FR3052181A1 - PROCESS FOR EXTRACTING NATURAL MATERIALS, IN PARTICULAR ROCKS - Google Patents

PROCESS FOR EXTRACTING NATURAL MATERIALS, IN PARTICULAR ROCKS Download PDF

Info

Publication number
FR3052181A1
FR3052181A1 FR1655131A FR1655131A FR3052181A1 FR 3052181 A1 FR3052181 A1 FR 3052181A1 FR 1655131 A FR1655131 A FR 1655131A FR 1655131 A FR1655131 A FR 1655131A FR 3052181 A1 FR3052181 A1 FR 3052181A1
Authority
FR
France
Prior art keywords
holes
extraction
ground
block
steps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
FR1655131A
Other languages
French (fr)
Other versions
FR3052181B1 (en
Inventor
Philippe Moranne
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to FR1655131A priority Critical patent/FR3052181B1/en
Priority to ES17174565T priority patent/ES2724407T3/en
Priority to EP17174565.6A priority patent/EP3255243B1/en
Priority to PT17174565T priority patent/PT3255243T/en
Publication of FR3052181A1 publication Critical patent/FR3052181A1/en
Application granted granted Critical
Publication of FR3052181B1 publication Critical patent/FR3052181B1/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G04HOROLOGY
    • G04BMECHANICALLY-DRIVEN CLOCKS OR WATCHES; MECHANICAL PARTS OF CLOCKS OR WATCHES IN GENERAL; TIME PIECES USING THE POSITION OF THE SUN, MOON OR STARS
    • G04B19/00Indicating the time by visual means
    • G04B19/22Arrangements for indicating different local apparent times; Universal time pieces
    • G04B19/221Arrangements for indicating different local apparent times; Universal time pieces mechanisms for correcting the hours hand only, i.e. independently for minutes and seconds hands
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/26Methods of surface mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C47/00Machines for obtaining or the removal of materials in open-pit mines
    • E21C47/10Machines for obtaining or the removal of materials in open-pit mines for quarrying stone, sand, gravel, or clay
    • GPHYSICS
    • G04HOROLOGY
    • G04BMECHANICALLY-DRIVEN CLOCKS OR WATCHES; MECHANICAL PARTS OF CLOCKS OR WATCHES IN GENERAL; TIME PIECES USING THE POSITION OF THE SUN, MOON OR STARS
    • G04B19/00Indicating the time by visual means
    • G04B19/02Back-gearing arrangements between gear train and hands
    • G04B19/025Back-gearing arrangements between gear train and hands for simultaneous indicating on several dials
    • GPHYSICS
    • G04HOROLOGY
    • G04BMECHANICALLY-DRIVEN CLOCKS OR WATCHES; MECHANICAL PARTS OF CLOCKS OR WATCHES IN GENERAL; TIME PIECES USING THE POSITION OF THE SUN, MOON OR STARS
    • G04B27/00Mechanical devices for setting the time indicating means
    • G04B27/005Mechanical devices for setting the time indicating means stepwise or on determined values
    • GPHYSICS
    • G04HOROLOGY
    • G04BMECHANICALLY-DRIVEN CLOCKS OR WATCHES; MECHANICAL PARTS OF CLOCKS OR WATCHES IN GENERAL; TIME PIECES USING THE POSITION OF THE SUN, MOON OR STARS
    • G04B27/00Mechanical devices for setting the time indicating means
    • G04B27/02Mechanical devices for setting the time indicating means by making use of the winding means
    • G04B27/04Mechanical devices for setting the time indicating means by making use of the winding means with clutch wheel

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Revetment (AREA)

Abstract

Ce procédé d'extraction de matériaux naturels hors d'un sol (2), comporte selon un ordre d'exécution variable, les étapes suivantes : a) réalisation d'un réseau de trous sensiblement verticaux dans le sol (2) selon un maillage prédéfini, les trous (6) présentant d'un diamètre supérieur à 1 m, b) réalisation de deux découpes sensiblement verticales entre deux trous voisins, c) réalisation d'une découpe sensiblement horizontale entre deux découpes verticales de manière à détacher un bloc, appelé barrette, se trouvant entre deux trous voisins, et extraction de ladite barrette, d) répétition des étapes b) et c) de manière à former une tranchée de forme polygonale délimitant ainsi un bloc, e) réalisation d'une découpe horizontale sous le bloc de manière à le libérer du sol et extraction dudit bloc, ledit bloc pouvant être d'un seul tenant ou en plusieurs morceaux.This method of extracting natural materials from a soil (2), comprises in a variable order of execution, the following steps: a) realization of a network of substantially vertical holes in the soil (2) according to a mesh predefined, the holes (6) having a diameter greater than 1 m, b) making two substantially vertical cuts between two adjacent holes, c) producing a substantially horizontal cut between two vertical cuts so as to detach a block, called strip, located between two adjacent holes, and extraction of said bar, d) repetition of steps b) and c) so as to form a trench of polygonal shape thus delimiting a block, e) realization of a horizontal cut under the block so as to release it from the ground and extraction of said block, said block can be in one piece or in several pieces.

Description

La présente invention concerne un procédé d'extraction de matériaux naturels, notamment de roches.The present invention relates to a method of extracting natural materials, including rocks.

Le domaine de la présente invention est ainsi notamment l'exploitation de carrières pour obtenir des roches (granit, grès, ...) destinés par la suite à être utilisés par exemple dans le domaine de la construction.The field of the present invention is thus in particular the exploitation of quarries to obtain rocks (granite, sandstone, ...) intended subsequently to be used for example in the field of construction.

Dans la plupart des carrières, il est encore fréquent d'utiliser des explosifs pour détacher des blocs de roches ou similaires du reste du gisement. Bien que la manipulation des explosifs soit de mieux en mieux maîtrisée, une certaine incertitude reste quant à la forme et la taille des blocs obtenus après l'explosion d'une charge de poudre.In most quarries, it is still common to use explosives to detach blocks of rocks or the like from the rest of the deposit. Although the handling of explosives is better controlled, some uncertainty remains as to the shape and size of the blocks obtained after the explosion of a powder charge.

En outre, un tel procédé génère des nuisances sonores importantes et les carrières sont de ce fait le plus souvent à l'écart des zones habitées et donc aussi des lieux d'utilisation des roches extraites. En plus des nuisances sonores, les carrières marquent le plus souvent esthétiquement le paysage et la zone correspondante est alors difficilement exploitable pour recevoir des bâtiments.In addition, such a method generates significant noise and quarries are therefore most often away from inhabited areas and therefore also places of use of extracted rocks. In addition to noise pollution, quarries most often mark the landscape and the corresponding area is difficult to exploit to receive buildings.

Il est connu, par exemple par le document FR2600375, d'exploiter une carrière par débitage direct de pierres ou similaires. Ce document propose par exemple de réaliser dans la surface supérieure d'un site et entre au moins deux bords de celui-ci une pluralité d'entailles verticales parallèles de hauteur identique prise à partir d'un même plan horizontal et définissant entre elles des plaque de pierre, puis d'enlever lesdites plaques de pierres de manière à obtenir un front de taille vertical le long d'un bord du site, puis à débiter sur toute la longueur du front de taille et de façon inclinée des blocs de pierre, de manière, d'une part, à permettre le passage des outils de débitage et, d'autre part, à former des appuis de référence de guidage pour obtenir un bon parallélisme d'au moins deux faces des blocs de pierre débités, puis à progresser perpendiculairement au front de taille au fur et à mesure du débitage en se plaçant sur les appuis de référence de guidage et à répéter ces opération lorsque le front de taille n'est plus exploitable, c’est-à-dire lorsque ledit front de taille n'est plus suffisant dans son épaisseur pour fournir des blocs de pierre utilisables.It is known, for example from document FR2600375, to operate a quarry by direct debiting of stones or the like. This document proposes for example to make in the upper surface of a site and between at least two edges thereof a plurality of parallel vertical notches of identical height taken from the same horizontal plane and defining between them plate of stone, then removing said stone slabs so as to obtain a vertical face height along an edge of the site, and then to cut along the entire length of the sloping face of the blocks of stone, on the one hand, to allow the passage of the debiting tools and, on the other hand, to form guiding reference supports to obtain a good parallelism of at least two faces of the cut stone blocks, then to progress perpendicularly to the face of the cutting edge as it is being cut by placing itself on the guide reference supports and repeating these operations when the cutting edge is no longer usable, that is to say when said forehead size is no longer sufficient in its thickness to provide usable blocks of stone.

La présente invention a pour but d'optimiser encore l'exploitation d'une carrière, et plus généralement l'extraction de matériaux naturels.The present invention aims to further optimize the operation of a quarry, and more generally the extraction of natural materials.

Un but de l'invention est de limiter les pertes de matériau et donc de permettre d'utiliser au maximum le matériau extrait. Ceci permet, outre une augmentation du rendement du site, de limiter la quantité de "déchets" à traiter et à évacuer.An object of the invention is to limit the loss of material and thus to allow maximum use of the extracted material. This allows, in addition to an increase in the yield of the site, to limit the amount of "waste" to be treated and evacuated.

Un autre but de la présente invention est aussi de limiter les nuisances, sonores et esthétiques, lors de l'extraction de roches ou similaires. De préférence, ces nuisances sont à ce point limitées qu'il devienne raisonnable de rapprocher le site d'extraction du lieu d'utilisation des matériaux extraits.Another object of the present invention is also to limit the nuisance, sound and aesthetics, during the extraction of rocks or the like. Preferably, these nuisances are so limited that it becomes reasonable to bring the extraction site of the place of use of the extracted materials.

Un autre but de la présente invention est de permettre la "réutilisation" du terrain une fois l'extraction de matériaux terminée. À cet effet, la présente invention propose un procédé d'extraction de matériaux naturels hors d'un sol, caractérisé en ce qu'il comporte selon un ordre d'exécution variable, les étapes suivantes : a) réalisation d'un réseau de trous sensiblement verticaux dans le sol selon un maillage prédéfini, les trous présentant d'un diamètre supérieur à 1 m, b) réalisation de deux découpes sensiblement verticales entre deux trous voisins, c) réalisation d'une découpe sensiblement horizontale entre deux découpes verticales de manière à détacher un bloc, appelé barrette, se trouvant entre deux trous voisins, et extraction de ladite barrette, d) répétition des étapes b) et c) de manière à former une tranchée de forme polygonale délimitant ainsi un bloc, e) réalisation d'une découpe horizontale sous le bloc de manière à le libérer du sol et extraction dudit bloc, ledit bloc pouvant être d'un seul tenant ou en plusieurs morceaux.Another object of the present invention is to allow the "reuse" of the land once the extraction of materials is complete. To this end, the present invention proposes a method of extracting natural materials out of a soil, characterized in that it comprises in a variable order of execution, the following steps: a) realization of a network of holes substantially vertical in the ground according to a predefined mesh, the holes having a diameter greater than 1 m, b) making two substantially vertical cuts between two adjacent holes, c) producing a substantially horizontal cut between two vertical cuts so detaching a block, called a bar, located between two adjacent holes, and extracting said bar, d) repeating steps b) and c) so as to form a trench of polygonal shape thus delimiting a block, e) embodiment of a horizontal cut under the block so as to release it from the ground and extraction of said block, said block can be in one piece or in several pieces.

Avec un tel procédé, l'emprise sur la surface du sol est maîtrisée car elle est limitée au maillage des trous. De plus, après exploitation de la roche, il reste un trou de taille limitée qu'il suffit de sécuriser. Aucune nuisance "visuelle" n'est produite : le site n'est que très peu affecté par l'exploitation de la matière naturelle. Ce procédé permet également un excellent rendement car il n'opère que par découpe. Il est même possible de récupérer du matériau des trous du maillage de trous car ces derniers sont d'un diamètre assez important.With such a method, the footprint on the soil surface is controlled because it is limited to mesh holes. Moreover, after exploitation of the rock, there remains a hole of limited size that it is enough to secure. No "visual" nuisance is produced: the site is only slightly affected by the exploitation of the natural material. This process also allows excellent performance because it operates only by cutting. It is even possible to recover holes from the mesh of holes because the latter are of a fairly large diameter.

Pour faciliter le travail d'extraction, les trous dans le sol définissent de préférence un maillage rectangulaire et encore de préférence carré. De la sorte, il est possible de garder des réglages d'outillages pendant de nombreuses opérations de découpes et autres.To facilitate the work of extraction, the holes in the ground preferably define a rectangular mesh and preferably square. In this way, it is possible to keep tooling settings during many cutting and other operations.

Dans un procédé d'extraction selon la présente invention, les trous réalisés dans le sol sont par exemple des trous cylindriques circulaires dont le diamètre est compris entre 2 et 3 m, de préférence entre 2,2 et 2,6 m. Cette taille de trou permet notamment d'utiliser la matière retirée pour faire ces trous et de limiter ainsi les pertes. Elle permet aussi de faciliter par la suite l'introduction de l'outillage pour réaliser les découpes du matériau naturel pour la formation des barrettes. Dans cette configuration, on peut aussi prévoir que les axes de deux trous voisins sont distants l'un de l'autre d'une distance comprise entre 5 et 10 m, de préférence entre 6 à 8 m.In an extraction process according to the present invention, the holes made in the ground are for example circular cylindrical holes whose diameter is between 2 and 3 m, preferably between 2.2 and 2.6 m. This size of hole allows in particular to use the material removed to make these holes and thus limit losses. It also facilitates the introduction of the tooling to make the cuts of the natural material for the formation of the bars. In this configuration, it can also be provided that the axes of two adjacent holes are spaced from each other by a distance of between 5 and 10 m, preferably between 6 and 8 m.

Pour limiter l'emprise sur la surface du terrain et augmenter le rendement (en m3 par m2) de la carrière, la profondeur des trous réalisés correspond à plusieurs fois la hauteur d'une barrette et/ou plusieurs fois la hauteur d'un bloc, et les étapes b) à e) sont répétées de manière à réaliser une cavité, appelée aussi puits, de plus en plus profonde dans le sol.To limit the influence on the surface of the ground and increase the yield (in m3 per m2) of the quarry, the depth of the holes made corresponds to several times the height of a bar and / or several times the height of a block and steps b) to e) are repeated so as to make a cavity, also called a well, deeper and deeper in the soil.

Pour ne pas fragiliser le terrain environnant, notamment lorsque l'emprise au sol devient importante, il est prévu que les étapes de réalisation et d'extraction de barrettes et de blocs sont répétées de manière à réaliser au moins deux (ou plus encore) puits voisins, un puits correspondant à l'extraction de plusieurs barrettes et blocs contigus et que deux puits sont séparés au moins partiellement par une paroi sensiblement verticale. Cette paroi verticale forme ainsi un renfort naturel (il n'est pas rajouté mais correspond à de la matière naturelle qui n'a pas été affectée par l'extraction et qui possède donc sa structure et ses liaisons d'origine). Il est envisageable de créer des passages entre deux puits voisins tout en gardant des renforts. La création de ces passages permet d'extraire une plus grande quantité de matériau naturel. Elle permet aussi d'avoir une liaison entre les deux puits si ces derniers sont réutilisés par la suite.In order not to weaken the surrounding terrain, especially when the footprint becomes large, it is expected that the steps of realization and extraction of bars and blocks are repeated so as to achieve at least two (or more) wells neighbors, a well corresponding to the extraction of several contiguous strips and blocks and that two wells are at least partially separated by a substantially vertical wall. This vertical wall thus forms a natural reinforcement (it is not added but corresponds to the natural material which has not been affected by the extraction and which therefore has its original structure and links). It is conceivable to create passages between two neighboring wells while keeping reinforcements. The creation of these passages makes it possible to extract a larger quantity of natural material. It also allows to have a connection between the two wells if they are reused thereafter.

Pour augmenter encore le rendement du présent procédé d'extraction, les trous sensiblement verticaux sont avantageusement réalisés en faisant une découpe périphérique de manière à récupérer au moins une partie du matériau correspondant. Une telle découpe périphérique peut être réalisée avec un outil tel celui décrit et revendiqué dans le document WO-2013/057442.To further increase the efficiency of the present extraction process, the substantially vertical holes are advantageously made by making a peripheral cut so as to recover at least a portion of the corresponding material. Such a peripheral cut can be made with a tool such as that described and claimed in WO-2013/057442.

La présente invention concerne également un procédé d'exploitation d'une carrière, caractérisé en ce qu'il comporte la mise en oeuvre d'un procédé d'extraction tel que décrit ci-dessus.The present invention also relates to a method of operating a quarry, characterized in that it comprises the implementation of an extraction method as described above.

Un tel procédé d'exploitation comporte des étapes définies pour l'extraction de matériau naturel hors du sol, lesdites étapes étant mises en œuvre de manière à réaliser un puits et ce procédé d'exploitation comporte en outre une étape d'aménagement dudit puits, par exemple en réalisant un plancher dans ledit puits. Ce plancher peut recouvrir le fond du puits -par exemple chape de béton (ou autre). Il peut s'agir aussi de la réalisation à une hauteur intermédiaire (ou à plusieurs hauteurs intermédiaires) d'un plancher. Tout matériau (béton, hourdis, poutres métalliques, bois, etc.) peut être utilisé pour la réalisation de ce plancher.Such an operating method comprises defined steps for the extraction of natural material from the ground, said steps being implemented so as to produce a well and this method of operation further comprises a step of fitting said well, for example by making a floor in said well. This floor can cover the bottom of the well-for example concrete screed (or other). It can also be the realization at an intermediate height (or several intermediate heights) of a floor. Any material (concrete, slabs, metal beams, wood, etc.) can be used for the realization of this floor.

Dans une variante de réalisation de ce procédé d'exploitation, on peut également prévoir des étapes de réalisation d'un bâtiment avec un toit couvrant au moins partiellement le réseau de trous réalisé dans le sol, ledit bâtiment pouvant être réalisé avant de faire les trous dans le sol. La réalisation d'un bâtiment avec un toit est indépendante de la réalisation de puits et/ou de sol(s) dans un puits. Un tel bâtiment permet de réaliser l'extraction de matériau naturel à couvert et donc d'améliorer grandement les conditions de travail des ouvriers intervenant pour réaliser cette extraction.In an alternative embodiment of this operating method, it is also possible to provide steps for producing a building with a roof at least partially covering the network of holes made in the ground, said building being able to be made before making the holes. in the ground. The realization of a building with a roof is independent of the realization of wells and / or soil (s) in a well. Such a building makes it possible to carry out the extraction of natural material under cover and thus to greatly improve the working conditions of the workers involved in carrying out this extraction.

Des détails et avantages de la présente invention apparaîtront mieux de la description qui suit, faite en référence au dessin schématique annexé sur lequel :Details and advantages of the present invention will become more apparent from the description which follows, given with reference to the appended schematic drawing in which:

La figure 1A est une vue en perspective illustrant une première étape d'un procédé d'extraction,FIG. 1A is a perspective view illustrating a first step of an extraction process,

La figure 1B est une vue de dessus de la figure 1 A,FIG. 1B is a view from above of FIG. 1A,

Les figures 2A-6A respectivement 2B-6B sont des vues correspondant à la figure 1A respectivement 1B pour des étapes ultérieures du procédé d'extraction, etFIGS. 2A-6A and 2B-6B respectively are views corresponding to FIG. 1A respectively 1B for subsequent steps of the extraction process, and

La figure 7 est une vue en perspective d'une carrière en cours d'exploitation ou à l’issue de son exploitation.Figure 7 is a perspective view of a quarry in operation or at the end of its operation.

Le procédé décrit ci-après est donné à titre purement illustratif. L'homme du métier comprendra notamment que l'ordre de certaines étapes peut être modifié sans changer sensiblement le résultat obtenu tout en présentant encore des avantages par rapport à un procédé d'extraction de l'art antérieur.The process described below is given purely by way of illustration. Those skilled in the art will understand in particular that the order of certain steps can be modified without substantially changing the result obtained while still having advantages over a prior art extraction method.

Comme illustré sur les figures 1A et 1B, il est proposé de réaliser un réseau de trous dans le sol. On suppose ici que l'on dispose d'un sol 2 sensiblement horizontal. Bien entendu, dans la nature il n'existe pas de sol parfaitement plan comme sur la figure. Il est toutefois possible de réaliser le réseau de trous aussi bien sur un terrain sensiblement plan, en plaine, que sur un terrain en pente, à flanc de coteau, sur une colline ou une montagne. Sur les figures, on a représenté à chaque fois un bloc parallélépipédique correspondant à un volume de sol duquel on va extraire du matériau naturel.As illustrated in FIGS. 1A and 1B, it is proposed to make a network of holes in the ground. It is assumed here that there is a substantially horizontal floor 2. Of course, in nature there is no perfectly flat ground as in the figure. However, it is possible to make the network of holes both on a substantially flat ground, in plain, on a slope, on a hillside, on a hill or mountain. In the figures, there is shown each time a parallelepiped block corresponding to a volume of soil from which we will extract natural material.

Dans la plupart des cas, que le sol soit sensiblement horizontal ou sensiblement en pente, les trous seront des trous s'étendant verticalement à partir de la surface 4 du sol. Cette orientation est naturelle et elle permettra de faciliter par la suite certaines opérations, notamment lorsqu'il s’agira de soulever des masses importantes pour les extraire du sol.In most cases, whether the soil is substantially horizontal or substantially sloping, the holes will be holes extending vertically from the surface 4 of the soil. This orientation is natural and it will facilitate subsequent operations, especially when it will lift large masses to extract them from the ground.

Les trous 6 sont de préférence des trous cylindriques circulaires. Cette forme est la plus facile à réaliser. Les trous seront faits de préférence avec un dispositif de forage qui réalise le trou en faisant tourner autour d'un axe de rotation un outil de forage dans sol.The holes 6 are preferably circular cylindrical holes. This form is the easiest to achieve. The holes will preferably be made with a drilling device that makes the hole by rotating a drilling tool around the ground about an axis of rotation.

Il est proposé ici de réaliser les trous dans le sol à l'aide d'un dispositif de forage tel celui décrit dans le document WO-2013/057442. Le procédé de forage des trous est alors par exemple un procédé tel celui décrit sur les pages 9 à 13 de ce document de l'art antérieur. Ce procédé permet de réaliser, étape par étape, des trous de diamètre important et aussi de grande profondeur en extrayant des blocs cylindriques de matériau naturel. Il est proposé ici de réaliser des trous dont le diamètre est de l'ordre de 2 à 3 mètres (m). Sur la figure 1A, une carotte 8 obtenue lors de la réalisation du forage d'un trou 6 du réseau en utilisant le dispositif de forage du document WO-2013/057442.It is proposed here to make the holes in the ground using a drilling device such as that described in WO-2013/057442. The method of drilling the holes is then for example a method such as that described on pages 9 to 13 of this document of the prior art. This method makes it possible to carry out, step by step, holes of large diameter and also of great depth by extracting cylindrical blocks of natural material. It is proposed here to make holes whose diameter is of the order of 2 to 3 meters (m). In FIG. 1A, a core 8 obtained during the drilling of a hole 6 of the network using the drilling device of document WO-2013/057442.

Les trous 6 réalisés présentent par exemple un diamètre de l'ordre de 2,4 à 2,5 m. On obtient alors des carottes 8 qui présentent un diamètre de plus de 2 m et qui peuvent tout à fait être exploitées après découpe, mise en forme et autres traitements.The holes 6 made have for example a diameter of the order of 2.4 to 2.5 m. Carrots 8 are obtained which have a diameter of more than 2 m and which can be fully exploited after cutting, shaping and other treatments.

Le réseau de trous 6 est réalisé par exemple sur la base d'un maillage rectangulaire, ou de préférence carré. Le pas entre deux trous 6 voisins (distance par exemple de centre à centre) est par exemple compris entre 5 et 10 m, de préférence entre 6 et 8 m. Ces dimensions sont données à titre illustratif pour donner un ordre de grandeur associé au procédé décrit ici. Elles ne sont toutefois pas limitatives. Bien entendu, en fonction des utilisations qui seront faites de la roche, ou autre matériau naturel, extraite, les dimensions des trous et le maillage seront adaptés. Pour des raisons de manipulations, il n'est en outre pas possible de découper de trop gros blocs de roche qui ne seraient pas transportables.The network of holes 6 is made for example on the basis of a rectangular mesh, or preferably square. The pitch between two adjacent holes 6 (distance for example from center to center) is for example between 5 and 10 m, preferably between 6 and 8 m. These dimensions are given by way of illustration to give an order of magnitude associated with the process described here. They are however not limiting. Of course, depending on the uses that will be made of the rock, or other natural material, extracted, the dimensions of the holes and the mesh will be adapted. For reasons of manipulation, it is also not possible to cut too large blocks of rock that would not be transportable.

Il est proposé ici de réaliser des trous 6 de grande profondeur, d'une dizaine à plusieurs dizaines de mètres, les uns après les autres, avant de continuer le procédé d'extraction.It is proposed here to make holes 6 of great depth, from ten to several tens of meters, one after the other, before continuing the extraction process.

