JP2000104247A - Structural body and installation method thereof - Google Patents

Structural body and installation method thereof

Info

Publication number
JP2000104247A
JP2000104247A JP10274438A JP27443898A JP2000104247A JP 2000104247 A JP2000104247 A JP 2000104247A JP 10274438 A JP10274438 A JP 10274438A JP 27443898 A JP27443898 A JP 27443898A JP 2000104247 A JP2000104247 A JP 2000104247A
Authority
JP
Japan
Prior art keywords
bag material
concrete
hole
mortar
collapse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10274438A
Other languages
Japanese (ja)
Inventor
Akira Oshima
章 大島
Takeyuki Kabasawa
健幸 樺澤
Shuji Kami
上  周史
Kazuyoshi Ota
和善 太田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Concrete Industries Co Ltd
Tenox Corp
Original Assignee
Nippon Concrete Industries Co Ltd
Tenox Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Concrete Industries Co Ltd, Tenox Corp filed Critical Nippon Concrete Industries Co Ltd
Priority to JP10274438A priority Critical patent/JP2000104247A/en
Publication of JP2000104247A publication Critical patent/JP2000104247A/en
Pending legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To provide a method for installing a structural body suited to a case of constructing in the earth. SOLUTION: An excavating hole 11 is excavated in the earth, and collapse preventing liquid 12 such as bentonite muddy water for preventing the excavating hole 11 from collapsing is filled therein. A structural body forming member 13 formed by beforehand installing a reinforcing material in a bag material is inserted in the excavating hole 11. Mortar or concrete is injected in the bag material from an upper part of the bag material in a hollow state of the structural body forming member 13 by a concrete pump, etc., to install a structural body 15 in the earth.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、袋材と補強材とを
用いる構造体およびその設置方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure using a bag material and a reinforcing material and a method for installing the same.

【0002】[0002]

【従来の技術】地中にチェーンソー形の掘削装置を鉛直
または斜めに所定の深度まで挿入し、そのまま横行させ
ることにより、地中に連続溝形の孔を掘削し、この孔
(以下、掘削孔という)中に鉛直の地中連続壁を築造し
たり、河川の法面に沿って斜めに連続傾斜壁の控え護岸
を築造する工法がある。
2. Description of the Related Art A chain saw type drilling device is inserted vertically or diagonally into the ground to a predetermined depth, and is traversed as it is to drill a continuous groove-shaped hole in the ground. There is a construction method of constructing a vertical underground continuous wall, or constructing a revetment with a continuous slope wall diagonally along the slope of the river.

【0003】これらの地中連続壁や控え護岸を築造する
際は、掘削孔の崩壊を防止するため、掘削孔の上部まで
ベントナイト泥水などの泥水を満たしながら掘削する。
When constructing these underground continuous walls and retaining seawalls, excavation is performed while filling up the upper part of the excavation hole with muddy water such as bentonite to prevent collapse of the excavation hole.

【0004】その後、鉄筋などの鋼材からなる補強材を
掘削孔中に配置した後、トレミー管などを用いて掘削孔
内にコンクリートを流し込み、連続壁を築造している。
[0004] After that, a reinforcing material made of steel such as a reinforcing bar is placed in the drilling hole, and concrete is poured into the drilling hole using a tremy tube or the like to construct a continuous wall.

【0005】[0005]

【発明が解決しようとする課題】このように、地中に構
造体を築造する際は、掘削孔の崩壊防止のため泥水を使
用するので、トレミー管などによってコンクリートを打
設する際に、コンクリート中に泥水が混入し、それによ
ってコンクリートの強度が低下したり、硬化後の壁に断
面欠損が生ずるなどの問題がある。
As described above, when constructing a structure underground, muddy water is used to prevent the collapse of the excavation hole. There is a problem that muddy water is mixed into the inside, whereby the strength of the concrete is reduced, and a section of the hardened wall is lost.

【0006】本発明は、このような点に鑑みなされたも
ので、地中に構造体を築造する場合に適する構造体およ
びその設置方法を提供することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a structure suitable for building a structure underground and a method of installing the structure.

【0007】[0007]

【課題を解決するための手段】請求項1に記載された発
明は、袋材と、この袋材に内蔵された補強材と、袋材の
内部に注入されて補強材と一体化されたモルタルおよび
コンクリートのいずれか一方とを具備した構造体であ
る。
According to the first aspect of the present invention, there is provided a bag material, a reinforcing material incorporated in the bag material, and a mortar injected into the bag material and integrated with the reinforcing material. And a structure provided with any one of concrete.

