EP3699391B1 - Soil drilling device and method for drilling in soil - Google Patents

Soil drilling device and method for drilling in soil Download PDF

Info

Publication number
EP3699391B1
EP3699391B1 EP20158158.4A EP20158158A EP3699391B1 EP 3699391 B1 EP3699391 B1 EP 3699391B1 EP 20158158 A EP20158158 A EP 20158158A EP 3699391 B1 EP3699391 B1 EP 3699391B1
Authority
EP
European Patent Office
Prior art keywords
sled
carriage
holder
drilling
drill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
EP20158158.4A
Other languages
German (de)
French (fr)
Other versions
EP3699391A1 (en
Inventor
Rene Schrinner
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tracto Technik GmbH and Co KG
Original Assignee
Tracto Technik GmbH and Co KG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tracto Technik GmbH and Co KG filed Critical Tracto Technik GmbH and Co KG
Publication of EP3699391A1 publication Critical patent/EP3699391A1/en
Application granted granted Critical
Publication of EP3699391B1 publication Critical patent/EP3699391B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/02Couplings; joints
    • E21B17/021Devices for subsurface connecting or disconnecting by rotation
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B17/00Drilling rods or pipes; Flexible drill strings; Kellies; Drill collars; Sucker rods; Cables; Casings; Tubings
    • E21B17/02Couplings; joints
    • E21B17/04Couplings; joints between rod or the like and bit or between rod and rod or the like
    • E21B17/042Threaded
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/20Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/28Enlarging drilled holes, e.g. by counterboring
    • E21B7/30Enlarging drilled holes, e.g. by counterboring without earth removal

