EP1507928B1 - A tubular pile encased in concrete and a pile-driving method - Google Patents

A tubular pile encased in concrete and a pile-driving method Download PDF

Info

Publication number
EP1507928B1
EP1507928B1 EP99961078A EP99961078A EP1507928B1 EP 1507928 B1 EP1507928 B1 EP 1507928B1 EP 99961078 A EP99961078 A EP 99961078A EP 99961078 A EP99961078 A EP 99961078A EP 1507928 B1 EP1507928 B1 EP 1507928B1
Authority
EP
European Patent Office
Prior art keywords
pile
tube
pile tube
ferrule
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
EP99961078A
Other languages
German (de)
English (en)
French (fr)
Other versions
EP1507928A2 (en
Inventor
Jouko Lehtonen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rautaruukki Oyj
Original Assignee
Rautaruukki Oyj
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rautaruukki Oyj filed Critical Rautaruukki Oyj
Publication of EP1507928A2 publication Critical patent/EP1507928A2/en
Application granted granted Critical
Publication of EP1507928B1 publication Critical patent/EP1507928B1/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Definitions

  • the present invention relates to a tubular pile to be encased in concrete, the pile comprising a metal pile tube to be driven into soil; an aperture/apertures in the upper end for feeding liquid concrete to the interior of the pile tube; and in the lower end a downwards tapering pile shoe, the diameter of the upper end of which is bigger than the diameter of the pile pipe, and to the area of which the lower end of the pipe tube opens for making it possible for the said concrete to come out.
  • the invention also relates to a method for driving the tubular pile into soil and encasing it in concrete, the tubular pile comprising a metal pile tube having an aperture/apertures in the upper end and in the lower end a tapering pile shoe the diameter of which is bigger than the diameter of the pile tube, and to the area of which the lower end of the pile tube opens.
  • the bearing capacity of building foundations is known to be improved by using piles driven into soil; in new construction, the piles usually consist of relatively long steel concrete piles and their parts.
  • piles driven into soil in new construction, the piles usually consist of relatively long steel concrete piles and their parts.
  • short and sectional piles are used, due to lack of space, because pile-driving may have to be conducted in small and low spaces inside a building.
  • light impacts or even vibrations are used for driving the piles into soil in order to avoid excessive trembling and to prevent the building around and above from being damaged.
  • an impact piece may be moved up and down inside the pile tube or, alternatively, impacts or vibrations may be directed to the upper end of the pile.
  • the internal volume of a tubular steel pipe is usually filled with concrete after driving the pile into soil.
  • a tubular steel pipe as such is preferable for this purpose, as it is easy to extend, for example, by welding or by using a suitable sleeve joint and, when driven into soil, the pile resistance is smaller than, for example, of a concrete pile, due to the smooth surface of the steel pile. If the pile tip cannot be driven into rock or some other similar well bearing structure, the pile has to act as a friction pile supporting itself to soil layers along the length of the pile. In a situation like this, the bearing capacity of the steel pipe is poor, due to its smooth surface, while the bearing capacity of a concrete pile is substantially better. This is true, for example, in clayey soil, in which the clay layer may be very thick.
  • NO-121440 discloses the injection of stabilizing mass in connection of a foundation pile driven into soil, consisting of otherwise completely conventional steel concrete pile with a concrete surface and a conventional rock tip [cf. for example Swedish standard SIS 911196: 1972-11-20], and of a channel extending through the steel concrete of the pile, through which channel the stabilizing mass is driven into soil near the pile tip.
  • This pile has to be driven into soil in the same way as conventional steel rock piles, and it has no small resistance due to the surface.
  • lime is used for stabilising the soil but, in this case, concrete is used, which probably refers to cement, as in the publication EP-0539 630 .
  • the pile shoe in accordance with the Norwegian publication has an end with a diameter substantially similar to that of the pile tube end and a projecting narrower tip section and, in this thin tip section, channels for injecting the stabilising substance into soil.
  • the object is to stabilise the soil near the tip of the pile and especially below it.
  • a formula is given to the tip length, according to which linear measure L is (R + r) ⁇ 3, i.e. in the picture, about three times the diameter of the tip section and approximately equal to the pile diameter. It is difficult to place the effectively bearing area at the point of the tip, as the area which is to be made bearing has a very limited surface area. Especially if the poorly bearing soil continues below the area containing cement and set at the tip, the meaning of such a set area may be non-existent or even harmful.
  • EP-0 539 630 A1 discloses a manufacturing method for a foundation pile screwed into soil, in which method, upon driving the pile into soil, first a mixture of water and bentonite is fed from the screw tip of the pile at a point in front and, as the screw tip of the pile reaches the bearing soil layer, a mixture of cement and water is fed under high pressure which is higher than hydrostatic pressure, whereafter the screw-like tip of the pile strongly mixes cement and soil.
  • the driving pressure for the cement mixture is very high, even 500 bar - 1000 bar.
  • a bearing zone of a large diameter is formed between the lower part of the pile and the bearing soil.
  • the method is complicated, as it first requires as drilling liquid a mixture of water and bentonite and thus equipment for changing the mass to be driven out of the tip.
  • the method requires large and expensive equipment both for screwing the pile into soil and for generating the said high pressure.
  • machines of this type usually are too large to be used, because they simply cannot fit into room or cellar spaces.
  • Both the solution of NO-121440 and of EP-0 539 630 require the mass to be fed under very high pressure, because the mass is fed into soil below the frontal surface of the tip where the counter pressure of soil is at the highest and the counter pressure has to be exceeded with pumping pressure.
  • the publication US-4 909 673 relates to an injection method according to which the pile tube is provided with a large number of injection apertures, injection valves being attached into there apertures from the inside of the pile so that friction between the pile and soil can be increased by injecting mortar setting to the outer surface of the steel pile.
  • this method requires that high pressures and large machines be used. Further, the structure is much too complicated and expensive to be used in small working projects, such as for increasing the bearing capacity of a single house, etc.
  • a method completely different from the ones described above is disclosed in the publication FI-30911 relating to a manufacturing method of a ram pile encased in concrete.
  • a tubular pile shank provided with a pile shoe with an open upper end and with a larger cross-section in the upper end than the cross-section of the pile shank, is rammed down into soil, and cement gruel or thin concrete is pressed along the hollow pile shank through the pile shoe into a cavity created between soil and the pile shank by action of the pile shoe.
  • liquid cement or concrete is thus pressed from above simultaneously and continuously with ramming into the created soil cavity under low pressure in order to continuously fill the cavity.
  • Publication GB-2 234 774 A describes a method of forming a pile and a method for supporting a building structure.
  • the pile disclosed includes a tubular casing and an enlargement or protrusion near its leading end as well as a plurality of apertures passing through the casing on the side of said protrusion, which apertures are at first closed or sealed off by a rupturable material.
  • a passage is at first formed through the wall and the footing of the building by a separate drilling work, whereafter the pile disclosed is guided through the preformed passage and driven further into the soil until a sufficient depth is reached.
  • the apertures in the casing are closed e.g.
  • GB-A-796262 discloses a tubular pile according to the preamble of claim 1
  • the object of the invention thus is to provide a metal, typically a steel pile, for example, a tubular pile, the outer surface of which, when driven into soil, could be encased in settable mass, such as concrete, without complicated, expensive, and/or large machines so that the bearing capacity of a finished pile with a concrete surface would be at least equal to the bearing capacity of prefabricated concrete piles.
  • Another object of the invention is to provide a metal pile, for example a tubular pile, which requires minimum power when driving it into soil, corresponding at most to the power a straight tubular steel tube requires in soil.
  • the third object of the invention is a metal pile, for example a tubular pile which, when driven into soil, would not tend to progress in a direction which is not in direct line with the intended direction, at least not to a harmful extent. At least in general outline, the pile should remain straight.
  • the fourth object of the invention is a pile of the type described with a simple structure and advantageous manufacturing and operating costs.
  • the fifth object of the invention relates to a method for driving such a metal pile into soil and encasing it in concrete, which can be carried out even in tight places and in different types of soil.
  • Still another object of the invention is to provide such a method which provides, for example, a tubular pile with good bearing capacity in different types of soil.
  • the object of the invention is to provide a pile-driving method and pile combining the easy installability of a tubular steel pile and the good adhesion of a concrete pile in soil.
  • the settable mass travels efficiently and fast through the apertures on the circumference from the interior of the metal pile tube to the cavity created around the pile tube by the ferrule merely by action of the sinking impacts and/or sinking vibrations of the pile so that it is not necessary to use pressure for feeding the hardening mass at the upper end of the pile tube above the ground surface, but the mass may simply be poured inside the pile tube.
  • the force required by the tubular pile for driving it into soil is small, and the bearing capacity of the finished tubular pile encased in and filled with concrete is excellent when it acts as friction pile either over its entire length or over a predetermined part of its length.
  • an advantage of the invention is that it is not necessary to arrange complicated means to the upper end of the pile tube for making it possible to simultaneously feed the settable mass and make the sinking impacts or vibrations as, in accordance with the invention, the stages are carried out separately.
  • the improved pile structure and installation method of the invention are excellently suited for the repair of building foundations, but the invention is not limited to this application.
  • the invention may be used in piles that are driven into soil both by driving and vibration.
  • the invention relates to a tubular pile 40 to be encased in concrete, the shank comprising a pile tube generally referred to with the reference number 2. Only when it is necessary to separate the various parts or sections of the pile tube from each other, more individual reference numbers 2a, 2b, 2c, etc. are used.
  • the general reference number 2 refers to these all.
  • the tubular pile 40 comprises a metal pile tube 2, usually of tubular steel material, to be driven or pushed into soil which may, in a way described below, consist of one or several pile sections 2a, 2b, 2c, etc.
  • the concepts “lower end”, “downwards”, “down”, etc. refer to the direction to which the pile sinks, or to the position in the direction to which the end is driven; and, correspondingly, the concepts “upper end”, “upwards”, “up”, etc., refer to the position of the pile end remaining above the ground or pointing outwards from the ground surface.
  • piles 40 are driven into soil in a vertical or close to a vertical position, as is shown in Figs 1A - 3 , so that the directions and sides explained above are self-evident, but they have to be understood in the way defined even if the centre line 31 of the pile formed an angle deviating considerably from the right angle to the horizontal level or to the level describing the ground surface 20; the deviation may be dozens of degrees of angle.
  • the cross-section of the pile tube 2 typically consists of conventional circular steel tube but, naturally, also a tube with a different cross-section, such as square, diamond-shaped, or rectangular, may be used.
  • the outer diameter D2 of the pile tube may be, irrespective of the cross-sectional shape, for example, 25 mm - 1500 mm, preferably between at least 40 mm and at most 300 mm, and typically between at least 50 mm and at most 200 mm.
  • the wall thickness of the pile tube 2 may be 1 mm - 20 mm, depending on the outer diameter of the pile tube, preferably at least 3 mm and at most 15 mm, and typically at least 5 mm and at most 12 mm.
  • the inner diameter of the pile tube naturally is smaller than the outer diameter by a measure corresponding to the wall thickness, and it forms the interior 12 of the pile tube, along which the concrete mass B passes from the upper end 29 to flow apertures 7.
  • the lengths of pile sections 2a, 2b, 2c, etc., of the pile tube 2 to be connected to each other are smaller than the height of the space, inside which the tubular pile 40 is driven into soil so that the lengths L2 of the pipe sections 2a, 2b, 2c., etc., often are at least 0.5 m and at most 3 m, typically 1 m - 2.5 m. If there is enough space, it naturally is possible to use also longer pile sections, e.g. 6 m or even longer.
  • the outer surface of the pile tube 2 is provided with adhesions 30, such as tack-welded pieces of steel strip or otherwise manufactures shapes, in order to improve the reciprocal adhesion between the settable concrete B and the pile tube.
  • adhesions 30 such as tack-welded pieces of steel strip or otherwise manufactures shapes, in order to improve the reciprocal adhesion between the settable concrete B and the pile tube.
  • the upper end of the pile tube 2 of the tubular pipe 40 remaining above the ground surface 32 or at last near the ground surface 32 and thus pointing towards external space includes an aperture or apertures 29 for feeding liquid concrete mass into the interior 12 of the pile tube.
  • the aperture 29 of the pile tube 2 is only an open tube end, into which the liquid concrete mass is poured, as is shown in Figs 1B, 1D and 1G .
  • the upper end of the pile tube may be provided with an aperture or apertures 29 either on the circumference of the tube and/or on a driving base which is possibly used at the upper end of the tube and used for transmitting force F driving the pile into soil, and which is not shown in the figures.
  • Such a driving base may consist, for example, of connection pieces 21 for the tube sections or of some other kind of pieces attachable to and releasable from the pile tube end, protecting the pile tube end from damage and deformation and distributing the force F directed to it in a desired way to the pile tube, with which force the tubular pile 40 is driven into soil.
  • a downwards tapering pile shoe 1 according to the invention and with a large outer diameter D 1 is provided at the lower end of the tubular pile 40; the pile tube and especially its interior 12 open to the area of the pile shoe 1 in order to make it possible for the concrete mass B to come out.
  • the pile shoe 1 of the invention comprises a longitudinal tip section 3 having a substantially uniform broadness, i.e. outer transverse dimensions along the length thereof, a tool tip 10 at the lower end, and a ferrule 6 at the upper end, the maximum diameter D1 of which is substantially larger than the outer diameter D2 of the pile tube.
  • the maximum diameter D1 of the ferrule forms a soil cavity M or a space T around the pile tube for the concrete B.
  • a desired layer thickness on the pile tube surface typically is at least 5 mm and at most 200 mm, generally at least 15 mm and at most 100 mm, preferably 30 mm - 50 mm.
  • the difference W between the maximum diameter D1 of the pile shoe and the outer diameter D2 of the pile tube is, as determined above, at least 10 mm - 400 mm, etc. It has to be noted that with the tubular pile of the invention, when using a pile shoe of the invention and following the method of the invention, the difference between the diameters of the pile shoe and the pile tube, etc., i.e. the thickness W in direction of the radius and the nominal thickness W B of the concrete layer are not exactly equal in real soil M, due to various reasons.
  • the nominal thickness W B of this concrete layer surrounding the steel pile tube, and thus the maximum diameter D1 creating the ferrule, may also be proportioned to the outer diameter D2 of the pile tube by arranging the maximum diameter D 1 about 1 - 4 times or preferably 1.5 - 2.5 times the outer diameter D2 of the pile tube. It has to be understood that if the cross-sectional shapes of the pile tube 2 and the ferrule 6 are different from each other, as is the case in the embodiment of Figs 5A and 5B and in the embodiment of Figs 6A and 6B , the derived thickness W and the nominal thickness W B of the concrete vary on different sides of the pile.
  • the real thickness W B of the concrete layer varies in the longitudinal direction of the pile, i.e. in the direction of the centre line 31, as is shown in Figs 1A - 3 .
  • the ferrule of the invention may be substantially cylindrical in the direction of the centre line of the pile, as in Fig. 6A .
  • the ferrule 6 of the invention has an outer surface 8 which at least in part narrows or tapers towards the tool tip 10, as is clearly shown in Figs 4A , 5A and 7 .
  • This outer surface may thus be in form of a truncated cone or a pyramid, or have otherwise tapering shape so that the side line in longitudinal sections through the pile centre line 31 corresponding to Figs 4A , 5A , 6A and 7 may be a straight line, a convex or concave curve, a step line with acute or rounded angles, or some other kind of line.
