EP2159528A2 - Heat exchanger made of aluminum alloy and method of producing same - Google Patents
Heat exchanger made of aluminum alloy and method of producing same Download PDFInfo
- Publication number
- EP2159528A2 EP2159528A2 EP20090169235 EP09169235A EP2159528A2 EP 2159528 A2 EP2159528 A2 EP 2159528A2 EP 20090169235 EP20090169235 EP 20090169235 EP 09169235 A EP09169235 A EP 09169235A EP 2159528 A2 EP2159528 A2 EP 2159528A2
- Authority
- EP
- European Patent Office
- Prior art keywords
- tube
- fin
- brazing
- mass
- heat exchanger
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000838 Al alloy Inorganic materials 0.000 title claims description 56
- 238000000034 method Methods 0.000 title claims description 28
- 238000005219 brazing Methods 0.000 claims abstract description 156
- 238000005260 corrosion Methods 0.000 claims abstract description 138
- 230000007797 corrosion Effects 0.000 claims abstract description 138
- 239000000463 material Substances 0.000 claims abstract description 69
- 239000000203 mixture Substances 0.000 claims abstract description 62
- 238000000576 coating method Methods 0.000 claims abstract description 39
- 239000011248 coating agent Substances 0.000 claims abstract description 37
- 239000011162 core material Substances 0.000 claims abstract description 24
- 239000011863 silicon-based powder Substances 0.000 claims abstract description 22
- 239000011230 binding agent Substances 0.000 claims abstract description 15
- 239000012535 impurity Substances 0.000 claims abstract description 13
- 230000004907 flux Effects 0.000 claims description 38
- 238000010438 heat treatment Methods 0.000 claims description 25
- 229910052782 aluminium Inorganic materials 0.000 claims description 11
- 230000008569 process Effects 0.000 claims description 10
- 239000011701 zinc Substances 0.000 description 105
- 239000011572 manganese Substances 0.000 description 41
- 238000000926 separation method Methods 0.000 description 31
- 230000000694 effects Effects 0.000 description 27
- 239000000945 filler Substances 0.000 description 25
- 239000010410 layer Substances 0.000 description 23
- 239000007788 liquid Substances 0.000 description 22
- 229910045601 alloy Inorganic materials 0.000 description 20
- 239000000956 alloy Substances 0.000 description 20
- XEEYBQQBJWHFJM-UHFFFAOYSA-N iron Substances [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 19
- 229910052710 silicon Inorganic materials 0.000 description 19
- 239000011651 chromium Substances 0.000 description 13
- 230000014759 maintenance of location Effects 0.000 description 13
- 238000009792 diffusion process Methods 0.000 description 11
- 230000000052 comparative effect Effects 0.000 description 10
- 229910052751 metal Inorganic materials 0.000 description 10
- 239000002184 metal Substances 0.000 description 10
- 229910052748 manganese Inorganic materials 0.000 description 9
- 230000002829 reductive effect Effects 0.000 description 9
- 230000003247 decreasing effect Effects 0.000 description 8
- 238000010586 diagram Methods 0.000 description 8
- 229910052742 iron Inorganic materials 0.000 description 8
- 230000036961 partial effect Effects 0.000 description 8
- 239000000843 powder Substances 0.000 description 8
- 238000012545 processing Methods 0.000 description 7
- KRHYYFGTRYWZRS-UHFFFAOYSA-M Fluoride anion Chemical compound [F-] KRHYYFGTRYWZRS-UHFFFAOYSA-M 0.000 description 6
- XUIMIQQOPSSXEZ-UHFFFAOYSA-N Silicon Chemical compound [Si] XUIMIQQOPSSXEZ-UHFFFAOYSA-N 0.000 description 5
- 238000005304 joining Methods 0.000 description 5
- 239000002245 particle Substances 0.000 description 5
- 239000008199 coating composition Substances 0.000 description 4
- 239000000470 constituent Substances 0.000 description 4
- 239000010703 silicon Substances 0.000 description 4
- 239000004925 Acrylic resin Substances 0.000 description 3
- 229920000178 Acrylic resin Polymers 0.000 description 3
- KFZMGEQAYNKOFK-UHFFFAOYSA-N Isopropanol Chemical compound CC(C)O KFZMGEQAYNKOFK-UHFFFAOYSA-N 0.000 description 3
- 229910052804 chromium Inorganic materials 0.000 description 3
- 238000005097 cold rolling Methods 0.000 description 3
- 230000007423 decrease Effects 0.000 description 3
- 230000005496 eutectics Effects 0.000 description 3
- 238000001125 extrusion Methods 0.000 description 3
- 238000005098 hot rolling Methods 0.000 description 3
- 230000002401 inhibitory effect Effects 0.000 description 3
- 229910000765 intermetallic Inorganic materials 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 230000002093 peripheral effect Effects 0.000 description 3
- 238000005096 rolling process Methods 0.000 description 3
- 238000012360 testing method Methods 0.000 description 3
- 229910052720 vanadium Inorganic materials 0.000 description 3
- 229910052725 zinc Inorganic materials 0.000 description 3
- 229910052726 zirconium Inorganic materials 0.000 description 3
- 229910018125 Al-Si Inorganic materials 0.000 description 2
- 229910021364 Al-Si alloy Inorganic materials 0.000 description 2
- 229910018182 Al—Cu Inorganic materials 0.000 description 2
- 229910018520 Al—Si Inorganic materials 0.000 description 2
- PWHULOQIROXLJO-UHFFFAOYSA-N Manganese Chemical compound [Mn] PWHULOQIROXLJO-UHFFFAOYSA-N 0.000 description 2
- -1 acryl Chemical group 0.000 description 2
- 239000012298 atmosphere Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 2
- 239000012141 concentrate Substances 0.000 description 2
- 239000012792 core layer Substances 0.000 description 2
- 230000001186 cumulative effect Effects 0.000 description 2
- 230000003628 erosive effect Effects 0.000 description 2
- 238000000265 homogenisation Methods 0.000 description 2
- 230000000670 limiting effect Effects 0.000 description 2
- 239000007791 liquid phase Substances 0.000 description 2
- 230000008018 melting Effects 0.000 description 2
- 238000002844 melting Methods 0.000 description 2
- 239000002244 precipitate Substances 0.000 description 2
- 238000000790 scattering method Methods 0.000 description 2
- 239000011856 silicon-based particle Substances 0.000 description 2
- JBQYATWDVHIOAR-UHFFFAOYSA-N tellanylidenegermanium Chemical compound [Te]=[Ge] JBQYATWDVHIOAR-UHFFFAOYSA-N 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 238000009736 wetting Methods 0.000 description 2
- 229910018131 Al-Mn Inorganic materials 0.000 description 1
- 229910018461 Al—Mn Inorganic materials 0.000 description 1
- 229910000714 At alloy Inorganic materials 0.000 description 1
- VYZAMTAEIAYCRO-UHFFFAOYSA-N Chromium Chemical compound [Cr] VYZAMTAEIAYCRO-UHFFFAOYSA-N 0.000 description 1
- LFQSCWFLJHTTHZ-UHFFFAOYSA-N Ethanol Chemical compound CCO LFQSCWFLJHTTHZ-UHFFFAOYSA-N 0.000 description 1
- PQLVXDKIJBQVDF-UHFFFAOYSA-N acetic acid;hydrate Chemical compound O.CC(O)=O PQLVXDKIJBQVDF-UHFFFAOYSA-N 0.000 description 1
- 238000007792 addition Methods 0.000 description 1
- 238000004220 aggregation Methods 0.000 description 1
- 230000002776 aggregation Effects 0.000 description 1
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000007598 dipping method Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000007610 electrostatic coating method Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 238000007429 general method Methods 0.000 description 1
- 238000001192 hot extrusion Methods 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000012299 nitrogen atmosphere Substances 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 239000003507 refrigerant Substances 0.000 description 1
- 239000011347 resin Substances 0.000 description 1
- 229920005989 resin Polymers 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 239000013535 sea water Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000007790 solid phase Substances 0.000 description 1
- 239000002904 solvent Substances 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
- 238000003892 spreading Methods 0.000 description 1
- 230000007480 spreading Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- LEONUFNNVUYDNQ-UHFFFAOYSA-N vanadium atom Chemical compound [V] LEONUFNNVUYDNQ-UHFFFAOYSA-N 0.000 description 1
- 229910052845 zircon Inorganic materials 0.000 description 1
- GFQYVLUOOAAOGM-UHFFFAOYSA-N zirconium(iv) silicate Chemical compound [Zr+4].[O-][Si]([O-])([O-])[O-] GFQYVLUOOAAOGM-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28D—HEAT-EXCHANGE APPARATUS, NOT PROVIDED FOR IN ANOTHER SUBCLASS, IN WHICH THE HEAT-EXCHANGE MEDIA DO NOT COME INTO DIRECT CONTACT
- F28D1/00—Heat-exchange apparatus having stationary conduit assemblies for one heat-exchange medium only, the media being in contact with different sides of the conduit wall, in which the other heat-exchange medium is a large body of fluid, e.g. domestic or motor car radiators
- F28D1/02—Heat-exchange apparatus having stationary conduit assemblies for one heat-exchange medium only, the media being in contact with different sides of the conduit wall, in which the other heat-exchange medium is a large body of fluid, e.g. domestic or motor car radiators with heat-exchange conduits immersed in the body of fluid
- F28D1/04—Heat-exchange apparatus having stationary conduit assemblies for one heat-exchange medium only, the media being in contact with different sides of the conduit wall, in which the other heat-exchange medium is a large body of fluid, e.g. domestic or motor car radiators with heat-exchange conduits immersed in the body of fluid with tubular conduits
- F28D1/053—Heat-exchange apparatus having stationary conduit assemblies for one heat-exchange medium only, the media being in contact with different sides of the conduit wall, in which the other heat-exchange medium is a large body of fluid, e.g. domestic or motor car radiators with heat-exchange conduits immersed in the body of fluid with tubular conduits the conduits being straight
- F28D1/0535—Heat-exchange apparatus having stationary conduit assemblies for one heat-exchange medium only, the media being in contact with different sides of the conduit wall, in which the other heat-exchange medium is a large body of fluid, e.g. domestic or motor car radiators with heat-exchange conduits immersed in the body of fluid with tubular conduits the conduits being straight the conduits having a non-circular cross-section
- F28D1/05366—Assemblies of conduits connected to common headers, e.g. core type radiators
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D53/00—Making other particular articles
- B21D53/02—Making other particular articles heat exchangers or parts thereof, e.g. radiators, condensers fins, headers
- B21D53/08—Making other particular articles heat exchangers or parts thereof, e.g. radiators, condensers fins, headers of both metal tubes and sheet metal
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K1/00—Soldering, e.g. brazing, or unsoldering
- B23K1/0008—Soldering, e.g. brazing, or unsoldering specially adapted for particular articles or work
- B23K1/0012—Brazing heat exchangers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F21/00—Constructions of heat-exchange apparatus characterised by the selection of particular materials
- F28F21/08—Constructions of heat-exchange apparatus characterised by the selection of particular materials of metal
- F28F21/081—Heat exchange elements made from metals or metal alloys
- F28F21/084—Heat exchange elements made from metals or metal alloys from aluminium or aluminium alloys
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F9/00—Casings; Header boxes; Auxiliary supports for elements; Auxiliary members within casings
- F28F9/02—Header boxes; End plates
- F28F9/04—Arrangements for sealing elements into header boxes or end plates
- F28F9/06—Arrangements for sealing elements into header boxes or end plates by dismountable joints
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F28—HEAT EXCHANGE IN GENERAL
- F28F—DETAILS OF HEAT-EXCHANGE AND HEAT-TRANSFER APPARATUS, OF GENERAL APPLICATION
- F28F2275/00—Fastening; Joining
- F28F2275/04—Fastening; Joining by brazing
Definitions
- the present invention relates to a heat exchanger made of an aluminum alloy and a method of producing the same. Specifically, the present invention relates to a heat exchanger made of an aluminum alloy and a method of producing the same in which separation of fins from tubes can be suppressed.
- Heat exchangers made of aluminum alloy comprises tubes, fins, and header pipes as main constituents.
- the heat exchangers are produced by brazing those constituents.
- brazing sheets clad with Al-Si alloy brazing material have been widely used in their production.
- Production cost of the heat exchanger has been reduced by using extruded tubes (hereafter referred to as tubes) having surfaces coated with a brazing composition composed of a mixture of a flux, a binder, and a Al-Si alloy powder and/or a Si powder.
- the tube since Si diffuses from the surface into the inside of the tube wall, the tube is made to have a high Si concentration in its surface and low Si concentration in the inside layer. As a result, the tube is formed a potential gradient such that the surface portion has a relatively high electric potential and the inside layer has a relatively low electric potential. Such a potential gradient increases corrosion of the tube and causes pitting to occur, causing leakage of a refrigerant, and reducing the strength of the tube.
- the Zn-concentrated fillets potential become less noble and thereby are corroded preferentially compared to the other portions of the heat exchanger. Where preferential corrosion of the fillets occurs, fins are separated from the tube surfaces, reducing heat transfer efficiency. In such a case, the heat exchanger cannot keep sufficient efficiency.
- patent reference 1 Japanese Unexamined Patent Application, First Publication, No. 2004-330233
- the inventors proposed a heat exchanger tube having an outer surface coated with a brazing composition that contained Si powder and a Zn-containing flux, where the amount of Si powder was controlled to be 1 to 5g/m 2 , and the amount of Zn-containing flux was controlled to be 5 to 20g/m 2 .
- the Si powder and the Zn containing flux are mixed in the coating of the above-described heat exchanger tube, the Si powder is fused to form brazing liquid filler at the time of brazing, Zn contained in the flux uniformly diffuses in the brazing liquid filler and is spread homogeneously on the tube surface. Since the diffusion rate of Zn in the liquid phase such as brazing liquid filler is far faster than the diffusion rate of Zn in a solid state, the tube surface is made to have a substantially homogeneous Zn concentration. As a result, a sacrificial anode layer is homogeneously formed on the tube surface, thereby improving corrosion resistance of the heat exchanger tube.
- a heat exchanger is made of an assembly including a tube, a fin, and a header pipe, wherein the tube is made of aluminum alloy having a composition containing, in mass %, 0.15 to 0.45 % of Mn, 0.20 to 0.50% of Si, and the balance consisting of Al and unavoidable impurities, and a coating of a brazing composition that is coated on a surface of the tube to which the fin is joined and contains 1.0 to 5.0g/m 2 of Si powder, 4.0 to 10.0 g/m 2 of Zn containing flux composed of KZnF 3 , and 0.5 to 3.0 g/m 2 of a binder; and the fin is made of an aluminum alloy containing, in mass %, 1.20 to 1.80 % of Zn, 0.70 to 1.20% of Si, 0.30 to 0.80% of Fe, 0.90 to 1.50% of Mn, one two or more elements selected from the group consisting of 0.05 to 0.20% of Zr, 0.01 to 0.10% of V, and 0.
- the assembly of the above-described heat exchanger may comprises a plurality of tubes, a plurality of fins, and at least two header pipes, wherein each of the tubes has a constitution of the above-described tube, each of the fins has a constitution of the above-described fin, and each of the header pipes has a constitution of the above-described header pipe.
- the tube may has flat surfaces, and the coating of the brazing composition may be formed on at least one flat surface (joint surface)of the tube such that side surfaces of the tube positioned on both sides of the flat surface are left not-coated with the brazing composition, and a perimeter (peripheral length) b of the uncoated side surface satisfies b ⁇ a ⁇ 1.5, where a denotes a width (height) of the side surface.
- perimeter b of the uncoated side surface may be measured as a peripheral length of the side surface on a cross section perpendicular to the lengthwise direction of the tube.
- the width a of the side surface coincident to the thickness of the tube.
- the tube may comprises: two main flat surfaces that are parallel to each other, elongate along a lengthwise direction of the tube; and two side surfaces positioned on both sides of the main surfaces, wherein a contact plane being in contact with the side surface is inclined from the flat surface.
- a sacrificial corrosion protection material of the header pipe may contains 0.60 to 1.20% by mass of Zn, and the balance consisting of Al and unavoidable impurities.
- a heat exchanger according to any one of the above-described constitutions may be produced by a process comprising:
- the predetermined brazing temperature may be in the range from 580 to 615°C.
- the tube added with appropriate amounts of Mn and Si has a corrosion resistance superior to the conventional alloy such as 1050 alloy or Al-Cu based alloy. Therefore, it is possible to reduce the amount of Zn contained in the flux for forming a sacrificial corrosion protection layer. As a result, it is possible to reduce the amount of Zn flowing to the fillet with the brazing liquid filler, thereby suppressing the preferential corrosion of the fillet. Thus, it is possible to prevent separation of the fin.
- Mn added to the tube suppresses the fluidity of the brazing liquid filler during the brazing process. Therefore, brazing liquid filler formed during the brazing process does not flow excessively to the fillet, and partial portion of the brazing liquid filler remains on the tube surface. As a result, it is possible to reduce a difference in the Zn concentration between the fillet and the tube surface, thereby suppressing preferential corrosion of the fillet, and preventing separation of the fin.
- the fin may be added with appropriate amounts of Si and Fe. Therefore, it is possible to generate intermetallic compounds of Si, Fe, and Mn. Since the intermetallic compounds increase the sacrificial corrosion protection effect by the fins, it is possible to reduce the content of Zn contained in the fin to provide the sacrificial corrosion protection effect. As a result, it is possible to reduce diffusion of Zn from the fin to the fillet, thereby preventing preferential corrosion of the fillet, and preventing separation of the fin.
- the fins are not likely to separate in the heat exchanger according to the present invention, corrosion proof of the tube by the sacrificial corrosion protection effect of the fin can be maintained for a long period of time. As a result, it is possible to prolong a life of the tube compared to a conventional heat exchanger.
- the coating of brazing composition on the surface of the tube to which the fin is brazed leaving an uncoated portion on the side surface. It is preferable to control the perimeter of the uncoated portion on the side surface of the tube to be within 1.5 times the width of the side surface of the tube.
- Zn-containing portion constitutes an anode portion
- Zn-free portion constituting the cathode portion is protected from corrosion by preferential corrosion of the anode portion.
- Zn-free portion side surface of the tube acting as the cathode portion has a large area
- Zn-containing portion brazing composition coated surface
- an outer surface of header pipes having a large surface area may act as a cathode and increases corrosion of the fillet.
- outer sacrificial corrosion protection material, and inner brazing material and by having the sacrificial corrosion protection material contains 0.60 to 1.20% by mass of Zn so as to have the sacrificial corrosion protection material of the header pipe be corroded preferentially, it is possible to suppress the preferential corrosion of fillet, thereby suppressing separation of the fin.
- the assembled fin, tube, and fillet are held at an intermediate temperature range from 530 to 575°C for 4 to 8 minutes, and subsequently heated to a brazing temperature.
- the assembly since the assembly is held for a predetermined duration at a temperature range at which flow of brazing liquid filler does not occur but diffusion of Zn to the tube does occur, it is possible to ensure sufficient diffusion of Zn into the tube wall of the tube. Therefore, it is possible to suppress the excessive concentration of Zn into the fillet. Therefore, it is possible to suppress the preferential corrosion of fillet, thereby suppressing separation of the fin from the heat exchanger.
- FIG. 1 is a schematic diagram that shows an embodiment of a heat exchanger according to the present invention.
- the heat exchanger 100 mainly comprises two header pipes 1, 2 that are bilaterally arranged in parallel to each other intervening a predetermined interval (clearance), a plurality of flat tubes 3 that are in parallel to each other and each joined to the header pipes 1, 2 at right angles, and a plurality of corrugated fins that are each joined to the upper and/or lower tubes 3.
- Header pipes 1, 2, tubes 3, and fins 4 are constituted of below-described aluminum alloys.
- the header pipe 1 and header pipe 2 have side surfaces opposed to each other, and a plurality of slits are formed in the side surface with a predetermined interval along lengthwise direction of each header pipe.
- An end portion of each tube 3 are inserted into the opposed slits of the header pipes 1, 2 such that the tube 3 is installed between the header pipes 1, 2.
- a plurality of tubes 3 are installed between the header pipes 1, 2 and are arranged with a predetermined interval.
- Each fin 4 is brazed to an upper surface or a lower surface of the tube 3. That is, as shown in FIG. 3 , fillets 8 are formed at joint portions where end portions of the tube 3 are inserted to the slits 6 of the header pipes 1, 2, and the tube 3 is brazed to the header pipes 1, 2.
- ridge portions (peak portions) of the wavy corrugated fin 4 are opposed to surface of adjacent tubes 3 and fillets 9 are formed between the ridge portions and the tube surface, Thus, corrugated fins are brazed to the surface of the tube 3.
- each tube 3 that is the surfaces to which the fin 4 is joined, are coated with a coating for brazing (coating 7 of a brazing composition).
- the coating 7 includes 1.0 to 5.0 g/m 2 of Si powder, 4.0 to 10.0 g/m 2 of Zn-containing fluoride based flux (e.g., KZnF 3 ), 0.5 to 3.0 g/m 2 of a binder (for example, acrylic resin).
- a tube 3 of the present embodiment has a constitution of a flat multi-port tube, as shown in FIG. 4 and FIG. 5 showing a transversal cross section of the tube 3.
- the tube 3 has a plurality of passages 3c in its interior, flat upper surface 3A, flat lower surface 3B, and side surfaces 3D adjacent to the surfaces.
- the coating 7 of brazing composition may be formed on the surface 3A and the surface 3B of the tube leaving uncoated portion on both sides of the coated portion. That is, boundaries between the coated portion and uncoated portion defines a width of the coating.
- the width of the coating is measured along a direction perpendicular to the lengthwise direction of the tube.
- a surface of the flat tube 3 of the present embodiment comprises: two main flat surfaces that are parallel to each other, elongate along a lengthwise direction of the tube 3, and constitute the surface 3A and surface 3B of the tube 3; and two side surfaces 3D positioned on both sides of the main surfaces, wherein a contact plane in contact with the side surface 3D is inclined from the main surface.
- a height (width) a of the side surface 3D that is, a thickness of the main body of the tube 3 and a perimeter b of the uncoated portion of the side surface satisfies b ⁇ a ⁇ 1.5.
- the perimeter b of the uncoated portion denotes a peripheral length of the uncoated portion on a cross section perpendicular to the lengthwise direction of the tube.
- side surface 3D of the tube 3 shown in FIG. 4 and FIG. 5 may have a shape composed of a flat face 3G and curved corner surface 3H as shown in FIG. 6A .
- the flat surface 3G of the side surface 3D may have a width of 0.45X
- each of the corner portions (curved portions of the side surface 3D) may have a height of 0.275X.
- the side surface of the tube 3 may be a curved surface.
- the side surface 3J may have an arc shaped outline on a transversal cross section of the tube such that a curvature radius R of the side surface 3J satisfies R > 1.003(X/2), where X is the thickness (dimension of the side surface) of the tube 3.
- the side surface of the tube 3 may be constituted of two flat faces (inclined faces) 3K inclined to each other.
- the inclined surfaces 3K may constitute a corner forming an corner angle ⁇ of ⁇ > 84°.
- the limitations of the shapes, R>1.003(X/2) in FIG. 6B and ⁇ > 84° are both defined based on a boundary conditions so as to satisfy b ⁇ a ⁇ 1.5 defined in the present invention.
- An assembly comprising a tube 3 and a fin 4 joined to the tube 3 through a fillet 9 may be formed by brazing a fin 4 made of an aluminum alloy of the below-described composition to a tube 3 made of the aluminum alloy of the below explained composition to have a transversal cross section as shown in FIG. 4 to FIGS.6A-C , using a coating 7 of brazing composition selected from the below-described composition.
- a side surface 3D not provided with a coating 7 of brazing composition constitutes a cathode portion 9 protected from corrosion, and the fin 4 and the fillet 9 constitute anode portions that are preferentially corroded.
- Corrosion rates of the preferentially corroded anode portions are largely affected by the area ratio of cathode portions (side surfaces 3D of the tube 3) to the anode portion. As the area ratio of the cathode portion (side surfaces 3D of the tube 3) is decreased, the corrosion rate of the anode portion (fin 4 and fillet 4) is decreased.
- the tube 30 has a flat side surfaces S1 as shown in FIG. 7A , relative area fraction of the side surface is decreased compared to a tube 31 having a curved surface S2 as shown in FIG. 7B .
- the shape of the tube 30 is superior to the shape of tube 31 in suppressing separation of the fin.
- composition used in the coating 7 of the brazing composition is explained.
- a Si powder is eroded with Al (aluminum) as a constituent of the tube and forms brazing filler joining the fin 4 and the tube 3.
- Si powder is fused to form a brazing liquid filler, and Zn contained in the flux homogeneously diffuses into the brazing liquid filler and is spread uniformly on the surface of the tube 3.
- the Diffusion rate of Zn in the brazing liquid filler is far faster (greater) than a diffusion rate of Zn in a solid phase. Therefore, the Zn concentration on the surface of the tube 3 is substantially homogenized. That is, the homogenous Zn-diffused layer is formed, and corrosion resistance of the tube 3 is improved.
- Amount of coating of Si powder 1.0 to 5.0 g/m 2
- the amount of Si powder in the coating is less than 1.0g/m 2 , brazability is deteriorated.
- an Si is coated with an amount exceeding 5.0g/m 2 , excessive formation of brazing metal tends to cause concentration of Zn.
- corrosion depth of the tube is increased, and it is impossible to obtain the intended effect for preventing separation of fins. Therefore, the amount of Si powder in the coating is controlled to be in the range of 1.0 to 5.0 g/m 2 .
- the grain size (grain diameter) of Si powder is less than 1 ⁇ m in D(50), it tends to increase a possibility of failing in forming a braze joint of fin 4 to tube 3, and the residual ratio of fm (ratio of fin escaped from separating) decreases.
- the grain size of Si particle exceeds 6 ⁇ m in D(50)
- the depth of corrosion in the tube 3 is increased. Therefore, it is preferable to control the grain size of Si powder to be within 1 to 6 ⁇ m in D(50), where D(50) denotes grain size where the cumulative volume of particles having equal size or smaller size than that size constitute 50% in volume of all the particles.
- D(50) may be measured using a laser beam scattering method.
- Zn containing fluoride-based flux forms a Zn diffused layer on the surface of the tube 3 at the time of brazing, and thereby improving pitting corrosion resistance of the tube.
- the flux removes oxide film from the surface of the tube 3 at the time of brazing, and increase spreading and wetting of the brazing filler, thereby improving the brazability.
- Amount of flux in the coating 4.0 to 10.0 g/m 2
- the amount of flux in the coating is less than 4.0g/m 2 , it is impossible to form the Zn-diffused layer sufficiently, and the corrosion resistance of the tube is deteriorated. In addition, it is impossible to destroy and remove the surface oxide film from the brazed tube excessively, resulting in poor brazing.
- the amount of the flux in the coating exceeds 10.0g/m 2 , Zn is concentrated in the fillet, especially in the eutectic portion. As a result, corrosion resistance of the fillet is deteriorated and separation of the fin is increased. Therefore, the amount Zn-containing, fluoride based flux in the coating was controlled to be 4.0 to 10.0g/m 2 .
- KZnF 3 may be used as the Zn-containing fluoride based flux.
- grain size of flux (flux powder) is smaller than 1 ⁇ m in D(50)
- depth of corrosion of the tube 3 increases by aggregation of flux powder.
- grain size of the flux exceeds 6 ⁇ m in D(50)
- joining of the fins 4 is likely to poor, resulting in reduction of the residual ratio of the fins 4. Therefore, grain size of the flux is preferably 1 to 6 ⁇ m.
- D(50) denotes the critical grain size (grain diameter) as an indicator of grain size distribution of a powder, where the cumulative volume of particles equal to or smaller than the size constitute 50% in volume of all the particles. D(50) may be measured using a laser beam scattering method.
- the coating composition contains a binder.
- acryl-based resin e.g., acrylic resin
- the binder may be used as the binder.
- the amount of binder in the coating is less than 0.5g/m 2 , workability (delamination-resistance) of the coating is deteriorated.
- the amount of the binder in the coating exceeds 3.0g/m 2 , the brazability is deteriorated. Therefore, the amount of binder in the coating is controlled to be 0.5 to 3.0g/m 2 .
- the binder is evaporated by heating at the time of brazing.
- a method of coating the brazing composition comprising Si powder, flux, and binder is not limited.
- coating of the brazing composition may be performed by an appropriate method selected from a spray method, a shower method, a flow-coater method, a roll-coater method, a brash-coating method, a dipping method, an electrostatic coating method, or the like.
- a portion of the tube coated by the brazing composition may be whole of the surface of the tube 3.
- the coating may be formed on a partial portion of the surface of the tube 3, provided that at least a portion of sufficient area in the vicinity of joint portion to which the fin 4 is joined is coated with the brazing composition such that the fin 4 may be joined to the tube 3 by brazing.
- the side surface of the tube 3 of the present invention is not coated with the brazing composition.
- a partial portion of the side surface may be coated with the brazing composition during coating of the brazing composition on e.g., upper surface.
- Such a tube 3 may also be applied as a tube 3 of the present invention.
- the tube 3 is made of aluminum alloy containing, in mass%, 0.15 to 0.45 % of Mn, 0.20 to 0.50% of Si, and the balance consisting of Al and unavoidable impurities.
- the tube 3 may be produced by extrusion of an aluminum alloy of the above-described composition.
- Mn is an element that improves corrosion resistance of the tube 3 and increases the mechanical strength of the tube 3.
- Mn has an effect of improving extrudability of the aluminum alloy during extrusion.
- Mn has an effect of suppressing fluidity of the brazing metal(brazing liquid filler), thereby suppressing the difference in concentration of Zn between the fillet 4 and the tube 3.
- Mn content is controlled to be 0.15 to 0.45% by mass.
- Preferable Mn content is 0.20 to 0.40% by mass.
- Silicon (Si) 0.20 to 0.50% by mass
- Si is an element having an effect of increasing strength and corrosion resistance of the tube 3.
- the Si content in the aluminum alloy for constituting the tube 3 is controlled to be 0.20 to 0.50% by mass.
- the Si content is preferably 0.25 to 0.45% by mass.
- the fin 4 to be joined to the tube 3 is constituted of an aluminum alloy containing, in mass %, 1.20 to 1.80% of Zn, 0.70 to 1.20% of Si, 0.30 to 0.80% of Fe, 0.90 to 1.50% of Mn, and further containing one or two or more element selected from 0.05 to 0.20% of Zr, 0.01 to 0.10% of V, and 0.01 to 0.10% of Cr, and the balance consisting of Al and unavoidable impurities.
- the fin 4 is produced by casting a molten alloy having the above-described composition in accordance with the general method, and working the cast alloy into a corrugated shape through, hot-rolling, cold-rolling or the like.
- the method of producing the fin 4 is not limited to a specific method. It is possible to apply known methods of producing a fin. In the following, reasons for limiting the composition of aluminum alloy constituting the fin 4 of the present invention is explained.
- Zinc (Zn) 1.20 to 1.80% by mass
- the presence of Zn reduces the electric potential of the fin 4 and provides the fin 4 with sacrificial corrosion protection effect.
- the sacrificial corrosion protection effect of the fin denotes an effect that preferential corrosion of the fin protects other members (e.g., tube) from corrosion.
- the fin cannot exhibits a sufficient sacrificial protection effect.
- the content af Zn exceeds 1.80%, Zn diffuses into the fillet in large amount during the brazing.
- the Zn concentration in the fillet 9 is increased, and the fillet is corroded before the fin 4 is corroded.
- the corrosion rate of the fin 4 is increased, and the life of the fin is shortened.
- the fin has the sacrificial corrosion protection effect only for a short time. Therefore, in the present invention, the Zn content of the fin 4 is controlled to be 1.20 to 1.80% by mass.
- the Zn content is preferably 1.45 to 1.55%.
- the presence of Si improves the high-temperature strength and the room-temperature strength of the fin 4.
- the content of Si in the fin is less than 0.70%, it is impossible to improve the high-temperature strength and room-temperature strength effectively.
- the Si content in the aluminum alloy for constituting the fin is controlled to be 0.70 to 1.20%.
- the Si content is preferably 0.95 to 1.10%.
- Fe improves the high-temperature strength and the room-temperature strength af the fin 4.
- the content of Fe is less than 0.30%, it is impossible to improve the high-temperature strength and the room-temperature strength effectively.
- the Fe content in the aluminum alloy for constituting the fin is controlled to be 0.30 to 0.80% by mass.
- Preferable Fe content is 0.47 to 0.53% by mass.
- Mn improves high-temperature strength and room-temperature strength of the fin 4.
- content of Mn is less than 0.90%, it is impossible to improve the high-temperature strength and the room-temperature strength of the fin 4 effectively.
- the Mn content in the aluminum alloy for constituting the fin is controlled to be 0.90 to 1.50 % by mass.
- the Mn content is preferably 1.15 to 1.25 % by mass.
- Si and Fe are controlled to be in the above-described ranges, Si and Fe respectively form Mn-containing precipitates, thereby reducing the amount of solid-solubilized Mn, and decreasing the electric potential of the fin 4.
- fin 9 is preferentially corroded compared to the primary portion of the fillet 9, thereby preventing separation of fillet 9.
- the Zr content of the aluminum alloy for constituting the fin is controlled to be 0.05 to 0.20% by mass.
- the Zr content is preferably 0.10 to 0.15 % by mass.
- V Vanadium (V): 0.01 to 0.10%
- V improves the high-temperature strength and the room-temperature strength of the fin 4.
- the content of V is less than 0.01 %, it is impossible to improve the high-temperature strength and the room-temperature strength of the fin 4 effectively.
- the V content in the aluminum alloy for constituting the fin is controlled to be 0.01 to 0.10% by mass. Preferable content is 0.02 to 0.08% by mass.
- the Cr content in the aluminum alloy for constituting the fin is controlled to be 0.01 to 0.10% by mass.
- the Cr content is preferably 0.02 to 0.08% by mass.
- the aluminum alloy constituting the fin of the present invention contains one, two or more selected from Zr, V, and C with a content of the above-described range.
- the header pipe 1 is constituted of a pipe wall having three layered structure including a core material 11, a sacrificial corrosion protection material 12 provided to the outer periphery of the core material 11, and a brazing material layer 13 provided to the inner periphery of the core material 11.
- the sacrificial corrosion protection material 12 By providing the sacrificial corrosion protection material 12 to the outer periphery of the core material 11, it is possible to obtain corrosion protection by the header pipe 1 in addition to the corrosion protection by the fin 4. Therefore, it is possible to increase the corrosion resistance of the tube 3, especially in the vicinity of the header pipe 1.
- the material 11 is constituted of a Al-Mn-based alloy.
- the core material 11 contains 0.05 to 1.50% by mass of Mn.
- the core material may further contain 0.05 to 0.8% by mass of Cu and/or 0.05 to 0.15% by mass of Zr.
- the balance of the above-described composition may be Al and unavoidable impurities.
- Sacrificial corrosion protection material 12 provided to the outer periphery of the core material 11 is constituted of an aluminum alloy containing 0.60 to 1.20% by mass of Zn, and the balance consisting of Al and unavoidable impurities.
- the sacrificial corrosion protection material 12 is integrated to the core material 11 as a clad layer by rolling (clad-rolling). The contents of the components of the sacrificial corrosion protection material 12 are limited based on the below described reason.
- Zinc(Zn) 0.60 to 1.20% by mass
- Zn is an element that provides the sacrificial corrosion protection material 12 with sacrificial corrosion protection effect.
- content of Zn is less than 0.60%, sufficient sacrificial corrosion protection effect cannot be obtained.
- content of Zn exceeds 1.20% by mass, corrosion-resistance of the sacrificial corrosion protection material 12 itself is deteriorated. That is, by excessive corrosion of the sacrificial corrosion protection material, effect of sacrificial corrosion protection cannot be maintained for a long time. Therefore, content of Zn in the sacrificial corrosion protection material 12 is preferably controlled within the range of 0.60 to 1.20%. Preferable content of Zn is 0.70 to 1.10% by mass.
- Clad ratio of the sacrificial corrosion protection material 12 to the core material is preferably 5 to 10%. That is, thickness of the sacrificial corrosion protection material 12 is preferably 5 to 10% of total thickness of the sacrificial corrosion protection material 12 and the core material 11. Where the clad ratio of the sacrificial corrosion protection material 12 is less than 5%, sufficient sacrificial corrosion protection effect cannot be obtained. Where the clad ratio of the sacrificial corrosion protection material 12 exceeds 10%, increase of the sacrificial corrosion protection effect does not correspond to the increasing thickness of the sacrificial corrosion protection material 12.
- the brazing material 13 provided to the inner periphery of the core material 11 is preferably constituted of Al-Si based alloy.
- the Al-Si based alloy contains 5.0 to 11.5% by mass of Si.
- the brazing material 13 is clad to the core material by rolling. Clad ratio of the brazing material 13 to the core material 11 is preferably 3 to 10% by mass. Where clad ratio of the brazing material 13 is less than 3%, sufficient brazing metal cannot be provided for constituting a fillet 8. Where the clad ratio of the brazing material 13 exceeds 10%, the brazing metal is provided excessively.
- FIG. 2 is an magnified view showing a partial portion of a pre-brazing assembly 101 constructed of the header pipes 1 (2), tubes 3 and fins 4, where tubes 3 are coated with the brazing composition on the surfaces joined with the fins 4.
- tube 3 is assembled to the header pipe 1 such that an end portion of the tube 3 is inserted to a slit 6 formed in the header pipe 1.
- the assembly 101 is heated to a temperature not lower than the melting point of the brazing material.
- the brazing material 13 is molten as shown in FIG. 3 , and tube 3 is joined to the header pipe 1, and the fin 4 is joined to the tube 3.
- the brazing material 13 in the inner periphery of the header pipe 1 is fused (molten) and flows to the vicinity of the slit 6, forming fillets 8 by which the header pipe 1 and the tube are joined.
- the coating 7 of the brazing composition is fused to form a brazing liquid filler that flows towards the vicinity of fin 4 by capillary effect and forms fillets 9 by which the tube 3 and the fin 4 are joined.
- the assembly is heated to an appropriate temperature in an appropriate atmosphere such as an inert atmosphere so as to fuse the brazing composition coating 7 and the brazing material 13. Then an activity of the flux is increased, and Zn contained in the flux precipitates on the surface of the brazed material(tube 3) and diffuses into the thickness direction of the tube 3.
- the activated flux decomposes oxide film on the surface of the tube 3 and oxide films on the surface of powder particles in the brazing composition, and increases wetting between the brazing metal and the brazed material.
- heating temperature is not lower than the melting point of the brazing material.
- the assembly is heated up to a temperature in a range of 580 to 615°C and held at that temperature for about 1 to 10 minutes.
- the assembly is retained (held) at an intermediate temperature within a range of 530 to 575°C for 4 to 8 minutes. While holding the intermediate temperature, Zn contained in the flux is diffused into the surface portion of the tube 3 and fixed in the tube. As a result, the amount of Zn flows to the fillet is reduced, and separation of the fin 4 is prevented.
- intermediate retention temperature is less than 530°C or retention time is shorter than 4 minutes
- Zn cannot diffuse into the surface portion of the tube 3 sufficiently.
- a large amount of Zn is contained in the brazing liquid filler flowing to the fillet 9.
- the retention temperature exceeds 575°C or the retention time exceeds 8 minutes
- Zn diffuse into the tube wall excessively, resulting in low Zn concentration on the surface portion of the tube 3.
- a satisfactory sacrificial corrosion protection layer is not formed on the surface of the tube 3, and a corrosion resistance of the tube is deteriorated. Therefore, intermediate retention conditions during the heating process are held at a temperature range of 530 to 575°C for a duration in a range of 4 to 8 minutes.
- the assembly may be heated from 530 to 575°C with a time of 4 to 8 minutes.
- the assembly may be held at 570°C for 4 to a time shorter than 8 minutes, Any other thermal history may be applied provided that the assembly is exposed to heating conditions in the temperature range of 530 to 575°C for a duration of not shorter than 4 minutes and not longer than 8 minutes.
- partial fraction of a matrix of the aluminum alloy constituting the tube 3 reacts with the brazing composition of the coating 7 and forms a brazing metal by which the tube 3 and the fin 4 are brazed.
- Zn contained in the flux diffuses into the surface portion of the tube 3, making the electric potential of the tube surface lower than that of the inner portion of the tube 3.
- satisfactory brazing metal is formed in the time of brazing without occurring residual silicon particles, and a fillet 9 of sufficient size is formed between the tube 3 and the fin 4.
- concentration of Zn to the fillet 9 is suppressed by the increased size of the fillet 9.
- the assembly is held at an intermediate temperature range of 530 to 575°C for 4 to 8 minutes and subsequently heated to the brazing temperature.
- the tube 3 by having the tube 3 to contain appropriate amounts of Mn and Si, that is, 0.15 to 0.45% by mass of Mn and 0.20 to 0.50% by mass of Si, it is possible to provide a tube having superior corrosion resistance compared to the conventional tube made of 1050 alloy or Al-Cu based alloy.
- Mn contained in the tube 3 suppress fluidity of the brazing liquid filler in the time of brazing. Therefore, excessive flow of brazing liquid filler to the fillet 9 is avoided, and partial fraction of the brazing liquid filler remains on the surface of the tube 3. Therefore, it is possible to suppress the difference in Zn concentration between the fillet 9 and the surface of the tube 3, thereby suppressing separation of fin 4.
- the heat exchanger 100 of the present embodiment appropriate amount of Si and Fe, that is, 0.7 to 1.20% by mass of Si and 0.30 to 0.80% by mass of Fe are added to the aluminum alloy constituting the fin. Therefore, it is possible to form intermetallic compounds of Si, Fe, and Mn, thereby improving sacrificial corrosion protection effect by the fin. Therefore, it is possible to suppress the amount of Zn in the fin to provide sacrificial corrosion protection effect. As a result, as shown in FIG. 8 , it is possible to reduce diffusion of Zn from the fin 4 to the fillet 9, thereby reducing concentration of Zn in the fillet 9. Therefore, it is possible to prevent preferential corrosion of the fillet 9, thereby suppressing separation of the fin 4.
- the coating of a brazing composition on the surface leaving the side surfaces uncoated, where the perimeter of a uncoated side surface is controlled to be within 1.5 times the thickness of the tube.
- Zn-containing portions constitute anode portions, and protect Zn-free portion as a cathode portion from corrosion by preferential corrosion of the anode portion. That is, as the Zn-free cathode portion (side surface of the tube) has a large area fraction, corrosion of the Zn-containing anode portion (brazing metal coated portion) is increased by the sacrificial corrosion protection effect.
- electric potential of outer surfaces of header pipes 1,2 also affect the corrosion of fillet 9 in the vicinity of the header pipes 1,2. Since each of the header pipes 1,2 has a large surface area, the electric potential of the tube has a large influence.
- the header pipes 1, 2 each comprises a core material 11, the outer sacrificial corrosion protection material 12, and inner brazing material 13, and the sacrificial corrosion protection material 12 contains Zn in an amount of 0.60 to 1.20% by mass, by the preferential corrosion of sacrificial corrosion protection material 12 of the header pipes 1, 2, it is possible to suppress preferential corrosion of the fillets 9 in the vicinity of the header pipes 1,2, for example, in the position shown by the oval dotted line shown in FIG. 9 , thereby suppressing separation of the fin 4.
- the assembly is held at an intermediate temperature range of 530 to 575°C for 4 to 8 minutes before heated up to the brazing temperature.
- FIG. 11 shows a comparison of the two cases. Where the retention was performed at a temperature range of 530 to 575°C for 4 to 8 minutes, as shown in the curve al, Zn diffuses into a deep portion in the tube 3. On the other hand, when the above-described retention is avoided, Zn does not diffuse into the deep portion of the tube 3.
- FIG. 12 is a diagram showing a Zn concentration profile along a depth direction in the tube 3 and position of the fin 4, where the retention has not been performed.
- FIG. 13 is a graph showing a Zn concentration profile along a depth direction in the tube 3 and position of the fin 4, where the retention has been performed.
- Si in the brazing material may form eutectic composition with Al resulting in increase of erosion.
- the depth of erosion is shown by the dotted line in each of FIG. 12 and FIG. 13 .
- the diffusion of Zn proceeds in the molten brazing liquid filler having the eutectic composition.
- the diffusion depth of Zn in the tube is reduced, and the amount of Zn concentrating in the fillet 9 generated in the surface portion of the tube joined with the fin is increased.
- Zn diffuses deeply into the tube 3, and the amount of Zn existing in the tube surface and concentrating in the fillet 9 is decreased. Therefore, the amount of Zn concentrated in the fillet 9 generated in the surface portion of the tube joined with the fin is decreased. Therefore, it is possible to inhibit preferential corrosion of the fillet 9, thereby preventing the separation of the fins 4.
- An aluminum alloy having a composition shown in Table 1 was cast from molten alloy for constituting tubes, and aluminum alloy having a composition shown in Table 2 was cast from a molten alloy for constituting fins.
- an aluminum alloy for core material, an aluminum alloy for sacrificial corrosion protection material, and an aluminum alloy for brazing material, each having a composition as shown in Table 3 were cast from molten alloys.
- the aluminum alloy for a tube was subjected to heat treatment for homogenization, and was subsequently subjected to hot extrusion so as to have a shapes as shown in transversal cross section in FIG. 4 and FIG.6A .
- the wall thickness was 0.30 mm
- the width was 18.0 mm
- the total thickness was 1.5 mm
- the height of flat face of the side surface was 0.6 mm
- the curvature radius of the corner portion was 0.45 mm.
- the wall thickness was 0.30 mm
- the width was 18.0 mm
- the total thickness was 1.5 mm
- the height of flat face of the side surface was 0.9 mm
- the curvature radius of the corner portion was 0.3 mm.
- tubes 31 having an arc shaped section of the side surface 3 as shown in FIG. 6B and FIG. 7B were produced such that a radius of the arc was 0.75 mm or 1.5 mm.
- a tube having a side surface constituted of inclined flat faces as shown in FIG, 6C was formed such that the angel between flat faces was 90°.
- the aluminum alloy for the fins was subjected to homogenization heat treatment, hot rolling, and cold rolling, thereby obtaining a plate of 0.08 mm in thickness.
- the plate was subjected to corrugated processing. Thus, fins 4 were produced.
- An aluminum alloy for sacrificial corrosion protection material, an aluminum alloy for core material, and an aluminum alloy for brazing material were each subjected to hot rolling and cold rolling to obtain plates each having a thickness of 0.12 mm, 1.30 mm, and 0.08 mm.
- Three layered clad plate was obtained using the aluminum alloy plate for core material as a center layer, and arranging the aluminum alloy plate for sacrificial corrosion protection material on one side, and aluminum alloy plate for brazing material on another side of the core material.
- the three layered clad plate was processed to an seam-welded pipe having a circular section. Header piepe 1 was produced by working the seam -welded pipe.
- Outer layer of the header pipe 1 was sacrificial corrosion protection material, and inner layer of the header pipe 1 was a brazing material.
- brazing composition was roll-coated on the surface of the tube 3, and was dried.
- the brazing composition was constituted of a mixture of silicon powder (grain size: 2.8 ⁇ m in D(50)), flux powder composed of KZnF 3 (grain size: 2.0 ⁇ m in D(50)), and acrylic resin (containing alcohol such as isopropyl alcohol as a solvent).
- the amount of each component mixed in the composition was controlled such that the amount of the component in the coating had a value as shown in Table 4.
- header pipes 1, tubes 3, and fins 4 were constructed to form constructed bodies having a shape of heat exchangers 100 as shown in FIG. 1 , and the heat exchangers were subjected to brazing using a condition selected from the below-described three conditions. In each case, the brazing was performed in a nitrogen atmosphere in a furnace.
- the assembly was heated from a room temperature to 570°C, kept at 570°C for 4 minutes, subsequently hearted to 600°C, and held at 600°C for 2 minutes.
- condition 2 the assembly was continuously heated to 600°C, and held at 600°C for 2 minutes, where the assembly passed the temperature range from 530 to 575°C for 6 minutes.
- condition 3 the assembly was continuously heated to 600°C, and held at 600°C for 2 minutes, where the assembly passed the temperature range from 530 to 575°C for 1 minutes.
- each heat exchanger was subjected to evaluation of brazability.
- a tube 3 of 100mm in length containing 33 joint portions joined to the fin 4 was cut out from the heat exchanger.
- a proportion of a length of the braze-joint to a width of fin (18 mm) was examined, and a ratio was calculated from the result of examination at 33 joint portions, and was shown in Table 4 as a joint ratio. Based on the value of a joint ratio, the brazability was evaluated.
- each of heat exchangers 100 was subjected to sea water acetic acid test (SWAAT) for 20 days to evaluate the corrosion resistance. After the test, the depth of corrosion of the tube 3, and the residual ratio of fin 4 (total length of fins remaining after the test/total length of brazed fins ⁇ 100) were measured. The results were shown in Table 4.
- the coated amount of Si is small, the separation of fin 4 occurs remarkably. Whereas, if the coated amount of Si is too large, the corrosion resistance of the tube 3 is deteriorated and the separation of the fins is increased (See Nos. 1 to 6).
- the coated amount of the flux is too small, the tube 3 has inferior corrosion resistance, and the failure of joint formation with the fin 4 increases. If the coated amount of flux is too large, the separation of the fin 4 occurs remarkably (See Nos.1 to 7).
- the tube 3 has inferior corrosion resistance (See Nos. 16 and 17).
- a perimeter of the arc that is, a perimeter b of the portion not-coated with the brazing composition preferably satisfies b ⁇ a ⁇ 1.5, where a denotes a thickness of the tube 3.
- sample No. 21 in which b ⁇ a ⁇ 1.5 is satisfied is superior both in corrosion resistance and residual ratio of fins.
- the assembly passes through the temperature range of 530 to 575°C during the heating process with a relatively long time of 6 minutes, it is possible to improve the corrosion resistance of the tube 3( see No.19), and it is possible to suppress the separation of the fin 4. However, if the assembly passes through the temperature range of 530 to 575°C during the heating process with a relatively short time of 1 minutes, separation of the fins 4 increases (see No. 20).
- a target value of corrosion depth of the tube was 75 ⁇ m or less, and a target value of a residual ratio of the fin was 70% or more.
- Heat exchangers 100 were produced in the same manner as in Example 1, while the tubes were made of aluminum alloy having a composition shown in Table 5. The depth of corrosion in the tube 3 and the residual ratio of fins 4 were examined in the same manner as in Example 1. The results are shown in Table 5. In this case, brazing composition of No. 4 shown in Table 4 was applied as a coating composition.
- the corrosion resistance of the tube 3 and the residual ratio of fins 4 vary depending on the Mn content and the Si content of the tube 3. Therefore, preferable contents in the present invention were specified to be 0.15 to 0.45 % by mass of Mn and 0.20 to 0.50 % by mass of Si.
- Heat exchangers 100 were produced in a same manner as in Example 1, while the fins were made of aluminum alloy having a composition shown in Table 6. The depth of corrosion in the tube 3 and the residual ratio of fins 4 were examined in the same manner as in Example 1. The results are shown in Table 6. In this case, a brazing composition of No. 4 shown in Table 4 was applied as the coating composition.
- the corrosion resistance of the tube 3 and the residual ration of fin 4 vary depending on the amounts of constituent elements of the aluminum alloy constituting the fin. Therefore it was discovered that the Zn, Si, Fe, and Mn contents in the aluminum alloy of the fins were required to be 1.20 to 1.80% by mass of Zn, 0.70 to 1.20% by mass of Si, 0.30 to 0.80 % by mass of Fe, and 0.90 to 1.50% by mass of Mn so as to achieve a high joint ratio of fin-tube joint, to provide high resistivity, and to increase a high residual ratio of fins.
- Heat exchangers 100 were produced in the same manner as in Example 1, while the header pipes were made of aluminum alloy having a composition shown in Table 7. The depth of corrosion in the tube 3 and the residual ratio of fins 4 were examined in the same manner as in Example 1(Table 7, Nos. 62 to 66).
- Heat exchangers 100 were produced in a same manner as in Example 1, while the header pipes were constituted of a three layered structure comprising a brazing material layer on the outer surface, and a sacrificial layer on the inner surface of the aluminum alloy constituting the core layer.
- the depth of corrosion in the tube 3 and residual ratio of fins 4 were examined in the same manner as in Example 1(Table 7, No. 67).
- the results are shown in Table 6.
- the brazing composition of No. 4 shown in Table 4 was applied as a coating composition.
- Table 7 Header pipe Core material Sacrificial corrosion protection material Brazing material Fin-tube joint ratio (%) Corrosion depth of tube ( ⁇ m) Residual ratio of fin (%) Mn (mass%) Al Zn (mass%) Al Si (mass%) Al 62 1.25 balance 0.55 balance 9.75 balance 95 75 70 63 1.25 balance 0.7 balance 9.75 balance 96 73 72 64 1.25 balance 1.1 balance 9.75 balance 96 70 76 65 1.25 balance 3.0 balance 9.75 balance 95 68 79 66 1.25 balance No sacrificial layer 9.75 96 265 25 67 1.25 balance 0.7 balance 9.75 balance 96 245 28 In sample 65, corrosion resistance of the header was relatively low.
- a corrosion resistance of the tube 3 and the residual ratio of the fins 4 tend to be inferior when the content of Zn in the alloy forming the sacrificial layer is lower or higher than a certain range of composition (No. 62, No.65). Therefore, in the present invention, the preferable content of Zn in the sacrificial corrosion protection material of the header pipe was specified to be 0.60 to 1.20% by mass.
- the header pipe was constituted of a three-layered structure having a sacrificial corrosion protection material in the internal side and brazing material in the outer side, the residual ratio of the fin 4 was deteriorated (No. 67 of Table 7).
- header pipe was constituted of two layered structure having an outer brazing material but lacking outer sacrificial corrosion protection material, as shown in sample No. 66 of Table 7, a corrosion resistance of the tube and the residual ratio of the fins were deteriorated.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Prevention Of Electric Corrosion (AREA)
- Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
- Laminated Bodies (AREA)
Abstract
Description
- The present invention relates to a heat exchanger made of an aluminum alloy and a method of producing the same. Specifically, the present invention relates to a heat exchanger made of an aluminum alloy and a method of producing the same in which separation of fins from tubes can be suppressed.
- Priority is claimed on Japanese Patent Application No.
2008-225324, filed September 2, 2008 - Heat exchangers made of aluminum alloy comprises tubes, fins, and header pipes as main constituents. The heat exchangers are produced by brazing those constituents. Conventionally, brazing sheets clad with Al-Si alloy brazing material have been widely used in their production. Production cost of the heat exchanger has been reduced by using extruded tubes (hereafter referred to as tubes) having surfaces coated with a brazing composition composed of a mixture of a flux, a binder, and a Al-Si alloy powder and/or a Si powder.
- However, since Si diffuses from the surface into the inside of the tube wall, the tube is made to have a high Si concentration in its surface and low Si concentration in the inside layer. As a result, the tube is formed a potential gradient such that the surface portion has a relatively high electric potential and the inside layer has a relatively low electric potential. Such a potential gradient increases corrosion of the tube and causes pitting to occur, causing leakage of a refrigerant, and reducing the strength of the tube.
- It is proposed to improve pitting corrosion resistance of the tube by using tubes having surface coated with a mixture of a Zn-containing flux and a Si powder or the like, and forming a Zn-diffused layer on the surface portion of the tube during the brazing process, thereby making the tube have a potential gradient where the surface portion has a relatively low electric potential and the inside layer has relatively high electric potential.
- However, where the Zn-containing flux is used in the brazing, a large amount of Zn flows with the brazing liquid filler and concentrates to fillets joining fins and the tubes.
- The Zn-concentrated fillets potential become less noble and thereby are corroded preferentially compared to the other portions of the heat exchanger. Where preferential corrosion of the fillets occurs, fins are separated from the tube surfaces, reducing heat transfer efficiency. In such a case, the heat exchanger cannot keep sufficient efficiency.
- In patent reference 1 (Japanese Unexamined Patent Application, First Publication, No.
2004-330233 - Since the Si powder and the Zn containing flux are mixed in the coating of the above-described heat exchanger tube, the Si powder is fused to form brazing liquid filler at the time of brazing, Zn contained in the flux uniformly diffuses in the brazing liquid filler and is spread homogeneously on the tube surface. Since the diffusion rate of Zn in the liquid phase such as brazing liquid filler is far faster than the diffusion rate of Zn in a solid state, the tube surface is made to have a substantially homogeneous Zn concentration. As a result, a sacrificial anode layer is homogeneously formed on the tube surface, thereby improving corrosion resistance of the heat exchanger tube.
- However, according to further investigation by the inventors, it was discovered that preferential corrosion of fillets could not be avoided where large amount of Zn concentrates to fillets. In such a case, even though the Zn concentration in the tube surface can be homogenized, a large difference in concentration of Zn between the fillet and the tube may causes preferential corrosion of the fillet, Therefore, in the process of carrying out the present invention, a requirement for controlling the difference in Zn concentration was taken into consideration.
- Based on the above-described circumstances, an object of the present invention is to provide a heat exchanger that exhibits high joint ratio of fins and tubes, in which corrosion of the tubes can be controlled to be a shallow level, and separation of the fins can be prevented. Another object of the present invention is to provide a method of producing the same heat exchanger.
- A heat exchanger according the present invention is made of an assembly including a tube, a fin, and a header pipe, wherein
the tube is made of aluminum alloy having a composition containing, in mass %, 0.15 to 0.45 % of Mn, 0.20 to 0.50% of Si, and the balance consisting of Al and unavoidable impurities, and a coating of a brazing composition that is coated on a surface of the tube to which the fin is joined and contains 1.0 to 5.0g/m2 of Si powder, 4.0 to 10.0 g/m2 of Zn containing flux composed of KZnF3, and 0.5 to 3.0 g/m2 of a binder; and the fin is made of an aluminum alloy containing, in mass %, 1.20 to 1.80 % of Zn, 0.70 to 1.20% of Si, 0.30 to 0.80% of Fe, 0.90 to 1.50% of Mn, one two or more elements selected from the group consisting of 0.05 to 0.20% of Zr, 0.01 to 0.10% of V, and 0.01 to 0.10% of Cr, and the balance consisting of Al and unavoidable impurities; the header pipe comprises a core material, an outer sacrificial corrosion protection material, and an inner brazing material; and the fin is joined to the tube, and the tube is joined to the header pipe by brazing in the heat exchanger. - The assembly of the above-described heat exchanger may comprises a plurality of tubes, a plurality of fins, and at least two header pipes, wherein each of the tubes has a constitution of the above-described tube, each of the fins has a constitution of the above-described fin, and each of the header pipes has a constitution of the above-described header pipe.
- In the above-described heat exchanger, the tube may has flat surfaces, and the coating of the brazing composition may be formed on at least one flat surface (joint surface)of the tube such that side surfaces of the tube positioned on both sides of the flat surface are left not-coated with the brazing composition, and a perimeter (peripheral length) b of the uncoated side surface satisfies b≤a×1.5, where a denotes a width (height) of the side surface.
- In the above-described heat exchanger, perimeter b of the uncoated side surface may be measured as a peripheral length of the side surface on a cross section perpendicular to the lengthwise direction of the tube. The width a of the side surface coincident to the thickness of the tube.
- In the above-described heat exchanger, the tube may comprises: two main flat surfaces that are parallel to each other, elongate along a lengthwise direction of the tube; and two side surfaces positioned on both sides of the main surfaces, wherein a contact plane being in contact with the side surface is inclined from the flat surface.
- In the above-described heat exchanger, a sacrificial corrosion protection material of the header pipe may contains 0.60 to 1.20% by mass of Zn, and the balance consisting of Al and unavoidable impurities.
- A heat exchanger according to any one of the above-described constitutions may be produced by a process comprising:
- making the fin contact the surface of the flat tube coated with the brazing composition;
- making the tube be assembled with the header pipe; and
- heating the assembly having the fin, tube, and header pipe to a predetermined brazing temperature, wherein the assembly is held at an intermediate temperature range from 530 to 575°C for 4 to 8 minutes during the heating, and is subsequently heated to the predetermined brazing temperature.
- In the above-described heat exchanger, the predetermined brazing temperature may be in the range from 580 to 615°C.
- According to the heat exchanger of the present invention, the tube added with appropriate amounts of Mn and Si has a corrosion resistance superior to the conventional alloy such as 1050 alloy or Al-Cu based alloy. Therefore, it is possible to reduce the amount of Zn contained in the flux for forming a sacrificial corrosion protection layer. As a result, it is possible to reduce the amount of Zn flowing to the fillet with the brazing liquid filler, thereby suppressing the preferential corrosion of the fillet. Thus, it is possible to prevent separation of the fin.
- According to the heat exchanger of the present invention, Mn added to the tube suppresses the fluidity of the brazing liquid filler during the brazing process. Therefore, brazing liquid filler formed during the brazing process does not flow excessively to the fillet, and partial portion of the brazing liquid filler remains on the tube surface. As a result, it is possible to reduce a difference in the Zn concentration between the fillet and the tube surface, thereby suppressing preferential corrosion of the fillet, and preventing separation of the fin.
- In the heat exchanger of the present invention, the fin may be added with appropriate amounts of Si and Fe. Therefore, it is possible to generate intermetallic compounds of Si, Fe, and Mn. Since the intermetallic compounds increase the sacrificial corrosion protection effect by the fins, it is possible to reduce the content of Zn contained in the fin to provide the sacrificial corrosion protection effect. As a result, it is possible to reduce diffusion of Zn from the fin to the fillet, thereby preventing preferential corrosion of the fillet, and preventing separation of the fin.
- Therefore, according to the present invention, it is possible to provide a heat exchanger, wherein fins are not likely to fall down compared to the conventional heat exchanger.
- Since the fins are not likely to separate in the heat exchanger according to the present invention, corrosion proof of the tube by the sacrificial corrosion protection effect of the fin can be maintained for a long period of time. As a result, it is possible to prolong a life of the tube compared to a conventional heat exchanger.
- In the heat exchanger of the present invention, it is preferable to form the coating of brazing composition on the surface of the tube to which the fin is brazed leaving an uncoated portion on the side surface. It is preferable to control the perimeter of the uncoated portion on the side surface of the tube to be within 1.5 times the width of the side surface of the tube.
- In the heat exchanger of the present invention having the tube brazed with fin, Zn-containing portion constitutes an anode portion, and Zn-free portion constituting the cathode portion is protected from corrosion by preferential corrosion of the anode portion. As the Zn-free portion (side surface of the tube) acting as the cathode portion has a large area, Zn-containing portion (brazing composition coated surface) is corroded severely by the sacrificial anode effect.
- Therefore, by reducing the area of Zn-free portion as much as possible, it is possible to suppress the progress of corrosion, inhibit preferential corrosion of the fillet, and suppress separation of the fins.
- In a heat exchanger, an outer surface of header pipes having a large surface area may act as a cathode and increases corrosion of the fillet. However, by constituting the header pipe of core layer, outer sacrificial corrosion protection material, and inner brazing material, and by having the sacrificial corrosion protection material contains 0.60 to 1.20% by mass of Zn so as to have the sacrificial corrosion protection material of the header pipe be corroded preferentially, it is possible to suppress the preferential corrosion of fillet, thereby suppressing separation of the fin.
- During the heating process in the process of producing a heat exchanger according to the present invention, the assembled fin, tube, and fillet are held at an intermediate temperature range from 530 to 575°C for 4 to 8 minutes, and subsequently heated to a brazing temperature. In this method, since the assembly is held for a predetermined duration at a temperature range at which flow of brazing liquid filler does not occur but diffusion of Zn to the tube does occur, it is possible to ensure sufficient diffusion of Zn into the tube wall of the tube. Therefore, it is possible to suppress the excessive concentration of Zn into the fillet. Therefore, it is possible to suppress the preferential corrosion of fillet, thereby suppressing separation of the fin from the heat exchanger.
-
-
FIG. 1 is a schematic diagram showing a front view of a heat exchanger according to one embodiment of the present invention. -
FIG. 2 is a schematic diagram showing a cross section of a partial portion of an assembly comprising header pipes, tubes, and fins according to the present invention at a state before brazing. -
FIG. 3 is a schematic diagram showing a cross section of a partial portion of an assembly comprising header pipes, tubes, and fins according to the present invention at a state after brazing. -
FIG. 4 is a transversal cross section of a tube according to the present invention. -
FIG. 5 is an exemplary drawing showing an anode portion and a cathode portion in the cross section of the tube according to the present invention. -
FIGS. 6A to 6C respectively show examples of a cross-sectional shape of side surface of a tube according to the present invention.FIG. 6A shows an example in which side surface of the tube has a flat surface constituting a main area and curved corner surfaces in the vicinity of the surface of the tube.FIG. 6B is a diagram showing an example in which the tube has a curved side surface.FIG. 6C is a diagram showing an example in which the side surface of the tube is constituted of two flat surfaces inclined to each other forming an angle θ. -
FIGS. 7A and 7B respectively show examples of a cross section of a tube according to the present invention.FIG. 7A shows an example where the side surface S1 of the tube has a flat surface.FIG. 7B shows a cross section of an example shown inFIG. 6B , where a whole area of the side surface S2 is a curved surface. -
FIG. 8 is a diagram showing an exemplary state of brazing a fin to a tube according to the invention, where the fin is brazed to the tube by fillets. -
FIG. 9 shows a state of the brazing tube, fins, and header pipes by fillets, where a surface of the header pipe is composed of a Zn-containing sacrificial corrosion protection material. -
FIG. 10 shows a state of a brazing tube, fins, and header pipes by fillets, where a surface of the header pipe is free of Zn. -
FIG. 11 is an exemplary drawing showing a concentration profile of Zn in the surface portion of the tube, showing profiles obtained by a brazing process of the fin to the tube in a case where the heating temperature is raised monotonously to the brazing temperature, and in a case where the heating temperature is held at an intermediate temperature for a predetermined duration and subsequently raised to the brazing temperature. -
FIG. 12 is a drawing explaining a concentration profile of Zn on the surface portion of the tube obtained by a brazing process of the fin to the tube in a case where heating temperature is raised monotonously to the brazing temperature. - FIG. is a drawing showing a concentration profile of Zn in the surface portion of the tube, showing a profile obtained by a brazing process of the fin to the tube in a case where a heating temperature is held at an intermediate temperature range for a predetermined duration and subsequently raised to the brazing temperature.
- In the following, an embodiment according to present invention is explained in detail with reference to the drawings.
-
FIG. 1 is a schematic diagram that shows an embodiment of a heat exchanger according to the present invention. Theheat exchanger 100 mainly comprises twoheader pipes flat tubes 3 that are in parallel to each other and each joined to theheader pipes lower tubes 3.Header pipes tubes 3, andfins 4 are constituted of below-described aluminum alloys. - Specifically, the
header pipe 1 andheader pipe 2 have side surfaces opposed to each other, and a plurality of slits are formed in the side surface with a predetermined interval along lengthwise direction of each header pipe. An end portion of eachtube 3 are inserted into the opposed slits of theheader pipes tube 3 is installed between theheader pipes tubes 3 are installed between theheader pipes fin 4 is brazed to an upper surface or a lower surface of thetube 3. That is, as shown inFIG. 3 , fillets 8 are formed at joint portions where end portions of thetube 3 are inserted to theslits 6 of theheader pipes tube 3 is brazed to theheader pipes corrugated fin 4 are opposed to surface ofadjacent tubes 3 andfillets 9 are formed between the ridge portions and the tube surface, Thus, corrugated fins are brazed to the surface of thetube 3. - At a state before brazing, surfaces of each
tube 3, that is the surfaces to which thefin 4 is joined, are coated with a coating for brazing (coating 7 of a brazing composition). Thecoating 7 includes 1.0 to 5.0 g/m2 of Si powder, 4.0 to 10.0 g/m2 of Zn-containing fluoride based flux (e.g., KZnF3), 0.5 to 3.0 g/m2 of a binder (for example, acrylic resin). - A
tube 3 of the present embodiment has a constitution of a flat multi-port tube, as shown inFIG. 4 and FIG. 5 showing a transversal cross section of thetube 3. Thetube 3 has a plurality of passages 3c in its interior, flatupper surface 3A, flatlower surface 3B, andside surfaces 3D adjacent to the surfaces. - At a state before the brazing, for example, the
coating 7 of brazing composition may be formed on thesurface 3A and thesurface 3B of the tube leaving uncoated portion on both sides of the coated portion. That is, boundaries between the coated portion and uncoated portion defines a width of the coating. Here, the width of the coating is measured along a direction perpendicular to the lengthwise direction of the tube. - A surface of the
flat tube 3 of the present embodiment comprises: two main flat surfaces that are parallel to each other, elongate along a lengthwise direction of thetube 3, and constitute thesurface 3A andsurface 3B of thetube 3; and twoside surfaces 3D positioned on both sides of the main surfaces, wherein a contact plane in contact with theside surface 3D is inclined from the main surface. - It is preferable that a height (width) a of the
side surface 3D, that is, a thickness of the main body of thetube 3 and a perimeter b of the uncoated portion of the side surface satisfies b ≤ a×1.5. Here, the perimeter b of the uncoated portion denotes a peripheral length of the uncoated portion on a cross section perpendicular to the lengthwise direction of the tube. - For example,
side surface 3D of thetube 3 shown inFIG. 4 and FIG. 5 may have a shape composed of aflat face 3G andcurved corner surface 3H as shown inFIG. 6A . For example, where thetube 3 has a thickness (dimension of side surface) of X, theflat surface 3G of theside surface 3D may have a width of 0.45X, and each of the corner portions (curved portions of theside surface 3D) may have a height of 0.275X. - As another example of the side surface of the
tube 3, the side surface may be a curved surface. For example, as shown in 6B, theside surface 3J may have an arc shaped outline on a transversal cross section of the tube such that a curvature radius R of theside surface 3J satisfies R > 1.003(X/2), where X is the thickness (dimension of the side surface) of thetube 3. - Alternatively, the side surface of the
tube 3 may be constituted of two flat faces (inclined faces) 3K inclined to each other. As shown inFIG. 6C , in a transversal cross section of thetube 3, theinclined surfaces 3K may constitute a corner forming an corner angle θ of θ > 84°. In the above-described examples, the limitations of the shapes, R>1.003(X/2) inFIG. 6B and θ > 84° are both defined based on a boundary conditions so as to satisfy b ≤ a × 1.5 defined in the present invention. - An assembly (assembled body) comprising a
tube 3 and afin 4 joined to thetube 3 through afillet 9 may be formed by brazing afin 4 made of an aluminum alloy of the below-described composition to atube 3 made of the aluminum alloy of the below explained composition to have a transversal cross section as shown inFIG. 4 toFIGS.6A-C , using acoating 7 of brazing composition selected from the below-described composition. In such an assembly, aside surface 3D not provided with acoating 7 of brazing composition constitutes acathode portion 9 protected from corrosion, and thefin 4 and thefillet 9 constitute anode portions that are preferentially corroded. - Corrosion rates of the preferentially corroded anode portions (
fin 4 and fillet 9) are largely affected by the area ratio of cathode portions (side surfaces 3D of the tube 3) to the anode portion. As the area ratio of the cathode portion (side surfaces 3D of the tube 3) is decreased, the corrosion rate of the anode portion (fin 4 and fillet 4) is decreased. - For example, when the
tube 30 has a flat side surfaces S1 as shown inFIG. 7A , relative area fraction of the side surface is decreased compared to atube 31 having a curved surface S2 as shown inFIG. 7B . As a result, it is possible to decrease the corrosion rate of thefillets 9. Thus, the shape of thetube 30 is superior to the shape oftube 31 in suppressing separation of the fin. - In a structure of the
tube 3, it is possible to suppress increase of corrosion by decreasing the area of theside surface 3D (cathode portion) free of Zn, thereby suppressing preferential corrosion offillet 9, it is possible to inhibit the separation offin 4, To decrease the area of aside surface 3D of atube 3, it is effective to make theside surface 3D to be constituted of flat surfaces. - In the following, composition used in the
coating 7 of the brazing composition is explained. - A Si powder is eroded with Al (aluminum) as a constituent of the tube and forms brazing filler joining the
fin 4 and thetube 3. At the time of brazing, Si powder is fused to form a brazing liquid filler, and Zn contained in the flux homogeneously diffuses into the brazing liquid filler and is spread uniformly on the surface of thetube 3. The Diffusion rate of Zn in the brazing liquid filler (liquid phase brazing metal) is far faster (greater) than a diffusion rate of Zn in a solid phase. Therefore, the Zn concentration on the surface of thetube 3 is substantially homogenized. That is, the homogenous Zn-diffused layer is formed, and corrosion resistance of thetube 3 is improved. - Where the amount of Si powder in the coating is less than 1.0g/m2, brazability is deteriorated. On the other hand, when an Si is coated with an amount exceeding 5.0g/m2, excessive formation of brazing metal tends to cause concentration of Zn. In addition, corrosion depth of the tube is increased, and it is impossible to obtain the intended effect for preventing separation of fins. Therefore, the amount of Si powder in the coating is controlled to be in the range of 1.0 to 5.0 g/m2.
- Where the grain size (grain diameter) of Si powder is less than 1 µm in D(50), it tends to increase a possibility of failing in forming a braze joint of
fin 4 totube 3, and the residual ratio of fm (ratio of fin escaped from separating) decreases. On the other hand, where the grain size of Si particle exceeds 6 µm in D(50), the depth of corrosion in thetube 3 is increased. Therefore, it is preferable to control the grain size of Si powder to be within 1 to 6 µm in D(50), where D(50) denotes grain size where the cumulative volume of particles having equal size or smaller size than that size constitute 50% in volume of all the particles. D(50) may be measured using a laser beam scattering method. - Zn containing fluoride-based flux forms a Zn diffused layer on the surface of the
tube 3 at the time of brazing, and thereby improving pitting corrosion resistance of the tube. In addition, the flux removes oxide film from the surface of thetube 3 at the time of brazing, and increase spreading and wetting of the brazing filler, thereby improving the brazability. - Where the amount of flux in the coating is less than 4.0g/m2, it is impossible to form the Zn-diffused layer sufficiently, and the corrosion resistance of the tube is deteriorated. In addition, it is impossible to destroy and remove the surface oxide film from the brazed tube suficiently, resulting in poor brazing. On the other hand, where the amount of the flux in the coating exceeds 10.0g/m2, Zn is concentrated in the fillet, especially in the eutectic portion. As a result, corrosion resistance of the fillet is deteriorated and separation of the fin is increased. Therefore, the amount Zn-containing, fluoride based flux in the coating was controlled to be 4.0 to 10.0g/m2. For example, KZnF3 may be used as the Zn-containing fluoride based flux.
- Where the grain size of flux (flux powder) is smaller than 1µm in D(50), depth of corrosion of the
tube 3 increases by aggregation of flux powder. Where the grain size of the flux exceeds 6 µm in D(50), joining of thefins 4 is likely to poor, resulting in reduction of the residual ratio of thefins 4. Therefore, grain size of the flux is preferably 1 to 6 µm. Here, D(50) denotes the critical grain size (grain diameter) as an indicator of grain size distribution of a powder, where the cumulative volume of particles equal to or smaller than the size constitute 50% in volume of all the particles. D(50) may be measured using a laser beam scattering method. - In addition to the Si powder and Zn-containing fluoride based flux, the coating composition contains a binder. For example, acryl-based resin (e.g., acrylic resin) may be used as the binder.
- Where the amount of binder in the coating is less than 0.5g/m2, workability (delamination-resistance) of the coating is deteriorated. On the other hand, where the amount of the binder in the coating exceeds 3.0g/m2, the brazability is deteriorated. Therefore, the amount of binder in the coating is controlled to be 0.5 to 3.0g/m2. In usual, the binder is evaporated by heating at the time of brazing.
- In the present invention, a method of coating the brazing composition comprising Si powder, flux, and binder is not limited. For example, coating of the brazing composition may be performed by an appropriate method selected from a spray method, a shower method, a flow-coater method, a roll-coater method, a brash-coating method, a dipping method, an electrostatic coating method, or the like. A portion of the tube coated by the brazing composition may be whole of the surface of the
tube 3. Alternatively, the coating may be formed on a partial portion of the surface of thetube 3, provided that at least a portion of sufficient area in the vicinity of joint portion to which thefin 4 is joined is coated with the brazing composition such that thefin 4 may be joined to thetube 3 by brazing. Substantially, the side surface of thetube 3 of the present invention is not coated with the brazing composition. Depending on the coating method, a partial portion of the side surface may be coated with the brazing composition during coating of the brazing composition on e.g., upper surface. Such atube 3 may also be applied as atube 3 of the present invention. - The
tube 3 is made of aluminum alloy containing, in mass%, 0.15 to 0.45 % of Mn, 0.20 to 0.50% of Si, and the balance consisting of Al and unavoidable impurities. Thetube 3 may be produced by extrusion of an aluminum alloy of the above-described composition. - In the following, a reason for the limitations on the elements of the aluminum alloy constituting the
tube 3. - Mn is an element that improves corrosion resistance of the
tube 3 and increases the mechanical strength of thetube 3. In addition, Mn has an effect of improving extrudability of the aluminum alloy during extrusion. Further, Mn has an effect of suppressing fluidity of the brazing metal(brazing liquid filler), thereby suppressing the difference in concentration of Zn between thefillet 4 and thetube 3. - Where the content of Mn is less than 0.15% by mass, it is impossible to achieve sufficient effects of improving corrosion resistance and strength of the tube. In addition, fluidity of the brazing filler cannot be suppressed effectively. On the other hand, when the Mn exceeding 0.45% by mass is contained, extrudability of the
tube 3 is deteriorated since high pressure extrusion is required. Therefore, in the tube of the present invention, Mn content is controlled to be 0.15 to 0.45% by mass. Preferable Mn content is 0.20 to 0.40% by mass. - As like as Mn, Si is an element having an effect of increasing strength and corrosion resistance of the
tube 3. - Where content of Si is less than 0.20%, it is impossible to effectively increase the corrosion resistance and strength of the tube. On the other hand, where Si exceeding 0.50% is contained, extrudability of the aluminum alloy is deteriorated. Therefore, in the present invention the Si content in the aluminum alloy for constituting the
tube 3 is controlled to be 0.20 to 0.50% by mass. The Si content is preferably 0.25 to 0.45% by mass. - The
fin 4 to be joined to thetube 3 is constituted of an aluminum alloy containing, in mass %, 1.20 to 1.80% of Zn, 0.70 to 1.20% of Si, 0.30 to 0.80% of Fe, 0.90 to 1.50% of Mn, and further containing one or two or more element selected from 0.05 to 0.20% of Zr, 0.01 to 0.10% of V, and 0.01 to 0.10% of Cr, and the balance consisting of Al and unavoidable impurities. Thefin 4 is produced by casting a molten alloy having the above-described composition in accordance with the general method, and working the cast alloy into a corrugated shape through, hot-rolling, cold-rolling or the like. In the present invention, the method of producing thefin 4 is not limited to a specific method. It is possible to apply known methods of producing a fin. In the following, reasons for limiting the composition of aluminum alloy constituting thefin 4 of the present invention is explained. - The presence of Zn reduces the electric potential of the
fin 4 and provides thefin 4 with sacrificial corrosion protection effect. Here, the sacrificial corrosion protection effect of the fin denotes an effect that preferential corrosion of the fin protects other members (e.g., tube) from corrosion. - Where the content of Zn is less than 1.20%, the fin cannot exhibits a sufficient sacrificial protection effect. On the other hand, where the content af Zn exceeds 1.80%, Zn diffuses into the fillet in large amount during the brazing. As a result, the Zn concentration in the
fillet 9 is increased, and the fillet is corroded before thefin 4 is corroded. In addition, the corrosion rate of thefin 4 is increased, and the life of the fin is shortened. As a result, the fin has the sacrificial corrosion protection effect only for a short time. Therefore, in the present invention, the Zn content of thefin 4 is controlled to be 1.20 to 1.80% by mass. The Zn content is preferably 1.45 to 1.55%. - The presence of Si improves the high-temperature strength and the room-temperature strength of the
fin 4. Where the content of Si in the fin is less than 0.70%, it is impossible to improve the high-temperature strength and room-temperature strength effectively. On the other hand, when Si content exceeds 1.20%, processability of the aluminum alloy during the work processing of the alloy to thefin 4 is deteriorated. Therefore, in the present invention, the Si content in the aluminum alloy for constituting the fin is controlled to be 0.70 to 1.20%. The Si content is preferably 0.95 to 1.10%. - As like as Si, Fe improves the high-temperature strength and the room-temperature strength af the
fin 4. Where the content of Fe is less than 0.30%, it is impossible to improve the high-temperature strength and the room-temperature strength effectively. On the other hand, where the Fe content exceeds 0.80%, processability of the aluminum alloy during the work processing of the alloy to thefin 4 is deteriorated, and the corrosion resistance of the fin itself is decreased. Therefore, in the present invention the Fe content in the aluminum alloy for constituting the fin is controlled to be 0.30 to 0.80% by mass. Preferable Fe content is 0.47 to 0.53% by mass. - As like as Si, Mn improves high-temperature strength and room-temperature strength of the
fin 4. Where content of Mn is less than 0.90%, it is impossible to improve the high-temperature strength and the room-temperature strength of thefin 4 effectively. On the other hand, where the Mn content exceeds 1.50 %, the processability of the aluminum alloy during the work processing of the alloy to thefin 4 is deteriorated. Therefore, in the present invention, the Mn content in the aluminum alloy for constituting the fin is controlled to be 0.90 to 1.50 % by mass. The Mn content is preferably 1.15 to 1.25 % by mass. - Where the content of Si and Fe are controlled to be in the above-described ranges, Si and Fe respectively form Mn-containing precipitates, thereby reducing the amount of solid-solubilized Mn, and decreasing the electric potential of the
fin 4. By this phenomena,fin 9 is preferentially corroded compared to the primary portion of thefillet 9, thereby preventing separation offillet 9. - Like Si, Zr improves the high-temperature strength and room-temperature strength of the
fin 4. Where the content of Zr is less than 0.05%, it is impossible to improve the high-temperature strength and the room-temperature strength effectively. On the other hand, where the Zr content exceeds 0.20%, the processability of the aluminum alloy during the work processing of the alloy to thefin 4 is deteriorated. Therefore, in the present invention, the Zr content of the aluminum alloy for constituting the fin is controlled to be 0.05 to 0.20% by mass. The Zr content is preferably 0.10 to 0.15 % by mass. - As like as Si, V improves the high-temperature strength and the room-temperature strength of the
fin 4. Where the content of V is less than 0.01 %, it is impossible to improve the high-temperature strength and the room-temperature strength of thefin 4 effectively. On the other hand, where the V content exceeds 0.10%, the processability of the aluminum alloy during the work processing of the alloy to thefin 4 is deteriorated. Therefore, in the present invention, the V content in the aluminum alloy for constituting the fin is controlled to be 0.01 to 0.10% by mass. Preferable content is 0.02 to 0.08% by mass. - Like Si, Cr improves the high-temperature strength and room-temperature strength of the
fin 4. Where the content af Cr is less than 0.01%, it is impossible to improve the high-temperature strength and the room-temperature strength effectively. On the other hand, where the Cr content exceeds 0.10%, the processability of the aluminum alloy during the work processing of the alloy to thefin 4 is deteriorated, Therefore, in the present invention, the Cr content in the aluminum alloy for constituting the fin is controlled to be 0.01 to 0.10% by mass. The Cr content is preferably 0.02 to 0.08% by mass. - The aluminum alloy constituting the fin of the present invention contains one, two or more selected from Zr, V, and C with a content of the above-described range.
- Next, a constitution of the
header pipe 1 is explained. - As shown in
FIG. 2 and FIG. 3 , theheader pipe 1 is constituted of a pipe wall having three layered structure including acore material 11, a sacrificialcorrosion protection material 12 provided to the outer periphery of thecore material 11, and abrazing material layer 13 provided to the inner periphery of thecore material 11. - By providing the sacrificial
corrosion protection material 12 to the outer periphery of thecore material 11, it is possible to obtain corrosion protection by theheader pipe 1 in addition to the corrosion protection by thefin 4. Therefore, it is possible to increase the corrosion resistance of thetube 3, especially in the vicinity of theheader pipe 1. - Preferably, the
material 11 is constituted of a Al-Mn-based alloy. For example, it is preferable that thecore material 11 contains 0.05 to 1.50% by mass of Mn. As the other elements, the core material may further contain 0.05 to 0.8% by mass of Cu and/or 0.05 to 0.15% by mass of Zr. For example, the balance of the above-described composition may be Al and unavoidable impurities. - Sacrificial
corrosion protection material 12 provided to the outer periphery of thecore material 11 is constituted of an aluminum alloy containing 0.60 to 1.20% by mass of Zn, and the balance consisting of Al and unavoidable impurities. The sacrificialcorrosion protection material 12 is integrated to thecore material 11 as a clad layer by rolling (clad-rolling). The contents of the components of the sacrificialcorrosion protection material 12 are limited based on the below described reason. - Zn is an element that provides the sacrificial
corrosion protection material 12 with sacrificial corrosion protection effect. - Where the content of Zn is less than 0.60%, sufficient sacrificial corrosion protection effect cannot be obtained. On the other hand, if the content of Zn exceeds 1.20% by mass, corrosion-resistance of the sacrificial
corrosion protection material 12 itself is deteriorated. That is, by excessive corrosion of the sacrificial corrosion protection material, effect of sacrificial corrosion protection cannot be maintained for a long time. Therefore, content of Zn in the sacrificialcorrosion protection material 12 is preferably controlled within the range of 0.60 to 1.20%. Preferable content of Zn is 0.70 to 1.10% by mass. - Clad ratio of the sacrificial
corrosion protection material 12 to the core material is preferably 5 to 10%. That is, thickness of the sacrificialcorrosion protection material 12 is preferably 5 to 10% of total thickness of the sacrificialcorrosion protection material 12 and thecore material 11. Where the clad ratio of the sacrificialcorrosion protection material 12 is less than 5%, sufficient sacrificial corrosion protection effect cannot be obtained. Where the clad ratio of the sacrificialcorrosion protection material 12 exceeds 10%, increase of the sacrificial corrosion protection effect does not correspond to the increasing thickness of the sacrificialcorrosion protection material 12. - The
brazing material 13 provided to the inner periphery of thecore material 11 is preferably constituted of Al-Si based alloy. Preferably, the Al-Si based alloy contains 5.0 to 11.5% by mass of Si. - The
brazing material 13 is clad to the core material by rolling. Clad ratio of thebrazing material 13 to thecore material 11 is preferably 3 to 10% by mass. Where clad ratio of thebrazing material 13 is less than 3%, sufficient brazing metal cannot be provided for constituting a fillet 8. Where the clad ratio of thebrazing material 13 exceeds 10%, the brazing metal is provided excessively. - Next, a method of producing a
heat exchanger 100 mainly constituted of the above-describedheader pipes 1,tubes 3, andfins 4 are explained. -
FIG. 2 is an magnified view showing a partial portion of apre-brazing assembly 101 constructed of the header pipes 1 (2),tubes 3 andfins 4, wheretubes 3 are coated with the brazing composition on the surfaces joined with thefins 4. InFIG. 2 ,tube 3 is assembled to theheader pipe 1 such that an end portion of thetube 3 is inserted to aslit 6 formed in theheader pipe 1. - In the time of brazing, the
assembly 101 is heated to a temperature not lower than the melting point of the brazing material. By this heating, thebrazing material 13 is molten as shown inFIG. 3 , andtube 3 is joined to theheader pipe 1, and thefin 4 is joined to thetube 3. At that time, thebrazing material 13 in the inner periphery of theheader pipe 1 is fused (molten) and flows to the vicinity of theslit 6, forming fillets 8 by which theheader pipe 1 and the tube are joined. Thecoating 7 of the brazing composition is fused to form a brazing liquid filler that flows towards the vicinity offin 4 by capillary effect and formsfillets 9 by which thetube 3 and thefin 4 are joined. - At the time of brazing, the assembly is heated to an appropriate temperature in an appropriate atmosphere such as an inert atmosphere so as to fuse the
brazing composition coating 7 and thebrazing material 13. Then an activity of the flux is increased, and Zn contained in the flux precipitates on the surface of the brazed material(tube 3) and diffuses into the thickness direction of thetube 3. In addition, the activated flux decomposes oxide film on the surface of thetube 3 and oxide films on the surface of powder particles in the brazing composition, and increases wetting between the brazing metal and the brazed material. - As explained above, heating temperature is not lower than the melting point of the brazing material. Where the
coating 7 of the brazing composition on thetube 3 and thebrazing material 13 of theheader pipe 1 have the above-described compositions, the assembly is heated up to a temperature in a range of 580 to 615°C and held at that temperature for about 1 to 10 minutes. In the present embodiment, on the way of heating of the assembly from a room temperature to the above-described heating temperature, the assembly is retained (held) at an intermediate temperature within a range of 530 to 575°C for 4 to 8 minutes. While holding the intermediate temperature, Zn contained in the flux is diffused into the surface portion of thetube 3 and fixed in the tube. As a result, the amount of Zn flows to the fillet is reduced, and separation of thefin 4 is prevented. - Where the intermediate retention temperature is less than 530°C or retention time is shorter than 4 minutes, Zn cannot diffuse into the surface portion of the
tube 3 sufficiently. As a result, a large amount of Zn is contained in the brazing liquid filler flowing to thefillet 9. On the other hand, where the retention temperature exceeds 575°C or the retention time exceeds 8 minutes, Zn diffuse into the tube wall excessively, resulting in low Zn concentration on the surface portion of thetube 3. As a result, a satisfactory sacrificial corrosion protection layer is not formed on the surface of thetube 3, and a corrosion resistance of the tube is deteriorated. Therefore, intermediate retention conditions during the heating process are held at a temperature range of 530 to 575°C for a duration in a range of 4 to 8 minutes. - In the above-described heating process according to the present invention, it is not necessary to perform the retention at the intermediate temperature at a constant temperature. For example, the assembly may be heated from 530 to 575°C with a time of 4 to 8 minutes. Alternatively, the assembly may be held at 570°C for 4 to a time shorter than 8 minutes, Any other thermal history may be applied provided that the assembly is exposed to heating conditions in the temperature range of 530 to 575°C for a duration of not shorter than 4 minutes and not longer than 8 minutes.
- In the time of brazing, partial fraction of a matrix of the aluminum alloy constituting the
tube 3 reacts with the brazing composition of thecoating 7 and forms a brazing metal by which thetube 3 and thefin 4 are brazed. During the brazing, Zn contained in the flux diffuses into the surface portion of thetube 3, making the electric potential of the tube surface lower than that of the inner portion of thetube 3. - According to the present embodiment, satisfactory brazing metal is formed in the time of brazing without occurring residual silicon particles, and a
fillet 9 of sufficient size is formed between thetube 3 and thefin 4. In addition, concentration of Zn to thefillet 9 is suppressed by the increased size of thefillet 9. - In the thus obtained
heat exchanger 100, an appropriate Zn diffused layer is formed on the surface of thetube 3, and pitting of thetube 3 is inhibited. In addition, corrosion of thefillet 9 is suppressed, and joining of thetube 3 and thefillet 4 are ensured for a long period of time, and satisfactory heat transfer efficiency is maintained. - According to the method of producing a
heat exchanger 100 of the present embodiment, the assembly is held at an intermediate temperature range of 530 to 575°C for 4 to 8 minutes and subsequently heated to the brazing temperature. By thus method, it is possible to retain the assembly at a temperature range at which flow of brazing liquid filler does not occur but diffusion of Zn into the tube does occur. Therefore, a large amount of Zn can diffuse into thetube 3, thereby suppressing excessive concentration of Zn into thefillet 9. Therefore, it is possible to suppress preferential corrosion of thefillet 9, thereby preventing separation of thefin 4 from the heat exchanger. - In the
heat exchanger 100 as described above, by having thetube 3 to contain appropriate amounts of Mn and Si, that is, 0.15 to 0.45% by mass of Mn and 0.20 to 0.50% by mass of Si, it is possible to provide a tube having superior corrosion resistance compared to the conventional tube made of 1050 alloy or Al-Cu based alloy. In addition, it is possible to reduce the amount of Zn in the flux for forming the sacrificial protection layer, specifically to be in the range of 4.0 to 10.0g/m2. Therefore, it is possible to reduce the amount of Zn flowing with the brazing liquid filler to form thefillet 9. Thus, it is possible to suppress preferential corrosion of thefillet 9, thereby inhibiting separation of thefin 4. - According to the heat-
exchanger 100 of the present embodiment, Mn contained in thetube 3 suppress fluidity of the brazing liquid filler in the time of brazing. Therefore, excessive flow of brazing liquid filler to thefillet 9 is avoided, and partial fraction of the brazing liquid filler remains on the surface of thetube 3. Therefore, it is possible to suppress the difference in Zn concentration between thefillet 9 and the surface of thetube 3, thereby suppressing separation offin 4. - According to the
heat exchanger 100 of the present embodiment, appropriate amount of Si and Fe, that is, 0.7 to 1.20% by mass of Si and 0.30 to 0.80% by mass of Fe are added to the aluminum alloy constituting the fin. Therefore, it is possible to form intermetallic compounds of Si, Fe, and Mn, thereby improving sacrificial corrosion protection effect by the fin. Therefore, it is possible to suppress the amount of Zn in the fin to provide sacrificial corrosion protection effect. As a result, as shown inFIG. 8 , it is possible to reduce diffusion of Zn from thefin 4 to thefillet 9, thereby reducing concentration of Zn in thefillet 9. Therefore, it is possible to prevent preferential corrosion of thefillet 9, thereby suppressing separation of thefin 4. - Therefore, according to the present embodiment, it is possible to provide a
heat exchanger 100 in which possibility of separation offins 4 is reduced compared to the conventional heat exchangers. - In addition, since separation of
fins 4 is not likely to occur in theheat exchanger 100 of the present embodiment, it is possible to maintain corrosion protection of thetubes 3 by the sacrificial effect of thefins 4 for a long period of time. As a result, it is possible to prolong life of thetube 3. - In the
heat exchanger 100 of the present embodiment, it is preferable to form the coating of a brazing composition on the surface leaving the side surfaces uncoated, where the perimeter of a uncoated side surface is controlled to be within 1.5 times the thickness of the tube. - In the
heat exchanger 100 of the presentinvention having tubes 3 brazed with thefins 4, Zn-containing portions constitute anode portions, and protect Zn-free portion as a cathode portion from corrosion by preferential corrosion of the anode portion. That is, as the Zn-free cathode portion (side surface of the tube) has a large area fraction, corrosion of the Zn-containing anode portion (brazing metal coated portion) is increased by the sacrificial corrosion protection effect. - Therefore, by suppressing the area of the Zn-free portion in the
tube 3, it is possible to suppress increase of corrosion by the sacrificial effect, thereby suppressing preferential corrosion of thefillet 9, and inhibiting separation of thefin 4. - According to the
heat exchanger 100 of the present embodiment, as like as electric potential of side surfaces of the tube, electric potential of outer surfaces ofheader pipes fillet 9 in the vicinity of theheader pipes header pipes - As shown in
FIG. 9 , where theheader pipes core material 11, the outer sacrificialcorrosion protection material 12, andinner brazing material 13, and the sacrificialcorrosion protection material 12 contains Zn in an amount of 0.60 to 1.20% by mass, by the preferential corrosion of sacrificialcorrosion protection material 12 of theheader pipes fillets 9 in the vicinity of theheader pipes FIG. 9 , thereby suppressing separation of thefin 4. - On the other hand, if the surfaces of the
core material 11 of theheader pipes fillet 9 is increased remarkably. If thefillet 9 is lost from the joint in accordance with the progress of corrosion, as shown in the portion surrounded by an oval dotted line onFIG. 10 , joining of thefin 4 to thetube 3 is weakened, resulting in separation offin 4. By providing the Zn-containing sacrificialcorrosion protection material 12 on the outer surface of theheader pipes FIG. 9 , it is possible to suppress preferential corrosion of thefillets 9 remarkably, thereby inhibiting separation of thefins 4. - In the method of producing a
heat exchanger 100 according to the present invention, the assembly is held at an intermediate temperature range of 530 to 575°C for 4 to 8 minutes before heated up to the brazing temperature. An effect of this thermal history is explained further with reference toFIGS. 11 to 13 . - In accordance with the above described production method, by holding the assembly at a temperature range of 530 to 575°C for 4 to 8 minutes, a larger amount of Zn diffuses into the
tube 3. On the other hand, where the above-described retention at the intermediate temperature range is avoided, Zn diffuses into the tube in smaller amount compared to the above-described case.FIG. 11 shows a comparison of the two cases. Where the retention was performed at a temperature range of 530 to 575°C for 4 to 8 minutes, as shown in the curve al, Zn diffuses into a deep portion in thetube 3. On the other hand, when the above-described retention is avoided, Zn does not diffuse into the deep portion of thetube 3. -
FIG. 12 is a diagram showing a Zn concentration profile along a depth direction in thetube 3 and position of thefin 4, where the retention has not been performed.FIG. 13 is a graph showing a Zn concentration profile along a depth direction in thetube 3 and position of thefin 4, where the retention has been performed. During the brazing, Si in the brazing material may form eutectic composition with Al resulting in increase of erosion. The depth of erosion is shown by the dotted line in each ofFIG. 12 and FIG. 13 . When the brazing metal is in a state of molten brazing liquid filler at the above-described temperature range, the diffusion of Zn proceeds in the molten brazing liquid filler having the eutectic composition. On the other hand, when the retention is not performed, the diffusion depth of Zn in the tube is reduced, and the amount of Zn concentrating in thefillet 9 generated in the surface portion of the tube joined with the fin is increased. When the retention is performed, Zn diffuses deeply into thetube 3, and the amount of Zn existing in the tube surface and concentrating in thefillet 9 is decreased. Therefore, the amount of Zn concentrated in thefillet 9 generated in the surface portion of the tube joined with the fin is decreased. Therefore, it is possible to inhibit preferential corrosion of thefillet 9, thereby preventing the separation of thefins 4. - An aluminum alloy having a composition shown in Table 1 was cast from molten alloy for constituting tubes, and aluminum alloy having a composition shown in Table 2 was cast from a molten alloy for constituting fins. For constituting header pipes, an aluminum alloy for core material, an aluminum alloy for sacrificial corrosion protection material, and an aluminum alloy for brazing material, each having a composition as shown in Table 3 were cast from molten alloys.
- The aluminum alloy for a tube was subjected to heat treatment for homogenization, and was subsequently subjected to hot extrusion so as to have a shapes as shown in transversal cross section in
FIG. 4 andFIG.6A . In the tube shown inFIG. 4 , the wall thickness was 0.30 mm, the width was 18.0 mm, the total thickness was 1.5 mm, the height of flat face of the side surface was 0.6 mm, and the curvature radius of the corner portion was 0.45 mm. In the tube shown inFIG. 6A , the wall thickness was 0.30 mm, the width was 18.0 mm, the total thickness was 1.5 mm, the height of flat face of the side surface was 0.9 mm, and the curvature radius of the corner portion was 0.3 mm. - In
addition tubes 31 having an arc shaped section of theside surface 3 as shown inFIG. 6B andFIG. 7B were produced such that a radius of the arc was 0.75 mm or 1.5 mm. A tube having a side surface constituted of inclined flat faces as shown inFIG, 6C was formed such that the angel between flat faces was 90°. - The aluminum alloy for the fins was subjected to homogenization heat treatment, hot rolling, and cold rolling, thereby obtaining a plate of 0.08 mm in thickness. The plate was subjected to corrugated processing. Thus,
fins 4 were produced. - An aluminum alloy for sacrificial corrosion protection material, an aluminum alloy for core material, and an aluminum alloy for brazing material were each subjected to hot rolling and cold rolling to obtain plates each having a thickness of 0.12 mm, 1.30 mm, and 0.08 mm. Three layered clad plate was obtained using the aluminum alloy plate for core material as a center layer, and arranging the aluminum alloy plate for sacrificial corrosion protection material on one side, and aluminum alloy plate for brazing material on another side of the core material. The three layered clad plate was processed to an seam-welded pipe having a circular section.
Header piepe 1 was produced by working the seam -welded pipe. Outer layer of theheader pipe 1 was sacrificial corrosion protection material, and inner layer of theheader pipe 1 was a brazing material.Table 1 Mn
(mass %)Si
(mass %)Al Al alloy for tube 0.25 0.25 balance Table 2 Zn
(mass%)Si
(mass%)Fe
(mass %)Mn
(mass%)Zr
(mass %)V
(mass%)Cr
(mass %)Al At alloy For fins 1.46 0.95 0,50 1,15 0,10 0.05 0.05 balance Table 3 Cu
(mass %)Mn
(mass%)Zr
(mass %)Zn
(mass %)Si
(mass %)Al Al alloy for Header pipe protection Core material 0.50 1.10 0.10 - - balance Sacrificial corrosion material - - - 0.95 - balance Brazing material - - - - 9.75 Balance - Next, brazing composition was roll-coated on the surface of the
tube 3, and was dried. - The brazing composition was constituted of a mixture of silicon powder (grain size: 2.8 µm in D(50)), flux powder composed of KZnF3 (grain size: 2.0 µm in D(50)), and acrylic resin (containing alcohol such as isopropyl alcohol as a solvent). The amount of each component mixed in the composition was controlled such that the amount of the component in the coating had a value as shown in Table 4.
Table 4 No. Coated amount (g/m2) Side surface of tube brazing condition Fin-tube joint ratio (%) Corrosion depth of tube (µm) Residual ratio of fin (%) Si powder KZnF3 flux powder Binder shape Ratio of perimeter 1 - 5.5 1.2 Flat+R:0.45 1.34 1 0 70 0 Comparative 2 0.5 5.5 1.2 Flat+R:0.45 1.34 1 65 68 10 Comparative 3 1.6 5.5 1.2 Flat+R:0.45 1.34 1 95 72 72 4 2.5 6.5 1.2 Flat+R:0.45 1.34 1 96 73 75 5 4.4 5.5 1.2 Flat+R:0.45 1.34 1 96 75 78 6 6.0 5.5 1.2 Flat+R:0.45 1.34 1 100 265 30 Comparative 7 2.5 - 1.2 Flat+R:0.45 1.34 1 10 >400 6 Comparative 8 2.5 3.5 1.2 Flat+R:0.45 1.34 1 96 320 25 Comparative 9 2.5 4.5 1.2 Flat+R:0.45 1.34 1 98 75 80 10 2.5 6.5 1.2 Flat+R:0.45 1.34 1 99 70 72 11 2.5 8 1.2 Flat+R:0.45 1.34 1 99 70 70 12 2.5 9 1.2 Flat+R:0.45 1.34 1 99 69 70 13 2.5 5.5 0.6 Flat+R:0.45 1.34 1 96 72 73 14 2.5 5.5 2.4 Flat+R:0.45 1.34 1 95 72 74 15 2.5 11 1.2 Flat+R:0.45 1.34 1 99 68 5 Comparative 16 2.5 5.5 - Flat+R:0.45 1.34 1 55 280 28 Comparative 17 2.5 5.5 3.5 Flat+R:0.45 1.34 1 69 295 35 Comparative 18 2.5 5.5 1.2 Semicircular Arc 1.57 1 98 98 65 Comparative 19 2.5 5.5 1.2 Flat+R:0.45 1.34 2 98 72 80 20 2.5 5.5 1.2 Flat+R:0.45 1.34 3 98 95 65 Comparative 21 2.5 5.5 1.2 Curved shape R: 1.5 1.05 1 99 72 76 22 2.5 5.5 1.2 Flat+R:0.3 1.22 1 99 71 80 23 2.5 5.5 1.2 flat faces angle: 90° 1.41 1 93 75 70 Condition 1: Heat to 570°C, hold 570°C for 4 minutes, heat to 600°C, and hold 600°C for 2 minutes
Condition 2: Continuously heating to 600°C and hold 600°C for 2 minutes, where heating from 530 to 575°C with 6 minutes
Condition 3: Continuously heating to 600°C and hold 600°C for 2 minutes, where heating from 530 to 575°C with 1 minutes - Next,
header pipes 1,tubes 3, andfins 4 were constructed to form constructed bodies having a shape ofheat exchangers 100 as shown inFIG. 1 , and the heat exchangers were subjected to brazing using a condition selected from the below-described three conditions. In each case, the brazing was performed in a nitrogen atmosphere in a furnace. - In the
condition 1, the assembly was heated from a room temperature to 570°C, kept at 570°C for 4 minutes, subsequently hearted to 600°C, and held at 600°C for 2 minutes. - In
condition 2, the assembly was continuously heated to 600°C, and held at 600°C for 2 minutes, where the assembly passed the temperature range from 530 to 575°C for 6 minutes. - In
condition 3, the assembly was continuously heated to 600°C, and held at 600°C for 2 minutes, where the assembly passed the temperature range from 530 to 575°C for 1 minutes. - After the brazing, each heat exchanger was subjected to evaluation of brazability. In each case, a
tube 3 of 100mm in length containing 33 joint portions joined to thefin 4 was cut out from the heat exchanger. In each of the joint portion, a proportion of a length of the braze-joint to a width of fin (18 mm) was examined, and a ratio was calculated from the result of examination at 33 joint portions, and was shown in Table 4 as a joint ratio. Based on the value of a joint ratio, the brazability was evaluated. - In addition, after the brazing, each of
heat exchangers 100 was subjected to sea water acetic acid test (SWAAT) for 20 days to evaluate the corrosion resistance. After the test, the depth of corrosion of thetube 3, and the residual ratio of fin 4 (total length of fins remaining after the test/total length of brazed fins × 100) were measured. The results were shown in Table 4. - From the results shown in Table 4, the followings was understood.