【0008】これにより、袋材の内部に注入されたモル
タルおよびコンクリートのいずれか一方は、袋材の外部
からの影響を受けずに補強材と一体化されるため、強度
や形状が確保される。
Accordingly, one of the mortar and the concrete injected into the bag material is integrated with the reinforcing material without being affected by the outside of the bag material, so that the strength and shape are secured. .

【0009】請求項2に記載された発明は、地中に孔を
掘削し、この孔に、補強材が内蔵された袋材を挿入し、
この袋材の内部にモルタルおよびコンクリートのいずれ
か一方を注入する構造体の設置方法である。
According to a second aspect of the present invention, a hole is excavated in the ground, and a bag material containing a reinforcing material is inserted into the hole.
This is a method of installing a structure for injecting either mortar or concrete into the inside of the bag material.

【0010】これにより、地中に掘削された孔中で、袋
材内にモルタルおよびコンクリートのいずれか一方を注
入することにより、袋材の外部からの影響を受けない構
造体を地中に設置する。
[0010] Thus, by injecting either mortar or concrete into the bag material in the hole excavated in the ground, a structure not affected by the outside of the bag material is installed in the ground. I do.

【0011】請求項3に記載された発明は、請求項2記
載の構造体の設置方法において、地中に掘削された孔
が、この孔の崩壊を防止するための崩壊防止液で満たさ
れた構造体の設置方法である。
According to a third aspect of the present invention, in the method of installing a structure according to the second aspect, a hole excavated in the ground is filled with a collapse preventing liquid for preventing collapse of the hole. This is how to install the structure.

【0012】これにより、孔の崩壊防止液中に、補強材
が内蔵された袋材を挿入し、この袋材内にモルタルおよ
びコンクリートのいずれか一方を注入することにより、
モルタルやコンクリートを崩壊防止液中へ直接打設する
際の、崩壊防止液の混入を防止し、それらの強度の低下
を防止するとともに、硬化後の壁の断面欠損などを防止
する。
[0012] Thereby, the bag material containing the reinforcing material is inserted into the liquid for preventing collapse of the holes, and one of mortar and concrete is injected into the bag material.
When the mortar or concrete is directly poured into the anti-collapse liquid, the anti-cold liquid is prevented from being mixed, the strength of the liquid is prevented from lowering, and the cross-sectional loss of the hardened wall is prevented.

【0013】[0013]

【発明の実施の形態】以下、本発明を、図面に示された
実施の一形態を参照しながら説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to an embodiment shown in the drawings.

【0014】図1(A)に示されるように、地中に孔11
を掘削するとともに、この孔(以下、掘削孔11という)
中に、この掘削孔11の崩壊を防止するためのベントナイ
ト泥水などの崩壊防止液12を注入して満たす。
[0014] As shown in FIG.
And drill this hole (hereinafter referred to as drill hole 11)
Inside, a collapse prevention liquid 12, such as bentonite mud, for preventing the collapse of the borehole 11 is injected and filled.

【0015】掘削孔11は、チェーンソー形の掘削装置
(図示せず)を地中の所定深度まで挿入し、そのまま横
行させることにより、またはオーガスクリュー形の掘削
装置を所定ピッチ毎に横へずらしながら地中に挿入する
ことにより形成する。
The drilling hole 11 is formed by inserting a chainsaw type drilling device (not shown) to a predetermined depth in the ground and traversing it as it is, or while shifting the auger screw type drilling device laterally at a predetermined pitch. It is formed by inserting it into the ground.

【0016】このチェーンソー形またはオーガスクリュ
ー形の掘削装置は、土を掘削するとともに、その掘削孔
11中にベントナイト泥水などの崩壊防止液12を注入する
機能も有する。
This chain saw type or auger screw type excavator excavates soil and excavates the excavation hole.
It also has a function of injecting a collapse prevention liquid 12 such as bentonite muddy water into 11.

【0017】図1(B)および(C)に示されるよう
に、このベントナイト泥水などの崩壊防止液12で満たさ
れた掘削孔11中に、予め袋材に補強材を内蔵させた構造
体形成部材13を挿入する。
As shown in FIGS. 1 (B) and 1 (C), in a drilling hole 11 filled with a collapse preventing liquid 12 such as bentonite muddy water, a structure in which a reinforcing material is previously incorporated in a bag material is formed. The member 13 is inserted.

