EP1846822A2 - System und verfahren für ein automatisiertes projektbüro und automatische risikobewertung und -meldung - Google Patents

System und verfahren für ein automatisiertes projektbüro und automatische risikobewertung und -meldung

Info

Publication number
EP1846822A2
EP1846822A2 EP05855725A EP05855725A EP1846822A2 EP 1846822 A2 EP1846822 A2 EP 1846822A2 EP 05855725 A EP05855725 A EP 05855725A EP 05855725 A EP05855725 A EP 05855725A EP 1846822 A2 EP1846822 A2 EP 1846822A2
Authority
EP
European Patent Office
Prior art keywords
project
user
questions
projects
risk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP05855725A
Other languages
English (en)
French (fr)
Inventor
Gene Clater
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Computer Aid Inc
Original Assignee
Computer Aid Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from US11/249,744 external-priority patent/US7640225B2/en
Application filed by Computer Aid Inc filed Critical Computer Aid Inc
Publication of EP1846822A2 publication Critical patent/EP1846822A2/de
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Definitions

  • the present invention is directed to a system and method for automation of project risk identification and in particular to such a system and method in which various qualitative and quantitative measures are combined to report a project's risk level, areas, and mitigation in an automatic and objective manner.
  • the Risk Assessment and Report Framework combines various project performance measurements as well as a comprehensive set of multifaceted questions to be processed by a risk engine to assess a project's level or risk, and the areas where risk exists. In addition to identifying risks, advice on mitigation of the identified risks, as well as tracking of mitigation actions is performed to enhance the system's ability to assess and provide future risk advice.
  • the framework collects data, either through Application Program Interfaces (APIs), or via direct data entry, on project performance measured by base Earned Value Analysis (EVA) data, quality data on defect rates, customer satisfaction ratings, manpower utilization, milestone progress.
  • EVA Earned Value Analysis
  • the risk engine uses the inputs to evaluate the performance against warning thresholds and limits to identify and report trouble.
  • a set of performance indicators are calculated from the main performance input to determine schedule and cost performance, as well as the level of risk and recoverability of the schedule and cost.
  • the risk engine uses data from question sets that survey various aspects of the projects activities to assess risk in various areas. Each question set and possible answers are categorized, scored, and weighted in such a way as to identify potential risk areas, and these risks are then reported via a dashboard to the user.
  • Questions sets are formed from a large question pool that contains all possible questions, risk categories, answers, and scores. New question sets are built by selecting questions from the pool and storing the question set into a question set library. The risk identification is broken down into several levels of classification and increasing detail according to a risk structure of risk categories, that each category contains risk areas, and that each risk area contains risk attributes. Each question in the question pool is assigned to a particular risk attribute; thus, when incorporated into a question set, it becomes part of the risk engine 's risk calculation.
  • the question sets are customizable and are assigned according to various classifications for a project.
  • Classifications for the project include a portfolio and a project type. Projects are broken down into one or more portfolios or collections which have some common characteristic or interest (for example, a business unit or line of business, or a particular technology, etc.).
  • Each portfolio has one or more question sets assigned to it that are used for assessment the elements of risk via the risk engine for all projects belonging to that portfolio.
  • there are project type questions sets are also be used for assessment the elements of risk via the risk engine for all projects belonging to that portfolio.
  • there are project type questions sets there are project type questions sets.
  • Each project has a type classification assigned to it, and that type automatically incorporates risk question set appropriate for the particular project type.
  • each project can add any additional or supplemental question sets as needed to expand the risk assessment coverage.
  • the risk engine provides for a role association for the question sets at each of those levels.
  • the roles allow users with different roles/responsibilities to provide input to the risk engine and have those perspectives combined into an overall risk assessment, and to identify differences in views for establishing consensus within a project.
  • the roles can include (but are in no way limited to) a Project Manager, a Quality Engineer, or a Project Sponsor.
  • the risk engine provides a facility for periodically "running" or stepping through the question sets for each project. The risk engine assembles the question sets, eliminates any duplication or overlap between question sets (as different question sets can share any number of questions from the larger question pool), and present a user with an orderly, unique, questionnaire.
  • Each user that has a particular role for a project creates an answer session for the questionnaire, and is presented with all questions appropriate for the role, portfolio, project type, and supplemental questions. Once all questions have be satisfactorily answered, the answers are submitted and the risk engine computes and updates the risk assessment for the project.
  • the risk engine combines the risk assessment scores, and metric scores from the EVA, quality, customer satisfaction, manpower, and progress, and reports those on a project or portfolio dashboard using a "stop light” kind of indicator (green, yellow/amber, red), to indicate an overall level of risk.
  • the overall risks can be "drilled” down on via a web browser based interface to display increasing levels of detail of the risk status. This drill down continues to the level of the questions and answers or metrics that are driving the overall status.
  • mitigation advice is made available to the user to identify actions to take that are appropriate to mitigate each risk.
  • mitigation advice is a mechanism for recording and tracking the mitigation actions taken and the results of those actions for automatic incorporation into the mitigation advice to provide heuristics to the mitigation component of the risk engine, providing all projects with improved mitigation advice as the risk engine continues to collect data.
  • the Automated Project Office integrates a Portfolio Analysis function that allows an organization to track its projects according to a high-level classification system that allows for understanding a particular project footprint or balance of efforts relative to an overall goal.
  • the preferred embodiment incorporates the MIT Model of portfolio classification, and uses it to perform a (classification) balance analysis, although those skilled in the art who have reviewed the present disclosure will appreciate that other models can be used instead of or in addition to the MIT model.
  • the MIT Model classifies projects as Infrastructure, Transactional, Informational, or Strategic, and uses the relative distributions of projects to those classifications to determine a position or balance for Cost Focused portfolio, Agility portfolio, or Balanced Cost and Agility portfolio.
  • the APO and organizations portfolio (of projects) can be tracked and measured according to the target position desired.
  • the APO integrates a Project Plan Validator facility using project heuristics to measure proposed project plan efforts by phase against known plan performance statistics for general project phases to determine if the plan contains the right work breakdown and effort distribution.
  • a project manager can quickly see if too much or too little time has been allocated to critical phases of the project, and make adjustments before the plan is baselined and commitments are made for delivery dates.
  • the validator uses statistics from completed projects to set the distribution of effort for a particular kind of project and can then be given, for example, a single number covering a single element from a plan, and determine the efforts by phase and total effort necessary for the project to be completed.
  • Integrated Project Management Office Toolkit and Process Asset Library [0026] Integrated Project Management Office Toolkit and Process Asset Library [0027]
  • the APO integrates a Project Management Office (PMO) Toolkit and Process Asset Library (PAL).
  • the toolkit provides essential documents and templates that correspond to PMO best practices, and additionally is coupled with the risk engine's mitigation advise to ensure the tools for risk mitigation are given additional visibility and tracking in the APO.
  • the integrated PAL allows documents and tools used by other APO projects to be shared and their usage automatically tracked by the APO to provide powerful means of identifying organizational best practices and tools. The tracking allows for locating high value, high usage items, and pruning of low value, unused items at appropriate time.
  • the Skills Engine of the APO provides a facility for tracking an organization's, or sub-unit's of the organization's people resources.
  • the Skills Engine provides first, and "inventory" of all skills within the organization or sub-organization using the APO. Beyond the skills inventory, the engine provides tracking of the resources and skills assigned to projects and with a view toward when the resources and associated skills will be available for further allocation as well as aiding in reallocation of skills and resources to other projects.
  • the Skills Engine provides for a skills search facility to locate resources with the skills needed for a project. In addition to the location of resources with needed skills, the engine allows for those resources to have a "claim" placed on them.
  • the claim facility can either be hard or soft.
  • a hard claim can be made for resources being placed on a project that has been contracted and has a start assigned.
  • a soft claim is made for resources for a project that is not formally committed to, but allows for identification of intent to utilize particular resources in the future. This capability of the engine gives managers and project managers a facility to identify what resources are to be used, and to act early on allocation of resources, resolution of resource conflicts, and identification of new resources with particular skill that need to be obtained.
  • the skills engine also provides a tracking of overall availability of the resources and skills in the organization with notifications and warnings for resources who are under allocated (relative to their defined availability), or not allocated at all. As part of this engine's processing, and outlook for the utilization that looks into the future alerts managers of upcoming under utilization, which provide a means to avoid lost organizational productivity because the resource might otherwise be left idle.
  • Fig. 1 shows a use-case diagram of the preferred embodiment
  • Fig. 2 shows a schematic overview of a Project Office Data System (PODS) on which the process of Fig. 1 can be implemented;
  • PODS Project Office Data System
  • FIG. 3 shows Fig. 3 shows a data model for PODS of Fig. 2;
  • Fig. 4 shows a flow chart of the operations of the preferred embodiment
  • Fig. 5 shows a main screen flow chart
  • Fig. 6 shows an administration screen flow chart
  • Fig. 7 shows a project initiation screen flow chart
  • Fig. 8 shows an active project screen flow chart
  • Fig. 9 shows a flow chart of the reports.
  • Fig. 10 shows a schematic diagram of a hardware configuration on which the preferred embodiment can be implemented
  • FIG. 1 An overview of the functionality of the preferred embodiment is shown in the use case diagram of Fig. 1.
  • the user 102 supplies project plan statistics 104 to a project plan validator 106, which returns effort distribution validation 108 to the user 102.
  • the integrated project management office toolkit/process asset library 110 supplies information to the user 102.
  • the user 102 supplies information on the skills and availability of workers as well as searches and claims for such workers, collectively designated 112, to a skills engine 114, which returns information 116 on resource and skill availability, tracking, notification, and alerts to the user 102.
  • the user 102 interacts in the following manner with the risk engine 118.
  • the user 102 forms custom questions, answers, and thresholds 120 into a question set 122, which becomes one of the user-defined and pre-packaged question sets 124 used by the risk engine 118.
  • the user 102 supplies the following input to the risk engine 118: earned value analysis (EVA) 126, question responses 128, performance measurements 130, quality data 132, customer satisfaction information 134, staff power utilization information 136, and milestone progress 138.
  • EVA earned value analysis
  • an external data gathering application 140 can gather data from the user 102 and supply such data to the risk engine 118 through an application programming interface (API) 142.
  • API application programming interface
  • the results of the operations performed by the risk engine 118 are output to the user 102 through one or more dashboards 144, which are user interfaces that provide such results in visual form.
  • the risk engine 118 determines schedule and cost performance 146 and levels of risk and recoverability 148 and outputs them in the form of the EVA output 150 to the dashboards 144.
  • the risk engine determines potential risk areas 152 and risk mitigation advice 154 and outputs them in the form of risk reporting 156 to the dashboards 144.
  • the risk reporting 156 can also include input directly from the user 102.
  • the risk engine can output an overall risk output 158 to the dashboards 144; the overall risk output can include a "stop light" indication for display on the dashboards 144 if the level of risk warrants it.
  • the risk engine 118 outputs information to a portfolio analysis 160, which can be standard or user-defined, which is output to the dashboards 144.
  • Fig. 1 The functionality shown in Fig. 1 and described above is implemented on a Project Office Data System (PODS), shown in Fig. 2 as 200.
  • PODS 200 is centered on a Project Management Office (PMO) database 202 which stores, among other things, assessment questionnaires 204.
  • PMO Project Management Office
  • the database receives information on projects 206 and skills 208 and allows reporting and querying by management 210 and subject matter experts (SME's) 212.
  • SME's subject matter experts
  • Fig. 3 shows a data model 300 for PODS. Table I below provides a brief description of the tables in the database. [0048] Table I
  • Figure 4 shows a flow chart of the operations of the preferred embodiment.
  • Figure 5 shows a main screen flow chart.
  • Figure 6 shows an administration screen flow chart.
  • Figure 7 shows a project initiation screen flow chart.
  • Figure 8 shows an active project screen flow chart.
  • Figure 9 shows a flow chart of the reports.
  • the PODS application Login page 402 protects the application and its resources from being accessed by unauthorized users. Only Active users are allowed to access the application. To access the application, the user is required to provide his/her login name and password. The login page is located in the root directory.
  • the login page is where the user types in his or her login name and password to gain access to the PODS application.
  • the user can specify whether after successful login to show first the password maintenance page 404 to update his or her current password. This can be accomplished by checking the checkbox "Change my password after successful login" before clicking on the Login button. If this is not checked, after successful login the user is transferred instead into the home page 406.
  • the login page would display the message "Invalid Login name/Password combination" to inform the user.
  • the home page 406 also known as the Portfolio Summary View Page, is displayed upon successful login. It contains two table summaries: Active Projects and Completed
  • the Active Projects table displays ongoing projects.
  • the Completed Projects table displays finished projects.
  • the projects in the both tables are sorted by project name in ascending order.
  • the data in both tables can also be sorted (ascending order) by column headings.
  • the Home page (Portfolio Summary view) provides a list of Active Projects and
  • the Home page is located in the root directory and is protected through user authentication. AU users are allowed to view this page once they have been authenticated and session is still valid.
  • the Create New Project page 408 allows the user to define a new project. Both the
  • Project Name and description are required fields.
  • the project ID is automatically generated upon creation of a new project.
  • the Create new project page is located in the root directory and is protected through user authentication. AU users are allowed to view this page once they have been authenticated and session is still valid.
  • the View Existing Project page 410 lists the Active Projects
  • the View Existing Project page 410 serves as a facility to filter projects by Customer
  • the Completed / Cancelled Projects list enumerates all projects that were finished or were called-off.
  • the Active Projects list enumerates all ongoing projects. AU projects in both lists can be double-clicked to show the page that corresponds to the current phase of the project.
  • the view existing project page 410 is located in the root directory and is protected through user authentication. AU users are allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation - General page 412 permits the user to define or update the
  • the save button will appear for projects whose Project Initiation - General information has not yet been defined. Otherwise, an update button will appear.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the fields have been filled-up. After saving the data in the database and if all the fields in the page have been filled-up, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • This page is located in the data attributes directory and is protected through user authentication. AU users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation - Assessment page 414 permits the user to define or update the Project Initiation — Assessment details of a new or existing project.
  • the save button will appear for projects whose Project Initiation - Assessment information has not yet been defined. Otherwise, an update button will appear.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the fields have been filled-up. After saving the data in the database and if all the fields in the page have been filled-up, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • This page is located in the data attributes directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation - Assessment page provides users the facility to define and/or update general project assessment information. A set of determinants are presented together with a set of possible answers to which the users can select from. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for newly-defined projects while the Update button appears for projects whose General Project Assessment information has already been defined.
  • the Project Initiation Assessment - Human Resources page 416 permits the user to define or update the Project Initiation Assessment — Human Resources details of a new or existing project.
  • the save button will appear for projects whose Project Initiation Assessment - Human Resources information has not yet been defined. Otherwise, an update button will appear.
  • There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Project Initiation Assessment - Human Resources page provides users a series of questions regarding the Human Resource aspect of a new project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for newly-defined projects while the Update button appears for projects whose Project Initiation Assessment for Human Resource information has already been defined. [0069] The contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category. This page is located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation Assessment - Quality page 418 permits the user to define or update the Project Initiation Assessment - Quality details of a new or existing project.
  • the save button will appear for projects whose Project Initiation Assessment - Quality information has not yet been defined. Otherwise, an update button will appear.
  • There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Project Initiation Assessment - Quality page displays a set of questions regarding the Quality aspect of a new project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for newly-defined projects while the Update button appears for projects whose Project Initiation Assessment for Quality information has already been defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page will be located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation Assessment - Risk page 420 permits the user to define or update the Project Initiation Assessment - Risk details of a new or existing project.
  • the save button will appear for projects whose Project Initiation Assessment - Risk information has not yet been defined. Otherwise, an update button will appear. There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Project Initiation Assessment - Risk page displays a set of questions regarding the Risk aspect of a new project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for newly-defined projects while the Update button appears for projects whose Project Initiation Assessment for Risk information has already been defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page will be located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation Assessment - Schedule page 422 permits the user to define or update the Project Initiation Assessment - Schedule details of a new or existing project.
  • the save button will appear for projects whose Project Initiation Assessment - Schedule information has not yet been defined. Otherwise, an update button will appear. There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Project Initiation Assessment - Schedule page displays a set of questions regarding the Schedule aspect of a new project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for newly- defined projects while the Update button appears for projects whose Project Initiation Assessment for Schedule information has already been defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page is located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation Assessment - Scope page 424 permits the user to define or update the Project Initiation Assessment - Scope details of a new or existing project.
  • the save button will appear for projects whose Project Initiation Assessment - Scope information has not yet been defined. Otherwise, an update button will appear. There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Project Initiation Assessment - Scope page displays a set of questions regarding the Scope aspect of a new project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for newly-defined projects while the Update button appears for projects whose Project Initiation Assessment for Scope information has already been defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page is located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation- Baselines 426 page permits the user to define or update the Project Initiation- Baselines details of a new or existing project.
  • the save button will appear for projects whose Project Initiation- Baselines information has not yet been defined. Otherwise, an update button will appear.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the fields have been filled-up. After saving the data in the database and if all the fields in the page have been filled-up, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Project Initiation - Baselines page serves as a facility where users can define and / or update information like planned start date, planned hours budget and planned staffing size for each phase of a project.
  • the Save button appears for newly-defined projects while the Update button appears for projects whose Project Initiation Baseline information has already been defined.
  • This page is located in the data attributes directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project - General page 428 permits the user to define or update the Active Project - General details of an active project.
  • the save button will appear for active projects whose Active Project - General information has not yet been defined. Otherwise, an update button will appear.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the fields have been filled-up. After saving the data in the database and if all the fields in the page have been filled-up, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • This page will be located in the data attributes directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project - General page displays the details and basic information of an active project. This serves as a facility where each detail item can be updated to reflect current changes in the status of the project (still active / completed / cancelled), project cost to date and others.
  • the Active Project - Cost page 430 permits the user to define or update the Active Project - Cost details of an active project.
  • the save button will appear for active projects whose Active Project - Cost information has not yet been defined. Otherwise, an update button will appear.
  • There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Active Project - Cost page displays specific questions regarding the Cost aspect of an active project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button The Save button appears for active projects whose cost information has not yet been defined while the Update button appears for active projects whose cost information has been previously defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page is located in the questionnaires directory and is protected through user authentication. AU users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project - Human Resources page 432 permits the user to define or update the Active Project - Human Resources details of an active project.
  • the save button will appear for active projects whose Active Project - Human Resources information has not yet been defined. Otherwise, an update button will appear. There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Active Project - Human Resources page displays specific questions regarding the Human resources aspect of an active project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for active projects whose human resources information has not yet been defined. The Update button appears for active projects whose Human Resources information has been previously defined. [0093] The contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category. This page is located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project - Quality page 434 permits the user to define or update the Active Project - Quality details of an active project.
  • the save button will appear for active projects whose Active Project - Quality information has not yet been defined. Otherwise, an update button will appear.
  • There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Active Project - Quality page displays specific questions regarding the Quality aspect of an active project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for active projects whose Quality- related information has not yet been defined. The Update button appears for active projects whose Quality-related information has been previously defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page is located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project - Risk page 436 permits the user to define or update the Active Project - Risk details of an active project.
  • the save button will appear for active projects whose Active Project - Risk information has not yet been defined. Otherwise, an update button will appear. There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Active Project - Risk page displays specific questions regarding the Risk aspect of an active project. A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for active projects whose Risk-related information has not yet been defined. The Update button appears for active projects whose Risk-related information has been previously defined.
  • the contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category.
  • This page is located in the questionnaires directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project - Schedule page 438 permits the user to define or update the Active Project - Schedule details of an active project.
  • the save button will appear for active projects whose Active Project — Schedule information has not yet been defined. Otherwise, an update button will appear. There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page. [00101]
  • the Active Project - Schedule page displays specific questions regarding the
  • Active Project - Scope details of an active project.
  • the save button will appear for active projects whose Active Project - Scope information has not yet been defined. Otherwise, an update button will appear.
  • There is a score corresponding to a question/answer combination which will be used to determine the color classification to be displayed in the reports.
  • the user can save the data in the database at any point, at any level of completion, but can only advance to the next page once all the questions have been answered. After saving the data in the database and if all the questions in the page have been answered, the user will be asked if he wants to proceed to the next page or go back to the home page.
  • the Active Project - Scope page displays specific questions regarding the
  • Scope aspect of an active project A set of answers for each question are presented but only one can be selected. There are two (2) buttons at the end of the page. These are the Save / Update button and the Clear button. The Save button appears for active projects whose Scope-related information has not yet been defined. The Update button appears for active projects whose Scope-related information has been previously defined. [00105] The contents of this page are dynamically loaded based on the data retrieved from the different tables in the database based on the category. This page will be located in the questionnaires directory and is protected through user authentication. AU users will be allowed to view this page once they have been authenticated and session is still valid. [00106] The Password Maintenance page 404 (shown twice in Fig.
  • the Security page 442 allows the security (SEC)-privileged users to update the password of other users using the Password maintenance page 404 and to add, update or delete (deactivate only in the database) a user using the User maintenance page 444.
  • SEC security
  • the Login ID is automatically generated upon creation of a new user. To delete a user, simply set the Active Status to No. For non SEC-privileged and non- ADMIN privileged user, set the Admin and Sec privilege flag to No respectively.
  • the Security page 442 contains the Password and User Maintenance tools and is only accessible for users with the SEC privilege.
  • the User Maintenance feature provides SEC-privileged users the functionality to add, update or delete (deactivated only in the database) users. To update or delete a user, simply enter the login name and click the search button to retrieve user data, then make the necessary changes and click the save button to update changes. To add a user, fill up all the required fields and click the save button to add the user.
  • the Password Maintenance feature provides SEC-privileged users the functionality to change other user's passwords.
  • the password field will be hashed using the MD5 algorithm before saving the data in the database.
  • a random set of two salt characters will be generated and added to the front of the password supplied to make a new password string.
  • the new password string is then hashed using the MD5 algorithm to obtain a new hashed password string converted to an ASCII hex string creating a "hexified" password string.
  • the salt characters are then added to the front of the "hexified" password string and then stored in the database.
  • the security page will be located in the root directory and is protected through user authentication. Only users with SEC privileges will be allowed to view this page once they have been authenticated and session is still valid.
  • the Add Customer/Manager page 446 allows ADMIN-privileged users to add a customer or project manager. To add a customer, simply fill in the customer name and click on the Enter customer button. The customer ID is automatically generated upon creation of a new customer. To add a project manager, fill in the project manager first name and last name and click on the Enter Project Manager button. The project manager ID is automatically generated upon creation of a new project manager.
  • the Add Customer function 448 allows ADMIN-privileged users to add a new customer to the system.
  • the Add Project Manager function 450 allows ADMIN- privileged users to add a new project manager to the system.
  • This Add Customer/Manager page will be located in the root directory and is protected through user authentication. Only users with ADMIN privileges will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project Initiation - Summary Report page 452 allows users to filter the newly-initiated project reports (not yet active) by Customer Name, Project Name, Project Manager, and Project Type. The user also has the option to select which type of Project Initiation report to generate (the available options include Identification / Team Dynamics / Assessment Info report 454, Project Stated Risk Info report 456, and Planned Project Baseline Info report 458). After selection, clicking on the Create Report button initiates creation of an online report. Clicking on the Clear button resets to default values all the input controls.
  • the Project Initiation Summary Report allows users to filter the newly- initiated project reports (not yet active) by Customer Name, Project Name, Project Manager, and Project Type. The user has also the option to select which type of Project Initiation report to generate.
  • the available Project Initiation reports include Identification / Team Dynamics / Assessment Info, Project Stated Risk Info, and Planned Project Baseline Info.
  • 454 shows the general assessment of the project in terms of Schedule, Scope, Risk, Human Resources, and Quality. Assessments are based on the information provided by the users from the Project Initiation pages.
  • the Project Initiation - Project Stated Risk Report 456 shows the assessment of potential risk items per project. This includes Technology, Delivery Date, Quality, Customer Satisfaction, Constraints and other miscellaneous risk items, including Critical Success Factors to be observed both for the customer and the developing organization.
  • the Project Initiation - Planned Project Baseline Report 458 shows planning values which include start date, end date, hours budget, and staff size for each phase of a project.
  • the Project Initiation - Details Report 460 serves as the facility for users to select a specific project to which different information which include Constraints 462, Risk
  • This page will be located in the reports directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Active Project report page 480 allows users to filter the active project reports by Customer Name, Project Name, Project Manager, Project Type and Status. There is an option to select which type of Project report to generate.
  • the available reporting options include Identification / Project Details / Project Management Info, Analysis and Business
  • Design Planning vs. Actual, Technical Design and Construction Planning vs. Actual, Testing and Implementation Planning vs. Actual, and Assessment.
  • This page is located in the reports directory and is protected through user authentication. All users will be allowed to view this page once they have been authenticated and session is still valid.
  • the Project - Identification / Project Details / Project Management Report 482 shows merging values from the identification and project details report and the project management information report. Issue tracking report values are included.
  • the Project - Analysis / Business Design Report 484 displays "Planned” values compared against "Actual" values for Start Date, End date, Hours Budget, and Staff
  • the Project - Technical Design / Construction Report 486 displays "Planned” values compared against “Actual” values for Start Date, End date, Hours Budget, and Staff
  • the Project - Testing / Implementation Report 488 displays "Planned” values compared against "Actual" values of Start Date, End date, Hours Budget, and Staff Size of the Testing and Implementation phases of active projects.
  • the Project - Assessment Report 490 displays comparisons between current and previous assessment of Schedule, Scope, Risk, Human Resources, Quality and Cost of active projects.
  • Figure 5 shows a main screen flow chart.
  • the user can log in, using the login screen 402, or change the password using the "change password" screen 404, and is brought to the home page 406.
  • the home page 406 includes a list of options 502 including the following: return to home page 504, create a new project 506, view an existing project 508, project initiation 510, reports 512, administration 514, and logout 516.
  • Figure 6 shows an administration screen flow chart of events that occur when the user chooses the administration option 514 of Fig. 5. From an administration page 602, a
  • SEC privileged user can go in step 604 to the security page 442, while an admin privileged user can go in step 606 to the add customer/manager page 446.
  • Figure 7 shows a project initiation screen flow chart of events that occur when the user chooses the project initiation option 510 of Fig. 5. From the Project Initiation -
  • General page 412 the user can go to a list of options 702, including home 504, create new project 506, view existing project 508, baseline statistics 426, active project 428, and reports 512.
  • the user can alternatively go to the Project Initiation - Assessment page 404 and thence to human resources 416, quality 418, risk 420, schedule 422, and scope 424.
  • Figure 8 shows an active project screen flow chart. From the active project page 428, the user can go to the cost 430, human resources 432, quality 434, risk 436, schedule 438, and scope 440.
  • Figure 9 shows a flow chart of the reports when the user selects the reports option 512. From the reports option 512, the user can go to the project initiation summary report 452, the project initiation detail reports 460, or the active project report 480. The user can alternatively go to a list of options 902 including home 504, create new project 506, view existing project 508, project initiation 510, and logout 516.
  • FIG 10 shows a schematic diagram of a hardware configuration 1000 on which the preferred embodiment can be implemented.
  • a Microsoft Windows NT Server platform 1002 runs Microsoft Internet Information Server (IIS) and a standard OLE DB Connection to a database server 1004 running Microsost SQL Server 2000.
  • the server 1002 communicates via standard protocols 1006 such as HTTP and TCP/IP with various clients, shown as client 1 1008-1, client 2 1008-2, client 3 1008-3, and client 4 1008-4.
  • the communication can take place over the Internet, an intranet, or any other suitable network.
  • Security for the PMO provides for user authentication as well as authorization for data entry/update and reporting.
  • Access is limited to authenticated (a login mechanism) and PMO authorized users.
  • the authorization mechanism must support user groups (or user classes).
  • Project data and reports are restricted to specifically authorized users or groups for each project.
  • the PMO has a tailorable question pool that can be adjusted for each organization using the PMO.
  • a base question pool, with the capability to select or reject the use of various questions, is included in the product.
  • a mechanism for adding new, organization specific questions must be available. The definition of new questions must support the risk analysis and health reporting the same as if the questions are part of the base question pool.
  • Questions are tiered (layered), as well as classified according to the project type.
  • Each project is given a "tier control level” that dictates the question depth.
  • the line of questioning is controllable at both a project and a global level, allowing the question "depth" to be set with the project.
  • the questions are also dictated by the project type, and the classification of each question according to project type (e.g., new development questions are only be presented for projects that are classified as new development; level 2 or deeper questions are only be presented for projects which have be set to that level or deeper).
  • All questions are assigned levels, project types, risk categories, life-cycle timing, risk factors (for each possible answer), and reactions to answers including but not limited to: If other questions will be opened or closed, if status will change, and if a notification will be activated, all depending on certain answers.
  • the Question Pool has a Maintenance function built into the program that allows for creating, changing, and removing questions from the Pool. This function will be open only to users with certain access permissions, and will allow the end user to manage and create their own questions as- well as the pre-packaged question set. This includes notifications that will detail any continuity issues that may arise when a question is deleted. There is also some consideration as to predicting potential conflicts between questions as new ones are added to the system.
  • the user can create custom questions sets that will apply to certain project types. In order to accomplish this, there needs to be a system to allow for the dynamic building of question sets from the complete question pool. This system can identify relationships between questions, so that when the user goes to save their new question set, they can be notified if they picked one question from the middle of hierarchy of questions, that there are other questions that should come with it.
  • the Maintenance function contains a function that will allow for the display of the different question sets based upon which project type they are assigned to. A user would come to this section, select a project type, and the program displays the list of questions that are assigned to that type.
  • the Maintenance function has a Periodic Review section. This is based off of the date created field attached to each question. The user will select an interval at which Questions will be marked for review, showing that the questions should be revisited to determine if they are still applicable or need to be edited. Once they have reviewed and updated if necessary, they will be able to mark the question as approved and it will not be flagged until the interval has passed again.
  • the Project Profile and Inventory provides a list of all projects under the PMO and profiles describing general and some technical aspects of each project. Use of the inventory provides information on past and current projects, their results, and allows comparison of project performance with other projects based on profile information.
  • the system has a means of adding, updating, and deleting project profile information by properly authorized users. Each operation (add, update, delete) is discretely assignable to authorized users.
  • the project asset classes are based on the MIT model for classification. The meanings of the classes are described below.
  • Infrastructure provides a shared, standardized capability base for the enterprise. Infrastructure projects lead to greater business flexibility and integration.
  • Informational systems provide information for managing the company. Their payoff comes from shorter time-to-market, superior quality, and the ability to set premium prices. They are moderately risky because companies often have difficulty acting on information to generate business value.
  • the program has functionality that will allow and manage the situation where two or more projects combine into one project at any given point in the projects' life cycles.
  • Performance tracking provides information over the life of a project as to how it is performing against task completion, costs, schedule (milestones), quality, and customer satisfaction.
  • the tracking uses defined thresholds and indicators to identify when a performance area is showing signs of trouble, and coupled with the risk analysis, helps to determine not only when action is needed, but what kind of action as well.
  • Performance tracking requires storing data attributes (measurements) and sets of measurements for each project.
  • the PMO must support integration: with TracerTM or integration with
  • Microsoft Project as a means of automating appropriate data gathering and calculations, and it must also support manual, stand-alone data collection.
  • the Earned Value Management measures, tracked in the performance data are key indicators showing the performance of the project, as well as providing budget and schedule projections for the project. Earned value management is based on the following general measurements.
  • Planned Value (formerly Budgeted Cost of Work Scheduled or BCWS): the cost of the work scheduled or planned to be completed in a certain time period according to plan.
  • Earned Value (formerly Budgeted Cost of Work Performed or BCWP): the planned cost of the work done up to a defined point in the project.
  • Actual Cost (formerly Actual Cost of Work Performed or ACWP): the actual cost of work up to a defined point in the project.
  • Planned Duration the number of days the project is scheduled to be performed over.
  • SPI Schedule Performance Index
  • 3 month and 6 month averages are meaningful between 25% and 100% completion for a project of adequate size to allow such durations; shorter duration projects can use smaller periods of time like 1 and 3 month averages.
  • the cumulative SPI is given the identifier
  • SPIcum while the averaged SPI is given identifiers SPIi, SPI 3 , SPI 6 for 1, 3, and 6 month averages respectively.
  • Cost Performance Index (CPI): (This is the inverse of the performance ratio
  • 3 month and 6 month averages are meaningful between 25% and 100% completion for a project of adequate size to allow such durations; shorter duration projects can use smaller periods of time like 1 and 3 month averages.
  • the cumulative CPI is given the identifier
  • CPIcum while the averaged CPI is given identifiers CPIi, CPI 3 , CPI 6 for 1, 3, and 6 month averages respectively.
  • CSI Cost Schedule Index
  • CSK0.8 or CSI>1.3 Serious problems exist, with little chance of recovering the schedule/budget.
  • the CSI is either a cumulative CSI or an averaged CSI, depending on which
  • SPI and CPI are used.
  • the choice of the SPI and CPI for the calculation must be the same; they will either be the cumulative or one of the (same) averages, e.g., it is incorrect to use
  • the index can be any one of the SPI, CPI, or CSI. Preference is for CPI or
  • CPI gives the "most likely” EAC
  • CSI gives a "pessimistic” EAC. Both the cumulative or averaged index can be used, and it is useful to be able to compare indexes to each other to establish a small range of possible outcomes.
  • Forecast At Completion Calculated estimate for the project budget needed to complete the work. This is traditionally the way many projects forecast the cost. The EAC is a better indicator (FAC is typically very low in its forecast).
  • Planned Duration The calculated duration of the project according to the baseline
  • Forecasted Duration The calculated estimate for the remaining duration of the project
  • Planned Percent Complete The percent of the budget that is planned to be completed.
  • Percent Spent The percent of the budget that has actually been used. [00193] To Complete Performance Index (Baseline): Required cost performance to meet the baseline (original budget).
  • ROT
  • Each Question and data attribute has an assigned risk category, and is assigned a risk weight that can be with positive or negative.
  • the risks are aggregated into the categories defined in SEI-93-TR-6, and used to provide an assessment of the areas of risk in the project.
  • the risk analysis also provides guidance on both mitigating/avoiding certain risks and guidance on addressing realized risks.
  • Mitigation strategies are taken from Capers Jones' work, Assessment and Control of Software Risks (ISBN 0-13-741406-4) (hereby incorporated by reference in its entirety into the present disclosure).
  • the question pool is tiered so that the level of detail in the questioning for a project can be adjusted to an appropriate level.
  • Each question and data attribute is assigned a risk factor either based upon a particular answer, or particular value. These factors are combined to produce a risk score in each area of risk classification.
  • the Risk Analysis is reported as part of the Health and Status Analysis, giving a stop light (Green, Yellow, and Red) indicator of each of the risk areas.
  • the indicator can be clicked on to drill down to see the elements that make-up that risk value.
  • Each risk element can also be drilled down into to see more and more detail about the risk.
  • each risk element provides guidance on risk mitigation approaches.
  • the risk classifications assigned to each question and attribute are those used for aggregating information related to the software risks as identified in Taxonomy-Based
  • Each classification is broken down into a set of elements, that further organize the questions and attributes. Each element is then broken down to a risk attribute.
  • the following subsections show the structure.
  • Product Engineering refers to the technical aspects of the work to be performed.
  • Design covers the design and feasibility of algorithms, functions or performance requirements, and internal and external product interfaces.
  • Code and Unit Test deals with the quality and stability of software or interface specifications, and constraints that may present implementation or testing difficulties.
  • Integration and Test covers integration and test planning, execution, and facilities for both the contractual product and for the integration of the product into the system or site environment.
  • the Development Process refers to the process by which the project proposes to perform the work specified by the requirements.
  • the Development System addresses the hardware and software tools and supporting equipment used in product development.
  • the Management Process deals with risks associated with planning, monitoring, and controlling budget and schedule; controlling factors in defining, implementing, and testing the product; managing project personnel; and handling external organizations.
  • Management Methods refers to methods for managing both the development of the product and project personnel.
  • Project Constraints is called Program Constraints in SEI-93-TR-6.
  • Resources address resources that the project is dependent on but are outside the project's control to obtain and maintain.
  • the Portfolio Health and Status Analysis provide a simple, high level view of the performance data, and indicate on-track, drifting, or off-track. Each project in the portfolio is shown, and the ability to drill down to greater detail on each project allows managers and executives the ability to see the project at just the level they need to follow and manage the results.
  • the basis of the health and status analysis is a number of attributes for the execution of the project, along with attributes for calculated performance limits.
  • the various thresholds and limits are used to calculate and assign a heath status for the relevant measure.
  • the status is to be displayed in a "stoplight” fashion: green, yellow, and red; for ok/on-track, drifting, and trouble respectively.
  • Financial data is tracked and displayed for each project, with the ability to control time periods, and organization units and roll-ups.
  • the data includes general expenses, payroll, and project revenue/income.
  • the financials are displayable by business (organizational) unit, with the ability to combine organizational units into a composite view.
  • the organizational units to be combined are selectable by the user, and selections persist across application sessions.
  • AU financials must have the ability to be displayed at resolutions of: weekly, monthly quarterly, and yearly, with an optional ability to show the previous year against the current year (with the same time resolution).
  • Key Goal Tracking allows an organization to list and conveniently report the current status of its key goals.
  • a key goal is a quantifiable target of achievement that can be monitored and the status of meeting said goal can be displayed based upon data, e.g.: 25%
  • Each key goal has an assignable owner, that is, the person who is responsible for tracking and updating the status of the key goal.
  • Checkpoints can be added, edited and removed at any time.
  • Objective Tracking allows an organization to list and conveniently report the current status of its objectives.
  • An objective is, unlike a Key Goal, a non-quantified target of achievement. While an objective may be monitored and tracked, a status decision for an objective is based more upon the reporting manager's thoughts on progress, than upon data, e.g.: SLA Improvements, Increase Level 1 Helpdesk Resolution.
  • Tasks can be added, edited and removed at any time by the Objective owner or an administrator.
  • Multi-level reporting allows varying details levels of the projects to be reported, from easy to read "stop-light” type charts, to line and bar graphs, to data sheets.
  • a project manager will see an overview of all projects he is responsible for.
  • An IT manager will see a higher level summary of the projects that are under his control, with the ability to drill down to the project level as desired.
  • the PMO In addition to the standard reports and views, the PMO must support ad hoc reporting (using tools like e.g., Crystal Reports).
  • the analysis uses a portfolio pyramid that is described by the following descriptions. At the base are the infrastructure investments. Built on that base are the transactional systems (which need a reliable infrastructure). At the top are the information producing and strategic systems.
  • the PMO using the data gathered, along with this model, will analyze the investment distribution. This distribution is used to evaluate the orientation of the IT portfolio and determine the level of alignment with the company's strategic focus.
  • Project Profile This will allow the user to see the distribution of the Portfolio based on the business areas the projects are operating beneath.
  • the Effort Distribution Analysis provides a manager with the ability to place a general effort breakdown of the project in the system for analysis and project plan validation.
  • the effort breakdown is based on a table of percentages of total effort for each major phase in the lifecycle, based on aggregate measures of completed projects. Such a table is tunable and verified by the application such that all roll-ups come to the correct percentages, and the total for the table rolls-up to 100%.
  • the system will determine if the projects breakdown is reasonable, within a defined threshold for each phase.
  • the indicators are a "stop-light" view of each phase (green, yellow, red) to show where phases may be under or over estimated.
  • the library is browsable by the user and allow viewing and downloading of the templates.
  • Completed templates is uploadable to the system and assigned to (associated with) the particular project to which they pertain.
  • the projects documents are viewable or downloadable by any appropriately authorized user.
  • the templates include:
  • a PMO homepage known as a Dashboard view
  • the Dashboard will need to display data, such as, but not limited to:
  • All facets of the project are displayed with their corresponding stop light indicators. Each facet is listed as a link to its corresponding data display. Whichever graph or data form is being displayed at the current time is highlighted in this list in an obvious manner. Additionally, the same highlighting is applied to which view the user is currently accessing. [00322] The limits for each facet needs to be manually changeable, and needs to be saved once changed.
  • the project information such as the sponsor, manager, location, and project type is displayed.
  • the yellow and red thresholds will also be graphed, but these will be based upon a percentage or fixed value, enumerated separately by the user.
  • the graph will have a line for both Actual and Baseline, as well as a variance line both above and below the baseline for the yellow and red thresholds.
  • the graph by default, displays 26 weeks. This number is able to be changed within the program to show a user defined date range on a project by project basis. Weeks start on the Sunday of a given week.
  • the customer satisfaction and quality graphs do not utilize a baseline but rather definable target zones.
  • the attributes associated with these graphs in addition to displaying the zones are the containment percent.
  • the yellow and red lines will denote target zones.
  • the graph by default, displays 26 weeks. This number can be changed within the program to show a user defined date range on a project by project basis. Weeks start on the Sunday of a given week.
  • Graphing is dynamic; that is, it includes a functionality that allows for the user to either define custom graphs, or overlay existing graphs in order to analyze how changes in one graph influence others. [00331] If data entry for the six project facets remains manual, place all data entry for the facets on one page for quick entry of weekly data.
  • Financial graphs can be displayed in three manners.
  • Date Range The financial data will be displayed in a monthly or quarterly view based upon the dates specified by the user.
  • the data for the financial graph are input and stored in some fashion, either automatically by working with Tracer, or by manual input on the part of the project manager.
  • Database tables are created to hold required data for displaying the dashboard items. This will include the items being tracked, as well as the detailed data for determining the status.
  • the system has data supplied weekly, and be able to report on those data on a week-by-week basis.
  • Each portfolio project will have an arbitrary number of weeks of baseline or planned data points, one set for each week for each area. All project/reporting areas will record weekly data point each area (for use in comparing to the baseline, or indicate the current health/status).
  • AU active projects are listed under the “Active” heading and contain the following:
  • Project Start - This can be based off the project start date listed in the project creation screen, and just restated here.
  • Scheduled Completion Date a reiteration of the original date the project was scheduled to be completed upon set on the Project Creation screen.

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Human Resources & Organizations (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
EP05855725A 2004-12-30 2005-12-30 System und verfahren für ein automatisiertes projektbüro und automatische risikobewertung und -meldung Withdrawn EP1846822A2 (de)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US64010404P 2004-12-30 2004-12-30
US11/249,744 US7640225B2 (en) 2004-10-14 2005-10-14 System and method for process automation and enforcement
PCT/US2005/047212 WO2006073978A2 (en) 2004-12-30 2005-12-30 System and method for an automated project office and automatic risk assessment and reporting

Publications (1)

Publication Number Publication Date
EP1846822A2 true EP1846822A2 (de) 2007-10-24

Family

ID=36648037

Family Applications (1)

Application Number Title Priority Date Filing Date
EP05855725A Withdrawn EP1846822A2 (de) 2004-12-30 2005-12-30 System und verfahren für ein automatisiertes projektbüro und automatische risikobewertung und -meldung

Country Status (6)

Country Link
EP (1) EP1846822A2 (de)
JP (1) JP2008527500A (de)
AU (1) AU2005322968A1 (de)
CA (1) CA2593045A1 (de)
MX (1) MX2007008041A (de)
WO (1) WO2006073978A2 (de)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9021095B2 (en) 2011-05-27 2015-04-28 Oracle International Corporation Method and system for implementing an on-demand scheduler in a mobile device
US9165011B2 (en) 2011-09-30 2015-10-20 Oracle International Corporation Concurrent calculation of resource qualification and availability using text search

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101139626B1 (ko) 2011-12-07 2012-04-27 우리투자증권 주식회사 운용과정 기반의 포트폴리오 리스크 평가 방법 및 시스템
WO2017154914A1 (ja) 2016-03-10 2017-09-14 三菱電機株式会社 プロジェクト管理支援システム、プロジェクト管理支援方法及びプロジェクト管理支援プログラム
CN107862444A (zh) * 2017-10-23 2018-03-30 青岛市市北区审计局 一种审计人员业绩考核自动化管理系统
CN113095606B (zh) * 2021-06-09 2021-08-31 北矿智云科技(北京)有限公司 设备维修的预判方法、装置及系统

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6714915B1 (en) * 1999-11-22 2004-03-30 International Business Machines Corporation System and method for project designing and developing a procurement and accounts payable system
US20020120490A1 (en) * 2001-02-26 2002-08-29 Gajewski Arthur Joseph Vehicle systems concept development process
US20040054610A1 (en) * 2001-11-28 2004-03-18 Monetaire Monetaire wealth management platform
US20030204462A1 (en) * 2002-04-30 2003-10-30 Eisler Clifford R. Method and system for administering the hedging of an employee deferred compensation plan using swaps and options
US7664664B2 (en) * 2003-04-23 2010-02-16 Oracle International Corporation Methods and systems for portfolio planning
US7698148B2 (en) * 2003-09-12 2010-04-13 Raytheon Company Web-based risk management tool and method
US20050114829A1 (en) * 2003-10-30 2005-05-26 Microsoft Corporation Facilitating the process of designing and developing a project

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See references of WO2006073978A2 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9021095B2 (en) 2011-05-27 2015-04-28 Oracle International Corporation Method and system for implementing an on-demand scheduler in a mobile device
US9165011B2 (en) 2011-09-30 2015-10-20 Oracle International Corporation Concurrent calculation of resource qualification and availability using text search

Also Published As

Publication number Publication date
WO2006073978A2 (en) 2006-07-13
AU2005322968A1 (en) 2006-07-13
CA2593045A1 (en) 2006-07-13
WO2006073978A3 (en) 2007-11-22
MX2007008041A (es) 2007-10-19
JP2008527500A (ja) 2008-07-24

Similar Documents

Publication Publication Date Title
US8041647B2 (en) System and method for an automated project office and automatic risk assessment and reporting
US11205141B2 (en) Methods and systems for resource and organization achievement
US7168045B2 (en) Modeling business objects
US7930201B1 (en) EDP portal cross-process integrated view
US8244565B2 (en) Individual productivity and utilization tracking tool
US20040002887A1 (en) Presenting skills distribution data for a business enterprise
US7519539B1 (en) Assisted profiling of skills in an enterprise management system
US7222330B2 (en) Project planning system with content loaded project planning template generator and a plurality of content loaded project planning templates
US20170147960A1 (en) Systems and Methods for Project Planning and Management
US6742002B2 (en) Computer-implemented and/or computer-assisted web database and/or interaction system for staffing of personnel in various employment related fields
US20070192157A1 (en) Interactive system for managing, tracking and reporting work and staff performance in a business environment
US20030135481A1 (en) Rules based method and system for project performance monitoring
US20100324952A1 (en) Continuous governance, risk and compliance management
US20100268705A1 (en) Database and data access layer
US20030018511A1 (en) Adaptable integrated-content product development system
US20040243458A1 (en) Method and system for organization management utilizing document-centric intergrated information exchange and dynamic data collaboration
Niessink et al. The IT service capability maturity model
EP0954813A1 (de) Strategisches managementsystem
WO2006073978A2 (en) System and method for an automated project office and automatic risk assessment and reporting
AU2010201888B2 (en) Individual productivity and utilization tracking tool
Hanschke et al. IT landscape management
Albadri et al. The Role of Controls to Minimize Risks of Information Technology Project Failures
Zenié et al. Analyzing and redesigning a remote sensing business process for rapid estimates of agriculture in Europe
Orci Capability Maturity Model for
Dludhlu Risk Evaluation in Project Management Implementation: The Case of Infrastructural Development Projects in Transnet

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20070727

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IS IT LI LT LU LV MC NL PL PT RO SE SI SK TR

AX Request for extension of the european patent

Extension state: AL BA HR MK YU

R17D Deferred search report published (corrected)

Effective date: 20071122

DAX Request for extension of the european patent (deleted)
RIC1 Information provided on ipc code assigned before grant

Ipc: G06Q 40/00 20060101AFI20080521BHEP

Ipc: G06F 9/46 20060101ALI20080521BHEP

Ipc: G05B 19/418 20060101ALI20080521BHEP

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION HAS BEEN WITHDRAWN

18W Application withdrawn

Effective date: 20080918