- If the coated amount of Si is small, the separation of
fin 4 occurs remarkably. Whereas, if the coated amount of Si is too large, the corrosion resistance of thetube 3 is deteriorated and the separation of the fins is increased (See Nos. 1 to 6). - If the coated amount of the flux is too small, the
tube 3 has inferior corrosion resistance, and the failure of joint formation with thefin 4 increases. If the coated amount of flux is too large, the separation of thefin 4 occurs remarkably (See Nos.1 to 7). - If the coated amount of binder is too small or too large, the
tube 3 has inferior corrosion resistance (See Nos. 16 and 17). - Where a side surface of the tube has an arc shape in a cross section, a perimeter of the arc, that is, a perimeter b of the portion not-coated with the brazing composition preferably satisfies b≤a×1.5, where a denotes a thickness of the
tube 3. In sample No. 18, where the ratio of b/a exceeds 1.50, occurrence of separation offins 4 slightly increases, resulting in inferior residual ratio of fin. - Even though the side surface of the
tube 3 has an arc shape, sample No. 21 in which b≤a×1.5 is satisfied is superior both in corrosion resistance and residual ratio of fins. - If the assembly passes through the temperature range of 530 to 575°C during the heating process with a relatively long time of 6 minutes, it is possible to improve the corrosion resistance of the tube 3( see No.19), and it is possible to suppress the separation of the
fin 4. However, if the assembly passes through the temperature range of 530 to 575°C during the heating process with a relatively short time of 1 minutes, separation of thefins 4 increases (see No. 20). - Sample No. 23 in which each side surface was made of two flat faces forming an angle θ of 90° and satisfying b=a×1.41 showed superior corrosion resistance of the tube and a better residual ratio of the fins.
- A target value of corrosion depth of the tube was 75 µm or less, and a target value of a residual ratio of the fin was 70% or more.
-
Heat exchangers 100 were produced in the same manner as in Example 1, while the tubes were made of aluminum alloy having a composition shown in Table 5. The depth of corrosion in thetube 3 and the residual ratio offins 4 were examined in the same manner as in Example 1. The results are shown in Table 5. In this case, brazing composition of No. 4 shown in Table 4 was applied as a coating composition.Table 5 Tube Mn Si Al Fin-tube joint ratio Corrosion depth of tube Residual ratio of fins Remark (mass%) (mass%) (%) (µm) (%) 24 0.13 0.35 balance 95 115 80 25 0.21 0.35 balance 96 75 78 26 0.30 0.35 balance 94 72 76 27 0.39 0.35 balance 95 70 72 28 0.47 0.35 balance 95 72 73 Excessive Mn, Reduced Extrudability 29 0.30 0.15 balance 96 102 78 30 0.30 0.26 balance 96 72 75 31 0.30 0.44 balance 95 75 70 32 0.30 0.52 balance 95 75 72 Excessive silicon, Reduced Extrudability - As shown in Table 5, the corrosion resistance of the
tube 3 and the residual ratio offins 4 vary depending on the Mn content and the Si content of thetube 3. Therefore, preferable contents in the present invention were specified to be 0.15 to 0.45 % by mass of Mn and 0.20 to 0.50 % by mass of Si. -
Heat exchangers 100 were produced in a same manner as in Example 1, while the fins were made of aluminum alloy having a composition shown in Table 6. The depth of corrosion in thetube 3 and the residual ratio offins 4 were examined in the same manner as in Example 1. The results are shown in Table 6. In this case, a brazing composition of No. 4 shown in Table 4 was applied as the coating composition.Table 6 Fin Zn (mass%) Si (mass%) Fe (mass %) Mn (mass %) Zr (mass %) V (mass %) Cr (mass %) Fin-tube joint ratio (%) Corrosion depth of tube (µm) Residual ration of fins (%) Remark 33 1.1 0.95 0.5 1.2 0.13 0.05 0.05 95 105 92 34 1.3 0.95 0.5 1.2 0.13 - 0.05 96 75 74 35 1.5 0.95 0.5 1.2 0.13 0.05 - 94 70 78 36 1.7 0.95 0.5 1.2 - 0.05 0.05 95 71 76 37 2.0 0.95 0.6 1.2 0.13 - - 95 92 60 38 1.5 0.6 0.5 1.2 0.13 - - 96 113 61 39 1.5 0.8 0.5 1.2 0.13 0.05 0.05 96 75 75 40 1.5 1.1 0.5 1.2 0.13 0.05 0.05 95 73 78 41 1.6 1.25 0.5 1.2 0.13 - - 95 90 60 42 1.5 0.95 0.25 1.2 0.13 - - 94 107 60 43 1.5 0.95 0.41 1.2 0.13 0.05 0.05 95 72 80 44 1.5 0.95 0.69 1.2 0.13 0.05 0.05 96 75 81 45 1.5 0.95 0.85 1.2 0.13 - - 94 85 60 46 1.5 0.95 0.5 0.85 0.13 0.05 0.05 95 105 72 47 1.5 0.95 0.5 1.1 0.13 0.05 0.05 95 73 75 48 1.5 0.95 0.5 1.39 0.13 0.05 0.05 96 75 70 49 1.5 0.95 0.5 1.2 0.1 0.05 0.05 96 74 74 50 1.5 0.95 0.5 1.2 0.15 0.05 0.05 96 75 73 51 1.5 0.95 0.5 1.52 0.13 - - 96 105 62 52 1.5 0.95 0.5 1.2 0.04 - - 95 82 72 Low strength fin 53 1.5 0.95 0.5 1.2 0.22 - - 95 80 76 Processability of fin was reduced 54 1.5 0.95 0.5 1.2 - 0.004 - 96 85 75 Low strength fin 55 1.5 0.95 0.5 1.2 - 0.02 - 95 75 73 56 1.5 0.95 0.5 1.2 - 0.08 - 94 75 72 57 1.5 0.95 0.5 1.2 - 0.12 - 94 82 71 Processability of fin was reduced 58 1.5 0.95 0.5 1.2 - - 0.004 95 89 75 Low strength fin 59 1.5 0.95 0.5 1.2 - - 0.02 96 75 71 60 1.5 0.95 0.5 1.2 - - 0.08 95 75 72 61 1.5 0.95 0.5 1.2 - - 0.12 95 80 74 Processability of fins was reduced - As shown in Table 6, the corrosion resistance of the
tube 3 and the residual ration offin 4 vary depending on the amounts of constituent elements of the aluminum alloy constituting the fin. Therefore it was discovered that the Zn, Si, Fe, and Mn contents in the aluminum alloy of the fins were required to be 1.20 to 1.80% by mass of Zn, 0.70 to 1.20% by mass of Si, 0.30 to 0.80 % by mass of Fe, and 0.90 to 1.50% by mass of Mn so as to achieve a high joint ratio of fin-tube joint, to provide high resistivity, and to increase a high residual ratio of fins. With respect to Zr, V, and Cr, it was discovered that preferable ranges of those elements in the fin of the present invention were 0.05 to 0.20% by mass of Zr, 0.01 to 0.10% by mass of V, and 0.01 to 0.10% by mass of Cr. -
Heat exchangers 100 were produced in the same manner as in Example 1, while the header pipes were made of aluminum alloy having a composition shown in Table 7. The depth of corrosion in thetube 3 and the residual ratio offins 4 were examined in the same manner as in Example 1(Table 7, Nos. 62 to 66). -
Heat exchangers 100 were produced in a same manner as in Example 1, while the header pipes were constituted of a three layered structure comprising a brazing material layer on the outer surface, and a sacrificial layer on the inner surface of the aluminum alloy constituting the core layer. The depth of corrosion in thetube 3 and residual ratio offins 4 were examined in the same manner as in Example 1(Table 7, No. 67). - The results are shown in Table 6. The brazing composition of No. 4 shown in Table 4 was applied as a coating composition.
Table 7 Header pipe Core material Sacrificial corrosion protection material Brazing material Fin-tube joint ratio (%) Corrosion depth of tube (µm) Residual ratio of fin (%) Mn (mass%) Al Zn (mass%) Al Si (mass%) Al 62 1.25 balance 0.55 balance 9.75 balance 95 75 70 63 1.25 balance 0.7 balance 9.75 balance 96 73 72 64 1.25 balance 1.1 balance 9.75 balance 96 70 76 65 1.25 balance 3.0 balance 9.75 balance 95 68 79 66 1.25 balance No sacrificial layer 9.75 96 265 25 67 1.25 balance 0.7 balance 9.75 balance 96 245 28 In sample 65, corrosion resistance of the header was relatively low. - As shown in
FIG. 7 , a corrosion resistance of thetube 3 and the residual ratio of thefins 4 tend to be inferior when the content of Zn in the alloy forming the sacrificial layer is lower or higher than a certain range of composition (No. 62, No.65). Therefore, in the present invention, the preferable content of Zn in the sacrificial corrosion protection material of the header pipe was specified to be 0.60 to 1.20% by mass. - When the header pipe was constituted of a three-layered structure having a sacrificial corrosion protection material in the internal side and brazing material in the outer side, the residual ratio of the
fin 4 was deteriorated (No. 67 of Table 7). - When the header pipe was constituted of two layered structure having an outer brazing material but lacking outer sacrificial corrosion protection material, as shown in sample No. 66 of Table 7, a corrosion resistance of the tube and the residual ratio of the fins were deteriorated.
- While preferred embodiments of the invention have been described and illustrated above, it should be understood that these are exemplary of the invention and are not to be considered as limiting. Additions, omissions, substitutions, and other modifications can be made without departing from the spirit or scope of the present invention. Accordingly, the invention is not to be considered as being limited by the foregoing description, and is only limited by the scope of the appended claims.
Claims (6)
- A heat exchanger made of an assembly including a tube, a fin, and a header pipe, wherein
the tube is made of aluminum alloy having a composition containing, in mass %, 0.15 to 0.45% of Mn, 0.20 to 0.50% of Si, and the balance consisting of Al and unavoidable impurities; a coating of a brazing composition that is coated on a surface of the tube to which the fin is joined and contains 1.0 to 5.0g/m2 of Si powder, 4.0 to 10.0 g/m2 of Zn containing flux composed of KZnF3, and 0.5 to 3.0 g/m2 of binder;
the fin is made of aluminum alloy containing, in mass %, 1.20 to 1.80% of Zn, 0.70 to 1.20% of Si, 0.30 to 0.80% ofFe, 0.90 to 1.50% of Mn, one or two or more elements selected from the group consisting of 0.05 to 0.20% of Zr, 0.01 to 0.10% ofV, and 0.01 to 0.10% of Cr, and the balance consisting of Al and unavoidable impurities;
the header pipe comprises a core material, outer sacrificial corrosion protection material, and an inner brazing material; and
the fin is joined to the tube, and the tube is joined to the header pipe by brazing in the heat exchanger. - A heat exchanger according to claim 1, wherein the tube has flat surfaces, and the coating of the brazing composition is formed on at least one flat surface of the tube such that side surfaces of the tube positioned on both sides of the flat surface are left not-coated with the brazing composition, and a perimeter b of the uncoated side surface satisfies b≤a×1.5, where a denotes a width of the side surface.
- A heat exchanger according to claim 1, wherein sacrificial layer of the header pipe contains 0.60 to 1.20% by mass of Zn, and the balance consisting of Al and unavoidable impurities.
- A heat exchanger according to claim 2, wherein the sacrificial corrosion protection material of the header pipe contains 0.60 to 1.20% by mass of Zn, and the balance consisting of Al and unavoidable impurities.
- A heat exchanger according to any one of claims 1 to 4, produced by a process comprising:constructing an assembly including a fin, a tube, and a header pipe by making the fin to contact the surface of the tube coated with the brazing composition, and making the tube to be assembled with the header pipe; andheating the assembly to a predetermined brazing temperature, wherein the assembly is held at an intermediate temperature range from 530 to 575°C for 4 to 8 minutes during the heating, and is subsequently heated to the predetermined brazing temperature.
- A heat exchanger according to claim 5, wherein the
predetermined brazing temperature is in the range from 580 to 615°C.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008225324 | 2008-09-02 |
Publications (3)
Publication Number | Publication Date |
---|---|
EP2159528A2 true EP2159528A2 (en) | 2010-03-03 |
EP2159528A3 EP2159528A3 (en) | 2013-12-25 |
EP2159528B1 EP2159528B1 (en) | 2015-11-04 |
Family
ID=41376403
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP09169235.0A Active EP2159528B1 (en) | 2008-09-02 | 2009-09-02 | Heat exchanger made of aluminum alloy |
Country Status (4)
Country | Link |
---|---|
US (1) | US20100051247A1 (en) |
EP (1) | EP2159528B1 (en) |
JP (1) | JP5548411B2 (en) |
CN (1) | CN101676667B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2728155A1 (en) * | 2012-11-06 | 2014-05-07 | BorgWarner Inc. | Heat exchange device for exchanging heat between fluids |
EP2758204A4 (en) * | 2011-09-22 | 2016-05-11 | Sapa As | Brazing pre-flux coating with improved corrosion performance |
Families Citing this family (34)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8640766B2 (en) | 2003-05-06 | 2014-02-04 | Mitsubishi Aluminum Co., Ltd. | Heat exchanger tube |
US9283633B2 (en) | 2003-05-06 | 2016-03-15 | Mitsubishi Aluminum Co. Ltd. | Heat exchanger tube precursor and method of producing the same |
JP5408017B2 (en) * | 2009-06-05 | 2014-02-05 | 株式会社デンソー | Cold storage heat exchanger |
DE102009055608A1 (en) * | 2009-11-25 | 2011-05-26 | Behr Gmbh & Co. Kg | Brazed aluminum heat exchanger |
EP2543951B1 (en) | 2010-03-02 | 2020-08-05 | Mitsubishi Aluminum Co.,Ltd. | Heat exchanger constituted of aluminum alloy |
US20110240280A1 (en) * | 2010-03-31 | 2011-10-06 | Kabushiki Kaisha Kobe Seiko Sho (Kobe Steel, Ltd.) | Aluminum alloy brazing sheet and heat exchanger |
JP5670100B2 (en) * | 2010-05-25 | 2015-02-18 | 株式会社Uacj | Method for producing aluminum alloy heat exchanger |
JP5815325B2 (en) * | 2011-08-09 | 2015-11-17 | 三菱アルミニウム株式会社 | Heat exchanger |
JP6030300B2 (en) * | 2011-12-28 | 2016-11-24 | 三菱アルミニウム株式会社 | Heat exchanger manufacturing method using pre-coated fin material and heat exchanger |
EP3961094A1 (en) * | 2012-01-31 | 2022-03-02 | Clean Thermodynamic Energy Conversion Ltd | Heat exchanger assembly and steam generator comprising said assembly |
JP5906113B2 (en) * | 2012-03-27 | 2016-04-20 | 三菱アルミニウム株式会社 | Extruded heat transfer tube for heat exchanger, heat exchanger, and method for producing extruded heat transfer tube for heat exchanger |
JP6002421B2 (en) * | 2012-04-03 | 2016-10-05 | 株式会社ケーヒン・サーマル・テクノロジー | Heat exchanger |
JP6106530B2 (en) * | 2013-06-07 | 2017-04-05 | 株式会社ケーヒン・サーマル・テクノロジー | Method for preventing corrosion of heat exchange pipe outer surface made of extruded aluminum and method for producing heat exchanger |
CN103436747B (en) * | 2013-08-07 | 2016-01-20 | 江阴新仁科技有限公司 | Heat exchange fin plate high-plasticity aluminum alloy and complete processing thereof |
JP6186239B2 (en) * | 2013-10-15 | 2017-08-23 | 株式会社Uacj | Aluminum alloy heat exchanger |
WO2015063903A1 (en) * | 2013-10-31 | 2015-05-07 | 三菱電機株式会社 | Corrosion resistance life diagnosis component, heat exchanger, and refrigeration and air conditioning device |
DE102014206612A1 (en) | 2014-04-04 | 2015-10-29 | Mahle International Gmbh | heat exchangers |
US10661395B2 (en) | 2014-07-30 | 2020-05-26 | Uacj Corporation | Aluminum-alloy brazing sheet |
CN106716042B (en) * | 2014-09-08 | 2019-04-05 | 三菱电机株式会社 | The manufacturing method of the plate-shaped fins of heat exchanger and heat exchanger |
JP7042023B2 (en) | 2014-12-11 | 2022-03-25 | 株式会社Uacj | Brazing method |
CN107003096A (en) | 2014-12-17 | 2017-08-01 | 开利公司 | Aluminum alloy finned heat exchanger |
CN106181126A (en) * | 2015-05-05 | 2016-12-07 | 播磨化成株式会社 | Heat exchanger component, soldering compositions and heat exchanger |
CN105331852A (en) * | 2015-10-15 | 2016-02-17 | 华峰日轻铝业股份有限公司 | Ultrathin high-strength aluminum alloy fin material and preparation method and application thereof |
JP6186455B2 (en) | 2016-01-14 | 2017-08-23 | 株式会社Uacj | Heat exchanger and manufacturing method thereof |
CN106091741A (en) * | 2016-06-17 | 2016-11-09 | 安徽天祥空调科技有限公司 | The Efficient automobile all-aluminum heat exchanger of a kind of high intensity and production technology thereof |
JP6312968B1 (en) | 2016-11-29 | 2018-04-18 | 株式会社Uacj | Brazing sheet and method for producing the same |
JP7053281B2 (en) | 2017-03-30 | 2022-04-12 | 株式会社Uacj | Aluminum alloy clad material and its manufacturing method |
JP7023126B2 (en) * | 2018-01-31 | 2022-02-21 | ダイキン工業株式会社 | Heat exchanger |
CN108195207A (en) * | 2018-03-06 | 2018-06-22 | 北京中热能源科技有限公司 | A kind of dry-and wet-type condenser of anti-scaling anti-corrosive |
JP6932102B2 (en) * | 2018-03-29 | 2021-09-08 | 株式会社Uacj | Aluminum alloy heat exchanger for exhaust gas recirculation system |
US20200033073A1 (en) * | 2018-07-25 | 2020-01-30 | Mahle International Gmbh | Heat exchanger |
KR102299498B1 (en) | 2019-09-06 | 2021-09-08 | 현대자동차주식회사 | Coating composition for tube of heat exchanger and coating method for tube of heat exchanger using the same |
CN114060139A (en) * | 2021-07-30 | 2022-02-18 | 艾酷沃(山东)新材料有限公司 | Automobile radiator capable of adjusting air volume and manufacturing method thereof |
