EP2251503B1 - Method for replacing a loadbearing wall - Google Patents

Method for replacing a loadbearing wall Download PDF

Info

Publication number
EP2251503B1
EP2251503B1 EP10004866.9A EP10004866A EP2251503B1 EP 2251503 B1 EP2251503 B1 EP 2251503B1 EP 10004866 A EP10004866 A EP 10004866A EP 2251503 B1 EP2251503 B1 EP 2251503B1
Authority
EP
European Patent Office
Prior art keywords
loadbearing
wall
beams
columns
recess
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Not-in-force
Application number
EP10004866.9A
Other languages
German (de)
French (fr)
Other versions
EP2251503A3 (en
EP2251503A2 (en
Inventor
Arvu Mägi
Joel Lipson
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Amhold AS
Original Assignee
Amhold AS
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Amhold AS filed Critical Amhold AS
Publication of EP2251503A2 publication Critical patent/EP2251503A2/en
Publication of EP2251503A3 publication Critical patent/EP2251503A3/en
Application granted granted Critical
Publication of EP2251503B1 publication Critical patent/EP2251503B1/en
Not-in-force legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0274Temporary shoring of wall opening
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0229Increasing or restoring the load-bearing capacity of building construction elements of foundations or foundation walls

Definitions

  • the invention belongs in the construction field, more specifically a method for replacing a loadbearing wall on infirm soil.
  • the problem underlying this invention is that often it is necessary to replace existing loadbearing walls with a beam-column system, such as to create a more spacious room in the course of reconstruction works.
  • the foundation under the loadbearing walls has insufficient loadbearing capacity or depth in order to apply the concentrated extra load received from the column.
  • the demolition of a loadbearing wall and building a beam-column bearing system often involves substantial working volumes, which do not justify the effect of more spacious premises. Often it is also necessary to dredge the floor beneath the level of the existing pad footing with the purpose of increasing the height of the existing plinth/basement floor.
  • the underground wall of the building is the penetrating part and it is made from reinforced concrete.
  • the ground wall of the building is connected to the underground wall by integration, in order to provide the ground part with higher resistance to the horizontal force that acts on the ground wall from the underground wall.
  • the upper part of the steel reinforcement is used, which is in the H shape and has the bottom section positioned in the connection part of the underground wall, containing steel tubes and steel piles, and the steel reinforcement is recessed into a column of the ground wall.
  • the steel reinforcement is fitted with a projecting double-end bolt and the underground cross-beam is intended for the upper part of the underground wall.
  • the method for the replacement of the loadbearing wall comprises the stages: on both sides of the loadbearing wall a recess is created for the loadbearing wall, piles are driven at the bottom of the recess down to a bearing soil layer and the recess is supported by means of a temporary supporting wall.
  • On-pile foundation is built on top of the driven piles, supporting the cross-beams that will be under the loadbearing columns to the foundation, after which the recess is backfilled and compacted and the temporary supporting walls removed.
  • the temporary supports that support the loadbearing structures of the ceiling of all floors and are supported on the on-pile foundation are installed on both sides of the loadbearing wall, openings are cut in the loadbearing wall for the loadbearing columns and the loadbearing columns are installed on the cross-beams. Then an opening is cut in the loadbearing wall for the loadbearing beam and one loadbearing beam is mounted to the loadbearing columns on one side of the loadbearing wall and then the second loadbearing beam is mounted to the other side of the loadbearing wall, filling the gap between the loadbearing beams with a fire retardant and sound insulating material, and demolishing the section of the loadbearing wall under the loadbearing beam. The installation of loadbearing columns and beams is repeated in the next gaps between the columns as provided above, until the column-beam loadbearing system is complete and building of the rough floor can be finished.
  • the figure presents the plan of a building, where the method for loadbearing wall replacement is applied.
  • recess 2 is created, at the bottom of which micro piles 3 are driven until reaching a loadbearing soil layer 4.
  • Recess 2 is created with a width that makes it possible for the machine that drives micro piles 3 to move and work.
  • recess 2 is supported with a temporary supporting wall 6. If the level of surface water 7 reaches over the bottom of recess 2, surface water is removed from recess 2 during construction works.
  • micro piles 3 After micro piles 3 are driven in, the on-pile foundation 8 from reinforced concrete is built on the piles.
  • the on-pile foundation 8 from reinforced concrete is reinforced near the upper and lower level by means of steel fittings 9. Steel fittings 9 are pre-tensioned.
  • Recess 2 micro piles 3 and on-pile foundation 8 are initially created on one side of loadbearing wall 1 and then to the other side of loadbearing wall 1.
  • Recess 2 is created at such distance from loadbearing wall 1 that the stability of foundation 10 of the loadbearing wall would be ensured, and taking into account supporting wall 6 of recess 2.
  • Cross-beams 12 that are rested on on-pile foundation 8, are installed under loadbearing columns 11 that support loadbearing wall 1. Cross-beams 12 are installed beneath the lower level 14 of the rough floor 13.
  • recess 2 is backfilled and compacted with mineral soil to compacting degree 1.00.
  • the temporary support walls 6 of recess 2 are removed.
  • An elastic layer 15 is installed between cross-beams 12 and the lower level 14 of the rough floor 13 in order to compensate various deformations in rough floor 13 and cross-beams 12 as a result of moisture and temperature fluctuations.
  • a temporary opening 16 with the width of cross-beams 12 is left in rough floor 13 for the installation of load bearing columns 11.
  • load bearing wall 1 After the installation of temporary supports 18, vertical openings are cut into load bearing wall 1 for two adjacent load bearing columns 11 and the columns are installed on cross-beams 12.
  • Loadbearing columns 11 are installed on cross-beams 12 by means of load-resistant anchor bolts 19.
  • Load-resistant anchor bolts 19 are supplied with pressure nuts 20 for adjusting the height of load bearing columns 11.
  • Loadbearing columns 11 are produced from steel tube jacket 21 and concrete core 22. With the interaction between concrete core 22 and steel tube jacket 21, i.e. load bearing column 11, the load bearing column 11 will achieve the optimum load stability and fire resistance.
  • load bearing beam 23 is repeated on the other side of load bearing wall 1.
  • the gap between load bearing beams 23 is filled with fire resistant and sound insulating material 26, such as with dense rock wool. Then the load bearing wall section 27 under load bearing beams 23 is demolished.
  • load bearing beams 23 are covered with a fire retardant and sound insulating material 26, such as dense rock wool boards or fire resistant gypsum boards, and the temporary supports 18 are removed.
  • loadbearing columns 11 and load bearing beam 23 are provided with extra tension by means of load-resistant bolts 19 and pressure nuts 20 in order to prevent deformations in loadbearing wall 1 and the load bearing structure 17 of the ceiling.
  • loadbearing columns 11 and load bearing beam 23 are covered with fire resistant mixture 29, which will ensure the steel tube jacket 21 and thereby also load bearing column 11 with optimum fire resistance in interaction with concrete core 22.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Description

    Technical field
  • The invention belongs in the construction field, more specifically a method for replacing a loadbearing wall on infirm soil.
  • Prior art
  • The problem underlying this invention is that often it is necessary to replace existing loadbearing walls with a beam-column system, such as to create a more spacious room in the course of reconstruction works. At this the foundation under the loadbearing walls has insufficient loadbearing capacity or depth in order to apply the concentrated extra load received from the column. The demolition of a loadbearing wall and building a beam-column bearing system often involves substantial working volumes, which do not justify the effect of more spacious premises. Often it is also necessary to dredge the floor beneath the level of the existing pad footing with the purpose of increasing the height of the existing plinth/basement floor.
  • In the patent application "Building structure" ( JP2002227303 , Takenaka Komuten Co, published on 14.08.2002) a solution for creating a more spacious room has been presented, stating a structure, where a steel supporting framework contains a steel framework column and cross-beams, reinforced concrete walls, while the cross-beam of the footing is positioned only along the lower part of the wall, the foundation is positioned in the bottom part of the steel framework column. Walls are located at suitable distances from each other in the crosswise direction and instead of installing the beam between the upper parts of the numerous adjacent walls, the bottom section of the lower part of the wall is connected to the cross-beam of the footing with a rigid connection.
  • From the technical nature, a solution presented in the patent application "Building structure" ( JP52705629 , Kajima Corp., published on 16.12.1982) is the closest to this invention. The underground wall of the building is the penetrating part and it is made from reinforced concrete. The ground wall of the building is connected to the underground wall by integration, in order to provide the ground part with higher resistance to the horizontal force that acts on the ground wall from the underground wall. In order to connect the underground wall with the ground wall and form a whole, the upper part of the steel reinforcement is used, which is in the H shape and has the bottom section positioned in the connection part of the underground wall, containing steel tubes and steel piles, and the steel reinforcement is recessed into a column of the ground wall. The steel reinforcement is fitted with a projecting double-end bolt and the underground cross-beam is intended for the upper part of the underground wall.
  • The known solutions do not solve the problem underlying the given invention.
  • Description of the invention
  • The method for the replacement of the loadbearing wall comprises the stages: on both sides of the loadbearing wall a recess is created for the loadbearing wall, piles are driven at the bottom of the recess down to a bearing soil layer and the recess is supported by means of a temporary supporting wall. On-pile foundation is built on top of the driven piles, supporting the cross-beams that will be under the loadbearing columns to the foundation, after which the recess is backfilled and compacted and the temporary supporting walls removed. Then the temporary supports that support the loadbearing structures of the ceiling of all floors and are supported on the on-pile foundation are installed on both sides of the loadbearing wall, openings are cut in the loadbearing wall for the loadbearing columns and the loadbearing columns are installed on the cross-beams. Then an opening is cut in the loadbearing wall for the loadbearing beam and one loadbearing beam is mounted to the loadbearing columns on one side of the loadbearing wall and then the second loadbearing beam is mounted to the other side of the loadbearing wall, filling the gap between the loadbearing beams with a fire retardant and sound insulating material, and demolishing the section of the loadbearing wall under the loadbearing beam. The installation of loadbearing columns and beams is repeated in the next gaps between the columns as provided above, until the column-beam loadbearing system is complete and building of the rough floor can be finished.
  • List of figures
  • The figure presents the plan of a building, where the method for loadbearing wall replacement is applied.
  • Exemplary embodiment of the invention
  • Next to loadbearing wall 1, in parallel with the wall, recess 2 is created, at the bottom of which micro piles 3 are driven until reaching a loadbearing soil layer 4. Recess 2 is created with a width that makes it possible for the machine that drives micro piles 3 to move and work. Depending on the geotechnical characteristics of subsoil 5, recess 2 is supported with a temporary supporting wall 6. If the level of surface water 7 reaches over the bottom of recess 2, surface water is removed from recess 2 during construction works.
  • After micro piles 3 are driven in, the on-pile foundation 8 from reinforced concrete is built on the piles. The on-pile foundation 8 from reinforced concrete is reinforced near the upper and lower level by means of steel fittings 9. Steel fittings 9 are pre-tensioned. Recess 2, micro piles 3 and on-pile foundation 8 are initially created on one side of loadbearing wall 1 and then to the other side of loadbearing wall 1. Recess 2 is created at such distance from loadbearing wall 1 that the stability of foundation 10 of the loadbearing wall would be ensured, and taking into account supporting wall 6 of recess 2.
  • Cross-beams 12 that are rested on on-pile foundation 8, are installed under loadbearing columns 11 that support loadbearing wall 1. Cross-beams 12 are installed beneath the lower level 14 of the rough floor 13.
  • After this, recess 2 is backfilled and compacted with mineral soil to compacting degree 1.00. The temporary support walls 6 of recess 2 are removed. An elastic layer 15 is installed between cross-beams 12 and the lower level 14 of the rough floor 13 in order to compensate various deformations in rough floor 13 and cross-beams 12 as a result of moisture and temperature fluctuations. During the construction of rough floor 13, a temporary opening 16 with the width of cross-beams 12 is left in rough floor 13 for the installation of load bearing columns 11.
  • Then temporary supports 18 that will receive the load of the loadbearing structure 17 of the ceiling are installed on both sides of load bearing wall 1 on all the floors, supporting the load bearing structure 17 of the ceiling and resting on on-pile foundation 8.
  • After the installation of temporary supports 18, vertical openings are cut into load bearing wall 1 for two adjacent load bearing columns 11 and the columns are installed on cross-beams 12. Loadbearing columns 11 are installed on cross-beams 12 by means of load-resistant anchor bolts 19. Load-resistant anchor bolts 19 are supplied with pressure nuts 20 for adjusting the height of load bearing columns 11.
  • Loadbearing columns 11 are produced from steel tube jacket 21 and concrete core 22. With the interaction between concrete core 22 and steel tube jacket 21, i.e. load bearing column 11, the load bearing column 11 will achieve the optimum load stability and fire resistance.
  • Then a hole is cut for loadbearing beam 23 into load bearing wall 1, for a half of its thickness, under the loadbearing structure 17 of the ceiling, and one loadbearing beam 23 is mounted to loadbearing columns 11. After mounting the first loadbearing beam 23, the gap between load bearing beam 23 and the load bearing structure 17 of the ceiling is closed with steel wedges 24, which will provide the load bearing beam 23 with the initial tension to support loadbearing wall 1 and the load bearing structure 17 of the ceiling. After wedging the first loadbearing beam 23, the space between the loadbearing structure 17 and load bearing beam 23 is filled with expanding assembly concrete 25 by gunning.
  • Then the method for the installation of load bearing beam 23 is repeated on the other side of load bearing wall 1. Prior to the installation of the second load bearing beam 23 on the other side of load bearing wall 1, the gap between load bearing beams 23 is filled with fire resistant and sound insulating material 26, such as with dense rock wool. Then the load bearing wall section 27 under load bearing beams 23 is demolished.
  • Then the whole method for the installation of loadbearing columns 11 and load bearing beams 23 is repeated in the next space between the columns. After completing the whole column-beam system, load bearing beams 23 are covered with a fire retardant and sound insulating material 26, such as dense rock wool boards or fire resistant gypsum boards, and the temporary supports 18 are removed.
  • Depending on the possible subsiding of piles 3, on-pile foundation 8 and cross-beam 12 as a result of the compacting of load bearing soil 4 and subsoil 5 and reduced tension in load bearing columns 11, loadbearing columns 11 and load bearing beam 23 are provided with extra tension by means of load-resistant bolts 19 and pressure nuts 20 in order to prevent deformations in loadbearing wall 1 and the load bearing structure 17 of the ceiling. When the subsiding of piles 3, on-pile foundation 8 and cross-beam 12 has ended, the gap between loadbearing column 11 and cross-beam 12 is cast with prestressed concrete 28, and rough floor 13 is completed. Prior to the finishing of load bearing columns 11 and loadbearing beam 23, loadbearing columns are covered with fire resistant mixture 29, which will ensure the steel tube jacket 21 and thereby also load bearing column 11 with optimum fire resistance in interaction with concrete core 22.