  • the truncated cone or pyramid is preferable in accordance with the invention, as with it the soil layer limited to the space or cavity T created around the pile tube 2 of the tubular pile 40 becomes compact in a more efficient way and, supposedly, with a lower force F driving the pile into soil, than if the side line did not form a substantially tapering form in the ferrule towards the tool tip.
  • the embodiments in Figs 4A , 5A and 7 are more preferable than the embodiment in Fig. 6 .
  • the cross-sectional shape of the ferrule against the centre line 31 of the pile may vary within extensive limits in the longitudinal section.
  • the cross-section may be oval or round, as in Fig.
  • the cross-sectional shape of the pile shoe 1 does not necessarily have to be identical with the cross-sectional shape of the pile tube 2.
  • the maximum diameter D 1 of the pile shoe has to fulfil the conditions determined above at every place on the circumference of the pile shoe.
  • both the maximum diameters D1 differing from each other have to be substantially larger than the outer diameter of the pile tube.
  • this tapering shape of the ferrule 6 is a separate feature independent of the tapering end shape of the pile shoe 1.
  • the distance L1 at the point R corresponding to the maximum diameter D1 of the ferrule 6 from said tool tip 10 is at least five times the outer diameter D2 of the pile so that a tip section 3 with principally uniform or linear outer dimensions over its length is arranged between the ferrule and the tool tip 10.
  • the tip section 3 between the tool tip and the ferrule and extending downwards from the ferrule 6, which tip section is not encased in concrete during driving of the tubular pile 40 into soil guides the entire tubular pile to go straight as it supports itself e.g. during the pile impacts and vibrations to soil M tightly surrounding the pile shoe 1 and, especially, the tip section 3.
  • a still more efficient guidance for the pile tube 2 and its tube sections 2a, 2b, etc. is achieved by arranging the distance L1 between the point R corresponding to the maximum diameter of the ferrule and the tool tip, i.e. the length of the tip section and a portion of the ferrule, so long that it is at least seven, and preferably ten times the outer diameter D2 of the pile tube.
  • the length L3 of the narrowing or tapering outer surface 8 of the ferrule 6 is at most 40% and typically under 30% of the length L1 between the point R of the maximum diameter of the ferrule and the tool tip 10.
  • the exemplary distance L1 is between 30 cm - 1 m, generally 0.5 m, or more.
  • the cross-sectional shape of the tip section 3 may vary within extensive limits, so it can be round, oval, angular, star shaped, a shape equipped with web, etc., but preferably it is a shape which is symmetrical in relation to one or several longitudinal planes passing through the centre line 31.
  • the tip section 3 may comprise a metal bar and metal tube made of solid material.
  • the said tip section 3 consists of, for example, section 2' of the pile tube 2, as in Fig. 7 ; or of a tube piece 11 fastened to the ferrule 6, as in Fig. 6A ; or of a portion 17 of a connection part 4 explained in more detail later; or of a bar piece 18 attached to a recess in the ferrule 6.
  • the actual pile tube 2 thus passes through the aperture 16 in the ferrule, the part 2' extending below the ferrule forming the tip section.
  • the ferrule is attached to the pile tube, and thus to the tip section, by welds forming the connection elements 15a.
  • the ferrule may naturally be attached also by rivets, screws or bolts passing through the ferrule and pile tube, or by other fastening means.
  • the tube section 11 has been pushed downwards of the ferrule 6 onto a projecting pin 33 and, when necessary, welded to the ferrule by using welds forming the connection elements 15a.
  • Fig. 6A the tube section 11 has been pushed downwards of the ferrule 6 onto a projecting pin 33 and, when necessary, welded to the ferrule by using welds forming the connection elements 15a.
  • the bar piece 18 has been pushed into the cavity 34 in the ferrule and, when necessary, welded to the ferrule by using welds forming the connection elements 15a. If the tube piece sits tightly enough on the pin 33, or if the bar piece fits tightly enough into the cavity 34, welding is not needed.
  • the outer diameter D3 of the tip section preferably is at most equal to the outer diameter D2 of the pile tube, but in some cases, a broader tip section 3 may be used, the outer diameter D3 of which however being substantially smaller than the maximum diameter D1 of the ferrule.
  • the outer diameter D3 of the tip section thus is smaller than the diameter of the pile tube, and the principal outer diameter of the tip section 3 varies in its length at most 30% of the difference between the diameters [D1 - D3] of the tip section and the ferrule, but usually at most 10% of the said difference.
  • the principal diameter is derived from a shape, which is given by a combination of those tip section portions forming over half of the cross-sectional circumference of the tip section.
  • the tip section has to be seen as having a substantially uniform broadness, although it contained support flanges 35 extending in the direction of the centre line 31, as is shown in broken lines in Fig. 6A , or other similar parts which cover typically only a fraction of the circumfrence of the tip section, and/or the tip section 9 contained a slightly extended part 36, as in Fig. 6A .
  • the pile shoe 1 further includes flow apertures 7 above the lowermost upwards free base 24 of the ferrule 6 surrounding the pile tube or its extension and passing through the circumferential surface 13, 22, 23 of the said pile shoe 1 and/or pile tube 2 and/or pile tube extension for the outflow of the concrete mass B.
  • the upwards free base refers to a surface transverse to the centre line of the pile, which is outside the outer diameter D2 of the pile tube 2 and the area of which is not limited by the cross-sectional area of the pile tube.
  • the flow apertures 7 are permanently open from the interior 12 of the pile tube to the exterior of the pile tube in radial directions.
  • the ferrule may comprise a principally flat upwards free base 24, as in Fig.
  • the ferrule 6 includes an upwards lifted outer edge 25, forming an upwards open recess 5 surrounding the pile tube 2 or its extension, such as the connection part 4.
  • the upwards open free base 24 consists of the base of the recess 5, as in Figs 4A , 5A and 7 , the base 24 then joining the said circumferential surface 13, 22, 23 and the ferrule or its upwards lifted outer edge 25 outside the flow apertures 7.
  • the base 24 is planar, but is may also be of some other shape. Radial flow apertures may be round or elongated, as can be seen in the figures, and they are generally equally spaced on the said circumferential surface.
  • the number of flow apertures is at least two, but most often there are three - five apertures approximately in the same height. If flow apertures 7 are arranged in several heights for extending the neck between the apertures, as in Figs 5A and 7 , the total number of the apertures may be bigger.
  • the added cross-sectional area of the flow apertures is smaller than the cross-sectional area of the interior 12 of the pile tube, so that it may be under 90%, under 70%, under 50%, or even about 30% of the cross-sectional area of the pile tube interior 12.
  • a diameter of the apertures may be, for example, 10 mm - 100 mm.
  • the internal outer diameter D5 of the ferrule recess 5 is substantially bigger than the upper diameter D4 of the next connection part, or the outer diameter D2 of the pile tube so that the thickness of the upwards lifted ferrule edge 25 would be small.
  • the flow apertures 7 are at least partly arranged on the plane of the outer edge 25 of the ferrule, or on the measure of the height H1 for the recess 5.
  • the recess height H1 here refers to the distance between the base 24 and the upwards lifted edge 25.
  • connection part 4 extending from above the ferrule to below, with which the ferrule 6 is joined to the pile tube 2, as is shown in Fig. 4A .
  • the outer upper diameter D4 of the upper part of the connection part is bigger than the outer lower diameter D3.
  • the difference between the diameters form a downwards pointing stop face to the connection part.
  • the ferrule again, is provided with a straight-through aperture 16 for the passing through of the connection element.
  • the stop face 14 of the connection element the upper diameter D4 of which is bigger than the diameter D6 of the ferrule aperture 16, supports itself to the base 15 of the ferrule.
  • connection part 4 comprises in its upper part an internal depression 26a for receiving the lower end of the pile tube 2 and a channel 27 which extends from the pile tube interior 12 at least to the flow apertures 7, the flow cross-section of the channel 27 preferably corresponding to the flow cross-section of the interior 12.
  • the connection part 4 consists either of the same piece as the tip section 3, as is shown in Fig. 4A or, alternatively, of a tip section and a stopping piece attached to each other.
  • the connection part may alternatively be provided with an outer recess or projection for the fastening of the pile tube in a similar way as has been done in Fig. 5A using the ferrule 6.
  • the pile tube 2 may be attached either to the ferrule 6 and the tip section 3 by using the connection part 4, as described above, or directly to the ferrule.
  • the ferrule comprises a thorough hole 16, the diameter D6 of which corresponds to the outer diameter D3 of the tip section, which in this case is equal to the outer diameter D2 of the pile tube, for passing through of the pile tube.
  • the ferrule 6 comprises an upwards pointing projection 19, the outer diameter D8 of which has been adapted to receive the end of the pile tube 2.
  • a circumferential depression 26b may be formed to the transition point of the said projection 19 and the base 24 of the recess 5 for ensuring that the pile tube end remains stable, for example, against bending forces in a similar way that has been described in the applicant's previous patent FI-81415 .
  • the ferrule is provided with an upwards pointing projection 19 with a circumferential depression 26a, the inner diameter D7 of which is adapted to receive the end of the pile tube 2.
  • the ferrule 6 includes a channel 27, extending from the interior 12 of the pile tube at least to the flow apertures 7.
  • the ferrule 6 or connection part 4 described above further comprise either first connection elements 15a, such as welds between the ferrule or the connection part and the pile tube; or second connection elements 15b, such as screws, rivets or bolts passing through the ferrule or connection part and the pile tube; or third connection elements 15c, such as the crimp connection described in the previous patent FI-81415 or some other kind of crimp connection, or a transverse grooving for adhesion between the pile tube 2 and the ferrule 6 or connection part 4.
  • the crimp connection of the said patent may be applied by using a male counterpart for the pile tube, as in the said publication, or a reversed structure in which there is provided a female counterpart for the end of the pile tube 2.
  • the threaded connection of Fig. 8A may be used for attaching the end of the pile tube 2 to the ferrule 6 or connection part 4 by applying it at this point between the ferrule or connection part and the pile tube.
  • the pile tube 2 consists of several tube sections 2a, 2b, 2c, etc.
  • the tube sections are connected to each other, for example, by connection pieces 21 or connections 20.
  • the connection pieces may comprise sleeves in accordance with Figs 8A and 8B , into which the tube sections of the pile tube project.
  • such a connection may be secured by screws or rivets 38 between the connection piece and the tube section, as in Fig. 8A , or by a weld between the sleeve-like connection piece and tube sections, or by a corresponding crimp connection as in the applicant's patent FI-81415 , except that a female counterpart i.e. a sleeve-like connection is used, as in Fig.
  • connection 21 again consists of a weld between the ends of the tube sections 2a and 2b, 2b and 2c, etc., as in Fig. 8C . It is in itself possible to also use a male counterpart which projects inside the tube sections, but it has the slight disadvantage that the cross-sectional area of the pile tube interior 12 becomes smaller at their point.