WO2024009131A1 (en) * | 2022-07-07 | 2024-01-11 | Jahdi Ahad | Aluminum radiator with high efficiency temperature control and regulation |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004330233A (en) | 2003-05-06 | 2004-11-25 | Mitsubishi Alum Co Ltd | Tube for heat exchanger |
JP2008225324A (en) | 2007-03-15 | 2008-09-25 | Dic Corp | Ocb mode liquid crystal display element |
Family Cites Families (47)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3878871A (en) * | 1973-11-12 | 1975-04-22 | Saliss Aluminium Ltd | Corrosion resistant aluminum composite |
AU8274587A (en) * | 1986-11-17 | 1988-06-16 | Furukawa Aluminum Co., Ltd. | Process for manufacturing heat exchanger |
JPH0191962A (en) * | 1987-06-12 | 1989-04-11 | Mitsubishi Alum Co Ltd | Manufacture of al heat exchanger |
JPH0320594A (en) * | 1989-06-19 | 1991-01-29 | Honda Motor Co Ltd | Heat exchanger |
JP2691069B2 (en) * | 1990-11-29 | 1997-12-17 | 住友軽金属工業株式会社 | Heat exchanger with excellent corrosion resistance and heat transfer |
US5260142A (en) * | 1990-12-28 | 1993-11-09 | Honda Giken Kogyo Kabushiki Kaisha | Corrosion-resistant clad material made of aluminum alloys |
JP2768393B2 (en) * | 1992-02-25 | 1998-06-25 | 住友軽金属工業 株式会社 | Aluminum alloy for heat exchanger fin material with excellent strength after brazing and sacrificial anode effect |
US5251374A (en) * | 1992-09-01 | 1993-10-12 | Gary A. Halstead | Method for forming heat exchangers |
JPH07207393A (en) * | 1993-09-08 | 1995-08-08 | Furukawa Electric Co Ltd:The | Manufacture of aluminum alloy brazing sheet for heat exchanger and heat exchanger made of aluminum alloy |
JPH08120379A (en) * | 1994-10-14 | 1996-05-14 | Mitsubishi Alum Co Ltd | Aluminum alloy member for brazing |
JP3505825B2 (en) * | 1994-11-28 | 2004-03-15 | 三菱アルミニウム株式会社 | Aluminum alloy heat exchanger fin material that retains high fatigue strength after brazing |
US5732767A (en) * | 1996-01-24 | 1998-03-31 | Modine Manufacturing Co. | Corrosion resistant heat exchanger and method of making the same |
JP3328923B2 (en) * | 1997-01-24 | 2002-09-30 | 日本軽金属株式会社 | Manufacturing method of aluminum heat exchanger core |
US20020007881A1 (en) * | 1999-02-22 | 2002-01-24 | Ole Daaland | High corrosion resistant aluminium alloy |
FR2797454B1 (en) * | 1999-08-12 | 2001-08-31 | Pechiney Rhenalu | ALUMINUM ALLOY STRIP OR TUBE FOR THE MANUFACTURE OF ARMED HEAT EXCHANGERS |
EP1090745B1 (en) * | 1999-10-04 | 2002-06-19 | Denso Corporation | Aluminum alloy clad material for heat exchangers exhibiting high strength and excellent corrosion resistance |
US6458224B1 (en) * | 1999-12-23 | 2002-10-01 | Reynolds Metals Company | Aluminum alloys with optimum combinations of formability, corrosion resistance, and hot workability, and methods of use |
US6939417B2 (en) * | 2000-03-08 | 2005-09-06 | Alcan International Limited | Aluminum alloys having high corrosion resistance after brazing |
JP4560902B2 (en) * | 2000-06-27 | 2010-10-13 | 株式会社デンソー | Heat exchanger and manufacturing method thereof |
JP2002103027A (en) | 2000-09-22 | 2002-04-09 | Mitsubishi Alum Co Ltd | Method of manufacturing heat exchanger |
JP2002361405A (en) * | 2000-09-25 | 2002-12-18 | Showa Denko Kk | Method for manufacturing heat exchanger |
JP3786840B2 (en) * | 2001-01-16 | 2006-06-14 | 株式会社ヴァレオサーマルシステムズ | Heat exchanger |
WO2002055947A1 (en) * | 2001-01-16 | 2002-07-18 | Zexel Valeo Climate Control Corporation | Heat exchanger |
JP2002256402A (en) * | 2001-02-28 | 2002-09-11 | Mitsubishi Alum Co Ltd | Method of producing fin material for use in heat exchanger |
JP2002277187A (en) | 2001-03-22 | 2002-09-25 | Mitsubishi Alum Co Ltd | Header pipe of heat exchanger and heat exchanger using the same |
JP2002294377A (en) | 2001-03-29 | 2002-10-09 | Kobe Steel Ltd | Aluminum alloy composite material for brazing |
TW552382B (en) * | 2001-06-18 | 2003-09-11 | Showa Dendo Kk | Evaporator, manufacturing method of the same, header for evaporator and refrigeration system |
JP4554144B2 (en) * | 2001-06-18 | 2010-09-29 | 昭和電工株式会社 | Evaporator |
JP2004042086A (en) * | 2002-07-11 | 2004-02-12 | Denso Corp | Soldering powder for soldering al material and method for soldering aluminum material using the same powder |
JP4440550B2 (en) * | 2003-01-31 | 2010-03-24 | 株式会社ティラド | Aluminum heat exchanger |
JP2004330223A (en) | 2003-05-02 | 2004-11-25 | Mitsubishi Materials Corp | Powder molding method, valve seat, and its manufacturing method |
JP2004330266A (en) | 2003-05-09 | 2004-11-25 | Denso Corp | Manufacturing method of lamination type heat exchanger |
JP2004339582A (en) * | 2003-05-16 | 2004-12-02 | Mitsubishi Alum Co Ltd | Tube for heat exchanger and heat exchanger |
JP2005016937A (en) * | 2003-06-06 | 2005-01-20 | Denso Corp | Aluminum heat exchanger with excellent corrosion resistance |
JP4284515B2 (en) | 2003-10-23 | 2009-06-24 | 株式会社デンソー | Aluminum alloy extruded header tank for heat exchanger and heat exchanger using this header tank |
WO2005078372A1 (en) | 2004-02-12 | 2005-08-25 | Showa Denko K.K. | Heat exchanger and method for manufacturing the same |
JP4290625B2 (en) | 2004-09-15 | 2009-07-08 | 三菱アルミニウム株式会社 | Header tank for heat exchanger using extruded aluminum alloy and heat exchanger provided with the same |
US20060102328A1 (en) * | 2004-11-16 | 2006-05-18 | Denso Corporation | Aluminum heat exchanger and manufacturing method thereof |
JP2006255755A (en) | 2005-03-17 | 2006-09-28 | Mitsubishi Alum Co Ltd | Aluminum alloy material for brazing and method for brazing aluminum alloy material |
JP2006348358A (en) * | 2005-06-17 | 2006-12-28 | Mitsubishi Alum Co Ltd | Aluminum-alloy extruded material for heat-exchanger, and flat tube with multi-holes for heat-exchanger and header for heat-exchanger using the same |
JP4541252B2 (en) | 2005-08-18 | 2010-09-08 | 三菱アルミニウム株式会社 | Aluminum alloy sheet for radiator tube |
DE602006017415D1 (en) | 2005-08-31 | 2010-11-18 | Showa Denko Kk | PLATTER PLATE AND MANUFACTURING METHOD THEREFOR |
JP2007147160A (en) | 2005-11-28 | 2007-06-14 | Mitsubishi Alum Co Ltd | Header pipe for heat exchanger, and heat exchanger |
JP4649326B2 (en) | 2005-12-26 | 2011-03-09 | 株式会社神戸製鋼所 | Aluminum clad material for header member and tank member of heat exchanger |
JP5049536B2 (en) * | 2006-08-24 | 2012-10-17 | 古河スカイ株式会社 | Aluminum piping material for automotive heat exchangers |
JP4111456B1 (en) | 2006-12-27 | 2008-07-02 | 株式会社神戸製鋼所 | Aluminum alloy brazing sheet for heat exchanger |
JP4473908B2 (en) | 2007-12-27 | 2010-06-02 | 株式会社神戸製鋼所 | Aluminum alloy clad material for heat exchanger and manufacturing method thereof |
-
2009
- 2009-09-02 JP JP2009202991A patent/JP5548411B2/en active Active
- 2009-09-02 US US12/552,719 patent/US20100051247A1/en not_active Abandoned
- 2009-09-02 CN CN200910173611.5A patent/CN101676667B/en active Active
- 2009-09-02 EP EP09169235.0A patent/EP2159528B1/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004330233A (en) | 2003-05-06 | 2004-11-25 | Mitsubishi Alum Co Ltd | Tube for heat exchanger |
JP2008225324A (en) | 2007-03-15 | 2008-09-25 | Dic Corp | Ocb mode liquid crystal display element |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2758204A4 (en) * | 2011-09-22 | 2016-05-11 | Sapa As | Brazing pre-flux coating with improved corrosion performance |
US9815150B2 (en) | 2011-09-22 | 2017-11-14 | Sapa As | Brazing pre-flux coating with improved corrosion performance |
EP2728155A1 (en) * | 2012-11-06 | 2014-05-07 | BorgWarner Inc. | Heat exchange device for exchanging heat between fluids |
WO2014072274A1 (en) * | 2012-11-06 | 2014-05-15 | Borgwarner Inc. | Heat exchange device for exchanging heat between fluids |
US9671170B2 (en) | 2012-11-06 | 2017-06-06 | Borgwarner Emissions Systems Spain, S.L.U. | Heat exchange device for exchanging heat between fluids |
Also Published As
Publication number | Publication date |
---|---|
CN101676667A (en) | 2010-03-24 |
EP2159528A3 (en) | 2013-12-25 |
EP2159528B1 (en) | 2015-11-04 |
JP2010085081A (en) | 2010-04-15 |
CN101676667B (en) | 2015-08-19 |
US20100051247A1 (en) | 2010-03-04 |
JP5548411B2 (en) | 2014-07-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2159528B1 (en) | Heat exchanger made of aluminum alloy | |
EP2543951B1 (en) | Heat exchanger constituted of aluminum alloy | |
EP2832873B1 (en) | Method for producing a heat transfer tube | |
EP2527078B1 (en) | Heat exchanger tube | |
EP1475598B1 (en) | Heat exchange tube | |
JP5750237B2 (en) | Method for producing aluminum alloy heat exchanger | |
JP5619538B2 (en) | Fluxless brazing method of heat exchanger having narrow channel inner fin and aluminum clad material used therefor | |
JP5670100B2 (en) | Method for producing aluminum alloy heat exchanger | |
JP4993440B2 (en) | High strength aluminum alloy clad material for heat exchangers with excellent brazeability | |
EP1038984B1 (en) | Corrosion protective sacrificial aluminum alloy for heat exchanger and aluminum alloy composite material highly resistant to corrosion for heat exchanger and heat exchanger using said composite material | |
JP2017145463A (en) | Aluminum alloy brazing sheet and manufacturing method, automotive heat exchanger using the brazing sheet | |
JP2005232506A (en) | Aluminum alloy clad material for heat exchanger | |
EP3670688A1 (en) | Aluminum alloy-brazing sheet for heat exchanger | |
JP4993439B2 (en) | High strength aluminum alloy clad material for heat exchangers with excellent brazeability | |
JP5614883B2 (en) | Fluxless brazing method of aluminum material, aluminum alloy brazing sheet for fluxless brazing, and aluminum alloy brazing material for fluxless brazing | |
EP3663423B1 (en) | Aluminum alloy brazing sheet for heat exchanger | |
JP2012057183A (en) | Aluminum alloy clad material and heat exchanging device using the same | |
JP2005232507A (en) | Aluminum alloy clad material for heat exchanger | |
JP6968598B2 (en) | Manufacturing method of aluminum alloy heat exchanger with excellent corrosion resistance and aluminum alloy heat exchanger | |
JP4263160B2 (en) | Aluminum alloy clad material and heat exchanger tube and heat exchanger using the same | |
WO2023228917A1 (en) | Heat exchanger and method for manufacturing same | |
EP4169647A1 (en) | Aluminum alloy extruded tube and heat exchanger | |
JP2022045656A (en) | Aluminum alloy bare material having excellent thermal conductivity and strength and brazing sheet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A2 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
PUAL | Search report despatched |
Free format text: ORIGINAL CODE: 0009013 |
|
AK | Designated contracting states |
Kind code of ref document: A3 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: F28D 1/053 20060101ALI20131118BHEP Ipc: B21D 53/08 20060101ALI20131118BHEP Ipc: F28F 21/08 20060101AFI20131118BHEP Ipc: B23K 1/00 20060101ALI20131118BHEP |
|
17P | Request for examination filed |
Effective date: 20140625 |
|
RBV | Designated contracting states (corrected) |
Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
RIC1 | Information provided on ipc code assigned before grant |
Ipc: B21D 53/08 20060101ALI20150119BHEP Ipc: B23K 1/00 20060101ALI20150119BHEP Ipc: F28D 1/053 20060101ALI20150119BHEP Ipc: F28F 21/08 20060101AFI20150119BHEP |
|
INTG | Intention to grant announced |
Effective date: 20150217 |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: MITSUBISHI ALUMINUM CO., LTD. Owner name: CALSONIC KANSEI CORPORATION |
|
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
RIN1 | Information on inventor provided before grant (corrected) |
Inventor name: HYOGO, YASUNORI Inventor name: SHINHAMA, MASAYOSHI Inventor name: SOGABE, MASAHIRO Inventor name: FUNATSU, TAKUMI Inventor name: ASANO, MASAMI Inventor name: KATSUMATA, MASAYA |
|
INTG | Intention to grant announced |
Effective date: 20150518 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MK MT NL NO PL PT RO SE SI SK SM TR |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: REF Ref document number: 759499 Country of ref document: AT Kind code of ref document: T Effective date: 20151115 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R096 Ref document number: 602009034593 Country of ref document: DE |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: MP Effective date: 20151104 |
|
REG | Reference to a national code |
Ref country code: LT Ref legal event code: MG4D |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MK05 Ref document number: 759499 Country of ref document: AT Kind code of ref document: T Effective date: 20151104 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IS Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160304 Ref country code: LT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: IT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: NO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160204 Ref country code: HR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: ES Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: LV Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160205 Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20160304 Ref country code: PL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CZ Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R026 Ref document number: 602009034593 Country of ref document: DE |
|
PLBI | Opposition filed |
Free format text: ORIGINAL CODE: 0009260 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: SM Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PLAX | Notice of opposition and request to file observation + time limit sent |
Free format text: ORIGINAL CODE: EPIDOSNOBS2 |
|
26 | Opposition filed |
Opponent name: MAHLE INTERNATIONAL GMBH Effective date: 20160804 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PLBB | Reply of patent proprietor to notice(s) of opposition received |
Free format text: ORIGINAL CODE: EPIDOSNOBS3 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20160902 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20170531 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160930 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160930 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160902 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160930 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160902 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160902 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R100 Ref document number: 602009034593 Country of ref document: DE |
|
PLCK | Communication despatched that opposition was rejected |
Free format text: ORIGINAL CODE: EPIDOSNREJ1 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT; INVALID AB INITIO Effective date: 20090902 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20160930 Ref country code: MK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20151104 |
|
PLBN | Opposition rejected |
Free format text: ORIGINAL CODE: 0009273 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: OPPOSITION REJECTED |
|
27O | Opposition rejected |
Effective date: 20180410 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R082 Ref document number: 602009034593 Country of ref document: DE Representative=s name: ZACCO LEGAL RECHTSANWALTSGESELLSCHAFT MBH, DE |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R081 Ref document number: 602009034593 Country of ref document: DE Owner name: MARELLI CORPORATION, SAITAMA-CITY, JP Free format text: FORMER OWNERS: CALSONIC KANSEI CORPORATION, SAITAMA-SHI, JP; MITSUBISHI ALUMINUM CO., LTD., TOKIO/TOKYO, JP Ref country code: DE Ref legal event code: R081 Ref document number: 602009034593 Country of ref document: DE Owner name: MA ALUMINUM CORPORATION, JP Free format text: FORMER OWNERS: CALSONIC KANSEI CORPORATION, SAITAMA-SHI, JP; MITSUBISHI ALUMINUM CO., LTD., TOKIO/TOKYO, JP |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R081 Ref document number: 602009034593 Country of ref document: DE Owner name: MARELLI CORPORATION, SAITAMA-CITY, JP Free format text: FORMER OWNERS: MA ALUMINIUM CORPORATION, TOKYO, JP; MARELLI CORPORATION, SAITAMA-CITY, SAITAMA, JP Ref country code: DE Ref legal event code: R081 Ref document number: 602009034593 Country of ref document: DE Owner name: MA ALUMINUM CORPORATION, JP Free format text: FORMER OWNERS: MA ALUMINIUM CORPORATION, TOKYO, JP; MARELLI CORPORATION, SAITAMA-CITY, SAITAMA, JP |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20240918 Year of fee payment: 16 |