Claims (6)

  1. Method for replacing a loadbearing wall, executed in a building that comprises a loadbearing wall, loadbearing columns supporting the loadbearing wall, foundation of the loadbearing wall, steel tubes and steel piles, comprising of the stages: cross-beams are installed in the foundation of the loadbearing wall, under the loadbearing columns that support the loadbearing wall, characterized in that
    a recess (2) is created next to the loadbearing wall (1), micro-piles (3) are driven at the bottom of the recess until a loadbearing layer (4), and the recess (2) is supported with a temporary supporting wall (6);
    on-pile foundation (8) is built on top of the driven piles (3), it is reinforced with steel reinforcement (9) and the steel reinforcement (9) is pre-tensioned;
    the recess (2), piles (3) and on-pile foundation (8) are created initially on one side of the loadbearing wall (1) and then on the other side of the loadbearing wall (1);
    the cross-beams (12) installed under the loadbearing columns (11) that support the loadbearing wall (1) are rested on the on-pile foundation (8), whereat the cross-beams (12) are installed below the lower surface (14) of the rough floor (13);
    the recess (2) is backfilled and compacted, apd the temporary supporting walls (6) of the recess (2) are removed;
    an elastic layer (15) is installed between the cross-beams (12) and the lower surface (14) of the rough floor;
    the temporary supports (18) that receive the load of the loadbearing structures (17) of the cellings of the floors and rest on the on-pile foundation (8) are installed;
    vertical openings are cut into the loadbearing wall (1) for two loadbearing columns (11) that are installed on cross-beams (12) by means of anchor bolts (19), while the anchor bofts are supplied with pressure nuts (20) that adjust the height of the loadbearing column (1);
    openings are cut for the loadbearing beams (23) into the loadbearing wall (1) by a half of its thickness, under the ceiling structure (17), and one of the loadbearing beams (23) is mounted to the loadbearing columns (11), and the gap between the first loadbearing beam (23) and the ceiling structures (17) is closed by wedging with steel wedges (24), and the gap is filled with expanding assembly concrete (25);
    the second loadbearing beam (23) is installed to the other side of the loadbearing wall (1), whereas the space between the loadbearing beams (23) is filled with a fire retardant and sound insulating material (26) and the section of the loadbearing wall (27) under the loadbearing beams (23) is demolished prior to the installation of the second loadbearing beam (23);
    then the previous mounting of loadbearing columns (11) and loadbearing beams (23) is repeated in the following spaces between columns;
    when the whole column-beam system is complete, the loadbearing beams (23) are covered with a fire retardant and sound insulating material (26) and the temporary supports (18) are removed;
    loadbearing columns (11) and the loadbearing beam (23) is provided with extra tension by means of bolts (19) and pressure nuts (20);
    when the subsiding of piles (3), on-pile foundation (8) and cross-beam has ended, the gap between the loadbearing column (11) and cross-beam (12) is cast with prestressed concrete (28) and the rough floor (13) is finished.
  2. Method according to claim 1, characterized in that the recess (2) is created at such distance from the loadbearing wall (1) that the stability of the loadbearing wall is ensured, and the recess (2) is created with such width that it would be possible for machines to move and work in the recess.
  3. Method according to claim 1, characterized in that the backfill of the recess is compacted with mineral soil to compacting degree 1.00.
  4. Method according to claim 1, characterized in that the loadbearing columns (11) are produced from a steel tube jacket (21) and a concrete core (22).
  5. Method according to claim 1, characterized in that rock wool and fire resistant gypsum are used as the fire retardant and sound insulating material (26).
  6. Method according to claim 1, characterized in that prior to the finishing of the loadbearing columns (11) and loadbearing beams (23), the loadbearing columns (11) are coated with a fire-retardant mixture (29).
EP10004866.9A 2009-05-08 2010-05-07 Method for replacing a loadbearing wall Not-in-force EP2251503B1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EEU200900045U EE00888U1 (en) 2009-05-08 2009-05-08 Carrier replacement method

Publications (3)

Publication Number Publication Date
EP2251503A2 EP2251503A2 (en) 2010-11-17
EP2251503A3 EP2251503A3 (en) 2013-10-30
EP2251503B1 true EP2251503B1 (en) 2014-10-01

Family

ID=41528913

Family Applications (1)

Application Number Title Priority Date Filing Date
EP10004866.9A Not-in-force EP2251503B1 (en) 2009-05-08 2010-05-07 Method for replacing a loadbearing wall

Country Status (2)

Country Link
EP (1) EP2251503B1 (en)
EE (1) EE00888U1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104863380A (en) * 2015-05-20 2015-08-26 中建三局第二建设工程有限责任公司 Overall replacement system for original building shock-insulation support and construction method

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2584989C1 (en) * 2015-03-11 2016-05-27 Федеральное государственное автономное образовательное учреждение высшего образования "Сибирский федеральный университет" Device for amplification of bearing structures
CN107724559B (en) * 2017-10-23 2019-07-05 南京百西思建筑科技有限公司 Existing building base isolation reinforcement construction process
CN109403654B (en) * 2018-11-05 2021-03-26 广东赛力克建筑技术工程有限公司 Underpinning and reinforcing method for existing building structure
CN111962901A (en) * 2020-08-14 2020-11-20 山东金城建设有限公司 Existing masonry structure reconstruction construction method
CN112482819A (en) * 2020-12-07 2021-03-12 苏州达康建筑科技有限公司 Method and structure for replacing concrete vertical member
CN114457842A (en) * 2022-02-24 2022-05-10 郎溪浩稳建设工程有限公司 Open cut method subway construction structure mechanics retaining wall reinforcing beam post
CN114517596B (en) * 2022-03-10 2024-04-02 山东省建筑科学研究院有限公司 Prestress pin key connection structure of prefabricated wallboard and masonry wall
CN117868556B (en) * 2024-03-13 2024-06-25 北京建工四建工程建设有限公司 Building dismantling and modifying support system taking building as bearing member
CN117967092B (en) * 2024-03-13 2024-09-17 北京建工四建工程建设有限公司 Construction method for removing and modifying building without temporary support of building

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57205629A (en) 1981-06-09 1982-12-16 Kajima Corp Building structure
JP2002227303A (en) 2001-01-29 2002-08-14 Takenaka Komuten Co Ltd Structure of building
DE20317225U1 (en) * 2003-11-08 2004-01-08 Schöck Entwicklungsgesellschaft mbH Construction element for force transfer, especially for retrofitting between two building parts during building renovation, has a wedge shape consisting of an outer covering element and a pressure-stable filling material
GB0409215D0 (en) * 2004-04-24 2004-05-26 Janjic Srdan Tensioned structural propping system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104863380A (en) * 2015-05-20 2015-08-26 中建三局第二建设工程有限责任公司 Overall replacement system for original building shock-insulation support and construction method

Also Published As

Publication number Publication date
EP2251503A3 (en) 2013-10-30
EE00888U1 (en) 2010-01-15
EP2251503A2 (en) 2010-11-17

Similar Documents

Publication Publication Date Title
EP2251503B1 (en) Method for replacing a loadbearing wall
CN112962663B (en) Construction method for narrow outer enclosure space of deep foundation
CN106193292A (en) A kind of steel frame assembled integral reinforced concrete shear wall structure system
WO2011114507A1 (en) Method of constructing underground structure to be newly built
KR100767952B1 (en) Pass way construction method below the existing foundation
CN113697640B (en) Finished well for integrally assembled elevator of existing multi-storey building and construction method
KR101727518B1 (en) Floor system for reducing story height in top down method and top down method using the same
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
JP5865567B2 (en) Connecting slab and its construction method
CN210106749U (en) Counter-force structure of soft soil foundation super large section push pipe jacking operation
CN109267578B (en) Inclined plane plain concrete structure and construction method thereof
JP3958319B2 (en) Prestressed temporary construction method
CN112502161B (en) Construction method of deep foundation pit supporting system
CN114319437A (en) Construction method for building retaining wall structure at open-cut storey-adding vertical shaft by subsurface excavation
KR100767953B1 (en) Separating method of Monowall with spandrel girders
JP2003003690A (en) Base isolation building and method for base isolation of exisiting building
KR102181416B1 (en) method of constructing earthquake-proof ALC house
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
JP6252860B2 (en) Construction method of seismic isolation building
KR101483865B1 (en) Construction Method of Underground Structure using Composite Wale
KR101736009B1 (en) Top-Down Construction Method For Underground Structure
CN216142027U (en) High-performance concrete prefabricated guide wall structure
CN221345616U (en) Prefabricated self-sinking foundation pit enclosure wall board
JP7565256B2 (en) How to rebuild a building
CN111074933B (en) Construction method of plate rib type cast-in-place anchor rod high retaining wall

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME RS

PUAL Search report despatched

Free format text: ORIGINAL CODE: 0009013

AK Designated contracting states

Kind code of ref document: A3

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

AX Request for extension of the european patent

Extension state: BA ME RS

RIC1 Information provided on ipc code assigned before grant

Ipc: E04G 23/02 20060101AFI20130926BHEP

17P Request for examination filed

Effective date: 20140221

RBV Designated contracting states (corrected)

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

INTG Intention to grant announced

Effective date: 20140519

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AL AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: AT

Ref legal event code: REF

Ref document number: 689644

Country of ref document: AT

Kind code of ref document: T

Effective date: 20141015

Ref country code: CH

Ref legal event code: EP

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: DE

Ref legal event code: R096

Ref document number: 602010019200

Country of ref document: DE

Effective date: 20141127

REG Reference to a national code

Ref country code: NL

Ref legal event code: VDEP

Effective date: 20141001

REG Reference to a national code

Ref country code: AT

Ref legal event code: MK05

Ref document number: 689644

Country of ref document: AT

Kind code of ref document: T

Effective date: 20141001

REG Reference to a national code

Ref country code: LT

Ref legal event code: MG4D

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150202

Ref country code: CZ

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: IS

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150201

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: NO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150101

Ref country code: LT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: LV

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: PL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150102

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: HR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

REG Reference to a national code

Ref country code: DE

Ref legal event code: R097

Ref document number: 602010019200

Country of ref document: DE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: RO

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: EE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: DK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

26N No opposition filed

Effective date: 20150702

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150531

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150531

Ref country code: LU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20150507

Ref country code: MC

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

REG Reference to a national code

Ref country code: IE

Ref legal event code: MM4A

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20150507

REG Reference to a national code

Ref country code: FR

Ref legal event code: PLFP

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20160526

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: FR

Payment date: 20160526

Year of fee payment: 7

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20160629

Year of fee payment: 7

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BG

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: SM

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

Ref country code: HU

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO

Effective date: 20100507

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: TR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 602010019200

Country of ref document: DE

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20170507

REG Reference to a national code

Ref country code: FR

Ref legal event code: ST

Effective date: 20180131

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20171201

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170507

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20170531

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MK

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AL

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20141001