  • a pile shoe of the invention is assembled of its possible elements using necessary measures on the pile-driving site or alternatively at the manufacturing factory, and next the pile shoe 1 is attached to the lower end of the pile tube 2, which is to be driven into soil, so that a usable tubular pile 40 is achieved, in which the flow apertures 7 for the concrete mass B are initially open, i.e. they are not closed so that an undisturbed flow is made possible for the concrete mass from the beginning of the pile driving without it being necessary to feed the concrete under pressure.
  • the tubular pile is placed to the desired point and position in relation to soil M and its surface 32, and then the tubular pile is driven into soil M in accordance with Fig. 1 using a pulsating force or some other corresponding force F having a frequence.
  • the device, with which force F is generated either as impacts or vibrations has not been shown in the figures, because it may be of any appropriate type.
  • the pile tube interior 12 is filled with liquid mortar, i.e. concrete mass B consisting of hydraulically settable binding agent, stone material as filler, as well as water and possible additives or the like.
  • the hydraulically settable binding agent most often used is cement, but also furnace slag, other corresponding binding agent or a combination of these may be used.
  • the pile tube is driven deeper into soil M by the said pulsating force F in accordance with Fig. 1C so that the concrete mass flows in the direction of the flows marked in the figure as the fluidity of the concrete mass increases from the initially open flow apertures 7 in the interior of the pile tube 2 around it and perhaps to some extent upwards to a cavity T made in the soil by the pile shoe 1.
  • the pulsating force F increases the fluidity or consistency of the concrete mass, i.e. the concrete mass reacts to such a handling in the same manner as thixotropic materials.
  • This flow from the interior 12 to the cavity T is apparently made more effective by an underpressure generated by a downwards advancing movement in the cavity T as well as that the flow V of the concrete mass B from the pile tube interior to the cavity T requires totally or partly a change of direction of only about 90°, as in Figs 5A , 6A and 7 , and/or a change of direction in a flat radius of about [D1 - D2]/2, as in Figs 4A , 5A and 7 .
  • the first tube section 2a After the first tube section 2a has been driven into soil at least in part, i.e. generally in most part, the first tube section 2a is extended with the second tube section 2b by using the above described connections 20 or connection pieces 21 for creating an extension in accordance with Fig. 1F .
  • the pile tube 2 is then further extended with new tube sections 2c, 2d, 2e, etc., and the said concrete mass B is alternately added at least in part into the pile tube interior 12, and the pile tube is driven deeper into soil by the pulsating force F, as is shown in Figs 1G and 1H , respectively. These stages are carried on until the tip section 2 of the tubular pile reaches the intended depth S 1 in soil M.
  • the liquid concrete mass B is added continuously as the tubular pile 40 is driven into soil and, when necessary, the final filling of the pile tube is carried out; after this the concrete mass B is let to set both around the pile tube and in the interior 12 of the pile tube 2.
  • the result is a finished tubular concrete pile in accordance with Fig. 2 .
  • the tubular pile 40 is first driven into soil M by the pulsating force F without the concrete mass B being fed into the pile tube interior until the tubular pile 40 has reached a certain depth S2, whereafter a part, such as one part of concrete is fed into the pile tube interior 12, and the short driving of the pile tube is carried out by the force F.
  • This short driving into soil corresponds, for example, to the cavity length T the amount of concrete mass in the pile tube is able to fill.
  • two or more fillings of the tubular pile and two or more driving stages with force F may be conducted, which also means said short driving of the tubular pile into ground, although respectively a longer length of cavity T.
  • the part between the ground surface and the upper side of a block thus created from the concrete mass to the cavity is filled around the tubular pile with stone material G, such as sand, gravel, or some other similar material.
  • the pile tube interior 12 is further filled with concrete B and the tubular pile is alternately driven further into soil M by force F, as is described above.
  • Concrete mass is thus fed into the pile tube interior without substantial overpressure, and the said pulsating or similar force F is generated by impacts and/or vibrations, and its maximum is such that a pressure impulse occurs in the pile tube interior which, according to present views, is at least 10 bar and preferably at least 15 bar, and the duration of which is at most 50 ms, generally 0.1 ms - 15 ms, typically 0.1 - 10 ms, and preferably as short as possible, such as under 5 ms.
  • the pulsating force thus generates a pressure impulse of short duration injecting mortar or concrete mass, the size of which in a test installation has been measured to be 20 - 50 bar or close to that value.
  • the level of the concrete mass B in the cavity T does not substantially rise during pile-driving, but remains principally on the same level within the variation limits caused by the alternation of the adding of mortar or concrete mass and the driving of the tubular pile into soil.
  • the adding of cemetitious mass B and the driving of the pile tube into the soil may be performed simultaneously, but this practice requires special arrangements for the aperture/apertures 29 at the upper end of the pile tube.
  • the time difference between adding/feeding the concrete mass B and subjecting the driving force F to the pile can be greatly varied from practically zero to consirebly longer time.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Rod-Shaped Construction Members (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
EP99961078A 1998-12-14 1999-12-13 A tubular pile encased in concrete and a pile-driving method Expired - Lifetime EP1507928B1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
FI982699A FI111405B (fi) 1998-12-14 1998-12-14 Betonilla ympäröity putkipaalu ja paalutusmenetelmä
FI982699 1998-12-14
PCT/FI1999/001027 WO2000036226A2 (en) 1998-12-14 1999-12-13 A tubular pile encased in concrete and a method for driving the tubular pile into the soil and encasing it in concrete

Publications (2)

Publication Number Publication Date
EP1507928A2 EP1507928A2 (en) 2005-02-23
EP1507928B1 true EP1507928B1 (en) 2008-03-26

Family

ID=8553105

Family Applications (1)

Application Number Title Priority Date Filing Date
EP99961078A Expired - Lifetime EP1507928B1 (en) 1998-12-14 1999-12-13 A tubular pile encased in concrete and a pile-driving method

Country Status (11)

Country Link
EP (1) EP1507928B1 (ru)
AT (1) ATE390521T1 (ru)
AU (1) AU1781600A (ru)
DE (1) DE69938438T2 (ru)
DK (1) DK1507928T3 (ru)
EE (1) EE04970B1 (ru)
FI (1) FI111405B (ru)
NO (1) NO20012890L (ru)
PL (1) PL204637B1 (ru)
RU (1) RU2236505C2 (ru)
WO (1) WO2000036226A2 (ru)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2024574B1 (en) * 2006-05-30 2009-10-14 Turun Ammattikorkeakoulu Method for forming a sheet pile structure, sheet pile element, sheet pile structure and use of a sheet pile structure for damping vibration
RU2492294C1 (ru) * 2011-12-27 2013-09-10 Открытое акционерное общество "Волгомост" Трубобетонная свая с усиленным основанием и способ ее сооружения
RU2543397C1 (ru) * 2013-10-08 2015-02-27 Михаил Федорович Егоров Металлическая опора и способ ее возведения
WO2019169180A1 (en) * 2018-02-28 2019-09-06 Aptim Intellectual Property Holdings, Llc Pressure grouted displacement screw piles
CN109881670B (zh) * 2019-03-26 2024-02-02 中国石油大学(北京) 一种海底自弃可回收的自升式钻井平台桩靴和钻井平台
CN110468830B (zh) * 2019-09-10 2024-07-02 河海大学 一种快速锚锭桩及施工方法
CN113969578A (zh) * 2021-12-13 2022-01-25 广州市番禺大石建筑工程有限公司 分段式基础桩及其施工方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB796262A (en) * 1956-10-05 1958-06-11 Mueller Ludwig Improvements in or relating to piles
DE1634470A1 (de) * 1965-11-04 1970-10-29 Mueller Ludwig Gruendungspfahl
BE794280A (fr) * 1972-06-05 1973-05-16 Mazzalai Quirino Dispositif pour realiser des fondations sur pieux executes dans le sol
DE3131559A1 (de) * 1981-08-08 1983-05-05 Brown, Boveri & Cie Ag, 6800 Mannheim "verfahren zur herstellung von ortbetonpfaehlen"
GB2234774B (en) * 1989-08-12 1994-01-12 Roxbury Ltd Improvements in or relating to piling methods

