EP1009951B1 - Procede de conduite d'une chaudiere a circulation forcee et chaudiere pour sa mise en oeuvre - Google Patents
Procede de conduite d'une chaudiere a circulation forcee et chaudiere pour sa mise en oeuvre Download PDFInfo
- Publication number
- EP1009951B1 EP1009951B1 EP97938700A EP97938700A EP1009951B1 EP 1009951 B1 EP1009951 B1 EP 1009951B1 EP 97938700 A EP97938700 A EP 97938700A EP 97938700 A EP97938700 A EP 97938700A EP 1009951 B1 EP1009951 B1 EP 1009951B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- outlet
- water
- fluid
- heat exchanger
- steam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B29/00—Steam boilers of forced-flow type
- F22B29/06—Steam boilers of forced-flow type of once-through type, i.e. built-up from tubes receiving water at one end and delivering superheated steam at the other end of the tubes
- F22B29/12—Steam boilers of forced-flow type of once-through type, i.e. built-up from tubes receiving water at one end and delivering superheated steam at the other end of the tubes operating with superimposed recirculation during starting and low-load periods, e.g. composite boilers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B35/00—Control systems for steam boilers
- F22B35/06—Control systems for steam boilers for steam boilers of forced-flow type
- F22B35/14—Control systems for steam boilers for steam boilers of forced-flow type during the starting-up periods, i.e. during the periods between the lighting of the furnaces and the attainment of the normal operating temperature of the steam boilers
Definitions
- the present invention relates to a method for driving a forced circulation boiler, in particular for a steam turbine, said boiler comprising at least a first heat exchanger heat whose input is connected to a water supply pipe and whose output is connected, through an adjustment valve, either to the input of a second heat exchanger, the output of which is connected to the steam turbine, either directly to the steam turbine.
- the invention also relates to a boiler for the implementation of this process.
- the invention without being limited thereto, relates more particularly to boilers supplying steam turbines used in thermal power plants for electricity production. These plants have, in fact, a boiler producing steam under pressure that drives a steam turbine driving a generator electricity.
- the boiler can be heated by a burner which burns a fossil fuel or fuel from industry.
- Boiler can also be a recovery boiler used in a so-called combined cycle thermal power plant.
- a fuel for example natural gas or fuel oil
- gas turbine driving an electricity generator.
- Gas exhaust of this gas turbine large in volume and rich in heat energy, are recovered in a boiler called recovery to produce pressurized steam which entrains, by means of a steam turbine, an electricity generator.
- the pressurized steam produced in the boiler instead to operate a turbine, can optionally be used to other needs.
- boilers always include heat exchangers operating as an evaporator (water) or a superheater (water steam) arranged horizontally or vertically in a flow of hot gases. Depending on their type of heating, their arrangement, their operating principle, etc ..., we can distinguish several types of boilers.
- the document DE 4303613 A1 describes a boiler with forced circulation including a steam-water separator liquid which, during start-up and when running stabilized boiler separates steam from fluid two-phase leaving the evaporator to drain the latter via a superheater to the turbine.
- Document JP-02016119 describes a boiler with "once through” forced circulation which includes using a separation flask to separate the vapor phase and water-liquid phase of the mixture biphasic leaving the evaporator of the boiler during from the start of the installation. Depending on the pressure reached by steam, it is either recondensed, either drained to the turbine.
- document US-3,135,096 describes a "once through" forced circulation boiler which includes two vapor-liquid separators where water and vapor are separated by gravity.
- a first separator (not shown) is placed after the evaporator to recirculate the unvaporized water via a blender the inlet of the evaporator and to drain the other fraction of the fluid to the boiler superheater.
- the second vapor-water / liquid separator is mounted in bypass with respect to the turbines of the installation, and in principle, is only used during from the start of the installation. This separator separates the liquid phase (water) and vapor phase of the fluid two-phase output from the superheater.
- the liquid phase (water) is drained to a condenser and the vapor phase is drained by means of three pressure regulators and controllers either towards a deaerator, either via a heat exchanger to this deaerator or to a condenser before return to the boiler economizer input.
- the water runs through the first part of the interchange until separator, where water and steam are separated by gravity. Water is drained from the separator to a condenser or other tank, while steam travels the second part of the exchanger to undergo a overheated. During this start-up phase, the separator is said to be in wet operation.
- the separator receives less in less water and at the end of the start-up phase, it only receives steam and becomes an element inert. It is then said in dry operation and the will remain during stabilized walking.
- the separator is a tank subjected to high pressure and high temperature. It is therefore a expensive element which, moreover, introduces constraints operating due to large wall thicknesses put into play. In stabilized operation, not only is a superfluous element, but it also causes pressure losses on the water / steam side, altering the installation performance.
- the object of the present invention is to provide a new process for operating a boiler forced circulation as well as a boiler for the implementation of the process allowing the removal of the separator.
- the present invention provides a process for operating a forced circulation boiler of the type described in the preamble which is characterized in that during the start-up phase, the regulating valve to the 2nd exchanger or the turbine is closed, in that, as long as the fluid at the output of the first exchanger is a two-phase fluid consisting of a mixture of water and steam, we transform, by condensation, all water vapor and in that when the fluid at the outlet of the first evaporator is pure steam, we gradually open the valve adjustment.
- Condensation of steam at the outlet of the first evaporator is carried out by mixing the two-phase fluid with water Power.
- the condensed water thus obtained is sent to the condenser and is thus recycled.
- the method according to the present invention makes it possible to eliminate the separator since there is no longer any separation between the vapor and water. According to the invention, as long as one is not in the presence of pure steam, all the steam is transformed into water and the passage of the mixture in the second exchanger or in the turbine.
- the control elements such as regulators thus always work in liquid medium.
- the removal of the separator or starter tank in addition to lower investment costs, eliminates thermal gradient constraints associated therewith.
- the process according to the invention also allows faster starting of the boiler and reduced pressure drop on the water / steam side in stabilized operation.
- the invention also provides a forced circulation boiler, in particular for a steam turbine, comprising at least a first heat exchanger, the inlet of which is connected to a pipe water supply and whose outlet is connected through a first regulating valve to a steam turbine, either directly, either through a second heat exchanger, characterized in that the outlet of the first exchanger is connected through a second valve adjustment at the supply line and through a valve expansion to a condensing device and in that the second valve adjustment is controlled by the temperature of the fluid upstream of the expansion valve so that during the startup, this temperature remains below the temperature of saturation.
- the boiler shown schematically in the figure is a recovery boiler placed downstream of a gas turbine in a combined cycle power plant. With a few transformations, it could however work with a burner.
- the boiler consists of two heat exchangers in series, namely an evaporator 10 producing, in steady operation, slightly overheated steam and final superheater 12 intended to heat the steam produced by the evaporator 10 at the desired temperature.
- the two exchangers 10 and 12 consist, in a conventional manner, of tubes, with or without fins, arranged here horizontally in an upward flow of gas hot symbolized by arrow 14 and formed by gases exhaust from a gas turbine.
- the evaporator is supplied with water by a pump 16 through a supply line 18.
- the flow rate in line 18 is adjusted by a flow control valve 20 under the control of a flow meter 22.
- the output of the evaporator 10 is connected to a non condenser shown through an outlet line 24 and a valve trigger 26 under the control of a pressure gauge 28.
- This valve trigger 26 controls and regulates the pressure in the the evaporator.
- the outlet of the evaporator 10 is also connected through a control valve 30 at the inlet of the superheater 12.
- the outlet thereof is connected through an outlet line 32 to the condenser and to the steam turbine not shown.
- the pressure in the circuit superheater 12 is controlled by an expansion valve 34 under the control of a pressure gauge 36 during the start-up phase, and by the steam turbine in stabilized operation.
- One of the features that characterizes the boiler circuit according to the present invention is a pipe 38 in bypass between the inlet pipe 18 and outlet pipe 24 of the evaporator and which allows the mixing of a controlled quantity of "cold" water with the two-phase mixture produced by the evaporator during the starting the boiler.
