EP1579087B1 - Vertical alignment and levelling of modular building units - Google Patents
Vertical alignment and levelling of modular building units Download PDFInfo
- Publication number
- EP1579087B1 EP1579087B1 EP03780339A EP03780339A EP1579087B1 EP 1579087 B1 EP1579087 B1 EP 1579087B1 EP 03780339 A EP03780339 A EP 03780339A EP 03780339 A EP03780339 A EP 03780339A EP 1579087 B1 EP1579087 B1 EP 1579087B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- building
- module
- modular building
- units
- building unit
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 230000002093 peripheral effect Effects 0.000 claims abstract description 15
- 238000000034 method Methods 0.000 claims description 6
- 229910000746 Structural steel Inorganic materials 0.000 claims description 5
- 229920001971 elastomer Polymers 0.000 claims description 4
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 238000007688 edging Methods 0.000 claims 3
- 238000009413 insulation Methods 0.000 description 6
- 238000003466 welding Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 239000002023 wood Substances 0.000 description 2
- 230000004308 accommodation Effects 0.000 description 1
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 239000013536 elastomeric material Substances 0.000 description 1
- 238000009408 flooring Methods 0.000 description 1
- 239000006260 foam Substances 0.000 description 1
- 238000010348 incorporation Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 239000011120 plywood Substances 0.000 description 1
- 229920001084 poly(chloroprene) Polymers 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/348—Structures composed of units comprising at least considerable parts of two sides of a room, e.g. box-like or cell-like units closed or in skeleton form
- E04B1/34815—Elements not integrated in a skeleton
- E04B1/3483—Elements not integrated in a skeleton the supporting structure consisting of metal
Definitions
- the invention relates to modular building units for use in the construction of largely prefabricated offices, hotels and apartment blocks, and buildings of a similar general nature.
- Such modular building units are box-like structures which can be manufactured and fitted-out off-site and then transported to a construction site for final assembly to form the internal rooms of a building.
- the invention also relates to a method for the erection of buildings using such modular building units, and in particular to the alignment of such a building and the levelling of the lower or ground floor units.
- the modules are hoisted by crane from the lorry or truck on which they had been transported, and stacked in a vertical and horizontal array cooperating to form the linked rooms of the final building.
- the accuracy required in the stacking process is relatively crude. It makes very little difference to the final stability of the building whether the individual modules are accurately positioned vertically one over the other, and generally it is considered to be adequate for the individual modular building units to be manipulated into their final positions by hand as they are lowered by crane.
- the accuracy of the vertical alignment of the individual building units in the array becomes of increasing importance.
- the invention comprises a modular building unit as specified in claims 1 to 6 herein.
- the edge location means provided by the cooperating location flange and peripheral recess of vertically adjacent modules, makes it possible accurately to position the modular building units one above the other in the array with the minimum reliance on skilled labour.
- the peripheral recess has an inside side wall which slopes upwardly and inwardly relative to the building module, to guide the vertically adjacent building module into position when stacking the modules one above the other during the erection of a building therefrom.
- the erection team manhandling the module into position as it is lowered by crane simply have to guide the module being hoisted into position to within about two or three centimetres of its final position, and the sloping inside side wall of the peripheral recess is sufficient to guide the module into its precise final position.
- the building modules according to the invention may be constructed as described and claimed in copending Patent Application No. W068004 filed herewith and linked together horizontally and vertically as described in W068006 filed herewith. They may be made from a lined skeletal shell of structural building elements as described and claimed in copending Patent Application No. W068007 filed herewith.
- the invention provides a method of building as specified in claim 7 herein.
- FIG 1 is a perspective view of a complete building module 1, constructed according to my copending Patent Application No W068004 and provided in addition with edge location means in accordance with this invention.
- the module comprises four walls, a floor and a roof.
- One end wall is shown in Figure 1 as having a window.
- the opposite end wall (not visible) would have a door.
- the window wall would be on the outside of the assembled building and the door wall would be on the inside, with the doors opening for example onto a corridor providing access to any of the modules in a given row.
