EP0442935A1 - Felsenanker und verfahren zur herstellung. - Google Patents

Felsenanker und verfahren zur herstellung.

Info

Publication number
EP0442935A1
EP0442935A1 EP89912755A EP89912755A EP0442935A1 EP 0442935 A1 EP0442935 A1 EP 0442935A1 EP 89912755 A EP89912755 A EP 89912755A EP 89912755 A EP89912755 A EP 89912755A EP 0442935 A1 EP0442935 A1 EP 0442935A1
Authority
EP
European Patent Office
Prior art keywords
tendon
clamp means
rock anchor
clamp
manufacturing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
EP89912755A
Other languages
English (en)
French (fr)
Other versions
EP0442935A4 (en
EP0442935B1 (de
Inventor
Neville Allan Hedrick
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Garford Pty Ltd
Original Assignee
Garford Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=3773499&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=EP0442935(A1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Garford Pty Ltd filed Critical Garford Pty Ltd
Publication of EP0442935A1 publication Critical patent/EP0442935A1/de
Publication of EP0442935A4 publication Critical patent/EP0442935A4/en
Application granted granted Critical
Publication of EP0442935B1 publication Critical patent/EP0442935B1/de
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • DTEXTILES; PAPER
    • D07ROPES; CABLES OTHER THAN ELECTRIC
    • D07BROPES OR CABLES IN GENERAL
    • D07B5/00Making ropes or cables from special materials or of particular form
    • D07B5/005Making ropes or cables from special materials or of particular form characterised by their outer shape or surface properties
    • DTEXTILES; PAPER
    • D07ROPES; CABLES OTHER THAN ELECTRIC
    • D07BROPES OR CABLES IN GENERAL
    • D07B7/00Details of, or auxiliary devices incorporated in, rope- or cable-making machines; Auxiliary apparatus associated with such machines
    • D07B7/16Auxiliary apparatus
    • D07B7/18Auxiliary apparatus for spreading or untwisting ropes or cables into constituent parts for treatment or splicing purposes
    • D07B7/187Auxiliary apparatus for spreading or untwisting ropes or cables into constituent parts for treatment or splicing purposes for forming bulbs in ropes or cables
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • E21D21/006Anchoring-bolts made of cables or wires

Definitions

  • the present invention relates to an improved rock anchor and a method of and an apparatus for manufacture thereof.
  • Rock anchors are steel tendons inserted down bore holes in a scree. A portion of the tendon is grouted, and a plate attached to the tendon. The tendon is then stressed; the plate bears upon the scree and thereby stabilises the scree.
  • Tendons typically comprise a plurality of steel strands wound together to form the tendon. • To adequately secure such tendons in cement, prior art methods have used machines to unravel the strands. Such machines have required people to initiate such unravelling prior to insertion into the machine. This is time consuming and hence expensive. The purpose of unravelling the strands is to increase the surface area of the tendon in contact with the cement to more securely embed the tendon in the cement.
  • the present invention provides an alternative form of tendon and a method and an apparatus for manufacture thereof.
  • a rock anchor comprising a ten. : composed c ! a plurality of strands, the tendon having at j.east one bulisous portion, wherein all the strands in the .or each bulbous portion are spaced apart from one another substantially around the periphery of each bulbous portion.
  • there is * provided an apparatus for manufacturing a rock anchor comprising two or more spaced clamp means movable relative to one another and able to clamp a tendon, and clamp displacement means to displace the clamp means relative to one another.
  • a method for manufacturing a rock anchor comprising clamping a tendon in two or more spaced clamp means movable relative to one another, displacing the movable clamp means towards the fixed clamp means to form at least one bulbous portion in the tendon, and releasing the tendon from the clamp means.
  • Figure 1 is a view of a rock anchor in accordance with the present invention
  • Figure 2 is an upper perspective view of a section taken along the line 2-2 of Figure 1;
  • Figure 3 is a side view of a first embodiment of a machine for manufacturing a rock anchor in accordance with the present invention
  • Figure 4 is a plan view of a second embodiment of a machine for manufacturing a rock anchor in accordance with the present invention in a bulb upsetting condition
  • Figure 5 is a plan view of the machine of Figure 4 in a tendon displacing condition
  • Figure 6 is a plan view of a third embodiment of a machine for manu acturing a rock anchor in accordance with the present invention in a bulb upsetting condition
  • Figure 7 is a transverse sectional view along lines 7-7 of Figures 4 to 6
  • Figure 8 is a transverse sectional view along lines 8-8 of Figures 4 to 6
  • Figure 9 is a transverse sectional view along line 9-9 of Figure 6.
  • FIG. 1 and 2 Shown in Figures 1 and 2 is a rock anchor 10 comprising a steel tendon 12.
  • the tendon 12 is composed of a plurality of outer strands 14 helically wound around a centre strand 15 to form the tendon 12. As shown, there are six outer strands 14 wound around the centre strands.
  • The,tendon 12 has a plurality of bulbous portions 16 spaced apart from one another along the length of the tendon. The portions of the strands 14 and 15, in the bulbous portions 16, are spaced apart from each other around the circumference of the bulbous portions 16, as shown.
  • the section line 2-2 has been taken through the fattest part of the bulbous portion 16. As seen in Figure 2, the centre strand 15 is displaced away from the centre of the tendon 12.
  • Each bulbous portion 16 has a bulb diameter defined as the diameter of the smallest tube through which the rock anchor 10 will pass.
  • the bulb periphery is indicated by the broken lines, marked 17 in Figure 2.
  • the outer strands 14 and the centre strand 15 are all located adjacent and within the bulb periphery 17. This enables cement to contact a greater surface area of the strands " 14 in use, as hereinbefore described.
  • the rock anchor 10 is thereby firmly embedded in the cement.
  • the centre strand 15 is displaced away from its normal central position, in the bulbous portions 16. When the rock anchor 10 is stressed, the load will be taken more evenly by the strands 14 and 15 than if the centre strand 15 was in its central position. If the centre strand 15 was in its central position, more load would be taken by the centre strand 15 than the outer strands 14. This would then lower the safety factor of the rock anchor 10 which could then fail at a much lower load.
  • FIG. 3 Shown in Figure 3 is a first embodiment of an apparatus 20 for manufacturing a rock anchor 10.
  • the apparatus 20 comprises a plurality of spaced clamp means 22 to clamp the tendon 12.
  • the spacing between adjacent clamp means 22 is initially set at a first predetermined distance.
  • This first predetermined length corresponds to an uninterrupted length of tendon 12 necessary to form a bulbous portion 16 having the correct or desired proportions.
  • the clamp means 22 are slidably mounted on a frame 24 supported by legs 26 and feet 27.
  • One of the clamp means 22' is fixed to the frame 24.
  • the fixed clamp means 22* is located at one end of the frame 24, in this case the left hand end, as shown in Figure 3.
  • Each clamp means 22 comprises an hydraulic ram 28 having a plate 30 attached thereto to bear on and thereby clamp the tendon 12 against an opposed plate 32. Springs 34 are provided to help bias the plates 30 and 32 apart when the ram 28 is released.
  • Each ram 28 is supplied with hydraulic pressure ' through a pipe 36 connected to a common manifold 38 and controlled by a valve 40.
  • Each clamp means 22 is provided with a stop 42 extending to the left, as shown, to limit movement of the plurality of clamp means 22 relative to each other.
  • a clamp displacement means such as an hydraulic ram 44 is fixed to. the right hand end of the frame 24 and is controlled by a valve 46.
  • the ram 44 has a plunger 45 which bears on the clamp means 22 on the right, as shown in Figure 2.
  • the ram 44 is able to displace the plurality of clamp means 22 relative to one another.
  • An hydraulic power source 48 supplies hydraulic pressure to the rams 28 and 44 and is controlled by a valve 50.
  • a tendon 12 is placed between the plates .30 and 32, of each clamp means 22.
  • the valves 40 and 50 are then opened to operate the rams 28.
  • the rams 28 move the plates 30 to bear on the tendon 12 and thereby clamp the tendon 12 against the opposed plates 32.
  • the valve 46 is then opened to operate the ram 44.
  • the ram 44 bears on the clamp means 22 on the right and displaces it towards the left. Since the clamp means 22' is fixed to the frame 24, the other clamp means 22 are displaced relative to one another. Such relative displacement causes the tendon 12 to be interrupted and the bulbous portions 16 to be formed in the tendon 12, between adjacent clamp means 22.
  • the stops 42 limit the displacement of one clamp means 22 relative to adjacent clamp means 22. Conveniently, the stops 42 limit the distance between adjacent clamp means 22 to a second predetermined distance. This second, predetermined distance corresponds to the bulbous portions 16 reaching their correct or desired proportions. Displacement of the ram 44 is continued until bulbous portions 16 of sufficient size and shape are formed. This may occur when each stop 42 contacts an adjacent clamp means 22 and movement of the clamp means 22 relative to one another is no longer possible.
  • the strands 14 are forced apart and the strand 15 is forced outwardly to a position adjacent the bulb periphery 17 as described above and a rock anchor 10 in accordance with the present invention is formed.
  • the valves 40 and 46 are then closed.
  • the springs 34 of the clamp means 22 urge the plates 30 away from the plates 32, thereby releasing the tendon 12.
  • the rock anchor 10 is then removed and may be used in known manner.
  • FIG. 4 Shown in Figures 4, 5, 7 and 8 is a second embodiment of an apparatus 52 for manufacturing a rock anchor 10.
  • Reference numerals used in Figure 3 denote like parts in Figures 4, 5, 7 and 8.
  • the hydraulic ram 28, associated with the fixed clamp means 22' is supplied with hydraulic pressure through a pipe 56.
  • the ram 28, associated with the slidable colamp means 22, is supplied with hydraulic pressure through a separate pipe 58.
  • the ram 44 of the displacement means has a separate pipe 60 to supply hydraulic pressure.
  • the pipes 56, 58 and 60 are connected to an hydraulic timer (not shown) which co-ordinates the action of both rams 28 and the ram 44.
  • each plate 30 and 32 has a recess 62.
  • the plates 30 and 32 have a centralising pin 64 located below the recesses 62 and extending between the plates 30 and 32. The pin 64 serves to support the tendon 12 and to guide the plates 30 and 32 toward one another so that the -recesses 62 clamp the tendon 12 therein.
  • the plate 30 contains a recess (not shown) which receives the pin 64 when the plates 30 and 32 are moved together by the ram 28.
  • a tendon 12 is first fed through the ram 44, between the plates 30 and 32, of the clamp means 22 and 22', and into the pipe 61.
  • the hydraulic timer operates and activates the ram 28, of the fixed clamping means 22'. This results in the clamping means 22' securely holding the tendon 12 by means of the plates 30 and 32.
  • the ram 28, of the slidable clamp means 22, is deactivated to allow the tendon 12 to slide between its plates 30 and 32.
  • the ram 44 is then activated and causes the plunger 45 to move to the left, toward the fixed clamp means 22'. This moves the carriage 54, with the slidable clamp means 22, to the left, toward the fixed clamp means 22'.
  • the ram 44 is deactivated.
  • the ram 28, of the slidable clamp means 22, is then activated to clamp the tendon 12 between the plates 30 and 32.
  • the ram 44 is then reactivated. This causes the plunger 45 to bear upon the plates 30 and 32, of the slidable clamp means 22, and displace the slidable clamp means 22 towards the fixed clamp means 22 l . Such relative displacement causes the bulbous portions 16 to be formed in the tendon 12 between the clamp means 22 and 22'.
  • the ram 44 then withdraws the plunger 45 away from the fixed clamp means 22'. This moves the carriage 54 with the slidable clamp means 22, to the right, away from the fixed clamp means 22'.
  • the ram 28, of the slidable clamp means 22, is then activated to clamp the tendon 12 by means of the plates 30 and 32.
  • the ram 28, of the fixed clamp means 22' is then deactivated to release the tendon 12.
  • the ram 44 is then activated, the plunger 45 extends and moves the carriage 54 and slidable clamp means 22 towards the fixed clamp means 22'.
  • the slidable clamp means 22 and the ram 44 function as a tendon displacement means to move the tendon 12.
  • This also moves the rock anchor 10 to the left and into the str ⁇ ght pipe 61.
  • the pipe 61 generally straightens out any bends that may have occurred when the bulbous portion 16 was formed.
  • the ram 44 is then deactivated to prevent any further movement of the tendon 12.
  • FIG. 6 and 9 Shown in “ Figures 6 and 9 is a third embodiment of an apparatus 66 for manufacturing a rock anchor 10 which is'a modification of the apparatus 52 of Figures 4, 5, 7 and 8. Like numerals denote like parts.
  • the apparatus 66 additionally comprises a tendon displacement means 68 to the right of the slidable clamp means 22 in Figure 6.
  • the tendon displacement means 68 comprises a slidable clamp means 70 carried by a carriage 72 slidable along the frame 24.
  • the clamp means 70 comprises an hydraulic ram 74 supplied with hydraulic pressure by a pipe 76.
  • the ram 74 has a plate 78 attached thereto to bear on and thereby clamp the tendon 12 against an opposed plate 80.
  • Each plate 78 and 80 has a recess 82, in a similar manner to the machine 52 of Figures 4, 5, 7 and 8.
  • the plates 78 and 80 have a centralising pin 84 located below the half recesses 82, in a similar manner to the machine 52 of Figures 4, 5, 7 and 8.
  • the tendon displacement means 68 further comprises a clamp displacement means in the form of an hydraulic ram 86 supplied with hydraulic pressure through a pipe 88.
  • the ram 86 has a plunger 90 which bears on the carriage 72 and is arranged to displace the sliding clamp means 70 to the left, as shown in Figure 6.
  • the tendon displacement means 68 is a separate item, as compared to the tendon displacement means of the apparatus 52.
  • the pipes 58 and 60 are connected to a common manifold 92 supplied with hydraulic pressure by a pipe 94.
  • a tendon 12 is first fed through between the plates 78 and 80, through the ram 44, between the plates 30 and 32, of the clamp means 22 and 22' and into the plate 61.
  • An hydraulic timer operates and simultaneously activates both of the rams 28 so that the clamps 22 and 22' securely hold the tendon 12..
  • the ram 86 is reactivated to allow the tendon 12 to slide between the plates 78 and 80. Further, at this stage, the clamp means 22 and 22' are the first predetermined distance (as defined hereinbefore) apart.
  • the ram 44 is then activated to move the carriage 54 to the left, towards the fixed clamp means 22'. This relative displacement interrupts the tendon 12 and forms a bulbous portion 16.
  • both rams 28 and the ram 44 are deactivated.
  • Ram 74 is then activated so that the tendon 12 is securely held in the slidable clamp means 70 by the plates 78 and 80.
  • the ram 86 is then activated and the plunger 90 moves the carriage 72 to the left, towards the fixed clamp means 22'.
  • Both rams 28 are then simultaneously activated and the process is repeated as many times as desired.
  • the present invention provides a rock anchor which is easily manufactured and does not require unravelling of the strands, and more rock anchors may be produced in the same time as compared to prior art systems.
  • the rock anchor of the present invention With the rock anchor of the present invention, the strands in the bulbous portions are separated and hence the rock anchor will be firmly embedded in the cement in the bore hole.
  • the tendon displacement means may alternately comprise an electric motor driving a wheel.
  • An idler wheel would bear upon the driven wheel and the tnedon would pass between the idler and driven wheels.
  • a timer would activate an electric motor to rotate the driven wheel and thereby move the tendon.
  • Modifications and variations such as would be apparent to a skilled addressee are deemed within the scope of the present invention.
  • the machine 20 may be provided with a hydraulic timer to co-ordinate the activation of the rams 28 and 44.
  • the ram 44 may have an adjustment means in the form of a threaded column to vary the position of the ram 44 along the frame.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Piles And Underground Anchors (AREA)
  • Dowels (AREA)
  • Curing Cements, Concrete, And Artificial Stone (AREA)
EP89912755A 1988-11-14 1989-11-14 Felsenanker und verfahren zur herstellung Expired - Lifetime EP0442935B1 (de)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
AU1416/88 1988-11-14
AUPJ141688 1988-11-14
PCT/AU1989/000486 WO1990005811A1 (en) 1988-11-14 1989-11-14 Improved rock anchor and method of manufacture

Publications (3)

Publication Number Publication Date
EP0442935A1 true EP0442935A1 (de) 1991-08-28
EP0442935A4 EP0442935A4 (en) 1992-06-03
EP0442935B1 EP0442935B1 (de) 1995-09-06

Family

ID=3773499

Family Applications (1)

Application Number Title Priority Date Filing Date
EP89912755A Expired - Lifetime EP0442935B1 (de) 1988-11-14 1989-11-14 Felsenanker und verfahren zur herstellung

Country Status (6)

Country Link
EP (1) EP0442935B1 (de)
AT (1) ATE127550T1 (de)
CA (1) CA2002806C (de)
DE (1) DE68924171T2 (de)
WO (1) WO1990005811A1 (de)
ZA (1) ZA898640B (de)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111842722A (zh) * 2020-08-30 2020-10-30 尤加东 一种钢绞线墩头

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5570976A (en) * 1991-07-26 1996-11-05 J.J.P. Geotechnical Engineering Pty. Ltd. Cable bolt
DE4203740C2 (de) * 1992-02-09 1996-07-11 Dyckerhoff & Widmann Ag Verfahren zum Herstellen eines Ankerelementes aus einer Litze aus verdrillten Stahldrähten
FR2726585A1 (fr) * 1994-11-09 1996-05-10 Fortin Jean Moyen d'ancrage d'un surmoulage plastique ou autre sur du cable
AU2005200714B2 (en) 2005-02-17 2011-10-27 Fci Holdings Delaware, Inc. Cable bulbing apparatus and method for forming bulbs in a cable bolt
KR101043127B1 (ko) * 2008-02-22 2011-06-20 (주) 케이씨지 Pc강연선을 이용한 지반보강공법 및 지반보강장치
WO2011047416A1 (en) * 2009-10-23 2011-04-28 Garford Pty Ltd Cable bolt

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1024696A (en) * 1962-10-26 1966-03-30 Cementation Co Ltd Improvements relating to subterranean anchorages
GB975642A (en) * 1962-11-12 1964-11-18 Cementation Co Ltd Improvements relating to subterranean anchorages
US3727298A (en) * 1971-06-10 1973-04-17 North American Rockwell Friction welding method
FR2378123A1 (fr) * 1977-01-24 1978-08-18 Bouvet Ets H Procede de fabrication d'une bequille metallique pour serrure et dispositif pour la mise en oeuvre du procede
FR2385485A1 (fr) * 1977-03-30 1978-10-27 Petroles Cie Francaise Machine d'aboutage de conduites pour pose en eaux de toutes profondeurs
CA1059351A (en) * 1977-11-01 1979-07-31 Paul J. Villgren Cable bolt
CH632948A5 (de) * 1978-11-10 1982-11-15 Schlatter Ag Einrichtung zum stirnseitigen aneinanderschweissen zweier profilstangen.
AU7976382A (en) * 1981-01-27 1982-08-05 Barry Garfield Frederick Pipe joining apparatus
US4492015A (en) * 1982-06-24 1985-01-08 Dearman Timothy Charles Apparatus for use in welding
US4722468A (en) * 1982-07-20 1988-02-02 Mcclure Gary W Boiler pipe tool for heliarc welding with tongue and groove interlock
GB8321550D0 (en) * 1983-08-10 1983-09-14 Dividag Systems Ltd Anchor
FR2571996B1 (fr) * 1984-10-22 1986-12-26 Alsthom Atlantique Dispositif exterieur d'aboutage de deux elements tubulaires en vue de leur assemblage par soudage
US4750662A (en) * 1987-02-10 1988-06-14 Larry And Associates Pipe welding alignment tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111842722A (zh) * 2020-08-30 2020-10-30 尤加东 一种钢绞线墩头

Also Published As

Publication number Publication date
DE68924171T2 (de) 1996-02-22
EP0442935A4 (en) 1992-06-03
CA2002806A1 (en) 1990-05-14
WO1990005811A1 (en) 1990-05-31
DE68924171D1 (de) 1995-10-12
CA2002806C (en) 1995-08-08
ZA898640B (en) 1990-09-26
CA2002806F (en) 1990-05-14
ATE127550T1 (de) 1995-09-15
EP0442935B1 (de) 1995-09-06

Similar Documents

Publication Publication Date Title
US5344256A (en) Rock anchor and method of manufacture
DE69725661T2 (de) Verfahren und gerät zur herstellung von nähfaden-nadel-zusammensetzung
US3658296A (en) System for post-tensioning and anchoring prestressing tendons
KR101989078B1 (ko) 렌치볼트 제조방법
US3140540A (en) Method for connecting presemiflanged rungs to preapertured spaced ladder rails
EP0442935A1 (de) Felsenanker und verfahren zur herstellung.
RU2764162C2 (ru) Устройство и способ изготовления проволочной сетки
CN116079319A (zh) 一种金属护栏加工用焊接设备
US4340802A (en) Method and apparatus for welding
GB2076714A (en) Method and apparatus for manufacturing double conical springs and the like
AU640906C (en) Improved rock anchor and method of manufacture
AU4621589A (en) Improved rock anchor and method of manufacture
EP0413790B1 (de) Kaltpressschweissmaschine und verfahren
US4312173A (en) Apparatus for bundling rods, tubes, sections, etc.
US3762196A (en) Pipe bending machine
KR101509182B1 (ko) 철근의 나사선 가공 장치
US3526941A (en) Method of fastening anchoring means to a tensioning wire
JP4047299B2 (ja) 鉄筋端部の熱間据込み加工装置及び熱間据込み加工方法
DE3231413C2 (de)
DE69704108T2 (de) Maschine und Verfahren zum Quetschen von einer Müffe an einem Betonstahl
CH693087A5 (de) Seilsägemaschine
US3426810A (en) Method of producing a grid reinforcement for concrete
US4813262A (en) Method for forming loop-shaped starting pieces such as metallic binding bands into prescribed final shapes
US4486991A (en) Tie-anchor for reinforcing cable
AU723113B2 (en) Bulb forming machine

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

17P Request for examination filed

Effective date: 19910514

AK Designated contracting states

Kind code of ref document: A1

Designated state(s): AT BE CH DE FR GB IT LI LU NL SE

A4 Supplementary search report drawn up and despatched

Effective date: 19920416

AK Designated contracting states

Kind code of ref document: A4

Designated state(s): AT BE CH DE FR GB IT LI LU NL SE

17Q First examination report despatched

Effective date: 19940316

GRAA (expected) grant

Free format text: ORIGINAL CODE: 0009210

AK Designated contracting states

Kind code of ref document: B1

Designated state(s): AT BE CH DE FR GB IT LI LU NL SE

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: AT

Effective date: 19950906

Ref country code: BE

Effective date: 19950906

Ref country code: NL

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 19950906

Ref country code: FR

Effective date: 19950906

REF Corresponds to:

Ref document number: 127550

Country of ref document: AT

Date of ref document: 19950915

Kind code of ref document: T

REF Corresponds to:

Ref document number: 68924171

Country of ref document: DE

Date of ref document: 19951012

ITF It: translation for a ep patent filed
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LU

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 19951130

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: CH

Payment date: 19951130

Year of fee payment: 7

NLV1 Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act
EN Fr: translation not filed
REG Reference to a national code

Ref country code: CH

Ref legal event code: PL

PLBE No opposition filed within time limit

Free format text: ORIGINAL CODE: 0009261

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT

26N No opposition filed
PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: LI

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 19961130

Ref country code: CH

Free format text: LAPSE BECAUSE OF FAILURE TO SUBMIT A TRANSLATION OF THE DESCRIPTION OR TO PAY THE FEE WITHIN THE PRESCRIBED TIME-LIMIT

Effective date: 19961130

REG Reference to a national code

Ref country code: GB

Ref legal event code: IF02

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: DE

Payment date: 20031105

Year of fee payment: 15

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: DE

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES

Effective date: 20050601

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: IT

Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED.

Effective date: 20051114

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: SE

Payment date: 20081107

Year of fee payment: 20

PGFP Annual fee paid to national office [announced via postgrant information from national office to epo]

Ref country code: GB

Payment date: 20081127

Year of fee payment: 20

REG Reference to a national code

Ref country code: GB

Ref legal event code: PE20

Expiry date: 20091113

PG25 Lapsed in a contracting state [announced via postgrant information from national office to epo]

Ref country code: GB

Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION

Effective date: 20091113