【0018】図1(D)に示されるように、コンクリー
トポンプなどから管14を経て、掘削孔11中に挿入された
構造体形成部材13の中空状態にある袋材の上部より、袋
材の内部にモルタルおよびコンクリートのいずれか一方
を注入して、地中に構造体15を設置する。
As shown in FIG. 1 (D), through the pipe 14 from a concrete pump or the like, the bag material in the hollow state of the structure forming member 13 inserted into the drilling hole 11 is taken out of the bag material. Either mortar or concrete is injected into the inside, and the structure 15 is installed underground.

【0019】図2(A),(B)に示されるように、モ
ルタルやコンクリートの供給を受ける構造体形成部材13
は、袋材16と、この袋材16に内蔵された補強材17とを有
している。
As shown in FIGS. 2 (A) and 2 (B), the structure forming member 13 which is supplied with mortar or concrete is provided.
Has a bag member 16 and a reinforcing member 17 built in the bag member 16.

【0020】構造体形成部材13の袋材16は、その使用目
的によって完全な止水性を有するものや、若干の透水性
を有するものなど、適時、状況に応じて最適な材料を使
用する。例えば合成樹脂フィルム、ゴムなどは止水性を
有し、布などは透水性を有する。この袋材16の上部に
は、モルタルまたはコンクリートを注入するための注入
口18が設けられている。
The bag material 16 of the structure forming member 13 is made of a material having perfect water stopping property or a material having a slight water permeability depending on the purpose of use, and is made of an optimal material according to the situation in a timely manner. For example, a synthetic resin film, rubber, and the like have water stopping properties, and a cloth and the like have water permeability. An injection port 18 for injecting mortar or concrete is provided at an upper portion of the bag material 16.

【0021】また、補強材17は、鉄筋や、鋼材などによ
り形成され、袋材16にある程度の膨らみを持たせるため
のスペーサ21が縦筋22に嵌装され、この縦筋22と横筋23
とが格子状に溶接されたものであり、この補強材17を包
込むように前記袋材16が形成されている。
The reinforcing member 17 is formed of a reinforcing bar, steel, or the like, and a spacer 21 for fitting the bag member 16 to a certain degree of swelling is fitted to the vertical bar 22.
Are welded in a lattice shape, and the bag material 16 is formed so as to enclose the reinforcing material 17.

【0022】そして、図3(A),(B)に示されるよ
うに、この袋材16の内部に、注入口18よりモルタルまた
はコンクリート24を注入して充填することにより、袋材
16を膨張させ、そのままモルタルまたはコンクリート24
を固化させて補強材17と一体化させることにより、構造
体15を形成する。モルタルまたはコンクリート24の注入
により袋材16が膨張すると、余分な崩壊防止液12は、掘
削孔11中からオーバーフローされる。
Then, as shown in FIGS. 3A and 3B, mortar or concrete 24 is injected from the injection port 18 into the inside of the bag material 16 to fill the bag material.
Inflate 16, mortar or concrete as it is 24
Is solidified and integrated with the reinforcing member 17 to form the structure 15. When the bag material 16 expands due to the injection of the mortar or the concrete 24, the excess collapse preventing liquid 12 overflows from the inside of the borehole 11.

【0023】図4に示されるように、掘削孔11は、前記
チェーンソー形の掘削装置を横行させるなどして溝状に
形成し、この掘削孔11内に複数の構造体15を、それらの
隣接する袋材16が接触するように施工することにより、
地中に連続壁を築造する。なお、ベントナイト泥水など
の崩壊防止液12中の固形分12a が、掘削孔11と、膨張し
た袋材16との隙間を埋めるように残る。
As shown in FIG. 4, the drilling hole 11 is formed in a groove shape by, for example, traversing the chainsaw drilling device, and a plurality of structures 15 are formed in the drilling hole 11 in the vicinity thereof. By constructing so that the bag material 16 to contact
Build a continuous wall underground. The solid content 12a in the collapse prevention liquid 12 such as bentonite muddy water remains so as to fill the gap between the excavation hole 11 and the expanded bag material 16.

【0024】これらの構造体15は、プレキャストコンク
リート部材と比べると、袋材16および補強材17を工場で
一体的に構成した場合であっても、軽量で施工現場まで
の運搬を容易に行える。さらに、袋材16および補強材17
をそれぞれ未完成状態で施工現場まで運搬して、施工現
場で溶接などにより完成させるようにすると、さらに運
搬しやすい利点がある。
These structures 15 are light in weight and can be easily transported to the construction site, even when the bag material 16 and the reinforcing material 17 are integrally formed in a factory, as compared with a precast concrete member. Furthermore, bag material 16 and reinforcing material 17
Is transported to the construction site in an unfinished state, and is completed at the construction site by welding or the like.