- the corner strip 2 is made from lightweight cold-formed structural steel by a folding or creasing operation, and comprises a front face 2a, a lower top face 2b, an inclined face 2c and an upper top face 2d.
- the front face 2a is secured to the structural uprights of the modular building unit, for example by spot welding or plug welding.
- the lower top face 2b lies over the horizontally aligned top ends of those structural uprights.
- the peripheral recess which extends around all four edges of the top of the module 1.
- the top of the module 1 is externally boarded with load-bearing panels 3 which are strong enough to bear the weight of the construction team members who are employed to erect a building from a number of such modular units.
- the upper top face 2d of the corner strip 2 lies in a recess formed in the top of the load-bearing panels 3, and over the upper top face 2d is adhered a strip 4 of acoustic insulation, for example a strip of rubber or elastomeric material such as high density neoprene foam.
- Another such strip 5 of acoustic insulation is adhered over the lower top face 2b of the corner strip 2, so as to provide good acoustic insulation between vertically adjacent stacked modules 1.
- An alternative sound insulation barrier could be obtained by laying the corner strip 2 over a layer of rubber or elastomeric or other sound-absorbing lining.
- Figure 3 shows the detail of the bottom periphery of each module 1, and also shows how that bottom detail cooperates with the peripheral recess around the top edge of the module vertically beneath it in the final building. That module beneath is shown in Figure 3 in broken line, but is exactly as described above with reference to Figure 2. In Figure 3 the strips 4 and 5 of acoustic insulation are shown compressed, as they would be in practice, by the weight of the module or modules 1 vertically above.
- the bottom detail of the module 1 is provided by a corner strip cold-formed so as to define a downwardly extending locating flange 6 into which the structural uprights (not shown) of the module rest.
- An outer wall of the flange 6 extends upwardly as an outside wall portion 7 of the corner strip, which is secured to the outside of the skeletal building module 1 by spot welding or plug welding for example.
- the inner wall of the flange 6 is bent to follow the angle of the inclined face 2c of the top corner strip 2, terminating in a bottom plate portion 8 which is welded to the bottoms of an array of cross-beams (not shown) which support the floor of the module 1.
- welding has been specified as the securing method of choice in the particular example illustrated, other securing methods such as bolts, rivets or even adhesive are feasible alternatives depending on the permanence of the intended building and the stresses to which it is expected to be exposed.
- a lowermost array of modules 1 is first manoeuvred into position and anchored to foundations. Then one by one the modules 1 of the next storey are hoisted into position by crane. As the modules 1 are lowered by the crane operator, they are pushed into position by a crew.
- the edge location provides accurate positioning of the modules on the modules of the floor below, and the workmen can walk freely on the roofs of the ground floor array of modules 1 because the top boarding 3 is load-bearing.
- the assembled modules may be locked together as described and claimed in my copending Patent Application No. W068006 .
- a continuous cable may be threaded through the wall cavities defined by mutually aligned vertical structural uprights of successive storeys of the building and tensioned as a continuous cable run from the building foundations to roof, to lock together the modules vertically.
- a series of interconnected tubes or rods may be used, each one storey in height, as described in my copending Application No W068007 .
- Similar interconnected tubes or rods may be used across the building in the horizontal plane, but generally it will be sufficient to connect the modules together horizontally using gutter plates straddling the roves of horizontally adjacent modules, which for sound insulation purposes are usually stacked with a small horizontal gap therebetween.
- the gutter plates not only tie the adjacent modules together horizontally but also prevent the ingress of rain between adjacent modules during erection.
- FIG. 4 shows a levelling unit which in practice is laid over the foundations or any given course of a building and accurately levelled before the next courses of building modules are hoisted into position.
- the levelling unit of Figure 4 is given the general reference 10 and comprises a peripheral structure of C-sections 11, each made from lightweight cold-formed structural steel.
- Running in parallel between the C-sections 11 forming the long edges of the base levelling unit 10 are an array of C-section cross-beams 12, each connected to the corresponding C-section peripheral beam 11 in exactly the same way as the floor and ceiling cross-beams are connected in the building modules of Figures 1 to 3.