Also Published As

Publication number Publication date
ATE390521T1 (de) 2008-04-15
FI982699A0 (fi) 1998-12-14
PL365835A1 (en) 2005-01-10
EP1507928A2 (en) 2005-02-23
DE69938438T2 (de) 2009-04-09
PL204637B1 (pl) 2010-01-29
NO20012890D0 (no) 2001-06-12
FI982699A (fi) 2000-06-15
WO2000036226A2 (en) 2000-06-22
EE04970B1 (et) 2008-02-15
WO2000036226A3 (en) 2004-11-18
FI111405B (fi) 2003-07-15
AU1781600A (en) 2000-07-03
NO20012890L (no) 2001-06-12
EE200100272A (et) 2002-10-15
DE69938438D1 (de) 2008-05-08
RU2236505C2 (ru) 2004-09-20
DK1507928T3 (da) 2008-07-21

Similar Documents

Publication Publication Date Title
US6732483B1 (en) Modular plastic pile systems and methods
US5707180A (en) Method and apparatus for forming piles in-situ
US7070362B2 (en) Reinforcement unit for a reinforcing a footing element when laying pile foundations with a pile, and method for placing a foundation pile and reinforcement of a footing element
EP0022844B1 (en) Method for the formation of a soil and water-retaining wall, soil and water-retaining wall formed in accordance with this method and forming mould for the formation of this soil and water-retaining wall
EP1507928B1 (en) A tubular pile encased in concrete and a pile-driving method
US5145291A (en) Method for forming a piling beneath a structure
JP3854850B2 (ja) 連結鋼管矢板とそれを用いた鋼管連結構造および鋼管矢板壁およびソイルセメント連続壁
JP2003119775A (ja) 基礎杭構造
WO2002016701A1 (en) Reinforcement structure for a foundation pile
CN207160041U (zh) 锚杆式人工挖孔桩
US6554544B1 (en) Method to build a water seal, creep-line increasing cutoff
TWI790741B (zh) 擋土牆及其建造方法
JPH09111758A (ja) 場所打ちコンクリート杭およびその施工法
RU72986U1 (ru) Свая
JP2003027462A (ja) 地中連続壁の構築方法及び地下構造物の構築方法
JP5360657B2 (ja) プレキャストコンクリート部材による擁壁
KR102603493B1 (ko) 건축기초로 이용되는 캡모듈을 포함하는 주열식 벽체
JP3784340B2 (ja) 杭基礎
JPH0257163B2 (ru)
JP4414325B2 (ja) 連結鋼管山留工法
GB2255990A (en) Underpinning buildings
KR20190109883A (ko) 흙막이 벽체용 고강도 phc 파일
JP2003049425A (ja) ソイルセメント合成継杭
JP5360658B2 (ja) プレキャストコンクリート部材による擁壁
JP2002371550A (ja) ソイルセメント合成既製杭の施工方法

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 20010319

AK Designated contracting states

Kind code of ref document: A2

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

AX Request for extension of the european patent

Extension state: AL LT LV MK RO SI

GRAP Despatch of communication of intention to grant a patent

Free format text: ORIGINAL CODE: EPIDOSNIGR1

RAX Requested extension states of the european patent have changed

Extension state: LV

Payment date: 20010316

Extension state: LT

Payment date: 20010316

GRAS Grant fee paid

Free format text: ORIGINAL CODE: EPIDOSNIGR3

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH CY DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE

AX Request for extension of the european patent

Extension state: LT LV

REG Reference to a national code

Ref country code: GB

Ref legal event code: FG4D

REG Reference to a national code

Ref country code: IE

Ref legal event code: FG4D

Ref country code: CH

Ref legal event code: EP

REF Corresponds to:

Ref document number: 69938438

Country of ref document: DE

Date of ref document: 20080508

Kind code of ref document: P

REG Reference to a national code

Ref country code: SE

Ref legal event code: TRGR

REG Reference to a national code

Ref country code: DK

Ref legal event code: T3

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080326

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080326

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: BE

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080326

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: PT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080901

Ref country code: ES

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080707

EN Fr: translation not filed
PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed

Effective date: 20081230

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: FR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20090116

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: MC

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081231

REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

GBPC Gb: european patent ceased through non-payment of renewal fee

Effective date: 20081213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080326

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: CY

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080326

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081231

Ref country code: IE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081215

Ref country code: CH

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081231

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20081213

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GR

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 20080627

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DK

Payment date: 20121228

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20130102

Year of fee payment: 14

Ref country code: DE

Payment date: 20121231

Year of fee payment: 14

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: NL

Payment date: 20121225

Year of fee payment: 14

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 69938438

Country of ref document: DE

REG Reference to a national code

Ref country code: DK

Ref legal event code: EBP

Effective date: 20131231

REG Reference to a national code

Ref country code: NL

Ref legal event code: V1

Effective date: 20140701

REG Reference to a national code

Ref country code: LT

Ref legal event code: MM9D

Effective date: 20131213

REG Reference to a national code

Ref country code: SE

Ref legal event code: EUG

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: SE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20131214

REG Reference to a national code

Ref country code: DE

Ref legal event code: R119

Ref document number: 69938438

Country of ref document: DE

Effective date: 20140701

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140701

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20140701

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DK

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20131231