GB270041A - Improvements in and relating to concrete linings for shafts, wells and other shaft-like structures - Google Patents
Improvements in and relating to concrete linings for shafts, wells and other shaft-like structuresInfo
- Publication number
- GB270041A GB270041A GB579526A GB579526A GB270041A GB 270041 A GB270041 A GB 270041A GB 579526 A GB579526 A GB 579526A GB 579526 A GB579526 A GB 579526A GB 270041 A GB270041 A GB 270041A
- Authority
- GB
- United Kingdom
- Prior art keywords
- concrete
- bars
- sheeting
- garland
- shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 235000000396 iron Nutrition 0.000 abstract 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract 4
- 230000002787 reinforcement Effects 0.000 abstract 4
- 238000009416 shuttering Methods 0.000 abstract 4
- 239000004568 cement Substances 0.000 abstract 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract 3
- 241000251468 Actinopterygii Species 0.000 abstract 2
- 238000012856 packing Methods 0.000 abstract 2
- 229910000831 Steel Inorganic materials 0.000 abstract 1
- 238000009412 basement excavation Methods 0.000 abstract 1
- 239000011449 brick Substances 0.000 abstract 1
- 238000011065 in-situ storage Methods 0.000 abstract 1
- 229910052742 iron Inorganic materials 0.000 abstract 1
- 239000007788 liquid Substances 0.000 abstract 1
- 239000004576 sand Substances 0.000 abstract 1
- 239000010959 steel Substances 0.000 abstract 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/04—Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Revetment (AREA)
Abstract
270,041. Blandford, T., and Gee, A. March 2, 1926. Shafts and wells.-A concrete lining for shafts, wells, and other shaft-like structures comprises a body of concrete cast in situ in contact with a back sheeting adjacent the ground and reinforcements, wholly embedded in the concrete, spaced from the back sheeting and unconnected thereto. The reinforcement may be arranged only in the half or third of the thickness of the concrete remote from the back sheeting. As excavation proceeds, corrugated iron sheets 1 are placed against the ground and held by iron rings 3 and wedges 4, lower rings 3 being supported from upper rings by hooks 5. After a desired depth is reached, a water garland 6 is built round the bottom of the sheeting 1, the garland comprising a wooden ring carrying a vertical iron ring; pipes 7 remove the water from the garland'. A wedge 8 is then cut out of the ground and a timber packing 9 laid on the shaft bottom. A steel base ring 10 is laid on the packing 9 and vertical angle irons 12 are placed in pockets in the ring 10, aligned angle irons 12 being connected by fish plates. Circumferential reinforcements 13 are threaded through apertures in the angle irons 12 and their ends are connected by a wired lap joint. Bars 18 on the rings 3, clamps 17 bolted to the angle irons 12 and engaging the bars 18, and lacing bars 19, secured to the bars 18, form temporary supports for the reinforcements 12, 13. Shuttering 16 is then built on the base ring 10 which is further provided with a footing of sand. Concrete is then filled in up to the garland 6, and after this concrete has set, broken brick covered with thick cement is filled in between the garland 6 and the corrugated sheeting 1. Further shuttering 16 is then erected and concreting continued in desired steps, the rings 3. wedges 4, bars 18, clamps 17, and lacing bars 19 being removed as the concreting is effected. On reaching the bottom of the previously finished portion of the lining, overlapping shuttering is provided to make the joint, and one or more pipes are passed through the shuttering and sheeting at 1 at this part; concreting is then completed and when the concrete has set, liquid cement is forced through the pipes 7 till all flow of water through the upper pipes has ceased ; after further setting, further cement may be injected at high pressure and the pipe 7 temporarily sealed. A further length of shaft is then excavated and lined, angle irons 12 of adjacent lengths being connected by fish plates. At intervals, permanent garlands 20 are provided, the shaft being widened at these points to give a uniform thickness of lining.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB579526A GB270041A (en) | 1926-03-02 | 1926-03-02 | Improvements in and relating to concrete linings for shafts, wells and other shaft-like structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB579526A GB270041A (en) | 1926-03-02 | 1926-03-02 | Improvements in and relating to concrete linings for shafts, wells and other shaft-like structures |
Publications (1)
Publication Number | Publication Date |
---|---|
GB270041A true GB270041A (en) | 1927-05-05 |
Family
ID=9802755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB579526A Expired GB270041A (en) | 1926-03-02 | 1926-03-02 | Improvements in and relating to concrete linings for shafts, wells and other shaft-like structures |
Country Status (1)
Country | Link |
---|---|
GB (1) | GB270041A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110094206A (en) * | 2019-05-08 | 2019-08-06 | 南方电网调峰调频发电有限公司 | A kind of vertical shaft tunnel concrete liner structure and method |
US11512591B2 (en) * | 2018-11-14 | 2022-11-29 | Redpath Deilmann Gmbh | Shuttering with supporting ring having expendable drawers |
CN115961973A (en) * | 2022-07-15 | 2023-04-14 | 中交一公局集团有限公司 | Tunnel lining trolley and tunnel construction method |
-
1926
- 1926-03-02 GB GB579526A patent/GB270041A/en not_active Expired
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11512591B2 (en) * | 2018-11-14 | 2022-11-29 | Redpath Deilmann Gmbh | Shuttering with supporting ring having expendable drawers |
CN110094206A (en) * | 2019-05-08 | 2019-08-06 | 南方电网调峰调频发电有限公司 | A kind of vertical shaft tunnel concrete liner structure and method |
CN115961973A (en) * | 2022-07-15 | 2023-04-14 | 中交一公局集团有限公司 | Tunnel lining trolley and tunnel construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3754066A (en) | Method of coating or lining a structural surface | |
CN109235493A (en) | Basement beam slab is backbreak and short formwork construction method in a kind of contrary sequence method | |
CN107268634A (en) | Deep basal pit waist rail construction typified form system | |
CN108330902B (en) | Construction method for cast-in-situ lower cross beam of high-pile wharf | |
CN107859039A (en) | A kind of temperature difference control of coal mill foundations mass concrete and detection method | |
GB270041A (en) | Improvements in and relating to concrete linings for shafts, wells and other shaft-like structures | |
US3221457A (en) | Monolithic wall slab and method of constructing same | |
CN107460873B (en) | Manual digging pile construction method | |
CN106703815B (en) | Abutment construction method in excavation | |
US1063672A (en) | Process of constructing sewers, aqueducts, &c. | |
GB732494A (en) | Improvements in or relating to concrete and the like piles | |
GB511080A (en) | Improvements relating to the construction of tunnels | |
US1353274A (en) | Tunnel construction | |
US1167159A (en) | Construction of concrete sewers, aqueducts, &c. | |
RU2671019C1 (en) | Method of establishing a standard foundation using ribbed slabs of ceilings (coverings) | |
CN207062956U (en) | A kind of deep basal pit waist rail construction typified form system | |
US1969229A (en) | Apparatus for forming concrete structures | |
US1539033A (en) | Method of and means for reenforcing wall foundations | |
US2341518A (en) | Grouting system | |
RU2647521C1 (en) | Method of manufacture of continuous plate foundations of box section from ribbed plates of overlapping | |
GB302101A (en) | Process of constructing reinforced and not reinforced concrete structures under water | |
US2338110A (en) | Graving dry dock and method of construction | |
CN106869134A (en) | Base plate for the base pit engineering for having subregion stake connects method | |
US2337378A (en) | Method of making piers | |
US2178916A (en) | Dam construction |