【0025】そして、掘削孔11内の崩壊防止液12中に、
この補強材17が内蔵された袋材16を挿入し、この袋材16
内にモルタルおよびコンクリート24のいずれか一方を注
入することにより、袋材16の外部にある崩壊防止液12の
影響を受けない構造体15を地中に設置できる。
Then, in the collapse prevention liquid 12 in the borehole 11,
The bag material 16 in which the reinforcing material 17 is incorporated is inserted, and the bag material 16 is inserted.
By injecting either mortar or concrete 24 into the inside, the structure 15 which is not affected by the collapse prevention liquid 12 outside the bag material 16 can be installed underground.

【0026】すなわち、モルタルやコンクリート24を崩
壊防止液12中へ直接打設した場合の、崩壊防止液12の混
入を袋材16で防止し、崩壊防止液12の混入によるモルタ
ルやコンクリート24の強度低下を防止するとともに、硬
化後の壁の断面欠損などを防止して、品質の安定した均
一な壁を築造できる。
That is, when the mortar or concrete 24 is directly poured into the anti-collapse liquid 12, the mixing of the anti-collapse liquid 12 is prevented by the bag material 16, and the strength of the mortar or concrete 24 due to the admixture of the anti-collapse liquid 12. Prevention of deterioration and prevention of cross-sectional loss of the cured wall can be achieved, and a uniform wall with stable quality can be constructed.

【0027】また、袋材16内に鉄筋や鋼材などで形成し
た補強材17を任意に配置できる。さらに、袋材16の横断
方向に補強材を兼ねたパイプを貫通させて配置すること
で、必要な量の背面水を抜くことが可能な、いわゆる透
水壁にも応用できる。
Further, a reinforcing member 17 formed of a reinforcing bar, a steel material, or the like can be arbitrarily arranged in the bag member 16. Further, by arranging a pipe which also serves as a reinforcing material in the transverse direction of the bag material 16 so as to penetrate the bag material, the present invention can be applied to a so-called water-permeable wall which can drain a necessary amount of back water.

【0028】なお、図示された実施形態の構造体15は、
地中に止水壁などの地中鉛直壁を連続的に築造する適用
例であるが、これに限定されるものではなく、河川の法
面に沿って斜めに控え護岸を築造するなどの地中傾斜壁
を連続的に築造する場合にも同様に適用できる。
The structure 15 of the illustrated embodiment is
This is an example of continuous application of underground vertical walls such as water barriers underground.However, the invention is not limited to this, and it is possible to construct dikes along slopes of rivers. The same can be applied to the case where the middle inclined wall is continuously constructed.

【0029】さらには、この構造体15は、地中連続壁の
一側を掘削することで、土留め壁または擁壁などの、大
気や水にも面する壁体を築造する場合にも適用可能であ
る。
Furthermore, this structure 15 is also applicable to a case where a wall facing the atmosphere or water, such as a retaining wall or a retaining wall, is constructed by excavating one side of an underground continuous wall. It is possible.

【0030】その上、この構造体15は、壁体のみに限ら
ず、地中などに柱体を設置する場合にも適用できる。そ
の場合は、補強材は、プレキャストコンクリート柱と同
様のかご形に形成するとよい。
In addition, the structure 15 can be applied not only to a wall but also to a case where a pillar is installed in the ground. In that case, the reinforcing material may be formed in the same cage shape as the precast concrete column.

【0031】[0031]

【発明の効果】請求項1記載の発明によれば、袋材の内
部に注入されたモルタルおよびコンクリートのいずれか
一方は、袋材の外部からの影響を受けずに補強材と一体
化されるため、現場施工で地中に築造する場合にも安定
した強度や形状を確保できる構造体を提供できる。
According to the first aspect of the present invention, one of the mortar and concrete poured into the bag material is integrated with the reinforcing material without being affected by the outside of the bag material. Therefore, it is possible to provide a structure capable of securing stable strength and shape even when building underground by on-site construction.

