Verfahren und vorrichtung zur montage einer windkraftanlage

Info

Publication number
EP2499357A2
EP2499357A2 EP10795029A EP10795029A EP2499357A2 EP 2499357 A2 EP2499357 A2 EP 2499357A2 EP 10795029 A EP10795029 A EP 10795029A EP 10795029 A EP10795029 A EP 10795029A EP 2499357 A2 EP2499357 A2 EP 2499357A2
Authority
EP
European Patent Office
Prior art keywords
wind power
power plant
mast
installation construction
elements
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP10795029A
Other languages
English (en)
French (fr)
Inventor
Pekka Luhtala
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
EASYWIND Oy
Original Assignee
EASYWIND Oy
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by EASYWIND Oy filed Critical EASYWIND Oy
Publication of EP2499357A2 publication Critical patent/EP2499357A2/de
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/91Mounting on supporting structures or systems on a stationary structure
    • F05B2240/915Mounting on supporting structures or systems on a stationary structure which is vertically adjustable
    • F05B2240/9151Mounting on supporting structures or systems on a stationary structure which is vertically adjustable telescopically
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines
EP10795029A 2009-11-09 2010-11-08 Verfahren und vorrichtung zur montage einer windkraftanlage Withdrawn EP2499357A2 (de)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FI20096161A FI20096161A (fi) 2009-11-09 2009-11-09 Menetelmä ja laitteisto tuulivoimalan kokoonpanemiseksi
PCT/FI2010/050898 WO2011055021A2 (en) 2009-11-09 2010-11-08 A method and an apparatus for assembling a wind power plant

Publications (1)

Publication Number Publication Date
EP2499357A2 true EP2499357A2 (de) 2012-09-19

Family

ID=41395211

Family Applications (1)

Application Number Title Priority Date Filing Date
EP10795029A Withdrawn EP2499357A2 (de) 2009-11-09 2010-11-08 Verfahren und vorrichtung zur montage einer windkraftanlage

Country Status (4)

Country Link
EP (1) EP2499357A2 (de)
EA (1) EA201290328A1 (de)
FI (1) FI20096161A (de)
WO (1) WO2011055021A2 (de)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI122698B (fi) 2010-12-28 2012-05-31 Easywind Oy Menetelmä ja laitteisto tuulivoimalan asentamiseksi korkeaan perustusrakennelmaan
DK3130796T3 (da) 2014-04-01 2019-09-23 Nabrawind Tech Sl Vindmøllesamlingssystem og dertilhørende fremgangsmåde
ES2717257T3 (es) * 2014-05-19 2019-06-20 Soletanche Freyssinet Sistema de montaje y procedimiento de montaje de una torre para aerogenerador
EP3705718B1 (de) 2019-03-07 2022-08-17 Siemens Gamesa Renewable Energy A/S Anordnung eines turmabschnitts eines windturbinenturms
CN113323811B (zh) * 2021-08-02 2021-10-12 山东辛丁技术有限公司 基于双发电机的风力发电设备
NO347712B1 (en) * 2022-02-16 2024-02-26 Tebina Energi As A windmill construction and a method for assembly of a windmill construction

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2369925T3 (es) * 2006-05-20 2011-12-09 W2E Wind To Energy Gmbh Dispositivo para erigir una torre de una instalación de energía eólica compuesta de segmentos de torre individuales.
US20090087311A1 (en) * 2007-09-29 2009-04-02 Gavin Raymond Wyborn Vertically Adjustable Horizontal Axis Type Wind Turbine And Method Of Construction Thereof
US8011098B2 (en) * 2008-08-19 2011-09-06 Vorhies Roger W Wind turbine erector
WO2010049313A2 (en) * 2008-10-31 2010-05-06 Vestas Wind Systems A/S Method of erecting a tower

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
None *
See also references of WO2011055021A2 *

Also Published As

Publication number Publication date
EA201290328A1 (ru) 2012-11-30
WO2011055021A3 (en) 2011-11-17
FI20096161A (fi) 2011-05-10
WO2011055021A2 (en) 2011-05-12
FI20096161A0 (fi) 2009-11-09

Similar Documents

Publication Publication Date Title
EP2372143B1 (de) Vorrichtung und Verfahren zum Aufrichten auf See eines schlanken Körpers wie eines Einzelpfeilers einer Windturbine
ES2369925T3 (es) Dispositivo para erigir una torre de una instalación de energía eólica compuesta de segmentos de torre individuales.
EP2499357A2 (de) Verfahren und vorrichtung zur montage einer windkraftanlage
US10815687B2 (en) Wind turbine assembly system and associated method
CN104428237A (zh) 自爬及伸缩式吊车和用于安装预制混凝土塔的方法
EP2374966A1 (de) Verfahren zum Konstruieren eines Hybridturms für einen Windgenerator
US20150014266A1 (en) Revolving tower crane
CA2436627A1 (en) Tilt-up and telescopic support tower for large structures
EP3517776B1 (de) Verfahren und ausrüstung für die ersetzung von teilen eines windkraftwerks
WO2012062352A1 (en) Lifting beam for use in hoisting a wind turbine blade
EP2368834B1 (de) Heb- und Senkausrüstung für Windgeneratorturbinen
NL2008018C2 (en) Method for installing an offshore wind turbine, installation barge for installing an offshore wind turbine.
KR102529595B1 (ko) 무거운 하중을 들어올리기 위한 장치
EP3314119B1 (de) Verfahren zum errichten eines kabelgebundenen windturbinenturms
EP3132137B1 (de) Mobile kranvorrichtung sowie verfahren zur temporären montage einer solchen kranvorrichtung
WO2023095003A1 (en) Wind turbine blade installation system and related methods
CN111511670A (zh) 操纵风力涡轮机部件的方法和具有起重机的风力涡轮机
WO2014097254A1 (en) Device and method for placing a structural component
EP2604568B2 (de) Kombinierte Hebebalkenanordnung für Windturbinenteile
EP2659131B1 (de) Verfahren und vorrichtung zur montage einer windenergieanlage auf einer hohen basisstruktur
CN109072866B (zh) 提升多转子风轮机的部件的方法
WO2014082684A1 (en) Lifting frame
WO2011081599A1 (en) A method for the construction of a wind-power unit and a device for carrying out the method
WO2022119452A1 (en) Systems and methods related to climbing and assembling tower structures
EP4077932A1 (de) Verfahren zum installieren oder entfernen von windturbinenkomponenten

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20120528

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO RS SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RIC1 Information provided on ipc code assigned before grant

Ipc: F03D 13/10 20160101AFI20170719BHEP

INTG Intention to grant announced

Effective date: 20170822

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn