EP0293381B1 - System for the insulation of mining installations and a method for implementing the system - Google Patents
System for the insulation of mining installations and a method for implementing the system Download PDFInfo
- Publication number
- EP0293381B1 EP0293381B1 EP87901166A EP87901166A EP0293381B1 EP 0293381 B1 EP0293381 B1 EP 0293381B1 EP 87901166 A EP87901166 A EP 87901166A EP 87901166 A EP87901166 A EP 87901166A EP 0293381 B1 EP0293381 B1 EP 0293381B1
- Authority
- EP
- European Patent Office
- Prior art keywords
- insulation
- rock
- thermal insulation
- accordance
- waterproof membrane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
- E21D11/383—Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
Definitions
- the present invention relates to a system for the insulation of tunnels, rock cavities and similar mining installations, in conjunction with which a draining layer and a waterproof membrane are installed immediately adjacent to the rock or on the surface of a reinforcing layer applied thereto, so that they follow the contours of the rock or the reinforcing layer.
- the invention also relates to a method for implementing the insulation system for the insulation of tunnels, rock cavities and similar mining installations, in conjunction with which a draining layer and a waterproof membrane are installed immediately adjacent to the rock or on the surface of a reinforcing layer applied thereto, so that they follow the contours of the rock or the reinforcing layer.
- ice encroaches upon the free clearance for the vehicles in rail and road tunnels, for example. This results in disruptions to the traffic. As the air temperature rises, the ice thaws and drops down. Equipment, vehicles and people, etc., can suffer damage and injury.
- Ice clearance work is both dangerous and costly. Deaths have occurred in Sweden in conjunction with ice clearance. Considerable sums are spent every year on ice clearance work. Ice clearance usually means that a road tunnel, for example, must be closed either completely or partially. The result is the disruption of traffic.
- insulated vaults made of plastic and sheet metal are installed inside tunnels.
- the disadvantages associated with these vaults are, for example, that they require a certain amount of space, which means that an increased tunnel cross-section must be blasted, or that inroads must be made on the free space for the traffic, for example. They are also expensive, and they involve long delivery and installation periods (prefabrication for different sizes of tunnel).
- the fire prevention authorities have also begun to adopt a negative attitude towards plastic vaults in traffic tunnels where vehicle fires, for instance, can occur. Extruded cellular plastic matting (AT-B-370 850) has also been used.
- this system exhibits the same disadvantages as those outlined above for the vaults.
- Experiments have also been conducted into heating the air, in this way preventing freezing. This is a very expensive method, however, and is susceptible to plant breakdown. Insulated drains are sometimes used locally. More often than not these produce a poor effect, since any water leakage due to blockages has to be removed from the area which has already been drained by the drains. Furthermore, such local applications provide poor protection against the cold.
- the principal object of the present invention is thus to prevent ice formation and to permit the advancing water to be led away in a drainage system.
- the invention must take up the smallest possible space, require a short installation period and be flexible (ease of adaptation to other tunnel cross-sections, etc.).
- the invention must also be suitable for use not only for the complete insulation of a timing installation, but also for the partial insulation of an installation.
- the rock itself maintains a comparatively even temperature of about +5°C throughout the year.
- the water which finds its way through the fissures in principle exhibits the same temperature as the surrounding rock.
- the aim of the invention is thus to prevent the cold air from cooling down the rock and the water.
- Said object is achieved by means of a method in accordance with the present invention, which is characterized essentially in that thermal insulation to counteract frost is installed on the surface of the waterproof membrane, and in that fire-retardant insulation is installed on the surface of said thermal insulation.
- a further object of the present invention is to disclose a method for making available a system for the insulation of tunnels, rock cavities and similar mining installations, in conjunction with which a draining layer and a waterproof membrane are installed immediately adjacent to the rock or on the surface of a reinforcing layer applied thereto, so that they follow the contours of the rock or the reinforcing layer.
- Said further object is achieved by means of a method in accordance with the present invention, which is characterized essentially in that thermal insulation is installed on the surface of the waterproof membrane for the purpose of counteracting frost, and in that fire-retardant insulation is installed on the surface of the thermal insulation.
- the invention consists of a number of components which are combined to produce a system for the frost insulation of mining installations.
- the system consists of the following components and is composed in the following manner.
- Installed immediately adjacent to the rock 1 or on the outside of a reinforcing layer 2 are, on the one hand, a draining layer 3 and, on the other hand, a waterproof membrane 4.
- the water is led away via the draining layer 3 to a drainage pipe which takes the water out of the installation.
- the draining layer 3 and the waterproof membrane 4 are installed close up against the rock 1 or the reinforcing layer 2, so that they follow the contours of the rock, requiring a minimum of space.
- This method has been used for many years for the removal of water, in so doing preventing dropping water and running water, etc., although no frost insulation is achieved in this design.
- a reinforcing mesh 5 can be attached to the surface of the waterproof membrane 4.
- Thermal insulation 5 consisting, for example, of polyurethane is then applied by spraying or by some other appropriate method.
- the reinforcing mesh 5 functions, where it is used, as a reinforcement inside the insulating layer, in this way producing a stable, insulating layer.
- the thickness of the insulation is simply varied depending on the air temperature with which the system is required to contend.
- a fire-resistant material 7 is applied to the outside of the thermal insulation 5, 6 in order to provide fire-proofing.
- the nature of the fire-resistant layer 7 may vary to suit the various requirements of the fire prevention authorities.
- a thin layer of fire-retardant plaster can usually be applied on the outside of the thermal insulation 5, 6.
- the frost insulating system thus consists of a number of components, all of which are available by length or by weight.
- the system is built up simply directly on site and can be adapted to suit different tunnel cross-sections and different requirements, etc. As it follows the contour of the rock, a minimum of space is required.
- the method by which it is applied is also suitable for systematic handling, so that not only entire mining installations, but also parts of mining installations can be insulated.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Architecture (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
- Building Environments (AREA)
- Cultivation Of Seaweed (AREA)
- Glass Compositions (AREA)
- Two-Way Televisions, Distribution Of Moving Picture Or The Like (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
- The present invention relates to a system for the insulation of tunnels, rock cavities and similar mining installations, in conjunction with which a draining layer and a waterproof membrane are installed immediately adjacent to the rock or on the surface of a reinforcing layer applied thereto, so that they follow the contours of the rock or the reinforcing layer.
- The invention also relates to a method for implementing the insulation system for the insulation of tunnels, rock cavities and similar mining installations, in conjunction with which a draining layer and a waterproof membrane are installed immediately adjacent to the rock or on the surface of a reinforcing layer applied thereto, so that they follow the contours of the rock or the reinforcing layer.
- Wherever water-bearing fissures pass through mining installations, tunnels, rock cavities and open cuts, etc., water is present in the form of moisture, drops or running/sprinkling water. This water can freeze in the winter. Undulating ice and icicles are then formed. This phenomenon occurs in those parts of a mining installation where the air temperature falls below the freezing point. Examples of those mining installations where this occurs are the outer parts of transport tunnels (tunnels which run from the surface down to a main tunnel) and rail and road tunnels which are open at both ends and thus permit cold air to flow into and through the tunnel. This phenomenon frequently occurs in rock cuttings along highways.
- The formation of ice poses major problems. In many cases the ice encroaches upon the free clearance for the vehicles in rail and road tunnels, for example. This results in disruptions to the traffic. As the air temperature rises, the ice thaws and drops down. Equipment, vehicles and people, etc., can suffer damage and injury.
- The ice must be chipped away (cleared) continuously in order to eliminate the risk of damage and to maintain the function of the installation. Ice clearance work is both dangerous and costly. Deaths have occurred in Sweden in conjunction with ice clearance. Considerable sums are spent every year on ice clearance work. Ice clearance usually means that a road tunnel, for example, must be closed either completely or partially. The result is the disruption of traffic.
- The formation of ice also affects the rock and any reinforcements in the installation. Blocks of rock can fall down when the water in a fissure freezes and forces out the block. Reinforcements made of sprayed concrete and poured concrete suffer frost damage as a result of rupture due to frost. This results in a reduced service life and in increased maintenance and repair costs.
- In summary, therefore, the formation of ice in mining installations gives rise to major problems associated with restricted use, the risk of damage, reduced service life and increased costs of maintenance and repair work. Continuous ice clearance is necessary, and this is both dangerous and costly.
- A number of different systems are currently available for solving the problem of ice formation. For example, insulated vaults made of plastic and sheet metal are installed inside tunnels. The disadvantages associated with these vaults are, for example, that they require a certain amount of space, which means that an increased tunnel cross-section must be blasted, or that inroads must be made on the free space for the traffic, for example. They are also expensive, and they involve long delivery and installation periods (prefabrication for different sizes of tunnel). The fire prevention authorities have also begun to adopt a negative attitude towards plastic vaults in traffic tunnels where vehicle fires, for instance, can occur. Extruded cellular plastic matting (AT-B-370 850) has also been used. Generally speaking, this system exhibits the same disadvantages as those outlined above for the vaults. Experiments have also been conducted into heating the air, in this way preventing freezing. This is a very expensive method, however, and is susceptible to plant breakdown. Insulated drains are sometimes used locally. More often than not these produce a poor effect, since any water leakage due to blockages has to be removed from the area which has already been drained by the drains. Furthermore, such local applications provide poor protection against the cold.
- The principal object of the present invention is thus to prevent ice formation and to permit the advancing water to be led away in a drainage system. At the same time the invention must take up the smallest possible space, require a short installation period and be flexible (ease of adaptation to other tunnel cross-sections, etc.). The invention must also be suitable for use not only for the complete insulation of a timing installation, but also for the partial insulation of an installation.
- The rock itself maintains a comparatively even temperature of about +5°C throughout the year. The water which finds its way through the fissures in principle exhibits the same temperature as the surrounding rock. The aim of the invention is thus to prevent the cold air from cooling down the rock and the water.
- Said object is achieved by means of a method in accordance with the present invention, which is characterized essentially in that thermal insulation to counteract frost is installed on the surface of the waterproof membrane, and in that fire-retardant insulation is installed on the surface of said thermal insulation.
- A further object of the present invention is to disclose a method for making available a system for the insulation of tunnels, rock cavities and similar mining installations, in conjunction with which a draining layer and a waterproof membrane are installed immediately adjacent to the rock or on the surface of a reinforcing layer applied thereto, so that they follow the contours of the rock or the reinforcing layer.
- Said further object is achieved by means of a method in accordance with the present invention, which is characterized essentially in that thermal insulation is installed on the surface of the waterproof membrane for the purpose of counteracting frost, and in that fire-retardant insulation is installed on the surface of the thermal insulation.
- The invention is described below in relation to two illustrative embodiments, in conjunction with which reference is made to the drawings, in which:
- Fig. 1 shows a first illustrative embodiment of an insulating system; and
- Fig. 2 shows a second illustrative embodiment of an insulating system.
- The invention consists of a number of components which are combined to produce a system for the frost insulation of mining installations. The system consists of the following components and is composed in the following manner. Installed immediately adjacent to the rock 1 or on the outside of a reinforcing layer 2 are, on the one hand, a draining layer 3 and, on the other hand, a waterproof membrane 4. The water is led away via the draining layer 3 to a drainage pipe which takes the water out of the installation. The draining layer 3 and the waterproof membrane 4 are installed close up against the rock 1 or the reinforcing layer 2, so that they follow the contours of the rock, requiring a minimum of space. This method has been used for many years for the removal of water, in so doing preventing dropping water and running water, etc., although no frost insulation is achieved in this design.
- It is proposed in accordance with the present invention to supplement the basic system with thermal insulation 6 in the following way, in so doing preventing frost formation. A reinforcing mesh 5 can be attached to the surface of the waterproof membrane 4. Thermal insulation 5 consisting, for example, of polyurethane is then applied by spraying or by some other appropriate method. The reinforcing mesh 5 functions, where it is used, as a reinforcement inside the insulating layer, in this way producing a stable, insulating layer. The thickness of the insulation is simply varied depending on the air temperature with which the system is required to contend.
- A fire-resistant material 7 is applied to the outside of the thermal insulation 5, 6 in order to provide fire-proofing. The nature of the fire-resistant layer 7 may vary to suit the various requirements of the fire prevention authorities. A thin layer of fire-retardant plaster can usually be applied on the outside of the thermal insulation 5, 6.
- In the case of rock 1 which exhibits a very uneven contour, it is possible first to install a smooth mesh 8 on the surface of the rock 1 or the sprayed concrete 2 for the purpose of evening out the contours, and to let this mesh 8 form part of the reinforcing layer 2. The system as previously described is then applied to the surface of mesh 8, as shown in Fig. 2, with a draining layer 3, a waterproof membrane 4 followed by reinforcement 5, if required, and by thermal insulation 6, and a fire-retardant layer 7.
- The frost insulating system thus consists of a number of components, all of which are available by length or by weight. The system is built up simply directly on site and can be adapted to suit different tunnel cross-sections and different requirements, etc. As it follows the contour of the rock, a minimum of space is required. The method by which it is applied is also suitable for systematic handling, so that not only entire mining installations, but also parts of mining installations can be insulated.
- Further advantages include the fact that existing systems for the removal of water can be supplemented easily with thermal frost insulation, so that the water which is leaking into the workings will not freeze;
- -that it can be constructed from a number of components, which are applied directly on site;
- -that it can be used in all kinds of mining installation, irrespective of their size and form, etc.;
- -that the nature of the insulation can be varied depending on the external temperature with which the system is to contend;
- -that it is a flexible system which follows the surface of the rock and thus takes up a minimum amount of space; and
- -that it can be provided with various kinds of fire protection.
- The invention is not restricted to the illustrative embodiments described above and illustrated in the drawings, but may be varied within the scope of the Patent Claims without departing from the idea of invention.
Claims (11)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| AT87901166T ATE58205T1 (en) | 1986-02-11 | 1987-02-11 | SYSTEM FOR INSULATION OF MINING EQUIPMENT AND METHOD OF IMPLEMENTING SUCH SYSTEM. |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| SE8600585 | 1986-02-11 | ||
| SE8600585A SE453113B (en) | 1986-02-11 | 1986-02-11 | INSULATION SYSTEM FOR STORAGE INSTALLATIONS AND PROCEDURES FOR ASTADKOMMA SYSTEM |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| EP0293381A1 EP0293381A1 (en) | 1988-12-07 |
| EP0293381B1 true EP0293381B1 (en) | 1990-11-07 |
Family
ID=20363420
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| EP87901166A Expired EP0293381B1 (en) | 1986-02-11 | 1987-02-11 | System for the insulation of mining installations and a method for implementing the system |
Country Status (6)
| Country | Link |
|---|---|
| EP (1) | EP0293381B1 (en) |
| AU (1) | AU7025987A (en) |
| FI (1) | FI88198C (en) |
| NO (1) | NO174524C (en) |
| SE (1) | SE453113B (en) |
| WO (1) | WO1987004756A1 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2911365A1 (en) * | 2007-01-15 | 2008-07-18 | Pastiforms S Soc Par Actions S | Multifunction liner for constructing e.g. tunnel, has strip whose rebates permit assembling of liner elements, and drainage layer whose protuberances are separated relative to each other to form drainage channels or drainage geotextile |
Families Citing this family (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE4025212A1 (en) * | 1990-08-09 | 1992-02-13 | Huels Troisdorf | TRAFFIC TUNNEL FOR COLD REGIONS |
| ATE180313T1 (en) * | 1993-10-14 | 1999-06-15 | Albert Thalmann | PROFILE STRIPS MADE OF FLEXIBLE SEALING MATERIAL |
| EP0725185A1 (en) * | 1996-01-08 | 1996-08-07 | Roland F. Wolfseher | Lining tunnels and method for its attachment |
| ES2118035B1 (en) * | 1996-03-18 | 1999-07-01 | Construcciones Aplicaciones Y | COATING SHEET. |
| ATE253172T1 (en) * | 1997-08-15 | 2003-11-15 | Koester Bauchemie Gmbh | METHOD FOR SEALING UNDERGROUND CAVITIES AGAINST WATER ENTRY |
| GB9815685D0 (en) * | 1998-07-20 | 1998-09-16 | Mbt Holding Ag | Waterproofer |
| WO2001007756A1 (en) * | 1999-07-23 | 2001-02-01 | William Claudio Bona | Lining system |
| US6793441B2 (en) | 2000-06-12 | 2004-09-21 | W. R. Grace & Co.-Conn. | Tunnel waterproofing method |
| US6767164B2 (en) | 2000-06-12 | 2004-07-27 | W. R. Grace & Co.-Conn. | Tunnel waterproofing construction method |
| FR2838159B1 (en) * | 2002-04-03 | 2004-12-17 | Etancheite D Ouvrages Souterra | WATERPROOF DEVICE FOR DRAINING PERCOLATING WATER ON A TUNNEL COATING |
| CN105587325B (en) * | 2014-10-22 | 2018-08-14 | 广东工业大学 | A kind of anti-icing composite plate in tunnel based on phase-change material |
| JP6534208B2 (en) * | 2015-09-15 | 2019-06-26 | 藤森工業株式会社 | Tunnel tarpaulin |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| AT339948B (en) * | 1975-06-30 | 1977-11-10 | Iso Bau Abdichtungen Im Hoch U | METHOD FOR FASTENING A SEALING FILM MADE OF PLASTIC ON A BASE AND FASTENING BODY FOR FASTENING PLASTIC FILMS TO PERFORM THE METHOD |
| DE2837333A1 (en) * | 1978-08-26 | 1980-03-06 | Dynamit Nobel Ag | Proofing walls against water seepage and pressure - with crosslinked polyolefin foam laminated to plasticised PVC ply lining |
| AT370850B (en) * | 1982-01-07 | 1983-05-10 | Seebode Gerhard | FASTENING DEVICE FOR THE APPLICATION OF INSULATING FILMS TO THE EXCAVATING SURFACES OF UNDERGROUND BUILDINGS |
-
1986
- 1986-02-11 SE SE8600585A patent/SE453113B/en not_active Application Discontinuation
-
1987
- 1987-02-11 WO PCT/SE1987/000063 patent/WO1987004756A1/en not_active Ceased
- 1987-02-11 AU AU70259/87A patent/AU7025987A/en not_active Abandoned
- 1987-02-11 EP EP87901166A patent/EP0293381B1/en not_active Expired
- 1987-10-09 NO NO874227A patent/NO174524C/en unknown
-
1988
- 1988-08-09 FI FI883697A patent/FI88198C/en not_active IP Right Cessation
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2911365A1 (en) * | 2007-01-15 | 2008-07-18 | Pastiforms S Soc Par Actions S | Multifunction liner for constructing e.g. tunnel, has strip whose rebates permit assembling of liner elements, and drainage layer whose protuberances are separated relative to each other to form drainage channels or drainage geotextile |
Also Published As
| Publication number | Publication date |
|---|---|
| SE8600585L (en) | 1987-08-12 |
| FI88198B (en) | 1992-12-31 |
| NO174524C (en) | 1994-05-25 |
| WO1987004756A1 (en) | 1987-08-13 |
| FI88198C (en) | 1993-04-13 |
| SE453113B (en) | 1988-01-11 |
| NO874227D0 (en) | 1987-10-09 |
| EP0293381A1 (en) | 1988-12-07 |
| FI883697A0 (en) | 1988-08-09 |
| FI883697L (en) | 1988-08-09 |
| NO174524B (en) | 1994-02-07 |
| AU7025987A (en) | 1987-08-25 |
| SE8600585D0 (en) | 1986-02-11 |
| NO874227L (en) | 1987-10-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| WO1987004756A1 (en) | System for the insulation of mining installations and a method for implementing the system | |
| CN114301024A (en) | A highway tunnel cable trench thermal insulation, temperature control and moisture-proof system | |
| CN106836663A (en) | The construction method of water-proof insulating roof | |
| RU2439260C2 (en) | Method of building roof collecting systems protection against icing | |
| EA039178B1 (en) | Tunnel profile element covering periphery of tunnel profile | |
| EP0375738B1 (en) | Fire resistant insulation composition | |
| Adnan et al. | Common utility tunnel for utility services at Putrajaya, new administrative centre of Malaysia | |
| RU2175364C2 (en) | Intra-city circular motorway | |
| Haynes et al. | Icing problems at Corps projects | |
| Mackinlay et al. | Roof design in regions of snow and cold | |
| EP1952980B1 (en) | Covering sheet | |
| CN220814149U (en) | Novel heat insulation structure for drainage ditches on two sides of railway in tunnel | |
| SU1082899A1 (en) | Surface gate of hydraulic structure | |
| RU2022102C1 (en) | Construction made of ice | |
| Grønhaug | Optimization of Linings in Road Tunnels | |
| KR100399874B1 (en) | Protecting method against water leakage of concrete cracks | |
| CN207795277U (en) | A kind of Tunnel Engineering anti-freezing structure of frozen ground regions | |
| JP2002322772A (en) | Gutter and fixing member for the same | |
| FI82110C (en) | VAEGTRUMMA. | |
| CN104989040B (en) | The cold area roofing antiseep drainage system practice | |
| Abildgren et al. | STOREBAELT EASTERN RAILWAY TUNNEL: FIXED EQUIPMENT AND RAILWAY SYSTEMS. | |
| Carey | Solving problems of ice-blocked drainage | |
| RU2296284C2 (en) | Horizontal heat exchanger | |
| Miller | How to Cope With Freeze Damage and Ice Buildup on Outside Storage Tanks | |
| JPH0234832B2 (en) | TOKETSUSURUSUIIKINIMOCHIIRUKOZOBUTSU |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PUAI | Public reference made under article 153(3) epc to a published international application that has entered the european phase |
Free format text: ORIGINAL CODE: 0009012 |
|
| 17P | Request for examination filed |
Effective date: 19880729 |
|
| AK | Designated contracting states |
Kind code of ref document: A1 Designated state(s): AT BE CH DE FR GB IT LI LU NL SE |
|
| 17Q | First examination report despatched |
Effective date: 19900412 |
|
| GRAA | (expected) grant |
Free format text: ORIGINAL CODE: 0009210 |
|
| AK | Designated contracting states |
Kind code of ref document: B1 Designated state(s): AT BE CH DE FR GB IT LI LU NL SE |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: NL Effective date: 19901107 Ref country code: BE Effective date: 19901107 |
|
| REF | Corresponds to: |
Ref document number: 58205 Country of ref document: AT Date of ref document: 19901115 Kind code of ref document: T |
|
| REF | Corresponds to: |
Ref document number: 3766105 Country of ref document: DE Date of ref document: 19901213 |
|
| ITF | It: translation for a ep patent filed | ||
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LU Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19910228 |
|
| ET | Fr: translation filed | ||
| NLV1 | Nl: lapsed or annulled due to failure to fulfill the requirements of art. 29p and 29m of the patents act | ||
| PLBE | No opposition filed within time limit |
Free format text: ORIGINAL CODE: 0009261 |
|
| STAA | Information on the status of an ep patent application or granted ep patent |
Free format text: STATUS: NO OPPOSITION FILED WITHIN TIME LIMIT |
|
| 26N | No opposition filed | ||
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: GB Payment date: 19940120 Year of fee payment: 8 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: DE Payment date: 19940203 Year of fee payment: 8 |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: FR Payment date: 19940207 Year of fee payment: 8 Ref country code: CH Payment date: 19940207 Year of fee payment: 8 Ref country code: AT Payment date: 19940207 Year of fee payment: 8 |
|
| ITTA | It: last paid annual fee | ||
| EAL | Se: european patent in force in sweden |
Ref document number: 87901166.6 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: GB Effective date: 19950211 Ref country code: AT Effective date: 19950211 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: LI Effective date: 19950228 Ref country code: CH Effective date: 19950228 |
|
| GBPC | Gb: european patent ceased through non-payment of renewal fee |
Effective date: 19950211 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: FR Effective date: 19951031 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: DE Effective date: 19951101 |
|
| REG | Reference to a national code |
Ref country code: FR Ref legal event code: ST |
|
| PGFP | Annual fee paid to national office [announced via postgrant information from national office to epo] |
Ref country code: SE Payment date: 19970217 Year of fee payment: 11 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: SE Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES Effective date: 19980212 |
|
| EUG | Se: european patent has lapsed |
Ref document number: 87901166.6 |
|
| PG25 | Lapsed in a contracting state [announced via postgrant information from national office to epo] |
Ref country code: IT Free format text: LAPSE BECAUSE OF NON-PAYMENT OF DUE FEES;WARNING: LAPSES OF ITALIAN PATENTS WITH EFFECTIVE DATE BEFORE 2007 MAY HAVE OCCURRED AT ANY TIME BEFORE 2007. THE CORRECT EFFECTIVE DATE MAY BE DIFFERENT FROM THE ONE RECORDED. Effective date: 20050211 |