- spacers (not shown) of C-section may be welded at staggered intervals between adjacent pairs of cross-beams 12, to create an overall rigid assembly. If desired, although not shown in Figure 4, that assembly can be clad over its top surface with load-bearing flooring similar to the boarding 3 of Figure 2.
- FIG. 10 Around the outside edge of the base levelling unit 10 (although again not shown in Figure 4) is a corner strip defining a peripheral recess exactly the same as the corner strip 2 described and illustrated with reference to Figure 2 around the top of each complete building module according to the invention.
- Figure 2 could equally be a section through one of the edges of the base levelling unit 10 of Figure 4, except that the line in Figure 2 referenced 1 and indicating the building module would in fact indicate the outside wall of the levelling unit 10 and the C-section peripheral members 11.
- levelling unit 10 In use, it is far easier to handle a levelling unit 10 than a complete fitted-out building module 1. Therefore after preparing the foundations of the building, one such levelling unit 10 is placed in position to define the footprint of each room to be created on successive floors of the finished building. Levelling of the individual levelling units 10 can be achieved by the insertion of metal shims or by the use of screw jacks, and is carried out with precision until an accurate level base or lower level course is created for the upper courses of the individual building modules 1 of the finished building.
- each levelling unit 10 As each levelling unit 10 is accurately positioned and levelled, it may be secured to the foundations or ground level structure by anchor bolts, tie straps or other appropriate anchorage means (not shown) so that the base course for the upper storeys of the building is both accurately levelled and secured to the foundations or ground level structure.
- individual building modules 10 are hoisted into position by a crane and are located by the edge recesses in the levelling units 10, exactly as described above in relation to the accurate assembly of the upper storeys of the building.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Floor Finish (AREA)
- Residential Or Office Buildings (AREA)
Abstract
Description
- The invention relates to modular building units for use in the construction of largely prefabricated offices, hotels and apartment blocks, and buildings of a similar general nature. Such modular building units are box-like structures which can be manufactured and fitted-out off-site and then transported to a construction site for final assembly to form the internal rooms of a building. The invention also relates to a method for the erection of buildings using such modular building units, and in particular to the alignment of such a building and the levelling of the lower or ground floor units.
- Particularly in the construction of hotels, apartments and student accommodation it is known to construct the buildings from lightweight building modules each of which is a skeletal steel shell formed from lightweight structural steel sections welded into a box-like structure and lined with boarding such as plasterboard, plywood or oriented strand board (OSB). Each building module is made initially as such a lined shell, and is then fitted-out to the desired standard of internal decoration in a factory before being transported to the final building site for incorporation into a building. Other building modules are known, made primarily from wood frames and wood boarding. Document
DE 298 08 134 U discloses building module with the features of the preambule ofclaim 1. - At the building site, the modules are hoisted by crane from the lorry or truck on which they had been transported, and stacked in a vertical and horizontal array cooperating to form the linked rooms of the final building. For low-rise buildings, the accuracy required in the stacking process is relatively crude. It makes very little difference to the final stability of the building whether the individual modules are accurately positioned vertically one over the other, and generally it is considered to be adequate for the individual modular building units to be manipulated into their final positions by hand as they are lowered by crane. For progressively higher rise buildings, the accuracy of the vertical alignment of the individual building units in the array becomes of increasing importance. Hitherto, however, the accuracy of the stacking has depended entirely on the skill of the crane driver in being able to hold the topmost building unit static, while skilled workers manoeuvre it manually into the correct vertically aligned position, before the tension in the crane cable is released and the building unit takes up its final position over the lower units in the stack.
- It is an object of this invention to provide, for such a modular building unit and building system, a means for automatically and accurately aligning the vertically adjacent building units in the stack. By making the alignment automatic and largely unreliant on the skill of the building workers manoeuvring the modular building units into position, it is possible to increase the height of buildings made from such modular units using unskilled labour, from a previous practical maximum of about five storeys to from twenty to thirty storeys.
- The invention comprises a modular building unit as specified in
claims 1 to 6 herein. The edge location means, provided by the cooperating location flange and peripheral recess of vertically adjacent modules, makes it possible accurately to position the modular building units one above the other in the array with the minimum reliance on skilled labour. Preferably the peripheral recess has an inside side wall which slopes upwardly and inwardly relative to the building module, to guide the vertically adjacent building module into position when stacking the modules one above the other during the erection of a building therefrom. Therefore the erection team manhandling the module into position as it is lowered by crane simply have to guide the module being hoisted into position to within about two or three centimetres of its final position, and the sloping inside side wall of the peripheral recess is sufficient to guide the module into its precise final position. - The building modules according to the invention may be constructed as described and claimed in copending Patent Application No.
W068004 W068006 W068007 - Finally, the invention provides a method of building as specified in
claim 7 herein. -
- Figure 1 is a perspective view of a modular building unit according to the invention;
- Figure 2 is a section taken along the line A-A of a top corner of the building unit of Figure 1;
- Figure 3 is a section taken along the line B-B through a bottom corner of the building unit of Figure 1; and
- Figure 4 is a perspective view of a levelling unit for use with the modular building unit of Figures 1 to 3.
- Figure 1 is a perspective view of a
complete building module 1, constructed according to my copending Patent Application NoW068004 - Around the outer edge of the top of the
module 1 is a peripheral recess which is defined by acorner strip 2, as shown in Figure 2. Thecorner strip 2 is made from lightweight cold-formed structural steel by a folding or creasing operation, and comprises afront face 2a, alower top face 2b, aninclined face 2c and anupper top face 2d. Thefront face 2a is secured to the structural uprights of the modular building unit, for example by spot welding or plug welding. Thelower top face 2b lies over the horizontally aligned top ends of those structural uprights. Between thelower top face 2b and theinclined face 2c is formed the peripheral recess which extends around all four edges of the top of themodule 1. - The top of the
module 1 is externally boarded with load-bearingpanels 3 which are strong enough to bear the weight of the construction team members who are employed to erect a building from a number of such modular units. Theupper top face 2d of thecorner strip 2 lies in a recess formed in the top of the load-bearingpanels 3, and over theupper top face 2d is adhered a strip 4 of acoustic insulation, for example a strip of rubber or elastomeric material such as high density neoprene foam. Anothersuch strip 5 of acoustic insulation is adhered over thelower top face 2b of thecorner strip 2, so as to provide good acoustic insulation between vertically adjacent stackedmodules 1. An alternative sound insulation barrier could be obtained by laying thecorner strip 2 over a layer of rubber or elastomeric or other sound-absorbing lining. - Figure 3 shows the detail of the bottom periphery of each
module 1, and also shows how that bottom detail cooperates with the peripheral recess around the top edge of the module vertically beneath it in the final building. That module beneath is shown in Figure 3 in broken line, but is exactly as described above with reference to Figure 2. In Figure 3 thestrips 4 and 5 of acoustic insulation are shown compressed, as they would be in practice, by the weight of the module ormodules 1 vertically above. - The bottom detail of the
module 1 is provided by a corner strip cold-formed so as to define a downwardly extending locatingflange 6 into which the structural uprights (not shown) of the module rest. An outer wall of theflange 6 extends upwardly as anoutside wall portion 7 of the corner strip, which is secured to the outside of theskeletal building module 1 by spot welding or plug welding for example. The inner wall of theflange 6 is bent to follow the angle of theinclined face 2c of thetop corner strip 2, terminating in abottom plate portion 8 which is welded to the bottoms of an array of cross-beams (not shown) which support the floor of themodule 1. Although welding has been specified as the securing method of choice in the particular example illustrated, other securing methods such as bolts, rivets or even adhesive are feasible alternatives depending on the permanence of the intended building and the stresses to which it is expected to be exposed. - When erecting a building from a number of modules according to the invention, a lowermost array of
modules 1 is first manoeuvred into position and anchored to foundations. Then one by one themodules 1 of the next storey are hoisted into position by crane. As themodules 1 are lowered by the crane operator, they are pushed into position by a crew. The edge location provides accurate positioning of the modules on the modules of the floor below, and the workmen can walk freely on the roofs of the ground floor array ofmodules 1 because thetop boarding 3 is load-bearing. - When each
upper storey module 1 is approximately in position, the crane driver lowers it its last few centimetres, and theinclined faces 2c guide it gently but accurately into register with the module below. - The assembled modules may be locked together as described and claimed in my copending Patent Application No.
W068006 W068007 - Figure 4 shows a levelling unit which in practice is laid over the foundations or any given course of a building and accurately levelled before the next courses of building modules are hoisted into position. The levelling unit of Figure 4 is given the
general reference 10 and comprises a peripheral structure of C-sections 11, each made from lightweight cold-formed structural steel. Running in parallel between the C-sections 11 forming the long edges of thebase levelling unit 10 are an array of C-section cross-beams 12, each connected to the corresponding C-sectionperipheral beam 11 in exactly the same way as the floor and ceiling cross-beams are connected in the building modules of Figures 1 to 3. For additional rigidity, spacers (not shown) of C-section may be welded at staggered intervals between adjacent pairs ofcross-beams 12, to create an overall rigid assembly. If desired, although not shown in Figure 4, that assembly can be clad over its top surface with load-bearing flooring similar to theboarding 3 of Figure 2. - Around the outside edge of the base levelling unit 10 (although again not shown in Figure 4) is a corner strip defining a peripheral recess exactly the same as the
corner strip 2 described and illustrated with reference to Figure 2 around the top of each complete building module according to the invention. Thus Figure 2 could equally be a section through one of the edges of thebase levelling unit 10 of Figure 4, except that the line in Figure 2 referenced 1 and indicating the building module would in fact indicate the outside wall of the levellingunit 10 and the C-sectionperipheral members 11. - In use, it is far easier to handle a
levelling unit 10 than a complete fitted-outbuilding module 1. Therefore after preparing the foundations of the building, onesuch levelling unit 10 is placed in position to define the footprint of each room to be created on successive floors of the finished building. Levelling of theindividual levelling units 10 can be achieved by the insertion of metal shims or by the use of screw jacks, and is carried out with precision until an accurate level base or lower level course is created for the upper courses of theindividual building modules 1 of the finished building. As each levellingunit 10 is accurately positioned and levelled, it may be secured to the foundations or ground level structure by anchor bolts, tie straps or other appropriate anchorage means (not shown) so that the base course for the upper storeys of the building is both accurately levelled and secured to the foundations or ground level structure. - Thereafter,
individual building modules 10 are hoisted into position by a crane and are located by the edge recesses in the levellingunits 10, exactly as described above in relation to the accurate assembly of the upper storeys of the building.
Claims (7)
- A modular building unit (1) comprising a skeletal shell lined to define the walls of a room or rooms, the building units (1) when stacked in a vertical and horizontal array cooperating to form the linked rooms of a building, characterised in that for precise location of one module or part thereof vertically over another in the resulting building, each module is provided around the perimeter of its base with a downwardly extending location flange (6), and each module is also provided with an external roof covering of load-bearing boarding (3) which extends close to but not up to the outside perimeter of the top of the module, and the external perimeter of the module 2a lad with an edging (2) of cold-formed lightweight steel which has a first portion (2a,2b) which laps around the top of the side and end walls of the module and a second portion (2c,2d) which laps over the outside edge of the boarding (3), so that between the first and second portions of the edging is formed a peripheral locating recess (2b, 2c) into which the location flange (6) of a vertically adjacent building module can accurately locate.
- A modular building unit according to claim 1, wherein the peripheral recess (2b,2c) has an inside side wall which slopes upwardly and inwardly relative to the building module, to guide the vertically adjacent building module into position when stacking the modules one above the other during the erection of a building therefrom.
- A modular building unit according to claim 1 or claim 2, wherein the modular building unit (1) comprises a skeletal shell of structural steel uprights and cross-members lined to define the walls of the room.
- A modular building unit according to any preceding claim, wherein the lined skeletal shell is clad with said external roof covering of load-bearing boarding (3) which extends close to but not up to the outside perimeter of the top of the module, so that the edge of the boarding lies along the inside edge of the locating recess.
- A modular building unit according to any preceding claim, wherein the locating recess is lined with a rubber or elastomeric or other sound-absorbing lining (4, 5).
- A modular building unit according to any of claims 1 to 4, wherein the edging of cold-formed lightweight steel (2) is laid over a layer of a rubber or elastomeric or other sound-absorbing lining (4, 5).
- A method of building using modular building units according to any of claims 1 to 6, wherein one or more levelling units (10) each comprising a skeletal shell of structural steel peripheral members (11) and cross-members (12) defining a footprint of a modular building unit according to any of claims 1 to 6 are positioned over a foundation or ground level structure of the building, and each is accurately levelled and located relative to the adjacent levelling units by the use of shims or screw jacks between the levelling units (10) and the building foundations or ground level structure; and the levelling units (10) are secured fast to the building foundations or ground level structure prior to placing individual modular building units (1) thereon, and locating those modular building units (1) by engagement of the generally extending location flange (6) around the perimeter of the base of each building unit into a peripheral recess (2b, 2c) formed around the respective levelling unit (10) into which the location flange (6) of the corresponding modular building unit (1) can accurately locate.
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GBGB0228173.1A GB0228173D0 (en) | 2002-12-03 | 2002-12-03 | Vertical alignment and levelling of modular building units |
GB0228173 | 2002-12-03 | ||
PCT/GB2003/005280 WO2004051018A1 (en) | 2002-12-03 | 2003-12-03 | Vertical alignment and levelling of modular building units |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1579087A1 EP1579087A1 (en) | 2005-09-28 |
EP1579087B1 true EP1579087B1 (en) | 2007-06-13 |
Family
ID=9948985
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP03780339A Expired - Lifetime EP1579087B1 (en) | 2002-12-03 | 2003-12-03 | Vertical alignment and levelling of modular building units |
Country Status (14)
Country | Link |
---|---|
US (1) | US20060168901A1 (en) |
EP (1) | EP1579087B1 (en) |
JP (1) | JP4441406B2 (en) |
CN (1) | CN100379930C (en) |
AT (1) | ATE364760T1 (en) |
AU (1) | AU2003288420A1 (en) |
CA (1) | CA2508366C (en) |
DE (1) | DE60314454T2 (en) |
ES (1) | ES2290523T3 (en) |
GB (1) | GB0228173D0 (en) |
HK (1) | HK1089217A1 (en) |
NZ (1) | NZ541054A (en) |
WO (1) | WO2004051018A1 (en) |
ZA (1) | ZA200505336B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102020002272A1 (en) | 2020-04-14 | 2021-10-14 | Wenker Gmbh & Co. Kg | Hybrid building |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8516961B2 (en) | 2007-05-08 | 2013-08-27 | Esko-Graphics Imaging Gmbh | Method and apparatus for loading and unloading flexographic plates for computer-to-plate imaging including separate loading and unloading areas |
WO2009108986A1 (en) * | 2008-03-07 | 2009-09-11 | Francesco Antonio Martino | A transportable building including a roof structure for stacking of multiple buildings |
JP5226454B2 (en) * | 2008-10-10 | 2013-07-03 | 三菱樹脂株式会社 | Divided cooling tower |
US20120102871A1 (en) * | 2010-10-27 | 2012-05-03 | Randall Bruce D | Self-registering, modular outbuilding apparatus and method |
US8683929B2 (en) * | 2011-09-05 | 2014-04-01 | Lifetime Products, Inc. | Table with nesting table top |
USD771272S1 (en) * | 2015-05-08 | 2016-11-08 | Gordon Hart | Skid mounted fire suppression shack |
ES2893150A1 (en) * | 2020-08-06 | 2022-02-08 | Sanz Arranz Tomas | Steel monoblock prefablock housing modules, structurally resistant for movement and transport, which joined each other by a rapid anchor system according to an easy and rapid assembly and disassembly building. (Machine-translation by Google Translate, not legally binding) |