Une deuxième étape est illustrée sur la figure 2 (figures 2A et 2B). Il s'agit ici d'extraire de la roche (on supposera dans la suite de la description que le matériau naturel exploité ici est de la roche, par exemple du granit, sans pour autant que le procédé d'extraction soit limité exclusivement à ce matériau).A second step is illustrated in Figure 2 (Figures 2A and 2B). This is to extract the rock (it will be assumed in the following description that the natural material used here is rock, for example granite, without the extraction process being limited exclusively to this type of rock. material).

Au cours de cette deuxième étape, un morceau de roche, appelé barrette 10, est extrait du sol. Pour extraire ladite barrette 10, on réalise une première découpe verticale 12 entre deux trous voisins jusqu'à une profondeur donnée, puis, toujours entre les deux mêmes trous 6, une seconde découpe verticale 14 est réalisée parallèlement et à distance de la première découpe verticale 12. Les deux découpes verticales sont réalisées jusqu'à une même profondeur. Elles peuvent être réalisées avec un fil de découpe tel celui décrit dans le document précité ou bien aussi avec un système de découpe du type de celui décrit dans le document FR2725931 ou bien encore WO-89/08525. Le dispositif de découpe peut pénétrer dans le sol au niveau des deux trous 6 se trouvant aux extrémités de la barrette 10. On définit de la sorte une portion de roche rattachée au reste du sol uniquement par une face inférieure. Pour détacher la barrette 10 du sol 2, il suffit qu'à la fin de la seconde découpe verticale 14, le système de découpe change de direction de découpe pour venir découper à l'horizontale et venir ainsi rejoindre le fond de la première découpe verticale 12.During this second stage, a piece of rock, called bar 10, is extracted from the ground. To extract said bar 10, a first vertical cut 12 is made between two adjacent holes to a given depth, then, still between the same two holes 6, a second vertical cut 14 is made parallel to and at a distance from the first vertical cutout. 12. The two vertical cuts are made to the same depth. They can be made with a cutting wire such as that described in the aforementioned document or also with a cutting system of the type described in document FR2725931 or even WO-89/08525. The cutting device can penetrate into the ground at the two holes 6 at the ends of the bar 10. In this way, a portion of rock attached to the remainder of the ground is defined only by a lower face. To detach the bar 10 from the floor 2, it suffices that at the end of the second vertical cut 14, the cutting system changes cutting direction to come cut horizontally and come and join the bottom of the first vertical cut 12.

Des moyens de levage non décrits ici peuvent être alors utilisés pour venir sortir la barrette 10 du sol. Ces moyens de levage peuvent être des moyens de levage classiques, connus de l'homme du métier, habituellement utilisés pour soulever de lourdes charges (blocs de roche) dans une carrière. À titre purement illustratif, si les trous 6 ont un diamètre de 2,5 m et que la distance entre deux trous voisins est de 7,5 m, alors une barrette 10 présentera une longueur de l'ordre de 5 m, une largeur de l'ordre de 2 m et une hauteur déterminée en fonction de l'utilisation qui sera faite de la roche de la barrette 10 et aussi bien entendu des possibilités de levage des moyens de levage utilisés. En fonction de ces derniers, les dimensions du maillage de trous dans le sol auront déjà été adaptées.Lifting means not described here can then be used to come out of the bar 10 soil. These lifting means may be conventional lifting means, known to those skilled in the art, usually used to lift heavy loads (blocks of rock) in a quarry. By way of illustration, if the holes 6 have a diameter of 2.5 m and the distance between two adjacent holes is 7.5 m, then a strip 10 will have a length of the order of 5 m, a width of the order of 2 m and a height determined according to the use to be made of the rock of the bar 10 and of course the lifting possibilities of the lifting means used. Depending on the latter, the dimensions of the mesh of holes in the ground will have already been adapted.

Les figures 2A et 2B suggèrent de retirer successivement des barrettes 10 du sol jusqu'à arriver au fond de deux trous 6 voisins. Ainsi, le dispositif de découpe reste en place au niveau de deux trous 6 voisins jusqu'à ce que toutes les barrettes 10 pouvant être découpées entre ces deux trous soient retirées du sol.Figures 2A and 2B suggest successively removing strips 10 from the ground until reaching the bottom of two neighboring holes 6. Thus, the cutting device remains in place at two neighboring holes 6 until all the bars 10 that can be cut between these two holes are removed from the ground.

Sur les figures jointes, un nombre limité de trous 6 a été représentés. Ces trous 6 sont disposés, dans la forme de réalisation purement illustrative du dessin, selon un maillage à maille carrée, sur trois lignes L1, L2 et L3 et huit colonnes C1 à C8.In the accompanying figures, a limited number of holes 6 has been shown. These holes 6 are arranged, in the purely illustrative embodiment of the drawing, in a mesh square mesh, three lines L1, L2 and L3 and eight columns C1 to C8.

Sur la figure 3, il est proposé dans une étape suivante de retirer des barrettes 10 entre d'autres trous 6. Ainsi, il est proposé ici de retirer des barrettes 10 orientées selon les lignes L1-L3 entre les colonnes Ci, Ci+1 sauf entre les colonnes C4 et C5.In FIG. 3, it is proposed in a next step to withdraw strips 10 between other holes 6. Thus, it is proposed here to remove strips 10 oriented along lines L1-L3 between columns Ci, Ci + 1 except between columns C4 and C5.

Dans les étapes suivantes, comme illustré sur la figure 4, des barrettes 10 orientées selon la direction des colonnes Ci sont extraites du sol. Le procédé ici peut être tout à fait le même que pour la première barrette 10 comme proposé plus haut. Sur la figure 4, les barrettes 10 sont extraites du sol sur la colonne C1 entre les lignes L1 et L2.In the following steps, as illustrated in Figure 4, bars 10 oriented in the direction of the columns Ci are extracted from the ground. The method here can be quite the same as for the first bar 10 as proposed above. In FIG. 4, the bars 10 are extracted from the ground on the column C1 between the lines L1 and L2.

Par la suite, comme illustré sur la figure 5, toutes les barrettes 10 orientées selon des colonnes Ci sont extraites. Une fois toutes les barrettes 10 retirées, il reste douze piliers 16 qui s'étendent chacun verticalement depuis un fond 18 d'un puits 20. De par les découpes des barrettes 10, en omettant de découper et retirer les barrettes sur les lignes Li entre les colonnes C4 et C5, on a réalisé deux puits 20 voisins.Subsequently, as illustrated in FIG. 5, all the bars 10 oriented along columns Ci are extracted. Once all the bars 10 have been removed, there remain twelve pillars 16 which each extend vertically from a bottom 18 of a well 20. By the cutouts of the bars 10, omitting to cut and remove the bars on the lines Li between C4 and C5 columns, two neighboring wells were made.