Definitions

  • the invention relates to an earth drilling device for drilling in the ground using a drill rod and a method for drilling in the ground using a drill rod.
  • Earth drilling devices in particular horizontal drilling devices, are used in order to drill earth holes, for example for supply and disposal lines, into the ground in a trenchless manner, or to replace old lines that have already been laid without trenching.
  • a drill rod having drill rod sections is usually used, in which the drill rod sections can be connected to one another.
  • EP 0 886 034 B1 It is known to use a carriage reciprocable in a frame for advancing and/or pulling a drill string.
  • the carriage has a socket for a section of drill string, so that the section of drill string can be moved in the direction of a feed axis to create the earth bore in the socket.
  • the drive acting on the drill rod section can have a rotational and/or translational effect on the drill rod section in the receptacle.
  • Another example of this can be EN19917538 be removed.
  • the holder of the drill rod that has already been inserted (drilled) into the ground is usually released and the carriage is moved in the opposite direction to the feed direction and a new drill rod section, which is to be connected to the drill rod that has already been drilled, placed in the mount of the slide.
  • the carriage is then moved in the feed direction and the drill string section is connected, in particular screwed, to the drill string that has already been drilled.
  • threads are arranged at the ends of the drill rod sections, which threads are used for screwing the drill rod sections.
  • the carriage For bolting on a drill string, it is common to "unlock" the carriage such that the carriage can move during the formation of the connection of the socket to the drill string and the connection of the string to the drilled string. Accordingly, the carriage moves in the direction of the drill string essentially by the length that is predetermined by the screwing process or processes. There are two screwing operations to be considered. On the one hand, screwing the new rod section to the drill rod and screwing the holder to the new rod section. Once the screwing process has been completed, the carriage must first be moved again carefully by means of the drive, in particular until the path that has been set by the screwing process or processes has been compensated for. Only then can you continue drilling with a higher feed force and higher speed.
  • the invention was therefore based on the object of creating an improved earth drilling device and a method for drilling in the ground, with which improved drilling of a ground drilling is possible, in particular faster drilling of the ground drilling is possible.
  • the core idea of the invention is to carry out a receptacle for a rod section, which is to be screwed to the drill rod that has already been drilled, so that it can be displaced relative to the carriage. Because the receptacle can be moved relative to the carriage, in particular in the direction of the drill rod or away from it, it is possible to compensate for a change in the position of the receptacle caused by the screwing in relation to the rod section to be screwed or loosened. It must also be taken into account that the position of the new rod section to be added also changes when it is connected to the drill rod and the receptacle.
  • the slide itself can - although the recording itself moved to compensate for the change in length caused by the screwing - stand still and, in particular, remain in direct frictional contact with the drive driving the carriage. In this way, the drilling process can be continued immediately after the screwing process.
  • a careful approach of the carriage after the lengthening of the drill string by means of a rod section to be screwed to the drilled drill string can be reduced or omitted entirely.
  • the inventors have broken with the idea that the mount must be rigid to the slide. Providing relative movement between the socket and the carriage contradicted the previous idea that there must be a solid, unchanging or fixed connection between the socket and the carriage in order to transmit the high forces required to be applied to the drill string.
  • the invention provides an earth-boring device for drilling in the ground by means of a drill rod, the earth-boring device having a drill carriage and a carriage that can be moved translationally on the drill carriage.
  • a receptacle is arranged on the carriage.
  • the receptacle is provided for screwing a section of rod to the drill rod or for loosening a section of rod from the drill rod by screwing.
  • the receptacle can be moved in translation relative to the carriage in that a carrier carrying the receptacle is slidably arranged on the carriage and is selectively releasably fixed to the carriage in order to compensate for a change in the position of the receptacle caused by the screwing.
  • an earth drilling device includes any device that moves, in particular, a drill rod containing rod sections in an existing or to be created channel in the ground, in order to create or widen a bore, in particular a horizontal bore, or to create lines or other long bodies to sink into the ground.
  • An earth drilling device can comprise a drive device which drives a drill rod in a pulling and/or pushing or pushing manner. It can additionally or alternatively be provided that the drive device drives the drill pipe in rotation.
  • An earth boring device can be a device that drives a drill string and that works in particular to displace soil.
  • horizontal drilling in the sense of the present description includes in particular any type of existing or to be created preferably at least partially horizontally running channels in a body, in particular earth channels including earth drilling, rock drilling or earth lines as well as underground or above-ground pipelines and water channels, which can be produced or drawn in by using an appropriate earth boring device.
  • drill pipe as used in the description includes any means that can be introduced into the ground in order to make a borehole in the ground.
  • the drill rod can in particular have a rod, a chain and/or a cable.
  • the term “drill rods” in the sense of the description does not exclusively include rigid drill rods having individual rod sections connected directly or indirectly to one another, but in particular all power transmission elements that can be used in an earth drilling device.
  • the drill rod assembly in particular at a front end, can comprise a drill head and/or a drill head tip that may be present or an area adjacent to the drill head that is configured as a drilling tool or has it.
  • the term "drilling rig” includes a particularly mobile frame on which a carriage for moving the drill string can be provided, which can be moved back and forth in the direction of the drill string axis in order to push or pull the drill string in the ground.
  • the carriage can be moved relative to the drill carriage using a linear drive.
  • the drill carriage can also have one or more clamping devices, via which the drill rod or a rod section to be attached can be fixed. It can be provided that a clamping device is provided on the drill mast, by means of which the free end of the drill rod (the end protruding from the ground) can be fixed in order to enable a new rod section to be connected to the drill rod that has already been drilled.
  • a receptacle is provided on the carriage, which can accommodate a new rod section to be added or removed, in particular at the end, in such a way that the receptacle fixes the rod section in a non-positive and/or positive manner in order to be able to drive the rod section, in particular rotating it about its longitudinal axis .
  • the receptacle can, for example, be designed in such a way that the receptacle comes into engagement at the end with a rod section that is to be loosened or screwed on, and a form fit is produced. If the recording is rotated, the rod section recorded by the recording can be rotated.
  • the term "position" of the receptacle or a section of rod includes, in particular, the position of the receptacle or section of rod as specified by the movement along the drill rig, with the position being able to change in particular in that the Recording located rod section bolted to the drill rod and the recording or unscrewed from this can be.
  • a change in position is thus a translational movement of the receptacle along the drill string axis.
  • the change in the position of the recording to be screwed or loosened rod section corresponds to the change in the position of the recording to the drill rod drilled.
  • the invention describes the fact that a carrier carrying the receptacle is slidably arranged on the carriage and can be fixed on the carriage.
  • the carriage can thus have a substructure relative to which the carrier can be displaced.
  • an optional fixation with the carriage/substructure or an optional fixation in relation to the carriage/substructure can be achieved. If the carrier is fixed relative to the carriage/substructure, the carriage/substructure and carrier can move together. If the fixation between the carrier and the carriage is selectively released, a relative movement between the carrier and the carriage can take place, with the result that the receptacle carried by the carrier can move relative to the carriage. While the carriage remains frictionally connected to the drive that drives the carriage, the receptacle can be moved with the carrier.
  • the direction in which the carrier can be displaced in relation to the carriage is aligned essentially in the direction of the drill rod or offset parallel to it.
  • the carrier can be fixed to the carriage by means of a bolt, which can be actuated, in particular, hydraulically.
  • a bolt on the carrier or carriage/substructure can move into a corresponding recess in the other of the two elements of the carrier and carriage.
  • a form fit can be formed between the carrier and the carriage in such a way that this form fit acts transversely to the direction in which the carrier can be displaced relative to the carriage/substructure.
  • the form fit is preferably formed in a direction which, very particularly preferably, forms an angle with the direction of displacement between the carrier and the carriage/substructure of more than 50°, in particular more than 60°, in particular more than 70°, in particular more than 80° has 90°.
  • a frictional connection can also be provided.
  • a sensor for detecting the end of the screwing process there is a sensor for detecting the end of the screwing process, the signal from which can be received by a control device in order to fix the receptacle to the carriage.
  • a control device in order to fix the receptacle to the carriage.
  • the introduction of the earth drilling device can be controlled largely automatically. If the sensor has detected the end of the screwing process, a signal which the sensor makes available to the control device can be used to indicate to the control device that fixing is to be carried out again can. In particular, if a carrier is provided, the carrier can be fixed again on the carriage/substructure.
  • control device in the sense of the description encompasses an embodiment of a controller, by means of which a directed influencing of the earth drilling device during operation, i.e. while carrying out or for starting or stopping an earth drilling, is possible.
  • the control device can be configured electrically or electronically.
  • Inputs and/or parameters entered by an operator for carrying out the drilling can be used by the control device—if necessary converted and/or processed into electrical signals—as inputs for the operation of the earth drilling device.
  • the earth drilling device can thus be operated or controlled by means of an input, in particular a parameter that may have been converted into an electrical signal.
  • a “parameter” in the sense of the description is understood to mean an input with which the operation of the earth drilling device can be influenced in a targeted manner.
  • the parameter can be transmitted to the control device as an input signal, by means of which the control device controls the operation of the earth drilling device.
  • a parameter can cause, for example, starting drilling with the earth drilling device or stopping drilling carried out with the earth drilling device.
  • the senor can be a limit switch, a proximity switch, a position switch or the like.
  • the receptacle is automatically or semi-automatically fixed to the carriage/substructure by means of a signal from a sensor.
  • the sensor can detect the position of the receptacle and/or a carrier that may be present.
  • a pressure sensor can be provided, which detects an increase in pressure in the hydraulic drive of the rotation for recording when the threads are closed or moved to the stop.
  • an input device which supplies a signal which can be received by a control device in order to achieve fixing of the drive means to the carriage/base.
  • the term "input device" in the context of the description includes any electrical or electronic device that is suitable for converting an input from an operator into an electrical signal.
  • the electrical signal can be processed without further processing or transmitted to the control device with the interposition of a processing of the signal, in particular a processing in one or more circuits, for example in an amplifier, in order to serve as an input or as an input signal of the control device.
  • the input device can be understood as an interface between an operator and the control device.
  • the input device can in particular be a keyboard, a joystick, a microphone, a switch, a push button or the like.
  • the invention also provides a method for drilling in soil by means of a drill string, wherein a translationally movable carriage is used for pulling and/or pushing the drill string.
  • a receptacle is arranged on the carriage, with which a rod section is screwed to or unscrewed from a drill rod. The receptacle is moved in a translatory manner relative to the carriage to compensate for a change in the position of the receptacle caused by the screwing.
  • the invention will be described in terms of two aspects relating to an earth boring device and a method for boring in soil.
  • the explanations on the individual aspects complement one another, so that the explanations for the earth drilling device are also to be understood as explanations of the description for the method and vice versa.
  • the description of the earth drilling device also discloses actions in the sense of the method or method steps relating to the method and vice versa.
  • the naming of a numerical value not only includes the actual numerical value, but also - in order to take into account production tolerances in particular - a range around the specific numerical value, which is +/-15%, preferably +/-10% , can be of the specified numerical value.
  • FIG. 1 shows a ground drilling device 1 in a schematic representation from the side, which works in a soil-displacing manner.
  • a drill rod which has rod sections 5, can be introduced into the ground in a translatory and rotary manner.
  • a carriage 4 can be moved back and forth on a drill carriage 2 .
  • the drill carriage 2 defines a drill rod axis 7 with the carriage 4 or a receptacle 3.
  • the receptacle 3 is designed on the carriage 4 in the form of an adapter or connection, by means of which a new rod section 5 to be connected is connected to the drill rod that has already been drilled and then can be placed in the ground.
  • the rod sections 5 are screwed together. For this purpose, corresponding threads that interact with one another are provided on the rod sections 5 at the ends.
  • the receptacle 3 forms a form fit with the rod section 5 to be connected to the drill rod that has already been drilled.
  • the rod section 5 is screwed to the bored drill rod and the receptacle 3 and then the carriage 4 is moved in the direction of the drill rod axis 7 on the drill carriage 2 .
  • the 2 shows a schematic view of the state before the receptacle 3 is connected to the rod section 5.
  • the carriage 4 has the receptacle 3, which is firmly connected to a carrier 9 with this.
  • the receptacle 3 is fixed to the carrier 9 in the direction of the drill rod axis 7 .
  • the receptacle 3 can rotate, but cannot be moved relative to the carrier 9.
  • the receptacle 3 can be displaced relative to a substructure 8 of the carriage 4, with the carrier 9 being able to be fixed relative to the substructure 8 as desired.
  • a form fit between a bolt 10 and a receiving bore 12 is provided.
  • the bolt 10 is designed as a displaceable bolt on the carrier 9 .
  • the bolt 10 is part of a locking device 6.
  • the bolt 10 can be moved in and out by means of a hydraulic cylinder 11. in the in 2
  • the position shown is that the carriage 4 is in a rear position on the drill carriage 2 and has moved onto a rod section 5 that is to be screwed to a drill string that is already in the ground.
  • the carrier 9 has shifted backwards in relation to the substructure 8 in the opposite direction to the drilling direction.
  • the carrier 9 is pulled forward on the substructure 8 .
  • the bolt 10 is in the retracted state during the screwing process, as shown in 2 is shown.
  • the bolt 10 can move into the receiving bore 12 of the substructure 8 and now prevents relative movement between the substructure 8 and the carrier 9.
  • the drilling process is now continued immediately; the carriage 4 can be moved as a whole, so that the carrier 9 and the substructure 8 can be moved together. A closing of the carriage 4 or substructure 8 until the carrier 9 hits the stop 13 can be avoided.
  • the bolt 10 can retract and the carrier 9 can move back with the receptacle 3 and the process of connecting a new rod section 5 to the drill rod that has been drilled can begin again.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Description

Die Erfindung betrifft eine Erdbohrvorrichtung zum Bohren in Erdreich mittels eines Bohrgestänges und ein Verfahren zum Bohren in Erdreich mittels eines Bohrgestänges.The invention relates to an earth drilling device for drilling in the ground using a drill rod and a method for drilling in the ground using a drill rod.

Erdbohrvorrichtungen, insbesondere Horizontalbohrvorrichtungen, kommen zum Einsatz, um in grabenloser Bauweise Erdbohrungen beispielsweise für Versorgungs- und Entsorgungsleitungen in das Erdreich einzubringen bzw. bereits verlegte Altleitungen grabenlos auszutauschen. Zum Einbringen der Erdbohrungen wird meist ein Bohrgestängeschüsse aufweisendes Bohrgestänge verwendet, bei dem die Bohrgestängeschüsse miteinander verbindbar sind.Earth drilling devices, in particular horizontal drilling devices, are used in order to drill earth holes, for example for supply and disposal lines, into the ground in a trenchless manner, or to replace old lines that have already been laid without trenching. In order to drill the earth bores, a drill rod having drill rod sections is usually used, in which the drill rod sections can be connected to one another.

