EP0503309A1 - Procédé pour la congélation accélérée de sol - Google Patents

Procédé pour la congélation accélérée de sol Download PDF

Info

Publication number
EP0503309A1
EP0503309A1 EP92102488A EP92102488A EP0503309A1 EP 0503309 A1 EP0503309 A1 EP 0503309A1 EP 92102488 A EP92102488 A EP 92102488A EP 92102488 A EP92102488 A EP 92102488A EP 0503309 A1 EP0503309 A1 EP 0503309A1
Authority
EP
European Patent Office
Prior art keywords
freezing
water
soil
earth
frozen
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP92102488A
Other languages
German (de)
English (en)
Inventor
Bodo Marx
Daniel Müller
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Messer Griesheim GmbH
Original Assignee
Messer Griesheim GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Messer Griesheim GmbH filed Critical Messer Griesheim GmbH
Publication of EP0503309A1 publication Critical patent/EP0503309A1/fr
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/10Preparation of the ground
    • E21D1/12Preparation of the ground by freezing
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Definitions

  • the invention relates to a method for accelerated freezing of soil according to the preamble of claim 1.
  • the soil around the objects is consolidated as a construction measure by freezing.
  • the freezing volume and duration of the freezing measures determine which freezing technique is preferred.
  • conventional freezing technology which works according to the refrigerator principle with a closed refrigeration cycle
  • freezing technology which uses a low-boiling, liquefied gas, usually nitrogen, as the refrigerant is working. Freezing lances are used to introduce the refrigerant and are arranged in the soil in the desired profile to be frozen.
  • DE-OS 21 56 420 shows a corresponding prior art.
  • the freezing work is integrated into the ongoing construction work and thus has an influence on the overall construction schedule.
  • follow-up works can only be carried out when the freezing work has at least largely been completed. Delays in the freezing work lead to delays or even downtimes in the subsequent plants. This leads to considerable cost increases.
  • the invention is therefore based on the object of creating a method which enables accelerated freezing of soil.
  • the invention is therefore based on the idea of pumping out the water present in the ground to be frozen, cooling it down to preferably close to 0 ° C. by means of a coolant and introducing it back into the ground.
  • the technology required for this is known per se from groundwater treatment, reference is made, for example, to DE-PS 19 45 605.
  • the water is conducted in a cycle through the soil to be frozen and also gradually cools it to a lower temperature so that subsequent freezing operations can be carried out more quickly.
  • the cooling of the water according to the invention can be carried out both before and during freezing work that is already in progress.
  • the nitrogen off-gas coming from the freezing lances can be used for water cooling. In this way, the sensitive cold content of the nitrogen gas can be optimally used.
  • the method according to the invention can be carried out not only with water standing in the freezer field, but also with strong groundwater movements. If such groundwater movements are present in the freezer area, the groundwater on the side flowing towards the freezer field is removed, cooled and injected again. In this way, higher groundwater velocities can be mastered, especially when freezing with liquid nitrogen.
  • a prerequisite for successful freezing of the ground is that the freezing ground has a sufficient water content, which in the frozen state gives the soil the actual strength. If the water content is too low for icing, the freezing ground is deliberately enriched with water by means of damming and sprinkling technology.
  • frost body 1 In the soil to be frozen is dashed Lines a frost body 1 shown, which fills the profile to be frozen. In the frost body 1 there are a large number of freezing lances 2 which are charged with refrigerant, namely liquid nitrogen. The excavation cross section 3 is not frozen in this case.
  • water is withdrawn from the ground to be frozen by a delivery well 4, cooled in the heat exchanger 6 to a temperature close to 0 ° C. and returned to the ground by swallowing well 5.
  • the water flows are shown by arrows not marked.
  • Liquid nitrogen is used as the coolant, which is removed from the store 7 and fed to the heat exchanger 6.
  • the nitrogen exhaust gas originating from the freezing lances 2 can also be used as a coolant in the heat exchanger 6.
  • Part of the cooled water is not returned to the ground through the swallowing well 5, but through the sprinkler system 8.
  • a barrier well 9 is also shown, through which groundwater is withdrawn, which originates from a groundwater flow in the direction of the soil to be frozen. This groundwater flow is indicated by arrows 10.
  • the groundwater taken through the barrier well 9 can also be cooled and reintroduced into the soil to be frozen.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
EP92102488A 1991-03-08 1992-02-14 Procédé pour la congélation accélérée de sol Withdrawn EP0503309A1 (fr)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
DE19914107455 DE4107455A1 (de) 1991-03-08 1991-03-08 Verfahren zum beschleunigten gefrieren von erdreich
DE4107455 1991-03-08

Publications (1)

Publication Number Publication Date
EP0503309A1 true EP0503309A1 (fr) 1992-09-16

Family

ID=6426784

Family Applications (1)

Application Number Title Priority Date Filing Date
EP92102488A Withdrawn EP0503309A1 (fr) 1991-03-08 1992-02-14 Procédé pour la congélation accélérée de sol

Country Status (2)

Country Link
EP (1) EP0503309A1 (fr)
DE (1) DE4107455A1 (fr)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453910B (zh) * 2013-09-22 2016-08-17 北京中煤矿山工程有限公司 一种斜冻结孔下冻结管装置
CN105857658A (zh) * 2016-05-23 2016-08-17 天津大学 具有调控功能的围堰砂袋吹填分流控制器及其使用方法

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102777185A (zh) * 2012-05-15 2012-11-14 张晓岩 一种斜井井筒施工工艺
CN108331584B (zh) * 2017-12-29 2019-11-15 上海建工集团股份有限公司 一种管幕下土方开挖方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE204162C (fr) *
DE1945605A1 (de) * 1969-02-13 1970-09-03 Yrjoe Reijonen & Veli Reijonen Verfahren und Vorrichtung zur Reinigung von Wasser aus einem Grundwasser-Brunnen
FR2113980A1 (fr) * 1970-11-16 1972-06-30 Union Carbide Canada Ltd

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE204162C (fr) *
DE1945605A1 (de) * 1969-02-13 1970-09-03 Yrjoe Reijonen & Veli Reijonen Verfahren und Vorrichtung zur Reinigung von Wasser aus einem Grundwasser-Brunnen
FR2113980A1 (fr) * 1970-11-16 1972-06-30 Union Carbide Canada Ltd

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104453910B (zh) * 2013-09-22 2016-08-17 北京中煤矿山工程有限公司 一种斜冻结孔下冻结管装置
CN105857658A (zh) * 2016-05-23 2016-08-17 天津大学 具有调控功能的围堰砂袋吹填分流控制器及其使用方法
CN105857658B (zh) * 2016-05-23 2017-12-12 天津大学 具有调控功能的围堰砂袋吹填分流控制器及其使用方法

Also Published As

Publication number Publication date
DE4107455A1 (de) 1992-09-10

Similar Documents

Publication Publication Date Title
EP0077943B1 (fr) Procédé pour la construction d'un tunnel
EP3063335B1 (fr) Procédé de production d'une masse de glace continue en cas de congélation de sol
DE2349071A1 (de) Spundwandelement und verfahren zum einbringen desselben
EP0503309A1 (fr) Procédé pour la congélation accélérée de sol
DE2424425A1 (de) Verfahren und vorrichtung zum haerten von stahlrohren
DE3112291A1 (de) "vorrichtung zum bodengefrieren"
DE1240789B (de) Vorrichtung zum Vortreiben einer Strecke oder eines Schachtes in sandigem oder wasserhaltigem Erdreich
DE2505668A1 (de) Vorrichtung an bohrausruestungen
EP0353219B1 (fr) L'arrière-bec d'un bouclier pour une machine d'avancement de tunnel à bouclier et méthode pour rendre étanche l'anneau circulaire entre l'arrière-bec du bouclier et éléments de revêtement
WO2011015341A1 (fr) Dispositif de pose d'une sonde géothermique
DE3447872A1 (de) Verfahren zur konsolidierung des gelaendes beim tunnelausbruch
DE10232174B4 (de) Injektionsvorrichtung zum Einbringen von Injektionsmedien in einen Boden
DE19930504B4 (de) Verfahren zum Auffahren von Strecken in stark wasserführenden Schichten und dafür geeignete Bohreinrichtung
DE1759309A1 (de) Verfahren zum Herstellen von unterirdischen Hohlraeumen
DE2727081A1 (de) Verfahren und vorrichtung zum abdichten von spundwaenden
DE329896C (de) Verfahren und Vorrichtung zum Abteufen von Schaechten, insbesondere durch wasserfuehrende Schichten
DE3036842A1 (de) Verfahren zum bodengefrieren
DE3026644C2 (fr)
EP1548228B1 (fr) Procédé de réalisation d'un forage souterrain et dispositif pour ce procédé
DE3232906C2 (fr)
DE2614221A1 (de) Verfahren und vorrichtung zur bodenvereisung fuer unterirdische bauwerke, baugruben oder dergleichen
DE19838487C1 (de) Für Düsenstrahlinjektionen in den Baugrund verwendetes Bohrrohr
DE242829C (fr)
EP0282472B1 (fr) Procédé et dispositif pour refroidir des barres et des fils
WO2003006792A1 (fr) Tunnelier

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH DE DK FR GB LI NL

17P Request for examination filed

Effective date: 19921022

17Q First examination report despatched

Effective date: 19941124

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 19950624