、実施の形態1のように、杭基礎部形成部分
に設けられる杭主筋を柱の主筋として用いることによ
り、杭基礎部形成部分の底部にベース配筋を設けずに、
当該杭基礎部形成部分にコンクリートを打設する方法を
行っても、従来と比べて、杭基礎部の作成を容易にでき
る。また、地盤表面被覆層13としては、アスファルト
などで形成してもよく、要は、杭基礎形成部分23のフ
ーチング部形成部分23Bや地中梁形成部分24などの
基礎形成部分の掘削作業の際に地盤と区別できて目印と
なり得るもの、及び基準線Xを移して墨出しできるもの
であれば、他の材料で形成してもよい。また、実施の形
態1では、地盤1に自立性がなければ、予め地盤全体の
地盤改良を行っておくと説明したが、少なくとも、フー
チング部形成部分23B及び地中梁部形成部分24など
の基礎形成部分に対応する部分の地盤を改良した後に、
この基礎形成部分に対応する地盤表面を除いた地盤表面
上に地盤表面被覆層13を設けるようにすればよい。例
えば、図5の破線に示すように、地盤が崩れない安定角
度Aに満たない部分だけを地盤改良したり、あるいは、
施工性を考えて、破線Bの範囲内でのみ地盤改良を行っ
てもよい。尚、これは、フーチング部形成部分23Bに
おいても同様である。さらに、縁切り材14としては、
シートの他に、ベニヤやキーストンプレートなど、要
は、フーチング形成部分23B及び地中梁部形成部分2
4の内面側とフーチング形成部分23B及び地中梁部形
成部分24に打設されるコンクリートとの縁を切れるも
のであれば何でもよい。また、実施の形態1において
は、地中梁構体を地組したが、例えば、仮設馬などを用
いて地中梁構体を組んで作成した後、支持用鉄筋16
(カンザシ筋)で吊架するようにしてもよい。また、本
願は、PC杭または鋼管杭などを用いる場合でも適用で
きる。尚、実施の形態1においては、丸柱の杭,フーチ
ング部を形成する場合を説明したが、これらの形状は任
意に設計できる。
In the first embodiment, the method of providing the ground surface covering layer in advance has been described. However, even when the ground surface covering layer is not provided, the work of forming the pile foundation and the underground beam as the foundation can be easily performed. Can be. In addition, without providing the ground surface covering layer, the footing of the pile foundation was created by installing base reinforcement and column reinforcement as in the past, and the ground In such a state that the underground beam structure is suspended via the ground surface covering layer so that the bottom of the underground beam structure provided in the center beam forming portion is separated from the bottom surface of the underground beam forming portion. Even when the method of placing concrete in the underground beam portion forming portion is performed, the underground beam portion can be easily created as compared with the conventional method. Contrary to the above, without providing the ground surface coating layer, only in the preparation of the footing portion of the pile foundation portion, as in Embodiment 1, the main reinforcement of the pile provided in the pile foundation portion forming portion is replaced with the main reinforcement of the column. By using as, without providing the base reinforcement at the bottom of the pile foundation part forming part,
Even when the method of placing concrete in the pile foundation portion forming part is performed, the creation of the pile foundation portion can be made easier as compared with the conventional method. Further, the ground surface covering layer 13 may be formed of asphalt or the like. In short, the ground surface covering layer 13 is used for excavation work of a foundation forming part such as a footing forming part 23B or an underground beam forming part 24 of a pile foundation forming part 23. Alternatively, any other material may be used as long as it can be distinguished from the ground and can be used as a mark, or can be shifted and printed with the reference line X. Also, in the first embodiment, it has been described that if the ground 1 does not have independence, the ground improvement of the entire ground is performed in advance, but at least the foundations such as the footing portion forming portion 23B and the underground beam forming portion 24 are formed. After improving the ground of the part corresponding to the formation part,
The ground surface covering layer 13 may be provided on the ground surface excluding the ground surface corresponding to the foundation forming portion. For example, as shown by the dashed line in FIG. 5, the ground is improved only in a portion where the ground does not collapse and is less than the stable angle A, or
Considering the workability, the ground improvement may be performed only within the range of the broken line B. The same applies to the footing portion forming portion 23B. Furthermore, as the edge cutting material 14,
In addition to the sheet, such as a veneer or a keystone plate, the key is the footing forming portion 23B and the underground beam forming portion 2
Any material can be used as long as it cuts the edge between the inner surface side of 4 and the concrete cast in the footing forming portion 23B and the underground beam portion forming portion 24. Further, in the first embodiment, the underground beam structure is grounded. However, for example, after the underground beam structure is assembled by using a temporary horse or the like, the supporting reinforcing bar 16 is formed.
(Kansashi muscle). Further, the present application can be applied even when a PC pile, a steel pipe pile, or the like is used. In the first embodiment, the case where the pillars and the footing portions of the round pillar are formed has been described, but these shapes can be arbitrarily designed.

【0016】[0016]

【発明の効果】請求項1に係る発明によれば、杭基礎部
形成部分のフーチング部形成部分において、底部にベー
ス配筋を設けなくてもよく、また、地中梁部形成部分に
おいて、底部に薄いコンクリート層を打設する作業、地
中梁鉄筋受架台,仮設通路,仮設昇降階段などを仮設し
て地中梁を組立てる煩雑な作業を行わなくてもよいの
で、従来と比べ、基礎としての杭基礎部,地中梁部の作
成作業を容易にできる。請求項2によれば、地中梁部形
成部分において、底部に薄いコンクリート層を打設する
作業、地中梁鉄筋受架台,仮設通路,仮設昇降階段など
を仮設して地中梁を組立てる煩雑な作業を行わなくても
よいので、従来と比べ、基礎としての地中梁部の作成作
業を容易にできる。請求項3によれば、杭基礎部形成部
分のフーチング部形成部分において、底部にベース配筋
を設けなくてもよいので、従来と比べ、基礎としての杭
基礎部の作成作業を容易にできる。請求項4によれば、
各請求項1,2,3の効果とともに、杭基礎部形成部
分、地中梁部形成部分の掘削作業は、地盤表面被覆層が
設けられていない部分の地盤を地盤表面被覆層に沿って
掘削するだけで、簡単に正確に行えるとともに、形成さ
れる杭基礎部形成部分、地中梁部形成部分がそのまま型
枠として機能し、埋戻し作業を行わなくてもよいので、
従来と比べて作業が簡単になる。また、地盤表面被覆層
の上に基準線を移すことができ、この移した基準線に基
づいて、以後、基礎の位置を正確に確認しながら施工が
行えるので、従来と比べて、杭基礎部,地中梁部など基
礎を設ける位置の位置精度を高くできる。請求項5によ
れば、地盤が、自立性のない地盤であっても、杭基礎部
形成部分、地中梁部形成部分をそのまま型枠として機能
させることが可能となり、請求項4と同様な効果が得ら
れる。
According to the first aspect of the present invention, it is not necessary to provide a base reinforcing bar at the bottom in the footing portion forming portion of the pile foundation portion forming portion, and the bottom portion is formed in the underground beam portion forming portion. It is not necessary to perform the work of placing a thin concrete layer on the ground and the complicated work of assembling the underground beam by temporarily installing the underground beam reinforced cradles, temporary passages, temporary elevating stairs, etc. The work of making the pile foundation and underground beam can be easily performed. According to the second aspect, in the underground beam portion forming portion, the work of casting a thin concrete layer on the bottom, the temporary installation of the underground beam reinforcing bar support, the temporary passage, the temporary elevating stairs, etc., to assemble the underground beam. Since it is not necessary to perform a simple operation, the operation of forming the underground beam as a foundation can be facilitated as compared with the related art. According to the third aspect, since the base reinforcing bar does not need to be provided at the bottom in the footing portion forming portion of the pile foundation portion forming portion, the work of creating the pile foundation portion as the foundation can be facilitated as compared with the related art. According to claim 4,
In addition to the effects of the first, second, and third aspects, in the excavation work of the pile foundation portion forming portion and the underground beam portion forming portion, the ground where the ground surface covering layer is not provided is excavated along the ground surface covering layer. By simply doing, it can be done easily and accurately, and the pile foundation part forming part, underground beam part forming part functions as a formwork as it is, and it is not necessary to perform backfilling work,
The work becomes easier than before. In addition, the reference line can be moved onto the ground surface coating layer, and based on this transferred reference line, the construction can be performed while checking the position of the foundation accurately. In addition, it is possible to increase the positional accuracy of a position where a foundation is provided such as an underground beam. According to the fifth aspect, even if the ground is a ground without independence, the pile foundation part forming part and the underground beam part forming part can function as they are as the formwork. The effect is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 1 is a process chart for explaining a method for creating a foundation of a building according to a first embodiment of the present invention.

【図2】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 2 is a process chart for explaining a method of forming a foundation of a building according to the first embodiment of the present invention.

【図3】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 3 is a process chart for explaining a method of creating a foundation of a building according to the first embodiment of the present invention.

【図4】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 4 is a process chart for explaining a method for creating a foundation of a building according to the first embodiment of the present invention.

【図5】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 5 is a process chart for explaining a method of creating a foundation of a building according to the first embodiment of the present invention.

【図6】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 6 is a process chart for explaining a method of creating a foundation of a building according to the first embodiment of the present invention.

【図7】 図6の詳細を示す図である。FIG. 7 is a diagram showing details of FIG. 6;

【図8】 この発明の実施の形態1による建築物の基礎
の作成方法を説明するための工程図である。
FIG. 8 is a process chart for explaining a method of creating a building foundation according to the first embodiment of the present invention.

【図9】 従来の建築物の基礎の作成方法の一例を説明
するための工程図である。
FIG. 9 is a process chart for explaining an example of a conventional method of creating a foundation of a building.

【図10】 従来の建築物の基礎の作成方法の一例を説
明するための工程図である。
FIG. 10 is a process chart for explaining an example of a conventional method of creating a foundation of a building.

【図11】 従来の建築物の基礎の作成方法の一例を説
明するための工程図である。
FIG. 11 is a process chart for explaining an example of a conventional method of creating a foundation of a building.

【図12】 従来の建築物の基礎の作成方法の一例を説
明するための工程図である。
FIG. 12 is a process chart for explaining an example of a conventional method for creating a foundation of a building.

【図13】 従来の建築物の基礎の作成方法の一例を説
明するための工程図である。
FIG. 13 is a process chart for explaining an example of a conventional method of creating a foundation of a building.

【図14】 従来の建築物の基礎の作成方法の一例を説
明するための工程図である。
FIG. 14 is a process chart for explaining an example of a conventional method for creating a foundation of a building.

【符号の説明】[Explanation of symbols]

1 地盤、2x 杭主筋、10A 地中梁、23 杭基
礎部形成部分(基礎形成部分)、23A 杭形成部分
(基礎形成部分)、23B フーチング部形成部分(基
礎形成部分)、24 地中梁部形成部分(基礎形成部
分)、1A 基礎形成部分に対応する地盤表面を除いた
地盤表面、13 地盤表面被覆層。
1 ground, 2x pile main bar, 10A underground beam, 23 pile foundation part (foundation part), 23A pile formation part (foundation part), 23B footing part formation part (foundation part), 24 underground beam part Forming part (base forming part), 1A Ground surface excluding the ground surface corresponding to the base forming part, 13 Ground surface coating layer.

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 地盤を掘削して、建築物の基礎としての
杭基礎部及び地中梁部を形成するための杭基礎部形成部
分及びこの杭基礎部形成部分と連続する地中梁部形成部
分を形成し、これら杭基礎部形成部分及び地中梁部形成
部分にコンクリートを打設して建築物の基礎を作成する
方法において、 上記杭基礎部形成部分に設けられる杭主筋を柱の主筋と
して用いることにより、上記杭基礎部形成部分の底部に
ベース配筋を設けずに、当該杭基礎部形成部分にコンク
リートを打設するとともに、上記地中梁部形成部分に配
設される地中梁構体の底部が上記地中梁成形部分の底面
より離反するように、当該地中梁構体を保持した状態
で、当該地中梁形成部分にコンクリートを打設して建築
物の基礎を作成するようにしたことを特徴とする建築物
の基礎の作成方法。
1. A pile foundation forming part for excavating the ground to form a pile foundation and an underground beam as a foundation of a building, and an underground beam forming part continuous with the pile foundation forming part. Forming a part, and placing concrete in the pile foundation part forming part and the underground beam part forming part to form a foundation of the building. By using as a base, without providing a base reinforcing bar at the bottom of the pile foundation portion forming portion, concrete is poured into the pile foundation portion forming portion, and an underground While holding the underground beam structure, concrete is poured into the underground beam forming portion to create a foundation for the building so that the bottom of the beam structure is separated from the bottom surface of the underground beam forming portion. Of a building characterized by How to create.
【請求項2】 地盤を掘削して、建築物の基礎としての
杭基礎部及び地中梁部を形成するための杭基礎部形成部
分及びこの杭基礎部形成部分と連続する地中梁部形成部
分を形成し、これら杭基礎部形成部分及び地中梁部形成
部分にコンクリートを打設して建築物の基礎を作成する
方法において、 上記地中梁部形成部分に配設される地中梁構体の底部が
上記地中梁成形部分の底面より離反するように、当該地
中梁構体を保持した状態で、当該地中梁形成部分にコン
クリートを打設して建築物の基礎を作成するようにした
ことを特徴とする建築物の基礎の作成方法。
2. A pile foundation portion for excavating the ground to form a pile foundation portion and an underground beam portion as a foundation of a building, and an underground beam portion continuous with the pile foundation portion forming portion. Forming a part, and placing concrete in the pile foundation part forming part and the underground beam forming part to create a foundation of the building; While holding the underground beam structure so that the bottom of the structure is separated from the bottom surface of the underground beam forming part, concrete is poured into the underground beam forming part to form the foundation of the building. A method of creating a foundation for a building, characterized in that:
【請求項3】 地盤を掘削して、建築物の基礎としての
杭基礎部を形成するための杭基礎部形成部分を形成し、
この杭基礎部形成部分にコンクリートを打設して建築物
の基礎を作成する方法において、 上記杭基礎部形成部分に設けられる杭主筋を柱の主筋と
して用いることにより、上記杭基礎部形成部分の底部に
ベース配筋を設けずに、当該杭基礎部形成部分にコンク
リートを打設して建築物の基礎を作成するようにしたこ
とを特徴とする建築物の基礎の作成方法。
3. Excavating the ground to form a pile foundation forming portion for forming a pile foundation as a foundation of a building;
In the method of casting concrete on the pile foundation portion forming part to create a foundation of a building, the pile main reinforcing bar provided on the pile foundation forming portion is used as the main reinforcing bar of the column, thereby forming the pile foundation forming portion. A method for producing a foundation for a building, wherein concrete is poured into the portion where the pile foundation is formed without forming a base reinforcing bar at the bottom to create a foundation for the building.
【請求項4】 上記杭基礎部形成部分や地中梁部形成部
分は、杭基礎部形成部分や地中梁部形成部分に対応する
地盤表面を除いた地盤表面上に予めコンクリートなどに
よる地盤表面被覆層を設けた後に、当該地盤表面被覆層
が設けられていない部分の地盤を掘削して形成するよう
にしたことを特徴とする請求項1または請求項2または
請求項3に記載の建築物の基礎の作成方法。
4. The pile foundation portion and the underground beam portion are formed on the ground surface excluding the ground surface corresponding to the pile foundation portion and the underground beam portion by a concrete surface or the like in advance. 4. The building according to claim 1, wherein, after the covering layer is provided, a portion of the ground where the ground surface covering layer is not provided is formed by excavation. 5. How to create a foundation for
【請求項5】 少なくとも上記杭基礎形成部分、地中梁
形成部分に対応する部分の地盤を改良した後に、上記杭
基礎形成部分、地中梁形成部分を形成するようにしたこ
とを特徴とする請求項4に記載の建築物の基礎の作成方
法。
5. The pile foundation forming part and the underground beam forming part are formed after at least the ground corresponding to the pile foundation forming part and the underground beam forming part is improved. A method for creating a foundation for a building according to claim 4.
JP10314543A 1998-11-05 1998-11-05 Foundation forming method for building Pending JP2000144762A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10314543A JP2000144762A (en) 1998-11-05 1998-11-05 Foundation forming method for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10314543A JP2000144762A (en) 1998-11-05 1998-11-05 Foundation forming method for building

Publications (1)

Publication Number Publication Date
JP2000144762A true JP2000144762A (en) 2000-05-26

Family

ID=18054566

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10314543A Pending JP2000144762A (en) 1998-11-05 1998-11-05 Foundation forming method for building

Country Status (1)

Country Link
JP (1) JP2000144762A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433891A (en) * 2011-08-31 2012-05-02 福州市第三建筑工程公司 Basement construction method and plug type bearing platform structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433891A (en) * 2011-08-31 2012-05-02 福州市第三建筑工程公司 Basement construction method and plug type bearing platform structure
CN102433891B (en) * 2011-08-31 2013-09-11 福州市第三建筑工程公司 Basement construction method and plug type bearing platform structure

Similar Documents

Publication Publication Date Title
JP4611113B2 (en) Integrated construction method of pile and column
KR100383268B1 (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
JP5480744B2 (en) Foundation for structure and its construction method
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JP2000144757A (en) Preparation of foundation for building
JP2000144762A (en) Foundation forming method for building
JP2000144756A (en) Preparation of foundation for building
JP3587479B2 (en) Construction method of pile of underground structure using PC member for underground wall
JPH10299003A (en) Foundation work using precast concrete member
JP2002021096A (en) Building and constructing method therefor
JP3790310B2 (en) Construction method of the building by the prior construction of steel frame
JP2001164559A (en) Construction method of continuous underground wall guide wall making use of l-type precast member
JPH03199528A (en) Steel frame foundation of construction
JPH08291526A (en) Construction method for underground structure
JP3567387B2 (en) How to build an underground skeleton
JPH0517955A (en) Execution method for direct foundation and form panel for direct foundation
KR100694762B1 (en) Method for constructing underground slabs and walls without preliminary wall-attached supports
JP2620035B2 (en) Construction method and structure of gas station office building
JPH10195886A (en) Foundation construction method
JP4399062B2 (en) Construction method of viaduct underground beam
JP2940451B2 (en) How to build underground structures
JP2004285613A (en) Construction method for building foundation
JP3105706B2 (en) Construction method of piled raft foundation using existing foundation
JP3238510B2 (en) Construction method of preceding slab floor
JPH02115419A (en) Method of constructing underground building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20051014

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070927

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080129

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20080603