Es ist beispielsweise aus EP 0 886 034 B1 bekannt, einen in einem Rahmen hin- und herbewegbaren Schlitten zum Vorschieben und/oder Ziehen eines Bohrgestänges zu verwenden. Der Schlitten weist eine Aufnahme für einen Bohrgestängeschuss auf, so dass der Bohrgestängeschuss in Richtung einer Vorschubachse zur Erstellung der Erdbohrung in der Aufnahme bewegt werden kann. Der auf den Bohrgestängeschuss wirkende Antrieb kann rotatorisch und/oder translatorisch auf den Bohrgestängeschuss in der Aufnahme wirken. Ein weiteres Beispiel diesbezüglich kann der DE 19917538 entnommen werden.For example, it's over EP 0 886 034 B1 It is known to use a carriage reciprocable in a frame for advancing and/or pulling a drill string. The carriage has a socket for a section of drill string, so that the section of drill string can be moved in the direction of a feed axis to create the earth bore in the socket. The drive acting on the drill rod section can have a rotational and/or translational effect on the drill rod section in the receptacle. Another example of this can be EN19917538 be removed.

Beim Gestängewechsel bzw. Verlängern eines Bohrgestänges wird üblicherweise die Aufnahme von dem bereits in das Erdreich eingebrachten (verbohrten) Bohrgestänge gelöst und der Schlitten entgegen der Vorschubrichtung verfahren und ein neuer Bohrgestängeschuss, der mit dem bereits verbohrten Bohrgestänge verbunden werden soll, in die Aufnahme des Schlittens eingebracht. Der Schlitten wird dann in Vorschubrichtung bewegt und der Bohrgestängeschuss mit dem schon verbohrten Bohrgestänge verbunden, insbesondere verschraubt. Hierzu sind an den Bohrgestängeschüssen endseitig Gewinde angeordnet, die zum Verschrauben der Bohrgestängeschüsse dienen. Zum Anschrauben eines Bohrgestängeschusses ist es üblich, den Schlitten derart "freizuschalten", dass sich der Schlitten während des Ausbildens der Verbindung der Aufnahme mit dem Gestängeschuss und dem Verbinden des Gestängeschusses mit dem verbohrten Bohrgestänge bewegen kann. Der Schlitten bewegt sich demzufolge in Richtung des Bohrstranges im Wesentlichen um die Länge, die durch den bzw. die Schraubvorgänge vorgegeben ist. Dabei sind zwei Schraubvorgänge zu berücksichtigen. Zum einen das Verschrauben des neuen Gestängeschusses mit dem Bohrgestänge als auch das Verschrauben der Aufnahme mit dem neuen Gestängeschuss. Ist der Schraubvorgang abgeschlossen, muss eine Bewegung des Schlittens mittels des Antriebs erst wieder vorsichtig durchgeführt werden, insbesondere bis der Weg, der sich durch den bzw. die Schraubvorgänge eingestellt hat, ausgeglichen ist. Erst dann kann wieder mit einer höheren Vorschubkraft und höherer Geschwindigkeit weiter gebohrt werden.When changing rods or lengthening a drill rod, the holder of the drill rod that has already been inserted (drilled) into the ground is usually released and the carriage is moved in the opposite direction to the feed direction and a new drill rod section, which is to be connected to the drill rod that has already been drilled, placed in the mount of the slide. The carriage is then moved in the feed direction and the drill string section is connected, in particular screwed, to the drill string that has already been drilled. For this purpose, threads are arranged at the ends of the drill rod sections, which threads are used for screwing the drill rod sections. For bolting on a drill string, it is common to "unlock" the carriage such that the carriage can move during the formation of the connection of the socket to the drill string and the connection of the string to the drilled string. Accordingly, the carriage moves in the direction of the drill string essentially by the length that is predetermined by the screwing process or processes. There are two screwing operations to be considered. On the one hand, screwing the new rod section to the drill rod and screwing the holder to the new rod section. Once the screwing process has been completed, the carriage must first be moved again carefully by means of the drive, in particular until the path that has been set by the screwing process or processes has been compensated for. Only then can you continue drilling with a higher feed force and higher speed.

Nachteilig ist daher, dass bei jeder Verlängerung des Bohrgestänges um einen weiteren Bohrgestängeschuss immer wieder ein neues Anfahren des Schlittens erfolgen muss und die Zeit zum Einbringen der Erdbohrung erhöht ist.It is therefore disadvantageous that each time the drill rod is lengthened by a further section of drill rod, the carriage has to be started up again and again, and the time required to drill the earth bore is increased.

Der Erfindung lag daher die Aufgabe zugrunde, eine verbesserte Erdbohrvorrichtung und ein Verfahren zum Bohren in Erdreich zu schaffen, mit der bzw. dem ein verbessertes Einbringen einer Erdbohrung möglich ist, insbesondere ein schnelleres Einbringen der Erdbohrung möglich ist.The invention was therefore based on the object of creating an improved earth drilling device and a method for drilling in the ground, with which improved drilling of a ground drilling is possible, in particular faster drilling of the ground drilling is possible.

Die Aufgabe wird durch die Gegenstände der nebengeordneten Patentansprüche gelöst. Vorteilhafte Weiterbildungen der Gegenstände der nebengeordneten Patentansprüche sind Gegenstand der jeweiligen abhängigen Patentansprüche und ergeben sich aus der nachfolgenden Beschreibung.The object is achieved by the subject matter of the independent patent claims. Advantageous developments of the subject matter of the subordinate patent claims are the subject matter of the respective dependent patent claims and result from the following description.

Kerngedanke der Erfindung ist es, eine Aufnahme für einen Gestängeschuss, der mit dem schon verbohrten Bohrgestänge schraubend verbunden werden soll, relativ verschieblich zum Schlitten auszuführen. Durch die Verschieblichkeit der Aufnahme relativ zum Schlitten, insbesondere in Richtung des Bohrgestänges bzw. von diesem weg, ist es möglich, einen Ausgleich einer durch das Schrauben hervorgerufenen Änderung der Lage der Aufnahme in Bezug auf den zu verschraubenden bzw. zu lösenden Gestängeschuss durchzuführen. Dabei ist auch zu berücksichtigen, dass sich die Lage des neu hinzuzufügenden Gestängeschusses auch beim Verbinden mit dem Bohrgestänge und der Aufnahme verändert. Der Schlitten selbst kann - obwohl sich die Aufnahme zum Ausgleich der Längenänderung durch das Schrauben bewegt - stillstehen und insbesondere in direktem Kraftschluss mit dem den Schlitten antreibenden Antrieb verbleiben. So kann unmittelbar nach dem Schraubvorgang der Bohrvorgang fortgesetzt werden. Ein vorsichtiges Anfahren des Schlittens nach dem Verlängern des Bohrgestänges mittels eines zu verschraubenden Gestängeschusses mit dem verbohrten Bohrgestänge kann verringert werden oder ganz entfallen.The core idea of the invention is to carry out a receptacle for a rod section, which is to be screwed to the drill rod that has already been drilled, so that it can be displaced relative to the carriage. Because the receptacle can be moved relative to the carriage, in particular in the direction of the drill rod or away from it, it is possible to compensate for a change in the position of the receptacle caused by the screwing in relation to the rod section to be screwed or loosened. It must also be taken into account that the position of the new rod section to be added also changes when it is connected to the drill rod and the receptacle. The slide itself can - although the recording itself moved to compensate for the change in length caused by the screwing - stand still and, in particular, remain in direct frictional contact with the drive driving the carriage. In this way, the drilling process can be continued immediately after the screwing process. A careful approach of the carriage after the lengthening of the drill string by means of a rod section to be screwed to the drilled drill string can be reduced or omitted entirely.