Par des découpes horizontales, les piliers 16 sont "tranchés" pour former des blocs de roche. Dans l'exemple numérique donné précédemment, chaque bloc présente en vue de dessus une forme sensiblement carrée d'environ 5 m de côté. La hauteur du bloc de roche est adaptée ici aussi en fonction de l'utilisation prévue de la roche et des possibilités de levage des moyens de levage disponibles. Comme suggéré sur la figure 6, si un bloc de grande hauteur est souhaitée (par exemple avec une dimension supérieure à 5 m dans l'exemple numérique précédent), alors une découpe horizontale est faite à la hauteur souhaitée et, afin de pouvoir lever extraire la roche du sol avec les moyens de levage disponibles, des découpes verticales supplémentaires sont prévues. La figure 6 propose de couper un bloc en six "sous-blocs". On a ainsi par exemple des "sous-blocs" présentant des dimensions de 6,0 x 2,5 x 1,7 m.By horizontal cuts, the pillars 16 are "sliced" to form blocks of rock. In the numerical example given above, each block has in a top view a substantially square shape of about 5 m side. The height of the block of rock is adapted here also according to the intended use of the rock and the lifting possibilities of the lifting means available. As suggested in FIG. 6, if a high-rise block is desired (for example with a dimension greater than 5 m in the previous numerical example), then a horizontal cut is made at the desired height and, in order to be able to lift out the soil rock with the available lifting means, additional vertical cuts are provided. Figure 6 proposes to cut a block into six "sub-blocks". For example, there are "sub-blocks" having dimensions of 6.0 x 2.5 x 1.7 m.

La figure 7 illustre le sol 2 une fois l'exploitation terminée. Pour optimiser la quantité de roche extraite, ou bien pour relier entre eux les deux puits 20, ou pour d'autres raisons, il est proposé de retirer de la roche encore entre les deux puits 20. En fonction des dimensions des puits 20, il est préférable, comme illustré sur la figure 7, de laisser des renforts entre les puits 20. Le terrain alentour n'est de ce fait pas fragilisé par l'exploitation du sol qui a été faite. Les dimensions de chaque puits dépendront de la nature du terrain et de sa stabilité et/ou également de l'utilisation ultérieure éventuelle qui sera faite du puits. Une originalité du procédé proposé est en effet la possibilité de réhabilitation du site d'exploitation qu'il propose. Ainsi l'extraction est réalisée non seulement en fonction des contraintes liées à l'extraction mais également en fonction des prévisions d'utilisation du site par la suite, une fois l'extraction de roche ou similaire terminée.Figure 7 illustrates the soil 2 when the operation is completed. To optimize the quantity of rock extracted, or to interconnect the two wells 20, or for other reasons, it is proposed to remove rock still between the two wells 20. Depending on the dimensions of the wells 20, It is preferable, as illustrated in FIG. 7, to leave reinforcements between the wells 20. The surrounding terrain is thus not weakened by the exploitation of the soil that has been made. The size of each well will depend on the nature of the land and its stability and / or the subsequent possible use of the well. An originality of the proposed process is indeed the possibility of rehabilitation of the exploitation site that it proposes. Thus the extraction is carried out not only according to the constraints related to the extraction but also according to the site use forecasts thereafter, once the rock extraction or the like completed.

Le procédé décrit ci-dessus permet de parfaitement maîtriser l'emprise à la surface du sol pour l'exploitation de la carrière. Dans l'exemple illustré au dessin, une emprise de 55 x 17,5 m, soit moins de 1.000 m2, permet en creusant à 25 m d'extraire environ 20.000 m3 de roche. Une telle carrière présente donc un très bon rendement. L'emprise sur la surface du sol étant parfaitement maîtrisée, il est possible de recouvrir la carrière avec un toit. En effet, il suffit de construire un hangar au-dessus du réseau de trous -avant ou après la réalisation de ce réseau de trous- pour travailler au sec.The method described above makes it possible to perfectly control the footprint on the soil surface for quarrying. In the example shown in the drawing, a footprint of 55 x 17.5 m, or less than 1,000 m2, allows digging at 25 m to extract about 20,000 m3 of rock. Such a career therefore has a very good performance. The footprint on the ground surface being perfectly controlled, it is possible to cover the quarry with a roof. Indeed, it is enough to build a shed above the network of holes - before or after the realization of this network of holes - to work dry.

Les nuisances sont limitées avec le procédé décrit ci-dessus. Bien entendu, il y a des nuisances sonores dues au fonctionnement des engins utilisés, aux moyens de transport et aux dispositifs de forage et découpage de la roche. Elles sont cependant limitées par rapport aux nuisances constatées habituellement par une carrière d'extraction de roche. Ce sont surtout les nuisances esthétiques qui sont le plus réduites. Après exploitation du sol et extraction de la roche, il reste des trous dans le sol qui ne viennent pas dénaturer le paysage environnant.The nuisances are limited with the method described above. Of course, there is noise pollution due to the operation of the equipment used, the means of transport and the drilling and cutting devices of the rock. However, they are limited compared to the nuisance usually found in a rock quarry. It is mainly the aesthetic nuisance that is the most reduced. After exploitation of the soil and extraction of the rock, there are holes in the soil that do not denature the surrounding landscape.

De plus, le site peut être par la suite réhabilité. Une dalle peut être réalisée au fond ou à une hauteur intermédiaire dans un puits de manière à former un ou plusieurs plancher(s) dans le puits. Il est possible ainsi de réaliser un bâtiment semi enterré. Les puits peuvent aussi être utilisés pour le stockage de matériaux, ou comme réserve d'eau, ou comme cuve de méthanisation, ....In addition, the site can be rehabilitated. A slab can be made at the bottom or at an intermediate height in a well so as to form one or more floor (s) in the well. It is possible to build a semi-buried building. The wells can also be used for the storage of materials, or as a water reserve, or as an anaerobic digestion tank, ....

Le procédé proposé est aussi bien adapté à des exploitations de petites dimensions (par exemple limitée à deux puits comme illustré sur le dessin annexé) qu'à des exploitations de grande taille : il suffit en effet d'adapter le réseau de trous, la profondeur d'exploitation. Des puits peuvent être réalisés ou non, etc...The proposed method is also well suited to small farms (for example limited to two wells as shown in the accompanying drawing) that large farms: it suffices to adapt the network of holes, the depth operating. Wells can be made or not, etc.

Grâce à la limitation des nuisances et/ou à la possibilité d'avoir une carrière de petites dimensions, le procédé -et donc le lieu d'exploitation- peut être mis en œuvre à proximité d'une ville ou d'un site d'utilisation des roches extraites.With the limitation of nuisances and / or the possibility of having a career of small dimensions, the process - and therefore the place of exploitation - can be implemented near a city or a site of use of extracted rocks.

Le procédé proposé peut s'adapter à tout type de terrain (plan, en pente, ...). Il est extrêmement modulable et peut ainsi s'adapter à toute configuration.The proposed process can adapt to any type of terrain (plan, slope, ...). It is extremely flexible and can adapt to any configuration.

La présente invention ne se limite pas au procédé décrit ci-dessus et aux variantes envisagées. Elle concerne également toutes les variantes évoquées et les variantes à la portée de l'homme du métier dans le cadre des revendications ci-après.The present invention is not limited to the method described above and the variants envisaged. It also relates to all the variants mentioned and variants within the scope of the skilled person within the scope of the claims below.

Claims (10)

REVENDICATIONS 1. Procédé d'extraction de matériaux naturels hors d'un sol (2), caractérisé en ce qu'il comporte selon un ordre d'exécution variable, les étapes suivantes : a) réalisation d'un réseau de trous (6) sensiblement verticaux dans le sol (2) selon un maillage prédéfini, les trous (6) présentant d'un diamètre supérieur à 1 m, b) réalisation de deux découpes (12, 14) sensiblement verticales entre deux trous (6) voisins, c) réalisation d'une découpe sensiblement horizontale entre deux découpes verticales (12, 14) de manière à détacher un bloc, appelé barrette, se trouvant entre deux trous (6) voisins, et extraction de ladite barrette (10), d) répétition des étapes b) et c) de manière à former une tranchée de forme polygonale délimitant ainsi un bloc, e) réalisation d'une découpe horizontale sous le bloc de manière à le libérer du sol et extraction dudit bloc, ledit bloc pouvant être d'un seul tenant ou en plusieurs morceaux.1. A method of extracting natural materials from a soil (2), characterized in that it comprises in a variable order of execution, the following steps: a) realization of a network of holes (6) substantially vertical in the ground (2) in a predefined mesh, the holes (6) having a diameter greater than 1 m, b) producing two cuts (12, 14) substantially vertical between two holes (6) neighbors, c) performing a substantially horizontal cut between two vertical cuts (12, 14) so as to detach a block, called a bar, located between two adjacent holes (6), and extraction of said bar (10), d) repetition of the steps b) and c) so as to form a trench polygonal shape thus delimiting a block, e) making a horizontal cut under the block so as to release it from the ground and extraction of said block, said block being able to be of a single holding or in several pieces. 2. Procédé d'extraction selon la revendication 1, caractérisé en ce que les trous (6) dans le sol (2) définissent un maillage rectangulaire.2. Extraction process according to claim 1, characterized in that the holes (6) in the ground (2) define a rectangular mesh. 3. Procédé d'extraction selon l'une des revendications 1 ou 2, caractérisé en ce que les trous (6) réalisés dans le sol (2) sont des trous cylindriques circulaires dont le diamètre est compris entre 2 et 3 m, de préférence entre 2,2 et 2,6 m.3. Extraction process according to one of claims 1 or 2, characterized in that the holes (6) made in the ground (2) are circular cylindrical holes whose diameter is between 2 and 3 m, preferably between 2.2 and 2.6 m. 4. Procédé d'extraction selon la revendication 3, caractérisé en ce que les axes de deux trous (6) voisins sont distants l'un de l'autre d'une distance comprise entre 5 et 10 m, de préférence entre 6 à 8 m.4. Extraction method according to claim 3, characterized in that the axes of two adjacent holes (6) are spaced from each other by a distance of between 5 and 10 m, preferably between 6 and 8. m. 5. Procédé d'extraction selon l'une des revendications 1 à 4, caractérisé en ce que la profondeur des trous (6) réalisés correspond à plusieurs fois la hauteur d'une barrette (10) et/ou plusieurs fois la hauteur d'un bloc, et en ce que les étapes b) à e) sont répétées de manière à réaliser une cavité, appelée aussi puits (20), de plus en plus profonde dans le sol.5. extraction process according to one of claims 1 to 4, characterized in that the depth of the holes (6) made is several times the height of a bar (10) and / or several times the height of a block, and in that steps b) to e) are repeated so as to make a cavity, also called well (20), deeper and deeper in the ground. 6. Procédé d'extraction selon l'une des revendications 1 à 5, caractérisé en ce que les étapes de réalisation et d'extraction de barrettes (10) et de blocs sont répétées de manière à réaliser au moins deux puits (20) voisins, un puits (20) correspondant à l'extraction de plusieurs barrettes (10) et blocs contigus et les deux puits (20) étant séparés au moins partiellement par une paroi sensiblement verticale.6. Extraction process according to one of claims 1 to 5, characterized in that the steps of producing and extracting strips (10) and blocks are repeated so as to achieve at least two wells (20) neighbors , a well (20) corresponding to the extraction of several strips (10) and contiguous blocks and the two wells (20) being at least partially separated by a substantially vertical wall. 7. Procédé d’extraction selon, l'une des revendications 1 à 6, caractérisé en ce que les trous (6) sensiblement verticaux sont réalisés en faisant une découpe périphérique de manière à récupérer au moins une partie du matériau correspondant.7. The extraction method according to one of claims 1 to 6, characterized in that the holes (6) substantially vertical are made by making a peripheral cut so as to recover at least a portion of the corresponding material. 8. Procédé d'exploitation d'une carrière, caractérisé en ce qu'il comporte la mise en œuvre d'un procédé d'extraction selon l'une des revendications 1 à 7.8. A method of operating a quarry, characterized in that it comprises the implementation of an extraction method according to one of claims 1 to 7. 9. Procédé d'exploitation selon la revendication 8, caractérisé en ce que les étapes définies à la revendication 1 sont mises en œuvre de manière à réaliser un puits (20) et en ce que le procédé d'exploitation comporte alors une étape d'aménagement dudit puits afin de réaliser un plancher dans ledit puits.9. Operating method according to claim 8, characterized in that the steps defined in claim 1 are implemented so as to achieve a well (20) and in that the operating method then comprises a step of installing said well to achieve a floor in said well. 10. Procédé d'exploitation selon l'une des revendications 8 ou 9, caractérisé en ce qu'il comporte des étapes de réalisation d'un bâtiment avec un toit couvrant au moins partiellement le réseau de trous réalisé dans le sol, ledit bâtiment pouvant être réalisé avant de faire les trous dans le sol.10. Operating method according to one of claims 8 or 9, characterized in that it comprises steps of producing a building with a roof at least partially covering the network of holes made in the ground, said building being able to be made before making holes in the ground.
FR1655131A 2016-06-06 2016-06-06 PROCESS FOR EXTRACTING NATURAL MATERIALS, IN PARTICULAR ROCKS Expired - Fee Related FR3052181B1 (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
FR1655131A FR3052181B1 (en) 2016-06-06 2016-06-06 PROCESS FOR EXTRACTING NATURAL MATERIALS, IN PARTICULAR ROCKS
ES17174565T ES2724407T3 (en) 2016-06-06 2017-06-06 Procedure for extracting natural materials, mainly from rocks
EP17174565.6A EP3255243B1 (en) 2016-06-06 2017-06-06 Method for extracting natural materials, in particular rocks
PT17174565T PT3255243T (en) 2016-06-06 2017-06-06 Method for extracting natural materials, in particular rocks

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR1655131A FR3052181B1 (en) 2016-06-06 2016-06-06 PROCESS FOR EXTRACTING NATURAL MATERIALS, IN PARTICULAR ROCKS
FR1655131 2016-06-06

Publications (2)

Publication Number Publication Date
FR3052181A1 true FR3052181A1 (en) 2017-12-08
FR3052181B1 FR3052181B1 (en) 2018-07-06

Family

ID=56896710

Family Applications (1)

Application Number Title Priority Date Filing Date
FR1655131A Expired - Fee Related FR3052181B1 (en) 2016-06-06 2016-06-06 PROCESS FOR EXTRACTING NATURAL MATERIALS, IN PARTICULAR ROCKS

Country Status (4)

Country Link
EP (1) EP3255243B1 (en)
ES (1) ES2724407T3 (en)
FR (1) FR3052181B1 (en)
PT (1) PT3255243T (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1989008525A1 (en) * 1988-03-11 1989-09-21 British Aerospace Plc Method and apparatus for cutting a solid block from one face of a workpiece
CN102678125B (en) * 2012-05-08 2015-03-18 江显秋 Sawing wire cutter for cave mining of mineral materials and cave mining method for mineral materials

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2600375B1 (en) 1986-06-18 1988-11-04 Bristot Frederic PROCESS FOR OPERATING A QUARRY AND DIRECT DEBITING OF STONES OR THE LIKE AND DEVICE FOR IMPLEMENTING SAME
FR2725931A1 (en) 1994-10-20 1996-04-26 Dg Construction Method of cutting of surface in material block
FR2981682B1 (en) 2011-10-19 2013-12-27 Ctic Sarl BIG DIAMETER DRILLING DEVICE

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1989008525A1 (en) * 1988-03-11 1989-09-21 British Aerospace Plc Method and apparatus for cutting a solid block from one face of a workpiece
CN102678125B (en) * 2012-05-08 2015-03-18 江显秋 Sawing wire cutter for cave mining of mineral materials and cave mining method for mineral materials

Also Published As

Publication number Publication date
PT3255243T (en) 2019-05-28
EP3255243B1 (en) 2019-02-13
EP3255243A1 (en) 2017-12-13
FR3052181B1 (en) 2018-07-06
ES2724407T3 (en) 2019-09-10

Similar Documents

Publication Publication Date Title
EP0240493A1 (en) Method for compaction-trussing-injection or decompaction-draining and construction of linear works or planar works in grounds.
CH711708B1 (en) Split slabs.
CH694431A5 (en) The process of formation of a retaining wall of a massive reinforced and reinforcing element for its implementation.
EP3255243B1 (en) Method for extracting natural materials, in particular rocks
FR2504953A1 (en) METHOD OF CONSTRUCTING A SECOND WALL CONSISTING OF CONCRETE PILES AND SECURE WALL THUS OBTAINED
FR2930111A1 (en) PROCESS FOR PRODUCING A VEGETABLE WALL
CH628382A5 (en) Construction element for the erection of walls, particularly retaining walls
KR101245252B1 (en) Masonry construction methods and construction stone units
FR2976004A1 (en) STRUCTURE COMPRISING A WALL IN GABIONS
EP0242497A1 (en) Tunnel construction process
FR2478716A2 (en) Socket for installing telegraph posts or fence posts - is made from folded sheet metal elements fitting inside one another to interlock
EP1082505B1 (en) Building demolition method and implementing equipment
KR200307169Y1 (en) Fence for slant ground
FR2807456A1 (en) Base for walls, barricade or road side slope is made of juxtaposed wired cylinders with apertures to receive rods to attach them together
EP3914779B1 (en) Prefabricated stackable caisson
CN214993792U (en) Collapse hillock protection network and use firm stake
FR2647481A1 (en) METHOD FOR REALIZING A FREE VOLUME IN THE BASEMENT BETWEEN EXISTING BUILDINGS AND CONSTRUCTION OBTAINED
KR102036985B1 (en) Recovery method of waste mine
WO2010003428A4 (en) Technique for building a stone pyramid independently from the shape of the base surface
CH699202A1 (en) Building block walls.
EP3320147B1 (en) Method for constructing a foundation including a step of cutting-of
FR2894267A1 (en) Outer separation structure manufacturing method for forming e.g. partition wall, involves pouring grout of hardenable material in formwork to form anchoring units such that formwork and excavations are simultaneously filled with grout
EP0353370A1 (en) Building substructure
FR2969672A1 (en) Method for enhancing resistance of foundation structure of pylon monopode, involves filling volume of trench with material including hydraulic binder to form wall adjacent to foundation structure
CA2022197A1 (en) Natural acoustical screen on composite wall

Legal Events

Date Code Title Description
PLFP Fee payment

Year of fee payment: 2

PLSC Publication of the preliminary search report

Effective date: 20171208

PLFP Fee payment

Year of fee payment: 3

PLFP Fee payment

Year of fee payment: 4

ST Notification of lapse

Effective date: 20210206