EP2080853A1 - Stabilizing receiving member for temporary structures - Google Patents

Stabilizing receiving member for temporary structures Download PDF

Info

Publication number
EP2080853A1
EP2080853A1 EP08075046A EP08075046A EP2080853A1 EP 2080853 A1 EP2080853 A1 EP 2080853A1 EP 08075046 A EP08075046 A EP 08075046A EP 08075046 A EP08075046 A EP 08075046A EP 2080853 A1 EP2080853 A1 EP 2080853A1
Authority
EP
European Patent Office
Prior art keywords
receiving member
main beams
supporting structure
member according
posts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP08075046A
Other languages
German (de)
French (fr)
Inventor
Petrus Johannes Lambertus De Leeuw
Guus Franciscus Johannes Kuunders
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SAFE BV
Original Assignee
SAFE BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAFE BV filed Critical SAFE BV
Priority to EP08075046A priority Critical patent/EP2080853A1/en
Publication of EP2080853A1 publication Critical patent/EP2080853A1/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/483Supporting heads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs

Definitions

  • the invention relates to a receiving member for bearing or supporting the main beams positioned on the top of a temporary supporting structure adjustable in height.
  • supporting structures For casting concrete plates and floors on formworks in building constructions, one mostly employs supporting structures, which are mostly built into spatial structures.
  • the spatial structures are mostly formed by metal scaffolding parts, designed as posts, coupling pipes and diagonal pipes, and further main beams for direct support of the formwork with the usual connecting and adjusting possibilities.
  • the top surface of the supporting structure, to wit the main beams, should be adjustable in height to allow usage for any height.
  • the height adjustment is achieved with posts designed as an inner pipe, which is vertically adjustable within an outer pipe of the post by a screw spindle structure.
  • the main beams extend across several points of support, to wit the posts.
  • main beams are to be mounted at a given height and after setting of the concrete surface, these must be removed from underneath the surface or the formwork by hand, said main beams are mostly embodied in (extruded) aluminium.
  • Main beams extending across several points of support affect the loads arising on the posts as a result of the occurrence of bending moments in said beams above said points of support. This provides an unequal bearing force distribution in the posts and due to that, the points of support or posts across which the main beams extend, will have to be dimensioned for said heavier loads.
  • a further disadvantage of the continuous main beams, which are generally not reinforced at their extremities, is that the extremities can easily get damaged, which may lead to an unfavourable direction of forces into the supporting structure.
  • the object of the present invention is to provide a modified and improved temporary supporting structure that does not have the above-mentioned disadvantages and can be put onto the market in an economically sound way.
  • a stabilizing receiving member is incorporated in the temporary supporting structure in an inventive way, characterized in that said receiving structure is provided with means for bearing and centring adapted head ends of main beams with provisions having been made for interconnecting and stabilizing the top plane of said supporting structure.
  • the advantage is that the top plane of the temporary supporting structure forms a very stable surface underneath the formwork.
  • the receiving member according to the invention is developed further in such a way, that said adapted head ends of the main beams are bevelled and can be retained between V-shaped upstanding wings of said supporting structure.
  • the advantage is that the head ends will bear on the receiving member in a stable way.
  • the receiving member according to the invention is developed further in such a way, that said retaining facility has been established by a retaining cam with a corresponding recess in the bottom side of the bevelled head ends of main beams, so that a centric connection can be achieved.
  • the receiving member according to the invention is developed further in such a way, that said facilities for mounting said interconnecting means are brackets welded to the V-shaped raised wings, a connecting lip being provided at the extremities of the interconnecting rods gripping over them.
  • the advantage is that a properly stabilizing structure of the top surface of the temporary supporting structure has been obtained.
  • Figure 1A shows a vertical longitudinal section of the top side of a temporary supporting structure 1 as employed at the moment (state of the art), in which figure 1B shows a vertical cross-section thereof.
  • the upper vertical posts 4 are embodied as outer pipes 3 provided with screw spindle 5 with inner pipe 6 for height adjustment of the main beams 7 having the usual formwork carriers 8 with the formwork parts 9 thereon.
  • the main beams 7 continue across at least one post 4, thus causing the post 4 across which main beam 7 extends to withstand a higher vertical bearing force.
  • the vertical posts 4 should be interconnected and strutted for reasons of stability. In the known construction according to the figures 1A and 1B this takes place with the interconnecting bars 10 and 11 and the diagonal bars 12 and 13.
  • interconnecting by means of interconnecting bars 10 and 11 and strutting by means of diagonal bars 12 does not occur at the level of the main beams 7, due to which stabilizing the supporting structure 1 in relation to horizontal forces is less effective and may lead to unstable situations.
  • Figures 2A and 2B illustrate the same vertical cross-sections of a supporting structure 1 provided with the receiving member 14 according to a preferred embodiment of the invention. See also figures 3 , 4 and 5 .
  • the receiving member 14 is inserted in the inner pipe 6 of the vertical post 4 by a short piece of pipe 15 (see figures 4 and 5 ).
  • FIG. 5 shows receiving member 14 according to a preferred embodiment of the invention in a perspective view.
  • a head plate 16 is welded to said short pipe 15 and an I-shaped profile 17 having V-shaped wings 18 and a body 19 is welded to said head plate.
  • Brackets 20 are welded to said V-shaped wings 18 for (torsionally stiff) connecting lip 21 of the interconnecting bars 22 to them.
  • a diagonal bar 30 can be connected in the way indicated.
  • a facility is mounted for tension stiff support of bevelled adapted head ends 23 of the adapted main beams 23, said facility gripping behind retaining cam 26.
  • a bolt (not illustrated) can secure head plate 16 to the head plate 27 of the inner pipe 6 of the post 4, to which end the slots 28 and 29 have been provided.
  • Figures 3 and 4 illustrate receiving member 14 in a mounted state ( figure 3 ) and in exploded view ( figure 4 ).
  • the bevelled head ends 23 are provided with reinforcing strips 31.
  • the adapted main beams 24 extend from receiving member 14 to receiving member 14 and are therefore girders on points of support at both extremities (statically determined).

Abstract

Formworks for concrete floors or beams to be cast are in practice supported by vertically adjustable, temporary structures (1). These are mostly comprised of system parts, to wit posts, beams and diagonals, in which the upper part of the posts (4) is mostly embodied as telescoping inner pipe and outer pipe with screw spindle (5) for enabling a large height adjustment.
The invention relates to a receiving member (14) for an optimum bearing of main beams and stabilization of the top of said structure.

Description

  • The invention relates to a receiving member for bearing or supporting the main beams positioned on the top of a temporary supporting structure adjustable in height.
  • For casting concrete plates and floors on formworks in building constructions, one mostly employs supporting structures, which are mostly built into spatial structures. The spatial structures are mostly formed by metal scaffolding parts, designed as posts, coupling pipes and diagonal pipes, and further main beams for direct support of the formwork with the usual connecting and adjusting possibilities. The top surface of the supporting structure, to wit the main beams, should be adjustable in height to allow usage for any height. The height adjustment is achieved with posts designed as an inner pipe, which is vertically adjustable within an outer pipe of the post by a screw spindle structure.
  • When the telescoping length of the inner pipe with screw spindle structure increases, there will be an increasing need for interconnecting and strutting, respectively, of the top of the inner pipe and the support of said main beam, respectively. This is structurally necessary to discharge horizontal forces from the formwork to the base of the supporting structure, said forces being caused by wind load and possible oblique positioning of said posts.
  • In practice, it is common use that the main beams extend across several points of support, to wit the posts.
  • Since the main beams are to be mounted at a given height and after setting of the concrete surface, these must be removed from underneath the surface or the formwork by hand, said main beams are mostly embodied in (extruded) aluminium.
  • Main beams extending across several points of support affect the loads arising on the posts as a result of the occurrence of bending moments in said beams above said points of support. This provides an unequal bearing force distribution in the posts and due to that, the points of support or posts across which the main beams extend, will have to be dimensioned for said heavier loads.
  • A further disadvantage of the continuous main beams, which are generally not reinforced at their extremities, is that the extremities can easily get damaged, which may lead to an unfavourable direction of forces into the supporting structure.
  • The above shows that the known supporting structures have a number of disadvantages.
  • The object of the present invention is to provide a modified and improved temporary supporting structure that does not have the above-mentioned disadvantages and can be put onto the market in an economically sound way.
  • To this end, a stabilizing receiving member according to the invention is incorporated in the temporary supporting structure in an inventive way, characterized in that said receiving structure is provided with means for bearing and centring adapted head ends of main beams with provisions having been made for interconnecting and stabilizing the top plane of said supporting structure.
  • The advantage is that the top plane of the temporary supporting structure forms a very stable surface underneath the formwork.
  • Further, the receiving member according to the invention is developed further in such a way, that said adapted head ends of the main beams are bevelled and can be retained between V-shaped upstanding wings of said supporting structure.
  • The advantage is that the head ends will bear on the receiving member in a stable way.
  • Then, the receiving member according to the invention is developed further in such a way, that said retaining facility has been established by a retaining cam with a corresponding recess in the bottom side of the bevelled head ends of main beams, so that a centric connection can be achieved.
  • Further, the receiving member according to the invention is developed further in such a way, that said facilities for mounting said interconnecting means are brackets welded to the V-shaped raised wings, a connecting lip being provided at the extremities of the interconnecting rods gripping over them.
  • The advantage is that a properly stabilizing structure of the top surface of the temporary supporting structure has been obtained.
  • Hereinafter, the invention is explained further by way of a preferred embodiment, shown in the drawing. There
    • fig. 1A shows a vertical longitudinal section through the top side of a temporary supporting structure according to the state of the art;
    • fig. 1B shows a vertical cross-section of the top of a temporary supporting structure according to the state of the art;
    • fig. 2A a vertical longitudinal section of the upper side of a temporary supporting structure with the receiving member according to the invention;
    • fig. 2B a vertical cross-section of the upper side of a temporary supporting structure according to the invention;
    • fig. 3 a perspective view of the receiving member a. o. according to the invention, in a mounted state;
    • fig. 4 a perspective view of the receiving member a. o. in an exploded view according to the invention; and
    • fig. 5 a perspective view of the receiving member according to a preferred embodiment of the invention.
  • Figure 1A shows a vertical longitudinal section of the top side of a temporary supporting structure 1 as employed at the moment (state of the art), in which figure 1B shows a vertical cross-section thereof. The upper vertical posts 4 are embodied as outer pipes 3 provided with screw spindle 5 with inner pipe 6 for height adjustment of the main beams 7 having the usual formwork carriers 8 with the formwork parts 9 thereon.
  • According to the state of the art, the main beams 7 continue across at least one post 4, thus causing the post 4 across which main beam 7 extends to withstand a higher vertical bearing force. This leads to unequal loads on the vertical posts 4, which may give rise to undesirable situations. Further, the vertical posts 4 should be interconnected and strutted for reasons of stability. In the known construction according to the figures 1A and 1B this takes place with the interconnecting bars 10 and 11 and the diagonal bars 12 and 13. As can be seen in figures 1A and 1B, interconnecting by means of interconnecting bars 10 and 11 and strutting by means of diagonal bars 12 does not occur at the level of the main beams 7, due to which stabilizing the supporting structure 1 in relation to horizontal forces is less effective and may lead to unstable situations.
  • Figures 2A and 2B illustrate the same vertical cross-sections of a supporting structure 1 provided with the receiving member 14 according to a preferred embodiment of the invention. See also figures 3, 4 and 5.
  • The receiving member 14 is inserted in the inner pipe 6 of the vertical post 4 by a short piece of pipe 15 (see figures 4 and 5).
  • Figure 5 shows receiving member 14 according to a preferred embodiment of the invention in a perspective view. A head plate 16 is welded to said short pipe 15 and an I-shaped profile 17 having V-shaped wings 18 and a body 19 is welded to said head plate. Brackets 20 are welded to said V-shaped wings 18 for (torsionally stiff) connecting lip 21 of the interconnecting bars 22 to them. Again, a diagonal bar 30 can be connected in the way indicated. In a slot of main beams 24, near the head ends 23 a facility is mounted for tension stiff support of bevelled adapted head ends 23 of the adapted main beams 23, said facility gripping behind retaining cam 26.
  • Further, a bolt (not illustrated) can secure head plate 16 to the head plate 27 of the inner pipe 6 of the post 4, to which end the slots 28 and 29 have been provided.
  • Figures 3 and 4 illustrate receiving member 14 in a mounted state (figure 3) and in exploded view (figure 4). For protecting the adapted main beams 24 from falling during mounting and demounting, the bevelled head ends 23 are provided with reinforcing strips 31.
  • The adapted main beams 24 extend from receiving member 14 to receiving member 14 and are therefore girders on points of support at both extremities (statically determined).
  • Further, it will be obvious, that a preferred embodiment of the invention has been described above and that many modifications and the like are possible without departing from the protective scope of this patent application.

Claims (6)

  1. Receiving member for bearing or supporting the main beams (24) positioned on the top of a height-adjustable, mostly temporary supporting structure (1), characterized in that said receiving member (14) is provided with means for bearing and centring the main beams (24) with adapted head ends (23) and in which facilities for interconnecting and stabilizing the top surface of said supporting structure (1) are provided.
  2. Receiving member according to claim 1, characterized in that said adapted head ends (23) of the main beams (24) are bevelled and can be retained between V-shaped raised wings (18) of said receiving member (14).
  3. Receiving member according to claim 2, characterized in that it is provided with a retaining cam (26) for centring the main beams (24) in relation to the posts (4).
  4. Receiving member according to claim 1, characterized in that said facilities for mounting interconnection connecting means are brackets (20) welded to the V-shaped raised wings (18).
  5. Receiving member according to claims 1 - 3, characterized in that said main beams (24) are extruded and manufactured of aluminium in the conventional way, in which said bevelled head ends (23) are provided with reinforcing members (31).
  6. Receiving member according to claim 3, characterized in that said main beams (24) are provided with a member engaging behind the retaining cam (26) such that the main beams (24) are interconnected with tension fixed in longitudinal direction.
EP08075046A 2008-01-17 2008-01-17 Stabilizing receiving member for temporary structures Withdrawn EP2080853A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
EP08075046A EP2080853A1 (en) 2008-01-17 2008-01-17 Stabilizing receiving member for temporary structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
EP08075046A EP2080853A1 (en) 2008-01-17 2008-01-17 Stabilizing receiving member for temporary structures

Publications (1)

Publication Number Publication Date
EP2080853A1 true EP2080853A1 (en) 2009-07-22

Family

ID=39537073

Family Applications (1)

Application Number Title Priority Date Filing Date
EP08075046A Withdrawn EP2080853A1 (en) 2008-01-17 2008-01-17 Stabilizing receiving member for temporary structures

Country Status (1)

Country Link
EP (1) EP2080853A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105715048A (en) * 2016-03-24 2016-06-29 广州市艺达机械有限公司 Early-dismounting beam connecting device for aluminum template
WO2020048451A1 (en) * 2018-09-04 2020-03-12 庄善行 Height-adjustable support and support device using same
EP3719236A1 (en) * 2019-04-03 2020-10-07 DOKA GmbH Formwork support, support device and ceiling formwork
CN112962960A (en) * 2021-02-09 2021-06-15 广西建工集团第三建筑工程有限责任公司 Early formwork stripping support system of coincide floor rigid coupling independent stay
CN114263343A (en) * 2022-01-28 2022-04-01 中建八局第二建设有限公司 Formwork erecting method for combined building construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3147081A1 (en) * 1981-05-30 1982-12-30 Udo 4836 Herzebrock Rose Supporting framework for concrete shutterings
DE4204788A1 (en) * 1992-02-18 1993-08-26 Peri Gmbh Head support for ceiling shuttering parts - has retainers for shuttering parts and supports arranged to form uniform shuttering face
DE4304438A1 (en) * 1993-02-13 1994-08-18 Peri Gmbh Wooden flanged beam
US5614122A (en) * 1993-02-20 1997-03-25 Peri Gmbh Ceiling form
DE102006015348A1 (en) * 2006-04-03 2007-10-04 Peri Gmbh Floor slab formwork system has multiple formwork element, and head of vertical support has anti-lift safety device fixes bearing of form work element in vertical direction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3147081A1 (en) * 1981-05-30 1982-12-30 Udo 4836 Herzebrock Rose Supporting framework for concrete shutterings
DE4204788A1 (en) * 1992-02-18 1993-08-26 Peri Gmbh Head support for ceiling shuttering parts - has retainers for shuttering parts and supports arranged to form uniform shuttering face
DE4304438A1 (en) * 1993-02-13 1994-08-18 Peri Gmbh Wooden flanged beam
US5614122A (en) * 1993-02-20 1997-03-25 Peri Gmbh Ceiling form
DE102006015348A1 (en) * 2006-04-03 2007-10-04 Peri Gmbh Floor slab formwork system has multiple formwork element, and head of vertical support has anti-lift safety device fixes bearing of form work element in vertical direction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105715048A (en) * 2016-03-24 2016-06-29 广州市艺达机械有限公司 Early-dismounting beam connecting device for aluminum template
CN105715048B (en) * 2016-03-24 2018-01-19 广州市艺达机械有限公司 Aluminum alloy pattern plate early tears beam joint device open
WO2020048451A1 (en) * 2018-09-04 2020-03-12 庄善行 Height-adjustable support and support device using same
EP3719236A1 (en) * 2019-04-03 2020-10-07 DOKA GmbH Formwork support, support device and ceiling formwork
CN112962960A (en) * 2021-02-09 2021-06-15 广西建工集团第三建筑工程有限责任公司 Early formwork stripping support system of coincide floor rigid coupling independent stay
CN114263343A (en) * 2022-01-28 2022-04-01 中建八局第二建设有限公司 Formwork erecting method for combined building construction

Similar Documents

Publication Publication Date Title
US10053875B1 (en) Formwork support system and formwork support prop
AU2010346421B2 (en) Scaffold and methods for installing or removing such a scaffold
US8978822B2 (en) Vertical frame of metal
US7748195B2 (en) Bracket and method for supporting a platform from concrete form tabs
KR100969992B1 (en) Concrete Sheeting System for A Bridge Pier
US20080172976A1 (en) Reusable Adjustable Hanger for Use with Joists and/or Double Wales
MXPA05007420A (en) Concrete slab form system.
US10407925B2 (en) Method of installing a formwork support system, formwork support system and longitudinal beam
EP2080853A1 (en) Stabilizing receiving member for temporary structures
CA2912199C (en) Suspended scaffolding structure and connector therefor
US20060175129A1 (en) Modular heavy duty support system
US4342440A (en) Concrete deck forming apparatus
AU2021424267A1 (en) Arrangement of scaffolding components
CN211522893U (en) Bridge overhanging support assembly
KR20090094423A (en) Apparatus for prevent fall and for maintening for fulling level of gang form
JP2524897B2 (en) Beam formwork receiver in formwork support device
KR200413590Y1 (en) Scaffold and construction structure thereof
KR20120003729U (en) System support Head
KR20020036198A (en) A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same
KR200397826Y1 (en) United supporting device for concrete form
KR20030000991A (en) Furnishing device of the bracket for a bridge construction
US4348004A (en) Ledger for concrete deck forming apparatus
AU2008100567A4 (en) A scaffolding stand for use in a formwork support system
CN114341449A (en) Column head for formwork support and use method thereof
KR200213539Y1 (en) Frame of safety workbench

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HR HU IE IS IT LI LT LU LV MC MT NL NO PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA MK RS

17P Request for examination filed

Effective date: 20091228

17Q First examination report despatched

Effective date: 20100129

AKX Designation fees paid

Designated state(s): DE NL

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 20100810