Die Erfinder haben mit der Vorstellung gebrochen, dass die Aufnahme starr zum Schlitten vorliegen muss. Eine relative Bewegung zwischen der Aufnahme und dem Schlitten vorzusehen, widersprach der bisherigen Vorstellung, dass bei der Übertragung der hohen erforderlichen Kräfte, die auf das Bohrgestänge aufgebracht werden, eine massive, unveränderliche bzw. feste Verbindung zwischen der Aufnahme und dem Schlitten vorliegen muss.The inventors have broken with the idea that the mount must be rigid to the slide. Providing relative movement between the socket and the carriage contradicted the previous idea that there must be a solid, unchanging or fixed connection between the socket and the carriage in order to transmit the high forces required to be applied to the drill string.

Die Erfindung schafft eine Erdbohrvorrichtung zum Bohren in Erdreich mittels eines Bohrgestänges, wobei die Erdbohrvorrichtung eine Bohrlafette und einen auf der Bohrlafette translatorisch bewegbaren Schlitten aufweist. Auf dem Schlitten ist eine Aufnahme angeordnet. Die Aufnahme ist zum schraubenden Verbinden eines Gestängeschusses mit dem Bohrgestänge oder zum schraubenden Lösen eines Gestängeschusses vom Bohrgestänge vorgesehen. Die Aufnahme zum Schlitten ist relativ translatorisch bewegbar, indem an dem Schlitten ein die Aufnahme tragender Träger verschiebbar angeordnet ist, der am Schlitten wahlweise lösbar fixiert ist, um für einen Ausgleich einer durch das Schrauben hervorgerufenen Änderung der Lage der Aufnahme zu sorgen.The invention provides an earth-boring device for drilling in the ground by means of a drill rod, the earth-boring device having a drill carriage and a carriage that can be moved translationally on the drill carriage. A receptacle is arranged on the carriage. The receptacle is provided for screwing a section of rod to the drill rod or for loosening a section of rod from the drill rod by screwing. The receptacle can be moved in translation relative to the carriage in that a carrier carrying the receptacle is slidably arranged on the carriage and is selectively releasably fixed to the carriage in order to compensate for a change in the position of the receptacle caused by the screwing.

Der Begriff "Erdbohrvorrichtung" umfasst im Sinne der Beschreibung jedwede Vorrichtung, die insbesondere ein Gestängeschüsse aufweisendes Bohrgestänge in einem bestehenden oder zu erstellenden Kanal in Erdreich bewegt, um eine Bohrung, insbesondere eine Horizontalbohrung, zu erstellen oder aufzuweiten, oder um Leitungen oder andere lange Körper in das Erdreich einzuziehen. Eine Erdbohrvorrichtung kann eine ein Bohrgestänge ziehend und/oder drückend bzw. schiebend antreibende Antriebsvorrichtung umfassen. Es kann zusätzlich oder alternativ vorgesehen sein, dass die Antriebsvorrichtung das Bohrgestänge rotatorisch antreibt. Eine Erdbohrvorrichtung kann eine ein Bohrgestänge antreibende Vorrichtung sein, die insbesondere Erdreich verdrängend arbeitet.In the context of the description, the term "earth drilling device" includes any device that moves, in particular, a drill rod containing rod sections in an existing or to be created channel in the ground, in order to create or widen a bore, in particular a horizontal bore, or to create lines or other long bodies to sink into the ground. An earth drilling device can comprise a drive device which drives a drill rod in a pulling and/or pushing or pushing manner. It can additionally or alternatively be provided that the drive device drives the drill pipe in rotation. An earth boring device can be a device that drives a drill string and that works in particular to displace soil.

Der Begriff "Horizontalbohrung" (horizontal drilling) im Sinne der vorliegenden Beschreibung umfasst insbesondere jede Art von bestehenden oder zu erstellenden vorzugsweise zumindest abschnittsweise horizontal verlaufenden Kanälen in einem Körper, insbesondere Erdkanäle einschließlich Erdbohrungen, Felsbohrungen oder Erdleitungen sowie unterirdische oder oberirdische Rohrleitungen und Wasserkanäle, die sich durch Einsatz einer entsprechenden Erdbohrvorrichtung herstellen oder einziehen lassen.The term "horizontal drilling" (horizontal drilling) in the sense of the present description includes in particular any type of existing or to be created preferably at least partially horizontally running channels in a body, in particular earth channels including earth drilling, rock drilling or earth lines as well as underground or above-ground pipelines and water channels, which can be produced or drawn in by using an appropriate earth boring device.

Der Begriff "Bohrgestänge" im Sinne der Beschreibung umfasst jedwedes Mittel, das im Erdreich eingebracht werden kann, um eine Bohrung in das Erdreich einzubringen. Das Bohrgestänge kann insbesondere ein Gestänge, eine Kette und/oder ein Seil aufweisen. Der Begriff "Bohrgestänge" umfasst dabei im Sinne der Beschreibung nicht ausschließlich starre, einzelne miteinander mittelbar oder unmittelbar verbundene Gestängeschüsse aufweisende Bohrgestänge, sondern insbesondere sämtliche Kraftübertragungselemente, die bei einer Erdbohrvorrichtung eingesetzt werden können. Ferner kann das Bohrgestänge, insbesondere an einem vorderseitigen Ende, einen Bohrkopf und/oder eine gegebenenfalls vorhandene Bohrkopfspitze oder einen dem Bohrkopf benachbarten Bereich umfassen, der als Bohrwerkzeug ausgestaltet ist bzw. dieses aufweist.The term "drill pipe" as used in the description includes any means that can be introduced into the ground in order to make a borehole in the ground. The drill rod can in particular have a rod, a chain and/or a cable. The term "drill rods" in the sense of the description does not exclusively include rigid drill rods having individual rod sections connected directly or indirectly to one another, but in particular all power transmission elements that can be used in an earth drilling device. Furthermore, the drill rod assembly, in particular at a front end, can comprise a drill head and/or a drill head tip that may be present or an area adjacent to the drill head that is configured as a drilling tool or has it.

Der Begriff "Bohrlafette" umfasst ein, insbesondere fahrbares, Gestell, auf dem ein Schlitten zum Bewegen des Bohrgestänges vorgesehen sein kann, der in Richtung der Bohrgestängeachse hin- und her bewegbar ist, um das Bohrgestänge drückend oder ziehend im Erdreich zu bewegen. Der Schlitten kann relativ zur Bohrlafette unter Verwendung eines Linearantriebs bewegt werden. Die Bohrlafette kann ferner eine oder mehrere Klemmeinrichtungen, über die das Bohrgestänge bzw. ein anzusetzender Gestängeschuss fixiert werden kann, aufweisen. Es kann vorgesehen sein, dass eine Klemmvorrichtung an der Bohrlafette vorgesehen ist, mittels derer das freie Ende des Bohrgestänges (das aus dem Erdreich herausragende Ende) fixiert werden kann, um ein Verbinden eines neu anzusetzenden Gestängeschusses mit dem schon verbohrten Bohrgestänge zu ermöglichen.The term "drilling rig" includes a particularly mobile frame on which a carriage for moving the drill string can be provided, which can be moved back and forth in the direction of the drill string axis in order to push or pull the drill string in the ground. The carriage can be moved relative to the drill carriage using a linear drive. The drill carriage can also have one or more clamping devices, via which the drill rod or a rod section to be attached can be fixed. It can be provided that a clamping device is provided on the drill mast, by means of which the free end of the drill rod (the end protruding from the ground) can be fixed in order to enable a new rod section to be connected to the drill rod that has already been drilled.

An dem Schlitten ist eine Aufnahme vorgesehen, die einen neu hinzuzufügenden bzw. einen zu lösenden Gestängeschuss, insbesondere endseitig, derart aufnehmen kann, dass die Aufnahme den Gestängeschuss kraft- und/oder formschlüssig fixiert, um den Gestängeschuss insbesondere drehend um seine Längsachse antreiben zu können. Die Aufnahme kann beispielsweise derart ausgestaltet sein, dass die Aufnahme endseitig in Eingriff mit einem zu lösenden bzw. zu verschraubenden Gestängeschuss gelangt und ein Formschluss erzeugt wird. Wird die Aufnahme gedreht, so kann der von der Aufnahme aufgenommene Gestängeschuss gedreht werden.A receptacle is provided on the carriage, which can accommodate a new rod section to be added or removed, in particular at the end, in such a way that the receptacle fixes the rod section in a non-positive and/or positive manner in order to be able to drive the rod section, in particular rotating it about its longitudinal axis . The receptacle can, for example, be designed in such a way that the receptacle comes into engagement at the end with a rod section that is to be loosened or screwed on, and a form fit is produced. If the recording is rotated, the rod section recorded by the recording can be rotated.