- the water flow in line 38 is regulated by an adjustment valve 40 under the control of a thermometer 42 measuring the temperature downstream of the pipe 38.
- the evaporator Before starting the gas turbine, the evaporator is pressurized to a pressure compatible with the turbine gas temperature. This pressure which is controlled by the expansion valve 26 can be lower than the nominal pressure (for example 100 bars). A minimum flow (for example 30%) is ensured by pump 16 and regulated by valve 20 with return to the condenser through the expansion valve 26. The control valve 30 is then closed and the superheater 12 is isolated from the the evaporator 10.
- the gas turbine is then started and stabilized at a load such that the exhaust gas temperature is higher about 100 ° C at the saturation temperature in the evaporator 10, or about 400 ° C for the selected pressure.
- thermometer 42 controls the progressive opening of the valve 40 to allow the flow, towards line 24, with a regulated flow rate of "cold” water so that the temperature is lower than the saturation temperature (by example 300 ° C).
- the vapor which begins to form in the evaporator 10 from the saturation temperature transforms, by this supply of "cold” water, into water, so that the valve trigger 26 always remains in water as it enters (with a mixture water / steam, it could not work) and keeps its capacity of setting.
- valve 40 under the control of the thermometer 42, opens further to allow the contribution of the amount of water needed to condense all the steam and in order that the temperature at B be kept below the temperature saturation. This scenario lasts until there is no more water in the outlet of the evaporator. From this moment, the temperature increases again due to overheating of the steam. The absence of water at the outlet of the evaporator is therefore easily can be identified by an increase in temperature at A. This detection is used to gradually open valve 30 to divert steam 30 to superheater 12 and to close gradually the valve 40 and the expansion valve 26.
- the load of the gas turbine can be increased.
- the water flow will be regulated by the temperatures of the steam at the evaporator 10 and superheater 12 outlets and the relief valve 34 increases the pressure to the nominal value.
- the temperature of the steam leaving the the evaporator keeps a slight overheating of around 50 ° C.
- the final temperature of the steam leaving the boiler will be as requested at nominal speed or can be controlled by a any additional desuperheater for partial loads or peak.
- the system for transforming steam into water during start-up can be transposed to the boiler outlet which, therefore, does not would have more than one heat exchanger.
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- Combustion & Propulsion (AREA)
- Chemical & Material Sciences (AREA)
- Control Of Steam Boilers And Waste-Gas Boilers (AREA)
- Steam Or Hot-Water Central Heating Systems (AREA)
- Engine Equipment That Uses Special Cycles (AREA)
- Fluidized-Bed Combustion And Resonant Combustion (AREA)
- Gasification And Melting Of Waste (AREA)
- Paper (AREA)
- Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
- Devices For Medical Bathing And Washing (AREA)
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
BE9600735A BE1010594A3 (fr) | 1996-09-02 | 1996-09-02 | Procede de conduite d'une chaudiere a circulation forcee et chaudiere pour sa mise en oeuvre. |
BE9600735 | 1996-09-02 | ||
PCT/BE1997/000098 WO1998010222A1 (fr) | 1996-09-02 | 1997-09-01 | Procede de conduite d'une chaudiere a circulation forcee et chaudiere pour sa mise en oeuvre |
Publications (2)
Publication Number | Publication Date |
---|---|
EP1009951A1 EP1009951A1 (fr) | 2000-06-21 |
EP1009951B1 true EP1009951B1 (fr) | 2002-11-13 |
Family
ID=3889939
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP97938700A Expired - Lifetime EP1009951B1 (fr) | 1996-09-02 | 1997-09-01 | Procede de conduite d'une chaudiere a circulation forcee et chaudiere pour sa mise en oeuvre |
Country Status (14)
Country | Link |
---|---|
US (1) | US6152085A (zh) |
EP (1) | EP1009951B1 (zh) |
JP (1) | JP2001508164A (zh) |
CN (1) | CN1138943C (zh) |
AT (1) | ATE227822T1 (zh) |
AU (1) | AU4107097A (zh) |
BE (1) | BE1010594A3 (zh) |
CA (1) | CA2264898C (zh) |
DE (1) | DE69717165T2 (zh) |
DK (1) | DK1009951T3 (zh) |
ES (1) | ES2186921T3 (zh) |
PT (1) | PT1009951E (zh) |
TR (1) | TR199900479T2 (zh) |
WO (1) | WO1998010222A1 (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19926326A1 (de) * | 1999-06-09 | 2000-12-14 | Abb Alstom Power Ch Ag | Verfahren und Anlage zum Erwärmen eines flüssigen Mediums |
SE518085C2 (sv) * | 2000-03-24 | 2002-08-20 | Roland Lundqvist | Anordning och förfarande för överföring av värme samt användning därav |
DE102010028720A1 (de) * | 2010-05-07 | 2011-11-10 | Siemens Aktiengesellschaft | Verfahren zum Betreiben eines Dampferzeugers |
WO2014175871A1 (en) * | 2013-04-24 | 2014-10-30 | International Engine Intellectual Property Company, Llc | Turbine protection system |
JP6290063B2 (ja) * | 2014-10-06 | 2018-03-07 | トクデン株式会社 | 過熱水蒸気生成装置 |
CN108506921B (zh) * | 2018-04-25 | 2024-04-30 | 西安西热节能技术有限公司 | 一种电站锅炉的中高压工业供汽系统及方法 |
Family Cites Families (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2124254A (en) * | 1934-03-15 | 1938-07-19 | Ledinegg Max | Method of high pressure steam generation |
US2170790A (en) * | 1936-10-12 | 1939-08-22 | La Mont Corp | Forced circulation vapor generator |
NL280175A (zh) * | 1961-07-27 | |||
GB1053515A (zh) * | 1963-03-23 | |||
CH599504A5 (zh) * | 1975-09-26 | 1978-05-31 | Sulzer Ag | |
CH632331A5 (de) * | 1978-10-03 | 1982-09-30 | Sulzer Ag | Verfahren zum anfahren eines zwanglaufdampferzeugers. |
DE3236979A1 (de) * | 1982-10-06 | 1984-04-12 | Deutsche Babcock Werke AG, 4200 Oberhausen | Zwangsdurchlaufdampferzeuger und verfahren zu seiner inbetriebnahme |
EP0308728B1 (de) * | 1987-09-21 | 1991-06-05 | Siemens Aktiengesellschaft | Verfahren zum Betreiben eines Durchlaufdampferzeugers |
JPH03221702A (ja) * | 1990-01-29 | 1991-09-30 | Toshiba Corp | 複圧式排熱回収熱交換器 |
DE4303613C2 (de) * | 1993-02-09 | 1998-12-17 | Steinmueller Gmbh L & C | Verfahren zur Erzeugung von Dampf in einem Zwangsdurchlaufdampferzeuger |
US5762031A (en) * | 1997-04-28 | 1998-06-09 | Gurevich; Arkadiy M. | Vertical drum-type boiler with enhanced circulation |
-
1996
- 1996-09-02 BE BE9600735A patent/BE1010594A3/fr not_active IP Right Cessation
-
1997
- 1997-09-01 CN CNB971985243A patent/CN1138943C/zh not_active Expired - Fee Related
- 1997-09-01 US US09/147,753 patent/US6152085A/en not_active Expired - Fee Related
- 1997-09-01 WO PCT/BE1997/000098 patent/WO1998010222A1/fr active IP Right Grant
- 1997-09-01 TR TR1999/00479T patent/TR199900479T2/xx unknown
- 1997-09-01 EP EP97938700A patent/EP1009951B1/fr not_active Expired - Lifetime
- 1997-09-01 AT AT97938700T patent/ATE227822T1/de active
- 1997-09-01 CA CA002264898A patent/CA2264898C/fr not_active Expired - Fee Related
- 1997-09-01 DK DK97938700T patent/DK1009951T3/da active
- 1997-09-01 PT PT97938700T patent/PT1009951E/pt unknown
- 1997-09-01 JP JP51206598A patent/JP2001508164A/ja not_active Ceased
- 1997-09-01 ES ES97938700T patent/ES2186921T3/es not_active Expired - Lifetime
- 1997-09-01 DE DE69717165T patent/DE69717165T2/de not_active Expired - Lifetime
- 1997-09-01 AU AU41070/97A patent/AU4107097A/en not_active Abandoned
Also Published As
Publication number | Publication date |
---|---|
ATE227822T1 (de) | 2002-11-15 |
CN1138943C (zh) | 2004-02-18 |
US6152085A (en) | 2000-11-28 |
CN1232533A (zh) | 1999-10-20 |
BE1010594A3 (fr) | 1998-11-03 |
DE69717165D1 (de) | 2002-12-19 |
PT1009951E (pt) | 2003-03-31 |
CA2264898A1 (fr) | 1998-03-12 |
AU4107097A (en) | 1998-03-26 |
DE69717165T2 (de) | 2003-07-17 |
ES2186921T3 (es) | 2003-05-16 |
WO1998010222A1 (fr) | 1998-03-12 |
TR199900479T2 (xx) | 2000-02-21 |
DK1009951T3 (da) | 2003-03-10 |
EP1009951A1 (fr) | 2000-06-21 |
CA2264898C (fr) | 2007-01-09 |
JP2001508164A (ja) | 2001-06-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8181463B2 (en) | Direct heating organic Rankine cycle | |
FR2551181A1 (fr) | Centrale a cycle mixte et deux combustibles | |
JP4818353B2 (ja) | ガス・蒸気複合タービン設備の始動方法 | |
