JP3918461B2 - Construction method for underwater foundation - Google Patents
Construction method for underwater foundation Download PDFInfo
- Publication number
- JP3918461B2 JP3918461B2 JP2001171695A JP2001171695A JP3918461B2 JP 3918461 B2 JP3918461 B2 JP 3918461B2 JP 2001171695 A JP2001171695 A JP 2001171695A JP 2001171695 A JP2001171695 A JP 2001171695A JP 3918461 B2 JP3918461 B2 JP 3918461B2
- Authority
- JP
- Japan
- Prior art keywords
- foundation
- caisson housing
- pile foundation
- load
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Foundations (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は、水中基礎の構築工法に関し、特に、サクション荷重を有効に作用させて水中基礎を構築する工法に関するものである。
【0002】
【従来の技術】
水中に基礎を構築する際に、杭基礎の場合は、押し込み力として打撃や振動などの機械力を利用することができるが、例えば、大型の護岸や海洋構造物のような大水深基礎では、このような機械力により、基礎構造物を沈設することが困難になる。
【0003】
そこで、このような大水深基礎の構築方法の一つとして、スカート部を有するケーソン躯体を、圧力差(サクション)を利用して、水底地盤中に沈設するサクション基礎工法と呼ばれている構築方法がある。
【0004】
このようなサクションを利用して沈設するスカート基礎は、ケーソン基礎,鋼管矢板ケーソン基礎などに代わる新しい基礎形式として、その用途の拡大が期待されている。
【0005】
図4,5には、このようなサクション基礎の構築工法の一例が示されており、同図に示したサクション基礎工法では、ケーソン躯体1は、筒状の側壁部2と、この側壁部2の下端側を閉塞する底版部3と、底版部3の外周縁下方に延設されたスカート部4とを備えている。
【0006】
スカート部4は、筒状に形成されていて、その壁厚内に揚水通路5が貫通形成され、底版部3を貫通するように揚水管6が設けられている。水中基礎を構築する際には、ケーソン躯体1が水底地盤7に沈設される。
【0007】
このとき、スカート部4の下端側を水底地盤7中に貫入させて、水の流入を阻止し、この状態で、スカート部4内の水を排水通路5や、底版部3を貫通する揚水管6を介して排除し、これによりスカート部4内の圧力を下げて、スカート部4の内外にサクション荷重を発生させて、このサクション荷重を利用して、ケーソン躯体1を水底地盤中に沈設する。
【0008】
また、その後、ケーソン躯体1を基礎などに利用するためには、所定の深度まで沈設した後、図5に示すように、底版部3と水底地盤7との間にモルタルなどの硬化性グラウト8を充填し、かつ、揚水管6を介して、スカート部4で囲繞した水底地盤7の水を揚水排除して、サクション荷重を水底地盤7に伝達させることが有効である。
【0009】
このような水中基礎の構築工法は、比較的施工が容易で、十分に水底地盤7中に根入れされたケーソン躯体1は、滑動,転倒,引き抜きに対する抵抗も著しく増大するという長所がある。
【0010】
ところが、図4,5に示すように、水底地盤7が、軟弱層7aと、その下部に支持層7bとが存在している場合には、スカート部4の先端は、支持層7bに到達するように沈設され、硬化性グラウト8は、軟弱層7aと底版部3との間に充填させることになる。このようなケーソン躯体1では、軟弱層7aに荷重が負荷されるので、上部工の完成後にも、軟弱層7aの圧密化により継続的な沈下が発生する。
そこで、従来は、このような継続的な沈下を防止するために、▲1▼.軟弱層7aを除去する方法。▲2▼.軟弱層7aを事前に圧密化させるか、または、地盤改良により安定化させる方法。▲3▼.ケーソン躯体1をサクション貫入させる際に、スカート部4の先端に、供用時よりも大きな荷重を印加して、大きいプレロード荷重を作用させる方法のいずれかの補助工法を採用していた。
【0011】
しかしながら、このような従来の水中基礎の構築工法には、以下に説明する技術的な課題があった。
【0012】
【発明が解決しようとする課題】
すなわち、▲1▼の補助工法では、軟弱層7aの除去により、多大な掘削除去費用がかかる。また、▲2▼の補助工法では、軟弱層7aの沈下が、落ち着くまでに、長時間を要し、工期が非常に長くかかる。
【0013】
さらに、▲3▼の補助工法では、供用時の荷重よりも大きなプレロード荷重に、耐えうる仕様にすると、ケーソン躯体1の構造形状が過大になり、非常に不経済な設計となる。