BE1028666B1 (en) * | 2020-10-01 | 2022-05-02 | Icontech | Prefabricated three-dimensional constructive module |
CA3107029A1 (en) * | 2021-01-26 | 2022-07-26 | Emerge Modular Ltd | Precast steel concrete module |
GB2612058A (en) * | 2021-10-20 | 2023-04-26 | Modulous Ltd | Modules for modular buildings |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2645114A (en) * | 1945-10-18 | 1953-07-14 | Amirikian Arsham | Hollow structure |
US3510997A (en) * | 1968-08-26 | 1970-05-12 | Eugene Ratych | Building system of preformed units |
AU454071B2 (en) * | 1970-11-05 | 1974-10-17 | Steel Frame Investments Pty. Ltd. | Building and method of erection |
US4614066A (en) * | 1985-12-09 | 1986-09-30 | Koppenberg Bruce G | Modular columbarium structure |
DE3915711A1 (en) * | 1989-01-31 | 1990-11-15 | Ibs Integriertes Bauen | COMPONENT FOR CREATING BUILDINGS, BUILDING PARTS OR THE LIKE. |
US5044544A (en) * | 1990-02-22 | 1991-09-03 | Sea-Land Corporation, Inc. | Modular cargo container |
GB2264726A (en) * | 1992-02-27 | 1993-09-08 | Chu Rey Chin | Demountable multi-storey car park |
DE29808134U1 (en) * | 1998-05-06 | 1999-09-30 | Elbe-Haus Industrie AG, 39596 Arneburg | Component and house module from several components |
-
2002
- 2002-12-03 GB GBGB0228173.1A patent/GB0228173D0/en not_active Ceased
-
2003
- 2003-12-03 AT AT03780339T patent/ATE364760T1/en not_active IP Right Cessation
- 2003-12-03 JP JP2004556539A patent/JP4441406B2/en not_active Expired - Fee Related
- 2003-12-03 CA CA002508366A patent/CA2508366C/en not_active Expired - Fee Related
- 2003-12-03 US US10/537,923 patent/US20060168901A1/en not_active Abandoned
- 2003-12-03 EP EP03780339A patent/EP1579087B1/en not_active Expired - Lifetime
- 2003-12-03 DE DE60314454T patent/DE60314454T2/en not_active Expired - Lifetime
- 2003-12-03 ES ES03780339T patent/ES2290523T3/en not_active Expired - Lifetime
- 2003-12-03 CN CNB2003801094472A patent/CN100379930C/en not_active Expired - Fee Related
- 2003-12-03 WO PCT/GB2003/005280 patent/WO2004051018A1/en active IP Right Grant
- 2003-12-03 NZ NZ541054A patent/NZ541054A/en unknown
- 2003-12-03 AU AU2003288420A patent/AU2003288420A1/en not_active Abandoned
-
2005
- 2005-07-01 ZA ZA200505336A patent/ZA200505336B/en unknown
-
2006
- 2006-08-29 HK HK06109578A patent/HK1089217A1/en not_active IP Right Cessation
Non-Patent Citations (1)
Title |
---|
None * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102020002272A1 (en) | 2020-04-14 | 2021-10-14 | Wenker Gmbh & Co. Kg | Hybrid building |
EP3896235A1 (en) | 2020-04-14 | 2021-10-20 | Wenker GmbH & Co. Kg | Hybrid building |
Also Published As
Publication number | Publication date |
---|---|
US20060168901A1 (en) | 2006-08-03 |
DE60314454T2 (en) | 2008-02-21 |
HK1089217A1 (en) | 2006-11-24 |
CN1745222A (en) | 2006-03-08 |
JP4441406B2 (en) | 2010-03-31 |
NZ541054A (en) | 2007-09-28 |
EP1579087A1 (en) | 2005-09-28 |
AU2003288420A1 (en) | 2004-06-23 |
CA2508366C (en) | 2008-02-26 |
CN100379930C (en) | 2008-04-09 |
ATE364760T1 (en) | 2007-07-15 |
ZA200505336B (en) | 2006-10-25 |
CA2508366A1 (en) | 2004-06-17 |
DE60314454D1 (en) | 2007-07-26 |
GB0228173D0 (en) | 2003-01-08 |
JP2006509127A (en) | 2006-03-16 |
WO2004051018A1 (en) | 2004-06-17 |
ES2290523T3 (en) | 2008-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
ZA200505336B (en) | Vertical alignment and levelling of modular building units | |
US8875445B2 (en) | Light weight modular units for staggered stacked building system | |
US3751864A (en) | Interstitial space frame system | |
US6298617B1 (en) | High rise building system using steel wall panels | |
JP5643205B2 (en) | Unit building system | |
US5402608A (en) | Prefabricated built-up building construction | |
EP2417308B1 (en) | Building and method of constructing a building | |
US6651393B2 (en) | Construction system for manufactured housing units | |
US4185423A (en) | Lightweight building module | |
US3304675A (en) | Building constructions | |
US20100058687A1 (en) | Method of constructing a multi-storey building using prefabricated modular panels | |
US8800724B1 (en) | Free standing elevator hoistway | |
US20090249714A1 (en) | Precast concrete modular stairwell tower | |
US20220213684A1 (en) | Modular composite action panel and structural systems using same | |
US5634315A (en) | Buildings method of construction | |
CN116547432A (en) | Building component, building structure formed by building component and construction method of building structure | |
EP0485317B1 (en) | Prefabricated modular construction | |
WO2006095266A1 (en) | Method of constructing structures using prefabricated materials | |
GB2623167A (en) | Kit of parts and method | |
US20040250482A1 (en) | Construction method and appartaus | |
WO2002064900A1 (en) | Modular structure | |
US4137684A (en) | Building panel | |
AU2012238289B2 (en) | Sandwiched panel construction and a method of manufacturing thereof | |
WO2023144554A1 (en) | A building framework and method of constructing the building framework | |
CA2457716A1 (en) | System and method for erecting buildings, and buildings thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 20050704 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PT RO SE SI SK TR |
|
AX | Request for extension of the european patent |
Extension state: AL LT LV MK |
|
DAX | Request for extension of the european patent (deleted) | ||
GRAP | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOSNIGR1 |
|
GRAS | Grant fee paid |
Free format text: ORIGINAL CODE: EPIDOSNIGR3 |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE BG CH CY CZ DE DK EE ES FI FR GB GR HU IE IT LI LU MC NL PT RO SE SI SK TR |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 Ref country code: CH Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D |
|
REF | Corresponds to: |
Ref document number: 60314454 Country of ref document: DE Date of ref document: 20070726 Kind code of ref document: P |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070913 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
NLV1 | Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act | ||
ET | Fr: translation filed | ||
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: BE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 Ref country code: PT Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20071113 Ref country code: BG Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070913 Ref country code: NL Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CZ Payment date: 20070927 Year of fee payment: 5 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: 732E |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2290523 Country of ref document: ES Kind code of ref document: T3 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: TP |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 Ref country code: GR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070914 |
|
26N | No opposition filed |
Effective date: 20080314 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: RO Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20071231 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: EE Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FI Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CY Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20071203 Ref country code: CZ Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20081203 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: TR Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20070613 Ref country code: HU Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT Effective date: 20071214 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 20091229 Year of fee payment: 7 Ref country code: IE Payment date: 20091216 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 20100105 Year of fee payment: 7 Ref country code: GB Payment date: 20091222 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20091224 Year of fee payment: 7 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20091221 Year of fee payment: 7 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20101203 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20110831 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20110103 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20101203 |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 60314454 Country of ref document: DE Effective date: 20110701 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20110701 Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20101203 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20101203 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20120220 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20101204 |