【0032】請求項2記載の発明によれば、地中に掘削
された孔に、補強材が内蔵された袋材を挿入し、この袋
材の内部にモルタルおよびコンクリートのいずれか一方
を注入するから、地中に掘削された孔内に直接モルタル
やコンクリートを注入する場合に比べて、孔内土壌など
の影響を受けない構造体を地中に設置できる。また、袋
材に補強材を内蔵しただけの軽量な状態のまま施工現場
まで運搬して、孔中で袋材内にコンクリートなどを注入
して構造体を完成させるので、運搬性が良いなどの現場
施工の利点も有する。
According to the second aspect of the present invention, a bag material containing a reinforcing material is inserted into a hole excavated in the ground, and one of mortar and concrete is injected into the inside of the bag material. Therefore, compared to a case where mortar or concrete is directly injected into a hole excavated in the ground, a structure that is not affected by soil in the hole can be installed in the ground. In addition, since it is transported to the construction site in a lightweight state with only built-in reinforcing material in the bag material, concrete is injected into the bag material in the hole and the structure is completed, so the transportability is good. It also has the advantage of on-site construction.

【0033】請求項3記載の発明によれば、地中に掘削
された孔が、この孔の崩壊を防止するための崩壊防止液
で満たされた状態で、この崩壊防止液中に、補強材が内
蔵された袋材を挿入し、この袋材内にモルタルおよびコ
ンクリートのいずれか一方を注入することにより、モル
タルやコンクリートを崩壊防止液中へ直接打設する際に
生ずる崩壊防止液の混入を防止し、モルタルやコンクリ
ートの強度低下を防止できるとともに、硬化後の壁の断
面欠損などを防止できる。
According to the third aspect of the present invention, the hole excavated in the ground is filled with the anti-collapse liquid for preventing collapse of the hole, and the reinforcing material is contained in the anti-collapse liquid. By inserting a bag material with a built-in, and injecting either mortar or concrete into this bag material, the mixing of the mortar or concrete that occurs when the mortar or concrete is directly poured into the crush prevention liquid is prevented. This can prevent the mortar and concrete from decreasing in strength, and can also prevent the cross-section of the cured wall from being lost.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る構造体の設置方法の実施の一形態
を示す説明図であり、(A)は掘削孔中に崩壊防止液が
満たされた状態を示す断面図、(B)はその掘削孔中に
構造体形成部材が挿入される途中の状態を示す断面図、
(C)はその掘削孔中に構造体形成部材が完全に挿入さ
れた状態を示す断面図、(D)はその構造体形成部材の
袋材内にコンクリートなどが注入されて構造体が形成さ
れた状態を示す断面図である。
FIG. 1 is an explanatory view showing an embodiment of a method for installing a structure according to the present invention, in which (A) is a cross-sectional view showing a state in which a collapse prevention liquid is filled in an excavation hole, and (B) is a sectional view. Sectional view showing a state in which a structure forming member is being inserted into the borehole,
(C) is a cross-sectional view showing a state where the structure forming member is completely inserted into the excavation hole, and (D) is a structure formed by injecting concrete or the like into the bag material of the structure forming member. FIG. 4 is a cross-sectional view showing a state in which the cover is folded.

【図2】(A)は同上構造体の補強材および袋材を示す
水平断面図、(B)はその垂直断面図である。
FIG. 2A is a horizontal sectional view showing a reinforcing material and a bag material of the above structure, and FIG. 2B is a vertical sectional view thereof.

【図3】(A)は同上構造体の水平断面図、(B)はそ
の垂直断面図である。
FIG. 3A is a horizontal sectional view of the above structure, and FIG. 3B is a vertical sectional view thereof.

【図4】同上構造体により形成された連続壁を示す断面
図である。
FIG. 4 is a cross-sectional view showing a continuous wall formed by the above structure.

【符号の説明】[Explanation of symbols]

11 孔 12 崩壊防止液 15 構造体 16 袋材 17 補強材 24 モルタルまたはコンクリート 11 holes 12 anti-collapse liquid 15 structure 16 bag material 17 reinforcing material 24 mortar or concrete

───────────────────────────────────────────────────── フロントページの続き (72)発明者 樺澤 健幸 東京都港区港南一丁目8番27号 日本コン クリート工業株式会社内 (72)発明者 上 周史 東京都港区赤坂六丁目13番7号 株式会社 テノックス内 (72)発明者 太田 和善 東京都港区赤坂六丁目13番7号 株式会社 テノックス内 Fターム(参考) 2D018 DA01 2D049 EA01 EA02 EA03 EA15 GA03 GB10 GD01 GE00 GE06  ──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Takeyuki Kabazawa 1-27-27 Konan, Minato-ku, Tokyo Inside Japan Concrete Industry Co., Ltd. No. 7 Tenox Co., Ltd. (72) Inventor Kazuyoshi Ota 6-13-7 Akasaka, Minato-ku, Tokyo F-term in Tenox Co., Ltd. (Reference) 2D018 DA01 2D049 EA01 EA02 EA03 EA15 GA03 GB10 GD01 GE00 GE06

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 袋材と、 この袋材に内蔵された補強材と、 袋材の内部に注入されて補強材と一体化されたモルタル
およびコンクリートのいずれか一方とを具備したことを
特徴とする構造体。
1. A bag material, a reinforcing material incorporated in the bag material, and one of mortar and concrete injected into the bag material and integrated with the reinforcing material. The structure to do.
【請求項2】 地中に孔を掘削し、 この孔に、補強材が内蔵された袋材を挿入し、 この袋材の内部にモルタルおよびコンクリートのいずれ
か一方を注入することを特徴とする構造体の設置方法。
2. A hole is excavated in the ground, a bag material containing a reinforcing material is inserted into the hole, and one of mortar and concrete is injected into the inside of the bag material. How to install the structure.
【請求項3】 地中に掘削された孔は、この孔の崩壊を
防止するための崩壊防止液で満たされたことを特徴とす
る請求項2記載の構造体の設置方法。
3. The method according to claim 2, wherein the hole excavated in the ground is filled with a collapse preventing liquid for preventing collapse of the hole.
JP10274438A 1998-09-29 1998-09-29 Structural body and installation method thereof Pending JP2000104247A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10274438A JP2000104247A (en) 1998-09-29 1998-09-29 Structural body and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10274438A JP2000104247A (en) 1998-09-29 1998-09-29 Structural body and installation method thereof

Publications (1)

Publication Number Publication Date
JP2000104247A true JP2000104247A (en) 2000-04-11

Family

ID=17541690

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10274438A Pending JP2000104247A (en) 1998-09-29 1998-09-29 Structural body and installation method thereof

Country Status (1)

Country Link
JP (1) JP2000104247A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010077593A (en) * 2008-09-24 2010-04-08 Chemical Grouting Co Ltd Method for constructing underground wall-like body
WO2014073078A1 (en) * 2012-11-08 2014-05-15 朝日エンヂニヤリング株式会社 Construction method for foundation pile
JP2014105560A (en) * 2012-11-29 2014-06-09 Hayashi Bussan Co Ltd Structure of underground wall, and method for configuring the same

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010077593A (en) * 2008-09-24 2010-04-08 Chemical Grouting Co Ltd Method for constructing underground wall-like body
WO2014073078A1 (en) * 2012-11-08 2014-05-15 朝日エンヂニヤリング株式会社 Construction method for foundation pile
JP5752858B2 (en) * 2012-11-08 2015-07-22 朝日エンヂニヤリング株式会社 Construction method of foundation pile
US10767333B2 (en) 2012-11-08 2020-09-08 Asahi Engineering Co., Ltd. Construction method for foundation pile
JP2014105560A (en) * 2012-11-29 2014-06-09 Hayashi Bussan Co Ltd Structure of underground wall, and method for configuring the same

Similar Documents

Publication Publication Date Title
KR100415809B1 (en) precast pile for braced wall and the method using the same
KR20180124795A (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR100375020B1 (en) a pole for mud wall and constrution method of fence for mud
KR20170000551U (en) Foundation block for retaining wall
KR200362565Y1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JP2000104247A (en) Structural body and installation method thereof
JP2007046343A (en) Liquefaction preventive construction method of ground just under existing building
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
KR100477357B1 (en) Construction method for retaining of earth
JP2000355949A (en) Reinforcing method for masonry retaining wall
KR100654973B1 (en) Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof
JP3253868B2 (en) Forming method of water passage section in continuous underground wall
JPS5936058B2 (en) How to construct a structure using underground continuous walls
WO2009139510A1 (en) Construction method for continuous cut-off wall using overlap casing
JPS6011178B2 (en) How to install standard piles for continuous underground wall construction
JP2874906B2 (en) Shaft construction method
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
JP2012237159A (en) Pile construction method
JP4274898B2 (en) Groundwater flow conservation method
JP2764482B2 (en) Construction method of large depth human hole
JP2524579B2 (en) Reinforcement method of existing retaining wall under water surface
KR20030091836A (en) A Continuous and Cut Off wall And Foundation Method By Overlap Casing
JPH09125347A (en) Building method of dam
JPH06240656A (en) Restoration of underground water
JP3608175B2 (en) Yamadome method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050921

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070704

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20071031