【0014】
本発明は、このような従来の問題点に鑑みてなされたものであって、その目的とするところは、工期の長期化を回避しつつ、経済的な構築が可能になる水中基礎の構築工法を提供することにある。
【0015】
【課題を解決するための手段】
上記目的を達成するために、本発明は、筒状の側壁と、前記側壁の下端に形成された底版部と、前記底版部の下方に延設されるスカート部とを備えたケーソン躯体に、サクション荷重を作用させて水底地盤中に沈設する水中基礎の構築工法において、前記ケーソン躯体の沈設予定個所の水底地盤中に、下端が支持層に到達する杭基礎を打設した後に、前記杭基礎の上方から前記スカート部の先端が支持層に到達するように、前記ケーソン躯体を沈設して、両者を一体化させて、供用荷重を前記杭基礎と前記ケーソン躯体とで分担する水中基礎の構築工法であって、前記杭基礎は、前記ケーソン躯体を前記水底地盤に沈設させる際に、前記スカート部先端に作用させることができるプレロード荷重と、前記ケーソン躯体に上部工を構築した際の供用荷重とに基づいて、両荷重の差分を推定演算し、この差分を前記杭基礎の荷重支持力として分担させるようにする。
【0016】
このように構成した水中基礎の構築工法によれば、ケーソン躯体の沈設予定個所の水底地盤中に、下端が支持層に到達する杭基礎を打設した後に、杭基礎の上方からスカート部の先端が支持層に到達するように、ケーソン躯体を沈設して、両者を一体化させて、供用荷重を杭基礎とケーソン躯体とで分担するので、水底地盤に荷重分担させる必要がなくなり、その結果、供用荷重を加えたときに水底地盤の圧密沈下が発生しない。
【0017】
供用荷重に伴う水底地盤の圧密沈下が発生しないと、その除去や地盤改良が不要になり、かつ、スカート部を供用荷重よりも大きなプレロードに耐え得る構造形状に設計する必要もなくなる。
【0019】
前記ケーソン躯体と前記杭基礎との一体化は、前記底版下の前記スカート部で囲繞された空間内に、前杭基礎の頭部を突出させ、前記空間内に硬化性グラウト材を注入充填して行うことができる。
【0020】
【発明の実施の形態】
以下、本発明の好適な実施の形態について、添付図面に基づいて詳細に説明する。図1から図3は、本発明にかかる水中基礎の構築工法の一実施例を示している。
【0021】
同図に示した水中基礎は、ケーソン躯体10と、杭基礎11とを備えている。ケーソン躯体10は、円筒ないしは角形形状の側壁部12と、この側壁部12の下端側を閉塞する底版部14と、底版部14の外周縁下方に延設されたスカート部16とを備えている。
【0022】
底版部14は、所定厚みを備えた盤状に形成されており、周縁が側壁部12の内面に一体に固設されている。スカート部16は、側壁部12の下方側を、そのまま直径を変えることなく下方に延長させた同一断面形状に形成されていて、その壁厚内に揚水通路18が、周方向に所定の間隔を隔てて複数貫通形成されている。
【0023】
また、底版部14には、これを上下方向に貫通するようにして揚水管20が複数取付けられている。以上のように構成されたケーソン躯体10は、地上の製作ヤードなどで構築され、基礎の構築現場まで曳航され、水底地盤26に沈設される。本実施例の水中基礎の構築工法では、このケーソン躯体10の沈設前に、まず、図1に示すように、杭基礎11の水底地盤26中への打設が行われる。
【0024】
杭基礎11は、複数本で構成されている。本実施例の杭基礎11は、水底地盤26の表層側の軟弱層26aを貫通して、その下端が支持層26bに到達するように打設される。
【0025】
本実施例の場合、複数本の杭基礎11の荷重支持力は、以下のように設定される。杭基礎11の荷重支持力の決定では、まず、ケーソン躯体10を水底地盤26に沈設させる際に、スカート部16の先端に作用させることができるプレロード荷重を求める。
【0026】
このプレロード荷重は、筒状の側壁12と、側壁12の下端に形成された底版部14と、底版部14の下方に延設されるスカート部16とを備えたケーソン躯体10の自重と、このケーソン躯体10に加え得るバラスト荷重と、ケーソン躯体10のスカート部16内の減圧によって発生するサクション荷重との加算値として求められる。
【0027】
この場合のバラスト荷重は、側壁12内に注入する水や載置可能な錘などの重量から決定される。なお、ケーソン躯体10は、上部工を構築した際の供用荷重に、所定の安全率を見込んで必要な支持力を算定し、この支持力から適正な断面形状などが、通常の設計法に従って設計されている。
【0028】
次に、ケーソン躯体10に上部工を構築した際の供用荷重と、前述したプレロード荷重との差分を推定演算し、この差分の荷重量が杭基礎11に要求される荷重支持力とし、この荷重支持力に基づいて杭基礎11の本数や断面形状,配置間隔などを決定する。
【0029】
杭基礎11のこのような決定が終了すると、これに基づいて選択された杭基礎11が、図1に示すように、水底地盤26中に打設される。この場合の杭基礎11は、この後に沈設されるケーソン躯体10のスカート部16内に、それぞれが位置するように打設される。
【0030】
杭基礎11は、各杭の杭頭が水底地盤26の表面から上方に若干突出するように打設され、所定数の打設が終了すると、次に、図2に示すように、ケーソン躯体10の沈設が行われる。
【0031】
ケーソン躯体10は、杭基礎11の上方からこれを覆うようにして沈設される。この沈設に当たっては、スカート部16の下端側を水底地盤26中に貫入させて、水の流入を阻止し、この状態で、スカート部16内の水を、揚水通路18や、揚水管20を介して排除することで、スカート部16内の圧力を下げて、スカート部16の内外にサクション荷重を発生させて、ケーソン躯体10を水底地盤26中に沈設する。
【0032】
そして、スカート部16が水底地盤26中に徐々に貫入して、ケーソン躯体10の沈設が進行し、図3に示すように、底版部14が水底地盤26の上面に近接し、スカート部16の下端が支持層26bの、所定の深度まで貫入すると、ケーソン躯体10の沈設を終了する。
【0033】
この沈設完了状態では、底版部14の下面側に、水底地盤26の表面と、スカート部16とで隔成された空間28が形成され、杭基礎11の杭頭は、この空間28内に突出している。
【0034】
次いで、この状態で、空間28内に、硬化性グラウト材30の充填注入が行われ、このグラウト材30硬化が終了すると、ケーソン躯体10と杭基礎11とが一体化されて、水中基礎の構築が完了する。
【0035】
さて、以上のようにして行う水中基礎の構築工法によれば、ケーソン躯体10の沈設予定個所の水底地盤26中に、下端が支持層26bに到達する杭基礎11を打設した後に、杭基礎11の上方にケーソン躯体10を沈設して、両者を一体化させて、供用荷重を杭基礎11とケーソン躯体10とで分担するので、水底地盤26に荷重分担させる必要がなくなり、その結果、供用荷重を加えたときに水底地盤の圧密沈下が発生しない。
【0036】
供用荷重に伴う水底地盤26の圧密沈下が発生しないと、軟弱層26aの除去や地盤改良が不要になり、かつ、スカート部16を、供用荷重よりも大きなプレロードに耐え得る構造形状に設計する必要もなくなり、工期の長期化を回避しつつ、経済的な構築が可能になる。
【0037】
つまり、本実施例では、通常の設計条件でケーソン躯体10を設計した際に、ケーソン躯体10に作用させることができるプレロード荷重で不足する荷重を、予め打設する杭基礎11で分担させるようにしている。
【0038】
このような構築工法によれば、軟弱層26aの強度,層厚にかかわらず、ケーソン躯体10を合理的で経済的なものにすることができ、しかも、沈下特性も改善できる。
【0039】
なお、上記実施例では、円筒状のケーソン躯体10に本発明を適用した場合を例示したが、本発明の実施は、この形状のケーソン躯体10に限られることはなく、例えば、スカート部16内が隔壁により仕切られた形状のケーソン躯体など、他の形状のケーソン躯体10に適用することもできる。
【0040】
【発明の効果】
以上、実施例で詳細に説明したように、本発明にかかる水中基礎の構築工法によれば、工期の長期化を回避しつつ、経済的な構築が可能になる。
【図面の簡単な説明】
【図1】本発明にかかる水中基礎の構築工法の一実施例を示す初期工程の断面説明図である。
【図2】図1の工程に引き続いて行われる工程の断面説明図である。
【図3】図2の工程に引き続いて行われる工程の断面説明図である。
【図4】従来の水中基礎の構築工法の一例を示す初期工程の断面説明図である。
【図5】図4の工程に引き続いて行われる工程の断面説明図である。
【符号の説明】
10 ケーソン躯体
11 杭基礎
12 側壁部
14 底版部
16 スカート部
18 揚水通路
20 揚水管
26 水底地盤
26a 軟弱層
26b 支持層
30 グラウト材[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a construction method for an underwater foundation, and more particularly to a construction method for constructing an underwater foundation by effectively applying a suction load.
[0002]
[Prior art]
When constructing foundations in the water, in the case of pile foundations, mechanical forces such as hammering and vibration can be used as pushing force, but for example, in deep foundations such as large revetments and offshore structures, Such mechanical force makes it difficult to set the foundation structure.
[0003]
Therefore, as one of the methods for constructing such a deep water foundation, a construction method called a suction foundation construction method in which a caisson housing with a skirt is submerged in the bottom of the ground using a pressure difference (suction). There is.
[0004]
The skirt foundation that is laid down by using such suction is expected to expand its application as a new foundation form that replaces the caisson foundation and the steel pipe sheet pile caisson foundation.
[0005]
FIGS. 4 and 5 show an example of a construction method for such a suction foundation. In the suction foundation construction method shown in FIG. 4, the caisson housing 1 has a
[0006]
The
[0007]
At this time, the lower end side of the
[0008]
After that, in order to use the caisson housing 1 as a foundation, as shown in FIG. 5, a
[0009]
Such an underwater foundation construction method is relatively easy to construct, and the caisson housing 1 sufficiently embedded in the submerged
[0010]
However, as shown in FIGS. 4 and 5, when the
Therefore, conventionally, in order to prevent such continuous settlement, {circle around (1)}. A method of removing the soft layer 7a. (2). A method in which the soft layer 7a is consolidated in advance or stabilized by ground improvement. (3). When the caisson housing 1 is inserted into the suction portion, any auxiliary method of applying a larger preload load to the tip of the
[0011]
However, such conventional underwater foundation construction methods have the following technical problems.
[0012]
[Problems to be solved by the invention]
That is, in the auxiliary method (1), a great excavation and removal cost is required due to the removal of the soft layer 7a. Further, in the auxiliary method (2), it takes a long time for the soft layer 7a to settle down, and the construction period is very long.
[0013]
Furthermore, in the auxiliary method (3), if the specification can withstand a preload load larger than the load at the time of service, the structure of the caisson housing 1 becomes excessively large, resulting in a very uneconomic design.
[0014]
The present invention has been made in view of such conventional problems, and the object of the present invention is to construct an underwater foundation that can be economically constructed while avoiding a prolonged construction period. Is to provide.
[0015]
[Means for Solving the Problems]
To achieve the above object, the present invention provides a caisson housing including a cylindrical side wall, a bottom plate portion formed at the lower end of the side wall, and a skirt portion extending below the bottom plate portion. In the construction method of an underwater foundation to be submerged in the bottom ground by applying a suction load, after placing a pile foundation in which the lower end reaches the support layer in the bottom bottom ground of the caisson frame to be submerged, the pile foundation The caisson housing is laid down so that the tip of the skirt portion reaches the support layer from above, and the two are integrated to construct an underwater foundation for sharing the service load between the pile foundation and the caisson housing It is a construction method, and the pile foundation is a preload load that can be applied to the tip of the skirt portion when the caisson housing is submerged in the water bottom ground, and an upper work is constructed on the caisson housing. Based on the use load, the difference between the two load estimating operation to the difference so as to share the load bearing capacity of the pile foundation.
[0016]
According to the construction method of the underwater foundation constructed in this way, after placing the pile foundation where the lower end reaches the support layer in the water bottom ground at the location where the caisson frame is to be set up, the tip of the skirt from above the pile foundation So that the caisson body is laid down so that both can reach the support layer , both are integrated, and the service load is shared between the pile foundation and the caisson body, so there is no need to share the load on the bottom ground, Consolidation subsidence does not occur when water service is applied.
[0017]
If consolidation settlement of the water bottom ground due to the service load does not occur, it is not necessary to remove or improve the ground, and it is not necessary to design the skirt portion to have a structure that can withstand a preload larger than the service load .
[0019]
The integration of the caisson housing and the pile foundation is accomplished by projecting the head of the front pile foundation into the space surrounded by the skirt under the bottom slab and injecting and filling a hardenable grout material into the space. Can be done.
[0020]
DETAILED DESCRIPTION OF THE INVENTION
DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described in detail with reference to the accompanying drawings. 1 to 3 show an embodiment of a construction method for an underwater foundation according to the present invention.
[0021]
The underwater foundation shown in the figure includes a
[0022]
The
[0023]
A plurality of pumping
[0024]
The
[0025]
In the case of a present Example, the load supporting force of the
[0026]
This preload load includes the weight of the
[0027]
The ballast load in this case is determined from the weight of water injected into the
[0028]
Next, the difference between the service load when the superstructure is constructed in the
[0029]
When such a determination of the
[0030]
The
[0031]
The
[0032]
Then, the
[0033]
In this set-up state, a
[0034]
Next, in this state, filling and injection of the
[0035]
Now, according to the construction method of the underwater foundation performed as described above, after placing the
[0036]
If consolidation settlement of the water bottom ground 26 due to the service load does not occur, it is not necessary to remove the soft layer 26a or improve the ground, and the
[0037]
That is, in the present embodiment, when the
[0038]
According to such a construction method, regardless of the strength and thickness of the soft layer 26a, the
[0039]
In the above embodiment, the case where the present invention is applied to the
[0040]
【The invention's effect】
As described above in detail in the embodiment, according to the construction method for an underwater foundation according to the present invention, it is possible to construct economically while avoiding a prolonged construction period.
[Brief description of the drawings]
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is a cross-sectional explanatory view of an initial process showing an embodiment of an underwater foundation construction method according to the present invention.
FIG. 2 is an explanatory cross-sectional view of a process performed subsequent to the process of FIG. 1;
3 is a cross-sectional explanatory diagram of a process performed subsequent to the process of FIG. 2. FIG.
FIG. 4 is an explanatory sectional view of an initial process showing an example of a conventional underwater foundation construction method.
FIG. 5 is an explanatory cross-sectional view of a process performed subsequent to the process of FIG. 4;
[Explanation of symbols]
DESCRIPTION OF
Claims (2)
前記ケーソン躯体の沈設予定個所の水底地盤中に、
下端が支持層に到達する杭基礎を打設した後に、前記杭基礎の上方から前記スカート部の先端が支持層に到達するように、前記ケーソン躯体を沈設して、両者を一体化させて、
供用荷重を前記杭基礎と前記ケーソン躯体とで分担する水中基礎の構築工法であって、
前記杭基礎は、前記ケーソン躯体を前記水底地盤に沈設させる際に、前記スカート部先端に作用させることができるプレロード荷重と、前記ケーソン躯体に上部工を構築した際の供用荷重とに基づいて、両荷重の差分を推定演算し、
この差分を前記杭基礎の荷重支持力として分担させるようにすることを特徴とする水中基礎の構築工法。A caisson housing including a cylindrical side wall, a bottom plate portion formed at the lower end of the side wall, and a skirt portion extending below the bottom plate portion is subjected to a suction load to be sunk in the water bottom ground. In construction method of underwater foundation,
In the submarine ground of the planned location of the caisson housing,
After placing the pile foundation where the lower end reaches the support layer, the caisson housing is sunk so that the tip of the skirt part reaches the support layer from above the pile foundation, and both are integrated,
An underwater foundation construction method for sharing in- service load between the pile foundation and the caisson housing ,
The pile foundation is based on the preload load that can be applied to the tip of the skirt when the caisson housing is submerged in the water bottom ground, and the service load when the superstructure is constructed on the caisson housing. Estimate the difference between both loads,
An underwater foundation construction method characterized in that this difference is shared as the load bearing capacity of the pile foundation .
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001171695A JP3918461B2 (en) | 2001-06-06 | 2001-06-06 | Construction method for underwater foundation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2001171695A JP3918461B2 (en) | 2001-06-06 | 2001-06-06 | Construction method for underwater foundation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JP2002364006A JP2002364006A (en) | 2002-12-18 |
| JP3918461B2 true JP3918461B2 (en) | 2007-05-23 |
Family
ID=19013420
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP2001171695A Expired - Fee Related JP3918461B2 (en) | 2001-06-06 | 2001-06-06 | Construction method for underwater foundation |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3918461B2 (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102644293A (en) * | 2012-04-25 | 2012-08-22 | 中交第二航务工程局有限公司 | Pile foundation bucket foundation and construction method thereof |
| CN102747854A (en) * | 2012-07-26 | 2012-10-24 | 中国神华能源股份有限公司 | Construction method of silo bottom structure |
| CN102747740A (en) * | 2012-07-26 | 2012-10-24 | 中国神华能源股份有限公司 | Construction method of silo foundation |
| CN103981905A (en) * | 2014-04-30 | 2014-08-13 | 天津大学 | Real-time monitoring method for sinking attitude of composite bucket foundation for offshore wind turbine |
Families Citing this family (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5495325B2 (en) * | 2010-08-20 | 2014-05-21 | 五洋建設株式会社 | Pile foundation structure, construction method of pile foundation structure and pile used for these |
| CN102776890A (en) * | 2012-08-02 | 2012-11-14 | 中交二航局第四工程有限公司 | Underwater pushing correcting method of steel cofferdam and pushing device of steel cofferdam |
| CN103967031B (en) * | 2013-01-24 | 2015-09-16 | 中交公路规划设计院有限公司 | A kind of caisson of consolidated subsoil and stake combination foundation and construction method thereof |
| CN103343544B (en) * | 2013-07-16 | 2015-07-15 | 江西建工第一建筑有限责任公司 | Construction method for large-scale open caisson |
| CN105350552A (en) * | 2015-09-25 | 2016-02-24 | 中国二十冶集团有限公司 | Underground water control method for backfilled sediment layer |
| CN107090844A (en) * | 2017-05-19 | 2017-08-25 | 中交第三航务工程局有限公司 | Offshore wind farm grouped piles cap composite foundation and construction method |
| CN112663664A (en) * | 2020-12-21 | 2021-04-16 | 中国能源建设集团浙江省电力设计院有限公司 | Combined foundation construction method for ultra-large open caisson structure |
| CN119754325B (en) * | 2025-01-16 | 2025-12-26 | 广州一建建设集团有限公司 | A method and structure for correcting the deviation of a caisson in strata with uneven hardness. |
| CN121827390B (en) * | 2026-03-06 | 2026-06-05 | 杭州江润科技有限公司 | Reinforcement of deep-water pile foundations with irregularly shaped steel casings for complex riverbeds: pile foundation structure and construction methods |
-
2001
- 2001-06-06 JP JP2001171695A patent/JP3918461B2/en not_active Expired - Fee Related
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102644293A (en) * | 2012-04-25 | 2012-08-22 | 中交第二航务工程局有限公司 | Pile foundation bucket foundation and construction method thereof |
| CN102644293B (en) * | 2012-04-25 | 2014-09-10 | 中交第二航务工程局有限公司 | Pile foundation bucket foundation and construction method thereof |
| CN102747854A (en) * | 2012-07-26 | 2012-10-24 | 中国神华能源股份有限公司 | Construction method of silo bottom structure |
| CN102747740A (en) * | 2012-07-26 | 2012-10-24 | 中国神华能源股份有限公司 | Construction method of silo foundation |
| CN102747854B (en) * | 2012-07-26 | 2014-10-22 | 中国神华能源股份有限公司 | Construction method of silo bottom structure |
| CN103981905A (en) * | 2014-04-30 | 2014-08-13 | 天津大学 | Real-time monitoring method for sinking attitude of composite bucket foundation for offshore wind turbine |
| CN103981905B (en) * | 2014-04-30 | 2016-02-24 | 天津大学 | A kind of offshore wind turbine compound cartridge type foundation immersion attitude method of real-time |
Also Published As
| Publication number | Publication date |
|---|---|
| JP2002364006A (en) | 2002-12-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104196034B (en) | A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam | |
| US20120155968A1 (en) | Construction method of cellar for building completed | |
| CN104264688A (en) | Manual hole digging non-uniform pile support construction technology | |
| CN104805854A (en) | Method for constructing deep-water ultra-long steel plate pile cofferdam in tide environment | |
| JP2002364006A (en) | Construction method of underwater foundation | |
| KR20130013287A (en) | Wet-type constructing method of pier foundation | |
| CN102626946A (en) | Manufacture method for concrete irregular fender post | |
| JP5976373B2 (en) | Pile foundation reinforcement structure and reinforcement method | |
| JP2002121754A (en) | Construction method of underwater foundation | |
| CN209636840U (en) | Can eliminate firming device of bucket shape foundation soil stopper phenomenon | |
| JP3534928B2 (en) | Construction method of seismic isolation pit for existing building | |
| CN1072746C (en) | Head and side grouting method for cast-in-situ pile | |
| JP2008208533A (en) | Caisson and its construction method | |
| JP5179636B1 (en) | Liquefaction prevention structure of solid foundation with steel pipe pile and solid foundation method with steel pipe pile | |
| CN202610808U (en) | Foundation Pit Supporting Structure Combined with Capping Pressure, Anchorage and Side Block | |
| CN103334428A (en) | Disc type cast-in-place concrete pile and construction process for same | |
| CN115977095B (en) | Construction method of concrete anti-seepage wall | |
| CN206591535U (en) | Combined type cofferdam | |
| CN214738333U (en) | Box culvert foundation reinforcement structure combined with Yonglin | |
| CN205000296U (en) | A Concrete Panel Structure Using High Toe Walls | |
| JP2003138584A (en) | Construction method of underground skeleton | |
| JPH0437205B2 (en) | ||
| JP3728659B2 (en) | Basement extension method | |
| JP4146561B2 (en) | Construction method of shaft | |
| CN224001966U (en) | Rock-socketed shallow-buried PC combined pile cofferdam suitable for bare rock foundation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040709 |
|
| A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20051219 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060425 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060623 |
|
| A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060829 |
|
| A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20061025 |
|
| TRDD | Decision of grant or rejection written | ||
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20070123 |
|
| A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20070205 |
|
| R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100223 Year of fee payment: 3 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110223 Year of fee payment: 4 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110223 Year of fee payment: 4 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120223 Year of fee payment: 5 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130223 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130223 Year of fee payment: 6 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140223 Year of fee payment: 7 |
|
| LAPS | Cancellation because of no payment of annual fees |