EP0598797A4 - Konstruktion von ringförmigen wänden. - Google Patents

Konstruktion von ringförmigen wänden.

Info

Publication number
EP0598797A4
EP0598797A4 EP9292917253A EP92917253A EP0598797A4 EP 0598797 A4 EP0598797 A4 EP 0598797A4 EP 9292917253 A EP9292917253 A EP 9292917253A EP 92917253 A EP92917253 A EP 92917253A EP 0598797 A4 EP0598797 A4 EP 0598797A4
Authority
EP
European Patent Office
Prior art keywords
wall
mould
mould surface
support assembly
axis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP9292917253A
Other languages
English (en)
French (fr)
Other versions
EP0598797A1 (de
Inventor
Antonio John Lazzarotto
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of EP0598797A1 publication Critical patent/EP0598797A1/de
Publication of EP0598797A4 publication Critical patent/EP0598797A4/de
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/062Forms for curved walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/34Horizontally-travelling moulds for making walls blockwise or section-wise
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/02Containers for fluids or gases; Supports therefor
    • E04H7/18Containers for fluids or gases; Supports therefor mainly of concrete, e.g. reinforced concrete, or other stone-like material

Definitions

  • This invention relates to the construction of annular walls as may be used, for instance, in large water storage tanks.
  • An alternative technique requires an internal framework to be erected on-site and the outer surface of the framework is sprayed with a concrete matrix to produce a tank.
  • a still further technique requires concentric inner and outer shells to be constructed into which concrete is poured to form a unitary circular wall. It will be apparent that maintaining the structural integrity of such an internal framework or concentric inner and outer shells, prior to application of the matrix is difficult in large scale applications and necessitates construction of the full circular internal framework or concentric shells prior to commencing spraying or pouring of the concrete.
  • an apparatus for constructing an annular wall comprising a mould having a substantially upright mould surface defining a surface of a segment of the wall to be constructed, the mould being attached to a support assembly mounted on pivot means located substantially on the central axis of the wall such that the mould is rotatable about the axis in a substantially horizontal plane, the arrangement being such that in use, the mould is positioned at a selected first angular location relative to the pivot means and a hardenable composition is applied to the mould surface to form a first wall segment, after which the mould is moved to an adjacent location and the hardenable composition is applied to the mould surface to form an adjacent wall segment.
  • a method of constructing an annular wall using the above-described apparatus comprising: forming a first wall segment by applying a hardenable composition to the mould surface and allowing the composition to harden, at least partially; moving the mould surface to an adjacent location; and applying the hardenable composition to the mould surface at the adjacent location to form an adjacent wall segment.
  • a frame arrangement for use in the construction of a reinforced wall, the arrangement comprising: a plurality of substantially upright supports positioned at spaced locations along a side of the wall to be constructed; a first layer of reinforcement secured to the supports such that the layer is parallel to the side of the wall and extends along the wall; a plurality of vertically spaced elongate truss members secured at one lengthwise edge to the supports such that the truss members extend laterally along the wall and such that they each lie in a substantially horizontal plane; and a second layer of reinforcement secured to the free lengthwise edge of each of the truss members such that the second layer is generally parallel to, but laterally spaced from, the first layer of reinforcement.
  • annular tank can be cast in situ without requiring extensive scaffolding or other framework to define a complete mould surface. Furthermore, the rotation of the mould surface around the pivot means enables the wall to be cast continuously or in a stepwise, or semi-continuous manner, thereby avoiding a difficulty encountered in the prior art in which the alignment of individual adjacent preformed wall segments requires sophisticated surveying or precision framework.
  • the annular wall is cylindrical, in which case the central axis constitutes the axis of curvature of the wall, and means are provided for adjusting the orientation of the mould surface relative to the support assembly such that the axis of curvature of the mould surface may be inclined relative to the axis of curvature of the wall and/or the axis of curvature of the mould surface may be moved such that it is slightly offset relative to the pivot means.
  • the support assembly is telescopic and includes driving means for moving the mould radially in a plane substantially normal to the axis of curvature of the wall. It is also desirable that the support assembly further comprises means for raising and lowering the support assembly to facilitate the insertion of means for preventing the apparatus from rotating when the hardenable composition is to be applied.
  • Adjacent wall segments may be post-tensioned, for instance, by disposing circumferentially extending conduits adjacent the outer surface of the mould surface and then spraying the hardenable composition onto and around them. After the annular wall has been cast, cables or other tensioning means disposed within the conduits can be tightened to post-tension the wall. Alternatively, external tensioning means can be disposed around the circumference of the hardened wall. Additionally, or alternatively, vertically extending conduits can also be disposed such that they extend vertically through the wall to receive vertically, extending tensioning means to assist in stressing of the wall. If it is desired to form the wall in a non- continuous manner, the individual hardened wall segments can be locked together by the circumferential tensioning means after a sealant has been interposed between adjacent wall segments.
  • the fluid hardenable composition will comprise a concrete such as CSR "Readymix” Super Spray Concrete with “Micropoz".
  • Other construction materials appropriate for moulding/casting onto the mould surface such as organic polymers will also be known to those skilled in the art.
  • the fluid composition is sprayable although other application techniques such as trowelling will also be appropriate in some circumstances.
  • the lateral extent (degrees of arc) of the mould surface is not particularly limited - for a cylindrical tank, a circumferential length of the order of 8.5 metres is convenient when constructing walls of 10 to 15 metres radius and 6.5 metres high.
  • the mould surface may define an arcuate cross- section such that the internal surface of the completed annular wall is a smooth circular surface.
  • the invention is not limited to this and other configurations of the mould surface are also appropriate.
  • a flat mould surface will produce a polygonal internal surface of the wall.
  • the apparatus could be used to produce conical walls by providing an inwardly directed sloping mould surface.
  • the method and apparatus are also adaptable to the construction of structures such as channels.
  • Figure 1 shows a perspective view of an embodiment of the apparatus of the present invention prior to spraying of the construction material
  • Figure 2 shows a cross-section of a wall under construction and the embodiment of Figure 1;
  • Figure 3 shows a plan view of the wall and apparatus of Figure 2 ;
  • Figure 4 shows a part sectional view of a frame arrangement for the wall
  • Figure 5 shows a perspective view of a detail of Figure 4.
  • Apparatus 14 in accordance with the invention comprises a pivot 16 in the form of a post located at the centre of the circular slab 12.
  • a radially extending support assembly 20 is rotatably mounted on the post and rides on swivel wheels 24.
  • Extending radially from the support assembly 20 is an arcuate sheet 26 having a radially outer surface defining a mould surface 28 with a horizontal cross-section corresponding to the internal diameter of wall 10 and extending vertically the height of the wall 10.
  • a typical height of the mould surface is 7.5 metres.
  • the support assembly 20 is of telescopic form and has, intermediate the pivot 16 and the mould surface 28, an hydraulic mechanism 30 serving to displace the arcuate sheet 26, and thus the mould surface 28, radially inward and radially outward relative to the pivot 16.
  • the apparatus 14 also comprises length adjustable props 27 which are connected to the radially inner surface of the arcuate sheet 26 and to the support assembly 20 by way of swivels (not shown) such that by adjusting the length of each prop 27, the orientation of the mould surface 28 relative to the support assembly 20 can be adjusted.
  • the axis of curvature of the mould surface 28 may be tilted backwardly or forwardly relative to the axis of curvature of the wall or, if the props 27 on one side of the support assembly are shortened, the axis of curvature of the mould surface may be slightly offset relative to the pivot 16.
  • Wall 10 in this embodiment is the retaining wall of a 22 metre diameter, 6.5 metre high water tank. Construction commences by pouring a reinforced concrete slab 12 in the form of a 22.5 metre circle with a deepened, reinforced circumferential rim 32. Within rim 32 is a circumferentially extending channel 34 into which wall 10 seats. Following hardening of the slab 12, the pivot 16 is installed at the radial centre of the slab 12 and the apparatus 14 is rotatably disposed thereon.
  • the frame arrangement 36 is then constructed and comprises a number of vertically extending soldiers 37 which are spaced around the radial outer edge of the rim 32 and a number of vertically spaced, laterally extending annular trusses 38, shown in detail in Figures 4 and 5.
  • the soldiers 37 are fixed at their bottom end to the slab 12 by way of bolts, for example, and a sheet of reinforcing mesh 40a is placed against the innermost edge of each soldier 37, as shown in Figure 4.
  • a number of the annular trusses 38 are then fixed to the soldiers 37, for example by tying securely with wire, at spaced intervals along their vertical length, thereby holding the mesh 40a in position.
  • a number of laterally extending conduits 42a are then located adjacent the radially inner surface of the sheet of reinforcing mesh 40a and are fixed to the trusses 38 by tying securely with wire.
  • a number of laterally spaced, vertically extending conduits 42b are then inserted lengthwise through apertures 44 in the trusses 38 such that they lie against the laterally extending conduits 42a and are likewise tied to the trusses 38.
  • the conduits 42a, 42b will serve to carry the post-tensioning tendons as will be described hereinafter.
  • a second, or inner, sheet of reinforcing mesh 40b is then placed against the radially innermost edge of the annular trusses 38 and is, again, tied to the other components of the frame.
