EP0317458A1 - Process and apparatus for laying a foundation by creating a solid mass constituted by the soil itself - Google Patents
Process and apparatus for laying a foundation by creating a solid mass constituted by the soil itself Download PDFInfo
- Publication number
- EP0317458A1 EP0317458A1 EP88430029A EP88430029A EP0317458A1 EP 0317458 A1 EP0317458 A1 EP 0317458A1 EP 88430029 A EP88430029 A EP 88430029A EP 88430029 A EP88430029 A EP 88430029A EP 0317458 A1 EP0317458 A1 EP 0317458A1
- Authority
- EP
- European Patent Office
- Prior art keywords
- slab
- anchor
- anchoring
- ground
- tie rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/50—Anchored foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/28—Stressing the soil or the foundation structure while forming foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/803—Ground anchors with pivotable anchoring members
Definitions
- the present invention relates to a method and a device for implementing a foundation by creating a solid mass formed by the soil itself.
- the technical sector of the invention is that of foundations for works made on the surface, such as electrical pylons, antennas or other similar works.
- foundations used industrially are based on the following bases: - Either make heavy foundations, a concrete block for example, embedded or in the ground.
- the tensile force on this type of solid in the case of a non-embedded solid must remain less than the weight of the foundation if we want it to maintain its effectiveness.
- the tensile force In the case of a bed embedded in the ground, the tensile force must remain lower than the sum of the following data: weight of the bed, weight of the earth above the bed, resulting on the bed of the lateral friction forces , sucking on the massif. It is noted in the case of an embedded solid that a major drawback, the rupture of the concrete solid, can occur if the following eventuality occurs: tensile force on the concrete greater than the weight of the foundation but less than the conjugation of the lateral friction and suction forces.
- the present invention aims to remedy the drawbacks of foundations currently used industrially and which have just been mentioned.
- the objective to be achieved is to create foundations by creating a massif made up of the soil itself.
- a loaded foundation induces a settlement of ground.
- the objective of the present invention is achieved by the method for implementing a foundation by creating a solid mass constituted by the soil itself, according to which method: - At least one deep anchoring point is made using anchoring means which are driven into the ground by threshing, which means extend in the anchoring position towards the ground surface to extend beyond of this surface; - a slab is placed on the surface which has at least one opening for the passage of the extensions of said anchoring means, - And a traction is exerted on this slab to prestress the ground by means of tensioning said anchoring means located above said slab until the service force necessary to maintain the structure to be achieved is obtained. area.
- a deep anchoring point is produced, so as to obtain an underground effect of a ground stop by anchoring means capable of being placed in a position substantially parallel to the surface of the ground and where is disposed said slab.
- a direct evaluation and control of the soil stress is obtained by using a slab whose face brought into contact with the ground has an area equal to a multiple or an integer sub-multiple of the square meter.
- a device which is characterized by the fact that it is made up of anchoring means comprising at least one anchoring line extending towards the surface of the ground to extend beyond of this surface, which anchor line is passed through a reserved opening in a slab bearing on the ground, which anchor line is connected to means for its tensioning, which are supported on said slab to put the soil in prestress under the effect of a traction exerted on the slab in the direction of the anchor point.
- the anchoring means of consist of an anchor comprising a rigid body comprising at least one end for attacking the ground and another end comprising an anvil to which a driving force is applied by threshing, which anchor further comprises a fin articulated about an axis transverse to said body and having a limited angle of movement of the order of 45 °, at least one anchoring line connected to said body at at least one point located between said end of attack and the center of gravity of the anchor body, said articulated fin being located opposite the attack end and whose pivot axis is offset from the median plane of the anchor body in which plane is located the threshing axis, in which the anchoring line is constituted by at least one tie rod connected to a fixing member pivoting about a transverse axis located in said median plane of the body of the anchor, which pulling is rigid and is made pa r a rod or a tube comprising connection means for aligning several tie rods as a function of the depth of insertion of the anchor into the ground, so that the last tie rod
- the aligned tie rods which constitute the anchor line, have their axis located substantially in the median plane of the body of the anchor and are located substantially in the center of the anvil. .
- the anvil is struck by means of open or closed cross-section profiles which surround the anchor line and which extend above the ground surface to be subjected to the action of threshing means.
- the slab has, on its upper face, a metal plate comprising an orifice situated to the right of the orifice of the slab, which is of a diameter greater than that of the slab to allow adjustments on two axes x / y.
- the means for tensioning the anchoring line consist of a frame bearing on said metal plate of the slab and comprising a conical housing whose generatrices of the wall converge towards the anchoring means at a point located on the axis of the tie rods constituting the anchor line whose last tie rod, which crosses the slab, extends into said conical housing and is threaded at its end to cooperate with a locking nut acting on corners placed in the conical housing and around the two tie rods by means of a ring inserted between the corners and the locking nut.
- the periphery of the tie rod coming into contact with the locking corners is ridged or has micro-threads to increase the anchoring of the corners on the tie rod.
- Said conical housing is reserved in a moving part, guided vertically on said frame, which moving part is supported on elastic means which surround the tie rod and which are inserted between said moving part and the bottom of the frame.
- the means for tensioning the anchor line consist of a beam to which is fixed the last tie rod which passes through the slab and the metal plate, which beam is located above the slab and the plate and is subjected to the action of at least two jacks located on either side of the tie rod and resting on the metal plate which covers the slab.
- Said beam comprises, in the middle, a ring comprising a conical orifice whose generatrices of the wall converge on the side of the anchoring point on a point situated on the axis of the tie rod and the fixing of the tie rod to the beam is carried out by locking corners distributed around the tie rod and arranged in the annular space existing between the tie rod and the conical orifice.
- the metal plate which covers the slab has a boss comprising a conical orifice coaxial with the orifice of the slab and whose generatrices of its wall converge on the side of the anchoring point on a point located on the axis of the tie rod and the support in tension of the anchoring line is obtained by locking wedges distributed around the tie rod and arranged in the annular space existing between the tie rod and the conical orifice of said boss so as to cancel the pressure of the fluid of the hydraulic circuit leading to said cylinders.
- the periphery of the tie rods brought into contact with the locking corners is ridged or has micro-threads to increase anchoring the corners on the tie rod.
- a predetermined holding point is placed at a certain depth in the ground.
- This holding point constitutes an anchor on which, from the surface, it is taken up again by means of a steel plate covering a concrete slab, or else by a steel plate or simply a concrete slab.
- the soil mass located below the slab, after stressing, has different mechanical characteristics from those existing before stressing. It is from these new mechanical characteristics that the strength of the massif as a foundation is determined.
- a vertical tension is exerted downwards on a plate (or slab) placed on the ground.
- This tension is obtained by the stiffening of an anchoring line fixed by one of its ends to a deep anchoring point to benefit from the underground effect of the ground stop and at its other end for example by tightening a bolt on the last element of the tie rod which constitutes said anchor line and which crosses the plate (or slab) placed on the surface.
- the underground effect of the floor stop can be obtained either by, for example, a plate-shaped anchor or by the articulated element anchoring device having a bent shape, which has been the subject of a patent application. French registered under No 84 07281.
- the junction between the underground floor stop device and the surface plate is made by means of tie rods constituted by a cable, a rod or a tube (or sets of rods or tubes) sized for the required force.
- the resumption of the effort on the tie is made by means of a system of claw corners or other equivalent means to avoid slippage.
- the surface plate is dimensioned in such a way that an evaluation and direct control of the soil stress can be obtained during the tensioning of the tie rod.
- the plate or the plate and the concrete slab
- the plate is made so that its surface is a multiple or an integer sub-multiple of the square meter.
- the underground anchor is installed by threshing.
- the stress recovery rod or tube is integral with the underground anchor.
- the anchor line consisting of a cable, a rod or a tube (or sets of rods and tubes) is put in place by means of false pile drivers constituted by tubes or profiles, in U for example, during threshing, at the same time as the anchoring.
- false pile drivers constituted by tubes or profiles, in U for example, during threshing.
- the rod or tube (or drill string or tube) that connects the underground anchor to the plate (and / or the surface slab) is gripped by the means described above by tightening the bolt or by other means comprising cylinders with pneumatic or hydraulic operation until the service force imposed by the structure produced is obtained. area.
- Elastic means such as springs or Belleville washers for example can be incorporated on the surface at the upper end of the head tie to compensate or take up the forces.
- the method according to the invention offers the advantage of being able to predetermine the holding capacity of the mass of land under stress and of improving it by stiffening more or less the surface plate (and / or slab) at its point. underground anchor. Indeed, throughout the threshing, knowing the master-couple at the sinking of the underground anchoring system, that is to say the contours of the cross sections to the axis of movement of the anchor line , we can, by knowing the threshing energy at each strike, determine the bearing capacity of the ground at each level of the anchoring. Furthermore, the surface plate (and / or slab) pulled towards the ground by the stiffening of the anchor line makes it possible, thanks to its compaction, to assess the stress of the ground on the surface. These two possibilities combined make it possible to correctly identify the possibilities of holding pre-stressed soil masses.
- the anchor 1 ( Figures 2 and 3) which is used in the device according to the invention is for example of the type of that described in French patent 84 07281. It is specified here that other similar anchoring means can find their application for the implementation of the method according to the invention.
- Such an anchor 1 comprises a rigid body comprising a conical or pyramidal part 1a1, the lower part of which ends with a leading end of the ground 1a2.
- Its upper part 1a3 is of a circular or square cross section and comprises an anvil 1a4 intended to be struck by driving forces obtained by threshing and by means of tubular elements or by U-shaped profiles 2, which surround an anchor line 3 fixed to a pivoting part 4 around an axis transverse to the anchor 1.
- the pivot axis 4a of the part 4 is located between the end 1a2 and the center of gravity of the anchor and in the plane of symmetry of the body 1a.
- the anchor 1 Opposite the leading end of the ground 1a2, the anchor 1 comprises an articulated element 5 forming a kind of fin, which is pivotally mounted on the body 1a around an axis 5a transverse to the anchor and offset with respect to the plane of symmetry of the body la in which the pivot axis 4a of the part 4 is also located.
- the articulated element 5 is designed to have a limited angular movement of the order of 45 °.
- the anchor 1 comprises a plate 6 projecting symmetrically with respect to the body 1a (FIG. 2) and comprising a rectangular part 6a, extending approximately from the axis pivot 5a of the articulated element 5 to the pivot axis 4a of the part 4, the cross section of the anchor at this location constituting the master torque of the anchor.
- the plate 6 is extended towards the leading end of the ground 1a2 by a symmetrical profiled part 6b to promote the penetration of the anchor into the ground, which part 6b is delimited by a series of edges 6b1 / 6b2 / 6b3 / 6b4 which converge at different angles on the axis of symmetry XX1 of the anchor.
- the plate 6 is stiffened by gussets 7/8 fixed on either side of the plate 6 forming deflectors and which converge on the axis of symmetry of the anchor XX1 to promote the penetration of the anchor into the ground .
- the anchor line 3 In the insertion position of the anchor 1, the anchor line 3 is located in the axis XX1 of the anchor 1.
- the anchor line and the intermediate threshing elements 2, or false threshing piles are substantially coaxial when these are formed by tubes.
- FIG. 1 of the drawing represents the anchoring of a pylon foot 9, which rests on the ground by means of a reinforced concrete slab 10, covered with a plate for example of steel 11, which slab and plate 10/11 are crossed by the anchor line 3.
- tie rods for example in the form of tubes 3a / 3b connected by a connection sleeve 12.
- FIG. 4 represents, on a larger scale, a pylon foot 9 and the means for tensioning the anchoring line to put the soil in prestress.
- the slab 10 has an orifice 10a, located to the right of an orifice 11a, of larger diameter, and reserved in the plate 11 which covers the upper face of the slab and to which plate is fixed the pylon foot 9.
- the difference the diameter of the orifices 10a / 11a allows adjustments to be made in X / Y of the plate 11 relative to the slab 10.
- Said pylon is in an inclined position and is constituted by a tubular element and has a manhole 9a to access the interior.
- the upper end of the tube 3b is passed through the holes 10a / 11a and extends inside the pylon foot 9 through a device for tensioning the anchor line.
- This device consists of a frame 13 bearing on the metal plate 11 and comprising a movable part 14 itself comprising a conical housing 15 in which the tube 3 has passed.
- the generatrices of the wall of said housing converge towards the anchor 1 at a point situated on the axis of the anchor line 3.
- the movable part 14 is supported on elastic means 15, for example Belleville washers, inserted between said movable part 14 and the bottom of the frame 13.
- the upper end 3b1 of the tube 3b is threaded and cooperates with a nut 17.
- a nut 17 In the conical housing 15 are arranged locking corners 18 distributed around the tube 3b, for example three in number and arranged at 120 °.
- a ring 19 disposed between the nut 17 and the corners 18 is connected to the latter by means of studs or other similar members 20.
- the tensioning of the anchor line 3 and correlatively, the prestressing of the ground is obtained by screwing the nut 17.
- the anchor pivots around the axis 4a, the fin 5 around the axis 5a until it comes to rest at the ground stop in a substantially parallel or ground position as shown in the drawing in FIG. 1.
- the periphery of the zone of the tie formed by the tube 3b brought into contact with the locking corners is ridged or has micro-threads to increase the anchoring of the corners in said tie.
- the prestressing of the ground is obtained by tightening more or less the nut 17 as that was previously exposed.
- These means consist of a beam 21 having in its middle a ring 22 comprising a conical orifice 22a whose generatrices of the wall converge towards the anchoring point on a point located on the axis of the tie rod 3b.
- the tie rod 3b is fixed to the beam 21 by locking corners 23, for example three in number and arranged at 120 °, distributed around the tie rod and arranged in the annular space existing between the tie rod 3b and the conical orifice 22a.
- the metal plate 11, which covers the slab 10 has a boss 24 comprising a conical orifice 24a coaxial with the orifice 10a of the slab and whose generatrices of its wall converge towards the anchoring point on a point located on the axis of the tube 3b.
- the tensioning of the anchor line is for example obtained by means of two cylinders 25/26, for example single acting and hydraulically operated.
- the tensioning of the anchoring line 3 is obtained for example by three locking corners 27 distributed at 120 ° around the tube 3b and arranged in the annular space existing between the tube and the conical orifice 24a.
- the periphery of the zones of the tubes 3b brought into contact with the locking corners 23/27 is striated or includes micro-threads for increase the anchoring of the corners in the tube. Also, the parts of the corners 18/23/27, brought into contact with the tubes can be serrated to further increase the embedding of the corners at the periphery of the tube.
- the method and the device according to the invention and, among other applications, can be used to stiffen clays or marls saturated or supersaturated with water or else to produce stable foundations in sand deserts.
Abstract
Description
La présente invention a pour objet un procédé et un dispositif pour mettre en oeuvre une fondation en créant un massif constitué par le sol lui-même.The present invention relates to a method and a device for implementing a foundation by creating a solid mass formed by the soil itself.
Le secteur technique de l'invention est celui des fondations pour des ouvrages réalisés en surface, tels que les pylones électriques, des antennes ou autres ouvrages similaires.The technical sector of the invention is that of foundations for works made on the surface, such as electrical pylons, antennas or other similar works.
Actuellement de tels ouvrages sont ancrés dans le sol dans des fondations généralement réalisées au moyen de massifs en béton, en béton armé ou en béton précontraint. Un autre moyen de mettre en oeuvre de telles fondations est de réaliser des points d'ancrage au moyen de pieux ou de groupes de pieux battus.Currently, such structures are anchored in the ground in foundations generally made using concrete, reinforced concrete or prestressed concrete foundations. Another means of implementing such foundations is to make anchor points by means of piles or groups of driven piles.
Les types de fondations utilisées industriellement reposent sur les bases suivantes :
- Soit réaliser des fondations d'un poids important, un bloc de béton par exemple, encastré ou dans le sol. L'effort à la traction sur ce type de massif dans le cas d'un massif non encastré doit rester inférieur au poids de la fondation si l'on veut que cette dernière conserve son efficacité.The types of foundations used industrially are based on the following bases:
- Either make heavy foundations, a concrete block for example, embedded or in the ground. The tensile force on this type of solid in the case of a non-embedded solid must remain less than the weight of the foundation if we want it to maintain its effectiveness.
Dans le cas d'un massif encastré dans le sol, l'effort à la traction doit rester inférieur à la somme des données suivantes : poids du massif, poids des terres au-dessus du massif, résultante sur le massif des forces de frottement latérales, succion sur le massif. On constate dans le cas d'un massif encastré qu'un inconvénient majeur, la rupture du massif de béton, peut se produire si l'éventualité suivante se présente : effort de traction sur le béton supérieur au poids de la fondation mais inférieur à la conjugaison des forces de frottement latérales et de succion.In the case of a bed embedded in the ground, the tensile force must remain lower than the sum of the following data: weight of the bed, weight of the earth above the bed, resulting on the bed of the lateral friction forces , sucking on the massif. It is noted in the case of an embedded solid that a major drawback, the rupture of the concrete solid, can occur if the following eventuality occurs: tensile force on the concrete greater than the weight of the foundation but less than the conjugation of the lateral friction and suction forces.
Par ailleurs un massif poids doit travailler dans sont tiers central, si un tassement différentiel se produit, il peut y avoir basculement du massif.
- Soit placer des pieux battus ou forés.In addition, a massive weight must work in its central third, if differential settlement occurs, there may be tilting of the massif.
- Either place beaten or bored piles.
Dans de telles fondations, les risques de tassements différentiels sont très minimes voire inexistants, cependant de telles fondations résistent mal aux efforts latéraux (cycliques ou non) pour lesquels les risques de déchaussement restent certains.In such foundations, the risks of differential settlements are very minimal or even nonexistent, however such foundations resist resistance to lateral forces (cyclic or not) for which the risks of heaving remain certain.
La présente invention vise à remédier aux inconvénients des fondations actuellement utilisées industriellement et qui viennent d'être évoquées.The present invention aims to remedy the drawbacks of foundations currently used industrially and which have just been mentioned.
L'objectif à atteindre est de réaliser des fondations en créant un massif constitué par le sol lui-même.The objective to be achieved is to create foundations by creating a massif made up of the soil itself.
Une fondation chargée induit un tassement de terrain.A loaded foundation induces a settlement of ground.
Si les charges de services de l'ouvrage réalisé en surface, impliquent des efforts de traction, le comportement de la fondation pose un problème de tenue eu égard à la mauvaise, sinon inexistante résistance à la traction du sol.If the service loads of the work carried out on the surface, involve tensile forces, the behavior of the foundation poses a problem of behavior in view of the poor, if not non-existent tensile strength of the soil.
L'objectif de la présente invention est atteint par le procédé pour mettre en oeuvre une fondation en créant un massif constitué par le sol lui-même selon lequel procédé :
- on réalise au moins un point d'ancrage profond en utilisant des moyens d'ancrage que l'on enfonce dans le sol par battage, lesquels moyens se prolongent en position d'ancrage vers la surface du sol pour s'étendre au-delà de cette surface;
- on place en surface une dalle qui comporte au moins une ouverture pour le passage des prolongements desdits moyens d'ancrage,
- et on exerce une traction sur cette dalle pour précontraindre le sol par des moyens de mise en tension desdits moyens d'ancrage situés au-dessus de ladite dalle jusqu'à obtenir la force de service nécessaire au maintien de l'ouvrage à réaliser en surface.The objective of the present invention is achieved by the method for implementing a foundation by creating a solid mass constituted by the soil itself, according to which method:
- At least one deep anchoring point is made using anchoring means which are driven into the ground by threshing, which means extend in the anchoring position towards the ground surface to extend beyond of this surface;
- a slab is placed on the surface which has at least one opening for the passage of the extensions of said anchoring means,
- And a traction is exerted on this slab to prestress the ground by means of tensioning said anchoring means located above said slab until the service force necessary to maintain the structure to be achieved is obtained. area.
Selon un mode préférentiel de mise en oeuvre dudit procédé, on réalise un point d'ancrage profond, de façon à obtenir un effet souterrain de butée de sol par des moyens d'ancrage susceptibles de se mettre dans une position sensiblement parallèle à la surface du sol et où est disposée ladite dalle.According to a preferred embodiment of said method, a deep anchoring point is produced, so as to obtain an underground effect of a ground stop by anchoring means capable of being placed in a position substantially parallel to the surface of the ground and where is disposed said slab.
Selon le procédé, on obtient une évaluatin et un contrôle directs de la contrainte du sol en utilisant une dalle dont la face mise au contact du sol est d'une surface égale à un multiple ou un sous-multiple entier du mètre carré.According to the method, a direct evaluation and control of the soil stress is obtained by using a slab whose face brought into contact with the ground has an area equal to a multiple or an integer sub-multiple of the square meter.
Pour la mise en oeuvre de ce procédé, on utilise un dispositif se caractérisant par le fait qu'il se compose de moyens d'ancrage comportant au moins une ligne d'ancrage s'étendant vers la surface du sol pour se prolonger au-delà de cette surface, laquelle ligne d'ancrage est passée dans un orifice réservé dans une dalle en appui sur le sol, laquelle ligne d'ancrage est reliée à des moyens pour sa mise en tension , lesquels sont en appui sur ladite dalle pour mettre le sol en précontrainte sous l'effet d'une traction exercée sur la dalle dans la direction du point d'ancrage.For the implementation of this method, a device is used which is characterized by the fact that it is made up of anchoring means comprising at least one anchoring line extending towards the surface of the ground to extend beyond of this surface, which anchor line is passed through a reserved opening in a slab bearing on the ground, which anchor line is connected to means for its tensioning, which are supported on said slab to put the soil in prestress under the effect of a traction exerted on the slab in the direction of the anchor point.
Dans un tel dispositif dont les moyens d'ancrage sont constitués par une ancre comprenant un corps rigide comportant au moins une extrémité d'attaque du sol et une autre extrémité comportant une enclume sur laquelle on applique une force d'enfoncement par battage, laquelle ancre comporte en outre un aileron articulé autour d'un axe transversal audit corps et ayant un angle de débattement limité de l'ordre de 45°, au moins une ligne d'ancrage reliée audit corps à au moins un point situé entre ladite extrémité d'attaque et le centre de gravite du corps de l'ancre, ledit aileron articulé étant situé à l'opposé de l'extrémité d'attaque et dont l'axe de pivotement est décalé par rapport au plan médian du corps de l'ancre dans lequel plan se situe l'axe de battage, dans lequel la ligne d'ancrage est constituée par au moins un tirant relié à un organe de fixation pivotant autour d'un axe transversal situé dans ledit plan médian du corps de l'ancre, lequel tirant est rigide et est constitué par une tige ou un tube comportant des moyens de raccordement pour pourvoir aligner plusieurs tirants en fonction de la profondeur d'enfoncement de l'ancre dans le sol, de telle sorte que le dernier tirant s'étende au-delà du niveau du sol pour permettre la mise en tension de la ligne d'ancrage.In such a device, the anchoring means of which consist of an anchor comprising a rigid body comprising at least one end for attacking the ground and another end comprising an anvil to which a driving force is applied by threshing, which anchor further comprises a fin articulated about an axis transverse to said body and having a limited angle of movement of the order of 45 °, at least one anchoring line connected to said body at at least one point located between said end of attack and the center of gravity of the anchor body, said articulated fin being located opposite the attack end and whose pivot axis is offset from the median plane of the anchor body in which plane is located the threshing axis, in which the anchoring line is constituted by at least one tie rod connected to a fixing member pivoting about a transverse axis located in said median plane of the body of the anchor, which pulling is rigid and is made pa r a rod or a tube comprising connection means for aligning several tie rods as a function of the depth of insertion of the anchor into the ground, so that the last tie rod extends beyond the level of the ground for allow tensioning of the anchor line.
En position d'enfoncement de l'ancre dans le sol, les tirants alignés, qui constituent la ligne d'ancrage, ont leur axe situé sensiblement dans le plan médian du corps de l'ancre et se situent sensiblement au centre de l'enclume.In the position of driving the anchor into the ground, the aligned tie rods, which constitute the anchor line, have their axis located substantially in the median plane of the body of the anchor and are located substantially in the center of the anvil. .
Pour enfoncer l'ancre dans le sol, l'enclume est frappée par l'intermédiaire de profilés à section droite ouverte ou fermée qui entourent la ligne d'ancrage et qui se prolongent au-dessus de la surface du sol pour être soumis à l'action des moyens de battage.To drive the anchor into the ground, the anvil is struck by means of open or closed cross-section profiles which surround the anchor line and which extend above the ground surface to be subjected to the action of threshing means.
De préférence, la dalle comporte, sur sa face supérieure, une plaque métallique comportant un orifice situé au droit de l'orifice de la dalle, lequel est d'un diamètre supérieur à celui de la dalle pour permettre des réglages sur deux axes x/y.Preferably, the slab has, on its upper face, a metal plate comprising an orifice situated to the right of the orifice of the slab, which is of a diameter greater than that of the slab to allow adjustments on two axes x / y.
Selon un mode de réalisation, les moyens pour la mise en tension de la ligne d'ancrage se composent d'un bâti en appui sur ladite plaque métallique de la dalle et comprenant un logement conique dont les génératrices de la paroi convergent vers les moyens d'ancrage sur un point situé sur l'axe des tirants constituant la ligne d'ancrage dont le dernier tirant, qui traverse la dalle, se prolonge dans ledit logement conique et est fileté à son extrémité pour coopérer avec un écrou de blocage agissant sur des coins placés dans le logement conique et autour des deux tirants par l'intermédiaire d'une bague insérée entre les coins et l'écrou de blocage.According to one embodiment, the means for tensioning the anchoring line consist of a frame bearing on said metal plate of the slab and comprising a conical housing whose generatrices of the wall converge towards the anchoring means at a point located on the axis of the tie rods constituting the anchor line whose last tie rod, which crosses the slab, extends into said conical housing and is threaded at its end to cooperate with a locking nut acting on corners placed in the conical housing and around the two tie rods by means of a ring inserted between the corners and the locking nut.
La périphérie du tirant mise au contact des coins de blocage est striée ou comporte des micro-filetages pour accroître l'ancrage des coins sur le tirant.The periphery of the tie rod coming into contact with the locking corners is ridged or has micro-threads to increase the anchoring of the corners on the tie rod.
Ledit logement conique est réservé dans une pièce mobile, guidée dans le sens vertical sur ledit bâti, laquelle pièce mobile est en appui sur des moyens élastiques qui entourent le tirant et qui sont insérés entre ladite pièce mobile et le fond du bâti.Said conical housing is reserved in a moving part, guided vertically on said frame, which moving part is supported on elastic means which surround the tie rod and which are inserted between said moving part and the bottom of the frame.
Selon un autre mode de réalisation, les moyens pour la mise en tension de la ligne d'ancrage se composent d'une poutre à laquelle est fixé le dernier tirant qui traverse la dalle et la plaque métallique, laquelle poutre est située au-dessus de la dalle et de la plaque et est soumise à l'action d'au moins deux vérins situés de part et d'autre du tirant et en appui sur la plaque métallique qui recouvre la dalle.According to another embodiment, the means for tensioning the anchor line consist of a beam to which is fixed the last tie rod which passes through the slab and the metal plate, which beam is located above the slab and the plate and is subjected to the action of at least two jacks located on either side of the tie rod and resting on the metal plate which covers the slab.
Ladite poutre comporte, en son milieu, une bague comportant un orifice conique dont les génératrices de la paroi convergent du côté du point d'ancrage sur un point situé sur l'axe du tirant et la fixation du tirant à la poutre est réalisée par des coins de blocage répartis autour du tirant et disposés dans l'espace annulaire existant entre le tirant et l'orifice conique.Said beam comprises, in the middle, a ring comprising a conical orifice whose generatrices of the wall converge on the side of the anchoring point on a point situated on the axis of the tie rod and the fixing of the tie rod to the beam is carried out by locking corners distributed around the tie rod and arranged in the annular space existing between the tie rod and the conical orifice.
La plaque métallique qui recouvre la dalle comporte un bossage comportant un orifice conique coaxial à l'orifice de la dalle et dont les génératrices de sa paroi convergent du côté du point d'ancrage sur un point situé sur l'axe du tirant et le maintien en tension de la ligne d'ancrage est obtenu par des coins de blocage répartis autour du tirant et disposés dans l'espace annulaire existant entre le tirant et l'orifice conique dudit bossage de manière à annuler la pression du fluide du circuit hydraulique aboutissant auxdits vérins.The metal plate which covers the slab has a boss comprising a conical orifice coaxial with the orifice of the slab and whose generatrices of its wall converge on the side of the anchoring point on a point located on the axis of the tie rod and the support in tension of the anchoring line is obtained by locking wedges distributed around the tie rod and arranged in the annular space existing between the tie rod and the conical orifice of said boss so as to cancel the pressure of the fluid of the hydraulic circuit leading to said cylinders.
La périphérie des zones du tirant mises au contact des coins de blocage est striée ou comporte des micro-filetages pour accroître l'ancrage des coins sur le tirant.The periphery of the tie rods brought into contact with the locking corners is ridged or has micro-threads to increase anchoring the corners on the tie rod.
Le principe de la précontrainte permet de décaler les efforts de services des ouvrages realisés en surface vers les compressions et de s'y maintenir pour ne travailler que dans le domaine des compressions stables.The principle of prestressing makes it possible to shift the service efforts of the works carried out on the surface towards the compressions and to remain there so as to work only in the field of stable compressions.
Dans une fondation réalisée par un massif de sol précontraint, un point de tenue prédéterminé est placé à une certaine profondeur dans le sol. Ce point de tenue constitue un ancrage sur lequel, à partir de la surface, on vient se reprendre par l'intermédiaire d'une plaque en acier recouvrant une dalle de béton, ou bien par une plaque en acier ou simplement une dalle de béton.In a foundation made by a pre-stressed soil mass, a predetermined holding point is placed at a certain depth in the ground. This holding point constitutes an anchor on which, from the surface, it is taken up again by means of a steel plate covering a concrete slab, or else by a steel plate or simply a concrete slab.
Le massif de sol situé au-dessous de la dalle, après mise en contrainte, possède des caractéristiques mécaniques différentes de celles existant avant la mise en contrainte. C'est à partir de ces nouvelles caractéristiques mécaniques que la tenue du massif en tant que fondation est déterminée.The soil mass located below the slab, after stressing, has different mechanical characteristics from those existing before stressing. It is from these new mechanical characteristics that the strength of the massif as a foundation is determined.
Sous la dalle en appui sur le sol par raidissement, sur l'ancrage, un réseau d'isocontraintes se répartit dans le sol affectant une partie du terrain avoisinant. Le volume, dont le poids des terres concernées par ces isocontraintes, est de ce fait bien supérieur à celui directement recouvert par la dalle et ainsi est capable de constituer un massif.Under the slab resting on the ground by stiffening, on the anchor, a network of iso-stresses is distributed in the ground affecting part of the neighboring land. The volume, including the weight of the earth affected by these iso-stresses, is therefore much greater than that directly covered by the slab and thus is capable of constituting a massif.
Pour la tenue des fondations, les inconvénients précédemment cités et inhérents à l'utilisation de massifs de béton encastrés ou non et aux pieux ou groupes de pieux enfoncés dans le sol, disparaissent pour la mise en oeuvre des fondations précontraintes en raison :
- de la suppression du tassement différentiel, la notion d'effort à support dans le tiers central disparaît, le travail se faisant dans l'axe de la fondation;
- de la suppression du risque de déchaussement du massif sollicité par des charges latérales si l'on considère l'importance du massif mobilisé par les isocontraintes.For the holding of foundations, the disadvantages previously mentioned and inherent in the use of concrete masses embedded or not and with piles or groups of piles driven into the ground, disappear for the implementation of prestressed foundations because:
- the elimination of differential settlement, the concept of support effort in the central third disappears, the work being done in line with the foundation;
- the elimination of the risk of loosening of the massif requested by lateral loads if we consider the importance of the massif mobilized by iso-stresses.