CA2016697A1 (en) | Method and apparatus for operating a combined cycle power plant having a defective deaerator | |
FR2524547A1 (fr) | Generateur de vapeur a gaz perdu et a degazeur | |
FR2973073A1 (fr) | Centrale a cycle combine | |
US6250258B1 (en) | Method for starting up a once-through heat recovery steam generator and apparatus for carrying out the method | |
FR2483514A1 (fr) | Centrale de production d'energie a cycles combines et procede pour y empecher la corrosion sulfureuse | |
US5840130A (en) | Cleaning of the water/steam circuit in a once-through forced-flow steam generator | |
US3756029A (en) | Gas/steam turbine plant and a method of operating same | |
JP2004526900A (ja) | ガスタービン用冷却材の冷却装置とガス・蒸気複合タービン設備 | |
EP1009951B1 (fr) | Procede de conduite d'une chaudiere a circulation forcee et chaudiere pour sa mise en oeuvre | |
US4487166A (en) | Start-up system for once-through boilers | |
JP6549342B1 (ja) | 発電プラント及びその運転方法 | |
EP3004571B1 (fr) | Procede de production d'energie par combustion de matieres, et installation pour la mise en oeuvre du procede | |
JP2009074726A (ja) | 貫流式排熱回収ボイラ | |
BE561251A (zh) | ||
JP2007291897A (ja) | 重質油改質燃料焚きガスタービン及び重質油改質燃料焚きガスタービンの運転方法 | |
US20240133319A1 (en) | System for readying sub-critical and super-critical steam generator, servicing method of said sub-critical and super-critical steam generator and method of operation of sub-critical and super-critical steam generator | |
CH522121A (fr) | Installation de production d'énergie | |
WO2023166340A1 (en) | System for readying sub-critical and super-critical steam generator, servicing method of said sub-critical and super-critical steam generator and method of operation of sub-critical and super-critical steam generator | |
BE532714A (zh) | ||
MXPA99002126A (en) | Method for operating a boiler with forced circulation and boiler for its implementation | |
BE547577A (zh) | ||
BE532837A (zh) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
17P | Request for examination filed |
Effective date: 19990309 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE |
|
17Q | First examination report despatched |
Effective date: 20010227 |
|
GRAG | Despatch of communication of intention to grant |
Free format text: ORIGINAL CODE: EPIDOS AGRA |
|
GRAG | Despatch of communication of intention to grant |
Free format text: ORIGINAL CODE: EPIDOS AGRA |
|
GRAH | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOS IGRA |
|
GRAH | Despatch of communication of intention to grant a patent |
Free format text: ORIGINAL CODE: EPIDOS IGRA |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LI LU MC NL PT SE |
|
REF | Corresponds to: |
Ref document number: 227822 Country of ref document: AT Date of ref document: 20021115 Kind code of ref document: T |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: FG4D Free format text: NOT ENGLISH |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: EP |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: FG4D Free format text: FRENCH |
|
REF | Corresponds to: |
Ref document number: 69717165 Country of ref document: DE Date of ref document: 20021219 |
|
REG | Reference to a national code |
Ref country code: DK Ref legal event code: T3 |
|
GBT | Gb: translation of ep patent filed (gb section 77(6)(a)/1977) |
Effective date: 20030303 |
|
REG | Reference to a national code |
Ref country code: GR Ref legal event code: EP Ref document number: 20030400497 Country of ref document: GR |
|
REG | Reference to a national code |
Ref country code: PT Ref legal event code: SC4A Free format text: AVAILABILITY OF NATIONAL TRANSLATION Effective date: 20030211 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2186921 Country of ref document: ES Kind code of ref document: T3 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed |
Effective date: 20030814 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: NV Representative=s name: CRONIN INTELLECTUAL PROPERTY |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PCAR Free format text: CRONIN INTELLECTUAL PROPERTY;CHEMIN DE PRECOSSY 31;1260 NYON (CH) |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DK Payment date: 20110824 Year of fee payment: 15 Ref country code: MC Payment date: 20110823 Year of fee payment: 15 Ref country code: CH Payment date: 20110829 Year of fee payment: 15 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: LU Payment date: 20120824 Year of fee payment: 16 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IE Payment date: 20120926 Year of fee payment: 16 Ref country code: SE Payment date: 20120824 Year of fee payment: 16 Ref country code: FI Payment date: 20120823 Year of fee payment: 16 Ref country code: GB Payment date: 20120828 Year of fee payment: 16 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GR Payment date: 20120920 Year of fee payment: 16 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 20120823 Year of fee payment: 16 Ref country code: IT Payment date: 20120828 Year of fee payment: 16 Ref country code: ES Payment date: 20120828 Year of fee payment: 16 Ref country code: DE Payment date: 20120827 Year of fee payment: 16 Ref country code: FR Payment date: 20121004 Year of fee payment: 16 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: PT Payment date: 20120302 Year of fee payment: 16 Ref country code: NL Payment date: 20120824 Year of fee payment: 16 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20120921 Year of fee payment: 16 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: MC Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20120930 |
|
REG | Reference to a national code |
Ref country code: PT Ref legal event code: MM4A Free format text: LAPSE DUE TO NON-PAYMENT OF FEES Effective date: 20140303 |
|
BERE | Be: lapsed |
Owner name: S.A. *COCKERILL MECHANICAL INDUSTRIES Effective date: 20130930 |
|
REG | Reference to a national code |
Ref country code: NL Ref legal event code: V1 Effective date: 20140401 |
|
REG | Reference to a national code |
Ref country code: SE Ref legal event code: EUG |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130902 Ref country code: FI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130901 |
|
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
REG | Reference to a national code |
Ref country code: DK Ref legal event code: EBP Effective date: 20130930 |
|
REG | Reference to a national code |
Ref country code: AT Ref legal event code: MM01 Ref document number: 227822 Country of ref document: AT Kind code of ref document: T Effective date: 20130901 |
|
REG | Reference to a national code |
Ref country code: GR Ref legal event code: ML Ref document number: 20030400497 Country of ref document: GR Effective date: 20140403 |
|
GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 20130901 |
|
REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST Effective date: 20140530 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: PT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140303 |
|
REG | Reference to a national code |
Ref country code: IE Ref legal event code: MM4A |
|
REG | Reference to a national code |
Ref country code: DE Ref legal event code: R119 Ref document number: 69717165 Country of ref document: DE Effective date: 20140401 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130901 Ref country code: IE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130901 Ref country code: BE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130930 Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130930 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130930 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140401 Ref country code: FR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130930 Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130901 Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130901 Ref country code: GR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140403 Ref country code: DE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20140401 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20141007 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DK Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130930 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130902 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20130901 |