Der Begriff "Lage" der Aufnahme bzw. eines Gestängeschusses umfasst im Sinne der Beschreibung insbesondere die Lage der Aufnahme bzw. des Gestängeschusses, wie diese durch das Verfahren entlang der Bohrlafette vorgegeben ist, wobei die Lage sich insbesondere dadurch verändern kann, dass der in der Aufnahme befindliche Gestängeschuss mit dem Bohrgestänge und der Aufnahme verschraubt bzw. von diesem losgeschraubt werden kann. Im Wesentlichen ist eine Änderung der Lage damit eine translatorische Bewegung der Aufnahme entlang der Bohrgestängeachse. Die Änderung der Lage der Aufnahme zum zu verschraubenden oder zu lösenden Gestängeschuss entspricht der Änderung der Lage der Aufnahme zum verbohrten Bohrgestänge.In the context of the description, the term "position" of the receptacle or a section of rod includes, in particular, the position of the receptacle or section of rod as specified by the movement along the drill rig, with the position being able to change in particular in that the Recording located rod section bolted to the drill rod and the recording or unscrewed from this can be. In essence, a change in position is thus a translational movement of the receptacle along the drill string axis. The change in the position of the recording to be screwed or loosened rod section corresponds to the change in the position of the recording to the drill rod drilled.

Die Erfindung beschreibt, dass an dem Schlitten ein die Aufnahme tragender Träger verschiebbar angeordnet, der am Schlitten fixierbar ist. Der Schlitten kann somit einen Unterbau aufweisen, gegenüber dem der Träger verschiebbar ist. Mittels des Trägers, der die Aufnahme trägt, kann eine wahlweise Fixierung mit dem Schlitten/Unterbau bzw. eine wahlweise Fixierung gegenüber dem Schlitten/Unterbau erreicht werden. Ist der Träger gegenüber dem Schlitten/Unterbau fixiert, so können sich Schlitten/Unterbau und Träger gemeinsam bewegen. Wird die Fixierung zwischen Träger und Schlitten wahlweise gelöst, so kann eine Relativbewegung zwischen dem Träger und dem Schlitten erfolgen mit dem Resultat, dass die von dem Träger getragene Aufnahme sich relativ zum Schlitten bewegen kann. Während der Schlitten im Kraftschluss mit dem den Schlitten antreibenden Antrieb verbleibt, kann die Aufnahme mit dem Träger verschoben werden. Dabei ist die Richtung, in der der Träger gegenüber dem Schlitten verschiebbar ist, im Wesentlichen in Richtung des Bohrgestänges bzw. parallel versetzt zu diesem ausgerichtet.The invention describes the fact that a carrier carrying the receptacle is slidably arranged on the carriage and can be fixed on the carriage. The carriage can thus have a substructure relative to which the carrier can be displaced. By means of the carrier, which carries the receptacle, an optional fixation with the carriage/substructure or an optional fixation in relation to the carriage/substructure can be achieved. If the carrier is fixed relative to the carriage/substructure, the carriage/substructure and carrier can move together. If the fixation between the carrier and the carriage is selectively released, a relative movement between the carrier and the carriage can take place, with the result that the receptacle carried by the carrier can move relative to the carriage. While the carriage remains frictionally connected to the drive that drives the carriage, the receptacle can be moved with the carrier. The direction in which the carrier can be displaced in relation to the carriage is aligned essentially in the direction of the drill rod or offset parallel to it.

In einer bevorzugten Ausführungsform ist der Träger am Schlitten mittels eines Bolzens, der insbesondere hydraulisch betätigbar ist, fixierbar. Hierdurch kann eine besonders einfache Ausgestaltung erreicht werden. Ein Bolzen am Träger oder Schlitten/Unterbau kann in eine entsprechende Aussparung des anderen der beiden Elemente von Träger und Schlitten einfahren. Insbesondere kann ein Formschluss derart zwischen dem Träger und dem Schlitten ausgebildet werden, dass dieser Formschluss quer zur Richtung wirkt, in der der Träger gegenüber dem Schlitten/Unterbau relativ verschieblich ist. Bevorzugt ist der Formschluss in einer Richtung ausgebildet, die einen Winkel mit der Verschiebungsrichtung zwischen dem Träger und dem Schlitten/Unterbau von mehr als 50°, insbesondere mehr als 60°, insbesondere mehr als 70°, insbesondere mehr als 80°, ganz besonders bevorzugt 90° aufweist. Alternativ oder zusätzlich kann auch ein Kraftschluss vorgesehen sein.In a preferred embodiment, the carrier can be fixed to the carriage by means of a bolt, which can be actuated, in particular, hydraulically. As a result, a particularly simple configuration can be achieved. A bolt on the carrier or carriage/substructure can move into a corresponding recess in the other of the two elements of the carrier and carriage. In particular, a form fit can be formed between the carrier and the carriage in such a way that this form fit acts transversely to the direction in which the carrier can be displaced relative to the carriage/substructure. The form fit is preferably formed in a direction which, very particularly preferably, forms an angle with the direction of displacement between the carrier and the carriage/substructure of more than 50°, in particular more than 60°, in particular more than 70°, in particular more than 80° has 90°. Alternatively or additionally, a frictional connection can also be provided.

In einer bevorzugten Ausführungsform ist ein Sensor zum Erkennen des Endes des Schraubvorgangs vorhanden, dessen Signal von einer Steuereinrichtung empfangen werden kann, um ein Fixieren der Aufnahme zum Schlitten zu erreichen. Hierdurch kann weitestgehend automatisch das Einbringen der Erdbohrvorrichtung gesteuert werden. Sofern mittels des Sensors das Ende des Schraubvorgangs erkannt wurde, kann mittels eines Signals, das der Sensor der Steuereinrichtung zur Verfügung stellt, der Steuereinrichtung angezeigt werden, dass eine Fixierung wieder durchgeführt werden kann. Insbesondere kann - sofern ein Träger vorgesehen ist - der Träger wieder am Schlitten/Unterbau fixiert werden.In a preferred embodiment, there is a sensor for detecting the end of the screwing process, the signal from which can be received by a control device in order to fix the receptacle to the carriage. In this way, the introduction of the earth drilling device can be controlled largely automatically. If the sensor has detected the end of the screwing process, a signal which the sensor makes available to the control device can be used to indicate to the control device that fixing is to be carried out again can. In particular, if a carrier is provided, the carrier can be fixed again on the carriage/substructure.

Der Begriff "Steuereinrichtung" im Sinne der Beschreibung umfasst eine Ausgestaltung einer Steuerung, mittels derer eine gerichtete Beeinflussung der Erdbohrvorrichtung im Betrieb, d.h. während der Durchführung oder zum Starten oder Stoppen einer Erdbohrung, möglich ist. Die Steuereinrichtung kann insbesondere elektrisch oder elektronisch ausgestaltet sein. Von einer Bedienperson eingegebene Eingaben und/oder Parameter zur Durchführung der Bohrung können von der Steuereinrichtung - gegebenenfalls umgewandelt und/oder aufbereitet in elektrische Signale - als Eingaben für den Betrieb der Erdbohrvorrichtung verwendet werden. Die Erdbohrvorrichtung kann damit mittels einer Eingabe, insbesondere eines Parameters, der gegebenenfalls in ein elektrisches Signal umgewandelt wurde, betrieben bzw. gesteuert werden.The term "control device" in the sense of the description encompasses an embodiment of a controller, by means of which a directed influencing of the earth drilling device during operation, i.e. while carrying out or for starting or stopping an earth drilling, is possible. In particular, the control device can be configured electrically or electronically. Inputs and/or parameters entered by an operator for carrying out the drilling can be used by the control device—if necessary converted and/or processed into electrical signals—as inputs for the operation of the earth drilling device. The earth drilling device can thus be operated or controlled by means of an input, in particular a parameter that may have been converted into an electrical signal.

Als "Parameter" im Sinne der Beschreibung wird eine Eingabe verstanden, mit der eine gerichtete Beeinflussung des Betriebs der Erdbohrvorrichtung möglich ist. Der Parameter kann als Eingabesignal an die Steuereinrichtung übermittelt werden, mittels dem die Steuereinrichtung den Betrieb der Erdbohrvorrichtung steuert. Ein Parameter kann beispielsweise ein Starten des Bohrens mit der Erdbohrvorrichtung oder ein Stoppen eines mit der Erdbohrvorrichtung durchgeführten Bohrens bewirken.A “parameter” in the sense of the description is understood to mean an input with which the operation of the earth drilling device can be influenced in a targeted manner. The parameter can be transmitted to the control device as an input signal, by means of which the control device controls the operation of the earth drilling device. A parameter can cause, for example, starting drilling with the earth drilling device or stopping drilling carried out with the earth drilling device.

In einer bevorzugten Ausführungsform kann der Sensor ein Endschalter, ein Näherungsschalter, ein Positionsschalter oder ähnliches sein. In einer bevorzugten Ausführungsform wird die Aufnahme am Schlitten/Unterbau automatisch oder halbautomatisch mittels eines Signals eines Sensors fixiert. Der Sensor kann die Position der Aufnahme und/oder eines gegebenenfalls vorhandenen Trägers erfassen. Es kann alternativ oder zusätzlich ein Drucksensor vorgesehen sein, der im Hydraulikantrieb der Rotation für die Aufnahme einen Druckanstieg erfasst, wenn die Gewinde zugefahren bzw. auf Anschlag gefahren werden.In a preferred embodiment, the sensor can be a limit switch, a proximity switch, a position switch or the like. In a preferred embodiment, the receptacle is automatically or semi-automatically fixed to the carriage/substructure by means of a signal from a sensor. The sensor can detect the position of the receptacle and/or a carrier that may be present. Alternatively or additionally, a pressure sensor can be provided, which detects an increase in pressure in the hydraulic drive of the rotation for recording when the threads are closed or moved to the stop.

In einer bevorzugten Ausführungsform ist eine Eingabeeinrichtung vorgesehen, die ein Signal liefert, das von einer Steuereinrichtung empfangen werden kann, um ein Fixieren des Antriebsmittels zum Schlitten/Unterbau zu erreichen. Hierdurch kann die Möglichkeit geschaffen werden, dass eine Bedienperson händisch ein Fixieren der Aufnahme zum Schlitten/Unterbau erreichen kann. Eine Bedienperson überwacht dabei den Vorgang des Hinzufügens bzw. Entfernens des letzten Gestängeschusses am Bohrgestänge.In a preferred embodiment, an input device is provided which supplies a signal which can be received by a control device in order to achieve fixing of the drive means to the carriage/base. As a result, the possibility can be created that an operator can manually fix the receptacle to the carriage/substructure. An operator monitors the process of adding or removing the last rod section on the drill rod.

Der Begriff "Eingabeeinrichtung" im Sinne der Beschreibung umfasst jedwede elektrische oder elektronische Vorrichtung, die geeignet ist, eine Eingabe einer Bedienperson in ein elektrisches Signal umzuwandeln. Das elektrische Signal kann ohne weiter aufbereitet zu werden oder unter Zwischenschaltung einer Aufbereitung des Signals, insbesondere eines Prozessierens in einer oder mehreren Schaltungen, beispielsweise in einem Verstärker, an die Steuereinrichtung übermittelt werden, um als Eingabe bzw. als Eingabesignal der Steuereinrichtung zu dienen. Die Eingabeeinrichtung kann als Schnittstelle zwischen einer Bedienperson und der Steuereinrichtung verstanden werden. Die Eingabeeinrichtung kann insbesondere eine Tastatur, ein Joystick, ein Mikrofon, ein Schalter, ein Druckknopf oder ähnliches sein.The term "input device" in the context of the description includes any electrical or electronic device that is suitable for converting an input from an operator into an electrical signal. The electrical signal can be processed without further processing or transmitted to the control device with the interposition of a processing of the signal, in particular a processing in one or more circuits, for example in an amplifier, in order to serve as an input or as an input signal of the control device. The input device can be understood as an interface between an operator and the control device. The input device can in particular be a keyboard, a joystick, a microphone, a switch, a push button or the like.

Die Erfindung schafft auch ein Verfahren zum Bohren in Erdreich mittels eines Bohrgestänges, wobei ein translatorisch bewegbarer Schlitten zum Ziehen und/oder Drücken des Bohrgestänges verwendet wird. Auf dem Schlitten ist eine Aufnahme angeordnet, mit der ein Gestängeschuss mit einem Bohrgestänge verschraubt oder von diesem abgeschraubt wird. Die Aufnahme wird relativ translatorisch zum Schlitten bewegt für ein Ausgleichen einer durch das Schrauben hervorgerufenen Änderung der Lage der Aufnahme.The invention also provides a method for drilling in soil by means of a drill string, wherein a translationally movable carriage is used for pulling and/or pushing the drill string. A receptacle is arranged on the carriage, with which a rod section is screwed to or unscrewed from a drill rod. The receptacle is moved in a translatory manner relative to the carriage to compensate for a change in the position of the receptacle caused by the screwing.

Die Erfindung wird hinsichtlich zweier Aspekte beschrieben, die eine Erdbohrvorrichtung und ein Verfahren zum Bohren in Erdreich betreffen. Die Ausführungen zu den einzelnen Aspekten ergänzen einander, so dass die Ausführungen für die Erdbohrvorrichtung auch als Ausführungen der Beschreibung für das Verfahren und umgekehrt zu verstehen sind. Mit der Beschreibung der Erdbohrvorrichtung sind auch Handlungen im Sinne des Verfahrens bzw. Verfahrensschritte betreffend das Verfahren offenbart und umgekehrt.The invention will be described in terms of two aspects relating to an earth boring device and a method for boring in soil. The explanations on the individual aspects complement one another, so that the explanations for the earth drilling device are also to be understood as explanations of the description for the method and vice versa. The description of the earth drilling device also discloses actions in the sense of the method or method steps relating to the method and vice versa.

Im Sinne der Beschreibung umfasst die Nennung eines Zahlenwertes, insbesondere einer Winkelangabe, nicht nur den eigentlichen Zahlenwert, sondern auch - um insbesondere fertigungstechnische Toleranzen zu berücksichtigen - einen Bereich um den konkreten Zahlenwert, der +/-15%, bevorzugt +/-10%, vom angegebenen Zahlenwert sein kann.For the purpose of the description, the naming of a numerical value, in particular an indication of an angle, not only includes the actual numerical value, but also - in order to take into account production tolerances in particular - a range around the specific numerical value, which is +/-15%, preferably +/-10% , can be of the specified numerical value.

Die vorstehenden Ausführungen stellen ebenso wie die nachfolgende Beschreibung beispielhafter Ausführungsformen keinen Verzicht auf bestimmte Ausführungsformen oder Merkmale dar.The above statements, like the following description of exemplary embodiments, do not represent a waiver of certain embodiments or features.

Die Erfindung wird im Folgenden beispielhaft anhand eines in den Figuren dargestellten Ausführungsbeispiels näher erläutert.The invention is explained in more detail below using an exemplary embodiment illustrated in the figures.

In den Zeichnungen zeigt:

Fig. 1
eine Seitenansicht einer Erdbohrvorrichtung in schematischer Darstellung;
Fig. 2
einen Schlitten einer Erdbohrvorrichtung vor dem Anschrauben eines Gestängeschusses an ein schon verbohrtes Bohrgestänge; und
Fig. 3
einen Schlitten einer Erdbohrvorrichtung nach dem Anschrauben eines neuen Gestängeschusses an das schon verbohrte Bohrgestänge.
In the drawings shows:
1
a side view of a Erdbohrvorrichtung in a schematic representation;
2
a carriage of an earth boring device prior to bolting a drill section to an already drilled drill string; and
3
a carriage of an earth boring device after screwing a new rod section to the already drilled rod.

Fig. 1 zeigt in einer schematischen Darstellung von der Seite eine Erdbohrvorrichtung 1, die erdreichverdrängend arbeitet. Mittels der Erdbohrvorrichtung 1 kann ein Bohrgestänge, welches Gestängeschüsse 5 aufweist, in das Erdreich translatorisch als auch rotatorisch eingebracht werden. Dazu ist ein Schlitten 4 auf einer Bohrlafette 2 hin und her bewegbar. Die Bohrlafette 2 definiert mit dem Schlitten 4 bzw. einer Aufnahme 3 eine Bohrgestängeachse 7. An dem Schlitten 4 ist die Aufnahme 3 in Form eines Adapters bzw. Anschlusses ausgebildet, mittels der ein neu zu verbindender Gestängeschuss 5 mit dem schon verbohrten Bohrgestänge verbunden und dann in das Erdreich eingebracht werden kann. 1 shows a ground drilling device 1 in a schematic representation from the side, which works in a soil-displacing manner. By means of the earth drilling device 1, a drill rod, which has rod sections 5, can be introduced into the ground in a translatory and rotary manner. For this purpose, a carriage 4 can be moved back and forth on a drill carriage 2 . The drill carriage 2 defines a drill rod axis 7 with the carriage 4 or a receptacle 3. The receptacle 3 is designed on the carriage 4 in the form of an adapter or connection, by means of which a new rod section 5 to be connected is connected to the drill rod that has already been drilled and then can be placed in the ground.

Die Gestängeschüsse 5 werden miteinander verschraubt. Hierzu sind endseitig entsprechende miteinander zusammenwirkende Gewinde an den Gestängeschüssen 5 vorgesehen. Die Aufnahme 3 bildet einen Formschluss mit dem mit dem schon verbohrten Bohrgestänge zu verbindenden Gestängeschuss 5 aus. Der Gestängeschuss 5 wird mit dem verbohrten Bohrgestänge und der Aufnahme 3 verschraubt und anschließend der Schlitten 4 in Richtung der Bohrgestängeachse 7 auf der Bohrlafette 2 verfahren.The rod sections 5 are screwed together. For this purpose, corresponding threads that interact with one another are provided on the rod sections 5 at the ends. The receptacle 3 forms a form fit with the rod section 5 to be connected to the drill rod that has already been drilled. The rod section 5 is screwed to the bored drill rod and the receptacle 3 and then the carriage 4 is moved in the direction of the drill rod axis 7 on the drill carriage 2 .

Die Fig. 2 zeigt in einer schematischen Ansicht den Zustand, bevor die Aufnahme 3 mit dem Gestängeschuss 5 verbunden ist. Der Schlitten 4 weist die Aufnahme 3 auf, die auf einem Träger 9 fest mit diesem verbunden ist. Die Aufnahme 3 ist am Träger 9 in Richtung der Bohrgestängeachse 7 fixiert. Die Aufnahme 3 kann sich drehen, ist aber nicht verschieblich zum Träger 9.the 2 shows a schematic view of the state before the receptacle 3 is connected to the rod section 5. The carriage 4 has the receptacle 3, which is firmly connected to a carrier 9 with this. The receptacle 3 is fixed to the carrier 9 in the direction of the drill rod axis 7 . The receptacle 3 can rotate, but cannot be moved relative to the carrier 9.

Die Aufnahme 3 ist gegenüber einem Unterbau 8 des Schlittens 4 verschieblich, wobei der Träger 9 gegenüber dem Unterbau 8 wahlweise fixiert werden kann. Hierzu ist ein Formschluss zwischen einem Bolzen 10 und einer Aufnahmebohrung 12 vorgesehen. Der Bolzen 10 ist als verschiebbarer Bolzen am Träger 9 ausgestaltet. Der Bolzen 10 ist Teil einer Verriegelungsvorrichtung 6. Der Bolzen 10 kann mittels eines Hydraulikzylinders 11 ein- und ausgefahren werden. In der in Fig. 2 dargestellten Position ist der Schlitten 4 in einer hinteren Position auf der Bohrlafette 2 und auf einen neu mit einem bereits im Erdreich befindlichen Bohrstrang zu verschraubenden Gestängeschuss 5 aufgefahren. Der Träger 9 hat sich gegenüber dem Unterbau 8 nach hinten entgegen der Bohrrichtung verschoben. Durch das folgende Anschrauben der Aufnahme 3 an den neuen Gestängeschuss 5 und das Anschrauben des neuen Gestängeschusses 5 an einen bereits im Erdreich befindlichen, nicht dargestellten Bohrstrang, wird der Träger 9 auf dem Unterbau 8 nach vorne gezogen. Der Bolzen 10 befindet sich während des Anschraubvorgangs in eingefahrenem Zustand, wie es in Fig. 2 dargestellt ist.The receptacle 3 can be displaced relative to a substructure 8 of the carriage 4, with the carrier 9 being able to be fixed relative to the substructure 8 as desired. For this purpose, a form fit between a bolt 10 and a receiving bore 12 is provided. The bolt 10 is designed as a displaceable bolt on the carrier 9 . The bolt 10 is part of a locking device 6. The bolt 10 can be moved in and out by means of a hydraulic cylinder 11. in the in 2 The position shown is that the carriage 4 is in a rear position on the drill carriage 2 and has moved onto a rod section 5 that is to be screwed to a drill string that is already in the ground. The carrier 9 has shifted backwards in relation to the substructure 8 in the opposite direction to the drilling direction. By subsequently screwing the mount 3 onto the new rod section 5 and screwing on the new rod section 5 to a drill string not shown that is already in the ground, the carrier 9 is pulled forward on the substructure 8 . The bolt 10 is in the retracted state during the screwing process, as shown in 2 is shown.

Sind beide Gewinde des neuen Gestängeschusses 5, d.h. sowohl das vordere Gewinde mit dem schon verbohrten Bohrgestänge als auch das hintere Gewinde mit der Aufnahme 3 vollständig verschraubt, befindet sich der Träger 9 in einer, in Fig. 3 dargestellten, vorderen Position. Der Bolzen 10 kann in dieser Position des Trägers 9 relativ zum Unterbau 8 in die Aufnahmebohrung 12 des Unterbaus 8 einfahren und verhindert nun eine Relativbewegung zwischen Unterbau 8 und Träger 9. In dieser Konstellation wird der Bohrprozess nun unmittelbar fortgesetzt; der Schlitten 4 kann gesamthaft bewegt werden, so dass Träger 9 und Unterbau 8 zusammen bewegt werden können. Ein Zufahren des Schlittens 4 bzw. Unterbaus 8 bis der Träger 9 am Anschlag 13 anstößt, kann vermieden werden. Ist der neue Gestängeschuss 5 mit dem schon verbohrten Bohrgestänge ins Erdreich eingebohrt, kann der Bolzen 10 einfahren und der Träger 9 kann mit der Aufnahme 3 zurückfahren und der Vorgang eines Verbindens eines neuen Gestängeschusses 5 mit dem verbohrten Bohrgestänge von neuem beginnen.If both threads of the new rod section 5, ie both the front thread with the drill rod that has already been drilled and the rear thread with the receptacle 3, are completely screwed, the carrier 9 is in a 3 shown front position. In this position of the carrier 9 relative to the substructure 8, the bolt 10 can move into the receiving bore 12 of the substructure 8 and now prevents relative movement between the substructure 8 and the carrier 9. In this constellation, the drilling process is now continued immediately; the carriage 4 can be moved as a whole, so that the carrier 9 and the substructure 8 can be moved together. A closing of the carriage 4 or substructure 8 until the carrier 9 hits the stop 13 can be avoided. If the new rod section 5 has been drilled into the ground with the drill rod that has already been drilled, the bolt 10 can retract and the carrier 9 can move back with the receptacle 3 and the process of connecting a new rod section 5 to the drill rod that has been drilled can begin again.

Claims (8)

  1. Ground drilling device (1) for drilling in soil by means of a drill string, wherein the ground drilling device (1) has a drilling carriage (2) and a sled (4) movable in translational motion on the drilling carriage (2), and a holder (3) is arranged on the sled (4)
    a) for the screwing connection of a rod section (5) to the drill string, or
    b) for the screwing detachment of a rod section (5) from the drill string, wherein the holder (3) can move in translational motion relative to the sled (4) characterized in that a support (9) bearing the holder is displaceably arranged on the sled (4), which is optionally detachably fixed on the sled (4) to compensate for a change in the position of the holder (3) caused by the screwing.
  2. Ground drilling device (1) according to claim 1, characterized in that the support (9) can be fixed to the sled (4) or to a substructure (8) of the sled (4) by means of a bolt (10) which more particularly is hydraulically actuatable.
  3. Ground drilling device (1) according to claim 1 or 2, characterized in that a sensor is provided to detect the end of the screwing process, the signal from which can be received by a control device to ensure fixing of the holder (3) to the sled (4).
  4. Ground drilling device according to claim 3, characterized in that the sensor can be a limit switch, a proximity switch, position switch or similar.
  5. Ground drilling device (1) according to one of the claims 1 to 4, characterized in that an input device is provided which supplies a signal which can be received by a control device to ensure fixing of the holder (3) to the sled (4).
  6. Method for drilling in the soil using a drill string, wherein a sled (4) which can be moved in translational motion is used for pulling and/or pushing the drill string, and on the sled (4), a holder (3) is arranged with which a rod section (5) is screwed onto or unscrewed from a drill string, wherein the holder (3) can be moved in translational motion relative to the sled (4), characterized in that the holder (3) is optionally detached from the sled (4) to compensate for a change in the position of the holder (3) caused by the screwing.
  7. Method according to claim 6, characterized in that an input device, which can be actuated by an operator, is provided and the holder (3) is optionally fixed to the sled (4) by means of an input on the input device.
  8. Method according to claim 6 or 7, characterized in that the holder (3) is optionally fixed to the sled (4) by means of a signal from a sensor.
EP20158158.4A 2019-02-20 2020-02-19 Soil drilling device and method for drilling in soil Active EP3699391B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DE102019001204.6A DE102019001204A1 (en) 2019-02-20 2019-02-20 Earth drilling device and method for drilling in the ground

Publications (2)

Publication Number Publication Date
EP3699391A1 EP3699391A1 (en) 2020-08-26
EP3699391B1 true EP3699391B1 (en) 2022-04-06

Family

ID=69784029

Family Applications (1)

Application Number Title Priority Date Filing Date
EP20158158.4A Active EP3699391B1 (en) 2019-02-20 2020-02-19 Soil drilling device and method for drilling in soil

Country Status (4)

Country Link
US (1) US11187046B2 (en)
EP (1) EP3699391B1 (en)
AU (1) AU2020201060B2 (en)
DE (1) DE102019001204A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE544771C2 (en) * 2021-03-26 2022-11-08 Epiroc Rock Drills Ab Method and system for detecting a loosened joint of a drill string

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0190669B1 (en) * 1985-02-06 1989-11-23 Ing. G. Klemm Bohrtechnik GmbH Drilling apparatus
DE4103196C2 (en) * 1991-02-02 1994-06-09 Tracto Technik Drill

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DD288303A7 (en) * 1988-09-02 1991-03-28 Sdag Wismut,De DEVICE FOR THE ELASTIC MOUNTING OF TURNING DRILLING MACHINES ON PREMATURE SLOTS OF DRILLING DEVICES
DE4113422C3 (en) 1991-04-25 1998-06-10 Klemm Bohrtech Earth drilling rig
DE29610316U1 (en) * 1996-06-12 1996-09-05 MTM Spindler & Schmid GmbH, 72535 Heroldstatt Device for the production of earth bores
DE19725628C1 (en) * 1997-06-17 1999-03-04 Tracto Technik Drilling device
DE19917538A1 (en) * 1999-04-19 2000-10-26 Flowtex Technologie Gmbh & Co Horizontal wet drilling tool uses vibration device for periodic impact of drill rod or drill head in longitudinal direction during horizontal displacement
US9719314B2 (en) * 2014-07-01 2017-08-01 Vermeer Corporation Drill rod tallying system and method
US10697260B2 (en) * 2017-02-02 2020-06-30 Cameron International Corporation Tubular rotation detection system and method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0190669B1 (en) * 1985-02-06 1989-11-23 Ing. G. Klemm Bohrtechnik GmbH Drilling apparatus
DE4103196C2 (en) * 1991-02-02 1994-06-09 Tracto Technik Drill

Also Published As

Publication number Publication date
AU2020201060A1 (en) 2020-09-03
US20200263505A1 (en) 2020-08-20
DE102019001204A1 (en) 2020-08-20
EP3699391A1 (en) 2020-08-26
US11187046B2 (en) 2021-11-30
AU2020201060B2 (en) 2021-10-07

Similar Documents

Publication Publication Date Title
EP2085566B1 (en) Drilling assembly
DE3114612C2 (en) Drilling jig for hard rock
EP2728104B1 (en) Method for producing a horizontally drilled bore hole in the ground and horizontal drilling device
DE102015105908A1 (en) Drill for creating a cased bore and method for operating a drill
DE102006043772A1 (en) Method and device for replacing buried old lines
EP2505762A2 (en) Drilling device and method for horizontal drilling
EP1580398B1 (en) Apparatus and method for subsoil construction
EP3287588B1 (en) Machine tool and method for machining a soil
EP3699391B1 (en) Soil drilling device and method for drilling in soil
AT508991B1 (en) METHOD OF DRILLING, IN PARTICULAR PUNCHING OR TURNING OF HOLES IN GROUND OR ROCK MATERIAL AND DEVICE HIEFÜR
DE102011000320A1 (en) Drilling rig for carrying out drilling in soil, comprises drilling frame, and drive unit slidably arranged on frame, where drive unit has rod cartridge for detachably connecting with drilling pipe, and drive motor standing with cartridge
EP3702576B1 (en) Earth boring device and use of an earth boring device
DE1608274C3 (en) Method for overburden drilling in soil or loose rock
DE102007012055B4 (en) Drilling apparatus, in particular for earth and rock drilling, method for making a hole in the ground and drilling arrangement
DE19738171A1 (en) Boring machine with driving slide on guide column
DE102015107194A1 (en) Drilling rig for generating or expanding a ground hole in the ground and method for controlling a feed drive of such a rig
DE3125082A1 (en) Method and tunnel-driving machine for producing tunnels of varying cross-section
EP3456914A1 (en) Dual head drilling device and method for producing a borehole
DE3423789C2 (en) Drilling device for rock drilling
DE1161524B (en) Method and device for producing drill shafts and similar bores
EP2843138A1 (en) Method and device for producing ground piles
DE102012010199B4 (en) Method and device for creating a borehole
EP3663504B1 (en) Earthworks method, earthworks device and earthworks installation
DE102012100989A1 (en) Device for moving a working fluid in the ground
DE102008036722B4 (en) Method, apparatus and drill head for introducing a hole in the soil

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN PUBLISHED

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: REQUEST FOR EXAMINATION WAS MADE

17P Request for examination filed

Effective date: 20210226

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: GRANT OF PATENT IS INTENDED

INTG Intention to grant announced

Effective date: 20210930

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE PATENT HAS BEEN GRANTED

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

Free format text: NOT ENGLISH

REG Reference to a national code

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 1481502

Country of ref document: AT

Kind code of ref document: T

Effective date: 20220415

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 502020000886

Country of ref document: DE

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Free format text: LANGUAGE OF EP DOCUMENT: GERMAN

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG9D

REG Reference to a national code

Ref country code: NL

Ref legal event code: MP

Effective date: 20220406

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220808

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220706

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220707

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220706

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: RS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220806

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 502020000886

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20230110

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

REG Reference to a national code

Ref country code: BE

Ref legal event code: MM

Effective date: 20230228

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230219

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230228

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230228

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20220406

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230219

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20230228

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20240321

Year of fee payment: 5

Ref country code: GB

Payment date: 20240222

Year of fee payment: 5

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20240221

Year of fee payment: 5