  • the vertical conduits serve to support the weight of the wall and, prior to subsequent operations, a cable is inserted into each vertical conduit such that one end of the cable extends from the bottom of the conduit and is ultimately held in position in the wall after the concrete composition has hardened.
  • the other end of the cable is threaded, for example, to cooperate with means, such as a nut, for tensioning the wall 10 after it has fully hardened.
  • the frame arrangement 36 stably supports the reinforcing mesh 40a, 40b and the conduits 42a, 42b such that their vibration is minimised when the concrete composition is sprayed onto them under high pressure.
  • the soldiers 37 are ultimately removed from the tank after the tank wall has fully hardened.
  • This frame arrangement is, of course, applicable to walls other than cylindrical walls, such as straight wall sections.
  • the arcuate mould surface 28 of the apparatus 14 is then manoeuvred so that the arcuate outer surface of the mould surface 28 coincides with the internal diameter of channel 34 in the slab 12, the support assembly 20 is raised to facilitate the insertion of stands and is then lowered again such that the arcuate sheet 26 cannot rotate about the pivot 16.
  • the wall segment is then formed by spraying a concrete composition such as "Super Spray with Micropoz" available from CSR Readymix Australia onto the mould surface thereby incorporating the tendon conduits and reinforcing mesh within the wall.
  • the operator spraying the concrete composition may be positioned upon a scissor lift which can be raised and lowered, thereby enabling him, and his ancillary spray equipment, to be positioned at the most appropriate position relative to the wall. Spraying is carried out until a wall depth of approximately 20 centimetres is achieved and the concrete composition is allowed to commence hardening.
  • the support assembly 20 is retracted radially inward such that the mould surface 28 is spaced laterally from the hardening wall, thereby providing a substantial gap between the mould surface 28 and the wall surface.
  • a formwork release agent may then be brushed or sprayed onto the mould surface 28 to assist in breaking the suction between the mould surface 28 and a subsequently formed wall surface.
  • the mould surface 28 is then rotated about the pivot 16 until it lies laterally adjacent the hardening segment 10' just formed.
  • the concrete composition is then sprayed onto the mould surface 28 to form a second wall segment 10' which is integral and coextensive with the previously formed and now hardening wall segment 10.
  • This forming process allows the complete cylindrical tank to be formed continuously in one piece and avoids a problem encountered with the prior art in which individual wall segments must be locked together and sealed to waterproof the tank.
  • a rubber mastic composition is interposed between the wall 10 and the channel 34 to ensure water-tightness.
  • the support assembly 20 includes an upstanding support (not shown) such that the upstanding support can rotate about the pivot 12 with the support assembly 20.
  • a roll of reinforcing mesh is fitted over the support so that on rotation of the apparatus about the pivot 12, a continuous sheet of mesh can be unwound from the roll.
  • each apparatus would rotate about a common pivot post such that, for example, each apparatus initially forms adjacent wall segments after which each apparatus is rotated in opposite directions about the common pivot, each forming sequential wall segments, and again come together again to form the last of the wall segments, thereby completing the tank.
  • the lateral (vertical) edges 46, 48 of the wall segment 10 are cleanly sculpted, in this case in the form of a counter- clockwise oriented "V"-shaped formation.
  • Adjacent wall segments have corresponding but opposed sculpting of their vertical edges to ensure that the segments key together to produce a water-tight seal.
  • the curved outer surface of each segment, measured horizontally, is of the order of 7.5 metres.
  • the hydraulic mechanism 30 is activated to displace the mould surface 28 radially inward from the now hardened wall segment, the swivel wheels 24 riding on the smooth surface of the slab 12.
  • the apparatus 14 with the mould surface 28 in its retracted (radially inward) position is rotated around the pivot post 16 until it lies laterally adjacent the hardened segment 10' .
  • the hydraulic mechanism 30 is again activated until mould surface 28 is flush with the inner diameter of the channel 34.
  • circumferential and vertical conduits are temporarily suspended adjacent but spaced from the mould surface and the concrete composition is sprayed to form a second wall segment adjacent and coextensive with the now hardened wall segment.
  • the lateral edge of the new segment immediately adjacent the edge of the pre-existing hardened segment is shaped to correspond in section therewith.
  • the mould surface 28 defines the internal wall of the completed water tank. It will also be apparent that the configuration of the apparatus can be modified so that the side of arcuate sheet 32 facing the pivot is the mould surface. In this embodiment the fluid composition will be applied from the "inside" of the wall and the mould surface will define the exterior face.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
EP9292917253A 1991-08-13 1992-08-05 Konstruktion von ringförmigen wänden. Withdrawn EP0598797A4 (de)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
AU7733/91 1991-08-13
AUPK773391 1991-08-13
PCT/AU1992/000411 WO1993004247A1 (en) 1991-08-13 1992-08-05 Construction of annular walls

Publications (2)

Publication Number Publication Date
EP0598797A1 EP0598797A1 (de) 1994-06-01
EP0598797A4 true EP0598797A4 (de) 1994-11-02

Family

ID=3775618

Family Applications (1)

Application Number Title Priority Date Filing Date
EP9292917253A Withdrawn EP0598797A4 (de) 1991-08-13 1992-08-05 Konstruktion von ringförmigen wänden.

Country Status (4)

Country Link
EP (1) EP0598797A4 (de)
CN (1) CN1070712A (de)
CA (1) CA2115241A1 (de)
WO (1) WO1993004247A1 (de)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2304188B1 (es) * 2004-05-11 2009-05-05 Ferroberica, S.L. Procedimiento para la construccion de depositos y similares, y molde para la formacion de tramos de anillo empleados en dicha construccion.
WO2008101268A2 (de) * 2007-02-22 2008-08-28 Wolf Modul Gmbh Schalung für behälter
CN105926929B (zh) * 2014-10-15 2018-01-30 中铁四局集团有限公司 一种直墙混凝土的浇筑施工方法
CN104925476B (zh) * 2015-06-30 2016-12-28 郑州远东耐火材料有限公司 弧形砖整体上墙平台
CN112709409A (zh) * 2020-12-25 2021-04-27 重庆工程职业技术学院 建筑装饰墙安装辅助支撑装置
CN114086758B (zh) * 2021-11-25 2023-04-04 北京住总集团有限责任公司工程总承包二部 一种散拼式清水混凝土圆弧墙体模板及其安装方法
WO2023235927A1 (en) * 2022-06-07 2023-12-14 Antonio John Lazzarotto Construction of annular concrete tanks on-site

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2339892A (en) * 1941-10-20 1944-01-25 William E Urschel Machine for building walls
FR1199605A (fr) * 1958-03-13 1959-12-15 Procédé de construction de structure de bâtiments, à l'aide de moules
FR1214534A (fr) * 1958-01-22 1960-04-08 Procédé de construction de citernes-réservoirs d'essence ou récipients similaires en béton et récipient fabriqué suivant ce procédé
US3120047A (en) * 1961-05-04 1964-02-04 John M Crom Method of making a liquid impervious wall
FR1494237A (fr) * 1966-07-26 1967-09-08 Coffrage mobile pour coulée de murs en béton et analogues
DE1933856A1 (de) * 1968-07-03 1970-01-08 Shimizu Construction Co Ltd Verfahren und Vorrichtung zur Herstellung von rund ausgebildeten Betonbauwerken
US4320075A (en) * 1977-11-28 1982-03-16 Nielson Jay P Self-propelled slip form method
US4371325A (en) * 1980-04-08 1983-02-01 Harbison Charles H Apparatus for forming structures in the form of segments of a sphere

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1207848A (en) * 1967-01-16 1970-10-07 Kao Jing-Hong Method and device for successively building concrete structures
DE2446927C3 (de) * 1974-10-01 1982-04-08 Josef 7611 Steinach Maier Großflächenschalung mit verschieden gekrümmten Flächen
DE8504548U1 (de) * 1984-02-23 1988-07-28 Jugo-Import-Export-Anstalt, Mauren Schalung für rotationssymmetrische, insbesondere zylindrische und kegelförmige, z.B. sich leicht nach oben verjüngende, Bauwerke

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2339892A (en) * 1941-10-20 1944-01-25 William E Urschel Machine for building walls
FR1214534A (fr) * 1958-01-22 1960-04-08 Procédé de construction de citernes-réservoirs d'essence ou récipients similaires en béton et récipient fabriqué suivant ce procédé
FR1199605A (fr) * 1958-03-13 1959-12-15 Procédé de construction de structure de bâtiments, à l'aide de moules
US3120047A (en) * 1961-05-04 1964-02-04 John M Crom Method of making a liquid impervious wall
FR1494237A (fr) * 1966-07-26 1967-09-08 Coffrage mobile pour coulée de murs en béton et analogues
DE1933856A1 (de) * 1968-07-03 1970-01-08 Shimizu Construction Co Ltd Verfahren und Vorrichtung zur Herstellung von rund ausgebildeten Betonbauwerken
US4320075A (en) * 1977-11-28 1982-03-16 Nielson Jay P Self-propelled slip form method
US4371325A (en) * 1980-04-08 1983-02-01 Harbison Charles H Apparatus for forming structures in the form of segments of a sphere

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
See also references of WO9304247A1 *

Also Published As

Publication number Publication date
CN1070712A (zh) 1993-04-07
WO1993004247A1 (en) 1993-03-04
CA2115241A1 (en) 1993-03-04
EP0598797A1 (de) 1994-06-01

Similar Documents

Publication Publication Date Title
US7004737B2 (en) Methods and apparatus for forming concrete structures
US6640505B1 (en) Hybrid arched overfilled structure
JP5629316B2 (ja) 伸縮式タワーアセンブリおよび方法
CN101832049B (zh) 混凝土结构连体筒体施工装置及方法
CN106836463A (zh) 承台及地梁结构的施工装置和施工方法
CN112663949A (zh) 现浇钢筋混凝土斜圆柱施工模具及方法
CN110778108A (zh) 复杂空间多曲面双层斜交混凝土网格结构的施工方法
CN110685434A (zh) 现浇多曲面双层斜交混凝土网格结构模架体系及施工方法
CN110700570A (zh) 一种现浇混凝土曲面斜筒体结构施工方法
WO1993004247A1 (en) Construction of annular walls
US4312167A (en) Method of constructing a storage tank
US4728073A (en) Formwork for forming reservoirs and pools
AU670037B2 (en) Construction of annular walls
US3470656A (en) On-site fabricated glass reinforced resin storage tank
KR101542045B1 (ko) 교각 시공방법 및 그에 따른 장치
CN109944478A (zh) 一种双曲线冷却塔施工方法
JP3943527B2 (ja) コンクリート貯槽及びその構築方法
US4076777A (en) Method and apparatus for forming a concrete roof
CN113073727A (zh) 一种污水构筑物施工方法
WO2023235927A1 (en) Construction of annular concrete tanks on-site
JPH01256636A (ja) 建築物躯体の施工方法
US4805371A (en) Building structures
AU595449B2 (en) Method of construction
GB2218453A (en) Fabricating structures
JPH03501280A (ja) プラツトホーム又は類似構造物用コンクリート柱の建設方法及び類似用途の柱部分

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19940222

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): DE ES FR GB GR IT

A4 Supplementary search report drawn up and despatched

Effective date: 19940916

AK Designated contracting states

Kind code of ref document: A4

Designated state(s): DE ES FR GB GR IT

17Q First examination report despatched

Effective date: 19950904

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn