GB2192419A - Method of producing a pile or a diaphragm wall - Google Patents
Method of producing a pile or a diaphragm wall Download PDFInfo
- Publication number
- GB2192419A GB2192419A GB08616799A GB8616799A GB2192419A GB 2192419 A GB2192419 A GB 2192419A GB 08616799 A GB08616799 A GB 08616799A GB 8616799 A GB8616799 A GB 8616799A GB 2192419 A GB2192419 A GB 2192419A
- Authority
- GB
- United Kingdom
- Prior art keywords
- pipe
- pile
- displacing
- pile shoe
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/32—Prefabricated piles with arrangements for setting or assisting in setting in position by fluid jets
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
A pile shoe (2) or a diaphragm wall footing fixed to the bottom of a reinforcing cage (1), and having a grouting pipe (3) and a displacing pipe (4) extending therethrough is placed into a bore (5). Water under pressure is then made to flow through the grouting pipe (3) to flush loose soil below the pile shoe (2) and to form slurry (51) which is then discharged to the ground level through the displacing pipe (4). Concrete (81) is then grouted into the reinforcing cage (1) and allowed to set, whereafter grout (52) and/or soil stabilizing agent is forced into the space around and below the pile shoe (2) or diaphragm wall footing to stabilize and strengthen the foundation. The cage (10) may be encased by a waterproof membrane (21) to prevent ingress of slurry (51). <IMAGE>
Description
SPECIFICATION
Slurry displacement and soil stabilization method for pile foundation
This invention relates to construction of castin-place concrete pile or diaphragm wall, particularly a method to flush and displace soil at the bottom of file foundation, and to fill grout and soil stabilizing agent after concrete grouting and setting of concrete in order to stabilize pile foundation.
Generally, foundation engineering is a key to support a building firmly. Conventionally, pile or diaphragm wall is constructed directly, a considerable quantity of slurry may accumulate in the bottom of pile bore or well, and it can't be displaced completely after grouting for making cast-in-piace concrete pile. The soil for support the pile is always loosen during boring process. Therefore stabilization of pile foundation is always not satisfactorily.
Conventionally, slurry in the bottom of pile bore or well is pumped out directly or displaced by concrete grouted to the bottom directly. However, dense slurry and loose soil at the bottom can't be removed by the conventionaly method, and then, pile foundation or diaphragm wall does not stand on satisfactorily stabilized ground, sinking may occur and safety of construction works is affected.
The present invention relates to a slurry displacement and soil stabilization method for pile foundation applicable to cast-in-place pile and diaphragm wall construction. It uses a pile shoe or a diaphragm wall footing fixed to the bottom of a reinaforcing cage, grouting pipe and displacing pipe penetration into the pile shoe or footing located in the bottom of a bored well, and high pressure water to flush soil below the pile shoe or footing to form slurry which is then discharged to ground level through the-ldisplacing pipe before grouting of concrete. After setting of the concrete, grout and/or soil stabilizing agent are filled to space around and below the pile shoe to stabilize the ground in order to increase loading capacity of the pile foundation or diaphragm wall, and to prevent from sinking.
Therefore, the main objective of the present invention isto provide an effective method for slurry displacement and soil stabilization which displace slurry and loss in the bottom of bored well both in the middle and corners of the well.
Another objective of the present invention is tb stabilize ground, increase loading capacity and prevent from sinking by filling grout and soil stabilizing agent after grouting.
Embodiments-of the invention are described by way of example, with reference to the drawings, in which:
Figure 1 is a sectional view illustrating application ofthe present invention In a bored well, the first embodiment according to the present invention;
Figure 2 illustrates connection of the grouting pipe and displacing pipe to the pile shoe in the first embodiment;
Figure 3 is a sectional view illustration application of the present invention with a pipe for both grouting and displacing for pile shoe of different pile shoe, the second embodiment according to the present invention, in which the manifolds are shown in perspective view;
Figure 4 illustrates the third embodiment according to the present invention;
Figure 5 is a sectional view illustrating working with the first embodiment according to the present invention; and
Figure 6 is a sectional view illustrating result of application of the first embodiment in a bored well.
Please refer to Figure 1, a sectional view of application of an embodiment in a bored well according to the present invention. The present invention involves Fixing of a pile shoe (2) to the-bottom of a reinforcing cage (1).
The pile shoe (2) can be a concrete structure precasted at the bottom of the reinforcing cage (1). During the precasting process, the lower manifold (32) of a grouting pipe (3) and the lower manifold (42) of a displacing pipe (4) are pre-installed within the pile shoe (2) so that the grouting pipe (3) and the displacing pipe (4) can penetrate into the pile shoe and connect to each other through some holes at the bottom of the pile shoe as shown in Figure 2. The manifolds of both the grouting and displacing pipes are distributed evenly at the bottom of the pile shoe in order to extend grouting and displacing effect.
After placing the reinforcing cage (1) with the pile shoe (2) into a bored well (5) till the pile shoe (2) has its bottom kept in touch with the ground (52), water can be filled into the ground (52) via the main pipe (31) and manifold (32) of the grouting pipe (3) and displaced to ground level through the manifold (42) and main pipe (41) of the displacing pipe (4).
In order to prevent from the flowing of slurry (51) into the reinforcing cage (1) above the pile shoe (2) through the gap between the pile shoe (2) and the bored well (5) which may affect further grouting, the reinforcing cage (1) above the pile shoe (2) are covered with water proof membrane- (21) made of PE film or other water proof material (see Figure 2).
Please refer to Figure 3, a sectional view of application of another embodiment in a bored well according to the present invention. It is different from that shown at Figure 2 in the shape of the pile shoe (2) and the way to contact with the ground, and it is an alternative choice to meet different soil condition and bore size.
In the latter embodiment, a single pipe (6) for grouting and displacing is used instead of the aforesaid grouting pipe (3) and displacing pipe (4). The pipe (6) has a main pipe (61) and a manifold (62) penetrating the pile shoe (2). During operation, water grouting and slurry displacement are done alternately.
Please refer to Figure 4, which illustrates the third embodiment according to the present invention to fist application of construction of diaphragm wall. It is different from that shown at Figure 2 in the shape of bored well (7)
reinforcing cage (1) and footing (2') for the diaphragm wall. The manifold (42) of the dis
placing pipe (4) and the- manifold (32) of the
grouting pipe (3) are distributed widely in the footing (2'), and number of main pipes (41
and 31) for the displacing pipe (4) and grout
ing pipe (3) can be increased if necessary.
Waterproof membrance is installed above the footing (2'). Please refer to Figure 5, a sec
tional view illustrating working with the first
embodiment. The grouting pipe (3) is connect
ing- a water-source so that water which flows
through the' main pipe (31), the manifold (32)
and the pipe shoe (2) is used to flush loose
soil on the ground (52) below the pile shoe
(2) in order to form slurry-,(51), which is then
discharged via the- manifold (42) at- the bottom
of the pile shoe (2) and the main pipe (41) to
the ground level. Finally, concrete (81) is
grouted through a grouting pipe (8) into the
reinforcing cage (1) above the pile shoe (2) till
the pile shoe gets contact with a predeter
mined rigid ground level. Grout and/or stabiliz
ing agent are filled by pressure grouting to the
space (9) around and below the pile shoe (2)
to improve soil condition (see Fig. 6) in order
to strengthen loading capacity of the pile and
to prevent from sinking.
For construction of diaphragm wall, the
same process of flushing slurry -displacement, grouting 'and soil improvement is applicable to
meet the'thigh loading capacity as required by
diaphragm wall and to prevent from sinking.
Claims (4)
1. A slurry displacement and. soil stabiliza
tion method for pile foundation by using of a
pile shoe or a diaphragm wall footing fixed to
the bottom of a reinforcing cage, a grouting
pipe and- a displacing pipe penetrating into the
pile shoe or diaphragm wall footing placed in
a bored -well and water-to flush loose soil in
the bottom of the bored well' through the
grouting pipe and displacing fipe to form
slurry which is then discharged to ground level
through the displacing pipe before concrete is
grouted into the reinforcing cage above the
pile shoe; and filling of-grout and soil stabiliz
ing agent to space around and below the pile
shoe after setting of concrete in order to
strengthen the foundation to increase loading
capacity and to prevent from sinking
2.A slurry displacement and soil stabiliza
tion method for pile foundation as claimed in
Claim 1 wherein a plurality of manifolds are distributed evenly at the bottom of the pile shoe or diaphragm wall footing, a half of the manifolds are connecting to a grouting pipe, and another half of the manifolds are connecting to a displacing pipe in order to increase contact of the grouting pipe and the displacing pipe to the ground for improving grouting and displacing effect.
3. A slurry displacement and soil stabilization method for pile foundation as claimed in
C!aim 1 wherein a plurality of manifolds -are distributed evenly at the bottom of the pile shoe or diaphragm wall footing and the manifolds are connecting to a pipe for grouting and displacing alternately.
4. A slurry displacement and soil stabiltzation method for pile foundation as claimed in
Claim 1 wherein the reinforcing cage above the pile shoe is covered with waterproof membrane to prevent from flow of slurry into the reinforcing cage through the gap between the pile shoe and the reinforcing cage.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB08616799A GB2192419A (en) | 1986-07-10 | 1986-07-10 | Method of producing a pile or a diaphragm wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB08616799A GB2192419A (en) | 1986-07-10 | 1986-07-10 | Method of producing a pile or a diaphragm wall |
Publications (2)
Publication Number | Publication Date |
---|---|
GB8616799D0 GB8616799D0 (en) | 1986-08-20 |
GB2192419A true GB2192419A (en) | 1988-01-13 |
Family
ID=10600828
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
GB08616799A Withdrawn GB2192419A (en) | 1986-07-10 | 1986-07-10 | Method of producing a pile or a diaphragm wall |
Country Status (1)
Country | Link |
---|---|
GB (1) | GB2192419A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103114854A (en) * | 2013-02-18 | 2013-05-22 | 中南大学 | Pillar robbing method of reconstructed artificial stud |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115030145B (en) * | 2022-06-24 | 2023-06-30 | 广东众安建筑工程有限公司 | Wing-expanding drilling and pile-side grouting construction method for tubular pile |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB443262A (en) * | 1934-06-09 | 1936-02-25 | Giovanni Rodio | Improvements in and relating to methods for manufacturing concrete piles |
GB669661A (en) * | 1949-08-12 | 1952-04-09 | Harold Franklin Rosevear | Improvements relating to concrete piles |
GB1556030A (en) * | 1975-11-11 | 1979-11-14 | Fondedile Spa | Process for providing a foundation pile and to a reinforcing insert for use in the process |
GB2088450A (en) * | 1980-11-19 | 1982-06-09 | Nevo Alex | Grouting piles |
GB2157750A (en) * | 1984-04-19 | 1985-10-30 | Juei Jse Lin | Improvements relating to cast-in-situ concrete pile construction |
-
1986
- 1986-07-10 GB GB08616799A patent/GB2192419A/en not_active Withdrawn
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB443262A (en) * | 1934-06-09 | 1936-02-25 | Giovanni Rodio | Improvements in and relating to methods for manufacturing concrete piles |
GB669661A (en) * | 1949-08-12 | 1952-04-09 | Harold Franklin Rosevear | Improvements relating to concrete piles |
GB1556030A (en) * | 1975-11-11 | 1979-11-14 | Fondedile Spa | Process for providing a foundation pile and to a reinforcing insert for use in the process |
GB2088450A (en) * | 1980-11-19 | 1982-06-09 | Nevo Alex | Grouting piles |
GB2157750A (en) * | 1984-04-19 | 1985-10-30 | Juei Jse Lin | Improvements relating to cast-in-situ concrete pile construction |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103114854A (en) * | 2013-02-18 | 2013-05-22 | 中南大学 | Pillar robbing method of reconstructed artificial stud |
Also Published As
Publication number | Publication date |
---|---|
GB8616799D0 (en) | 1986-08-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105155551B (en) | Pressure compensation type foundation pit supporting structure and construction method | |
CN108612111B (en) | Steel pipe pile, foundation pit support structure and construction method of foundation pit support structure | |
CS238291B1 (en) | Compacted deep foundation and method and equipment for its construction | |
US2923133A (en) | Method for making pile structures with concrete casings | |
CN109505641A (en) | A kind of soft-rock tunnel bottom plate anchor pouring reinforcement method | |
CA1185441A (en) | Process of forming a continuous wall in the ground | |
JP3918461B2 (en) | Construction method for underwater foundation | |
GB2192419A (en) | Method of producing a pile or a diaphragm wall | |
CN216194845U (en) | Pebble covering layer steel sheet pile cofferdam system | |
US3299644A (en) | Underpinning system and method of constructing same | |
KR100381454B1 (en) | The sheet pile with water proof grouting groove and injection method of water proof grouting | |
WO2018221781A1 (en) | Pile and construction method therefor | |
CN111827097B (en) | Concatenation formula reinforced concrete bridge abutment structure | |
KR101745363B1 (en) | complex Temporary utility and its construction Method | |
CN211523179U (en) | Subway station faces integration envelope forever | |
WO2007114727A1 (en) | Soil compacting method and a device for carrying out said method | |
CN109778873B (en) | Method and device for grouting and water stopping between enclosure piles | |
RU2260654C1 (en) | Method for bored and cast-in-place pile forming along with ground compaction at hole bottom | |
RU2014392C1 (en) | Method for reinforcing foundation base | |
JPH047780B2 (en) | ||
CN214061557U (en) | Backfill miscellaneous soil composite foundation structure | |
RU2059044C1 (en) | Method for compacting dispersed soils | |
JP2662579B2 (en) | Impermeable wall and method of constructing the same | |
JP2005030132A (en) | Underwater foundation structure and underwater foundation construction method | |
RU55796U1 (en) | DEVICE FOR SOIL SEALING AND SOIL BASIS WITH TECHNOGENIC FRAME |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WAP | Application withdrawn, taken to be withdrawn or refused ** after publication under section 16(1) |