Les avantages ci-avant mentionnés s'expliquent par le fait que le comportement mécanique du sol peut être contrôlé et modulé par un raidissement plus ou moins important du sol sur un point d'ancrage profond, pour rester toujours en deça des limites du fluage du sol, des moyens mécaniques élastiques mis en place en surface permettront toujours de reprendre la variation des efforts mis en jeu.The advantages mentioned above are explained by the fact that the mechanical behavior of the soil can be controlled and modulated by a more or less significant stiffening of the soil on a deep anchor point, so as to always remain below the limits of the creep of the ground, elastic mechanical means installed on the surface will always allow the variation of the forces involved to be taken up again.
Selon le procédé pour réaliser un massif de sol précontraint, on exerce une tension verticale vers le bas sur une plaque (ou dalle) posée sur le sol. Cette tension s'obtient par le raidissement d'une ligne d'ancrage fixée par une de ses extrémités à un point d'ancrage profond pour bénéficier de l'effet souterrain de la butée de sol et à son autre extrémité par exemple par le serrage d'un boulon sur le dernier élément du tirant qui constitue ladite ligne d'ancrage et qui traverse la plaque (ou la dalle) placée en surface.According to the method for producing a pre-stressed soil mass, a vertical tension is exerted downwards on a plate (or slab) placed on the ground. This tension is obtained by the stiffening of an anchoring line fixed by one of its ends to a deep anchoring point to benefit from the underground effect of the ground stop and at its other end for example by tightening a bolt on the last element of the tie rod which constitutes said anchor line and which crosses the plate (or slab) placed on the surface.
L'effet souterrain de la butée de sol peut être obtenue soit par exemple par une ancre en forme de plaque ou encore par le dispositif d'ancrage à élément articulé ayant une forme coudée, qui a fait l'objet d'un dépôt de brevet français enregistré sous le No 84 07281.The underground effect of the floor stop can be obtained either by, for example, a plate-shaped anchor or by the articulated element anchoring device having a bent shape, which has been the subject of a patent application. French registered under No 84 07281.
La jonction entre le dispositif de butée de sol souterrain et la plaque de surface se fait au moyen de tirants constitués par un câble, une tige ou un tube (ou des trains de tiges ou de tubes) dimensionnés pour l'effort requis. La repris de l'effort sur le tirant se fait au moyen d'un système de coins à griffes ou autres moyens équivalents pour éviter les glissements.The junction between the underground floor stop device and the surface plate is made by means of tie rods constituted by a cable, a rod or a tube (or sets of rods or tubes) sized for the required force. The resumption of the effort on the tie is made by means of a system of claw corners or other equivalent means to avoid slippage.
Dans le but d'améliorer les performances antiglissantes du dispositif de blocage, on peut prévoir par exemple des micro-filetages sur le dernier tirant émergeant de la dalle en appui sur le sol dans la zone de contact avec les coins.In order to improve the non-slip performance of the blocking device, it is possible, for example, to provide micro-threads on the last tie emerging from the slab bearing on the ground in the area of contact with the corners.
Selon l'invention, la plaque de surface est dimensionnée de telle façon que l'on puisse obtenir une évaluation et un contrôle direct de la contrainte du sol au cours de la mise en tension du tirant. Pour obtenir cette évaluation, la plaque (ou la plaque et la dalle de béton) est réalisée de telle sorte que sa surface soit un multiple ou un sous-multiple entier du mètre carré.According to the invention, the surface plate is dimensioned in such a way that an evaluation and direct control of the soil stress can be obtained during the tensioning of the tie rod. To obtain this evaluation, the plate (or the plate and the concrete slab) is made so that its surface is a multiple or an integer sub-multiple of the square meter.
L'ancrage souterrain est mis en place par battage.The underground anchor is installed by threshing.
La tige ou le tube de reprise à l'effort de contrainte est solidaire de l'ancrage souterrain.The stress recovery rod or tube is integral with the underground anchor.
La ligne d'ancrage, constituée par un câble, une tige ou un tube (ou des trains de tiges et de tubes) est mise en place au moyen de faux pieux de battage constitués par des tubes ou des profilés, en U par exemple, au cours du battage, en même temps qui l'ancrage. Une fois l'ancrage souterrain positionné à la profondeur requise, les faux pieux de battage sont retirés. La tige ou le tube (ou le train de tiges ou de tubes) qui relie l'ancrage souterrain à la plaque (et/ou la dalle) de surface est saisie par les moyens décrits ci-dessus par serrage du boulon ou par d'autres moyens comportant des vérins à fonctionnements pneumatique ou hydraulique jusqu'à l'obtention de la force de service imposée par l'ouvrage réalisé en surface. Des moyens élastiques, tels que que des ressorts ou des rondelles Belleville par exemple peuvent être incorporés en surface à l'extrémité supérieure du tirant de tête pour compenser ou reprendre les efforts.The anchor line, consisting of a cable, a rod or a tube (or sets of rods and tubes) is put in place by means of false pile drivers constituted by tubes or profiles, in U for example, during threshing, at the same time as the anchoring. Once the underground anchor is positioned at the required depth, the pile drivers are removed. The rod or tube (or drill string or tube) that connects the underground anchor to the plate (and / or the surface slab) is gripped by the means described above by tightening the bolt or by other means comprising cylinders with pneumatic or hydraulic operation until the service force imposed by the structure produced is obtained. area. Elastic means, such as springs or Belleville washers for example can be incorporated on the surface at the upper end of the head tie to compensate or take up the forces.
Le procédé selon l'invention offre l'avantage de pouvoir prédéterminer la capacité de tenue du massif de terrain mis en contrainte et d'améliorer celle-ci en raidissant plus ou moins la plaque (et/ou la dalle) de surface sur son point d'ancrage souterrain. En effet, tout au long du battage, en connaissant le maître-couple à l'enfoncement du système d'ancrage souterrain, c'est-à-dire les contours des sections transversales à l'axe du mouvement de la ligne d'ancrage, on peut, en connaissant l'énergie de battage à chaque frappe, déterminer la portance du sol à chaque niveau d'enfoncement de l'ancre. Par ailleurs, la plaque (et/ou la dalle) de surface tirée vers le sol par le raidissage de la ligne d'ancrage permet, grâce à son tassement, d'évaluer la contrainte du sol en surface. Ces deux possibilités conjuguées permettent de cerner correctement les possibilités de tenue des massifs de sol précontraints.The method according to the invention offers the advantage of being able to predetermine the holding capacity of the mass of land under stress and of improving it by stiffening more or less the surface plate (and / or slab) at its point. underground anchor. Indeed, throughout the threshing, knowing the master-couple at the sinking of the underground anchoring system, that is to say the contours of the cross sections to the axis of movement of the anchor line , we can, by knowing the threshing energy at each strike, determine the bearing capacity of the ground at each level of the anchoring. Furthermore, the surface plate (and / or slab) pulled towards the ground by the stiffening of the anchor line makes it possible, thanks to its compaction, to assess the stress of the ground on the surface. These two possibilities combined make it possible to correctly identify the possibilities of holding pre-stressed soil masses.
La description suivante se réfère aux dessins annexés qui illustrent, sans aucun caractère limitatif, des exemples de réalisation d'un dispositif selon l'invention pour la mise en oeuvre de massifs de sol précontraints.
- - La figure 1 est une vue en coupe schématique d'un dispositif d'ancrage d'un pied de pylone électrique.
- - La figure 2 est une vue en élévation d'une ancre utilisée dans le dispositif de la figure 1.
- - La figure 3 est une vue de l'ancre de la figure 2 suivant la flèche F.
- - La figure 4 est une vue en élévation coupe à plus grande échelle d'un pied de pylone de la figure 1 illustrant un exemple de moyens pour la mise en tension de la ligne d'ancrage.
- - La figure 5 est une vue en élévation coupe d'un autre exemple de moyens pour la mise en tension de la ligne d'ancrage.
- - Figure 1 is a schematic sectional view of an anchoring device for an electric pylon base.
- - Figure 2 is an elevational view of an anchor used in the device of Figure 1.
- - Figure 3 is a view of the anchor of Figure 2 along arrow F.
- - Figure 4 is a sectional elevation view on a larger scale of a pylon foot of Figure 1 illustrating an example of means for the tensioning of the anchor line.
- - Figure 5 is a sectional elevation view of another example of means for tensioning the anchor line.
L'ancre 1 (figures 2 et 3) qui est utilisée dans le dispositif selon l'invention est par exemple du type de celle décrite dans le brevet français 84 07281. On précise là que d'autres moyens d'ancrage similaires peuvent trouver leur application pour la mise en oeuvre du procédé selon l'invention.The anchor 1 (Figures 2 and 3) which is used in the device according to the invention is for example of the type of that described in French patent 84 07281. It is specified here that other similar anchoring means can find their application for the implementation of the method according to the invention.
Une telle ancre 1 comporte un corps rigide la comportant une partie conique ou pyramidale 1a₁ dont la partie inférieure se termine par une extrémité d'attaque du sol 1a₂. Sa partie supérieure 1a₃ est d'une section droite circulaire ou carrée et comporte une enclume 1a₄ destinée à être frappée par des forces d'enfoncement obtenues par battage et par l'intermédiaire d'éléments tubulaires ou par des profilés en U 2, qui entourent une ligne d'ancrage 3 fixée à une pièce pivotante 4 autour d'un axe transversal à l'ancre 1.Such an
L'axe de pivotement 4a de la pièce 4 est situé entre l'extrémité 1a₂ et le centre de gravité de l'ancre et dans le plan de symétrie du corps 1a.The
A l'opposé de l'extrémité d'attaque du sol 1a₂, l'ancre 1 comporte un élément articulé 5 formant une sorte d'aileron , lequel est monté pivotant sur le corps 1a autour d'un axe 5a transversal à l'ancre et décalé par rapport au plan de symétrie du corps la dans lequel est également situé l'axe de pivotement 4a de la pièce 4. L'élément articulé 5 est conçu pour avoir un débattement angulaire limité de l'ordre de 45°.Opposite the leading end of the ground 1a₂, the
Dans le plan où est situé ledit axe d'articulation de la pièce 4, l'ancre 1 comporte une plaque 6 débordant symétriquement par rapport au corps 1a (figure 2) et comportant une partie rectangulaire 6a, s'étendant approximativement de l'axe de pivotement 5a de l'élément articulé 5 jusqu'à l'axe de pivotement 4a de la pièce 4, la section transversale de l'ancre à cet endroit constituant le maître-couple de l'ancre. La plaque 6 se prolonge vers l'extrémité d'attaque du sol 1a₂ par une partie profilée symétrique 6b pour favoriser la pénétration de l'ancre dans le sol, laquelle partie 6b est délimitée par une suite de bords 6b₁/6b₂/6b₃/6b₄ qui convergent suivant des angles différents sur l'axe de symétrie XX₁ de l'ancre.In the plane where said articulation axis of the
La plaque 6 est raidie par des goussets 7/8 fixés de part et d'autre de la plaque 6 formant des déflecteurs et qui convergent sur l'axe de symétrie de l'ancre XX₁ pour favoriser la pénétration de l'ancre dans le sol.The
Dans la position d'enfoncement de l'ancre 1, la ligne d'ancrage 3 est située dans l'axe XX₁ de l'ancre 1.In the insertion position of the
Dans cette position, la ligne d'ancrage et les éléments intermédiaires de battage 2, ou faux pieux de battage, sont sensiblement coaxiaux lorsque ceux-ci sont constitués par des tubes.In this position, the anchor line and the
On se reporte maintenant à la figure 1 du dessin qui représente l'ancrage d'un pied de pylone 9, lequel repose sur le sol par l'intermédiaire d'une dalle en béton armé 10, recouverte d'une plaque par exemple en acier 11, lesquelles dalle et plaque 10/11 sont traversées par la ligne d'ancrage 3.Referring now to Figure 1 of the drawing which represents the anchoring of a
Celle-ci est constituée de tirants par exemple sous la forme de tubes 3a/3b raccordés par un manchon de raccordement 12.This consists of tie rods, for example in the form of tubes 3a / 3b connected by a
La figure 4 représente, à plus grande échelle, un pied de pylone 9 et les moyens de mise en tension de la ligne d'ancrage pour mettre le sol en précontrainte.FIG. 4 represents, on a larger scale, a
La dalle 10 comporte un orifice 10a, situé au droit d'un orifice 11a, de plus grand diamètre, et réservé dans la plaque 11 qui recouvre la face supérieure de la dalle et à laquelle plaque est fixé le pied de pylone 9. La différence de diamètre des orifices 10a/11a permet de procéder à des réglages en X/Y de la plaque 11 par rapport à la dalle 10. Ledit pylone est dans une position inclinée et est constitué par un élément tubulaire et comporte un trou d'homme 9a pour accéder à l'intérieur.The
L'extrémité supérieure du tube 3b est passée à travers les orifices 10a/11a et se prolonge à l'intérieur du pied de pylone 9 à travers un dispositif de mise en tension de la ligne d'ancrage. Ce dispositif se compose d'un bâti 13 en appui sur la plaque métallique 11 et comportant une pièce mobile 14 comportant elle-même un logement conique 15 dans lequel est passé le tube 3. Les génératrices de la paroi dudit logement convergent vers l'ancre 1 sur un point situé sur l'axe de la ligne d'ancrage 3. La pièce mobile 14 est en appui sur des moyens élastiques 15, par exemple des rondelles Belleville, insérées entre ladite pièce mobile 14 et le fond du bâti 13.The upper end of the
L'extrémité supérieure 3b₁ du tube 3b est filetée et coopère avec un écrou 17. Dans le logement conique 15 sont disposés des coins de blocage 18 répartis autour du tube 3b, par exemple au nombre de trois et disposés à 120°. Une bague 19 disposée entre l'écrou 17 et les coins 18 est reliée à ceux-ci au moyen de goujons ou autres organes similaires 20.The upper end 3b₁ of the
La mise en tension de la ligne d'ancrage 3 et corrélativement la mise en précontrainte du sol est obtenue en vissant l'écrou 17. Lors de la mise en tension de la ligne d'ancrage 3, l'ancre pivote autour de l'axe 4a, l'aileron 5 autour de l'axe 5a jusqu'à ce qu'elle s'immobilise en butée de sol dans une position sensiblement parallèle ou sol tel que cela est représenté sur le dessin de la figure 1.The tensioning of the
La périphérie de la zone du tirant constitué par le tube 3b mise au contact des coins de blocage est striée ou comporte des micro-filetages pour accroître l'ancrage des coins dans ledit tirant.The periphery of the zone of the tie formed by the
La précontrainte du sol est obtenue en serrant plus ou moins l'écrou 17 tel que cela a été précédemment exposé.The prestressing of the ground is obtained by tightening more or less the
Un autre mode d'exécution des moyens pour la mise en tension de la ligne d'ancrage 3 est représenté à la figure 5 du dessin.Another embodiment of the means for tensioning the
Ces moyens se composent d'une poutre 21 comportant en son milieu une bague 22 comportant un orifice conique 22a dont les génératrices de la paroi convergent vers le point d'ancrage sur un point situé sur l'axe du tirant 3b. La fixation du tirant 3b à la poutre 21 est réalisée par des coins de blocage 23 par exemple au nombre de trois et disposés à 120°, répartis autour du tirant et disposés dans l'espace annulaire existant entre le tirant 3b et l'orifice conique 22a.These means consist of a
Selon ce mode de réalisation, la plaque métallique 11, qui recouvre la dalle 10 comporte un bossage 24 comportant un orifice conique 24a coaxial à l'orifice 10a de la dalle et dont les génératrices de sa paroi convergent vers le point d'ancrage sur un point situé sur l'axe du tube 3b.According to this embodiment, the
La mise en tension de la ligne d'ancrage est par exemple obtenue au moyen de deux vérins 25/26, par exemple à simple effet et à fonctionnement hydraulique. Le maintien en tension de la ligne d'ancrage 3 est obtenu par exemple par trois coins de blocage 27 répartis à 120° autour du tube 3b et disposés dans l'espace annulaire existant entre le tube et l'orifice conique 24a.The tensioning of the anchor line is for example obtained by means of two
Après que les coins de blocage ont été enfoncés et ancrés dans le tube 3b, on réduit la pression dand le circuit hydraulique jusqu'à annulation de la pression de service.After the locking corners have been inserted and anchored in the
Comme pour le dispositif décrit en référence à la figure 4, la périphérie des zones des tubes 3b mises au contact des coins de blocage 23/27 est striée ou comporte des micro-filetages pour accroître l'ancrage des coins dans le tube. Egalement, les parties des coins 18/23/27, mises au contact des tubes peuvent être dentelées pour encore accroître l'encastrement des coins à la périphérie du tube.As for the device described with reference to FIG. 4, the periphery of the zones of the
Le procédé et le dispositif selon l'invention et entre autre application, peuvent être mis en oeuvre pour raidir des argiles ou marnes saturés ou sursaturés d'eau ou encore pour réaliser des fondations stables dans les déserts de sable.The method and the device according to the invention and, among other applications, can be used to stiffen clays or marls saturated or supersaturated with water or else to produce stable foundations in sand deserts.
On notera qu'en ce qui concerne la ligne d'ancrage 3, les éléments rigides (tirants, tubes ou autres) pourront être remplacés par des câbles appropriés.It will be noted that with regard to the
Claims (15)
- on réalise au moins un point d'ancrage profond en utilisant des moyens d'ancrage (1/3) que l'on enfonce dans le sol par battage, lesquels moyens (3) se prolongent en position d'ancrage vers la surface du sol pour s'étendre au-delà de cette surface;
- on place en surface une dalle (10) qui comporte au moins une ouverture (10a) pour le passage des prolongements desdits moyens d'ancrage (3),
- et on exerce une traction sur cette dalle (10) pour précontraindre le sol par des moyens de mise en tension desdits moyens d'ancrage situés au-dessus de ladite dalle (10) jusqu'à obtenir la force de service nécessaire au maintien de l'ouvrage à réaliser en surface.1. Method for implementing a foundation by creating a solid mass constituted by the soil itself, characterized by the following operations:
- At least one deep anchoring point is made using anchoring means (1/3) which are driven into the ground by threshing, which means (3) extend in the anchoring position towards the surface of the soil to extend beyond this surface;
- a slab (10) is placed on the surface which has at least one opening (10a) for the passage of the extensions of said anchoring means (3),
- And a traction is exerted on this slab (10) to prestress the ground by means of tensioning said anchoring means located above said slab (10) until obtaining the service force necessary to maintain the structure to be produced on the surface.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
FR8715654 | 1987-11-09 | ||
FR8715654A FR2622909B1 (en) | 1987-11-09 | 1987-11-09 | METHOD AND DEVICE FOR IMPLEMENTING A FOUNDATION BY CREATING A MASS CONSTITUTED BY THE SOIL ITSELF |
Publications (2)
Publication Number | Publication Date |
---|---|
EP0317458A1 true EP0317458A1 (en) | 1989-05-24 |
EP0317458B1 EP0317458B1 (en) | 1994-05-18 |
Family
ID=9356722
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
EP88430029A Expired - Lifetime EP0317458B1 (en) | 1987-11-09 | 1988-11-08 | Process and apparatus for laying a foundation by creating a solid mass constituted by the soil itself |
Country Status (8)
Country | Link |
---|---|
US (1) | US5026213A (en) |
EP (1) | EP0317458B1 (en) |
AT (1) | ATE105891T1 (en) |
AU (1) | AU612744B2 (en) |
DE (1) | DE3889631T2 (en) |
ES (1) | ES2054854T3 (en) |
FR (1) | FR2622909B1 (en) |
WO (1) | WO1989004402A1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0408479A1 (en) * | 1989-07-13 | 1991-01-16 | Technologies Speciales Ingenierie - T.S.I. (S.A.) | Temporary road and process for using the same |
FR2746131A1 (en) * | 1996-03-15 | 1997-09-19 | Tecnivalor | ARTICULATED BASES AND METHOD AND SYSTEM FOR LAYING WORKS ON SAID BASES |
EP0884420A1 (en) | 1997-06-13 | 1998-12-16 | Tecnivalor | Method and apparatus for a footing in the ground opposing lateral and slipping efforts |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB8926092D0 (en) * | 1989-11-17 | 1990-01-10 | Seamark Systems | Subsea apparatus |
FR2660353A1 (en) * | 1990-03-30 | 1991-10-04 | Technologies Speciales Ingenie | Earthquake resistance methods and shields |
FR2708949B1 (en) * | 1993-08-12 | 1999-01-29 | Texmar | Method and device for the creation of dynamic foundations confined to the elastic domain of the ground. |
US6237289B1 (en) * | 1996-01-16 | 2001-05-29 | Foresight Products, Inc. | Ground Anchor |
GB0113711D0 (en) * | 2001-06-06 | 2001-07-25 | Corus Uk Ltd | Foundation blocks |
FR2845705B1 (en) * | 2002-10-15 | 2005-05-27 | Ineo Reseaux Haute Tension | METHOD FOR STRENGTHENING THE FOUNDATIONS OF A PYLONE |
US20080008539A1 (en) * | 2006-07-05 | 2008-01-10 | Con-Tech Systems Ltd. | Void form for constructing post-tensioned foundation piles |
GB201106118D0 (en) * | 2011-04-12 | 2011-05-25 | Gripple Ltd | Ground stabilising device |
CN110241839B (en) * | 2019-06-20 | 2021-08-06 | 浙江兴岛机械股份有限公司 | Suction type cylindrical foundation |
WO2022056485A1 (en) * | 2020-09-14 | 2022-03-17 | Array Technologies, Inc. | Anchor for support structure |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1063854A (en) * | 1952-05-24 | 1954-05-07 | Method and devices for constructing foundations for maritime structures | |
FR1209949A (en) * | 1958-05-02 | 1960-03-04 | Stup Procedes Freyssinet | Improvements to methods and anchoring devices for prestressing bars |
US4043133A (en) * | 1976-07-21 | 1977-08-23 | Yegge Lawrence R | Structure and method of constructing and test-loading pile anchored foundations |
US4044513A (en) * | 1974-12-23 | 1977-08-30 | Foresight Industries | Earth anchor |
GB2106947A (en) * | 1981-09-17 | 1983-04-20 | Abraham Behar | Pre-stressed structural member |
FR2524031A1 (en) * | 1982-03-29 | 1983-09-30 | Bertrand Jean | Ground anchor for guy line - has tapped socket and threaded pin for anchor extension |
FR2524030A1 (en) * | 1982-03-25 | 1983-09-30 | Precontrainte Ste Fse | Anchor head for progressively contracted composite tie rod - has truncated anchoring pin wedged into anchoring ring orifice |
EP0161190A2 (en) * | 1984-05-11 | 1985-11-13 | Institut Français du Pétrole | Anchoring device comprising a hinged angular part |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3087308A (en) * | 1957-08-26 | 1963-04-30 | Raymond Int Inc | Method of installing piles for resisting upward soil movements |
IT1078510B (en) * | 1975-11-11 | 1985-05-08 | F Soc An Fondedile Spa Ora Fon | FOUNDATION POLE FOR ALTERNATE COMPRESSION AND TRACTION EFFORTS |
-
1987
- 1987-11-09 FR FR8715654A patent/FR2622909B1/en not_active Expired - Lifetime
-
1988
- 1988-11-08 AU AU27125/88A patent/AU612744B2/en not_active Ceased
- 1988-11-08 US US07/381,746 patent/US5026213A/en not_active Expired - Lifetime
- 1988-11-08 EP EP88430029A patent/EP0317458B1/en not_active Expired - Lifetime
- 1988-11-08 DE DE3889631T patent/DE3889631T2/en not_active Expired - Lifetime
- 1988-11-08 AT AT88430029T patent/ATE105891T1/en not_active IP Right Cessation
- 1988-11-08 WO PCT/FR1988/000549 patent/WO1989004402A1/en unknown
- 1988-11-08 ES ES88430029T patent/ES2054854T3/en not_active Expired - Lifetime
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1063854A (en) * | 1952-05-24 | 1954-05-07 | Method and devices for constructing foundations for maritime structures | |
FR1209949A (en) * | 1958-05-02 | 1960-03-04 | Stup Procedes Freyssinet | Improvements to methods and anchoring devices for prestressing bars |
US4044513A (en) * | 1974-12-23 | 1977-08-30 | Foresight Industries | Earth anchor |
US4043133A (en) * | 1976-07-21 | 1977-08-23 | Yegge Lawrence R | Structure and method of constructing and test-loading pile anchored foundations |
GB2106947A (en) * | 1981-09-17 | 1983-04-20 | Abraham Behar | Pre-stressed structural member |
FR2524030A1 (en) * | 1982-03-25 | 1983-09-30 | Precontrainte Ste Fse | Anchor head for progressively contracted composite tie rod - has truncated anchoring pin wedged into anchoring ring orifice |
FR2524031A1 (en) * | 1982-03-29 | 1983-09-30 | Bertrand Jean | Ground anchor for guy line - has tapped socket and threaded pin for anchor extension |
EP0161190A2 (en) * | 1984-05-11 | 1985-11-13 | Institut Français du Pétrole | Anchoring device comprising a hinged angular part |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0408479A1 (en) * | 1989-07-13 | 1991-01-16 | Technologies Speciales Ingenierie - T.S.I. (S.A.) | Temporary road and process for using the same |
FR2649735A1 (en) * | 1989-07-13 | 1991-01-18 | Technologies Speciales Ingenie | EMERGENCY BEARING TRACK AND METHOD FOR IMPLEMENTING THE SAME |
FR2746131A1 (en) * | 1996-03-15 | 1997-09-19 | Tecnivalor | ARTICULATED BASES AND METHOD AND SYSTEM FOR LAYING WORKS ON SAID BASES |
WO1997035083A1 (en) * | 1996-03-15 | 1997-09-25 | Tecnivalor | Articulated bases and process and system for implanting structures on said bases |
EP0884420A1 (en) | 1997-06-13 | 1998-12-16 | Tecnivalor | Method and apparatus for a footing in the ground opposing lateral and slipping efforts |
Also Published As
Publication number | Publication date |
---|---|
US5026213A (en) | 1991-06-25 |
AU612744B2 (en) | 1991-07-18 |
FR2622909B1 (en) | 1991-04-19 |
WO1989004402A1 (en) | 1989-05-18 |
AU2712588A (en) | 1989-06-01 |
EP0317458B1 (en) | 1994-05-18 |
FR2622909A1 (en) | 1989-05-12 |
ES2054854T3 (en) | 1994-08-16 |
ATE105891T1 (en) | 1994-06-15 |
DE3889631D1 (en) | 1994-06-23 |
DE3889631T2 (en) | 1994-11-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP0317458B1 (en) | Process and apparatus for laying a foundation by creating a solid mass constituted by the soil itself | |
CA3031301C (en) | Apparatus and method for driving a pile into the ground prior to lifting and stabilizing the foundations of a building | |
CA2576628C (en) | Device and method for a tower reinforcing foundation | |
WO1980002173A1 (en) | Securing device with sliding sleeves,in particular for posts | |
FR2845705A1 (en) | Pylon foundation reinforcing procedure uses concrete blocks connected to outside plate anchors by tensioned cables | |
FR2692611A1 (en) | Precast concrete fixing plate for lamp post installation - holds post baseplate with nuts on threaded tops of holding down bolts anchored in concrete foundation hole in plate for electric cables | |
EP0884420A1 (en) | Method and apparatus for a footing in the ground opposing lateral and slipping efforts | |
FR2992335A1 (en) | SUPPORT STRUCTURE, ASSOCIATED SUPPORTING DEVICE, AND SKIABLE TRACK LEADING DEVICE USING THE SAME | |
FR2797288A1 (en) | DEVICE FOUNDATION ANCHORED IN THE GROUND BY DAMAGE | |
WO2003040515A1 (en) | Guide device in an offshore drilling installation | |
FR2648841A1 (en) | Underpinning method | |
BE876763A (en) | METHOD AND DEVICE FOR SUPPORTING A BUILDING FROM AN UNDERGROUND GALLERY. | |
FR2560268A1 (en) | Stopping and supporting devices intended to be driven into the ground by percussion in order to install training equipment, fences, etc. | |
WO2017134370A1 (en) | Modular device for creating an anchor point in the ground | |
FR2548707A1 (en) | APPARATUS FOR EXCAVATING HOLES OR TRENCHES | |
FR2915498A1 (en) | DEVICE AND METHOD FOR ESTABLISHING A FOUNDATION HELICOIDAL MICROPY | |
CH421472A (en) | Method of constructing a building structure in the basement, and structure obtained according to this method | |
EP2439337B1 (en) | Concrete-free anchoring device | |
FR2825730A1 (en) | Construction procedure for retaining structure against existing supporting surface uses partition with fastenings forming back-filled space | |
EP4253664A1 (en) | Retaining structure and retaining device thereof | |
FR2519045A1 (en) | Foundation for buildings - comprises vertical cavity having enlarged upper end which aids resistance to horizontal forces | |
FR3092348A1 (en) | IN-SITU REINFORCEMENT PROCESS OF A CONSOLE SLAB ANCHORED BY A THERMAL BRIDGE BREAKER | |
FR2708949A1 (en) | Method and device for producing dynamic foundations confined to the elastic region of the ground | |
FR3080123A1 (en) | METHOD OF RECOVERY IN WORK BY MICROPIEUX | |
FR2775306A1 (en) | Protection structure against falling masses |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH DE ES GB GR IT LI LU NL SE |
|
17P | Request for examination filed |
Effective date: 19900115 |
|
17Q | First examination report despatched |
Effective date: 19901031 |
|
RAP1 | Party data changed (applicant data changed or rights of an application transferred) |
Owner name: CASTOLA, CHARLES-ALAIN |
|
GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH DE ES GB GR IT LI LU NL SE |
|
REF | Corresponds to: |
Ref document number: 105891 Country of ref document: AT Date of ref document: 19940615 Kind code of ref document: T |
|
REF | Corresponds to: |
Ref document number: 3889631 Country of ref document: DE Date of ref document: 19940623 |
|
ITF | It: translation for a ep patent filed |
Owner name: JACOBACCI CASETTA & PERANI S.P.A. |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FG2A Ref document number: 2054854 Country of ref document: ES Kind code of ref document: T3 |
|
GBT | Gb: translation of ep patent filed (gb section 77(6)(a)/1977) |
Effective date: 19940805 |
|
REG | Reference to a national code |
Ref country code: GR Ref legal event code: FG4A Free format text: 3012898 |
|
EAL | Se: european patent in force in sweden |
Ref document number: 88430029.4 |
|
PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
26N | No opposition filed | ||
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 20011018 Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GR Payment date: 20011025 Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: LU Payment date: 20011115 Year of fee payment: 14 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: CH Payment date: 20011128 Year of fee payment: 14 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: IF02 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20021108 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20021109 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: AT Payment date: 20021122 Year of fee payment: 15 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: ES Payment date: 20021125 Year of fee payment: 15 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: CH Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20021130 Ref country code: LI Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20021130 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: NL Payment date: 20021130 Year of fee payment: 15 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GR Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20030609 |
|
EUG | Se: european patent has lapsed | ||
REG | Reference to a national code |
Ref country code: CH Ref legal event code: PL |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: AT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20031108 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: ES Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20031110 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 20040601 |
|
NLV4 | Nl: lapsed or anulled due to non-payment of the annual fee |
Effective date: 20040601 |
|
REG | Reference to a national code |
Ref country code: ES Ref legal event code: FD2A Effective date: 20031110 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 20071108 Year of fee payment: 20 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: IT Payment date: 20071114 Year of fee payment: 20 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: BE Payment date: 20071203 Year of fee payment: 20 |
|
PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 20071114 Year of fee payment: 20 |
|
BE20 | Be: patent expired |
Owner name: *CASTOLA CHARLES-ALAIN Effective date: 20081108 |
|
REG | Reference to a national code |
Ref country code: GB Ref legal event code: PE20 Expiry date: 20081107 |
|
PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Free format text: LAPSE BECAUSE OF EXPIRATION OF PROTECTION Effective date: 20081107 |